REQUEST FOR INFORMATION (RFI) FOR SUBMARINE DAMAGE CONTROL AND FIRE FIGHTING TRAINING FACILITY FOR THE INDIAN NAVY

1. The Ministry of Defence, Government of India intends to procure One Damage Control and Fire Fighting Training Facility along with its associated equipment and civil works.

2. This Request for Information (RFI) consists of two parts as indicated below:-

(a) Part I. The first part of the RFI incorporates operational characteristics and features that should be met by the equipment. A few important technical parameters of the proposed equipment are also mentioned.

(b) Part II. The second part of the RFI states the methodology of seeking response of vendors. Submission of incomplete response format will render the vendor liable for rejection.

Part I

3. The Intended Use of Equipment. The Submarine Damage Control and Fire Fighting Training Facility is required to be set up at Vishakhapatnam, Andhra Pradesh, India depending on the land requirement and availability to impart realistic training to personnel on damage control and fighting fire in the closed and confined (space constrained) submarine environment.

4. Important Technical Parameters. The Submarine Damage Control and Fire Fighting Training Facility would be set up at Vishakhapatnam. The design of the Submarine Damage Control and Fire Fighting Training Facility should meet the requirements at Appendix A. The vendor is to provide parawise compliance for aspects brought out at Appendix A along with specific comments for compliance (if any). The vendor is to provide following additional inputs:-

(a) Approximate Cost Estimate. Indicative cost for setting up the Submarine Damage Control and Fire Fighting Training Facility. It should take into account all aspects of supply, installation, integration, training, Factory Acceptance Trials (FATs), Onsite System Acceptance Test (OSAT) & life cycle support. The indicative cost should also cater to the AMC as per details in Appendix A. Other aspects (if any), may be mentioned specifically.

(b) Vendor is to indicate whether he has supplied the same or similar equipment to any other customer. Additionally, the vendor is to indicate whether similar equipment is in use in any other Navy.

(c) Vendor is to indicate the manpower required to operate and maintain the training facility. Additionally, the details of training required for such personnel is also to be indicated.

(d) Vendors may consider RFI as advance information to obtain requisite Government clearances.

2

(e) Tentative Delivery Schedule. The overall timeframe of production, delivery with stage wise break-up of the entire project post conclusion of contract is required to be submitted.

(f) Payment Terms. Vendor is to indicate acceptability to the terms of payment as per DPP-16.

(g) Vendor is to indicate its capability to execute the project and provide product support including:-

(i) Technical support being provided for maintenance and support of the facility during its service life, including warranty. The service life of the facility should be at least 30 years.

(ii) Modalities for Annual Maintenance Contract including spares, post warranty period.

(h) Vendor is to indicate the provisions for upgradeability of equipment to avoid system obsolesce.

(j) Vendor is to indicate restrictions related to exports in its country and how long will it take to get clearance.

(k) The details of the land requirement and electrical power requirements for creation of the training facility.

(l) Earliest date by which OEM is willing to give a presentation at Naval Headquarters, New Delhi.

5. Vendor should confirm that the following conditions are acceptable:-

(a) The solicitation of offers will be as per ‘Single Stage –Two Bid System’. It would imply that a ‘Request for Proposal’ would be issued soliciting the technical and commercial offers together, but in two separate sealed envelopes. The validity of commercial offers would be at least 18 months from the date of submission of offers.

(b) The technical offers would be evaluated by a Technical evaluation Committee (TEC) to check its compliance with RFP.

(c) Amongst the vendors cleared by TEC, a Commercial Negotiation Committee (CNC) would decide the lowest cost bidder (L1) and conclude the appropriate contract.

(d) Vendor would be bound to provide product support for time period specified in the RFP, which includes spares and maintenance tools/jigs/fixtures for field and component level repairs.

(e) Vendor is to accept all conditions of DPP-16, if not, which Para/ Clause of DPP-16 is not acceptable is to be indicated. Further, the vendor would be required to accept the general conditions of contract given in the Standard Contract Document at Chapter VII of DPP placed at www.mod.nic.in.

3

(f) Integrity Pact. An Integrity Pact along with appropriate Integrity Pact Bank Guarantee (IPBG) is a mandatory requirement in the instant case. (Refer Annexure I to Appendix M of Schedule I of Chapter II of DPP 2016).

(g) -cum-Warranty Bond. A performance-cum-Warranty Bond both equal to 5% of value of the Contract is required to be submitted after signing of the contract.

Part II

6. Procedure for Response

(a) Vendor must fill the form of response as given in Appendix B to Chapter II DPP 2016. Apart from filling details about company, details about the exact product meeting the generic technical specifications should also be carefully filled. Additional literature on the product may be attached with the form. Vendors are to provide para wise compliance in a tabular format to this RFI along with reasons for non-compliance, if any to all aspects of this RFI.

(b) The filled form should be dispatched at under mentioned address:-

Principal Director Submarine Acquisition Directorate of Submarine Acquisition IHQ MoD(Navy) Room No. 120, 'C' wing Sena Bhawan New Delhi – 110 010

Tel: +91-11-2301 0162 Fax No.: +91-11- 23010830 e-mail: [email protected]

(c) The last date of acceptance of filled form is 03 Aug 16. The vendors shortlisted for issue of RFP would be intimated. A presentation on the subject may also be sought in case it is felt that certain parameters mentioned in replies to this RFI need further clarification.

7. The Government of India invites responses to this request only from Original Equipment Manufacturers (OEM) / Authorised Vendors / Government Sponsored Export Agencies (applicable in case of countries where domestic laws do not permit direct export by OEMs) / Vendors with experience of production of Training Simulators of equivalent complexity. The end user of the equipment is the Indian Navy.

8. This information is being issued with no financial commitment and the Ministry of Defence reserve the right to change or vary any part thereof at any stage. The Government of India also reserves the right to withdraw it should it be so necessary at any stage. The acquisition process would be carried out under the provisions of DPP-2016.

4

Appendix A (Refers to Para 4)

OPERATIONAL AND TECHNICAL PARAMETERS FOR SUBMARINE DAMAGE CONTROL AND FIRE FIGHTING TRAINING FACILITY

SECTION A

INTRODUCTION

1. A state-of-the-art Submarine Damage Control (DC) and Fire Fighting (FF) Training Facility is required to be set up at Visakhapatnam to impart realistic training to personnel on damage control and fighting fire onboard submarines.

2. Role of Training Facility. The training facility should be designed to fulfill following roles:-

(a) Ab initio training of personnel joining submarines for damage control and fire fighting.

(b) Refresher training of submarine personnel for damage control and fire fighting.

3. Training Objectives. The Submarine DC and FF simulator training objectives are as follows:-

(a) Trainee will acquire knowledge and practice skills for Damage Control and Fire Fighting onboard a submarine in a near realistic environment.

(b) Adaptability of a trainee to tackle an emergency in the closed and confined (space constrained) submarine environment.

(c) Enabling a trainee to comprehend the fundamental principles and concepts necessary to mitigate, solve and control an emergency whilst exposed to the elements of flooding, smoke, fire and heat within the compartment.

(d) Enable a trainee to acquire knowledge and practice correct use of Individual Protective Devices (IPD) and breathing sets.

(e) Enable trainees of affected and adjacent compartments to take necessary action regarding energising / de-energising equipments/systems, measurement of microclimate of affected compartment, procedure of entering the affected compartment by an investigation / repair party along with associated gear, methodology of inspection and evacuation of affected compartment etc.

5

(f) The simulator should also be capable of facilitating the following training aspects:-

(i) Training of individual watch-keepers in responding to a flooding incident damage control and fire emergency.

(ii) Training of multiple trainees forming a team representing compartment crew, in responding to flooding damage control and fire emergency.

(iii) Training / examining of Command Teams at central command posts by Submarine Workup Team on proficiency in responding to a damage control and fire fighting emergency whilst directing the compartment crew in affected / non affected compartments.

(g) A team of trainees comprising a compartment crew should be able to undertake following common actions:-

(i) Switching on / off, emergency lighting / easy access lighting.

(ii) Switching on / off, all electrical equipment in the compartment like compartment blowers / ATUs, and individual machinery cooling blowers / fans if any, etc.

(iii) Shifting of combustible, regenerative and explosive material near scene of fire / flooding to a safer location within the compartment / to the adjacent compartment (circumstances permitting).

(iv) Preparation of the compartments to be ready for undertaking diving and surfacing evolutions (primarily ventilation, compartment dewatering systems and electrical equipments).

General Arrangement

4. The Simulator is to be a fully independent training facility for damage control and fire fighting with following sections:-

(a) Damage Control Simulator. (b) Fire Fighting Simulator. (c) Instructor Station. (d) DC Gear Practice area. (e) First aid fire fighting training area (Open fire hart). (f) Instruction area (Class rooms). (g) Administrative area. (h) Training material storage area. (j) First aid Post. (k) Power management system including emergency power backup. (l) Fuel storage, handling and transfer system. (m) Water storage, treatment and handling system.

6

(n) Air conditioning and ventilation system. (p) Hydraulic system/ Actuator power pack. (q) Maintenance area. (r) Any other facility as necessary for independent operation of training facility.

5. The simulators should be housed in covered shed(s) of adequate height and partially cladded on sides. A Electric Overhead Travelling (EOT) crane of suitable rating for undertaking repairs and overhauls of the simulators should also be provided in the shed(s).

6. Broad Operational Philosophy. The simulators should be integrated facility to undertake the DC and FF exercises independently or in tandem. The control rooms in simulators manned by the trainees akin to the control room in a submarine shall be the main post for control of all activities pertaining to the exercises by the trainees. The exercises in the DC and FF simulator shall be monitored & controlled by the instructor(s) from the instructor station. The instructor station would be able to initiate, control, monitor and generate desired responses to an actual emergency whilst tasking the trainee or the compartment crew at various near realistic scenarios. The instructor station would also be used for conducting debrief at the end of the exercise, towards this there should be facility for generating the reports and video playback of the actions undertaken by the trainees. The instructor station should have the facility of modifying the standard exercises.

7. Training Load. The training facility should be able to handle the following training load on each simulator. The related infrastructure of the simulator should be designed so as to meet this training load:- (a) 15 trainees per Day. (b) 1500 trainees per Year.

8. Rules and Regulations. All structures of the simulators and its end portal supports should be designed, inspected and certified as per Indian Register of Shipping (IRS) rules. The structural design should cater for the maximum operational loads with adequate factor of safety in the design. The steel structure with portal frames should be Finite Element Method (FEM) analysed for IRS approval. Systems and Items on the training unit which do not fall under IRS scope of approval should be as per NES / Indian Naval specifications and requirements. These specifications may be sought by the vendor. These are to be further inspected & certified by Naval authorities / project team. System drawings are to be approved by Navy. Civil work and external utilities should be designed and constructed according to good engineering practices. However, Commercial items and hydraulic components may be certified by OEM.

9. Design Life. Not less than 30 years.

7

SECTION B

DAMAGE CONTROL SIMULATOR

General Arrangement

1. The DC Simulator would primarily simulate various flooding emergencies likely onboard a submarine in space constrained environment. In addition to the flooding emergencies, the DC simulator should simulate High Pressure (HP) Air leakages in order to train the personnel on the actions required in case of HP air Leakage. The equipment (including mock-ups/dummies) in the compartment shall be arranged to create the peculiar confined spaces onboard the submarines.

2. The DC simulator shall consist of three compartments:-

(a) Control Room. (b) Auxiliary Machinery Room. (c) Engine room.

3. The simulator should be mounted on longitudinal axis and should be bearing on two steel portal frames fixed on to a suitable RCC foundation. Suitable actuators are to be mounted on the support frame to tilt the training unit to a selected position up to 20 either side of the vertical. The oscillation frequency and amplitude should be controlled from the instructor station. The control system should be provided with preset oscillation modes and also provision to input the parameters from instructor station to control the oscillations. The actuator system should have microprocessor based control system and should have facility for control from the Instructor station and local control panel.

4. The compartments of the DC simulator should be on two deck structure with the entry for the simulator from the top of the control room. The entry in the simulator should be through a circular conning tower into the control room.

5. The passageway for the compartments should be through circular escape hatches similar in design to the hatches in EKM class of submarines. In addition the floodable compartments should be provided with emergency exits opening directly outside the simulator.

6. Compartments should be provided with water overflow pipes to maintain the maximum water flooding level. Damage control gear should be stored in all three compartment for use by the trainees.

7. The compartments should be equipped with dummies or non functional equipment or static mock-ups to simulate realistic environment and feel of actual compartments of a submarine.

8

Control Room

8. The control room should be the primary trainee control station of all actions in the DC simulator. The control room should be provided with following:-

(a) Systems control and indication panel of all equipment in DC Simulator. (b) Simulated indicators for depth of Submarine, Depth Below Keel, List & Trim and any other indicator as deemed necessary as per design. (c) Motion control panel with facility to simulate the speed and control surfaces (planes) of submarine. The speed and planes will be controlled by the trainee depending on the emergency. (d) Intercom system and broadcast system. (e) Indication for fire warning and system (of FF Simulator). (f) Emergency stop switch. (g) Control for Emergency Lights.

9. The DC control room should also serve as an integrated control station for the DC and FF simulator in case of exercising FF and DC emergencies simultaneously. During simultaneous control of both simulators the trainee in the control room of the DC Simulator should be able to communicate with all compartments of the FF simulator, monitor the fire warning indications on the FF simulator and initiate emergency shutdown of the exercises. Therefore the DC simulator control room should be provided with necessary control, indication and communication system for control of FF simulator along with the DC simulator. The selection of mode of control for the DC simulator or tandem control of DC and FF simulator should be provided at instructor station.

Auxiliary Machinery Room

10. The auxiliary machinery room should be the second compartment of the simulator and should be divided in two levels. The compartment should be provided with high pressure water pipeline leakage, HP Air leak simulation, valve leak etc.

11. Components in lower deck:- (a) Garbage ejector. (b) Ballast System with pump. (c) Sea water system pipelines for leak simulation. (d) Water mist generator to simulate high pressure leak. (e) Mock-up/ dummies of Pump.

12. Components in upper deck:- (a) Electrical switchboards. (b) Ballast pump starters. (c) Hatch to engine room and control room. (d) Compartment pressurization system. (e) Compartment air cooler. (f) Water mist fire fighting system.

9

(g) HP Air system.

Engine Room

13. Engine room should be the third compartment of the simulator and should be divided in two levels.

14. Components in lower deck:- (a) Sea water system with dummy pumps. (b) Sea water Inlet valves. (c) Overboard Valves. (d) Rubber compensator. (e) Dummy/ Mock-up of Diesel Engines. (f) Dummy/ Mock-up of HP Air compressors. (g) Shafting with stern gland mockup.

15. Components in upper deck:- (a) Electrical switchboards. (b) Air Conditioning plant for DC simulator. (c) Hatch to Auxiliary Machinery compartment. (d) Compartment pressurization system. (e) Compartment air cooler. (f) DC gear.

Sea water System

16. The DC simulator shall have atleast two independent sea water system with complex loops of pipelines along with consumers/ mock-ups and associated isolating valves. The system should be laid in auxiliary machinery compartment and engine room. The pipelines of the system are to be arranged in a manner to simulate the piping routing onboard the submarines. The systems shall have (at least) following components:-

(a) Sea water Inlet valves. (b) Overboard Valves. (c) Three consumers in each system. (d) Filters. (e) Isolating valves for all filters and consumers. (f) Rubber Compensators.

17. The system components and pipelines are to be provided with various leaking positions simulating different types of sea water leakages possible in sea water systems. These leak locations are to be remotely controlled by the instructor from the instructor station. The type of leaks should be of the following types (not restricted to these):-

10

(a) Piping system with flanges/unions of various dimensions to simulate flooding through flange/unions leaks.

(b) Pipe bends for simulation flooding through break / leak from pipe bend.

(c) Leakage from Valve to simulate leakage from the valve flanges or valve glands.

(d) Safety valves for simulation of over pressure situation.

(e) Pressure gauges along with capillary union based piping for simulating minor leak/flooding.

(f) Compensator leak/crack/burst on the outlet of the positive displacement pump for simulation flooding emergency due to wrong configuration of system valves. The exercise would also expose trainee for technique in renewal of a compensator onboard (may be included in the scope, if required).

(g) Bilge suction valve with faulty non-return element for simulating flooding emergency due to defective valve.

(h) Pre-drilled holes in the piping system strategically located to simulate flooding emergency in a constrained space / difficult accessible locations onboard submarine.

18. In case of a high pressure leakage the water converts into mist, to simulate such a situation the auxiliary machinery compartment should be provided with water mist generators.

Flooding System

19. The flooding of the compartment should be undertaken by two methods:-

(a) Through the water seepage from the leaks in the sea water systems. (b) Through independent flooding arrangement in the compartments for faster flooding.

20. The flooding rate is to be calibrated based on the simulated depth and the size of hole in the system.

Draining System

21. An independent draining/deballasting arrangement system is to be provided in all DC compartments. The draining system should have at least following components:-

(a) One draining/Deballasting pump.

11

(b) Fixed suction strainers with Non return isolating valves. (c) Portable suction strainers.

22. The deballasting system should be provided with a source of flooding from a defective non return isolating valve in auxiliary machinery room.

23. The arrangement for the draining system should be such that the trainee should be able to prepare the system and initiate the action of the draining the flooded compartment.

HP Air System

24. The DC compartment should be provided with one air system to depict the HP Air system onboard the submarine (however the actual pressure may be limited to 6- 8 Kgf/cm2). The air systems should have at least following components:-

(a) HP air Panel. (b) Safety valves. (c) Isolating valves. (d) Reducers. (e) Pressure gauges. (f) Air bottles.

25. The air system should have facility to simulate the following:-

(a) Defective pipe unions. (b) Safety valve malfunction. (c) Defective system valves.

26. The compressed air for the system should be supplied by the air compressor housed outside the simulator with only air piping routed to the simulator for charging the air bottle(s) in the simulator.

Garbage Ejector

27. The Auxiliary Machinery compartment should be provided with a dummy garbage ejector along with the associated water systems. The system should have the facility of simulating the leakage from the garbage ejector due to defective inner lid and / or system pipelines.

Stern Gland Leak

28. The engine room should be provided shafting arrangement along with stern gland to simulate leakage through stern gland. The leak stopping arrangement for stern gland should be a pneumatic seal arrangement similar to the arrangement onboard SSK submarines.

12

Compartment Lighting

29. All the DC simulator compartments should be provided with two sets of lighting:- (a) Main compartment lighting. (b) Emergency Compartment Lighting.

30. The lighting mode selection should be possible from the control room and the instruction station.

Ventilation System

31. Provision to ventilate the DC simulator compartments is to be provided with Supply and Exhaust Blower. The blower capacities are to be designed to facilitate recirculation of air in the compartment at a rate of not less than 1X compartment volume per minute.

32. The ventilation system should be provided with isolating valves in the bullheads so as to enable pressurization of the compartment by the trainees.

33. During the flooding operation, the Air conditioning / ventilation in the affected compartment should be shut off by the trainee. Necessary safety features are to be included in the system so as to override the trainee actions in case of requirement of emergency ventilation of the compartments.

34. Provision should be made for suitable hot air supply to the flooded compartments for drying the compartments on completion of damage control exercises. A combination of forced and natural exhaust through hoods should be provided on upper deck for these compartments.

Emergency Draining System

35. The DC Simulator is to be provided with fail safe arrangement for draining the flooded water in the compartment. The emergency draining arrangement should enable draining of the flooded compartment within 01 minute from the initiation of emergency draining command.

Smoke

36. To increase the difficulty of the trainees during the exercises there should be a facility to introduce non toxic, biodegradable training smoke in all the DC compartments. The control of the smoke generator is to be provided in the instructor station. The rate of induction of smoke should be such that the visibility is reduced to 50 % in less than two minutes.

Electrical Equipment

37. Electrical equipments shall be provided in each compartment of the DC simulator for practicing actions to be undertaken on electrical equipment by the

13 trainee in case of damage. The electrical equipments shall be mock–ups/dummies with only the action switch operational along with provision for remote indication of the action performed on the equipment. Each compartment should have following electrical equipment dummies:-

(a) Switchboard. (b) Starter. (c) Emergency light switch. (d) Emergency Lantern.

38. Electrical equipments should be positioned above the maximum water level or adequate protection should be provided to avoid any water spillage/spray on these equipment in all operating conditions of the simulator.

Emergency Stopping

39. In case of any eventuality, provision to terminate the exercise should be provided at following locations:-

(a) All compartments of DC simulator. (b) Instructor station. (c) Any other location is deemed suitable based on the simulator design.

40. The emergency stopping of the exercise should activate the following:-

(a) Initiate emergency draining of all the compartment. (b) Position the simulator in zero list and zero trim condition. (c) Initiate ventilation in the compartment. (d) Switch on all lighting of the compartment. (e) Stopping of all flooding.

41. On actuation of the emergency shutdown a delay timer one minute is to be provided before the simulator is available for usage. All the emergency stop buttons should be hard wired to the control system (except the wireless controllers, if any).

42. Compartment pressurization. Compartment pressurization facility similar to that on a submarine to simulate damage control by the submarine in a tactical situation wherein coming to PD /surfacing of the submarine is not an option. The pressurisation of the compartment in actual is to be limited to a maximum of 0.5 kgf/cm2 (however the display of the same be scaled up on a pressure gauge to read as 5 Kgf/cm2). The compartment is to be provided with a depth gauge to simulate the depth of the submarine and a pressure gauge for checking the compartment air pressure. The compartments of the simulator are not required to be pressure tight, however the pressure gauge is to depict the pressure rise based on the action of the trainees (may be simulated using PLC control).

14

Motion Control of DC Simulator

43. The DC simulator should be mounted on longitudinal axis bearings which should be supported by steel portal frames at the two ends. The hydraulic system should be required to:-

(a) Heel the DC Simulator from 0° to 20° max. either side i.e. ± 20° & keep locked in any position.

(b) Roll the DC Simulator up to ±15° in 20 Sec under all loading conditions. Per cycle i.e. a roll frequency of about 0.052 Radian / Sec.

44. The hydraulic system/power pack should be remotely operated and have dual redundancy. There should be provision for manual operation in the event of power failure. Operation should be from both the power pack area as well as instructor station. Provision should be made for bringing the DC Simulator to neutral position (0°) from tilted position and stopped, in the event of emergency stop.

45. Hatches. The hatches in the compartments and the escape hatch in the control room of the DC simulator shall be similar to the compartment hatched of EKM class of submarines. The weight and mode of operation should be same as that of the compartment and escape hatches of EKM class of submarine.

46. BiBs. All compartments to be provided with Built in Breathing System for escape practice of trainees.

47. Compartment Monitoring. All compartments should be provided with following sensors with indications being available at the control room and the instructor station. All these sensors should be integrated with control system to provide safe operation of the Simulator.

(a) Compartment pressure sensors. (b) Water level sensors.

(c) Gas monitoring sensors for monitoring percentage of CO2 and O2.

15

SECTION C

FIRE FIGHTING SIMULATOR

General Arrangement

1. The Fire Fighting (FF) Simulator should be designed for training naval personnel in fighting fires onboard submarines in a realistic environment. The equipment (including dummies) in the compartment shall be arranged to create the peculiar confined spaces onboard the submarines. All dummies in the fire compartment should be flame resistant and should be able to sustain the heat without any damage.

2. The FF simulator compartments should have the facility to simulate fires corresponding to the likely fires that may occur in the respective compartments onboard a submarine. Standard patterns of fire for galley, general fire, electrical fire, oil fire etc. should be generated using gaseous fuel. The training scenarios created in the compartments should be repeatable and consistent. Depending on the type of fire simulated, the under trainees will fight the fire using appropriate fire fighting aid. The fire fighting simulator should be designed as per DIN En 14097.

3. The Fire Fighting Simulator should contain 04 compartments, namely:-

(a) Torpedo room with Battery deck.

(b) Control Room.

(c) Galley & mess deck.

(d) Machinery Room.

FF Simulator Control Room

4. The control room should be primary trainee control station of the actions in the FF simulator. The control room should be the second compartment of the FF Simulator. The control room should be provided with following:-

(a) Systems control and indication panel of all equipment in FF Simulator. (b) Simulated indicators for depth of Submarine, Depth Below Keel, List & Trim and any other indicator as deemed necessary as per design. (c) Intercom system and broadcast system. (d) Control and indication for fire warning and firefighting system. (e) Emergency stop switch. (f) Emergency lighting control. (g) Motion control panel with facility to simulate the speed and control surfaces (planes) of submarine. The speed and planes will be controlled by the trainee depending on the emergency.

16

Machinery Room / Engine Room

5. Engine room should be the fourth compartment of the simulator and should consist of following equipment and systems:-

(a) Diesel Engine Mock–up/dummy. (b) Compressor Mock-up/Dummy. (c) Sea water systems (with pumps). (d) Fuel Systems. (e) Lub oil system (with pumps). (f) Ventilation Blowers.

6. Following fire emergencies with varying degrees of difficulties to be simulated in the compartment should be (but not limited to these):-

(a) Fuel flange leak fire. (b) Bilge fire. (c) Diesel Engine Exhaust fire.

Galley and Mess Deck

7. Third compartment of the FF simulator should house Galley & Mess decks and should consist of following equipment and systems:-

(a) Galley equipment. (b) Three living spaces. (c) Air conditioning Unit. (d) Electrical Switchboard & Breakers.

8. Following fire emergencies with varying degrees of difficulties to be simulated in the compartment should be (but not limited to these):-

(a) Electrical fire. (b) Galley Oil fire. (c) Bunk fire with fire ball effect.

9. Strobe light effect for electrical fire simulation on switchboard/breakers to enhance the realistic quotient should be provided.

Torpedo Room and Battery Room

10. Torpedo room should form the first compartment of the FF simulator and should house the following (but not limited to these):-

(a) Duumy Torpedoes on racks. (b) Battery Pit hatch. (c) Accommodation space. (d) Water sprinkling system for torpedo compartment.

17

11. Following fire emergencies with varying degrees of difficulties to be simulated in the compartment should be (but not limited to these):-

(a) General fire in living accommodation space. (b) Electrical fire on the battery post /switchboard. (c) Battery Pit fire.

12. Temperature rise in the torpedo compartment is to be simulated using hot air blower. The reserve torpedo sprinkling system/ nozzle based system (similar to EKM submarine reserve torpedo sprinkling system) should be provided for training the compartment crew for its preparation and activation procedure.

Fire Control

13. Computer controlled fire initiation and monitoring from the instructor station. This would allow trainee to realistically respond and attempt fighting / extinguishing the fire/flames. The fires should be under the overall control of an integrated computerised system located in the facility’s central control room. Provision should exist for each fire to be controlled locally by the instructor/ safety officer conducting the training course. The data logging management system and logistics are to be integrated by suitable software.

14. The simulator should also enable actions by the affected compartment crew and adjacent compartment for preparation of the affected compartment for evacuation and activation of fixed fire fighting system. Further the crew could be trained for inspection of the affected compartment post activation of fixed fire fighting system.

Flame Management

15. The main burner gas supply and combustion air supply must be separate from pilot burner gas and combustion air supply. Pilot flame management is to monitor the pilot burner continuously and if the pilot burner fails, all gas supply system must shut down automatically to ensure unburned fuel is not released into the fire compartment. The pilot burner should be located/ housed so that it is not visible to the trainees and to also ensure that the flame is not put off automatically whilst doing the exercise. The flame safe guard system will instantaneously shut down and lock out the fuel supply to the main and pilot burner in the event of a pilot flame failure or ignition failure. Each fire simulation system must be acceptance test to Part 6 of DIN EN 14097 and Part 2 of DIN EN 14097 has to be carried out by an approved authority, which has to issue a certificate of compliance.

16. Various flame strength and thus heat levels should be generated. This is to be achieved by controlling and regulating the height of the main flame. For example, for relatively small fires just one flame height can be provided.

18

17. The flame generation system should contain a separate and automatic shut off valve connected to the control system of the trainer in order to shut off the gas flow should a failure of electrical power occur or in the event of any emergency.

18. The main flame control valves will be designed to reproduce realistic flame size, spread, decrease, suppression and re-flash depending on the operating parameters entered into the computer system by the operator with regards to the gas flow rate required by a particular fireplace/scenario.

Burner

19. The burner should primarily ensure the following:-

(a) Give the typical “Yellow” flame pattern of a carbonaceous fire.

(b) Burn with as complete combustion as possible whilst maintaining the “yellow” pattern flame.

(c) Soot should not to be formed.

(d) Be configurable with regard to flame spread and overall heat release.

(e) Be instantaneously extinguished in less than three seconds in the event of a safety violation.

(f) After shutdown, be available for reigniting within 02 Minutes.

20. The burner is to be mounted as close to the fire place as possible to minimize hidden flame height. The release of sulphur oxide and benzene are to be maintained at acceptable levels for long term exposure of the trainers. Each burner is to be provided with a dedicated fuel supply and control line in accordance with BS EN 746. The flame height and spread is to be controlled by a fully modulating control valve integral to the fuel management system. The burner is to be so configured that the flame height and heat release are fixed. Thereafter, the flame growth and decay is determined by the position of fuel control valve, which can be controlled remotely. Additionally, the growth decay and intensity should be controlled to suit a particular training scenario to enable introduce raw trainees to less intense version of a particular fire. These parameters can be selected from the fire place control panel or remotely from control room. The fuel system should confirm to BS EN 746-2 safety standards and IEC 61508 for functional safety of electric/ electronics/ programmable related systems.

Flame Extinguishing Control

21. Two methods, manual and automatic for controlling the flame extinguishing should be provided in the system. The fires will react in accordance with how the trainee applies the extinguishing media.

22. Using the manual method, the strength of the flames will be capable of being controlled by the instructor using the hand held remote control/ local panel. The

19 flames are deactivated based on the visual assessment and judgment of the instructor and initiated by him/her if it is deemed that the extinguishing agent has been applied correctly.

23. Using the automatic method, the flames will die down and be deactivated by the control system only if the trainee has applied the extinguishing agent for the correct period of time and, in some fire points, if the temperature has descended below preset values.

24. Burner Emissions. The fire simulator burner should not lead to unacceptable levels of sulphur oxides, benzene and particulates. The emission from the FF Simulator is required to be adequately treated for NOx and SOx to ensure that the permissible levels of pollution are not exceeded. The norms will be in accordance with the existing international norms, ISO 14001 and other environmental standards may be referred to for guidance.

25. Exhaust Monitoring System. The exhaust gas monitoring system should continuously monitor the exhaust gas of all the burn room for abnormal level of following gases:-

(a) Carbon Monoxides.

(b) Nitrogen Dioxide.

(c) Propane.

26. Compartment Monitoring. All compartments should be provided with following sensors with indications being available at the control room and the instructor station. All these sensors should be integrated with control system to provide safe operation of the Simulator.

(a) Compartment pressure sensors.

(b) Gas monitoring sensors for monitoring percentage of H2, CO, CO2 and O2.

Fire Fighting Aids

27. Various Fire fighting aids to be provisioned in the FF simulator compartments to enable trainees to take requisite actions in case of fire onboard a submarine. Following fire fighting modes to be provided in the FF Simulator:-

(a) Portable Fire Fighting Aids. Following types of portable fire extinguishers encountered onboard a submarine should be made available in all compartments akin to that on actual submarine.

(i) AFFF Extinguishers.

(ii) CO2 / Halon Extinguishers.

20

(iii) DCP Extinguisher (dummy for operation training, however extinguishing agent should not dry chemical powder, to avoid damage to the simulator over repeated use).

(b) Fixed Fire Fighting Systems.

(i) An AFFF based extinguisher system with extendable reels (akin to VPL system onboard Sindhughosh class of submarines).

(ii) Water mist based system to simulate LOX/Halon based fire extinguishing System onboard submarines.

(iii) A Reserve Torpedo Sprinkling System as provided on Sindhughosh class submarines would also be required for compartment crew training.

(iv) One firefighting hose point (similar to Ships) in galley and mess deck compartment.

28. BiBs. All compartments to be provided with Built in Breathing System for escape practice of trainees.

29. Hot Entry in Compartment. The entry into the machinery room should be heated using hot air blower to simulate effect of heat while entering the fire affected compartment. The blower output should be controllable to vary the temperature of output air from 50 °C to 100 °C.

Electrical Equipment

30. Electrical equipments shall be provided in each compartment of the FF simulator for practicing actions to be undertaken on electrical equipment by the trainee in case of damage. The electrical equipments shall be dummies with only the action switch operational along with provision for remote indication of the action performed on the equipment. Each compartment should have following electrical equipment dummies:-

(a) Switchboard. (b) Starter. (c) Emergency light switch. (d) Emergency Lantern.

31. Electrical equipments should be positioned above the maximum water level or adequate protection should be provided adequate protection to avoid any water spillage/spray on these equipments in all operating conditions of the simulator.

32. Compartment pressurization. Compartment pressurization facility similar to that on actual submarine to practice the entry in the effected compartment by pressurizing the adjacent compartment to prevent smoke transfer. The compartment pressuring should be indicated by release of air into the compartment and the rate of pressurized air release should be adequate to restrict the smoke transfer. The

21 compartment pressure indication should be simulated using the control system. Pressure rise in the compartment may not be same as that displayed on the pressure indicator.

Emergency Stop

33. In the event of emergency in the simulator or should the safety staff notice a problem with the trainees necessitating termination of the exercise, number of emergency stop device buttons are to be provided in all compartments. These emergency stop switches should be provided at following locations:-

(a) All compartments of FF simulator.

(b) Instructor station.

(c) The local instructor control unit.

34. On operation of emergency stop, following actions to be initiated:-

(a) All compartment lighting to be switched on including the emergency lights.

(b) Main fuel service valve to be shut stopping all fires.

(c) Torpedo sprinkling system to stop.

(d) Ventilation fans to increase to full speed for smoke clearance.

(e) Evacuation broadcast to the unit.

35. The emergency stop should get activated automatically in case of following:

(a) High concentrations of gaseous fuel.

(b) High temperature alarm.

(c) System failure.

(d) When un-burnt pockets of fuel are found.

(e) High concentration of CO.

36. All emergency stop switches are to be illuminated and sufficiently guarded/ shielded to prevent accidental activation. Manual shut down is to be independent of the computer operation and is to over ride all commands.

37. A timer in the control software should prevent the unit from being restarted to ensure that the compartments are completely purged. Purging should be done at purge rate of 80 times (minimum) the room volume per hour before restarting/resetting the unit.

22

Ventilation Systems

38. The FF Simulator should house two independent ventilation systems:-

(a) Trainee ventilation system. This ventilation system should be handled by the trainees during the course of the fire exercises depending on the actions to be taken on the particular emergency.

(b) Simulator Ventilation System. This ventilation system is to be controlled by the instructor and is primarily for the operation and safety of the simulator.

Trainee Ventilation System

39. Trainee ventilation system should be designed to ventilation system akin to the ventilation system onboard EKM submarines. The system should have supply and exhaust fans along with the isolating valves for all compartments.

Simulator Ventilation System

40. The ventilation system should be designed adequately so as to ensure complete combustion of the fuel, rapid exhausting of the hot fuel gases and other products of combustion. Accumulation of unburnt fuels will be prevented at all times. The design of ventilation system will be simple, direct and fail safe.

41. The system will comprise of ventilation fans of appropriate capacity with heating chambers, associated trunking, dampers, expansion bellows, etc. The fans will be in an acoustic and thermal enclosure to reduce noise and heat dissipation to outside environment. Exhaust fans will also be provided to exhaust the hot air from the compartments. The emergency exhaust fan will have a provision to be started remotely by press of an emergency button available at the instructor station while the hot air fans should stop with the operation of this button. The dampers associated with the respective blowers should close or open as appropriate with starting/stopping of the blowers.

42. Forced ventilation should be provided in FF simulator compartments for the following functions:-

(a) Automatic and frequency driven to supply the required fresh air for complete combustion in the fire rooms.

(b) At maximum capacity while switching on the system for 30 Sec in order to remove any smoke or residual fuel.

(c) In case of an emergency (activation of emergency stop device, high gas concentration or high temperature), the ventilation system should run automatically on full purge. Clearance of artificial smoke to allow evacuation in an emergency situation to achieve a level of visibility of 3m all round in two minutes.

23

(d) Regulations of fire room temperature to desired temperatures.

(e) Supply hot air for raising the temperature of the exercise area. The specified temperature will be achieved within 30 minutes on starting the system.

(f) Extraction of hot air to atmosphere in case of an emergency to bring down the temperature of the exercise compartments within 2 minutes.

(g) To maintain a flow of combustion and dilution of air to the fire such that there can be no build up of unburned hydrocarbons in the fire room.

(h) To remove the smoke after completion of exercise.

43. Each compartment should be fitted with a forced ventilation blower to extract smoke from the compartment in the event of emergency. The ventilation system should be able to regulate the room temperature to preset parameters depending on the scenario choice within the controlled system. The ventilation is to operate via dampers and should serve all activated fire rooms automatically with the required combustion air and if necessary should operate as an emergency purge system. Also, before the system starts, automatic purge of requisite time to ensure 80 times of room volume per hour is ensured. In case of multiple fires in same compartment the purge rate is to be increased to 100 times of room volume per hour.

44. The FF Control room should be provided with air conditioning system and should be insulated from the adjacent compartments to minimize the heat load in control room.

Gas Monitoring System

45. Each compartment of FF Simulator is to be installed with two gas sensors so as to measure the level of gas in the compartment and activation of ventilation/ purging of the compartments. Additionally, adequate number of sensors should be fitted around the training area to monitor gas leaks. The gas monitoring system should have auto diagnostic function so as to warn in case the tests have not been carried out within a pre determined time frame or the results are negative.

46. A battery backup facility for the controls and the safety system is to be provided so that the safety aspects are not compromised in the case of non availability of normal and alternate supply. The fuel detection system should be capable of operating continuously (24X7) even when the training facility is shut down or in standby mode. The failure of fuel sensing hardware should be automatically indicated on the control panel and initiate emergency shutdown of the simulator.

47. Temperature Monitoring System. The control system should ensure that maximum temperature levels in the compartments should not exceed 350° at 2 mtrs from the source in any direction. The temperature monitoring system is to monitor the temp of compartments in FF Simulator continuously during the training

24 sessions. At least two operating temperature sensors have to be installed in each rooms set at a max temp of 250o C at one meter height from floor. Control system should automatically commence purging of compartments in case of temperature of the compartment reaches 250o C. To ensure adequate safety for the trainees, an additional temperature sensor is to be fitted in the ceilings on all FF Simulator compartments. Control system should initiate emergency shutdown in case temperature reached 350o C at the ceiling sensor and activate the ventilation at maximum purge rate.

48. Smoke Generators. Each burn room is to be provided with at least one smoke generator. The maximum opacity level at should limit the visible of upto 50 cm at height of 1 meter. The rate of smoke generation should be such that the compartment achieves maximum opacity in one minute of initiation of the smoke generation. The smoke should not cause any interference to any of the operating components. The smoke should be non-flammable, non toxic and biologically degradable.

49. Internal Fittings. The fittings inside the compartments including the fuel burners, pipelines, valves, lighting fittings, ventilation system etc. should withstand the temperatures generated by the simulated fires. The material in the compartments is to maintain structural integrity in all fire scenarios.

50. Flood Alarm System. A Flood Alarm System with water level sensors is to be installed in all simulator compartments with indicators located in the instructor station. The flood alarm system is initiate alarm and drain water if the water level in the compartment rises above safe height for personnel and equipment in the compartment.

51. Fuel. The FF Simulator will use propane as the fuel for simulation of various classes of fires. The fuel system should be able to fail safe and close automatically in case of power failure. Additionally the fuel system should be able to diagnose erratic operation of the system valves and indicate the same on the control panel.

52. First Aid Fire Fighting Practice Area. A first aid fire fighting practice area is to be set up with live fire with a facility to house 10 trainees at one time with the complex for of the training facility. The practice area should have two burners to familiarize the trainees with the use of fire extinguishers. The practice area should be covered from top with adequate roof height to withstand exposure from high. Effective heat dissipation arrangements are to be provided to avoid exposure of trainees to high temperature during fires. The practice area should be covered from all sides to avoid ingress of water during heavy rains and inclement weather. The practice area is provided with drains on the sides for the extinguishant/water to drain out completely on completion of an exercise.

25

Fabrication of FF Simulator

53. The floors will be fabricated from steel plate and grating formed to create drains and cambered surface without trip hazards. Scuppers are to be provided along each training compartment bulkheads to allow the ingress of water.

54. Bulkheads, decks and deck heads are to be protected from flame impingement and from temperatures exceeding 500°C. The bulkheads decks and deck heads in the fire compartments will be protected with insulation that should be able to withstand 1000°C. The temperature sensors are to be placed at appropriate areas within the fire rooms to monitor the temperatures. A certification from an accredited laboratory/ organisation certifying that the thickness and the standard of the plate to be used and also insulation material will sustain 1000° C is to be provided.

Lighting

55. The lighting in the compartments should be designed to achieve 100 lux at floor level. The compartment lights should withstand both the extreme heat of the fire and the thermal shock when the fire extinguishing system is operated. All light fittings should have IP66 protection.

56. The lighting arrangements in the FF simulator should also cater to the following:

(a) Standard florescent and bulkhead fittings as provided onboard submarines are provided on the simulators. In fire compartments, incandescent light fittings are used.

(b) On operation of the emergency stop device, 24V DC emergency supply is to be switched on in all operational areas for emergency lighting.

(c) Automatic emergency lanterns (AELs) are to be installed onboard the simulator to enable escape routes to be visible.

(d) Photo-luminescent stickers/indicators are also to be provided to supplement the AELs.

26

SECTION D

COMMON SYSTEMS FOR DC AND FF SIMULATOR

Control System

1. The centralized control of simulators and all other related control is to be provided in the instructor station which is to be located in the administrative building. The complete exercise is set up and controlled from this position and the control is passed over to the simulator for the operator/safety instructor to commence the exercise. The control system should have facility to create exercise scenarios in offline mode, which can be played out at a later time during conduct of live exercises. Provision should also be made for activation and deactivation of different systems depending on the class of submarine being trained. The mode of exercise is to be decided from the instructor station prior transferring the control to the instructor in the simulator or the control room of the respective simulator (as necessary). All controls including fire and flame management, flooding of units along with ventilation/crash stop functions are to be provided at the instructor station. Control of flame/ ventilation/crash stop, drainage of the respective exercise compartments shall in addition be available within a remote wireless unit to be carried by the instructor conducting the respective exercise.

2. The control system should be capable of carrying out self diagnostic checks prior starting the system. It should incorporate daily operational readiness tests to confirm satisfactory operation of the entire system prior to the start of daily training.

3. The control system should have adequate processing power to assure real time processing of all assigned functions and assure error free operation of the training facility.

4. A diagnostic menu is to be incorporated in the control system which would offer a selection of tests that automatically check all major trainer system components. These should include water detectors, pilot diagnostics, valve diagnostics and propane pressure, temperature sensors, gas monitoring system and air compressor function.

5. The local exercise position would be manned by the safety officer/instructor. The local panel should located outside all exercise areas at a convenient location so that the safety officer instructor does not obstruct the trainees doing the exercise and at the same time has the complete view of the exercise area to enable A suitable hand held wireless frequency based control device incorporating necessary controls may be provided in lieu. The system should be protected from the radio frequencies which may interfere with the safety systems of the simulator or frequencies used by external safety agencies.

6. Trainee Control Stations in Simulators. The trainee control stations in both simulators should cater for actions to be taken by the trainees during the training exercises. The front facia of the control stations should be designed using

27

LED based displays/ multifunction consoles which can replicate control panels to display the control systems onboard submarines. Provision should be made to display the control stations of different class of submarine depending on the training being undertaken.

Broadcast and Intercom System

7. General Broadcast System. A broadcast system should be installed with loudspeakers positioned at various locations in the training facility. Input to the broadcast system should be either from microphone stations or through multimedia player.

(a) Microphone Stations. High sensitivity rugged construction microphones should be provided at the following stations:

(i) Instructor station

(ii) DC control room

(iii) FF control room

(iv) Fuel storage watch-keeping post

(v) Reception

(b) A multimedia player should be positioned in the instructor station to broadcast realistic submarine noises through the broadcast system.

(c) Two Amplifiers should be provided, with only one will be operational at a time and the other being a hot spare enabling change over by a switch provided on the panel.

(d) The system also incorporates an action alarm facility.

(e) Adequate metal housing speakers of reputed make should be installed at various suitable locations to cover the complete area of the training facility.

8. DC Simulator Broadcast System. A local broadcast system for announcements within the DC simulator and FF Simulator should be provided in Control room of DC simulator. The system should be provided with selection for broadcast within the DC simulator or within DC & FF Simulator.

9. FF Simulator Broadcast System. A local broadcast system for announcements within the FF Simulator should be provided in Control room of FF simulator.

10. Intercom System. Intercom system for 2 way communication should be provided comprising of single line communication assemblies. Intercom stations should be provided in all areas and posts manned during operation of training unit as well as control and operation areas. The intercom station of DC simulator should be capable of interconnection with all compartments of DC and FF simulator; however

28 the intercom station of FF control room should be capable of interconnection with compartments of FF simulator only. A message tube as existing onboard EKM submarines between compartments is also to be provided on the bulkheads of compartments.

11. Besides the above, a Sound Powered Telephone system should also be provided interconnecting all the compartments in each simulator.

12. A flashing beacon should be provided on the exterior of each simulator to indicate the exercise is in process and is a hazardous condition.

Audio Simulation.

13. The simulators should be provided with facility to generate sounds of machinery and other equipment as onboard submarines. It should also have the provision to initiate the sounds of specific machineries which is to be started/stopped by the trainees. Audio simulation of damage leaks, water flow, etc are to be provided. The blowing of tanks is also to be simulated by audio simulation.

Visual Monitoring System

14. CCTV Camera. A suitable CCTV system of reputed make should be provided in both the simulators. The CCTV system should comprise of a central processing unit, a light emitting diode (LED) display unit(s) of suitable size and digital cameras to cover all the positions of simulators. The central processing unit to be linked to high resolution, splash proof, anti condensate & environmental resistant housing digital cameras positioned at agreed locations. The arrangement should enable the viewer to see the coverage of any number of cameras at tandem on the display unit in equal number of windows as that of the number of locations selected for viewing. The system enables the operator to switch between the cameras and also to record the coverage on a digital media.

15. IR Camera/. A suitable IR Camera /TIC system independent of CCTV system of reputed make should be provided in both the simulators. The IR Camera /TIC should be provided in all compartments of the DC and FF Simulator except the control rooms of each simulator.

16. In addition to the CCTV and IR / Thermal Imaging Camera, glass windows are to be provided at suitable places in the simulator for the instructors to monitor the trainees.

17. Escape Markings. The training facility should be provided with self illuminated or photo-luminescent stickers/indicators to guide personnel in case of emergency.

29

Fire Alarm System

18. A suitable Fire alarm system should be provided in the training facility. System should comprise of IR photo electric detectors, ionization detector and rate of rise fixed temp heat detectors located at appropriate places inside the training facility.

Emergency Warning Indication

19. A suitable audio and visual warning system comprising a claxon and pulsating lights is to be provided for announcing actual emergency in the training facility.

Freshwater Storage and Handling

20. Water should be stored in a sump tank below the simulators from where the water should be pumped to the overhead water tank through one of the transfer pumps located in the pump room.

21. Water Storage Tank. Suitable overhead water storage tank(s) to be provided to hold sufficient quantity for undertaking two times the water requirement for consecutive exercises in DC and FF simulators. Water storage tanks should be provided directly over the water transfer pumps. The tank should be provided with water level sensors and indication of the same to be available at instructor station and pump station.

22. Underground Drain Tank. On conclusion of exercises, flood water should be discharged under gravity to the underground drain tank through drain trough below the simulators. The underground drain tank should be of capacity to hold the three times the volume of water drained in consecutive exercises in DC and FF simulators. A suitable water filtration unit should also be provided to filter and treat the sump water prior pumping water to the overhead tank. The tank should be provided with water level sensors and indication of the same to be available at instructor station and pump station.

23. Water Transfer System. The water transfer system should be divided in following systems:-

(a) Underground Drain Tank to Overhead Tank. To transfer water from underground drain tank to the overhead tank. The system should have at least two identical transfer pump of suitable capacity to fill the overhead tank in not more than 30 minutes of pump operation of a single pump. The system should be integrated with the water treatment system.

(b) Overhead Tank to DC Simulator. The system should transfer water to the system pipelines and the compartment flooding systems. The system should have provision to drain water by gravity to the system pipelines and also using pressure pumps to regulate the rate of flow of water. Necessary safeties to be provided in the system to prevent damage due to the pressure rise while blocking the leaking holes during the conduct of exercise. This

30

system should be provided with pressuring capabilities and flow control in order to simulate the varying flow rate & pressure based on the depth of the submarine.

(c) Overhead Tank to FF Simulator. The system should transfer the water from the overhead tank to the consumers in the FF Simulator. The water should be supplied to the AFFF extinguisher system under gravity, however the water for the torpedo sprinkling system and water mist system should be provided under pressure based on design.

24. Water Treatment System. A suitable water treatment unit should be provided to filter and treat the sump water prior pumping water from the underground drain tank to the overhead tank. The treatment system should also be capable to treat the water in the overhead tank and underground drain tank in case of non utilization of water for a long duration. The treatment system should prevent any biological growth in the water and maintain the requisite pH to avoid degradation of piping and structural components.

25. Material for Construction. Materials used should be appropriate for their intended use, and should be able to withstand rigor of the training environment, which includes heat, thermal shocks and physical forces of extinguishing water applications during the training. Selected materials should not produce any harmful toxic effects/ by products.

31

SECTION E

SUPPORT SYSTEM

1. Power Management System. The buyer’s scope for the power supply should be till the incoming main electric power supply pole. The responsibility of receiving the supply from the pole till final distribution to all consumers of the training facility is the scope of the Seller.

2. Emergency Power Supply. In the event of failure of the incoming state electricity power supplies, provision is to be made for automatic switching over to own generated power supply. For this purpose, a Self excited and self Regulated brushless Battery started Diesel Generator set of suitable capacity to cater for the maximum peak load of the training facility should be provided.

3. Compressed Air System. A compressed air system to cater for the requirement of air leak simulations in DC simulator and the water mist generators in DC & FF simulators should be provided in the training facility. One air compressor of suitable capacity and pressure rating for handling the requirement to be provided with necessary control system for automatic operation so as to meet the dynamic requirements of compressed air by the simulator.

4. BA Set Charging Facility. A dual redundancy BA set charging facility along with the charging point to charge used BA sets also should provided in the training facility at appropriate location. The facility should have a breathing air Compressor along with associated fittings which can charge BA sets and sufficient points so as to charge at the rate of five BA sets per hour.

5. Fuel Storage and Distribution System. The location of the propane tank storage and distillate fuels necessary will be in accordance with the existing state regulations. The size of the propane storage tank/ cylinder facility is to be determined for undertaking at least 30 fire exercises (all fire burners operated together) per month without requirement of refill. Underground propane storage facility may be provided, if deemed necessary. Propane storage area is to be provided with sprinkling system for temperature control. The distribution of the fuels will be through a system of pipes with necessary manifolds and valves of acceptable specification. The distribution system should be designed to simulate the fires in the fire compartment in accordance with demand irrespective of the number of burners in use. The gas is to be supplied to simulators through steel pipes and flash back arrestor is to be provided for safety of the propane gas system. The propane gas system is to be provided with gas flow meter to enable monitoring and accounting the gas consumption. The gas storage facility is to be designed and established in accordance with CCOE/PESO norms and is to be governed by static and mobile pressure vessel code 1981 (or newer, if any).

32

6. Obtaining the governmental clearances for setting up the propane storage facility shall be the responsibility of the seller. However, all the documents for this purpose from Indian Navy shall be provided on request of the Seller.

7. First Aid Post. The training facility will be provided with integral first aid/ medical emergency room with necessary medical equipment.

8. Maintenance Area. A maintenance area for undertaking the primary maintenance of the equipment and training gear of training facility is to be constructed within the complex of the training facility.

9. Training Equipment. Following training equipment are to be provided. The design/ model of these equipment will be the contemporary design/ model being used by the IN at the time of delivery.

Sl Equipment Quantity (a) Emergency Life Support Apparatus 50 (b) Compressed Air Breathing Apparatus 50 (c) Bristol suits/ Aluminised Fire proximity suit 15 (d) Thermal Imaging Camera 03 (e) Portable Communication Sets (Motorola) 10 (f) DC box (Comprising of all tools for damage control 05 exercises as existing in the submarines)

(g) Portable CO2 / Halon Extinguisher 20 (h) DCP Extinguisher 15 (j) AFFF Extinguisher 20 (k) Flood Light 15 (l) Breathing lines with Mask for BIBs 50 (m) Training sets for Oxyboks/ Rakshakavach. 20

33

SECTION F

TRAINING AND ADMINISTRATION COMPLEX

1. The training facility is to include a training and administration complex to support the DC and FF Simulators. The training and administration complex should follow GRIHA Norms. The requirement for the Training and administration complex is enumerated in following paragraphs. However, additional requirement based on the design are to be included in the facility. All the rooms and facilities in the training and administration complex should be furnished with all computers, work stations, furniture upholstery, accessories etc.

2. Training Class Room and Training Aids. The training facility will have two class rooms with necessary training aids separately earmarked to cater to class strength of 25 trainees at a time. The class rooms should be equipped with a projection system along with computers so that the exercises in the training facility can be played back to the trainees for analysis of their actions/errors. The number of Training aids should cater to 25 trainees being simultaneously trained at the facility. The classrooms should also be equipped with the seating arrangement for trainees and instructors.

3. Toilets /Change Room. The training facility will have adequate number of male and female showering and changing facilities including toilets along with the adequate number of storage lockers for trainees.

4. Storage Area. The training facility will have adequate store rooms of sufficient area to store the protective clothing and equipment etc. Lockers and other stowage arrangements are to be provided in these storage areas.

5. Office Space. Following office space to be provided in the training facility:-

(a) Office space for Officer in-charge of the facility. (b) Office space for Instructors. (c) Office space for maintenance of crew. (d) Conference hall for seating 12 personnel.

6. HVAC System. A suitable centralized Heating Ventilation and Air conditioning (HVAC) system for the complex to be provided.

7. Handling Equipment. One Vehicle for transportation of equipment and one fork lift of suitable capacity for movement of equipment within the training facility to be provided.

34

SECTION G

ADDITIONAL WORKS & SERVICES

1. The bidder should offer the complete service ranging from conceptual studies through detailed design, fabrication, installation, commissioning and maintenance post commissioning. The bidder should also quote for developing the area around the facility by landscaping and arboriculture.

Civil Works

2. The following civil works should be required for the operation of the Training Facility:-

(a) Administrative and Training Infrastructure

(b) DC & FF Simulator Shed

(c) Underground Sump

(d) Overhead Tank

(e) Pump Room

(f) Change rooms & Showers space

(g) DG and Switchboard Room

(h) R.C.C. foundation Simulators

(i) Area and security lighting of complex

(j) Any other work necessary as deemed mandatory for the training facility

3. Detailed designs / drawing of all the above works should be made after carrying out soil testing, survey work and analyzing various forces on structure by the Seller. All the civil works structural design and drawings should be approved by a recognized agency. Permission to cut trees shall be taken by the Navy and the actual clearance of trees shall be part of seller’s scope of work

4. Roads. Lateral roads and leveling of ground after surveying, laying of tar road around training facility unit would be required to be carried out, if required.

5. Fencing. Fencing around the training facility is to be provided of approved design.

35

All Inclusive Comprehensive Annual Maintenance Contract (AIAMC)

6. The AIAMC is to be provided by the Seller through complete life of the training facility (as defined at Section A) to carry out maintenance and defect rectification of training facility inclusive of spares. The repair and maintenance philosophy for the training facility post warranty will be provided by the Seller, through the AIAMC. The Seller would be committed to provide Indian Navy the requisite spares and consumables for maintenance of the training facility to ensure its long term serviceability. The consumables required during the course of training operations would be supplied by the Indian Navy.

7. The AIAMC package will support the following maintenance tasks:

(a) Rectification of defects as soon on reporting of the same. (b) Consultancy on technical issues. (c) Planned preventive maintenance as per recommendation of the OEM (d) Onsite maintenance support by Seller’s personnel. (e) Component and sub assembly level repairs/ replacement (as applicable) of the equipment/ sub equipment would be undertaken by the Seller at no extra cost. (f) In case of malfunction of any major equipment and sub-equipment of the training facility, joint analysis would be undertaken by both Navy and the firm to determine whether the malfunction is attributed to operator error or material failure/ equipment breakdown. (g) All major equipment, sub equipment and components (including auxiliary equipment like air conditioners, diesel generators etc) fitted in the training facility will fall under the purview of the AIAMC.

8. The Seller should design the training facility to achieve an availability factor of 92%.

9. In case, the defective equipment/ component is required to be taken to the Sellers site of repairs, the Seller will make arrangements for collection, transportation and return of the same to the Buyer. The Seller will be required to give a replacement during this period.

Training

10. The training in the simulator would be conducted by the SELLER, following Operator – Trainer – Maintainer concept, where in the simulator complex would be operated and maintained by the OEM hired personnel. The training would be conducted by OEM hired personnel under supervision of IN crew.

36

Inspection

11. All structures of the training unit are to be designed as per standard plates and sections available in India and FEM analysed for IRS approval. Systems and equipment in the training facility that do not fall under the IRS scope are to be approved by Indian Naval Agencies. The Navy will approve all drawings pertaining to the training facility including system drawings. The OEM will certify all commercial items. The acceptance test and issuance of certificate of compliance for fire simulation system would be carried out be an approved mutually agreed third party.

37

Appendix B (Refers Para 6)

INFORMATION PROFORMA (INDIAN VENDORS)

1. Name of the Vendor/Company/Firm.

(Company profile, in brief, to be attached)

2. Type (Tick the relevant category).

Original Equipment Manufacturer (OEM) Yes/No

Authorised Vendor of foreign Firm Yes/No (attach details, if yes)

Others (give specific details)

3. Contact Details.

Postal Address:- __ _

City : State :

Pin Code : Tele :

Fax : URL/Web Site:

4. Local Branch/Liaison Office in Delhi (if any).

Name & Address:

Pin code : Tel : Fax :

5. Financial Details.

(a) Category of Industry (Large/medium/small Scale) : __

(b) Annual turnover : (in INR)

(c) Number of employees in firm:

(d) Details of manufacturing infrastructure :

(e) Earlier contracts with Indian Ministry of Defence/Government agencies :

38

Contract Number Equipment Quantity Cost

6. Certification by Quality Assurance Organisation.

Name of Agency Certification Applicable from Valid till (date & (date & Year) year)

7. Details of Registration

Agency Registration No Validity (Date) Equipment

DGS&D DGQA/DGAQA/DGNAI OFB DRDO Any other Government Agency

8. Membership of FICCI/ASSOCHAM/CII or other Industrial Associations

Name of Organization Membership Number

9. Equipment/Product Profile (to be submitted for each product separately)

(a) Name of Product :

(IDDM Capability to be indicated against the product)

(Should be given category wise for eg. All products under night vision devices to be mentioned together)

(b) Description (attach technical literature):

(c) Whether OEM or Integrator :

(d) Name and address of Foreign collaborator(if any):

(e) Industrial License Number:

(f) Indigenous component of the product (in percentage):

(g) Status (in service /design & development stage):

39

(h) Production capacity per annum:

(j) Countries/agencies where equipment supplied earlier (give details of quantity supplied):

(k) Estimated price of the equipment

10. Alternatives for meeting the objectives of the equipment set forth in the RFI.

11. Any other relevant information:

12. Declaration. It is certified that the above information is true and any changes will be intimated at the earliest

Note : Para 44 and Appendix F to Chapter II may be refered

(Authorised Signatory)

40

INFORMATION PROFORMA (FOREIGN VENDORS)

1. Name of the Vendor /Company /firm. ______(Company profile, in brief, to be attached)

2. Type (Tick the relevant category).

Original Equipment Manufacturer (OEM) Yes/No

Government Sponsored Export Agency Yes/No (Details of Registration to be provided)

Authorised Vendor of OEM Yes/No (attach details)

Others (give specific details) ______

3. Contact Details.

Postal Address: ______

City : ______Province: ______

Country: ______Pin/Zip Code:______

Tele: ______Fax:______

URL/Web Site:______

4. Local Branch /Liaison Office/Authorised Representatives, in India (if any).

Name & Address: ______

City: ______Province: ______

Pin Code: ______Tel: ______Fax:______

5. Financial Details.

(a) Annual Turnover:______USD

(b) Number of Employees in firm ______

(c) Details of manufacturing infrastructure available ______

41

(d) Earlier contracts with Indian Ministry of Defence/Government agencies:

Agency Contract Number Equipment Quantity Cost

6. Certification by Quality Assurance Organisation (if applicable).

Name of Agency Certification Applicable from Valid till (Date & Year) (Date & Year)

7. Equipment /Product Profile (to be submitted for each product separately)

(a) Name of Product: ______(Should be given category wise for e.g. all products under night vision devices to be mentioned together) (b) Description (attach technical literature): ______(c) Whether OEM or Integrator:______(d) Status (in Service/Design Development stage):______(e) Production capacity per annum:______(f) Countries where equipment is in service:______(g) Whether export clearance is required from respective Government:______(h) Any Collaboration/Joint Venture/Co-production/Authorised dealer with Indian Industry (give details): Name & Address:______Tel:______Fax:______(j) Estimated price of the equipment ______

8. Alternatives for meeting the objectives of the equipment set forth in the RFI.

9. Any other relevant information______

10. Declaration. It is certified that the above information is true and any changes will be intimated within five (05) working days of occurrence.

(Authorized Signatory)