Future plans for Railway Power Supply

Energy Plan, Nils Grønneberg Infrastructure – Energy – Planning (Engineering)

The engineering section is one of two sections in the Planning (Engineering) and Project department

12 employees specialising in electricity/energy

2 Infrastructure – Energy – Plan

• Investigation of need for Railway Power Supply, nationally

Simulation and load analyses based on: − traffic information (current and future wagon-routing tables) − infrastructure information (gradient, tunnel, catenary, etc.) − stock information (train types, composition, freight loads, characteristics) − converter data (equipment, types, performance, characteristics, etc.) − converter failure scenarios.

Technical-financial analysis with recommended measures

Advisor assistance through framework agreements

3 Infrastructure – Energy – Plan

• Concept designs for relevant converter stations

Define location, concept and dimensioning.

Stakeholder analyses and environmental impact.

Technical-financial pilot project with recommended solution, forming the basis for detailed planning, approval and potential tendering.

4 Infrastructure – Energy – Plan

• Professional support:

Provide technical expertise for the projects

Specify technical requirements

Evaluate tenders

Follow up technical deliveries

5 Infrastructure – Energy – Plan

• Framework conditions

National Transport Plan (NTP)

Expansion and development of railway sections

Amendment of traffic and equipment

Refurbishment of CL installation (AT)

Technical Regulations (TRV)

Regulations, etc.

Allocation – order from Jernbane Directorate

6 Investigation areas, Energy Supply

(2018) • Line (2012) • Line (2012) − with Flåm Line • Sørlandet Line (2017) − etc. • region (2018) − Eastern

7 Investigation areas, Energy Supply

• Oslo area, scope: − () − Gjøvik Line − Line − Main Line and − Østfold Line, East/West, Line and Line − Line − Line − Sørlandet Line (Nordagutu) − etc.

8 Plans in the Oslo area

• New central converter station – Oslo East

Concept design, part 1 (location): Åsland (Follo Line) Concept design, part 2 (dimensioning): Initiated

Provisional plan: Static converters, 4 x 40 MVA

Turnkey contract: 2019-2021

• Closure of Alnabru and Holmlia converter stations

9 Plans in the Oslo area

• Temporary converter station in Vestfold

Linked to new double track Nykirke - Barkåker (UNB) Concept design work has not commenced Land earmarked at new Skoppum station

Provisional plan: Install mobile static converter (existing) Use existing converter 15 MVA Remaining until Drammen converter is operational

Turnkey contract: 2022-2024

• Closure of Skoppum and Larvik converter station (relocation of mobile static converter)

10 Plans in the Oslo area

• New converter station in Hønefoss

Linked to construction of the new Concept design work to commence in 2020 Land suggested at new stabling area in Hønefoss

Provisional plan: Establish new converter station 4 static converters Power requirement 60 MVA

Turnkey contract: 2022-2025

• Closure of existing converter station

11 Plans in the Oslo area

• Upgrading of Jessheim converter station

Necessary increase in performance for increasing Intercity traffic

This measure will also facilitate regeneration

New static converter in existing or new building

Turnkey contract: 2027-2030

12 Plans in the Oslo area

• New converter station at Drammen

Recommended in the long term, before investment needs in Asker

Planning work not commenced Possible location slightly west of Gulskogen/Drammen Requires AT system Oslo-Drammen

Indication: New static converter station Power requirement 60 MVA

Turnkey contract: 2032-2035

• Asker can be closed when Drammen and Hønefoss converters are operational

13 Plans in the Oslo area

• New converter station at

Necessary increase in performance on Dovre Line south Linked to new double track plots south of Hamar (Kleverud – Sørli/Åkersvika)

Concept design work completed. Location is determined

The project is in the detailed planning phase …… (more info in next entry)

• Closure of Tangen converter station (losing track access) • Closure and relocation of mobile converter station at Rudshøgda (Used elsewhere, e.g. on the )

14 Plans for the Sørlandet Line

• Refurbishment/upgrading of Kjelland converter station

Necessary increase in performance on Sørlandet Line

Concept design work has commenced

Provisional plan: New static converters Power requirement 30 MVA

Turnkey contract: 2019-2021

15 Plans for the Sørlandet Line

• Refurbishment/upgrading of Nelaug converter station The concept design work will commence in 2018 Concept development for modernisation of station in or outside existing rock caverns

Implementation: 2020-2022

• Increased performance in Leivoll converter station Planning work to commence in 2024 Preparations at the station and replacement of rotary converters

Implementation: 2026-2027

• Closure of Sira and Krossen converter stations Can be implemented when the two previous measures have been implemented

16 Plans for the Dovre Line

• Upgrading of Dombås converter station Necessary increase in performance south of Dovre Replacement of rotary converters to 2x10 MVA

Implementation: 2023-2025

• Possible provisionally increased performance at converter station Poss. replacement of rotary converters

17 Plans for the Dovre Line

• New converter station at Berkåk

Necessary increase in performance at Dovre Line north / electrification of Røros Line Planning work not commenced. Possible reuse of rotary converters (typically 2x10 MVA) Requires at least a new building and switchgear installation.

Implementation: 2026-2029 or later:

• Closure of Oppdal/Lundamo/Stavne converter station To be assessed when Berkåk is operational Also to be viewed in conjunction with the establishment of Hell converter station (ETM project)

18 Plans for the Dovre Line

• New converter station at Fåvang

Refurbishments and rationalisation on the Dovre Line Planning work not commenced, but requires at least a new building and coupling installation. Possible reuse of rotary converters (typically 2x10 MVA)

Implementation: 2030-2033 or later:

• Closure of Fåberg converter station Can be implemented when Fåvang is operational • Closure of Fron converter station Can be implemented when Fåvang is operational

19 Plans for the Bergen Line

• Capacity increase at Haugastøl and converter stations.

Necessary increase in performance at Bergen Line, Reuse of rotary converters

Implementation: 2026-2028 or later:

20 Plans for the Bergen Line

• New converter station at

To be assessed in connection with capacity increase on double track to Voss Planning work not commenced – needs must be assessed in greater detail

Implementation: 2030-2033 or later:

• Closure of Dale converter station May possibly be implemented when Voss is operational

21 Plans for the Ofoten Line

• New converter station at

Necessary increase in performance and reduction of risk on the Ofoten Line

Concept design work, part 1 is completed Plot at Sildvik is secured Capacity-related survey being carried out now Static converters, estimated power requirement 60 MVA

Implementation: 2020-2023

• Closure of Rombak converter station Can be implemented when the new Narvik converter station is operational

22 Transfer capacity at CL

• Upgrading to AT system or other reinforcement of CL:

- necessary for a number of our measures - necessary to allow use of installed power - necessary to achieve sufficient redundancy • Plans are in place for a number of the sections • Input for the action programme from Energy Supply

23