Public Disclosure Copy The World Bank Implementation Status & Results Report : Gansu Urban Infrastructure Improvement Project (P123133)

China: Gansu Qingyang Urban Infrastructure Improvement Project (P123133)

EAST ASIA AND PACIFIC | China | Transport & Digital Development Global Practice | IBRD/IDA | Investment Project Financing | FY 2012 | Seq No: 12 | ARCHIVED on 25-Jun-2018 | ISR33237 | Public Disclosure Authorized

Implementing Agencies: People's Republic of China, QINGYANG PMO

Key Dates

Key Project Dates

Bank Approval Date:31-May-2012 Effectiveness Date:24-Sep-2012 Planned Mid Term Review Date:26-Jan-2015 Actual Mid-Term Review Date:26-Mar-2015 Original Closing Date:31-Dec-2017 Revised Closing Date:31-Dec-2018 Public Disclosure Authorized Project Development Objectives

Project Development Objective (from Project Appraisal Document) To assist Xifeng to improve selected urban infrastructure services including urban roads and urban environmental services.

Has the Project Development Objective been changed since Board Approval of the Project Objective? No

PHRPDODEL

Components Public Disclosure Authorized Name Component 1(a) Urban Infrastructure Improvement - Urban Bypass:(Cost $96.16 M) Component 1(b) Urban Infrastructure Improvements - Integrated Road Corridor:(Cost $11.00 M) Component 1(c) Urban Infrastructure Improvements - Drainage and Sewage:(Cost $35.20 M) Component 1(d) Urban Infrastructure Improvements - Wastewater Treatment Plant:(Cost $30.11 M) Component 2 Institutional Strengthening and Capacity Building:(Cost $3.07 M)

Overall Ratings

Name Previous Rating Current Rating

Progress towards achievement of PDO  Moderately Satisfactory  Moderately Satisfactory Public Disclosure Authorized Overall Implementation Progress (IP)  Moderately Satisfactory  Moderately Satisfactory Overall Risk Rating  Substantial  Substantial

6/25/2018 Page 1 of 9 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report China: Gansu Qingyang Urban Infrastructure Improvement Project (P123133)

Implementation Status and Key Decisions

Overall implementation has made very good progress since the last mission. Cumulative disbursement of the Bank loan as of now stands at USD66 million, which corresponds to a 22% increase over last mission. Of the 20 contracts in the project, 15 have already been procured (of which seven are completed) and five contracts are pending. The outstanding issues of land availability and resettlement which had impacted the implementation progress have been largely solved. Close attention will need to be paid to the timely completion of the wastewater treatment plant.

Risks

Systematic Operations Risk-rating Tool

Risk Category Rating at Approval Previous Rating Current Rating

Political and Governance  --  Low  Low Macroeconomic  --  Moderate  Moderate Sector Strategies and Policies  --  Substantial  Substantial Technical Design of Project or Program  --  Substantial  Substantial Institutional Capacity for Implementation and -- Substantial Substantial Sustainability    Fiduciary  --  Substantial  Substantial Environment and Social  --  Moderate  Moderate Stakeholders  --  Low  Low Other  --  --  -- Overall  --  Substantial  Substantial

Results

Project Development Objective Indicators

PHINDPDOTBL

 Journey time saved for through traffic (freight) (Minutes, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 28.40 18.50 18.20 18.20

Date 30-Apr-2012 17-Oct-2017 31-May-2018 31-Dec-2018

PHINDPDOTBL

 Share of through traffic (freight) on two corridors increased (East) (# of trucks over 24 hours and %) (Text, Custom)

6/25/2018 Page 2 of 9 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report China: Gansu Qingyang Urban Infrastructure Improvement Project (P123133)

Baseline Actual (Previous) Actual (Current) End Target

Value 9.1 (0%) 18.70 20 (120%) 22 (142%)

Date 30-Apr-2012 17-Oct-2017 31-May-2018 31-Dec-2018

PHINDPDOTBL

 Share of through traffic (freight) on 2 corridors increased (West) (# of trucks over 24 hours and %) (Text, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 66.2 (0%) 75.00 70 (6%) 72 (9%)

Date 30-Apr-2012 17-Oct-2017 31-May-2018 31-Dec-2018

PHINDPDOTBL

 Service speed of buses during rush hour on Nan Bei Street Corridor (km/hr) (and % change) (Kilometers, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 10.30 15.80 15.50 15.50

Date 30-Apr-2012 17-Oct-2017 31-May-2018 31-Dec-2018

PHINDPDOTBL

 Built up area serviced by storm water/wastewater networks increased (Percentage, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 50.60 67.00 73.50 92.00

Date 30-Apr-2012 17-Oct-2017 31-May-2018 31-Dec-2018

PHINDPDOTBL

 Wastewater pollution reduction (COD) (tons/year) (Metric ton, Custom)

6/25/2018 Page 3 of 9 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report China: Gansu Qingyang Urban Infrastructure Improvement Project (P123133)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 0.00 0.00 2,569.00

Date 30-Apr-2012 17-Oct-2017 31-May-2018 31-Dec-2018

PHINDPDOTBL

 Wastewater pollution reduction (SS) (tons/year) (Metric ton, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 0.00 0.00 2,219.00

Date 30-Apr-2012 17-Oct-2017 31-May-2018 31-Dec-2018

PHINDPDOTBL

 Volume(mass) of BOD pollution load removed by treatment plant under the project (Tones/year, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 0.00 0.00 1,168.00

Date 30-Apr-2012 17-Oct-2017 31-May-2018 31-Dec-2018

Overall Comments

Intermediate Results Indicators

PHINDIRITBL

 Passenger ridership of buses during rush hour on Nan Bei Street corridor increased (and % change) (Number, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 5,845.00 11,500.00 11,500.00 12,000.00

Date 30-Apr-2012 17-Oct-2017 31-May-2018 31-Dec-2018

6/25/2018 Page 4 of 9 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report China: Gansu Qingyang Urban Infrastructure Improvement Project (P123133)

PHINDIRITBL

 Bus stops reconstructed/upgraded (Number, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 17.00 17.00 33.00

Date 30-Apr-2012 17-Oct-2017 31-May-2018 31-Dec-2018

PHINDIRITBL

 Unsignalized zebras converted to signalized mid-block crossings on the 3 corridors (# of crossings) (Number, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 15.00 48.00 48.00 103.00

Date 30-Apr-2012 17-Oct-2017 31-May-2018 31-Dec-2018

PHINDIRITBL

 Intersections with traffic channelized (Number, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 12.00 23.00 23.00 27.00

Date 30-Apr-2012 17-Oct-2017 31-May-2018 31-Dec-2018

PHINDIRITBL

 % of users expressing positive opinion on services (from user satisfaction surveys) (Percentage, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 27.00 62.00 62.00 65.00

Date 30-Apr-2012 17-Oct-2017 31-May-2018 31-Dec-2018

6/25/2018 Page 5 of 9 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report China: Gansu Qingyang Urban Infrastructure Improvement Project (P123133)

PHINDIRITBL

 New drainage/sewage pipe construction completed (km, % cumulative) (Percentage, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 27.50 27.50 100.00

Date 30-Apr-2012 17-Oct-2017 31-May-2018 31-Dec-2018

PHINDIRITBL

 Drainage/sewage pipe reconstruction completed (km, cumulative %) (Percentage, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 20.40 20.40 100.00

Date 30-Apr-2012 17-Oct-2017 31-May-2018 31-Dec-2018

PHINDIRITBL

 Wastewater treatment plant investment completed (US$, cumulative %) (Percentage, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 0.00 42.00 100.00

Date 30-Apr-2012 17-Oct-2017 31-May-2018 31-Dec-2018

PHINDIRITBL

 Associated construction of pipes completed (km, cumulative %) (Percentage, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 0.00 3.00 100.00

Date 30-Apr-2012 17-Oct-2017 31-May-2018 31-Dec-2018

6/25/2018 Page 6 of 9 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report China: Gansu Qingyang Urban Infrastructure Improvement Project (P123133)

PHINDIRITBL

 Studies completed (cumulative number) (Number, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 3.00 3.00 5.00

Date 30-Apr-2012 17-Oct-2017 31-May-2018 31-Dec-2018

PHINDIRITBL

 Staff trained (cumulative number) (Number, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 125.00 125.00 110.00

Date 30-Apr-2012 17-Oct-2017 31-May-2018 31-Dec-2018

PHINDIRITBL

 Average annual number of fatalities and severely injusred in project corridors over a three-year period (relative to base year) (Number, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 14.00 7.00 7.00 9.00

Date 30-Apr-2012 11-Nov-2016 31-May-2018 31-Dec-2018

PHINDIRITBL

 Roads rehabilitated, Non-rural (Kilometers, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 8.71 8.71 16.06

Date 30-Apr-2012 11-Nov-2016 31-May-2018 31-Dec-2018

6/25/2018 Page 7 of 9 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report China: Gansu Qingyang Urban Infrastructure Improvement Project (P123133)

PHINDIRITBL

 Roads constructed, non-rural (Kilometers, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 0.54 2.53 5.76

Date 30-Apr-2012 11-Nov-2016 31-May-2018 31-Dec-2018

Overall Comments

Data on Financial Performance

Disbursements (by loan)

Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed Disbursed

P123133 IBRD-81700 Effective USD 100.00 100.00 0.00 65.62 34.38 66%

Key Dates (by loan)

Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date

P123133 IBRD-81700 Effective 31-May-2012 12-Jul-2012 24-Sep-2012 31-Dec-2017 31-Dec-2018

Cumulative Disbursements

6/25/2018 Page 8 of 9 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report China: Gansu Qingyang Urban Infrastructure Improvement Project (P123133)

Restructuring History

Level 2 Approved on 23-Aug-2016

Related Project(s)

There are no related projects.