<<

Approach Spans to the West Bridge

144. 4 Thomas A. Kane James E. Carpenter John H. Clark Principal-in-Charge Project Engineer Bridge Engineer and Project Manager Andersen Bjornstad Andersen Bjornstad Andersen Bjornstad Kane Jacobs, Inc. Kane Jacobs, Inc. Kane Jacobs, Inc. Seattle, Washington Seattle, Washington Seattle, Washington

onstruction efficiencies inherent in C some of the largest precast pre- stressed concrete girders used to date Synopsis in the United States are speeding the Some of the largest precast Freeway Bridge towards its scheduled 1985 completion. This prestressed concrete girders complex $87 million urban freeway used to date in the United project consists of four major units as States are currently being in- illustrated in Fig. 1. stalled on the West Seattle The West Interchange connects the Freeway Bridge in Washing- existing West Seattle Viaduct and sur- face streets to the main span crossing the ton. This report describes the West Waterway (main navigation chan- design/construction system nel). The Harbor Island unit carries the adopted for the projects Har- roadway across the industrial area and bor Island, West Interchange, East Waterway. The East Interchange and East Interchange units. unit connects the project to the existing Spokane Street Viaduct, Viaduct, and surface streets. The segmentally constructed, post-

C

OG4 HARBOR ISLAND F

ILl WEST4 SEATTLE y,Q

WEST MAIN ARB R I EAST INTERCHANGE SPAN APP OAG INTCHGE

5600

Fig. 1. Map of project area showing location of approach.

Table 1. Summary of approach contracts. Girders Contract Deck Area Number Description (sq ft) Number Lin. ft 5 Harbor Island Approach 168,125 161 24,183 6 West Interchange 245,719 242 30,216 7 East Interchange 222,730 294 27,291

Note: 1 sq ft = 0.09 Ins : 1 It = 0.305 in.

tensioned concrete box girders com- I. Soil conditions required expensive prising the three-span West Waterway and heavy pile foundations. Crossing have been described else- 2. Surface traffic conditions and pub- where. 1g This paper focuses on the pre- lic desires favored a layout which min- cast prestressed concrete girder system imized the number of columns and pro- used for the Harbor Island, West Inter- vided an "open" appearance. change, and East Interchange units, 3. Construction phasing to accommo- The magnitude of the project is indi- date traffic routing through the site cated in Table 1, which lists the num- during construction severely restricted ber and lengths of girders and roadway the possible pier locations. areas for the main units. The principal design issues faced in the development of the approach units Girder Design were aesthetics, economy, construction staging, and design for good seismic re- Several site constraints combined to sponse. The solution, which evolved result in a clear need to maximize the from these considerations, is a series of span length while still preserving the rigid frames made up of precast pre- economy inherent in precast pre- stressed concrete girders and cast-in- stressed girder construction. For exam- place reinforced concrete columns, cap ple: beams, and roadway slab.

PCI JOURNAL/November-December 1983 59

0

P Axp itLEp. AExp. Jt ^123102 102 116 120 121 151 154 164 164 158 I 189 189 (31) (31) (35)! 137) 1 (37) (37) (46) (47) (50) öT (48)1(58) ! (58)

Fig. 2. West Interchange plan (top) and elevation (bottom). Span lengths given in feet (m). 31011 - tions to this section were made which 21 - 4 allowed easy adaptation of the existing standard forms (Fig. 3). 1. The web width was increased from 5 to 6 in. (127 to 152 mm), thus in- creasing the shear capacity of the sec- tion and allowing more room for con- crete placement around the post-ten- M 120 ? sioning tendons. S 120 _ 2. The flange width and thickness were increased to provide better stabil- ity during handling and erection. Draped Post-tension Using the modified section, the max- imum girder length of 154 ft (47 m) Stroight Pretensions i was established after consultation with local precasters. Longer and heavier girders would have been beyond the capabilities of existing transportation 2- r^ equipment and would have made erec- tion more difficult. These limitations Fig. 3. Girder Section showing established an upper limit on span modifications (M120) to standard section length for this structure type. Horizon- (S120), tal clearance requirements over surface streets and railroad required a 185-ft (56 m) span adjacent to the main span unit which was achieved by widening The construction sequence was the typical 10-ft (3 m) cast-in-place cap planned so as to maximize the devel- beam into a 70-ft (21 m) long cast-in- opment of dead load continuity mo- place reinforced concrete box girder ments at the piers. The rigid frames over the pier. were an essential feature of the design Prestressing of I-girders is provided for proper seismic response. Fig. 2 by a combination of straight preten- shows the plan of the West Inter- sioned strands in the bottom flange and change, which consists of four separate draped post-tensioned tendons. The frames and two ramp structures which straight pretensioned strands furnish frame into the main roadway. adequate prestress for removal from the Variations of the basic design theme pretensioning bed and handling in the for the units were (1) different girder yard. Some of the straight pretensioned sections for shorter spans in areas of strands were debonded by plastic sharp curvature; (2) shorter frame sleeves near the end for stress control. lengths; and (3) the insertion of simple Release strengths required were less spans where required to decouple than would have been required for a seismic response motions between fully pretensioned design. Camber frames. growth is better controlled since post- The largest standard girder section tensioning can be delayed until higher available was the Washington State strength and modulus of elasticity are Department of Transportation 120 achieved. The turnover time for the Series girders which had previously beds was thus held to 24 hours. Post- been utilized for spans up to about 145 tensioning operations were off the criti- ft (44 m). To allow the longer spans cal path and were performed at the yard needed for this project, two modifica- storage locations.

PCI JOURNAUNovember-December 1983 61 An essential element in achieving the in one pour. This additional negative utmost structural efficiency and in sat- moment reduced the required positive isfying the seismic design requirements moment at the midspan of the girders, was the construction sequence. This but more importantly it prevented mo- sequence was designed to obtain signif- ment reversal (i.e., positive moments at icant dead load negative moments at the piers) under seismic response con- the piers through the sequencing of the ditions. It is difficult to provide con- slab pours. Staging the slab casting se- structahle, efficient details to resist pos- quence so that the sections over the itive moments at the piers in precast piers were cast before the sections over girder construction. the central portions of the slab resulted The construction sequence used is in a larger dead load negative moment illustrated in Figs. 4 and 5. Poor foun- than would result if the slab were cast dation conditions made it necessary to

Step 1. Construct pier up to construction joint at cap beam soffit.

Step 2. Erect girder and cap beam falsework.

Step 3. Erect girders.

Fig. 4. Construction sequence.

62 Step 4. Cast cap beams.

Step 5. Cast slab over piers.

Step 6. Cast slab over midspan portion.

Step 7. Cast barrier curbs and complete.

Fig. 4 (continued). Construction sequence.

PCI JOURNAUNovember-December 1983 63 support the erected girders on steel falsework founded on the permanent pile caps. This specification require- ment prevented premature overloading of the shear-friction connections be- tween the girders and the cast-in-place cap beam due to falsework settlement. Close attention was given to the de- tailing of reinforcing steel projecting from the ends of the girders. This rein- forcement had to be closely coordinated with cap beam reinforcing to avoid in- terference. The resulting detail is the overlapping 180-degree hooks shown in Fig. 6. The reinforcement required for positive moment (due to seismic loads) where the girders framed into a pier with an expansion joint at the far side usually required additional mild steel at the bottom flange. The bottom straight pretensioned strands were ex- tended in the cap beam in all girders. Fig. 5. Girders erected on falsework prior Fig. 6 also shows the shear keys which to casting cap beams and deck slab. were developed to meet design shear requirements. Dapped-end girders at expansion joints had additional shear keys on the sides where the end dia- phragm framed in. Plans of detailing for the cap beam and girder interface included a scale model of the cap beam and all required reinforcement (Fig. 7). This model proved to be a helpful aid in preventing reinforcing steel conflicts. As a result of i1 this prior planning, the project has ex- perienced a minimum of field problems of reinforcing steel conflicts.

Construction

Or Concrete strength for the girders was specified at 7000 psi (49 MPa). This strength requirement is met routinely by precasting plants in the area. Trans- fer strength for pretensioning was 4000 to 5500 psi (28 to 38 MPa) depending upon the girder details. Strength at ap- plication of the post-tensioning was re- quired to he 6000 psi (42 MPa). Fig. 6. Shear-friction reinforcement in The mix designs used for girder girder ends. manufacture were predicated upon the

64 Fig. 7. Cap beam scale model.

Table 2. Typical concrete mix designs. Amount per Cubic Yard Material Contract 5, 7 Contract 6 Cement, Type III 605 lbs 605 lbs 752 lbs Water, total 249 lbs 212 lbs 300 lbs Dry, fine aggregate (F.M. 3.1) 1190 lbs 1435 lbs 1176 lbs Dry, coarse aggregate (7/a in.) —— 1743 lbs Dry, coarse aggregate ('/z in.) 2105 lbs 1985 lbs - Water-reducing admixture 42 oz 30 oz 40 oz Superplasticizer — 60 oz - Slump 3-5 in. 3-5 in. 3-5 in Note: 1 1b = 0.45 kg; 1 ox - 28.35 g; l iu. - 25.4 mm. pretensioning transfer strength, since Summary this strength was the critical require- ment for girder removal from the cast- The precast girder approach struc- ing bed. Some of the typical mix de- tures on this project were successful in signs used are shown in Table 2. overcoming the traditional aesthetic Weather conditions prevalent at the objections to precast girder structures. time of casting were the final determi- This success was due to the attention nant in mix design selection. given to (1) achieving a harmonious Erection of the 75-ton (68 t) girders pattern and arrangement of girders in required two 200-ton (181 t) cranes, as the structure as viewed from below; (2) shown in Fig. 8. Girders were trans- maximum span lengths; and (3) the de- ported by tractors with steerable rear tails providing cap beam soffits flush trailers, as shown in Fig. 9. with the girders (Fig. 10).

PCI JOURNAUNovember-December 1983 65 Fig. B. Erection of girders.

Fig. 9. Girder transportation using steerable rear trailers.

66 Fig. 10. View from beneath structure.

Preliminary design studies clearly Credits indicated the economy of precast girder construction over competitive structure West Seattle Design Team: Andersen types and these studies were reflected Bjornstad Kane Jacobs, Inc., Seattle, in the bids received. Precast girder Washington; Parsons Brinckerhoff, construction also facilitated the mainte- Seattle, Washington; Tudor Engi- nance of traffic through the area during neers, Seattle, Washington; Kramer, construction by minimizing the false- Chin and Mayo, Seattle, Washington; work required. and Contech Consultants, Seattle, Washington. Special Consultant: Dr. A. H. Mattock, University of Washington, Seattle, REFERENCES Washington, Girder Manufacturers: Concrete 1. Kane, T. A., Carpenter, J. E., and Clark, Technology Corporation, Tacoma, J. H., "Concrete Answer to Urban Trans- Washington, and Prestressed Con- portation Problems," Concrete Interna- crete Products, Woodinville, Wash- tional, August 1981, pp. 85-92. ington. 2. "Girder Duo Cantilevers in Union," En- General Contractors: Kiewit-Grice: (a gineering News Record, November 25, 1982, pp. 26-27. joint venture), Seattle, Washington, 3. "Record Girders Trucked to Site," En- and Moseman Construction, Seattle, gineering News Record, March 24, 198.3, Washington. p. 69. Owner: City of Seattle.

PCI JOURNALINovember-December 1983 67