Initial Environmental Examination

April 2011

VIE: Transport Connections in Northern Mountainous Provinces Project (Ha Giang Province)

Prepared by the People’s Committee of Ha Giang Province for the Asian Development Bank

ABBREVIATIONS

ADB – Asian Development Bank BOD – biological oxygen demand DARD – Department of Agriculture and Rural Development DCI – Department of Culture and Information DDC – detailed design consultants DMP – Drainage Management Plan DO – dissolved oxygen DONRE – Department of Natural Resources and Environment EA – executing agency ECP – erosion control plan EIA – environmental impact assessment EMP – environmental management plan ESO – environment and safety officer FPD – Provincial Forest Protection Department GRC – grievance redress committee GOV – Government of Viet Nam HIV-AIDS – human immunodeficiency virus-acquired immune deficiency syndrome IEE – initial environmental examination JCC – joint coordination committee for Transport Connections in Northern Mountainous Provinces Project: project implementation stage MARD – Ministry of Agriculture and Rural Development MMP – materials management plan MONRE – Ministry of Natural Resources and Environment MOT – Ministry of Transport NDCP – noise and dust control plan NGO – non-governmental organization NPOSF – Nui Pia Oac Special Use Forest PCC – project coordinating consultant PDOT – Provincial Department of Transport PPMU – provincial project management unit PPC – Provincial Peoples’ Committee PPE – personal protective equipment PSC – project supervision consultant REA – rapid environmental assessment ROW – right-of-way RP – resettlement plan RRP – Report and Recommendation of the President SC – steering committee for Transport Connections in Northern Mountainous Provinces Project: loan processing stage SEMP – specific environmental management plans SPS – ADB’s Safeguard Policy Statement (2009) SR – sensitive receiver TA – technical assistance TCNMP – Transport Connections in Northern Mountainous Provinces TCVN and – national technical standards of Viet Nam QCVN TOR – terms of reference TRP – tree-cutting and replanting plan TSS – total suspended solids

TSP – total suspended particulates TTMP – temporary transport management plan UIRP – utilities and irrigation reprovisioning plan UXO – unexploded ordnance WMSDP – waste management and spoil disposal plan WPSP – workers and public safety plan

WEIGHTS AND MEASURES dB(A) – decibel (A-weighted) ha – hectare km – kilometer km/h – kilometer per hour m – meter m2 – square meter m3 – cubic meter masl – meter above sea level mg/l – milligram per liter mg/m3 – milligram per cubic meter MPN/100ml – most probable number per 100 milliliter

This initial environmental examination is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature.

In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

CONTENTS

I. EXECUTIVE SUMMARY ...... 1 A Overview ...... 1 B Policy, Legal And Administrative Framework ...... 1 C Description of the Project ...... 2 D Description of the Environment ...... 2 E Anticipated Environmental Impacts and Mitigation Measures ...... 3 F Information Disclosure, Consultation and Participation ...... 4 G Grievance Redress Mechanism ...... 5 H Environmental Management Plan ...... 5 I Conclusion and Recommendations ...... 6

II. POLICY AND LEGAL FRAMEWORK ...... 9 A Environmental Regulatory Compliance ...... 9

III. DESCRIPTION OF THE PROJECT ...... 11 A Background ...... 11 B Existing Road ...... 11 C Proposed upgrading ...... 12 D Proposed bridge improvements and culverts ...... 13 E Implementation Schedule ...... 13

IV. DESCRIPTION OF ENVIRONMENT ...... 17 A Physical Environment ...... 17 B Biological Environment ...... 21

V. ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES ...... 32 A Design / Pre-Construction Phase ...... 32 B Construction Phase ...... 39 C Operational Phase ...... 56 D Cumulative Environmental Impact Associated with the Project Locations ...... 57

VI. INFORMATION DISCLOSURE, CONSULTATION AND PARTICIPATION ...... 58 A Identification of Stakeholders ...... 58 B Consultation with Stakeholders ...... 58

C Concerns Addressed ...... 59 D Information disclosure and Participation ...... 59

VII. GRIEVANCE REDRESS MECHANISM ...... 60

VIII. ENVIRONMENTAL MANAGEMENT PLAN ...... 61 A Implementation Arrangements ...... 61 B Environmental Mitigation ...... 63 C Environmental Monitoring ...... 96 D Reporting ...... 97 E Capacity Building ...... 100

IX. CONCLUSIONS AND RECOMMENDATIONS ...... 102 FIGURES Figure I.1 Location of Project Roads for TA 7245 VIE Figure I.2 Location of Project Road the Project roads Ha Giang Figure III.1 Proposed road width & typical conditions adjacent to the Project roads Figure III.3 Typical Road Cross Sections Figure IV.1 Protected Areas in Ha Giang Province Figure IV.2 Dong Van Karst Plateau Geopark Figure IV.3 Project road stretch TL176A and Du Gia Nature Reserve

TABLES Table II.1 International Conventions to which Viet Nam is a Party (environmental) Table III.1 Current and proposed widths on Project roads in Ha Giang Province Table III.2 Geometric Design Standard Adopted for roads in Ha Giang Province Table III.3 Estimates of earthworks & structures for Project roads in Ha Giang Table III.4 Assessment of the Bridges and Recommendations Table IV.1 Water quality along Project roads in Ha Giang Province Table IV.2 Air quality and noise along Project roads in Ha Giang Province Table IV.3 Land Use in Ha Giang Province Table IV.4 Du Gia Nature Reserve – Location, management and resources Table V.1 Maximum allowable concentration of pollutants in surface water Table V.2 QCVN/TCVN Standards applicable to the project. Table VI.1 Summary of Main Environmental Concerns from Public Consultation Table VIII.1 Responsibilities for EMP Implementation Table VIII.2 Environmental Mitigation & Environmental Performance Monitoring Plan Table VIII.3 Summary of Estimated Costs for EMP Implementation (4.5 years) Table VIII.4 Environmental Effects Monitoring Plan for Project Roads Table VIII.5 Indicative Terms of Reference for Environmental Management Capacity Building of PMU and PDOT

APPENDICES Appendix A Selected Photographs Appendix B Information Disclosure, Consultation and Participation Appendix C Letter of No Objection from Du Gia Nature Reserve Management Board Appendix D Letter of No Objection from Dong Van Karst Plateau Geopark Management Board Appendix E List of Culverts

I. EXECUTIVE SUMMARY

A Overview 1. The Government of the Socialist Republic of Viet Nam (GOV) has requested the Asian Development Bank (ADB) to provide financing to facilitate investments to support the upgrading of roads proposed in the technical assistance (TA) Transport Connections in Northern Mountainous Provinces Project TA 7245 – VIE (TCNMP). The TCNMP proposes a comprehensive program to upgrade and rehabilitate 12 roads in six northern provinces with a total length of about 304 km in Ha Giang, Yen Bai, Cao Bang, Tuyen Quang, Lao Cai, and Bac Kan (Figure I.1). The executing agencies (EA) are the respective Provincial People’s Committee (PPC) of each province. The implementing agencies (IA) will be six separate provincial project management units (PPMU) that are already established in all provinces except for Yen Bai province, which plans to establish its PPMU within 2011. 2. The Project supports ADB's Viet Nam Country Partnership Strategy 2007 to 2010 and GOV's Socio Economic Development Plan (2006-2020) that identifies a lack of rural infrastructure in the northern mountainous region as a constraint towards effective poverty reduction. In Ha Giang province the Project will cover stretches of two provincial roads in the network. The Project road stretches selected for improvement are along TL176A and TL183. This report is the initial environmental examination (IEE) for the improvement of the relevant section of the Project roads in Ha Giang Province (Figure I.2). This IEE is prepared by the Ha Giang PPC to ensure that the Project road design, construction and operation will comply with the provisions of ADB's Safeguard Policy Statement 2009 (SPS). 3. The proposed road improvement works are within the right of way (ROW) designated for the Project roads but some construction may take place on land yet to be acquired depending on detailed designs. These areas were subject to rapid environmental assessment. Based on ADB’s Safeguard Policy Statement 2009 (SPS), ADB has classified the Project as Category “B” and requires the preparation of an IEE. 4. The objectives and scope of this IEE are to (i) assess the existing environmental conditions along and in the vicinity of the Project roads (ii) identify potential environmental impacts from the proposed road improvement works (iii) evaluate and determine the significance of the impacts; (iv) develop an environmental management plan (EMP) detailing mitigation measures, monitoring activities, reporting requirements, institutional responsibilities and cost estimates to address adverse environmental impacts; and (v) carry-out public consultations to document any issues/concerns that stakeholders may have on the Project and to ensure that such concerns are addressed in the project design and mitigation measures. 5. This IEE is submitted to ADB by the Ha Giang PPC and the final IEE report will be disclosed to the public through the ADB website and to the public in Viet Nam by the PPC and PPMU. The IEE will also be disclosed by the PPC to the Ministry of Natural Resources and Environment (MONRE) and provincial Department of Natural Resources and Environment (DONRE) and to the local authorities in Ha Giang province for review and identification of additional environmental assessment and environmental permits that may be required.

B Policy, Legal And Administrative Framework 6. The Project shall comply with requirements of ADB SPS 2009 and the GOV’s Guidelines on Implementation of Law on Environmental Protection 2006 (under Law on Environmental Protection 2005 as amended by Decree 21-2008). The Ministry of Natural Resources and Environment (MONRE) has delegated powers to DONRE to approve environmental assessments and MONRE will receive a copy of the environmental assessment before construction commences. However certain activities commonly associated with infrastructure projects such as quarry operations, extraction of gravel or discharge of waste water will also require permission from the relevant provincial level Page 1

authorities. PPMU will submit the IEE to DONRE and disclose the scale and scope of the Project to the environmental authorities in due course.

C Description of the Project 7. The rehabilitation and upgrading of TL176A and TL183 will involve some alterations to the roads width by 1 m or less in some places on either side to improve road geometry within the ROW. The ROW is different for each road but it is approximately 3 m from edge of the slope or embankment either side of the road base. This puts the ROW at least 6 m either side of the centerline even for the narrowest parts of the roads. There will be a need for limited resettlement and the resettlement pans will be accomplished by the Provincial Peoples Committee of Ha Giang (PPC) who will also carry out the required social interventions. 8. The lengths of the roads are approximately 29.2 km for TL176A and 34.6 km for TL183 (Figure I.2). The construction of the improvements to TL176A and TL183 should be straightforward but as yet there are no detailed designs for these works. The existing alignments go through several villages. Road TL176A will be upgraded to Vietnamese Standard VI (VN VI) and road TL183 will be upgraded to VN IV. For purposes of the conceptual design it is assumed that where slope cutting is necessary the roads will generally be widened on the uphill side creating a requirement to excavate spoil but there are limited opportunities to use this material as fill. Therefore spoil disposal will be significant but other construction impacts should be of a scale typical for a road upgrading project. 9. Bridges on the Project roads will be improved to accommodate vehicles in accordance with Viet Nam Code for Bridge Design (HL 93 and 22TCN -272-05) constructed as permanent concrete and steel structures. There are 2 bridges and 204 culverts that have been considered for improvement or reconstruction. 10. A joint coordination committee (JCC) for the Project will be established to coordinate and monitor the activities of the six PPMUs. The JCC will be chaired by the Vice-chairman of Bac Kan PPC and comprise Vice-chairpersons of the six PPCs. The JCC will retain an international project coordinating consultant (PCC) with environmental capability provided by a suitably qualified international and national environment specialists to assist the PPMUs. The PPMUs will engage national detailed design consultants (DDC), national contractors and national project supervision consultants (PSC) for upgrading and/or reconstruction of the roads. The target date for completion of reconstruction and upgrading is by end 2016.

D Description of the Environment 11. The climate is subtropical and the area is subject to heavy rainfall between April and October. The roads are fairly flat in some places but there are many undulating and steeper sections through the hill terrain. During rainy periods surface water on the road runs to the adjacent fields and canals and in the hills via crossing drainage structures and culverts. The mountainous area of Ha Giang Province provides the catchment for several rivers including Lo, Chay, Nhiem, Sao, Gam, Bac, and Mien. The rivers and their tributaries serve agriculture and domestic water supply. 12. The biological environment is dominated by agriculture. There are also several areas of biodiversity and conservation value in Ha Giang Province. Tay Con Linh, Phong Quang and Bat Dai Son, Phong Quang-Vi Xuyen and Cang-Bac Me are all more than 5 km from any of the roads under consideration. The Project Roads do not cross a National Park or Nature Reserve or Protection Forest and none of the land in the ROW is production forest or protected forest but the buffer zone of Du Gia Nature Reserve is about 2.5 km south and west of the Project Road 176A. The valuable ecological resources in the core areas protected for the natural habitats for rare or endangered species in Du Gia Nature Reserve is much farther than 2.5 km south and west of the stretch of Project road TL176A selected for improvement (Appendix B). The Project Road 176A crosses the Dong Van Karst Plateau Geopark (DVKPG) which is protected

Page 2

for it’s geological resources and scenic landscape created by the extensive area of karst mountain formations. 13. The local provincial environmental authorities have not identified any issue of additional interference with sites protected for their biodiversity for TL176A and TL183. There does not appear to be any direct interference with protected forests or the geological resources due t the small scale nature of the works and because the works will be within the ROW for existing roads TL176A and TL183. The social and human impacts to village life and impacts to social infrastructure will be of short duration and these have also been subject to detailed assessment in the Resettlement Plan. Cattle are kept along on the Project roads and other animals and birds near the roads are typical of those that tolerate disturbance by human settlement. There are a few large trees that will need to be avoided in the detailed designs but if cut, compensatory tree planting will take place. 14. Ha Giang is developing socially and has an improving economy with many home craft enterprises. Traditional shop houses are located at intervals all along TL176A and TL183 and ribbons of residential development are present throughout the settlement areas. The land around the Project roads is used for rice cultivation. Rain-fed rice paddies and cultivation of vegetable and cash crops, in some cases based on shifting cultivation, are more common in the hilly areas. As yet the rivers are not subject to heavy industrial pollution and there are institutional arrangements to control pollution in future. 15. There are no sites of cultural significance found close to TL176A and TL183. There are schools, hospitals and some places of worship within sight of the Project roads in some nearby villages. All will be set back from where the road works are currently planned to take place and no significant impacts are anticipated.

E Anticipated Environmental Impacts and Mitigation Measures 16. The potential environmental impacts will require mitigation measures to minimize the impacts in the design, construction and operational phases. The main issues relate to planning design of road structures and drainage and control construction impacts such as spoil and waste disposal, traffic interruption, noise and dust during construction. The buffer distance between the works on the Project roads and the nearest residential sensitive receivers is ample in most cases. should only be moderate disturbance to the surrounding areas from the works provided the EMP is implemented fully. 17. Starting at the detailed design stage and throughout construction the PPMU will retain a suitably qualified environmental and safety officer (ESO) and with the assistance of the PCC will ensure proper implementation of the EMP prepared for the project. PPMU with the assistance of the PCC will: (i) disclose the final Project road design to DONRE and ADB; (ii) check that the Project site works boundaries correspond with those disclosed in this IEE; (iii) prepare tender documents to include the EMP to ensure the contractors comply with environmental requirements; (iv) ensure environmentally responsible procurement and the acceptability of sufficient borrow sites for rock based materials agreed with DONRE; (v) plan spoil and waste disposal (vi) plan to preserve and avoid road side trees and compensate for trees that will be removed; (vii) confirm hydrological and drainage impacts of the Project and ensure detailed bridge designs take account of a 100 year return rain storm event; (viii) plan to minimize disturbance of vehicular traffic and pedestrians during construction (viii) take baseline water quality, air and noise samples before construction commences; and (ix) assist the contractors to orient workers on EMP provisions as well as health and safety aspects. The PPMU will also make a reassurance check with the responsible authority that there is no potential threat from unexploded ordnance (UXO) before works commence. 18. Construction impacts will mainly be from works to reconstruct the road base, repairing bridges, renewing culverts across streams, providing better crossing drains in embankments and repairing road embankment base courses, and surfacing works. The location for construction works will be well away from most of the nearest residential

Page 3

sensitive receivers (SRs) that are outside the ROW and in principle this should allow ample buffer distance to attenuate many potential nuisances. 19. The PCC shall prepare specific EMPs (SEMPs) during detailed design phase. These SEMPS will include (i) waste management and spoil disposal; (ii) temporary drainage; (iii) temporary traffic management; (iv) materials management; (v) erosion control; (vi) noise and dust control; (vii) utilities and irrigation reprovisioning; and (vi) workers and public safety. Contractors will be required to commit to implementing the Project EMP and the SEMPs. The SEMPs will be based on the EMP matrix presented in this IEE (Table VIII.2). PCC with conduct workers’ orientation on implementation of construction mitigation measures in the Project EMP and SEMPs and shall monitor the implementation of EMP provisions. Unsuitable soils, spoil and construction waste will be disposed of to sites approved by DONRE as agreed with local authorities and disposal will be monitored. Wastes will not be burned. The acceptability of the borrow and quarry sites for fill materials will be agreed with DONRE and corresponding required environmental permit or clearance will be obtained by the contractors prior to operation of such sites. Building materials will be obtained from sites approved by DONRE using local sources as practicable to minimize transportation and stockpiling of building materials. Work that will result to emission of high noise levels will not be undertaken at night in the vicinity of sensitive receptors. A qualified environment and safety officer will be identified by the Contractors before construction commences. Facilities for workers and public safety, construction site offices and worker camps will be regulated in line with the labor codes of Viet Nam. Complaints will be monitored and investigated and additional mitigation measures will be implemented, as necessary. The EMP will be updated by PCC if unexpected impacts occur. 20. The Project road stretches pass through agricultural areas and villages and small towns. The TL176A runs through the Dong Van Karst Plateau Geopark protected for its landscape and geological resources. The PPMU will co-operate with the Geopark’s management board to introduce mitigation measures during construction phase to avoid or minimize impacts to this protected area. The landscape and forests will be protected and mitigation measures have been included in the EMP to prevent further conversion or degradation of biodiversity and to provide enhancement where practicable. 21. Due to the distance to the nearest nature reserve and the small scale nature of the proposed road works, there are no measurable adverse impacts on critical or natural habitats that can be foreseen which could impair the biodiversity value or function of nature reserves or protected forest areas. The improvements to the Project road stretches are not anticipated to lead to a reduction in the population of any recognized endangered or critically endangered species and there will be no loss of valuable habitats that could compromise the host ecosystem. 22. The operation of the improved Project roads should have little effect on the surrounding environment and the introduction of the wider pavement can be expected to reduce air pollution from disturbed dust and noise from vehicles on the smoother roads. The improvement of the Project roads will be within the existing corridor keeping vehicles away from sensitive receivers such as residences, commercial premises and schools that are set back from the Project roads. Gaseous and particulate emissions from the expected traffic flows will be well dispersed road to be affected and there will be insufficient traffic to increase noise above the acceptable standards. The upgrading is likely to increase the vehicle speed but additional future traffic should be moderate and unlikely to create many community safety issues and overall the condition of the road facilities will be enhanced and driving conditions should improve. Routine safety measures, signage and road markings will be introduced to reduce driving risk further and will be verified at detailed design stage.

F Information Disclosure, Consultation and Participation 23. The stakeholder consultation process has disseminated information in advance on the upgrading works and the expected impacts and the proposed mitigation measures.

Page 4

The process also gathered information on relevant concerns of the community so as to address these in the project implementation stages. 24. The results indicated there was very strong support for the Project and the main environmental concerns were interference with connection to water and power supplies, construction noise and dust. Other responses are mainly concerns on prompt compensation for land acquisition and a wish for further consultation between the local people and the Project authorities as well as concern that compensation for land to be acquired by PPC should be fair. The environmental concerns raised by the stakeholders shall be controlled and minimized by thorough implementation of the EMP.

G Grievance Redress Mechanism 25. Existing arrangements for redress of grievances are through complaints to the committees up to the District level and then through the PPC and back to PPMU. 26. Through a Grievance Redress Committee (GRC), PPMU shall promptly address affected people’s concerns, complaints, and grievances about the Project’s environmental performance at no costs to the complainant and without retribution. The GRC, which shall be established by PPMU before commencement of site works, shall be chaired by PPMU and shall have members from the contractors, ward and district committees, DONRE, local NGO, and women’s organization. Grievances can be filed in writing or verbally with any member of the GRC. The committee will have 15 days to respond with a resolution. If unsatisfied with the decision, the existence of the GRC shall not impede the complainant’s access to the Government’s judicial or administrative remedies. 27. The PPC through the PPMU shall make public the existence of this grievance redress mechanism through public awareness campaigns. PPMU shall also provide telephone numbers for complaints and these shall be publicized through the media and numbers placed on the notice boards outside the site and suggestion/complaints boxes will be placed outside the construction camps and yards. Locally affected people will still be able to express grievances through the ward or district committees and these would be referred to PPMU through the usual channels in those committees.

H Environmental Management Plan 28. The institutional requirements and responsibilities for various stakeholders including the EA, JCC, PCC, PPMU, DDC, PSC and contractors have been identified. The Project EMP as well as the SEMPs will be used as a basis for an environmental compliance program. The EMP was compiled by close reference to best practices and in line with SPS. A suite of mitigation measures has been proposed and the IEE concludes that the impacts will be manageable if the mitigation measures spelled out in the EMP are implemented thoroughly. Any conditions of the environmental clearance from DONRE and any subsequent licenses and approvals from local authorities will also be included in the environmental requirements for the Contractors in the compliance program. The requirements of the IEE, Project EMP and SEMPs will be included in the contracts. The effective implementation of the design and construction stage mitigation in the EMP shall be audited by PPMU, PCC and ADB as part of the loan conditions. The main monitoring of the contractor’s environmental performance on implementation of the SEMPs and various provisions of the Project EMP will be done by PPMU assisted by the PCC. If this is done effectively the impacts can be controlled well within acceptable limits. 29. PPMU with assistance from PCC shall: (i) update the EMP during detailed design phase should there be additional environmental impacts not identified in this IEE and for which appropriate mitigation measures have not been included in the EMP; (ii) prepare a new or supplementary environmental assessment report in compliance with SPS if there are any additional components or changes in the Project such as specific location/alignment, among others, that will result to adverse environmental impacts and are not within the scope of the environmental assessment report approved by ADB. The

Page 5

above documents shall be submitted by PPMU to ADB for review and clearance prior to implementation.

I Conclusion and Recommendations 30. The Project construction is restricted to areas within the ROW as far as can be ascertained at this stage. This IEE study was carried out when the Project roads upgrading work was at the conceptual stage of design during the TA 7245 REG. Secondary data and preliminary observations and ambient environmental baseline surveys were used to assess the scale of environmental impacts and public consultation and site reconnaissance were carried out in order complete the environmental assessments in a comprehensive manner and recommend suitable mitigation measures. The impacts from construction and operation will be manageable and no insurmountable impacts are predicted, provided that the EMP is included in the contract documents, and the EMP provisions are implemented and monitored to the fullest extent. In the event that any design details change the locations or scope of the proposed works the environmental assessment and EMP shall be reviewed and revised accordingly. PPMU shall ensure that the EMP is included in the contract documents.

Page 6

Figure I.1: Location of Project Roads for TA 7245 VIE

Page 7

Figure I.2: Location of Roads the Project roads in Ha Giang Province

Page 8

II. POLICY AND LEGAL FRAMEWORK

A Environmental Regulatory Compliance 31. The environmental regulations of GOV for environmental assessment rules are set out in the Guidelines on Implementation of Law on Environmental Protection 20061 (under Law on Environmental Protection 2005 as amended by Decree 21-20082) that requires environmental assessment (in the form of an EIA) for listed projects. MONRE has delegated powers to DONRE to approve the environmental assessment for provincial projects and MONRE will receive a copy of the environmental assessment before construction commences. In this case the environmental assessment will be the IEE prepared for ADB. Therefore PPMU will submit the IEE to DONRE Provincial Environmental Protection Service in the province to disclose the scale and scope of the projects to the environmental authorities in due course and as required under SPS. In Viet Nam the environmental assessment process is established and the rules, regulations, procedure and processes for environmental impact assessment of development activities have been reviewed under decree 80/2006 ND-CP. The rules and guidelines on environmental management have been amended under decree 21/2008 ND-CP (February 2008). The main decrees and statutory instruments of relevance to this IEE are: i) Decree 21-2008-ND-CP of the Government of the Socialist Republic of Viet Nam. on Amendment of and addition to a number of articles of Decree 80-2006-ND-CP dated 28 Feb 2008 providing detailed regulations for implementation of the Law on Protection of the Environment. ii) Decree 80-2006-ND-CP of the Government of the Socialist Republic of Viet Nam. of the Government dated 9 Aug 2006 providing detailed regulations and guidelines for implementation of some articles on the Law on Environmental Protection. iii) Viet Nam Environmental Protection Law, amended in 2005, approved by the National Assembly on 12/12/2005, validity from 01/07/2006. iv) Governmental Decree No. 81/2006/ND/CP dated 09/08/2006 of the Government On instruction for fines for breach of Environmental Protection Law’s implementation. v) Circular No. 08/2006/TT-BTNMT dated 08/09/2006 of the Ministry of Natural Resources and Environment providing instruction of environmental strategic assessment, environmental impact assessment, and environmental protection commitment. vi) Viet Nam standards on environment protection (TCVN and QCVN) from 1995 to 2010. vii) Government Decree N0.121/2004/ND-CP dated 12/05/2004 providing the regulations on settlement of violations on environmental protection (in replacement of the Decree No 26/CP dated 26/04/1996). 32. Pollution standards prescribed for the protection of the environment are described in the Law on Environmental Protection (and the TCVN and QCVN standards as amended).

1 Guidelines on Implementaion of Law on Environmental Protection 2006 – 80/2006/ND-CP require EIA for new construction of Grade IV roads and for upgrading of roads from Class I to III. Upgrading of roads that are Class IV or V to Class III is not specifically mentioned. The EIA has similar scope and content to IEE for ADB. 2 Decree 21-2008 28 February 2008 - Amendment of and addition to a number of articles of Decree 80-2006- ND-CP of the government dated 9 August 2006 providing detailed regulations for implementation of the Law on Protection of the Environment.

Page 9

The following standards will be referred to for ambient environmental monitoring of the Project: QCVN 08:2008/BTNMT (surface water quality), QCVN 05:2009/BTNMT (air quality), and TCVN 5949:1998 (noise). Certain project activities commonly associated with road improvement such as quarry operations, extraction of gravel or discharge of waste water also require licenses that are issued at the provincial level by DONRE and Provincial Peoples Committee offices (PPC) depending on the duration and scale of those activities. PPC offices are the authorities to decide on the permit requirements at the provincial level. 33. In Viet Nam the environmental assessment process is established but the rules, regulations, procedure and processes for environmental impact assessment of development activities have recently been reviewed under decree 80/2006 ND-CP. The rules and guidelines on environmental management have been amended under decree 21/2008 ND-CP (February 2008). 34. PPMU/PCC will review the IEE at the detailed design stage in the light of future developments and forward required revisions of documents to DONRE and ADB. The EMP will be updated by the PCC at the detailed design stage should there be additional environmental impacts not identified in this IEE and for which appropriate mitigation measures have not been included in the EMPInternational Conventons 35. Viet Nam is a party to several international conventions that are relevant to environmental management (Table II.1). None of the conventions has any direct or specific relevance for this IEE as the Project does not encounter any areas of environmental sensitivity covered by the conventions. Table II.1: International Conventions to which Viet Nam is a Party (environmental). Convention Title Convention date Viet Nam participation Convention on Wetlands of International Importance 1971 [20 September 1988] Especially as Waterfowl Habitat (RAMSAR) Protocol to Amend the Convention on Wetlands of 1982 International Importance Especially as Waterfowl Habitat, Paris. Convention Concerning the Protection of the World 1972 [19 October 1987] Cultural and Natural Heritage Convention on International Trade in Endangered Species 1973 [20 January 1994] Wild Fauna and Flora UN Environmental Modification Convention (ENMOD) 1977 [26 August 1980] FAO International Code of Conduct on the Distribution and Use of Pesticides Montreal Protocol on Substances that Deplete the Ozone 1987 [26 January 1994] Layer London Amendment to the Montreal Protocol on 1990 Substances that Deplete the Ozone Layer, London. Copenhagen Amendment to the Montreal Protocol on 1992 Substances that Deplete the Ozone Layer, Copenhagen. Basel Convention on the Control of Transboundary 1995 [13 March 1995] Movements of Hazardous Wastes and their Disposal United Nations Framework Convention on Climate Change 1992 [16 November 1994] Convention on Biological Diversity 1992 [16 November 1994]

Page 10

III. DESCRIPTION OF THE PROJECT

A Background 36. The existing road infrastructure needs to be improved because the standards and conditions of many of the roads in Viet Nam are inadequate to meet rapidly growing demand for efficient travel. This situation limits national development and economic growth. 37. The existing conditions of the Project roads vary and are good in some places but only fair to poor in some places. The road is sealed in some sections and earthen shoulders are often in poor condition. Some of the bridges are in poor condition and have wide holes in places which are repaired improperly from time to time. The culverts are in fair condition but some require major upgrading and repair. 38. The JCC will engage a project coordinating consultant (PCC) who will assist the JCC and the PPMUs to manage detailed design and supervision of construction. Procurement at the provincial level will be using project detailed design consultant engineers (DDC) who will be responsible for detailed design. It is assumed that the PPMU will undertake the project construction supervision (possibly assisted by construction supervision consultants). Reconstruction and upgrading will be completed by end 2013. The PPMU in Ha Giang Province (PPMU) will engage the DDC and for purposes of this IEE it is assumed that there will be a conventional NCB bidding to secure contractors for upgrading and/or reconstruction of the road. Detailed design, bidding, securing contractors and upgrading works are proposed to take place over a two year period between 2011 and 2013.

B Existing Road 39. The sections of the existing roads due for upgrading connect several parts of Ha Giang Province. The current widths and proposed widening are summarized in Table III.1. At it’s northern end TL176A connects from the junction of National Highway 4C and runs 33.8 km southwards to Coc Pang at the northern edge of the Du Gia Nature Reserve. Road TL183 connects from the junction of National Highway 2 and runs more than 50 km towards Bang Lang (This road runs on to join with provincial road 279). The major portion of the traffic on these roads consists of motor bikes (more than 80%) with a few cars, trucks and public motor vehicles. Some trucks carrying people as well as goods in and out of the area. Traffic flows counted in September 2009 resulted in 436 (on TL176A) and 734 (on TL183) vehicles per day3.

Table III.1 : Current and proposed widths on Project roads in Ha Giang Province Current Current Proposed Proposed Widening Road Start Finish Length formation Pavement pavement formation Class required Name (Km) (Km) (km) width (m) width (m) width (m) width (m) (m)@ TL176A (PR) 0.000 10.550 10.55 5.0 3 3.5 6.0 VI 1.0 10.550 11.570 1.02 12.0 8 3.5 6.0 VI NIL 11.570 24.250 12.68 5.0 3 3.5 6.0 VI 1.0 24.250 29.200 4.95 6.0 3 3.5 6.0 VI Nil TL183 (PR) 0.000 34.600 34.6 6.5 3.2 5.5 7.5 IV 1.0 Source: Consultants TA 7245 Topographical Survey Report Dec 2009 @ = Based on formation width.

3 TA 6478 Final Report June 2010.

Page 11

40. The existing alignments pass by many villages and isolated settlements. The roads are fairly flat in many places and then undulating with some steeper sections through the hilly terrain.

C Proposed upgrading 41. The Project roads TL176A and TL183 require rehabilitation and upgrading to Class VI and IV respectively. This will involve some alterations to the width by 1 m in some places to improve road geometry. The ROW for these roads is defined as 3 m from the toe of the embankment slope (below) or 3 m from the top of the cut slope (above) the road. In most places therefore the existing ROW either side of the centerline, is ample for the proposed rehabilitation works (Figure III.1 and Appendix 1). The works for TL176A and TL183 will therefore take place within the existing road corridor and no significant impacts are expected outside the road corridor. However to get a better road geometry some resettlement and minor land acquisition may be involved in some locations, subject to detailed design. The proposed geometric design standard and widening is shown in Table III.2. Figure III.2 shows typical cross sections for the proposed road standards. Table III.2 : Geometric Design Standard Adopted for Ha Giang Road TL176A TL183 Length of Road 33.8 Km 50.2 Km Dong Thanh - Bac Quang Start Point (name / locale) Du Gia commune – Yen Minh District District Yen Binh commune - Quang Binh Finish Point (name / locale) Mau Due commune – Yen Minh District District Proposed standard# VN VI VN IV Parameter unit Current Formation Width m 5 – 8 6.5 – 9 (approx. by observation) # Proposed additional width m 0 – 1 0 - 1 Design speed km/h 20 40 Number of lanes no. 1 2 Formation width m 6 7.5 Traffic lane width m 3.50 5.50 Maximum longitudinal gradient % 11 9 Minimum horizontal curvature m 15 60 Minimum radii of vertical curves: crest m 200 1000 Minimum radii of vertical curves: sag m 100 450 Pavement Structure Surface Bituminous treatment Bituminous treatment Source: Ministry of Transport (Vietnamese Standard TCVN 4054) and Consultants., # Final Report TA 7245. 42. The road works will include (i) excavation and reconstruction of the embankment, (ii) reconstruction of one carriageway (3.5 to 5.5 wide) plus hard shoulders; (iii) repair and reconstruction of bridges (iv) ensuring drainage and access near villages and at other key areas is unimpaired by extension of numerous culverts; (v) upgrading road drainage and (vii) installing slope stabilization and bioengineering measures, landscaping and accessories. Compensatory planting will also be required for any trees that are removed although this is not expected to be a major task. There will also be waste disposal issues for the works as there will be a surplus of cut materials in many areas where these materials cannot be reused on the project. Total cut materials are estimated to amount to about 353,258 m3 of which about 30% will be rock cutting. However the rock is grade 3 and grade 4 and can be excavated by powered mechanical equipment and there should be no need for blasting. Some of this material may be used as fill for the embankment to offset the need to extract fresh rock based materials from quarries and borrow pits. This would reduce the requirement for rock based materials for embankments, currently estimated at 161,289 m3 (Table III.3). 43. The works are generally expected to take place within approximately 7 m of the centerline of the alignment subject to detailed design (allowing about 3 m temporary working space either side).

Page 12

Table III.3 : Estimates of earthworks and structure works for Project roads in Ha Giang

Road TL176A TL183 Total Excavation (soil and rock – m3) 147,825 205,433 353,258 Embankment (rock based materials - m3)) 42,144 119,145 161,289 Bridges 0 2 2 Culverts to be replaced or extended 70 134 204 Bitumen (tones) 473 1,795 2,268 Source: TA 7245 Consultants, Final Report TA 7245 VIE.

D Proposed bridge improvements and culverts 44. Improvements are required to 2 bridges and 204 culverts (Table III.3). The types of improvements for the bridges are included in Table III.4. The locations of culverts are indicated in Appendix E. Table III.4 Assessment of the Bridges and Recommendations - Ha Giang Bridge Name Location Length Width Assessment Recommendation 176A 1 Bridge No.1 Km 31+500.31 16 6.5 Good condition Keep unchanged 2 Bridge No.2 Km33+777.67 12 6.5 Good condition Keep unchanged 183 1 Khuoi Lieng (1) Km 2+567.97 43.6 4.5 Good condition Widen (by 2 m) 2 No name Km7+047.73 5.5 6.5 Good condition Keep unchanged 3 No name Km7+612.04 6.0 6.5 Good condition Keep unchanged 4 No name Km9+250.99 4.5 6.5 Good condition Keep unchanged 5 No name Km9+469.32 8.0 6.5 Good condition Keep unchanged 6 No name Km9+724.29 8.0 6.5 Good condition Keep unchanged 7 No name Km10+378.11 5.0 7.8 Good condition Keep unchanged 8 No name Km10+922.25 8.0 6.5 Good condition Keep unchanged 9 No name Km11+273.85 5.0 7.5 Good condition Keep unchanged 10 No name Km12+241.66 6.0 7.5 Good condition Keep unchanged 11 Khuoi Lieng (2) Km12+893.96 75.00 5 Good condition Widen (by 1.5 m) 12 No name Km15+785.39 10.0 6.5 Good condition Keep unchanged 13 No name Km16+945.21 6 6.5 Good condition Keep unchanged 14 No name Km18+790.91 14.5 6.5 Good condition Keep unchanged 15 No name Km23+485.70 22.0 7.5 Good condition Keep unchanged 16 Vang Ma Km24+589.24 65.0 7.0 Good condition Keep unchanged 17 No name Km28+377.20 10.1 6.5 Good condition Keep unchanged 18 No name Km30+296.01 5.0 8.5 Good condition Keep unchanged 19 Tien Yen Km30+835.74 30.0 6.5 Good condition Keep unchanged 20 No name Km31+349.37 4.5 7.5 Good condition Keep unchanged 21 No name Km39+172.68 15.0 6.0 Good condition Keep unchanged 22 No name Km43+791.41 22.0 7.5 Good condition Keep unchanged 23 No name Km46+712.29 18.0 6.5 Good condition Keep unchanged 24 No name Km46+997.92 7.0 6.5 Good condition Keep unchanged

Source: TA7245 Final Report Bridge Engineering. Load as per Bridges Design Standards 22TCN-272-05.

E Implementation Schedule 45. The implementation schedule for the Project has not been worked out in detail by the SC and potential bidding contractors have not yet been identified. However in principle it is intended to start the detailed design phase in 2012 and the Project works in all provinces will commence in 2013 and last until 2016. The likely commencement and duration of the

Page 13

Project works may vary in each province and will depend to a large extent on the duration of the detailed design phase (Appendix D).

Page 14

Figure III.1: Proposed road width and typical conditions adjacent to PR 176A and PR 183

Page 15

Figure III.2: Typical Cross Sections

Page 16

IV. DESCRIPTION OF ENVIRONMENT

A Physical Environment

1. Meteorology and Climate 46. The climate in Ha Giang is subtropical and influenced by the annual south west monsoon. There are two seasons. Dry season starts from November and lasts until March. The rainy season is between April and October. During the dry season no rain may fall for several months and it is cooler. The rainfall varies and the average precipitation is about 1,200-1,800 mm. About 73% to 81% of the rain falls during the period from May to September. The yearly average temperature is about 230C, rising to a maximum of 330C during May and August. Main direction of wind is from the South – East. In winter, wind direction is from the North – East (up to 20 % of the time) bringing cold air from China.

2. Topography, Geology, and Soils 47. The topography of Ha Giang Province is mainly mountainous, with elevations above 500masl typically characterized by steep terrain, narrow river valleys, and low agricultural potential. This mountainous landscape extends across most of the north of the country, except for the plain of Dong Van. Ha Giang is mostly rocky mountains. Together, the alluvial plains and river terraces cover only about 20% of the land area. Large proportion of the mountain area is limestone karst and the rest is for other types of rock including granite. Soils along the rivers’ banks are mixtures of silt clay and stone particulates that have been flushed by run off and precipitated from the water. These soils are poor in organic matter. In paddy terraces, narrow hill valleys soil quality is greatly improved as agricultural cultivation is common. Waterlogged areas with muddy layers and flooded grasses are sometimes seen in small areas. 48. In general the whole province is divided into three parts as follows:  The northern part with high altitude includes many high mountains and narrow valleys formed of limestone and metamorphic rocks.  The western part includes high mountains formed of granite and its weathered products.  The low-mountain that includes low hills and some large plains formed of shale and schist overlain by a yellow soil cover of 0.8 to 2.0 meters. 49. The Project roads are in the biophysically diverse northern mountainous highlands of Viet Nam. The north parts of Viet Nam have encountered major earthquakes and Ha Giang areas have also been subject to moderate seismic activity in the recent past but there is no record of recent volcanic activity in the mountains. The steep mountainous slopes, with their moderately thin layers of soils, are particularly prone to erosion when vegetation is removed and soils are exposed to rainfall and surface water flows. Thus, water quality in the mountain streams and rivers can be rapidly degraded when soils are eroded and flushed in to them, and result increased turbidity that reduces water quality for aquatic life and domestic and livestock consumption. Heavy rainfall is responsible for deteriorated sections of the provincial and rural roads. The Project roads pass through sedimentary limestone material. In between these karst ridges and slopes are recently deposited gravels and silts in narrow river valleys. However soil type should have very little bearing on the implementation of the works.

Page 17

3. Surface and Groundwater 50. The mountainous area of Ha Giang Province provides the catchment for several rivers including Lo, Chay, Nhiem, Sao, Gam, Bac, and Mien. The rivers and their tributaries serve agriculture and domestic water supply. The water flow varies between seasons from 2-10 liters per second (l/s) in the dry season to about 50 to 400 l/s in the rainy season. Water level also varies by 2 to 2.5 meters between seasons. In the dry season it is difficult for people living in mountainous areas to get enough water for their daily requirements. 51. Road TL176A runs at some distance along the valley of the Nam Lang stream, a small branch of Gam river. 52. Road TL183 follows the valley of the Khuoi Luong River from Binh Tong and crosses the river three times at Km2+558, Km12+893 and Km24+589 but is generally at a distance of more than 50m only coming within 25 m at about Km3+850 and Km16+600. After Km34 the road passes over a crest into the valley of the river Ngoi Giang, crossing that river at Km35+580, Km39+172 and Km43+791. Road TL183 also comes within 25 m at of the river at about Km40+100. Road TL183 run alongside the Chung and Con rivers at a distance of several hundred meters for most of the way from Vinh Tuy to Yen Binh. There is an intersection of Chung, Con and Bac rivers at a location about 4km to road TL183. After this intersection, there is an extended branch of Bac river across the road TL183 at Bang Lang village. Other smaller rivers run nearby road TL183 before the confluence with Con and Lo river at Vinh Tuy river intersection. 53. The rivers and streams are an important resource to the people in the project area. River flows are the highest from April to October. Most of the streams and creeks discharge all year round carrying high sediment loads, depositing large quantities of gravels and sands in the lower reaches. During the wet season some of the bridges and culverts are regularly inundated, cutting off roads and villages. The area around Mau Due, Du Gia has limestone caves and subterranean rivers travel through the rock formations. 54. The area provides a wide range of aquatic resources for subsistence and trade, as well as water for drinking, bathing, and crop irrigation. In addition, these rivers form local transportation routes and have potential for local small hydropower stations. There are not many navigable rivers in the project area and transportation is mainly reliant on the roads. 55. None of the rivers near the Project roads are subject to industrial pollution but there is a number of newly developed small workshops scattered alongside the roads. Some mines are in operation mostly for limestone and/or gemstone exploitation. Bamboo processing and saw mills are also present on the banks of the rivers that will affect the water quality in future. The nearest other industry is the Ha Giang industrial park, several tens of km from the project roads. 56. Domestic water supply is generally obtained from wells within the boundary of properties or uphill streams and river water is used for irrigation ad livestock. Therefore B1 is the appropriate standards for comparison purposes. Water quality monitoring was undertaken at 9 locations on Project roads in Ha Giang. The results are presented in Table IV.1.

Page 18

Table IV.1: Water quality at watercourses along the Project roads – Ha Giang

Total Coliform DO BOD COD SS Ref Sampling Location pH 5 oil (MPN/100 (mg/l) (mg/l) (mg/l) (mg/l) (mg/l) ml)

Road TL176A TL176AWQ Stream – Du Già commune - Yên Minh district 8.3 8.1 1 2 14 0.08 400 1 N 22o55’52”; E 105o13’26” TL176AWQ Nà Đon stream – Mậu Duệ commune - Yên Minh district 7.8 7.2 1 3 11 0.1 390 2 N 23o03’44”; E 105o13’20” Road TL183 Cò stream (Khuổi Niếng bridge) – Vĩnh Tuy town, Bắc TL183WQ-1 8.0 7.8 1 2 14 0.1 380 Quang district; N 22o14’40”; E 104o53’13” Cầu Kiềng stream - Đồng Yên commune, Bắc Quang TL183WQ-2 7.8 7.8 1 4 73 0.2 540 N 22o13’25”; E 104o48’11” Cò stream (Khuổi Niếng bridge) – Vĩnh Tuy town, Bắc TL183WQ-3 7.6 6.2 2 4 11 0.1 320 Quang district; N 22o14’40”; E 104o53’13” Cầu Kiềng stream - Đồng Yên commune, Bắc Quang TL183WQ-4 7.4 6.2 2 4 13 0.2 290 N 22o13’25”; E 104o48’11” Cò stream (Khuổi Niếng bridge) – Vĩnh Tuy town, Bắc TL183WQ-5 7.4 6.0 2 5 14 0.3 310 Quang district; N 22o14’40”; E 104o53’13” Cầu Kiềng stream - Đồng Yên commune, Bắc Quang TL183WQ-6 8.0 6.3 2 5 12 0.1 280 N 22o13’25”; E 104o48’11” Stream - Quang Bình town, Quang Bình district TL183WQ-7 7.3 6.8 2 5 18 0.3 620 N 22o24’34”; E 104o35’13” QCVN 08:2008/BTNMT (Column A1 – domestic supply after treatment) 6-8.5 ≥6 4 10 20 0.01 2500

QCVN 08:2008/BTNMT (Column B1 – irrigation and livestock ) 6-8.5 ≥4 15 30 500 0.1 7500 Source: TA 7245 Consultant’s surveys 2009. Figures in bold italics exceed A1 – underlined exceed B1.

57. In some residential areas, surface water may be contaminated by domestic wastes as levels of oil and grease in almost all water samples collected from Ha Giang exceeded the standard for total oil and grease in surface water (QCVN 08: 2008/BTNMT, column A1). The explanation may be high levels from domestic sources from food and cooking waste discharged to streams and that many of the sampling points are not in big streams or rivers but only in small water ways. In addition there is the local custom of washing motor bikes in the nearest stream which will cause oily residues to accumulate. The concentrations of oil and grease also exceed the limits allowed for surface water of agricultural usages. (QCVN 08: 2008/BTNMT, column B1). Beside, the levels of oil and grease, water analysis indicates the samples are still within the limits allowed for surface water of agricultural usage. (QCVN 08: 2008/BTNMT, column B1). 58. Groundwater is abundant in Ha Giang territory. People in urban and low-mountain areas are popularly using groundwater in shallow wells for domestic purposes. However, due to the structure of geology here, it is not so easy to dig a well for ground water. Beside, intensive use of the water is lowering the water level in shallow wells in built up areas. Ground water in Ha Giang has high hardness and total dissolved solids and needs to be treated before use for daily activities. Thus, many people in Ha Giang still rely on surface water sources and/or water leaching from rocky mountains.

4. Air Quality 59. Air quality monitoring was undertaken at 14 locations on Project roads in Ha Giang. The results ate presented in Tables IV.2. In general, air quality levels are within acceptable limits of Vietnamese environmental standards. The gaseous pollutants of

Page 19

carbon monoxide (CO), sulphur dioxide (SO2), nitrogen dioxide (NO2) from traffic appear to be well dispersed in the open terrain and there is potentially adequate dispersion in the wide main streets of the towns. Air quality appears to be generally acceptable. The exceptions are dust concentrations. Dust in many analyzed samples exceed the Viet Nam standards. This is understandable owing to the difficult situation of the transportation system in the province. All existing roads in the project area are of poor quality. Traffic vehicles find it difficult to move along the roads with weak foundations and broken surface pavements. Engines must run with high capacity and of course make more noise. Dust arises as traffic passes over unsealed shoulders of roads in many places making its high concentration in the air over the bad roads. 60. The areas near the towns at Mau Due, Du Gia, Minh Ngoc, Hoang Su Phi, Vinh Tuy and Yen Binh have more potential sources of atmospheric pollution mainly from domestic sources but these are not making significant impacts on air quality based on observation. These areas are more polluted due to significant town development as well as emissions from a few modest industrial establishments. The othe source of air pollution is dust arising from ground or soil disturbance. Dust concentrations will be higher, if only intermittently, within about 10m of the Project roads when dust rises from the shoulders as vehicles pass, although dust levels are not high enough to obscure vision significantly, based on field observations. The Viet Nam criteria currently set by the MONRE or the standards set by World Bank will be used for the assessment whichever is stricter. Table IV.2 : Air quality and noise along the Project roads – Ha Giang

o T Humidity Noise CO SO NO Dust Pb Ref Sampling Location 2 2 (oC) (%) (dBA) (mg/m3) (mg/m3) (mg/m3) (mg/m3) (mg/m3) Road TL176A People's committee of Du Gia TL176AAQ commune; 31 83 51.0 3.6 0.006 0.004 0.41 0.0003 -1 N 22o55’52”; E 105o13’26” Head office’s Lung Ho TL176AAQ commune- Yen Minh district; 30 84 45.3 3.2 0.004 0.003 0.31 0.0003 -2 N 22o59’13”; E 105o14’20” People's committee of Mau TL176AAQ Due commune; N 23o03’51”; 29 86 49.0 3.6 0.004 0.003 0.36 0.0005 -3 E 105o13’55” Road TL183 TL183AQ- Highway 2 three way cross 1 roads to Luc Yen 31 79 51.0 1.8 0.004 0.001 0.26 0.0001 N 22o15’16”; E 104o54’19” TL183AQ- Three way cross roads, near 2 People's committee Đong Yen 33 80 48.0 2.0 0.002 0.001 0.29 0.0001 commune ;N 22o11’54”; E 104o46’37” TL183AQ- Near stream – Vi Thuong 3 commune, Quang Binh district; 32 82 49.0 1.8 0.004 0.001 0.30 0.0003 N 22o14’32”; E 104o44’22” TL183AQ- Market of Thuong Binh village 4 – Vi Thuong commune, N 30 81 47.0 1.8 0.004 0.001 0.28 0.0003 22o16’07”; E 104o43’11” TL183AQ- People's committee – Tien 5 Yen commune; N 32 79 49.0 1.9 0.004 0.001 0.24 0.0004 22o16’50”; E 104o42’31” TL183AQ- Three way cross roads of 6 Xuan Giang commune, N 31 80 49.0 1.9 0.003 0.001 0.48 0.0004 22o19’08”; E 104o40’19” TL183AQ- The center of Bang Lang 32 81 49.0 1.9 0.003 0.001 0.31 0.0001 7 commune, Quang Binh; N

Page 20

o T Humidity Noise CO SO NO Dust Pb Ref Sampling Location 2 2 (oC) (%) (dBA) (mg/m3) (mg/m3) (mg/m3) (mg/m3) (mg/m3) 22o21’52”; E 104o38’09” TL183AQ- Highway 2 three way cross 1 roads to Luc Yen 31 79 51.0 1.8 0.004 0.001 0.26 0.0001 N 22o15’16”; E 104o54’19” QCVN 05 -2009 BTNMT (1-hr) - - - 30 0.35 0.2 0.3 - WHO guideline (1-hr)* - 0.2 - - TCVN 5949-1998 residential (World Bank) - - 60 (55) - - - - - Source: TA 7245 Consultant’s surveys 2009. *Environmental Health and Safety General Guidelines Washington 2007 Land use in the vicinity of all sampling points was village houses surrounded by agricultural land

5. Noise 61. Noise from vehicles is not a concern in the areas around the Project roads at present as traffic is confined to occasional vehicles. Noise levels are within acceptable limits of Vietnamese standards and WHO guideline. There is no criterion for road traffic noise in Viet Nam therefore the World Bank ambient noise criteria will also be applied. The World Bank applies an ambient standard of Leq55dB(A) for residential areas, hospitals and schools. Where the background exceeds the ambient standards the World Bank criterion is background +3dB(A). The Viet Nam ambient standards are Leq50dB(A) for residential areas, hospitals and schools and Leq60dB(A) for residential areas. Measurements of background noise were taken as 1hour LeqdB(A) at more than one location on each road. Background noise ranged from Leq45.3dB(A) to Leq53.0dB(A) with traffic. Therefore in the settlements and towns where traffic runs throughout the day the Viet Nam criterion of Leq50dB(A) for school and hospital sensitive receivers is potentially exceeded but the Leq60dB(A) criterion for residential sensitive receivers is not exceeded. As some of the Viet Nam criteria are exceeded at some times of the day it is recommended that in order to make a consistent assessment for all locations the existing World Bank criterion of background +3dB(A) will be applied in the assessment. The Viet Nam criterion of Leq40dB(A)1hour can be used for nighttime. However there is a general presumption that there will be no night time working except in exceptional circumstances.

B Biological Environment

1. Agriculture 62. Rice is the staple food of the Viet Nam People but in the cultivated areas around the Project roads there is only a limited portion of the land area suitable for wet-paddy cultivation due to the project area’s terrain. Large wet-paddy areas are found in many of the project areas but rain-fed rice fields are also common. Although rice is the staple food but only a limited portion of the land area is suitable for wet-paddy cultivation. Rain- fed rice paddies are also common and swidden rice cultivation is also practiced and vegetable and cash crops are produced as a substitute for rice deficiencies in many areas based on shifting cultivation. In addition to rice cultivation, a number of vegetable and cash crops are produced on a more commercial basis and as a substitute for rice deficiencies. In some cases, these are produced based on shifting cultivation. These crops include soya beans, cassava, green beans, peanuts, job’s tear, sesame, corn, teak, mulberry fiber, and a variety of fruit trees. People maintain vegetable gardens near streams and riverbanks and plant fruit trees near their house to supplement diets and to generate cash income. A variety of vegetables are grown such as cabbage, cucumbers, tomatoes, lettuce, chilly eggplant, and pumpkin.

Page 21

Table IV.3 : Land Use in Ha Giang Province

Total Area (ha) Agriculture Forestry Special Use Land Homesteads 794600 149200 378300 9000 6100 %* 18.8% 47.5% 1.1% 0.8% Source: Statistical Yearbook of Vietnam 2008, Statistical Publishing House, 2009 . *Unused land is not listed

63. Only about 19% of the total land area is classified as arable Table IV.3). The forested land area has declined significantly since the 1970s as a result of logging and slash-and-burn farming. Cash crops, mainly tea and nut are also grown. Herbal medicinal plant cultivation is also common practice of the minority peoples for self medication and market sale. 64. Some of the valleys have good agricultural potential. Despite these significant areas of good agricultural potential, income levels are very low and people are vulnerable to land degradation, declining crop yields and low incomes limit the capacity of households to obtain food.

2. Forestry 65. The land for 6 m either side of the Project Roads centerline is declared as the ROW (Figure III.1). The Project roads do not cross a National Park or Nature Reserve or Protection Forest and none of the land in the ROW is production forest or protected forest. The lands adjacent to the ROW (more than 6 m from the roads) are mainly agricultural land. Production forests in some areas are allotted to individual households (FPD 2010, Appendix B) but they are mostly several kilometers (usually more than 3 km) from the Project roads. The production forests are plantations where residents plant certain tree species which are harvested later. Popular trees for planting include acacia, casuarinas, cajput, eucalyptus, and chinaberry but the most common is mo or “fat” tree (Mangleitia glauca). Trees within production forest areas with land use title can be cut and will probably go for local use. If for some unexpected reason the Project roads’ alignment is changed and trees need to be cut for the upgrading of project roads there will be a need for the design consultants (DDC) to inform the forest authority so they can plan, mark and cut them first. 66. The local production forests are managed by the Forest Protection Department (FPD) in the Provincial Office of Department of Agriculture and Rural Development (DARD) according to the instructions and quotas for cutting and planting received from Ministry of Agriculture and Rural Development (MARD). The production forests that are outside the ROW are degraded and not that densely vegetated with mature trees but mainly small-diameter trees, bamboos and shrubs. Local officials indicated that trees can be cut with permission form the forest authority who will mark the trees and areas of bamboo for cutting. Bamboo cutting is regulated by the villages under quotas. There is good cooperation locally with the villages and the forest authority is notified of sales and the authorities levy charges for the forest products that are cut. 67. The local forestry officers in Ha Giang could not provide any detailed information on the location or species composition of the nearest production forest or protected forests. Timber extraction is generally local small-scale/saw-mill production of timber for local construction purposes. 68. No other records of the species composition or the boundaries of the forests could be identified but the forestry officials have indicated that much of the standing crop is bamboo and other small trees and shrubs. Planted specimens of bamboo, acacia, pine, cajuput, linh and cedrela are apparently the most common nearest the Project roads. The chief officer of FPD in Ha Giang indicated that the widening of the roads is not a

Page 22

concern to FPD because the proposed road works are modest and the roads has been in place for many years.

3. Fauna and Flora 69. The human impact on the vegetation is most pronounced in the areas where grasslands created by numerous cycles of forest clearance for agriculture and their reversion to fallow gradually transformed the forest to short grassland with secondary regrowth forest. 70. In 2007, the total forest-cover of Ha Giang province was 301,182.93 ha (approximately 38% of the province’s area). This includes 80% natural forests and 20% planted forests. At present, about 84,326 ha are protected river-head forests and natural reserves protected by policies of national and local governments. The forest ecosystems have a high biodiversity and contain many valued and endangered species protected by law in Vietnam. 71. There are several areas in Ha Giang Province that have been considered for protection for their biodiversity and conservation value. Tay Con Linh, Phong Quang and Bat Dai Son, Phong Quang-Vi Xuyen and Cang-Bac Me are all more than 5 km from any of the roads under consideration in this Project. Du Gia Nature reserve is about 2.5 km south west from the southern end of Project road 176A.

4. Don Van Karst Plateau Geopark 72. The whole of Project road 176A is within the Dong Van Karst Plateau Geopark, an area promoted internationally for landscape and geological significance. The Dong Van Karst Plateau Geopark was established in 2009 by Decision 4844/QD-UBND and the Management Board was also set up at that time decisions 4845&6/QD-UBND (all dated 19th November 2009). DVKPG was recognized by UNESCO in 2010. 73. Project Road TL176A is settled for all its length and it runs through a series of small villages. In between the villages there are agricultural fields in flatter areas in between the limestone karst outcrops and a few areas of trees planted on the hills for harvesting later. The vegetation near the road is mainly grass, ferns and shrubs with agricultural crops in the fields and a few scattered trees. 74. The sensitivity of the DVKPG to environmental change as a result of the Project road stretch TL176A needs to be considered. The location and proximity suggests that there could be direct, indirect or induced effects from the Project works but DVKPG Management Board (DVKPGMB) did not indicate any concern in this regard and they consider the protected area may not necessarily be sensitive to direct, induced or indirect Project road impacts because there is only modest widening to an existing road. 75. Consultations with DVKPGMB did not indicate any current problems with any illegal activities affecting the geological resources. The extraction of raw materials near the project road will be controlled because all of the Project road is within the DVKPG but there is no wholesale moratorium on such activities in the DVKPG. Rather, DVKPGMB expect to be consulted and permission must be obtained from the DVKPGMB before any borrow pits are opened up and before worker camps and disposal sites are selected because landscape and visual impacts should be avoided. 76. The DVKPGMB did not see the need for any project specific mitigation measures to protect the DVKPG resources but routine controls on worker camp operations, opening up borrow pits and worker camps and disposal sites should be included to prevent damage to DVKPG resources. These measures are included in the EMP in addition to the normal administrative requirements from DONRE and agreements with local district authorities and commune PPCs that PPMU must obtain before work can start.

Page 23

77. It is expected by DVKPGMB that in principle all waste materials must be removed from the DVKPG but this may not be practical in all cases. Therefore DVKPGMB shall be consulted in advance during the detailed design stage and again before bidding commences in case the PPMU wishes to set up any project related facilities in areas of DVKPG. DVKPGMB must approve in advance all project facilities to be located in the DVKPG and may also require additional mitigation measures to avoid project impacts especially in areas which are potentially sensitive to geological landscape and visual impacts. 78. However overall DVKPGMB indicated that because the Project road has been in existence for a long time there would appear not to be any major opportunity for induced impacts due to possible increases in uncontrolled access for exploitation of DVKPG resources caused by the improved road conditions due to the Project. However as DVKPG is recognized by UNESCO the DVKPGMB must be notified about the project in advance in due course. DVKPGMB do not envisage any difficulties in obtaining UNESCO concurrence for the Project road but it will be necessary to compile a report for UNESCO in advance. Hence DVKPGMB must be informed and consulted as soon as possible in the detailed design phase so that the requisite report can be compiled for UNESCO. No additional measures were requested by DVKPGMB. This seems reasonable given that there are already other local statutory and guideline controls in operation by DONRE and the local authorities. 79. The chairman of DVKPGMB indicated that they did not have any in principle objection to the Project road (Appendix D) and the widening of the road was not a concern to DVKPGMB because the roads works were modest and the road has been in place for many years before the DVKPG was declared.

5. Du Gia Nature Reserve 80. The end of Project road TL176A is about 2.5 km from the area known as Du Gia Nature Reserve (DGNR) that has been identified for conservation, due to its biodiversity. DGNR is also recognized as an Important Bird Area by Birdlife International. 81. The southern stretch of road TL176A passes roughly north to south near the Du Gia Nature Reserve but this is not the Project road stretch (Figure IV.3). The road TL176A was in place before the special forest use was declared. 82. In 1993 the Provincial Peoples Committee of Ha Giang issued Decree No 137/UB- QD to establish and develop Special Use Forests in the province including Du Gia4. The Du Gia (Du Gia-Yen Minh) Nature Reserve was identified in 1994 by Decision 647/QĐ, dated 24th November 1994, by Ha Giang PPC. 83. According to the investment plan, originally the total area of the proposed nature reserve was 24,293 ha, comprising a strict protection area of 7,652 ha, a forest rehabilitation area of 14,294 ha and an administration and services area of 2,347 ha. In addition, there was a buffer zone of 19,700 ha. 84. An investment plan was prepared in 1994 and approved by PPC of Ha Giang (PPC) and subsequently by MARD and a nature reserve management board was established with four persons following Decision No 647/QD-UB of PPC. The DGNR management board is chaired by the provincial FPD. Location, management and resources are presented in Table IV.4 (source MONRE 2010). 85. Biodiversity surveys of DGNR carried out in 2000 recorded 61 bird species including the globally threatened beautiful nuthatch Sitta formosa. Further rapid biodiversity

4 Sourcebook of Existing and Proposed Protected Areas in Viet Nam, IUCN – Bird Life International 2004.

Page 24

surveys conducted by BirdLife International (May 2002) recorded an additional 55 species. Because of its importance for beautiful nuthatch and biome-restricted species, Du Gia qualifies as an Important Bird Area. 86. DGNR was also confirmed to support a significant population of Tonkin Snub-nosed Monkey Rhinopithecus avunculus. This globally critically endangered species is endemic to , and the population at Du Gia is believed to be one of the largest remaining. DGNRMB indicated that the home range for Tonkin Snub-nosed Monkey in DGNR is about5 km south west of the end of the project road, 87. The Ha Giang FPD indicated that the DGNR core zone and buffer zone boundaries have subsequently been modified and reduced to exclude many agricultural areas and include other areas of important and improving habitat. 88. Based on field inspection and maps obtained in February 2011, DGNR buffer zone is about 2.5 km from the start of the project road at its nearest point.. The protected habitats which are much further south west are where the rare species are believed to range and these core areas are well away from the Project road. Figures IV.1 and IV.3 are based on the map provided by the FPD. 89. Information and maps received from Ha Giang FPD indicate that the DGNR has been included on the provincial and district zoning maps. The edge of the buffer zone for Du Gia Nature Reserve is confirmed by Ha Giang FPD as shown on the land use map for the commune (2007) and is be managed by the Ha Giang FPD. The current boundary is shown on Figure IV.3.

Page 25

Table IV.4 : Du Gia Nature Reserve – Location, management and resources (MONRE 2010). ITEM DETAILS Name of Nature Reserves DU GIA Establishment decision Decision No. 647 dated Nov 24 1994 of Ha Giang People’s Committee. Location Located on 3 Districts: Du Gia Commune of Yen Minh District; Minh Son Commune of Bac Me District, Tung Ba Commune of Vi Xuyen District. Geographic coordinates 22 0 48'30''- 22 0 58'00'' N; 105 0 3'00''- 105 0 20'30'' E. Area 11,794.7 ha (After review) Strictly protected area 6429 ha Ecological restoration area 5365.7 ha Administrative Services Buffer Organizational Structure Total staff includes 5 people: 1 director, 1 deputy director, in charge of technical affairs, 1 financial officer & 1 staff. Tasks Protect &develop forests, especially animals &plants with rare genes. Organize experimental production & scientific research. Make social &economic improvement &improve living standards for people with models of forest-garden, in the form of agroforestry. Educate on protecting forests &protecting the village. Climate, hydrology Du Gia area is cold in the winter &cool wet in the summer, serious water shortage in the winter, the rainy season from July to August; dry season from November to April next year. Average annual temperature is 20.1 0 C; Max 35 0 C; Min 8 0 C. Average annual rainfall is 1575mm Average humidity 82%, the highest 89% lowest 68%. Number of sunshine hours in year: 594 hours As the upstream region of streams flowing into the Gam River in the south &Mien river in southwest. There is a large soaking spring system in the North to Coc village in Du Gia commune. Intermittent seasonal rainfall, large falls with huge potential for micro hydropower. Due to high mountain terrain, cool weather, the change of weather accelerates the weathering process good for plant growth. Performance 1. Construction work: Construction of an office of 150m2, 02 forest protection stations (already downgraded &no longer in use). 2. The forest management &protection: Since the establishment, the management & protection is done in several stages by the characteristics of the unit, as follows: * Period from establishment to the year 2000 with principal activities: 6501 hectares of forest protection; Regeneration &ecological restoration of 7196 ha; Settlement for 33 households in the reserve. The period from 2001 to 2008: Project 661: Planting new forests of 1268.5 ha; Regeneration & restoration of forest outside protected area: 4216.7 ha; However, re-aforestation & forest regeneration &restoration are done largely outside the area of conservation (only 100 ha planted in conservation area); Open 6 forestry extension courses for transfer of technology to farmers. * 2009: To continue implementing Project 661 as assigned by the PPC: Planting new forests: 100 ha in protected areas; To manage &protect forests; Having delivered documents related to the forest management & protection, forest fire control . in many different forms to communes & villages & to people living in protected areas; Presently in reserves area there is illegal exploitation of forest products (timber and non timber). 3. Conservation &scientific research: Approaching the investment support program of the project's biodiversity conservation (VCF). 4. Eco-tourism activities &environmental education advocacy: There are no activities for ecotourism in the reserves. Biodiversity resources 1.Flora: Closed evergreen rain forest &tropical humid evergreen closed wet tropical forest in mountains. Composition of plants was initially investigated in NR &there are 289 species of higher plants in 83 families in which 2 Lycopodiophyta species; 13 Pteridophyta species, 3 Gymnospermae species, 271 Angiospermae species; Dicotyledones: 232 species; Monocotyledons: 39 species. Especially with the presence of Fokienia hodginsii (well-known endemic in Vietnam) that is a valuable export crops &rare genetic resources. Besides, Cupressaceae, Bignoniaceae, Burretiodendron hsienmu, Garcinia fagraeoides are distributed over a large area with high reserves. 2. Fauna: Vertebrate fauna in the area has 171 species in 73 families &24 orders Basic characteristics of the forest fauna are the limestone, dominated by species adapted to difficult terrain like mountain goats, monkeys, squirrels.

90. The road TL176A runs south from Pho Bang International Border Crossing (about 45 km) to Mau Due and then Lung Ho for several tens of kilometers before running directly through the centre of the Du Gia NR. The section of Project road 176A is not

Page 26

within the area of Du Gia Nature Reserve as confirmed by FPD. The origin of the Project road section for improvement commences several kilometers north east of the Du Gia core area. The FPD officials have commented that the core zones for protection are much further south and west than the Project Road 176A. The FPD officials did not express any concerns for illegal logging or hunting in the areas around Project road 176A as there is very little habitat remaining in these areas. The Deputy Manager of Resource Management Department of DONRE in Ha Giang has also commented that there are no other protected areas within 1 km of the Project road 176A. 91. Therefore whereas there are some valuable ecological resources and protected sites well to the south west of the stretch of Project road TL176A selected for improvement it is not near the buffer zone or core areas protected for natural habitats for rare or endangered species.

C. Social-Cultural Environment

1. Human Issues and Quality of Life 92. Ha Giang province is situated in the northeast of Viet Nam sharing a border with China. It is enclosed by China to the north, provinces of Ha Giang to the west the province of Cau Bang and Tuyen Quang to the east and Yen Bai to the south. Total area of the province is 793,600 hectares (ha). The province has a population of 708,000 people giving a population density 89 persons/km2. Twenty-two (22) different ethnic groups including Kinh people and the rest ethnic minorities such as Mong, Tay, Dao, Nung, Giay, La Chi, Hoa, Pa Then, Co Lao, Lo Lo, Bo Y, Khmu, Tai Daeng, Yao, Tai Kao, Tai Meuay, Tai Neua, Phu Noi live in Ha Giang. More than 94% of the population lives in rural areas. Kinh people occupy 12% of the total population and live mainly in district towns and commune headquarters. 93. The average population density of 89 persons/ km2 is relatively high for a rural area especially in Asia. About 68% of the total population lives on the lowlands and the river valleys, mainly in urban areas. Yao and H’mong ethnic groups live on the lower mountainous slopes, and make up about 22% of the population. In Ha Giang, the Viet Nam Soung are highlanders who usually live in areas 1000 meters above sea level (masl) or more and they make up about 10% of the total population. They retain their traditional languages and culture in the extremely remote areas that they and inhabit. 94. The strong agricultural pressures constrain the opportunities for people living in these areas. Income levels are generally very low except in the main towns and the areas around the Project roads have some of the most disadvantaged districts in Viet Nam. A detailed description of the socioeconomic environment of the study area is given in a separate Ethnic and Poverty Assessment Report for the project.

2. Land Use 95. The Project roads run along several valleys. The dominant land use in the vicinity of the Project road stretches is mainly agriculture that has been developed over many cycles in the past centuries. There are also large areas of swidden agriculture on the hills with some areas of irrigated rice and vegetable fields in the flatter valley bottoms. There are also several towns and villages scattered all along the Project roads. The hinterland of the towns and villages is agricultural with some areas of plantation forests. 96. Ha Giang has abundant natural resources and a rugged landscape. The province is famous for limestone mountains and many caves. Du Gia Nature Reserve, with its high numbers of mammals and other wildlife species, has ecotourism potential. The FFI Society is in the process of researching ecotourism development in the area that would provide income to local communities in support of conservation.

Page 27

97. The Dong Van Karst Plateau Geopark has been declared to be of international importance and is another ecotourism attraction. The province is also home to Lung Cu peak – the northerly point of Vietnam and Cong Troi (heaven’s gate). Pho Bang and Thanh Thuy Border Crossings are important historic sites. The province has spectacular scenery. Ha Giang is famous for its intricate silk and cotton weavings and other textiles.

3. Cultural and historical sites, schools and housing 98. There are no sites of cultural significance found near Project roads. There are places of worship nearby in some villages. There are graves in a few places along the road but 5m outside the road corridor and more than 10 m from the centerline and away from where the rehabilitation and upgrading works would need to take place. 99. Schools are located along the Project roads in a few locations usually at distances of more than 30 m. The boundaries of the school playgrounds and gates are generally near the road (within 10 m) but the noise sensitive facades of the school buildings are generally set well back from the Project roads by more that 30 m; outside the corridor of impact. However three schools are particularly vulnerable to impacts as they will be closer to the works at Du Gia, Mau Due on road TL176A and Vinh Tuy, Yen Minh on road TL183. 100. Traditional shops and houses are located at intervals all along the Project roads and residential development is spread out in patches along the roads. The ROW is not marked out in detail but in the villages the front facades of some of the houses are generally next to the road (just outside the corridor of impact) with the front fences and walls or temporary structures just a few meters from the existing road edge in many places. Some land acquisition will be required in places and relocation of some properties or resettlement. Land acquisition requirements are in the Resettlement Plan.

4. Power supply 101. Electrical power is supplied in Ha Giang from the grid in Vietnam known as EVN (Electricity of Vietnam). The low voltage distribution network runs on poles adjacent to the Project road and will need to be protected during the works. Many of these poles and lines may need to be reprovisoned before the upgrading works commence to ensure continuity of power supply. Small hydropower stations are present in Ha Giang and contribute a reasonable amount of electricity for local consumption. The Project road works do not create any impacts on these stations.

Page 28

Figure IV.1: Protected Areas in Ha Giang Province

Page 29

Figure IV.2: Dong Van Karst Plateau Geopark

Page 30

Figure IV.3: Du Gia Nature Reserve Buffer Zone

Page 31

V. ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES

102. This section discusses the potential environmental impacts of the proposed upgrading of road the Project roads and identifies mitigation measures to minimize the impacts in the design, construction and operation. 103. The main physical issues relate to impacts such as earthworks, erosion control, obtaining rock based construction materials, noise, dust, spoil disposal, disposal of other waste, and water quality. Blasting cannot be ruled out but the requirement for blasting is likely to be minimal and will be determined at the detailed design stage and reviewed during construction. The construction for the civil works will create dust, noise and vibration and the prevention of landslides must be addressed. The main biological issues relate to acquisition of agricultural land, impacts to rivers and removal of occasional trees in the works areas. There is no issue of interference with sites protected for their biodiversity as the stretch of Project road TL176A is about 2.5 km from the buffer zone of Du Gia Nature Reserve. There will also be no interference with protected forests as the works will be within the ROW for the Project roads. As such, adverse impacts on critical or natural habitats that which could impair the biodiversity value or function of nature reserves or protected forest areas are not foreseen. The improvements to the Project road stretches are not anticipated to lead to a reduction in the population of any recognized endangered or critically endangered species and there will be no loss of valuable habitats that could compromise the host ecosystem. Mitigation measures have been included in the EMP to prevent further conversion or degradation of biodiversity and to provide enhancement where practicable. With regard to the Dong Van Karst Plateau Geopark, the Project works are not anticipated to cause damage to this protected area since the Project will be undertaken on the existing road TL176A which will require modest widening (1 m at the most). Further, proper implementation of mitigation measures included in the EMP will avoid or minimize impacts to areas which are potentially sensitive to geological landscape and visual impacts.The social and human impacts to village life and impacts to social infrastructure will be of short duration and these have been subject to detailed assessment in the Resettlement Plan. 104. The potential environmental impacts in the design, construction and operational phases are assessed below. Where impacts are significant enough to exceed accepted environmental standards, mitigation is proposed in order to reduce residual impact to acceptable levels and achieve the expected outcomes of the project. The criteria for assessment are in line with ADBs SPS, or if the GOV standard is stricter, the national standards and criteria set by GOV. Where GOV has no set of standards or guidelines, the standards given in World Bank’s Environmental Health and Safety Guidelines5 are used. The EMP is presented in Table VIII.2 as a matrix of mitigation and monitoring measures to prevent or minimize the impacts.

A Design / Pre-Construction Phase 105. The proposed project involves upgrading of a single carriageway existing road. As the existing alignment of the road will be followed, route selection is established but there may be minor adjustment at the detailed design stage. There are a number of mitigation measures that will need to be carried out by the project detailed design consultant engineers (DDC) and checked by the PCC to avoid construction impacts by good design to minimize operational environmental impacts. DDC will be engaged by the PPMU. The PCC will be engaged by the JCC. Detailed design will be required to ensure that the upgraded road can cope with flooding. Bridges will be designed to withstand a

5 World Bank, Environmetal Health and Safety General Guidelines 2007, Washington D.C.

Page 32

100 year return storm event and culverts will be designed to withstand a 25 year return storm event in line with Viet Nam standards (TCVN 4054 – 20056). In line with ADB policy on environmentally responsible procurement, opportunities to provide environmental enhancements will also be identified in the detailed design as well as routine matters such as avoiding unnecessary removal of trees and compensatory and enhancement planting. The opportunities for design, construction and operational enhancements have been included in the Environmental Management Plan (EMP). However as the detailed designs will be completed later, the IEE (together with the EMP) will be updated by the PCC based on the designs by the DDC during the detailed design phase, or a new environmental assessment report will be undertaken for submission to ADB if there are any changes to Project design that would result to environmental impacts or risks that are not within the scope of the current IEE.

1. Design measures and project disclosure 106. The DDC in cooperation with PCC and PPMU will prepare the detailed designs to address the requirements below including, but not necessarily be limited to the following design requirements, and all relevant measures in Table VIII.2: i) Acquisition of agricultural land will be minimized for temporary facilities (if needed) by selecting preferred locations in detailed designs for construction yards and asphalt plant on barren or marginal land and agree terms with local community. ii) Potential solution spaces to ensure sufficient disposal space for cut surface spoil materials and to avoid fly-tipping will be identified in advance by the DDC and approved by PPMU and PCC and the local community before bidding. iii) Arrangements will be made to facilitate the timely production and supply of rock and bitumen based materials for construction and to avoid impacts due to unnecessary stockpiling near the Project roads. iv) Extensions and improvements of drainage culverts for the Project roads road will be designed to account for increased rain due to a once in 100 year return storm event. v) Hydrological and drainage impacts during construction will be minimized by including in the detailed design early phasing of replacement of culverts and other infrastructure. vi) Disruption to current facilities for water supply will be avoided and facilities will be retained or re-provisioned before construction works commence; provisions will be made to preserve the operation of current facilities for water supply in sufficient quantity in agreement with the local community. vii) Disruption to current power supply will be avoided and movement of power lines will be planned well in advance. Power distribution circuitry will be re-provisioned before construction works commence; provisions will be made to preserve the operation of current facilities for power supply in sufficient quantity in agreement with the local power supply company. viii) Plans to minimize disturbance of vehicular traffic and pedestrians during construction will be included in the detailed designs. Phasing for construction will retain a passing lane along part of the road during construction in detailed designs programming and avoid community severance. ix) Aim to provide enhancements under ADB policy on environmentally responsible procurement and avoid negative impacts due to unnecessary removal of trees. 107. The roads requiring improvement are part of the existing road corridor and although the RoW is wide enough for the upgrading there are some encroachments and there will

6 TCVN 4054 – 2005: Bridges 100 yer return storm enent, culverts 25 year return storm enent.

Page 33

be some requirement for resettlement. This will probably be needed at a few hundred locations subject to confirmation and these requirements are presented in the Resettlement Plan. 108. The final alignment will be disclosed to DONRE and a check will be made at the detailed design stage that the road alignment has been designed as planned. The IEE/EMP shall be updated by the PPMU/PCC and resubmitted to ADB and incorporating any recommendations and requirements from the DONRE/MONRE, should there be additional environmental impacts not identified in this IEE and for which appropriate mitigation measures have not been included in the EMP. Further, if during detailed design there are any changes to Project design (such as change in alignment) that would result to environmental impacts or risks that are not within the scope of the current IEE, the PCC during the detailed design phase shall update the IEE (together with the EMP) or prepare a new environmental assessment report for submission to ADB. Prior to preparation of the updated or new environmental assessment report, the proposed Project change shall be screened by ADB for its potential environmental impacts and risks to determine the appropriate extent and type of environmental assessment to be undertaken. During Project implementation either, an updated IEE, an updated EMP or a new environmental assessment report, as necessary, shall be submitted to ADB for clearance, if any unanticipated environmental risks and impacts arise. The appropriate document for submission shall be determined by ADB. PPMU will also establish the Grievance Redress Mechanism at this stage before site works commence.

2. Project boundaries change near sensitive receivers 109. The residential sensitive receivers (SRs) near the Project road the Project roads are generally set back sufficiently for traffic fumes to be dispersed and road traffic noise will not be sufficient to affect the sensitive receivers. At this stage and given the modest traffic flows it appears that neither the Viet Nam criterion of 60B(A) for sensitive developments such as residences or the World Bank criterion of 55B(A) at the sensitive receiver for new noise sensitive developments such as residences, schools, colleges and hospitals could comfortably be achieved in the operation al phase. Noise and dust in construction will need to be controlled. 110. There are no medical facilities near the Project roads the Project roads. The roadside cemeteries are generally set back from the working areas and the DDC will carefully design the Project road works to avoid the cemeteries. The occasional roadside tea and food stalls are also set back from the likely working areas for road rehabilitation. There are many schools in Project road areas but the sensitive facades are also set well back from the road by more than 50m. There may be some as yet unidentifiable refinements to the alignment at the detailed design stage that mean the works must take place over a slightly different area. As mentioned above, a new environmental assessment or an updated IEE (together with the EMP) shall be prepared by PPMU/PCC if refinements or changes to the project alignment, based on the detailed design, would result to environmental impacts or risks that are not within the scope of the current IEE. Such documents shall be submitted for ADB’s review before changes are implemented.

3. Environmental capacity development of PPMU 111. PCC/PPMU will make sure that PPMU’s Environmental and Safety Officer (ESO) is trained and prepared to ensure that future contractors will be primed to cooperate with the implementing agency, project management, PSC, PCC and local population in the mitigation of environmental impacts. The PPMU would dedicate a suitably qualified staff as ESO to undertake this task. The PCC will also develop strengthening plan for the environmental management by PPMU and retention of environmental staff. Details of the proposed environmental capacity building for PPMU are provided in Chapter VIII (Environmental Management Plan).

Page 34

4. Preparation of site specific EMPs 112. The contractors will be primed by including the Project EMP (Table VIII.2 of the IEE) and specific EMPs (SEMPs) in the bidding and contract documentation. Prior to bidding, the PCC will produce a series of method statements or SEMPs that the contractors will need to implement. The broad content of the SEMPs is included in the construction mitigation section. The SEMPs will demonstrate the manner (location, responsibilities, schedule/ timeframe, budget, etc.) in which the contractors will implement the mitigation measures specified in the EMP. 113. Based on the EMP, the following method statements or SEMPs shall be prepared by the PCC in the preconstruction/detailed design stage for implementation by the contractors: i) Waste Management and Spoil Disposal Plan (WMSDP) for handling, storage, treatment, transport and disposal of solid and liquid wastes, hazardous materials, hazardous wastes and excavation spoils. The plan will include a provision prohibiting disposal of wastes within the Dong Van Karst Plateau Geopark. There must also be a provision that disposal of excavation spoils within DVKPG will not be undertaken unless: a) prior approval is obtained from DVKPGMB and UNESCO, b) disposal of excavation spoils will not cause negative visual impacts, and c) will not adversely affect the protected geological resources within DVKPG. The WMSDP will also provide details of a trip ticket system to ensure that contractors dispose excavation spoils in approved areas. Such system will be designed so that the PSC and PCC could readily monitor the volume and disposal site of excavation spoils, and to ensure that the total volume of spoils disposed will not exceed the maximum capacity of disposal sites approved by local authorities. ii) Materials Management Plan (MMP) detailing arrangements to be made to facilitate the timely production and supply of construction materials to avoid impacts due to unnecessary stockpiling outside the Project site. iii) Drainage Management Plan (DMP) to ensure that construction works will not cause ponding/flooding within the Project site, construction camps, borrow/quarry areas, other areas used for project-related activities and adjacent areas. iv) Erosion Control Plan (ECP) to ensure that construction works will not cause excessive runoff and siltation of adjacent waterways within the Project site, have sufficient provisions to ensure stabilization of cut slopes and other erosion-prone areas, minimize hydrological impacts, flooding and erosion of river banks and adjacent areas and to protect the works under construction; v) Tree-cutting and Replanting Plan (TRP) to ensure indiscriminate tree-cutting shall be avoided by clearly defining areas where vegetation removal is necessary based on Project requirements and that replanting shall be done to compensate for lost trees. vi) Temporary Traffic Management Plan (TTMP) to minimize disturbance of vehicular traffic and pedestrians during construction. Access arrangements for vehicles accessing the Project area will be formulated such that this will avoid community disturbance and severance and will at least retain a passing lane along all roads used during construction. vii) Utilities and Irrigation Reprovisioning Plan (UIRP) to minimize interruption to power, water supply telecoms and irrigation system; viii) Noise and Dust Control Plan (NDCP) to minimize impacts to sensitive receptors (residential areas, schools, hospitals, etc.) due to construction works, sourcing and transport of construction materials, and other project-related activities. ix) Workers and Public Safety Plan (WPSP) to identify interfaces between the works and public and ensure worker and public safety and prevent accidents due to the construction works.

Page 35

5. Environmentally responsible procurement 114. All the above management plans will be agreed in advance with PPMU/PCC in the project preparation phase and included in contract documentation. The requirements in the contract will include full implementation of the EMP. PPMU/PCC shall ensure that the EMP are included in the bid and contract documents for civil works. PPMU shall require the contractor to engage capable and trained staff or site agents to take responsibility for the environmental management at the working level and to audit the effectiveness of the contractor’s SEMP and review mitigation measures as the project proceeds. The effective implementation of the SEMP will be audited as part of the loan conditions and the executing agency (PPC) will be prepared for this. In this regard, the JCC and PPMU (implementing agency) will also prepare to allow sufficient resources for the PCC to fulfill the EMP requirements. The international and national environment specialists in PCC will train environmental officers of PPMU to guide the contractors on the environmental aspects of road construction. This process has begun on other road projects and will be carried forward in this project. Any recent recommendations and initiatives from MONRE/DONRE or other local environmental and forestry authorities will be incorporated in the EMP and updated and audited as necessary.

6. Unexploded ordinance (UXO) 115. In order to avoid the risks from UXO and avoid accidents, the PPMU will coordinate with appropriate agencies at the design stage to identify if UXO is a potential threat to works in the project areas and PPMU shall commission UXO clearing, as necessary. The contractors shall only commence site works after advise from PPMU that the UXO clearing firm has certified that the project areas are already cleared of UXO.

7. Ambient environmental baseline data a. Air quality and Noise 116. Baseline data on air quality and noise levels shall be collected before commencement of civil works. Such data will help in assessing project impacts during implementation. 117. PCC shall collect baseline data on total suspended particulates (TSP) and noise levels at each district along the alignment. At least two weeks before commencement of civil works, field sampling for TSP and noise will be conducted at representative sensitive receptors (SR), i.e., sampling stations shall be established and sampled for various SR types as follows: (i) residential area, (ii) school/office, (iii) temple and (iv) hospital/health center. Field measurements for TSP shall be carried out using 1-hr averaging period based on the prescribed methodology in QCVN 05:2009/BTNMT (Viet Nam Ambient Air Quality Standard) 118. Noise impacts may be short lived, although can be very intrusive if not controlled properly. Noise measurement shall be undertaken at the same sites sampled for TSP and shall follow the methodology specified in TCVN 5949: 1998 (Noise in Public and Residential Areas– Allowable Noise Levels). Noise shall be measured in dB(A) over a 24 hours covering the different periods (i.e., 6h to 18h, 18h to 22h and 2h to 6h). Measurement will also be taken to establish if the World Bank criterion of Leq55dB(A)1- hour is exceeded at the measurement points. If it is exceeded by the existing noise a criterion of background +3dB(A) will be applied in the monitoring. The criterion of Leq50dB(A) can be used where background is below Leq50dB(A)1hour. Works are not expected to be carried out at night but if this is unavoidable for unexpected reasons separate measurements will also be taken before construction commences to establish if the Viet Nam criterion of Leq40dB(A)1-hour is exceeded and the monitoring assessment criteria will be established accordingly.

Page 36

119. Information such as recent rainfall will be documented as part of the baseline measurement. The sampling report will also specify if the sampling was undertaken during the rainy or dry season. Time and date of sampling, sources of dust and noise emissions during the sampling period, comparison of results to applicable standards shall also be included in the report. Actual location of the sampling stations shall be described in the report and plotted on a map together with GPS readings. The noise and TSP baseline monitoring will be reported by PCC at the end of the detailed design period, either in the detailed design report or in a dedicated baseline monitoring report before the bidding documents are completed. b. Water quality 120. Baseline data on surface water quality shall be collected by PCC. Sampling points shall be established in at least three major river crossings were bridge repairs and replacement will be undertaken as well as on river/stream sections close to construction camps (i.e., rivers that will most likely receive run-off/discharge from construction/workers’ camps). Baseline sampling shall be conducted at least two weeks before civil works contractors are deployed. Parameters will include pH, temperature, turbidity, dissolved oxygen (DO), oil and grease, and total suspended solids (TSS). For rivers/streams close to construction/workers’ camps, the following additional parameters shall also be analyzed: biological oxygen demand – 5 days (BOD5), coliform and fecal coliform. Sampling and analytical methodology shall be consistent with QCVN 08:2008/BTNMT (Viet Nam National Regulation for Surface Water Quality). 121. PCC shall collect water samples 20 m before (upstream) and 20 m after (downstream) the bridges at mid-width and mid-depth at each of the river crossings along the road alignment to establish a reference baseline. An industry standard multi- parameter water quality meter could be used for pH, DO, turbidity and temperature. 122. Information on weather conditions during sampling, recent rainfall, etc. will be documented as part of the baseline measurement. The sampling report will also specify if the sampling was undertaken during the rainy or dry season. Time and date of sampling, potential sources of contaminants/pollutants during the sampling period, comparison of results to applicable standards shall also be included in the report. Actual location of the sampling stations shall be described in the report and plotted on a map together with GPS readings. The water quality baseline monitoring will be reported by PCC at the end of the detailed design period, either in the detailed design report or in a dedicated baseline monitoring report before the bidding documents are completed.

Table V.1 –Maximum allowable concentration of pollutants in surface water. Permissible Limit No. Parameter Unit A B A1 A2 B1 B2 1 pH 6-8.5 6-8.5 5.5-9 5.5-9 2 Dissolved Oxygen (DO) mg/l ≥ 6 ≥ 5 ≥ 4 ≥ 2 3 Total Suspended Solids (TSS) mg/l 20 30 50 100 4 Oil & grease mg/l 0.01 0.02 0.1 0.3 5 BOD5 mg/l 4 6 15 25 6 Coliform MPN/ 100ml 2500 5000 7500 10000 7 Fecal coliform MPN/100ml - - - - Source: QCVN 08:2008/BTNMT Note: A1: Water source for domestic use and other purposes. A2: Water source for domestic use with appropriate treatment technology; for aquatic organism conservation and other purposes. B1: Water source for Irrigation or other similar purposes. B2: Water source for waterway transport and other purpose of low quality water uses. Parameters 1 to 4: to be analyzed for all river/stream samples Parameters 5 to 7: to be analyzed only for samples from river and stream sections which are likely to receive/or will receive run-off/discharge from construction/workers’ camps

Page 37

123. For rivers that do not mix well, and/or are highly polluted such that it is likely that there will be different DO and TSS values at river bottom than at mid depth, samples shall be collected near river bottom. 124. Information such as recent rainfall will be documented as part of the baseline measurement. The sampling report will also specify if the sampling was undertaken during the rainy or dry season. Potential sources of pollution shall also be included in the report. 125. The (Table V.2) below shows the QCVN standards that will be used for the Project.

Table V.2 – QCVN/TCVN Standards applicable to the project. Subject Standard Comment

TCVN 5949: 1998 (Noise in Public and Residential Areas– Leq50dB(A) 1hour schools hospitals Noise Allowable Noise Levels) Leq60dB(A) 1hour residential Baseline +3dB(A) Use if TCVN is exceeded by baseline QCVN 05:2009/BTNMT (Viet Nam Ambient Air Quality Air Quality Standard) QCVN 08:2008/BTNMT (Viet Nam National Regulation for Water Quality Surface Water Quality) Labour Code of Viet Nam, Decree 06/CP 1995, Decree / 202 Safety ND-CP OP 2002 and Circular 13/ BYT 24 Oct 1996. Source: MONRE Website

8. Enhancements 126. Environmental enhancements have not been a major consideration in the assessment of earlier projects. However it is noted that it has been common practice in many paces to plant trees along highways to provide visual interest in line with best international practice for highway design. Locations to create some local soft landscaping where successful planting of trees and shrubs could be accomplished and should be investigated at the detailed design stage. This practice should be in addition to tree replacement and be encouraged as far as practicable and to foster good will with the local community. It is also possible that the cross drainage and culverts may be modified to assist in the collection of surface water for irrigation purposes. Other opportunities for enhancements can be assessed prior to construction and proposed enhancements should be discussed with the local population to identify stewardship of any planting and also to serve as a vehicle for further public consultation at the implementation stage and to assist in public relations.

9. Measures to ensure protection of Don Van Karst Plateau Geopark (DVKPG) 127. The chairman of Dong Van Karst Plateau Geopark Management Board indicated that they did not have any in principle objection to the Project road and the widening of the road was not a concern to DVKPGMB because the roads works were modest and the road has been in place for many years before the DVKPG was declared. 128. However the DVKPG is potentially sensitive to environmental change as a result of the Project road stretch TL176A. DVKPG is recognized by UNESCO and the DVKPGMB must be notified about the project in advance in due course. DVKPGMB do not envisage any difficulties in obtaining UNECO concurrence for the Project road but it will be necessary to compile a report for UNESCO in advance. Hence DVKPGMB must be informed and consulted as soon as possible in the detailed design phase so that the requisite report can be compiled for UNESCO. Therefore the following mitigation measures are included in the EMP. i. Contact and liaise with Dong Van Karst Plateau Geopark Management Board and all relevant local authorities, district and commune PPCs.

Page 38

ii. Work with DVKPGMB and relevant local authorities, to provide sufficient information for DVKPGMB to prepare the necessary reports to DVKPGMB’s national and international collaborators and supporting organizations. iii. Ensure that there is sufficient time to compile report and inform collaborators (e.g. UNESCO) prior to bidding. iv. Commence bidding only after receipt of concurrence from collaborators including UNESCO. v. Any additional requirements or mitigation measures shall be implemented and operational before start of construction of on the relevant Project road 176A.

B Construction Phase 129. The source of the construction impacts from Project roads will include (i) excavation and reconstruction of the embankments, (ii) reconstruction of the single carriageway pavement (5.5 m wide) plus hard shoulders; (iii) construction, repair and reconstruction of bridges (iv) ensuring road drainage and access near villages and at other key areas is unimpaired by extension of numerous culverts; and (vi) installing slope stabilization and bioengineering measures, landscaping and accessories. In the hilly areas there will also be some slope cutting which will give rise to significant amounts of spoil for disposal. In this IEE project construction supervision is assumed to be carried out by PPMU.

1. Activate SEMPs and obtain permits and licenses. 130. The PCC will be engaged by JCC to assist PPMU in line with ADB policy on environmentally responsible procurement. The PCC will train and supervise the contractors to carry forward the environmental mitigation measures and enhancements identified in the detailed designs. The PCC will prepare SEMPs at the design stage. The benchmark for monitoring and reporting on the contractor’s environmental performance are the Project EMP (Table VIII.2 of the IEE), SEMPs,and any additional mitigation measures that may be required during construction phase. PPMU shall ensure that contractors and their suppliers comply with all statutory requirements for permits from DONRE with regard to use of mechanical equipment, establishment and operation of construction plants such as asphalt plant, concrete batching plant, rock crusher, spoils disposal, etc.

2. Orientation of contractor 131. PCC shall orient the workers on implementation of construction mitigation measures in the Project EMP, SEMPs and any additional mitigation measures that may be required during construction phase.

3. Loss of trees and impacts to fauna 132. The tree-cutting and replanting plan (TRP) designed by the PCC will be prepared with the designs and before vegetation clearing is undertaken. Cut slopes will be designed not to undercut or destabilize adjacent tree lined slopes and clearing of trees will be minimized in SEMP. The local forestry authority will be informed and will approve cutting and replacement of cut of trees based on the TRP. The PCC and PSC will ensure that contractors follow the TRP and local forest authorities may monitor marking of vegetation that will be removed under its jurisdiction. The TRP will be agreed with forest authority prior to commencement of construction. The PSC and PCC will supervise and monitor to check that the contractors do not remove any trees not covered by the TRP prior to commencement or during construction unless agreed with the PSC, PCC, PPMU and forest authority. 133. The PSC and PCC will supervise and monitor to check that the contractors to carry forward the mitigation measures and environmental enhancements identified in the

Page 39

SEMP as well as routine matters such as avoiding unnecessary removing of trees and compensatory and enhancement planting. 134. The PSc and PCC will supervise and monitor a ban on use of forest timber and Workers shall be prohibited from cutting trees for firewood. 135. Invasive species shall not be introduced. During replanting/revegetation works, new alien plant species (i.e., species not currently established in the region of the project) shall not be used unless carried out with the existing regulatory framework for such introduction. All replanting and compensatory planting will be planned in full agreement with the local forest authority. 136. The contractors will not use or permit the use of wood as a fuel for the execution of any part of the Works, including but not limited to the heating of bitumen and bitumen mixtures, and to the extent practicable shall ensure that fuels other than wood are used for cooking, and water heating in all his camps and living accommodations. The contractors shall not buy or use wood from the illegal sources (that come from the illegal logging). No construction camps, asphalt mixing plants, material storage sites are to be located in the forest areas. The contractors will take all precautions necessary to ensure that damage to vegetation is avoided due to fires resulting from execution of the works. The Contractor will immediately suppress the fire, if it occurs, and shall undertake replanting to replace damaged vegetation. 137. The PPMU, PSC and PCC will supervise and monitor a ban on use of forest timber that will be included in the SEMP and workers shall be prohibited from cutting trees for firewood. The TRP will include as a minimum consideration of: i) Identification of trees to be cut and locations ii) Ban on use of timber for fuel and ban taking of cycads and orchids from forests. iii) Justification for tree cutting as and alternative to road realignment. iv) Permissions from land owners, authorities and permits from PFPD for cutting. v) Methods for marking, protection of uncut cut trees and limitations to cutting. vi) Methods and timing for safe cutting to minimize interference with normal traffic. vii) Methods to remove trees cut timber and avoid stockpiling cut brushwood on site. viii) Methods to avoid under cutting adjacent tree lined slopes. ix) Programme for cutting trees and enhancement planting. x) Compensatory tree planting programme agreed with authorities & PFPD. xi) Discussion of the PSC, PCC/PPMU inspection/monitoring role. xii) Agreement on publicity/public consultation requirements.

4. Drainage and hydrology 138. The drainage system, irrigation and water resources on surrounding lands will be affected by construction activities as follows: a) local water supplies will need to be tapped to meet campsite and construction requirements, so bringing project based water use into competition with local use; b) surface and subsurface water resources near the selected Project road sections could be contaminated by fuel and chemical spills, or by solid waste and effluents generated by the kitchens and toilets at construction campsites; c) irrigation channels cross the works areas and require reprovisioning, (d) natural streams may become silted by borrow material (earth) in the runoff from the construction area, workshops and equipment washing-yards. The contractors will be required to implement the provisions of the Drainage Management Plan and to provide drainage facilities to avoid ponding/flooding within the Project site, construction camps, borrow/quarry areas, other areas used for project-related activities and adjacent areas. Potential impacts on water quality are already identified in the subsequent sections (e.g., under hazardous materials and hazardous waste disposal, water quality, etc.). 139. In areas close to the sensitive receiver (SR), the contractors will provide appropriate drains so that the outfalls of the surface run-off from the carriageway are diverted away

Page 40

from the SR. Measures will also be taken by the contractors during the construction phase to ensure that storm drains and road drainage systems are regularly cleared to maintain storm water flow.

5. Utilities and reprovisioning 140. Local water supplies, electrical power supply, telecommunications and irrigation water supply must be maintained during the works. Therefore the need to reprovide for power supply cables, telecommunication cables, irrigation or other water supplies needs to be reassessed and reconfirmed by the contractors well before works commence. Therefore the contractors will: i) Discuss with PCC and PPMU and update Utilities and Irrigation Facilities Reprovisioning Plan ii) Reconfirm railway, power, water supply, telecommunications and irrigation systems likely to be interrupted by the works and trees to be cut. iii) Contact all relevant local authorities for utilities and local village groups to plan reprovisoning of power, water supply, telecommunications and irrigation systems. iv) Relocate and reconnect utilities well ahead of commencement of construction works and coordinate with the relevant utility company at the provincial and district levels for relocation and reconnection well before works commence and include for compensatory planting for trees. v) Inform affected communities well in advance. vi) Arrange reconnection of utilities and irrigation channels in the shortest practicable time before construction commences. vii) If utilities are accidentally damaged during construction it shall be reported to the PSC, PCC and utility authority and repairs arranged immediately at the contractor’s expense.

6. Materials exploitation and management of quarry and borrow areas 141. In the detailed design stage the PCC will produce a Materials Management Plan (MMP) for implementation by the contractors. The plan must have a provision that no quarry sites and borrow areas within the Dong Van Karst Plateau Geopark shall be established and/or used for the Project unless: a) prior approval is obtained from DVKPGMB and UNESCO, and b) such activities will not cause negative impacts on the protected geological resources and landscape within DVKPG.The MMP will seek, as far as is reasonably practicable, to minimize the use of non-renewable resources and rock based materials and also to balance cut and fill requirements and contribute to the minimization of impacts due to extraction of rock based materials. As a first priority, where surplus materials arise from the removal of the existing surfaces these will be used elsewhere on the project for fill (if suitable) before additional rock, gravel or sand extraction is considered. The TA team has estimated that less than 10% may be reusable. 142. The MMP will include as a minimum consideration of the following: i) Required materials, potential sources and estimated quantities available. ii) Impacts to identified sources and availability. iii) Excavated slope material for reuse and recycling methods to be employed. iv) Endorsement from DONRE and local groups for use of sources. v) Methods of transportation to minimize interference with normal traffic. vi) Constraints of regular delivery schedule to reduce stockpiling on site. vii) Programme for reuse of slope excavated material for reuse viii) Programme for delivery of quarry and borrow materials. ix) Discussion of the PSC, PCC/PMU inspection/monitoring role. x) Agreement on publicity/public consultation requirements. 143. The contractors will be responsible to:

Page 41

i) Balance cut and fill requirements to minimize impacts from extraction of aggregates. ii) Ensure that no quarry sites and borrow areas within the Dong Van Karst Plateau Geopark are established and/or used for the Project unless: a) prior approval is obtained from DVKPGMB and UNESCO, and b) such activitites will not cause negative impacts on the protected geological resources and landscape within DVKPG. iii) Prioritize use of existing quarry sites with suitable materials and update the list of quarries and borrow pits monthly in MMP and report to PPMU and minimize impacts on other local resources. iv) Procure materials only from DONRE authorized quarries and borrow sites. v) If the contractors shall operate the quarry site, required environmental permits shall be secured prior to operation of quarry/borrow areas. vi) Borrow/quarry sites shall not be located in productive land and forested areas. vii) Follow compensatory planting plan if trees have to be removed. viii) Stockpile topsoil for later use and fence and re-contour borrow pits after use ix) Topsoil, overburden, and low-quality materials shall be properly removed, stockpiled near the site, and preserved for rehabilitation. x) Use quarry with highest ratio between extractive capacity (both in terms of quality) and loss of natural state. xi) Use quarry sites lying close to the alignment, with a high level of accessibility and with a low hill gradient; xii) Do not use quarries in areas of natural woodland or near rivers which provide food and shelters for birds and other animals. xiii) Damaged access roads agricultural land and other properties due to transport of quarry/borrow materials, other construction materials and due to various project-related activities shall be reinstated upon completion of construction works at each section. xiv) During quarry/borrow site operation, provide adequate drainage to avoid accumulation of stagnant water. xv) It is preferable to avoid or reduce the sections of quarry sites located on river bed. If it is not possible to locate quarries out of river beds, quarry sites lying on small rivers and streams shall be avoided. xvi) Alluvial terraces or alluvial deposits which lie on the river beds but not covered by water in normal hydrological conditions, shall be preferred; xvii) In quarries in the mountainous or hilly areas, or wherever slopes are important, cut terraces after extraction and implement a drainage system and vegetation cover for rehabilitation. xviii) Upon completion of extraction activities, quarry and borrow pits shall be dewatered and fences shall be installed, as appropriate, to minimize health and safety risks. xix) Ensure borrow pits are left in a tidy state with stable side slopes and proper drainage in order to avoid creation of water bodies favorable for mosquito breeding xx) To avoid drowning when pits become water-filled, measures such as fencing, providing flotation devices such as a buoy tied to a rope, etc. shall be implemented.

7. Spoil Disposal 144. The works will require major cutting to upgrade Project roads. It is estimated by the TA team that about 353,258 m3 of soil and rock based materials must be cut. The

Page 42

requirement for filling materials is expected to be much less (about 161,289 m3) and the TA team estimated that less than 10% can be reused near the same area for filling. Therefore there will be a surplus of more that 300,000m3 of soil based materials for reuse as fill material or disposal as spoil elsewhere. Therefore there will be a significant surplus of rock and soil based materials as spoil and if disposal is not planned in advance there will be significant impacts and environmental degradation due to the improper disposal of these materials. 145. In some locations the use of this immediately available material will reduce the need for additional extraction of rock based materials. The surplus material should be graded and the suitable cut materials directed for reuse as far as possible on Project roads and subsequently on other roads and other local infrastructure projects. This will reduce the need to extract other rock and gravel resources from vulnerable hillsides and river beds. The surplus can then be stockpiled at locations agreed with local authorities for use on other local district projects or other nationally planned infrastructure. 146. The surplus rock and soil based materials for disposal must be controlled to avoid potential impacts due improper disposal. A waste management and spoil disposal plan (WMSDP) will be required to ensure waste from Project road upgrading is managed properly and to reduce, reuse and recycle waste wherever possible. Contractors will initially review the PCC’s options for stockpiling and disposal locations for cut surface materials and reconfirm or propose alternative disposal locations for agreement with PPMU and local authorities. The WMSDP will cover all aspects of construction waste disposal. It is preferred that government land is used for dumping of material. If private land is to be used for the purpose of dumping it shall commence only after written permission from the land owner is checked and recorded by the PPMU and PCC and agreeable to DONRE. 147. Mitigation measures will seek to control the impacts at source in the first place. The PPMU assisted by the PCC will be responsible to report the update of the cut and fill estimates in conjunction with asphalt and aggregate materials planning (MMP) between the different areas and advise on overall balancing for cut and fill materials to minimize impacts on local resources. (Mitigation measures for cut slopes are covered under erosion control). 148. The Spoil Disposal section of the WMSDP will include consideration of the following i) Disposal of excavation spoils within DVKPG will not be undertaken unless: a) prior approval is obtained from DVKPGMB and UNESCO, b) disposal of excavation spoils will not cause negative visual impacts, and c) will not adversely affect the protected geological resources within DVKPG. ii) Locations and quantities of spoil arising. iii) Agreed locations for disposal / endorsement from DONRE and local groups. iv) Methods of transportation to minimize interference with normal traffic. v) Establishment of acceptable working hours and constraints. vi) Agreement on time scale and programme for disposal and chain of custody. vii) Programming issues including the time of year and available resources. viii) Details of a trip ticket system to ensure that contractors dispose excavation spoils in approved areas. Such system will be designed so that the PSC and PCC could readily monitor the volume and disposal site of excavation spoils, and to ensure that the total volume of spoils disposed will not exceed the maximum capacity of disposal sites approved by local authorities. ix) Discussion of the PSC, PCC/PMU inspection/monitoring role. x) Establishment of complaints management system for duration of the works xi) Agreement on publicity/public consultation requirements (advance signing etc.). 149. Mitigation measures will seek to prevent slope collapse impacts and control the impacts at source in the first place. The PPMU assisted by the PSC and PCC will be responsible to monitor the progress of cutting slopes and the implementation of

Page 43

mitigation measures, to minimize impacts. The mitigation measures in the Spoil Disposal section of the WMSDP will include but not necessarily be limited to: (i) Disposal of excavation spoils within DVKPG will not be undertaken unless: a) prior approval is obtained from DVKPGMB and UNESCO, b) disposal of excavation spoils will not cause negative visual impacts, and c) will not adversely affect the protected geological resources within DVKPG. (ii) Spoil will not be disposed of in rivers and streams or other natural drainage path. (iii) Spoil will not be disposed of on fragile slopes, flood ways, wetland, farmland, forest, religious or other culturally sensitive areas or areas where a livelihood is derived. (iv) Surplus spoil will be used where practicable for local repair works to fill eroded gullies and depression areas and degraded land in consultation with local community. (v) Spoils shall only be disposed to areas approved by local authority. (vi) Spoil disposal will be monitored by PSC, PCC/PPMU and recorded using a written chain of custody (trip-ticket) system to the designated disposal sites. (vii) Spoil will be to disposed of to disused quarries and abandoned borrow pits where practicable. (viii) Disposed spoil will be spread in 15 cm layers and compacted to optimum moisture content, covered with topsoil, landscaped and provided with drainage and vegetation to prevent erosion in line with best practice. (ix) Spoil disposal shall not cause sedimentation and obstruction of flow of watercourses, damage to agricultural land and densely vegetated areas. (x) Under no circumstances will spoils be dumped into watercourses (rivers, streams, drainage, irrigation canals, etc.) (xi) The spoils disposal site shall be located at least 50 m from surface water courses and shall be protected from erosion by avoiding formation of steep slopes and grassing.

8. General Construction Waste Management 150. Uncontrolled waste disposal operations can cause significant impacts. Mitigation measures will seek to reduce, recycle and reuse waste as far as practicable. The PPMU assisted by the PCC will be responsible to monitor the contractor’s progress of implementing the provision of the WMSDP and mitigation measures specified in the Project EMP. 151. The General Waste section of the WMSDP will include consideration of all matters related to solid and liquid waste disposal including the following: i) Wastes will not be disposed within DVKPG. ii) Expected types of waste and quantities of waste arising. iii) Waste reduction, reuse and recycling methods to be employed iv) Agreed reuse and recycling options and locations for disposal / endorsement from DONRE and local groups. v) Methods for treatment and disposal of all solid and liquid wastes. vi) Methods of transportation to minimize interference with normal traffic. vii) Establishment of regular disposal schedule and constraints for hazardous waste. viii) Programme for disposal of general waste / chain of custody for hazardous waste. ix) Discussion of the PSC, PCC/PMU inspection/monitoring role. x) Establishment of complaints management system for duration of the works xi) Agreement on publicity/public consultation requirements (advance signing etc.). 152. The Contractors mitigation measures in the General Waste section of the Spoils WMSDP will include but not necessarily be limited to the measures listed below. The contractors shall ensure implementation of these measures.

Page 44

i) Disposal of wastes will not be undertaken within the Dong Van Karst Plateau Geopark . ii) Areas for disposal to be agreed with local authorities and checked and recorded and monitored by the PSC, PCC/PPMU. iii) Segregation of wastes shall be observed. Cleared foliage, shrubs and grasses may be given to local farmers for fodder and fuel. Organic (biodegradables) shall be collected and disposed of on site by composting (no burning on site). iv) Recyclables shall be recovered and sold to recyclers. v) Residual and hazardous wastes shall be disposed of in disposal sites approved by local authorities. vi) Construction/workers’ camps shall be provided with garbage bins. vii) Burning of construction and domestic wastes shall be prohibited. viii) Disposal of solid wastes into canals, rivers, other watercourses, agricultural field and public areas shall be prohibited. ix) There will be no site-specific landfills established by the contractors. All solid waste will be collected and removed from the work camps and disposed in local waste disposal sites. x) Waste disposal areas approved by local authorities shall be rehabilitated, monitored, catalogued, and marked.

9. Hazardous materials and hazardous waste disposal 153. Use of hazardous substances such as oils and lubricants can cause significant impacts if uncontrolled or if waste is not disposed correctly. Mitigation measures will seek to control access to and the use of hazardous substances such as oils and lubricants and control waste disposal. The PPMU assisted by the PSC and PCC will be responsible to monitor the contractor’s progress of implementing the WMSDP to avoid or minimize impacts from use of hazardous substances such as oils and lubricants. 154. The Contractors mitigation measures in the Hazardous Waste section of the Spoil and Waste Management Plan of the SEMP will include but not necessarily be limited to the following measures. The contractors shall ensure implementation of such measures. i) Ensure that safe storage of fuel, other hazardous substances and bulk materials are agreed by PPMU/PCC and PSC and have necessary approval/permit from DONRE and local authorities. ii) Hydrocarbon, toxic material and explosives will be stored in adequately protected sites consistent with national and local regulations to prevent soil and water contamination. iii) Equipment/vehicle maintenance and refueling areas will be confined to areas in construction sites designed to contain spilled lubricants and fuels. Such areas shall be provided with drainage leading to an oil-water separator that will be regularly skimmed of oil and maintained to ensure efficiency. iv) Fuel and other hazardous substances shall be stored in areas provided with roof, impervious flooring and bund/containment wall to protect these from the elements and to readily contain spilled fuel/lubricant. v) Segregate hazardous wastes (oily wastes, used batteries, fuel drums) and ensure that storage, transport and disposal shall not cause pollution and shall be undertaken consistent with national and local regulations. vi) Ensure all storage containers are in good condition with proper labeling. vii) Regularly check containers for leakage and undertake necessary repair or replacement. viii) Store hazardous materials above flood level. ix) Discharge of oil contaminated water shall be prohibited. x) Used oil and other toxic and hazardous materials shall be disposed of in an authorized facility off-site.

Page 45

xi) Adequate precautions will be taken to prevent oil/lubricant/ hydrocarbon contamination of channel beds. xii) Ensure availability of spill clean up materials (e.g., absorbent pads, etc.) specifically designed for petroleum products and other hazardous substances where such materials are being stored. xiii) Spillage, if any, will be immediately cleared with utmost caution to leave no traces. xiv) Spillage waste will be disposed at disposal sites approved by local authorities and approved by PSC/PPMU. xv) All areas intended for storage of hazardous materials will be quarantined and provided with adequate facilities to combat emergency situations complying with all the applicable statutory stipulation. xvi) The contractors shall identify named personnel in the management plan/SEMP in-charge of storage sites for hazardous materials and ensure they are properly trained to control access to these areas and entry will be allowed only under authorization.

10. Asphalt, hot mix plant, rock crushing and bitumen supply 155. The rock crushing activities will generate noise and dust and pavement works will generate gas and odor from the asphalt hot-mix plant and noise from the compaction of the pavement. Upgrading Project roads will require more than 160,000 m3 of rock based material and about more than 2,000 tons of asphalt. Although the emissions from powered mechanical equipment that supply crushed rock and bitumen will be rapidly dispersed in the open terrain they will need to be sited carefully to avoid complaints. The works for the pavement in any section of the road are estimated by the TA Team to take only 1 to 2 weeks depending on the terrain and therefore emissions from mobile powered mechanical equipment for road surfacing will be short lived. 156. In order to maintain the existing air quality of the project area in a condition acceptable to the local population compliance with the following mitigation measures will be needed: (i) Cement batching and aggregate mixing plant shall be located as far as possible (preferably at least 500m) from settlements and habitation or as required by environmental regulations. (ii) All conditions of DONRE permits and local guidelines shall be observed. (iii) Dust suppression equipment shall be installed at cement and aggregate mix plants. (iv) Areas of construction on the roads as well as the haul road (especially where the works are within 50m of the SRs) shall be maintained damp by watering the construction area. (v) Where local roads are used for haulage they shall be kept in serviceable condition and any damage shall be repaired promptly without interference to local travel routes. (vi) Storage sites, mixing plants, and bitumen (hot mix) plants will be at least 500m downwind of the nearest human settlements or as otherwise required under DONRE permits and guidelines. (vii) All hot-mix plants, crushers, and batching plants will be located in agreement with the local town or municipality and installed on a sealed area only after receiving approval from the relevant local authority and DONRE. (viii) The above Project facilities (asphalt plant, crushing plant, etc.) will not be located within Dong Van Karst Plateau Geopark. 157. Due to the locations of the works fumes from bitumen and chemicals are likely to be well dissipated in the open terrain and the TCVN/QCVN standards should not be exceeded. However phenol compounds in the bitumen have a very low odor threshold and extremely low concentrations can cause nuisances. These are unlikely to

Page 46

accumulate to toxic levels but the plant for the supply of molten bitumen should be sighted as far away from sensitive receivers as is practicable. Asphalt plant and rock crusher activities (if required) will be controlled and hot-mix plants should not be located within 500m of any sensitive receiver, river bank or irrigation channel but located at convenient sites nearby but at least 500m (in the prevailing downwind direction) from sensitive receptors such as residences, schools, hospitals. 158. Bituminous materials will generally be applied using machines but if bituminous compounds are to be applied by hand labor methods and melted in heaters the fuel used shall be kerosene, diesel or gas fuel. Fuel wood shall not be used for heating bitumen; neither will bitumen be used as fuel. 159. Bitumen drums will be stored in a dedicated area, not scattered along the works and any small accidental spills of bitumen or chemicals will be cleaned up immediately. The waste including the top 2cm of any contaminated soil and disposed of as chemical waste to an approved landfill or approved local authority disposal site in line with the WMSDP. 160. It is possible that contamination of soil may occur from oils and chemicals at bitumen plant sites, workshop areas, equipment washing-yards and along the roads works. The contamination may limit the future use of land for agricultural purposes. 161. The following practices will be adopted to minimize the risk of soil contamination: i) The contractors will prevent soil contamination and will be required to instruct and train their workforce in the storage and handling of materials and chemicals that can potentially cause soil contamination. ii) Debris generated by the dismantling of existing pavement will be recycled subject to the suitability of the material. iii) Bitumen will not be allowed to enter either running or dry streambeds and nor will be disposed of in ditches or small unlined waste disposal sites prepared by the contractor. iv) Bitumen storage and mixing areas shall be protected against spills and all accidentally contaminated soil must be properly handled according to applicable national and local laws and regulations. As a minimum, these areas must be segregated, such that any spills can be immediately contained and cleaned up. v) Any petroleum products used in the preparation of the bitumen mixture must also be carefully managed to avoid spills and contamination of the local water table and streams. Bitumen and other hydrocarbon residues will be disposed of as hazardous waste. vi) All accidental spills of bitumen or chemicals will be cleaned up immediately with the top 2cm of any contaminated soil underneath and disposed of as chemical waste to a site approved by the local authority. vii) Solid waste generated during construction and at campsites will be properly treated and safely disposed of only in demarcated off-site waste disposal sites identified and agreed with PPMU and the local community and local authorities.

11. Noise and Dust 162. Earthworks and rock crushing activities will be the main sources of dust. The works in any given section of the road will generally be of short duration and in many locations there will be sufficient buffer distance between the work corridor and the existing SRs such that no significant impact is expected from the construction works on residential sensitive receivers in terms of noise, vibration, and dust. Also works will not take place at night except in special circumstances justifiable to the PSC and PPMU.

Page 47

163. However noise and dust were recognized as nuisances by the local population but were also considered acceptable nuisances in view of the likely short duration of the works and that there were good benefits from future improved road conditions. Nevertheless it is good practice to control all dusty materials at source so that nuisances do not occur and visibility on the adjacent road is not impaired and so that road safety can be maintained or improved. As a general approach it is recommended that if works are within 15m of any sensitive receivers, the contractor should install dust barrier segregation between the works at the road edge and the sensitive receivers. The segregation should be easily erectable 2.5m high and designed to retain dust and provide a temporary visual barrier to the works. The materials could be plastic or tarpaulin sheets or alternatively sections of the locally made close woven fences could be used (made by local artisans). Where dust is the major consideration the barrier can take the form of tarpaulins or fences strung between two poles mounted on a concrete base. These can be moved along the road as the work proceeds. The other mitigation measure will include: i) If the surface is dry water will be sprinkled on the road and exposed surfaces when work is carried out within 50m of residences or roadside food stalls. ii) No work will be carried out within 500m of any settlement during the night (2100hrs to 0700hrs). iii) If works have given rise to complaints over dust, the contractor shall investigate the cause, report it in the monthly progress reports and review and propose alternative mitigation measures before works recommence. iv) All heavy equipment and machinery shall be fited in full compliance with the national and local regulations (TCVN 5949 – 1998). v) Fuel-efficient and well-maintained haulage trucks will be employed to minimize exhaust emissions. Smoke belching vehicles and equipment shall not be allowed and shall be removed from the project. vi) Vehicles transporting soil, sand and other construction materials will be covered with tarpaulin sheets to avoid impact from dust. Speed limits of such vehicles within the works site and on unpaved edge areas of the Project roads will be established and agreed with the PSC. 164. The need for large stockpiles should be minimized by careful planning of the supply of materials from controlled sources. Stockpiles should not be located within 100m of schools, hospitals or other public amenities such as wells and pumps and should be covered with tarpaulins when not in use and at the end of the working day to enclose dust. If large stockpiles (more than 25 m3) of crushed materials are necessary they should be enclosed with side barriers and also covered when not in use. 165. Schools are particularly vulnerable to construction impacts and the scheduling of works near schools should be scheduled after discussions with the school principals to avoid impacts. In addition, as a general approach it is recommended that if works are within 15 m of schools school façade the contractor should install dust barrier segregation between the works and the school façade. The segregation should be easily erectable 2.5 m high and designed to retain dust and provide a temporary visual barrier to the works. In addition, it is recommended that where the schools request, close-fitting dust barrier segregation shall be provided to cover school windows and doors during the works. 166. PCC shall undertake semi-annual monitoring of TSP and noise at the stations which were sampled during pre-construction phase. Field measurements shall also be carried out, as necessary, to validate complaints.

Page 48

12. Blasting and vibration 167. At this stage the specific requirement for blasting is not known. It is clear from discussions with the project team and observations that blasting will not be the method of choice because most of the surface materials can be removed with powered mechanical equipment (PME). It is therefore anticipated that powered mechanical equipment and a lot of local labor with hand tool methods will be used to upgrade the Project roads. 168. In the event that blasting is required in special circumstances only controlled blasting will be allowed. Blasting will only be carried out in line with the rules set down by the local authorities and DONRE in the prescribed manner and after prior notice to all local residents and the local town authorities. One month prior to the blasting in any area, the contractors will undertake a condition survey including photographs will be made of all residences within 500 m of the blast sites. The condition of the residences shall be agreed with the PSC in case there are any future claims for damage to residences due to the blasting. All blasting shall be carried out in the daytime and at regular intervals after siren warnings. All residents within 500m of the blast sites shall be kept informed of the plans and progress of blasting and residents shall be temporarily evacuated and provided with alternative accommodation if required. 169. No blasting will be allowed at night. Controlled blasting will strictly follow the license requirements from DONRE and other authorities. Pre-splitting should be undertaken. Where the vibration from blasting is exceeding the maximum permissible level, information from the blasting should be used to modify blasting patterns and calculate a reduced charge for future blasts with the aim of eradicating damage and to minimize damage as far as possible. Blasting shall be under careful and strict management of properly trained and licensed personnel. The contractor shall observe proper warning and precautionary measures to ensure safety of residents, pedestrians, motorists and structures during blasting.

13. Erosion control and runoff 170. Engineering controls that include erosion protection measures will be designed and installed to control soil erosion both at all the constructed works and in peripheral areas, particularly in borrow areas and along haul tracks. The Erosion Control Plan (ECP) produced by the PCC and slope stabilization measures in the detailed designs will be implemented and maintained by the contractors during construction to protect the works. 171. The ECP will include consideration of the following: i) Climate and rainfall for the area and checking weather forecasts. ii) Terrain and typical locations susceptible to erosion and runoff. iii) Protection of the works and potential impacts to the environment. iv) Erosion control methods to be employed, locations and installation timing. v) Limits to stockpiling on sites near waterways and irrigation channels. vi) Discussion of the PSC, PCC/PPMU inspection/monitoring role. vii) Agreement on publicity/public consultation requirements. 172. Mitigation measures for cut slopes will be required by the contractors to prevent slope collapse. These will include but not necessarily be limited to: (i) Stockpile topsoil for immediate replanting after completion of work. (ii) Minimize damage and cutting of surrounding vegetation during slope formation. (iii) Protect the cut slope with planted vegetation, bioengineering or conventional civil engineering structures as soon as practicable after cutting. (iv) Prevent erosion and protect the cut slope with temporary or permanent drainage as soon as practicable after cutting.

Page 49

(v) If new erosion occurs accidentally, back fill immediately to restore original contours. 173. In order to preserve the constructed slopes and other works and embankments from soil erosion and runoff. i) Low embankments will be protected from erosion by seeding and planting indigenous grasses that can flourish under local conditions. ii) High embankments, i.e. 2m high and above, will be considered for protection by constructing stone pitching or a riprap across the embankment immediately after the works are completed. This practice will also be applied along cross-drainage structures where embankments are more susceptible to erosion by water runoff. iii) The contractors will also be required to include appropriate measures for slope protection, i.e. vegetation cover and stone pitching, as required in the detailed construction drawings and implement them accordingly. 174. Payments will be linked to the completion of the works as indicated by the installation of erosion control measures to protect the works to the satisfaction of PCC/PMU.

14. River protection and bridge repair 175. The Project proposes to replace or repair 204 culverts and 2 bridges. Careless construction and poor materials control can cause blockage to rivers and streams. Therefore in areas along and near rivers and streams the following will be carried out: i) Earth and stones will be properly disposed of so that they do not block rivers and streams, resulting in adverse impact on water quality and flow regime. ii) In bridge repair and demolition sites, the bridge structure will not be dropped into the river but alternative means will be used to avoid "dropping the bridge" into rivers/streams. This will be done by "sawing" appropriate sections of the bridge and using cranes to lift these sections away or alternatively by construction of a platform onto which the bridge could be lowered. iii) Cofferdams, silt fences, sediment barriers or other devices will be used as appropriate based on the design to prevent migration of silt during excavation and boring operations within streams. If cofferdams are used, these will be dewatered and cleaned to prevent siltation by pumping from cofferdams to a settling basin or a containment unit. iv) Other erosion control measures above and covering open surfaces with grasses and creepers to reduce runoff will be implemented as early as possible in construction.

15. Water Quality 176. In order to prevent water contamination the following precautionary measures will be undertaken by the contractors: i) Lubricants will be stored in dedicated enclosures with a sealed floor >50m from water bodies. ii) Solid waste from construction activities will not be thrown in rivers and shall be disposed of as per the WMP and there will be NO BURNING of waste. iii) Construction storage/stockpiles shall be provided with bunds to prevent silted run-off. iv) Stockpiled materials will be covered to reduce run-off. v) Stockpiling or borrow sites will not be allowed within 100m of water body. vi) If complaints occur there will be monitor and investigation of water quality. vii) Work in rivers will be scheduled during dry season and work duration shall be as short as possible.

Page 50

viii) Bare slopes shall be stabilized Immediately after works completed. ix) Stockpile areas and storage areas for hazardous substances shall be located away from water bodies. x) Washing of machinery and vehicles in surface waters shall be prohibited. 177. If complaints are received, the incidents and possible sources of water supply disruption will be investigated by the ESO in PPMU (assisted by the PCC) and where the complaint can be substantiated; water samples will be taken and analyzed based on the baseline monitoring results. In response to complaints to either the contractor or the local authorities the PCC and the PPMU will be immediately informed so that water quality measurements will be taken (by ESO assisted by PCC) 20 m before (upstream) and 20 m after (downstream) of the works giving rise to complaint in line with the methodology used in for baseline sampling. Samples will be taken as soon after the complaint as possible and analyzed immediately and again two weeks after the complaint to determine if water quality has been restored. Impacts will be determined by reference to the baseline results from the preconstruction stage. The criteria will be based on the QCVN 08 2008 BTNMT.

16. Water Resources 178. The availability of water for the works will need to be investigated by the PCC at the detailed design stage. A preliminary assessment of water availability should include consultation with the local authorities. In the event that sufficient water sources can be identified the local water resources could be used if sufficient yield is likely to be available. However local community water resources will not be used without the permission of the local authority. In the even that there is insufficient water available locally for the works the contractor must make alternative arrangements. 179. Measures to mitigate the adverse impact on water resources and surface drainage patterns have been incorporated into the other drainage mitigation measures. 180. The contractors will carry out the following measures to mitigate the impact of using local community water resources, and the impacts on rivers, where required: i) In all areas availability of water will be assessed to evaluate the impact on community resources. Project water will be brought in by tanker as necessary without depleting local village supplies. ii) Camps will be located at least 500m away from the nearest local settlement to prevent the contamination of community-owned water resources. iii) The contractors will be required to maintain close liaison with local communities to ensure that any potential conflicts related to common resource utilization for project purposes are resolved quickly. iv) Guidelines will be established to minimize the wastage of water during construction operations and at campsites. v) The use of river bed for construction materials will be avoided and minimized. vi) Confine winning river materials to 20% of river width in any location and keep away from river banks. vii) Reinstate river banks if necessary. viii) Re-provision irrigation channels affected by works two weeks before commencement of works to satisfaction of ESO in PPMU (assisted by PCC) and local community. ix) All irrigation canals along the alignment shall be clearly marked on the ground to prevent accidental dumping of fill materials into these canals; x) In case of obstruction or damage, irrigation ditches and ponds shall be cleaned or repaired immediately.

Page 51

17. Construction camps and canteen facilities 181. The contractors will adopt good management practices to ensure that fuels and chemicals, raw sewage, wastewater effluent, and construction debris/scarified material is disposed of in controlled conditions to reduce the risk of contamination. The proposed measures include: i) Worker camp location and facilities located at least 500m from settlements and agreed with local communities and facilities approved by PSC and PPMU and managed to minimize impacts. No project facilities (construction camps, workers’ camps, etc.) will be established within Dong Van Karst Plateau Geopark unless: a) prior approval is obtained from DVKPGMB and UNESCO, and b) such activities will not cause negative impacts on the protected geological resources and landscape within DVKPG. ii) Construction camp(s) will be established in areas with adequate drainage in order to prevent water logging at the camp and formation of breeding sites for mosquitoes in order to facilitate flow of the treated effluents. iii) Potable water, clean water for showers, hygienic sanitation facilities/toilets with sufficient water supply, worker canteen/rest area and first aid facilities will be provided. Separate toilets shall be provided for male and female workers. iv) Hire and train as many local workers as possible. v) Provide adequate housing for all workers at the construction camps and establish clean canteen/eating and cooking areas. vi) Portable lavatories (or at least pit latrines in remote areas) shall be installed and open defecation shall be prohibited and use of lavatories encouraged by cleaning lavatories daily and by keeping lavatory facilities clean at all times. vii) Wastewater effluent from contractors’ workshops and equipment washing- yards will be passed through gravel/sand beds and all oil/grease contaminants will be removed before discharging it into natural streams. Oil and grease residues shall be stored in drums awaiting disposal in line with the agreed WMSDP. viii) Predictable wastewater effluent discharges from construction works shall have the necessary permits from DONRE and local authorities before the works commence. ix) Borrow pits and natural depressions with pre-laid impervious liners will be used to dispose of scarified/scraped asphalt, and then covered with soil. This will check potential groundwater contamination. Options for completely or partially recycling scraped scarified materials will also be taken into account. x) As much as possible, food shall be provided from farms nearby or imported to the area. Bush meat supplies banned to discourage poaching. Solid and liquid waste managed in line with Waste Management Plan. xi) Use of guns and hunting equipment by workers will be banned and dismiss workers taking or using green timber or hunting or in possession of wildlife. xii) Camp site will be cleaned up to the satisfaction of and local community after use. xiii) All waste materials shall be removed and disposed to disposal sites approved by local authorities xiv) Land used for campsites shall be restored to the original condition as far as practicable and the area shall be planted with appropriate trees / shrubs as soon as practicable after it is vacated and cleaned.

18. Sanitation and Disease Vectors 182. Potential sanitation and impacts from disease will need to be controlled by maintaining hygienic conditions in the worker camps and implementing the social and health programmes for the Project. The contractor will ensure that:

Page 52

i) Measures to prevent malaria shall be implemented (e.g., provision of insecticide treated mosquito nets to workers, installation of proper drainage to avoid formation of stagnant water, etc.). ii) Standing water will not be allowed to accumulate in the temporary drainage facilities or along the roadside, to prevent proliferation of mosquitoes. iii) Temporary and permanent drainage facilities will be designed to facilitate the rapid removal of surface water from all areas and prevent the accumulation of surface water ponds. iv) Malaria controls and HIV-AIDS education will be implemented in line with social programmes and plans for the project. v) HIV/AIDS awareness and prevention program shall be implemented in line with social plans.

19. Safety Precautions for Workers 183. Worker occupational health and safety is generally governed by the Labour Code of Viet Nam, Decree 06/CP (20 Jan 1995), Decree / 202 ND-CP OP (27 Dec 2002) and Circular 13/ BYT 24 Oct 1996). A Worker and Public Safety Plan (WPSP) will be prepared by the PCC to establish routine safety measures as required by Labor Code of Viet Nam and by good engineering practice and will include provisions for first aid facilities. 184. Mitigation measures to be implemented by contractors to ensure health and safety of workers are as follows: (i) At least one month before construction commences the contractors will demonstrate to PPMU that the WPSP will be properly resourced and a qualified safety officer will be identified by the contractors in the bid. (ii) The contractors will conduct of training (assisted by PCC) for all workers on safety and environmental hygiene at no cost to the employees. The contractor will instruct workers in health and safety matters as required by law and by good engineering practice and provide first aid facilities. (iii) The contractors will instruct and induct all workers in health and safety matters (induction course) including construction camp rules and site agents/foremen will follow up with toolbox talks on a weekly basis. Workforce training for all workers starting on site will include safety and environmental hygiene. (iv) Fencing on all areas of excavation greater than 1m deep and sides of temporary works shall be observed. (v) Workers shall be provided with of appropriate personnel safety equipment such as safety boots, helmets, gloves, protective clothes, breathing mask, goggles, and ear protection at no cost to the workers. (vi) Ensure reversing signals are installed on all construction vehicles. 185. The contractors will implement the following measures for workers’ safety: i) Instruction and induction of all workers in health and safety matters, including railway safety as necessary. ii) Provision of potable water supply in all work locations. iii) Establishment of safety measures as required by law and by good engineering practice and provision of first aid facilities. iv) Fencing on all excavation, borrow pits and sides of temporary bridges. v) Providing to all workers appropriate personal protective equipment (PPE) such as safety shoes, hard hats, safety glasses, ear plugs, gloves, etc. vi) Scheduling of regular (e.g. weekly tool box talks) to orientate the workers on health and safety issues related to their activities as well as on proper use of PPE.

Page 53

vii) Where worker exposure to traffic cannot be completely eliminated, protective barriers shall be provided to shield workers from traffic vehicles. Another measure is to install channeling devices (e.g., traffic cones and barrels) to delineate the work zone. viii) Construction camps shall be provided with toilets/sanitation facilities in accordance with local regulations to prevent any hazard to public health or contamination of land, surface or groundwater. These facilities shall be well maintained and cleaned regularly to encourage use and allow effective operation. 186. Facilities for workers and public safety, construction site offices and canteen will be regulated in line with the Labor Code of Viet Nam. Complaints will be monitored and investigated and mitigation measures will be revised and the SEMP will be updated as necessary if unexpected impacts occur. All measures related to workers’ safety and health protection shall be free of charge to workers. The occupational health and safety plans to be submitted by the contractor before construction commences can be extended to cover public safety and approved by PPMU assisted by PCC.

20. Public Safety 187. Public safety, particularly of pedestrians and children can be threatened by the excavation of the trenches for side drain construction. Fencing will be installed prior to excavation work commencing on all sides of temporary excavations. The plans will include provisions for site security and guards, trench barriers and covers to other holes and any other safety measures as necessary. The contractor will provide warning signs at the periphery of the site warning the public not to enter and define this in the SEMP. The contractor will restrict the speed of project vehicles and also control traffic by contra- flow and provide flag men and warning signs at either end of the works where the traveling lanes must be temporarily reduced. The contractors will implement the following safety measures for the public: i) Barriers (e.g., temporary fence), shall be installed at construction areas to deter pedestrian access to the roadway except at designated crossing points. ii) The general public/local residents shall not be allowed in high-risk areas, e.g., excavation sites and areas where heavy equipment is in operation and these sites will have a watchman at the entrance to keep public out. iii) Speed restrictions shall be imposed on Project vehicles and equipment traveling within 50m of sensitive receptors (e.g. residential, schools, temples, etc.). iv) Upon completion of construction works, borrow areas will be backfilled or temporarily fenced, awaiting backfilling. v) Provisions for site security, trench barriers and covers to other holes and any other safety measures as necessary. vi) Provide warning signs at the periphery of the site warning the public not to enter and define this in the WPSP. vii) Strict imposition of speed limits along residential areas and where other sensitive receptors such as schools, hospitals, and other populated areas are located. viii) Educate drivers on safe driving practices to minimize accidents and to prevent spill of hazardous substances (fuel and oil) and other construction materials during transport. 188. The contractors will provide information boards near the work sites to inform and instruct the public on how to conduct themselves and to be aware of their surroundings if they must approach the works. The Public Safety section of the Worker and Public Safety Plan will include but not necessarily be limited to the following: i) Statement of contractor’s safety policy for Workers and Public. ii) Legal requirements (e.g. Labour Code of Viet Nam, Decree 06/CP 1995, Decree / 202 ND-CP OP 2002 and Circular 13/ BYT 24 Oct 1996).

Page 54

iii) Works safety issues and public safety issues. iv) Training the workforce and informing the public on works safety issues. v) Establishment and monitoring of acceptable working practices to protect safety. vi) Common concerns with traffic and road safety (e.g. traffic flow/delay requirements). vii) Discussion of the PSC, PCC/PMU inspection/monitoring role. viii) Establishment of complaints management system for duration of the works ix) Agreement on publicity/public consultation requirements. x) Reporting of accidents. xi) Complaints management.

21. Traffic Management 189. Construction activities on the Project road are likely to cause hindrance in traffic flow if not mitigated properly. A Temporary Traffic Management Plan (TTMP) will be developed by the PCC during detailed design phase and its provisions will be implemented by the contractors during construction phase. The main objectives of the plan shall be to maximize the safety of the workforce and the traveling public. The main secondary objective will be to keep traffic flowing as freely as possible. The TTMP will include consideration of the following: i) Lane availability and minimizing interference with traffic flows past the works site. ii) Establishment of acceptable working hours, constraints and public safety issues. iii) Agreement on time scale and establishment of traffic flow/delay requirements. iv) Programming issues including the time of year and available resources. v) Discussion of the PSC, PCC/PPMU inspection/monitoring role. vi) Establishment of complaints management system for duration of the works vii) Agreement on publicity/public consultation requirements (advance signing etc.). 190. The contractors shall implement the following mitigation measures: a. Implement provisions of the TTMP and awareness program for road and rail traffic. b. Communicate to the public through local officials regarding the scope and schedule of construction, as well as certain construction activities causing disruptions or access restrictions. c. Coordinate with local traffic authorities to implement appropriate traffic diversion schemes to avoid inconvenience due to project operations to road users, ensure smooth traffic flow and avoid or minimize accidents, traffic hold ups and congestion. d. In coordination with local traffic officials, schedule transport of materials to avoid congestion, set up clear traffic signal boards and traffic advisory signs at the roads going in and out the road and bridge construction sites to minimize traffic build-up. e. Provide safe vehicle and pedestrian access around construction areas. f. Installation of bold diversion signs that would be clearly visible even at night and provide flag persons to warn of dangerous conditions; 24hrs if necessary. g. Provide sufficient lighting at night within and in the vicinity of construction sites. h. Designation of traffic officers in construction sites.

22. Archaeological and cultural artifacts. 191. Viet Nam has a rich archaeological heritage although no major archaeological site has been identified within 100m of Project roads. Therefore the contractor will take the following precautions to avoid disturbance of any as yet undiscovered archaeologically valuable artifacts. i) Site agents will be instructed to keep a watching brief for relics in excavations.

Page 55

ii) Should any potential items be located, the PSC and ESO will immediately be contacted and work will be temporarily stopped in that area. iii) The ESO will inform the PSC and with the assistance of the PCC determine if that item is of potential significance. If it is so an officer from the Department of Culture and Information (DCI) will be invited to inspect the site and work will be stopped to allow time for inspection. iv) Until DCI has responded to this invitation work will not re-commence in this location until agreement has been reached between DCI, PSC and PPMU/PCC as to any required mitigation measures, which may include structured excavation.

23. Enhancements 192. Environmental enhancements such as tree planting near the road will be explored in the detailed designs and included in the Tree-cutting and Replanting Plan. Enhancements shall be re-assessed prior to construction and proposed enhancements should be discussed by the contractors with the local population to identify stewardship of any planting and also to serve as a vehicle for further public consultation at the implementation stage and to assist in public relations. Environmental enhancements introduced in the detailed designs may include tree planting. The panted specimens should be maintained and monitored for three years after planting to ensure their survival in line with the Tree-cutting and Replanting Plan

C Operational Phase 193. During the operational phase of the Project the Provincial Department of Transport (PDOT) will maintain the roads. 194. The improvement of the hard shoulders on road the Project roads and the improvement of the asphalt surfaced roads can be expected to reduce road traffic noise and air pollution from dust. The improvement of the Project roads road will be within the existing corridor keeping vehicles away from sensitive receivers and at this stage it is difficult to see that any residences or commercial premises or schools will still be close enough to the the Project roads road to be affected by noise and dust so as to exceed the assessment criteria.

1. Noise 195. The Viet Nam the ambient noise standard (TCVN 5949-1998) is Leq60dB(A) for residential sensitive receivers and World Bank criterion is (Leq55dB(A) for residential. school and hospital sensitive receivers. The TCVN criterion is more than 8dB(A) above the existing measured noise levels outside the towns. The main noise source in most areas is traffic nose and in order for the existing background to be exceeded by +8dB(A) the existing traffic would have to be more than quadrupled. Traffic forecasts indicate that traffic is not expected to quadruple for at least twenty years. Therefore the project is believed to be sustainable in terms of road traffic noise. No operational mitigation measures are required.

2. Gaseous Emissions 196. Vehicle emissions (gaseous) as indicated concentration of oxides of nitrogen will be the main air pollution sources during operation. There will be few other sources of emissions near the the Project roads road other than from domestic fuel burning. Sensitive receivers are set far enough back from the the Project roads road to allow adequate dispersion that there will be no significant impacts at the sensitive receivers.

3. Particulate Emissions 197. Vehicle emissions (particulate contamination) such as dust and fumes will also be air pollution sources during operation however toxic residues from vehicle emissions

Page 56

near the the Project roads road are unlikely to accumulate or create significant impacts under the local conditions. Dust from the existing road will be reduced due to the better asphalt surface for the new road. Therefore the project is believed to be sustainable in terms of gaseous and particulate emissions and no operational mitigation measures are required.

4. Soil Erosion 198. Soil erosion will be prevented by developing a comprehensive suite of engineering controls in the detailed designs to prevent and maintain erosion. A system will be devised and engineered to control erosion and flooding on either side of the embankments in case of heavy rains. Apart from affecting the community lands and resources, this would otherwise cause natural streams and irrigation channels to become silted. 199. Measures will also be taken during the operational phase to ensure that storm drains and highway drainage systems are periodically cleared to maintain clear drainage to allow rapid dispersal of storm water flow. An adequate system of monitoring, reporting and maintenance will be developed.

5. Driving Conditions and Community Safety 200. The rehabilitation and widening of the the Project roads road is likely to increase the vehicle speed on the road. Increases in traffic flow indicate additional future traffic should be moderate and unlikely to create many community safety issues. Overall the condition of the road facilities will be enhanced and driving conditions should improve. Routine safety measures, signage and road markings should be introduced to reduce driving risk further in accident prone areas and provide enhancements to driving conditions.

6. Tree planting 201. . Environmental enhancements introduced in the detailed designs may include tree planting, as necessary. The panted specimens should be maintained and monitored for three years after planting to ensure their survival in line with the Tree-cutting and Replanting Plan

7. Water Resources 202. Complaints about the contractors’ works will be resolved in the construction phase. The scale of the works indicates that there are unlikely to be any impacts that continue into the operational phase.

D Cumulative Environmental Impact Associated with the Project Locations 203. There should be no significant adverse cumulative impacts expected from the roads in TCNMP. Overall the improvement in the road system and Viet Nam will potentially lead to growing traffic, commercial activities, that may indirectly lead to additional pollution. It is not possible to quantify these impacts at this stage. However the TCNMP will be carried out on existing roads and there is not likely to be any significant change to the current pattern of movements caused by road upgrading that could potentially lead to uncontrolled access for exploitation of minerals or forest resources. The statutory provisions under the laws of Viet Nam cover pollution control, the forestry protection acts cover exploitation of forest products and there are also laws to protect wildlife in both countries. These laws are established but institutional strengthening is required and improvements in resources are needed to achieve better enforcement to support strategic management of pollution control and resource exploitation in the long term. 204. The Project roads are a part of an already well developed network and although the TCNMP will increase traffic gradually there will be other benefits in improved traveling conditions and vehicle cost savings that will off set the traffic impacts.

Page 57

VI. INFORMATION DISCLOSURE, CONSULTATION AND PARTICIPATION

205. The objectives of the stakeholder consultation process was to disseminate information on the project and its expected impact, long-term as well as short-term, among primary and secondary stakeholders, and to gather information on relevant issues so that the feedback received could be used to address these issues at early stages of project design. Another important objective was to determine the extent of the concerns amongst the community, to address these in the project implementation and to suggest appropriate mitigation measures.

A Identification of Stakeholders 206. Stakeholders are people, groups, or institutions that may be affected by, can significantly influence, or are important to the achievement of the stated purpose of a proposed intervention. The stakeholders consulted for the stretch of the subject Project road included individuals representing 60 persons from 20 family groups in 7 villages in the two districts that the Project roads run through. These were considered to be representative of the community living in the area, the road users, the business associated with the road and the locally elected representatives. Consultations took place in September 2009 and July 2010. Dates and locations are presented in Appendix B.

B Consultation with Stakeholders 207. The results of the public consultations are recorded in Appendix B. The main environmental concerns included protecting water supplies, preventing damage to local electricity cables and other infrastructure and utilities surroundings construction areas. Prompt completion of the works and minimization of land acquisition were also requested by many local stakeholders. Increased traffic noise and controlling project workers and sanitation during construction were also concerns. Full and prompt compensation for land acquisition was also raised as a social issue. No significant operational phase impacts were identified and the communities along the Project roads indicated they would fully support the rehabilitation Project. The affected persons also fully expect that the necessary arrangements to compensate loss of property are addressed before construction commences. Results are summarized broadly in Table VI.1. Further information is provided in Appendix B.

Table VI.1 Summary of Main Environmental Concerns from Public Consultation

Concerns Expressed* How concerns are addressed in IEE Water supply is from collected water and this Facilities will be identified before construction commences and reprovisioning planned before must be protected. Local people need clean construction commences and agreed with local authority in Utilities & Infrastructure water. Management Plan. Power and other facilities will be identified before construction commences and reprovisioned The villages are reliant on electrical power. The before construction commences and agreed with local authority in Utilities & Infrastructure distribution lines on poles be protected. Management Plan. The contractor(s) will commit to implementing the mitigation measures identified in the Project Contractor should control the impacts EMP and SEMPs and will be monitored by PSC, PCC/PMMU. Start soon and complete a soon as possible PCC and PPMU will monitor progress of the works Parties should agree on compensation before To be addressed in the Resettlement Plan work starts PDOT/PPMU will disclose project details to the Commune PPCs. The IEE will be posted on Steering Committee should disclose the plans ADB’s website.. Contractors to publicize schedule for works. Requirement of EMP to disclose to local authorities and update during the works. PPMU should handle the compensation. To be addressed in the Resettlement Plan Requirement of EMP and SPS 2009 to be included in SEMP. Harness this support by fostering continuing consultation, ensuring Contractor’s proper and timely implementation of Negative impacts should be minimized. EMP provisions by incorporating EMP in tended and contract documents and regular monitoring and prompt resolution of complaints through GRM.

Page 58

Concerns Expressed* How concerns are addressed in IEE PPMU should manage and supervise the The implementation of the EMP will be closely monitored by PCC/PPMU and PSC contractors’ work. PMU should discuss compensation with local To be addressed in the Resettlement Plan people. * In many cases the interviewees were at first reluctant to discuss. The concerns are inferred from the replies in the field .

C Concerns Addressed 208. Concerns with respect to road alignment and drainage design and the disturbance or destruction of crops and gardens, private property and community disturbance have been brought to the attention of the project proponent and the relevant parties are well aware of the potential for local disturbance that can result from poorly controlled contractors. The main issues raised are addressed in the environmental management plan, as far as is reasonably practicable at this stage; a resettlement plan has been prepared to compensate for affected persons that can reasonably be predicted at this stage. Unforeseen impacts will also be captured by the requirements to update the environmental management plan and inform ADB in response to any unpredicted impacts that arise periodically as necessary. 209. The objectives of the stakeholder consultation process was to disseminate information on the Project construction and the expected impact, long-term as well as short-term, among primary and secondary stakeholders, and to gather information on relevant issues. Another important objective was to determine the extent of the concerns amongst the community, to address these in the project implementation and to suggest appropriate mitigation measures. The feedback received has been used to address these issues at early stages of project design.

D Information disclosure and Participation 210. Concerns have been expressed that the SC should disclose the road construction works in advance and complaints monitoring will provide further opportunities for consultation and can assist in public participation. Providing information through local authority offices will provide a conduit for the improvement of the project implementation to better serve the stakeholders. Public consultation can also assist in i) harnessing cooperation from informed people to help local authorities reconfirm the extent of local permits and licenses that will be required at a later stage; ii) obtaining cooperation from informed residents and groups which to avoid cost and time in dealing with complaints; iii) identifying local infrastructure projects or other local initiatives that will interface with the Project roads with assistance from informed local authorities; iv) the collection of anecdotal information on the current condition of the local environment including aspects of forest and wildlife and conservation. 211. The environmental assessment process under the SPS 2009 requires the disclosure of the IEE to the public during the completion of the IEE to be in strict adherence to the rules. This process will be concluded by displaying the IEE at the PPC Headquarters during the period when the IEE is disclosed on the ADB website

Page 59

VII. GRIEVANCE REDRESS MECHANISM

212. Existing arrangements for redress of grievances for affected persons are through complaints to the village and commune committees up to the district level and then through the PPC and back to the agency (e.g. PDOT/PPMU) that implements a project. This indirect route will remain in place to preserve the usual administrative remedies. There will be a need to deal with complaints and grievances during construction for this project, Therefore another mechanism will be available to affected persons whereby complaints can also be made direct to the PPMU (with the usual authorities PPC being kept informed). 213. Through a Grievance Redress Committee (GRC), PPMU shall promptly address affected people’s concerns, complaints, and grievances about the Project’s environmental performance at no costs to the complainant and without retribution. The GRC, which shall be established by PPMU before commencement of site works, shall be chaired by PPMU and shall have members from the contractor, ward and district committees, DONRE, local NGO, and women’s organization. Grievances can be filed in writing or verbally with any member of the GRC. The committee will have 15 days to respond with a resolution. If unsatisfied with the decision, the existence of the GRC shall not impede the complainant’s access to the Government’s judicial or administrative remedies. 214. PPMU shall make public the existence of this grievance redress mechanism through public awareness campaigns. PPMU shall also set-up a hotline for complaints and the hotline shall be publicized through the media and numbers placed on the notice boards outside the site and suggestion/complaints boxes be placed outside the construction camps and yards as well as on notice boards outside the Ha Giang provincial offices near the Project roads. Locally affected people will still be able to express grievances through the ward or district committees and these would be referred to PPMU through the usual channels in those committees. 215. The GRC will develop and maintain a database of all complaints received related to the Project and actions taken to resolve complaints, disputes or questions about the Project. It is also proposed that a hotline to PPMU/ESO be set up for complaints and that the hotline is publicized through the media and numbers placed on the notice boards outside the Ha Giang provincial offices near the Project road. The JCC and PPMU shall publicize the existence of the grievance redress mechanism through public awareness campaigns.

Page 60

VIII. ENVIRONMENTAL MANAGEMENT PLAN

A Implementation Arrangements 216. In Viet Nam the environmental regulations of GOV are derived from the Law on Environmental Protection (2006) and subsequent decrees and regulations. The environmental assessment rules are set out in the Guidelines on Implementation of Law on Environmental Protection 2006 (under Law on Environmental Protection 2005) that requires Environmental Impact Assessment (EIA). DONRE will review the IEE and before construction can commence. 217. The project owner (PPC/PPMU) is required to obtain approval from the Ministry of Natural Resources and Environment (MONRE) following environmental assessment and public consultation. It has been clarified by MONRE that although the Guidelines on Implementation of Law on Environmental Protection 2006 applies the PPMU should disclose the scale and scope of the Project works at the detailed design stage so that DONRE can decide on procedures that need to be completed under the environmental laws in view of the pending developments in environmental assessment procedures in Viet Nam. Therefore PPC/PPMU will submit the IEE to DONRE to disclose the scale and scope of the projects in due course and obtain approval. 218. Pollution standards for the protection environment are described in the Law on Environmental Protection (2006). The following standards will be referred to for water quality, noise, dust monitoring during implementation of the Project: QCVN 08:2008/BTNMT (surface water quality), QCVN 05:2009/BTNMT (air quality), and TCVN 5949:1998 (noise). Certain associated project activities commonly associated with road improvement such as quarry operations, extraction of gravel or discharge of waste water also require licenses that are issued at the provincial level depending on the duration and scale of those activities. DONRE is the authority to decide on the permit requirements at the provincial level. The table below defines the responsibilities for EMP implementation. 219. During project implementation, the joint coordination committee (JCC) will engage one (1) international environment specialist and two (2) national environment specialists to undertake PCC’s tasks with regard to EMP implementation and monitoring (see Table VIII.1) for the six Project provinces (Lao Cai, Yen Bai, Bac Kan, Cao Bang, Tuyen Quang and Ha Giang) . The estimated cost for engaging these specialists and other expenses related to EMP implementation are presented in Table VIII.3. 220. The PPMUs will engage national project supervision consultants (PSC). Included in the PSC’s responsibilities (Table VIII.1) is to ensure that the contractors implement the provisions of the Project EMP and SEMPs. Table VIII.1: Responsibilities for EMP Agency Responsibilities

Provincial People’s  Executing agency with overall responsibility for project construction and Committee (PPC) operation  Ensure that sufficient funds are available to properly implement the EMP  Ensure that the Project, regardless of financing source, complies with the provisions of the EMP and ADB Safeguard Policy Statement 2009 (SPS)  Ensure that Project implementation complies with Government environmental policies and regulations  Ensure that tender and contract documents include the Project EMP and SEMPs  Submit semi-annual monitoring reports on EMP implementation to ADB

Page 61

Provincial Project  Ensure that EMP provisions are strictly implemented during various project Management Unit phases (design/pre-construction, construction and operation) to mitigate under PDOT environmental impacts to acceptable levels (PPMU)  Undertake monitoring of the implementation of the EMP (mitigation and monitoring measures) with assistance from PSC and PCC.  Ensure that Project implementation complies with ADB's environmental policy and safeguards policy statement (SPS 2009) principles and requirements  For project duration, commit and retain a dedicated staff within PPMU as environment and safety officer (ESO) to oversee EMP implementation  Ensure that environmental protection and mitigation measures in the EMP are incorporated in the detailed design  Obtain necessary environmental approval(s) from DONRE prior to award of civil works contracts  Include the Project EMP and SEMPs in the bid and contract documents for civil works;  Establish an environmental grievance redress mechanism, as described in the IEE, to receive and facilitate resolution of affected peoples' concerns, complaints, and grievances about the Project's environmental performance  With assistance from PCC, prepare semi-annual environmental monitoring reports for submission to ADB  Based on the results of EMP monitoring, identify environmental corrective actions and prepare a corrective action plan, as necessary, for submission to ADB Joint Coordination  Engage environment specialists under the Project Coordinating Consultant Committee (JCC) to ensure proper implementation and monitoring of EMP provisions

Project  Ensure that the DDC incorporate into the project design the environmental Coordinating protection and mitigation measures identified in the EMP for the design Consultant (PCC) stage;  Assist PPMU to ensure that all environmental requirements and mitigation measures from the IEE and EMP are incorporated in the bidding documents and contracts  During detailed design phase carry out baseline data collection on air quality, noise and surface water quality (as specified in the EMP)  During detailed design phase, prepare method statement/SEMPs (Erosion Control Plan, Waste Management and Spoils Disposal Plan, Noise and Dust Control Plan, etc.) described in the IEE/EMP.  Implement all mitigation and monitoring measures for various project phases specified as PCC’s tasks in the EMP  Work with JCC and PPMU to execute any additional environmental assessment prior to project construction as required in the EMP (e.g., preparation of new or supplementary environmental assessment in case of change in alignment that will result to adverse environmental impacts that are not within the scope of the IEE prepared during loan processing, etc.)  Undertake environmental management capacity building activities for PPMU as described in the IEE and EMP.  Engage international and national environment specialists to ensure proper implementation of EMP provisions. Through these specialist, the PCC shall: (i) ensure proper and timely implementation of PCC’s tasks specified in the EMP, (ii) conduct environmental training as specified in the IEE/EMP for PPMU, (iii) conduct workers’ orientation on EMP provisions, (iv) undertake regular monitoring of the contractor’s environmental performance, as scheduled in the EMP (v) conduct field measurements for surface water quality, dust and noise as required in the EMP, and (v) prepare environmental baseline report and environmental semi-annual environmental monitoring reports , as specified in the EMP, for submission to ADB

Page 62

Detailed Design  Incorporate into the project design the environmental protection and Consultant (DDC) mitigation measures identified in the EMP for the design stage;  During detailed design phase provide all necessary information to the PCC to facilitate preparation of SEMPs (Erosion Control Plan, Waste Management and Spoils Disposal Plan, Noise and Dust Control Plan, etc.) described in the IEE/EMP.  During detailed design phase notify PCC and JCC of any change in alignment or project design/components and provide all necessary information to the PCC to facilitate preparation of any additional environmental assessment prior to project construction as required in the EMP (e.g., preparation of new or supplementary environmental assessment in case of change in alignment that will result to adverse environmental impacts that are not within the scope of the IEE prepared during loan processing, etc.)  During detailed design phase provide all necessary information to the PPMU and SC and JCC to facilitate obtaining environmental approvals from DONRE prior to award of civil works contracts Contractors  Recruit qualified environmental officer to ensure compliance with environmental statutory and contractual obligations and proper  Provide sufficient funding and human resources for proper and timely implementation of required mitigation measures in the EMP  Implement additional environmental mitigation measures, as necessary Provincial  Responsible for operation and maintenance of Project road Department of  Implement EMP monitoring during operation Transport (PDOT)

Department of  Review and approve environmental assessment reports required by the Natural Resources Government. and Environment  Undertake monitoring of the project’s environmental performance based on (DONRE) their mandate

B Environmental Mitigation 221. The anticipated environmental impacts and mitigation measures discussed in the previous section is presented in Table VIII.2. The table also shows responsibilities and timeframe/schedule for implementation of mitigation measures and monitoring. 222. Table VIII.2 shows that most mitigation activities during pre-construction are to be implemented by the PCC while during construction, measures shall be primarily implemented by the contractors. During operation stage, PDOT shall undertake environmental mitigation and monitoring requirements specified in the EMP. To ensure implementation of mitigation measures during construction, the EMP shall be included in the tender and contract documents for civil works. Contractors’ conformity with environmental contract procedures and specifications shall be regularly monitored by PPMU with assistance from PCC and results shall be reported semi-annually to ADB.

Page 63

Table VIII.2: Environmental Mitigation and Environmental Performance Monitoring Plan for the Project roads in Ha Giang

Impact mitigation Performance and Impact monitoring

Environmental Objective Proposed Mitigation Measures Responsible to Timing to Locations Mitigation Parameter to Frequency & Responsible Monitoring Concern (MM) Implement MM Implement MM Implement MM Cost monitor Verification to Monitor Cost DESIGN & PRE-CONSTRUCTION

1. Design Incorporate design 1. Secure the services of the Project 1: Joint Coordinating 1 to 2: All Project road Cost included Environmental Completion detailed JCC/PPMU/ , Cost met by measures and measures in the Coordinating Consultant (PCC) to address EMP Committee (JCC) Start of detailed stretches. in PPMU, DCC approval for design/prior to start DONRE PPMU project project disclosure project design to requirements at the detailed design phase. 2&3: Provincial design. and PCC the Project of site works. Once. staffing minimize 2. Notify Project to DONRE and identify and Project Management 3: Before start of civil staffing. obtained from environmental impacts. obtain environmental permits / certificates under Unit (PPMU) works DONRE Compliance with VIE statutory environmental assessment process, 4: Project 4 & 5 (i to ix): During Response statutory including those that may be required by Dong Coordinating detailed design from DONRE environmental Van Karst Plateau Geopark Management Board Consultant (PCC) phase on permits. assessment process. in relation to project works and facilities within 5 (i to ix): PCC, Require in Dong Van Karst Plateau Geopark (DVKPG). In Establishment of PPMU and Detailed PCC contract. particular, during detailed design phase for Grievance Redress Design Consultant check at Project road 176A, the Dong Van Karst Plateau Mechanism (GRM) (DCC) detailed Geopark Management Board (DVKPGMB) will design. be consulted and that a requisite Project report Complete will be compiled to obtain UNESCO’s check of items concurrence on the Project. DVKPGMB and 1 to 5. UNESCO must approve in advance all project facilities (workers’ camps, borrow areas, etc.) to be located in the DVKPG. The following will also be undertaken during detailed design phase: i) Contact and liaise with DVKPMGMB and all relevant local authorities, district and commune PPCs. ii) Work with DVKPGMB and relevant local authorities, to provide sufficient information to prepare the necessary reports to DVKPGMB’s national and international (UNESCO) collaborators and supporting organizations. iii) Ensure that there is sufficient time to compile report and inform collaborators (e.g. UNESCO) prior to bidding. iv) Commence bidding only after receipt of concurrence from collaborators including

Page 64

Impact mitigation Performance and Impact monitoring

Environmental Objective Proposed Mitigation Measures Responsible to Timing to Locations Mitigation Parameter to Frequency & Responsible Monitoring Concern (MM) Implement MM Implement MM Implement MM Cost monitor Verification to Monitor Cost UNESCO. 3. Implement plan for Grievance Redress Mechanism as described in the IEE 4. Based on the requirements of the IEE (Chapter V. A and B, and Project EMP Table VIII.2)), prepare the following method statements/specific EMPs (SEMPs) for implementation by contractors. Such SEMPs shall not be in conflict with any provisions of the Project EMP: Waste Management and Spoil Disposal Plan, Materials Management Plan, Drainage Management Plan, Erosion Control Plan, Tree-cutting and Replanting Plan, Temporary Transport Management Plan, Utilities and Irrigation Reprovisioning Plan, Noise and Dust Control Plan, and Workers and Public Safety Plan: 5. Coordinate with the Detailed Design Consultant (DDC) to incorporate the following measures in the project design: i) Minimize acquisition of agricultural land for temporary facilities by selecting preferred locations in detailed designs for construction yards and asphalt plant on barren or marginal land and agree terms with local community. ii) Identify potential solution spaces to ensure sufficient disposal areas for cut surface spoil materials and to avoid fly-tipping. Obtain approval from local authorities and local community before bidding. iii)Make arrangements to facilitate the timely production and supply of rock and bitumen based materials for construction and to avoid impacts due to unnecessary stockpiling near the Project roads. iv)Design extensions and improvements of drainage culverts for Project roads to account for increased rain due to a once in 100 year return storm event. v)Minimize hydrological and drainage impacts

Page 65

Impact mitigation Performance and Impact monitoring

Environmental Objective Proposed Mitigation Measures Responsible to Timing to Locations Mitigation Parameter to Frequency & Responsible Monitoring Concern (MM) Implement MM Implement MM Implement MM Cost monitor Verification to Monitor Cost during construction by including in the detailed design early phasing of replacement of culverts and other infrastructure. vi)Disruption to current facilities for water supply will be avoided and facilities will be retained or re-provisioned before construction works commence; provisions will be made to preserve the operation of current facilities for water supply in sufficient quantity in agreement with the local community. vii) Plan and implement reprovisioning of power and water supply lines before construction works commence to avoid disruption of services. Ensure that provisions will be made to preserve the operation of current facilities in sufficient quantity in agreement with the local utility company. viii) Prepare plans to minimize disturbance of vehicular traffic and pedestrians during construction. Ensure that phasing for construction will retain a passing lane along part of the road during construction in detailed designs programming and avoid community severance. ix) Aim to provide enhancements in the design based on ADB policy on environmentally responsible procurement and avoid negative impacts due to unnecessary removal of trees. 2. Project EMP can control 1. Coordinate with DCC to incorporate the 1 (i to iii): PCC, Detailed design All project roads. Included in Require in Once, during PPMU Cost met by boundaries/ impacts and following in the project design: DCC, PPMU PCC cost. PCC contract. detailed design. PPMU project location change compliance required i) Design upgrading works within ROW, to 2 to 4: PCC check at DD staffing for environmental laws. avoid graves, cemeteries and other sensitive Complete receptors (SR). check of items ii). Detailed design alignment to minimize loss of 1 to 4 on trees and other vegetation. detailed design. iii). Detailed design to provide for enhancement (e.g., landscaping, tree replanting) where practicable. 2. Make plans for tree replacement in

Page 66

Impact mitigation Performance and Impact monitoring

Environmental Objective Proposed Mitigation Measures Responsible to Timing to Locations Mitigation Parameter to Frequency & Responsible Monitoring Concern (MM) Implement MM Implement MM Implement MM Cost monitor Verification to Monitor Cost coordination with local authorities and District Forestry Office. 3. Update the EMP should there be additional environmental impacts identified during detailed design and for which appropriate mitigation measures have not been included in the EMP. Submit updated EMP to ADB for review before start of civil works. 4. Prepare a new or supplementary environmental assessment report in compliance with the environmental assessment and review framework and ADB’s Safeguard Policy Statement 2009 if there are any additional components or modifications in the Project such as change in specific location/alignment, among others, that will result to adverse environmental impacts and are not within the scope of the environmental assessment report prepared during loan processing. Submit the report to ADB for review before start of related civil works. 3. Environmentally 1. EMP is included in tender documents to 1 & 2: 1 & 2: Bid preparation All project roads Included in bid 1 & 2: Bid preparation PPMU Cost met by EMP provisions are responsible ensure that mitigation measures are budgeted PCC, PPMU 3 & 4: Before start of cost Inclusion in bid stage. PPMU project procurement and to prepare the contractors for environmental docs staffing properly implemented 3: PCC, PPMU civil works responsibilities.

by selected 2. Specify in bid document that Contractors shall 3 & 4: Check Before start of site engage capable and trained staff or site contractors. compliance works agent(s) to take responsibility for the environmental management and safety issues at the working level and to monitor the effectiveness and review mitigation measures as the project proceeds. 3. Contractors recruit qualified staff to oversee implementation of environmental and safety measures specified in the EMP. 4. Environmental Develop environmental 1. PPMU to commit and retain dedicated staff 1: PPMU Initiate during All Project roads Cost included Require in Prior to start of PPMU, Cost met by capacity management capacity for project duration to oversee EMP 2 & 3: PCC detailed design phase in PPMU and PCC contract. site works and PPMU project development of PPMU to ensure implementation and continue PCC cost Check at DD. throughout staffing proper EMP 2. PCC to train PPMU to build their capacity on throughout project Complete construction implementation and EMP implementation, monitoring and reporting construction training and phase

Page 67

Impact mitigation Performance and Impact monitoring

Environmental Objective Proposed Mitigation Measures Responsible to Timing to Locations Mitigation Parameter to Frequency & Responsible Monitoring Concern (MM) Implement MM Implement MM Implement MM Cost monitor Verification to Monitor Cost promote environmental using workshops and on-the-job training check before awareness among techniques and case studies. and during workers. 3. Conduct workers’ orientation on EMP construction. provisions. Such orientation shall be periodically conducted by the PCC as every new contractor is engaged.

5. Plan Spoil and Minimize waste; avoid 1. Re-use of waste materials & spoil disposal PCC Detailed design All Project roads Cost included Require in Once, detailed PPMU Cost met by Waste Disposal fly-tipping and locations included in bid and contract phase (before in PCC cost. PCC contract. design phase PPMU project pollution. documents. bidding) Check at DD staffing 2. Prepare a WASTE MANAGEMENT PLAN Complete and SPOIL DISPOSAL PLAN. The plan shall check of items cover handling, storage, treatment, transport 1 to 5 and disposal of solid and liquid wastes, hazardous materials, hazardous wastes and excavation spoils. Ensure that the plan will include a provision prohibiting disposal of wastes within the Dong Van Karst Plateau Geopark. There must also be a provision that disposal of excavation spoils within DVKPG will not be undertaken unless: a) prior approval is obtained from DVKPGMB and UNESCO, b) disposal of excavation spoils will not cause negative visual impacts, and c) will not adversely affect the protected geological resources within DVKPG. 3. The General Waste section of the WASTE MANAGEMENT PLAN and SPOIL DISPOSAL PLAN will include consideration of all matters related to solid and liquid waste disposal including the following: i)Expected types of waste and quantities of waste arising. No wastes (construction wastes, garbage.trash) will be disposed within Dong Van Karst Plateau Geopark) ii)Waste reduction, reuse and recycling methods to be employed iii) Agreed reuse and recycling options and locations for disposal / endorsement from

Page 68

Impact mitigation Performance and Impact monitoring

Environmental Objective Proposed Mitigation Measures Responsible to Timing to Locations Mitigation Parameter to Frequency & Responsible Monitoring Concern (MM) Implement MM Implement MM Implement MM Cost monitor Verification to Monitor Cost DONRE and local groups. iv)Methods for treatment and disposal of all solid and liquid wastes. v)Methods of transportation to minimize interference with normal traffic. vi)Establishment of regular disposal schedule and constraints for hazardous waste. vii)Programme for disposal of general waste / chain of custody for hazardous waste. viii)Discussion of the PSC, PPMU/PCC inspection/monitoring role. ix)Establishment of complaints management system for duration of the works x)Agreement on publicity/public consultation requirements (advance signing etc.). 4. The Waste Management Plan and Spoil Disposal Plan shall include a section on Hazardous Materials and Waste section. This will detail the mitigation measures, organizational arrangements, resources, facilities, etc. to avoid environmental as well as health and safety impacts due to use and disposal of hazardous materials/substances. 5. The Spoil Disposal section of the Waste Management Plan and Spoil Disposal Plan will include consideration of the following: i)Locations and quantities of spoil arising from the construction works. ii)Agreed locations for disposal / endorsement from DONRE and local groups. Disposal of excavation spoils within DVKPG will not be undertaken unless: a) prior approval is obtained from DVKPGMB and UNESCO, b) disposal of excavation spoils will not cause negative visual impacts, and c) will not adversely affect the protected geological resources within DVKPG. iii)Methods of transportation to minimize interference with normal traffic. iv)Establishment of acceptable working hours

Page 69

Impact mitigation Performance and Impact monitoring

Environmental Objective Proposed Mitigation Measures Responsible to Timing to Locations Mitigation Parameter to Frequency & Responsible Monitoring Concern (MM) Implement MM Implement MM Implement MM Cost monitor Verification to Monitor Cost and constraints. v)Agreement on time scale and programme for disposal and chain of custody. vi)Details of a trip ticket system to ensure that contractors dispose excavation spoils in approved areas. Such system will be designed so that the PSC and PCC could readily monitor the volume and disposal site of excavation spoils, and to ensure that the total volume of spoils disposed will not exceed the maximum capacity of disposal sites approved by local authorities. vii)Programming issues including the time of year and available resources. viii)Discussion of the PSC, PPMU/PCC inspection/monitoring role. ix))Establishment of complaints management system for duration of the works ix)Agreement on publicity/public consultation requirements (advance signing etc.). 6. Plan Avoid stockpiling of 1. Designs to balance cut and fill where PCC Detailed design All Project roads Cost included Require in Once, detailed PPMU Cost met by construction rock based materials possible. phase (before in PCC fees. PCC contract. design phase PPMU project materials and erosion runoff. 2. Prepare a MATERIALS MANAGEMENT bidding) Check at DD staffing management PLAN. The plan shall detail the arrangements to Complete be made to facilitate the timely production and check of items supply of construction materials to avoid 1 to 2 impacts due to unnecessary stockpiling outside the Project site. There will be a provision that no quarry sites and borrow areas within the Dong Van Karst Plateau Geopark will be established and/or used for the Project unless: a) prior approval is obtained from DVKPGMB and UNESCO, and b) such activities will not cause negative impacts on the protected geological resources and landscape within DVKPG.As a minimum, the plan shall consider the following: (i) Required materials, potential sources and estimated quantities available, (ii) Impacts to identified sources and availability,

Page 70

Impact mitigation Performance and Impact monitoring

Environmental Objective Proposed Mitigation Measures Responsible to Timing to Locations Mitigation Parameter to Frequency & Responsible Monitoring Concern (MM) Implement MM Implement MM Implement MM Cost monitor Verification to Monitor Cost (iii) Excavated slope material for reuse and recycling methods to be employed, (iv) Required endorsements from DONRE and local groups for use of sources. (v) Methods of transportation to minimize interference with normal traffic. (vi) Constraints of regular delivery schedule to reduce stockpiling on site. vii) Measures to be employed to mitigate nuisances to local residents. (viii) Program for reuse of slope excavated material for reuse (ix) Program for delivery of quarry and borrow materials. (x) Discussion of the PSC, PPMU/PCC inspection/monitoring role. (xi) Agreement on publicity/public consultation requirements. 7. Drainage and To minimize 1. Coordinate with DCC to ensure that designs PCC, PPMU, DCC Detailed design All Project roads Cost included Require in Once, detailed PPMU Cost met by Hydrological hydrological impacts for bridges and culverts are sufficient to control phase (before in PCC and PCC contract. design phase PPMU project Impacts flooding and erosion of flooding with appropriate drainage structures to bidding) DDC fees. Check at DD staffing river banks. cater for worst case flow and rainfall from 100 year return storm and to dissipate energy of flow Complete to reduce erosion. check of items 2. Prepare DRAINAGE MANAGEMENT PLAN. 1 to 2 The plan shall detail measures and other provisions to ensure that construction works will not cause ponding/flooding within the Project site, construction camps, borrow/quarry areas, other areas used for project-related activities and adjacent areas.

7. Erosion Control To minimize 1. Coordinate with the DCC to incorporate the 1: PCC, PPMU, Detailed design All Project roads Cost included Require in Once, detailed PPMU Cost met by and Flooding hydrological impacts, following measures in the project design: DCC phase (before in PCC and PCC contract. design phase PPMU project i) Incorporate erosion control and slope DDC fees. Check at DD flooding damage to the bidding) staffing works and erosion of stabilization measures in the engineering design 2: PCC river banks. such as side ditches and berms, rock lining and Complete slope walls, and provision of vegetation cover check of

Page 71

Impact mitigation Performance and Impact monitoring

Environmental Objective Proposed Mitigation Measures Responsible to Timing to Locations Mitigation Parameter to Frequency & Responsible Monitoring Concern (MM) Implement MM Implement MM Implement MM Cost monitor Verification to Monitor Cost on slopes, where appropriate. implementation ii) Cut slopes designed not to undercut or of items 1 to 2 destabilize adjacent tree lined slopes. iii) Temporary drainage works are to be designed based on the historical flood data and flood forecasting. iv) Ensure design includes prevention of flooding in adjacent areas during rehabilitation or construction of bridges. v) Incorporate in the design side drainage structures to divert the stream water at construction sites. vi) Design incorporates sufficient sizes of drains to take design flows. 2. Prepare an EROSION CONTROL PLAN. The plan shall detail the arrangements/provisions to ensure that construction works will not cause excessive runoff and siltation of adjacent waterways within the Project site, have sufficient provisions to ensure stabilization of cut slopes and other erosion-prone areas, minimize hydrological impacts, flooding and erosion of river banks and adjacent areas and to protect the works under construction. The plan will consider the following: i) Climate and rainfall for the area and checking weather forecasts. ii) Terrain and typical locations susceptible to erosion and runoff. iii) Protection of the works and potential impacts to the environment. iv) Erosion control methods to be employed, locations and installation timing. v) Limits to stockpiling on sites near waterways and irrigation channels. vi) Discussion of the PSC, PCC/PPMU inspection/monitoring role. vii) Agreement on publicity/public consultation requirements.

Page 72

Impact mitigation Performance and Impact monitoring

Environmental Objective Proposed Mitigation Measures Responsible to Timing to Locations Mitigation Parameter to Frequency & Responsible Monitoring Concern (MM) Implement MM Implement MM Implement MM Cost monitor Verification to Monitor Cost 8.Traffic Condition Minimize traffic 1. Contact all relevant local authorities and local PCC Detailed design All Project roads Cost included Require in Once, detailed PPMU Cost met by disruption and village groups to plan traffic management. phase (before in PCC fees. PCC contract. design phase PPMU project congestion. Check at DD 2 Prepare a TEMPORARY TRAFFIC bidding) staffing MANAGEMENT PLAN to minimize disturbance of vehicular traffic and pedestrians during Complete construction. Access arrangements for vehicles check of items accessing the Project area will be formulated 1 to 2 such that this will avoid community disturbance and severance and will at least retain a passing lane along all roads used during construction. The plan will include consideration of the following i)Lane availability and minimizing interference with traffic flows past the works site. ii)Establishment of acceptable working hours and constraints. iii)Agreement on time scale and establishment of traffic flow/delay requirements. iv)Programming issues including the time of year and available resources. v)Discussion of the PSC, PCC/PPMU inspection/monitoring role. vi)Establishment of complaints management system for duration of the works vii)Agreement on publicity/public consultation requirements (advance signing etc.). 9. Protect and Minimize interruption 1. Identify all power, water supply, PCC Detailed design All Project roads Cost included Require in Once, detailed PPMU Cost met by reprovision to power, water supply telecommunications and irrigation systems likely phase (before in PCC fees. PCC contract. design phase PPMU project irrigation and telecoms and irrigation to be interrupted by the works. bidding) Check at DD staffing utilities system 2. Contact all relevant local authorities for utilities and local village groups to plan Complete reprovisoning of power, water supply, check of items telecommunications and irrigation systems. 1 to 3 3. Prepare a UTILITIES and IRRIGATION REPROVISIONING PLAN to minimize interruption to power, water supply, telecoms and irrigation systems.

Page 73

Impact mitigation Performance and Impact monitoring

Environmental Objective Proposed Mitigation Measures Responsible to Timing to Locations Mitigation Parameter to Frequency & Responsible Monitoring Concern (MM) Implement MM Implement MM Implement MM Cost monitor Verification to Monitor Cost 10. Tree cutting Minimize tree cutting 1. Contact all relevant local authorities, forestry PCC Detailed design All Project roads Cost included Require in Once, detailed PPMU Cost met by authority and local village groups to plan tree phase (before in PCC fees. PCC contract. design phase PPMU project cutting and replanting. bidding) Check at DD staffing 2. Prepare a TREE CUTTING AND REPLANTING PLAN to avoid indiscriminate Complete tree-cutting. The plan shall clearly define areas check of items where vegetation removal is necessary based 1 to 2 on Project requirements and shall have provisions for replanting to compensate for lost trees. The plan shall prohibit introduction of invasive species and shall specify that new alien plant species (i.e., species not currently established in the region of the project) shall not be used unless carried out within the existing regulatory framework for such introduction. 11. Noise and dust Minimize noise and 1. Reconfirm all noise and dust sensitive PCC Detailed design All Project roads Cost included Require in Once, detailed PPMU Cost met by management dust receivers likely to be affected by construction phase (before in PCC fees. PCC contract. design phase PPMU project works. bidding) Check at DD staffing 2. Contact local village groups to plan mitigation in advance. Complete 3. Prepare a NOISE and DUST CONTROL check of PLAN to minimize impacts to sensitive receptors contractor’s (residential areas, schools, temples, hospitals, implementation etc.) due to construction works, sourcing and of items 1 to 3 transport of construction materials, and other project-related activities. 12. Workers and Avoid accidents due to Prepare a WORKERS and PUBLIC SAFETY PCC Detailed design All Project roads Cost included Require in Once, detailed PPMU Cost met by public safety construction works PLAN to identify interfaces between the works phase (before in PCC fees. PCC contract. design phase PPMU project and the public, formulate measures to ensure bidding) staffing safety of workers and the public, and prevent Complete accidents due to the construction works. check at DD

13. Unexploded Avoid accidents due to 1. Coordinate with appropriate agencies at the PPMU Prior to contractor All Project roads Included in Complete Once, prior to PPMU, JCC Cost met by JCC Ordnance UXO design stage to identify if UXO is a potential selection. Project cost check of items start of site works and PPMU threat to works Reassurance check 1 to 3 project staffing 2. Based on the findings, engage an authorized before works UXO clearing contractor, as necessary. commence 3. Ensure that the contractors shall only commence site works after the UXO clearing

Page 74

Impact mitigation Performance and Impact monitoring

Environmental Objective Proposed Mitigation Measures Responsible to Timing to Locations Mitigation Parameter to Frequency & Responsible Monitoring Concern (MM) Implement MM Implement MM Implement MM Cost monitor Verification to Monitor Cost firm has certified that the project areas are already cleared.

CONSTRUCTION STAGE 1. Activate Avoid impacts from 1. Implement provisions of Project EMP and Contractor 1. Throughout Cost included 1. Check that Before start of site Cost met by management plans unplanned activities. SEMPs for waste and spoil disposal, materials construction phase in contractors contractors works and PSC, PCC and and obtain permits/ management, drainage, erosion control, tree- fees have throughout PPMU project 2. Before start of site licenses. cutting and replanting, traffic, utilities and works. resources to construction staffing irrigation reprovisioning, noise and dust control implement phase and workers and public safety. Project EMP, Bi-weekly PCC, PPMU SEMPs 2. Contractors and their suppliers comply with all statutory requirements for permits from 2. Complete As part of day- Project DONRE with regard to use of mechanical check of all today project Supervision equipment, establishment and operation of necessary construction Consultant construction plants such as concrete batching environmental supervision (PSC) plant, rock crusher, spoils disposal, etc. approvals/per-

mits. 2. Orientation for Contractors & workers 1. Contractors clearly separate resources 1: Contractors 1: Before start of site All Project roads Cost included Complete 1: Before start of PCC, PPMU, Cost met by Contractors, trained to implement applied to mitigation measures. Tenders identify 2: PSC, PCC works in contracts for check of site works PSC PSC, PCC and Workers on mitigation measures named staff to supervise implementation of PSc, PCC and implementation PPMU project 3: Contractors 2: Within one month 2: Within one environmental and and better PRoject EMP, SEMPs. Contractors of items 1 to 3 staffing of start of site works month of start of social implementation of 2. PSC and PCC shall conduct and as new construction and management. EMP. training/orientation involving construction contractors are as new workers and /PPMU with regard to engaged contractors are implementation of mitigation measures in the 3. Upon deployment engaged SEMPs and Project EMP (i.e., those specified of workers to project 3: Bi-weekly in the IEE) and any additional measures site (every 2 weeks) identified during detailed design phase. during

3. Implement malaria controls and HIV-AIDS construction. education and prevention program in line with social plans

PSC (monitoring to be done as part of day-to-day project construction supervision)

Page 75

Impact mitigation Performance and Impact monitoring

Environmental Objective Proposed Mitigation Measures Responsible to Timing to Locations Mitigation Parameter to Frequency & Responsible Monitoring Concern (MM) Implement MM Implement MM Implement MM Cost monitor Verification to Monitor Cost 3. Loss of Minimize impacts to 1. Monitoring and marking of vegetation that will 1: Contractors, 1 to 2: Before tree- All Project roads Cost included Check 1 to 3: Prior to PCC, PPMU Cost met by not be removed agreed with forest authority vegetation and flora and fauna District Forestry cutting is in contracts implementation and during PSC, PCC and impacts to fauna prior to commencement of construction. Office (DFO) implemented of items 1-12 construction (Bi- PPMU project 2. Forest authority to approve replacement of 2: DFO/local forestry 3 to 11: Throughout weekly) staffing cut trees to be undertaken based on the tree office construction phase 4 to 12: Bi-weekly cutting and replanting plan. 3. Clearing of trees minimized based on Tree- 3 to 11: Contractors

cutting and Replanting Plan. 1 to 12 (as part of 4. Prohibit cutting of trees for firewood and for day-to-day project PSC use in Project. construction 5. During replanting/revegetation works, new supervision) alien plant species (i.e., species not currently established in the country or region of the project) shall not be used unless carried out with the existing regulatory framework for such introduction. Invasive species shall not be introduced into new environments. 6. Prohibit workers from hunting wild animals. 7. As much as possible, bridge works will be scheduled in dry season to minimize adverse impacts to fishery, river water quality and other aquatic resources. 8. The contractors will not use or permit the use of wood as a fuel for the execution of any part of the Works, including but not limited to the heating of bitumen and bitumen mixtures, and to the extent practicable shall ensure that fuels other than wood are used for cooking, and water heating in all his camps and living accommodations 9. Contractors shall not buy or use wood from the illegal sources (that come from the illegal logging) 10. No construction camps, asphalt mixing plants, material storage sites are to be located in the forest areas. 11. Contractors will take all precautions necessary to ensure that damage to vegetation is avoided due to fires resulting from execution of the works. The Contractors will immediately suppress the fire, if it occurs, and shall undertake replanting to replace damaged

Page 76

Impact mitigation Performance and Impact monitoring

Environmental Objective Proposed Mitigation Measures Responsible to Timing to Locations Mitigation Parameter to Frequency & Responsible Monitoring Concern (MM) Implement MM Implement MM Implement MM Cost monitor Verification to Monitor Cost vegetation. 4. Drainage and To minimize 1. Implement provisions of DRAINAGE Contractors Throughout Throughout project Included in Check Bi-weekly PCC, PPMU Cost met by implementation Hydrological hydrological impacts MANAGEMENT PLAN (DMP) prepared by PCC construction phase site, particularly at project and bid PSC, PCC, Impacts flooding and erosion of during detailed design phase. bridges, causeways, costs of items 1-8 PPMU project As part of day-to- PSC river banks. irrigation canals and staffing 2. Provide adequate drainage facilities at day project all areas considered construction sites and project-related facilities construction prone to flooding. (construction camps, borrow areas, etc.) to supervision avoid ponding and flooding.

3. Implement agreed designs for bridges and culverts sufficient to control flooding as designed and to dissipate energy of flow to reduce erosion. 4 Protect or reprovision irrigation channels that cross the works areas. Damaged irrigation canals shall be immediately repaired. 5. Protect natural streams that may become silted by construction runoff, workshops and equipment washing-yards. 6. Minimize alterations in the project corridor’s surface drainage patterns as much as possible: 7. Drains to be constructed so that the outfalls of the surface run-off from the carriageway are diverted away from the SRs. 8 Ensure that storm drains and drainage systems are periodically cleared to maintain storm water flow during construction. 5. Utilities Prevent interruption of 1. Implement provisions of the UTILITIES and Contractors 2 to 6: Before start of Throughout project Cost included Check 2 to 6: Before PCC, PPMU Cost met by services such as implementation IRRIGATION REPROVISIONING PLAN (UIRP) construction site in contracts construction PSC, PCC and electricity and water of items 1-8 prepared by PCC during detailed design. 7 & 8: During 7 & 8: Bi-weekly PPMU project during relocation of the 2. Reconfirm power, water supply, construction staffing utilities line telecommunications and irrigation systems likely /connections. Repair 1 to 8: as part of to be interrupted by the works. PSC damaged access day-to-day project 3. Contact all relevant local authorities for roads. construction utilities and local village groups to plan supervision reprovisoning of power, water supply, telecommunications and irrigation systems. 4. Utilities shall be relocated and reconnected well ahead of commencement of construction works and contractors shall coordinate with utility company for relocation and reconnection

Page 77

Impact mitigation Performance and Impact monitoring

Environmental Objective Proposed Mitigation Measures Responsible to Timing to Locations Mitigation Parameter to Frequency & Responsible Monitoring Concern (MM) Implement MM Implement MM Implement MM Cost monitor Verification to Monitor Cost well before works commence. 5. Affected communities shall be properly informed in advance. 6. Reconnection of utilities shall be done at the shortest practicable time before construction commences. 7. Utilities damaged during construction shall be reported to the PSC, PPMU and utility authority and repairs arranged immediately. 8. Access roads, agricultural land and other properties damaged during transport of construction materials and other project-related activities shall be reinstated upon completion of construction works at each section 6. Materials Minimize impacts from 1. Implement MATERIALS MANAGEMENT Contractors 1 to 13: Throughout Project site, quarry Cost included Check Bi-weekly PCC, PPMU Cost met by exploitation and materials extraction, PLAN or MMP prepared by PCC during construction and borrow sites in contract implementation PCC and PPMU management of transportation and detailed design phase and ensure that no quarry of items 1-17 project staffing 14 to 17: Upon as part of day-to- PSC quarry and borrow storage. sites and borrow areas within the Dong Van completion of day project areas Karst Plateau Geopark are established and/or materials extraction construction used for the Project unless: a) prior approval is supervision obtained from DVKPGMB and UNESCO, and b) such activities will not cause negative impacts on the protected geological resources and landscape within DVKPG. 2. Balance cut and fill requirements to minimization impacts from extraction of aggregates. 3. Prioritize use of existing quarry sites with suitable materials and update the list of quarries and borrow pits monthly in MMP and report to PPMU and minimize impacts on other local resources. 4. Procure materials only from DONRE authorized quarries and borrow sites. 5. If the contractors shall operate the quarry site, required environmental permits shall be secured prior to operation of quarry/borrow areas. 6. Follow compensatory planting plan if trees have to be removed 7. Stockpile topsoil for later use and fence and re-contour borrow pits after use. Topsoil,

Page 78

Impact mitigation Performance and Impact monitoring

Environmental Objective Proposed Mitigation Measures Responsible to Timing to Locations Mitigation Parameter to Frequency & Responsible Monitoring Concern (MM) Implement MM Implement MM Implement MM Cost monitor Verification to Monitor Cost overburden, and low-quality materials shall be properly removed, stockpiled near the site, and preserved for rehabilitation. 8. Use quarry with highest ratio between extractive capacity (both in terms of quality) and loss of natural state; 9. Use quarry sites lying close to the alignment, with a high level of accessibility and with a low hill gradient; 10. Do not use quarries in areas of natural woodland or near rivers which provide food and shelters for birds and other animals. 11. Borrow/quarry sites shall not be located in productive land and forested areas. 12. During quarry/borrow site operation, provide adequate drainage to avoid accumulation of stagnant water. 13. It is preferable to avoid or reduce the sections of quarry sites located on river bed. If it is not possible to locate quarries out of river beds, quarry sites lying on small rivers and streams shall be avoided. Alluvial terraces or alluvial deposits which lie on the river beds but not covered by water in normal hydrological conditions, are preferred; 14. In quarries in the mountainous or hilly areas, or wherever slopes are important, cut terraces after extraction and implement a drainage system and vegetation cover for rehabilitation. 15. Ensure borrow pits are left in a tidy state with stable side slopes and proper drainage in order to avoid creation of water bodies favorable for mosquito breeding 16. Upon completion of extraction activities, quarry and borrow pits shall be dewatered and fences shall be installed, as appropriate, to minimize health and safety risks. 17. To avoid drowning when pits become water- filled, measures such as fencing, providing flotation devices such as a buoy tied to a rope, etc. shall be implemented.

Page 79

Impact mitigation Performance and Impact monitoring

Environmental Objective Proposed Mitigation Measures Responsible to Timing to Locations Mitigation Parameter to Frequency & Responsible Monitoring Concern (MM) Implement MM Implement MM Implement MM Cost monitor Verification to Monitor Cost 7. Spoil Disposal Control spoil and 1. Implement corresponding provisions of Contractors Throughout Project site and Cost included Check Bi-weekly PCC, PPMU Cost met by construction waste WASTE MANAGEMENT and SPOIL DISPOSAL construction phase spoils disposal sites in contracts implementation PSC, PCC and disposal, oily and PLAN (WMSDP) prepared by the PCC and of items 1-12 PPMU project as part of day-to- PSC hazardous wastes. ensure that wastes (construction wastes, staffing day project garbage/trash) will not be disposed within Dong Spoils disposal construction Van Karst Plateau Geopark. Disposal of will be supervision excavation spoils within DVKPG will not be monitored by undertaken unless: a) prior approval is obtained PSC/PCC/PP from DVKPGMB and UNESCO, b) disposal of MU and excavation spoils will not cause negative visual recorded using impacts, and c) will not adversely affect the a written chain protected geological resources within DVKPG.. of custody 2. Areas for disposal to be agreed with land (trip-ticket) owner and DONRE checked and recorded by system to the the PSC, PCC/PPMU and monitored designated 3. Spoil disposal areas to be rehabilitated disposal sites. monitored, catalogued, and marked. 4. Spoil will not be disposed of in rivers and streams or other natural drainage path. 5. Spoil will not be disposed of on fragile slopes, flood ways, wetland, farmland, forest, religious or other culturally sensitive areas or areas where a livelihood is derived. 6. Surplus spoil will be used where practicable for local repair works to fill eroded gullies and depression areas and degraded land in consultation with local community. 7. Spoils shall only be disposed to areas approved by local authority. 8. Spoil will be to disposed of to disused quarries and abandoned borrow pits where practicable. 9. Disposed spoil will be spread in 15cm layers and compacted to optimum moisture content, covered with topsoil, landscaped and provided with drainage and vegetation to prevent erosion in line with best practice. 10. Spoil disposal shall not cause sedimentation and obstruction of flow of watercourses,

Page 80

Impact mitigation Performance and Impact monitoring

Environmental Objective Proposed Mitigation Measures Responsible to Timing to Locations Mitigation Parameter to Frequency & Responsible Monitoring Concern (MM) Implement MM Implement MM Implement MM Cost monitor Verification to Monitor Cost damage to agricultural land and densely vegetated areas. 11. Under no circumstances will spoils be dumped into watercourses (rivers, streams, drainage, irrigation canals, etc.) 12. The spoils disposal site shall be located at least 50 m from surface water courses and shall be protected from erosion by avoiding formation of steep slopes and grassing. 8. General Reduce, reuse and 1. Implement corresponding provisions of Contractors Throughout Project site and Cost included Check Bi-weekly PCC, PPMU Cost met by Construction recycle waste and WASTE MANAGEMENT and SPOIL DISPOSAL construction phase waste disposal in contracts implementation PSC, PCC and Waste Disposal contamination due to PLAN prepared by the PCC and ensure that areas of items 1-10 PPMU project as part of day-to- PSC poor waste disposal disposal of wastes (construction wastes, staffing day project practices. garbage/trash) will not be undertaken within the construction Dong Van Karst Plateau Geopark. supervision 2. Areas for disposal to be agreed with land

owner and DONRE checked; and recorded and monitored by the PCC/PPMU. 3. Waste disposal areas approved by local authorities shall be rehabilitated, monitored, catalogued, and marked. 4. Segregation of wastes shall be observed. Cleared foliage, shrubs and grasses can be given to local farmers for fodder and fuel. Organic (biodegradables) shall be collected and disposed of on site by composting (no burning on site). 4. Recyclables shall be recovered and sold to recyclers. 5. Residual and hazardous wastes shall be disposed of in disposal sites approved by local authorities. 6. Construction/workers’ camps shall be provided with garbage bins. 7. Burning of construction and domestic wastes shall be prohibited. 8. Disposal of solid wastes into canals, rivers, other watercourses, agricultural field and public areas shall be prohibited.

Page 81

Impact mitigation Performance and Impact monitoring

Environmental Objective Proposed Mitigation Measures Responsible to Timing to Locations Mitigation Parameter to Frequency & Responsible Monitoring Concern (MM) Implement MM Implement MM Implement MM Cost monitor Verification to Monitor Cost 9. There will be no site-specific landfills established by the contractors. All solid waste will be collected and removed from the work camps and disposed in local waste disposal sites. 10. Solid waste generated during construction and at campsites to be treated and safely disposed only in demarcated off-site waste disposal sites identified and agreed with PSC/PPMU, local community and local authorities.

9. Use of Minimize 1. Implement corresponding provisions of Contractors Throughout Throughout Project Cost included Check Bi-weekly PCC, PPMU Cost met by hazardous contamination due to WASTE MANAGEMENT and SPOIL DISPOSAL construction phase site, storage areas, in contracts implementation PSC, PCC and substances and use and storage of PLAN prepared by the PCC. equipment and of items 1-17 PPMU project as part of day-to- PSC hazardous waste hazardous substances vehicle maintenance staffing 2. Ensure that safe storage of fuel, other day project disposal and refueling areas hazardous substances and bulk materials are construction agreed by PSC/PPMU and have necessary supervision approval/permit from DONRE and local

authorities. 3. Hydrocarbon, toxic material and explosives will be stored in adequately protected sites consistent with national and local regulations to prevent soil and water contamination. 4. Equipment/vehicle maintenance and refueling areas will be confined to areas in construction sites designed to contain spilled lubricants and fuels. Such areas shall be provided with drainage leading to an oil-water separator that will be regularly skimmed of oil and maintained to ensure efficiency. 5. Fuel and other hazardous substances shall be stored in areas provided with roof, impervious flooring and bund/containment wall to protect these from the elements and to readily contain spilled fuel/lubricant. 6. Segregate hazardous wastes (oily wastes, used batteries, fuel drums) and ensure that storage, transport and disposal shall not cause pollution and shall be undertaken consistent with national and local regulations.

Page 82

Impact mitigation Performance and Impact monitoring

Environmental Objective Proposed Mitigation Measures Responsible to Timing to Locations Mitigation Parameter to Frequency & Responsible Monitoring Concern (MM) Implement MM Implement MM Implement MM Cost monitor Verification to Monitor Cost 7. Ensure all storage containers are in good condition with proper labeling. 8. Regularly check containers for leakage and undertake necessary repair or replacement. 9. Store hazardous materials above flood level. 10. Discharge of oil contaminated water shall be prohibited. 11. Used oil and other toxic and hazardous materials shall be disposed of in an authorized facility off-site. 12. Adequate precautions will be taken to prevent oil/lubricant/ hydrocarbon contamination of channel beds. 13. Ensure availability of spill clean up materials (e.g., absorbent pads, etc.) specifically designed for petroleum products and other hazardous substances where such materials are being stored. 14. Spillage, if any, will be immediately cleared with utmost caution to leave no traces. 15. Spillage waste will be disposed at disposal sites approved by local authorities and by PSC. 16. All areas intended for storage of hazardous materials will be quarantined and provided with adequate facilities to combat emergency situations complying with all the applicable statutory stipulation. 17. The Contractors shall identify named personnel in the management plan/SEMP in- charge of these sites and ensure they are properly trained to control access to these areas and entry will be allowed only under authorization. 10. Asphalt plant Avoid air pollution, 1. Locate asphalt plant, rock crushers and Contractors 1: During selection All Project roads and Cost included Check 1: Before PCC, PPMU Cost met by rock crushers, nuisances, traffic bitumen supply off road and (wherever of locations for project-related in contracts implementation establishment of PSC, PCC and bitumen usage obstacles and practicable) at least 500 m from nearest asphalt plant, rock facilities of items 1-9 facilities, 2 to 9: PPMU project and soil contamination sensitive receivers (residential areas, schools, crusher, bitumen Bi-weekly staffing contamination hospital, etc.) and rivers and install and maintain storage dust suppression equipment. Such Project 2 to 9: Throughout 1 to 9: as part of facilities/plants will not be located within Dong construction phase day-to-day project PSC Van Karst Plateau Geopark. construction

Page 83

Impact mitigation Performance and Impact monitoring

Environmental Objective Proposed Mitigation Measures Responsible to Timing to Locations Mitigation Parameter to Frequency & Responsible Monitoring Concern (MM) Implement MM Implement MM Implement MM Cost monitor Verification to Monitor Cost 2. Bitumen should not be used as fuel. Fuel supervision wood not for bitumen heating. Bitumen drums stored in dedicated area not scattered along

Project roads and other project facilities. 3. Bitumen will not be allowed to enter either running or dry streambeds and nor will be disposed of in ditches or small waste disposal sites prepared by the contractors. 4. Bitumen storage and mixing areas shall be protected against spills and all contaminated soil must be properly handled according to applicable national and local laws and regulation. As a minimum, these areas must be contained, such that any spills can be immediately contained and cleaned up. Any petroleum products used in the preparation of the bitumen mixture must also be carefully managed to avoid spills and contamination of the local water table. 5. Fuel wood shall not be used for heating bitumen and bitumen shall be not used as fuel. 6. Bitumen drums shall be stored in a dedicated area, not scattered along the works 7. All accidental spills of bitumen or chemicals should be cleaned up immediately with the top 2cm of any contaminated soil underneath and disposed of as chemical waste to a site approved by the local authority. 8. Prevent soil contamination requiring contractors to instruct and train their workforce on storage and handling of materials and chemicals that can potentially cause soil contamination. 9. Recycle debris generated by dismantling of existing pavement subject to the suitability of the material.

11. Noise and To minimize air 1. Implement the NOISE and DUST Contractors Throughout All Project roads Cost included Check Bi-weekly and PCC, PPMU Cost met by spot checks dust nuisances impacts effectively and CONTROL PLAN (NDCP) prepared by the construction phase in contracts implementation PSC, PCC and avoid complaints due PCC. of items 1-16 PPMU project

to the airborne dust. 2. Restrict works to daylight hours within 500m as part of day-to- staffing

Page 84

Impact mitigation Performance and Impact monitoring

Environmental Objective Proposed Mitigation Measures Responsible to Timing to Locations Mitigation Parameter to Frequency & Responsible Monitoring Concern (MM) Implement MM Implement MM Implement MM Cost monitor Verification to Monitor Cost of residential settlements and hospitals. day project PSC 3. Powered mechanical equipment and vehicle construction emissions to meet national TCVN/QCVN supervision standards. All construction equipment and vehicles shall have valid certifications indicating compliance to vehicle emission standards. 4. Construction equipment and vehicles will be maintained to a good standard and shall be provided with muffler silencers. Machinery causing excessive pollution will be banned from construction sites. 5. Monitor and investigate complaints; propose alternative mitigation measures. 6. Keep stockpiles moist 7. Tightly cover trucks transporting construction materials (sand, soil, cement, gravel, etc.) to avoid or minimize spills and dust emission. 8. On rainless day undertake watering, at least twice per day, on dusty and exposed areas at construction yards, materials stockpile, construction sites, access roads, quarry areas, borrow sites and other project areas where residential sites and other sensitive receptors such as schools, hospital, etc. are located nearby. If works are within 15m of any sensitive receivers, the contractors shall install dust barrier between the works at the road edge and the sensitive receivers (e.g. 2.5 m high temporary walls, etc.) 9. Mixing and crushing plants operations will be equipped with dust suppression devices such as water sprays. 10. Clean up road surfaces after work. 11. Temporary noise barriers shall be used, as necessary, in sites where sensitive receptors are present, such as residential areas, schools, hospitals, temples, etc. 12. To protect buildings and structures from vibration, non-vibrating roller shall be used in construction sites near buildings and structures. 13. Structures which are damaged due to vibration caused by the Project shall be repaired

Page 85

Impact mitigation Performance and Impact monitoring

Environmental Objective Proposed Mitigation Measures Responsible to Timing to Locations Mitigation Parameter to Frequency & Responsible Monitoring Concern (MM) Implement MM Implement MM Implement MM Cost monitor Verification to Monitor Cost immediately as directed by PSC/PPMU. 14. Machinery shall be turned off when not in use. 15. Pile driving during to be schedule for day time if construction site is near sensitive receptors or approved by DONRE, local authority and PSC. 16. Impose speed limits on construction vehicles to minimize dust emission along areas where sensitive receptors are located (houses, schools, hospitals, etc.).

12. Blasting (if Perform safe blasting 1. Before sites works, blasting plan to be Contractors 1: Before site works Sections of project Cost included Check 1: Before PCC, PPMU Cost met by required) and prevent damage prepared by contractors and approved by 2 to 11: Throughout alignment where in contracts implementation construction PSC, PCC and and nuisances from PSC/PPMU in writing. Contractors to implement construction phase. blasting will be of items 1-11 2 to 11: Bi-weekly PPMU project blasting blasting plan provisions. undertaken and spot checks staffing 2. All the statutory laws, regulation, rules etc.,

pertaining to acquisition, transport, storage, 1 to 11: as part of handling and use of explosives will be strictly PSC followed. Blasting will be carried out as per day-to-day project VietNam statutory requirements with notification construction to DONRE and local police. supervision 3. No blasting will take place without condition survey of the buildings within 500 m and permission and monitoring by the PSC/PPMU. 4. People living near blasting sites will be informed of blasting times prior to the blasting. 5. Warning sirens will be sounded before blasting. 6. Pre-splitting shall be undertaken. 7. Blast blankets will be laid over the blast area to reduce flying rock 8. Where the vibration from blasting is exceeding the maximum permissible level, or damage occurs to local property information from the blasting shall be used to modify blasting patterns and calculate a reduced charge for future blasts 9. Blasting will not be undertaken at night. 10. Blasting shall be under careful and strict management of properly trained and licensed

Page 86

Impact mitigation Performance and Impact monitoring

Environmental Objective Proposed Mitigation Measures Responsible to Timing to Locations Mitigation Parameter to Frequency & Responsible Monitoring Concern (MM) Implement MM Implement MM Implement MM Cost monitor Verification to Monitor Cost personnel. Workers at blasting sites will be trained prior to blast operations and provided with safety equipment and earplugs. 11. Observe proper warning and precautionary measures to ensure safety of residents, pedestrians, motorists and structures during blasting. 13. Erosion Protect established 1. Implement the Erosion Control Plan (ECP) Contractors Throughout Throughout project Cost included Check Bi-weekly PCC, PPMU Cost met by PSC, PCC and control/run-off works. produced by the PCC and implement slope construction phase site and all in contracts implementation stabilization measures specified in the detailed vulnerable slopes of items 1-12 PPMU project as part of day-to- PSC designs and maintained during construction to agreed with staffing day project protect the works. PSC/PPMU. construction 2. Establish vegetation and erosion protection supervision immediately after completion of works in each stretch / sector. 3. Check weather forecasts and minimize work in wet weather. 4. Stockpile topsoil for immediate replanting after cutting. 5. Minimize damage and cutting of surrounding vegetation during slope formation. 6. Protect the cut slope with planted vegetation, bioengineering or conventional civil engineering structures as soon as practicable after cutting. 7. Include and implement appropriate measures for slope protection, i.e. vegetation cover and stone pitching, as required in the detailed construction drawings. 8. Prevent erosion and protect the cut slope with temporary or permanent drainage as soon as practicable after cutting. 9. If new erosion occurs accidentally, back fill immediately to restore original contours. 10 Low embankments will be protected from erosion by seeding and planting indigenous grasses that can flourish under local conditions. 11. High embankments, i.e. 2m high and above, will be considered for protection by constructing stone pitching or a riprap across the embankment immediately after the works are completed. This practice will also be applied

Page 87

Impact mitigation Performance and Impact monitoring

Environmental Objective Proposed Mitigation Measures Responsible to Timing to Locations Mitigation Parameter to Frequency & Responsible Monitoring Concern (MM) Implement MM Implement MM Implement MM Cost monitor Verification to Monitor Cost along cross-drainage structures where embankments are more susceptible to erosion by water runoff. 12. Payments will be linked to the completion of the works as indicated by the installation of erosion control measures to protect the works to the satisfaction of PSC/PPMU. 14. River Protect rivers and In sections along and near rivers and streams: Contractors At all times All rivers and Cost included Check Bi-weekly PCC, PPMU Cost met by 1. Rocks and stones will be disposed not to protection and maintain river flow streams with repair in contracts implementation PSC, PCC and bridge repair block rivers and streams. and reconstruction of items 1 to 4 PPMU project as part of day-to- PSC 2. In bridge repair and demolition sites, the works. staffing bridge structure will not be dropped into the river day project but alternative means will be used to avoid construction "dropping the bridge" into rivers/streams. This supervision will be done by "sawing" appropriate sections of the bridge and using cranes to lift these sections away or alternatively by construction of a platform onto which the bridge could be lowered. 3. Cofferdams, silt fences, sediment barriers or other devices will be used as appropriate based on the design to prevent migration of silt during excavation and boring operations within streams. If cofferdams are used, these will be dewatered and cleaned to prevent siltation by pumping from cofferdams to a settling basin or a containment unit. 4. Other erosion control measures above and covering open surfaces with grasses and creepers to reduce runoff will be implemented as early as possible in construction. 15. Water quality Prevent water quality 1. Store lubricants, fuels in dedicated Contractors Throughout All Project road Cost included Check Bi-weekly PCC, PPMU Cost met by enclosures at least 50 m from water bodies. PSC, PCC and impacts due to construction phase stretches and in contracts implementation negligence and ensure 2. Solid waste from construction activities and project-related of items 1 to10 PPMU project as part of day-to- PSC unavoidable impacts workers camps will not be thrown in rivers and facilities staffing day project managed effectively. other water courses (drainage, irrigation, etc.) 3. Construction storage/stockpiles shall be construction provided with bunds to prevent silted run-off. supervision 4. Stockpiled materials will be covered to reduce silted run-off. 5. No stockpiling or borrow sites at least 100m of water body.

Page 88

Impact mitigation Performance and Impact monitoring

Environmental Objective Proposed Mitigation Measures Responsible to Timing to Locations Mitigation Parameter to Frequency & Responsible Monitoring Concern (MM) Implement MM Implement MM Implement MM Cost monitor Verification to Monitor Cost 6. Work in rivers will be scheduled during dry season and work duration shall be as short as possible. 7. Immediate stabilization of bare slopes shall be undertaken. 8. Construction storage/stockpiles shall be provided with bunds to prevent silted run-off. 9. Stockpile areas and storage areas for hazardous substances shall be located away from water bodies. 10. Washing of machinery and vehicles in surface waters shall be prohibited.

16. Water Mitigate the impact of 1. Assess availability of water and evaluate Contractors Throughout Throughout project Cost included Check Bi-weekly PCC, PPMU Cost met by impact on use of local water resources to PSC, PCC and resources using local community construction phase site, construction in contracts implementation water resources. ensure that water utilization for Project shall not camps of items 1to11 PPMU project deplete local village supplies. as part of day-to- PSC staffing 2. Bring in project water by tanker as necessary. day project 3. Worker camps will be located at least 500m construction from the nearest settlement to prevent the supervision contamination of community-owned water resources. 4. Maintain close liaison with local communities to ensure that any potential conflicts related to common resource utilization for project purposes are resolved quickly. 5. Establish and implement guidelines to minimize the wastage of water during construction and at campsites. 6. Avoid or minimize use of river bed for construction materials. 7. Confine winning river materials to 20% of river width in any location and keep away from river banks. 8. Reinstate river banks if necessary. 9. Re-provision irrigation channels affected by works two weeks before commencement of works to the satisfaction of local community . 10. All irrigation canals along the alignment shall be clearly marked on the ground to prevent accidental dumping of fill materials into these canals.

Page 89

Impact mitigation Performance and Impact monitoring

Environmental Objective Proposed Mitigation Measures Responsible to Timing to Locations Mitigation Parameter to Frequency & Responsible Monitoring Concern (MM) Implement MM Implement MM Implement MM Cost monitor Verification to Monitor Cost 11. In case of accidental obstruction or damage, irrigation ditches and ponds shall be cleaned or repaired immediately. 17. Operation of Worker facilities not to 1. Worker camp location and facilities located at Contractors 1 & 2: During Project site, Cost included Check 1 & 2: Once for PCC, PPMU Cost met by least 500 m from settlements and agreed with workers camps cause nuisance or selection of locations construction camps in contracts. implementation each location, PSC, PCC and exploit forest of wildlife local communities and facilities approved by for workers camps. of items 1 to16 prior to PPMU project PSC and managed to minimize impacts. No resources. 3 to 16: Throughout establishment of staffing project facilities (construction camps, workers’ construction phase facilities camps, etc.) will be established within Dong Van 3 to 16: Bi-weekly Karst Plateau Geopark unless: a) prior approval

is obtained from DVKPGMB and UNESCO, and b) such activities will not cause negative impacts 1 to 16: as part of PSC on the protected geological resources and day-to-day project landscape within DVKPG. construction 2. Construction camps will be established in supervision areas with adequate natural drainage channels in order to facilitate flow of the treated effluents. 3. Hire and train as many local workers as possible. 4. Provide adequate housing for all workers at the construction camps and establish clean canteen/eating and cooking areas. 5. Portable lavatories (or at least pit latrines in remote areas) shall be installed and open defecation shall be prohibited and prevented by cleaning lavatories daily and by keeping lavatory facilities clean at all times. 6. Provide separate hygienic sanitation facilities/toilets and bathing areas with sufficient water supply for male and female workers. 7. Wastewater effluents from contractors’ workshops and equipment washing-yards will be passed through gravel/sand beds and all oil/grease contaminants will be removed discharging it into natural streams. Oil and grease residues shall be stored in drums awaiting disposal in line with the agreed Waste Management Plan and consistent with national and local regulations. 8. Predictable wastewater effluent discharges from construction works shall have the necessary permits from DONRE and local

Page 90

Impact mitigation Performance and Impact monitoring

Environmental Objective Proposed Mitigation Measures Responsible to Timing to Locations Mitigation Parameter to Frequency & Responsible Monitoring Concern (MM) Implement MM Implement MM Implement MM Cost monitor Verification to Monitor Cost authorities before the works commence. 9. Borrow pits and natural depressions with pre- laid impervious liners will be used to dispose of scarified/scraped asphalt, and then covered with soil. This will check potential groundwater contamination. 10. Options for completely or partially recycling scraped scarified materials will also be taken into account. 11. As much as possible, food shall be provided from farms nearby and bush meat supplies will be banned to discourage poaching. 12 Ban use of guns and hunting equipment by workers and dismiss workers taking or using green timber or hunting or in possession of wildlife. 13. Camp site will be cleaned up to the satisfaction of and local community after use. 14. Solid and liquid waste will be managed in line with Waste Management Plan. 15. All waste materials shall be removed and disposed to disposal sites approved by local authorities 16. Land used for campsites shall be restored to the original condition as far as practicable and the area shall be planted with appropriate trees / shrubs as soon as practicable after it is vacated and cleaned. 18. Sanitation and Control of infectious 1. Standing water will not be allowed to Contractors Throughout Throughout project Cost included Check Bi-weekly PCC, PPMU Cost met by Diseases accumulate in the temporary drainage facilities diseases. construction. site, workers camps in contracts. implementation PSC, PCC and or along the roadside to prevent proliferation of of items 1 to 4 PPMU project as part of day-to- PSC mosquitoes. staffing 2. Temporary and permanent drainage facilities day project will be designed to facilitate the rapid removal of construction surface water from all areas and prevent the supervision accumulation of surface water ponds. 3. Malaria controls ((e.g., provision of insecticide treated mosquito nets to workers, installation of proper drainage to avoid formation of stagnant water, etc.) and HIV-AIDS education will be implemented in line with social plans for the project.

Page 91

Impact mitigation Performance and Impact monitoring

Environmental Objective Proposed Mitigation Measures Responsible to Timing to Locations Mitigation Parameter to Frequency & Responsible Monitoring Concern (MM) Implement MM Implement MM Implement MM Cost monitor Verification to Monitor Cost 4. HIV/AIDS awareness and prevention program shall be implemented in line with social plans under the Project 19. Safety Ensure worker safety. 1. Implement the Worker and Public Safety Plan Contractors Throughout Throughout project Cost included Check Bi-weekly PCC, PPMU Cost met by (WPSP) prepared by PCC and instructs workers Precautions for the construction phase site in contracts implementation PSC, PCC and Workers in health and safety matters. of items 1 to 10 PPMU project 2. Establish safety measures as required by law as part of day-to- PSC Check staffing and by good engineering practice and provide day project compliance to first aid facilities that are readily accessible by construction Labour Code workers . supervision of Viet Nam, 3. Scheduling of regular (e.g., weekly tool box Decree 06/CP talks) to orient the workers on health and safety 1995, Decree / issues related to their activities as well as on 202 ND-CP proper use of PPE. OP 2002 and 4. Fencing on all excavation, borrow pits and Circular 13/ sides of temporary bridges BYT 24 Oct 5. Workers shall be provided with appropriate 1996. personal protective equipment (PPE) such as safety shoes, hard hats, safety glasses, ear plugs, gloves, etc. at no cost to the employee. 6. Where worker exposure to traffic cannot be completely eliminated, protective barriers shall be provided to shield workers from traffic vehicles. Another measure is to install channeling devices (e.g., traffic cones and barrels) to delineate the work zone. 7. Workers shall be provided with reliable supply of potable water. 8. Construction camps shall be provided with adequate drainage to avoid accumulation of stagnant water. 9. Construction camps shall be provided with toilets/sanitation facilities in accordance with local regulations to prevent any hazard to public health or contamination of land, surface or groundwater. These facilities shall be well maintained to allow effective operation. 10. Ensure reversing signals are installed on all construction vehicles. 20. Public safety Prevent accident with 1. Install barriers (e.g., temporary fence) at Contractors At all times Throughout project Cost included Check Bi-weekly PCC, PPMU Cost met by construction areas to deter pedestrian access to public in local throughout roads, borrow areas in contracts implementation PSC, PCC and the roadway except at designated crossing and other areas PPMU project

Page 92

Impact mitigation Performance and Impact monitoring

Environmental Objective Proposed Mitigation Measures Responsible to Timing to Locations Mitigation Parameter to Frequency & Responsible Monitoring Concern (MM) Implement MM Implement MM Implement MM Cost monitor Verification to Monitor Cost community points. construction phase utilized for the of items 1 to 4 as part of day-to- PSC staffing 2. The general public/local residents shall not be Project day project allowed in high-risk areas, e.g., excavation sites construction and areas where heavy equipment is in supervision operation and such sites have a watchman to keep public out. 3. Speed restrictions shall be imposed on Project vehicles and equipment when traveling within 50 m of sensitive receptors (e.g. residential, schools, temples, etc.). 4. Upon completion of construction works, borrow areas will be backfilled (if suitable materials are available, e.g., excavation spoils) or fenced. 21. Traffic Minimize disturbance 1. Implement the Temporary Traffic Contractors Throughout Throughout project Cost included Check Bi-weekly PCC, PPMU Cost met by Management Plan (TTMP) prepared by PCC Conditions of traffic and traffic construction phase site in contracts implementation PSC, PCC and congestion during detailed design phase. of items 1 to 8 PPMU project as part of day-to- PSC 2. Communicate to the public through local staffing officials regarding the scope and schedule of day project construction, as well as certain construction construction activities causing disruptions or access supervision restrictions. 3. In coordination with local traffic authorities, implement appropriate traffic diversion schemes to avoid inconvenience due to project operations to road users, ensure smooth traffic flow and avoid or minimize accidents, traffic hold ups and congestion 4. In coordination with local traffic officials, schedule transport of materials to avoid congestion, set up clear traffic signal boards and traffic advisory signs at the roads going in and out the road and bridge construction sites to minimize traffic build-up. 5. Provide safe vehicle and pedestrian access around construction areas. 6. Install bold diversion signs that would be clearly visible even at night and provide flag persons to warn of dangerous conditions (24 hours, as necessary) 7. Provide sufficient lighting at night within and in the vicinity of construction sites..

Page 93

Impact mitigation Performance and Impact monitoring

Environmental Objective Proposed Mitigation Measures Responsible to Timing to Locations Mitigation Parameter to Frequency & Responsible Monitoring Concern (MM) Implement MM Implement MM Implement MM Cost monitor Verification to Monitor Cost 8. Designate traffic officers in construction sites. 22. Archaeological Preservation of chance 1. Site agents instructed to keep a watching Contractors Throughout All areas. Cost included Check Before PCC, PPMU Cost met by finds of cultural and brief for relics and cultural construction. in contracts. implementation construction and PSC, PCC and archaeological relics. 2. Should any potential items be located, the artifacts. Check and report on of items 1 to 4 Bi-weekly checks. PPMU project identified during PSC and PPMU will immediately be contacted same day. staffing construction and work will be temporarily stopped in that as part of day-to- area. PSC 3. If the site supervisor determines that the item day project

is of potential significance, an officer from the construction Department of Culture and Information (DCI) will supervision be invited to inspect the site and work will be stopped. 4. Until DCI has responded to this invitation work will not re-commence in this location until agreement has been reached between DCI, PSC and PPC/PPMU as to any required mitigation measures, which may include excavation. 23. Enhancements Provide environmental Contractors to reconfirm and implement Contractors Throughout All areas. Cost included Confirmed Before PCC, PPMU Cost met by enhancements (e.g., landscaping, tree enhancement of the construction. in contracts. implementation construction and PSC, PCC and replanting) identified at the detailed design project of required Bi-weekly checks. PPMU project stage. enhancements staffing

as part of day-to- PSC day project construction supervision

OPERATIONAL STAGE

1. Soil erosion To minimize excessive 1. Ensure that storm drains and highway Provincial Throughout operation Slopes with Included in Check Semi-annual PPC Cost met by for erosion. drainage systems are periodically cleared to Department of protection measures operation and implementation PPC staffing maintain clear drainage to allow rapid dispersal Transport (PDOT) and new wash out. maintenance of items 1 to 3 of storm water flow. cost 2. Ensure rapid response in case of landslips and implement thorough maintenance programme along erosion-prone areas . 3. Undertake surveillance and re-vegetation for areas prone to erosion and landslips. 2. Road Safety Minimize road 1. Undertake road safety awareness campaigns Provincial Throughout operation All Project roads Included in Check Semi-annual PPC Cost met by for

Page 94

Impact mitigation Performance and Impact monitoring

Environmental Objective Proposed Mitigation Measures Responsible to Timing to Locations Mitigation Parameter to Frequency & Responsible Monitoring Concern (MM) Implement MM Implement MM Implement MM Cost monitor Verification to Monitor Cost accidents. for local residents and other road users of Department of operation and implementation PPC staffing Project roads. Transport (PDOT) maintenance of items 1 to 3 2. Install and maintain road warning signs and cost markings. 3. Monitor road accidents and implement necessary preventive measures (awareness campaigns, provision of appropriate road furniture to enhance road safety and control traffic).

3. Tree survival Ensure survival of Monitor survival of trees / shrubs and grass in PDOT and District During operation. All Project road Included in First three Semi-annual for PDOT and Cost met by planted trees. bioengineered slopes (e.g. at landslides, also Forestry Office stretches operation and years of 1st 3 years of DFO PDOT and DFO transplanted / compensatory planting trees) and (DFO) maintenance operation operation staffing replant, as necessary. cost

Page 95

C Environmental Monitoring

1. Compliance Monitoring 223. Table VIII.2 above also shows the program for monitoring the compliance on various provisions of the EMP during pre-construction, construction and operation phases. PCC needs to implement a number of measures during detailed design phase (e.g., incorporation of environmental design measures into the detailed design, preparation of method statements/SEMPs, etc.) and this will be confirmed by PPMU to ADB. During construction, most of the mitigation measures shall be implemented by the contractors and their environmental performance, in terms of implementation of such measures, shall be monitored by PCC. The timing or frequency of monitoring is also specified in Table VIII.2. During operation EMP implementation shall be the responsibility of PDOT. i) Design Stage 224. PPMU shall ensure that EMP measures for the design stage are incorporated in the detailed design. The effective incorporation of the EMP in the civil works contracts shall also be ensured be by PPMU with assistance from PCC and this, along with implementation of EMP provisions, shall be audited by ADB as part of the loan conditions. 225. Prior to implementation of the Project the IEE and EMP will be updated and amended, as necessary, by PCC after the detailed designs are complete and contracting arrangements are known. Such updating shall be based on reconfirmation and any additional information on the assumptions made at this feasibility stage on location scale and expected conditions of the Project. For example, in this case if there is additional land required (although not confirmed as yet) the designs may be amended and the environmental significance must be reviewed. Although no major additional impacts would be anticipated based on the information provided to date, the performance and evaluation schedules to be implemented during project construction can be reviewed, updated, and costs estimates can be revised if necessary. ii) Pre-construction Stage 226. Implementation of construction of the Project will need to comply with environmental requirements and clearance that has been obtained from DONRE for the whole Project at a provincial level for any statutory environmental assessment or an indication that no further assessment is required. PCC will also need to confirm that Contractor(s) and their suppliers have complied with all statutory requirements for permits from DONRE and provincial authorities. PCC shall also check that Contractor(s) have all the necessary valid licenses and permits for use of powered mechanical equipment if necessary and the use of local water supplies (and to construct or operate plant such as for cement batching or asphalt/bitumen (if required) in line with all environmental regulations and permit conditions from provincial authorities. (N.B. local suppliers of cement and bitumen will be preferred if practicable). iii) Construction Stage 227. The PCC shall undertake regular monitoring of the contractor’s implementation of mitigation measures specified in the Project EMP and SEMPs. Likewise, as part of its day to day project supervision, the PSC shall ensure that contractors comply with the Project EMP and SEMPs. iv) Operational Stage 228. PDOT shall implement the EMP mitigation and monitoring requirements during operation such as monitoring of erosion control measures, survival of planted trees, etc.

Page 96

Accidents along the Project roads shall also be monitored as basis for implementation of mitigation measures to improve road safety.

2. Environmental Effects Monitoring 229. As shown in Table VIII.3, PCC shall undertake baseline environmental monitoring for air quality, noise and surface water quality. One-time sampling shall be conducted prior to start of site works at the specified locations. During construction, PCC shall undertake quarterly monitoring of surface water quality and semi-annual monitoring of air quality and noise in the same locations sampled during pre-construction. Additional sampling occasions shall be carried out and additional parameters shall be analyzed (as necessary) to validate complaints and/or investigate pollution events caused by the project.

D Reporting 230. SC/PPMU shall submit the following environmental monitoring reports to ADB: 231. Baseline Monitoring Report: The results of baseline data collection carried out by PCC on air quality, noise and surface water quality (as specified in the EMP) shall be submitted to ADB prior to commencement of civil works. 232. Environmental Monitoring Reports: Environmental monitoring reports shall cover the status of EMP implementation in terms of required mitigation measures for different project phases, results of environmental effects monitoring (air quality, noise and surface water quality), necessary remedial actions to effectively address negative environmental impacts due to project implementation, status of environmental capacity building activities as well as documentation of complaints received and corresponding action/resolution. The environmental monitoring reports will be submitted to ADB semi- annually during the construction period and annually for two years after completion of construction. Table VIII.3: Summary of Estimated Costs for EMP Implementation (4.5 years)a A. Estimated cost for all six Project provinces A.1 Environment specialists in PCC: cost includes remuneration, air fare (for international only) and per diemb  One (1) international: 8 person-months, intermittent 208,500  Two (2) national: 100 person-months, full-time 375,000 A.2 Environmental effects monitoring, training/orientation, local transportation, suppliesb 200,000 A.3 Environmental mitigation measures included in project cost, bid cost A.4 Construction of two forestry check points: USD7,000 each (in Bac Kan and Tuyen 14,000 Quang provinces)c Total for all Project provinces USD 797,500 B. Estimated cost for Ha Giang onlyd B.1 Environment specialists in PCC: cost includes remuneration, air fare (for international only) and per diemb  One (1) international: 2 person-months, intermittent 44,500  One (1) national: 21 person-months, intermittent 79,000 B.2 Environmental effects monitoring, training/orientation, local transportation, suppliesb 42,000 Total for Ha Giang USD 165,500 aincludes design and construction phases bincluded in PCC cost cincluded in contractor’s bid cost or funded by potential co-financier dpro-rated based on total length of Project roads in the province

Page 97

Table VIII.4: Environmental Effects Monitoring Plan for the Project roads in Ha Giang Province Environmental Aspect Parameters Location Means of Monitoring Frequency Implementation Responsibility PRE-CONSTRUCTION 1. Ambient surface water pH, temperature, turbidity, dissolved 1. At each Project road, establish sampling Analytical methods outlined in QCVN 08:2008/BTNMT Once, during the month prior to PCC quality oxygen (DO), oil and grease, and total points in at least three major river crossings (Viet Nam National Regulation for Surface Water construction. suspended solids (TSS) where bridge repairs and replacement will be Quality) undertaken. At river crossings, collect water samples 50m before For rivers/streams close to 2. Establish sampling points on river/stream (upstream) and 50m after (downstream) the bridges at construction/workers’ camps, the following sections that are close to construction camps mid-width and mid-depth. additional parameters shall also be (i.e., rivers that will most likely receive run- Submit baseline monitoring report to ADB at the end of analyzed: biological oxygen demand – 5 off/discharge from construction/workers’ the detailed design period (For monitoring report days (BOD5), coliform and fecal coliform. camps). content, see Chapter V, Sec. A.7 of the IEE).

2 Ambient air quality and Total suspended particulate (TSP) At each Project road, undertake field Analytical method outlined in QCVN 05:2009/BTNMT Once, during the month prior to PCC noise sampling at representative sensitive (Viet Nam Ambient Air Quality Standard) construction. receptors (SR). That is, sampling stations shall be established and sampled for various Submit baseline monitoring report to ADB at the end of SR type as follows: (i) residential area (ii) the detailed design period (For sampling and monitoring school, (iii) temple and (iv) hospital/health report requirements, see Chapter V, Sec. A.7 of the center. IEE).

3. Noise Noise levels dB(A) covering different Same stations established for ambient air Analytical method outlined in TCVN 5949: 1998 (Noise Once, during the month prior to PCC periods specified in TCVN 5949: 1998 quality in Public and Residential Areas– Allowable Noise construction. (Noise in Public and Residential Areas– Levels). Allowable Noise Levels).

Submit baseline monitoring report to at the end of the detailed design period (For sampling and monitoring report requirements, see Chapter V, Sec. A.7 of the IEE). CONSTRUCTION 1. Ambient surface water 1. pH, temperature, turbidity, dissolved 1. Same stations sampled during pre- Analytical methods outlined in QCVN 08:2008/BTNMT Quarterly as well as in response to PCC quality oxygen (DO), oil and grease, and total construction phase. (Viet Nam National Regulation for Surface Water complaints and during pollution suspended solids (TSS) Quality) events 2. Other locations to validate complaints or At river crossings, collect water samples 50m before 2. For rivers/streams close to during pollution events (e.g., fuel spill, etc.) (upstream) and 50m after (downstream) the bridges at construction/workers’ camps, the following mid-width and mid-depth. additional parameters shall also be Include results of environmental effects monitoring in analyzed: biological oxygen demand – 5

Page 98

Environmental Aspect Parameters Location Means of Monitoring Frequency Implementation Responsibility days (BOD5), coliform and fecal coliform. the semi-annual EMP implementation monitoring report to be submitted by PPMU to ADB. 3. Other relevant parameters to be analyzed to validate complaints and pollution events

2 Ambient air quality and Total suspended particulate (TSP) 1. Same stations sampled during pre- Analytical method outlined in QCVN 05:2009/BTNMT Semi-annual and in response to PCC noise construction phase. (Viet Nam Ambient Air Quality Standard) complaints

2. Other locations to validate complaints Include results of environmental effects monitoring in the semi-annual EMP implementation monitoring report to be submitted by PPMU to ADB. 3. Noise Noise levels dB(A) covering different 1. Same stations sampled during pre- Analytical method outlined in TCVN 5949: 1998 (Noise Semi-annual and in response to PCC periods specified in TCVN 5949: 1998 construction phase. in Public and Residential Areas– Allowable Noise complaints (Noise in Public and Residential Areas– Levels). Allowable Noise Levels). 2. Other locations to validate complaints Include results of environmental effects monitoring in the semi-annual EMP implementation monitoring report to be submitted by PPMU to ADB..

Page 99

E Capacity Building 233. In Viet Nam, the environmental assessment process is established but environmental awareness and capability for implementation of EMP in infrastructure projects of both the executing agency (PPC) and the implementation agency (PPMU) are limited and in development. There is no staff with direct responsibility to bring environmental issues to the notice of senior management. The status quo is that in PPMU is that engineering officers may be delegated to check environmental matters on an ad hoc basis. There is no capacity to check the adequacy of the Project EMP or SEMPs. The IEEs and EMP are referred to the environmental department in DONRE for approval. The environmental department in MOT is not directly involved with project implementation. In the long term it is recommended that a new environmental management unit should be set up to improve this capacity in the PPMU in PDOT that could work with the various environmental and forestry agencies as required. 234. The most significant challenge is the lack of human and financial resources and necessary infrastructure. To address this constraint, PDOT/PPMU will designate a full time staff as environment and safety officer (ESO) to handle the environmental aspects of the Project during implementation stage. The ESO and other relevant staff of PPMU and PDOT will be trained by the environment specialists of the PCC based on the indicative terms of reference presented in Table VIII.5. 235. The requisite ESO staff in PPMU should be delegated prior to the commencement of the tendering for the detailed design activities in order to work full time with PCC to ensure the inclusion of environmental requirements can be translated into contractual works for completion also respond to unexpected circumstances. The PCC environmental specialists can then train the environmental officers (ESO) in PPMU “on the job”. The ESO can initially fall back on assistance from PCC as they develop experience. 236. The PCC will also conduct workers’ orientation on Project EMP and SEMP provisions. Such orientation shall be periodically conducted by the PCC as every new contractor is engaged. The ESO in PPMU can take over this role as they develop capacity. 237. The table below shows the indicative terms of reference for the environmental management capacity building activity to be conducted by PCC for PPMU and PDOT staff tasked to oversee EMP implementation.

Page 100

Table VIII.5: Indicative Terms of Reference for Environmental Management Capacity Building of PPMU and PDOT

Objective 1. Build capacity and procedures in undertaking systematic environmental assessments in accordance with Government regulations and ADB guidelines. 2. Provide training on international best practice on environmental management, monitoring and reporting. 3. Provide guidance on how to effectively incorporate environmental measures into project design and how to incorporate EMP provisions into tender and contract documents.

Tasks/Scope of Work 1. Undertake training needs analyses and review prevailing government regulations and donor guidelines governing the assessment and management of environmental impacts for road development; 2. Review the skills of PPMU and PDOT staff to establish existing capacity on environmental assessments, environmental monitoring and implementation of mitigation measures for road development project; 3. Prepare the training plan and associated materials (modules); 4. Deliver the training which may be through a combination of hands- on assistance, on-the-job training, and training workshops; 5. Evaluate the effectiveness of the training measuring improvements in attitudes and skills achieved; 6. Modify the training modules as necessary; 7. Hand-over the amended training modules to the project manager for use in the delivery of the training; and 8. Prepare report on result of training. Recommended Within 6 months from start of civil works Timeframe

Target participants Staff in PPMU and PDOT responsible for environmental management.

Staff Resources International and national environmental specialist with at least 15 years experience on environmental management of road projects and must possess relevant post-graduate degree in civil engineering, environmental management and other relevant courses. With working knowledge of safety issues and at least 3 years experience in conducting environmental management training.

Page 101

IX. CONCLUSIONS AND RECOMMENDATIONS

238. This IEE concludes that the construction impacts will be manageable if the mitigation measures are implemented thoroughly. The EMP is based on the type, extent and duration of the identified environmental impacts. The EMP has been prepared by close reference to best practices and in line with SPS. 239. This IEE study was carried out when the Project roads were at the initial stage of design during the TA 7245 (VIE). Secondary and primary data were used to assess the environmental impacts in a comprehensive manner and public consultation and route reconnaissance were carried out in order complete the environmental assessments and recommend suitable mitigation measures. The IEE report provides a picture of potential environmental impacts associated with the upgrading of the Project roads and suitable mitigation measures have been recommended. The EMP will be reviewed by the PCC as a basis for preparing SEMPs. Both Project EMP and SEMPs will be included in bidding documents for civil works. In the event that any design details for the locations or scope of the Project roads are changed, the IEE and EMP shall be reviewed and revised accordingly and submitted to ADB for review and clearance. 240. The upgrading of the Project roads offers a robust option for the enhancement of the existing road network. Several actions are required during the detailed design stage to minimize impacts to acceptable levels. The negative environmental impacts from the rehabilitation will mostly take place during the construction stage. The construction impacts should be very predictable and manageable and with appropriate mitigation few residual impacts are likely. Additional human and financial resources will be required to improve environmental capability and to progress and achieve necessary statutory compliance and environmental clearance certification for the Project roads or associated activities that also require environmental permits under the environmental laws of Viet Nam. 241. The responsibilities for the implementation of mitigation measures and the parities responsible will be clearly defined in contracts and agreements and the implementation by various parties will be monitored by PPMU with assistance from PCC and PSC. 242. Most of the anticipated environmental impacts related to the the Project roads will take place during the construction phase, there are no identifiable cumulative impacts during operation. The implementation of the environmental mitigation measures during the construction period shall be the responsibility of the contractors and shall be closely monitored by the PSC and PCC and these requirements will be included in contracts. PDOT will maintain the road and shall undertake the appropriate operational mitigation measures for maintenance during the lifetime of the Project roads. 243. Whereas the implementation of the environmental mitigation measures during the construction period will be assigned to the contractors, experience suggests that contractors may have little impetus or interest to deal with environmental problems in the absence of performance linked criteria. Therefore, the required environmental mitigation must be clearly described in the contract documents at the bidding stage and environmental performance and the completion of mitigation should be linked to payment milestones in the contracts. 244. Contractor environmental awareness training will undertaken by the PCC and this can assist PPMU to develop environmental awareness at all levels. It will require sustained effort over several years to achieve proactive management of environmental responsibilities but TCNMP and other previous ADB projects have also included provision to consolidate this process and over time so that environmental improvements can accrue in line with good sustainable practice and ADB guidelines. The ESO in the PPMU will be supported in the short term by the PCC who will be able to liaise with and advise the PPMU to better utilize the available staff resources to support environmental management. This capability can be used to extend environmental awareness for the

Page 102

contractors in the short term. In the medium to long term PPMU can strengthen the support their environmental management and dovetail the efforts with the environmental officers in MOT. At the completion of the TCNMP the environmental officers in PPMU will be retained in PPMU and their environmental obligations could be more easily taken up for more ambitious projects in future. 245. The construction is restricted to the existing road corridor and as far as can be ascertained at this stage the will be some small areas of land required where there road geometry is improved but these areas will generally be small and there is not likely to be any significant additional land required to complete the construction. However, it is possible that some additional land may be required at the detailed design stage. A resettlement plan and resettlement framework have been prepared to establish policies and procedures for payment of compensation to affected people for lost or damage assets. The scope of land acquisition impacts, where they occur, will be limited to the areas of the road where the geometry needs to be adjusted and in thee areas there will be some displacement of housing and affected people will experience small losses of crops, trees, fences or other secondary structures. 246. Environmental impact and compliance monitoring activities will focus on compliance with license conditions and EMP provisions, recording implementation of mitigation measures, recording environmental parameters, reviewing contractor environmental performance and proposing remedial actions to address unexpected impacts and complaints. 247. The EMP and SEMP prepared for the Project, will be used as a basis for an environmental compliance program in a regular programme of environmental monitoring and auditing. In addition, any conditions included as part of the environmental compliance from the Government (MONRE/DONRE) will also be included as a basis for the environmental monitoring and compliance program. Therefore, continued monitoring of (i) the implementation of mitigation measures, (ii) the implementation of the conditions of environmental compliance and (iii) the environmental impact related to the maintenance of the Project roads will be carried out regularly as scheduled in the EMP. Environmental monitoring reports will be submitted semi-annually by PPMU to ADB. 248. The IEE report is prepared based on the preliminary designs for rehabilitation and upgrading proposals along the specified routes. At the implementation stage, PPMU through PCC will make arrangements to monitor the schedules of mitigation measures and conduct of environmental effects monitoring activities specified in the EMP. With these measures in place, environmental impacts of the Project should be manageable and will not result in any residual impacts which are above accepted environmental standards. No further or additional impact assessment is considered necessary at this stage. .

Page 103

Appendix A: Selected Photographs

Photograph 1 TL176A Typical road Km 00.0

Photograph 2 TL176A Typical road Km 06.0

Photograph 3 TL176A Typical road and bridge Km 15.4

Page 104

Photograph 4 TL176A Typical road and bridge Km 18.2

Photograph 5 TL183 Typical road Km 3.1

Photograph 6 TL183 Typical road Km 6.0

Page 105

Photograph 7 TL183 Typical road and bridge Km 10.9

Photograph 8 TL183 Typical road and bridge Km 30.3

Page 106

Appendix B: Information Disclosure, Consultation and Participation

Appendix B Summary of Information Disclosure, Consultation and Participation

Tổng kết công tác Tham vấn cộng đồng Bảng Ax B 1 – Questions posed to provincial officials (July 2010) - Các câu hỏi dành cho các Cơ quan chính quyền địa phương

Số thứ tự Information Provided - Các thông tin cơ bản về dự án 1 As consultants for the ADB Project Transport Connectivity Project in Northern Mountainous Provinces we are collecting information from provincial officials.

VN Chúng tôi là Đơn vị vTư vấn của ADB và đang thực hiện công tác thu thập thông tin từ chính quyền địa phương

2 Do you know about the road upgrading Project? Let me clarify

VN Ông có biết về dự án này không ? Hãy để tôi giải thích

3 In HG there will be three roads upgraded under this project (reduced to two roads)

3VN Tại các tỉnh Hà Giang / Yên Bái / Cao Bằng / Tuyên Quang / Lào Cai / Bắc Kạn sẽ có 20 tuyến đường đựoc nâng cấp, cải tạo trong dự án này (reduced to 12 roads)

4 The roads are :

4VN The roads include - Các tuyến đường bao gồm:

Ha Giang Province - TL 176A, TL 177 and TL 183. (TL 177 has been excluded from the project scope)

5 The roads will be widened by up to 1m

VN Các tuyến đường sẽ được mở rộng từ 1m

6 The project will be detailed designed in 2011 and contractors will be selected later in 2011

VN Dự án đựoc thiết kế kỹ thuật vào năm 2011 cuối năm 2011 sẽ tiến hành đấu thầu xây lắp

7 Construction will be for a few weeks to months in each location but will complete all the project in 2013

VN Công tác xây dựng bất đầu tròng vòng vài tuàn hay vài tháng tùy tuyến đường và sẽ đựoc hoàn thành vào năm 2013

Page 108

QUESTIONAIRES/ PHIẾU THU THẬP THÔNG TIN Name: Nguyen The Phuong VN: Họ và tên Nguyễn Thế Phương Province/District Ha Giang VN: Tỉnh/Huyện Hà Giang Workplace Ha Giang DONRE VN: Cơ quan Sở Tài nguyên và Môi trường Hà Giang Position: Deputy Manager of Resource Management Department VN: Chức vụ Phó Trưởng phòng Quản lý tài nguyên Time:/ Date 2 p.m – July 25th 2010 VN:Giờ/ Ngày/Tháng 14 giờ ngày 25/7/2010

Number / STT Các câu hỏi Questions Answers/Trả lời

1 Do you agree on the road upgrading project? Yes

VN Anh có đồng ý với dự án này không ? Có

2 What kinds of forests do you know in your district witin about 50m-100m from the Project road No forest

VN Trong phạm vi 50m kể từ tuyến đường được nâng cấp, anh có biết có khu vực rừng rậm nào không ? Không có rừng rậm

3 Are there any protected areas or protected forests around the area within 1km from the Project roads? No

VN Trong phạm vi 1km từ tuyến đường, anh có biết có khu vực nào cần được bảo tồn hay không ? Không

4 Are any cultural relic or heritage in the area of 50m from the Project roads? No

VN Liệu có di tích văn hoá nào trong phạm vi 50 m kể từ tuyến đường? Không Are there any special protected building within 50m from the road? (military base or special protected building, 5 No etc.) VN Có các di tích lịc sử, văn hoá, khảo cổ gần tuyến đường hay không? Không Where are the protected forest other areas of archaeological, religious, cultural or historical sites near the 6 Location of waste dumping must be cared roads? VN Theo ý kiến của anh, các vấn đề môi trường cần lưu ý trong dự án là gì? Cần lưu ý các vị trí đổ đất, đá thải

7 In your opinion, what can be environmental problems we should pay attention to? Noise, dust during construction

VN Theo ý kiến của quý vị, có vấn đề môi trường nào chúng ta cần chú ý? Tiếng ồn, khói bụi khi thi công dự án

8 Does your department have enough capability to support the project with processing of licenses and permits Yes

VN Cơ quan của quý vị có đủ khả năng để hỗ trợ dự án về các thủ tục hành chính (chứng nhận và cấp phép)? Có khả năng hỗ trợ theo phân cấp

Page 109

Number / STT Các câu hỏi Questions Answers/Trả lời

Yes Are there any quarries/borrow pits in your district about 1km from the Project roads? What are the procedures to 9 for exploiting rock based materials in the province? Exploiting quarries must follow regulations from the provincial government. Có mỏ đá, mỏ nằm trong quy hoạch chung Có Mỏ đá hay Mỏ vật liệu trong phạm vi 1 km kể từ tuyến đường hay không? Trình tự thủ tục tiến hành khai VN của tỉnh, được khai thác sau khi có đủ các thủ thác đá trong khu vực? tục cấp phép theo quy định của địa phương There are observation stations in Bac me, Bac 10 Are there any meteorological and hydrography observation stations? Quang, Tan Quang Intersection; starting point of Bac Quang – Xin Man Road Có các trạm quan trắc ở trung tâm các huyện VN Trong khu vực dự án có trạm quan trắc khí tượng thuỷ văn nào không ? Bắc Mê, Bắc Quang, ngã ba Tân Quang điểm đầu của đường Bắc Quang đến Xín Mần 11 Do you have any suggestions to reduce such environmental impacts ? No

VN Anh có kiến nghị gì để giảm thiểu tác động môi trường hay không ? Không

12 Do you have any other suggestions ideas? No

VN Anh có kiến nghị gì khác nữa không ? Không

Page 110

Appendix B2 Public Consultation with affected people near TL176A and TL183 (September 2009) Table Ax B 2.1 – Questions posed to local people in Ha Giang Province Number Question

1 Do you agree with the project of expanding the road? 2 When upgraded, does the road contribute to develop economy of local ( traveling, agriculture)? How it facilitates local traffic? Do you have any idea on the environmental, land, utilities issues, compensation, ground clearing? What are potential 3 environmental problems of this project? 4 Do you have any idea to reduce the effect on environment? 5 Suggestions / other opinions.

Table Ax C 2.2 – Responses from local people in Ha Giang Province A. Road TL176A – Ha Giang

1. 2. 3. 4 5 Date Participants Occupation Location Agree Develop Issues raised / Concerns Ideas to reduce environmental with Other suggestions economy expressed Impacts Project

1 15/9/09 Mr. Tran Farmer Na lia – Du Yes Yes - Water supply not available - Project Steering Committee - Contractors inform the Van Tai, a Gia – Yen - Electricity from national web should make public the plan for local people the due family of 6 Minh District - It is good that the project will the project implementation time for starting the with 3 improve living standard in the village -The contractors must take project works females - The project must be done in a way effective measures to reduce the - Project should be that minimize the negative impacts on negative impacts due to the road started at the soonest the environment and the everyday life upgrading works possible practices of the local people - Give assistance to agricultural production in the project areas 2 15/9/09 Mr. Trinh Famer Cup Pao - Du Yes Yes - Water supply not available - Needs of assistance for the - PMU officer should be Van Thanh, Gia – Yen - Electricity from national web local people to get clean water the one in charge of a family of 4 Minh District - It is good that the project will supply handling compensation with 2 improve living standard in the village -The contractors must take payments to the local females - Agreement of compensation on land effective measures to reduce the people acquisition by the project negative impacts due to the road - Any actions which are - The project steering committee upgrading works beneficiary to the local should pay attention on activities people must be directed development for the region of the by project officers project 3 15/9/09 Mr. Lu Xa Farmer Cup Pao-Du Yes Yes - Water supply not available - Needs of assistance for the - Improvements of the Tua, a family Gia – Yen - Electricity from national web local people to get clean water project road must be of 3 with 1 Minh District - It is good that the project will supply directed by the PMU female improve living standard in the village - Project gives some small - Start to make road - Agreement of compensation on land assistances for planting trees improvement acquisition by the project with high market values immediately

Page 111

- Compensation cost must be agreed and recognized by the project and local people 4 15/9/09 Mr. Sung A Farmer Na lia – Du Yes Yes - Water supply not available - Project Steering Committee - Contractors inform the Chu, a Gia – Yen - Electricity from national web should make public the plan for local people the due family of 5 Minh District - It is good that the project will the project implementation time for starting the with 2 improve living standard in the village project works females - The project must be done in a way - Project should be that minimize the negative impacts on started at the soonest the environment and the everyday life possible practices of the local people 5 15/9/09 Mr. Ly A Farmer Lung Ho 3 – Yes Yes - Water supply not available -The contractors must take - PMU officer should be Tien Lung Ho – - Electricity from national web effective measures to reduce the the one in charge of Yen Minh - It is good that the project will negative impacts due to the road handling compensation District improve living standard in the village upgrading works payments to the local - Agreement of compensation on land - The PMU talks with people people acquisition by the project about the cost of land and crop - Any actions which are - Compensation cost must be agreed lost due to the project beneficiary to the local and recognized by the project and people must be directed local people by project officers 6 15/9/09 Mr. Giang A Farmer Lung Ho 3 – Yes Yes - Water supply not available - Needs of assistance for the - Improvements of the Phao, a Lung Ho – - Electricity from national web local people to get clean water project road must be family of 4 Yen Minh - It is good that the project will supply directed by the PMU with 2 improve living standard in the village -The contractors must take - Start to make road females - Agreement of compensation on land effective measures to reduce the improvement acquisition by the project negative impacts due to the road immediately - The project steering committee upgrading works should pay attention on activities development for the region of the project 7 15/9/09 Mr. Vang A Farmer Nam Nga – Yes Yes - Water supply not available - Project Steering Committee - Contractors inform the Thuan, a Yen Minh - Electricity from national web should make public the plan for local people the due family of 4 District - It is good that the project will the project implementation time for starting the with 1 improve living standard in the village project works female - The project must be done in a way - Project should be that minimize the negative impacts on started at the soonest the environment and the everyday life possible practices of the local people 8 15/9/09 Mr. Sung A Farmer Nam Nga – Yes Yes - Water supply not available - Project Steering Committee - Contractors inform the Khua, a Yen Minh - Electricity from national web should make public the plan for local people the due family of 4 District - It is good that the project will the project implementation time for starting the with 3 improve living standard in the village -The contractors must take project works females - Agreement of compensation on land effective measures to reduce the - Project should be acquisition by the project negative impacts due to the road started at the soonest - The project steering committee upgrading works possible should pay attention on activities - Give assistance to agricultural development for the region of the production in the project areas project

Page 112

9 15/9/09 Mr. Giang A Farmer Nam Nga – Yes Yes - Water supply not available - Needs of assistance for the - PMU officer should be Chais, a Yen Minh - Electricity from national web local people to get clean water the one in charge of family of 4 District - It is good that the project will supply handling compensation with 1 improve living standard in the village -The contractors must take payments to the local female - Agreement of compensation on land effective measures to reduce the people acquisition by the project negative impacts due to the road - Any actions which are - Compensation cost must be agreed upgrading works beneficiary to the local and recognized by the project and people must be directed local people by project officers

Page 113

B. Road TL183 – Ha Giang

1. 2. 3. 4 5 Name of Date Profession Location Agree participants Develop Issues raised / Concerns Ideas to reduce environmental with Other suggestions economy expressed Impacts Project

1 13/9/09 Mrs. Doan Farmer Yen Trung – Yes Yes - Water supply not available - Project Steering Committee - Contractors inform the Thi Thao, a Tien Yen – - Electricity from national web should make public the plan for local people the due family of 8 Quang Binh - It is good that the project will the project implementation time for starting the with 4 District improve living standard in the village -The contractors must take project works females - The project must be done in a way effective measures to reduce the - Project should be that minimize the negative impacts on negative impacts due to the road started at the soonest the environment and the everyday life upgrading works possible practices of the local people - Give assistance to agricultural production in the project areas 2 13/9/09 Mrs. Nong Farmer Yen Trung – - Water supply not available - Needs of assistance for the - PMU officer should be Thi May, a Tien Yen – - Electricity from national web local people to get clean water the one in charge of family of 7 Quang Binh - It is good that the project will supply handling compensation with 4 District improve living standard in the village -The contractors must take payments to the local females - Agreement of compensation on land effective measures to reduce the people acquisition by the project negative impacts due to the road - Any actions which are - The project steering committee upgrading works beneficiary to the local should pay attention on activities people must be directed development for the region of the by project officers project 3 13/9/09 Mr. Doan Retired Yen Trung – - Water supply not available - Needs of assistance for the - Improvements of the Trong Luong, Tien Yen – - Electricity from national web local people to get clean water project road must be a family of 6 Quang Binh - It is good that the project will supply directed by the PMU with 4 District improve living standard in the village - Project gives some small - Start to make road females - Agreement of compensation on land assistances for planting trees improvement acquisition by the project with high market values immediately - Compensation cost must be agreed and recognized by the project and local people 4 13/9/09 Mr. Nong Van Farmer Yen Trung – - Water supply not available - Project Steering Committee - Contractors inform the Thanh, a Tien Yen – - Electricity from national web should make public the plan for local people the due family of 4 Quang Binh - It is good that the project will the project implementation time for starting the with 2 District improve living standard in the village project works females - The project must be done in a way - Project should be that minimize the negative impacts on started at the soonest the environment and the everyday life possible practices of the local people 5 13/9/09 Mrs. Vu Thi Teacher, Pho Moi, - Water supply not available -The contractors must take - PMU officer should be Dieu, a family Yen Binh, - Electricity from national web effective measures to reduce the the one in charge of of 3 with 1 Retired Quang Binh - It is good that the project will negative impacts due to the road handling compensation female District improve living standard in the village upgrading works payments to the local - Agreement of compensation on land - The PMU talks with people people

Page 114

acquisition by the project about the cost of land and crop - Any actions which are - Compensation cost must be agreed lost due to the project beneficiary to the local and recognized by the project and people must be directed local people by project officers 6 13/9/09 Mr. Nguyen Commune Pho Moi, - Water supply not available - Needs of assistance for the - Improvements of the Van Doanh, a People Yen Binh, - Electricity from national web local people to get clean water project road must be family of 4 Committee Quang Binh - It is good that the project will supply directed by the PMU with 2 staff District improve living standard in the village -The contractors must take - Start to make road females - Agreement of compensation on land effective measures to reduce the improvement acquisition by the project negative impacts due to the road immediately - The project steering committee upgrading works should pay attention on activities development for the region of the project 7 13/9/09 Mr. Le Trong Business Pho Moi, - Water supply not available - Project Steering Committee - Contractors inform the Hy, a family Yen Binh, - Electricity from national web should make public the plan for local people the due of 3 with 2 Quang Binh - It is good that the project will the project implementation time for starting the female District improve living standard in the village project works - The project must be done in a way - Project should be that minimize the negative impacts on started at the soonest the environment and the everyday life possible practices of the local people 8 13/9/09 Mrs. Nguyen Business Pho Cao, - Water supply not available - Project Steering Committee - Improvements of the Thi Nga, a Dong Yen, - Electricity from national web should make public the plan for project road must be family of 4 Quang Binh - It is good that the project will the project implementation directed by the PMU with 2 District improve living standard in the village -The contractors must take - Start to make road females - Agreement of compensation on land effective measures to reduce the improvement acquisition by the project negative impacts due to the road immediately - The project steering committee upgrading works should pay attention on activities - Give assistance to agricultural development for the region of the production in the project areas project 9 13/9/09 Mrs. Nguyen Business Pho Cao, - Water supply not available - Needs of assistance for the - PMU officer should be Thi Lam, a Dong Yen, - Electricity from national web local people to get clean water the one in charge of family of 4 Quang Binh - It is good that the project will supply handling compensation with 2 District improve living standard in the village -The contractors must take payments to the local females - Agreement of compensation on land effective measures to reduce the people acquisition by the project negative impacts due to the road - Any actions which are - Compensation cost must be agreed upgrading works beneficiary to the local and recognized by the project and people must be directed local people by project officers 1 13/9/09 Mrs. Nguyen Farmer Pho Cao, - Water supply not available - Project Steering Committee - PMU officer should be 0 Thi Lam, a Dong Yen, - Electricity from national web should make public the plan for the one in charge of family of 4 Quang Binh - It is good that the project will the project implementation handling compensation with 3 District improve living standard in the village -The contractors must take payments to the local females - The project must be done in a way effective measures to reduce the people that minimize the negative impacts on negative impacts due to the road - Any actions which are the environment and the everyday life upgrading works beneficiary to the local practices of the local people - Give assistance to agricultural people must be directed production in the project areas by project officers

Page 115

1 13/9/09 Mrs. Nguyen Farmer Pho Cao, - Water supply not available - Project Steering Committee - Contractors inform the 1 Thi Le, a Dong Yen, - Electricity from national web should make public the plan for local people the due family of 3 Quang Binh - It is good that the project will the project implementation time for starting the with 2 District improve living standard in the village project works females - Agreement of compensation on land - Project should be acquisition by the project started at the soonest - The project steering committee possible should pay attention on activities development for the region of the project

Page 116

Page 117

Page 118

Table Ax B 3 – Responses from Provincial FPD on Nature Reserves DETAILED RESPONSES TO QUESTIONNAIRE FOR NATURE RESERVES ASSESSMENT Ha Giang Questions 176A Near nature reserve Du Gia Provincial road 176A is 73 km long. The road’s section that will be improved by the project (from km 38 to km 73) does not pass through the NR. Starting point of the project road’s section is 10km far from Du Gia NR. [field 1. Length of the Provincial Road that passes through the buffer zone of Nature Reserve ? inspection and maps obtained Feb 2011 showed Du Gia Nature Reserve buffer zone to be 2.5km from the start of the project road at its nearest point.] 2. The distance from the Road, at the nearest point, to the core zone of Nature Reserve? It is 10km. Mainly agricultural land & gardens allotted to individual households. [field inspection Feb 2011 showed occasional 3. Current land use along the Project Road (kinds of land ? managed by whom ) plantation forests also. It is 10 km [field inspection and maps obtained Feb 2011 showed Du Gia Nature Reserve buffer zone to be 2.5km 4. Distance to the nearest protected forest/natural forest/dense forests from Project Road? from the start of the project road at its nearest point 5. Is there protected historical or cultural site alongside the road and distance of nearest point from the Project Road? No historical or cultural sites alongside the road 176A It is very far from Du Gia NR. [field inspection and maps obtained Feb 2011 showed Du Gia Nature Reserve buffer 6. Distance of Project Road from known habitat/frequented areas of the Tonkin snub-nosed monkey (Rhinopithecus zone to be 2.5km from the start of the project road at its nearest point. According to FPD The habitat frequented by avunculus) and other endangered / threatened / rare species within the Nature Reserve? Rhinopithecus avunculus is much further to the south and west but the distance is not specified. 7. Could you provide to us the Map of the Nature Reserve that includes the Project Road? Yes, the map could be provided 8. Do you have Management Board for Nature Reserve ? How many persons are there in the Management Board ? Yes, the management board has 4 people 9. When was the Nature Reserve established ? by whom and which decision ? (some main outlines of the decision The NR was established in 1994 by Decision 647/QĐ, dated 24/11/1994, by Ha Giang PPC should be described 10. Do you have any programmes to protect the rare or endangered species in the Nature Reserve ? If yes, please Yes, there has been a project on limestone mountain’s biodiversity in the NR. Budget for the project is funded by Ha describe some main points of the programmes? Giang PPC since 1994 11. Do you agree with the project to improve the Project Road? What are your main concerns about environmental Agree with the project for improvement of the road 176A; impacts by the project ? If you do not agree with the project, please describe the reasons Mr. Hoàng Văn Tuệ, 12. Contact information ? Head, Division of Natural Reservation Name - Position – Working Agency – Telephone Number –Fax number of the respondent) Ha Giang Forest Agency Tel/Fax: 02193875770; Mobile phone: 01258279927 HA GIANG FORESTRY AGENCY DU GIA NATURE RESERVE MANAGEMENT BOARD Leader’s confirmation Director, Chief of MB Information provided by. Mr. Hoàng Ngọc Tường Mr. Vũ Văn Thành Signed and Sealed 9 Sept. 2010 * subject to confirmation

Page 119

Page 120

Appendix C: Letter of No Objection from Du Gia Nature Reserve Management Board

Page 121

Appendix D: Letter of No Objection from Dong Van Karst Plateau Geopark Management Board

Page 122

Appendix E List of Culvert Locations Dimensions (m) Length No. Type of culverts Station (m) Provincial Road TL 176A Diameter Width Height Φ Dimensions (m) Length 35 Box culvert Km 18+905.33 0.8 0.8 5 No. Type of culverts Station Diameter Width Height (m) 36 Box culvert Km 19+212.1 0.8 0.8 5 Φ 37 Box culvert Km 19+730.6 0.8 0.8 5 1 Box culvert Km 0+00 0.8 0.8 7 38 Box culvert Km 19+975.98 0.8 0.8 5 2 Box culvert Km 0+365.37 0.8 0.8 5 39 Pipe culvert Km 21+175.16 0.75 6 3 Box culvert Km 0+474.07 0.6 0.6 5 40 Pipe culvert Km 22+501.16 0.75 6 4 Box culvert Km 0+722.38 0.6 0.6 5 41 Pipe culvert Km 23+251.96 0.75 6 5 Box culvert Km 2+081.62 0.8 0.8 5 42 Pipe culvert Km 23+330.84 0.75 7 6 Box culvert Km 3+027.19 0.6 0.6 5 43 Pipe culvert Km 23+430.45 0.75 6 7 Box culvert Km 3+605.76 0.8 0.8 5 44 Pipe culvert Km 23+642.48 0.75 7 8 Box culvert Km 4+516.06 0.8 0.8 5 45 Pipe culvert Km 23+912.67 0.75 6 9 Box culvert Km 4+776.03 0.8 0.8 5 46 Pipe culvert Km 24+099.83 0.75 7 10 Box culvert Km 5+155.4 0.8 0.8 5 47 Pipe culvert Km 24+413.4 0.8 6 11 Box culvert Km 5+462.01 0.8 0.8 5 48 Pipe culvert Km 24+488.76 1 7 12 Box culvert Km 5+770.44 0.8 0.8 5 49 Pipe culvert Km 24+601.84 0.75 6 13 Box culvert Km 6+206.22 0.8 0.8 5 50 Pipe culvert Km 24+859.58 0.75 6 14 Box culvert Km 6+490.22 0.8 0.8 5 51 Pipe culvert Km 24+960.42 0.75 6 15 Box culvert Km 6+671.82 0.8 0.8 5 52 Pipe culvert Km 25+124.21 0.75 6 16 Box culvert Km 7+385.82 0.8 0.8 5 53 Pipe culvert Km 25+281.8 0.6 6 17 Box culvert Km 7+993.62 0.8 0.8 5 54 Pipe culvert Km 25+393.84 0.6 6 18 Box culvert Km 8+283.10 0.8 0.8 5 55 Pipe culvert Km 25+717.36 0.75 6 19 Box culvert Km 9+561.28 0.8 0.8 5 56 Pipe culvert Km 25+922.39 0.75 7 20 Box culvert Km 9+830.82 0.8 0.8 5 57 Pipe culvert Km 26+144.1 0.75 7 21 Box culvert Km 10+278.36 0.8 0.8 5 58 Pipe culvert Km 26+247.1 0.75 6 22 Box culvert Km 11+251.55 0.8 0.8 5 59 Pipe culvert Km 26+514.29 0.75 5 23 Box culvert Km 12+480.53 0.8 0.8 5 60 Pipe culvert Km 26+733.23 0.75 5 24 Box culvert Km 13+875.7 0.8 0.8 6 61 Pipe culvert Km 26+866.07 0.75 6 25 Box culvert Km 14+719.97 0.8 0.8 5 62 Pipe culvert Km 27+075.16 0.75 6 26 Box culvert Km 15+536.71 0.8 0.8 5 63 Pipe culvert Km 27+191.21 0.75 6 27 Box culvert Km 15+970.19 0.8 0.8 5 64 Box culvert Km 27+457.92 0.8 0.8 5.5 28 Box culvert Km16+479.23 0.8 0.8 5 65 Box culvert Km 27+585.88 0.8 0.8 6 29 Box culvert Km 17+540.8 0.8 0.8 5 66 Pipe culvert Km 27+723.82 0.75 6 30 Box culvert Km 17+705.71 0.8 0.8 5 67 Pipe culvert Km 27+889.39 0.75 7 31 Box culvert Km 17+943.4 0.8 0.8 5 68 Pipe culvert Km 28+531.26 0.75 5 32 Box culvert Km 18+273.86 0.8 0.8 5 69 Pipe culvert Km 28+927.42 0.75 6 33 Box culvert Km 18+490.54 0.8 0.8 5 70 Pipe culvert Km 29+123.05 0.75 6 34 Box culvert Km 18+799.95 0.8 0.8 5

Page 123

Provincial Road TL183 Dimensions (m) Length No. Type of culverts Station (m) Diameter Φ Width Height Dimensions (m) Length No. Type of culverts Station (m) 36 Box culvert Km 10+774.77 0.8 0.8 6 Diameter Φ Width Height 37 Box culvert Km 11+070.32 0.8 0.8 6.5 1 Pipe culvert Km 0+304.33 0.8 12 38 Box culvert Km 11+517.78 0.8 2 Pipe culvert Km 0+508.38 1 7 39 Box culvert Km 11+775.12 0.8 0.6 6 3 Pipe culvert Km 0+937.79 1 7 40 Box culvert Km 12+036.92 0.8 0.8 6 4 Box culvert Km 1+709.61 0.8 1 6 41 Box culvert Km 12+128.34 1 1 6 5 Box culvert Km 1+746.94 3 2 4.5 42 Box culvert Km 12+353.89 0.8 0.8 6 6 Box culvert Km 2+193.64 0.8 0.8 6 43 Box culvert Km12+443.88 0.8 0.8 6 7 Box culvert Km 3+036.05 1.2 1 6 44 Box culvert Km 12+627.2 0.8 0.7 6 8 Box culvert Km 3+181.97 0.8 0.8 7 45 Box culvert Km 12+750 0.8 0.8 6 9 Box culvert Km 3+350.45 0.8 0.6 6 46 Box culvert Km 13+688.46 1.2 1 7 10 Box culvert Km 3+456.29 0.8 0.8 6 47 Box culvert Km13+878.62 0.8 7 11 Box culvert Km 3+607.62 0.8 0.8 6 48 Box culvert Km 13+889.59 0.8 0.8 7 12 Box culvert Km 3+939.24 0.8 0.7 6 49 Box culvert Km 13+998.26 0.8 0.8 7 13 Box culvert Km 4+038.47 0.8 0.8 6 50 Box culvert Km 14+169.71 0.8 0.8 7 14 Box culvert Km 4+231.33 0.8 0.8 6 51 Box culvert Km 14+293.81 0.8 0.8 7 15 Box culvert Km 4+671.7 0.8 0.8 6 52 Box culvert Km 14+690.25 0.8 0.8 7 16 Box culvert Km 4+893.65 0.8 0.8 6 53 Box culvert Km 14+843.85 1.2 1 6 17 Box culvert Km 4+950 0.8 0.8 6 54 Box culvert Km 15+209.46 0.8 0.8 7 18 Box culvert Km 5+173.45 0.8 0.9 6 55 Pipe culvert Km 15+306.16 1.2x1.2 7 19 Box culvert Km 5+213.52 0.8 0.8 6 56 Box culvert Km 15+367.45 0.8 0.8 6.5 20 Box culvert Km 5+550 0.8 0.8 6 57 Box culvert Km 15+477.78 0.8 0.8 7 21 Box culvert Km 5+922.17 0.8 0.8 6 58 Box culvert Km 16+128.9 1.2 1 6 22 Box culvert Km 6+525.81 0.8 0.8 6 59 Box culvert Km 16+279.77 0.8 0.8 6 23 Pipe culvert Km 7+098.68 1.2x1.2 7 60 Box culvert Km16+381.56 0.8 0.8 6 24 Box culvert Km 7+241.23 0.8 0.7 7 61 Box culvert Km 16+387.82 0.8 0.8 6 25 Box culvert Km 7+280.85 0.6 0.6 7 62 Box culvert Km 16+564.51 0.8 6 26 Box culvert Km 7+638.3 0.3 6.5 63 Box culvert Km 16+674.46 0.8 0.8 6 27 Box culvert Km 7+863.71 0.8 0.8 6 64 Pipe culvert Km17+592.63 1 8 28 Box culvert Km 7+948.45 0.8 0.8 6 65 Box culvert Km17+884.72 0.8 0.8 8 29 Box culvert Km 8+370 0.8 6 66 Box culvert Km 18+084.85 0.8 0.8 7 30 Box culvert Km 8+604.81 0.8 0.8 8 67 Box culvert Km 19+158.39 0.8 0.7 7 31 Box culvert Km 9+451.2 0.8 0.8 7 68 Box culvert Km 19+605.8 1.2 1.2 7 32 Box culvert Km 9+853.57 0.8 0.8 7 69 Box culvert Km 19+809.44 1 7 33 Box culvert Km 10+103.01 0.6 0.6 6 70 Pipe culvert Km 19+968.66 0.8 8 34 Box culvert Km 10+333.7 0.6 0.6 7 71 Pipe culvert Km 20+029.52 0.8 8 35 Box culvert Km 10+586.57 1.2 7

Page 124

Dimensions (m) Length Dimensions (m) Length No. Type of culverts Station No. Type of culverts Station (m) (m) Diameter Φ Width Height Diameter Φ Width Height

72 Pipe culvert Km 20+119.84 0.8x0.8 8 108 Box culvert Km 27+886.62 0.8 0.8 7 73 Box culvert Km20+353.27 0.8 0.8 7 109 Box culvert Km 27+984.89 0.8 0.8 7 74 Pipe culvert Km 20+362.35 1.2 7 110 Box culvert Km 28+761.45 0.8 0.8 7 75 Pipe culvert Km 20+664.71 0.8 7 111 Box culvert Km 29+259.86 0.8 0.8 6 76 Box culvert Km 20+680.4 1 6 112 Box culvert Km 29+363.14 0.8 0.8 6 77 Box culvert Km 21+009.81 0.8 0.8 7 113 Box culvert Km 29+485.57 0.8 0.8 6 78 Box culvert Km 21+399.57 0.8 0.8 7 114 Box culvert Km 29+597.33 0.8 0.8 6 79 Box culvert Km 21+580 0.6 0.6 7 115 Box culvert Km 29+711.21 0.8 0.8 6 80 Box culvert Km 22+107.22 0.8 0.8 6 116 Box culvert Km 29+793.27 0.8 0.8 6 81 Box culvert Km 22+153.02 0.8 0.8 6 117 Box culvert Km 29+944.46 0.8 6 82 Box culvert Km 22+686.2 0.8 0.8 7 118 Box culvert Km 30+314.5 0.8 0.8 6 83 Box culvert Km 22+960.36 1.2 1.2 6 119 Box culvert Km 30+474.33 0.8 0.8 6 84 Box culvert Km 0.8 0.8 7 120 Box culvert Km 30+557.25 0.8 0.8 7 85 Box culvert Km23 23+769.64TL183 8 0.8 0.8 7 121 Box culvert Km 31+402.96 0.8 0.8 7 86 Box culvert Km 24+015.85 0.8 0.6 7 122 Box culvert Km 31+755.74 0.8 0.8 7 87 Box culvert Km 24+440.51 0.8 0.8 5 123 Box culvert Km 31+907.47 0.6 0.6 7 88 Box culvert Km 24+762.5 1.2 1.2 6 124 Box culvert Km 32+167.51 0.6 0.6 7 89 Box culvert Km 25+109.84 0.8 6 125 Box culvert Km 32+469.42 0.8 0.8 7 90 Pipe culvert Km 25+462.83 1.2x1.2 7 126 Box culvert Km 33+064.28 0.8 0.8 7 91 Box culvert Km 25+515.29 0.8 0.8 7 127 Box culvert Km 33+190.10 0.8 0.8 7 92 Box culvert Km 25+590.29 0.8 0.8 7 128 Box culvert Km 33+235.12 0.8 0.8 7 93 Box culvert Km 25+644.68 0.8 0.8 6 129 Box culvert Km 33+637.3 0.8 0.8 7 94 Box culvert Km 25+731.06 0.8 0.8 6 130 Box culvert Km 33+820.67 0.8 0.8 7 95 Box culvert Km 25+824.56 0.8 0.8 6 131 Box culvert Km 34+290.14 0.8 0.8 7 96 Box culvert Km 25+880.38 0.8 0.8 6 132 Box culvert Km 34+362.99 0.6 0.6 7 97 Box culvert Km 25+959.16 0.8 0.8 6 133 Box culvert Km 34+490.79 1.2 1.2 7 98 Box culvert Km 26+149.78 0.8 0.8 6 134 Box culvert Km 34+514.52 1 1 7 99 Box culvert Km 26+240.66 1.5 1.5 7 100 Box culvert Km 26+262.22 0.8 0.8 6 101 Box culvert Km 26+547.52 0.8 0.8 7 102 Box culvert Km 26+698.18 0.8 0.8 7 103 Box culvert Km 26+851.04 0.8 0.8 7 104 Box culvert Km 26+928.56 0.8 0.8 7 105 Box culvert Km 27+466.88 0.8 0.8 7 106 Box culvert Km 27+602.13 0.8 0.8 7 107 Box culvert Km 27+614.43 0.8 0.8 7

Page 125

Page 126