Review of Prioritized Projects Hon’ble CM conducted Review for Prioritized Projects RECORD OF DISCUSSION

Date Monday, 12th November 2018

Time 08:20 PM to 09:00 PM

Agenda Progress review on Prioritized projects by Hon’ble Chief Minister, A.P

Venue Conference room, AP Secretariat, .

. Shri. D. Uma Maheswara Rao, Hon’ble Minister, WRD . Smt. Rekha Rani, Commissioner R&R . District collectors Attendees . Forest department . Ground water department . Chief Engineers from Tirupathi, Anantapuram, , , & . Consultants to APWRD

Page 1 of 6

Action to be # Project / Topic Gist of discussions Timeline taken by

Hon’ble CM reviewed status of prioritized projects. Overall status of 62 prioritized projects :  Projects inaugurated: 16 nos. For 1 Overall status -  Projects ready for inauguration: 6 nos. information  Projects in progress: 40 nos.

Hon’ble CM requested to provide timelines for all the prioritized projects. Hon’ble CM and Hon’ble Minister reviewed the water flow/release of HNSS. CE, Anantapuram informed the water shall reach as per the below plan:

th — Lepakshi – 20 Nov’18 For 2 Release of Water - — Madaksira – 15th Nov’18 information — Cherlopally – 15th Nov’18 — Water will reach Chittor border via PBR by 20th Dec’18. Hon’ble CM instructed to ensure that water reaches Kuppam region by 15th Jan’19. Hon’ble CM reviewed the status of following projects (Detailed progress of projects attached in annexure): — Adavipalli Reservoir – CE, TGP informed reservoir works are completed and requested for extension of time for Peddamandyam lift till 20th Feb’18 — Kuppam Branch Canal (HNSS Phase II) – CE, TGP informed only 100m of LA is pending and expediting the works. Requested for extension of time till 15th Projects under CE, Nov’18 For 3 - Tirupathi — Barrage –Proposed to connect Head Regulator to Survypalli canal by information 15th Nov’18. Hon’ble CM raised concern for delayed works. — Sangam Barrage – Hon’ble CM raised concern for the delayed works. Also, instructed to entrust the work to new agency if current agency is not performing as per program. — Lifting of water from Somasila Swarnamuki link canal (Merlapaka Reservoir) to Mallemadugu Reservoir and Mallemadugu to Balaji Reservoir

Page 2 of 6

Action to be # Project / Topic Gist of discussions Timeline taken by — Mallemadugu Reservoir, Balaji Reservoir, Venugopala sagar Reservoir – Forest clearance to be cleared by Nov’18. — Somasila Swarnamuki link canal – CE, TGP informed project is progressing as per schedule. — Water Supply to Mulapalli and other 4 tanks – CE, TGP informed works are in progress. Hon’ble CM instructed by 15th Jan’19 water supply to reach tanks. Hon’ble CM reviewed the status of following projects (Detailed progress of projects attached in annexure): Projects under CE, For 4 — Lifting of water from to Upper Pennar Project - Anantapuram information — Lifting of water from Jeedipalli Reservoir to Bhairavanithippa Project — Mid Pennar South Canal CE, Anantapuram informed investigation work completed and procurement of Phase wise Community Lift pipes are under progress. CE, 5 program to be cum Drip Irrigation Hon’ble CM instructed to submit phase wise program along with major Anantapuram submitted milestones. Water Supply to Hon’ble CM reviewed the balance quantities to be executed for earthwork, For 6 Western Mandals of structures and concrete. CE, agreed to complete the work as per the given - information timeline. CE, Kadapa briefed about the status of seven packages (package details are included in the attached annexure). For 7 GNSS Phase II - Hon’ble CM instructed to expedite all package tenders and target to complete information tenders by Nov’18. — Yerram Chinnapoli Reddy Korisapadu L.I Scheme: CE, Ongole informed court case on LA of 340.23 Acres is still pending. Detailed

program for — Poola Subbiah : Project under CE, Tunnel works of 8 CE, Ongole briefed about progess of Poola Subbiah Veligonda Project and issues CE, Ongole Ongole Veligonda of Refurbishment of TBM and replacement of deteriorated length of conveyor belt. project to be Also informed, Boring works will start by 15th Nov’18. submitted.

Hon’ble CM instructed to submit detailed program for Tunnel works Page 3 of 6

Action to be # Project / Topic Gist of discussions Timeline taken by

Hon’ble CM instructed to expedite the works and aim to complete work by Feb’19.

Hon’ble CM reviewed the balance quantities to be executed and instructed to Detailed submit a detailed program for the balance works execution. program for Chintalapudi Lift CE, KDS, 9 balance qty. Irrigation Scheme Vijayawada Hon’ble CM instructed to work out for the alternative water drawls from Polavaram execution to be RMC through gravity instead of expenditure of lifting pumps. submitted Sujala A time bound SE, LMC, 10 Sravanthi Project Hon’ble CM instructed to submit a time bound program for the project program to be Tuni Phase-I works submitted — B.R.R.Vamsadahra project: CE, NC informed works are progressing as per the schedule. — Offshore Reservoir on : Hon’ble CM raised concern for slow progress of works and reviewed balance quantities to be executed. Projects under CE, For 11 - NC, Visakhapatnam — Taraka Rama Thirtha Sagaram Reservoir Project: CE, NC informed Package 21- Information LA of 188.76Acres to be acquired and Package 21 A – R&R issues in 3 villages. — Modernisation of Thotapalli Old Canal System: CE, NC informed tenders are finalized & agreement to be concluded.

— Hagari (Vedavathi Project) Lift irrigation scheme: CE informed DPR submitted to the government for Rs. 1942.80 Crs. Projects under CE, For 12 - Kurnool — Rajolibanda Diversion Scheme (RDS) Right Canal: CE informed DPR submitted Information to the government for Rs. 1497.22 Crs

— Construction of new barrage (10 TMC) across near (V): CE informed there is no response for the 2nd call of tender. Projects under CE, Tenders called for the 3rd time. Bid submission closing date is 22nd Nov’18 & For 13 - KDS, Vijayawada Price Bid opening date is 27th Nov’18. information — Mukthyala Lift irrigation Scheme: Remarks of ENC(Irrigation) are being attended by CE/KDS and CE/NSP.

Page 4 of 6

Action to be # Project / Topic Gist of discussions Timeline taken by — Extension Channel from Km 47.00 to Km 77.00: CE informed DPR preparation is under progress and same will be submitted by 14th Nov’18. — -Chanubanda Lift Irrigation Scheme: CE informed DPR will be submitted by 19th Nov’18 — Varikapudisela LI Scheme (Macharla Lift): CE informed proposals are under preparation and also informed 36 acres are under Wildlife land. Hon’ble CM instructed to check for alternatives to avoid disturbance of wildlife land acquisition. — Construction of new barrage across Krishna River near Chodavaram(V): CE informed DPR submitted and Administrative approval under process.

Interlinking of CE, NC, Visakhapatnam informed preparation of DPR is under process and Vamsadhara and — For 14 th - Bahuda Rivers will be completed by 30 Nov’18. information

Hon’ble CM reviewed the various works under Neeru –Chettu Scheme. CE informed briefed the status of the works as follows: — 74% of De-silting works completed — 289 cascades are pending and will completed in the month of Nov’18 For 15 Neeru Chettu - — 77% of Jungle clearance completed information — 249 tanks to be are yet to be restorted

Hon’ble CM instructed to expedite all the works under the scheme.

Tenders for Hon’ble CM instructed to call for the tenders of excavated soil distribution in the 16 excavated soil in right main canal of Polavaram. Also, instructed, transparency should be maintained Polavaram RMC in all the transactions.

For 17 Water Management Hon’ble CM informed there is 34% deficit in the rainfall this year, has - information failed and ground water has depleted compared to last year.

Page 5 of 6

Action to be # Project / Topic Gist of discussions Timeline taken by Hon’ble CM instructed that each and every measure for better water management to be taken up and it is the responsibility of all the Engineers of the department to ensure efficient water management. Hon’ble CM also instructed the following requirement to be met priority wise: — Drinking water demand — Protection of crop yields — Industry water requirement — Horticulture requirement

Hon’ble CM also informed to study areas for the plantation along the canal bunds. Grounding of New Hon’ble CM instructed to complete the tender process of all the new projects by For 18 - Projects Nov’18 and Agency to ground works. information Encl.: Annexure 1 (Brief status of 62 prioritized projects as on 12th Nov’18)

Page 6 of 6

ANNEXURE I Status of prioritized projects as on 12 November 2018 Target Date of project Sl no. Project Major Issue / Current status completion Inaugurated projects - 15 nos. 1 Purushotha Patnam LIS Inaugurated on 15th Aug 2017 - Construction of Anicut across Sarada 2 Inaugurated on 6th Sept 2017 - River 3 Mutchumarri LIS Inaugurated on 8th Sept 2017 -

4 Kandaleru Left Canal – Lift Scheme Inaugurated on 12th Nov 2017 -

5 – CBR Lifts Inaugurated on 3rd Jan 2018 -

6 Siddapuram Lift Irrigation Scheme Inaugurated on 7th Jan 2018 -

7 Modernisation of Yerracalva Inaugurated on 8th Jan 2018 - Formation of Pogonda Reservoir in 8 Inaugurated on 19th Feb 2018 - West Godavari 9 SH-31 Road Work (GNSS Phase I) Inaugurated on 6th June 2018 - Pulakurthy LI Scheme 10 Inaugurated on 23rd Aug 2018 - (Guru Raghavendra Project) 11 Chinasana LI Scheme on VLMC Inaugurated on 15th Sep 2018 -

12 Kondaveeti Vagu Pumping Scheme Inaugurated on 16th Sep 2018 - Gorakallu Balancing Reservoir (Sri 13 Inaugurated on 22nd Sep 2018 - Narasimharaya Sagar) 14 Owk Tunnel (GNSS Phase I) Inaugurated on 22nd Sep 2018 -

15 Pulikanuma LIS Inaugurated on 22nd Sep 2018 -

16 Gandikota Reservoir (GNSS Phase I) Inaugurated on 30th Oct 2018 Projects ready for Inauguration - 7 nos. 17 Pedapalem LI Scheme on Krishna River Ready for inauguration -

18 K.L. Rao Sagar Ready for inauguration - Kandula Obul Reddy Gundlakamma 19 Ready for inauguration - Reservoir Project 20 Marala Reservoir Ready for inauguration -

21 Cherlopally Reservoir Ready for inauguration - Madakasira Branch Canal beyond 22 Ready for inauguration - Gollapalli Reservoir Projects in progress under purview of CE, Tirupathi Reservoir : Project works completed Adavipalli Reservoir (HNSS Phase-II) & Reservoir Completed. 23 Adavipalli Lift (Peddamandyam lift on Lift scheme :7 no of Towers are dismantled and being relocated due to railway Main canal) and power transmission line issue.Requested for extension of time up to 20 Lift scheme : 20-Nov-18 Nov 2018.

Work in progress at 4.173 Km. Out of 24 structures remaining, 24 nos. in 24 Kuppam Branch Canal (HNSS Phase II) 15/Nov/18 progress. Expected date of completion:15 Nov 2018.

Proposed to connect Head Regulator to Survypalli canal by 15-11-2018.85.90 % 25 Nellore Barrage 31/Dec/18 of work completed.Requested extension up to 31 Dec 2018. Overall project completion 64.85% Rafts, 42 nos. completed out of 42 nos. 26 Sangam Barrage 28/Feb/19 Piers, 74 nos. completed out of 86 Nos. Requested extension up to 28 Feb 2019 Water Supply to Mulapalli and other 4 27 Works Grounded.Requested Extension of Time upto 28 Feb 2019 28/Feb/19 tanks.

Part-A: Lifting of water from Merlapaka to Mallemadugu Reservoir : Estimate for Rs.288.80 Crs submitted to Government for according Lifting of water from Somasila Administrative approval.Government communicated certain remarks and the Swarnamuki link canal (Merlapaka 28 replies submitted on 10 Oct'18. 31/Mar/19 Reservoir) to Mallemadugu Reservoir Part-B: Replies to the remarks called for by the Government are submitted. and Mallemadugu to Balaji Reservoir Requested extension up to 31-03-2019.

Page 1 of 5 ANNEXURE I Status of prioritized projects as on 12 November 2018 Target Date of project Sl no. Project Major Issue / Current status completion Forest clearance proposals submitted to the Government of . 29 Mallemadugu Reservoir 31/Dec/18 Two no. of structures, Balance quantities of 13.65 cum of earth work and 24,744cum of concrete is to be executed. Forest clearance proposals submitted to the Government of India. 30 Balaji Reservoir Balance quantities to be executed : EW - 47.96 lakh cum & Concrete - 32,356 31/Dec/18 cum. 12.32% of work completed. Authentication of CA Lands in process. Earthwork to the tune of 38.86 lakh 31 Venugopala sagar Reservoir cum, concreting of 33,300 cum and bund making for a lengh of 1 Km is to be 31/Dec/18 executed. All formalities required for stage-I clearance have been uploaded. Earthwork to Somasila Swarnamuki link canal. (from 32 the tune of 7.52 lakh cum, concreting of 17,900 cum and canal excavation for a 31/Dec/18 km 56.000 to 100.425) lengh of 3.025 Km is to be executed. Reservoir : Tender evaluation report submitted to COT approval Lifting of water from SSG Canal to Lift scheme: Agreement Concluded and work is in progress. Pipe 33 31/Mar/19 Althurupadu Reservoir (2.356 TMC) manufacturing is in process.Designs of Electro-Mechanical items are in progress. Projects in progress under purview of CE, Work stopped due to water release in to the Canal. Work will be resumed after Widening of HNSS Main Canal under closing of canals. 34 31/Mar/19 Phase-I Earth work of 1.47 Cr cum and concrete of 3.12 lakh cum is to be exuecuted.

Civil works- LA Work is under progress and DN is published for LA of 870 Lifting water from Jeedipalli Reservoir acres. 35 30/Jun/19 to Bhairavanithippa Project. Electro-mechanical works tenders are finalized and Agreement was concluded. Designs and Drawings under progress. Water lifting from Jeedipalli Reservoir LA works and Canal Earth Work Excavation are in progress. Survey 36 30/Jun/19 to Upper Pennar completed. DN published. Upto 40th KM : Earthwork of 7.18 lakh cum and concrete of 1.71 lakh cum is to be executed. Modernization of Mid – Pennar South 40th KM to 84 KM : 37 Canal from Km 0.000 to Km 40.000 & 31/Mar/19 Earthwork of 2.84 lakh cum and concrete of 2.22 lakh cum is to be executed. from Km 40.000 to Km 84.000 Water is released to the Mid-Pennar South Canal and Work will resume after closure of canals.

Works grounded. 90 % of investigation work is completed and execution of Community Lift cum Drip Irrigation, 38 civil work will be started by 15-Nov-2018. Requested extension up to 30-Jun- 30/Jun/19 Uravakonda 2019.

Feasibility is under study. Drawal of 6 TMC of water from Chitravathi Balancing Reservoir to HNSS Supply water from CBR to HNSS Main Phase –II System through Yogivemana Reservoir to strengthen the existing Canal, Punganur Branch Canal, ayacut of 12880 acres under Yogivemana Project apart from improving ground Kuppam Branch Canal (KBC) in Chittor 39 water levels. - District through Yogivemana Reservoir Project. Water supply to Punganur Branch Canal, Kuppam Branch Canal and HNSS Main Canal

Projects in progress under purview of CE, Kadapa

Page 2 of 5 ANNEXURE I Status of prioritized projects as on 12 November 2018 Target Date of project Sl no. Project Major Issue / Current status completion Package I: Declaration and Award are under process inSDC ,GNSS Unit-II, Kadapa. Recasting of the Estimate with current SSR 2018-19 for an amount of Rs. 577.00 Crores was submitted on Dt. 06.10.2018 to the Govt. Package II:Contract is pre-closed. Settlement of accounts is under process. The Estimate with current SSR 2018-19 for Rs 555.34 Crores is submitted to Government on 18-09-2018. Package III:Work is in progress.Proposals for Stage-I forest Clearance submitted on 19-09-2018 to MoEF Regional Office, . Package IV: Pre-closure of old contract is under process. Survey completed for LA and Preliminary notice is to be issued.Uploading for Stage-I forest 40 GNSS Ph-II up to Kodur in Kadapa Dist. Clearance completed. The file is under process at DFO, Kadapa. 31/Mar/19 Package V: Proposals of Stage-I Forest Clearance submitted to Principal Secretary, Forest & Environment from PCCF, Guntur on 26.10.2018 Package VI: Pre-closure proposals of contract on mutual consent basis submitted to the Government on 24.07.2018. Returned with remarks and are under process. Joint survey for LA is completed for 132.71 Acres. PN to be done for 92 Acres. Package VII: The work is pre-closed. Settlement of accounts is in progress.Joint survey for LA is in progress. Peg marking for LA is in progress. Estimate for Balance Quantities with current SSR 2018-19 is under scrutiny at Division Level.

Page 3 of 5 ANNEXURE I Status of prioritized projects as on 12 November 2018 Target Date of project Sl no. Project Major Issue / Current status completion Projects in progress under purview of CE, Kurnool

Hagari (Vedavathi Project) Lift irrigation DPR submitted to Government for Rs.1942.80 Crs. 41 - scheme

Water Supply to Western Mandals of 42 Works in progress 31/Jan/19 Kurnool District Inter State issue - State is objecting for completing the balance survey work (95% of Survey work completed). Five Villages will be submerged 43 Formation of Gundrevula Reservoir in Mahabubnagar Dt. CWC,KRMB and Telangana Govt. to be addressed for co- - operation and concurrence. Govt. instructed CE, ISWR, to examine and furnish a detailed report. Rajolibanda Diversion Scheme (RDS) DPR submitted to Government for Rs.1479.22 Crs. 44 - Right Canal Projects in progress under purview of CE, Ongole

Villagers obstructing work demanding compensation for structures and crops. Yerram Chinnapoli Reddy Korisapadu Court case on LA of 340.23 Ac. Valuation of structures in Thurpupalem and 45 31/Dec/18 LIS Pedduru villages completed and DN was published on 20.Aug.18. Earth work to the tune of 14.98 lakh cum and concrete of 19,216 cum is to be executed. Head Regulator Work is stopped due to raise in water levels in Srisailam Reservoir. Gantry is fixed to lay CC for lining.Requested extension up to 28.Feb.2019.

Refurbishment of TBM and replacement of deteriorated length of conveyor belt is under process.Changing of damaged rollers and conveyor belt is in Poola Subbiah Veligonda - Tunnels I & 46 progress. 15/Jan/19 II and Head Regulator Conveyor belt trail run is made on 02.11.2018

Requested extension for Tunnel-1 up to 28-02-2019 and agreement for Tunnel 1 concluded on 14-10-2018. Tunnel – II: Handing over of TBM & other equipment by the old agency to new agency is under process.Requested extension up to 31.Aug.2019. Projects in progress under purview of CE, North coast Visakhapatnam Due to release of water and continuous rains, the works are not being taken up. BRR Vamsadhara Project Stage II 47 Works will be resumed after completion of Monsoon season (Probably in the 31/Mar/19 Phase II 1st week of December 2018). 60.39 % of work completed. Work is programmed to be completed by 31.03.2019. Interlinking of Vamsadhara and Balance Land of 55.00 Acres is programmed to be acquired by 30th Nov 2018 48 31/Dec/18 Nagavali Rivers by Revenue Authorities.53.93 % of work completed.

Progress of work is hampered due to rains. 32.42 % of work completed. R&R Offshore reservoir on Mahendratanaya 49 issues for 2 PDF Villages. Requested extension of Target date of completion 31/Jul/19 River up to 31-07-2019

Interlinking of Vamsadhara and 50 Preparation of DPR under process and will be completed by 30.11.2018 30/Jun/20 Bahuda Rivers Balance L.A 188.76 Acres out of which 136.41Acres is pending with LA Authorities and it is being pursued with L.A. Authorities. Taraka Rama Thirtha Sagaram SLSC cleared the deletion Proposals . Notice issued under Clause 61 of APDSS 51 30/Jun/19 Reservoir to resume the work immediately. The 2nd Revised estimate for Rs.740.24 Crs is prepared for according revised administrative approval Modernisation of Thotapalli Old canal 52 Tenders are finalized. Agreement to be Concluded. - System Projects in progress under purview of CE, KDS, Vijayawada Construction of new barrage (10 TMC) There is no response for the 2nd call of tender.Tenders called for third time. 53 across Krishna river near Bid submission closing date :22.11.2018.Price Bid opening date: 27.11.2018 . 1/May/20 Vykuntapuram. Interlinking Of Godavari – Penna Rivers Tenders are finalized.Agreement to be Concluded. Partial completion by 54 Phase-1 31/Dec/18 Projects in progress under purview Engineer in chief PIP (SE,LMC,Tuni) Part 1: Formation of Pedapudi reservoir, Gravity Canal - Agreement concluded and works commenced.LP Schedules are under preparation.

Uttarandhra Sujala Sravanthi Project Part 2 : Excavation of leading channel and Two stage lifiting at 55 30/Jun/19 Phase-I works Jammadulapalem and Teeda and Canal Distributory network to irrigate an Ayacut of 1.3 lakh acres in Vishakhapatnam District. Agreement concluded. Works will commence.

Page 4 of 5 ANNEXURE I Status of prioritized projects as on 12 November 2018 Target Date of project Sl no. Project Major Issue / Current status completion Projects in progress under purview CE, GDS - Dowlaiswaram Stage-I clearance was accorded by the MOEF to an extent of 347.64Ha. Uploading for Stage-I Clearance of 69.30 Ha Forest Land for Phase-II (Canal) works completed. Forest Department was requested to consider to adjust the 56 Chintalapudi Lift Irrigation Scheme CA in lieu of diversion of 69.30Ha in already submitted CA scheme for 28/Feb/19 519.88Ha towards the total forest land diversion of 417.27Ha. Trail Run for 2 pumps are completed. 700 Cusecs of water being lifted. Land Acquisition case in Hon’ble High Court is being pursued by land acquisition authorities. Projects in progress under purview Chief Engineer, Minor, Vijayawada & JMD, APSIDC (Kuppam Constituency) 57 Minor Irrigation Works and Lift Schemes in Kuppam Area PALAR CHECKDAMS: New 30 No's File sent to Finance Dept. On 05.11.2018. A 31/Mar/19

PALAR CHECKDAMS : Re construction Administrative sanction accorded vide G.O.Rt.No.802, dated 09-11-2018. B and Repairs - 13 No’s 31/Jan/19

PALAR CHECKDAMS : Re construction Administrative sanction accorded vide G.O.Rt.No.802, dated 09-11-2018. C and Repairs - 8 No’s 31/Jan/19

Improvements to feeder channel from File sent to Finance Dept. On 05.11.2018. for vetting of draft G.O.e-Office file Jambu cheruvu to PB Natham cheruvu D No.303198. 31/Dec/18 near PB Natham (v) in Kuppam (M)

Reconstruction of Checkdam across Administrative sanction accorded vide G.O.Rt.No.778, dated 05-11-2018 Manjalamadugu vanka near V. E 31/Dec/18 Mittapalli (V) in Kuppam (M)

Extension of tank bund on L/S and R/s Remarks of Finance Department have been communicated to CE, MI vide of Existing tank bund of D.K.palli to F Memo, dated 05-11-2018. 30/Nov/18 safeguard from Encroachments

Improvements to Check Dam across File sent to Finance Dept. On 20.10.2018. e-Office file No.646838. Peddavanka near Athinatham (V) in G 31/Mar/19 Gudupalli (M)

Excavation of Diversion Channel from Preethichamanuru percolation tank near Preethichamanuru Village in File sent to Finance Dept. On 04.11.2018. e-Office file No.604237 H 30/Apr/19 Santhipuram Mandal to Daseganuru Cheruvu of Kuppam Mandal

Construction of Lift scheme on pedda vanka (Kalli Vanka) near athinartham village of gudupalli mandal of chittoor Administrative sanction accorded vide G.O.Rt.No.782, dated 05-11-2018. I district to feed chain of tanks and 30/Apr/19 providing of drinking water facility to kuppam

Construction of Lift on Musalimadugu Admn Sanction accorded vide G.O.Rt.No.782, dated 05-11-2018. J tank near Veernamala (V) in 30/Apr/19 Ramakuppam(M) Mukthyala Lift irrigation Scheme Engineer-in- Chief(I) called certain remarks. Remarks of ENC(Irrigation) are 58 - being attended by CE/KDS and CE/NSP. Extension Guntur Channel from Km 59 47.00 to 77.00 Preparation of DPR is in progress. Dec-20

Varikapudisela LI Scheme ( Macharla Proposals are under preparation. 60 - Lift) Vissannapeta-Chanubanda Lift Survey and Leveling operations work for preparation of DPR is in progress. 61 Irrigation Scheme -

Construction of new barrage across 62 Administrative approval under process. - Krishna River near Chodavaram(V)

Page 5 of 5