<<

4/17/2018

West and Ballard Link Extensions

Stakeholder Advisory Group Meeting | April 17, 2018

Agenda

Welcome & Introductions Previous Meeting Summary What We Heard – March Alternatives Development Process Level 1 Alternatives Evaluation Results Next Steps & Next Meeting

1 4/17/2018

What we heard - March

Early Scoping Summary Report

• Early scoping: Feb. 2 – March 5 • 3 public meetings, 1 agency meeting and online open house • 2,800+ total comments received via meetings and other methods • All comments captured in Early Scoping Summary Report

2 4/17/2018

External Engagement Report: March 2018

Neighborhood forums Spring Schedule

• 4/21: Chinatown / Int’l District

• 4/23: Denny / SLU / Seattle Center

• 5/2: Midtown / Westlake

• 5/5: Delridge / Avalon / Alaska Junction

• 5/9: SODO / Stadium

• 5/12: Ballard / Interbay / Smith Cove

6

3 4/17/2018

Alternatives development process

Community engagement and collaboration

8

4 4/17/2018

Alternatives development process

LEVEL 1 LEVEL 2 LEVEL 3 PREFERRED Alternatives development Alternatives development Alternatives development ALTERNATIVE*

Early-2018 Mid-2018 Late-2018 / Early-2019 Early-2019

Conduct early scoping Technical analysis Refine and screen alternatives Study ST3 representative Refine and screen project and alternatives alternatives Conduct Environmental Impact Statement Screen alternatives (EIS) scoping

PUBLIC INVOLVEMENT PUBLIC INVOLVEMENT PUBLIC INVOLVEMENT

*The Sound Transit Board identifies preferred alternatives and other alternatives to study.

Where we’re going

Getting to a Level 1 recommendation

• Today’s meeting, April 17th – Learn about the Level 1 alternatives and evaluation results • Next meeting, April 24th – Collectively make recommendations that will be shared with the Elected Leadership Group and Sound Transit Board

5 4/17/2018

Screening process

Broad range of initial alternatives

Refine remaining alternatives

Further evaluation

Preferred Alternative

Purpose and need

• Provide high quality rapid, reliable, and efficient peak and off-peak light rail transit service to communities in the project corridors defined in ST3.

• Improve regional mobility by increasing connectivity and capacity through to meet projected transit demand.

• Connect regional growth centers as described in adopted regional and local land use, transportation, and economic development plans and Sound Transit’s Regional Transit Long-Range Plan.

• Implement a system that is consistent with the ST3 Plan that established transit mode, corridor, and station locations and that is technically feasible and financially sustainable to build, operate, and maintain.

• Expand mobility for the corridor and region’s residents, which include transit dependent, low income, and minority populations.

• Encourage equitable and sustainable urban growth in station areas through support of transit-oriented development, station access, and modal integration in a manner that is consistent with local land use plans and policies.

• Preserve and promote a healthy environment and economy by minimizing adverse impacts on the natural, built and social environments through sustainable practices.

6 4/17/2018

Evaluation criteria

• Reliable service • Financial sustainability • Travel times • Historically underserved populations • Regional connectivity • Station area land use plan consistency • Transit capacity • Modal integration • Projected transit demand • Station area development opportunities • Regional growth centers served • Environmental effects • ST Long-Range Plan consistency • Traffic operations • ST3 consistency • Economic effects (new) • Technical feasibility

Purpose and need Provide high quality rapid, reliable and efficient peak and off-peak light rail transit service to communities in the project corridors defined in ST3

Level 1 criteria and measure Reliable service • Potential service interruptions and recoverability Travel times • Light rail travel times

14

7 4/17/2018

Purpose and need Improve regional mobility by increasing connectivity and capacity through downtown Seattle to meet projected transit demand

Level 1 criteria and measure Regional connectivity Projected transit demand • Network integration and operational • Ridership potential flexibility to meet future demand Transit capacity • Passenger carrying capacity in downtown

15

Purpose and need Connect regional growth centers as described in adopted regional and local land use, transportation and economic development plans and Sound Transit’s Long-Range Plan

Level 1 criteria and measure Regional centers served • Station proximity to PSRC-designated regional centers Sound Transit Long-Range Plan consistency • Accommodates future light rail extensions beyond ST3

16

8 4/17/2018

Purpose and need Implement a system that is consistent with the ST3 Plan that established transit mode, corridor and station locations and that is technically feasible and financially sustainable to build, operate and maintain Level 1 criteria and measures

ST3 consistency Financial sustainability • Mode, route and general station • Qualitative capital cost locations per ST3 comparison • Potential operating plan effects Technical feasibility • Engineering constraints • Constructability issues • Operational constraints

17

Purpose and need Expand mobility for the corridor and region’s residents, which include transit dependent, low income and minority populations

Level 1 criteria and measure Historically underserved populations • Opportunities for historically underserved populations

18

9 4/17/2018

Purpose and need Encourage equitable and sustainable urban growth in station areas through support of transit-oriented development, station access and modal integration in a manner that is consistent with local land use plans and policies Level 1 criteria and measures Station area land use plan Station area development consistency opportunities • General station locations consistent with • Development potential local land use plans • Station proximity to Seattle-designated urban centers / villages Modal integration • Bus / rail and rail / rail integration • Bicycle, pedestrian and persons

with limited mobility connectivity 19

Purpose and need Preserve and promote a healthy environment and economy by minimizing adverse impacts on the natural, built and social environments through sustainable practices

Level 1 criteria and measure Environmental effects Economic effects • Protected natural resources • Freight movement and access • Protected built and social environment on land and water • Burden on historically underserved • Business and commerce effects populations Traffic operations • Traffic circulation and access

20

10 4/17/2018

Level 1 alternatives evaluation

West Seattle/ Duwamish

Interbay/Ballard

Downtown

SODO ST3 Representative Project Study segments 22

11 4/17/2018

Avoids Dravus interchange

Fixed bridge supports more reliable service

= Key Findings

(Compared to ST3 Representative Project) Sample segment Key Level 1 findings – Sample alternative 23

Sample segment Sample alternative

Evaluation Measures

Fixed bridge supports more reliable service

ST3 Representative Project (Baseline)

Elliott/15th / 16th / Fixed Bridge

West of BNSF / 20th / 17th / Fixed Bridge

West of BNSF / 20th / 17th / Tunnel

East of BNSF/14th/Movable Bridge

Elliott/Armory Avoids Dravus Way/14th/Tunnel interchange

West of BNSF / 20th / Tunnel

Higher Performance Comparable Performance Lower Performance

12 4/17/2018

Sample segment summary

ST3 Representative Project • Baseline for comparison • Avoids 15th Ave/Dravus interchange Alternatives with Elliott/15th/16th/Fixed Bridge more potential • Supports more reliable service Alternative • Key findings

Alternative • Key findings Alternatives with greater challenges Alternative • Key findings

Not practical Alternative • Key findings suggestions Alternative • Key findings

25

• Map of alternative

• Evaluation measures

• Segment summary

• Small Group Discussion

13 4/17/2018

Intentionally blank

Level 1 alternatives

West Seattle/Duwamish

• ST3 Representative Project

• Pigeon Ridge/West Seattle Tunnel

• West Seattle Bridge/ Fauntleroy

• Yancy Street/West Seattle Tunnel

• Oregon Street/Alaska Junction

• West Seattle Golf Course/ Alaska Junction

28

14 4/17/2018

West Seattle/Duwamish Early scoping feedback 29

West Seattle/Duwamish Level 1 alternatives 30

15 4/17/2018

Difficult design Design and construction and construction constraints through at Pigeon Point Duwamish

Good coverage of rider sheds

Neighborhood impacts

Terminal station is constrained; difficult = Key Findings extension to south West Seattle/Duwamish Key Level 1 findings – ST3 Representative Project 31

West Seattle/Duwamish ST3 Representative Project

Evaluation Measures

ST3 Representative Project (Baseline)

Pigeon Ridge / West Seattle Tunnel

West Seattle Bridge / Fauntleroy

Yancy Street / West Seattle Tunnel

Oregon Street / Alaska Junction

West Seattle Golf Course / Alaska Junction

Higher Performance Comparable Performance Lower Performance

16 4/17/2018

Avoids major Two tunnels and Port areas underground stations

Fewer neighborhood impacts Potential in-water work in Lower Duwamish Superfund site

Improved transition to extend south in future = Key Findings

(Compared to ST3 Representative Project) West Seattle/Duwamish Key Level 1 findings – Pigeon Ridge/West Seattle Tunnel 33

West Seattle/Duwamish Pigeon Ridge/ West Seattle Tunnel

Evaluation Measures

Two tunnels; potential constructability and cost issues; fewer curves

ST3 Representative Project (Baseline)

Pigeon Ridge / West Seattle Tunnel

West Seattle Bridge / Fauntleroy

Yancy Street / West Seattle Tunnel Duwamish crossing- Good future Oregon Street / possible Superfund Alaska Junction extension to site, in-water work, south West Seattle Golf golf course edge Course / Alaska Junction

Higher Performance Comparable Performance Lower Performance

17 4/17/2018

Design and construction Isolated station; constraints through Port areas near Port property

Avoids Delridge neighborhood but affects properties along Fauntleroy

Avoids Pigeon Point

Avoids sensitive natural areas

Improved transition to extend south in future = Key Findings

(Compared to ST3 Representative Project) West Seattle/Duwamish Key Level 1 findings – West Seattle Bridge/Fauntleroy 35

West Seattle/Duwamish West Seattle Bridge/ Fauntleroy

Evaluation Measures

Good future extension to south

ST3 Representative Project Avoids sensitive (Baseline) environmental areas

Pigeon Ridge / in Pigeon Point and West Seattle Tunnel Longfellow Creek

West Seattle Bridge / Fauntleroy

Yancy Street / West Seattle Tunnel Affect Port and Oregon Street / Alaska Junction business operations

West Seattle GolfDelridge and Alaska Junction Course / Alaska Junction stations on periphery of land use centers Higher Performance Comparable Performance Lower Performance

18 4/17/2018

Lessens effects to Design and construction neighborhoods but constraints through Port areas passes over Nucor

Avoids Pigeon Long tunnel Point

Consolidates stations; less pop/emp served

Improved transition to extend south in future = Key Findings

(Compared to ST3 Representative Project) West Seattle/Duwamish Key Level 1 findings – Yancy Street/West Seattle Tunnel 37

Yancy Street/ West West Seattle/Duwamish Seattle Tunnel

Evaluation Measures

Consolidates stations; lessless pop/pop/emp servedserved

ST3 Representative Project (Baseline)

Pigeon Ridge / West Seattle Tunnel Fewer neighborhood impacts West Seattle Bridge / Fauntleroy

Yancy Street / West Seattle Tunnel

Oregon Street / Alaska Junction Affects Port West Seattle Golf Doesn’t directly serve and business Long tunnel; Course / Alaska Avalon and Delridge Junction operations potential cost issues land use centers Higher Performance Comparable Performance Lower Performance

19 4/17/2018

Design and construction Avoids Pigeon constraints through Port areas Point

Affects Oregon St and 44th Ave

Avoids Fauntleroy and Alaska St

= Key Findings

Improved transition to (Compared to ST3 extend south in future Representative Project) West Seattle/Duwamish Key Level 1 findings – Oregon Street/Alaska Junction 39

Oregon Street/ West Seattle/Duwamish Alaska Junction

Evaluation Measures

Good transit integration at Alaska Junction Station

ST3 Representative Project (Baseline)

Pigeon Ridge / West Seattle Tunnel Generally similar Affects Port and business operations, to Representative West Seattle Bridge / Project Fauntleroy and also near California Yancy Street / West Seattle Tunnel

Oregon Street / Alaska Junction

West Seattle Golf Course / Alaska Junction Affects Oregon St Higher Performance Comparable Performance Lower Performance and 44th Ave

20 4/17/2018

Eliminates station; less pop/emp served

Fewer neighborhood impacts

Short tunnel with station under Alaska St Affects Golf Course (4(f) resource); requires demonstrating no other prudent and feasible alternative = Key Findings

(Compared to ST3 Representative Project) West Seattle/Duwamish Key Level 1 findings – West Seattle Golf Course/Alaska Junction 41

West Seattle/Duwamish West Seattle Golf Course / Alaska Junction

Evaluation Measures

Doesn’t serve Avalon; affects golf course

ST3 Representative Project Eliminates station; (Baseline) less pop/emp servedPigeon Ridge / West Seattle Tunnel

West Seattle Bridge / Fauntleroy

Yancy Street / West Seattle Tunnel Golf course 4(f) resource; potential habitat impacts; Oregon Street / Alaska Junction some fewer residential impacts

West Seattle Golf Course / Alaska Junction

Higher Performance Comparable Performance Lower Performance

21 4/17/2018

Section 4(f)

• Stipulates that United States Department of Transportation (USDOT) agencies, such as the Federal Transit Administration (FTA), cannot approve the use of land from publicly owned parks, recreational areas, wildlife and waterfowl refuges, or public and private historical sites unless:

- There is no feasible and prudent avoidance alternative to the use of land; and includes all possible planning to minimize harm to the property resulting from such use; OR - The Administration determines that the use of the property will have a de minimis impact

43

Intentionally blank

22 4/17/2018

West Seattle/Duwamish summary ST3 Representative Project • Baseline for comparison

Alternatives • Avoids Fauntleroy and Alaska; better orientation south Oregon Street/Alaska Junction with more • Affects Oregon St and 44th Ave potential • Lessens effects to Junction and Delridge; better orientation south West Seattle Bridge/Fauntleroy • Creates isolated Delridge Station Pigeon Ridge/West Seattle Tunnel • Lessens effects to Port, Junction, Delridge; better orientation south • Requires two tunnels; may require 3rd Party funding • Lessens effects to Junction and Delridge; better orientation south Alternatives Yancy Street/West Seattle Tunnel • Consolidates stations; potentially not consistent with ST3 Plan with greater • Requires tunnel; may require 3rd Party funding challenges • Crosses golf course, Section 4(f) West Seattle Golf Course/Alaska • Lessens effects to Junction, Delridge Junction (Tunnel) • Eliminates station; potentially not consistent with ST3 Plan Tunnel under Duwamish • Impractical tunnel depth and length • Existing structure not built to accommodate LRT Not practical West Seattle Bridge suggestions • Constructability issues Gondola, rail/bus bridge • Mode not consistent with ST3 Plan Extensions to Alki, Admiral, etc. • Not included in ST3 Plan or long range plan 45

West Seattle/Duwamish Level 1 alternatives 46

23 4/17/2018

Intentionally blank

Level 1 alternatives

SODO

• ST3 Representative Project

• Massachusetts Tunnel Portal

• Surface E-3

48

24 4/17/2018

SODO Early scoping feedback 49

SODO Level 1 alternatives 50

25 4/17/2018

Temporary impact to Ryerson Base Modifications to WSDOT during construction ramps and potential Limited area for impacts to planned “S” construction phasing development

Ground improvements Cut-and-cover construction required for elevated guideway Temporary closure of potential impacts along 5th and elevated SODO Station Royal Brougham for cut- Avenue S and-cover construction

= Key Findings SODO 51 Key Level 1 findings – ST3 Representative Project 51

SODO ST3 Representative Project

Evaluation Measures

ST3 Representative Project (Baseline)

Massachusetts Tunnel Portal

Surface E-3

Higher Performance Comparable Performance Lower Performance

26 4/17/2018

Avoids impact to Ryerson Base

Grade separation Avoids modifications to at Holgate WSDOT ramps and potential impacts to “S” development

Reduced need for More property Longer tunnel; Reduces cut-and-cover ground improvements required poor soils construction on 5th Ave in for elevated guideway Chinatown/Int’l District

= Key Findings

(Compared to ST3 Representative Project) SODO Key Level 1 findings – Massachusetts Tunnel Portal 53

SODO Massachusetts Tunnel Portal

Evaluation Measures

ST3 Representative Project (Baseline)

Massachusetts Tunnel Portal

Surface E-3

Higher Performance Comparable Performance Lower Performance Reduces potential effects to freight, traffic, and business during construction Avoids potential effects to Longer tunnel historic INS building; alignment; more reduces cut-and-cover in property required Chinatown/Int’l District

27 4/17/2018

Permanent impact Increased area available to Ryerson Base Potential permanent Grade separation at for construction; less closure of Royal Lander and Holgate service disruption Brougham

At-grade SODO Stadium Station on Station Reduced need for both lines ground improvements Avoids modifications to for elevated guideway WSDOT ramps

= Key Findings

(Compared to ST3 Representative Project) SODO Key Level 1 findings – Surface E-3 55

SODO Surface E-3

Evaluation Measures

ST3 Representative Project (Baseline)

Massachusetts Tunnel Portal

Surface E-3

Higher Performance Comparable Performance Lower Performance

Improves light rail network reliability; Eliminates existing grade crossings at Avoids modifications to WSDOT two Stadium Stations provides greater Lander and Holgate Streets ramps; increased area available for regional connectivity construction; less service disruption

28 4/17/2018

International District/Chinatown Station

57

International District/Chinatown Station

58

29 4/17/2018

International District/Chinatown Station

59

Intentionally blank

30 4/17/2018

SODO summary

ST3 Representative • Baseline for comparison Alternatives Project with more potential • Less service disruption during construction Surface E-3 • Accommodates Stadium Station on both lines • Eliminates existing grade crossings at Lander, Holgate; closes Royal Brougham • Reduces cut-and-cover construction on 5th Ave in Chinatown/Int’l District • Less service disruption during construction Massachusetts Portal • Eliminates existing grade crossing at Holgate • Requires longer tunnel; more property; may require 3rd Party funding

Maintain buses on E-3 • Not practical due to ROW constraints

Not practical suggestions First Ave alignment • Alignment and stations locations not consistent with ST3

Design for potential extension south to • Not included in ST3 or long range plan Georgetown

61

SODO Level 1 alternatives 62

31 4/17/2018

Intentionally blank

Level 1 alternatives

Downtown Seattle

• ST3 Representative Project

• 5th/Mercer

• 5th/Harrison

• 6th/Boren/Roy

• 8th/6th/Republican

• 5th/Roy/Consolidated SLU Station

64

32 4/17/2018

Downtown Early scoping feedback 65

Downtown Level 1 alternatives 66

33 4/17/2018

Tunnel portal in limited ROW

Underground sewer conflict on Republican Street

Station under Tunnel construction SR 99 off-ramp through/under building tie-backs

= Key Findings Downtown Key Level 1 findings – ST3 Representative Project 67

Downtown ST3 Representative Project

Evaluation Measures

ST3 Representative Project (Baseline)

5th/Harrison

5th/Mercer

6th/Boren/Roy

8th/6th/Republican

5th/Roy/Consolidated SLU Station

Higher Performance Comparable Performance Lower Performance

34 4/17/2018

Station construction under existing Westlake Station Reduced underground sewer conflict

Shorter alignment

Decreased station area = Key Findings coverage; potentially move (Compared to ST3 Representative Project) Denny Station south Downtown Key Level 1 findings – 5th/Harrison 69

Downtown 5th/Harrison

Construction Evaluation Measures under existing Westlake Station Generally comparable to more challenging ST3; off-setting pros/cons

ST3 Representative Project (Baseline)

5th/Harrison

5th/Mercer

6th/Boren/Roy

8th/6th/Republican

5th/Roy/Consolidated SLU Station

Higher Performance Comparable Performance Lower Performance

35 4/17/2018

Tunnel portal near steep slope and in park property

Station construction under existing Westlake Station Larger underground sewer conflict on

Potential effects to Mercer during construction

Increased station = Key Findings area coverage Longer alignment (Compared to ST3 Representative Project) Downtown Key Level 1 findings – 5th/Mercer 71

Downtown 5th/Mercer

Evaluation Measures

Larger underground sewer conflict on Mercer Street; construction under existing Westlake Station

ST3 Representative Tunnel portal Project on steep slope, (Baseline) park property

5th/Harrison

5th/Mercer

6th/Boren/Roy Potential effects to traffic and freight on 8th/6th/Republican Mercer during construction 5th/Roy/Consolidated SLU Station

Higher Performance Comparable Performance Lower Performance

36 4/17/2018

Tunnel portal near steep slope and in park property

Reduced underground sewer conflict

Tunnel construction under/adjacent to I-5 walls; avoids tiebacks on 5th Ave

= Key Findings Increased station Longer alignment area coverage (Compared to ST3 Representative Project) Downtown Key Level 1 findings – 6th/Boren/Roy 73

Downtown 6th/Boren/Roy

Evaluation Measures

Avoids underground sewer conflicts

ST3 Representative Project (Baseline) Seattle Center Station on edge of Uptown 5th/Harrison urban center; degraded ped/bike access 5th/Mercer

6th/Boren/Roy

8th/6th/Republican Tunnel portal on steep slope, 5th/Roy/Consolidated park property SLU Station

Higher Performance Comparable Performance Lower Performance

37 4/17/2018

Construction risk of Longer alignment, tunneling under I-5 at deeper station two locations

Location of Midtown Station not consistent with ST3 plan

= Key Findings

(Compared to ST3 Representative Project) Downtown Key Level 1 findings – 8th/6th/Republican 75

Downtown 8th/6th/Republican

Evaluation Measures

Midtown Station location not consistent with ST3 plan

ST3 Representative Project (Baseline) Longer alignment; construction under I-5; th 5 /Harrison deeper Midtown Station

5th/Mercer

6th/Boren/Roy

8th/6th/Republican

5th/Roy/Consolidated Longer walk/bike SLU Station distance to commercial core Higher Performance Comparable Performance Lower Performance

38 4/17/2018

Tunnel portal near steep slope and in park property

Station construction under existing Westlake Station Reduced underground sewer conflict

Number of stations not consistent with ST3 plan

= Key Findings Longer alignment (Compared to ST3 Representative Project) Downtown th Key Level 1 findings – 5 /Roy/Consolidated SLU Station 77

Downtown 5th/Roy/Consolidated SLU Station

Evaluation Measures Consolidated station reduces constructability issues

Number of stations not consistent with ST3 plan

ST3 Representative Project (Baseline) Seattle Center Station on edge of Uptown urban 5th/Harrison center; degraded ped/bike access 5th/Mercer

6th/Boren/Roy Tunnel portal on steep slope,

8th/6th/Republican park property

5th/Roy/Consolidated SLU Station Reduced traffic impacts during Higher Performance Comparable Performance Lower Performance construction

39 4/17/2018

Downtown summary ST3 Representative Project • Baseline for comparison

• Avoids utility conflicts on Republican and station under SR 99 off-ramp Alternatives with 5th/Harrison • Decreased station coverage; potentially move Denny Station south more potential • Avoids utility conflicts on Republican and station under SR 99 off-ramp 6th/Boren/Roy • Increases construction risk due to I-5 walls along 6th Ave; avoids tiebacks on 5th Ave

• Avoids utility conflicts on Republican and station under SR 99 off-ramp Alternatives with 5th/Mercer • Increases construction risk due to large sewer on Mercer greater challenges 5th/Roy/Consolidated SLU • Avoids utility conflicts on Republican and station under SR 99 off-ramp Station • Consolidates stations; potentially not consistent with ST3

• Increases construction risk due to two crossings under I-5 8th/6th/Republican (First Hill) • First Hill station not consistent with ST3

Use Downtown Seattle Transit • Existing DSTT capacity constraints Not practical Tunnel (DSTT) suggestions Design for potential extensions • Extensions to north and/or east not included in ST3 or long range plan to north and/or east

79

Downtown Level 1 alternatives 80

40 4/17/2018

Intentionally blank

Level 1 alternatives

Interbay/Ballard

• ST3 Representative Project

• Elliott/15th/16th/Fixed Bridge

• West of BNSF/20th/17th/Fixed Bridge

• West of BNSF/20th/17th/Tunnel

• East of BNSF/14th/Movable Bridge

• Elliott/Armory Way/14th/Tunnel

• West of BNSF/20th/Tunnel

82

41 4/17/2018

Interbay/Ballard Early scoping feedback 83

Interbay/Ballard Level 1 alternatives 84

42 4/17/2018

Proximity to existing bridge; constructability Affects traffic on Affects issues Elliott and 15th Fishermen’s Terminal

Fully grade separated alignment

Water crossing permits required Affects service reliability due to movable bridge Affects property in station area

= Key Findings Interbay/Ballard Key Level 1 findings – ST3 Representative Project 85

Interbay/Ballard ST3 Representative Project

Evaluation Measures

ST3 Representative Project (Baseline)

Elliott/15th / 16th / Fixed Bridge

West of BNSF / 20th / 17th / Fixed Bridge

West of BNSF / 20th / 17th / Tunnel

East of BNSF/14th/Movable Bridge

Elliott/Armory Way/14th/Tunnel

West of BNSF / 20th / Tunnel

Higher Performance Comparable Performance Lower Performance

43 4/17/2018

Affects Fishermen’s Avoids Dravus Terminal interchange

Fixed bridge supports more reliable service

= Key Findings

(Compared to ST3 Representative Project) Interbay/Ballard Key Level 1 findings – Elliott/15th/16th/Fixed Bridge 87

Interbay/Ballard Elliott/15th/16th/Fixed Bridge

Evaluation Measures

Fixed bridge potentially adds cost

Fixed bridge supports more reliable service

ST3 Representative Project (Baseline)

Elliott/15th / 16th / Fixed Bridge

West of BNSF / 20th / th 17 / Fixed Bridge Affects Fishermen’s

West of BNSF / 20th / Terminal 17th / Tunnel

East of Avoids Dravus BNSF/14th/Movable interchange Bridge

Elliott/Armory Way/14th/Tunnel

West of BNSF / 20th / Tunnel

Higher Performance Comparable Performance Lower Performance

44 4/17/2018

Longer Fixed bridge supports Long bridge span alignment Avoids Fishermen’s more reliable service over BNSF tracks; Terminal poor soils Proximity to historic district

Avoids Elliott and Construction and 15th Aves property displacement within Ballard core

= Key Findings

(Compared to ST3 Representative Project) Interbay/Ballard Key Level 1 findings – West of BNSF/20th/17th/Fixed Bridge 89

Interbay/Ballard West of BNSF/20th/17th/Fixed Bridge

Evaluation Measures

Fixed bridge potentially adds cost

Fixed bridge supports more reliable service

ST3 Representative Project (Baseline) Avoids Fishermen’s Terminal Elliott/15th / 16th / Fixed Bridge

West of BNSF / 20th / 17th / Fixed Bridge

West of BNSF / 20th / 17th / Tunnel

East of BNSF/14th/Movable Bridge Closer to Ballard Elliott/Armory historic core Way/14th/Tunnel

West of BNSF / 20th / Tunnel

Higher Performance Comparable Performance Lower Performance

45 4/17/2018

Avoids Fishermen’s Terminal Longer Tunnel supports more Long bridge span alignment reliable service; avoids over BNSF tracks; in-water construction poor soils

Avoids Elliott and 15th Aves

= Key Findings

(Compared to ST3 Representative Project) Interbay/Ballard Key Level 1 findings – West of BNSF/20th/17th/Tunnel 91

Interbay/Ballard West of BNSF/20th/17th/Tunnel

Evaluation Measures

Tunnel supports more reliable service

ST3 Representative Project (Baseline) Closer to Ballard historic core Elliott/15th / 16th / Fixed Bridge

West of BNSF / 20th / 17th / Fixed Bridge

West of BNSF / 20th / 17th / Tunnel

East of BNSF/14th/Movable th Bridge Avoids Elliott/15 , Tunnel potentially Fishermen’s Terminal adds cost Elliott/Armory Way/14th/Tunnel and Salmon Bay waterway West of BNSF / 20th / Tunnel

Higher Performance Comparable Performance Lower Performance

46 4/17/2018

Station near Terminal 91 but access constrained Avoids Fishermen’s from other areas At-grade Terminal alignment Water crossing permits required

Avoids Elliott and 15th Aves

Station within BINMIC Industrial area

= Key Findings

(Compared to ST3 Representative Project) Interbay/Ballard Key Level 1 findings – East of BNSF/14th/Movable Bridge 93

Interbay/Ballard East of BNSF/14th/Movable Bridge

Evaluation Measures

Stations within industrial areas

ST3 Representative Project (Baseline) Avoids Elliott Elliott/15th / 16th / th Fixed Bridge and 15 Ave

West of BNSF / 20th / 17th / Fixed Bridge

West of BNSF / 20th / 17th / Tunnel

East of BNSF/14th/Movable Bridge

Elliott/Armory Way/14th/Tunnel Station near Terminal 91 West of BNSF / 20th / Tunnel but access constrained from other areas Higher Performance Comparable Performance Lower Performance

47 4/17/2018

Constrained Avoids Fishermen’s construction areas Terminal

Tunnel supports more reliable service; avoids in-water construction

Avoids Elliott and 15th Aves Avoids Dravus and Nickerson interchanges

= Key Findings

(Compared to ST3 Representative Project) Interbay/Ballard Key Level 1 findings – Elliott/Armory Way/14th/Tunnel 95

Interbay/Ballard Elliott/Armory Way/14th/Tunnel

Evaluation Measures

Tunnel crossing supports more reliable service

ST3 Representative Project (Baseline)

Elliott/15th / 16th / Fixed Bridge

West of BNSF / 20th / 17th / Fixed Bridge Avoids Elliott/15th, West of BNSF / 20th / Fishermen’s Terminal th 17 / Tunnel and Salmon Bay East of waterway BNSF/14th/Movable Bridge

Elliott/Armory Way/14th/Tunnel

West of BNSF / 20th / Tunnel potentially Tunnel adds cost Stations within industrial areas Higher Performance Comparable Performance Lower Performance

48 4/17/2018

Avoids Fishermen’s Terminal Longer Tunnel supports more Long bridge span alignment reliable service; avoids over BNSF tracks; in-water construction poor soils

Construction and Avoids Elliott and displacement within 15th Aves Ballard core

= Key Findings

(Compared to ST3 Representative Project) Interbay/Ballard Key Level 1 findings – West of BNSF/20th/Tunnel 97

Interbay/Ballard West of BNSF/20th/Tunnel

Evaluation Measures

Tunnel crossing supports more reliable service

ST3 Representative Project (Baseline)

Elliott/15th / 16th / Tunnel potentially Fixed Bridge adds cost

West of BNSF / 20th / 17th / Fixed Bridge

West of BNSF / 20th / 17th / Tunnel Avoids Elliott/15th, East of BNSF/14th/Movable Fishermen’s Terminal Bridge and Salmon Bay Elliott/Armory waterway Way/14th/Tunnel

West of BNSF / 20th / Tunnel

Higher Performance Comparable Performance Lower Performance

49 4/17/2018

Interbay/Ballard summary ST3 Representative Project • Baseline for comparison • Avoids 15th Ave/Dravus interchange Elliott/15th/16th/Fixed Bridge • Supports more reliable service (no bridge openings) Alternatives with • Avoids Elliott Ave,15th Ave and Fishermen’s Terminal more potential West of BNSF/20th/17th/Fixed Bridge • Supports more reliable service • Avoids Elliott Ave,15th Ave and Fishermen’s Terminal East of BNSF/14th/Movable Bridge • Locates station on 14th Ave within industrial area • Avoids Elliott Ave, 15th Ave, Fishermen’s Terminal and Salmon Bay West of BNSF/20th/17th Tunnel • Requires tunnel; may require 3rd Party funding • Avoids Elliott Ave, 15th Ave, Fishermen’s Terminal and Salmon Bay Elliott/Armory Way/14th/Tunnel • Requires tunnel; may require 3rd Party funding

Alternatives with • Avoids Elliott Ave, 15th Ave, Fishermen’s Terminal and Salmon Bay greater West of BNSF/20th/Tunnel • Requires longer tunnel; may require 3rd Party funding challenges • Requires construction and displacement within Ballard core Tunnel through Queen Anne/Interbay • Depth and length impractical; would affect downtown tunnel depth Not practical Extensions to 65th, 85th, Northgate • Not included in ST3 plan suggestions Multi-modal • ST3 plan defined project as rail-only bridge Eliminate or add stations • Not consistent with ST3 plan

99

Interbay/Ballard Level 1 alternatives 100

50 4/17/2018

Next steps

Sample recommendation worksheet

Advance? Comments/ Discussion ST3 Representative Project • Avoids 15th Alternatives Ave/Dravus Elliott/15th/16th/Fixed with more interchange Bridge potential • Supports more reliable service

Alternative • Key findings

Alternatives Alternative • Key findings with greater challenges Alternative • Key findings

Not practical Alternative • Key findings suggestions Alternative • Key findings

102

51 4/17/2018

soundtransit.org/wsblink

52