1 Micron Sample Chamber Preliminary Design Review
DESIGN REVIEW REPORT Report No. TR-391-003-20-0
The Design Review Report Shall include at a minimum: The title of the item or system; Findings/List of Action Items – these are items A description of the item; that require formal action and closure in writing Design Review Report Number; for the review to be approved. See SLAC The type of design review; Document AP-391-000-59 for LUSI Design The date of the review; Review Guidelines. The names of the presenters Concerns – these are comments that require The names, institutions and department of the action by the design/engineering team, but a reviewers response is not required to approve the review The names of all the attendees (attach sign-in Observations – these are general comments and sheet) require no response Completed Design Checklist.
TYPE OF REVIEW: Preliminary Design Review WBS: 1.3 Coherent X-ray Imaging Title of the Review 1 micron Sample Chamber Preliminary Design Review Presented By: Armin Busse, Paul Montanez, Sébastien Boutet Report Prepared By: Date: Reviewers/Lab : John Arthur/ SLAC John Bozek/ SLAC Nicholas Kelez/ LBNL
Distribution:
Attachments: Review Slides Design Checklist Calculations Other Purpose/Goal of the Review: • Assess the completeness of the physics and engineering requirements for the CXI 1 micron Sample Chamber • Review the preliminary design of the CXI 1 micron Sample Chamber and evaluate how well it meets the requirements • Review the interfaces that have been identified and how well they have been communicated to the relevant parties (includes controls and software interfaces, safety review committees) • Assess plans for fabrication, assembly, testing and inspection, and maintenance • Review the cost estimate and schedule. • Identify high-risk elements and evaluate plans to mitigate the risk. • Identify safety issues
Comment on whether the component design is ready to proceed to final design
Form AP-391-000-59-0 Design Review Report
Introduction and outcome summary of the review: The design for the 1-micron system sample chamber appears to be appropriately detailed for this stage of the design process. The review committee did not express any major concerns regarding the design choices made so far, and the design team is urged to continue with the final design process. A few specific issues that should be addressed as part of the final design are given below, as well as general observations about the major design choices that have been made.
Findings/Action Items: The following issues should be addressed during the final design process, and the resulting decisions should be explained at the final design review:
• The vibration environment of the chamber should be considered, and the choice between using a rigid attachment to the floor vs a vibration-damping attachment should be explained. • The stability and alignment requirements of the system should be compiled. A breakdown of how each subassembly/subsystem contributes to that tolerance budget should be presented. • A calculation of the stability of the target position on the breadboard mounted to the vacuum chamber and series of linear and rotary stages should be carried out, particularly considering the long travel stages. • The system was specified to be 1800 lbs, close to the 2000 lb limit of the crane. Care should be taken in the lifting plan to ensure that the weight limit of the crane is not exceeded. Additionally, plans for rigging and fixturing the chamber should be included in the design. • The large number of in-vacuum motions create many possible clash configurations. Plans for limiting travel and preventing crashing of internal components should be developed. • The addition of a cryo-trap for the particle beam should be considered, and the decision to include or exclude a cryo-trap should be explained. • The choice between viton-sealed and all-metal valves should be carefully considered and explained.
Report No:TR-391-003-20 Page 2 of 3
Concerns: None
Observations: The vacuum specification for this chamber is 10-7 Torr. Both upstream and downstream areas of the beamline will operate at different pressures, including UHV in the mirror chamber shortly upstream. The plan is to include differential pumping isolation systems immediately upstream and downstream of this chamber. This is a good plan, and the calculations used to design the differential pumping systems should be presented at the instrument final design review.
This chamber includes a large number of in-vacuum motions, motors, and wiring. The plan is to include internal patch panels to allow removal of motors and motion stages without complete disassembly of the chamber. This is a good plan, given the moderate vacuum requirement for the chamber. Nevertheless, the motors, stages, and wiring should be chosen and installed with care to assure operation with minimal required maintenance.
Report No:TR-391-003-20 Page 3 of 3 CXICXI 11 micronmicron SampleSample ChamberChamber PreliminaryPreliminary DesignDesign ReviewReview WBSWBS 1.3.5.1.11.3.5.1.1
Sébastien Boutet - CXI Instrument Scientist
March 4 2009
Sébastien BOUTET [email protected] CXI Outline
CXI Overview Experimental Configurations 1 micron Chamber Physics Requirements Summary
2 Sébastien Boutet [email protected] CXI Molecular Structure Determination by Protein Crystallography
Atomic resolution can be achieved for reproducible objects with crystallography Macromolecular crystallography has been extremely successful Molecular structure is crucial for medical applications and understanding of biological function. Inability to produce large high quality crystals is the main bottleneck. Important classes of biomolecules are difficult to crystallize to date. Membrane proteins Free electron lasers may permit structural determination without crystals
3 Sébastien Boutet [email protected] CXI Ultrafast Coherent Diffractive Imaging of Biomolecules
One pulse, one measurement Sample Environment, Slits, Apertures Noisy diffraction Particle pattern Injection LCLS pulse
Wavefront Sensor Or 2nd Detector Focusing 2D Detector with hole
5 7 Combine 10 -10 measurements into 3D dataset Gösta Huldt, Abraham Szöke, Janos Hajdu (J.Struct Biol, 2003 02- ERD-047)
Single Pulse Diagnostics 4 Sébastien Boutet [email protected] CXI Image Reconstruction/ Phase Retrieval
Use a computer to phase the scattered light, rather than a lens
A lens recombines λ A lens recombines θ thethe scattered scattered rays rays withwith correct correct phases phases Resolution is limited by wavelength toto give give the the image image Imaging with a lens and size and quality of the optic
Prior knowledge about object
λ AnAn algorithm algorithm finds finds θ Algorithm thethe phases phases that that are are consistentconsistent with with measurementsmeasurements and and Lensless diffractive imaging priorprior knowledge knowledge
Resolution: δ = λ /sinθ = λ /NA Resolution is limited by wavelength and size of the detector 5 Sébastien Boutet [email protected] CXI CXI Instrument Location
Near Experimental Hall
X-ray Transport Tunnel AMO XPP
XCS CXI Endstation Source to Sample distance : ~ 440 m
Far Experimental Hall
6 Sébastien Boutet [email protected] CXI Far Experimental Hall
CXI Control Room Lab Area XCS Control Room
Hutch #6
X-ray Correlation Spectroscopy Coherent X-ray Imaging Instrument Instrument
7 Sébastien Boutet [email protected] CXI CXI Instrument in Hutch 5
8 Sébastien Boutet [email protected] CXI CXI Instrument Design
Particle injector 1 micron KB system (not shown)
Diagnostics & Wavefront Monitor eam LCLS B
Sample Chamber
Detector Stage Precision Instrument Stand
9 Sébastien Boutet [email protected] CXI CXI 1 micron Sample Chamber
Purpose Position samples mounted on a substrate Provide a high vacuum environment to minimize air scatter Position apodized apertures to clean the edges of the beam Provide a flexible environment for various user experiments Provide an interface for the delivery of samples in a particle beam
10 Sébastien Boutet [email protected] CXI Apodized Edge Apertures
If 1 part in 106 of the LCLS beam gets scattered off the slits onto the detector, there is on average 1 photon per pixel and the background is too high! LCLS Beam Soft edge apertures, such as etched Silicon minimize scattering. Use extra apertures to remove the scatter from the upstream apertures.
11 Sébastien Boutet [email protected] CXI Configuration 1: Fixed Target Forward Scattering
Sample raster stage 3-axis translation At least 1 aperture close to the sample 3-axis translation stage Direct beam passes through hole in the detector
12 Sébastien Boutet [email protected] CXI Configuration 2: Injected Particles Forward Scattering
At least 2 apertures close to the sample 3-axis translation stage Sample delivered to the LCLS beam free-standing as a particle beam Particle Injector interface above the interaction region Capability to use an alignment laser to orient the particles Laser port interface(s) Sample explosion diagnostics Ion and Electron Time-of-Flight interfaces Direct beam passes through hole in the detector
13 Sébastien Boutet [email protected] CXI Configuration 3: Pump-Probe on Fixed Targets
Sample raster stage 3-axis translation At least 1 aperture close to the sample 3-axis translation stage Pump laser port with line of sight to the interaction region Line of sight does not need to be on the upstream side Direct beam passes through hole in the detector
14 Sébastien Boutet [email protected] CXI Configuration 4: Pump-Probe Experiments with Injected Nanoparticles
At least 2 apertures close to the sample 3-axis translation stage Sample delivered to the LCLS beam free-standing as a particle beam Particle Injector interface above the interaction region Capability to use an alignment laser to orient the particles Laser port interface(s) Sample explosion diagnostics Ion and Electron Time-of-Flight interfaces Pump laser port with line of sight to the interaction region Direct beam passes through hole in the detector
15 Sébastien Boutet [email protected] CXI Configuration 5: Time-delay on Fixed Targets
Detector placed upstream of the sample Turned 180 degrees to face the downstream end of the beamline Beam passes through the hole in the detector Sample raster stage 3-axis translation Mirror to reflect the beam on raster stage 5-axis (X, Y, Z, pitch, yaw) Reflected beam passes through the hole in the detector
16 Sébastien Boutet [email protected] CXI Time-Delay Holography with Hard X-rays
t=0
t=l/c
t=2l/c
object reference
Soft X-rays Hard X-rays
17 Sébastien Boutet [email protected] CXI Configuration 6: Time-delay with Injected Particles
Detector placed upstream of the sample Turned 180 degrees to face the downstream end of the beamline Beam passes through the hole in the detector Aperture raster stage 3-axis translation Mirror to reflect the beam on raster stage 5-axis (X, Y, Z, pitch, yaw) Reflected beam passes through the hole in the detector
18 Sébastien Boutet [email protected] CXI Time-Delay Holography with Injected Particles
An aperture must be used downstream of the sample to remove the scatter from t=0 the mirror which is much stronger than the signal from the nanoparticle. t=l/c
t=2l/c
19 Sébastien Boutet [email protected] CXI Requirements
Overall Requirements Components common to all configurations to the extent possible Flexibility for future upgrades, modifications for user Lot of ports and large volume Size Requirements Large volume for future upgrades Maximize the solid angle of the exit flange for future large detector Chamber Positioning Requirements Handled by the Precision Instrument Stand Interaction region locate 8 m from the 1 micron KB System
20 Sébastien Boutet [email protected] CXI Requirements
Vacuum Requirements 10-7 Torr pressure Assumptions: ‘Unshielded’ beam path of 10 cm for 1 μm2 beam Biomolecule ~ 500kDa ~ 5 x 104 atoms
Background scatter 1% 500 atoms in path
Atoms in background gas same z as in the molecule p ≤ 1 x10-7 torr Capability to vent chamber only
Valves upstream and downstream of chamber Detector in separate chamber Rapid venting and pump-down cycle Gate valve in front of the turbo-pump so it does not need to spin down
21 Sébastien Boutet [email protected] CXI Fixed Targets Forward Scattering
22 Sébastien Boutet [email protected] CXI Injected Particles Forward Scattering
23 Sébastien Boutet [email protected] CXI Fixed Targets Time-delay Scattering
24 Sébastien Boutet [email protected] CXI Injected Particles Time-delay Scattering
25 Sébastien Boutet [email protected] CXI In-Vacuum Motions
26 Sébastien Boutet [email protected] CXI Requirements Access Requirements Easy access to internal components for modification Large door rapidly opened and closed Interface Requirements Chamber interfaces with detector stage on downstream side Large port for large detector Interface with Particle Injector on top Through 6” flange Interface with Ion TOF Laser ports
27 Sébastien Boutet [email protected] CXI CXI Particle Injector
Injector Purpose Deliver support-free single particles to the LCLS beam Injector Requirements Particle beam focus < 250 microns Particle size range 10 – 1500 nm Aerodynamic lens Stack of concentric orifices with decreasing openings. Random particle arrival in time and space Not synchronized with LCLS beam Not every pulse will hit a particle
28 Sébastien Boutet [email protected] CXI Particle Injector at FLASH March 08
29 Sébastien Boutet [email protected] CXI CXI Detector Stage CXI Detector
30 Sébastien Boutet [email protected] CXI Requirements
Controls Requirements Different controls configuration for each experimental configuration All motion remotely controlled Possibility to turn off all optical encoding if it creates background on detector. Software limits (absolute and relative) to avoid collisions Every position recorded in metadata Vacuum interlocks Safety Requirements Pump not directly below the chamber so nothing gets dropped in it Pressure relief as per 10CFR851
31 Sébastien Boutet [email protected] CXI Summary
32 Sébastien Boutet [email protected] CXI 33 Sébastien Boutet [email protected] CXI CXICXI 11 micronmicron SampleSample ChamberChamber PreliminaryPreliminary DesignDesign ReviewReview WBSWBS 1.3.5.1.11.3.5.1.1
Sébastien Boutet - CXI Instrument Scientist Paul Montanez - CXI Lead Engineer Armin Busse - CXI Engineer
March 4th, 2009
Armin Busse [email protected] CXI Outline
CXI Overview Experimental Configurations 1 micron Chamber Physics Requirements Preliminary Design and Analyses Design Interfaces Controls Safety Cost & Schedule Summary
2 Armin Busse [email protected] CXI Preliminary Design and Analysis
Location
Y
X
Z
3 Armin Busse [email protected] CXI Preliminary Design and Analysis
Preliminary Design and Analyses - Overview Tank Assembly Design (Chamber) Inside of the Sample Chamber Assembly Outside of the Sample Chamber Assembly Assembly, Installation and Maintenance To Do (open issues)
4 Armin Busse [email protected] CXI Preliminary Design and Analysis
Preliminary Design and Analyses - Overview Tank Assembly Design (Chamber) Identify Port Usage Viewports, Flanges and Door Inside of the Sample Chamber Assembly Outside of the Sample Chamber Assembly Assembly, Installation and Maintenance To Do (open issues)
5 Armin Busse [email protected] CXI Preliminary Design and Analysis
Preliminary Design and Analyses - Overview Tank Assembly Design (Chamber) Inside of the Sample Chamber Assembly Base Plate Design Electric connectors and routing Entrance Shield Outside of the Sample Chamber Assembly Assembly, Installation and Maintenance To Do (open issues)
6 Armin Busse [email protected] CXI Preliminary Design and Analysis
Preliminary Design and Analyses - Overview Tank Assembly Design (Chamber) Inside of the Sample Chamber Assembly Outside of the Sample Chamber Assembly Telescope Assembly Adapter to Up-Beam Components Adapter to Down-Beam Components T-Cross Gate Valves Pump Assembly, Installation and Maintenance To Do (open issues)
7 Armin Busse [email protected] CXI Preliminary Design and Analysis
Preliminary Design and Analyses - Overview Tank Assembly Design (Chamber) Inside of the Sample Chamber Assembly Outside of the Sample Chamber Assembly Assembly, Installation and Maintenance Anticipated assembly order Bolts (Major Bolt Assemblies) Rigging To Do (open issues)
8 Armin Busse [email protected] CXI Preliminary Design and Analysis
Preliminary Design and Analyses - Overview Tank Assembly Design (Chamber) Inside of the Sample Chamber Assembly Outside of the Sample Chamber Assembly Assembly, Installation and Maintenance To Do (open issues)
9 Armin Busse [email protected] CXI Preliminary Design and Analysis
Preliminary Design and Analyses Tank Assembly Design (Chamber) Identify Port Usage Immediate Usage and Stay-Clears Rotatable vs. Non-Rotatable Viewports, Flanges and Door Planned Viewports (Future), blanked off as needed ITOF (Ion Time-Of-Flight) Supplemental Ports and Spares Door, Double-Hinge Up-Beam
10 Armin Busse [email protected] CXI Preliminary Design and Analysis
Identify Port Usage
BEAM
Non-Rotatable CF
Rotatable CF
11 Armin Busse [email protected] CXI Preliminary Design and Analysis
Identify Port Usage – Viewports and Blanks
BEAM
12 Armin Busse [email protected] CXI Preliminary Design and Analysis
Identify Port Usage – Telescope Port
BEAM
13 Armin Busse [email protected] CXI Preliminary Design and Analysis
Identify Port Usage – Laser Ports
BEAM
14 Armin Busse [email protected] CXI Preliminary Design and Analysis
Identify Port Usage – Camera Ports
BEAM
15 Armin Busse [email protected] CXI Preliminary Design and Analysis
Identify Port Usage – Particle Injector
BEAM
16 Armin Busse [email protected] CXI Preliminary Design and Analysis
Identify Port Usage – Ion Time-Of-Flight (ITOF)
BEAM
17 Armin Busse [email protected] CXI Preliminary Design and Analysis
Identify Port Usage – T-Cross and Electric Connectors
BEAM
18 Armin Busse [email protected] CXI Preliminary Design and Analysis
Identify Port Usage – Spare Laser Ports and ETOF
BEAM
19 Armin Busse [email protected] CXI Preliminary Design and Analysis
Identify Port Usage – Entrance and Exit Flange
BEAM
20 Armin Busse [email protected] CXI Preliminary Design and Analysis
Identify Port Usage – Gatevalves and Pump
BEAM
21 Armin Busse [email protected] CXI Preliminary Design and Analysis
Identify Port Usage - Overall View
BEAM
22 Armin Busse [email protected] CXI Preliminary Design and Analysis
Identify Port Usage – User Side
BEAM
23 Armin Busse [email protected] CXI Preliminary Design and Analysis
Identify Port Usage – User Side
BEAM
24 Armin Busse [email protected] CXI Preliminary Design and Analysis
Identify Port Usage – Entrance Aperture
BEAM
25 Armin Busse [email protected] CXI Preliminary Design and Analysis
Identify Port Usage – Alternative Telescope Port
BEAM
26 Armin Busse [email protected] CXI Preliminary Design and Analysis
Identify Port Usage – Door
BEAM
27 Armin Busse [email protected] CXI Preliminary Design and Analysis
Identify Port Usage – Base Plate Assembly
BEAM
28 Armin Busse [email protected] CXI Preliminary Design and Analysis
Inside of the Sample Chamber Assembly Base Plate Design Function Mount and Motion Components Stage selection 1st and 2nd Apertures and individual motion 3rd Aperture and individual motion 4th Aperture (Sample) and individual motion Combined motion of 3rd and 4th Apertures Telescope Assembly and individual motion Particle Beam Aperture and individual motion Configurations Electric connectors and routing Entrance Shield
29 Armin Busse [email protected] CXI Preliminary Design and Analysis
Base Plate Design – Function
3rd Aperture 2nd Aperture
Sample 1st Aperture
BEAM
Particle Aperture
30 Armin Busse [email protected] CXI Preliminary Design and Analysis
Base Plate Design – Mount and Motion
Rail
Ball Bearing
Support Plate
31 Armin Busse [email protected] CXI Preliminary Design and Analysis
Base Plate Design – Component Motion I
Nom. Motion Range Resolution Repeatability Vacuum Position First aperture x 0 mm -10 mm < x < 10 mm 0.1 µm 0.3 µm 10-7 Torr position First aperture y 0 mm -10 mm < y < 10 mm 0.1 µm 0.3 µm 10-7 Torr position Second aperture x 0 mm -10 mm < x < 10 mm 0.1 µm 0.3 µm 10-7 Torr position Second aperture y 0 mm -10 mm < y < 10 mm 0.1 µm 0.3 µm 10-7 Torr position Third aperture x 0 mm -10 mm < x < 350 mm 0.1 µm 0.3 µm 10-7 Torr position Third aperture y 0 mm -10 mm < y < 10 mm 0.1 µm 0.3 µm 10-7 Torr position Third aperture z -25 mm -35 mm < z < -15 mm 0.1 µm 0.3 µm 10-7 Torr position
Manufacturer Micos Manufacturer Micos Linear Stage PP-30 Linear Stage VT-50 Travel Range +/- 9 mm or Travel Range 490 mm +/- 15 mm Resolution 0.1 µm Resolution 0.1 µm Repeatability +/- 0.1 µm Repeatability +/- 0.1 µm Load 50 N / 20Nm Axial Load 4 N Vacuum 10-7 Torr Vacuum 10-7 Torr
33 Armin Busse [email protected] CXI Preliminary Design and Analysis
Base Plate Design – Component Motion II
Nom. Motion Range Resolution Repeatability Vacuum Position Sample x position 0 mm -10 mm < x < 350 mm 0.1 µm 0.3 µm 10-7 Torr Sample y position 0 mm -10 mm < y < 10 mm 0.1 µm 0.3 µm 10-7 Torr Sample z position 0 mm -10 mm < z < 10 mm 0.1 µm 0.3 µm 10-7 Torr Sample yaw 0 degree ±5Ü 5 µrad 5 µrad 10-7 Torr Sample pitch - course 0 degree ±180Ü 10 mrad 20 mrad 10-7 Torr Sample pitch - fine 0 degree ±5Ü 5 µrad 5 µrad 10-7 Torr Particle aperture x 0 mm -10 mm < x < 10 mm 10 µm 10 µm 10-7 Torr position Particle aperture z 0 mm -10 mm < y < 10 mm 10 µm 10 µm 10-7 Torr position Time-delay mirror x 0 mm -10 mm < x < 10 mm 0.1 µm 0.3 µm 10-7 Torr position Time-delay mirror y 0 mm -10 mm < y < 10 mm 0.1 µm 0.3 µm 10-7 Torr position
Manufacturer Micos Manufacturer Micos Manufacturer New Focus Manufacturer Micos Linear Stage VT-50 Linear Stage PP-30 Picomot. 8301-UHV Rot. Stage PR-36 Travel Range 490 mm Travel Range +/- 9 mm or Travel Range 12.7 mm Travel Range 0...360° +/- 15 mm +/- 6.2° (L=2.3”) Resolution 0.1 µm Resolution Pitch Resolution 0.1 µm Resolution Yaw < 0.030 µm 0.019 µrad Repeatability +/- 0.1 µm 0.51 µrad (L=2.3”) Repeatability +/- 0.1 µm Repeatability < 0.9 µrad Load 50 N / 20Nm Repeatability 20% in open loop Axial Load 4 N Radial Pitch Torque Vacuum 10-7 Torr Load 22 N 3 Ncm, blocking Vacuum 10-7 Torr Vacuum 10-9 Torr Vacuum 10-7 Torr
34 Armin Busse [email protected] CXI Preliminary Design and Analysis
Base Plate Design – Component Motion III
Nom. Motion Range Resolution Repeatability Vacuum Position Time-delay mirror z -15 mm -25 mm < z < -5 mm 0.1 µm 0.3 µm 10-7 Torr position Time-delay mirror 0 degree ±5 5 µrad 5 µrad 10-7 Torr pitch - fine Ü Time-delay mirror 0 degree ±5 5 µrad 5 µrad 10-7 Torr yaw Ü Sample viewer 0 mm -10 mm < x < 10 mm 0.1 µm 0.3 µm 10-7 Torr mirror x position Sample viewer 0 mm -10 mm < y < 10 mm 0.1 µm 0.3 µm 10-7 Torr mirror y position Sample viewer 0 degree ±5 1 mrad 1 mrad 10-7 Torr mirror pitch Ü Sample viewer 0 degree ±5 1 mrad 1 mrad 10-7 Torr mirror yaw Ü [SP-391-001-43-0, Table 5]
Manufacturer Micos Manufacturer Micos Manufacturer New Focus Manufacturer New Focus Linear Stage PP-30 Rot. Stage PR-36 Picomot. 8301-UHV Picomot. 8301-UHV Travel Yaw 12.7 mm Travel Range +/- 9 mm or Travel Range 0...360° Travel Pitch 12.7 mm +/- 7.1° (L=2”)single +/- 15 mm +/- 3.5° (L=4”)single Resolution 0.019 µrad Resolution Yaw < 0.030 µm +/- 7.1° (L=4”)double Resolution 0.1 µm 0.59 µrad (L=2”) Repeatability < 5 µrad Resolution Pitch Repeatability +/- 0.1 µm Repeatability 20% in open loop Radial Roll Torque < 0.030 µm Axial Load 4 N up to 160 Ncm Load 22 N 0.30 µrad (L=4”) Vacuum 10-7 Torr Vacuum 10-7 Torr Vacuum 10-9 Torr
35 Armin Busse [email protected] CXI Preliminary Design and Analysis
1st and 2nd Apertures and individual motion
BEAM
Y-stage
X-stage
37 Armin Busse [email protected] CXI Preliminary Design and Analysis
3rd Aperture and individual motion
BEAM
Y-stage
X-stage
Z-stage
39 Armin Busse [email protected] CXI Preliminary Design and Analysis
4th Aperture (Sample) and individual motion
BEAM
Pitch motor
Y-stage
X-stage
Z-stage
Yaw motor long X-stage
41 Armin Busse [email protected] CXI Preliminary Design and Analysis
Components Aperture 1st through 4th
43 Armin Busse [email protected] CXI Preliminary Design and Analysis
Combined motion of 3rd and 4th Apertures I
Alternate viewer location
BEAM
44 Armin Busse [email protected] CXI Preliminary Design and Analysis
Combined motion of 3rd and 4th Apertures III BEAM
47 Armin Busse [email protected] CXI Preliminary Design and Analysis
Telescope Assembly and individual motion I BEAM
48 Armin Busse [email protected] CXI Preliminary Design and Analysis
Telescope Assembly and individual motion II
Mirror with hole Pico motors
Y-stage
X-stage
BEAM
49 Armin Busse [email protected] CXI Preliminary Design and Analysis
Particle Beam Aperture and individual motion I
Particle Aperture
Part. Aprt. stages BEAM
51 Armin Busse [email protected] CXI Preliminary Design and Analysis
Particle Beam Aperture and individual motion II
X-stage
Z-stage
52 Armin Busse [email protected] CXI Preliminary Design and Analysis
Inside of the Sample Chamber Assembly Base Plate Design Configurations Forward Scattering Forward Scattering with injected Particles Time-Delay Scattering Time-Delay Scattering with Injected Particles Electric connectors and routing Loops for long travel stages Disconnect terminal Loops for Base Plate motion Entrance Shield
54 Armin Busse [email protected] CXI Preliminary Design and Analysis
Configurations – Forward Scattering
Detector
BEAM
55 Armin Busse [email protected] CXI Preliminary Design and Analysis
Configurations – Forward Scattering
Detector
BEAM
56 Armin Busse [email protected] CXI Preliminary Design and Analysis
Configurations – Forward Scattering with Inject. Particles
Particle Beam
BEAM
57 Armin Busse [email protected] CXI Preliminary Design and Analysis
Configurations – Forward Scattering with Inject. Particles
Particle Beam
BEAM
58 Armin Busse [email protected] CXI Preliminary Design and Analysis
Configurations – Time-Delay Scattering
BEAM
59 Armin Busse [email protected] CXI Preliminary Design and Analysis
Configurations – Time-Delay Scattering with Inject. Particles
BEAM
60 Armin Busse [email protected] CXI Preliminary Design and Analysis
Electric connectors and routing I (worst case path)
BEAM
61 Armin Busse [email protected] CXI Preliminary Design and Analysis
Electric connectors and routing II
cable interface
62 Armin Busse [email protected] CXI Preliminary Design and Analysis
Entrance Shield
63 Armin Busse [email protected] CXI Preliminary Design and Analysis
Outside of the Sample Chamber Assembly Telescope Assembly Function Mount and Motion Accessories Adapter to Up-Beam Components Adapter to Down-Beam Components T-Cross Gate Valves Pump
65 Armin Busse [email protected] CXI Preliminary Design and Analysis
Telescope Assembly
BEAM
66 Armin Busse [email protected] CXI Preliminary Design and Analysis
Telescope Assembly - Section
BEAM
67 Armin Busse [email protected] CXI Preliminary Design and Analysis
Telescope Assembly - Section
Outside Mirror Inside Mirror
68 Armin Busse [email protected] CXI Preliminary Design and Analysis
Adapter, T-Cross, Gate Valves and Pump
BEAM
69 Armin Busse [email protected] CXI Preliminary Design and Analysis
Assembly, Installation and Maintenance Anticipated assembly order In the Lab Tank Assembly Viewports Base Plate Assembly and related Cables Entrance Shield T-Cross and remaining Cables Down-Beam Adapter and assoc. Gate Valve Transport and mount to Instrument Stand In the FEH Hutch Gate Valve, bottom Pumps and associated parts
70 Armin Busse [email protected] CXI Preliminary Design and Analysis
Assembly, Installation and Maintenance Bolts (Major Bolt Assemblies) Mounting space and optional direction Rigging SLAC Facilities Rigging Department Mass Interfaces (Attachment Points Chamber) Door Maintenance
71 Armin Busse [email protected] CXI Preliminary Design and Analysis
Bolts (Major Bolt Assemblies)
Red Bolt Assemblies: The bolts can only BEAM be inserted from one side. Green Bolt Assemblies: The bolts can be inserted from both sides.
72 Armin Busse [email protected] CXI Preliminary Design and Analysis
Bolts (Major Bolt Assemblies)
BEAM
73 Armin Busse [email protected] CXI Preliminary Design and Analysis
Rigging I
Mass: ~1800 lb Lift Mount 6 locations UNC 1/2-13 UNC Swivel Hook 2500 lb / each “Rope” either static or adjustable (27-48”) Crane Hook height 10 ft 2000 lb capacity Lift ~30” to clear T-Cross Yellow: 90” 30” lift capability Green: 102” 18” lift capability T-Cross might need to be attached after BEAM Chamber placement on the Stand
74 Armin Busse [email protected] CXI Preliminary Design and Analysis
Rigging II
Lift Mount 6 possible location, usually 3 used for lift Green Lift scheme for Assembly Yellow Lift scheme for Tank alone Teal Lift scheme BEAM for Door alone
75 Armin Busse [email protected] CXI Preliminary Design and Analysis
To Do (open issues) Chamber Considered Sample Chamber Entry Flange reduction to CF 14” Considered alternative Particle Injector mount increase to CF 8” Sample Chamber Door lock/rest in open position Seismic Feet (final interface TBD) Inside the Chamber Implementation of encoders for Sample Yaw and Inner Telescope Mirror motion Considered Particle Aperture Stand reposition on Base Plate as needed Wire routing Considered Bottom Base Plate stiffness increase
76 Armin Busse [email protected] CXI Preliminary Design and Analysis
To Do (open issues) Outside the Chamber Interface to Instrument Stand, detailed mount Pump Support to Instrument Stand (Frame) to reduce risk of leak Considered Bellows on Detector Adapter (Detector) General Alignment features Vacuum compatibility design
77 Armin Busse [email protected] CXI Outline
CXI Overview Experimental Configurations 1 micron Chamber Physics Requirements Preliminary Design and Analyses Design Interfaces Controls Safety Cost & Schedule Summary
78 Armin Busse [email protected] CXI Design Interfaces
Design Interfaces - Overview Up-Beam Down-Beam Instrument Stand (Frame) Particle Injector ITOF (Ion Time-Of-Flight) Detector Floor Adjacent Beamline Controls Rigging Other
79 Armin Busse [email protected] CXI Design Interfaces
Design Interfaces Up-Beam 19-9/16” Wire-Seal Flange (currently) Adapter, Gate Valve and Spool or Adapter, Gate Valve and Detector Down-Beam 19-9/16” Wire-Seal Flange Adapter, Gate Valve, Spool and Detector or Adapter, Gate Valve and Detector or Blank Flange
80 Armin Busse [email protected] CXI Design Interfaces
Instrument Stand (Frame) Welded Support Feet Tank Assembly Support (Dampening to Floor TBD) Telescope Support TBD (pending Instrument Stand Design) Turbo-Pump Support TBD (pending Instrument Stand Design) Space Allocation Space for Gate Valve Space for Roughing Pump Routing for Control Cables
81 Armin Busse [email protected] CXI Design Interfaces
Design Interfaces – Outside of Sample Chamber
BEAM
82 Armin Busse [email protected] CXI Design Interfaces
Design Interfaces – Outside of Sample Chamber
BEAM
83 Armin Busse [email protected] CXI Design Interfaces
Design Interfaces – Outside of Sample Chamber
BEAM
84 Armin Busse [email protected] CXI Design Interfaces
Design Interfaces – Adjacent Beamline
H6 Beam pipe
86 Armin Busse [email protected] CXI Design Interfaces
Particle Injector Intrusion towards Interaction Point 6” Conflat Flange (Currently) Mount and Preliminary Design (TBD) Supply Lines (TBD) ITOF (Ion Time-Of-Flight) Intrusion towards Interaction Point (TBD) 8” Conflat Flange Mount and Preliminary Design (TBD) Supply Lines (TBD)
87 Armin Busse [email protected] CXI Design Interfaces
Detector Intrusion to the Up-Beam Position Intrusion to the Down-Beam Position 14” Conflat Flange (Down-Beam) Floor Placement and mount of Roughing Pump Adjacent Beamline No current conflicts, monitoring...
88 Armin Busse [email protected] CXI Design Interfaces
Design Interfaces – Inside of Sample Chamber
BEAM
89 Armin Busse [email protected] CXI Design Interfaces
Design Interfaces – Inside of Sample Chamber
90 Armin Busse [email protected] CXI Design Interfaces
Controls Sub-D Connectors for Stages and Motors Connectors for Interlocks Multi-Pin Connector for Ion-Gauge Power Connector Pump Rigging Hoist Ring Mounts, Thread UNC 1/2”-13 for 2500lb See also Preliminary Design & Analysis / Assembly, Installation and Maintenance / Rigging Other Alignment Door opening Maintenance access Setup-Modification access
92 Armin Busse [email protected] CXI Outline
CXI Overview Experimental Configurations 1 micron Chamber Physics Requirements Preliminary Design and Analyses Design Interfaces Controls Safety Cost & Schedule Summary
93 Armin Busse [email protected] CXI Controls
Controls - Overview Pico Motors (New Focus) Rotary Piezo Stage (Micos) Linear Piezo Stages (Micos) Linear Ball Screw Stage (Micos) Particle Injector ITOF (Ion Time-Of-Flight) Experimental Lasers Telescope (Questar) Cameras Pumps (Turbo and Roughing Pump) Interlocks
94 Armin Busse [email protected] CXI Controls
Controls PCDS Photon Control and Data Acquisition Systems provides EPICS support Pico Motors (New Focus) PCDS will support Rotary Piezo Stage (Micos) Vendor committed to providing source code PCDS will support Linear Piezo Stages (Micos) Vendor committed to providing source code PCDS will support Linear Ball Screw Stage (Micos) PCDS already supported
95 Armin Busse [email protected] CXI Controls
Particle Injector motorized stepper motors PCDS already supported external particle generator TBD ITOF (Ion Time-Of-Flight) established (AMO) - Voltage via electronic PCDS will support Experimental Lasers no current in project scope PCDS provides Laser Safety Systems PCDS support Laser Control Systems (AMO)
96 Armin Busse [email protected] CXI Controls
Telescope (Questar) camera link PCDS already supported motorized stepper motor for focus Details on stepper motor not available yet 5” Mirror pico-Motor PCDS will support Cameras established (LUSI Profile Monitors) PCDS will support Pumps (Turbo and Roughing Pump) PCDS already supported
97 Armin Busse [email protected] CXI Controls
Interlocks (Safety) Door – Gate Valves PCDS already supported Particle Injector – Pressure Sensor PCDS already supported Gate Valves - Detector Hardware Solution (Detector) Pump – Gate Valves PCDS already supported MPS system to turn of the beam PCDS already supported
98 Armin Busse [email protected] CXI Outline
CXI Overview Experimental Configurations 1 micron Chamber Physics Requirements Preliminary Design and Analyses Design Interfaces Controls Safety Cost & Schedule Summary
99 Armin Busse [email protected] CXI Safety
Safety Risk: Vacuum pressure in Tank leading to implosion Approve Tank for this usage Protect unused Viewports from Damage Risk: Venting of the Sample Chamber with sudden increase in pressure Interlocks for Pumps and Gate Valves Develop Venting Procedure Risk: Overpressurizing of Tank leading to explosion Approve Tank for this usage Use Burst Disk to limit maximum pressure (ASME certified UHV burst disk , 10CFR851 compliant, 11.5 psi)
100 Armin Busse [email protected] CXI Safety
Risk: Interference of moving machine components Minimize interference of moving components Use of Limit Switches or Software Lockouts for Machine Protection Risk: Machine Protection Machine Protection System safeguarded by interlocks Risk: Electrical Safety To comply with OSHA/DOE regulations, all electronics will have certification either through a National Recognized Testing Laboratory (NRTL) or the Authority Having Jurisdiction (AHJ) as per the SLAC Electrical Equipment Inspection Program
101 Armin Busse [email protected] CXI Safety
Risk: Seismic Event Rigid mount to Instrument Stand (final Interface TBD) High Center of Gravity (~47in above floor, ~1900lb) cannot be efficiently reduced and needs to be transferred to and carried by the Instrument Stand Hardstop for Chamber Door Mechanical Locks for Chamber Door
102 Armin Busse [email protected] CXI Outline
CXI Overview Experimental Configurations 1 micron Chamber Physics Requirements Preliminary Design and Analyses Design Interfaces Controls Safety Cost & Schedule Summary
103 Armin Busse [email protected] CXI Cost & Schedule Cost & Schedule Month end January 2009
Arrows indicate baseline dates
104 Armin Busse [email protected] CXI Cost & Schedule
Month end January 2009
Control Account / Work Package FY2007 FY2008 FY2009 FY2010 FY2011 FY2012 Cumulative
1.3.05.01 CXI Room Temperature Environment
9110351 Design & Engr - CXI Sample Chamber BCWS $ - $ 1,224 $ 140,418 $ 86,765 $ - $ - $ 228,407
BCWP $ - $ 569 $ 40,486 $ - $ - $ - $ 41,055
ACWP $ - $ 529 $ 35,458 $ - $ - $ - $ 35,987
9110352 Procurement - CXI Sample Chamber BCWS $ - $ - $ - $ 247,024 $ - $ - $ 247,024
BCWP $ - $ - $ - $ - $ - $ - $ -
ACWP $ - $ - $ - $ - $ - $ - $ -
9110353 Fab & Assembly - CXI Sample Chamber BCWS $ - $ - $ - $ 69,474 $ 40,570 $ - $ 110,044
BCWP $ - $ - $ - $ - $ - $ - $ -
ACWP $ - $ - $ - $ - $ - $ - $ -
9110354 Testing - CXI Sample Chamber BCWS $ - $ - $ - $ - $ 3,743 $ - $ 3,743
BCWP $ - $ - $ - $ - $ - $ - $ -
ACWP $ - $ - $ - $ - $ - $ - $ -
Control Account Totals: BCWS $ - $ 2,322 $ 216,362 $ 403,264 $ 44,312 $ - $ 666,260
BCWP $ - $ 569 $ 40,486 $ - $ - $ - $ 41,055 SPI=1.68 ACWP $ - $ 529 $ 35,458 $ - $ - $ - $ 35,987 Performance Data Cumulative to Date At Completion CPI=1.14 Control Account Actual Work Package Budgeted Cost Cost Variance Latest Work Work Work Schedule Cost Budgeted Revised Variance Scheduled Performed Performed Estimate
1.3.05.01 CXI Room Temperature Environment
9110351 Design & Engr - CXI Sample Chamber $ 24,431 $ 41,055 $ 35,987 $ 16,624 $ 5,068 $ 228,407 $ 228,153 $ 254
9110352 Procurement - CXI Sample Chamber $ - $ - $ - $ - $ - $ 247,024 $ 247,024 $ -
9110353 Fab & Assembly - CXI Sample Chamber $ - $ - $ - $ - $ - $ 110,044 $ 110,044 $ -
9110354 Testing - CXI Sample Chamber $ - $ - $ - $ - $ - $ 3,743 $ 3,743 $ -
Control AccountTotals: $ 24,431 $ 41,055 $ 35,987 $ 16,624 $ 5,068 $ 589,218 $ 588,964 $ 254
105 Armin Busse [email protected] CXI Outline
CXI Overview Experimental Configurations 1 micron Chamber Physics Requirements Preliminary Design and Analyses Design Interfaces Controls Safety Cost & Schedule Summary
106 Armin Busse [email protected] CXI Summary
1 micron Sample Chamber preliminary design is well advanced Controls issues have been addressed in partnership with the Controls Group and are easily implemented Cost/Schedule No foreseeable schedule issues at this point, positive schedule variance Schedule Performance Index (SPI) = 1.68 Positive cost variance implies that we are efficient in accomplishing the scheduled work, i.e. costs are running under budget Cost Performance Index (CPI) = 1.14
107 Armin Busse [email protected] CXI Summary
To Do list Design Instrument Stand for the 1 micron Sample Chamber (dependent also on the Detector Stage interface) Develop detailed solutions from the preliminary design Develop an alignment plan Design ready to advance to final design
108 Armin Busse [email protected] CXI 109 Armin Busse [email protected] CXI