National/International flood risk management planning Case Study: Basin

Workshop on Flood Risk Management Measures & Links to EU WFD , November 11-12 2015

Mirza Sarač ISRBC Secretariat Sava river basin Sava – the largest by (contribution: 25%)

SAVA COMMISSION

•Established in 2005 (Secretariat: in 2006; Seated in )

•Established for implementation of the Framework Agreement on the Sava River Basin (FASRB)

•Four countries involved Country Share of the basin Share of the • and Herzegovina, (%) territory (%) •Croatia, • and • Bosnia & Herzegovina 39.2 75.8 oMontenegro Croatia 26.0 45.2 . It was involved at the beginning (as a part of Serbia & ) Serbia 15.5 17.4 . Cooperation on technical level, in Slovenia 12.0 52.8 some fields of work . Formalization of cooperation (until Montenegro 7.1 49.6 the full membership) under consideration 0.2 0.6

• Study for regulation and management of the Sava River (UN, 1972)

• Protocol on Flood Protection to the FASRB (ISRBC, 2010)

Workshop on Flood Risk Management Measures & Links to EU WFD 2 Significant floods

Year of flood Affected area/river

Oct/Nov 1896 River

Apr 1932 Sava River

Oct 1933 Sava River

Nov 1944 Sava River

Oct 1964 Sava River

Dec 1966 Sava and

Dec 1968 River

Jan 1970 Sava and rivers

Oct 1974 Sava, , Kupa and

Jul 1989 Krapina River

1990 Upper Sava River Basin

Oct/Nov 1998 Upper Sava River Basin

Nov 1998 Kupa River

Jul 1999 , and Gračica rivers

Jun 2001 , and Ljuboviđa r.

Mar 2006 Tamnava, Ub and Gračica rivers

Apr 2006 Sava River

Sep 2007 Upper Sava River Basin

Mar 2009 Tamnava, Ub and Gračica rivers

Dec 2009 Upper Sava River Basin

May/Jun 2010 Middle Sava River Basin

Sep 2010 Middle Sava River Basin

Dec 2010 Drina, Kupa and Una rivers

Feb 2014 Kupa River

May 2014 Middle/lower Sava River Basin Workshop on Flood Risk Management Measures & Links to EU WFD 3 ISRBC Modes of cooperation in FRM planning

Article 4 of the Protocol states: With aim to achieve the objectives of this Protocol, and on the basis of documents as referred to in Article 3 paragraph 1 of this Protocol, the Parties shall cooperate on: (a) Preparation of the Program for development of the Flood Risk Management Plan in the Sava River Basin (b) Undertaking of Preliminary Flood Risk Assessment (c) Preparation of Flood Maps (d) Development of Flood Risk Management Plan in the Sava River Basin (e) Establishment of the Flood Forecasting, Warning and Alarm System in the Sava River Basin (f) Exchange of information significant for sustainable flood protection (g) Implementation of all measures and activities of mutual interest, originating from planning documents or activities from items (a) to (f) above or other mutually agreed measures and activities

Program for development Area with Preliminary Flood Risk of the Flood Risk Potential Flood Hazard Flood Risk Flood Risk Management Management Significant Maps Maps Asssessment Plan Plan in the Flood Risk Sava River basin

Workshop on Flood Risk Management Measures & Links to EU WFD 4 ISRBC Flood risk management planning

• Sava Flood Action Plan in 2009 • Program for development of the Sava FRM Plan (drafted) – Program shall be adopted by the ISRBC (within six months as of the entry into force of the Protocol) – Program shall comprise all elements relevant for development of the Sava FRM Plan (responsibilities of the Parties, mechanisms of the plan development, holders of he particular acitivities and their realisation deadlines) • Joint PFRA report prepared (first list of APSFR) • Initial flood vulnerability assesment performed • Climate Change issue addressed through different projects

www.savacommission.org/publication Workshop on Flood Risk Management Measures & Links to EU WFD 5 Preliminary Flood Risk Assessment

Article 6 of the Protocol states: 1. Each Party shall undertake Preliminary Flood Risk Assessment for its part of the Sava River Basin, taking into account the Directive 2007/60/EC 2. In the process of Preliminary Flood Risk Assessment, the Parties shall exchange all relevant data, in principle, through the Sava Commission or bilaterally, as appropriate 3. In the case of bilateral exchange of the relevant data from paragraph 2 of this Article, the latter shall also be delivered to the Sava Commission, without delay 4. Based on the Preliminary Flood Risk Assessment, each Party shall, on the part of the Sava River Basin on its territory, identify those areas for which it concludes that potential significant flood risk exists or might be considered likely to occur 5. Each Party shall, through the Sava Commission, inform the other Parties on the identified areas from Paragraph 4 of this Article – Prepared by the 6. The Sava Commission shall coordinate the activities on harmonization of the areas identified pursuant to paragraph 4 of this Article shared by two or more Parties, identified by the Parties as the areas of mutual interestISRBC for flood in 2014 protection

APSFR 1912

Bosnia & Herzegovina 155 (87 in RoS N/C)

Croatia 1688

Serbia 27

Slovenia 42

Montenegro N/A

Workshop on Flood Risk Management Measures & Links to EU WFD 6 Flood Maps

Article 7 of the Protocol states: 1. Each Party shall prepare Flood Maps for the areas identified in the Preliminary Flood Risk Assessment as referred to in Article 6 of this Protocol for the part of the Sava river basin under its jurisdiction, taking into account the Directive 2007/60/EC 2. Each Party shall, through the Sava Commission, inform other Parties on the Flood Maps prepared for its territory 3. The respective Parties shall agree upon the methodology for mapping of the flood areas shared by two or more Parties, identified according to the Article 6 paragraph 4 of this Protocol, and, thereof, inform the Sava Commission 4. The Parties may, for purpose of joint implementation of the activities from paragraph 1 of this Article, agree to develop a joint methodology for preparation of Flood Maps for the whole Sava River Basin 5. The Sava Commission shall coordinate the development of the Methodology from paragraph 4 of this Article

Workshop on Flood Risk Management Measures & Links to EU WFD 7 Sava Flood Risk Management Plan

Article 8 of the Protocol states: 1. The Parties shall prepare the Flood Risk Management Plan for the Sava River Basin, in accordance with the content defined by the Directive 2007/60/EC, and taking into account all relevant aspects of flood risk management 2. The flood Risk Management Plan shall, in particular, define the goals of the flood risk management of common interest on the Sava River basin level 3. Taking into account the principle of solidarity and the no harm rule in accordance with the Article 9 of the FASRB, the Flood Risk Management Plan for the territory of one Party shall not stipulate measures that may, by their magnitude or impact, significantly increase the flood risk on the territory of the other Party, unless those measures are coordinated and agreed between the Parties concerned 4. The Sava Commission shall coordinate the development of the Flood Risk Management Plan 5. Flood Risk Management Plan shall be adopted by the Parties, upon proposal of the Sava Commission

WBIF project - Improvement of Joint Flood Management Actions in the Sava River Basin

• Approved in June 2014 by WBIF and WB • Geographical coverage: 5 countries (BA, HR, ME, RS, SI) • Beneficiaries: BA, ME, RS • Components – Flood Risk Management Plan for the Sava River Basin, including Programme of Measures (Component 1) – Flood Forecasting and Warning System for the basin (Component 2) • Budget:2,0 mil EUR Workshop on Flood Risk Management Measures & Links to EU WFD 8 WBIF project - Component 1 Flood Risk Management Plan for the Sava River Basin, including the Programme of measures, with the following main components:

• A summary of the conclusions relevant for the basin, drawn from the Preliminary Flood Risk Assessment, flood hazard and risk maps • Setting up of the list of Programme of Measures relevant for the basin as a whole and description of the proposed prioritisation, timing and manner of implementing the PoM including details of the bodies responsible for implementation • In determining the proposed measures for achieving the objectives, the Plan shall have regard to: – The costs and benefits of different methods of managing the flood risk – The information included in the flood hazard and risk maps – The river basin management plan for the basin – The effect of floodplains that retain flood water – The WFD environmental objectives – The climate change impacts – The transboundary impacts of the proposed measures • The Plan shall also provide a proposal of: – Modes of cooperation of the Sava countries in the flood defence emergency situations – Arrangements in the basin for forecasting and warning – Environmental Impact Assessment Study for the PoM. The study should ensure ecological foundations for identification of special environment protection requirements. Specifically, a said study shall define type and level of PoM realization impact on environment, as well as optimum mitigation measures aimed at reducing, or eliminating, harmful impacts

Workshop on Flood Risk Management Measures & Links to EU WFD 9 Exchange of information within FRM planning

Article 10 of the Protocol states: 1. In case of flood that induces or may induce transboundary impact, the Parties shall, without delay, inform the Parties that might be affected by this impact, through the System or any other appropriate manner in line with the agreed procedure for exchange of information important for flood defense 2. The Parties shall, through the hydro-meteorological services and institutions responsible for flood protection, ensure timely exchange of meteorological and hydrological data, analyses and information important for flood protection, especially the timely forecast of high waters, in line with the agreed procedure 3. The Parties shall inform each other on changes of their regulations and plans relevant to the flood protection in the Sava River Basin

– Establishment of the SavaGIS core funcionalities (2014-2015) • Flood Management dataset development – Establishment of the SavaHIS (2015) • Near real-time application development, as effective common channel for exchanging and viewing the hydrologic and meteorological data and information in emergency situations, primarily those related to flood events

Workshop on Flood Risk Management Measures & Links to EU WFD 10 Exchange of information within FRM planning – Sava GIS

• Overall objective of the SavaGIS – common platform of the ISRBC community to enable sharing and disseminating of information and knowledge about protection of the and water management activities in the Sava River Basin

Establishment of the Sava GIS is focused in following benefit areas:

1. Int. River Basin Management 2. Flood Management 3. Accident Prevention and Control 4. Navigation Safety Management 5. Sediment Management

Workshop on Flood Risk Management Measures & Links to EU WFD 11 Sava GIS – FRM segment

• FRM database (geodatabase) – Preliminary Flood Risk Assessment – Areas with Potential Significant Flood Risk – Flood Hazard and Risk Maps – Historical Floods – Flood Protection Structures

• Database model is created based on • EU FD reporting Guidance 2013 • EU WFD reporting Guidance 2016 v.4.9 1 Feature Dataset, • INSPIRE Directive and professional 17 Feature Classes, requirements 26 Tables (Object Classes), • ICPDR database model v.4.2 30 Relationship Classes and 26 Domains

Workshop on Flood Risk Management Measures & Links to EU WFD 12 Sava GIS – FRM segment • Web-based application for data and metadata management

• FGDB file is structured as a template – in accordance with the WFD Reporting Guidance 2016 i.e. SavaGIS RBM and FRM database model – *.mxd templates for the data migration into fgdb – ArcGIS 10.x – document with instructions for template usage

• WFS Service

Workshop on Flood Risk Management Measures & Links to EU WFD 13 Sava GIS – FRM segment

• Sava Geoportal for searching, disseminating, processing and visualization information to the stakeholders and public

http://savagis.org/ Workshop on Flood Risk Management Measures & Links to EU WFD 14 SavaGIS metadata catalog

• Based on GeoNetwork – Allows search of spatial datasets and services based on their metadata records – Used to describe other services or spatial data and spatial datasets through metadata

• INSPIRE compatible Discovery Services – Metadata search – enables metadata retrieval based on different criteria – Metadata editing – enables authorized modification of metadata, i.e. insert, update and delete – Harvesting – enables automatic periodically metadata retrieval from remote metadata catalogue

• Metadata format: ISO19115, with ISO 19139 xml implementation

Workshop on Flood Risk Management Measures & Links to EU WFD 15 Thank You for Attention !!!

International Sava River Basin Commission Kneza Branimira 29 10000 Zagreb Croatia

www.savacommission.org

Workshop on Flood Risk Management Measures & Links to EU WFD 16