The World Bank Report No: ISR8135

Implementation Status & Results Benin Emergency Urban Env. Project (P113145)

Operation Name: Benin Emergency Urban Env. Project (P113145) Project Stage: Implementation Seq.No: 3 Status: ARCHIVED Archive Date: 29-Oct-2012 Country: Benin Approval FY: 2011 Product Line:IBRD/IDA Region: AFRICA Lending Instrument: Emergency Recovery Loan Implementing Agency(ies): AGETUR, SERHAU Key Dates Board Approval Date 26-Apr-2011 Original Closing Date 31-Dec-2015 Planned Mid Term Review Date 09-Dec-2013 Last Archived ISR Date 02-May-2012 Public Disclosure Copy Effectiveness Date 13-Dec-2011 Revised Closing Date 31-Dec-2015 Actual Mid Term Review Date

Project Development Objectives Project Development Objective (from Project Appraisal Document) To improve infrastructure and mitigate the negative environmental impact of floods in Agglomeration and to increase Benin level of preparedness for future flooding. Has the Project Development Objective been changed since Board Approval of the Project?

Yes No

Component(s)

Component Name Component Cost 1. Drainage Improvement and Rehabilitation 23.56 2. Municipal Solid Waste Management 13.82 3. Improved Municipal Wastewater Management and Sanitation 4.70 4. Flooding and Disaster Risk Preparedness and Management 5.03 5. Project Management 2.89

Overall Ratings Previous Rating Current Rating Progress towards achievement of PDO Satisfactory Satisfactory Overall Implementation Progress (IP) Satisfactory Satisfactory Overall Risk Rating Low Low

Implementation Status Overview Public Disclosure Copy The project implementation is progressing satisfactorily. The project received the initial project advance of USD$ 2.7 million in early June 2012 and project activities in the five components

Page 1 of 7 The World Bank Report No: ISR8135

have long started. Recently (September 2012) due to the floods occasioned by the over-flowing of the Niger River in Northern Benin, the project mobilized a team to the various communities; in particular and Karimama. The team held sensitization sessions with the communities on behavior change before, during and after flooding; adaptation mechanisms; and basic hygiene most especially boiling and filtering water before drinking.

Key terms of references have been cleared and the following contracts are about to be signed: (i) EIA of the drainage channels (P, AA, W2 and Wbis) and the Fifadji bridge; (ii) technical studies and supervio supervisory works for the construction of Fifadji bridge; (iii) sensitization and communication aspects of flooding and Disaster Risk Management; (iv) technical studies and supervisory works on the opening of a new cell and rehabilitation of the access road to the Ouesse landfill site; (v) sensitization of the Public on municipal wastes; (vi) environmental audit of the existing landfill cell and EIA of the access road to the landfill sites; and (vii) peer educators and community first responders in the municipalities. Public Disclosure Copy

The following consultancies are ongoing: (i) organizational and financial study of solid waste pre-collection in Abomey-Calavi and Seme-Kpodji; and (iii) technical and economic feasibility study of municipal solid waste management system in the selected municipalities of Cotonou, Abomey-Calavi, , Seme-Kpodji, and Porto Novo. On the whole implementation status is satisfactory and it is expected that December / early January 2013, the civil works will commence.

Locations Country First Administrative Division Location Planned Actual Benin Not Entered Porto-Novo

Benin Not Entered Ouidah

Benin Not Entered Ouesse

Benin Not Entered Lac Nokoue

Benin Not Entered Cotonou

Benin Not Entered Abomey-Calavi

Benin Not Entered Porto-novo

Benin Not Entered AguZguZs

Benin Not Entered Seme-kpodji

Benin Not Entered Cotonou

Benin Not Entered Sainte-Rita

Public Disclosure Copy Benin Not Entered Fifadji

Benin Not Entered Fidjrosse-

Page 2 of 7 The World Bank Report No: ISR8135

Country First Administrative Division Location Planned Actual Benin Not Entered Fiyegnon

Benin Not Entered Avotrou

Benin Not Entered Akpakpa

Benin Not Entered Seme-Podji

Benin Not Entered Abomey-Calavi

Benin Not Entered So-ava Public Disclosure Copy Results

Project Development Objective Indicators Indicator Name Core Unit of Measure Baseline Current End Target Percentage reduction of households vulnerable Percentage Value 70.00 70.00 30.00 to flooding in the targeted municipalities as a Date 26-Apr-2011 08-Oct-2012 31-Dec-2015 result of improved infrastructure Comments 70% of households vulnerable The contracts for the technical By project end, there will be to flooding in the targeted studies and EIAs of the 30% reduction of households municipalities due to clogged rehabilitation of clogged vulnerable to flooding in the drainage infrastructure. drains and channels that targeted municipalities as a would lead to improved result of improved drainage drainage and reduced infrastructure. flooding is about to be signed. Number of alerts on flood risks issued per year Number Value 0.00 0.00 20.00 using the Flood Early Warning System Date 26-Apr-2011 08-Oct-2012 31-Dec-2015 Comments There are no alerts on flood The negotiation of the By project end, 20 alerts on risks due to lack of Flood contract for the flood early flood risks would have been Early Warning System. warning system of the Oueme issued per year using the river is ongoing. Further, the Flood Early Warning System. process for the purchase of 25 hydro-metric stations to aid in the warning process has reached an advance stage.

Intermediate Results Indicators Public Disclosure Copy

Page 3 of 7 The World Bank Report No: ISR8135

Indicator Name Core Unit of Measure Baseline Current End Target Length of drainage network rehabilitated Kilometers Value 0.00 0.00 8.60 Date 26-Apr-2011 08-Oct-2012 31-Dec-2015 Comments Clogged drainage networks in No change as yet; as the The By project end, 8.6 kilometers the targeted areas. contracts for the technical of drainage network studies and EIAs of the rehabilitated. rehabilitation of clogged drains and channels are about to be signed. Rehabilitation of Fifadji Bridge Yes/No Value No No Yes Date 26-Apr-2011 08-Oct-2012 31-Dec-2015 Public Disclosure Copy Comments The Fifadji bridge in a bad The contracts for the EIA, By end of project, the Fifadji state and not rehabilitated technical studies and bridge has been rehabilitated supervisory works for the rehabilitation/construction of the Fifadji bridge has been finalized and approved by the Bank; and is due for signature. Number of municipal solid waste collection Number Value 13.00 13.00 40.00 points and/or transfer stations constructed and Date 26-Apr-2011 08-Oct-2012 31-Dec-2015 operational Comments operational collection points The economic and technical By project end, 40 solid waste constructed by PGUD-2 and feasibility study of the solid collection points and/or CIDA available in the 5 waste management system in transfer stations constructed municipalities. Benin and in particular in the and operational in the 5 selected municipalities is adjoining municipalities. ongoing. The results of this study will form the blue print for the civil works with respect to the construction of collection points, controlled dump sites and transfer stations in the five participating municipalities. Direct project beneficiaries Number Value 695000.00 700000.00 1401000.00 Date 26-Apr-2011 08-Oct-2012 31-Dec-2015 Comments At baseline direct project For now, not much has been By project end, 1401000 beneficiaries are estimated at done as most civil works have beneficiaries will have not commenced yet. However benefited from the project, out Public Disclosure Copy

Page 4 of 7 The World Bank Report No: ISR8135

695000, out of which 361400 about 5000 persons benefited of which 729000 (52%) are (52%) are female. from the sensitization females. workshops on behavior change before. during and after flooding. This was undertaken in the communities of Karimama and Malanville in northern Benin due to the overflow of the Niger River. Female beneficiaries Percentage Value 52.00 52.00 52.00 Sub Type

Public Disclosure Copy Supplemental Wastewater master plan developed for Yes/No Value No No Yes Cotonou Agglomeration (composed of Date 26-Apr-2011 08-Oct-2012 31-Dec-2015 Cotonou, Abomey-Calavi and Seme-Podji) and Porto Novo Comments There are no wastewater The evaluation of the short- By project end, the master plans for Cotonou listed consultants on the wastewater master plan for agglomeration and Porto technical assistance to Cotonou Agglomeration and Novo. SONEB (the national water Porto Novo will be available. supply agency) with respectto wastewater management is ongoing. It is only when this technical assistance is in place that other activities in the component such as the development of wastewater master plans (covering Cotonou, Abomey-Calavi and Seme-Podji) and the wastewater and drainage pilot project will be undertaken. Pilot low-cost small scale sanitation project Yes/No Value No No Yes implemented and operational Date 26-Apr-2011 08-Oct-2012 31-Dec-2015 Comments Absence of operational The evaluation of the short- By project end, there will be sanitation project (even listed consultants on the pilot low-cost small scale smalll-scale). technical assistance to sanitation project that has SONEB (the national water been implemented and is supply agency) with respectto operational. wastewater management is ongoing. It is only when this technical assistance is in Public Disclosure Copy place that other activities in

Page 5 of 7 The World Bank Report No: ISR8135

the component such as the development of wastewater master plans (covering Cotonou, Abomey-Calavi and Seme-Podji) and the wastewater and drainage pilot project will be undertaken. Targeted municipalities with Communal Flood Number Value 2.00 2.00 22.00 Contingency Plans Date 26-Apr-2011 08-Oct-2012 31-Dec-2015 Comments Communal flood contingency The following contracts are By project end, 22 communal plans funded by the UNDP in about to be signed: (i) flood contingency plans would two communities in the sensitization of the grand have been prepared and Public Disclosure Copy targeted municipalities public on inundations; and (ii) operationalized in the proximity sensitization, pair targeted municipalities. educators and implementation of contingency plans; and the following ToRs are in the process of being finalized: (i) cartography of inundated zones; and (ii) organizational analysis of national management of disaster response. Installation of Flood Early Warning System Yes/No Value No No Yes (FEWS) Date 26-Apr-2011 08-Oct-2012 31-Dec-2015 Comments Lack of FEWS in the country. Negotiation of the contract for By project end, there will be The GTZ has done some the Early Warning System of installation of Flood Early feasibility studies on the Mono inundation of the Oueme Warning System (FEWS) on River. River is ongoing. The process the Oueme River. of the purchase of 25 hydro- metric stations is ongoing

Data on Financial Performance (as of 25-Apr-2012)

Financial Agreement(s) Key Dates Project Ln/Cr/Tf Status Approval Date Signing Date Effectiveness Date Original Closing Date Revised Closing Date P113145 IDA-49370 Effective 26-Apr-2011 07-Jun-2011 13-Dec-2011 31-Dec-2015 31-Dec-2015

Disbursements (in Millions) Project Ln/Cr/Tf Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed

Public Disclosure Copy P113145 IDA-49370 Effective XDR 31.60 31.60 0.00 2.25 29.35 7.00

Page 6 of 7 The World Bank Report No: ISR8135

Disbursement Graph Public Disclosure Copy

Key Decisions Regarding Implementation The project implementation status is satisfactory. Recently (September 2012) due to the floods occasioned by the over-flowing of the Niger River in Northern Benin, the project mobilized a team to the various communities; in particular Malanville and Karimama. The team held sensitization sessions with the communities on behavior change before, during and after flooding; adaptation mechanisms; and basic hygiene most especially boiling and filtering water before drinking. it is expected that December / early January 2013, the civil works will commence; at that time all ongoing technical studies and safeguards documents would have been completed and validated.

Restructuring History There has been no restructuring to date.

Related Projects There are no related projects. Public Disclosure Copy

Page 7 of 7