Review of Prioritized Projects Hon’ble CM conducted Review for Prioritized Projects RECORD OF DISCUSSION

Date Monday, 01st October 2018

Time 03:40 PM to 05:30 PM

Agenda Progress review on Prioritized projects by Hon’ble Chief Minister, A.P

Venue Conference room, AP Secretariat, Velagapudi.

. Shri. D. Uma Maheswara Rao, Hon’ble Minister, WRD . Shri. Shashi Bhushan Kumar, Secretary, WRD . Smt. Rekha Rani – Commissioner, R&R . Shri M. Venkateswara Rao, EnC, WRD Attendees . District collectors . Forest department . Ground water department, APSRAC and M/s Vassar Labs . Chief Engineers from Tirupathi, Ananthapuram, Kadapa, Ongole, & Visakhapatnam . Consultants to APWRD

Page 1 of 6

Action to be # Project / Topic Gist of discussions Timeline taken by

Hon’ble CM and Minister of water resources reviewed status of prioritized projects. Overall status of 57 prioritized projects :  Projects inaugurated: 15 nos. For 1 Overall status -  Projects ready for inauguration: 2 nos. information  Projects in progress: 40 nos.

Hon’ble CM requested to provide timelines for all the prioritized projects. CE, Neeru Chettu briefed progress of works and agreed to complete remaining 542 cascades by the end of October.

Hon’ble CM reviewed works on various schemes under Neeru Chettu Program. He instructed the team to increase the number of Poclains and complete all the balance works at the earliest. Neeru Chettu For 2 - Cascade schemes Hon’ble CM instructed to clear the balance payments (~INR 700 Cr) to all the Information contractors in Neeru Chettu Program.

Secretary, Finance informed that this amount is not included in the budget. Hon’ble CM instructed to borrow money and clear the payments at the earliest.

M/s Vassar Labs presented the work on SCADA for water system. M/s Vassar Labs further explained that the work is still under progress & data is being requested from the concerned CEs.

SCADA for water For 3 Highlights of SCADA View: - systems Information — Water flow of five major rivers and around 40 medium & minor rivers are represented until final distributary. — Inflow, Outflow and capacity (current level & Max. level) of the reservoirs are shown on the reservoirs icon by single click.

Page 2 of 6

Action to be # Project / Topic Gist of discussions Timeline taken by — It is planned to make the system interactive & information shall be available by clicking on the respective reservoirs/ offtakes.

Hon’ble CM appreciated work and instructed to do further study integrate E-panta and Micro Irrigation to the work. Hon’ble CM also suggested to extend the work to show the status of water flow to individual cultivated farm.

Hon’ble CM suggested to conduct an exhibition on SCADA in every district and educate the people on the water resources available across the state.

Secretary, WRD briefed on the water allocation to HNSS model work done by M/s KPMG. Highlights of Water allocation Model: — Current water flow sequence and level — Water allocation planned for FY’18-19 Water allocation to — Details of total reservoirs, Distributaries and Tanks For 4 - HNSS — Hindrances in the planned current flow Information — Possible action to be taken

Hon’ble CM instructed to prepare a detailed irrigation model to aim for “Equity in Distribution of Water” and standard modules to be prepared for Mandal level work. Hon’ble CM instructed to expedite the following projects for the inauguration: — Marala Reservoir — Cherlopally Reservoir CE, Chittor Inauguration of — Madakasira Branch Canal beyond Gollapalli Reservoir 5 CE, - Projects — Adavipalli Lift Anatapuram — Adavipalli Reservoir — Kuppam Branch Canal

Page 3 of 6

Action to be # Project / Topic Gist of discussions Timeline taken by Hon’ble CM instructed to prepare for Gundlakamma Reservoir Project inauguration in the month of October.

CE, Anantapuram briefed on the status of water reachability to the following projects: — Marala Reservoir & Cherlopally Reservoir – 10th Oct’18 — Madakasira Branch Canal – 1st Nov’18 — Kuppam Branch Canal – 1st Dec’18 — Hindupur – 20th Nov’18 — Gollapalli – 5th Oct’18 — Punganoor – 1st Nov’18 Hon’ble CM instructed plan for the water release as per the following sequence: — Cherlopally reservoir to Punganoor — Adavipalli Lift Scheme to Adavipalli Reservoir — Gollapalli to Hindupur to Madakasira

Adavipalli Reservoir For 6 Nellore Barrage - Adavipalli Reservoir: Hon’ble CM instructed to complete works and ensure water information Sangam Barrage availability end October.

Nellore & Sangam Barrage: Hon’ble CM raised concerns on the slow progress of the works and delayed completion date of the project.

Mallimadugu Reservoir, Balaji Reservoir, Hon’ble CM instructed Forest department to clear all the Forest related Venugopala sagar For 7 issues of Mallimadugu Reservoir, Balaji Reservoir, Venugopal Sagar Reservoir and - Reservoir, information Somasila Swarnamuki link canal. Somasila Swarnamuki link canal.

Page 4 of 6

Action to be # Project / Topic Gist of discussions Timeline taken by CE, Kadapa briefed about the status of the work for all the packages:

Package 1: Declaration and Award are under process in SDC ,GNSS Unit-II, Kadapa. Package 2: Proposals for Stage-I forest Clearance submitted to the Principal Secretary, Forest & Environment on 17th Sep’18 For 8 GNSS Phase II - information Package 3: Proposals for Stage-I forest Clearance submitted to the Nodal Officer, Principal Chief Conservator of Forest, Chennai from Principal Secretary , Forest & Environment on 19th Sep’18

Package 4&5: Stage-I clearance completed.

CE, Ongole informed about the refurbishment of TBM. He informed that the Poola Subbiah replacement of deteriorated length of conveyor belt is under process. 9 CE, Ongole - Veligonda Project Hon’ble CM raised concern about the prolongation of the issue and instructed to expedite the works.

CE, GDS, Dowlaiswaram informed motors will be delivered by 15th Oct’18. Chintalapudi Lift For 10 Hon’ble CM instructed to expedite the procurement process and raised - Irrigation Scheme information concern for the delay in procurement.

Uttarandhra Sujala For 11 Sravanthi Project Hon’ble CM instructed to submit detailed program for the project. - information Phase-I works Taraka Rama Thirtha Secretary, WRD instructed CE, NC, Vishakapatnam to submit complete proposal 12 CE, NC - Sagaram Reservoir of LA.

Grounding of New Hon’ble CM instructed to expedite the process of all the new projects to aim for For 13 - Projects immediate grounding information Encl.: Annexure 1 (Brief status of 57 prioritized projects as on 01st Oct’18) Page 5 of 6

Page 6 of 6

ANNEXURE I Status of prioritized projects as on 01 October 2018 Target Date of project Sl no. Project Major Issue / Current status completion Inaugurated projects - 15 nos. 1 Purushotha Patnam LIS Inaugurated on 15th Aug 2017 - Construction of Anicut across Sarada 2 Inaugurated on 6th Sept 2017 - River 3 Mutchumarri LIS Inaugurated on 8th Sept 2017 -

4 Kandaleru Left Canal – Lift Scheme Inaugurated on 12th Nov 2017 -

5 Gandikota – CBR Lifts Inaugurated on 3rd Jan 2018 -

6 Siddapuram Lift Irrigation Scheme Inaugurated on 7th Jan 2018 -

7 Modernisation of Yerracalva Inaugurated on 8th Jan 2018 - Formation of Pogonda Reservoir in 8 Inaugurated on 19th Feb 2018 - West Godavari 9 SH-31 Road Work (GNSS Phase I) Inaugurated on 6th June 2018 - Pulakurthy LI Scheme 10 Inaugurated on 23rd Aug 2018 - (Guru Raghavendra Project) 11 Chinasana LI Scheme on VLMC Inaugurated on 15th Sep 2018 -

12 Kondaveeti Vagu Pumping Scheme Inaugurated on 16th Sep 2018 - Gorakallu Balancing Reservoir (Sri 13 Inaugurated on 22nd Sep 2018 - Narasimharaya Sagar) 14 Owk Tunnel (GNSS Phase I) Inaugurated on 22nd Sep 2018 -

15 Pulikanuma LIS Inaugurated on 22nd Sep 2018 - Projects ready for Inauguration - 2 nos. Pedapalem LI Scheme on Krishna 16 Ready for inauguration - River 17 K.L. Rao Sagar Ready for inauguration - Projects in progress under purview of CE, Tirupathi Reservoir : Project works completed Adavipalli Reservoir (HNSS Phase-II) & Reservoir Completed. 18 Adavipalli Lift (Peddamandyam lift on Lift scheme : Transmission towers 118 nos. completed, 2 towers works in Main canal) progress. Project shall be completed by 31 Aug 2018. Requested for Lift scheme : 15-Oct-18 extension of time up to 15 Oct 2018. Work in progress at 5.198 Km. Out of 143 structures, 67 nos. in progress. 19 Kuppam Branch Canal (HNSS Phase II) Balance 76 nos. of structures to be taken up. Expected date of completion:15 15/Nov/18 Nov 2018.

Overall completionstatus 85.04%. 20 Nellore Barrage Balance quantities : Earthwork - 5.16 lakh cum and concreting - 11,288 cum 15/Oct/18 Requested for extension of time up to 15 Oct 2018.

Overall project completion 64.85% 21 Sangam Barrage Rafts, 41 nos. completed out of 42 nos. 30/Nov/18 Piers, 70 nos. completed out of 86 Nos.

Water Supply to Mulapalli and other 4 22 31/Dec/18 tanks. Bid Evaluation Reports were submitted to COT for approval of tender. Part-A: Lifting of water from Merlapaka to Mallemadugu Reservoir : Lifting of water from Somasila Estimate for Rs.288.80 Crs submitted to Government for according Swarnamuki link canal (Merlapaka Administrative approval.Government communicated certain remarks and the 23 - Reservoir) to Mallemadugu Reservoir replies are under submission. and Mallemadugu to Balaji Reservoir Part-B: Replies to the remarks called for by the Government are submitted on estimate for Rs. 198.00 Crores Forest clearance proposals submitted to the Government of . 24 Mallimadugu Reservoir 31/Dec/18 Two no. of structures, Balance quantities of 15.11 lakh cum of earth work and 24,889cum of concrete is to be executed. Page 1 of 5 ANNEXURE I Status of prioritized projects as on 01 October 2018 Target Date of project Sl no. Project Major Issue / Current status completion Forest clearance proposals submitted to the Government of India. 25 Balaji Reservoir 31/Dec/18 Balance quantities to be executed : EW - 48.15 lakh cum & Concrete - 32,356 cum Authentication of CA Lands in process. Earthwork to the tune of 40.81 lakh 26 Venugopala sagar Reservoir cum, concreting of 33,300 cum and bund making for a lengh of 1.52 Km is to 31/Dec/18 be executed.

Somasila Swarnamuki link canal. (from All formalities required for stage-I clearance have been uploaded. 27 31/Dec/18 km 56.000 to 100.425) Project status : 65.56% completed.

Lifting of water from SSG Canal to Reservoir tender proposals are under finalization in COT. Lift portion 28 31/Mar/19 Althurupadu Reservoir (2.356 TMC) agreement concluded and work is in progress

Projects in progress under purview of CE, Anantapur Rectification measures are done and will be completed by 10 Oct 2018. 29 Marala Reservoir Reservoir will be filled after completion of rectification measures. Requested 10/Oct/18 extension of time up to 10-Oct-2018 Rectification measures are done and will be completed by 10 Oct 2018. 30 Cherlopally Reservoir Reservoir will be filled after completion of rectification measures. Requested 10/Oct/18 extension of time up to 10-Oct-2018 Work in progress. Canal of 2.2 Km, earth work - 3.75 lakh cum and concrete - Madakasira Branch Canal beyond 31 41,740 cum is to be executed. 31/Oct/18 Gollapalli Reservoir Requested extension of time up to 31-Oct-2018 Work stopped due to water release in to the Canal. Work will be resumed Widening of HNSS Main Canal under after closing of canals. 32 31/Mar/19 Phase-I Earth work of 1.47 Cr cum and concrete of 3.12 lakh cum is to be exuecuted.

Civil works- LA Work is under progress and Canal Excavation work to be Lifting water from 33 started on 10-10-2018. Electro-mechanical works tenders approved in 30/Jun/19 to Bhairavanithippa Project. COT Water lifting from Jeedipalli Reservoir Works grounded.Investigation abd Preparation of LP Schedules are In 34 30/Jun/19 to Upper Pennar progress.

Upto 40th KM : Modernization of Mid – Pennar South Earthwork of 7.18 lakh cum and concrete of 1.71 lakh cum is to be executed. 35 Canal from Km 0.000 to Km 40.000 & 31/Mar/19 from Km 40.000 to Km 84.000 40th KM to 84 KM : Earthwork of 2.84 lakh cum and concrete of 2.22 lakh cum is to be executed.

Works grounded. 85 % of investigation work is completed and execution of Community Lift cum Drip Irrigation, 36 civil work 30/Jun/19 Uravakonda will be started by 15-Oct-2018. Requested extension up to 30-Jun-2019.

Projects in progress under purview of CE, Kadapa To store 12TMC water, 3066 PDF’s of Rama Chandra Nagar colony, Kondapuram needs to be shifted. The Government vide G.O Rt. No.619, Proposed for Inauguration dated.04.Sep.2018 sanctioned an amount of Rs.198.975 Crores towards one by Hon’ble CM after 12 37 Gandikota Reservoir (GNSS Phase I) time gratuitous relief to PDF’s for filling 12 TMC of water in Gandikota TMC of Water is stored in Reservoir. reservoir. Payment is being made to PDFs and the shifting is going on. Declaration and Award are under process in SDC ,GNSS unit-II, Kadapa. Recasting of the Estimate with current SSR 2018-19 will be submitted by 01- 38 GNSS Ph-II up to Kodur in Kadapa Dist. 31/Mar/19 Oct-2018.

Projects in progress under purview of CE, Kurnool Hagari (Vedavathi Project) Lift irrigation Hydrological clearances in progress. Agency finalized for SID operations. 39 - scheme Investigation works in progress.

Water Supply to Western Mandals of 40 Works in progress 31/Jan/19 Kurnool District Page 2 of 5 ANNEXURE I Status of prioritized projects as on 01 October 2018 Target Date of project Sl no. Project Major Issue / Current status completion Inter State issue - State is objecting for completing the balance survey work (95% of Survey work completed). Five Villages will be submerged 41 Formation of Gundrevula Reservoir in Mahabubnagar Dt. CWC,KRMB and Telangana Govt. to be addressed for co- - operation and concurrence. Govt. instructed CE, ISWR, to examine and furnish a detailed report. Replies to remarks on DPR submitted to Govt. along with estimate for an Rajolibanda Diversion Scheme (RDS) 42 amount of Rs.1485.00 Cr.Administrative approval to be received - Right Canal Projects in progress under purview of CE, Ongole

Kandula Obul Reddy Gundlakamma LA Process initiated in the approved alignment. 98% of work completed. 43 31/Dec/18 Reservoir Project Earthwork of 2.41 lakh cum and concrete of 10,743 cum is to be executed.

Villagers obstructing work demanding compensation for structures and crops. Court case on LA of 340.23 Ac. Valuation of structures in Thurpupalem and Yerram Chinnapoli Reddy Korisapadu 44 Pedduru 31/Dec/18 LIS villages completed and DN was published on 20.Aug.18. Earth work to the tune of 14.98 lakh cum and concrete of 19,216 cum is to be executed. Head Regulator Work is stopped due to raise in water levels in Srisailam Reservoir. Gantry is fixed to lay CC for lining.Requested extension up to 15.Jan.2019. Poola Subbiah Veligonda - Tunnels I & 45 15/Jan/19 II and Head Regulator Refurbishment of TBM and replacement of deteriorated length of conveyor belt is under process. Requested extension for Tunnel-1 up to 15-01-2019. Requested extension for Tunnel-2 up to 31-05-2019. Projects in progress under purview of CE, North coast Visakhapatnam Due to release of water and continuous rains, the works are not being taken up. BRR Vamsadhara Project Stage II 46 Works will be resumed after completion of Monsoon season (Probably in the 31/Mar/19 Phase II 1st week of December 2018). Work is programmed to be completed by 31.03.2019. Interlinking of Vamsadhara and 47 Revenue authorities plan to complete balance LA of 135.46 acres by 30th Sep 2018 31/Dec/18 Nagavali Rivers

Progress of work is hampered due to rains.Canal work is programmed to be Offshore reservoir on Mahendratanaya 48 completed by 31.03.2019. 32.42 % of work completed. R&R issues for 2 PDF 31/Dec/18 River Villages.

High Level Canal from Hiramandalam 49 Preparation of DPR under process and will be completed by 15.10.2018 30/Jun/20 Reservoir to Itchapuram Balance L.A 193.211 Acres is being pursued with L.A. Authorities. SLSC cleared the deletion Proposals . Notice issued under Clause 61 of Taraka Rama Thirtha Sagaram 50 APDSS to resume the work immediately. 30/Jun/19 Reservoir R & R Works are under progress in Agraharam, Koradapeta and Padalapeta. 44.49 % of work completed.(Both Packages) Modernisation of Thotapalli Old 51 Tenders process to be completed (evaluation is under process). - Regulator System Projects in progress under purview of CE, KDS, Vijayawada

52 K.L.RAO Pulichinthala Project Will be Inaugurated after storing of 30 TMC of water during current season -

Construction of new barrage (10 TMC) Tenders called for and last date for bid submission is 04 Oct'18.Technical bid 53 across near will be opened on 4 Oct'18.Price bid will be opened on 8 Oct'18 1/May/20 . Period of Completion 24 months Tenders called for and last date for bid submission is 01 Oct'18. Technical Bid Interlinking Of Godavari – Penna Rivers Partial completion by 54 will be opened on 03 Oct'18.Price Bid will be opened on 06 Oct'18 Phase-1 31/Dec/18 Period of Completion 24 months.

Page 3 of 5 ANNEXURE I Status of prioritized projects as on 01 October 2018 Target Date of project Sl no. Project Major Issue / Current status completion Projects in progress under purview Engineer in chief PIP (SE,LMC,Tuni) Part 1: Formation of Pedapudi reservoir, Gravity Canal - Agreement concluded and works commenced.

Uttarandhra Sujala Sravanthi Project Part 2 : Excavation of leading channel and Two stage lifiting at 55 30/Jun/19 Phase-I works Jammadulapalem and Teeda and Canal Distributory network to irrigate an Ayacut of 1.3 lakh acres in Vishakhapatnam District. Agreement concluded. Works will commence.

Projects in progress under purview CE, GDS - Dowlaiswaram Stage-I clearance accorded by the MOEF to an extent of 347.64Ha. Uploading For Stage-I Clearance of 69.30 Ha Forest Land for Phase-II (Canal) works 56 Chintalapudi Lift Irrigation Scheme completed.Forest land for Phase-II (canal) work were uploaded. 28/Feb/19 Land Acquisition case in Hon’ble High Court is being pursued by land acquisition authorities. Projects in progress under purview Chief Engineer, Minor, Vijayawada & JMD, APSIDC (Kuppam Constituency) 57 Minor Irrigation Works and Lift Schemes in Kuppam Area PALAR CHECKDAMS: New 30 No's CE Minor submitted proposals to ENC (AW) For approval vide letter dated 25- A 31/Mar/19 Sep-2018.

The Finance department returned the proposals on 25.09.2018 to re examine regarding cost per acre, as reconstruction /repair cost for the old checkdams is PALAR CHECKDAMS : Re arrived as Rs. 76,280/- which is on higher side as against normal ceiling of Rs. B construction and Repairs - 13 No’s 31/Jan/19 40,500/- and requested to resubmit proposal in the next financial year 2019- 20 along with benefit cost ratio. e-Office file No. 480511 PALAR CHECKDAMS : Re Estimates for Rs .23.28 Crs submitted to Govt. for Administrative C construction and Repairs - 8 No’s sanctions.File is sent to Finance department on 23.08.2018. 31/Jan/19 e-Office file No. 590700 Improvements to feeder channel from Estimate for Rs. 3.25 Crs submitted to Govt. for Administrative approval Jambu cheruvu to PB Natham cheruvu after attending Remarks. D 31/Dec/18 near PB Natham (v) in Kuppam (M) e-Office file No. 303198

Reconstruction of Checkdam across Estimate for Rs. 5.90 Crs submitted to Govt. for Administrative approval after Manjalamadugu vanka near V. E attending Remarks. 31/Dec/18 Mittapalli (V) in Kuppam (M) e-Office file No. 620043

Extension of tank bund on L/S and R/s The Estimate for Rs. 1.43 Crs submitted to Government by CE Minor Irrigation of Existing tank bund of D.K.palli to vide letter dated 25-Sep-2018. F 30/Nov/18 safeguard from Encroachments

Improvements to Check Dam across Peddavanka near Athinatham (V) in CE Minor Irrigation communicated remarks on the proposal to SE/IC Chittoor. G 31/Mar/19 Gudupalli (M)

Excavation of Diversion Channel from The estimates for Rs. 18.43 Crs submitted to Govt. for Administrative Preethichamanuru percolation tank approval. near Preethichamanuru Village in H e-Office file No.604237 30/Apr/19 Santhipuram Mandal to Daseganuru Cheruvu of Kuppam Mandal

Construction of Lift scheme on pedda vanka (Kalli Vanka) near athinartham village of gudupalli mandal of chittoor The Estimate for an amount of Rs. 2.38 Crs is prepared. The estimate will be I district to feed chain of tanks and 30/Apr/19 submitted to Govt.after receipt of LA proposals from SE, IC, Chittoor. providing of drinking water facility to kuppam town

Page 4 of 5 ANNEXURE I Status of prioritized projects as on 01 October 2018 Target Date of project Sl no. Project Major Issue / Current status completion The estimate will be submitted to Govt.after receipt of LA proposals from SE, IC,Chittoor. Construction of Lift on Musalimadugu The estimate will be submitted to Govt. after receipt of LA proposals from SE, J tank near Veernamala (V) in 30/Apr/19 IC, Chittoor. Ramakuppam(M)

Page 5 of 5