EX33.1 ATTACHMENT 5

REGIONAL EXPRESS RAIL – ENABLING WORKS UPDATE

Project Description Current Status Early stations improvements include a variety of off-corridor work on existing stations on the GO Network. Includes: rail platform edge tile Early GO Rail installations, new digital signage, elevator RFP issued Station modernization, secured bike parking, electric March 29, 2018. Improvements vehicle charging stations, station access, provision for future retail, and State of Good Repair (SOGR). This project involves double tracking the corridor from Unionville Station to . It includes the realignment of the existing tracks, the addition of a new track, layout/grading work, installation of noise walls, signal works, retaining Stouffville GO walls, widening of bridges, extension of Construction is Rail Corridor pedestrian underpass, crash wall protection, underway. Improvements upgrade at level crossings, extension of culverts and protection of existing signals/utilities. interchange improvements with TTC and the future Eglinton Crosstown LRT (ECLRT) will be delivered as part of the ECLRT project. Double tracking along the 58-kilometre GO Environmental GO Rail corridor between and Aurora, Assessment Corridor three major bridge expansions, new road Notice to Improvements crossings, and track and signalling to support proceed received 15-minute two-way all-day service. October 2017. Park Downsview Park GO Station: adjoining the GO Station in Downsview Park TTC Subway Station currently service; under construction. Scope includes a new construction was platform and ticket sales. completed January 2018. Barrie GO Rail Caledonia GO Station: Located at Eglinton and Corridor Stations the Barrie Corridor, and will link the Eglinton Design to be Crosstown LRT with the Barrie GO Rail Corridor. completed late Scope includes new platforms, new station 2018 with building, pedestrian bridge linking to the construction Caledonia Crosstown Station, and a platform starting early canopy. 2019. Regional Express Rail – Enabling Works Update 1 Project Description Current Status Stouffville GO Station modifications at Agincourt GO, Milliken Rail Corridor Contract GO and Unionville GO stations, and construction Stations and awarded on of a new road under rail grade separation at March 8, 2018. Steeles Avenue, adjacent to Milliken GO Station. Grade Separation Construction of a new, two-track tunnel under Contract the Highway 401/409 interchange, including Highway 401/409 awarded on grading, retaining wall(s) and related works from Rail Tunnel December 14, west of Islington Avenue to east of Kipling 2017. Avenue. Construction of a new bus terminal to accommodate MiWay and GO buses (which will Contract Kipling GO Bus replace the existing facilities at the Islington awarded on Terminal Subway Station), new accessible pedestrian March 22, 2018. connections to the GO Rail Platform and TTC subway, and parking replacement for the TTC. Design work to be completed in spring 2018.

Accommodate new third track, new station Work on the building, new tunnel, existing platform Rouge Hill GO addendum for rehabilitation, new connection to Port Union Station the to Waterfront Park, and electrification enabling Pickering third works. track EA that is required for the park connection commenced in July 2017. New third track between Guildwood GO station and Beechgrove Drive, which will include Lakeshore East grading, retaining walls, culvert extensions and RFP expected to GO Rail Corridor the construction of three new road under rail be issued in (Central Corridor grade separations at Morningside Avenue, spring 2018. Expansion) Galloway Road, and Scarborough Golf Club Road. New third track between Beechgrove Drive and Lakeshore East Durham Junction and includes grading, retaining RFP issued GO Rail Corridor walls, culvert extensions and the expansion and November 17, (East Corridor upgrading of Highland Creek and Rouge River 2017. Expansion) bridges.

Regional Express Rail – Enabling Works Update 2 Project Description Current Status Infrastructure required for a new fourth track between Scarborough Junction and Don River Lakeshore East Detailed design and includes grading, retaining walls and culvert GO Rail Corridor is underway. extensions and the expansion of the Danforth (West Corridor RFQ issued on Avenue, Warden Avenue, Birchmount Road and Expansion) March 2, 2018. Woodbine Avenue bridges and improvements to Danforth GO station. Eliminate the existing at grade crossing at Mile RFP issued on Davenport 4.6 between the single track GO Newmarket February 28, Diamond subdivision (Barrie Corridor) and the two tracks 2018. of the CP North Subdivision. Includes tunnels and platform upgrades at Lakeshore West RFQ issued on Exhibition GO station; full station rehabilitation at GO Rail Corridor December 7, GO and Long Branch GO stations; and Improvements 2017. various other corridor and station improvements. Work includes track construction to support RER service levels with allowances for future stations at St. Clair Avenue and , grading, Construction Kitchener GO Bloor Street bridge realignment, West Toronto commenced on Rail Corridor rail realignment and connection to the City fourth track in Improvements of Toronto Phase 2 rail path, and Bloor GO August 2017. station connection to Dundas TTC Subway station. RFP for new A variety of initiatives including three new east south platform approach tracks and crossovers to facilitate expected to be increases train routing capacity into Union issued in April Station; additional west approach mainline 2018. capacity and increased track speed capabilities; Union Station a new Bay Concourse that increases overall Rail Corridor and concourse capacity and adds retail and vertical TPAP Notice of Revitalization access and a new bus terminal at 81 Commencement to replace and double the capacity of the current for the East terminal. This bus terminal project is being Track work undertaken in partnership with a private expected to be developer. issued April 2018.

This attachment was prepared by .

Regional Express Rail – Enabling Works Update 3