Review of Prioritized Projects Hon’ble CM conducted Review for Prioritized Projects RECORD OF DISCUSSION

Date Monday, 23rd July 2018

Time 4.30pm to 7.30pm

Agenda Progress review on Prioritized projects by Hon’ble Chief Minister, A.P

Venue Conference room, AP Secretariat, Velagapudi.

. Shri. D. Uma Maheswara Rao, Hon’ble Minister, WRD . Smt. Rekha Rani – Commissioner, R&R . Shri M. Venkateswara Rao, EnC, WRD . District collectors Attendees . Forest department . Ground water department, APSRAC and M/s Vassar Labs . Chief Engineers from Tirupathi, Ananthapuram, Kadapa, Ongole, & Visakhapatnam . Consultants to APWRD

Page 1 of 5

Action to be # Project / Topic Gist of discussions Timeline taken by

Hon’ble CM and Minister of water resources reviewed status of prioritized projects. Overall status of 56 prioritized projects : For 1 Overall status -  Projects inaugurated: 9 nos. information  Projects ready for inauguration: 6 nos.  Projects in progress: 41 nos. CE, Kurnool inquired about whether to take water inflow or wait till 25th August for Information on th intake of water. Hon’ble CM instructed to complete all the works by 25 August’18 For 2 inaugurated - and ensure water shall be taken from Owk to Gandikota. Information Projects

Secretary, WRD informed that all CEs to note that water to be filled in all the tanks. Phase 1- 40% filling in all tanks & Phase 2- 30% and Phase 3-30%. Until Phase-1 For 3 Filling of tanks 40% is not filled in all tanks, phase 2 cannot be initiated. - Information Ensure to fill all the tanks by gravity, otherwise fill by minor lifts.

Secretary, WRD informed all 4 CEs to coordinate so that HNSS, GNSS, SRBC, TGB, HLC, LLC, day wise offtake schedule is prepared for main canals for offtake Offtake wise water wise release of water schedule. A Whatsapp group should be prepared for sharing For 4 - release schedule the information across the 4 CEs. Information Hon’ble CM informed that water shall be pushed by gravity in HLC. Ensure cost effective pushing of water from Srisailam.

CE, Tirupathi briefed status to Hon’ble CM.  Adavipalli Reservoir – 190 Cum of concrete is balance. Project shall be ready for  Adavipalli Adavipalli inauguration by 31st July’18 reservoir reservoir shall 5  Nellore Barrage  Kuppam Branch canal- Works slowed down by contractor in wake of claim CE, Tirupathi be completed  Sangam Barrage settlement. EnC informed that SLSC meeting shall be held this week and the by 31st July’18  Venugopal Sagar issue shall be resolved within 2-3 days.  Nellore Barrage – 82% of work is completed.  Sangam Barrage – 76% of works is completed

Page 2 of 5

Action to be # Project / Topic Gist of discussions Timeline taken by  Venugopal Sagar - DGPS Survey for CA Land shall be completed by 25th July’18

CE, Anantapuram briefed status to Hon’ble CM.  Marala reservoir Completion of  Cherlopalli  Marala & Cherlopalli reservoirs - Rectification measures are in progress and will CE, Madakasira 6 reservoir be completed by 31-07-2018 Anantapuram Branch canal by  Madakasira  Madakasira Branch Canal – All bottlenecks cleared. Project shall be completed 31st July’18 Branch Canal by 31st July’18

CE, Kadapa briefed status to Hon’ble CM  Gandikota  Reservoir (GNSS Gandikota reservoir – 17 Habitations shifted out of 26 affected habitations. 7701 Phase I) PDFs shifted out of 19261 PDFs. For storing 12 TMC, 3782 PDFs to be shifted. DGPS 7  GNSS Ph-II up to  GNSS Ph-II up to Kodur in Kadapa Distt. - DGPS Survey for 5 Packages CE, Kadapa uploading by Kodur in Kadapa completed. Stage -1 uploading shall be completed by 26-07-2018 26th July’18 Dist. Hon’ble CM instructed commissioner R&R to clear the issue.

Hon’ble CM instructed that on 15-August’18, Hiramandalam reservoir shall be inaugurated. Hon’ble CM informed that it shall be declared that 5 TMC water Hiramandal  Hiramandalam storage is ready and balance shall be ready by September/October. CE, 8 Reservoir by Reservoir Srikakulam 15th August’18 CE, Srikakulam informed that 5 TMC water can be stored by 10th August’18

Hon’ble CM reviewed the Ground Water status. M/s Vassar labs briefed the status of rainfall in the state. Ground Water Hon’ble CM informed that 9 For Info - Status 1. Ground Water & Surface water balancing is to be done by conjunctive use of water. 2. Rain fed crops should be sustained by implementing rain guns.

Page 3 of 5

Action to be # Project / Topic Gist of discussions Timeline taken by Hon’ble CM reviewed status of Neeru Chettu works Secretary, WRD informed that there is traction in the works of cascade Neeru Chettu- construction. Action plan is prepared for cascade execution- District wise plotting 10 Cascades of cascades has been completed on the map. A special Chief Engineer, Shiva Ram CE, MI - development shall be responsible for district wise grounded and ungrounded Cascades and completion of the same.

Hon’ble CM instructed to have a time bound program for completion of 10 lakhs farm ponds (cumulative). Maintenance shall be done properly. 11 Neeru Pragati CE,MI - All de silting works shall be completed within 6 months. (Work worth 64 Crores). 2 contractors shall be finalized & required equipment to be mobilized.

Hon’ble CM informed that filling of all the balance tanks execution shall be completed by 31st March’19. Fill all tanks through gravity, simple lifts or mobile lifts.

Secretary, WRD informed that a project to develop 10000 tanks is inspired by our Neeru Pragati- For 12 own Hon’ble CM’s thought process to develop tanks as a living cascade- total - Filling of tansk Information command area under this project of developing 10, 000 tanks is 90,000 Hectares. There is a strong forward and backward integration like changing of cropping pattern & increase in efficiency. Overall convergence of Horticulture, fisheries & WRD is also planned.

Hon’ble CM informed that All new Lift Irrigation schemes to be synchronized with JMD- Micro irrigation. APSIDC/ 13 Drip Irrigation. - Hon’ble CM also instructed to have target of converting 10 lakh acres per year to Micro micro irrigation. Irrigation Micro 14 Sowing Advise Hon’ble CM advised to provide audio/video based sowing advise to the farmers - Irrigation

Page 4 of 5

Action to be # Project / Topic Gist of discussions Timeline taken by Hon’ble CM informed that for Nagarjuna Sagar right canal, water shall be provided. For 15 Cropping Pattern First crop shall go for Dry crop and if water is available for second crop, then they - information can go for wet crop. Encl.: Annexure 1 (Brief status of 56 prioritized projects as on 23rd July’18)

Page 5 of 5

ANNEXURE I Target Date of project Sl no. Project Current status completion Inaugurated projects 1 Purushotha Patnam LIS Inaugurated on 15th Aug 2017 - Construction of Anicut across Sarada 2 Inaugurated on 6th Sept 2017 - River 3 Mutchumarri LIS Inaugurated on 8th Sept 2017 - 4 Kandaleru Left Canal – Lift Scheme Inaugurated on 12th Nov 2017 - 5 Gandikota – CBR Lifts Inaugurated on 3rd Jan 2018 - 6 Siddapuram Lift Irrigation Scheme Inaugurated on 7th Jan 2018 - 7 Modernisation of Yerracalva Inaugurated on 8th Jan 2018 - Formation of Pogonda Reservoir in 8 Inaugurated on 19th Feb 2018 - West Godavari 9 SH-31 Road Work (GNSS Phase I) Inaugurated on 6th June 2018 - Projects ready for Inauguration 10 Pedapalem LI Scheme on Ready for inauguration - 11 Chinasana LI Scheme on VLMC Ready for inauguration - 12 Owk Tunnel (GNSS Phase I) Ready for inauguration - Gorakallu Balancing Reservoir (Sri 13 Ready for inauguration - Narasimharaya Sagar) 14 Pulikanuma LIS Ready for inauguration - Pulakurthy LIS (Guru Raghavendra 15 Ready for inauguration - Project)

Page 1 of 8 ANNEXURE I Target Date of project Sl no. Project Current status completion Projects in progress under purview of CE, Tirupathi Reservoir : Gates erection in progress. Requesting to consider revised completion date as 31-July-18 Adavipalli Reservoir (HNSS Phase-II) & Reservoir by 31-July-18 16 Adavipalli Lift (Peddamandyam lift on Lift scheme : Erection of Pump house roof and 132/6.6KV, Sub station is in Lift scheme by 31-July-18 Main canal) progress, 115 Transmission towers completed, 3 Nos in progress & 2 Nos to be tackled. 1.315 Km length of Pipe Line is in progress Part A :From Km. 0.00 to Km 39.225 (up to II lift) : Pump house erection in Canal shall be made progress through by 30 July 2018 17 Kuppam Branch Canal (HNSS Phase II) Part B : Work is progress in 5.037 Km. 3,15,374 cum earth work & 38,070 cum Structures and balance concrete is to be completed. out of 134 Nos. of structures, 48 are in works shall be progress & 86 to be taken up. complebted by 30-Aug-18 18 Nellore Barrage Overall completionstatus 82%. Project shall be completed by 31st Aug'18 31/Aug/18 Overall project completion 76% 19 Sangam Barrage Rafts, 38 nos. completed out of 42 nos. 31/Aug/18 Piers, 68 nos. completed out of 86 Nos. Alienation of Forest land- DGPS survey completed for 760 Ha of CA land for both Mallimadugu Reservoir and Balaji Reservoirs. Forest Dept requested 20 Mallimadugu Reservoir 31/Dec/18 additional CA land. DGPS survey of 266.67 Ha of additional CA land is in progress and will be completed by 25-07-2018. Alienation of Forest land- Forest and CA land is combined proposal for both Mallimadugu Reservoir and Balaji Reservoirs. DGPS survey will be completed 21 Balaji Reservoir 31/Dec/18 by 25-07-2018. Work is in progress Proposals for extra payment for additional lead for formation of Bund are submitted to Govt for approval. Alienation of Forest land- DGPS Survey for CA Land is in progress and will be 22 Venugopala sagar Reservoir 31/Dec/18 completed by 25-07-2018. Alienation of Forest Land (375.472 Ha) Alienation of Forest land- The PCCF, authenticated DGPS Survey for Somasila Swarnamuki link canal. (from 23 21.213 Ha of CA Lands. Stage-1 uploading will be completed by 27-7-2018. 31/Dec/18 km 56.000 to 100.425) 62.93% of work completed. Govt accorded administrative approval for Rs. 39.48 Crores on 04.06.2018. Water Supply to Mulapalli and 24 Tenders opened. Bid evaluation is under process. 31/Dec/18 other 4 tanks.

Page 2 of 8 ANNEXURE I Target Date of project Sl no. Project Current status completion Lifting of water from Somasila Swarnamuki link canal to Mallemadugu Lifting of water from Somasila Reservoir :Estimate for Rs 288.80 Cr submitted to Government for according Swarnamuki link canal to Mallemadugu 25 Administrative approval. 31/Dec/18 Reservoir and Mallemadugu to Balaji Lifting of water from Mallemadugu to Balaji Reservoir: Estimate for Rs 198.00 Reservoir Cr submitted to Govt. for according administrative approval Althurupadu Balancing Reservoir : Tenders are under scrutiny in COT. Lifting of water from SSG Canal to 26 31/Mar/19 Althurupadu Reservoir Althurupadu Lift Scheme : Tenders are under scrutiny in COT

Page 3 of 8 ANNEXURE I Target Date of project Sl no. Project Current status completion Projects in progress under purview of CE, Anantapur At Km 458.00 in the Tunnel, spoil is continuously falling from top Rectification measures are being done and will be completed by 31-07-2018 27 Marala Reservoir 31/Jul/18 Reservoir will be filled during khariff season, when sufficient water is available in . At Km 458.00 in the Tunnel, spoil is continuously falling from top Rectification measures are being done and will be completed by 31-07-2018 28 Cherlopally Reservoir 31/Jul/18 Reservoir will be filled during khariff season, when sufficient water is available in Jeedipalli reservoir. Madakasira Branch Canal beyond 29 Works in Progress 31/Jul/18 Gollapalli Reservoir Widening of HNSS Main Canal under 30 Works in Progress 31/Jul/18 Phase-I 14,11,300 Cum of Earthwork is completed out of 30,61,650 Cum. Modernization of Mid – Pennar South Construction of Structures is under progress. 31 Canal from Km 0.000 to Km 40.000 & 7,16,500 Cum of Earthwork is completed out of 15,97,480 Cum. 31/Mar/19 from Km 40.000 to Km 84.000 Construction of Structures is under progress.

Civil Works- Work started on 30-06-2018 Lifting of water from Jeedipalli 32 Electro Mechanical Works- Price bids opened on 19.07.2018 and Evaluation 30/Jun/19 Reservoir to Upper Pennar Project Reports submitted to COT for approval. Lifting of water from Jeedipalli 33 Reservoir to Upper Pennar Project Works started 30/Jun/19

Community Lift cum Drip Irrigation Agreement Concluded on 15.06.2018. Investigation work will be completed by 34 Project 15-08-2018 30/Apr/19

Page 4 of 8 ANNEXURE I Target Date of project Sl no. Project Current status completion Projects in progress under purview of CE, Kadapa 17 habitations Shifted out of 26 affected habitations. 7701 PDFs Shifted out of 19261 PAFs/PDFs . Will be inaugurated after 35 Gandikota Reservoir (GNSS Phase I) For storing 12TMC water, 3782 PDF’s of Rama Chandra Nagar colony, 12 TMC water stored in Kondapuram are to be shifted. reservoir The proposals of R&R are under process with Commissioner,R&R. Forest clearances : DGPS Survey for 5 Packages is Completed.Stage -1 Uploading will be completed by 26-07-2018 . Package-1 DN Completed. Declaration and Award are under process in SDC ,GNSS Unit-II, Kadapa. Estimate for Rs 530.00 Cr for balance work submitted to GOVT for approval . Package-2 Contract is pre-closed. Settlement of accounts is under process . Estimate of Rs 525.00 Cr for balance work submitted to GOVT. for approval. LA of 159.96 Ac in PN stage, 34.36 Ac in PD stage, 74 Ac in SDR stage and 25.35 Ac in award Stage DGPS Survey completed for CA land Uploading for Stage-I 36 GNSS Ph-II up to Kodur in Kadapa Dist. Clearance completed. Package-3 Work is in progress. Enumeration of trees is completed. Digitization of data is under progress @ DFO, Kadapa Package-4 Pre-closure of old contract is under process. Estimate of Rs 516.720 Cr for balance work submitted to GOVT. for approval. DGPS survey completed Uploading for Stage-I Clearance by 26-07-2018. Package-5 Pre-closure of old contract is under process. Estimate for balance work for Rs 477.26Cr submitted to GOVT. for approval. DGPS survey completed. Uploading for Stage-I Clearance by 26-07-2018 Projects in progress under purview of CE, Kurnool Hagari (Vedavathi Project) Lift irrigation Hydrological clearances in progress. Tenders finalization for SID operations is in 37 - scheme progress Water Supply to Western Mandals of 38 Finalization of Tenders is under process at COT. 31/Jan/19 Kurnool District Page 5 of 8 ANNEXURE I Target Date of project Sl no. Project Current status completion 95% of Survey work completed.5 No of Villages will be submerged in Mahabubnagar Dt .CWC,KRMB and Govt. to be addressed for co- 39 Formation of Gundrevula Reservoir - operation and concurrence. Govt. instructed CE, ISWR, to examine and furnish a detailed report to Govt. Rajolibanda Diversion Scheme (RDS) Replies to remarks on DPR submitted to Govt. on 15-6-2018 along with 40 - Right Canal estimate for an amount of Rs.1485.00 Cr. Projects in progress under purview of CE, Ongole Kandula Obul Reddy Gundlakamma Investigation is being conducted by the agency for alternate proposals in 41 31/Jul/18 Reservoir Project Duddukur Village as agreed by the land owners. Villagers obstructing work demanding compensation for structures and crops. Court case on LA of 340.23 Ac Project is proposed to be Valuation of structures in Thurpupalem and Pedduru villages completed. inaugurated during next Yerram Chinnapoli Reddy Korisapadu 42 L.A is in process for R & R Colony to resettle the PDFs of Thurpupalem and khariff season after LIS Pedduru villages. impounding water in the Crop compensation report submitted to the Govt., by the District Collector, reservoir. Ongole. Tunnel 1 : 77m (91%) completed out of 85m Tunnel 2 : 77m (73%) completed out of 105m

Proposal for entrustment for additional 500 m length of Tunnel – 1 at non EPC rates to the Head regulator agency submitted to the Government. Head Regulator Veligonda Project - Tunnels I & II & 43 3.60 KM in Tunnel-1 & 8.037 Km in Tunnel-2 Km were deleted under clause completion : 17 Sept Head Regulator 60(c) from the existing agencies. Hon’ble High Court passed orders (5 June'18) 2018 on the WP filed by the original agencies of Tunnel-1 and Tunnel-2,.

Fresh Deletion orders will be issued as per the court orders.Bid evaluation to be submitted to COT for approval.

Page 6 of 8 ANNEXURE I Target Date of project Sl no. Project Current status completion Projects in progress under purview of CE, KDS, Vijayawada INR 49.00 Cr shall be released to Dt. Collector, Suryapet, Telangana, towards After storing 30 TMC of shifting of 4 L.I Schemes. The Joint Collector & Project Administrator, K.L.R.S 44 K.L.RAO water during Kharif Pulichintala Project, Guntur is requested to authorize and transmit the amount season to District Collector, Suryapet. Work in progress under Police Protection. Eviction of houses started and Earth work excavation in Fore bay portion is in progress . Permission for ROW from 45 Kondaveeti Vagu Project 31/Jul/18 Railway authorities is being pursued through AP Transco. Request for time upto 31-7-2018 for inauguration. Construction of new barrage (10 TMC) 46 across Krishna river near Tender notification issued on 9th July'18 1/May/20 . Interlinking Of Godavari – Penna Rivers Preparation of Designs & Estimates are under progress Tenders notification Partial completion by 31 47 Phase-1 shall be issued by 25th July'18 Dec'18 Proposal is under examination in Inter state and hydrology aspects. 48 Mukthyala Lift irrigation Scheme - Technical feasibility is under study. Modernisation of Thotapalli Old GoAP accorded administrative approval for an amount of Rs.195.34 Cr., vide 49 - Regulator System G.O.MS.No.67, dated 28th June 2018. Tender process shall commence shortly. Survey work commenced. High Level Canal from Hiramandalam 50 Action Plan :Preparation of DPR by August'18 & Submission of estimates by Reservoir to Itchapuram September'18 Projects in progress under purview Engineer in chief PIP (SE,LMC,Tuni) PART 1: Formation of Pedapudi reservoir, Gravity Canal etc. Agreement concluded. Work started.

Uttarandhra Sujala Sravanthi Project PART 2:Excavation of leading channel and Two stage lifiting at 51 - Phase-I works Jammadulapalem and Teeda and Canal Distributory network to irrigate an Ayacut of 1.3 Lakh Acres in Vishakhapatnam District . Tenders are opened and Bid evaluation submitted to COT for approval.

Projects in progress under purview CE, GDS - Dowlaiswaram

Page 7 of 8 ANNEXURE I Target Date of project Sl no. Project Current status completion RRemarks of SLSC on revised estimate are being attended. Stage-I clearance was accorded by the MOEF to an extent of 347.64Ha. Uploading For Stage-I Clearance of 69.30 Ha Forest Land for Phase-II (Canal) 52 Chintalapudi Lift Irrigation Scheme 28/Feb/19 works completed. Land Acquisition case in Hon’ble High Court is being pursued by land acquisition authorities. Projects in progress under purview of CE, Northcoast- Visakhapatnam Package-87& 88: The work is in progress. Proposed to draw 4000 Cusecs of water completing all the critical structures by 10.08.2018. Proposed to 31.07.2018 so as to store Vamsadhara Project Stage II Phase II complete the erection of gates and draw 6000Cusecs of water by 8.00TMC of water in 53 15.09.2018.Proposed to complete erection of gates and store 5TMC of water Reservoir. by10.8.2018 Proposed to store 6TMC of water by 15 09 2019 Interlinking of Vamsadhara and Land Acquisition is under process . 54 31/Dec/19 Nagavali Rivers Proposals sent to Govt for release of Rs.38.23 Crores for land acquisition Offshore reservoir on 55 Work in Progress. 31/Dec/19 Mahendratanaya River Balance L.A 216.41 Acres is being pursued with L.A. Authorities. Taraka Rama Thirtha Sagaram 56 SLSC cleared the deletion Proposals. Notices issued to resume the balance 30/Jun/19 Reservoir Project work. R & R Works are under progress in Agraharam, Koradapeta and Padalapeta.