Quick viewing(Text Mode)

Utilities Statement

Utilities Statement

Cuadrilla Elswick Ltd Temporary Shale Gas Exploration Roseacre Wood,

Utilities Statement

RW_PL_Utilities Statement June 2014

Cuadrilla Elswick Ltd Temporary Shale Gas Exploration at Roseacre Wood, Lancashire Utilities Statement

Contents

Page

1 Introduction 2

2 Existing Utilities (Exploration Works) 3 2.1 Sources of Information 3 2.2 Utilities in Close Proximity to the Site 3

3 Existing Utilities (Monitoring Works) 5

4 Physical Impacts on Existing Utilities Networks from the Exploration Works 6 4.1 Protection of the Gas Main 6 4.2 Protection of the MoD Communications Apparatus 6 4.3 Effects of Induced Seismicity 6 4.4 Vibrations from heavy plant 8

5 Physical Impacts on Existing Utilities Networks from the Monitoring Works 10

6 Utilities Supplies to the Exploration Works 11 6.1 Electricity 11 6.2 Water Supply 11 6.3 Foul Drainage 12 6.4 Return Water 12 6.5 Other Waste Waters 12 6.6 Gas 12 6.7 Telecommunications 13

7 Utilities Supplies to the Monitoring Works 14

8 Conclusions 15 8.1 Exploration Works 15 8.2 Monitoring Works 15

Appendices

Appendix A Utility Record Plans

REP/230382-10/C002 | Issue |

Cuadrilla Elswick Ltd Temporary Shale Gas Exploration at Roseacre Wood, Lancashire Utilities Statement

1 Introduction

This Utilities Statement has been prepared by Arup on behalf of Cuadrilla Elswick Ltd (Cuadrilla) in support of planning applications to Lancashire County Council (LCC) for temporary shale gas exploration works at a site close to Roseacre Wood, Roseacre. Its purpose is to identify utility apparatus in and around the area; state how the site will connect to the local utility networks; and to assess how these networks may be affected by the proposed development. This statement describes the impacts on the existing electricity, gas, water, foul drainage and telecommunications networks. Surface water drainage is covered in the site-specific Flood Risk Assessment. This Utilities Statement has been prepared to support two separate planning applications associated with the Project, and has therefore been structured accordingly:-  The Exploration Works (comprising the Exploration Site [well pad], Access and Extended Flow Test areas)  Monitoring Works

REP/230382-10/C002 | Issue |

Cuadrilla Elswick Ltd Temporary Shale Gas Exploration at Roseacre Wood, Lancashire Utilities Statement

2 Existing Utilities (Exploration Works)

2.1 Sources of Information Plans were obtained through Groundwise Ltd. in October 2013 to confirm utility apparatus that may be present within the vicinity of the Roseacre Wood site. Copies of these plans can be found in Appendix A. Gas, electricity and water apparatus have been identified within the vicinity of the site. Confirmation has been received from the following utility providers that they do not have apparatus within the vicinity of the site:  (Cable & Wireless)  BSKYB  CityFibre  McNicholas (KPN and TATA)  Verzion  GTC – Envoy  SSE Pipelines Ltd / Neos Networks  OFCOM  Orange  Trafficmaster  KCOM  Energetics  Colt  Instalcom (inc. Level 3)  Interoute  Virgin Media  Vtesse

Plans provided by United Utilities (UU) show that there are no public sewers within the vicinity of the site. Discussions have also been held with DHFCS Inskip regarding the impact on their private utilities networks within their landownership.

2.2 Utilities in Close Proximity to the Site From the utility records obtained, Gas utility apparatus was identified within the site boundary. DHFCS Inskip has overhead communications cables crossing the access route. Water and electricity apparatus have been identified in close proximity to the site as described below. The presence of these utilities will be stated in the Cuadrilla site H&S Manual and locations shown on site notice boards.

2.2.1 Gas A 42” ST (steel) high pressure gas main has been identified as passing beneath the access track, to the east of the exploration site. National Grid plans showing the

REP/230382-10/C002 | Issue |

Cuadrilla Elswick Ltd Temporary Shale Gas Exploration at Roseacre Wood, Lancashire Utilities Statement

route of the main can be found in Appendix A. This main forms part of the National Transmission System (NTS). The main passes approximately 30m away from the south-east corner of the well pad at its closest point. There are no records of other gas apparatus in the vicinity of the site, including in the village of Roseacre.

2.2.2 Electricity Cables Records show the presence of high voltage above ground electricity pylons approximately 300m to the west of the exploration site. Low voltage electrical supplies are provided to local residential properties via cabling installed in Roaseacre Road. A plan of this is shown in Appendix A.

2.2.3 Water mains A 6” diameter UU potable water main runs alongside Roseacre Road, approximately 400m to the east of the exploration site. Records show this as an asbestos cement pipeline which continues northwards past Stanley Farm. A 90mm diameter branch from the 6” main continues along Roseacre Road and through the village of Roseacre, approximately 350m to the north of the exploration site.

2.2.4 Telecommunications BT Openreach plans show no apparatus in or immediately surrounding the Roseacre Wood exploration site. Plans show that BT does have underground plant in Roseacre Road serving the village of Roseacre approximately 350m to the north of the exploration site. The plans suggest this main follows Roseacre Road to the east and then southwards where it passes approximately 400m to the east of the exploration site.

2.2.5 MoD Communications Apparatus A series of Ministry of Defence (MOD) antenna masts are located approximately 750m to the east of the exploration site. These are part of the MoDs communication network and are located on the DHFCS Inskip site. The application includes for the potential to divert some HGV traffic through this area passing below existing (private) overhead communications cabling.

REP/230382-10/C002 | Issue |

Cuadrilla Elswick Ltd Temporary Shale Gas Exploration at Roseacre Wood, Lancashire Utilities Statement

3 Existing Utilities (Monitoring Works)

The monitoring works have been located generally to avoid conflict with existing utilities networks. In addition, prior to the construction of these installations, Cuadrilla’s Contractor(s) will undertake a review of safe dig records to identify locations of any utility apparatus and define the exact location of a monitoring point which avoids any conflict (eg moving a meter or two to one side). Where working close to existing utilities infrastructure, relevant industry standard procedures and working practices for working near these assets will be followed.

REP/230382-10/C002 | Issue |

Cuadrilla Elswick Ltd Temporary Shale Gas Exploration at Roseacre Wood, Lancashire Utilities Statement

4 Physical Impacts on Existing Utilities Networks from the Exploration Works

4.1 Protection of the Gas Main Enhancement of the existing access track is proposed in order to provide HGV access to the exploration site from Roseacre Road. As this track passes over the high pressure gas main, a concrete protection slab will be required to spread the load of HGV traffic al. The protection works will be designed and undertaken in accordance with National Grid’s publication “Specification for Safe Working in the Vicinity of National Grid High Pressure Gas Pipelines and associated installations – Requirements for Third Parties” (National Grid document T/SP/SSW/22, August 2007) Discussions are on-going between Cuadrilla and National Grid to confirm the details of the protection works required.

4.2 Protection of the MoD Communications Apparatus The planning application includes for the ability to direct some HGV traffic via the MoD’s DHFCS Inskip facility. Currently a 3.5m clearance is provided to these cables. To protect against potential damage, where the roadway passes below overhead cables, these cables shall be raised to provide a minimum of 5.4m headroom This will be achieved by extending the height of the poles supporting the cables. Discussions are on-going between Cuadrilla and the MoD to agree the details of protection works to the overhead cables,

4.3 Effects of Induced Seismicity Hydraulic fracturing of the wells forms part of the operation to extract shale gas. The hydraulic fracturing process has the potential to cause small seismic tremors [induced seismicity].

For the Roseacre Wood site and the surrounding areas, the mechanism of hydraulic fracturing and the risk of induced seismicity has been assessed in the Environmental Impact Assessment and is reported in the Environmental Statement (ES) accompanying the Planning Applications. In exceptional circumstances, hydraulic fracturing may induce a seismic event that can be felt at the ground surface. It is therefore considered prudent to assess the potential for ground borne vibrations to damage nearby utilities under these exceptional circumstances. This has been assessed using information from the Induced Seismicity chapter of the ES.

Considering the mitigation measures that will be implemented as part of the Project, a maximum magnitude seismic event induced by hydraulic fracturing operations is estimated to be approximately 1.5 ML. However, to mitigate against this risk, a “Traffic Light System” will be implemented to monitor seismicity and to ensure that hydraulic fracturing activities will be stopped and the well depressurised if vibrations are recorded which reach the pre-agreed trigger level (0.5 ML). This is discussed further in the Induced Seismicity chapter of the ES.

REP/230382-10/C002 | Issue |

Cuadrilla Elswick Ltd Temporary Shale Gas Exploration at Roseacre Wood, Lancashire Utilities Statement

It is considered that the source of an induced seismic event may be anywhere within the area defined by the red line drawing (see Planning Application drawings). This comprises an area which extends for approximately 2km west of the Roseacre Wood site. The minimum depth epicentre of an induced seismic event is likely to occur at approximately 1.95km depth (i.e. within the shale rock formations).

Based on the analysis of the ground motion hazard associated with hydraulic fracturing at the Roseacre Wood site, it is anticipated that a 1.5 ML induced seismic event could produce maximum ground motions at the surface in the region of 0.4 to 1.8mm/s (mean and 95 percentile/worst case values respectively). These vibrations will reduce with distance from the source location.

To put these values into context, Table B1 in BS 5228-2:20091 has been reproduced as Table 1 below presenting the response of humans to various levels of ground borne vibrations. It is noted that the maximum levels of vibrations anticipated for a 1.5 ML induced seismic event (0.4 - 1.8 mm/s) are around the level at which vibrations may be just felt by humans at the ground surface. It is noted that depending on the sensitivity of the environment (i.e. time of day, type of building) and the frequency of the vibrations, the response of humans may be greater or smaller.

Ground Response vibration ML [Peak Particle Velocity] (mm/s) 0.14 Vibration might be just perceptible in the most sensitive situations for most vibration frequencies associated with construction. At lower frequencies, people are less sensitive to vibration. 0.3 Vibration might be just perceptible in residential environments. 1.0 It is likely that vibration of this level in residential environments will cause complaint, but can be tolerated if prior warning and explanation has been given to residents. 10 Vibration is likely to be intolerable for any more than a very brief exposure to this level. Table 1 - Guidance on human response to construction vibration from BS 5228-2:2009.

BS5228-2:2009 states that, in the absence of specific criteria from the asset owners, services [utilities] should not be subjected to a maximum peak particle velocity (PPV) greater than 30mm/s. BS5228-2:2009 also states that a PPV of 30 mm/s gives rise to a dynamic stress which is equivalent to approximately only 5% of the allowable working stress in typical concrete constructions and even less in iron or steel.

1 “Code of Practice for Noise and Vibration Control on Construction and Open Sites. Vibration.” BSI Dec 2008

REP/230382-10/C002 | Issue |

Cuadrilla Elswick Ltd Temporary Shale Gas Exploration at Roseacre Wood, Lancashire Utilities Statement

National Grid guidelines for vibrations in the vicinity of high pressure gas mains2 state that pipelines shall be limited to a maximum PPV of 75mm/s for vibration inducing operations such as piling, demolition and/or blasting, to prevent damage to the asset.

Based on the assessment of induced seismicity and the predicted ground motions for a 1.5 ML event of 0.4 to 1.8mm/s, it is considered highly unlikely that the structural integrity of the gas main, HV electricity cables, UU water main or DHFCS Inskip utilities within the vicinity of the Roseacre Wood site would be damaged or affected by the ground motions associated with hydraulic fracturing at the Roseacre Wood site.

4.4 Vibrations from heavy plant

4.4.1 HGV movements Since the gas main is located within the site boundary and water and electricity mains and buried telecommunications cabling are present within Roseacre Road, National Grid, UU ENWL and BT Openreach should be contacted by the Contractors to confirm any specific protection measures which may be required whilst large plant is brought on to the site. However, since the water and electricity mains and the telecommunications cabling are installed in public highway subject to HGV loads, it is assumed that these utilities are located at depths in accordance with National Joint Utilities Group (NJUG) guidelines. Therefore it is not envisaged that any additional protection works will be required in the highway for normal road-going plant. Similarly, HGVs currently access through the DHFCS Inskip site. Any vibration from proposed development traffic along this route is therefore not considered to have an impact on existing MoD utilities. Cuadrilla should maintain close dialogue with DHFCS Inskip during their operations to confirm that the existing utilities are not being affected.

4.4.2 Vibration from Surface Activities within the Exploration Site Activities on the well pad, including vehicle movements, will cause ground borne vibration. The figure below compares the predicted maximum vibrations from induced seismicity (0.4mm/s to 1.8mm/s PPV) with vibration from various sources that might otherwise be present in a typical construction environment. For comparison purposes, Figure 1 includes vibration from a HGV passing over a 20mm surface defect, which may occur, for example, where there is a poorly reinstated trench. Other activities are those that might be required during highway maintenance works and some heavier engineering, including piling. Many of

2 “Specification for Safe working in the Vicinity of National Grid High Pressure Gas Pipelines and associated installations – Requirements for third parties”, National Grid, T/SP/SSW/22, August 2007

REP/230382-10/C002 | Issue |

Cuadrilla Elswick Ltd Temporary Shale Gas Exploration at Roseacre Wood, Lancashire Utilities Statement

these are likely to be used from time to time in the vicinity of buried utilities and other structures. The levels of vibrations created from construction operations and vehicle movements are in a similar order of magnitude as those which could be created by an induced seismic event. Compared to published guidance on the vulnerability of services, as described above, it is therefore be concluded that the utilities should not be affected by vibrations from heavy plant or machinery activity within the site.

100 Hammer driven piling**

Wacker plate compactor*

10

Cat D5H dozer*

HGV, 20mm defect, 30mph*** 1 Bomag BW135AD tandem

roller* PPV (mm/s) PPV Bomag Pavement Recycler*

0.1 CFA piling**

0.4mm/s

0.01 1 10 100 1.8mm/s Distance (m)

Figure 1 – Comparison of ground borne vibrations vs source distance

Notes: * From Transport Research Laboratory Report 429 Groundborne vibrations from mechanised construction works. Hiller D M and Crabb G I (2000). TRL, Crowthorne ** From A comparison of noise and vibration from percussive and bored piling. Proc Underground Construction 2003, pp 213-224. Hiller D. Hemming Group Limited. *** From Transport and Road Research Laboratory Research Report 429 Traffic induced vibrations in buildings. Watts G R (1990). TRRL, Crowthorne

REP/230382-10/C002 | Issue |

Cuadrilla Elswick Ltd Temporary Shale Gas Exploration at Roseacre Wood, Lancashire Utilities Statement

5 Physical Impacts on Existing Utilities Networks from the Monitoring Works

There are no anticipated impacts on existing utilities from the installation or operation of the seismic monitoring works. Should it be required, the array point can be moved locally (ie by a metre or two) to avoid any impact on existing utilities networks.

REP/230382-10/C002 | Issue |

Cuadrilla Elswick Ltd Temporary Shale Gas Exploration at Roseacre Wood, Lancashire Utilities Statement

6 Utilities Supplies to the Exploration Works

6.1 Electricity Electrical power is required on the Exploration Site during operational phases (mobilisation, hydraulic fracturing and flow-back testing) of the development. Due to the exploratory stage of the project, the electrical demand for the site will be met by on-site generators. A connection may be made to the electricity network to provide small power requirements to supply offices, welfare facilities, site lighting etc. This will be a low voltage connection which is not envisaged to impact significantly on the local network capacity.

6.2 Water Supply The principle water demands from the site are during the hydraulic fracturing operations. During other times, water will be required to support the drilling operation, site cleaning and welfare operations. The water demand during hydraulic fracturing operations is anticipated to be approximately 765m3 of water per day (a maximum of one hydraulic fracturing stage will be carried out in a single day). This water will be supplied from the United Utilities (UU) potable water network. UU have identified two potential points of connections; the 6” main in Roseacre Road or a larger trunk main located approximately 1.5km to the north of the site (see Appendix S of the ES for confirmation). UU have confirmed that the trunk main has the capacity to supply the Well Pad Site without restrictions. However, due to its distance, this is not the preferred point of connection. UU’s preferred point of connection is to the 6” main in Roseacre Road. UU have undertaken hydraulic modelling and confirmed that it should be possible to meet the 765m3/day demand for the majority of the time from this 6” main in Roseacre Road with minor enabling works. To ensure that supply can be maintained to other UU customers, UU propose to install a pressure sustaining valve (PSV) to ensure that the pressure in their network is maintained to meet their supply commitments to existing customers (principally local residential properties and farms). During times of high demand on the network, the PSV would function to limit flow to the Roseacre Wood site. In such a scenario, the valve operates automatically, such that when demand on the network falls (for example during the night) Cuadrilla would be able to draw flows at a higher rate. This restriction can be overcome by providing sufficient on-site storage such that storage tanks could be filled at times of low demand. In addition, the re-use of fracturing fluid and potential use of collected rainwater would help to reduce total water demand and hence the flow rate drawn from the UU mains network.

REP/230382-10/C002 | Issue |

Cuadrilla Elswick Ltd Temporary Shale Gas Exploration at Roseacre Wood, Lancashire Utilities Statement

6.3 Foul Drainage Domestic foul drainage from site welfare facilities will be routed into temporary storage facilities on site which will then be periodically tankered to nearby wastewater treatment works. Therefore, no connection to a public sewer is required. Blackwater (toilet) and greywater (welfare) drainage will be kept separate.

6.4 Return Water Return waters refer to both ‘flowback fluids’ and ‘produced water’ returned after the hydraulic fracturing process. Flowback fluid is the proportion of the fluid used for fracturing operations which flows back to the surface on release of the pressure within the system. Flowback fluid can contain minerals, hydrocarbons and Naturally Occurring Radioactive Materials (NORM) and is returned to the surface following well stimulation. Produced waters are waters present in geological formations that may be released during the extraction of gas. The produced waters may also contain minerals, hydrocarbons and NORM. Return waters from hydraulic fracturing and flow testing will be collected and disposed of at wastewater treatment facilities specifically licenced to treat this wastewater. The quantities of return waters from the operation of the proposed development have been confirmed to be within the capacity of the individual treatment facilities.

6.5 Other Waste Waters Rainwater collected on the site during the drilling and hydraulic fracturing process will be collected and removed from site via a tanker. This waste water will be disposed of at a suitably licenced wastewater treatment works. There will also be a requirement to deal with waste drilling water and drilling muds used and generated during the well drilling phase of the project. These will be recycled on site where possible and resulting wastewater will be tankered off site to a suitably licenced wastewater treatment works.

6.6 Gas For the Extended Flow Test phase of the works a connection to the gas grid will be made in order to discharge of gas yielded from the wells and to measure the change in gas flow rate over time. Connection will be made to the National Transmission System directly to the east of the exploration site. Consultation with National Grid has confirmed that this main has sufficient capacity to accept the likely gas flows that may be generated from the site. A connection would be made via a buried 150mm diameter steel or plastic pipeline from the site. Liaison with National Grid regarding the technical detail of this connection is on-going.

REP/230382-10/C002 | Issue |

Cuadrilla Elswick Ltd Temporary Shale Gas Exploration at Roseacre Wood, Lancashire Utilities Statement

6.7 Telecommunications Broadband communications to the site will be provided via connection to the buried telecommunications infrastructure running along Roseacre Road.

REP/230382-10/C002 | Issue |

Cuadrilla Elswick Ltd Temporary Shale Gas Exploration at Roseacre Wood, Lancashire Utilities Statement

7 Utilities Supplies to the Monitoring Works

During construction of the Monitoring Works, power, water and communication requirements will be met by temporary generators, water bowsers and mobile phones. Surface Array (Traffic Light System) The surface array is a network of shallow buried seismic monitoring stations which comprise shallow pits (to a depth of approximately 0.5m below ground level) within which sensitive seismometers will be located. The installation of each surface array station will also include small junction boxes (glass reinforced plastic kiosks approximately 1.1m high and located between 1 to 3m from the seismometer). The surface array sites do not require any connection to permanent utility apparatus. They rely on mobile phone communication and battery operated equipment during operation to run the seismometer, data logging equipment, model and GPS units. Buried Array The buried array will comprise deep buried (up to a depth of approximately 100m below ground level) seismic monitoring stations containing seismometers. The surface treatment of these will comprise a small concrete pad or collar with an inspection cover mounted flush with the ground surface. The buried arrays sites do not require any connection to permanent utility apparatus. They rely on mobile phone communication and battery operated equipment during operation to run the seismometer, data logging equipment, modem and GPS units. Groundwater Monitoring Boreholes Boreholes will be sunk to allow water samples to be taken from underlying aquifers. The monitoring boreholes do not require any permanent utilities connections.

REP/230382-10/C002 | Issue |

Cuadrilla Elswick Ltd Temporary Shale Gas Exploration at Roseacre Wood, Lancashire Utilities Statement

8 Conclusions

8.1 Exploration Works A 42” high pressure gas main has been identified crossing below the proposed access route to the exploration site. Protection works may be required to enable increased HGV movements above this main. This is likely to comprise a concrete relieving slab and Cuadrilla should liaise with National Grid to agree the details of these protection works.

As part of the project, connection to this gas main is also proposed facilitate Extended Flow testing of the wells. Cuadrilla is in discussion with National Grid regarding the details of these connection works.

Records show a 6” diameter UU potable water main running alongside Roseacre Road, approximately 400m to the east of the site. A 90mm diameter branch from the 6” main continues along Roseacre Road and through the village of Roseacre. It is proposed that water is supplied to the site from the 6” main subject to the installation of a Pressure Sustaining Valve to ensure that the supply to other UU customers is maintained.

Planning permission is also sought to route some HGV traffic through the MoD’s DHFCS Inskip facility. Existing overhead communications cabling along the proposed route should be raised in order to provide increased headroom (recommended 5.4m) for development traffic to pass underneath.

The risk of potential damage to utility networks from ground born vibrations is considered extremely low as predicted maximum ground motions at the surface in the region of 0.4 to 1.8mm/s are well below those of guidance thresholds which could result in damage. The principle electrical demand from the site will be met by on-site generators. Small power (electricity) and telecommunications supplies to offices, welfare units etc. will be met via connections to the local networks located in Roseacre Road.

Foul water and other waste waters will be tankered off site to appropriately licenced wastewater treatment facilities and no connection to public sewers is to be sought.

8.2 Monitoring Works There are no anticipated impacts on existing utilities from the installation or operation of the monitoring works. During construction of the monitoring works, power, water and communication requirements will be met by temporary generators, water bowsers and mobile phones.

REP/230382-10/C002 | Issue |

Cuadrilla Elswick Ltd Temporary Shale Gas Exploration at Roseacre Wood, Lancashire Utilities Statement

The monitoring works sites do not require any connection to permanent utility apparatus. They rely on mobile phone communication and battery operated equipment during operation to power seismometers, data logging equipment, modem and GPS units.

REP/230382-10/C002 | Issue |

Appendix A Utility Record Plans

A1 Affected Utilities

Page A1

HIGH VOLTAGE POWER LINES - NAT GRID NAT - LINES POWER VOLTAGE HIGH

90mm PE WATER PE 90mm

WATER

WATER

WATER

WATER

WATER

WATER

WATER

WATER

WATER

WATER

WATER

90mm PE WATER PE 90mm

WATER

WATER

WATER

WATER

WATER

WATER

WATER WATER WATER

90mm PE WATER

WATER

WATER

WATER

WATER

WATER

WATER

WATER

WATER

WATER

WATER

WATER

WATER

WATER WATER

90mm PE WATER

WATER

WATER

WATER

WATER

WATER

WATER

WATER

WATER 90mm PE WATER

WATER

WATER

WATER

HIGH PRESS GAS MAINS GAS GAS

GAS

GAS

HIGH PRESSGAS GAS MAINS

HIGH PRESS GAS MAINS GAS GAS

HIGH PRESS GAS MAINS WATER

GAS GAS

GAS GAS

GAS GAS

GAS GAS

GAS GAS GAS

GAS GAS GAS

GAS GAS

GAS GAS

GAS

GAS

GAS GAS GAS

GAS GAS

GAS GAS

GAS GAS

GAS GAS GAS GAS GAS GAS GAS GAS GAS GAS GAS GAS GAS GAS GAS

WATER

WATER 6"WATER AC WATER

WATER

WATER

WATER

WATER

WATER

WATER

6" ACWATER WATER

WATER

WATER

WATER

WATER

6" AC WATER AC 6"

WATER

WATER

WATER

WATER

WATER

WATER

WATER

6" AC WATER AC WATER 6"

WATER

WATER

WATER

WATER

WATER

WATER

WATER WATER WATER WATER WATER WATER

WATER

WATER WATER WATER WATER AC 6"

WATER

WATER WATER WATER WATER WATER WATER WATER AC 6" 6" AC WATER AC 6" WATER 1:5000@A3 WARNING! This area contains Gas Mains Operating at High Pressure in Excess of 7 bar. Before excavating in the area call 0800 688588.

SCALE: Not to scale LP MAINS This plan shows those pipes owned by National Grid Gas plc in their role as a MAPS Viewer Version 5.6.7.0 MP MAINS Licensed Gas Transporter (GT). Gas pipes owned by other GTs, or otherwise privately owned, may be present in this area. USER ID: carol.hey Information with regard to such pipes should be obtained from the relevant owners. The information shown on this plan IP MAINS is given without warranty, the accuracy thereof cannot be guaranteed. Service pipes, valves, syphons, stub connections, DATE: 17/10/2013 LHP MAINS etc. are not shown but their presence should be anticipated. No liability of any kind whatsoever is accepted by NHP MAINS National Grid Gas plc or their agents, servants or contractors for any error or EXTRACT DATE: 16/03/2013 omission. Safe digging practices, in accordance with HS(G)47, must be used to verify and establish the actual position of mains, pipes, services and other apparatus on site before any mechanical plant is used. It is your responsibility to ensure MAP REF: SD4335 Local Machine that this information is provided to all persons (either direct labour or contractors) working for you on or near gas CENTRE: 343714, 435714 apparatus. The information included on this plan should not be referred to beyond a period of 28 days from the date This plan is reproduced from or based on the of issue. Further information on all DR4s can be determined by calling the DR4 hotline on 01455 892426 (9am-5pm) OS map by National Grid Gas plc, with the sanction A DR4 is where a potential error has been identified within the asset record and a process is currently underway to of the controller of HM Stationery Office. investigate and resolve the error as appropriate. Crown Copyright Reserved. WARNING! This area contains Gas Mains Operating at High Pressure in Excess of 7 bar. Before excavating in the area call 0800 688588.

SCALE: Not to scale LP MAINS This plan shows those pipes owned by National Grid Gas plc in their role as a MAPS Viewer Version 5.6.7.0 MP MAINS Licensed Gas Transporter (GT). Gas pipes owned by other GTs, or otherwise privately owned, may be present in this area. USER ID: carol.hey Information with regard to such pipes should be obtained from the relevant owners. The information shown on this plan IP MAINS is given without warranty, the accuracy thereof cannot be guaranteed. Service pipes, valves, syphons, stub connections, DATE: 17/10/2013 LHP MAINS etc. are not shown but their presence should be anticipated. No liability of any kind whatsoever is accepted by NHP MAINS National Grid Gas plc or their agents, servants or contractors for any error or EXTRACT DATE: 16/03/2013 omission. Safe digging practices, in accordance with HS(G)47, must be used to verify and establish the actual position of mains, pipes, services and other apparatus on site before any mechanical plant is used. It is your responsibility to ensure MAP REF: SD4336 Local Machine that this information is provided to all persons (either direct labour or contractors) working for you on or near gas CENTRE: 343736, 436069 apparatus. The information included on this plan should not be referred to beyond a period of 28 days from the date This plan is reproduced from or based on the of issue. Further information on all DR4s can be determined by calling the DR4 hotline on 01455 892426 (9am-5pm) OS map by National Grid Gas plc, with the sanction A DR4 is where a potential error has been identified within the asset record and a process is currently underway to of the controller of HM Stationery Office. investigate and resolve the error as appropriate. Crown Copyright Reserved. WARNING! This area contains Gas Mains Operating at High Pressure in Excess of 7 bar. Before excavating in the area call 0800 688588.

SCALE: Not to scale LP MAINS This plan shows those pipes owned by National Grid Gas plc in their role as a MAPS Viewer Version 5.6.7.0 MP MAINS Licensed Gas Transporter (GT). Gas pipes owned by other GTs, or otherwise privately owned, may be present in this area. USER ID: carol.hey Information with regard to such pipes should be obtained from the relevant owners. The information shown on this plan IP MAINS is given without warranty, the accuracy thereof cannot be guaranteed. Service pipes, valves, syphons, stub connections, DATE: 17/10/2013 LHP MAINS etc. are not shown but their presence should be anticipated. No liability of any kind whatsoever is accepted by NHP MAINS National Grid Gas plc or their agents, servants or contractors for any error or EXTRACT DATE: 16/03/2013 omission. Safe digging practices, in accordance with HS(G)47, must be used to verify and establish the actual position of mains, pipes, services and other apparatus on site before any mechanical plant is used. It is your responsibility to ensure MAP REF: SD4336 Local Machine that this information is provided to all persons (either direct labour or contractors) working for you on or near gas CENTRE: 343800, 436899 apparatus. The information included on this plan should not be referred to beyond a period of 28 days from the date This plan is reproduced from or based on the of issue. Further information on all DR4s can be determined by calling the DR4 hotline on 01455 892426 (9am-5pm) OS map by National Grid Gas plc, with the sanction A DR4 is where a potential error has been identified within the asset record and a process is currently underway to of the controller of HM Stationery Office. investigate and resolve the error as appropriate. Crown Copyright Reserved.

A2 Unaffected Utilities

Page A2

Debbie Miller

From: Willis, Lynda [[email protected]] Sent: 18 October 2013 14:24 To: Debbie Miller Subject: BSkyB Telecommunications Services Ltd Plant Enquiry - PEN13-10-1695 : Groundwise Searches Ltd - 12480DM

Attention: Debbie Miller - Groundwise Searches Ltd

Dear Sir/Madam,

RE: At Roseacre, Lancashire, PR4 3UE

Thank you for your enquiry.

Please be advised that BSkyB Telecommunications Services Ltd will not be affected by these works.

Best endeavours have been made to ensure accuracy, however if you require further information, please contact us. If you would like to submit your plant enquiries electronically, please send them to [email protected]

Please be advised that our fax number has changed to 0207 032 3252.

Regards

NRSWA Department Network Infrastructure and Planning BSKYB Telecommunications Services Ltd 70 Buckingham Avenue SLOUGH SL1 4PN

T +44 (0) 207 032 3234/250 F +44 (0) 207 032 3252 E [email protected]

Information in this email including any attachments may be privileged, confidential and is intended exclusively for the addressee. The views expressed may not be official policy, but the personal views of the originator. If you have received it in error, please notify the sender by return e-mail and delete it from your system. You should not reproduce, distribute, store, retransmit, use or disclose its contents to anyone. Please note we reserve the right to monitor all e-mail communication through our internal and external networks. SKY and the SKY marks are trademarks of British Sky Broadcasting Group plc and Sky International AG and are used under licence. British Sky Broadcasting Limited (Registration No. 2906991), Sky-In-Home Service Limited (Registration No. 2067075) and Sky Subscribers Services Limited (Registration No. 2340150) are direct or indirect subsidiaries of British Sky Broadcasting Group plc (Registration No. 2247735). All of the companies mentioned in this paragraph are incorporated in England and Wales and share the same registered office at Grant Way, Isleworth, Middlesex TW7 5QD.

1 Debbie Miller

From: John Shrieves [[email protected]] Sent: 18 October 2013 14:04 To: Debbie Miller Subject: RE: 12480DM - Site : At Roseacre, Lancashire, PR4 3UE - Requests: Urgent - Please Reply ASAP

You recently requested information pertaining to the above location and in relation to CityFibre Holdings Ltd plant.

I can confirm that at this current time we have NO PLANT which may be affected by your proposed works.

However, due to the nature of our works this could change dependant on the roll out of the programmes. The validity of this response is 6 weeks, after such time a new enquiry would need to be made.

Please see the points of contact below if they are required:

516 Chadwick House Road Birchwood Park Warrington WA3 6AE 0333 150 7282 [email protected]

From: Debbie Miller [mailto:[email protected]] Sent: 18 October 2013 13:56 To: [email protected]; [email protected]; 'KCOM'; 'BSKYB'; [email protected]; [email protected]; 'INSTALCOM'; 'VERIZON'; Noticing; [email protected]; [email protected] Subject: Ref: 12480DM - Site : At Roseacre, Lancashire, PR4 3UE - Requests: Urgent - Please Reply ASAP

Ref: 12480DM Site : At Roseacre, Lancashire, PR4 3UE Grid reference: Top Left-343248,436722 Top Right-344136,436989 Bottom Left-343310,435719 Bottom Right-344449,435794 Centre-343843,436289 Requests: Urgent - Please Reply ASAP

For your reference, we have provided a site plan. Please use both the grid reference/postcode & site plan when responding to our requests.

We are doing research on the above site for a client and would be grateful if you could confirm whether the above operators have any cabling or apparatus in the immediate vicinity. Should there be anything detected in the vicinity plus 50 meters around the site, I would appreciate a plan showing the location. The reason we need the information is so our client can avoid digging through your cables or can investigate the potential for connecting with your network.

I enclose location plans of the site for your convenience and look forward to hearing from you. We shall of course be providing a copy of your response to our client as part of a wider report on the site including reports from other utility companies or providers.

Should you have any problems in identifying the location of the sites or should you require further clarification of the details requested, please do not hesitate to contact me.

I look forward to receiving details from you and thank you in advance for your assistance in this matter.

Kind regards, 1 Debbie Miller

From: Plant Enquiries [[email protected]] Sent: 21 October 2013 16:29 To: Debbie Miller Subject: RE: 12480DM - Site : At Roseacre, Lancashire, PR4 3UE - Requests: Urgent - Please Reply ASAP

Dear Sir/Madam, Thank you for submitting your recent plant enquiry. Based on the information provided, I can confirm that Energetics does not have any plant within the area(s) specified in your request. Please be advised that it may take around 10 working days to process enquiries. In the unlikely event that you have been waiting longer than 10 working days, or require further assistance with outstanding enquiries, please call 01925 438052 Please ensure all plant enquiries are sent to [email protected]

Regards

Vicky Williams Plant Enquiries Team

Energetics Design & Build The White House Greenalls Avenue Warrington WA4 6HL e: [email protected] t: 01925 438052 w: www.energetics-uk.com

From: Debbie Miller [mailto:[email protected]] Sent: 18 October 2013 13:56 To: Plant Enquiries; [email protected]; 'KCOM'; 'BSKYB'; [email protected]; [email protected]; 'INSTALCOM'; 'VERIZON'; [email protected]; [email protected]; [email protected] Subject: Ref: 12480DM - Site : At Roseacre, Lancashire, PR4 3UE - Requests: Urgent - Please Reply ASAP

Ref: 12480DM Site : At Roseacre, Lancashire, PR4 3UE Grid reference: Top Left-343248,436722 Top Right-344136,436989 Bottom Left-343310,435719 Bottom Right-344449,435794 Centre-343843,436289 Requests: Urgent - Please Reply ASAP

For your reference, we have provided a site plan. Please use both the grid reference/postcode & site plan when responding to our requests.

We are doing research on the above site for a client and would be grateful if you could confirm whether the above operators have any cabling or apparatus in the immediate vicinity. Should there be anything detected in the vicinity plus 50 meters around the site, I would appreciate a plan showing the location.

1 21-Oct-2013 Our Ref: BU00008962 Your Ref: 12480DM

Energy House Woolpit Business Park Woolpit Bury St Edmunds IP32 9UP

T: 01359 243376 Toby Coyte-Broomfield E: [email protected] www.gtc-uk.co.uk Groundwise Suite 8, Chichester House, 45 Chichester Road, Southend on Sea Essex SS1 2JU

APPARATUS NOT AFFECTED

Re: Site Location: Site at Roseacre Lancashire

Grid Reference: 343843,436289

Dear Toby Coyte-Broomfield

Thank you for your enquiry concerning apparatus in the vicinity of your proposed work. Brookfield Utilities UK can confirm that we have no apparatus in the vicinity but please note that other asset owners may have and that you should ensure that all transporters/ distributors have been consulted.

Please note Brookfield Utilities UK assets now include those owned and operated by: * GTC Pipelines Limited * Independent Pipelines Limited * Quadrant Pipelines Limited * Electricity Network Company Limited * Independent Power Networks Limited * Independent Water Networks Limited * Independent Fibre Networks Limited

All future plant enquiries must contain accurate Easting and Northing references to enable us to process your enquiry efficiently.

If you have any queries or require any further information, please do not hesitate to contact me on 01359 243376.

Yours sincerely,

Danni Bourne Planning Supervisor

The Gas Transportation Company Limited (GTC) is a company registered in Guernsey, Channel Islands, registered number 29431. VAT registered number 688 8971 40 NON AFFECTED PLANT ENQUIRY SEARCH RETURN NOTIFICATION KCOM GROUP 5TH FLOOR PROSPECT HOUSE PROSPECT STREET KINGSTON UPON HULL HU2 8PU

Kingston Planner: SS Our Search Ref: 150028 Your Ref: 12480DM Undertaker Name: GROUNDWISE SEARCHES LTD Location: At Roseacre, Lancashire, PR4 3UE

With regards to your request for details of existing services in the search area supplied, we can confirm that based on the details provided to us, we have no buried plant or equipment in the identified area.

This is valid for 3 months from the date of receipt of this email.If any further information is required, please call 01482 603479, or email our group email address - [email protected]

21 October 2013 Page 1 of 1 12480DM – 21/10/2013 OFCOM

UNAFFECTED

OFCOM

Riverside House 2a Southwark Bridge Road London SE1 9HA

Tel: 020 7981 3040

OFCOM

You may wish to contact the mobile phone operators directly. Links to their websites are provided below along with specific contact details for enquiries relating to mobile phone masts. If you are enquiring about a particular mast please quote the Operator Site Ref.

Airwave T-Mobile Orange O2 UK

Airwave Solutions Limited Hatfield Business Park Orange Personal Communication Telefonica O2 Europe plc Wellington Street Hatfield Services Ltd Network Consultation Help Desk Slough Hertfordshire St James Court 1 Brunel Way Berks AL10 9BW Great Park Road Slough SL1 1YP Almondsbury Berkshire Tel: 0870 321 6047 Bristol SL1 1XL Telephone: +44 (0)8000 11 33 99 BS32 4QJ Fax: 01707 319022 Telephone: 01753 564 306 Fax: 020 7557 9000 Telephone: 0870 376 Email: [email protected] Fax: 0870 376 4770 Fax: 08715 289 235 Email:ServiceDesk.Receptionist@airw avesolutions.co.uk Web: http://www.t-mobile.co.uk Email: Email: [email protected] Site.Information@everythingeverywh Web: ere.com Web: http://www.o2.com/ http://www.airwavesolutions.co.uk/ Web: http://www.orange.co.uk/

Network Rail Vodafone 3

Community Relations EMF Advisory Unit 5 Hester House Network Rail Battersea Vodafone Ltd 40 Melton Rail London London The Exchange SW11 4AN NW1 2EE Building 1330 Arlington Business Park Telephone: 0800 9177354 Telephone: 08457 11 41 41 Theale Or 01628 765000 RG7 4SA Fax: 020 7557 9000 Email: DLCTO3rdLineTechnicalSupport@thre Telephone: 01635 677706 Email: e.co.uk RailwayCommunicationsSystem@net workrail.co.uk Fax: 01635 234858 Web: www.three.co.uk

Web: http://www.networkrail.co.uk/ Email: [email protected]

OFCOM

Riverside House 2a Southwark Bridge Road London SE1 9HA

Tel: 020 7981 3040

12480DM – 21/10/13 ORANGE

UNAFFECTED

For Orange UK Plant Search support contact May Gurney IS Support team: 01603-727399

Debbie Miller

From: careline [[email protected]] Sent: 21 October 2013 09:57 To: Debbie Miller Subject: RE: 12480DM - Site : At Roseacre, Lancashire, PR4 3UE - Requests: Urgent - Please Reply ASAP

This location is NOT AFFECTED by TATA or KPN apparatus.

Please note:

McNicholas, on behalf of our client, accept no liability for claims arising from inaccuracies, omissions or errors contained within your plant enquiry request.

If you require further information please do not hesitate to contact us.

Regards

McNicholas Plant Enquiry Team

Email - [email protected] Telephone – 0330 055 8466/8469 Facsimile – 01923 802704

Website - www.mcnicholas.co.uk

Our team. Your solution.

From: Debbie Miller [mailto:[email protected]] Sent: 18 October 2013 13:56 To: [email protected]; [email protected]; 'KCOM'; 'BSKYB'; [email protected]; plantenquiries; 'INSTALCOM'; 'VERIZON'; [email protected]; [email protected]; [email protected] Subject: Ref: 12480DM - Site : At Roseacre, Lancashire, PR4 3UE - Requests: Urgent - Please Reply ASAP

Ref: 12480DM Site : At Roseacre, Lancashire, PR4 3UE Grid reference: Top Left-343248,436722 Top Right-344136,436989 Bottom Left-343310,435719 Bottom Right-344449,435794 Centre-343843,436289 Requests: Urgent - Please Reply ASAP

For your reference, we have provided a site plan. Please use both the grid reference/postcode & site plan when responding to our requests.

1 12480DM – 21/10/13

UNAFFECTED

Trafficmaster Ltd

Martell House University Way Cranfield BEDS MK43 0TR

Switchboard: +44 (0)1234 759000

Fax: +44 (0)1234 759145

Debbie Miller

From: UK OSP-Team [[email protected]] Sent: 21 October 2013 09:59 To: Debbie Miller Subject: RE: Ref: 12480DM - Site : At Roseacre, Lancashire, PR4 3UE - Requests: Urgent - Please Reply ASAP

Dear Sirs

Verizon Business is a licensed Statutory Undertaker.

We have reviewed your plans and have determined that Verizon Business (Formally known as MCI WorldCom, MFS) has no apparatus in the areas concerned.

If you have any further queries please do not hesitate to call.

Yours faithfully

Chris Pile

Plant Protection Officer E.mail [email protected]

Chris.Pile Plant Protection Officer OSP-Infrastructure Field Operations, UK Office:01293 611736

Mobile:07990 774438 www.verizon.com

From: Debbie Miller [mailto:[email protected]] Sent: 18 October 2013 13:56 To: [email protected]; [email protected]; 'KCOM'; 'BSKYB'; [email protected]; [email protected]; 'INSTALCOM'; UK OSP-Team; [email protected]; [email protected]; [email protected] Subject: Ref: 12480DM - Site : At Roseacre, Lancashire, PR4 3UE - Requests: Urgent - Please Reply ASAP

Ref: 12480DM Site : At Roseacre, Lancashire, PR4 3UE Grid reference: Top Left-343248,436722 Top Right-344136,436989 Bottom Left-343310,435719 Bottom Right-344449,435794 Centre-343843,436289 Requests: Urgent - Please Reply ASAP

For your reference, we have provided a site plan. Please use both the grid reference/postcode & site plan when responding to our requests.

We are doing research on the above site for a client and would be grateful if you could confirm whether the above operators have any cabling or apparatus in the immediate vicinity. Should there be anything detected in the vicinity plus 50 meters around the site, I would appreciate a plan showing the location. The reason we need the information is so our client can avoid digging through your cables or can investigate the potential for connecting with your network.

1 Debbie Miller

From: Kumar, Krishnaraj [[email protected]] Sent: 21 October 2013 11:46 To: Debbie Miller Subject: RE: 12480DM - Site : At Roseacre, Lancashire, PR4 3UE - Requests: Urgent - Please Reply ASAP

This response is made only in respect to electronic communications apparatus forming part of the Vodafone Limited electronic communications network formerly being part of the electronic communications networks of Cable & Wireless UK, Energis Communications Limited, Thus Group Holdings Plc and Your Communications Limited.

Please accept this email as confirmation that Vodafone does not have apparatus within the vicinity of your proposed works detailed below.

Many thanks.

Plant Enquiries Team T: 01454 662881 E: [email protected]

ATKINS working on behalf of

PLEASE NOTE:

The information given is indicative only. No warranty is made as to its accuracy. This information must not be solely relied upon in the event of excavation or other works carried out in the vicinity of Vodafone plant. No liability of any kind whatsoever is accepted by Vodafone, its servants, or agents, for any error or omission in respect of information contained on this information. The actual position of underground services must be verified and established on site before any mechanical plant is used. Authorities and contractors will be held liable for the full cost of repairs to Vodafone's apparatus and all claims made against them by Third parties as a result of any interference or damage.

Diversionary works may be necessary if the existing line of the highway/railway or it's levels are altered, where apparatus is affected. Where apparatus is affected and requires diversion, you must submit draft details of the proposed scheme with a written request for a 'C3 Budget Estimate' to the above address. These estimates should be provided normally within 20 working days from receipt of your written request. Please include proof of this C2 response when requesting a C3.  Please consider the environment before printing this e-mail

From: Debbie Miller [mailto:[email protected]] Sent: 18 October 2013 18:26 To: [email protected]; National Plant Enquiry's; 'KCOM'; 'BSKYB'; [email protected]; [email protected]; 'INSTALCOM'; 'VERIZON'; [email protected]; [email protected]; [email protected] Subject: Ref: 12480DM - Site : At Roseacre, Lancashire, PR4 3UE - Requests: Urgent - Please Reply ASAP

Ref: 12480DM Site : At Roseacre, Lancashire, PR4 3UE Grid reference: Top Left-343248,436722 Top Right-344136,436989 Bottom Left-343310,435719 Bottom Right-344449,435794 Centre-343843,436289 Requests: Urgent - Please Reply ASAP

1 Debbie Miller

From: Plant enquiries [[email protected]] Sent: 25 October 2013 09:07 To: Debbie Miller Subject: RE: 12480DM - Site : At Roseacre, Lancashire, PR4 3UE - Requests: Urgent - Please Reply ASAP

Dear Sir/Madam,

Thank you for your enquiry for the above reference.

We can confirm that Colt Technology Services do not have apparatus near the above location.

Search is based on Overseeing Organisation Agent data supplied; we do not accept responsibility for O.O. Agent inaccurate data.

If we can be of any further assistance please do not hesitate to contact us.

Kind regards,

Plant Enquiry Team

Please consider the environment before printing this email.

This e-mail and any files transmitted with it are confidential and are intended solely for the use of the intended recipient(s). If you are not the intended recipient, you must not copy, distribute or take any action based on this communication. If you have received this communication in error please contact [email protected] and delete this communication and any copies of it. Any views or opinions presented are solely those of the author and do not necessarily represent those of C A Telecom LTD. C A Telecom LTD monitors e-mails to ensure that its systems operate effectively and to minimise the risk of viruses.

From: Debbie Miller [mailto:[email protected]] Sent: 18 October 2013 13:56 To: [email protected]; [email protected]; 'KCOM'; 'BSKYB'; [email protected]; [email protected]; 'INSTALCOM'; 'VERIZON'; [email protected]; [email protected]; [email protected] Subject: Ref: 12480DM - Site : At Roseacre, Lancashire, PR4 3UE - Requests: Urgent - Please Reply ASAP

Ref: 12480DM Site : At Roseacre, Lancashire, PR4 3UE Grid reference: Top Left-343248,436722 Top Right-344136,436989 Bottom Left-343310,435719 Bottom Right-344449,435794 Centre-343843,436289 Requests: Urgent - Please Reply ASAP

1

Debbie Miller

From: Interoute Enquiries [[email protected]] Sent: 18 October 2013 14:02 To: Debbie Miller Subject: RE: 12480DM - Site : At Roseacre, Lancashire, PR4 3UE - Requests: Urgent - Please Reply ASAP

To whom it may concern

Thank you for your enquiry regarding the above proposals at the above location

We would advise that we are unaware of any Interoute plant or services in this Location as indicated in your enquiry.

We bring to your attention the fact that whilst we try to ensure the information we provide is accurate, the information is provided Without Prejudice and Interoute and its Agents accept no liability for claims arising from any inaccuracy, omissions or errors contained in this response.

All responses are only vaild for 28 days

Yours faithfully

PLANCAST Plant Enquiry Department

The Old Haybarn Rosebery Mews, Mentmore Bedfordshire LU7 0UE

T: 01296 662647 www.plancast.co.uk

Save Paper - Do you really need to print this email? This email and any attachments are or may be confidential and legally privileged and are sent solely for the attention of the addressee(s). If you have received this email in error, please delete it from your system: it's use, disclosure or copying is unauthorised. Statements and opinions expressed in this email may not represent those of PLANCAST. Any representations or commitments in this email are subject to contract.

Registered office: 1st Floor, The Old Haybarn, Rosebery Mews, Mentmore LU7 0UE. Registered in England and Wales with number 4455025 VAT No. 8567 195 80

From: Debbie Miller [mailto:[email protected]] Sent: 18 October 2013 13:56 To: [email protected]; [email protected]; 'KCOM'; 'BSKYB'; [email protected]; [email protected]; 'INSTALCOM'; 'VERIZON'; [email protected]; Interoute Enquiries; [email protected] Subject: Ref: 12480DM - Site : At Roseacre, Lancashire, PR4 3UE - Requests: Urgent - Please Reply ASAP

Ref: 12480DM

1

Debbie Miller Virgin Media Groundwise Field Services Suite 8 Chichester House Units 1-12 45 Chichester Road Broad Lane Southend on Sea Mayfair Business Park SS1 2JU Bradford Yorkshire BD4 8PW

Tel: 0870 888 3116 Opt 2 Fax: 01268 468557

Plant Enquiry Ref: VM/CIP/175947 Your Letter Date: 21/10/2013 Your Ref: 12480DM Date: 29/10/2013

Dear Mrs Miller

Enquiry Location: At Roseacre, Lancashire PR4 3UE

Thank you for your enquiry regarding work at the above location.

Virgin Media and Viatel plant should not be affected by your proposed work and no strategic additions to our existing network are envisaged in the immediate future.

Should your request be in relation to a New Development and you require an estimate to be prepared for Virgin Media to service your proposed development, please submit this request for costs along with site drawings (scale 1:500) to:

Virgin Media New Build Virgin Media 1 Dove Wynd Strathclyde Business Park Bellshill ML4 3AL

This information is only valid on the date of issue. If your start date is 3 months or more from the date of this letter, please re-apply for updated information.

Yours faithfully,

National Plant Enquiries Team email: [email protected]

Please note: National Plant Enquiries Team (Bradford) cover and respond to plant enquiries for all ex ntl:Telewest franchise areas.

www.cuadrillaresources.com

www.arup.com