Renwick Gallery Renovation American

1661 NW Washington, DC ______

Submitted by the

Preliminary and Final Approval Project Information

Commission meeting date: September 12, 2013 NCPC review authority: Federal projects in the District of Columbia - 40 U.S.C. § 8722(b)(1) and (d) Applicant request: Approve preliminary site and building plans Delegated / consent / open / executive session: Delegated NCPC Review Officer: J. Hirsch NCPC File number: 7518

Project summary: The Smithsonian Institution has submitted preliminary and final site and building plans for the Renwick Gallery Renovation. The Renwick Gallery is a National Historic Landmark that was originally constructed as the beginning in 1859. The last major renovation for the building was completed from 1967 to 1972 when it was restored to an art gallery after being used for other purposes for several decades. Since the 1967-1972 renovation, when the building’s first modern systems were installed, incremental improvements have been made, including exterior masonry repair and restoration, interior exhibit gallery improvements and other infrastructure repairs. However, most of the existing building systems date to the initial renovation and have reached or surpassed the point of useful service. In addition, the building does not comply with current life safety codes and has deficiencies relate to compliance with current accessibility requirements. The purpose of the propose renovation is to replace and renovate major infrastructure systems and improve interior conditions to ensure the preservation of the building and provide safe and sustainable building conditions for efficient operations, presentation and preservation of the collection, and a superior visitor experience.

The primary focus of the proposed renovation is the interior which will have limited impacts on the exterior of the building. The following summarizes the exterior alterations: 1) a new elevator penthouse will project above the central roof plane, to enable the elevator run to extend to upper mechanical equipment levels, providing safe access for maintenance; 2) exterior windows will be replaced with new high-performance custom units with frame, muntin and glass division characteristics and profiles to match historic design; 3) the existing wheelchair ramp at the 17th Street side will be replaced with a new, compliant, concrete ramp with improved railing and lighting; and 4) the existing exterior egress stair in the alley north of the building will be modified, with improvements to address life safety codes. 2 Project Information

Project summary: Other items included in the project will impact the exterior, but there will be no notable change to the building’s appearance. This includes the following: 1) roofing will be installed at the majority of roof surfaces, where existing roofing is near its end of service life. (Character-defining slate mansards and decorative metal roof components shall remain as existing, with repairs where necessary.); 2) masonry facades will be repointed and repaired as needed; 3) roof gutters and storm leaders on the north and east facades are deteriorated, and will be replaced in kind. (South and west gutters and leaders were previously rehabilitated and are in good condition.); 4) existing damaged exterior plaster at the base of the building will be restored; 5) new water, sewer, and stormwater mains will be installed, with no change to the streetscape anticipated; and 6) existing gas, electric, and data service mains will remain.

3 Project Location

4 Existing and Proposed Roof Conditions

5 Existing Roof Conditions

6 Proposed Roof Conditions

Design proposed in 2011 would altered historic roof framing and had potential for adverse effect on historic 7 resource; proposed design minimizes effects and reduces visual impacts Viewshed analysis

Smithsonian mocked up location for elevator extension to analyze potential effects on historic and visual resources 8 Viewshed analysis

9 Viewshed analysis

10 Window Replacement

34 windows will be replaced with aluminum frame windows with steel reinforcing

11 Window Replacement

12 Window Replacement

13 Window Replacement

14 Existing Conditions – Ramp at 17th Street

15 New Ramp at 17th Street

16 Egress Stair

Egress stair between Renwick Gallery and the Executive Office Building will be modified to incorporate code upgrades and provide access to the adjacent cooling tower platform 17 Egress Stair

18