Public Disclosure Copy The World Bank Implementation Status & Results Report : Urban Infrastructure Improvement Project (P123133)

China: Gansu Qingyang Urban Infrastructure Improvement Project (P123133)

EAST ASIA AND PACIFIC | China | Transport & ICT Global Practice | IBRD/IDA | Specific Investment Loan | FY 2012 | Seq No: 7 | ARCHIVED on 01-Dec-2015 | ISR21419 |

Implementing Agencies: QINGYANG PMO

Key Dates

Key Project Dates

Bank Approval Date:31-May-2012 Effectiveness Date:24-Sep-2012 Planned Mid Term Review Date:26-Jan-2015 Actual Mid-Term Review Date:26-Mar-2015 Original Closing Date:31-Dec-2017 Revised Closing Date:31-Dec-2017

Project Development Objectives

Project Development Objective (from Project Appraisal Document) To assist Xifeng to improve selected urban infrastructure services including urban roads and urban environmental services.

Has the Project Development Objective been changed since Board Approval of the Project Objective? No

PHRPDODEL

Components

Name Component 1(a) Urban Infrastructure Improvement - Urban Bypass:(Cost $82.26 M) Component 1(b) Urban Infrastructure Improvements - Integrated Road Corridor:(Cost $11.53 M) Component 1(c) Urban Infrastructure Improvements - Drainage and Sewage:(Cost $37.28 M) Component 1(d) Urban Infrastructure Improvements - Wastewater Treatment Plant:(Cost $32.31 M) Component 2 Institutional Strengthening and Capacity Building:(Cost $3.30 M)

Overall Ratings

Name Previous Rating Current Rating

Progress towards achievement of PDO  Moderately Unsatisfactory  Moderately Unsatisfactory Overall Implementation Progress (IP)  Unsatisfactory  Unsatisfactory Overall Risk Rating  Substantial  Substantial

12/1/2015 Page 1 of 10 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report China: Gansu Qingyang Urban Infrastructure Improvement Project (P123133)

Implementation Status and Key Decisions

Since the loan became effective in September 2012 progress in all components of the project has been very slow. Of the total 21 contracts, only one civil works contract has been completed; one goods contract completed; three civil works contracts are under construction; and three service contracts ongoing. It is expected that several contracts will be initiated soon which will support a pick up in project implementation progress. It has been decided to restructure the project to take account of the delays, slow disbursement and reducing some of the project risks. It is still expected that the project will achieve its PDO by the end of the extended closing date.

12/1/2015 Page 2 of 10 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report China: Gansu Qingyang Urban Infrastructure Improvement Project (P123133)

Risks

Systematic Operations Risk-rating Tool

Risk Category Rating at Approval Previous Rating Current Rating

Political and Governance  --  Substantial  Low Macroeconomic  --  Low  Moderate Sector Strategies and Policies  --  Substantial  Substantial Technical Design of Project or Program  --  Substantial  Substantial Institutional Capacity for Implementation and -- Substantial Substantial Sustainability    Fiduciary  --  Substantial  Substantial Environment and Social  --  Substantial  Substantial Stakeholders  --  Low  Low Other  --  --  -- Overall  --  Substantial  Substantial

Results

Project Development Objective Indicators

PHINDPDOTBL

 Journey time saved for through traffic (freight) (Minutes, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 28.40 28.40 19.50 18.20

12/1/2015 Page 3 of 10 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report China: Gansu Qingyang Urban Infrastructure Improvement Project (P123133)

Date 30-Apr-2012 15-Jun-2015 26-Nov-2015 31-Dec-2017

PHINDPDOTBL

 Share of through traffic (freight) on two corridors increased (East) (# of trucks over 24 hours and %) (Text, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 9.1 (0%) 9.1 (0%) 11.8 (30%) 22 (142%)

Date 30-Apr-2012 15-Jun-2015 26-Nov-2015 31-Dec-2017

PHINDPDOTBL

 Share of through traffic (freight) on 2 corridors increased (West) (# of trucks over 24 hours and %) (Text, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 66.2 (0%) 66.2 (0%) 71.5 (8%) 72 (9%)

Date 30-Apr-2012 15-Jun-2015 26-Nov-2015 31-Dec-2017

PHINDPDOTBL

 Service speed of buses during rush hour on Nan Bei Street Corridor (km/hr) (and % change) (Kilometers, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 10.30 10.30 13.60 15.50

Date 30-Apr-2012 15-Jun-2015 26-Nov-2015 31-Dec-2017

PHINDPDOTBL

 Built up area serviced by storm water/wastewater networks increased (Percentage, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 50.60 50.60 59.20 92.00

Date 30-Apr-2012 15-Jun-2015 26-Nov-2015 31-Dec-2017

12/1/2015 Page 4 of 10 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report China: Gansu Qingyang Urban Infrastructure Improvement Project (P123133)

PHINDPDOTBL

 Wastewater pollution reduction (BOD) (tons/year) (Metric ton, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 0.00 0.00 1168.00

Date 30-Apr-2012 15-Jun-2015 26-Nov-2015 31-Dec-2017

PHINDPDOTBL

 Wastewater pollution reduction (COD) (tons/year) (Metric ton, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 0.00 0.00 2569.00

Date 30-Apr-2012 15-Jun-2015 26-Nov-2015 31-Dec-2017

PHINDPDOTBL

 Wastewater pollution reduction (SS) (tons/year) (Metric ton, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 0.00 0.00 2219.00

Date 30-Apr-2012 15-Jun-2015 26-Nov-2015 31-Dec-2017

Overall Comments

Intermediate Results Indicators

PHINDIRITBL

 Road construction completed (by km) (Percentage, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 2.40 7.40 100.00

Date 30-Apr-2012 15-Jun-2015 26-Nov-2015 31-Dec-2015

12/1/2015 Page 5 of 10 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report China: Gansu Qingyang Urban Infrastructure Improvement Project (P123133)

PHINDIRITBL

 Passenger ridership of buses during rush hour on Nan Bei Street corridor increased (and % change) (Number, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 5845.00 5845.00 9700.00 12000.00

Date 30-Apr-2012 15-Jun-2015 26-Nov-2015 31-Dec-2017

PHINDIRITBL

 Bus stops reconstructed/upgraded (Number, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 0.00 17.00 33.00

Date 30-Apr-2012 15-Jun-2015 26-Nov-2015 31-Dec-2016

PHINDIRITBL

 Unsignalized zebras converted to signalized mid-block crossings on the 3 corridors (# of crossings) (Number, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 15.00 15.00 48.00 103.00

Date 30-Apr-2012 15-Jun-2015 26-Nov-2015 31-Dec-2016

PHINDIRITBL

 Intersections with traffic channelized (Number, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 12.00 12.00 19.00 27.00

Date 30-Apr-2012 15-Jun-2015 26-Nov-2015 31-Dec-2016

12/1/2015 Page 6 of 10 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report China: Gansu Qingyang Urban Infrastructure Improvement Project (P123133)

PHINDIRITBL

 % of users expressing positive opinion on services (from user satisfaction surveys) (Percentage, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 27.00 27.00 53.00 65.00

Date 30-Apr-2012 15-Jun-2015 26-Nov-2015 31-Dec-2017

PHINDIRITBL

 New drainage/sewage pipe construction completed (km, % cumulative) (Percentage, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 0.00 41.00 100.00

Date 30-Apr-2012 15-Jun-2015 26-Nov-2015 31-Dec-2017

PHINDIRITBL

 Drainage/sewage pipe reconstruction completed (km, cumulative %) (Percentage, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 0.00 0.00 100.00

Date 30-Apr-2012 15-Jun-2015 26-Nov-2015 31-Dec-2017

PHINDIRITBL

 Wastewater treatment plant investment completed (US$, cumulative %) (Percentage, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 0.00 0.00 100.00

Date 30-Apr-2012 15-Jun-2015 26-Nov-2015 31-Dec-2017

12/1/2015 Page 7 of 10 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report China: Gansu Qingyang Urban Infrastructure Improvement Project (P123133)

PHINDIRITBL

 Associated construction of pipes completed (km, cumulative %) (Percentage, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 0.00 0.00 100.00

Date 30-Apr-2012 15-Jun-2015 26-Nov-2015 31-Dec-2017

PHINDIRITBL

 Studies completed (cumulative number) (Number, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 0.00 1.00 5.00

Date 30-Apr-2012 15-Jun-2015 26-Nov-2015 31-Dec-2017

PHINDIRITBL

 Staff trained (cumulative number) (Number, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 45.00 81.00 110.00

Date 30-Apr-2012 15-Jun-2015 26-Nov-2015 31-Dec-2017

PHINDIRITBL

 Average annual number of fatalities and severely injusred in project corridors over a three-year period (relative to base year) (Number, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 14.00 -- 6.00 9.00

Date 30-Apr-2012 -- 26-Nov-2015 31-Dec-2017

Overall Comments Values enteres are the revised values reported by the PMO on November 26, 2015. M&E reporting is still not robust and the Team will continue the dialogue with the PMO aiming at securing more reliable values.

12/1/2015 Page 8 of 10 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report China: Gansu Qingyang Urban Infrastructure Improvement Project (P123133)

Data on Financial Performance

Disbursements (by loan)

Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed Disbursed

P123133 IBRD-81700 Effective USD 100.00 100.00 0.00 11.53 88.47 12%

Key Dates (by loan)

Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date

P123133 IBRD-81700 Effective 31-May-2012 12-Jul-2012 24-Sep-2012 31-Dec-2017 31-Dec-2017

Cumulative Disbursements

Restructuring History

There has been no restructuring to date.

Related Project(s)

12/1/2015 Page 9 of 10 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report China: Gansu Qingyang Urban Infrastructure Improvement Project (P123133)

There are no related projects.

12/1/2015 Page 10 of 10 Public Disclosure Copy