Environmental Monitoring Report

Semestral Report July-December 2012

VIE: Northern Power Transmission Expansion Sector Project

Prepared by the Local Implementation consultant (LIC), with information mostly provided by VICA consultant for the Northern Power Project Management Board and the Asian Development Bank.

VIE 2225 NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT

ABBREVIATION

ADB Asian Development Bank CEP Certification of Environmental Protection CMC Construction Monitoring Consultants CPC People’s Committee CPPMB Central Power Project Management Board DPC District People’s Committee DONRE Department of Natural Resources & Environment EM Environmental Monitoring EMF Electromagnetic Field EMP Environment Management Plan ES Environmental Sanitation IEE Initial Environmental Examination LIC Local Implementation Consultant MONRE Ministry of Natural Resource & Environment NPPMB Northern Power Project Management Board NPT National Power Transmission Corporation PPTA Project Preparatory Technical Assistance PPE Personnel Protective Equipment PTC Power Transmission Company QCVN Technical Standard ROWs Right of Ways SPS Safeguard Policy Statement S/S Substation TCVN Vietnam Standard T/L Transmission line VICA VICA International Consultants Company

Semi-Annual Environmental Monitoring Report Page 2 VIE 2225 NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT

CONTENTS

ABBREVIATION ...... 2 EXECUTIVE SUMMARY ...... 4 1. OVERVIEW ...... 6 1.1 Project Background ...... 6

1.2 Objectives and Study Approach ...... 8

2. ENVIRONMENTAL COMPLIANCE OF SUBPROJECTS ...... 8 2.1 500 kV Son La- Nho Quan- Hoa BinhT/L and 500kV Son La-Hiep Hoa T/L Subprojects ...... 12

2.2 500kV Hiep Hoa Substation ...... 18

2.3 220kV Thanh Hoa – Vinh Transmission line ...... 23

2.4 220kV Bim Son substation and 220kV Tuyen Quang substation ...... 27

2.5 Three additional subprojects of 220kV Kim Dong Substation, 220kV Thuong Tin – Kim Dong T/L and Hai Duong 2 S/S ...... 28

3. CONCLUSIONS AND RECOMMENDATIONS ...... 29 3.1 Conclusions ...... 29

3.2 Recommendations ...... 29

ANNEXES ...... 31 Annex No.1. Detailed construction status of 220kV Thanh Hoa-Vinh T/L subproject (as of December 31 st 2012) ...... 32

Annex No.4. List of interviewed officials ...... 36

Annex No.5. Technical report prepared by transmission line and Hoa Binh transmission line ...... 38

Annex No.6. Environmental Monitoring Template for 220kV Thanh Hoa- Vinh Transmission Line ...... 47

Annex No.7. Environmental Monitoring Template for 500kVSon La- Hiep Hoa T/L ... 53

Annex No.8. Environmental Monitoring Template for 500kV Hiep Hoa Substation ... 57

Semi-Annual Environmental Monitoring Report Page 3 VIE 2225 NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT

EXECUTIVE SUMMARY

In 2005, the Asian Development Bank (ADB) financed a Project Preparatory Technical Assistance (PPTA) to provide consultants that will assist the Northern Power Project Management Board (NPPMB) in the preparation of Initial Environmental Examination (IEE) for the following three core subprojects: (i) 500 kV Son La Hoa Binh and Son La Nho Quan transmission line, (ii) 220 kV Thanh HoaNghi SonVinh transmission line, and (iii) extension of Van Tri 220 kV substation. The IEE for Son La – Hoa Binh – Nho Quan Transmission Line (TL) and 220kV Thanh Hoa –Vinh Transmission Line Subprojects were both approved by ADB and the Government of Viet Nam and will be updated and finalized following the detailed design, subject to ADB review and approval. For the Van Tri Substation, it was determined during the PPTA that no land acquisition will be involved and no IEE was prepared. The PPTA consultants also prepared an Environment Policy Framework to guide the NPPMB in the preparation of IEE for the following subprojects: (i). Son La Hiep Hoa 500 kV Transmission Line (TL);

(ii). Quang Ninh Mong Duong 500 kV TL;

(iii). Hiep Hoa 500 kV substation;

(iv). Expansion of 500kV Thuong Tin; and

(v). Ha Tinh Thach Khe 220 kV TL

At present, two subproject (Ha Tinh Thach Khe 220kV T/L and Quang Ninh Mong Duong 500kV T/L) have been replaced by three new subprojects (500kV Nho Quan substation 2nd transformer, 220kV Tuyen Quang substation and 220kV Bim Son substation). To utilize the loan savings, the Electricity of Viet Nam (EVN) with the agreement of ADB decided to add three more subprojects into the Loan 2225VIE namely Kim Dong 220kV substation, Hai Duong 2 220 KV substation and Thuong TinKim Dong 220kV T/L. As such, in the VIE2225 framework, there are 12 subprojects namely (i) Son La – Hoa Binh – Nho Quan 500kVTransmission Line, (ii) 220kV Thanh Hoa – Vinh T/L; (iii) Son La Hiep Hoa 500 kV Transmission Line; (iv) Expansion of 500kV Thuong Tin; (v)Extension 220kV Van Tri Substation; (vi)Hiep Hoa 500 kV substation; (vii) 220kV Bim Son substation; (viii) 220kV Tuyen Quang substation; (ix) Extension 500kV Nho Quan substation 2nd transformer; (x) Kim Dong 220kV s/s; (xi) Thuong TinKim Dong 220kV T/L; and (xii)Hai Duong 2 220 KV s/s. On February 2, 2010, Northern Power Project Management Board (NPPMB) and VICA International Consultants Company (VICA) signed a consultancy contract on “Resettlement and Environmental Consultancy of Northern Power Transmission Expansion Project funded by ADB”. VICA will help NPPMB to supervise the environmental compliance of subprojects during the construction and operation stages. In 2011, the 4th, 5th, 6th and 7th monitoring reports were prepared and submitted to NPPMB. In 2012, the 8 th , 9th , 10 th and 11 th monitoring reports prepared by VICA were implemented in April, June, September and December, respectively Due to the changes on the list of subprojects and other issues during the project implementation, there was a need to have corrective action plan to comply with the requirements of the ADB environmental safeguards. To assist the NPPMB in its compliance with the environmental safeguards of ADB, a local implementation consultant (LIC) for the environment was employed in the project. The LIC was engaged in the project for 22 months, starting March 2012.

Semi-Annual Environmental Monitoring Report Page 4 VIE 2225 NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT

Since then, on behalf of NPPMB, LIC Environment has provided support to VICA consultants to ensure the environmental compliance of the whole VIE2225 project to ADB Safeguard Policy Statement (SPS) 2009 and environmental regulation of the Government of Viet Nam. This semiannual environmental monitoring report was prepared with information provided mostly from results of 10th and 11th monitoring reports prepared by VICA covering the period from July to December 2012. Some information has been referred to the 3rd and 4 nd Quarterly Reports prepared by LIC and submitted to NPPMB and ADB. The preparation of semiannual report was additionally requested by ADB during its Review Mission to Vietnam in September 2012. To develop the report, the LIC has worked with the NPPMB, VICA and local authorities in subproject areas to update the environmental compliance of the subprojects and conducted site visit and public consultation in Hai Duong 2 220kV Substation.

Semi-Annual Environmental Monitoring Report Page 5 VIE 2225 NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT 1. OVERVIEW

1.1 Project Background

1. Project ”Northern Power Transmission expansion sector” represents a 5 year time slice of Electricity of Viet Nam’s (EVN) transmission expansion program, covering 500kV and 220kV transmission lines, and associated substations. The project covers the northern part of Viet Nam which is relatively poor. The project will enable power to be supplied to the planned industrial zones in the region, thereby facilitating employment and income generating opportunities. Thus it will benefit the poor and ethnic minorities living in the project area. The project will also create the potential for power interconnection between Viet Nam and the People’s Republic of China.

2. The Project is to (i) strengthen the northern transmission network to improve system’s reliability and quality of supply, (ii) facilitate power transmission by removing transmission bottlenecks, (iii) reduce transmission losses, and (iv) facilitate efficient utilization of existing and planned power plants.

3. The Project was approved on 21 December 2005. The loan agreements were signed on 22 August 2006 and declared effective on 24 November 2006 for a total loan amount of $360 million. Original loan closing date was 31 December 2010 and extended on a onetime basis to 31 December 2013.

4. Under the Project, nine subprojects comprising three core subprojects, three noncore subprojects and three replacement subprojects have been implemented in Northern Viet Nam. The three core subprojects are: (i) 500 kV Son La Hoa Binh and Son La Nho Quan transmission line, (ii) 220 kV Thanh HoaNghi SonVinh transmission line, and (iii) extension of Van Tri 220 kV substation. Three noncore subprojects are: i) Son La Hiep Hoa transmission line; (ii) expansion of Thuong Tin 500 kV substation; and (iii) Hiep Hoa 500 kV new substation. Three subprojects which replaced originally proposed Ha TinhThach Khe and Quang Ninh Mong Duong transmission lines are: (i) expansion of the Nho Quan 500 kV substation (2nd transformer), (ii) Tuyen Quang 220 kV new substation and (iii) Bim Son 220 kV new substation. The above three replacement subprojects were decided based on the priority electricity supply requirements.

5. Three additional subprojects have been proposed for implementation utilizing the loan savings of about $29 million. The proposed new projects are: (i) Hai Duong 220 kV new substation; (ii) Kim Dong 220 kV new substation; and (iii) Thuong Tin Kim Dong 220 kV transmission line.

6. As such, in the VIE2225 framework, there are 12 subprojects namely (i) Son La – Hoa Binh – Nho Quan 500kVTransmission Line, (ii) 220kV Thanh Hoa – Vinh T/L; (iii) Son La - Hiep Hoa 500 kV Transmission Line; (iv) Expansion of 500kV Thuong Tin; (v) Extension 220kV Van Tri Substation; (vi)Hiep Hoa 500 kV substation; (vii) 220kV Bim Son substation; (viii) 220kV Tuyen Quang substation; (ix) Extension 500kV Nho Quan substation 2nd transformer; (x) Kim Dong 220kV s/s; (xi) Thuong Tin-Kim Dong 220kV T/L; and (xii)Hai Duong 2 220 KV s/s

7. NPPMB and CPPMB are two implementing units. Out of the nine approved subprojects, NPPBM is implementing eight subprojects and CPPMB is implementing one subproject which is Hiep Hoa 500 kV new substation.

Semi-Annual Environmental Monitoring Report Page 6 VIE 2225 NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT

Semi-Annual Environmental Monitoring Report Page 7 VIE 2225 NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT

8. In the implementation progress, international and domestic experts will assist NPPMB and CPPMB in environmental management planning and implementation of resettlement plans.

9. VICA Consultants International Company Ltd. (VICA) has been engaged by NPPBM since February 2010 to provide services in preparation of safeguards (environment and resettlement) documents. VICA will also help NPPMB to supervise the environmental compliance of subprojects during the construction and operation.

10. To further assist NPPMB to review safeguards documents to ensure compliance with ADB safeguards policy and to monitor implementation of the safeguards the local implementation consultant (LIC) environment has been engaged in a lumpsum contract for 22 months, starting from March, 2012

11. This semiannual environmental monitoring report will mention on: (i) spot check environmental compliance of sub projects under VIE2225 Loan covering the period from July 2012 to December 2012 and (ii) recommendations to improve the environmental safeguard compliance in the next period 1.2 Objectives and Study Approach

1. At present, among the 12 subprojects, the 220kV Thanh Hoa – Vinh T/L was constructed with no significant environmental impacts, 220kV Bim Son Substation, 220kv Tuyen Quang started construction on December and there were also no anticipated significant environmental impacts. The IEEs of the three new subprojects: (i) 220 KV Kim Dong substation; (ii) Thuong Tin Kim Dong T/L and (iii) Hai Duong 2 substation were approved by ADB and are currently under the bidding stage. The remaining six subprojects are operational and no significant environmental issues are of concern.

2. The main objectives of the project monitoring are to implement the environmental monitoring program; assess the environment condition at the construction sites; and strengthen the effectiveness of the environmental monitoring system with the participation of the relevant stakeholders.

3. To achieve these objectives, the methodology employed are the following :

4. Review of project documents IEEs, Loan Agreement, Project Documents, Environmental Monitoring Reports, Memorandum of understanding from ADB’s missions, ADB ‘s SPS 2009, ADB’s Guidelines on environmental assessment, and the 10 th and 11 th Environmental Monitoring Report prepared by VICA;

5. Maintain close dialogue with ADB Safeguard Specialists, NPPMP, CPPMP, VICA, LIC social, CMCs, contractors, and local authorities; and

6. Site visits. Several visits were conducted to spot check the environmental compliance in the following subprojects 500kV Son La – Hiep Hoa transmission line; 500kV Hiep Hoa substation;, 220kV Thanh Hoa – Vinh transmission line; Van Tri; Thuong Tin Kim Dong; Kim Dong substation; Hai Duong 2 substation; and Hiep Hoa substation.

2. ENVIRONMENTAL COMPLIANCE OF SUBPROJECTS

The status of the environmental compliance of the subprojects and LIC activities are summarized in Table 1.

Semi-Annual Environmental Monitoring Report Page 8 VIE 2225 NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT Table 1: Implemented activities in 12 subprojects of VIE-2225 (As of December 31st, 2012)

No Subproject Location CEP IEE Status LIC activities

SUBPROJECTS THAT ARE COMPLETED AND OPERATIONAL

1 500 kv Son La Nho eight districts of Done Done Construction completed • LIC provided support to VICA in the spot Quan Hoa Binh T/L provinces of Son La and energized in check monitoring on December 2012 Ninh Binh and Hoa Binh December 2010 . • LIC reviewed the spot check monitoring report No 11th prepared by VICA

• No required any action in next quarter

2 500kV Son La Hiep 19 districts of five Done Done Construction completed • LIC provided support to VICA in the spot Hoa Transmission Line provinces of Son La, and energized in 31 check monitoring on December 2012 March 2012 Phu Tho, Vinh Phuc, Thai Nguyen and Bac • LIC reviewed the spot check monitoring Giang reports No 11th prepared by VICA • No required any action in next quarter

3 500kV Hiep Hoa Hiep Hoa district of Done Done Construction completed • LIC conducted the spot check monitoring Substation Bac Giang province and energized in 31 on Sep 2012 and provided technical March 2012 assistance to VICA for the spot check monitoring on December 2012

• LIC reviewed the spot check monitoring reports No 11th prepared by VICA

• It not required any action in next quarter

None None 4 Expansion of 500kV Thuong Tin, Construction completed • Expansion of substations are on the Thuong Tin Substation and energized in January existing premises, hence, there are no 2011 significant environmental impacts

Semi-Annual Environmental Monitoring Report Page 9 VIE 2225 NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT • It is therefore not required any action

5 Expansion 500kV Nho Nho quan district, Ninh None None Completed and has been • Expansion of substations are on the Quan substation Binh prov. energized in March 2012 existing premises, hence, there are no significant environmental impacts

• It is therefore not required any action

SUBPROJECTS THAT ARE UNDER CONSTRUCTION

6 220kV Thanh Hoa – 10 districts of two Done Done Under construction • LIC conducted the spot check monitoring Vinh Transmission line provinces Thanh Hoa 365/391 foundation have on Sep 2012 and Nghe An been built • LIC reviewed the spot check monitoring 164/391 towers have reports No 11th prepared by VICA and been erected implemented some corrective actions

7 220kV Bim Son Bim Son town, Thanh Done Done Under construction • LIC will conduct the quarterly spot check substation Hoa province monitoring for the civil works in 2013

8 220kV Tuyen Quang Yen Son town, Tuyen Done Done Under bidding (equipment • LIC will conduct the quarterly spot check substation Quang province and construction of substation, feeders of monitoring for the civil works in 2013 220kv, 110kv, 35kv)

SUBPROJECTS THAT ARE UNDERGOING THE BIDDING PROCESS

9 Extension 220kV Van Van Tri, Hanoi None None Under bidding (equipment • Expansion of substations are on the Tri Substation only) existing premises, hence, there are no significant environmental impacts

• It is therefore not required any action

10 220kV Kim Dong Kim Dong district, Done Done Under bidding • LIC conducted the spot check monitoring Substation Hanoi on Sep 2012

• LIC will conduct the quarterly spot check

Semi-Annual Environmental Monitoring Report Page 10 VIE 2225 NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT monitoring for the civil works in 2013

11 220kV Thuong Tin – Thuong Tin district, Done Done Under bidding • LIC conducted the spot check monitoring Kim Dong transmission Hanoi and twoistricts of on Sep 2012 line Khoai Chau and Kim Dong of Hung Yen • LIC will conduct the quarterly spot check province monitoring for the civil works in 2013

12 220kV Hai Duong 2 Kinh Mon district, Hai Done Done Under bidding • LIC conducted the spot check monitoring Substation Duong prov. on Sep 2012

• LIC will conduct the quarterly spot check monitoring for the civil works in 2013

Semi-Annual Environmental Monitoring Report Page 11 VIE 2225 NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT

2.1 500 kV Son La- Nho Quan- Hoa BinhT/L and 500kV Son La-Hiep Hoa T/L Subprojects

2.1.1 Background of 500 kV Son La- Nho Quan- Hoa BinhT/L

7. The length of transmission line is 289.9km, in which the double circuit is 177km and two single circuits are 28.6km and 77.3km. The subproject passes through the provinces of Son La, Hoa Binh and Ninh Binh provinces, 11 districts, and 36 communes. The transmission line includes a 25km offshoot line to a switch bay in Hoa Binh. The subproject is comprised of the construction and installation of; (i) 269 km of double circuit 500kV transmission line and associated composite optical fiber earth wire, (ii) 500kV, 65MVar Shunt Reactor, (iii) 500kV capacitor, and (iv) 500kV switch gear. The construction component of subproject completed and the transmission lines were put in use in December 2010. This is one of the three core subprojects aimed to improve the electricity branch structure of the Northern Transmission Power Cooperation (NPT) and the power supply capacity in Viet Nam.

8. The transmission line was fully energized in November 2010 and has been transmitting power from Son La hydropower since December 2010. 2.1.2 Background of 500kV Son La - Hiep Hoa Transmission Line

9. The total length of Son LaHiep Hoa T/L was 268.47km. The rightofway (ROW) of the T/L was determined in the Decree No. 106/2005/NĐCP and for 500 kV transmission line which was delimited by two vertical planes in parallel to the line on two sides and the distance from the planes to the nearest wire was 7m. The average width of the ROW was 30.45m. The starting point of Son La – Hiep Hoa 500kV T/L was the Son La 500KV substation and the ending point was Hiep Hoa 500KV substation. The T/L traversed 19 districts.

10. The transmission line has been in operation since 31 March 2012 and it is temporarily under the management of the operation unit. 2.1.3 Environmental Compliance of 500kV Son La - Hiep Hoa and Son La-Nho Quan-Hoa Binh Transmission Line

11. On May 2011, VICA carried out its 4th monitoring mission to some sites of the subprojects. It was found that there were no environmental issues during the operation of the subproject. It was also reported by the local resident living along the ROW of the subproject that there was no significant impact of electromagnetic field during the operation of the subprojects.

Picture 1. House of local resident near the ROWs at Yen Quang commune, Nho Quan district – Ninh Binh province ( 4th monitoring report of VICA)

12. In December 2012, LIC provided support to VICA to carry out its 11 th environmental monitoring mission to spot check to the site to ensure that the electromagnetic field will not be a significant impact in the subproject area.

Semi-Annual Environmental Monitoring Report Page 12 VIE 2225 NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT

Picture 2. Hoa Binh PTC Picture 3: North West PTC

13. 500kV Son LaHoa BinhNho Quan T/L and 500kV Son LaHoa Binh subproject are supervised and managed by the Hoa Binh Power Transmission Company (PTC) and North West Power Transmission Company, respectively. The consultant team worked with Hoa Binh PTC and North West operation units to review the existing management of two transmission lines under the project. The key contents focus on type of ROWs, guidelines and frequency of ROW and tower inspection, waste collection after ROW clearance, and other potential problems that may be encountered during the operation of the transmission lines.

14. Operation Management: The number of workers of each unit is approximately 20 persons. Their duties are to operate and maintain not only towers under the project but also other towers allocated by National Transmission Line Company. Each worker performed five field inspections in a month to inspect tower and ROW allocated and the maintenance of the transmission line. The remaining working days are spent at the office unit. All offices are provided with sanitation facilities including drainage, hygienic toilet with septic tank and waste bins for waste collection. Thus, the environmental impact of the operation of the office is insignificant.

15. Right of way (ROW) maintenance: The type of ROWs under two these transmission lines are the following: (i) Plantation forest (i.e. in Tam Duong, Moc Chau districts) or (ii) Natural forest (i.e. in Mai Chau, Moc Chau districts); or (iii) Rice or crop fields (corn and cassava) (i.e. on the plain in Nho Quan district, on the hill in Mai Son district). ROW maintenance plays an important role in power transmission operation. The frequency of transmission line inspection is specified by the National Transmission Line Company as:

• ROW inspection (including ROW clearance, if any): (i) during the day/ day time: every month; (ii) at night time: every three months;

• Technical inspection: (i) At unit: every month; (ii) at power transmission branch: every three months;

• Intensive inspection: prior to holidays such as New Year, Independent day, Labour day, political or socioeconomic events such as Party congress, National Assembly meeting, People’s Council meeting, extreme weather conditions such as storm, heavy rain, or overloaded transmission line; and

• Incident inspection: Accidents (i.e. lightning, for example).

16. Based on the IEE, the use of chemicals like herbicides and pesticides in ROW clearance has the potential to have a significant impact on the environment. In the project, all transmission line units confirm that no pesticides and herbicides were used during ROW maintenance.

Semi-Annual Environmental Monitoring Report Page 13 VIE 2225 NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT

ROW clearance is done by mechanical equipment like machete and electric hand saw as shown below.

Picture 4. Machete for cutting weeds Picture 5 : Electric hand saw for cutting big trees

Picture 6. Weeds are cut inside the tower No. 89, Mai Picture 7. Litchi trees are cut inside the ROW Son district, Son La province (Son La – Hiep Hoa between towers No. 8888, Mai Son district, Son La 500kV T/L) province (Son La – Hiep Hoa 500kV T/L)

17. Waste collection after clearance: For grasses and small trees, the leaves cut from the clearing operation were left inside the tower for natural decomposition. However, no more weeds can develop inside the tower; there is no impact on the tower. For larger trees, the timber is given to the owners.

18. Difficulties in ROW management: Some sections of ROWs in the Son LaHiep Hoa 500kV transmission line were not accounted and officially handed to the operation units. In order to facilitate the transfer of management to the operation unit, NPPMB should conduct the inventory of trees and properties inside the ROW. Other ROWs for the transmission line are properly maintained.

Semi-Annual Environmental Monitoring Report Page 14 VIE 2225 NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT

Picture 8. Trees inside ROW is not cleared among towers No. 8587, Mai Son district, Son La province because the compensation price has not been achieved yet (Son La – Hiep Hoa 500kV transmission line)

Picture 9. ROW is clear among towers No. 8890, Picture 10 . ROW is clear between towers No. 110 Mai Son district, Son La province (Son La – Hiep 111, Son La province (Son La – Nho Quan – Hoa Hoa 500kV T/L) Binh 500kV T/L)

19. Labor safety : To ensure work safety in an electric company, safety procedures and guidelines are prepared and applied by all operation units including: (i) Decision No. 1186/QDEVN dated 07/12/2011 issued by EVN on Standard No. QT0301; (ii) Decision No. 0299/QDNPT dated 12/11/2012 issued by NPT on Standard No. QT0412.

20. Safety training is conducted annually and personnel protective equipments (PPE) are provided to all the workers. Personnel protective equipment consist of clothing, helmet, boots, for each

Semi-Annual Environmental Monitoring Report Page 15 VIE 2225 NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT

worker and one electromagnetic field protective clothing for each unit when working on tower operation. For the large repair of transmission line, the PPEs is included in the general work cost.

Picture 11 . Labor equipment book provided for each worker at Viet Tri transmission line unit

Picture 12 . Equipment store at Mai Son Picture 13. Electromagnetic field protective transmission line unit clothing at Mai Son transmission line unit

21. As regulated, health of all workers are examined all workers’ health are examined every six months at the given hospitals or clinics. However, prior to working on the electricity tower, health examination must be conducted at medical room under transmission line unit.

22. Hazard and Risk Management : Landslides surrounding the tower, lightning are some incidents arisen at Son La – Hiep Hoa 500kV transmission line. The occurrence of storms or heavy rains is the main reason for these incidents. To protect the base of the tower, revetment and

Semi-Annual Environmental Monitoring Report Page 16 VIE 2225 NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT

drainage are constructed surrounding the tower (Photo 1415). However, the revetment would sometimes slide the tower No. 90, for example. (Photo 1637)

Picture 14 . Drainage for rainwater at the tower No. Picture 15 . Drainage for rainwater flow at the tower 89, Mai Son district, Son La province No. 85, Mai Son district, Son La province

Picture 16. Revetment was constructed surrounding Picture 17. Revetment slide at the tower No. 90, the tower No.89, Mai Son district, Son La province Mai Son district, Son La province

23. Transmission lines are a potential hazard to aircraft during takeoff and landing. To ensure safety, each tower with over 70 m high will be painted red and white colors to improve the visibility to pilots and lessen the risk of collision.

24. Electromagnetic field: As regulated in IEE, EMF should be annually measured, yearly at the least. However, only EMP of Son La – Hiep Hoa 500kV transmission line has been measured many times by power transmission branches up to the monitoring time. For Son La – Hoa Binh – Nho Quan 500kV transmission line, only Tay Bac Transmission Unit has carried out electromagnetic field measurement at two locations out of the ROWs, closed to residential area at tower No.95 and 96 – Na Bo commune, Mai Son district, Son La province.

25. According to the regulation at Article 1 (4.2.a) of Decree No. 81/2009/NDCP dated 12/10/2009 by the Government on some amended articles of Decree No. 106/2005/NDCP dated 17/8/2005 by the Government stipulating the detail regulation and guideline of some articles of Electricity Law on safety protection for high voltage grid. The results compared with the current regulation showed that all meet the standard and as the previous measured results ( please see annex 3)

Semi-Annual Environmental Monitoring Report Page 17 VIE 2225 NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT

Picture 18. Red and white colors painted on the Picture 19. Red and white colors painted on the tower, Pho Yen district, Thai Nguyen province tower crossing Lo river, Dong Thinh commune, Vinh Phuc province

2.2 500kV Hiep Hoa Substation

2.2.1 Background of 500 kV Hiep Hoa Substation

26. CPPMB is implementing Hiep Hoa 500 kV substation project. The substation is to be powered by Son La hydropower station through 300 km long 500 kV transmission line. Prime Minister’s approval for construction and investment plan of 500 kV Son LaSoc Son transmission line in was obtained in 2005. The original location of substation was proposed at Soc Son. In April 2006, it was decided to move the location of the 500 kV substation from Soc Son to Hiep Hoa situated about 10 km north because the original location is a flood prone area and the provincial authorities not agreeing to the. Two of the three 500 kV power transformers of Hiep Hoa substation were commissioned on 17 December 2011 and the third unit was commissioned on 27 March 2012.

Picture 20. Hiep Hoa Substation Main Picture 21. 500kV Hip Hoa Substation Office

Semi-Annual Environmental Monitoring Report Page 18 VIE 2225 NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT

27. Hiep Hoa 500kV substation was built to meet the increasing demand of electricity in the the Northern power system, especially Hanoi area, while receiving power from the hydro power plants in the Northwest area and thermal power plants in the Northeast area, especially Son La hydropower plant and Quang Ninh and Mong Duong thermalpower plants. Besides, Hiep Hoa Substation creates circuit connections between the regions in the electrical system, enhancing the safe operation and the stability for the national electricity system, reducing power loss in the transmission network. Therefore, the construction of Hiep Hoa 500kV substation is needed for the improvement of the national electricity system. 2.2.2 Environmental Compliance

28. On March and September 2012, LIC visited the site and on June and December 2012, VICA has carried out the 11th monitoring mission to the project site. It was reported that there were no significant environmental issues in the area from the operation of the project. The following were observed during the site visits:

29. Hazardous wastes management: Electrical transformers and other substation equipment used oil for insulation and cooling. There are three transformers using a total of 50 tons of oil. The oil used in the equipment does not contain PCB. However, disposal of equipment containing oil must follow the guidelines on the proper disposal of hazardous wastes. In order to prevent a potential oil leak to surface water, the site will be graded to direct surface runoff to two underground oil ponds (about 100 m 3 for each). A berm was built around all oilfilled equipment and a buried drain pipe will direct surface runoff, along with any oil, to the oil pond. Any accidental release of oil will be contained until it can be collected, transported, treated and disposed by an accredited hazardous waste transporter, treater and disposal plant. These mitigating measures will minimize the potential impacts on the environment of the accidental release of oil.

Picture 22.: Two underground oil ponds at Hiep Hoa 500kV Substation

30. The substation will be equipped with batteries to provide backup power for monitoring, alarm, protective relaying, instrumentation and control, and emergency lighting during power outages. Batteries are normally replaced when they are damaged. The damaged battery is considered as a hazardous waste. Damaged battery, and other wastes such as small batteries (AA or AAA), and fluorescent light tubes will be collected, transported, treated and disposed by an accredited hazardous waste transporter, treater and disposal plant. The substation manager board is planning to buy containers for hazardous wastes in the next quarter.

Semi-Annual Environmental Monitoring Report Page 19 VIE 2225 NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT

Picture 23.: Battery room at Hiep Hoa 500kV Substation

31. Fire prevention system: The operation of the substation is subject to the risk of fire hazard. Incidents such as downed power lines or equipment failure could generate sparks and start a fire. However, the risk of fire was minimized on the installation of highspeed relay equipment. Moreover, a fire fighting system is installed around the substation during the construction phase for fire prevention (Photo 4649). Also, fireextinguishers are placed in the substation (Photo 45, 47). All equipment are regularly checked.

Picture 24: Water tank and pumping control house Picture 25: Fireextinguishers on each floor of for fire fighting and daily workers’ usage control house

Picture 27: Diagram of fire fighting system at Hiep Hoa 500kV substation

Picture 26:Fire fighting system around the substation (the red)

Semi-Annual Environmental Monitoring Report Page 20 VIE 2225 NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT

32. Substation security . In terms of safety and security, the following should be regularly inspected fences, gates, signs, alarm system, lighting system, camera, ground wire system, fire protection equipment, oilfilled equipment. Warning signs are installed at danger sites (Photo 50). There are more than 70 highvoltage lamps installed inside the substation with adjusted intensity.

Picture 26:: Warning signs at Hiep Hoa 500kV substation

Picture 27: Automatic camera and high voltage lamps at Hiep Hoa 500kV substation

33. As regulated, health examination is conducted twice a year for all workers working at the substation and at the transmission lines.

34. Electromagnetic field: As soon as operation, NPPMB cooperated with many relevant stakeholders including DPCs, CPCs, operation units at project sites to measure EMF at

Semi-Annual Environmental Monitoring Report Page 21 VIE 2225 NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT

project site (See annex 3). It was observed the safety system is in place and the operation staffs are aware of the EMF impact and prepare the working shift plan to respond to the issue

35. According to the regulation at Article 1 (4.2.a) of Decree No. 81/2009/NDCP dated 12/10/2009 by the Government on some amended articles of Decree No. 106/2005/NDCP dated 17/8/2005 by the Government stipulating the detail regulation and guideline of some articles of Electricity Law on safety protection for high voltage grid. The results compared with the current regulation showed that all meet the standard and as the previous measured results.

36. Other concerns: There are a total of 21 workers in the substation and four workers are assigned per shift. The control house is designed to meet all the daily needs of the workers, including the following: (i) Domestic waste baskets; (ii) Sanitary toilet with septic tank; (iii) Trees in front of control house to reduce noise and improve microclimate for workers; (iv) Runoff drainage around the substation designed with manholes to keep sand and silt, bar screen for large waste, which is separated with the beam system to oil ponds; (v) The construction of substation has impact on the water flow. An irrigation canal system around the substation is constructed to drain the water in and out of the area.

Picture 28: Bar screen before manhole of drainage Picture 29: Sanitary toilet at the control house system

Picture 30 : Waste Baskets to maintain cleanliness Picture 31 : Control house for workers. in the control house

Semi-Annual Environmental Monitoring Report Page 22 VIE 2225 NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT

Picture 32 : Green trees planted in front of and beside the control house

Picture 33 : Irrigation canals around the substation

2.3 220kV Thanh Hoa – Vinh Transmission line

2.3.1 Background of 220 kV Thanh Hoa-Vinh T/L

37. Thanh Hoa Vinh 220 kV Transmission Line was one of three core subprojects of Northern Power Transmission Expansion Project (other two projects are 500 kv Son La Nho Quan Hoa Binh T/L and Van Tri S/s). The line has a length of 148.3 km passing through ten districts of the two provinces of Thanh Hoa and Nghe An.

38. The 220kV Thanh Hoa – Vinh transmission line will be connected to three substations. For the project activities, the feeder bay of all three substations would be constructed to expand the substation including (i) 220KV Thanh Hoa Substation, (ii) 220kV Nghi Son Substation, and (iii) 220KV Hung Dong Substation. At this quarter, only 220kV Hung Dong Substation has started construction.

2.3.2 Environmental Compliance

39. In order to take over the supervision duties from VICA starting in 2013, LIC started the spot check monitoring to some sites of subproject in Vinh city, Nghi Loc and Dien Chau district, Nghe An province in September 2012. In particular, LIC has visited the Hung Dong 220Kv S/S, which is the ending point of the 220KV Thanh HoaVinh S/S. In Nghi Loc districts, LIC visited some towers and consulted with some DPCs of Nghi Van and Nghi Hung. Similarly, LIC has visited some towers and consulted with some DPCs of Dien Cat and Dien Tho in Dien

Semi-Annual Environmental Monitoring Report Page 23 VIE 2225 NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT

Chau district, Nghe An province. Most of the visited towers are located in sensitive areas of road crossing, cemetery, river, worker camp, material storage locations.

40. The observations from the site visits and consultations are the following; (i) There are no significant environmental pollution due to the construction activities; (ii) the construction of tower foundation has temporarily affect the agriculture practice and in order to address the temporary impact, the contractors/NPPMP compensated the affected people; (iii) the construction of tower foundation has temporally stopped in prevention forest in Nghi Loc district and angle tower position due to land conversion agreement with the Nghi Loc forest management and the lacking of spare part of the angle tower which should be supplied by NPPMB; (iv) the consulted CPCs agreed and supported the subproject and suggested that the best month for the tower construction is in November or December, after the harvest season of farmers; and (v) some household under the ROW of the T/L are concerned on the health effects of electromagnetic field during the operation of the subproject;

41. On November 2012, VICA carried out the 11th monitoring mission to some sites of the subproject. Up to the monitoring time, 93% of tower foundation and 22% of tower erection completed (Annex1), the project progress is behind the agreed schedule for the following reasons: (i) The handover sites to contractors is pending: 26 towers (accounting for 7%), in which: 10 towers from No. 160A to No. 169A in the protection forest (Nghe An province) are in need of the Government’s permission and 16 towers located in the resident land: no agreement with the compensation price is the reason that the sites is not handed over to contractors; (ii) Accessories for tower erection and stringing are not fully supplied by NPPMB.

42. The contractors complied with the mitigation measures to minimize the impact on the environment and on the people in the project area. In particular, there are some issues as following: (i) Rehabilitation of the project area upon completion of site work has been mostly conducted by contractors; (ii) Some sections of the existing roads were used as access road. The contractors have consolidated or repaired after construction completion. In particular the contractors have back filled the top soil, to repair the access roads; (iii) Construction materials gathered at the road side could obstruct the traffic safety but only in some road sections; (iii) The domestic and construction waste were found in some construction sites; (iv) Even the contractors have been complied with labor safety regulations by wearing labour protective equipment, especially helmet, safety belt for workers; but there some workers are not using boots and gloves at the construction site.

Picture 34: Rehabilitation upon completion of Picture 35: Rehabilitation upon completion of tower foundation No. 102A, bidding lot 6.3 – Do tower foundation No. 116A, bidding lot 6.3 – Dien Thanh, Yen Thanh, Nghe An – VIET A Xuan, Dien Chau, Nghe An – VIET A

Semi-Annual Environmental Monitoring Report Page 24 VIE 2225 NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT

Picture 36: Rehabilitation is not done at the tower Picture 37: Backfilling is not done at the tower No. No. 105A, bidding lot 6.3 – Dien Thap, Dien Chau, 99A, bidding lot 6.3 – Do Thanh, Yen Thanh, Nghe Nghe An VIETA An VIETA without warning signs

Picture 38: Access road has just constructed to Picture 39: Access road expanded to the tower the tower No. 209A, bidding lot 6.3 – Hung Dong, No. 34A, bidding lot 6.2 Mai Hung, Quynh Luu, Vinh city, Nghe An IEC Nghe An. Yen Lac Co., Ltd

Picture 40: Access road consolidated to the tower Picture 41: Access road expanded to the tower No. 7A, bidding lot 6.2 – Truong Lam, Tinh Gia, No. 28A, bidding lot 6.2 – Mai Hung, Quynh Luu, Thanh Hoa – SDA11 Nghe An. Yen Lac Co., Ltd

Semi-Annual Environmental Monitoring Report Page 25 VIE 2225 NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT

43. Domestic wastes were scattered at some towers. The wastes are mainly from tower erection activity such as papers placed between tower bars (Picture 4243). Some domestic wastes and remaining construction material are also found at towers No. 34A and 28A (Picture 44 45). The domestic wastes produced at houses renting for workers are often collected by local environmental unit. However, domestic wastes generated at project camps are not often collected. Contractors should follow the guidelines on the collection and disposal of wastes.

Picture 42: Piece of papers are not collected at Picture 43 : Papers not collected at the tower No. the tower No. 202A, bidding lot 6.3 – ongoing 4A, bidding lot 6.2 – ongoing tower erection – tower erection – Nghi Van, Nghi Loc, Nghe An Truong Lam, Tinh Gia, Thanh Hoa – SDA11 IEC

Picture 44: Pieces of papers not collected at the Picture 45: Domestic wastes produced during tower No. 78, bidding lot 6.2 Te Loi commune, tower foundation construction are not collected Nong Cong district, Thanh Hoa province tower and disposed as regulated at the tower No. 34A, erection completed VECC. bidding lot 6.2 – Mai Hung, Quynh Luu, Nghe An. Yen Lac Co., Ltd – tower foundation completed

44. Labor Safety : Only a limited towers are under erection during the monitoring time because each contractor have one or two teams (each team consisting of 12 workers) for tower erection, and each team can be erected for one tower. As mentioned in the previous Semi Annual Environmental Monitoring report, work safety is especially taken notice during tower erection. Objects and workers falling from height are reminded by contractors. Even the contractor has been complied with work safety regulations by equipped labour protective equipment, especially helmet, safety belt for workers; some workers are not using boots and

Semi-Annual Environmental Monitoring Report Page 26 VIE 2225 NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT

gloves at the construction site (Picture 4445). The consultant team still reminds all workers and all contractors taking more notice on that for the next towers and coming activities .

Picture 46: Workers wear labour protective Picture 47: Workers wear labour protective clothing during tower erection at the tower No. clothing during tower erection at the tower No. 28A, 202A, bidding lot 6.3 Nghi Van, Nghi Loc, Nghe bidding lot 6.2 – Mai Hung, Quynh Luu, Nghe An. An IEC Yen Lac Co., Ltd

45. Although there were no reports of any accident to local people on the sites, the contractors shall pay attention to having signs and fencing placed fully in order to ensure occupational safety during construction. The site restoration shall be performed for the next works; the sites shall be cleaned right after the construction phase is completed; impacts on traffic and irrigation shall be immediately resolved; Continue monitor the operation of equipments and construction machines follow the regulations; strictly follow the regulations on hygiene and environmental protection and work safety.

46. Since the subproject is still in progress, environmental monitoring should be continuously observed in the next quarter. In addition, the capacity building for stakeholder could be an issue. LIC with supported by NPPMB will work closely with VICA to make sure the environmental compliance in whole subproject areas. 2.4 220kV Bim Son substation and 220kV Tuyen Quang substation

2.4.1 Background

47. Subproject of Tuyen Quang 220kV substation is proposed in order to meet capacity transmission for Tuyen Quang Provincial load in particular and for region in general; enhance reliability and safety of power supply and power quality for Tuyen Quang’s and Northern Vietnam region’s power network. The project creates combination among regions in Northern Vietnam mountainous power system that is an important basis to operate system that is stable and contributes to reduce the loss of capacity of the system. The proposed Tuyen Quang 220kV substation is located on low hill area planting eucalyptus and tea in Kim Phu Commune, Yen Son District, Tuyen Quang Province.

48. The proposed Bim Son 220kV substation is located in Bac Son , Bim Son town, Thanh Hoa province. Main project features are the 220kV side, the 110 kV side and The 35kV and 22kV side. Main objects of subproject are contributing to meet the electricity supply demand for Bim Son town and industry zones, strengthen and enhance networks that provide the longterm stability and reliability for two provinces Thanh Hoa and Ninh Binh; To increase stability, operational safety for power network and reduce the loss of electric energy, the loss of power in the grid and contribute to raise the efficiency of electricity production and trading of

Semi-Annual Environmental Monitoring Report Page 27 VIE 2225 NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT

EVN. Therefore, 220kV Bim Son substation will play an important part in the power source which mainly supply electricity for the fast development of load in this area. 2.4.1 Environmental Compliance

49. The civil work contracts have just been awarded to contractors. It is expected that construction will commence in late December. The civil works contracts are estimated at $3.343 million and $3.623 million for Tuyen Quang and Bim Son substations, respectively.

50. There is no need to do spot check monitoring this year because the project has just commenced construction in December.

51. However, LIC will work closely with NPPMP to conduct the spot check environmental monitoring in the July 2013. 2.5 Three additional subprojects of 220kV Kim Dong Substation, 220kV Thuong Tin – Kim Dong T/L and Hai Duong 2 S/S

52. There are three additional subprojects for VIE2225 in order to utilize loan savings. The three subprojects are Hai Duong 220 kV new substation, King Dong 220 kV new substation, Thuong Tin Kim Dong 220 kV transmission line.

53. VICA is responsible for the preparation of IEE and CEP in order to comply with the ADB SPS 2009 and Government, respectively. LIC reviewed and evaluated the IEEs of Kim Dong 220kV S/s and 220kV Thuong TinKim Dong T/L.

54. LIC was also requested by NPPMB to prepare the IEE for 220KV Hai Duong 2 S/S. Several meetings with NPPMP and ADB Safeguard Specialist were conducted in order to help the LIC to understand the project and properly prepare the IEE.

55. LIC was also requested by NPPMB to prepare the IEE for 220KV Hai Duong 2 S/S. LIC was requested to organize the public consultation in project area of Hai Duong 2 S/s. Public consultation meeting was held in 21 April 2012 in An Phu commune, Kinh Mon district, Hai Duong province. The revised IEE has also been approved by ADB on September, 2012.

Picture 48. The proposed site for the 220kV Kim Picture 49. ROW of 220kV Thuong TinKim Dong Dong S/S in Toan Thang commune, Kim Dong T/L (feeder side at the Kim Dong S/S district, Hung Yen province (close to the National Road No 18)

Semi-Annual Environmental Monitoring Report Page 28 VIE 2225 NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT

Picture 50. Current condition at the site of Hai Duong 2 220kV substation in An Phu commune, Kinh Mon district, Hai Duong province 56. LIC suggest that the three subprojects would be closely monitored during the construction in the next half year of 2013. Before that, however, LIC will provide support to NPPPM to ensure the agreed EMP should be incorporated in the bidding documents.

3. CONCLUSIONS AND RECOMMENDATIONS

3.1 Conclusions

57. Overall, the contractors implement the mitigation measures during the construction phase and site restoration after the completion of construction.

58. 500kV Son La – Hiep Hoa and 500kV Son LaNho QuanHoa Binh transmission line subproject have operated properly and up to now there is no accident or problem recorded. Site restoration for borrowed lands was completed; affected road has been repaired; electrical field intensity inside and outside of ROW are lower than permitted level; the ROW distance has been maintained.

59. 500kV Hiep Hoa substation subproject is also operated properly. Up to the time of the monitoring trip, there is no accident recorded. The management and operation unit is also closely monitoring the cleanliness and fire prevention in the project area and control house. Site restoration for borrowed road, canal closed to the substation has been done completely. the electromagnetic field (EMF) is under safe condition

60. 220kV Thanh Hoa – Vinh transmission line subproject has completed construction of nearly all the tower foundation and the contractor is starting to construct the tower installation and stringing. The impact on local environment from subproject activities is unremarkable; site restoration for borrowed land has been done well.

61. 220Kv Bim Son and 220kV Tuyen Quang Substation are just being constructed. No environmental concerns were observed.

62. IEEs of 220 kv Thuong Tin Kim Dong subproject, Kim Dong S/S, Hai Duong 2 S/S are being finalized with the guidance of ADB.

3.2 Recommendations

63. For the environmental concerns, the consultant recommendations the following to help the stakeholders improve the implementation of the environmental management plan:

Semi-Annual Environmental Monitoring Report Page 29 VIE 2225 NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT

64. 500kV Son La – Hiep Hoa transmission line subproject: continue maintenance activities on the ROW, regularly inspect occupational safety along the transmission line; periodically measure the intensity of electrical field; ensure safety for maintenance workers during their work on the line.

65. 500kV Hiep Hoa substation subproject: Continue maintain the substation well and ensure the safety for operation workers; conduct medical examination periodically for operation workers; equip and maintain fire fighting gear regularly. It is needed to periodically monitor the electromagnetic field (EMF)

66. 220kV Thanh Hoa – Vinh transmission line subproject: The site restoration shall be performed for the next works; the sites shall be cleaned right after completion, impacts on traffic and irrigation shall be immediately resolved, strictly follow the regulations on hygiene and environmental protection and work safety.

67. 220Kv Bim Son and 220kV Tuyen Quang Substation, 220 kv Thuong Tin Kim Dong subproject, Kim Dong S/S, Hai Duong 2 S/S should be properly monitored in the succeeding site visits.

Semi-Annual Environmental Monitoring Report Page 30 VIE 2225 NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT

ANNEXES

Semi-Annual Environmental Monitoring Report Page 31 VIE 2225 NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT

Annex No.1. Detailed construction status of 220kV Thanh Hoa-Vinh T/L subproject (as of December 31 st 2012)

Number Tower Tower Wire # Contractor Tower code of Commune/District Foundation erection stringing towers Power construction installation Ltd. Dong Son district: Thieu Van, Thieu Trung commune Company No. 4 (PCC4) Dong Son district: Dong Hoang, Dong Ninh, Dong Hoa commune. 1. SP(1)51 51 51 0 0 Trieu Son district: Khuyen Nong, Dong Tien, Dong Thang commune Nong Cong district: Hoang Son, Trung Chinh commune Vietnam electricity construction joint Nong Cong district: Trung Chinh, Trung Y, Te Thang, Te Tan, Te Nong, Te Loi, 52138 2. stock corporation 87 85 0 0 Thang Tho, Cong Liem, Cong Chinh, Cong Binh, yen My commune 108B, 109B Tinh Gia district: Phu Son, Cat Son commune Song Da joint stock company No. 11 139169, Tinh Gia district: Phu Son, Phu Lam, Tung Lam, Tan Truong, Truong Lam 3. 166B 49 33 0 0 commune. 1A13A, 1B Quynh Luu district: Quynh Thien commune Power construction installation Ltd. 4. 14A27A 14 14 0 0 Quynh Luu district: Hoang Mai, Quynh Vinh commune Company No. 2. Branch 7 5. Yen Lac Ltd Company 28A51A 24 22 0 0 Quynh Luu district: Mai Hung, Quynh Xuan, Quynh Van, Quynh Thach commune Power construction installation Ltd. 6. 52A57A 6 6 0 0 Quynh Luu district: Quynh Hoa commune Company No. 2. Branch 6 Power construction installation Ltd. 7. 58A64A 7 7 0 0 Quynh Luu district: Quynh Hoa, Quynh My commune Company No. 2. Branch 4 Power construction installation Ltd. Quynh Luu district: Quynh My, Quynh Lam, Quynh Giang commune 8. 65A78A 14 13 8 0 Company No. 2. Branch 2 Dien Chau district: Dien Doai commune Power construction installation Ltd. 9. 79A87A 9 9 7 0 Dien Chau district: Dien Doai, Dien Yen commune Company No. 2. Branch 3 Viet A investment commercial Dien Chau district: Dien Yen, Dien Thap, Dien Lien, Dien Xuan, Dien Hong, Dien 10. industrial group holdings company 88A128A 41 36 8 0 Hanh, Dien Quang, Dien Cat commune Yen Thanh district : Do Thanh commune Mechanical Installation Joint Stock 11. 129A154A 26 26 20 0 Dien Chau district: Dien Cat, Dien Loi, Dien Tho, Dien Phu commune Company (INCO) Electrical Mechanical Installation 155A Dien Chau district: Dien Thinh commune 12. and Construction Joint Stock 213A(EP), 59 36 30 0 Nghi Loc district: Nghi Hung, Nghi Thuan, Nghi Hoa, Nghi Dien, Nghi Van commune Company (IMEC) 194B, 201B Vinh city: Hung Dong commune Total 390 361 87 0 0 % completed 93 22 0 0

Semi-Annual Environmental Monitoring Report Page 32 VIE 2225 NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT

Annex No.2. Summary of subprojects during operation phase

Location Number Son La – Hiep Hoa Expansion 500kV Expansion 500kV Operation unit Son La – Hoa Binh – Nho Quan Hiep Hoa 500kV of staff 500kV transmission Thuong Tin Nho Quan 500kV transmission line substation line Substation substation Starting time for operation April 2012 September 2011 April 2012 January 2011 March 2011 1 Tay Bac Power Transmission Muong La unit 20 VT01 VT69 0170 (2 lines) Mai Son unit 29 VT70 VT125 71210 (2 lines) Phu Yen unit 34 VT126 VT283 Viet Tri unit 28 VT284 VT408 2 Hoa Binh Power Transmission Moc Chau unit 15 212352 (2 lines) Mai Chau unit 29 353400 (2 lines) 401417 (Line 1: Son La – Hoa Binh) 0260 (Line 2: Son La – Nho Quan) Lac Son unit 31 61162 (Line 2: Son La – Nho Quan) Hoa Binh unit 32 418451 (Line 1: Son La – Hoa Binh) 3 Ninh Binh Power Transmission Nho Quan unit 38 163190 (Line 2: Son La – Nho Quan) Nho Quan substation 21 Nho Quan Substation 4 Thai Nguyen Power Transmission Soc Son unit 20 VT409 VT551 Hiep Hoa 500kV substation 21 Hiep Hoa 500kV substation 5 Ha Noi Power Transmission (Power Transmission Company 1) Thuong Tin Substation 20 500kV Thuong Tin Substation Note: Each unit manages more than one transmission line, subproject included.

Semi-Annual Environmental Monitoring Report Page 33 VIE 2225 NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT

Annex No.3. Monitoring data for the intensity of electromagnetic field in 550kV Son La – Hiep Hoa T/L and 500kV Hiep Hoa substation

Standard

Inside the Outside the (Point a, Term 2, Location Date Weather ROW ROW item 4, Article 1, Decree No. 81/2009/ND-CP)

Location 1: Residential 13/6/2012 Sunny <5kV/m area (Thu Lo hamlet, 0.389 kV/m 45.9 V/m Trung Thanh commune, Thai Nguyen)

Location 2: In the field 13/6/3012 Sunny <5kV/m (Trung Thanh commune, 2.4 kV/m 1.2 kV/m Thai Nguyen)

Location 3: At the 500kV 13/6/2012 Sunny <5kV/m Hiep Hoa substation 1.3 kV/m 27 V/m (Bac Giang)

Location 4: Quarter 3 15/6/2012 Drizzly, <5kV/m Phu Loc commune high 2.83.23 1.0 KW/m G7404G7405 (closed to humidity KW/m a road)

Location 5: On the dam 15/6/2012 Sunny <5kV/m body, closed to the 2.3 KW/m 0.5 KW/m section over Red river (Phu Tho)

House of Mr. Nguyen Thanh Ben, Block 7, Phu Ho commune, Phu Tho town, Phu Tho (inside 28/8/2012 36.00 V/m ≤ 1000 V/m the house). 500kV Transmission line Son La – Hiep Hoa

House of Mr. Lai Huu Tien, Block 5, Xuan 3000.00 29/8/2012 ≤ 5000 V/m Quang commune, Tam V/m Nong district, Phu Tho (outside). Transmission

Semi-Annual Environmental Monitoring Report Page 34 VIE 2225 NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT

Standard

Inside the Outside the (Point a, Term 2, Location Date Weather ROW ROW item 4, Article 1, Decree No. 81/2009/ND-CP) line Son La – Hiep Hoa

House of Mr. Ngo Van Hai, Block 10, Hien Quan commune, Tam 30/8/2012 4.5 V/m ≤ 1000 V/m Nong. Transmission line Son La – Hiep Hoa

House of Mr. Tran Trong Suot, Tien Lu commune, Lap Thach district, Vinh 29/11/2012 89 V/m ≤ 1000 V/m Phuc. Transmission line Son La – Hiep Hoa

Semi-Annual Environmental Monitoring Report Page 35 VIE 2225 NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT

Annex No.4. List of interviewed officials

Contact No. Name Position number NPPMB Technical specialist CMC of Thanh HoaVinh 01658.211.556 1. Hoang Dinh Thai T/L Technical specialist CMC of Thanh HoaVinh 0912.437736 2. Hoang Kim Hai T/L 3. Vũ Xuân An Technical staff 0982233805 4. Vũ Mnh Quân Technical staff 0983301829 Contractors Technical staff, Electrical Mechanical Installation 0983.509.963 5. Truong Van Tu and Construction Joint Stock Company Technical staff, Mechanical Installation Joint 0949.943.173 6. Nguyen Duc Thanh Stock Company Technical staff, Power construction installation 0986.662.790 7. Bui Van Mao Ltd. Company No. 2, Branch No.3 8. Bui Van Nam Chairman of Dien Doai CPC 0986.101.330 9. Nguyen Ba Tinh Chairman of Quynh Lam CPC 01689.707.278 Technical staff, Power construction installation 0962.885.248 10. Nguyen Van Hao Ltd. Company No. 2, Branch No.2 Technical staff, Song Da Construction and 0916.869.838 11. Ly Dinh Hieu Service JSC. 12. Ha Huu Tri Technical staff, Song Da No. 11 company 0984 119 456

13. Nguyen Xuan Hong Technical staff, Yen Lac company 096 381 5649

Power Transmission

Companies (PTC)

14. Gian Dinh Minh Technical staff, 220kV Hung Dong Substation 0983.406.588

15. Nguyen Cong An Head of Mai Son unit 0915 223 736

16. Phan Dong Minh Vicedirector, Hoa Binh PTC 0963 316 727

Deputy head department of Technical, Hoa Binh 0989 127 609 17. Dinh The Hung PTC

18. Tran Quoc Dat Safety staff, Hoa Binh PTC 0915 438 047

19. Pham Van Nguyen Vicedirector, Northwest PTC 0963 220 969

20. Phan Quoc Hong Safety staff, Northwest PTC 0913 587 714

21. Dang Van Sinh Head of Viet Tri unit 0963 636 939 22. Nguyen Duc Hung Director, Thai Nguyen PTC 23. Tran Dinh Nam Deputy head, 500kv Hiep Hoa substation 0962 191 173

Commune People

Committee (CPC)

24. Le Viet Tuan Chairman of Nghi Van CPC 0985.548.489 0383.612.204 25. Nguyen Van Khai Vice chairman of the Party of Nghi Hung CPC

Semi-Annual Environmental Monitoring Report Page 36 VIE 2225 NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT

Contact No. Name Position number 26. Hoang Van Thai Land official, Nghi Hung CPC 01263.981.647 27. Nguyen Xuan Huy Vice chairman of Dien Cat CPC 0984.352.566 28. Dang Quang Trung Vice chairman of Dien Tho CPC 0984.659.968 29. Bui Van Nam Chairman of Dien Doai CPC 0986.101.330 30. Nguyen Ba Tinh Chairman of Quynh Lam CPC 01689.707.278 31. Do The Thong Chairman of Truong Lam CPC 0986.542.377 32. Chu Tuan Dung Land construction official, Nghi Thuan CPC 0977 659 318 33. Dang Ba Kien Vicechairman, Nghi Thuan CPC 0975 477 158 34. Nguyen Xuan Quang Vicechairman, Hung Dong CPC 0982 537 255 35. Ho Van Thanh Technical staff – Viet A company 0905 516 254 36. Ho Xuan Huong Vicechairman, Do Thanh CPC 01699 557 247 37. Ho Sy Tan Land official, Do Thanh CPC 01666 090 098 38. Truong Van Thuy Chairman, Dien Xuan CPC 0979 986 757 39. Dinh Xuan Loc Land official, Dien Yen CPC 0916 546 919 40. Le Quang Hao Head of village No. 15, Dien Yen commune 0169 4346 517 41. Nguyen Duc Chau Vice chairman, Dien Yen CPC 0948 280 769 42. Nguyen Duy Thao Chairmain, Quynh Xuan CPC 0983 451 377 43. Le Van Ba Vicechairman, Quynh Van CPC 0987 723 195 44. Nguyen Van Xung Vicechairman, Tung Lam CPC 0977 193 946 45. Le Duc Nam Chairman, Phu Lam CPC 0985 506 616 46. Hoang Van Khanh Chairman, Te Thang CPC 0988 832 873 47. Ha Van Tich Vicechairman, Tong Dau CPC 0919 746 048 48. Ha Van Nhung Vicechairman, Dong Bang CPC 0944 755 659 49. Tran Van Dong Chairman, Dai Thanh CPC 0936 709 519

Semi-Annual Environmental Monitoring Report Page 37 VIE 2225 NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT

Annex No.5. Technical report prepared by Northwest transmission line and Hoa Binh transmission line

Technical report prepared by Hoa Binh Power Transmission

Semi-Annual Environmental Monitoring Report Page 38 VIE 2225 NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT

Semi-Annual Environmental Monitoring Report Page 39 VIE 2225 NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT

Semi-Annual Environmental Monitoring Report Page 40 VIE 2225 NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT

Semi-Annual Environmental Monitoring Report Page 41 VIE 2225 NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT

Semi-Annual Environmental Monitoring Report Page 42 VIE 2225 NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT

Semi-Annual Environmental Monitoring Report Page 43 VIE 2225 NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT

Technical report prepared by Northwest Power Transmission

Semi-Annual Environmental Monitoring Report Page 44 VIE 2225 NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT

Semi-Annual Environmental Monitoring Report Page 45 VIE 2225 NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT

Semi-Annual Environmental Monitoring Report Page 46 VIE 2225 NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT

Annex No.6. Environmental Monitoring Template for 220kV Thanh Hoa- Vinh Transmission Line 1. Environmental monitoring checklist Project: 2225 – VIE Northern Power Transmission Expansion Sector Project; Subproject: 220kV Thanh Hoa – Vinh transmission line subproject Monitor name: VICA Consultants International Ltd. Contractor: Electrical Mechanical Installation and Construction JSC. Monitoring timing: Morning Weather condition: Sunny, breeze Monitoring date: 21/11/2012 Monitoring location: The route in Vinh city and Nghi Loc district, Nghe An. Compliant Follow-Up action Environmental Mitigation measures Remarks issues Yes/No Needed

• Cover the trucks in charge of material transport to prevent falls. Dust and exhaust • Water the transport roads and construction sites in dry weather. Yes N/A fumes • The machines should possess appropriate certificates. • The construction work should be performed on day, not at night or in resting Noise and hours. Yes N/A vibration

• Arrange waste water collection ditches around the foundation pit and retention Construction pit to reduce turbidity before discharge to local canals. waste water • Avoid spillage oil at the construction site N/A Ongoing tower erection • Cover and protect construction material

• Conduct the construction work properly to ensure the construction progress. • The excavated soil should be used for backfilling the foundations. Soil pollution, soil Yes N/A erosion • Grow grass, build stone embankment around foundations on large slopes or places with weak geology. • The restoration work should be conducted for all borrowed areas • The excavated soil should be used for backfilling the excavations. A little wastes are papers placed between • Collect all superabundant material The contractor should collect as Solid waste Yes tower bars not collecting at the tower No. soon as tower erection completed 202A (ongoing tower erection)

• The excavated soil should be used for backfilling the excavations. A little wastes are papers placed between • Collect all superabundant material The contractor should collect as Solid waste Yes tower bars not collecting at the tower No. soon as tower erection completed 202A (ongoing tower erection)

• Use trucks with loads appropriate to roads. A damaged section road in Nghi Thuan Traffic obstruction • Install signs near roads. The contractor should use a suitable Yes commune due to accessories transportation. and damages • Repair segments of roads and other public properties damaged by the material truck for transportation The contractor has paid fund for repair transport.

Semi-Annual Environmental Monitoring Report Page 47 VIE 2225 NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT

Compliant Follow-Up action Environmental Mitigation measures Remarks issues Yes/No Needed

• Make access roads and carry out site restoration for borrowed land. • Manage the construction sites, collect waste and dispose it in designate places. • Propagandize and raise workers’ awareness of social evils. • Conduct health examination for workers periodically. Impacts on • Register for workers’ residences with the authorities. Yes people’ health • Equip workers with personal safety equipment and require them to use it at work. • Provide workers with all medical facilities and medicines. • Keep workers’ camps clean; provide wastebaskets for waste collection. Attachment: (notes, photographs)

Some pecies of papers are not collected at the tower No. 202A Workers wear labour protective equipment during tower erection The access road to the tower No. 209A expanded and (on-going tower erection, bidding lot 6.3, IEC company at the tower No. 202A, bidding lot 6.3, IEC company rehabilitated, bidding lot 6.3, IEC company

Semi-Annual Environmental Monitoring Report Page 48 VIE 2225 NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT

2. Environmental compliance inspection and monitoring form

Project: 2225 – VIE Northern Power Transmission Expansion Sector Project; Implementing Agency: NPPMB Subproject: 220kV Thanh Hoa – Vinh Transmission Line Monitoring Agency: VICA Consultants International Ltd. Location: Do Thanh, Yen Thanh, Nghe An Date: 22/11/2012 Contractor: Viet Á investment commercial industrial group holdings company Reporting Period: 4 th quarter 2012 Implementation phase: Preconstruction/ Construction /Operation 1. Contractor:

Contractor(s) environmental awareness Yes/No Actions Required Contractor response/comment

Does the contractor aware of the mitigation measure should be Yes N/A N/A applied?

Does the contractor have a copy of Environmental Management Yes N/A N/A Plan (EMP)?

2. Mitigation compliance inspection Contractor Endorsed by Mitigations Impact / Mitigation measures Mitigations Impact response/ effective? Action implemented observed/ comment (From EMP) required Implementin Monitoring (Yes/No) (1 to 5)* Location g agency agency

• Dust and exhaust fumes Cover the trucks in charge of material transport to prevent falls. N/A Water the transport roads and construction sites in dry weather. The machines should possess appropriate certificates

• Noise and vibration The construction work should be performed on day, not N/A at night or in resting hours.

Semi-Annual Environmental Monitoring Report Page 49 VIE 2225 NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT

Contractor Endorsed by Mitigations Impact / Mitigation measures Mitigations Impact response/ effective? Action implemented observed/ comment (From EMP) required Implementin Monitoring (Yes/No) (1 to 5)* Location g agency agency

• Construction waste water Arrange waste water collection ditches around the foundation pit and retention pit to reduce turbidity before discharge to local canals. N/A Avoid spillage oil at the construction site Cover and protect construction material

• Soil pollution, soil erosion Conduct the construction work properly to ensure the construction progress. Backfilling at The excavated soil should be used for backfilling the the towers No. foundations. Yes Observation at Agreed Agreed Agreed 3 98A, 99A to be Grow grass, build stone embankment around the site safety foundations on large slopes or places with weak geology. The restoration work should be conducted for all borrowed areas

• Solid waste The excavated soil should be used for backfilling the Observation at Yes 2 N/A Agreed Agreed Agreed excavations. the site Collect all superabundant material

• Traffic obstruction and damages Ensure the traffic safety Use trucks with loads appropriate to roads. during erection Yes 2 Agreed Agreed Agreed Observation at of towers; Install signs near roads. the site Repair the roads damaged Semi-Annual Environmental Monitoring Report Page 50 VIE 2225 NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT

Contractor Endorsed by Mitigations Impact / Mitigation measures Mitigations Impact response/ effective? Action implemented observed/ comment (From EMP) required Implementin Monitoring (Yes/No) (1 to 5)* Location g agency agency

Repair segments of roads and other public properties damaged by the material transport. Make access roads and carry out site restoration for borrowed land • Impacts on people’ health

Manage the construction sites, collect waste and dispose it in designate place. Propagandize and raise workers’ awareness of social evils.

Conduct health examination for workers periodically. N/A Agreed Agreed Agreed Control board, Register for workers’ residences with the authorities. Yes 2 Camps Equip workers with personal safety equipment and require them to use it at work. Provide workers with all medical facilities and medicines. Keep workers’ camps clean; provide wastebaskets for waste collection Mitigation effective rating criteria (indicative examples)

1 Very good (all required mitigation implemented 2 Good (the majority of required mitigation implemented 3 Fair (some mitigations implemented 4 Poor (few mitigations implemented)/ Very poor (very few mitigations implemented) 5 Very poor (few mitigations implemented)

Semi-Annual Environmental Monitoring Report Page 51 VIE 2225 NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT

3. Environmental incidents during reporting period (if relevant) Endorsed by Environmental incidents (accidents, Date/ Reported Description/ Action taken Further action required spills, complaint) Location by Location Implementing Monitoring agency agency

N/A

4. Summary of Actions required and follow-up (if relevant) Follow-up Action required Timeframe Responsible parties (to be completed if inspection/ monitoring indicates actions

are required)

Backfilling at the towers No. 98A and 99A to be safety Next month Contractor Action required: Environmental compliance inspection To be safety during tower erection, rehabilitating the temporary land, to ensure in the next monitoring traffic safety during erection

Provision of awareness signs and barriers at construction sites Next month Contractor Effective: Yes

Inspection completed by: VICA Consultants International Ltd. Date: 22/11/2012 Signature: Le Thi Dinh/Nguyen Thi Thu Trang

Semi-Annual Environmental Monitoring Report Page 52 VIE 2225 NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT

Annex No.7. Environmental Monitoring Template for 500kVSon La- Hiep Hoa T/L 1.Environmental monitoring checklist

Project: Northern power transmission expansion project, Loan L2225 – VIE Project owner : NPPMB

Subproject : 500kV Son La – Hiep Hoa transmission line Monitoring unit : VICA Consultants Ltd.

Location : Trung Thanh commune, Pho Yen district, Thai Nguyen province

Date : December 12-13, 2012 Operation unit: Northwest transmission line- Power Transmission Company 1

Report No. : 4 th Quarter of 2012 Phase: Preparation / Construction / Operation

1. Operation unit:

Environmental awareness of operation unit Yes/No Requested activities Comments from operation unit

Does the operation unit aware of the mitigation measure should be applied? Yes N/A N/A

Does the operation unit have a copy of Environmental Management Plan Yes N/A N/A (EMP)?

2. Monitor the compliance of mitigation measures Implement Comments Confirmed by Impact / Mitigation measures mitigation Effectiveness Observed impacts/ from Requested action (In accordance with EMP) measure from 1 to 5* Location operation Operation Monitoring (Yes/No) unit unit unit

••• Fire, explosion, electric shock Maintain the ROW to NPPMB - Ensure safety distance of ROW follow regulations ROW among towers be safety, prevent and should hand Yes 2 Agreed Agreed No. VT85-VT90 response timely over all - Install protection relay on the line to break the circuit automatically incidents ROWs under when accident happen. transmission

Semi-Annual Environmental Monitoring Report Page 53 VIE 2225 NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT

Implement Comments Confirmed by Impact / Mitigation measures mitigation Effectiveness Observed impacts/ from Requested action (In accordance with EMP) measure from 1 to 5* Location operation Operation Monitoring (Yes/No) unit unit unit

- Monitor forest fire due to electric explosion lines to operation unit

••• Aviation accident The tower No. 273 Yes 1 N/A N/A Agreed Agreed - Tower higher than 70m will be painted in color and install signal crossing by Lo river lights

••• High voltage tower collapse

- Calculate geological characters in design and construct tower foundation pit. Discover rapidly the Yes 2 Tower No. VT85-VT90 landslide to response Agreed Agreed Agreed - Install lightning protection system. promptly - Prohibit fishing activities on the bank and river at the over river section.

••• Impact on people’s health of electrical field intensity The resident are not permitted to encroach Not allow to construct house, office, restaurant… in the ROW. EMF measured and ROW under Yes 2 Agreed Agreed Agreed - Measure electrical field intensity at some location closed to the saved by operation units transmission line ROW periodically Regularly measure EMF as regulated

••• Impact on local ecology ROW clearance as Yes 2 Check ROW require using simple Agreed Agreed Agreed - Tree clearance to ensure ROW safety follow regulations in Decree method, pesticide is

Semi-Annual Environmental Monitoring Report Page 54 VIE 2225 NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT

Implement Comments Confirmed by Impact / Mitigation measures mitigation Effectiveness Observed impacts/ from Requested action (In accordance with EMP) measure from 1 to 5* Location operation Operation Monitoring (Yes/No) unit unit unit

No.106/2005/ND-CP, no tree clearance outside of ROW not permitted to apply

••• Safety operation of the transmission line - Install safety sign at all the towers Check on field and Yes 1 provide labor protective N/A N/A Agreed Agreed - Install lightning protection system equipment as required - Equip protection gear for operation workers

Indicator for mitigation measure effectiveness (for reference) 1 Very good (implemented all mitigation measures) 2 Good (implemented nearly all mitigation measures) 3 Medium (implemented some mitigation measures) 4 Poor (Implement few of mitigation measures) 5 Very poor (nearly no mitigation measures has been implemented)

3. Environmental risk (if any)

Confirmed by: Environmental risk Reported Description / Date / Location Performed action Other requested action (accident, spillage, complain) by: Location Implement Monitoring ation unit unit

Revetment slide VT90, VT119, Northwest Mai Son, Muong Cover nylon to prevent continuously Promptly response the incidents Agreed Agreed VT122, VT124, transmission La districts landslide by suitable technical VT126, VT129… line Fix pits to slide the tower

Semi-Annual Environmental Monitoring Report Page 55 VIE 2225 NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT

Dredge sewerage to drain the water

4. Generalize all requested action and the next action (if any)

Requested action Time frame Responsible Next action organization (Requested action by the monitoring/supervise team)

Discover the incident as soon as possible Coming phase Operation unit Reponses timely incidents

Monitoring completed by : VICA Consultants Date: 14/12/2012 Signed: Le Thi Dinh/Nguyen Thi Thu Trang

Attached: (notes, photos)

Revetment slide at the tower No. 90, Mai Sơn, Son La Trees in the ROW among towers No. VT8587 have not Mechete for ROW clearance cleared yet due to compensation uncompleted

Semi-Annual Environmental Monitoring Report Page 56 VIE 2225 NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT

Annex No.8. Environmental Monitoring Template for 500kV Hiep Hoa Substation 1.Environmental monitoring checklist Project: Northern power transmission expansion project, Loan L2225 – VIE Subproject: Hiep Hoa 500kV substation Monitoring company: VICA Consultants Ltd. Operation unit: Power Transmission No.1 Company Monitoring time: Morning Weather condition: Sunny, breeze; Date: 14/12/2012 Location: Dai Thanh commune, Hiep Hoa, Bac Giang

Implement Next action Environmental issues listed Mitigation measures Noted in EMP Yes/No Necessary

Install danger signs at the area with high risk of high voltage electricity; Impact on community health Regularly checking electric equipment to replace the damage one if any and safety due to high voltage Yes N/A electricity, electrical field Periodically measure electrical field intensity to ensure it is lower than permitted level intensity

Set up operation and maintenance schedule to identify potential risk and oil spillage; checking oil Fire explosion and oil, level in the pit; dangerous chemical spillage In designing phase, the height of the substation must be consider to avoid overwhelming rainwater Yes N/A risk in the oil pit during rainy season; Do not use cooling oil with PCBs and other harmful substances. Checking, maintain and repair substation equipment regularly; Noise caused by substation Yes N/A operation Plant tree around the substation to mitigate and minimize noise All kind of waste must be collected and have a suitable treatment; Domestic waste and waste Set up a waste management system monitoring schedule to ensure all kind of waste will be Yes N/A water of operation worker collected and treated follow current regulations.

Semi-Annual Environmental Monitoring Report Page 57 VIE 2225 NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT

Implement Next action Environmental issues listed Mitigation measures Noted in EMP Yes/No Necessary

Checking equipment regularly to identify and treat in time any oil spillage accident Strictly follow fire prevention regulations; Training and practice fire fighting activities; Fire, explosion, electric shock Fire fighting equipments and workers must follow current regulations of the Government Yes N/A During operation process, relay on the line will break the circuit automatically when accident happens. ROW must follow the technical regulations in Decree106 of the Government, thus, fire due to transmission line explosion will not happen

Lightning protection system has been connected to the ground wire system surrounding substation Wire break or lightning in accordance with current regulations. Checking regularly to prevent accident Yes N/A protection system accident

Attached: Some photos at 500kV Hiep Hoa substation area

Underground oil ponds at Hiep Hoa Bar screen before manhole of drainage Warning signs at the transformer area Firefighting system around the substation 500kV Substation system inside Hiep Hoa 500kV Substation

Semi-Annual Environmental Monitoring Report Page 58 VIE 2225 NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT

2. Environmental compliance monitoring sample

Project: Northern power transmission expansion project, Loan L2225 – VIE Operation unit: Power Transmission No.1 Company Subproject : 500kV Hiep Hoa substation Monitoring company : VICA Consultants Ltd. Location : Dai Thanh commune, Hiep Hoa, Bac Giang. Date: 14/12/2012 Report: 2 nd Quarter of 2012 Phase: Preparation/Construction/Operation 1.Contractor:

Environmental awareness of the contractor Yes/No Requested activities Comments from contractor

Does the contractor aware of the mitigation measure should be Yes N/A N/A applied? Does the contractor have a copy of Environmental Management Yes N/A N/A Plan (EMP)?

2.Monitor the compliance of mitigation measures

Implement Effectiven Confirmed by Observed Comments Impact / Mitigation measure mitigation ess Requested impacts/ from measure action (In accordance with EMP) from 1 to Location contractor Implement. Monitorin (Yes/No) 5* Unit g unit

* Impact on community health and safety due to high voltage electricity and electrical field intensity Continue Install danger signs at the area with high risk of high voltage electricity; perform Yes 1 Substation Agreed Agreed Agreed Regularly checking electric equipments to replace the damaged one if any safety - Periodically measure electrical field intensity to ensure it is lower than permitted activities level * Fire explosion and oil, dangerous chemical spillage risk Set up operation and maintenance schedule to identify potential risk and oil Continue spillage; checking oil level in the pit; perform Yes 1 Substation Agreed Agreed Agreed In designing phase, the height of the substation must be consider to avoid safety overwhelming rainwater in the oil pit during rainy season; activities Do not use cooling oil with PCBs and other harmful substances.

Semi-Annual Environmental Monitoring Report Page 59 VIE 2225 NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT

* Noise caused by substation operation Continue Checking, maintain and repair substation equipment regularly; perform 1 Substation Agreed Agreed Agreed Plant tree around the substation to mitigate and minimize noise Yes safety activities

* Domestic waste and waste water of operation worker Continue All kind of waste must be collected and have a suitable treatment; perform Yes 1 Substation Agreed Agreed Agreed Set up a waste management system monitoring schedule to ensure all kind of safety waste will be collected and treated follow current regulations activities

* Fire, explosion, electric shock

Checking equipment regularly to identify and treat in time any oil spillage accident Continue Strictly follow fire prevention regulations; perform Training and practice fire fighting activities; Yes 1 Substation safety Fire fighting equipments and workers must follow current regulations of the activities Agreed Agreed Agreed Government During operation process, relay on the line will break the circuit automatically when accident happens. ROW must follow the technical regulations in Decree106 of the Government, thus, fire due to transmission line explosion will not happen

* Wire break or lightning protection system accident Continue Lightning protection system has been connected to the ground wire system perform Yes 1 Substation Agreed Agreed Agreed surrounding substation in accordance with current regulations. Checking regularly safety to prevent accident activities

Indicator for mitigation measure effectiveness (for reference) 1 Very good (implemented all mitigation measures) 2 Good (implemented nearly all mitigation measures) 3 Medium (implemented some mitigation measures) 4 Poor (Implement few of mitigation measures) 5 Very poor (nearly no mitigation measures has been implemented)

Semi-Annual Environmental Monitoring Report Page 60 VIE 2225 NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT

3.Environmental risk (if any)

Confirmed by: Environmental risk Date / Reported Description / Performed action Other requested action (accident, spillage, complain) Location by: Location Implementation Monitoring unit unit N/A

4. Generalize all requested action and the next action (if any) Responsible Next action Requested action Time frame organization (Requested action by the monitoring/supervise team)

N/A

Monitoring completed by : VICA Consultants Date: Signed: Nguyen Thi Thu Trang/Le Thi Dinh

Fire extinguisher has been wellequipped Trash bin at the control house Irrigation canal closed to the substation has been dredged.

Semi-Annual Environmental Monitoring Report Page 61