Review of Prioritized Projects Hon’ble CM conducted Review for Prioritized Projects RECORD OF DISCUSSION

Date Monday, 08th October 2018

Time 04:00 PM to 05:30 PM

Agenda Progress review on Prioritized projects by Hon’ble Chief Minister, A.P

Venue Conference room, AP Secretariat, Velagapudi.

. Shri. D. Uma Maheswara Rao, Hon’ble Minister, WRD . Shri. Shashi Bhushan Kumar, Secretary, WRD . Smt. Rekha Rani – Commissioner, R&R . Shri M. Venkateswara Rao, EnC, WRD Attendees . District collectors . Forest department . Ground water department, APSRAC and M/s Vassar Labs . Chief Engineers from Tirupathi, Ananthapuram, Kadapa, Ongole, & Visakhapatnam . Consultants to APWRD

Page 1 of 4

Action to be # Project / Topic Gist of discussions Timeline taken by

Hon’ble CM and Minister of water resources reviewed status of prioritized projects. Overall status of 57 prioritized projects :  Projects inaugurated: 15 nos. For 1 Overall status -  Projects ready for inauguration: 3 nos. information  Projects in progress: 39 nos.

Hon’ble CM requested to provide timelines for all the prioritized projects. Secretary, WRD briefed about 8 ongoing & 3 New projects under CE, Tirupathi.

CE, TGP informed Adavipalli Lift (Peddamandyam Lift) works will finish by 21st Oct’18 and Kuppam Branch Canal works will finish by 16th Nov’18.

Hon’ble CM raised concerned for delayed works in Nellore Barrage. Secretary, WRD and EnC, WRD visited the sites and instructed to entrust part of Projects under CE, works of Nellore Barrage to another agency to expedite works. For 2 - Tirupathi CE, TGP informed action has initiated to entrust the part of work to another information agency.

CE, TGP informed Mallemadugu Reservoir, Balaji Reservoir, Venugopal Sagar Reservoir and Somasila Swarnamukhi Link Canal are under issues of Alienation of Forest Lands.

Hon’ble CM instructed Forest department to expedite the approvals at the earliest. Hon’ble CM requested for the plan of water releases across all the projects. Secretary, WRD and CE, Anantapuram briefed on the status of water reachability to the following projects: Status of Water th For 3 — Gollapalli – 5 Oct’18 - Reachability information — Cherlopally- 20th Nov’18 — PBC – 20th Nov’18 — Kuppam Branch Canal – 08th Dec’18

Page 2 of 4

Action to be # Project / Topic Gist of discussions Timeline taken by — Punganoor – 20th Nov’18

Hon’ble CM instructed to review the schedule of water release and plan to reach water to Chittor district by end of January. Hon’ble CM reviewed project status of the following projects: — Marala and Cherlopally reservoir — Madakasira Branch Canal — Widening of HNSS Main Canal Projects under CE, — Mid-Pennar South Canal For 4 - Anantapuram — Lifting of water from Jeedipalli to Upper Pennar Project Information — Lifting of water from to Bhairavanithippa Project — Community Lift cum Drip Irrigation Project

Project Status are shown in the attached annexure. CE, Kadapa briefed about the status of the work for all the packages: Package 1: Declaration and Award are under process in SDC, GNSS Unit-II, Kadapa. Package 2&3: Proposals for Stage-I forest Clearance submitted to the Nodal Officer, Principal Chief Conservator of Forest, Chennai from Principal Secretary , For 5 GNSS Phase II - Forest & Environment on 19-Sep-2018 Information Package 4&5: Stage-I clearance completed. Hon’ble instructed to transfer Package 6&7 to CE, Kadapa from CE, Tirupathi and Also, instructed to ground all the packages by month of November. Hon’ble CM instructed to arrange for inauguration of Kandula Obul Reddy Gundlakamma Reservoir Project.

Project under CE, CE, Ongole briefed about progess of Poola Subbiah Veligonda Project and issues For 6 - Ongole of Refurbishment of TBM and replacement of deteriorated length of conveyor belt. Information

JC, Prakasham requested for the Bill payment of Rs. 30cr. For the veligonda region. Secretary, WRD informed issue will be resolved.

Page 3 of 4

Action to be # Project / Topic Gist of discussions Timeline taken by

Hon’ble CM reviewed works on various schemes under Neeru Chettu Program.

Neeru Chettu For 7 CE, Neeru Chettu briefed the status of De-silting works, Jungle works, and - Cascade schemes Information Cascade developments. Hon’ble CM instructed to complete cascade developments works by end of October.

Hon’ble CM appreciated Joint Collector, Kadapa for the RR works of 1065 PDF’s For 8 LA&RR - in the region information

Cleaning of For 9 Hon’ble CM instructed come up with models of cleaning of all the reservoirs. - Reservoirs information

Grounding of New Hon’ble CM instructed to expedite the process of tenders for all the new projects For 10 - Projects by end of November. information

Hon’ble CM instructed to include 4 new projects to the Prioritized Projects: — - Canal Lift Irrigation(Extension) New Projects to For 11 — Thiruvuru-Chintalpudi canal Lift irrigation - include information — Macharla Lift — CBR to HNSS Scheme Encl.: Annexure 1 (Brief status of 57 prioritized projects as on 08st Oct’18)

Page 4 of 4

ANNEXURE I Status of prioritized projects as on 08 October 2018 Target Date of project Sl no. Project Major Issue / Current status completion Inaugurated projects - 15 nos. 1 Purushotha Patnam LIS Inaugurated on 15th Aug 2017 - Construction of Anicut across Sarada 2 Inaugurated on 6th Sept 2017 - River 3 Mutchumarri LIS Inaugurated on 8th Sept 2017 -

4 Kandaleru Left Canal – Lift Scheme Inaugurated on 12th Nov 2017 -

5 Gandikota – CBR Lifts Inaugurated on 3rd Jan 2018 -

6 Siddapuram Lift Irrigation Scheme Inaugurated on 7th Jan 2018 -

7 Modernisation of Yerracalva Inaugurated on 8th Jan 2018 - Formation of Pogonda Reservoir in 8 Inaugurated on 19th Feb 2018 - West Godavari 9 SH-31 Road Work (GNSS Phase I) Inaugurated on 6th June 2018 - Pulakurthy LI Scheme 10 Inaugurated on 23rd Aug 2018 - (Guru Raghavendra Project) 11 Chinasana LI Scheme on VLMC Inaugurated on 15th Sep 2018 -

12 Kondaveeti Vagu Pumping Scheme Inaugurated on 16th Sep 2018 - Gorakallu Balancing Reservoir (Sri 13 Inaugurated on 22nd Sep 2018 - Narasimharaya Sagar) 14 Owk Tunnel (GNSS Phase I) Inaugurated on 22nd Sep 2018 -

15 Pulikanuma LIS Inaugurated on 22nd Sep 2018 - Projects ready for Inauguration - 3 nos. Pedapalem LI Scheme on Krishna 16 Ready for inauguration - River 17 K.L. Rao Sagar Ready for inauguration -

18 Gandikota Reservoir (GNSS Phase I) Ready for inauguration Projects in progress under purview of CE, Tirupathi Reservoir : Project works completed Adavipalli Reservoir (HNSS Phase-II) & Reservoir Completed. 19 Adavipalli Lift (Peddamandyam lift on Lift scheme : Transmission towers 118 nos. completed, 2 towers works in Main canal) Lift scheme : 21-Oct-18 progress. Requested for extension of time up to 21 Oct 2018.

Work in progress at 5.198 Km. Out of 143 structures, 67 nos. in progress. 20 Kuppam Branch Canal (HNSS Phase II) Balance 76 nos. of structures to be taken up. Expected date of completion:15 15/Nov/18 Nov 2018. Overall completion status 85.31%. Balance quantities : Earthwork - 5.16 lakh cum and concreting - 10,818 cum. Head regulator will be ready by 10 Nov 2018 and water can be let out to Survepalli Canal. 21 Nellore Barrage 31/Dec/18 The Agency is not able to raise the funds to maintain the tempo of the work. Action initiated for deletion of part of the work and to entrust to another agency. OverallRequested project for extensioncompletion of 64.85% time up to 31 Dec 2108. Rafts, 41 nos. completed out of 42 nos. 22 Sangam Barrage 31/Dec/18 Piers, 74 nos. completed out of 86 Nos. Requested extension up to 31 Dec 2018 Water Supply to Mulapalli and other 4 23 31/Dec/18 tanks. Bid Evaluation Reports were submitted to COT for approval of tender. Part-A: Lifting of water from Merlapaka to Mallemadugu Reservoir : Lifting of water from Somasila Estimate for Rs.288.80 Crs submitted to Government for according Swarnamuki link canal (Merlapaka Administrative approval.Government communicated certain remarks and the 24 - Reservoir) to Mallemadugu Reservoir replies are under submission. and Mallemadugu to Balaji Reservoir Part-B: Replies to the remarks called for by the Government are submitted on estimate for Rs. 198.00 CroresPage 1 of 5 ANNEXURE I Status of prioritized projects as on 08 October 2018 Target Date of project Sl no. Project Major Issue / Current status completion Forest clearance proposals submitted to the Government of . 25 Mallimadugu Reservoir 31/Dec/18 Two no. of structures, Balance quantities of 14.75 lakh cum of earth work and 24,744cum of concrete is to be executed. Forest clearance proposals submitted to the Government of India. Government has approved for additional lead for Soil. 26 Balaji Reservoir 31/Dec/18 Balance quantities to be executed : EW - 48.12 lakh cum & Concrete - 32,356 cum Authentication of CA Lands in process. Earthwork to the tune of 40.35 lakh 27 Venugopala sagar Reservoir cum, concreting of 33,300 cum and bund making for a lengh of 1.52 Km is to 31/Dec/18 be executed. All formalities required for stage-I clearance have been uploaded. Earthwork to Somasila Swarnamuki link canal. (from 28 the tune of 11.00 lakh cum, concreting of 19,400 cum and canal excavation for 31/Dec/18 km 56.000 to 100.425) a lengh of 4.745 Km is to be executed.

Lifting of water from SSG Canal to Reservoir tender is to be called for. Lift portion agreement concluded and 29 31/Mar/19 Althurupadu Reservoir (2.356 TMC) work is in progress

Projects in progress under purview of CE, Anantapur Rectification measures are done and will be completed by 15 Oct 2018. 30 Marala Reservoir Reservoir will be filled after completion of rectification measures. Requested 15/Oct/18 extension of time up to 15-Oct-2018 Rectification measures are done and will be completed by 15 Oct 2018. 31 Cherlopally Reservoir Reservoir will be filled after completion of rectification measures. Requested 15/Oct/18 extension of time up to 15-Oct-2018 Work in progress. Canal of 2.2 Km, earth work - 3.74 lakh cum and concrete - Madakasira Branch Canal beyond 32 37,599 cum is to be executed. 31/Oct/18 Gollapalli Reservoir Requested extension of time up to 31-Oct-2018 Work stopped due to water release in to the Canal. Work will be resumed Widening of HNSS Main Canal under after closing of canals. 33 31/Mar/19 Phase-I Earth work of 1.47 Cr cum and concrete of 3.12 lakh cum is to be exuecuted.

Civil works- LA Work is under progress and Canal Excavation work to be Lifting water from Jeedipalli Reservoir 34 started on 10-10-2018. Electro-mechanical works tenders approved in 30/Jun/19 to Bhairavanithippa Project. COT Water lifting from Jeedipalli Reservoir Works grounded.Investigation, LA works and Canal Earth Work Excavation 35 30/Jun/19 to Upper Pennar are in progress. Upto 40th KM : Earthwork of 7.18 lakh cum and concrete of 1.71 lakh cum is to be executed. Modernization of Mid – Pennar South 40th KM to 84 KM : 36 Canal from Km 0.000 to Km 40.000 & 31/Mar/19 Earthwork of 2.84 lakh cum and concrete of 2.22 lakh cum is to be executed. from Km 40.000 to Km 84.000 Water is released to the Mid-Pennar South Canal and Work will resume after closure of canals.

Works grounded. 85 % of investigation work is completed and execution of Community Lift cum Drip Irrigation, 37 civil work 30/Jun/19 Uravakonda will be started by 15-Oct-2018. Requested extension up to 30-Jun-2019.

Projects in progress under purview of CE, Kadapa

Page 2 of 5 ANNEXURE I Status of prioritized projects as on 08 October 2018 Target Date of project Sl no. Project Major Issue / Current status completion Package I: Declaration and Award are under process in SDC ,GNSS unit-II, Kadapa. Recasting of the Estimate with current SSR 2018-19 will be submitted by 01-Oct-2018. Package II:Contract is pre-closed. Settlement of accounts is under process.Proposals for Stage-I forest Clearance submitted to the Nodal officer, Principal Chief Conservator of Forest, Chennai from Principal Secretary , Forest & Environment on 04-10-2018. Package III: Proposals for Stage-I forest Clearance submitted to the Nodal Officer, Principal Chief Conservator of Forest, Chennai from Principal Secretary , Forest & Environment on 19-09-2018. Package IV: Pre-closure of old contract is under process. Survey completed 38 GNSS Ph-II up to Kodur in Kadapa Dist. for LA and Preliminary notice is to be issued.Uploading for Stage-I forest 31/Mar/19 Clearance completed. Package V: Pre-closure of old contract is under process.Uploading for Stage-I Clearance is completed and it is under process at DFO, Kadapa. Package VI: Under CE, Tirupathi: Maps and RAW data for forest lands submitted to Forest Dept., for authentication and enumeration.Pre-closure proposals of contract on mutual consent basis submitted to the Government on 24.07.2018. Package VII: Under CE, Tirupathi:The work is pre-closed. Settlement of accounts is in progress.Joint survey for LA is in progress. Estimate for Balance Quantities with current SSR 2018-19 is under scrutiny at Division Level. Projects in progress under purview of CE, Kurnool Hagari (Vedavathi Project) Lift irrigation Hydrological clearances in progress. Agency finalized for SID operations. 39 - scheme Investigation works in progress.

Water Supply to Western Mandals of 40 Works in progress 31/Jan/19 Kurnool District Inter State issue - State is objecting for completing the balance survey work (95% of Survey work completed). Five Villages will be submerged 41 Formation of Gundrevula Reservoir in Mahabubnagar Dt. CWC,KRMB and Telangana Govt. to be addressed for co- - operation and concurrence. Govt. instructed CE, ISWR, to examine and furnish a detailed report. Rajolibanda Diversion Scheme (RDS) Remarks on DPR are being attended and will be submitted by 15.10.18. 42 - Right Canal Projects in progress under purview of CE, Ongole

Kandula Obul Reddy Gundlakamma LA Process initiated in the approved alignment. 98% of work completed. 43 31/Dec/18 Reservoir Project Earthwork of 2.41 lakh cum and concrete of 10,743 cum is to be executed.

Villagers obstructing work demanding compensation for structures and crops. Court case on LA of 340.23 Ac. Valuation of structures in Thurpupalem and Yerram Chinnapoli Reddy Korisapadu 44 Pedduru 31/Dec/18 LIS villages completed and DN was published on 20.Aug.18. Earth work to the tune of 14.98 lakh cum and concrete of 19,216 cum is to be executed. Head Regulator Work is stopped due to raise in water levels in Srisailam Reservoir. Gantry is fixed to lay CC for lining.Requested extension up to 15.Jan.2019.

Poola Subbiah Veligonda - Tunnels I & Refurbishment of TBM and replacement of deteriorated length of conveyor 45 15/Jan/19 II and Head Regulator belt is under process. Requested extension for Tunnel-1 up to 15-01-2019 and agreement for Tunnel 1 concluded on 04 Oct 2018. Tunnel – II: Handing over of TBM & other equipment by the old agency to new agency is under process. Projects in progress under purview of CE, North coast Visakhapatnam Due to release of water and continuous rains, the works are not being taken up. BRR Vamsadhara Project Stage II 46 Works will be resumed after completion of Monsoon season (Probably in the 31/Mar/19 Phase II 1st week of December 2018). Work is programmed to be completed by 31.03.2019. Interlinking of Vamsadhara and Balance Land of 135.46 Acres is programmed to be acquired by 15th October 47 31/Dec/18 Nagavali Rivers 2018 by Revenue Authorities.51.48Page 3 of 5 % of work completed. ANNEXURE I Status of prioritized projects as on 08 October 2018 Target Date of project Sl no. Project Major Issue / Current status completion Progress of work is hampered due to rains.Canal work is programmed to be Offshore reservoir on Mahendratanaya 48 completed by 31.07.2019. 32.42 % of work completed. R&R issues for 2 PDF 31/Dec/18 River Villages.

High Level Canal from Hiramandalam 49 Preparation of DPR under process and will be completed by 15.10.2018 30/Jun/20 Reservoir to Itchapuram Balance L.A 193.211 Acres is being pursued with L.A. Authorities. SLSC cleared the deletion Proposals . Notice issued under Clause 61 of Taraka Rama Thirtha Sagaram 50 APDSS to resume the work immediately. 30/Jun/19 Reservoir R & R Works are under progress in Agraharam, Koradapeta and Padalapeta. 44.49 % of work completed.(Both Packages) Modernisation of Thotapalli Old 51 Tenders process to be completed (evaluation is under process). - Regulator System Projects in progress under purview of CE, KDS, Vijayawada

52 K.L.RAO Pulichinthala Project Will be Inaugurated after storing of 30 TMC of water during current season -

Construction of new barrage (10 TMC) No response for the called tenders. 53 across near 1/May/20 . Interlinking Of Godavari – Penna Rivers Tender evaluation is under process. Partial completion by 54 Phase-1 31/Dec/18

Page 4 of 5 ANNEXURE I Status of prioritized projects as on 08 October 2018 Target Date of project Sl no. Project Major Issue / Current status completion Projects in progress under purview Engineer in chief PIP (SE,LMC,Tuni) Part 1: Formation of Pedapudi reservoir, Gravity Canal - Agreement concluded and works commenced.

Uttarandhra Sujala Sravanthi Project Part 2 : Excavation of leading channel and Two stage lifiting at 55 30/Jun/19 Phase-I works Jammadulapalem and Teeda and Canal Distributory network to irrigate an Ayacut of 1.3 lakh acres in Vishakhapatnam District. Agreement concluded. Works will commence.

Projects in progress under purview CE, GDS - Dowlaiswaram Stage-I clearance accorded by the MOEF to an extent of 347.64Ha. Uploading For Stage-I Clearance of 69.30 Ha. Forest Land for Phase-II (Canal) works 56 Chintalapudi Lift Irrigation Scheme completed. Forest land for Phase-II (canal) work were uploaded. 28/Feb/19 Land Acquisition case in Hon’ble High Court is being pursued by land acquisition authorities. Projects in progress under purview Chief Engineer, Minor, Vijayawada & JMD, APSIDC (Kuppam Constituency) 57 Minor Irrigation Works and Lift Schemes in Kuppam Area PALAR CHECKDAMS: New 30 No's CE Minor submitted proposals to ENC (AW) For approval vide letter dated 25- A 31/Mar/19 Sep-2018. PALAR CHECKDAMS : Re The proposal is returned and requested to resubmit proposal in the next B construction and Repairs - 13 No’s financial year 2019-20 along with benefit cost ratio. 31/Jan/19 e-Office file No. 480511 PALAR CHECKDAMS : Re Estimates for Rs .23.28 Crs submitted to Govt. for Administrative C construction and Repairs - 8 No’s sanctions.File is sent to Finance department on 23.08.2018. 31/Jan/19 e-Office file No. 590700 Improvements to feeder channel from Estimate for Rs. 3.25 Crs submitted to Govt. for Administrative approval Jambu cheruvu to PB Natham cheruvu after attending Remarks. D 31/Dec/18 near PB Natham (v) in Kuppam (M) e-Office file No. 303198

Reconstruction of Checkdam across Estimate for Rs. 5.90 Crs submitted to Govt. for Administrative approval after Manjalamadugu vanka near V. E attending Remarks. 31/Dec/18 Mittapalli (V) in Kuppam (M) e-Office file No. 620043

Extension of tank bund on L/S and R/s The Estimate for Rs. 1.43 Crs submitted to Government for administrative of Existing tank bund of D.K.palli to F approval. 30/Nov/18 safeguard from Encroachments

Improvements to Check Dam across Peddavanka near Athinatham (V) in CE Minor Irrigation communicated remarks on the proposal to SE/IC Chittoor. G 31/Mar/19 Gudupalli (M)

Excavation of Diversion Channel from The estimates for Rs. 18.43 Crs submitted to Govt. for Administrative Preethichamanuru percolation tank approval. near Preethichamanuru Village in H e-Office file No.604237 30/Apr/19 Santhipuram Mandal to Daseganuru Cheruvu of Kuppam Mandal

Construction of Lift scheme on pedda vanka (Kalli Vanka) near athinartham village of gudupalli mandal of chittoor The Estimate for an amount of Rs. 2.38 Crs is prepared. The estimate will be I district to feed chain of tanks and 30/Apr/19 submitted to Govt.after receipt of LA proposals from SE, IC, Chittoor. providing of drinking water facility to kuppam town

The Estimate for an amount of Rs. 2.38 Crs. is prepared.The estimate will be Construction of Lift on Musalimadugu submitted to Govt. after receipt of LA proposals from SE, IC, Chittoor. J tank near Veernamala (V) in 30/Apr/19 Ramakuppam(M)