County Council - Planned Road Works This edition of the bulletin as automatically generated on the 19 Mar 2020

For more information about roadworks call our Customer Service Centre: 0116 3050001

Road Name/ Number & Description Contractor/Client Estimated Expected Traffic Notes Location Start Date End Date Management

LUTTERWORTH ROAD Rectify Defects after water main Asset Creation 02/03/2020 01/05/2020 Traffic Control (Multi-Way renewals works Distribution West Signals)

ARNESBY

OAK LANE LAY A NEW GAS SERVICE 4 East of Network 16/03/2020 20/03/2020 Road Closure METERS FROM THE MAIN EMLDZ S81 LOCATED IN THE ARNESBY NEARSIDECARRIAGEWAY WELFORD ROAD to rectify defects after water mains Asset Creation 25/03/2020 24/05/2020 Traffic Control (Multi-Way renewal works Distribution West Signals)

ARNESBY

WELFORD ROAD Diversion and closure of a bridleway LCC (Section 50/278/184) 01/01/2020 30/06/2021 Road Closure across plot of land.

ARNESBY

BROOK LANE Drainage Improvement Works (Flood LCC (Works Promoter) 17/02/2020 26/06/2020 Some Carriageway Alleviation) (See parent job 484422) Incursion

BILLESDON

CHURCH STREET Drainage Improvement Works (Flood LCC (Works Promoter) 18/02/2020 29/06/2020 Road Closure Alleviation) 12:35:59

BILLESDON

FOOTPATH C21 Drainage Improvement Works (Flood LCC (Works Promoter) 17/02/2020 26/06/2020 Road Closure Alleviation) (See parent job 484422)

BILLESDON

LEICESTER ROAD Drainage Improvement Works (Flood LCC (Works Promoter) 17/02/2020 26/06/2020 Some Carriageway Alleviation) (See parent job 484422) Incursion

BILLESDON

LEICESTER ROAD Reset 2 no. manholes covers in the LCC (Works Promoter) 24/03/2020 25/03/2020 Traffic Control (Two-Way verge either side of the farm Signals) entrance. Investigate to find break in BILLESDON the pipe and replace - reported 2m in Road Name/ Number & Description Contractor/Client Estimated Expected Traffic Notes Location Start Date End Date Management

MARKET PLACE Drainage Improvement Works (Flood LCC (Works Promoter) 17/02/2020 26/06/2020 Road Closure Alleviation) (See parent job 484422)

BILLESDON

MARKET ROAD Drainage Improvement Works (Flood LCC (Works Promoter) 17/02/2020 26/06/2020 Some Carriageway Alleviation) (See parent job 484422) Incursion

BILLESDON

ROLLESTON ROAD Drainage Improvement Works (Flood LCC (Works Promoter) 17/02/2020 26/06/2020 Road Closure Alleviation) (See parent job 484422)

BILLESDON

ROLLESTON ROAD 2 x SOW 4m of 90mm PE and 4m of New Connections Req 23/03/2020 25/03/2020 Road Closure 63mm PE to connect onto existing East 180mm PE main via UPT with BILLESDON 80mm outlet & 1 x SV TILTON ROAD Iinstall two new gullies at the culvert. LCC (Works Promoter) 26/03/2020 27/03/2020 Traffic Control (Two-Way Signals)

BILLESDON

WEST LANE Drainage Improvement Works (Flood LCC (Works Promoter) 17/02/2020 26/06/2020 Some Carriageway Alleviation) (See parent job 484422) Incursion

BILLESDON

HUNTER BOULEVARD Boundary box Install & tap main for STW Water East 27/03/2020 27/03/2020 Lane Closure logg Job in Footway (6mm Bitmac (Tarmac) ) BITTESWELL

VALLEY LANE Urgent excavation in highway to Western Power, 6136 SE 16/03/2020 24/03/2020 Some Carriageway locate and repair LV cable fault. 23:15:00 Incursion

BITTESWELL

COTTAGE LANE Emergency road closure for public LCC (Works Promoter) 03/02/2020 17/04/2020 Road Closure safety 14:57:42

BROUGHTON ASTLEY

COVENTRY ROAD Boundary box Install & tap main for STW Water East 25/03/2020 27/03/2020 Traffic Control (Two-Way logg Job in Verge (Grass ) Signals)

BROUGHTON ASTLEY

DUNTON ROAD Water main renewals via Open cut/ Asset Creation 13/02/2020 25/03/2020 Road Closure DD methods approx 2500m across Distribution West scheme Transfer of services and BROUGHTON ASTLEY installation of valves/hydrants Water Road Name/ Number & Description Contractor/Client Estimated Expected Traffic Notes Location Start Date End Date Management

FOOTPATH W50 Skip - Licence- 787600 LCC (Permit Authority) 13/03/2020 19/03/2020 Some Carriageway 08:22:03 Incursion

BROUGHTON ASTLEY

FROLESWORTH ROAD Replace 1 existing pole 0.5m x 0.5m BT 23/03/2020 23/03/2020 Traffic Control (Give and Take)

BROUGHTON ASTLEY

STATION ROAD ShortCommPipe Renew 25mm with STW Water East 23/03/2020 24/03/2020 Traffic Control (Give and Trailer Job in Footway (6mm Bitmac Take) (Tarmac) ) BROUGHTON ASTLEY

STATION ROAD Replace 1 existing pole 0.5m x 0.5m BT 24/03/2020 24/03/2020 Traffic Control (Give and Take)

BROUGHTON ASTLEY

STATION ROAD Water main renewals via Open cut/ Asset Creation 16/03/2020 24/04/2020 Road Closure DD methods approx 2500m across Distribution West scheme Transfer of services and BROUGHTON ASTLEY installation of valves/hydrants STATION ROAD connect up the new 250mm water Asset Creation 24/02/2020 04/04/2020 Some Carriageway mains and bring into commission Distribution West Incursion

BROUGHTON ASTLEY

SWANNINGTON ROAD Build 1 precast chamber in 915mm x BT 17/03/2020 19/03/2020 No Carriageway Incursion 445mm x 965mm deep in Footway,Install 2m of 1 way poly duct BROUGHTON ASTLEY in Footway RUGBY ROAD Construction of vehicular crossover LCC (Section 50/278/184) 12/03/2020 24/03/2020 Traffic Control (Two-Way into new housing development (S184) Signals)

CATTHORPE

RUGBY ROAD Storm drainage connection LCC (Section 50/278/184) 12/03/2020 24/03/2020 Traffic Control (Two-Way Signals)

CATTHORPE

BELL STREET Relay 6 no. kerb and patch18m2 LCC (Works Promoter) 24/03/2020 25/03/2020 Traffic Control (Multi-Way carriageway and 6m2 footway. Signals)

CLAYBROOKE MAGNA

MANOR ROAD Long Comm Pipe Repair 15mm Stop STW Water East 19/03/2020 23/03/2020 Traffic Control (Give and visible or significant leakage Job in 07:55:00 Take) Footway (6mm Bitmac (Tarmac) ) CLAYBROOKE MAGNA Road Name/ Number & Description Contractor/Client Estimated Expected Traffic Notes Location Start Date End Date Management

MAIN ROAD Tree trimming & traffic light head No Western Power, 6133 26/03/2020 26/03/2020 Traffic Control (Two-Way excavation. Works in conjunction with & Nuneaton Signals) DY633M61330637869B. CLAYBROOKE PARVA

ULLESTHORPE ROAD Tree trimming & traffic light head No Western Power, 6133 26/03/2020 26/03/2020 Traffic Control (Two-Way excavation. Works in conjunction with Hinckley & Nuneaton Signals) DY633M61330637869A. CLAYBROOKE PARVA

MAIN STREET 40 m2 Footway patch required LCC (Works Promoter) 27/03/2020 27/03/2020 Traffic Control (Two-Way (F/WAY Deterioration) Signals)

COTESBACH

MAIN STREET Outside The Chesford , Main Street, LCC (Permit Authority) 19/03/2020 24/03/2020 Some Carriageway Drayton, LE16 8SD 11:28:40 Incursion

DRAYTON

BROUGHTON LANE Water main renewals via Open cut/ Asset Creation 06/01/2020 04/04/2020 Road Closure DD methods approx 2500m across Distribution West scheme Transfer of services and DUNTON BASSETT installation of valves/hydrants Water COOPERS LANE GAS SERVICE DISCONNECTION East of England Network 23/03/2020 25/03/2020 No Carriageway Incursion WITH EXCAVATION UNDER OUR EMLDZ S81 MANDATORY OBLIGATIONTO DUNTON BASSETT COMPLY WITH GAS SAFETY COOPERS LANE dis-Connection pit as part of the Asset Creation 23/03/2020 27/03/2020 No Carriageway Incursion water main renewal works taking Distribution West place on Brought lane/dunton road DUNTON BASSETT

LAYBY OFF A426 SOUTHBOUND SD stone storage if required. LCC (Works Promoter) 01/03/2020 31/08/2020 Road Closure RO

DUNTON BASSETT

LEICESTER ROAD Remedial working BT 19/03/2020 23/03/2020 No Carriageway Incursion

FLECKNEY

LEICESTER ROAD GAS GOVERNOR REPLACMENT - East of England Network 02/03/2020 03/04/2020 Traffic Control (Two-Way OPEN CUT 18M OF 125MM MP PE EMLDZ S81 Signals) INSTALLATION OF NEW DISTRICT FLECKNEY GAS GOVERNOR AND REMOVAL MAIN STREET Replace gully grate and patch around LCC (Works Promoter) 27/03/2020 27/03/2020 Traffic Control (Stop/Go gully. Boards)

FLECKNEY Road Name/ Number & Description Contractor/Client Estimated Expected Traffic Notes Location Start Date End Date Management

GALLOW FIELD ROAD Boundary box Install & tap main for STW Water East 21/03/2020 22/03/2020 Traffic Control (Multi-Way logg Job in Carriageway (10mm Signals) Bitmac (Tarmac) ) FOXTON

LUTTERWORTH ROAD Short Comm Pipe Repair 15mm STW Water East 19/03/2020 23/03/2020 Traffic Control (Give and Stop visible or significant leakage Job 08:07:00 Take) in Footway (6mm Bitmac (Tarmac) ) GILMORTON

DINGLEY ROAD Hydrant Rebuild chamber Job in STW Water East 24/03/2020 26/03/2020 Traffic Control (Two-Way Carriageway (10mm Bitmac (Tarmac) Signals) ) GREAT BOWDEN

LANGTON ROAD 2 Way lights to be carried out for the NR-LNE PM BUILDINGS 20/03/2020 20/03/2020 Traffic Control (Two-Way repair or replace of fencing . Hours of AND CIVILS (CENTRAL Signals) work 0800 - 1700 WEST) GREAT BOWDEN

HIGH STREET 1 joint hole in tarmac footway for Western Power, 6144 24/03/2020 27/03/2020 Some Carriageway supply alteration Leicestershire South Incursion

GREAT EASTON

ASHBY RISE SIGNAL USE ONLY BT - Inc S81 25/03/2020 27/03/2020 Traffic Control (Multi-Way Signals)

GREAT GLEN

FERNIE DENE Install 3m of 1 way poly duct in BT 17/03/2020 19/03/2020 No Carriageway Incursion Footway 14:00:00

GREAT GLEN

LONDON ROAD De-silt structure as there is moderate LCC (Works Promoter) 23/03/2020 10/04/2020 Traffic Control (Two-Way silting throughout. (ST:Revenue) Signals)

GREAT GLEN

LONDON ROAD 1 joint hole in tarmac footway and Western Power, 6144 19/03/2020 28/03/2020 Traffic Control (Two-Way 239m trenching in tarmac footway for Leicestershire South Signals) reinforcement scheme GREAT GLEN

LONDON ROAD A6 Lay new 355mm PE adjacent to Construction Delivery and 01/04/2019 31/07/2020 Some Carriageway existing main. Commercial (Asset Creati Incursion

GREAT GLEN

OAKS ROAD 8m Excavation in Carriageway to GTC - Power On 16/03/2020 27/03/2020 Some Carriageway install new Gas Main onto new Connections Incursion development GREAT GLEN Road Name/ Number & Description Contractor/Client Estimated Expected Traffic Notes Location Start Date End Date Management

OAKS ROAD Foul & Storm connection LCC (Section 50/278/184) 09/03/2020 17/04/2020 Road Closure

GREAT GLEN

OAKS ROAD Foul and storm outfalls, bellmouth, LCC (Section 50/278/184) 02/03/2020 05/06/2020 Road Closure pavement construction, gullies, drainage, resurfacing junction of GREAT GLEN Forest Road and Road STRETTON ROAD M J Quinn to Reshell existing BT BT - Inc S81 25/03/2020 27/03/2020 Traffic Control (Multi-Way cabinet with 2m duct into JUF10. 5m Signals) duct in footway from JUF10 into GREAT GLEN DSLAM MAIN STREET Scaffolding - Licence approved LCC (Permit Authority) 12/03/2020 25/03/2020 Some Carriageway 16:56:50 Incursion

GUMLEY

MEDBOURNE ROAD Please remove 7m of plastic grass LCC (Works Promoter) 23/03/2020 24/03/2020 Traffic Control (Give and blocks as marked with yellow spray Take) and fill with compacted 3 t recycled HALLATON stone, also relay one 6x5 kerb and NORTH END Please install new gulley outside no LCC (Works Promoter) 27/03/2020 27/03/2020 Traffic Control (Multi-Way 17. and connect into storm system. Signals)

HALLATON

SCOTLAND LANE POLE REPLACEMENT IN FW BT - Inc S81 20/03/2020 24/03/2020 Some Carriageway Incursion

HOUGHTON ON THE HILL

UPPINGHAM ROAD 31m trenching in tarmac footway and Western Power, 6144 23/03/2020 26/03/2020 Some Carriageway tarmac road and grass verge for pole Leicestershire South Incursion changes - ESQCR HOUGHTON ON THE HILL

UPPINGHAM ROAD SERVICE ROAD POLE REPLACEMENT IN VERGE BT - Inc S81 20/03/2020 24/03/2020 Traffic Control (Give and Take)

HOUGHTON ON THE HILL

WALTON LANE Dig required in footway to repair out BT - Inc S81 18/03/2020 20/03/2020 No Carriageway Incursion of service telephone cable. BT Fault 12:57:00 reference EM0UGH76 HUSBANDS BOSWORTH

WELFORD ROAD Treeworks LCC (Section 50/278/184) 26/03/2020 26/03/2020 Traffic Control (Two-Way Signals)

HUSBANDS BOSWORTH Road Name/ Number & Description Contractor/Client Estimated Expected Traffic Notes Location Start Date End Date Management

WELFORD ROAD Install vehicular access to new LCC (Section 50/278/184) 16/03/2020 25/03/2020 Traffic Control (Two-Way housing development Signals)

HUSBANDS BOSWORTH

BULLER STREET Temporary light Head - Working in Asset Creation 24/02/2020 03/04/2020 Traffic Control (Multi-Way the carriageway & Footpath Distribution West Signals) installing 146m x 180mm PE water KIBWORTH BEAUCHAMP main as part of the watermain DOVER STREET Temporary light Head - Working in Asset Creation 24/02/2020 03/04/2020 Traffic Control (Multi-Way the carriageway & Footpath Distribution West Signals) installing 146m x 180mm PE water KIBWORTH BEAUCHAMP main as part of the watermain FLECKNEY ROAD Skip - Licence approved LCC (Permit Authority) 17/03/2020 23/03/2020 Some Carriageway 13:33:21 Incursion

KIBWORTH BEAUCHAMP

FLECKNEY ROAD Working in the carriageway & Asset Creation 24/02/2020 03/04/2020 Traffic Control (Multi-Way Footpath installing 146M x 180mm Distribution West Signals) PE water main as part of the KIBWORTH BEAUCHAMP watermain reinforcement with service HARCOURT ROAD Temporary light Head - Working in Asset Creation 24/02/2020 03/04/2020 Traffic Control (Multi-Way the carriageway & Footpath Distribution West Signals) installing 146m x 180mm PE water KIBWORTH BEAUCHAMP main as part of the watermain IMPERIAL ROAD Temporary light Head - Working in Asset Creation 24/02/2020 03/04/2020 Traffic Control (Multi-Way the carriageway & Footpath Distribution West Signals) installing 146m x 180mm PE water KIBWORTH BEAUCHAMP main as part of the watermain LAYBY OFF A6 NORTHBOUND SD stone storage if required. LCC (Works Promoter) 01/03/2020 31/08/2020 Road Closure HARBOROUGH ROAD

KIBWORTH BEAUCHAMP

LUTTERWORTH ROAD Boundary box Install & tap main for STW Water East 24/03/2020 26/03/2020 Traffic Control (Two-Way logg Job in Verge (Grass ) Signals)

KIMCOTE

MAIN STREET SEW REP - NOTICE ONLY. STW Waste 18/03/2020 24/03/2020 Traffic Control (Two-Way URGENT DIG REQUIRED IN CW TO 11:00:00 Signals) REPAIR BADLY DAMAGED SEWER LEIRE URGENT DUE TO HIGH RISK OF WHITE HOUSE CLOSE position of site cabin Asset Creation 17/03/2020 20/04/2020 No Carriageway Incursion Distribution West

LEIRE Road Name/ Number & Description Contractor/Client Estimated Expected Traffic Notes Location Start Date End Date Management

BELLFIELDS STREET LAY NEW DOMESTIC 32MM PE East of England Network 25/03/2020 27/03/2020 Traffic Control (Give and SERVICE 8M FROM MAIN IN EMLDZ S81 Take) CARRIAGEWAY LITTLE BOWDEN

KETTERING ROAD forward planning of Water mains Asset Creation 06/01/2020 06/01/2021 Some Carriageway renewal Distribution West Incursion

LITTLE BOWDEN

FOOTPATH A25 Construction works on site, LCC (Section 50/278/184) 28/10/2019 26/04/2020 Road Closure temporary diversion of public footpaths A23, A24 and A25 LUBENHAM

FOOTPATH BOTAT A30 Skip - Licence approved LCC (Permit Authority) 18/03/2020 24/03/2020 Some Carriageway 15:23:17 Incursion

LUBENHAM

LEICESTER ROAD 2 joint holes in tarmac footway and Western Power, 6141 04/01/2020 20/03/2020 Traffic Control (Two-Way 50m trenching in tarmac footway for Kettering Signals) cable overlay. Works in conjunction LUBENHAM with DY641M61412149416ABCDEF MARSTON ROAD SD stone storage if required. LCC (Works Promoter) 02/03/2020 31/08/2020 Some Carriageway Incursion

LUBENHAM

PAGET ROAD Long Comm Pipe Renew 1.5" STW Water East 17/03/2020 19/03/2020 Some Carriageway Carriageway type 4 (up to 0.5 MSA) 09:04:00 Incursion Works in Footway & Carriageway LUBENHAM Significant leak Job in Footway (6mm BILTON WAY M J Quinn to Reshell existing BT BT - Inc S81 20/03/2020 20/03/2020 Traffic Control (Multi-Way cabinet with 1m duct into JUF10 Signals)

LUTTERWORTH

COVENTRY ROAD Contraflow to allow construction of LCC (Section 50/278/184) 01/03/2020 17/11/2020 Contra-Flow new roundabout

LUTTERWORTH

COVENTRY ROAD Build crossovers in prep for LCC (Section 50/278/184) 03/03/2020 17/11/2020 Road Closure contraflow works Overnight closures 20.00-06.00 (in LUTTERWORTH both directions) CRESCENT ROAD Install 2 no. gullies, 10m 150mm LCC (Works Promoter) 23/03/2020 25/03/2020 Traffic Control (Two-Way storm pipe to gully no. 1 and 2.2m Signals) 150mm storm pipe to gully no. 2. LUTTERWORTH Road Name/ Number & Description Contractor/Client Estimated Expected Traffic Notes Location Start Date End Date Management

CRESCENT ROAD 30m2 carriageway patching. Follows LCC (Works Promoter) 26/03/2020 26/03/2020 Traffic Control (Two-Way job 510644 Signals)

LUTTERWORTH

DUNLEY WAY Urgent excavation in highway to Western Power, 6136 SE 17/03/2020 24/03/2020 Some Carriageway locate and repair LV cable fault. Warwickshire 15:00:00 Incursion

LUTTERWORTH

DUNLEY WAY Urgent excavation in highway to Western Power, 6133 15/03/2020 20/03/2020 Some Carriageway locate and repair LV cable fault. Hinckley & Nuneaton 23:20:00 Incursion

LUTTERWORTH

LEICESTER ROAD LUTTERWORTH 20 - DSLAM BT 20/03/2020 20/03/2020 No Carriageway Incursion 625803 - REMEDIAL WORKS - to clear Highway Defect in FW LUTTERWORTH

LEICESTER ROAD signal use only BT - Inc S81 20/03/2020 20/03/2020 Traffic Control (Multi-Way Signals)

LUTTERWORTH

LINDEN DRIVE Small Main Repair Collar 4" Stop STW Water East 18/03/2020 20/03/2020 Traffic Control (Give and visible or significant leakage Job in 10:22:00 Take) Footway (6mm Bitmac (Tarmac) ) LUTTERWORTH

LUTTERWORTH ROAD Further drainage survey works to LCC (Section 50/278/184) 23/03/2020 02/04/2020 Lane Closure assist in design of new road layout

LUTTERWORTH

LUTTERWORTH SOUTHERN BYPASS Further drainage survey works to LCC (Section 50/278/184) 23/03/2020 02/04/2020 Lane Closure assist in design of new road layout

LUTTERWORTH

LUTTERWORTH SOUTHERN BYPASS Lane Closure in collab with the LCC (Section 50/278/184) 01/03/2020 17/11/2020 Lane Closure contraflow on A4303 linked to HMS779854 LUTTERWORTH

ROUNDABOUT AT M1 JUNCTION 20 AT Further drainage survey works to LCC (Section 50/278/184) 23/03/2020 02/04/2020 Lane Closure THE JUNC assist in design of new road layout

LUTTERWORTH

STATION ROAD Large Main Repair Collar 8" Stop STW Water East 14/03/2020 20/03/2020 Some Carriageway visible or significant leakage Job in 22:31:02 Incursion Carriageway (10mm Bitmac (Tarmac) LUTTERWORTH ) Road Name/ Number & Description Contractor/Client Estimated Expected Traffic Notes Location Start Date End Date Management

ALVINGTON WAY Traffic light head only - no Western Power, 6141 04/01/2020 20/03/2020 Traffic Control (Multi-Way excavation. Works in conjunction with Kettering Signals) DY641M61412149416ABCDEF

CLARENCE STREET forward planning of Water mains Asset Creation 06/01/2020 06/01/2021 Some Carriageway renewal Distribution West Incursion

MARKET HARBOROUGH

FAIRFIELD ROAD build chamber in verge on existing Virgin Media - National Inc 23/03/2020 25/03/2020 No Carriageway Incursion track and extend 3m duct in verge S81 onto customer premises MARKET HARBOROUGH

FARNDON ROAD Small Main Repair Collar 4" Repairs STW Water East 18/03/2020 20/03/2020 Traffic Control (Two-Way in footway and verge Stop visible or 16:36:00 Signals) significant leakage Job in Footway MARKET HARBOROUGH (6mm Bitmac (Tarmac) ) FROM B6047 LEICESTER ROAD TO ST 10m trenching in tarmac road for Western Power, 6141 06/01/2020 20/03/2020 Traffic Control (Multi-Way LUKES HO cable overlay. Works in conjunction Kettering Signals) with DY641M61412149416ABCDEF MARKET HARBOROUGH

GARDINER STREET Skip - Licence approved LCC (Permit Authority) 16/03/2020 22/03/2020 Some Carriageway 14:05:29 Incursion

MARKET HARBOROUGH

GARDINER STREET Replace 1 existing pole BT 25/03/2020 27/03/2020 Traffic Control (Give and Take)

MARKET HARBOROUGH

HIGH STREET Pacopatch all ironwork. 18 Gullies LCC (Works Promoter) 08/03/2020 05/04/2020 Traffic Control (Stop/Go and 7 Manhole covers (C/WAY Iron 08:54:00 Boards) work) MARKET HARBOROUGH

HILLCREST AVENUE Traffic light head only - no Western Power, 6141 04/01/2020 20/03/2020 Traffic Control (Multi-Way excavation. Works in conjunction with Kettering Signals) DY641M61412149416ABCDEF MARKET HARBOROUGH

HILLSIDE ROAD Replace 1 existing pole 0.5m x 0.5m BT 24/03/2020 26/03/2020 Traffic Control (Give and on private - permit required for Take) vehicles only MARKET HARBOROUGH

KETTERING ROAD Boundary Box Install 25mm with STW Water East 23/03/2020 25/03/2020 Traffic Control (Two-Way Trailer Job in Footway (10mm Bitmac Signals) (Tarmac) ) MARKET HARBOROUGH Road Name/ Number & Description Contractor/Client Estimated Expected Traffic Notes Location Start Date End Date Management

KETTERING ROAD Final reinstatement Asset Creation 27/03/2020 31/03/2020 Traffic Control (Multi-Way Distribution West Signals)

MARKET HARBOROUGH

KETTERING ROAD forward planning of Water mains Asset Creation 06/01/2020 06/01/2021 Some Carriageway renewal Distribution West Incursion

MARKET HARBOROUGH

KINGSTON WAY RSBF - Cores to Kilby Road, Fleckney LCC (Section 50/278/184) 10/03/2020 01/04/2020 Traffic Control (Two-Way in conjunction with HMS766426 Signals)

MARKET HARBOROUGH

KINGSTON WAY Foul sewer connection and manhole LCC (Section 50/278/184) 10/03/2020 03/04/2020 Traffic Control (Two-Way construction Signals)

MARKET HARBOROUGH

LEICESTER ROAD Remedial reinstatement to rectify Virgin Media - National Inc 23/03/2020 23/03/2020 No Carriageway Incursion reported defects - Box loose fillet S81 breaking up. Top soil and seed MARKET HARBOROUGH required. Kerb broken. LEICESTER ROAD Locate and excavate 1 blockage in BT 25/03/2020 27/03/2020 No Carriageway Incursion existing duct

MARKET HARBOROUGH

LEICESTER ROAD SOW 20m of 90mm PE to connect New Connections Req 23/03/2020 27/03/2020 Traffic Control (Two-Way onto existing 4"CI main via UPT with East Signals) 80mm outlet MARKET HARBOROUGH

LEICESTER ROAD 3 joint holes in tarmac footway and Western Power, 6141 04/01/2020 20/03/2020 Traffic Control (Multi-Way grass verge and 877m trenching in Kettering Signals) tarmac footway and tarmac road and MARKET HARBOROUGH grass verge for cable overlay LOGAN COURT Replace 1 existing pole 0.5m x 0.5m BT 25/03/2020 27/03/2020 Traffic Control (Give and Take)

MARKET HARBOROUGH

LOGAN CRESCENT Replace 1 existing pole 0.5m x 0.5m BT 25/03/2020 27/03/2020 Traffic Control (Give and Take)

MARKET HARBOROUGH

LUBENHAM HILL SERVICE ROAD FOR Short 0.1-4.5m Full Ex 32mm MDPE New Connections East - 26/03/2020 28/03/2020 Traffic Control (Give and NUMBERS 8 New Water Connection - Install 2 x Water Take) 32mm MDPE services from boundary MARKET HARBOROUGH to 63mm MDPE main. Main is Road Name/ Number & Description Contractor/Client Estimated Expected Traffic Notes Location Start Date End Date Management

MORLEY STREET Foul Sewer Connection LCC (Section 50/278/184) 16/03/2020 20/03/2020 Traffic Control (Priority Working)

MARKET HARBOROUGH

NELSON STREET Skip - Licence approved LCC (Permit Authority) 14/02/2020 26/03/2020 Some Carriageway 11:00:11 Incursion

MARKET HARBOROUGH

PATRICK STREET Skip - Licence approved LCC (Permit Authority) 13/03/2020 19/03/2020 Some Carriageway 15:27:59 Incursion

MARKET HARBOROUGH

PATRICK STREET Skip - Licence approved LCC (Permit Authority) 23/03/2020 29/03/2020 Some Carriageway 14:52:30 Incursion

MARKET HARBOROUGH

SPRINGFIELD STREET Total Area 25m2 C/W - Please LCC (Works Promoter) 20/03/2020 20/03/2020 Road Closure patch 25m of damaged carriageway (C/WAY Deterioration) MARKET HARBOROUGH

ST MARYS ROAD UNBLOCK DUCT IN FOOTWAY Virgin Media - Kelly 18/03/2020 19/03/2020 No Carriageway Incursion FOR CUSTOMER CONNECTION Communication

MARKET HARBOROUGH

THE WOODLANDS 1 joint hole in tarmac footway for Western Power, 6141 04/01/2020 20/03/2020 Traffic Control (Give and cable overlay. Works in conjunction Kettering Take) with DY641M61412149416ABCDEF MARKET HARBOROUGH

WARTNABY STREET Skip - Licence approved LCC (Permit Authority) 13/03/2020 19/03/2020 Some Carriageway 15:50:39 Incursion

MARKET HARBOROUGH

WATSON AVENUE 3rd Light Head in conjunction with New Connections Req 16/03/2020 19/03/2020 Traffic Control (Multi-Way LB516A6W/12209465A East Signals)

MARKET HARBOROUGH

WESTERN AVENUE Boundary box Renew 25mm Job in STW Water East 20/03/2020 24/03/2020 Traffic Control (Give and Footway (6mm Bitmac (Tarmac) ) Take)

MARKET HARBOROUGH

ASHLEY ROAD Investigate blockages in drainage run LCC (Works Promoter) 23/03/2020 25/03/2020 Traffic Control (Two-Way and repair. Signals)

MEDBOURNE Road Name/ Number & Description Contractor/Client Estimated Expected Traffic Notes Location Start Date End Date Management

DRAYTON ROAD Repair to break in pipe 0.5 metres in LCC (Works Promoter) 26/03/2020 26/03/2020 Traffic Control (Two-Way depth. Signals)

MEDBOURNE

LUTTERWORTH ROAD Further drainage survey works to LCC (Section 50/278/184) 23/03/2020 02/04/2020 Traffic Control (Two-Way assist in design of new road layout Signals)

MISTERTON WITH WALCOTE

GLEN ROAD Lay new 355mm PE adjacent to Construction Delivery and 01/04/2019 31/07/2020 Some Carriageway existing main. Commercial (Asset Creati Incursion

NEWTON HARCOURT

LUTTERWORTH ROAD 85m trenching in tarmac footway for Western Power, 6136 SE 27/03/2020 04/04/2020 Traffic Control (Multi-Way cable diversion. works in conjunction Warwickshire Signals) with DY636M61362198016BC NORTH KILWORTH

STATION ROAD Air valve Rebuild chamber Job in STW Water East 24/03/2020 26/03/2020 Traffic Control (Priority Verge (Grass ) Working)

NORTH KILWORTH

SOMERBY ROAD Carriageway resurfacing Scheme in LCC (Works Promoter) 16/03/2020 20/03/2020 Road Closure schemes pool

OWSTON AND NEWBOLD

ASHBY ROAD Replace collapsed pipe from gully to LCC (Works Promoter) 18/03/2020 20/03/2020 Traffic Control (Multi-Way the brook. 07:48:48 Signals)

PEATLING PARVA

GREEN ROAD Installation of Event Duration Monitor Capital Delivery - Manhole 24/03/2020 24/03/2020 Traffic Control (Give and in MH SP52934261 estimated 20 min and CCTV surveys Take) duration PRIMETHORPE

FLECKNEY ROAD 676.24m2 Pre surface dressing LCC (Works Promoter) 22/03/2020 22/03/2020 Road Closure patching 2020 totalling 676.24

SADDINGTON

COVERT LANE POLE REPLACWEMENT IN VERGE BT - Inc S81 20/03/2020 24/03/2020 Traffic Control (Multi-Way Signals)

SCRAPTOFT

CATTHORPE ROAD Traffic light head in conjunction with Asset Creation 23/03/2020 25/03/2020 Traffic Control (Multi-Way LB501A6W/11832131A Distribution West Signals)

SHAWELL Road Name/ Number & Description Contractor/Client Estimated Expected Traffic Notes Location Start Date End Date Management

LUTTERWORTH ROAD Traffic light head in conjunction with Asset Creation 23/03/2020 25/03/2020 Traffic Control (Multi-Way LB501A6W/11832131A Distribution West Signals)

SHAWELL

MAIN STREET Std Sew Rep 225mm 3m deep - STW Waste 09/03/2020 20/03/2020 Road Closure Await EMERGENCY DIG TO 09:15:00 REPAIR PIPE ON GRASS SHAWELL EMBANKMENT RAISED FROM MAIN STREET Traffic light head in conjunction with Asset Creation 23/03/2020 25/03/2020 Traffic Control (Multi-Way LB501A6W/11832131A Distribution West Signals)

SHAWELL

SWINFORD ROAD Water main repair Asset Creation 23/03/2020 25/03/2020 Traffic Control (Multi-Way Distribution West Signals)

SHAWELL

WELFORD ROAD Remove 2x posts (RTA) dispose. LCC (Works Promoter) 20/03/2020 20/03/2020 Traffic Control (Multi-Way Install 2x 76mm posts and re-attach Signals) existing sign. SHEARSBY

DEBDALE LANE Reset gully and patch around. LCC (Works Promoter) 27/03/2020 27/03/2020 Traffic Control (Stop/Go Boards)

SMEETON WESTERBY

RUGBY ROAD Small Sluice Valve Re-pack 4" Job in STW Water East 16/03/2020 19/03/2020 Traffic Control (Two-Way Verge (Grass ) 08:10:00 Signals)

SOUTH KILWORTH

RUGBY ROAD Emergency Repair on leaking water Asset Creation 17/03/2020 20/03/2020 Traffic Control (Multi-Way main in the carriageway. Distribution West 10:48:00 Signals)

SOUTH KILWORTH

WALCOTE ROAD 2 joint holes in grass verge and 6m Western Power, 6136 SE 17/03/2020 20/03/2020 Traffic Control (Two-Way trenching in grass verge for new Warwickshire Signals) supply, disconnection of supply SOUTH KILWORTH

FOREST RISE Small Main Repair Collar 4" Stop STW Water East 18/03/2020 20/03/2020 Traffic Control (Priority visible and significant leakage Job in 12:25:00 Working) Footway (6mm Bitmac (Tarmac) ) THURNBY

GRANGE LANE POLE REPLACEMENT IN FW BT - Inc S81 20/03/2020 24/03/2020 Traffic Control (Multi-Way Signals)

THURNBY Road Name/ Number & Description Contractor/Client Estimated Expected Traffic Notes Location Start Date End Date Management

PULFORD DRIVE Remedial Works - Kerbs not fitted GTC - Power On 25/03/2020 28/03/2020 Some Carriageway correctly alignment incorrect. Gap Connections Incursion between CW and kerb line requires THURNBY attention UPPINGHAM ROAD NMA Defect CLO - Remedial Rein STW Water East 20/03/2020 21/03/2020 Traffic Control (Two-Way by CLO "Take up 6m kerbs and relay Signals) take up footway and relay plus relay THURNBY .800 x 6m in cway. HRA Black Chips UPPINGHAM ROAD 1 joint hole in grass verge and 6m Western Power, 6144 23/03/2020 25/03/2020 No Carriageway Incursion trenching in grass verge for new Leicestershire South supply THURNBY

FISHPONDS LAYBY UPPINGHAM ROAD SD stone storage if required. LCC (Works Promoter) 01/03/2020 31/08/2020 Road Closure

TUGBY

FAIRWAY MEADOWS Build 2 precast chamber in 915mm x BT 18/03/2020 24/03/2020 Some Carriageway 445mm x 965mm deep in Incursion Footway,Install 17m of 1 way poly ULLESTHORPE duct in Carriageway,Install 42m of 1 FROLESWORTH ROAD LAY NEW DOMESTIC 32MM PE East of England Network 18/03/2020 20/03/2020 No Carriageway Incursion SERVICE 3M FROM MAIN IN EMLDZ S81 VERGE ULLESTHORPE

LUTTERWORTH ROAD Stop tap Renew 25mm Stop visible STW Water East 18/03/2020 20/03/2020 Traffic Control (Give and or significant leakage Job in Verge 14:02:00 Take) (Grass ) ULLESTHORPE

MILL ROAD Lay and comission new main and 9 East of England Network 23/03/2020 27/03/2020 Traffic Control (Give and servicesConnect onto existing main EMLDZ S81 Take) in public carry out main / service ULLESTHORPE laying using open cut or moling with CHURCH FARM LANE NMA Defect CLO - Remedial Rein STW Water East 26/03/2020 26/03/2020 Some Carriageway by CLO Job in Carriageway (10mm Incursion StoneMastic Asphalt ) WILLOUGHBY WATERLEYS

PEATLING ROAD Rectify defects after water main Asset Creation 18/03/2020 24/03/2020 Traffic Control (Multi-Way renewal works Distribution West Signals)

WILLOUGHBY WATERLEYS

FLECKNEY ROAD Lay new 355mm PE adjacent to Construction Delivery and 01/04/2019 31/07/2020 Some Carriageway existing main. Commercial (Asset Creati Incursion

WISTOW