<<

Environmental Monitoring Report

Project Number: 43025-013 July 2018

PRC: Urban Infrastructure Development Project

Prepared by Tianshui Project Management Office for Tianshui Municipal Government, Tianshui Environment Protection Bureau, and the .

This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area. # 10 Semi-annual Report July 2018 (through January to June 2018)

People’s Republic of : Gansu Tianshui Urban Infrastructure Development Project

Prepared by Tianshui Project Management Office(Tianshui Urban Construction and Investment Co.) for the Tianshui Municipal Government, Tianshui Environment Protection Bureau, and the Asian Development Bank.

This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

ABBREVIATIONS

ADB = Asian Development Bank BOD5 = Biochemical Oxygen Demand In Five Days CEIA = Consolidated Environmental Impact Assessment CHP = Combined Heat And Power CO2 = Carbon Dioxide CODcr = Chemical Oxygen Demand CSC = Construction Supervision Company EA = Executing Agency EIA = Environmental Impact Assessment EMP = Environmental Management Plan ERP = Environmentally Responsible Procurement EMU = Environmental Management Unit GEPB = Gansu Environment Protection Bureau GRM = Grievance Redress Mechanism HES = Heat Exchange Stations IA = Implementing Agency LIEC = Loan Implementation Environmental Specialist MEE = Ministry of Ecology and Environment NH3-N = Ammonia Nitrogen NO2 = Nitrogen Dioxide PM10 = Particulate Matter Smaller Than 10 Micrometers PPCU = Project Public Complaints Unit PPMS = Project Performance Management System PPTA = Project Preparatory Technical Assistance PRC = People’s Republic Of China SEPP = Soil Erosion Protection Plan SO2 = Sulfur Dioxide SPS = Safeguard Policy Statement TEMC = Tianshui Environmental Monitoring Center TEPB = Tianshui Environment Protection Bureau TMG = Tianshui Municipal Government TN = Total Nitrogen TP = Total Phosphorus TPMO = Tianshui Project Management Office TSP = Total Suspended Particle TUCIC = Tianshui Urban Construction And Investment Group Co. Ltd. TWRB = Tianshui Water Resource Bureau

II

ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

Basic Information

Borrower People’s Republic of China Classification Target classification: general intervention (more indirectly addressing poverty reduction)

Sector (subsectors): multisector – municipal infrastructure, transport and communications, energy (other municipal services: energy utility services and urban transport)

Themes (subthemes): economic growth, environmental sustainability, capacity development (promoting economic efficiency, institution and organizational development, and urban environmental improvement)

Climate changes: mitigation and adaptation

Location impact: urban (high)

A. Qinzhou heating network (being implemented). B. Chengji road and flood control facilities (completed and being Description of commissioned). Project Outputs C. Urban roads and bridges (completed and being commissioned). D. Capacity development and institutions strengthening (being implemented). Environment A Assessment Involuntary A Resettlement Indigenous People C Assessment Period of Estimated until 30 September 2018 Implementation Estimated Project 31 December 2018 Completion Date Executing Agency Tianshui Municipal Government

III

ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

Component A: heating network (at construction stage); including seven (7) civil works contract packages: CH1 to CH7 (site construction status see photos in below page); and associated facility (Qinzhou district heating supply plant)

IV

ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

CH1- contract just signed, CH2- 98% completed, 200m CH3- 95% completed, 180m CH4- 92% completed, to fully HES civil works under branch pipe remained, and to trunk pipe and some branch complete by August 2018 construction, and to fully fully complete by August 2018 pipes remained,, to fully complete by October 2018 complete by August 2018

CH5- 70% completed, 3 km CH6- started construction in CH7- under bidding process, Associated facility-Qinzhou remained, to fully complete by May, 800m pipes or 10% to start construction in August district heating source plant- August 2018 works completed, and to fully 2018, and to fully complete by main structure completed, complete by August 2018 October 2018 commissioned in 2017/2018 heating season, and other ancillary facilities under construction

V

ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

Component B-Chengji road and flood control facilities and Component C- Tianshui urban transport improvement (both at commission stage), site operation status see photos in below page

VI

ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

C01(K0+000~K3+250) C02 Sunjiaping bridge C03(K3+650~K7+000)

C04(K7+000~K10+360) C05 Xiakou Bridge C06 New Road Network

C07 Shuangqiao bridge C08 Shetang bridge C09-Chiyu Road

VII

ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

Report Structure

Chapter 3-Loan covenants &review mission requirements

Compliance review Chapter 4-Mitigation measures Chapter 1-Project introduction Chapter 5-Field survey Chapter 8-Corrective and monitoring, results action plans Chapter 2-Proponent assessment environmental management responsibilities Chapter 9-Conclusions Chapter 6-Institutional recommendations development

Chapter 7-Public consultation and GRM

EXECUTIVE SUMMARY

This Semi-Annual Environmental Monitoring Report (EMR) describes the environmental monitoring and mitigation measures undertaken with regard to the domestic Environmental Impact Assessment (EIA) reports, the Consolidated Environmental Impact Assessment (CEIA) and the revised EMP provisions during the implementation period from January to June 2018 of the Gansu Tianshui Urban Infrastructure Development Project (“the Project”).

In this report we briefly provide: (i) documentation review and compliance with environmental regulations; (ii) environmental institutional structure and responsibility; (iii) mitigation measures undertaken to minimize adverse environmental impacts arising from the construction of the Project facilities;(iv)environmental monitoring and status of ambient environmental quality; and (v) conclusions and recommendations.

As of 30 June 2018, the Project is assessed to be some 90% complete overall. In this reporting period, the mitigation measures and monitoring program were generally carried out satisfactorily. Attention has been paid on water, air quality and noise control, soil erosion protection, etc. Through the implementation of these measures, the destruction to the environment has been lowered to a minimum level possible during construction. However, to some certain extent there were still unavoidable impacts on the environment. Some recommendations are put forward to make improvement on environmental protection in the next reporting period. Particularly, more efforts are required on traffic control and demolition of small boilers during heating network component implementation, flood prevention facilities maintenance (for details please see Section 5.2.1) as well as road operation safety and vegetation restoration upon completion of road &bridge civil works contracts under components B and C.

ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

Table of Contents

ABBREVIATIONS II BASIC INFORMATION III TABLE OF CONTENTS IX LIST OF TABLES X 1. INTRODUCTION 1 1.1 Report Purpose and Rationale 1 1.2 Project Background, Objective and Components 1 1.3 Project Implementation Progress 3 2. PROPONENT’S ENVIRONMENTAL MANAGEMENT RESPONSIBILITIES 6 2.1 Institutional Responsibilities for Environmental Management 6 2.2 Environmentally Responsible Procurement (ERP) 12 3. COMPLIANCE WITH ENVIRONMENT RELATED PROJECT COVENANTS 13 4. ENVIRONMENTAL MITIGATIONS AND COMPENSATION MEASURES IMPLEMENTED IN THE REPORTING PERIOD 29 5. SUMMARY OF FIELD SURVEY AND ASSESSMENT 34 5.1 Monitoring plan and responsibilities 34 5.2 Monitoring Results 44 6. INSTITUTIONAL STRENGTHENING AND TRAINING 58 7. PUBLIC CONSULTATION AND GRIEVANCE REDRESS STATUS 62 8. KEY ENVIRONMENTAL ISSUES AND NEXT-STEP ACTION PLAN 69 8.1 Key Issues Identified in the last (nineth) EMR 69 8.2 Key Issues Identified in this (tenth) EMR 69 8.3 Corrective actions taken to address key Issues Identified in the last (nineth) EMR during this reporting period 69 8.4 Action Plan of Environmental Monitoring &Evaluation (M&E) In the Next Reporting Period 69 9. CONCLUSION 72 9.1 Overall Progress of Implementation of Environmental Management Measures 72 9.2 Problems Identified and Actions Recommended 72 APPENDICES ERROR! BOOKMARK NOT DEFINED. APPENDIX 1 APPLICABLE ENVIRONMNETAL STANDARDS 74 APPENDIX 2 TABLE A2- 1 SUMMARY OF POTENTIAL ENVIRONMENTAL IMPACTS AND THE MITIGATION MEASURES IMPLEMENTED 76 APPENDIX 3 TABLE A3- 1 SUBMISSION STATUS OF ENVIRONMENTAL PROTECTION OPERATION AND SUPERVISION PLAN/MANUALSAND INTERNAL ENVIRONMENTAL MONITORING REPORTS (FROM APRIL 2016 TO JUNE 2018) 90 APPENDIX 4 CERTIFICATE OF ONSITE SAMPLING AND LABORARTORY TESTING AGENCY ( YITONG MONITORING COMPANY) AND SCANNED COPY OF TESTING DATA 95

ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

List of Tables Table 1- 1 Project Implementation Progress (as of 30 June 2018) ...... 3

Table 2-1 Updated Environmental Responsibilities Matrix and Fulfillment Status ...... 8

Table 3- 1Compliance with Environment Related Project Covenants ...... 15 Table 3- 2 Implementation Status Of Environmental Requirements In The MOU On November 5th, 2013 ...... 21 Table 3- 3 Implementation Status of Environmental Requirements In The MOU On October 24th, 2014 ...... 24 Table 3- 4 Implementation Status of Environmental Requirements In The MOU On May 6th, 2015 ...... 25 Table 3-5 Implementation Status Of Environmental Requirements In The MOU On April 14th, 2016 ...... 26 Table 3-6 Implementation Status of Environmental Requirements In The MOU On August 24th, 2017 ...... 27

Table 4- 1 Actual vs Estimated Major Environmental Mitigation Costs – Component A (as of June 2018) ...... 31

Table 5- 1 Air Quality Data during 2015/2016, 2016/2017 and 2017/2018 Heating Seasons in Qinzhou District ...... 36 Table 5- 2 Environmental Quality Protection Objectives ...... 38 Table 5- 3 Environmental Monitoring Program ...... 40 Table 5- 4 Environmental Monitoring Sampling Arrangements ...... 43 Table 5- 5 Standard Monitoring Methods of Ambient Air, Noise and Water ...... 44 Table 5- 6 Summary of air quality monitoring data ...... 52 Table 5- 7 Summary of acoustic quality monitoring data ...... 52 Table 5- 8 The Summary of Balance for earth works in the Contracts CH1/Ch4/CH6 under component A (as of June 2018) ... 54 Table 5-9 Monitoring Results of Soil Erosion through January 2016 to June 2017 ...... 55

Table 6- 1 Implementation status of Institutional Strengthening and Training Program ...... 58

Table 7-1 Information disclosure on the Qinzhou district heating source plant and heating pipeline network (component A), rendered by THC ...... 62 Table 7-2 Questionnaire Survey during Implementation Stage ...... 64 Table 7-4 Implementation Status and Future Public Consultation Plan ...... 67

Table 8- 1 Action Plan for Environmental M&E InThe Next Reporting Period ...... 70

Table 9-1 Suggestions And Recommendations ...... …………………………………………………..72

Table A1-1 Ambient Air Quality Standard (Class II) ...... 75 Table A1-2 Acoustic Environment Quality Standard ...... 75

Table A2- 1 Summary of Potential Environmental Impacts and the Mitigation Measures Implemented ...... 76

Table A3- 1 Submission Status Of Environmental Protection Operation And Supervision Plan/ManualsAnd Internal Environmental Monitoring Reports ...... 90

ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

1. INTRODUCTION

1.1 Report Purpose and Rationale

1. As defined in the domestic EIAs and consolidated environmental impact assessment (CEIA, January 20111) for Gansu Tianshui Urban Infrastructure Development Project (the Project) under ADB Loan, semi-annual environmental monitoring reports (EMR) have to be prepared by the borrower in order to evaluate and assess overall project activities to ensure the effective implementation of the environmental management plan (EMP).

2. The purpose of the tenth EMR is to document the environmental management activities and compliance with the revised EMP of this Project by 30 June 2018. This report is prepared in accordance with the environmental monitoring program as part of the environmental management plan (EMP) revised in December 2014 and disclosed in May 2015 on ADB’s website. As the tenth EMR, it will not only cover the construction (for component A-heating network) and commission phases (for components B and C-roads and bridges, flood control), but also demonstrate compliance with the EMP for the design, bidding, and construction preparation stages. In line with targets aimed at reducing the negative environmental impacts of the Project and in accordance with all the relevant specifications and standards of the PRC, as well as the policies of the Asian Development Bank (ADB), this report will emphasize: (i) progress made in implementing the EMP, (iii) environmental compliance, (iv) institutional strengthening and training, (v) public consultation, and (vi) problems that have occurred and corrective actions taken.

3. This report is prepared by the TPMO and the two IAs (THC and TUCIC) with the assistance from China General Consultant & Investment Co. Ltd. (CGCI), as the loan implementation consultant. The monitoring plan was updated on the basis of discussion with TEPB and approved by ADB.

1.2 Project Background, Objective and Components

4. The Gansu Tianshui Urban Infrastructure Development Project was approved with the amount of $100 million on 29 June 2011, signed on 25 October 2011 and became effective on 14 May 2012. The Project will assist Tianshui to promote balanced and environmentally sustainable urbanization, and to improve living conditions in Tianshui. The impact of the Project is better living conditions in Tianshui municipality. The outcome of the Project is improved heating, transport, and flood control services in Tianshui municipality. The Project has four outputs: (i) Qinzhou district heating network (component A), (ii) Chengji road and flood control facilities (component B), (iii) Tianshui urban transport improvements (component C), and, (iv) capacity development and institutional strengthening (component D). The Project was delegated to PRCM for administration on 30 June 2015. The original physical completion of the Project and closing date were on 30 June 2016 and 31 December 2016, respectively. Due to the change of heating source plant2, project implementation of Qinzhou district heating network component is delayed for about two years and the current loan closing date is 31 December 2018.

1 Available from https://www.adb.org/projects/documents/gansu-tianshui-urban-infrastructure-development-project- environmental-impact-asse. 2 Due to the minor scope change, an environmental due diligence was undertaken in 2013~2014 in accordance with ADB’s SPS (2009). An updated domestic EIA was approved in May 2014 by Gansu Provincial Environmental Protection Department (GEPD). An Addendum to the Consolidated Environmental Impact Assessment including a revised EMP was approved and disclosed in May 2015 by ADB (https://www.adb.org/projects/documents/prc-gansu- tianshui-urban-infrastructure-devt-project-may-2015-addendum-eia) .

Page | 1 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

5. Tianshui municipal government (TMG) is the executing agency, and Tianshui Urban Construction ADB and Investment Group (TUCIC) and Tianshui Heating Company (THC) are the implementing agencies. As of 30 June 2018, eight loan administration missions were fielded to Tianshui, including the loan midterm review conducted on 28 October – 5 November 2013.

6. Project components. The Project includes four components/outputs: (i) Qinzhou district heating network (component A3)—upgrading of Qinzhou district's central heating network by decommissioning 194 outdated -fired boilers, building a 33.7 km primary heat transmission network, constructing 76 heat- exchange stations, and increasing district-heating coverage by 6 million m2; (ii) Chengji road and flood control facilities (component B)—constructing the 12km Chengji road and flood control embankment along the Xi river’s north bank, including two large bridges, with related public transportation facilities4; (iii) Tianshui urban transport improvements (component C)—improving urban roads and related services especially for public transport and non-motorized transport (NMT) by constructing four new roads with a total length of 4.9 km, rehabilitating one road with a total length of 2.0 km, constructing three bridges, and developing related services, including drainage pipelines and sewers, energy-saving lighting, public green areas, and road-safety features; and (iv) Capacity development and institutional strengthening (component D)—providing support in two areas (a) to TPMO and implementing agencies to ensure efficient and effective project implementation in compliance with ADB requirements; and (b) an urban transport capacity development program including holistic urban road design and road safety audit, people-centric urban transport planning, road network management and maintenance, and related training.

7. A minor change in scope and implementation arrangement was approved on 9 September 2015 to accommodate: (i) change of associated facility for component A: Qinzhou district heating network: due to 2 years of delay in the construction of the original combined heat and power (CHP) plant source as an associated facility under the Project, in 2013, TMG decided to fully fund and build its own heat plant to supply heating to Qinzhou district without waiting for the CHP; (ii) partial cancellation of roads in Maiji road network (package C06) under component C: to avoid unnecessary delay of project completion due to difficulty in timely resettlement, TMG proposed to cancel some parts of roads under a subcomponent package C06: Maiji road network, and it was confirmed that the urban road network of the Maiji new district remains fully functional without the cancelled portions of roads; (iii) change of procurement packaging for component D: Capacity development and institutional strengthening: the TMG proposed to streamline the consulting packages from five to one since startup consultants (packages CS2 and CS3) were found not relevant by the time of the loan inception mission as the main loan implementation consultant firm under package CS1 was already mobilized; the tasks under packages CS4 and CS1 were found overlapping; and the contents of package CS5 were reviewed with TMG and deemed not relevant anymore for the Project; and (iv) change of funding source: TMG informed ADB in August 2013 that it will no longer avail of the China Development Bank domestic loan for the Project and the required financing would be covered by TMG.

3 There were changes of the associated facilities, namely the CHP and associated tunnel &pipelines during mid-term review in October of 2013. 4 Some minor changes were incurred and environmental due diligence was undertaken in 2014.The main output has not been changed.

Page | 2 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

1.3 Project Implementation Progress

8. As of 30 June 2018, cumulative contract awards and disbursement are $88.4million (88.4% of total loan amount) and $85.1 million (85.1 of total loan amount). The construction of Chengji road and flood control facilities (Output 2), and Tianshui urban transport improvements (Output 3) have been completed by 30 June 2016. Due to the change of heating source plant, project implementation of Qinzhou district heating network (Output 1) is ongoing and will be completed by 31 October 2018. Capacity development and institutional strengthening are ongoing and will be completed by the end of 2018. The overall project implementation is on track. The below Table 1-1 shows the latest project implementation progress. Table 1- 1 Project Implementation Progress (as of 30 June 2018) Current Planned Activities in The Component Implementation Description Status Future The component’s scope includes: constructing a 39.307 km primary network; constructing 76 heat exchange stations and a regulating center; the estimated total investment (including land acquisition and resettlement) is approximately CNY494 million. The amount of ADB loan for the construction of pipeline network is USD29.3 million (equivalent to CNY181.0 million), accounting for 36.2% of the total investment; the rest capital amounts to CNY318.6 million, which is domestic funded, accounting for 63.8%. Detailed progress is provided below.

CH1 - Construction of control center and 46 heat exchange stations.The contract is under bidding stage and will be signed in March 2018. 46 heat exchange stations and a control center will be built before Oct 2018.

CH2 - Primary heat pipeline laying in Chiyu Road to Hongan Road. The contract was awarded for Gansu No.2 Installation Engineering Co., Ltd. in May Partially 2016. The total length of the heating pipeline is 15.4 km. As of 30 June 2018, bidding the heating pipeline had been completed with 80%. documents A- Qinzhou 5 underway. district heating CH3 - Primary heat pipeline laying in Chengji Road, Huangcheng Road and

network Yinbin. The contract was awarded to Gansu No.1 Installation Engineering Co., The others Ltd. on 17 May 2017. The total length of the heating pipeline is 7.78 km. As of being 30 June 2018, 7.18 km pipeline laying has been completed. implemented. CH4 - Primary heat pipeline laying in Xihuang West Road. The contract was awarded in August 2017. The total length of the heating pipeline is 9.36 km. As of 30 June 2018, 8.07 km pipeline laying has been completed.

CH5 - Primary heat pipeline laying in Chengji Road, Huangcheng Road and Yinbin. The contract was awarded to the No.7 Construction Group Share Limited on 09 December 2016. The total length of the heating pipeline is 11.53 km. As of 30 June 2018, 8.16 km pipeline laying has been completed.

CH6 - Primary heat pipeline laying in Minshan Road and Xihuang Road. The contract was awarded on 14 May 2018. The total length of the heating pipeline is 8.41 km. As of 30 June 2018, 0.94 km pipeline laying has been completed.

CH7 - Construction and Installation of the dispatch center and 30 heat

5 Status on associated facility-the Heat Source Plant: The land use right of the Heat Source Plant was obtained. Now the fund for land acquisition and resettlement has been allocated to the Qinzhou District Land Acquisition Office, the land acquisition and resettlement work is being carried out. The design of the heat source plant is in bidding process, and the preliminary design is expected to be approved soon by Gansu Provincial DRC. The civil works contractor has entered into the site and the boilers and related equipment have been manufactured.

Page | 3 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

Current Planned Activities in The Component Implementation Description Status Future exchange stations. The contract is under bidding stage and will be awarded in Q2 2018. The control center and pipelines will be constructed and installed before the end of Sept. 2018.

E1 - Procurement and installation of automatic control electrical equipment for 46 heat exchange stations (HESs) and the relay pumping station. The contract is expected to be awarded by August 2018, and the automatic control and electrical equipment for the 46 HESs will be installed by October 2018.

E2 - Procurement and installation of automatic control electrical equipment for 30 HESs and the relay pumping station. The bidding documents will be submitted for ADB review by July 2018 and be awarded in August 2018. The equipment is expected to be supplied by Oct 2018.

Associated Heat Source Plant. The Qinzhou district heating source plant has been completed. The main structure of the heating source plant has been completed. Three out of total five boilers were put into operation by 2017 heating season. The Heat Source Plant will be fully completed by October 2018.Three out of total five boilers were installed and put into operation in 2017/2018 heating season, serving for 6 million m2 heating area, out of 11 million m2 total design heating area under this project.

The estimated total investment is approximately CNY680.82 million. Construction of Chengji Road and Flood Control Facilities was commenced in June 2012, and completed and put into operation in June 2016, as detailed below. The domestic completion audit is under preparation.

C01 - Chengji Road and integrated flood control facilities (K0+000~K3+250): The contract was awarded for Construction Engineering Group Co. Ltd. on 10 December 2012. The construction was completed on 28 July 2016. The Chengji Road with secondary urban trunk road is 25km long and 24 m wide, including the bridge with the length of 680 m. The road is situated in the north bank of Xi River with the flood control facilities and the design standard of flood return period is one in 100 years. The contract value is CNY43.7 million (equivalent to USD7.0 million).

C02 - Sunjiaping Xi River Bridge: The contract was awarded for China Railway 20 Bureau Group Co. Ltd. on 28 May 2012. The construction was completed on 11 November 2014. The Sunjiaping Xi River Bridge was designed by B-Chengji road completed and “CSCEC AECOM CONSULTANTS CO., LTD”. The main bridge is the total and flood control being length of 305m, the width of 35 m. The contract value is CNY79.5 million facilities and commissioned (equivalent to USD13.0 million).

C03 - Chengji Road and integrated flood control facilities (K3+650~K7+000): The contract was awarded for Eight Metallurgical Construction Group Co. Ltd. on 15 November 2012. The construction was completed on 28 July 2016. The road is the total length of 3.35 km, including roadwork, riverbank construction, lighting, drainage and Yangpo Bridge - a medium-size bridge. The contract value is CNY56.8 million (equivalent to USD9.5 million).

C04 - Chengji Road and integrated flood control facilities (K7+000~K10+360): The contract was awarded for Gansu Xinggcheng Construction Engineering Co. Ltd. on 15 November 2012. The construction was completed on 28 July 2016. The road is the total length of 3.36 km, including roadwork, riverbank construction, lighting, and drainage. The contract value is CNY45.8 million (equivalent to USD7.6 million).

C05 - Xiakou Bridge: The contract was awarded for Lanzhou

Page | 4 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

Current Planned Activities in The Component Implementation Description Status Future Municipal Construction Group Co. Ltd. on 28 May 2012. The construction was completed on 28 November 2015. The Xiakou Wei River Bridge was also designed by “CSCEC AECOM CONSULTANTS CO., LTD”. The total length of the bridge is 370 m. The contract value is CNY68 million (equivalent to USD11.3 million).

C06 - Maiji District New Road Network: The estimated total investment is approximately CNY73.58 million. The contract was awarded for Gansu Fourth Construction Group Co. Ltd. on 15 November 2012. The site is located at the south bank of Wei River, Maiji District. The four roads under the road network are urban secondary roads with a total length of 4.9 km. The contract value is CNY61.7 million (equivalent to USD10.3 million). Construction of Maiji District New Road Network was commenced in January 2013, and completed and put into operation in August 2016.

C07 - Shuangqiao Bridge: The estimated total investment is approximately CNY119.06 million. The contract was awarded for No.4 Engineering Co., Ltd of CRC on 28 April 2014. The superstructures of Shuangqiao Bridge are four spans arch bridge. The total length of the bridge is 907 m, and the width of the bridge is 24 m. The contract value is CNY87.8 million (equivalent to USD14.3 million). Construction of Shuangqiao Bridge was commenced in January 2013, and completed and put into operation in August 2016.

C- Tianshui urban C08 - Shetang Wei River Bridge: The estimated total investment is transport approximately CNY64.68 million. The contract was awarded for No. 5 improvement Engineering Co., Ltd. of CRSG on 30 November 2012. It is located in the Shetang Industrial Park, Maiji District, crossing the Wei River, connecting the industrial park with National road G310. The Shetang Wei River Bridge is designed by Municipal Engineering Design Institute. The total length of the main bridge is 331.4 m, and the width of the bridge is 20 m. Contract value is CNY50.8 million (equivalent to USD8.5 million). Construction of Shetang Wei River Bridge was commenced in December 2012, and completed and put into operation in November 2015.

C09 - Chiyu Road rehabilitation: The estimated total investment is approximately CNY73.66 million. The contract was awarded for Tianshui Chengxing Municipal Engineering Co. Ltd. on 10 November 2012. The subcomponent involves 2km long existing Chiyu road widening and rehabilitation, including Nangou River crossing bridge. The construction was commenced in December 2012. Contract value is CNY56.7 million (equivalent to USD9.4 million). Construction of Chiyu Road rehabilitation was commenced in January 2013, and completed and put into operation in June 2014.

China General Consulting and Investment Co., Ltd (CGCI) was recruited and fielded its services in Oct 2012 for the Project management. An overall training D-capacity program was prepared and submitted to ADB and PMO in the initial report in development and October 2012. A series of training for PMO and IAs staff were held on contract Underway institutional management, financial management, resettlement plans updating, road and strengthening bridges construction and management, heating, GRM and environment management. The PMO submitted and the ADB approved the contract variation request in 2017.

Page | 5 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

2. PROPONENT’S ENVIRONMENTAL MANAGEMENT RESPONSIBILITIES

2.1 Institutional Responsibilities for Environmental Management

9. Based on the domestic EIAs and the CEIA, the Project environmental management system(EMS), consisting of inspection, monitoring, reporting, and initiating corrective actions or measures, was set up prior to project implementation to ensure smooth implementation of EMP(subject to be updated with the Project progress). In the design stage, TPMO and the IAs passed on the EMP to the design institutes for incorporating mitigation measures into the detailed designs of the components. The EMP was reviewed and confirmed at the end of the detailed design, and was finally passed onto selected contractors. To ensure that contractors to comply with the EMP’s provisions, TPMO and the IAs prepared and provided the following specification clauses for incorporation into the bidding procedures: (i) a list of environmental items to be budgeted by the bidders in their proposals; and (ii) environmental clauses for contract conditions and specifications. Environmental management units (EMUs) were established by the IAs prior to the start of the Project implementation. They are in charge of the responsibility of coordinating and supervising the EMP implementation. The EMUs are headed by the deputy general managers of the IAs. Meanwhile, TPMO has drawn the expertise from TEPB in supervising the Project EMS. TUCIC as one of the implementing agencies signed contract with the Tianshui Environmental Monitoring Station (TEMS) in 2012. TEMS conducted eight semi-annually environmental monitoring campaigns since December 2012. THC as the implementing agency for heating component signed an agreement of intent with the Lanzhou Yitong Environmental Monitoring Company (LZYT), a certified monitoring service company as shown below, in May 2016. Since then, LZYT has conducted three semi-annually environmental monitoring campaigns. Table 2-1 below updates the environmental responsibilities of each organization and the status of fulfillment during implementation.

Page | 6 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

Page | 7 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

Table 2-1 Updated Environmental Responsibilities Matrix and Fulfillment Status During Implementation Stage-As of June 2018 Responsible Environmental Phase Contact Details Status of Fulfillment Agencies Responsibilities Construction Gansu Miss Jiaojiao (i) Conduct Asbestos Risk (i) Fulfilled; Provincial Assessment and prepare Environmental Asbestos Management Plan; Science ensure safe handling, Research transport and disposal of Institute, asbestos contaminated GDWDC waste; (ii) Supervise contractors in (ii) Fulfilled. implementing asbestos THC informed that 12 boilers management plan. involved with ACM. Among of them, 5 boilers are outside of THC jurisdiction, so local EPB will handle them, For the remaining 7 boilers, on 11 Sept. 2017, THC engaged a licensed institute who safely removed, transported and finally disposed asbestos containing materials (ACM) at Gansu province hazardous waste disposal center in compliance with the asbestos management plan, under supervision by TEPB. The relevant information is being collected and will be reported in details in next (11th) EMR, to be submitted to the ADB by January 2019. TPMO, IAs, TUCIC and THC (0938-8632483): CSCs (Mr. Chen Bo(overall environmental management) /Mr. Guo Yulong (18093822109, for heating pipe network) /Mr. Bo (13919663537, for associated facility- heating source plant) Advise on implementation of Ms. Yin (air quality supervision)/ Being fulfilled mitigation measures Mr. Du Junfeng (Acoustic environment supervision)/ Mr. Zhao Wei(Supervision on solid waste management) Ms. Wen(Hotline management)

Page | 8 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

Responsible Environmental Phase Contact Details Status of Fulfillment Agencies Responsibilities CH1- Gansu provincial installation company (Miss Li Lingna/project manager, 18189514310; Mr. Wei Xianli/EHS manager 18693204869)

CH2- Gansu provincial installation company (Miss Li Wen/project manager, 13993829592, [email protected]; Mr. Feng Tao/EHS manager, 15825806099, [email protected])

CH3- Gansu 1st construction company (Mr. Su Weijun/project manager, 15562579756; Miss Wang Yan/EHS manager, 18719726158) Implementation of mitigation Contractors CH4-Gansu Engineering Installation Group measures and conduct internal Being fulfilled Company(Mr. Feng Tao/project manager, monitoring 15825806099; Mr. Kang Ling/EHS engineer,15593389221)

CH5- Gansu 7th construction company (Mr. Wang Jianfeng/project manager, 18109447843, [email protected]; Mr. Sheng Hongyan/EHS manager, 18193839255, [email protected])

CH6- Lanzhou municipal construction company (Mr. Wang Xiaolong/project manager; Mr. Xu Jianjun/EHS manager)

CH1- Shanghai Fuda Construction supervision company (Mr. Tao Yanshou/project manager, 15095700968; Mr. Zhao Junhong/EHS manager, 15293132183, [email protected])

CH2- Shanghai Fuda Construction supervision company (Mr. Zhao Junhong/EHS manager, Conduct supervision and 13993868207, [email protected]) internal inspection for CSCs Being fulfilled implementation of mitigation CH3- Shanghai Fuda Construction supervision measures. company(Mr. Tao Yanshou/project manager, 15095700968, [email protected]; Mr. Zhao Junhong/EHS manager, 15293132183/13993868207, [email protected])

Page | 9 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

Responsible Environmental Phase Contact Details Status of Fulfillment Agencies Responsibilities CH4- Shanghai Fuda Construction supervision company (Mr. Zhao Junhong/EHS manager, 13993868207, [email protected])

CH5- Shanghai Fuda Construction supervision company(Mr. Tao Yanshou/project manager, 15095700968, [email protected]; Mr. Zhao Junhong/EHS manager, 15293132183/13993868207, [email protected])

CH6- Shanghai Fuda Construction supervision company(Mr. Tao Yanshou/project manager, 15095700968, [email protected]; Mr. Zhao Junhong/EHS manager, 15293132183/13993868207, [email protected])

Mr. Yang Yonghong, Director of Environmental Implementation of compliance / Being fulfilled. Management Department, TEPB; external monitoring, supervision

Tel : 0938-8214104 of implementation of mitigation measures. 0938-12369 Cell:13993829590 Tianshui Environmental Add: 69#, Dazhong Rd.,Qingzhou District, Tianshui Supervision Team, the City subordinate of TEPB, conducts regular enforcement and TEPB, TEMS, compliance site inspection on LZYT , the construction sites in

LSMI(Tianshui accordance with PRC’s Xiangyun soil Mr. Zhao Xiaoli, principal of TEMS, domestic environmental laws Semi-annually monitoring is erosion and Tel : 0938-8210917 and regulations. undertaken by the TEMS and ecological Add: 69#, Dazhong Rd.,Qingzhou District, Tianshui LZYT respectively. consulting firm), City TWRB

Miss Wang Weijin, principal of Lanzhou Yitong

Environmental Monitoring Company (LZYT), Tel : 0931-8279965 Add:571-2#, Zhangsutan road, Chengguan District, Lanzhou City

Mr. Li Changlu, principal of Tianshui Xiangyun soil

Page | 10 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

Responsible Environmental Phase Contact Details Status of Fulfillment Agencies Responsibilities erosion and ecological consulting firm The first and second soil erosion monitoring was conducted by Tianshui Xiangyun soil erosion and ecological consulting firm. Some soil erosion monitoring was undertaken through 2016~2017 for the Qinzhou district heating supply plant- the associated facility to component A, and the THC provided data in the 1st half of 2018, then those data are included in this EMR, Section 5.2. China General Consultant & Investment Advise on the mitigation Being fulfilled Co. Ltd; measures; and provide Mr. Li Zhi/Mr.NieMingtao, comprehensive technical support to TPMO and the IAs for LIEC Cell: 15117992350/18086056438 environmental management. Prepare semiannual environmental verification reports. TUCIC and THC, CGCI(LIEC) Being fulfilled. The first semi-annual EMR was disclosed on ADB’s website in March 2013, the second EMR in Prepare semi-annual January 2014, the third EMR in environment performance report April 2014, the fourth in TPMO under the assistance from February 2015, the fifth EMR in CGCI. May 2015, the sixth in Jan 2016, the seventh in Oct 2016, the eighth in Aug 2017, the ninth EMR.in Apr.2018 and this is the tenth EMR. ADB = Asia Development Bank, CSC = construction supervision company, = Design Institute(s), GDWDC = Gansu Provincial Dangerous Waste Disposal Center; LIEC = Loan Implementation Environmental Consultants, LSMI = Licensed Soil Monitoring Institute, MFMB = Municipal Facilities Management Bureau, TEMS = Tianshui Environmental Monitoring Station, TEPB = Tianshui Environmental Protection Bureau, TPMO = Tianshui Project Management Office, TWRB = Tianshui Water Resource Bureau.

Page | 11 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

2.2 Environmentally Responsible Procurement (ERP)

10. The English EMP was revised during mid-term review in October of 2013 and disclosed on ADB’s website in May 2015. The Chinese EMP is attached as an enclosure for each signed contract.

Page | 12 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

3. COMPLIANCE WITH ENVIRONMENT RELATED PROJECT COVENANTS

11. So far, all due environmental covenants in Loan Agreement and Project Agreement are in compliance, with some still to be enacted. A list of loan covenants and compliance status is shown in the Table 3-1 below.

12. The ADB midterm review mission was fielded in Tianshui on 28 October – 5 November 2013. The objectives of the mission are to (i) review the main issues that cause the implementation delay for the Project, (ii) conduct due diligence of the district heating component and newly proposed heat source plant as an associated facility to the Project, (iii) examine and assess whether attainment of the Project’s immediate objective is likely, (iv) review the technical, environmental, social, institutional, administrative, organizational, economic and financial aspects of the Project, (v) review the loan covenants, to assess whether they are still relevant, or need to be changed or waived due to changing circumstances, (vi) revise the Project implementation schedule, procurement plan and s-curve to reflect the current project content and situation, and (vii) update the Project administration manual, and relevant appendixes. The mission held discussions with officials of the Tianshui Municipal Government (TMG), which is the executing agency (EA) for the Project; the Tianshui Project Management Office (TPMO); Tianshui Urban Construction and Investment Company (TUCIC) and Tianshui Heating Company (THC) which are the implementing agencies (IAs); and other relevant agencies. The mission visited Maiji road, Shuanqiao bridge, Chiyu road, and sites related to district heating network and newly proposed heat plant. The Table 3-2 describes the latest implementation status of environmental requirements in the MOU by far. The environmental requirements have been complied with or are being complied with or to be complied with. .

13. The ADB midterm review mission was fielded in Tianshui on 20-24 October 2014. The objectives of the mission are to (i) conduct due diligence of heat source plant and component A design change, (ii) conduct due diligence of design changes under components 2 and 3, (iii) review contract variation proposals, (iv) review consulting package 5 selection progress, and (v) prepare documents required for making minor change in scope and implementation arrangements. The mission and officials from the executing agency (EA) for the Project, Tianshui project management office (TPMO), two project implementation agencies (IAs), namely Tianshui Urban Construction Investment Group Co. Ltd. (TUCIC) and Tianshui Heating Company (THC), and other relevant stakeholders held a series of meetings. The mission also conducted site visits on 22 October 2014 to better understand the current progress of the Project. The Table 3-3 describes the latest implementation status of environmental requirements in the MOU by far. The environmental requirements have been complied with or are being complied with or to be complied with.

14. An ADB loan review mission (the mission) was fielded in Tianshui on 4-6 May 2015. The objectives of the mission are to review the Project implementation status, and to make arrangement for project delegation from ADB EASS to PRCM. The mission and officials from the executing agency (EA) for the Project, Tianshui project management office (TPMO), two project implementation agencies (IAs), namely Tianshui Urban Construction Investment Group Co. Ltd. (TUCIC) and Tianshui Heating Company (THC), and other relevant stakeholders held a series of meetings. The mission also conducted site visit on 5 May 2015 to better understand the current progress of the Project. A wrap-up meeting was held on 6 May 2015 for a joint review of the findings of the mission.The Table 3-4 describes the latest implementation status of environmental requirements in the MOU by far. The environmental requirements have been complied with or are being complied with or to be complied with.

Page | 13 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

15. An ADB loan review mission (the mission) was fielded in Tianshui on 12-14 Apr 2016. The objectives of the mission are to review (i) the overall progress of the Project and implementation issues, (ii) status of land acquisition and resettlement, (iii) impacts to environment and poverty reduction, (iv) audit findings and financial management, (v) compliance with loan covenants, (vi) contract awards and disbursements progress, and (vii) potential loan extension; and identify measures for improving project performance. The Mission made field visits to project sites, and conducted discussions with officials from the executing agency (EA), Tianshui project management office (TPMO), two project implementation agencies (IAs), namely Tianshui Urban Construction Investment Group Co. Ltd. (TUCIC) and Tianshui Heating Company (THC), tendering agency, the Consultant, and other relevant stakeholders. The Table 3-5 describes the latest implementation status of environmental requirements in the MOU by far. The environmental requirements have been complied with or are being complied with or to be complied with.

16. An ADB loan review mission (the Mission) was fielded in Tianshui on 22-24 August 2017. The objectives of the Mission are to review (i) the overall progress of the Project and implementation issues, (ii) status of land acquisition and resettlement, (iii) impacts to environment and poverty reduction, (iv) audit findings and financial management, (v) compliance with loan covenants, (vi) contract awards and disbursements progress, and (vii) procurement issues; and identify measures for improving project performance. The Mission made field visits to project sites, and conducted discussions with officials from the executing agency (EA), Tianshui project management office (PMO), two project implementation agencies (IAs), namely Tianshui Urban Construction Investment Group Co. Ltd. (TUCIC) and Tianshui Heating Company (THC), tendering agency, the Consultant, and other relevant stakeholders. The Table 3-6 describes the latest implementation status of environmental requirements in the MOU by far. The environmental requirements have been complied with or are being complied with or to be complied with.

Page | 14 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

Table 3- 1Compliance with Environment Related Project Covenants

Environmental Relevant Covenant Reference Status of Compliance Notes Loan Agreement SCHEDULE 3 Allocation and Withdrawal of Loan Proceeds Notwithstanding any other provision of this 8 Being complied with. Loan Agreement, no disbursement shall be made for Component A, until (i) the Gansu (i) and (ii): The FSR and EIA on the CHP and Development and Reform Commission or transmission pipelines by China Huaneng National Energy Commission, as the case Group had been finished, but construction has may be, has approved China Huaneng been delayed. During mid-term review in Group’s pre-approval application for the October/November 2013, Qinzhou district combined heat and power plant; (ii) TMG heating source plant and associated pipelines has provided to ADB the approved the are proposed as main heating source for Project’s feasibility study reports and EIAs Component A instead of the original designed for the CHP and transmission pipelines; CHP and transmission pipelines. The revised and (iii) TMG has engaged a licensed FSR was finished in March 2014 and approved institute and conducted an asbestos risk by Gansu provincial DRC in June 2014. The assessment for all 199 small boilers draft EIA was reviewed by the expert panel in affected by the Project. March 2014 and was approved in May 2014 by Gansu Provincial EPB. The land was approved in January 2015 by Gansu Provincial Land Resource Bureau. The detailed drawings were finished in 2015.

(iii)Due to the above changes, there will be 194 small boilers to be demolished. THC engaged a licensed institute (Gansu provincial environmental science research institute) in conducting asbestos risk assessment and preparing asbestos management plan for all 194 small boilers to be affected by the Project. THC informed that 12 boilers involved with ACM. Among of them, 5 boilers are outside of THC jurisdiction, so local EPB will handle them, For the remaining 7 boilers, on 11 Sept. 2017, THC engaged a licensed institute who safely removed, transported and finally disposed asbestos containing materials (ACM) at Gansu province hazardous waste disposal center in compliance with the asbestos management plan, under supervision by TEPB. The relevant information is being collected and will be reported in details in next (11th) EMR, to be submitted to the ADB by January 2019. Project Agreement GPG and TMG shall carry out the Project Section Being complied with. with due diligence and efficiency, and in 2.01(a) conformity with sound administrative, financial, engineering, environmental and urban development practices. TMG shall at all times conduct its business Section Being complied with. in accordance with sound administrative, 2.11(a) financial, environmental and urban The Project environmental management development practices, and under the system has been established and involves supervision of competent and experienced different levels of departments, including management and personnel. TUCIC/THC, TEPB/TEMS/LZYT, LIEC,

Page | 15 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

Environmental Relevant Covenant Reference Status of Compliance Notes constructors and CSCs, also updated with the Project implementation progress. TMG shall at all times operate and Section Partially being complied with for the maintain its plants, equipment and other 2.11(b) components B and C (roads) already property relating to the Project, and from completed and open to traffic. time to time, promptly as needed, make all necessary repairs and renewals thereof, all For component A (heating network) still under in accordance with sound administrative, implementation, to be complied with during financial, engineering, environmental, operational stage. urban development, and maintenance and operational practices. The LIEC observed several sections of flood prevention dykes under component B - Chengji road and flood control facilities were dismantled due to other project intervention (as shown in the below layout figures). This component was completed in 2016. Considering the rainy season is coming, there had been big risks on soil erosion and dyke collapse in the near future. All construction activities affecting ADB-financed component should get approvals from all relevant government departments, in particular on soil erosion and flood control assessment. After the completion of this intervention project, the flood control standard of the restored dyke should ensure the annual probability of seasonal flooding along Chengji flood embankment reduced to 1%. In addition, due to raining season, the LIEC suggested immediate rectification, emergency response plan and to apply good O&M practices to ensure the flood safety. (for details please see Section 5.2.1)

SCHEDULE Execution of Project; Financial Matters Environment TMG shall cause each Implementing 9 Being complied with. Agency to construct, operate, maintain, and monitor the Project facilities in strict PRC’s environmental laws and regulations, conformity with (i) the Borrower’s all ADB’s SPS are being complied with. applicable laws and regulations, including national, provincial, and municipal laws and All environmental mitigation and monitoring regulations and standards on measures have been or will be incorporated environmental protection, district heating, into the design and bidding documents and health, labor, and occupational safety, and construction contracts. ADB’s Safeguard Policy Statement; and (ii) all environmental mitigation and monitoring Environmental mitigation costs have been measures detailed in EIAs, Project EIA and identified and special costs for appropriate EMP under the guidance of TEPB or other environmental protection and pollution designated environmental monitoring prevention have been guaranteed. centers. TMG shall cause the Implementing Agencies to incorporate such mitigation and monitoring measures into the design and bidding documents and construction contracts. TMG shall ensure that facilities associated 10 Being or to be complied with during with the Project are constructed, operated, construction and operation stage. maintained, and monitored in strict

Page | 16 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

Environmental Relevant Covenant Reference Status of Compliance Notes conformity with (a) all applicable laws and The associated facility with the component A regulations, including national, provincial, (CHP to Qinzhou district heating source plant) and municipal laws and regulations and were proposed to change during mid-term standards on environmental protection, review in October/November 2013. The district heating, health, labor, and domestic EIA report was prepared in occupational safety; and (b) all accordance with PRC environmental environmental mitigation and monitoring regulations. An EMP including environmental measures detailed in the applicable monitoring program was developed, and an environmental impact assessments for the environmental due diligence review was associated facilities under the guidance of undertaken correspondingly in accordance the TEPB or other designated with ADB’s SPS (2009). environmental monitoring centers. The changes in the associated facility are reflected in the revised EMP of December 2014, which has been disclosed on ADB’s website since May 2015.

The Qinzhou district heating source plant started construction in January 2016, with main structure completed in Oct. 2017, already commissioned in 2017/2018 heating season, and will be fully completed in Oct. 2018 , and put into operation in Nov. 2018 .

TMG shall cause the Implementing 11 Being complied with or to be complied with. Agencies to ensure that sufficient resources and fulltime personnel are The Project environmental management provided in monitoring EMP system has been established and involves implementation, under the guidance and different levels of departments, including supervision of the TEPB or other TUCIC/THC,TEPB/TEMS/LZYT,LIEC, environmental monitoring centers. TMG, constructors and CSCs. through PMO, shall submit to ADB, the EMP progress reports and information on Contractors/CSCs have implemented internal Project implementation and the monitoring and submitted monthly internal environmental performance of the Works monitoring report to TUCIC/THC, under the contractors, the Implementing Agencies guidance and supervision of the and the loan implementation environmental TEPB/TEMS/LIEC (see the Appendix 3). consultants. These reports shall include (a) semiannual environmental performance The LIEC has regularly reviewed the internal reports on EMP implementation, and (b) monitoring report submitted by the environmental compliance monitoring and constructors/supervisors. audit report of the completion of each major component. TMG shall ensure that (a) Ten semi-annual environmental ADB may request that further performance reports have been included environmental mitigation actions be taken, in the semi-annual progress reports as deemed necessary, and may determine (including the mid-term review report) further mitigation measures for different respectively. stages, if necessary. TMG shall establish a grievance review mechanism as provided (b) Environmental compliance monitoring and in the EMPs to receive affected peoples' audit report of the completion of each concerns, complaints, and grievances major component will be prepared until about the Project's environmental impacts. completion of each road civil works contract (components B and C) in second half of 2018.

An environmental GRM had been established and is operated by TPMO and IAs. As required, the GRM was updated by TPMO and approved by ADB in May 2015.

Page | 17 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

Environmental Relevant Covenant Reference Status of Compliance Notes

In response to requirements under ADB’s 12 Being complied with. Safeguard Policy Statement, the environment performance of the Project TEMS, as qualified external monitoring shall be verified by an external monitor, agency, has conducted eight periods’ external which will review all environment reports, monitoring on the road civil works contract including internal and compliance (components B and C) according to the monitoring reports and the semi-annual environmental monitoring program in the EMP environment performance report, and of CEIA, respectively in Jan 2013, Aug.2013, prepare a semi-annual environment Dec.2013, Jul. 2014, Mar.2015, Jul. 2015, monitoring verification report. The report Mar.2016 and Dec 2016. shall confirm the Project’s compliance with the EMP, the conditions to the issuance of Lanzhou Yitong Environmental Monitoring the environmental clearance and the Company (LZYT) has conducted two external Borrower’s legislated standards, and shall monitoring campaign on the heating pipeline identify any environment-related network civil works contract (component A) implementation issues and necessary according to the environmental monitoring corrective actions. program in the EMP of CEIA in May/August/September 2016, June/July 2017 and Oct 2017, and May 2018.

Tianshui Xiangyun soil erosion and ecological consulting firm(Tianshui Soil Erosion Protection Monitoring Station (TSEPMS)) conducted the first soil erosion monitoring in April 2014, and the second from May 2014 to May 2015. Some soil erosion monitoring was undertaken through 2016~2017 for the Qinzhou district heating supply plant- the associated facility to component A, and the THC provided data in June 2018, then those data are included in this EMR, Section 5.2.

The 1st semi-annual external environmental monitoring report as baseline was disclosed on ADB’s website in March of 2013.

The 2nd semi-annual external environmental monitoring report was disclosed on ADB’s website in January of 2014.

The 3rd EMR was disclosed in April 2014 and the 4th February 2015.

The 5th EMR was disclosed in Jun. 2015.

The 6th was disclosed in Jan 2016.

The 7th was submitted in Oct 2016.

The 8th was submitted in Aug 2017.

The 9th was submitted in Apr 2018.

This is the 10th EMR. TMG, through PMO, shall ensure that the 13 Being complied with. capacity-building program described in the See Chapter 6. EMP is implemented as planned from June 2011 until physical completion of the Project.

Page | 18 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

Environmental Relevant Covenant Reference Status of Compliance Notes TMG shall ensure that the deconstruction 14 Pedestrian bridge: complied with for the and disposal of old coal-fired boilers and contract package C07 in component C. single-family heating stoves, as well as the Heating related facilities: Complied with in the pedestrian bridge under the Project, follows component A. national regulations on disposal of construction waste, and are done with approval and supervision by TEPB. In case that presence of asbestos is 15 Complied with in the component A. identified by the asbestos risk assessment, TMG shall ensure that an asbestos THC has recruited a qualified institute to management plan is developed for all conduct asbestos risk assessment and affected boiler houses. TMG shall cause prepare asbestos management plan. The THC to ensure that the contractors receive asbestos risk assessment and prepare adequate training on asbestos asbestos management plan were submitted to management, occupational health and ADB in December 2013. safety, and that the rehabilitation or deconstruction of asbestos containing The asbestos risk assessment and asbestos boiler houses is conducted and supervised management plan were endorsed by TEPB in in conformity with the ADB approved 2014. (no approval procedure is needed from asbestos management plans. TEPB or Tianshui Work Safety Administration )

THC informed that 12 boilers involved with ACM. Among of them, 5 boilers are outside of THC jurisdiction, so local EPB will handle them, For the remaining 7 boilers, on 11 Sept. 2017, THC engaged a licensed institute who safely removed, transported and finally disposed asbestos containing materials (ACM) at Gansu province hazardous waste disposal center in compliance with the asbestos management plan, under supervision by TEPB. Please see the photos in next page. The relevant information is being collected and will be reported in details in next (11th) EMR, to be submitted to the ADB by January 2019.

TMG shall engage an expert geological 16 Partly complied with. team to conduct a thorough soil condition evaluation along the Chengji Road and Gansu Zhongjian Municipal Engineering delineate the areas that have potential Investigation Design Institute, as a qualified risks for mudslides before project institution, did the geotechnical investigation implementation. Based on the evaluation including soil condition. In addition, the results, TMG shall develop a detailed land monographic study on Xiaoyanzhai, Yanji use plan for the entire area between the Xi Village and Yangpo was done. Tianshui Land River and Beishan Mountain. TMG shall Resource Bureau attended the expert review ensure that areas with high potential risk of meeting. mudslides are clearly defined and marked as a non-urban development zone. TMG shall ensure that a mudslide 17 Partly complied with. monitoring system is installed in the Beishan Mountain to record rainfall, The geotechnical survey conducted between surface water flow, unusual noise, earth Chengji road and Beishan Mountain concluded cracks, deformation and movement. TMG that the area is generally stable and not prone shall also ensure that an emergency to mud- or landslides. However, two areas response plan is developed and were identified with more elevated risk implemented to respond to any possible (Yangpo, Yangjiahewan). mudslides. The mudslide monitoring plan was prepared by CSCEC AECOM Consultants Co., Ltd.

Page | 19 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

Environmental Relevant Covenant Reference Status of Compliance Notes (previously called as Northwest Municipal Engineering Design Institute) in February 2014. The plan was implemented prior to rain season (July to September).

Meanwhile, the contractors conducted irregular on-site observation. In January 2018, TUCIC informed that the relevant constructors undertook mudslide monitoring during construction stage. TMG shall ensure that the hydrological 18 Being complied with. monitoring stations in Tianshui, Nanhechuan and Beidao regularly monitor The hydrological monitoring data from 2013 up the Xi River’s and Wei River’s hydrology, to date is available. The rainfall monitoring river bed morphology and sediment station under TUCIC monitor rainfall in transport, and share the monitoring data Tianshui city. Further Tianshui Flood with PMO. Based on such monitoring data, Prevention Office under TWRB monitors the PMO shall assess the risks to and potential hydrological status of Xi River and Wei River. impacts on, the safety of affected Once unexpected emergency occurs, Tianshui communities during construction and Flood Prevention Office will assess the operation and shall establish preventive potential impacts and risks, also notice PMO measures and plans to address them in a and other relevant agencies if required. manner commensurate with the identified risks and impacts. Public Awareness TMG shall cause the Implementing 26 Being complied with. Agencies to undertake public awareness campaigns through information disclosure, education and consultation on the Project and its benefits, including but not limited to information related to the RPs, EMPs, Gender Action Plan and Social Development Action Plan under the Project.

Page | 20 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

Table 3- 2 Implementation Status of Environmental Requirements In The MOU On November 5th, 2013

(Updated as of June 2018)

No. Requirements in the MOU Current status/Next plan Remarks 1 Paragraph 43. EMP implementation and supervision Complied with. See Table arrangements…. In order to strengthen EMP implementation and 2-1 of supervision arrangements for component A, THC agreed to assign THC has assigned adequate staffs for EMP coordination Para.9. sufficient environmental staff for EMP coordination, and to contract TEMS and supervision, and engaged Lanzhou Yitong for external monitoring, prior to commencement of construction works. Environmental Monitoring Company (LZYT) since May (June 2014). 2016 to conduct external environmental monitoring

2 Paragraph 45. Environment monitoring and EMP progress Submitted and disclosed in ADB’s project website in reports …The 2nd EMR, covering the period April to October 2013, will January 2014. be submitted to ADB by 15 November 2013, prominently describing the issues defined in Appendix __, para. 4 (i)-(xi).

(i) Project implementation progress, including main construction activities during reporting period; Done.

(ii) Institutional setup for EMP implementation; Done.

(iii) Updated mitigation measures plan accounting for detailed Covered in the updated EMP, finalized and disclosed on design and the proposed change in the associated facility to district ADB project website in May 2015. heating component;

(iv) Updated monitoring plan, defining responsibilities, parameters, Covered in the updated EMP, finalized and disclosed on frequency and location; ADB project website in May 2015

(v) Monitoring results, including assessment of compliance with Done. relevant standard and targets, and trend analysis (accounting for previous monitoring results);

Done. The summary of submission status of the internally (vi) Main inspection activities and results of CSCs; reporting sees the Appendix 3 of the 2nd EMR6.

(vii) Contractor performance, site investigation results; Done. The summary of submission status of the internal reporting sees the Appendix 3 of the 2nd EMR. (viii) Training activities, including actual trainings conducted during

6 https://www.adb.org/projects/documents/gansu-tianshui-urban-infrastructure-development-project-emr-jan2014

Page | 21 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

No. Requirements in the MOU Current status/Next plan Remarks reporting period, and planned activities during next reporting period; Done.

(ix) Public consultation, including actual consultation activities Done. conducted during reporting period, and planned activities during next reporting period;

(x) Description of the grievance redress mechanism (GRM), i.e., the local Environmental Protection Bureau (EPB)’s hotline (12369), and Done. grievances received and redressed during the reporting period; and

(xi) Problems that have occurred and corrective actions (proposed Done. or implemented). 3 Paragraph 46. …Grievance Redress Mechanism (GRM, Appendix _, (i) Covered in the updated EMP, finalized and para. 10): The mission reviewed, and concurred with, the revised GRM. disclosed on ADB project website in May 2015. The following agreements were reached: (i) the revised GRM will be (ii) Documented in the 2nd external environmental documented in the updated EMP; (ii) its development, including changes monitoring report. and trainings conducted, will be documented in the 2nd EMR; (iii) the (iii) Complied with so far . GRM will be used to develop contract-specific GRM flowcharts, which will be disclosed at each construction site, not later than end of November 2013 (for civil works contracts under implementation). 4 Paragraph 47. Mud- and landslide risk management along Chengji Complied with. Road (Appendix __, para. 12). The geotechnical survey conducted between Chengji road and Beishan Mountain concluded that the area is The mudslide monitoring plan was prepared by CSCEC generally stable and not prone to mud- or landslides. However, two areas AECOM Consultants Co., Ltd. (previously called as were identified with more elevated risk (Yangpo, Yangjiahewan). To Northwest Municipal Engineering Design Institute) in adequately address the risk, it was agreed that TUCIC will develop and February 2014. The plan was implemented prior to rain implement by May 2014 an observation and monitoring system for these season (July to September). Meanwhile, the contractors two sites, with the support of qualified experts. conducted irregular on-site observation. In Jan 2018, TUCIC informed that the relevant constructors undertook mudslide monitoring during construction stage.

5 Paragraph 48. Asbestos Risk Assessment (ARA, Appendix _, para. (i) The asbestos risk assessment report and management 12). The draft ARA for existing boilers prepared by Gansu Provincial plan were submitted to TEPB and ADB for recording. Also Environmental Science Research Institute (ESRI, contracted by THC) those reports were submitted to Tianshui Work Safety identified asbestos containing materials (ACM) in 32 of the 194 boilers to Administration. However, Tianshui Work Safety be decommissioned, with three-quarter of the amount located in 4 boiler Administration need not approve those reports. houses. Next steps were discussed, and the following agreements reached: (i) By 31 December 2013, the revised ARA including (ii) Complied with. THC informed that 12 boilers involved management plan will be submitted to TEPB and the Tianshui Work with ACM. Among of them, 5 boilers are outside of THC Safety Administration for appraisal, and to ADB for information; (ii) THC jurisdiction, so local EPB will handle them, For the will hire a licensed institute to safely remove, transport and dispose ACM remaining 7 boilers, on 11 Sept. 2017, THC engaged a in compliance with the asbestos management plan; (iii) ESRI will confirm licensed institute who safely removed, transported and through post-cleanup assessment that the sites are ACM-free and ready finally disposed asbestos containing materials (ACM) at

Page | 22 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

No. Requirements in the MOU Current status/Next plan Remarks for deconstruction. Gansu province hazardous waste disposal center in compliance with the asbestos management plan, under supervision by TEPB. Please see the photos in next page. The relevant information is being collected and will be reported in details in next (11th) EMR, to be submitted to the ADB by January 2019.

(iii) To be complied with. The post-cleanup assessment had been included in the revised asbestos management plan. 6 Paragraph 49 …; Environment safeguards due diligence for proposed change in scope (Appendix _, para. 15, 16). The proposed change in scope was screened for environmental impacts in accordance with ADB’s Operations Manual section F1/OP. The mission confirmed that (i) the change in scope only relates to the heat source, a facility associated to the Project; (ii) it will not induce significant incremental impacts that were not considered at project approval stage; (iii) while the Project will remain category A, the change can be classified as category C for environment, subject to confirmation by ADB’s Regional and Sustainable Development Department (RSDD). An action plan was agreed upon to process environment safeguards for the proposed change in scope:

(i) THC will get all remaining approvals for the new heat source, (i) The revised FSR was finished in March 2014 and including geological hazard assessment (November 2013), EIA (Gansu approved by Gansu provincial DRC in June 2014. The Provincial Environment Protection Bureau, May 2014), and FSR draft EIA was reviewed by expert panel in March 2014 and (Tianshui Development and Reform Committee, June 2014); approved in May 2014 by Gansu provincial EPB.

(ii) The Consultant will update the consolidated EIA and EMP to (ii) Complied with. The revised EMP was submitted as reflect and highlight all proposed changes. The updated consolidated EIA scheduled and disclosed on ADB’s project website in May and EMP will be submitted to ADB for approval and disclosure, by 30 2015. November 2013;

(iii) …

Page | 23 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

Table 3- 3 Implementation Status of Environmental Requirements In The MOU On October 24th, 2014

(Updated as of June 2018)

No. Requirements in the MOU Current status 1 TUCIC will submit an environmental report on C01 changes to Complied with. Submitted by TUCIC and approved by TEPB. TEPB by 31 October 2014, addressing the issues and defining required mitigation measures. 2 TEPB will review environmental report on C01 changes and Complied with. The environmental report was approved by determine by 30 November 2014 whether a domestic EIA report TEPB on 17 Nov. 2014. Neither significant issue identified, nor is required. EIA was required to update.

3 Contract TEMS for EMP external monitoring, prior to Complied with. commencement of construction works (expected to start from January 2015). THC as the implementing agency for heating component signed an agreement with Lanzhou Yitong Environmental Monitoring Company (LZYT) in May 2016.

The construction of the heating component was started in 2016. Lanzhou Yitong Environmental Monitoring Company (LZYT) conducted the first external environmental monitoring in May/August/September 2016,June/July 2017 and the second in Oct 2017, the third in May 2018.

4 THC will conduct public consultation nearby newly added Complied with. Incorporated into Chapter 6 of the 5th EMR7. alignments and submit ADB a report, covering the results of public consultation at environmental sensitive receptors

7 https://www.adb.org/projects/documents/gansu-tianshui-urban-infrastructure-development-project-may-2015-emr

Page | 24 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

Table 3- 4 Implementation Status of Environmental Requirements In The MOU On May 6th, 2015

(Updated as of June 2018)

No. Requirements in the MOU Current status 1 Environment. No major issues. ADB is satisfied with the Complied with. environmental monitoring reports. During the site visit, mission noticed that contractor was throwing rubbish into the river. Loan The LIEC undertook relevant training in May 2015. It was implementation consultant will advise the contractors to prevent confirmed of no such issues being incurred during the LIEC’s such activities. site visit in January 2016, April 2016, July 2017, Jan/April/June 2018.

Page | 25 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

Table 3-5 Implementation Status Of Environmental Requirements In The MOU On April 14th, 2016

(Updated as of June 2018)

No. Requirements in the MOU Current status 1 Para. 26. …The mission reminded implementing agencies and PMO to keep Complied with. This is the tenth EMR monitoring and monitoring and reporting environmental impacts constantly during construction reporting environmental impacts constantly during and operation in terms of EMP requirements. construction and operation in terms of EMP requirements

2 Para. 27…. Further to the suggestions provided in the EMR, the Mission Being complied with. requested PMO to follow up the improvement activities as below: • More efforts are required on water and soil conservation to prevent soil • Being underway. Soil erosion prevention was erosion in the next stage. It is recommended that water and soil emphasized with onsite training during site visit in Jan conservation at borrow areas and construction waste disposal sites be 2018. SEPP monitoring is being undertaken by a better considered and strengthened to reduce soil erosion during rainy qualified institute. seasons. However, it is recognized that most water and soil conservation works could be carried out only after the whole construction is finished. • For these contracts to start construction, environmental management • Complied with for the heating source plant and contract system should be developed prior to implementation, along with good package CH2/CH3/CH4/CH5 and associated facilities- practices of environment, healthy, and safety (EHS) for training. It is Qinzhou district heating source plant of heating necessary to strengthen the internal monitoring and supervision, and component. Relevant training was provided to the THC, take necessary corrective action if required. contractors, and CSCs in Jan 2018. Sample internal monitoring reports were provided. • Environmental responsibilities should be more clearly defined and more • Being improved. Corresponding training was provided, tailor-made training should be provided for the all relevant as shown above. Moreover, project environmental environmental management agencies to improve the environmental completion related training was provided to the nine management, monitoring and reporting during construction period. road civil contractors/CSCs (components B and C) in April 2016 and to the heating piping civil works contractors/CSCs (component A) in Jan/Apr/Jun 2018. • The contractors should strengthen the construction supervision and • Being underway. management, and minimize the negative impact on the environment. Meanwhile, it is necessary to strengthen the environmental management training for the construction workers, and enhance their awareness of environment protection so as to ensure smooth implementation of the EMP. • Environmental protection costs incurred should be identified and special • Complied with for all the signed contracts. The costs for appropriate environmental protection and pollution prevention environmental mitigation costs are being collected. should be guaranteed.

Page | 26 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

Table 3-6 Implementation Status of Environmental Requirements in The MOU On August 24th, 2017

(Updated as of June 2018)

No. Requirements in the MOU Current status 1 Para. 35. …In line with the EMP requirements, environmental Complied with. For details please see the para. 10 in Chapter 2. specification clauses have been/should be prepared in the civil work contracts. 2 Para. 37. Environmental Monitoring Report. …. The 8th report (covering the period May 2016 to July 2017) was issued late due to delays in consulting service contract extension. The Mission reiterated the reporting requirements as defined in the consolidated EIA, project agreement, PAM and EMP, which is semi-annual consolidated environmental monitoring reports (EMR) to be submitted by the TPMO, with support of the external monitoring agencies and LIEC, and submitted to ADB for approval and disclosure. The PMO was requested (a) Complied with. The 8th EMR was submitted and approved by ADB in to support the external environmental consultant. (a) The 8th report Aug 2017. should be submitted to ADB in August 2017 and (b) the 9th report (b) Complied with. The 9th EMR was submitted and approved by ADB in covering the period July to December 2017 should be submitted to ADB Apr 2018. This is the 10th semi-annual EMR; and the 11th semi- in February 2018. annual EMR shall be submitted to ADB by 30 January 2019 3 Para. 38. Site Management Issues. .... It was noted that there has Being complied with. Samples of public service interval and restoration been complex public utilities in the Project area, which is one of the please see the photos in next page. biggest challenges encountered by contractors, although a three- dimensional underground detection was undertaken before construction Information disclosure and some public consultation activities were to avoid damage of underground facilities, potential accidents, fulfilled during this reporting period. For details please see the Chapter excessive costs, and construction delays. External monitors and the 7. PMO were reminded of the need for ongoing public consultation with affected persons throughout implementation. 4 Para. 39. Grievance Redress Mechanism, Information Disclosure Being complied with. and Public Consultation. It was observed that information boards are installed at all work sites and offices with key project contacts and Information disclosure and some public consultation activities were activities and details of the complaints procedures. External safeguard fulfilled during this reporting period. For details please see the Chapter monitors will follow up arrangements for grievance redress mechanism 7. and information disclosure in the safeguard monitoring reports due for submission to ADB in August. 5 Para. 40.Decommission of 194 boilers. In 2014, the asbestos risk Being complied with. assessment report and management plan were submitted to TEPB and ADB for recording. Since some out of 194 boilers will be THC informed that 12 boilers involved with ACM. Among of them, 5 decommissioned prior to November 2016 when this project starts to boilers are outside of THC jurisdiction, so local EPB will handle them, supply heating, THC will hire a licensed institute to safely remove, For the remaining 7 boilers, on 11 Sept. 2017, THC engaged a licensed transport and dispose asbestos containing materials (ACM) in institute who safely removed, transported and finally disposed asbestos compliance with the asbestos management plan; and will confirm containing materials (ACM) at Gansu province hazardous waste disposal through post-cleanup assessment that the sites are ACM-free and center in compliance with the asbestos management plan, under ready for deconstruction before decommission of boilers. supervision by TEPB. Please see the photos in next page. The relevant information is being collected and will be reported in details in next (11th) EMR, to be submitted to the ADB by January 2019.

Page | 27 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

Public service interval and restoration (contract CH05 as sample)

Restoration of telecommunication pipes Roadlight power cable Water supply pipes

Decommission of small boilers- licensed institute safely removed, transported and disposed asbestos containing materials (ACM) in compliance with the asbestos management plan

Page | 28 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

4. ENVIRONMENTAL MITIGATIONS AND COMPENSATION MEASURES IMPLEMENTED IN THE REPORTING PERIOD

17. Based on the revised EMP (May 2015 version), potential environmental impacts of the Project and the mitigation measures during this reporting period are summarized in the Appendix 2. The implementation status of the mitigation measures are summarized in the last columns of the tables for comparison with the designed mitigation measures stated in the revised EMP. In summary, the mitigation measures have to date been implemented effectively. A scale rating for quantifying each contract’s performance in term of EMP implementation (trial toolkit) was applied and the weighted average rates 3.9 to 4.0 (3 stands for Meets expectations and 4 stands for Exceeds expectation) illustrate that all contracts had effectively implemented EMP during this reporting period. Especially for the contract CH5, excavation methods of heating piping at five urban main road sections with heavy traffic volume (Hezhuo road, Minshan road, Taoyuan road, Tianqing road and Beiyuanzi road) are changed to directional drilling, and at West bridge and Qilidun bridge of Xi River are changed to pipe jacking from original planned open excavation to avoid adverse environmental impacts and lessen traffic disturbance (see below meeting notes from THC in Feb 2017).

Page | 29 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

18. The Status of the EMP Budget. According to the approved CEIA and EMP, the total environmentally related cost for the Project, including costs for soil erosion protection, is $6.6437 million (CNY44.21 million), or 2.93% of the total estimated budget of the Project. However, the Project plan has been changed slightly since the CEIA was done in 2007. Up to date, most of the mitigation measures are covered by the total cost of the construction contracts. Besides, TPMO and IAs have some budget allocated for external environmental monitoring, institutional strengthening, training and public consultation. By far, it is noted that no relevant cost has been recorded excluding the EIA study for the Project preparation, external environmental monitoring and soil erosion monitoring for components B and C. All roads and bridges civil works contracts have almost been completed. Environmental PCR related training was provided to the two IAs, nine road civil contractors/CSCs in April 2016/April and June 2018 respectively. The sample data list following the format of the approved CEIA was provided to the constructors for preparation. During site visits in June 2018, the LIEC suggested that the contractors collect data on all the relevant EMP cost, including soil erosion protection cost. In addition, the contractors of contract packages CH01, CH02, CH03 and CH06 reported that the actually incurred mitigation costs are CNY75,400, CNY 482,725, CNY 137,500 and CNY 382,500 by 30 June 2018, as shown in the below table.

19. Preparation of project completion review (PCR). The LIEC informed the PMO that the new regulation in the PRC on environmental acceptance after construction completion came into effect since October 2017 and requested them to check with TEPB for the preparation and approval of the environmental acceptance report for the project. Regardless of domestic environmental acceptance procedure, the LIEC advised the PMO to prepare and submit to ADB a consolidated environmental assessment including all the project components under ADB and domestic financing prior to the PCR mission scheduled on 10-14 Dec 2018. Environmental PCR related training was provided by the CGCI to the two IAs, all civil contractors/CSCs in April 2016/April and June 2018, respectively. The data list was provided to the IAs/contractors for preparation. The PCR data including environmental mitigation such as soil erosion prevention and control cost, loan covenants compliance (such as mudslide-free land use plan and mudslide monitoring; hydrological monitoring data sharing) and project benefits (eg coal savings) be collected and reported in the future EMRs, project progress reports, and the consolidated environmental assessment.

Page | 30 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

Table 4- 1 Actual vs Estimated Major Environmental Mitigation Costs – Component A (as of June 2018)

Budgeted at CEIA Actual as of Jun 2018 Contract CH01 Contract CH03 Contract CH03 Contract CH06 Item Cost (CNY) Cost Source of Fund Cost Cost Source of Source Cost Source Cost Source (USD) (CNY) (CNY) Fund of Fund (CNY) of Fund (CNY) of Fund EIA Study 200,000 29,295 Executing Agency 30,000 THC 30,000 THC 30,000 THC 30,000 THC Soil erosion protection including spoil disposal 220,000 32,225 Contractors site restoration Mitigation measures for 80,000 11,718 Contractors soil contamination Mitigation measures for wastewater discharge 9,000 1,318 Contractors from construction sites and camps Construct equalization and sedimentation tanks in the HESs for pH 300,000 43,943 Contractors adjustment and sedimentation Mitigation of dust 38,000 Contract 110,825 Contrac 64,500 Contract 105,000 Contract generated from or of tor of or of or of construction and CH01 CH02 CH03 CH06 100,000 14,648 Contractors transportation of construction materials and wastes Mitigation measures for emissions from vehicles 15,000 2,197 Contractors and construction equipment Disposal of solid wastes Contract Contrac Contract Contract including storage of 80,000 11,718 Contractors 10,000 or of 10,800 tor of 19,000 or of 3,000 or of hazardous materials CH01 CH02 CH03 CH06 during construction Soundproof facilities and measures during Contrac Contract construction including 90,000 13,183 Contractors 100,000 tor of 50,000 or of 250,000 vibration impact CH02 CH03 mitigation

Page | 31 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report Budgeted at CEIA Actual as of Jun 2018 Contract CH01 Contract CH03 Contract CH03 Contract CH06 Item Cost (CNY) Cost Source of Fund Cost Cost Source of Source Cost Source Cost Source (USD) (CNY) (CNY) Fund of Fund (CNY) of Fund (CNY) of Fund Disposal of solid waste generated by demolishing Implementing 200,000 8 29,295 small boilers Agency (management cost) Disposal of asbestos and Implementing ACM during demolishing 1,000,000 150,276 Agency & owners small boilers of small boiler Construction site safety 23,000 Contract 206,000 Contrac 9,500 Contract including emergency or of tor of or of 20,000 2,930 Contractors preparedness and CH01 CH02 CH06 response Planting trees and landscaping in the relay pumping station; protection of vegetation, 150,000 21,972 Contractors re-vegetation of disturbed areas (include fauna protection) Physical cultural Contractors resources protection 5,000 732 during construction Mitigation measures for Contractors Impact to traffic and public facilities, 80,000 11,718 community safety during construction Environmental monitoring Contractors 203,000 29,735 during construction Inspection and monitoring Agency of asbestos during 100,000 15,028 demolishing small boilers Training on handling and TPMO managing asbestos 30,000 4,508 containing material (ACM) Soundproof measures in 100,000 14,648 Implementing

8 The budget is for contract management expenses only. The current practice in the Project area is that contractors sell scrap and steel after demolishing small boilers and stoves for their labor payments, therefore the owners of the small boilers will not need to pay the contractors if asbestos is not identified during the asbestos risk assessment.

Page | 32 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report Budgeted at CEIA Actual as of Jun 2018 Contract CH01 Contract CH03 Contract CH03 Contract CH06 Item Cost (CNY) Cost Source of Fund Cost Cost Source of Source Cost Source Cost Source (USD) (CNY) (CNY) Fund of Fund (CNY) of Fund (CNY) of Fund the 78 HESs and the Agency relay pumping station during operation (/yr) Mitigation measures for Implementing wastewater treatment 150,000 21,972 Agency (/yr) Measures for Implementing occupational and Agency 50,000 7,324 community health and safety (/yr) Review Compliance of Implementing the Associated facilities 3,000 439 Agency (/yr) Re-employment training Executing Agency for affected workers of 228,6009 33,485 199 small boilers being decommissioned Environmental TPMO 4,400 Contract 60,000 Contrac 4,000 Contract 15,000 Contract management training for or of tor of or of or of 6,000 879 construction and CH01 CH02 CH03 CH06 operation Environmental monitoring Implementing 85,000 12,451 during operation (/yr) Agency Implementing Contingency 150,000 22,430 Agency 75,400 Contract 482,725 Contrac 137,500 Contract 382,500 Contract Total 3,654,600 549,200 or of tor of or of or of CH01 CH02 CH03 CH06 Source:CEIA and the contractors of CH01, CH02 ,CH03 and CH06.

9 The budget is for re-employment training only

Page | 33 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

5. SUMMARY OF FIELD SURVEY AND ASSESSMENT

5.1 Monitoring plan and responsibilities

20. The environmental monitoring, including the environmental benefits monitoring, was incorporated in the project performance management system (PPMS) indicators for the Project. The TPMO, with assistance from the IAs (TUCIC, THC), is responsible for analyzing and consolidating the data through their management information system. The PPMS was designed to allow adequate flexibility to adopt remedial actions regarding project design, schedules, activities, and development impacts. TPMO, the IAs, and the loan implementation consultant are systematically collecting data on inputs and outputs of the Project components, the agreed related environmental and other indicators to be used to measure project impact.

21. One of the impact indicators in the DMF is related to environment , i.e. average of 20% was changed to respectively 15%, 30% and 10% reduction in air pollutants SO2, NO2, and PM10 from 0.068, 0.035 and 0.082 mg/m3 during heating seasons by 2020 (baseline year 2009) in Tianshui municipality. It is noted that the indicator of NOx was removed from Ambient Air Quality Standard (GB 3095-2012) by State Environmental Protection Agency (currently MEE) in January of 2000. Instead, the indicator of NO2 is applied herein. Tianshui City Annual Environmental Reports have revealed relative good air quality (but with relatively high PM10) in Tianshui City, as shown below: 3  SO2, NO2, and PM10 were 0.026, 0.027 and 0.067 mg/m respectively in Tianshui City in 2013 3  SO2, NO2, and PM10 were 0.026, 0.026 and 0.065 mg/m respectively in Tianshui City in 2014; slightly better than 2013 level 3  SO2, NO2, and PM10 were 0.032, 0.039 and 0.079 mg/m respectively in Tianshui City in 2015; worse than the past years’ level; and the PM10 minor exceeded the annual average standard limit (0.070 mg/m3 ) of Grade 2, Ambient Air Quality Standard (GB 3095-2012) 3  SO2, NO2, and PM10 were 0.027, 0.036 and 0.080 mg/m respectively in Tianshui City in 2016; mild compared to 2015 level; and the PM10 minor exceeded the annual average standard limit (0.070 mg/m3 ) of Grade 2, Ambient Air Quality Standard (GB 3095-2012) 3  SO2, NO2, and PM10 were 0.024, 0.035 and 0.087 mg/m respectively in Tianshui City in 2017; mild compared to 2016 level (2017 Gansu Provincial Annual Environmental 10 Statement ); and the PM10 minor exceeded the annual average standard limit (0.070 mg/m3 ) of Grade 2, Ambient Air Quality Standard (GB 3095-2012) 3  SO2, NO2, and PM10 were 0.019, 0.034 and 0.076 mg/m respectively in Tianshui City in the 1st half of 2018 (calculated according to data from Ministry of Ecology and Environment, while the 2018 monthly Tianshui City Environmental Statement has not been issued yet).

22. Updated background environmental quality in Tianshui based on 201511 and 201612 Tianshui City Annual Environmental Statements (2017 statement not yet disclosed) and information from Gansu Provincial Environmental Protection Department13.  Air quality. 3  SO2, NO2, and PM10 were 0.036, 0.038 and 0.075 mg/m respectively in Qinzhou District, where the heating component will serve for, in 2016;PM10 and PM2.5 were 0.123 and 0.050 mg/m3(daily average) through January to May 2018;

10 http://www.gsep.gansu.gov.cn/Department/list.jsp?urltype=tree.TreeTempUrl&wbtreeid=1076 11 http://www.tshb.gov.cn/hjzl/detail.php?n_no=12883 12 http://www.tshb.gov.cn/hjzl/detail.php?n_no=14669 13 http://www.gsep.gansu.gov.cn/Department/list.jsp?urltype=tree.TreeTempUrl&wbtreeid=1889

Page | 34 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

3  SO2, NO2, and PM10 were 0.018, 0.034 and 0.086 mg/m respectively in Maiji District, where the Maiji road network subcomponent serves for, in 2016; PM10 and PM2.5 were 0.128 and 0.060 mg/m3(daily average) through January to May 2018;

Air quality in Qinzhou District through Jan to May 2018 160 140 120

100 API(dimensionless) 80 PM10 (μg/m3) 60 PM2.5(μg/m3) 40 20 0 Jan-18 Feb-18 Mar-18 Apr-18 May-18

Air quality in Maiji District through Jan to May 2018 160 140 120

100 API(dimensionless) 80 PM10 (μg/m3) 60 PM2.5(μg/m3) 40 20 0 Jan-18 Feb-18 Mar-18 Apr-18 May-18

Figure Monthly Air Quality of Qinzhou District and Maiji District14

14 The Air Pollution Index (API) is a simple and generalized way to describe the air quality, which is used in Malaysia. It is calculated from several sets of air pollution data. It was formerly used in and Kong.

Page | 35 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

Table 5- 1 Air Quality Data during 2015/2016, 2016/2017 and 2017/2018 Heating Seasons in Qinzhou District

Month SO2 NO2 PM10 PM2.5 CO 03_8h

Nov 2015 63 48 62 34 1.7 34

Dec 2015 111 64 88 51 1.7 40

Jan 2016 104 58 77 49 3.1 65

Feb 2016 78 44 99 48 2.3 74

Mar 2016 31 41 74 33 1.2 96

Nov 2016 65 51 140 64 2.1 75

Dec 2016 84 62 165 90 2.3 74

Jan 2017 81 54 157 80 2_0 84

Feb 2017 52 42 105 59 1.4 104

Mar 2017 32 46 91 46 1.3 114

Nov 2017 43 51 115 52 1.4 71

Dec 2017 66 59 170 74 2 62

January 2018 49 50 124 71 2.1 77

February 2018 41 43 125 60 2.1 93

March 2018 17 42 116 42 0.8 119

Grade II, Ambient Air Quality Standard (GB 3095-2012) 150 80 150 75 4 160 Compliance status (Y/N) Y Y N N Y Y Data source: THC requested from TEPB

 The air quality in Tianshui City fluctuated in different seasons of 2017. Due to national wide hazy weather and winter heating season, dust pollution was worse than any other month in January 2018 and the monitoring data showed incompliance with the Environment Ambient Air Quality Standard (GB3095—2012) Grade II Standard mainly due to coal burning. More rain precipitation and plantation contributed better air quality in other seasons. This is consistent with the status in 2015 and 2016. Overall, the air quality of 305 days (or 83.6%) in 2017 met Environment Ambient Air Quality Standard (GB3095—2012) Grade II Standard.

Page | 36 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

 Surface water quality.  Wei river quality in 2016 is good. All four monitoring sections at branch and two monitoring sections at tributaries can satisfy Grade III of Environment Quality Standard of Surface Water (GB3838—2002), better than that in 2015.  Xi river, one of Wei river’s tributaries, was heavily polluted, worse than Class V mainly due to CODcr, BOD5, TP, NH3-N and LAS exceeding Grade V standard limit. Three bridges were built over these above two main rivers in Tianshui.

 Acoustic environment is relatively good (according to 2017 Gansu Provincial Annual Environmental Statement15).  The average noise (Leq) was 49.8 dB(A) in Tianshui City in 2017.  The average traffic noise of roads in the urban area was 64.4dB(A), in compliance with the standard level of 70 dB(A) in Environmental Quality Standard for Noise (GB3096-2008), Class 4a.

23. One of the outcome indicators in DMF is related to environment, i.e. heating-related carbon dioxide emissions reduced from 1,082,200 to 654,400 tons per annum by 2016 (baseline year 2009) in Tianshui municipality. Due to the change of the associated facility to the district heating component A causing heating supply area changed, the heating-related carbon dioxide emissions will be reduced from 961,589 to 559,023 tons per annum. Coal inputs per annum for Qinzhou district heating were reduced from 566,396 tons during 2012/13 heating season (base year) to 531,652 tons during 2013/14 heating season, 510,384 tons during 2016/17 heating season and 510,384 tons during 2017/18 heating season. The reduction also contributes about 24% (= (566,396-510,384)/237,120(target value)) of heating-related carbon dioxide emissions from 961,589 to 866,496 tons yearly (=(961,589 -866,496)/(961,589 -559,023)). Coal input for 2017/2018 heating season was under audit and will be provided by THC by August 2018 then reflected in the next EMR scheduled by January 2019.

24. The relevant trainings on environmental monitoring, asbestos management, and soil erosion protection are also included in the Project output and activities of the DMF. The implementation status sees the Chapter 6.

25. Environmental quality targets, sampling and analytical methods. According to the EIAs, CEIA and actual project status, the Project’s environmental management objectives are as Table 5-2 below.

15 http://www.gsep.gansu.gov.cn/Department/list.jsp?urltype=tree.TreeTempUrl&wbtreeid=1076

Page | 37 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

Table 5- 2 Environmental Quality Protection Objectives Item Type of Objective Protection Objective Location Qinzhou district heating network (Component A) Residential Tianshui Hailin Hospital 50m to the pipeline 80m area ,Institutions, Hospital of Maternal and Child Health to the pipeline Schools nearby the district Tianshui No.4 Middle School 50m to the pipeline 100m heating Pipeline Tianshui Vocational School to the pipeline 50m to the Yifu Middle School pipeline 100m to the School for Employees’ Children of Changcheng pipeline Factory Gansu Provincial Vocational School 100m to the pipeline Gansu Provincial Mechanic Industrial School Xisishili 100m to the pipeline Primary School 150m to the pipeline 50m Hailin Vocational School to the pipeline 70m to the District’s Party School pipeline 200m to the Noise and Tianshui Normal College pipeline 200m to the air Tianshuijun Primary School pipeline Residential area Hospital of Maternal and Child Health 100 m to No. 30 HES ,Institutions, Tianshui Hailin Hospital 20 m to No. 44 HES School-nearby the District’s Party’s School 50 m to No. 2 HES HESs and the Tianshui No.4 Middle School 100 m to No. 5 HES Relay Pumping Tianshui Normal College 200 m to No. 7 HES Stations Municipal Vocational College 100 m to No. 9 HES Minshan Mechanic Industrial School 50 m to No. 35 HES Municipal Party’s School 100 m to No. 40 HES School for Employees’ Children of Changcheng 200 m to No. 47 HES Factory Xinxing Kindergarten 100 m to No. 48 HES Gansu Vocational School 100 m to No. 57 HES Gansu Provincial Mechanic Industrial School 100 m to No. 58 HES Chengji road and flood control facilities (Component B) Zaoyuan Village, Yanjiahewan Village, Sunjiaping, North side of the road Xiaojia Village, Dengjia Village, Yangpo, Shuiyanzai, Residential area Air & Noise Jinjia Village, Wujia Village, Xiakou Village School SunjiapingYifu Primary School, Shuiyanzai Primary School Farmland ; Total area is 8859mu including 836.63mu farmland; Along the road ;

Earth borrow pit ; Affected vegetation, cultivated land, soil erosion and Along the road ; landscape; High filled and Affected vegetation, cultivated land, soil erosion and High filled deep excavated landscape; Ecological sectionsK1+420,K1+620 road sections Environme ;Deep excavated

nt/Soil : sections Erosion K0+860 K0+960,K1+08 0,K1+200,K6+120,K6+20 0

Alignments and structures; harmony with the Along the road Landscape ; surrounding landscape

Page | 38 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

Xi River Wulipu Quality Standard for Surface Water Environment Downstream flow along Bridge ~ entrance (Class III) (GB3838-2002) Quality Standard for the north bank of the to Wei River Main Surface Water Environment (Class III) (GB3838-2002) river. (Shuangqiao Xi Surface stream of the Wei River Bridge) Shetang Water River Wei River Bridge

Tianshui urban transport improvements (Component C)

Maiji New District Road River; Quality standard for surface water 620m right of the Water Mapaoquan Environment (Class II) (GB3838-2002) road network /Ecological Water Park Environme (Class II water Scenic zone; 125m right of the nt source protection road network zone) Affected plantation, soil erosion and landscape Along the road ; Shuangqiao Xi River Bridge Air and Residential area Residential buildings of Tianshui No.1 Normal school East side of the road Noise School Tianshui No.1 Normal school East side of the road Xi River Wulipu Quality Standard for Surface Water Jian Bridge Water Bridge ~ entrance to Environme Wei River Environment (Class III) (GB3838-2002) nt Shetang Wei River Bridge Land/farmland Vegetation, soil erosion and landscape on the 31mu Nearby the bridge Ecological occupied acquired farmland Environme Landscape Harmony with the surrounding landscape Along the line nt High filled road Affected vegetation, cultivated land, soil erosion and Along the line sections landscape Water Quality Standard for Surface Water Environment Location for the bridge Environme Wei River (Class III) (GB3838-2002) crossing the river nt Chiyu Road Residential area at the crossroad to Tianshui Jun, Two sides of the road. Residential area Majiaxiatou Village and Xishili Village and Yanxin South side of road Air & Noise School Village School for Children of Employees of No. 213 Factory Farmland Occupied farmland of 21mu Along the road

Temporary use of Affected vegetation, farmland, soil erosion and Along the road land landscape Ecological Affected vegetation, farmland, soil erosion and Along the road Environme High filled and landscape nt deep excavated road sections Coordination with the landscape along Along the line Landscape Water Nangou River Quality standard for Surface Water Environment Location of the river Environme (Class III) (GB3838-2002) bridge rehabilitation nt

26. An environmental monitoring program as part of the revised EMP is presented in Table 5-3. This program considers the scope of monitoring; monitoring parameters; locations; time and frequency; and implementing and supervising agencies. The monitoring follows the methodology provided in the national standard methods for monitoring pollutants. Other associated standards

Page | 39 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

are national environmental quality standards and pollutant emission standards. The external monitoring will be undertaken on a semi-annually basis.

Table 5- 3 Environmental Monitoring Program Who Who Subject Parameter Location Frequency Implements Supervise Construction Stage Internal monitoring: at At least four times per year Contractors, IAs TPMO domestic wastewater One sampling each day CSCs, IAs TPMO, Quality of pH, NH3-N, discharge points of all each time, twice per year TEMS TEPB work-camp CODCr,SS, oil, work-camp. domestic total coliform Compliance monitoring: wastewater at selected camps (30% of the total camps). Internal monitoring: at all Wastewater effluent sites, Contractors, IAs TPMO Quality of of the construction sites. at least four times per year CSCs, TPMO, construction pH, SS, oil Compliance monitoring: One sampling each day TEMS TEPB wastewater at selected sites (30% of each time, twice per year the total construction sites) Two locations, respectively Internal monitoring: once Contractors, TEPB, upstream and downstream per month CSCs TEMS TPMO of Shuangqiao Bridge, Compliance monitoring: TEPB, Xiakou Bridge, Shetang 1 time per day, for 3 TPMO pH, SS, DO, Wei River Bridge; consecutive days , twice Surface Water NH3-N, TP, oil, The boundary of Class-II per year including once in quality CODCr, Total water resource protection dry season and once in coliform zone, East of Weihe River; rainy season at least three locations at K7+000~K10+360 section., and at least one location at K3+650~K7+000 section. Inspection of Internal monitoring: at all dust mitigation construction sites and measures (water At least four times per nearby areas. spraying, cover year. Twice per year External monitoring: at all IAs TEPB, transport including once in dry construction sites and TPMO vehicles, etc); season and once in rainy Contractors, nearby area. Asphalt TPMO, Ambient air and Inspection season. CSCs IAs, plants, unpaved EPB of maintenance Compliance monitoring: LIEC TEMS construction road, and TEPB,TPM and condition of twice per day for 3 construction sites nearby O vehicles and consecutive days, twice schools, hospitals and construction per year. residential areas (18 equipment. TSP, points). SO2, NO2 Internal monitoring: once All 20 sensitive receivers in day time, once at night, for the component B and once per month. TEPB, C, 50 m away from Compliance monitoring: Contractors, TPMO Noise Leq boundary of the twice a year: a day each CSCs TEMS TEPB, construction sites; 3 time and two samples each TPMO sensitive receivers for the day, once during daytime, component A. once during nighttime. Quantity of Internal monitoring: IAs, Soil erosion erosion and Radom check after Contractors, Borrow pit and spoil sites. TPMO, (a) environmental rainstorm (rainfall > CSCs LIEC and ecologic 50mm), monthly,

Page | 40 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

Who Who Subject Parameter Location Frequency Implements Supervise External monitoring: LSMI TPMO, twice a year; and once TEPB, after completion of TWRB constructions. Slope stability, All subgrade slope, Internal monitoring: Contractors, IAs TPMO, vegetation retaining twice a year. CSCs, LIEC survival and walls, converts, underpass LSMI TPMO, coverage rate, and compacted trenches. TEPB, topsoil stockpile, TWRB compacted External monitoring: pipeline once a year, and once after trenches, and completion of construction. rehabilitate construction sites. Compensatory Disposal sites, borrow pit External monitoring: LSMI TPMO, plantings, and temporary construction random spot check, and TEPB, Revegetation of occupied lands. once after completion of TWRB borrow pit, constructions, at least spoil disposal four times per year. sites and construction sites. Asbestos and Demolishing 32 small External monitoring: GDWDC; TPMO, airborne boilers where ACM have clearance sampling after qualified TEPB, IAs asbestos in been identified out of 194 completion of asbestos environment small boilers during rehabilitation works monitoring asbestos risk assessment following ISO/FDIS institute Asbestos and 16000-7: Indoor air – ACM Visual inspection and Part 7: Sampling sampling of strategy for airborne determination of asbestos airborne asbestos fiber concentrations Health status, Construction sites and Internal monitoring: Contractors, IAs TPMO hygiene status, work camps. monthly. CSCs THB, TPMO, Occupational availability of External monitoring: TPMO TEPB, health and clean water, once a year. THB safety emergency response plans. Compliance with The CHP and the Review of compliance TPMO, IA ADB, Associated approved EIAs transmission monitoring reports of TEPB facilities and the EMPs. tunnel/pipeline. associated facilities.

Operation Compliance monitoring: Four times per year in Jan., TEMS TEMS TPMO, All 17 sensitive locations Apr., Jul. and Oct. (once in TEPB along the roads, and daytime and once at night). TPMO, nearby the bridges Once per heating season. TEPB Compliance monitoring: 30% of the 76 HESs, 5m Noise Leq from the wall of the HESs Compliance monitoring: surrounding the dispatching center, 5m from the pump houses.

Page | 41 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

Who Who Subject Parameter Location Frequency Implements Supervise Internal monitoring: Once a month. Twice per IA TEMS TPMO, discharge points of the heating season. TEPB TDS, pH, CL - water softening equipment TEPB, IA, HES Hardness, CL -, in al HESs. TPMO wastewater pH, sulfate, Compliance monitoring: carbonate. discharge points of the water softening equipment in 30% of 76 HESs. Compliance monitoring: Once per heating season. TEMS TEPB, IA, Domestic pH, SS, oil, discharge points of the wastewater CODcr. relay pumping station and 10% of the HESs. Internal monitoring: Twice per heating season. IA, TPMO, Relay pumping station and TEPB Collection and HESs. Solid waste disposal (b) procedures for solid waste. Compliance monitoring: Once per heating season. TEMS TEPB, IA, Relay pumping station and TPMO HESs. Green areas along Chengji Once a year. IAs, MFMB TEPB, Road and the bridges TPMO Inspect areas, trees on two sides TWRB, Vegetation vegetation of roads; vegetation along survival and embankment, recovered coverage rate. pipeline trenches, grass on retaining walls. Vehicle All of the roads and Morning and afternoon IA, TTMA numbers–road bridges. rush hours, once a year. MFMS Traffic flow (b) use (against predictions). Hydrological stations Hydrology: Daily for Tianshui and TWRB upstream and downstream hydrological stations; River Beidao Hydrology of Xi river embankment, 2 morphology, sediment Hydrological (water level, sites along Xi River transport: during and after stations Flood control water flow), river embankment identified at extreme river flows, at least morphology, PPTA stage,and additional twice a year. sediment sites in the SEPP for the transport new heating source plant and associated pipelines. Northern Mountain along Xi Automated system for TLRB TLRB, River embankment rainfall, noise, and rock TEPB Rainfall, noise, particularly, Yangpo and deformation. earth cracks, Yanjiahe. . Mudslide rock deformation Inspection for earth cracks, control (b) and movement, rock deformation, integrity integrity of of drainage and culvert drainage and system; monthly during wet culvert system season.

The CHP/ new heating Review of environmental TPMO, IA, ADB, Associated Compliance with source plant and the monitoring reports of TEPB facilities approved EIAs transmission associated facilities. and EMPs. tunnel/pipeline. ADB = Asia Development BANK, BOD5 = 5-day biochemical oxygen demand, Cl- = chloride, CODcr = chemical oxygen demand, CSC = Construction Supervision Company, DO= dissolved oxygen, Leq = equivalent continuous sound pressure level (dB), LSMI = licensed soil erosion institute, MFMB = Municipal Facilities Management Bureau, NH3-N = Ammonia Nitrogen, NOx = nitrogen oxides, SO2 = sulfur dioxides, SS = suspended solids, TDS = total dissolved solids, TEMS = Tianshui Environmental Monitoring Station.TEPB = Tianshui Environmental Protection Bureau, TLRB = Tianshui Land Resource Bureau, TP = total phosphorus, TSP = total suspended particle, TWRB = Tianshui Water Resource Bureau, yr = year。

27. Environmental Monitoring Sampling Arrangements. According to the environmental protection targets for sensitive receivers and possible major environmental impacts by construction

Page | 42 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report specified in the EIAs and CEIA, the EMP updated in May 2015 for different components under the Project, along with the actual project progress, field survey and environmental monitoring for component A have been conducted by Lanzhou Yitong Environmental Monitoring Company (LZYT) during this reporting period. The work scope for the external environment monitoring of the Project includes: a) For the component A during construction period, the locations and time of monitoring is determined according to the actual construction progress, activities and routes; and b) For the components B and C under operation, as the operational monitoring was undertaken in 2016, a project completion environmental monitoring was suggested during the April and June 2018 site visits by the LIEC while no monitoring was undertaken during this reporting period.

28. Based on the current project progress, the detailed sampling arrangements at this stage are shown in the below Table 5-4.

Table 5- 4 Environmental Monitoring Sampling Arrangements

Subject Parameter Location Time &Frequency

All 17 sensitive receivers for once per day for 3 the component B and C, 50 consecutive days, twice Air quality TSP, SO2, NO2 m away from boundary of per year. the construction sites All 17 sensitive receivers for twice a year: twice a day each the component B and C, 50 time ,once during m away from boundary of daytime, once during Acoustic Leq(dB(A)) the construction sites nighttime. environment

Quantity of erosion and Borrow pit and spoil sites. twice a year; and once environmental and ecologic after completion of restoration constructions. Slope stability, vegetation All sub-grade slope, retaining once a year, and once survival and coverage rate, walls, culverts, underpass after completion of topsoil stockpile, and compacted trenches construction. compacted Soil erosion pipeline trenches, and rehabilitate construction sites. Compensatory plantings, Disposal sites, borrow pit random spot check, at least Re-vegetation of borrow and temporary construction four times per year, and pit, occupied lands. once after completion of spoil disposal sites and constructions construction sites. Health status, hygiene Construction sites and work camps. Once per year and covered in Occupational status, availability of clean the internal monitoring. health and water, emergency safety response plans.

29. Standard monitoring methods: Table 5-5 shows the standard monitoring methods, detection limits, and the standard code for each of the monitoring parameters.

Page | 43 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

Table 5- 5 Standard Monitoring Methods of Ambient Air, Noise and Water Monitoring Detection Media Method (Standard No.) Standard Limit Parameter Limit TSP (mg/m3) Gravimetric (GB/T15432-1995) 0.001 0.30 Ambient air—Determination of sulfur

3 dioxide —Formaldehyde absorbing- SO2 (mg/m ) 0.005 0.15 pararosaniline spectrophotometry Air (HJ 482-2009) Ambient air—Determination of sulfur dioxide —Formaldehyde absorbing- 3 NO2 (mg/m ) pararosaniline spectrophotometry (HJ 0.003 0.12 482-2009) Equivalent Environmental quality standard for 60 (day)/ Noise Continuous A Sound 0.5 noise (GB3096-2008) 50 (night) (Leq)

Soil See Paras. 36 to 44 of this Chapter 5. erosion

5.2 Monitoring Results

5.2.1 Emission Discharge (Source) Monitoring Results

30. TPMO/TUCIC and the CSCs regularly and irregularly inspected the environmental status on the construction sites. Tianshui Environmental Supervision Team, the subordinate of TEPB, also periodically conducted site inspection to check compliance status. Internal environmental monitoring was carried out by the contractors. Continuous emission monitoring system (CEMS) is being installed to monitor the exhaust pollutants from the Qinzhou district heating supply plant, the associated facility to component A. The monitoring data will be collected and reported in the future EMRs. The submission status of environmental protection operation and supervision plan/manuals and internal environmental monitoring reports see the Appendix 3. The photos of some samples are shown below.

Page | 44 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

HES of the 3rd Middle School (April 2018)

Enclosed construction site

Dust control by sprinkler and tarpaulin

Site photos in June 2018 (contract CH01)

Page | 45 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

Monthly internal monitoring report (March 2018)

Dust control by tarpaulin coverage and enclosure by fencing board

Plantation protection along the section Dust control by sprinkler

Site photos in June 2018 (contract CH04)

Page | 46 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

Dust control by tarpaulin coverage and by sprinkler

Trench safety prevention and enclosed construction site by fencing board

Site photos in June 2018 (contract CH06)

Page | 47 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

31. So far, the LIEC conducted several visits to the construction sites to verify the environmental performance, respectively in October 2012, March 2013, June 2013, July 2013, September 2013, October 2013,July 2014,October 2014, April 2015, January 2016, April 2016 , July/August 2017, April/June 2018. The results of site inspection have indicated that the mitigation measures have being well implemented on site. The LIEC highlighted the importance of maintaining compliance throughout the entire project implementation. As for environmental safeguards concern, the site visits confirmed that mitigation measures during construction including dust controlling, construction site control, construction wastewater collection measures, the use of adequate safety equipment are satisfactory. The completed heating pipeline network with its associated facility (Qinzhou district heating supply plant) under component A and road & bridge under components B and C do not have any significant adverse environmental safeguards impacts. The LIEC also emphasized that the construction sites management should be strengthened to minimize the potential safety issues to nearby residents in particular at crowed public places. In addition, by considering the construction safety during rainy season, the LIEC also required the contractors to adopt adequate measures to ensure the impacts mitigation.

Safety warning boards (contract CH01, in June 2018)

Traffic control by fencing board and trench safety protection (contract CH04, in June 2018)

Enclosed construction site by fencing board Dust control by sprinkler (contract CH06, in June 2018)

Page | 48 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

32. Flood control concerns. The LIEC was informed and observed several sections of flood prevention dykes under component B - Chengji road and flood control facilities were dismantled due to other project intervention (as shown in the below layout figures). This component was completed in 2016. Considering the rainy season is coming, there had been big risks on soil erosion and dyke collapse in the near future. All construction activities affecting ADB-financed component should get approvals from all relevant government departments, in particular on soil erosion and flood control assessment. After the completion of this intervention project, the flood control standard of the restored dyke should ensure the annual probability of seasonal flooding along Chengji flood embankment reduced to 1%. In addition, due to raining season, the LIEC suggested immediate rectification, emergency response plan and to apply good O&M practices to ensure the flood safety according to Project Agreement Section 2.11(b) “TMG shall at all times operate and maintain its plants, equipment and other property relating to the Project, and from time to time, promptly as needed, make all necessary repairs and renewals thereof, all in accordance with sound administrative, financial, engineering, environmental, urban development, and maintenance and operational practice”.

Component B - Chengji road and flood control facilities

other project intervention

Relationship between the flood prevention dykes under component B and other project intervention

Page | 49 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

5.2.2 Assessment

33. Based on the aforementioned field survey and internal environmental check, there is no significant environmental impact found, the construction discharge of construction wastewater, emission of dust and acoustic environment are kept at environmentally acceptable level. In connection with flood control facilities under component B, the LIEC will further discuss this issue with PMO, TUCIC and CGCI to collect detailed information and find solutions and report the progress in future quarterly project progress reports and future EMRs.

5.2.3 Ambient Monitoring Program Results

34. In June 2016, the Shuangqiao bridge (across Xi river, one of Wei river’s tributaries) was open to traffic. According to 2016 Tianshui City Annual Environmental Statement16, Xi river was heavily polluted (at EPB’s only one regular monitoring section, about 7km downstream of the Shuangqiao bridge), worse than Class V mainly due to CODcr, BOD5, TP, NH3-N and LAS exceeding Grade V standard limit. During this reporting period, no water water quality test was conducted. The environmental monitoring data of reference project (another domestic project EIA disclosed on TEPB’s website17) also indicated TP, NH3-N and LAS exceeding Grade V standard limit. To some extent, this reflects the background pollution status of Xi river. The contribution from the Project is estimated very minor.

EPB’s regular monitoring section

Reference project

Xi River

Shuangqiao bridge

35. The data of the construction air monitoring are shown in Table 5-6 for the 6 sensitive receptors nearby the construction sites of the component A (heating pipeline network). According to the results, it is found that the daily average concentrations of TSP, SO2, NO2 meet Environment Ambient Air Quality Standard (GB3095—2012) Grade II Standard due to the appropriate mitigation measures taken.

16 http://www.tshb.gov.cn/hjzl/detail.php?n_no=14669, while the 2017 Tianshui City Annual Environmental Statement is still unavailable. 17 Integrated circuit high density packaging industrial upgrading project, http://www.tshb.gov.cn/, Oct 2017

Page | 50 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

CH5

#H16 #H15 #17 #H10 #H11 CH3 #18 #H12 #H6 #19 CH6 #20 CH4 #H13 #H14 #H5 CH2 #H1 #H7 #H8 #H9 #H4 #H2 #H3

Note: During this reporting period, six points ( #H15 to 20) nearby contracts under construction(CH5 and CH6) were monitored while the other four (#H1 to 14) were no construction nearby so without being monitored.

Page | 51 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

Table 5- 6 Summary of air quality monitoring data Monitoring results(µg/m3) No. Location Sampling date/time TSP SO2 NO2 Environment Ambient Air Quality Standard (GB3095—2012) Grade II 300 150 80 Qinzhou district heating network (component A) 3 May 2018 132 6 34 H15#(nearby Tianshui Minshan 4 May 2018 Not contract CH5 to 129 32 Technician School detected construct) 5 May 2018 95 6 32 Not 3 May 2018 151 13 detected H16#(nearby Tianshui Children 4 May 2018 Not contract CH5 to and Maternity 144 11 detected construct) Hospital 5 May 2018 Not 148 13 detected H17#(nearby 3 May 2018 185 6 43 Tianshui Party contract CH5 to 4 May 2018 155 8 33 School construct) 5 May 2018 145 7 38 H18#(nearby Tianshui 3 May 2018 112 8 22 contract CH6 to Changcheng 4 May 2018 98 7 21 construct) School 5 May 2018 102 6 23 H19#(nearby 3 May 2018 131 4 16 Tianshui Hailing contract CH6 to 4 May 2018 118 5 15 Hospital construct) 5 May 2018 111 5 14 H20#(nearby 3 May 2018 127 8 33 Tianshui Hailing contract CH6 to 4 May 2018 148 9 27 Technician school construct) 5 May 2018 128 10 30

37. Table 5-7 shows the daytime and nighttime noise monitoring results for the 6 sensitive receivers(#H4 to 9) nearby the construction sites of the component A (heating pipeline network). The noise monitored at these points has met Grade 2 requirements of Environmental Quality Standard for Noise (GB3096-2008). So the adverse impacts were limited.

Table 5- 7 Summary of acoustic quality monitoring data Monitoring results(Leq, dB(A)) No. Location Sampling date/time Daytime Nighttime Environmental Quality Standard for Noise 60 50 (GB3096-2008), Class 2(excluding 4# applicable) Qinzhou district heating network (component A)-under implementation H15#(nearby Tianshui Minshan Technician contract CH5 to 3 May 2018 55.5 42.9 School construct) H16#(nearby Tianshui Children and contract CH5 to 3 May 2018 53.9 44.4 Maternity Hospital construct) H17#(nearby contract CH5 to Tianshui Party School 3 May 2018 56.2 43.2 construct) H18#(nearby Tianshui Changcheng contract CH6 to 3 May 2018 56.2 40.1 School construct) H19#(nearby Tianshui Hailing Hospital 3 May 2018 55.7 42.6 contract CH6 to

Page | 52 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

Monitoring results(Leq, dB(A)) No. Location Sampling date/time Daytime Nighttime construct) H20#(nearby Tianshui Hailing Technician contract CH6 to 3 May 2018 56.8 49.4 school construct)

5.2.4 Assessment

38. According to the field survey and environment monitoring, the water, air and noise environment monitoring results are summarized as below:

a) According to the historical monitoring results of the water quality for the Xi River in previous reporting periods, it is found that pH and the concentration of SS, DO, NH3-N, TP, , CODCr, Total coliform at the monitoring locations meet the Environment Quality Standard of Surface Water(GB3838—2002) Grade III Standard due to the appropriate mitigation measures taken, excluding 2 river sections were monitored of COD or TP exceeding the standard of surface water quality (GB3838—2002) Grade III, merely meeting the Grade V, which possibly due to the wastewater discharged nearby Shuangqiao Xihe Bridge construction site, Xihe River. TUCIC explained that those sections’ incompliance might be contributed by the following factors: (a) the selected sections nearby are dense areas with high population and traffic flow;(b) dry season with a little rain; and (c) the adjacent domestic wastewater was directly discharged into the water bodies.

During this reporting period, no water quality test was undertaken. According to 2016 Tianshui City Annual Environmental Statement18, Xi river was heavily polluted (at EPB’s regular monitoring section, about 7km downstream of the Shuangqiao bridge), worse than Class V mainly due to CODcr, BOD5, TP, NH3-N and LAS exceeding Grade V standard limit. During this reporting period, the environmental monitoring data of reference project (another domestic project EIA disclosed on TEPB’s website19) also indicated TP, NH3-N and LAS exceeding Grade V standard limit. To some extent, this reflects the background pollution status of Xi river. The contribution from this project is estimated very minor.

b) Ambient Air Monitoring Survey- For the six monitoring points (#H15 to 20) nearby the component A (heating pipeline network) , the monitoring results can satisfy the national air quality standards. As the monitoring locations are new and quite different from other monitoring points previously monitored, no comparison analysis is undertaken.

c) Noise Monitoring Survey- The noises at those 6 sensitive points adjacent to the Project (#H15 to 20) have met the requirement of Environmental Quality Standard for Noise (GB3096-2008), Class II. As the monitoring locations are new and quite different from other monitoring points previously monitored, no comparison analysis is undertaken.

d) The onsite supervision, field sampling and laboratory testing results indicate compliance and mitigation measures were undertaken to control project-related adverse environmental impacts to an acceptable level.

18 http://www.tshb.gov.cn/hjzl/detail.php?n_no=14669 19 Integrated circuit high density packaging industrial upgrading project, http://www.tshb.gov.cn/, Oct 2017

Page | 53 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

5.2.5 Results of Soil Erosion Protection Monitoring

39. The summary of earth works in the contracts CH1/CH4/CH6 under component A is shown below.

Table 5- 8 The Summary of Balance for earth works in the Contracts CH1/Ch4/CH6 under component A (as of June 2018) Contract Excavation(m3) Fill(m3) Disposal(m3) Note:

Backfill earth was temporarily stored at an CH1 1,200 1,000 200 abandoned brick factory site; and the excessive soil was disposed to Qinzhou district heating supply plant Backfill earth was temporarily stored at an CH4 45,482 39,162 6,320 abandoned brick factory site; and the excessive soil was disposed to Qinzhou district heating supply plant Backfill earth was temporarily stored at nearby CH6 abandoned factory site; and the excessive soil was disposed to Shetang industrial park

40. For the Qinzhou district heating supply plant- the associated facility to component A, the THC engaged Yangling Shengshidadi Water and Soil Conservation Ecological Consulting company (SYWSCC) to undertake soil erosion monitoring during January 2016 to June 2017.

41. Visual inspections have been carried out for the water and soil conservation works with construction progress. And five quarterly soil erosion monitoring reports have been prepared on basis of site inspection findings and monitoring results by SYWSCC for the Qinzhou district heating supply plant- the associated facility to component A through January 2016 to June 2017.

42. Some soil erosion monitoring was undertaken through 2016~2017 for the Qinzhou district heating supply plant- the associated facility to component A, and the THC provided data in April 2018, then those data are included in this (10th) EMR.

Page | 54 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

Table 5-9 Monitoring Results of Soil Erosion through January 2016 to June 2017 (Qinzhou district heating supply plant- the associated facility to component A) Phase Area Baseline Intensity Erosion Erosion Baseline Actual Increased Erosion Area duration Erosion Erosion Amount (t) (t/km2/year) (t/km2/year) (ha) (year) Amount (t) Amount (t) Q2 of 2016 500 3000 6.31 0.25 7.89 47.33 39.44 Q3 of 2016 500 3000 6.31 0.25 7.89 45.83 38.19 Heating Q4 of 2016 500 3000 6.31 0.25 7.89 45.83 38.19 supply plant Q1 of 2017 500 3000 6.31 0.25 7.89 47.33 39.44 Q2 of 2017 500 3000 6.31 0.25 7.89 47.33 39.44 Q2 of 2016 500 3000 0.05 0.25 0.06 0.38 0.31 Q3 of 2016 500 3000 0.05 0.25 0.06 0.38 0.31 Access road Q4 of 2016 500 3000 0.05 0.25 0.06 0.38 0.31 Q1 of 2017 500 3000 0.05 0.25 0.06 0.38 0.31 Q2 of 2017 500 3000 0.05 0.25 0.06 0.15 0.09 Q2 of 2016 1500 7500 9.78 0.25 36.68 183.38 146.70 Q3 of 2016 1500 7500 9.78 0.25 36.68 183.38 146.70 Q4 of 2016 146.70 Construction Heating pipe 1500 7500 9.78 0.25 36.68 183.38 period Q1 of 2017 1500 7500 9.78 0.25 36.68 157.13 120.45 Q2 of 2017 1500 7500 9.78 0.25 36.68 157.13 120.45 Q2 of 2016 3000 9000 0.82 0.25 6.15 18.45 12.30 Q3 of 2016 3000 9000 0.82 0.25 6.15 6.15 - Water supply Q4 of 2016 3000 9000 0.82 0.25 6.15 18.45 12.30 pipe Q1 of 2017 3000 9000 0.82 0.25 6.15 - - Q2 of 2017 3000 9000 0.82 0.25 6.15 - - Q2 of 2016 1600 5600 0.19 0.25 0.76 2.66 1.90 Q3 of 2016 1600 5600 0.19 0.25 0.76 0.76 - Power Q4 of 2016 1600 5600 0.19 0.25 0.76 0.76 - supply pipe Q1 of 2017 1600 5600 0.19 0.25 0.76 - - Q2 of 2017 1600 5600 0.19 0.25 0.76 - - Construction Q2 of 2016 0 500 0.15 0.25 0.00 0.19 0.19

Page | 55 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

Phase Area Baseline Intensity Erosion Erosion Baseline Actual Increased Erosion Area duration Erosion Erosion Amount (t) (t/km2/year) (t/km2/year) (ha) (year) Amount (t) Amount (t) sites/camps Q3 of 2016 0 500 0.15 0.25 - - - Q4 of 2016 0 500 0.15 0.25 - - - Q1 of 2017 0 500 0.15 0.25 0.19 1.13 0.94 Q2 of 2017 0 500 0.15 0.25 0.19 1.13 0.94 Q2 of 2016 17.30 51.54 252.37 188.54 Q3 of 2016 17.30 51.29 236.49 185.20 Subtotal Q4 of 2016 17.30 51.22 248.72 197.50 Construction Q1 of 2017 17.30 51.72 205.95 154.23 period Q2 of 2017 17.30 51.72 205.73 154.00 Total 17.30 51.72 205.73 154.00

Page | 56 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

5.2.6 Assessment

Erosion Status in the Monitoring Periods from January 2016 to June 2017(component B - Chengji road and flood control facilities)

43. Soil loss analysis. During the second monitoring periods (January 2016 to June 2017), total erosion amount was 205.73 t with 154t increased amount and baseline erosion of 51.72t. The soil loss calculation is detailed in above Table 5-9. Besides, some recommendations were raised to improve coverage of onsite temporary spoils stockpiling site and dust control on construction access road (the following pictures are extracted from the Q2 of 2017 soil erosion monitoring report).

Page | 57 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

6. INSTITUTIONAL STRENGTHENING AND TRAINING

44. The implementation status of institutional strengthening and training program is shown as Table 6-1. In comparison with the program defined in the EMP, the institutional strengthening part is newly added.

Table 6- 1 Implementation status of Institutional Strengthening and Training Program Targeted Activities Agencies/At Contents Implementation status Next step action plan tendees Institutional Strengthening (Newly added on the basis of the EMP) Defining institutional arrangements for Fulfilled. See Para. 9 in Chapter To be strengthened in the next environmental management, monitoring, and 2. reporting period for the heating supervision; defining positions and network component. responsibilities; appointing and recruiting personnel;

Recruiting and contracting EMC for external TEMS was contracted as environmental monitoring; independent external environmental monitoring agency for components B and C (road network).

TPMO, Lanzhou Yitong Environmental Institutional IAs(TUCIC,T Monitoring Company (LZYT) was Strengthening HC), TEPB contracted as independent external environmental monitoring agency for the heating pipeline network civil works (component A).

Recruiting and contracting a LIEC for the overall CGCI (including LIEC) was Project, for environmental contracted as loan implementation management consultancy international consultant.

The project environmental Environmental Management System management system has been To be strengthened in the next Strengthening and Improvement. established. reporting period for the heating network component. TPMO,IAs(T Developing environmental management Environmental protection clauses The operational environmental Environmental UCIC, clauses and incorporating them into were developed and incorporated guidelines will be developed Management THC), construction and operational contracts into construction contracts. before components B and C Clauses and Contractors; (road network) operation. For Protocols CSCs Environmental monitoring the new civil works contracts

Page | 58 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

Targeted Activities Agencies/At Contents Implementation status Next step action plan tendees Developing/refining environmental monitoring program was prepared. of the heating network protocols component, the environmental The environmental monitoring protection clauses, program was updated to be tailor- environmental monitoring and made to the actual situations of emergency response the Project in the revised EMP procedures will be (May 2015). incorporated.

Developing environmental emergency The environmental emergency response procedures response procedures for construction activities were developed and are in place.

Training ADB‘s and PRC‘s TPMO, IAs, ADB‘s SPS and other environmental regulations; Training session was organized environmental contractors Project applicable PRC‘s environmental laws, by the LIEC in October 2012, July laws, regulations policies, standards and regulations; International 2014, Apr 2016, July 2017 and and policies environmental management practice in civil Jan 2018. constructions;

Grievance TPMO, GRM structure, responsibilities, timeframe Types Training session was organized To be strengthened in the next Redress PPCU, IAs, of grievances, eligibility assessment Gender by the LIEC in October 2012, reporting period. Mechanism GRM entry responsive GRM Reporting procedures. October 2013, July 2014, Apr points, TEPB 2015, Apr 2016, July 2017, Jan 2018 and June 2018. EMP TPMO, IAs, Responsibility and duties during construction, Training session was organized implementation contractors management and environmental protection; by the LIEC in October 2012, Task of environmental protection during October 2013, July 2014, Apr construction; 2015, Apr 2016 , July 2017 and Key environmental protection contents during Jan 2018. construction; Various environmental forms and reporting EMP improvement and corrective actions; Based on the actual case, adjustment and improvement of EMP.

Page | 59 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

Targeted Activities Agencies/At Contents Implementation status Next step action plan tendees Emergency TMG, Environmental accident, crisis and mitigation All contract-level emergency To be conducted as required. response TWRB, measures; Emergency response team, preparedness plans are TPMO, IAs, procedure and actions. Flood and mudslide documented in place (see contractors emergency planning. Flood early warning Appendix 3). system Handling and GDWDC, Relevant standards, Development of asbestos The draft asbestos risk To be strengthened in the next managing Contractors, management plan; Procedures for monitoring assessment report and asbestos reporting period. asbestos CSCs, EPB asbestos; Potential health effects related to management plan have been containing asbestos exposure, employee personal drafted. The revisions were material (ACM) protective equipment, work practices, personal finished and submitted to TEPB hygiene, medical monitoring, Respiratory for recording in Dec. 2013. protection programs and medical monitoring Training was conducted before programs; Additional safety hazards on asbestos removal, transport and disposal of abatement projects. ACM in Sept. 2017.

Environmental TPMO, IAs, Relevant technologies and good construction Fourteen site visits had been To be strengthened in the next technologies contractors practice for environmental protection. conducted and handing-on reporting period. Also soil trainings have been undertaken erosion prevention is to be Theories and TPMO, Risks for soil erosion, storm rain and other by the LIECs to cover site strengthened during future site practices on soil TWRB, IAs, geologic hazards; Mitigation measures for soil environmental protection, visits. erosion protection and erosion protection. environmentally responsible contractors construction practices, emergency response and soil erosion prevention.

A thematic training on green construction was conducted in Jan 2018 and June 2018. Environmental TPMO, Monitoring and inspection methods, data Training session was organized monitoring, TWRB, IAs, collection and processing, interpretation of data, by the LIEC in October 2012, inspection, and TEMS and reporting system. October 2013, July 2014, April reporting contractors 2015, April 2016, July 2017 and Jan 2018.

Page | 60 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

45. On 20 June 2018, the LIEC conducted course training at the THC office meeting room. Some 11 persons from the civil works and equipment installation contracts of heating source plant (the associated facility) and civil works contracts of heating pipeline network CH1/CH2/CH3/CH4/CH5/CH6, including their contractors/CSCs, attended the training meeting. The training contents cover European Union (EU), Switzerland and USA’s green construction technologies to support and encourage the knowledge and understanding of green construction practices by those implementing detailed design in the field. The participants showed strong interests also expressed the below concerns:  In this training, the benefits and goals of green construction, currently often unknowable by just reading construction documents, are clearer to the construction team, and more easily, and completely, implemented throughout the construction of the project.  The construction team learnt about all facets of green construction on the jobsite, gaining hands-on experience with pipeline excavation, backfilling, and etc. As reference, the LIEC sent the Chinese translation versions of EU’s Best environmental management practice for the building and construction sector (Final Draft, September 2012) and Managing Your Environmental Responsibilities – USEPA to the relevant constructors and CSCs. Meanwhile, the project environmental completion and Grievance Redress Mechanism GRM) related training was provided to the heating piping civil works contractors/CSCs (component A) in June 2018 during the training session.

46. In addition, the contractors of heating piping contracts CH1/CH2/CH3/CH4/CH5/CH6 conducted various environmental, health and safety training before and during construction respectively through this reporting period. All training materials and training records have been documented (see Appendix 3).

Page | 61 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

7. PUBLIC CONSULTATION AND GRIEVANCE REDRESS STATUS

47. The public consultation plan in the EMP is being implemented. Given the significance of most remaining works through the downtown area of Qinzhou district, the LIEC followed up arrangements for grievance redress mechanism and information disclosure. The implementation status of the public consultation plan is shown in the below Tables 7-1 to 7-4. Future plans in the next reporting period for public involvement during the implementation phase are developed as shown in the below Table 7-4.

Table 7-1 Information disclosure on the Qinzhou district heating source plant and heating pipeline network (component A), rendered by THC

Date Snapshots of web-based information disclosure 16 Sept. 2017, Sohu.com, informing the Qinzhou district heating source plant to be put into operation by 10 Nov 2017

16 Sept. 2017, , informing the asbestos contained materials in the demolished small boilers being properly collected, temporarily stored and disposed by designated professional team

http://www.fangwu0938.com/article/article_4073.html 3 Nov 2017, Tianshui Daily, informing the Qinzhou district heating source plant to be completed and commissioned

Page | 62 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

CH06 signboards on contract information, environmental GRM, site environmental and safety management requirements, in June 2018

Page | 63 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

Table 7-2 Questionnaire Survey during Implementation Stage

Page | 64 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

48. Assessment of public consultation results. The interviewees were overall satisfied with the project construction site environmental management performance while expected significant environmental benefits to be brought after the whole project is put into operation at end 2018. Meanwhile, the LIEC suggested enhancing GRM information disclosure to ascertain timely response and resolution given any material adverse environmental impacts to the surrounding residents.

Page | 65 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

49. THC/TUCIC assigned its deputy general manager for the overall GRM operation of Component A/B/C. And another engineer of THC/TUCIC was designated for daily operation on the GRM. In the reporting period, no compliance or grievance was received. The public consultation during June 2018 confirmed that no complaint had been received so far.

50. According to TEPB’s information for the Qinzhou district heating supply plant-associated facility to the component A, on 16 November 2017 there was a complain on heating operation noise from a nearby villager (Mr. Shi). TEPB investigated and revealed that the heating operation noise disturbance was due to the soundproof doors and windows had not been installed timely. THC has agreed to install soundproof doors and windows before commencement of next heating season to ensure compliance and minimize adverse impacts to acceptable level. The below screenshots shows the information disclosed on TEPB’s website for the complaint made by Mr. Shi and responses by TEPB.

Complain (16 Nov 2017) on TEPB’s website Reply on TEPB’s website,16 January 2018 http://www.tshb.gov.cn/html/2018/huanjingzhifaxinxi_0116/6485.html http://www.tshb.gov.cn/html/2018/xinjianhuifu_0106/6997.html

Page | 66 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

Table 7-3 Implementation Status and Future Public Consultation Plan In the Next Reporting Period

Implementation Next Step Action Organizer Approach Times Subject Participants Status Plan B. Construction (for all components) TPMO,IAs, Questionnaire At least once a Actual construction impacts, Residents within Four times To be LIEC survey, or interview year complaints, comments and construction area, respectively in strengthened in suggestions from affected and affected Nov 2014, Jul the second half of public and stakeholders; stakeholder 2017, Jan and Jun 2018. adjusting mitigation measures enterprises and 2018 by LIEC for if necessary; comments to the agencies the GRM. villagers/residents nearby the civil works contract sites.

Please see the above paras. 47 to 48.

Public workshop At least once a Adjustment of mitigation Representatives Once in Jul 2014. year measures if necessary, of residents and An environmental construction impacts, other stakeholders management comments and suggestions; workshop was comments to the GRM. undertaken to promote awareness and collect opinions from the representatives of the nearby villagers, constructors, supervisors and other major stakeholders.

C. Operation (for components B and C) Implementing Questionnaire At least once Effectiveness of mitigation Residents within Twice respectively To be agencies, survey, or interview in the first measures, impacts of project’s area of in Jul 2017 and strengthened in TPMO, LIEC years of operation, comments and influence, and Jan 2018 by LIEC the second half of operation recommendations, and representatives of for the 2018. residents and villagers/residents

Page | 67 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

Implementation Next Step Action Organizer Approach Times Subject Participants Status Plan comments to the GRM other stakeholders nearby the the components B&C.

Please see the above paras. 47 to 48.

Public workshop As needed, Effects of mitigation measures, Representatives Not applicable so based on impacts of operation, of residents and far public comments and suggestions. other stakeholders consultation

Public satisfaction Once after first Evaluation, comments and Representatives Not yet To be conducted survey year of suggestions for each of residents and in the second half operation component and other stakeholders of 2018 subcomponent.

IAs, TPMO and Press conference Once after first Evaluation of the project Experts from Not yet To be conducted TMG year of (benefits and negative various in the second half operation impacts), comments and stockholders, and of 2018 in form of suggestions during operation, local medias public satisfaction and public opinions. survey

Page | 68 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

8. KEY ENVIRONMENTAL ISSUES AND NEXT-STEP ACTION PLAN

8.1 Key Issues Identified in the last (ninth) EMR

51. No major environmental issue was identified in the last EMR.

8.2 Key Issues Identified in this (tenth) EMR

52. The domestic environmental completion audit is expected to finish by the second half of 2018.

8.3 Corrective actions taken to address key Issues Identified in the last (ninth) EMR during this reporting period

53. Not applicable.

8.4 Action Plan of Environmental Monitoring &Evaluation (M&E) In the Next Reporting Period

54. It is expected that all of the road civil works contracts will be under commissioning and heating civil works contracts will be completed and put into trial operation in the second half of 2018. The focus of environmental M&E will shift to the following five aspects: (a) emphasize soil erosion protection including vegetation restoration of construction site;; (b) enhance the implementation of EMP and mitigation measures to minimize the negative environmental impact of the contracts under construction and commissioning; (c)strengthen water, air and acoustic quality analysis and pay a close attention to the causes of incompliance and remediation measures to secure safe water supply, air quality and acoustic environment; (d) reporting; and (e) training. An action plan is defined in Table 8-1.

Page | 69 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

Table 8- 1 Action Plan for Environmental M&E in the Next Reporting Period

Time frame/ Implementation Supervision Action Description Note Frequency Agency Agency Mitigation Emphasize soil erosion The second Contractors TPMO(THC);T Focus on Measures protection of construction half of 2018 WRB;CSCs;LI feedback and site, including heating EC adjustment. network component in the Project

Enhance the The second Contractors/operato TPMO(TUCIC/ Focus on implementation of half of 2018 rs THC); TEPB; feedback and environmental CSCs; adjustment. management plan and LIEC mitigation measures to minimize the negative environmental impact of the components under construction and commissioning Internal Finish monthly internal Monthly in the Contractors/operato TPMO(THC); Focus on Monitoring monitoring reports second half of rs and/or TEPB; LIEC causes of And 2018 CSCs, incompliance Inspection and remediation measures External Inspection of procedural Irregularly; at LIEC TPMO(TUCIC/ Focus on Inspection compliance with EMP least once THC); TEPB; causes of every six incompliance months and remediation measures External Construction-related Semi- IAs with assistance TPMO; TEPB; Focus on monitoring pollution sources and annually , to be from LIEC TWRB causes of impacts on ambient submitted by incompliance environmental quality; January 2019 and remediation finish the 9th measures Environmental Monitoring Report

Public Local residents The second IAs TPMO(TUCIC/ consultatio half of 2018 THC); TEPB ns

Completion Finish domestic The second Contractors ADB; inspection acceptance procedures. half of 2018 for (under guidance TPMO; TEPB; and Prepare the ADB and assistance TUCIC; acceptanc environmental environmental from LIEC) CSSs e for performance report PCR of road finished according to ADB’s component contracts requirements

Page | 70 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

55. Work Plan For the LIEC For The Next Six Month  In the environmental completion check and acceptance for road components (B and C) scheduled by in the second half of 2018, to prepare a simple database (spreadsheet) at TPMO to record all compliance environmental monitoring data (e.g., the results of soil erosion, water, air and acoustic monitoring) and a storage system for environmental reports generated by the specialist and PMO. Ensure that TPMO understands and is able to access the spreadsheet and storage system;  To work with TPMO and IAs to identify the key environmental concerns related to the Project activities in the operation period;  To conduct field inspections to ensure the implementation of mitigation measures specified in the EMP;  To undertake training workshop and the APs/stakeholders consultation and interview;  To draft the 11th semi-annual environmental monitoring report. These will summarize the results of environmental compliance monitoring in the next six months, any compliance issues, and actions taken to resolve the issues.

Page | 71 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

9. CONCLUSION

9.1 Overall Progress of Implementation of Environmental Management Measures

56. Based on the external environmental monitoring of Gansu Tianshui Urban Infrastructure Development Project, it is found that the contractors of the 1 HES civil works and 5 heating piping civil works contracts (CH1/CH2/CH3/CH4/CH5/CH6) and another heating associated facility- Qinzhou heating source plant under construction and the roads/bridges under commission have undertaken relevant environmental mitigation measures specified in the CEIA/updated EMP and project EIA reports, and shown enough concerns on the possible negative environmental impacts due to the Project implementation.

57. The potential adverse impacts of noise, dust and wastewater generated during construction have been minimized by relevant mitigation measures and there was minor significant impact on nearby sensitive receptors. The air quality and noise monitoring show overall compliance with the requirement of the national standards.

9.2 Problems Identified and Actions Recommended

58. Based on the site survey and monitoring, the relevant suggestions and recommendations are listed as below. Notably, some recommendations are raised to strengthen flood control facilities maintenance (Section 5.2.1), enhance GRM (Chapter 7), and improve coverage of onsite temporary spoils stockpiling site and dust control on construction access road(Section 5.2.6).

Table 9-1 Suggestions and Recommendations

Implementati Supervision No. Suggestions And Recommendations Time Framework on Agencies Agencies a) More efforts are required on public utility Every civil works Contractors TPMO(TUCIC, protection and demolition of small boilers contract THC); TEPB; during heating network component implementation period CSCs; implementation, and acoustic quality during (from starting to LIEC roads and bridges operation. ending). b) For these contracts to start construction, Mobilization stage of Contractors; TPMO(TUCIC, environmental management system should every civil works CSCs THC); be developed prior to implementation, along contract package. TEPB; with good practices of environment, healthy, Every civil works LIEC and safety (EHS) for training. It is necessary contract to strengthen the internal monitoring and implementation supervision, and take necessary corrective period(from starting to action if required. ending) c) Environmental responsibilities should be Mobilization stage of Contractors; TEPB more clearly defined and more tailor-made every civil works CSCs; training should be provided for the all contract package. TUCIC/THC; relevant environmental management Every civil works LIEC agencies to improve the environmental contract management, monitoring and reporting implementation during construction period. period(from starting to ending) d) The contractors should strengthen the Every civil works Contractors TPMO(TUCIC, construction supervision and management, contract THC); CSCs; and minimize the negative impact on the implementation TEPB; environment. Meanwhile, it is necessary to period(from starting to LIEC strengthen the environmental management ending)

Page | 72 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

Implementati Supervision No. Suggestions And Recommendations Time Framework on Agencies Agencies training for the construction workers, and enhance their awareness of environment protection so as to ensure smooth implementation of the EMP. e) Environmental protection costs incurred Every civil works Contractors TPMO(TUCIC, should be identified and special costs for contract THC); CSCs; appropriate environmental protection and implementation TEPB; pollution prevention should be guaranteed. period(from starting to LIEC ending)

10 APPENDICES

1. Applicable Environmental Standards

2. Summary of Potential Environmental Impacts and the Mitigation Measures Implemented

3. Submission Status Of Environmental Protection Operation And Supervision Plan/Manuals And Internal Environmental Monitoring Reports

4. Certificate of Onsite Sampling and Laboratory Testing Agency (Lanzhou Yitong Monitoring Company) and Scanned Copy of Testing Data

Page | 73 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

APPENDIX 1 APPLICABLE ENVIRONMENTAL STANDARDS

Page | 74 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

(1) Ambient Air

Table A1-1 Ambient Air Quality Standard (Class II) Unit: mg/m3

Standard No. Item Daily Average

1 SO2 0.15

GB3095-2012 2 TSP 0.30

3 NO2 0.08

(2) Acoustic Environment

Table A1-2 Acoustic Environment Quality Standard (GB3096-2008), Unit: Leq[dB(A)] Noise Limit Category Range of Usage Daytime Nighttime

Regions dominated by residence, cultural and educational Class I 55 45 organizations

Class II Residential, commercial and industrial confounding area 60 50

Class 4a On both sides of the urban trunk road 70 55

Table A1-3 Emission Standard Of Environment Noise For Boundary Of Construction Site (GB 12523-2011), Unit: Leq[dB(A)]

Daytime Nighttime

<70 <55

Page | 75 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

Appendix 2 Table A2- 1 Summary of Potential Environmental Impacts and the Mitigation Measures Implemented20 The following performance rating scale is the standard rating scale for the current cycle.

Level 5(BP) : Sets a standard for best construction environmental management practices Performance far exceeded expectations due to exceptionally high quality of work performed in all essential areas of responsibility, resulting in an overall quality of work that was superior; and either 1) included the completion of a major goal of project EMP, or 2) made an exceptional or unique contribution in support of local environmental improvement objectives. This rating is achievable by any construction contracts though given infrequently.

Level 4(IC): Shows innovation and creativity Performance consistently exceeded expectations in all essential areas of responsibility, and the quality of work overall was excellent. Semi-annual goals were met.

Level 3 (ME): Satisfactory Performance consistently met expectations in all essential areas of responsibility, at times possibly exceeding expectations, and the quality of work overall was very good. The most critical annual goals were met.

Level 2 (I): Partially complete Performance did not consistently meet expectations – performance failed to meet expectations in one or more essential areas of responsibility, and/or one or more of the most critical goals of project EMP were not met. A corrective action plan to improve performance must be attached, including timelines, and monitored to measure progress.

Level 1 (U): Unsatisfactory Performance was consistently below expectations in most essential areas of responsibility, and/or reasonable progress toward critical goals of project EMP was not made. Significant improvement is needed in one or more important areas. A plan to correct performance, including timelines, must be outlined and monitored to measure progress. Represented contract constructors should use the current forms approved by their respective IAs.

20

Page | 76 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

Potential Rating of Implementation status and compliance with EMP Item Impacts Mitigation Measures and/or Safeguards (see above rating scale from 1-5) for each civil works contract and Issues CH01 CH02 CH03 CH04 CH05 CH06 CH07 Weighted average rating 3.95 3.95 3.95 3.95 3.95 3.95 Not yet due A. Preconstruction Phase (only component A applicable during this reporting period) Construction Bidding and Incorporate environmental mitigation measures 4 4 4 4 4 4 n/a Preparation contract indicated in the EIAs and the EMP into bidding documents/ documents and construction contracts for all Environmental subcomponents. LIEC, or invited environment management specialists and/or officials from TEPB provide training training/ Confirm on construction environmental management and borrow pit, spoil implementation and supervision of environmental disposal sites mitigation measures to contractors and construction /Environmental supervision companies. Confirm approved spoil operation and disposal sites and borrow pit location. Prepare an supervision environmental operation and supervision plan/manual Manual/Engage for all construction activities. Prepare an internal ment of internal environmental monitoring plan to meet the requirements environmental in the EIAs, the CEIA and the EMP. monitoring Engagement of Prepare a compliance environmental monitoring plan to 4 4 4 4 4 4 n/a compliance meet the requirements in the EIAs, the CEIA and the environmental EMP. Establish a Project Public Complaints Unit monitoring/ (PPCU) in TPMO‘s office; provide training for PPCU Establishment of members and GRM access points; Disclose the operational PPCU‘s phone number, fax, address, and email to the GRM public on TMG‘s website and on information boards at each construction site. B. Construction Phase

Page | 77 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

Soil erosion Minimize active open excavation areas during trenching 4 4 4 4 4 4 n/a due to activities and use appropriate compaction techniques construction for pipe trenches construction; Provide temporary activities detention ponds or containment to control silt runoff; Construct intercepting ditches and drains to prevent runoff entering construction sites, and divert runoff from sites to existing drainage; Strip and stockpile topsoil, cover or seed temporary soil stockpiles; Limit construction and material handling during periods of rain and high winds; During road and bridge construction, maintaining slope stability at cut faces by implementing erosion protection measures such as terraces and silt barriers; Stabilize all cut slopes, embankments, and other erosion-prone working area Soil & while work is going on. All earthwork disturbance areas Geology will be stabilized within 30 days after earthwork is ceased at the site; Pay sufficient attention to drainage after land recovery to prevent water accumulation. Adopt appropriate construction techniques, such as sinking wells and cofferdams; Properly slope or re- vegetate disturbed surfaces, such as compacted pipeline trenches and cut banks; Protect slopes on both sides of bridges and culverts to prevent soil and water loss and to keep the ecosystem on balance; Plant grass to protect slopes, especially on sandy soil and terraced slopes; Appropriately set up temporary construction camps and storage areas to minimize the land area required and impact on soil erosion; and Conduct soil erosion monitoring by a qualified unit based on the SEPP, to be submitted to TPMO, TEPB and the TWRB.

Page | 78 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

Borrow pit and Confirm sites for borrow earth and spoil disposal after 4 4 4 4 4 4 n/a spoil disposal consulting with the TEPB and TWRB before sites constructions; Implement a strict borrow pit and disposal sites rehabilitation and restoration program during construction; Apply temporary soil stabilization, such as covering with plastic film, geo-textile, or similar materials if permanent protection works cannot be carried out in time during the rainy season; Apply erosion control blankets and check dams to control erosion in concentrated flow paths; Apply permanent soil stabilization measures, such as vegetation and re- vegetation when closing borrow site and its temporary access roads. Rehabilitate and return the borrow pit and spoil disposal sites to forest land, to sufficiently restore the ecological balance. Conduct project completion audit to confirm that the borrow pit was rehabilitated in accordance with the approved rehabilitation plan and government regulations; held contractors liable in case of non-compliance. Soil Properly store petroleum products, hazardous materials 4 4 4 4 4 4 n/a contamination and wastes on impermeable surfaces in secure, covered areas, and use best management practices to avoid soil contamination; Remove all construction wastes from the site to approved waste disposal sites or landfills; and Provide spill cleanup measures and equipment at each construction site and conduct training to contractors‘ employees in emergency spill response procedures. Water Siltation of Collect wastewaters from culverts and underpass 4 4 4 4 4 4 n/a Quality water bodies constructions in sediment tanks, retention ponds, or filter tanks to remove silts and oil, reuse for the tunneling operations; Bridge construction: Pump slurry to shore and dispose of the cutting materials properly to reduce the disturbance of sediments and the residual impact to water quality leading to short-term increase in SS concentrations in the rivers immediately downstream from the bridge construction sites.

Page | 79 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

Wastewater Equip all construction drainage and areas for washing 4 4 4 4 4 4 n/a from construction equipment with water collection basins and construction sediment traps; Install appropriate septic disposal sites and systems at construction camps along with proper camps maintenance protocols; Backwash Construct an equalization and sedimentation tank in 4 Not Not Not Not Not Not yet water from each HES for pH adjustment. applicabl applicabl applicabl applicabl applicabl due HESs e e e e e Wastes Dumping of construction solid waste and garbage into 4 4 4 4 4 4 n/a water bodies shall be prohibited; and Dispose solid waste in consultation with TEPB to protect both surface water and groundwater sources. Handling of Prepare and conduct a construction material (including 4 4 4 4 4 4 n/a chemicals chemicals) handling protocol; and Store all toxic, hazardous, or harmful construction materials including petroleum products on an impermeable surface and manage these materials in such a way as to prevent spillage or leakage to nearby water bodies.

Page | 80 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

Acoustic Noise Ensure noise levels from equipment and machinery 4 4 4 4 4 4 n/a Environme generating conform to PRC standard of GB12523-90 (Noise limits nt from for Construction Site), properly maintain machinery to construction minimize noise; Apply noise reduction devices or activities methods where piling equipment is operating within 500 m of sensitive sites, such as schools, hospitals and residential areas; Locate sites for rock crushing, concrete-mixing, and similar activities > 1 km away from the sensitive areas; To reduce noise at night, restrict the operation of machinery generating high levels of noise, such as piling, compacting and movement of heavy vehicles along urban and village roads, between 20:00 and 06:00 the next day in accordance with PRC regulations; Reach agreements with nearby schools and residents regarding heavy machinery work to avoid any unnecessary disturbances. If disturbance cannot be avoided, compensate affected residents; Place temporary hoardings or noise barriers around noise sources during construction, if necessary; Monitor noise at the sensitive areas at regular intervals (refer to monitoring plan of the EMP). If noise standards are exceeded, equipment and construction conditions shall be checked, and mitigation measures shall be implemented to rectify the situation; Conduct weekly interviews with residents living adjacent to construction sites to identify community complaints about noise, and seek suggestions from community members to reduce noise annoyance; and Community suggestions will be used to adjust work hours of noise-generating machinery. Vibration Vibration Prohibition of, pipeline trench compacting, pilling and 4 4 4 4 4 4 n/a generating by road roller operation at night. compacting and rolling

Page | 81 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

Ambient Dust Spray water on construction sites and material handling 4 4 4 4 4 4 n/a Air Generating by routes where fugitive dust is generated once a day; Pay construction particular attention to dust suppression near sensitive activities receptors such as schools, hospitals, or residential areas; Store construction materials in appropriate places and cover, seed, or spray them to minimize fugitive dust; and Cover vehicles carrying soil, sand, or other fine materials to and from the construction sites. Air emission Locate asphalt plants and mixers as far away as 4 4 4 4 4 4 n/a from vehicles possible (at least 200 m downwind) from the nearest and residential areas and other sensitive receptors; Ensure construction vehicle emissions are in compliance with PRC equipment standards of GB18352-2005, GB17691-2005, GB11340-2005, GB2847-2005, and GB18285-2005; Initiate a regular inspection and certification system for vehicle and equipment emission; and Maintain vehicles and construction machinery to a high standard to ensure efficient running and fuel-burning and compliance with emission standards. Solid Solid waste Licensed demolition companies shall be contracted to 4 4 4 4 4 4 n/a Waste generated by carry out demolition of small boilers, houses and demolishing pedestrian bridge; Maximize reuse/recycling of small boilers deconstruction wastes generated during the demolition houses, (e.g. iron, bricks, windows, doors, steel bars etc., sold pedestrian to local waste recycling stations), dispose other bridge demolition debris on municipal solid waste landfills or special construction and demolition debris landfills, subject to approval by TEPB; and Contractors shall ensure proper collection, storage, and disposal of demolishing wastes, and multi-compartment collection bins shall be provided to facilitate the reuse, recycling and composting of solid waste.

Page | 82 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

Asbestos Identify, properly label and pack asbestos as well as n/a 4 n/a n/a impact during demolishing debris contaminated with asbestos during THC informed that 12 boilers involved with demolishing demolishing small boilers, and transport them in specific ACM. Among of them, 5 boilers are outside small boilers closed vehicles to the secured landfill of GDWDC in of THC jurisdiction, so local EPB will handle houses Lanzhou in accordance with the World Bank‘s EHS them, For the remaining 7 boilers, on 11 Guideline 21 . Proper protective clothing and specific Sept. 2017, THC engaged a licensed equipment shall be provided by GDWDC to its trained institute who safely removed, transported team and demolishing contractors‘ workers involving and finally disposed asbestos containing demolishing and disposal of asbestos during materials (ACM) at Gansu province deconstruction of the small boilers. Train workers on the hazardous waste disposal center in hazards, danger and procedures of working in areas compliance with the asbestos management contaminated with asbestos. plan, under supervision by TEPB. The relevant information is being collected and will be reported in details in next (11th) EMR, to be submitted to the ADB by January 2019. Solid waste Establish temporary storage for construction wastes 4 4 4 4 4 4 n/a generated by away from water bodies and public areas, regularly haul construction to a suitable landfill or designated dumping site; Provide activities appropriate waste storage containers, reach agreements with local villages or residential communities for waste disposal, where appropriate, through the local facilities; Hire a contractor with the proper credentials to remove all wastes from sites to approved waste disposal sites according to the appropriate standards; Proper remove and dispose residual materials, wastes and contaminated soils that remain on the ground after construction. Any planned paving or vegetating of the area should be done as soon as the materials are removed to stabilize the soil; and prohibit burning of waste.

21The World Bank EHS (Good Practice Note: Asbestos: Occupational and Community Health Issues);

Page | 83 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

Health and Construction Ensure that all employees of contractors are properly 4 4 4 4 4 4 n/a Safety site safety trained to respond safely to an emergency involving a (including hazardous material or petroleum spill and other emergency accidents; Prepare and conduct a construction safety preparedness plan, and establish an emergency team; Implement and response) safety measures around the construction sites to protect the public, including warning signs to alert the public to potential safety hazards, and barriers to prevent public access to construction sites; Store petroleum products, hazardous materials, and wastes appropriately, on an impermeable surface in a secure, covered area, and separating stored hazardous waste from non-hazardous waste; Minimize the storage of petroleum products and hazardous, reactive, ignitable, and flammable materials on-site, and conducting regular inspections; Ensure fuel supplier is properly licensed and follows the proper protocol for transferring fuel in compliance with standards of JT 3145-88; Carry out vehicle, machinery, and equipment maintenance and refueling so that spilled materials do not pollute the local environment; Locate fuel storage and refilling areas at least 300 m from drainage structures and important water bodies; and Provide oil traps for service and parking areas. Work camp Require contractors to safeguard environmental 4 4 4 4 4 4 n/a health and hygiene in the construction camps, including provision hygiene of high quality water supply and sanitation; Ensure all construction sites provide the necessary personal protective equipment and other resources to create a safe working environment; and Require construction site operations to comply with the PRC State Administration of Worker Safety Laws and Regulations.

Page | 84 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

Flora and Protection of Preserve existing vegetation where no construction 4 4 4 4 4 4 n/a Fauna vegetation, re- activity is planned or temporarily preserve vegetation vegetation of where activity is planned for a later date; Planting trees disturbed and grass based on the detailed designs; Properly areas; planting compact and re-vegetate the DH pipeline trenches after and construction; Protect existing trees and grassland compensator y during road, bridge and pipeline construction, if a tree planting trees has to be removed or an area of grassland disturbed, and grass replant trees and re-vegetate the area after construction; Remove trees or shrubs only as a last resort if they impinge directly on the permanent works or approved necessary temporary works; and In compliance with the PRC‘s forestry law, undertake compensatory planting of an equivalent or larger area of affected trees and vegetation. Fauna No endangered species were identified in the Project 4 4 4 4 4 4 n/a area; Take special precautions during and after construction for the protection of small animals, reptiles, and of common species that live in the vegetated roadside areas, medians, embankments and slopes, inner areas of bridges, and especially the green areas and roadside parks. Physical Establish and conduct chance-find procedures for Not Not Not Not Not Not Not Cultural physical cultural resources; Cultural heritage sites will applicabl applicabl applicabl applicabl applicabl applicabl applicabl Resources be preserved where identified. Strictly in accordance e e e e e e e with PRC regulations, no person shall destroy, damage, deface, conceal or otherwise interfere with the relic; and If a new site is unearthed, work should be stopped immediately and TCB and the PMO promptly notified, and construction will resume only after a thorough investigation and with the permission of the appropriate authority.

Page | 85 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

Social and Impact to traffic Carry out approved traffic control and operation plans, 3 3 3 3 3 3 n/a Economy and public (approved by Tianshui traffic police brigade), which facilities, shall include provisions for diverting or scheduling community construction traffic to avoid morning and afternoon peak safety traffic hours, regulating traffic at road crossings, building interim roads, selecting transport routes to reduce disturbance to regular traffic. Reinstating roads, and opening them to traffic as soon as the construction is completed; Carefully and clearly mark pedestrian-safe access routes; If school children are in the vicinity, include traffic safety personnel to direct traffic during school hours; Maintain a supply for traffic signs (including paint, easel, sign material, etc.), road marking, and guard rails to maintain pedestrian safety during construction; Plan construction activities so as to minimize disturbances to utility services. Temporary land occupation shall be planned well ahead of construction to minimize its impact. Land shall be restored to its original condition after construction; and Conduct three-dimensional underground detection before construction to avoid damage of underground facilities, potential accidents, excessive costs, and construction delays.

Resettlement Compensate all affected persons and resettle in a See See See See See See See timely and adequate manner, in accordance with the resettle resettle resettle resettle resettle resettle resettle resettlement plan; Conduct resettlement site ment ment ment ment ment ment ment environmental protection measures including garbage monitori monitori monitori monitori monitori monitori monitori disposal, water supply and sanitation, and monitoring of ng ng ng ng ng ng ng drinking water, air, noise and community health. report report report report report report report

Page | 86 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

Potential Rating of Implementation status and compliance with EMP Item Impacts Mitigation Measures and/or Safeguards (see above rating scale from 1-5) for each civil works contract and Issues

C. Operation Phase (Components B, C (Urban Transportation Improvement and Flood Control Facility) - under commissioning, applicable during this reporting period)

C01 C02 C03 C04 C05 C06 C07 C08 C09 Weighted average rating 4 4 4 4 4 4 4 4 4 Ambient Air Vehicle Include provisions for motor vehicle emission control in 4 4 4 4 4 4 4 4 4 emission the bidding documents for all new gas stations in the City including gasoline and diesel. Contractors that include clean energy stations in their bids will be given favorable consideration and preference if all other conditions are equal among the bidders; Include similar provisions in tendering documents for the procurement of new buses by the municipal bus companies. Bidders (bus suppliers) who propose buses with clean fuels and who have installed more advanced emission control systems will be given preferential consideration, assuming all other conditions are equal. Bus manufacturers that cannot meet the new emission control standards will not be allowed to bid; All vehicles must pass an emission test as part of the annual vehicle safety and environmental protection inspection. Vehicles that cannot meet the standards on the basis of current regulations and environmental considerations shall be upgraded or taken out of traffic; Air pollution compliance monitoring will be undertaken by TEMS in accordance with the monitoring program in the EMP; and Set up speed-limit signs and adopt corresponding measures at places where the actual values measured for air pollution exceed the standard. Surface & Pollution from Routinely collect and properly dispose litter and debris 4 4 4 4 4 4 4 4 4 Ground storm water from sidewalks, driveways, and parking lots, especially

Page | 87 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

Water runoff near Wei River and Xi River and storm drains; Place garbage bins and containers along the road network; and Prohibit the construction of car washing and gas stations near rivers and drainage channels. Dangerous or Warning signs to drivers and emergency phone 4 4 4 4 4 4 4 4 4 toxic spills numbers shall be posted along the bridges; resulting from road traffic The environmental emergency response plan and an accidents emergency response team under TEPB shall be established before the roads/bridges open to traffic; Spillage must be immediately reported to TEPB for proper action and response to minimize negative impact to the environment; Prohibit vehicles transporting dangerous goods from parking near sensitive receivers along the roads, where “No Parking” signs should be put up to avoid traffic accidents; and Promoting compliance through awareness building and education for relevant transport enterprises and drivers. Acoustic Traffic noise Construct noise barriers or noise insulation windows at 4 4 4 4 4 4 4 4 4 Environmen sites where noise levels are monitored exceed PRC t standards by more than 3 dB; Set up no-honking signs along new /upgraded roads; No new schools, hospitals or other sensitive facilities will be allowed to be built within 200 m from the central line of the roads to prevent noise impacts to these facilities in the future. Flora Vegetation Properly maintain all vegetation cover. 4 4 4 4 4 4 4 4 4 Soil Soil erosion Inspect erosion protection measures including seeded 4 4 4 4 4 4 4 4 4 or stabilized slopes, drainage structures and retaining walls at least twice during the first year of the roads’ operation to ensure that they are maintained properly and are functioning as designed; and

Page | 88 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

Properly maintain newly planted trees along the roads, especially during the first two years operation of the Project. Geologic Flood control Check integrity of the embankment, and clean the 4 4 4 4 4 4 4 4 4 Hazard culverts and drainage pipes and other mudslide and flood control system etc.

Review and adapt the existing flood early warning system and flood emergency response mechanism.

Adjust the existing monitoring system for river hydrology, morphology and sediment transport along the Chengji road and Xi river embankment. Landslides A mudslide monitoring system will be installed in the 4 4 4 4 4 4 4 4 4 and mudslides Beishan Mountain to record rainfall, surface water flow, unusual noise, earth cracks, deformation and movement. The early warning and emergency response plan will be reviewed and adjusted with the necessary institutional support to respond to any possible mudslides. Ensure all slope stabilization sites will be inspected regularly. If signs of failure are discovered, repair will be immediately initiated. Inspect and clean all road culverts and drainage pipes from debris, repair damages. Environmen Insufficient Conduct training for environmental management; 4 4 4 4 4 4 4 4 4 t environmental Managemen management Refine and maintain a GRM. t capacity

Page | 89 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

Appendix 3 Table A3- 1 Submission Status Of Environmental Protection Operation And Supervision Plan/Manuals And Internal Environmental Monitoring Reports (From April 2016 to June 2018) Civil Environmental Protection/Flood Internal Monthly Environmental Works Prevention/Construction safety Operation And Monitoring Report Contract Constructor CSC Supervision Plan/Manuals Package Submission Date Note Submission Date Note No. CH1 Gansu Shanghai 25 October 2017 Safety training 31 October 2017 October 2017 provincial Fuda regulations/safety inspection 30 November 2017 November 2017 installation Construction and management 31 March 2018 March 2018 company supervision regulations 30 April 2018 April 2018 company 30 October 2017 31 May 2018 May 2018 Key risk sources 30 June 2018 June 2018 identification matrix/ List of key risk sources 30 October 2017 Dust control plan October 2017 Fire prevention plan 10 May 2017 Fire facilities distribution records

CH2 Gansu Shanghai 15 March 2017 Trench excavation and 25 May 2016 May 2016 provincial Fuda support plan 25 June 2016 June 2016 installation Construction 25 July 2016 July 2016 company supervision 28 April 2016 Emergency response plan 25 August 2016 August 2016 company 25 September 2016 September 2016 30 April 2016 Safeguards and dust control 25 October 2016 October 2016 plan 25 November 2016 November 2016 25 December 2016 December 2016 April 2016 Sample safety knowledge 25 January 2017 January 2017 examination prior to 25 March 2017 March 2017 construction (for construction 25 April 2017 April 2017 workers) 25 May 2017 May 2017 25 June 2017 June 2017 22 April/ 8 May/18 May Safety training records 25 July 2017 July 2017 31 August 2017 August 2017 20 May 2016 Environmental training 30 September 2017 September 2017 materials and training 31 October 2017 October 2017 records 30 November 2017 November 2017

Page | 90 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

Civil Environmental Protection/Flood Internal Monthly Environmental Works Prevention/Construction safety Operation And Monitoring Report Contract Constructor CSC Supervision Plan/Manuals Package Submission Date Note Submission Date Note No.

June 2016 Public opinion survey records

June 2017 Quality and safety promotion plan and training record (14 June)

March 2016 ~July Personal protection 2017 equipment (PPE) distribution records

Summary of onsite July 2017 environmental cost

CH3 Gansu 1st Shanghai 1 April 2017 Safety management plan/ 25 May 2017 May 2017 construction Fuda traffic management plan/ fire 25 June 2017 June 2017 company Construction prevention plan 25 July 2017 July 2017 supervision 25 August 2017 August 2017 company 30 April 2017 Dust control plan/emergency 25 September 2017 September 2017 response plan 25 October 2017 October 2017 25 November 2017 November 2017 1 May 2017 Emergency response training record

5 May 2017 emergency respond Safety education plan

10 May 2017 Inventory of fire presentational equipment

20 May 2017 Safety training records

June 2017 Personal protection equipment (PPE) distribution records

Page | 91 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

Civil Environmental Protection/Flood Internal Monthly Environmental Works Prevention/Construction safety Operation And Monitoring Report Contract Constructor CSC Supervision Plan/Manuals Package Submission Date Note Submission Date Note No.

June 2017 Public opinion survey records

July 2017 Summary of onsite environmental cost

CH4 Gansu Shanghai August 2017 Public opinion survey 30 September 2017 September 2017 provincial Fuda records 31 October 2017 October 2017 installation Construction 30 November 2017 November 2017 company supervision 18 August 2017 Personal protection 31 March 2018 March 2018 company equipment (PPE) distribution 30 April 2018 April 2018 records 31 May 2018 May 2018 30 June 2018 June 2018 20 August 2017 Emergency response plan

22 August 2017 Fire prevention plan 22 August 2017 Safeguards and dust control plan

20 August 2017 Traffic management plan Safety training records

22/27 August 2017 Safety training records

CH5 Gansu 7th Shanghai March 2017 Construction environmental 25 April 2017 April 2017 construction Fuda management plan 25 May 2017 May 2017 company Construction 25 June 2017 June 2017 supervision March 2017 Fencing and traffic 25 July 2017 July 2017 company management plan 25 August 2017 August 2017 25 September 2017 September 2017 15 March 2017 Trench excavation and 25 October 2017 October 2017 support plan 25 November 2017 November 2017

March 2017 Fire prevention plan 25 March 2018 March 2018

Page | 92 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

Civil Environmental Protection/Flood Internal Monthly Environmental Works Prevention/Construction safety Operation And Monitoring Report Contract Constructor CSC Supervision Plan/Manuals Package Submission Date Note Submission Date Note No. 25 April 2018 April 2018 17 March 2017 Dust control plan/ fire 25 May 2018 May 2018 prevention plan 25 June 2018 June 2018

17 March 2017 Construction safety management plan

28 March 2017 Safety training records (for construction workers)

1 April 2017 Civilized and safe construction plan

April 2017 Emergency response plan

5 May 2017 Comprehensive measures of dust control

June 2016 Public opinion survey records July 2017 Flood emergency response plan/ traffic management plan/ Emergency response plan for interval of utility service

CH6 Lanzhou Shanghai May 2018 Safety training 31 October 2017 October 2017 municipal Fuda regulations/safety inspection 30 November 2017 November 2017 construction Construction and management 31 March 2018 March 2018 company supervision regulations 30 April 2018 April 2018 company May 2018 31 May 2018 May 2018 Dust control plan 30 June 2018 June 2018 May 2018 Traffic control management plan for Minshan road and

Page | 93 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

Civil Environmental Protection/Flood Internal Monthly Environmental Works Prevention/Construction safety Operation And Monitoring Report Contract Constructor CSC Supervision Plan/Manuals Package Submission Date Note Submission Date Note No. Xihuang Ave. 25 May 2018 Public opinion survey records (for 4 residents) May 2018 Emergency response plan for pipeline temporary breakdown June 2018 Fire prevention plan 20 June 2018 Personal protection equipment (PPE) distribution records

Associated China Non- Gansu N/A N/A 25 Apr 2016 April 2016 facilities- ferrous 12th Jingjian 25 May 2016 May 2016 Qinzhou Metallurgy 25 June 2016 June 2016 district Construction 25 July 2016 July 2016 heating Company; 25 August 2016 August 2016 source 25 September 2016 September 2016 plant Gansu 25 October 2016 October 2016 Engineering 25/30 Nov 2016 November 2016 Installation 25/31 Dec 2016 December 2016 Company 25/30 January 2017 January 2017 28 February 2017 February 2017 25/29 March 2017 March 2017 25/30 April 2017 April 2017 25/31 May 2017 May 2017 25/30 June 2017 June 2017 25/31 July 2017 July 2017 31 August 2017 August 2017 30 September 2017 September 2017 31 October 2017 October 2017 30 November 2017 November 2017

Page | 94 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

Appendix 4 Certificate of Onsite Sampling and Laboratory Testing Agency (Lanzhou Yitong Monitoring Company) and Scanned Copy of Testing Data

Page | 95 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

Page | 96 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

Page | 97 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

Page | 98 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

Page | 99 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

Page | 100 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

Page | 101 Jump back to Table of Contents ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

Page | 102 Jump back to Table of Contents

ADB Loan - 2760 10th External Environmental Gansu Tianshui Urban Infrastructure Development Project Monitoring Report

(this page is intentionally left empty)

Page | 103 Jump back to Table of Contents