Public Disclosure Copy The World Bank Implementation Status & Results Report Guiyang Guangzhou Railway (P107559)
Guiyang Guangzhou Railway (P107559)
EAST ASIA AND PACIFIC | China | Transport & ICT Global Practice | IBRD/IDA | Specific Investment Loan | FY 2009 | Seq No: 10 | ARCHIVED on 22-Dec-2015 | ISR21785 |
Implementing Agencies: China Railway Corporation
Key Dates
Key Project Dates
Bank Approval Date:16-Apr-2009 Effectiveness Date:26-Aug-2009 Planned Mid Term Review Date:31-Dec-2015 Actual Mid-Term Review Date:-- Original Closing Date:31-Dec-2015 Revised Closing Date:31-Dec-2015
Project Development Objectives
Project Development Objective (from Project Appraisal Document) The development objective of the project is to provide additional transport capacity and reduce transport time between the less developed western region in southwest China and the relatively more developed Pearl River delta region.
Has the Project Development Objective been changed since Board Approval of the Project Objective? No
PHRPDODEL
Components
Name GuiGuang Railway:(Cost $12527.00 M)
Overall Ratings
Name Previous Rating Current Rating
Progress towards achievement of PDO Satisfactory Satisfactory Overall Implementation Progress (IP) Moderately Satisfactory Satisfactory Overall Risk Rating Low Low
Implementation Status and Key Decisions
The project has constructed a new double track, electrified, signaled railway line between Guiyang and Guangzhou. Originally the line was planned to
12/22/2015 Page 1 of 6 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Guiyang Guangzhou Railway (P107559)
be a mixed freight and passenger line. However, after changes to the Medium and Long Term Railway Network plan, the line was changed to a higher speed (250 kph) passenger-only line. The project was restructured February 6, 2013, to reflect this change. The 847 km long railway was put into operation at the designed maximum speed of 250 km/h on December 26, 2014, and no significant technical problems have been reported. At present, 15 pairs of stopping trains are operated daily between Guiyang and Guilin and 25 pairs of trains between Guilin and Guangzhou. In addition, one train pair daily runs direct between Guiyang and Guangzhou. Travel time has decreased from about 24 hours to just over four hours.
12/22/2015 Page 2 of 6 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Guiyang Guangzhou Railway (P107559)
Risks
Systematic Operations Risk-rating Tool
Risk Category Rating at Approval Previous Rating Current Rating
Political and Governance -- Low Low Macroeconomic -- Low Low Sector Strategies and Policies -- Low Low Technical Design of Project or Program -- Low Low Institutional Capacity for Implementation and -- Low Low Sustainability Fiduciary -- Low Low Environment and Social -- Moderate Moderate Stakeholders -- Low Low Other -- -- Low Overall -- Low Low
Results
Project Development Objective Indicators
12/22/2015 Page 3 of 6 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Guiyang Guangzhou Railway (P107559)
PHINDPDOTBL
Average number of pairs of express passenger trains operated per day (Text, Custom)
Baseline Actual (Previous) Actual (Current) End Target
25 Guilin-Guangzhou, 24 Guilin-Guangzhou, Value 3 15 Guiyang-Guilin, 1 20 11 Guiyang-Guilin Guiyang - Guangzhou
Date 31-Dec-2008 27-Mar-2015 01-Dec-2015 31-Dec-2016
PHINDPDOTBL
Average travel time of express passenger trains (minutes). (Text, Custom)
Baseline Actual (Previous) Actual (Current) End Target
Value 1500 249 251 250
Date 31-Dec-2008 27-Mar-2015 01-Dec-2015 31-Dec-2016
Overall Comments
Intermediate Results Indicators
PHINDIRITBL
% of Bank-financed goods contracted (by value) (Text, Custom)
Baseline Actual (Previous) Actual (Current) End Target
Value 0 100% 100% 100
Date 31-Dec-2008 31-Dec-2014 31-Dec-2014 31-Dec-2014
PHINDIRITBL
% of civil works completed (physical % complete) (Text, Custom)
Baseline Actual (Previous) Actual (Current) End Target
Value 0 100% 100% 100
Date 31-Dec-2008 31-Dec-2014 31-Dec-2014 31-Dec-2014
Overall Comments
12/22/2015 Page 4 of 6 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Guiyang Guangzhou Railway (P107559)
Data on Financial Performance
Disbursements (by loan)
Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed Disbursed
P107559 IBRD-76780 Effective USD 300.00 300.00 0.00 289.30 10.70 96%
Key Dates (by loan)
Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date
P107559 IBRD-76780 Effective 16-Apr-2009 03-Jun-2009 26-Aug-2009 31-Dec-2015 31-Dec-2015
Cumulative Disbursements
Restructuring History
Level Approved on 06-Feb-2013
12/22/2015 Page 5 of 6 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Guiyang Guangzhou Railway (P107559)
Related Project(s)
There are no related projects.
12/22/2015 Page 6 of 6 Public Disclosure Copy