UNDERSTANDING THE ENERGY SUPPLY CHAIN Engr. Eduardo B. Fernandez
E-Power Mo: Energy Consumer and Stakeholders Conference 12 July 2017 | Philippine International Convention Center, Pasay City
Department of Energy Empowering the Filipinos PRESENTATION OUTLINE
1 2
Power Demand and What is WESM Supply Chain • WESM Basic Features • Power Myth • How WESM bidding • Transformation of fuel works into electricity • RTD Scenarios • Types of Power Plant Power Demand and Supply Chain
TRANSMISSION
DISTRIBUTION GENERATION
CONSUMERS
Department of Energy Empowering the Filipinos Reality Check
Bakit sobrang mataas ang presyo ng ating kuryente?
Mali ba ang composition ng power Bakit parang mas mababa generation mix ng ating bansa? ang presyo ng kuryente nung panahon ng NPC?
Bakit mas mataas ang presyo Tama nga ba na ng kuryente natin compared privatized ang planta ng sa ibang ASEAN countries? NPC?
Kaya ba mataas ang ating power rate gawa ba ng WESM?
Department of Energy Empowering the Filipinos Transformation of fuel into electricity
Department of Energy Empowering the Filipinos NPC Assets
. NPC Power Plants 121 (11,361 MW) . Transmission lines (10,494 ckt. km.) . Substation Capacity (20,041 MVA)
Department of Energy Empowering the Filipinos NPC Assets
Department of Energy Empowering the Filipinos Types of Power Plant
GENERATION Base Load Plants CUSTOMERS
• Plants which can generate dependable power to consistently meet demand • Produce continues, reliable and efficient power at low cost • Run 24/7 throughout the year except in cases of repairs or scheduled maintenance
600 MW 610 MW 1294 MW Pagbilao Coal-fired Power Plant Leyte Geothermal Power Plant Sual Coal-fired Power Plant
Department of Energy Empowering the Filipinos Types of Power Plant
GENERATION Intermediate Load Plants CUSTOMERS
Fill the gap between base load and peaking plants • Larger than peaking plants so the construction cost are higher • They also run more efficiently
500 MW 1060 MW 1200 MW San Lorenzo Natural Gas-fired Plant Sta Rita Natural Gas-fired Plant Ilijan Natural Gas-fired Plant
Department of Energy Empowering the Filipinos Types of Power Plant
GENERATION Peak Load Plants CUSTOMERS
• Provide power during peak system demand period • Higher responsive to changes in electrical demand and can be started up relatively quickly (Hydroelectric Power Plant) • Very expensive to operate, relative to the amount of power they produce and the cost of fuel to power them (Oil-based power plant)
116 MW 360 MW 755MW Subic Diesel Power Plant Magat Hydroelectric Power Plant CBK Hydroelectric Power Plant
Department of Energy Empowering the Filipinos Typical Load Curve
Peak Reserve Margin Requirement
MW Intermediate
Base load
TIME OF DAY
Department of Energy Empowering the Filipinos Stacking of Power Plants
GENERATION
DIESEL 10,000
OIL THERMAL
8000 HYDRO
6000
NATURAL GAS
4000
2000 COAL
MW GEOTHERMAL
Department of Energy Empowering the Filipinos Coal Power Plant
Department of Energy Empowering the Filipinos Pagbilao Power Plant
2 X 382 MW, Isla Grande-Quezon
Department of Energy Empowering the Filipinos Natural Gas Power Plant
Department of Energy Empowering the Filipinos Natural Gas Combined Cycle Power Station
1,200 MW Ilijan, Batangas
Department of Energy Empowering the Filipinos Hydro Electric Power Plant
Department of Energy Empowering the Filipinos Magat Hydroelectric Power Plant
360 MW Santiago City / Alfonso Lista, Ifugao / Ramon, Isabela
Department of Energy Empowering the Filipinos WESM Stakeholders
GENERATORS TRANSMISSION
DISTRIBUTION
CONSUMERS
Department of Energy Empowering the Filipinos How WESM Bidding Works
G DUs/ECG NPC Market Clearing Plants Results: Energy 2 s 4 demand MCPs and MOT Reserve requirements G Energy 1 offers/bids System Condition: NPC IPPs Reserve • Outages 3 offers • Contingencies • Transmission limits 7 Billing & Settlement Dispatch G Charges & Payments Instruction IPPs s: Dispatch 5 targets G Revenue Meters: NGCP G Metered values 6 IPPAs G WESM Basic Features
GROSS POOL - All energy transactions are scheduled in the market
GROSS DISPATCH - Generators submit energy offers (price and Quantity) for central scheduling and dispatch
TRADING HOURS - 24 hours/day, 7 days per week
LOCATIONAL MARGINAL PRICE - Marginal price computed at each node or location to reflect transmission loss and/or congestion WESM Basic Features
GOVERNANCE - Governed by stakeholders (PEMC)
TRADING GUARANTEES - Prudential guarantees to assure payment
NET SETTLEMENT - Bilateral Contract quantities transacted in the pool, but, can be settled outside of the market. Ex-ante price and quantity aligned with ex-post price and quantity
BILLING & SETTLEMENT - 60 days period for B&S How WESM Bidding Works
• WESM
GENERATION CUSTOMERS DUs/ECs
Hydro C Geogas F Diesel H P 0,000/MWh P P 4,000/MWh 25 MW 3,000/MWh 200 MW 150MW
Hydro B 50 MW P Natgas E Roxas Boulevard Demand 1,000/MWh - P 1,000/MWh Bunker G Requirements: 600 MW P 3,500/MWh Wind/Solar 100MW 300 MW 5 MW Priority Dispatch Coal D P 2,500/MWh 115 MW
Run-of-River 50 MW Biomass Non- 5MW Scheduled Priority Dispatch Merit Order Table
Market Clearing Price - Php 3,500/MWh (marginal cost of meeting demand) Marginal Plant – Bunker G Price Taker
P/MWhr 600 MW 4,000
3,000
2,000
1,000
300 400 550 MW Geogas F Bunker G Diesel H Hydro B Coal D P 3,000/MWh P 3,500/MWh P 4,000/MWh 50 MW P 150MW 300 MW 200 MW P 1,000/MWh 2,500/MWh Biomass Hydro C 115 MW 5 MW Non- Natgas E P Plant Solar/Wind Priority scheduled - P 0,000/MWh Pmin 5 MW Dispatch 25 MW Must Plants 1,000/MWh Dispatch 100MW Merit Order Table
P/MWhr 600 MW 4,000
3,000
2,000
1,000
300 400 550 MW Geogas F Bunker G Diesel H Hydro B Coal D P 3,000/MWh P 3,500/MWh P 4,000/MWh 50 MW P 150MW 300 MW 200 MW P 1,000/MWh 2,500/MWh Biomass 115 MW 5 MW Non- Natgas E Plant Solar/Wind Priority scheduled - P Pmin 5 MW Dispatch Must Plants 1,000/MWh Dispatch 100MW Merit Order Table
Market Clearing Price - Php 4,000/MWh (marginal cost of meeting demand) Marginal Plant – Diesel H Price Taker
P/MWhr 600 MW 4,000
3,000
2,000
1,000
300 400 550 MW
Geogas F Bunker G Diesel H Coal D P 3,000/MWh P 3,500/MWh P 4,000/MWh P 150MW 300 MW 200 MW 2,500/MWh Biomass 115 MW 5 MW Non- Natgas E Plant Solar/Wind Priority scheduled - P Pmin 5 MW Dispatch Must Plants 1,000/MWh Dispatch 100MW Merit Order Table
P/MWhr 600 MW 4,000
3,000
2,000
1,000
300 400 550 MW
Geogas F Bunker G Diesel H Coal D P 3,000/MWh P 3,500/MWh P 4,000/MWh P 150MW 300 MW 200 MW 2,500/MWh Biomass 115 MW 5 MW Non- Natgas E Plant Solar/Wind Priority scheduled - P Pmin 5 MW Dispatch Must Plants 1,000/MWh Dispatch 100MW Real Time Facility Status
Department of Energy Empowering the Filipinos Thank You!