Stirling Council Housing Land Audit 2019 Contents

Contents 1. Summary Page 2 2. Definitions Page 3 3. Local Development Plan Page 4 4. Methodology Page 5 5. Statistical Analysis Page 7 Appendix A: Schedule of Sites Appendix B: Sites completed 1st July 2018 – 30th June 2019

1

1. Summary

Stirling Council produces an annual audit of housing land to show completions and annual programming forecasts for the Stirling Council Planning Authority area. This excludes the area of the Council that forms the and the Trossachs National Park. The audits provide a snapshot of the availability of housing land on the 30th June each year. Planning Advice Note 2/2010: Affordable Housing and Housing Land Audits and Scottish Planning Policy 2014 (SPP) establish Housing Land Audits as the method for monitoring housing land. The 2 key functions of the audits are to:

 Demonstrate the availability of sufficient effective housing land to meet the requirement for a 5 year effective supply at all times; and  Provide a snapshot of the amount of land available at any particular time. SPP (2014) highlights that all planning authorities must demonstrate that they are maintaining at least a 5 year effective supply of land at all times. This audit is the established means to monitor this requirement and is presented annually. SPP also requires that planning authorities allocate in their Local Development Plans (LDP'S) a range of sites which are effective or are expected to become effective within the plan period to meet the Housing Land Requirement in full. This audit monitors this progress and will inform future LDP reviews.

2019 Summary

Number of sites 78

5 Year Effective Supply Target 2866

5 Year Effective Supply 3058

Years supply 5.3

2

2. Definitions

The Stirling Council Housing Land Audit 2019, in accordance with SPP (2014) and PAN 2/2010 sets out the following definitions in relation to housing land supply: Time Periods

For a site to be considered as part of the 5 Year Effective Supply all 7 Tests of Effectiveness, as set out in PAN 2/2010, have to be satisfied.

5 Year Effective Supply Calculation

Remaining Target (LDP Housing Supply Target - Completions in Plan Period) Revised Annual Target Remaining Years in LDP

5 Year Effective Programming Years Supply Revised Annual Target

The 5 Year Effective Supply is the programmed output used to assess if the Council is in compliance with the requirement of SPP to maintain a 5 year effective supply of land at all times. This is based on the annual Housing Supply Target as set out in the LDP. There is no standard methodology for calculating the 5 year effective land supply which has led to different approaches being used across . In light of a recent planning appeal decision in Stirling, it is considered appropriate for the compound approach, as set out above. To be used to determine if a 5 year effective supply of land is being maintained.

3

3. Local Development Plan

The adopted Local Development Plan is the Stirling Local Development Plan 2018. The plan was adopted by the Council on 8th October 2018.

4

4. Methodology

The audit is a continual process that starts by weekly monitoring of the planning schedule to identify new sites to be included in the audit. This is then supplemented by assessing sites from the previous audits for any changes, for example, to site capacity or contact details. On the 30th June, the base date of the audit, Developer Intention Surveys are sent out to all sites identified from the monitoring stage, except small sites of less than 4 units. This survey allows the Council to capture accurate and up to date information on each sites progress and expected future development. This information is provided by landowners and developers. The survey is supported by site visits to assess development where needed. Once this information has been compiled, draft programming is prepared and sent to Homes for Scotland to allow early discussion on sites included in the audit.

Agreement and Monitoring Publishing

Housing Land Audit Methodology Stakeholder Data meeting gathering

Drafting of programming

A meeting is then held, usually in September, to agree the contents of the audit with key stakeholders. Council officers, representing the Planning, Housing and Education departments, Registered Social Landlords, Homes for Scotland, developers and infrastructure providers are invited to attend the meeting. Once agreement has been reached on the programming the final audit document is prepared. There is a time lag while completion data for the previous year is prepared for all sites by Building Standards and the audit is usually published in October or November. This year a meeting took place on 23rd October and regrettably agreement could not be reached on the programming of all sites with Homes for Scotland. Of the 78 sites in the audit agreement was not reached on 7 sites and these are detailed below.

5

Ref (HLA / Site Name Settlement Reason for Non-agreement Stirling Council Assessment LDP) SC112 / KH HfS do not agree that Tests of Pre-application advice has been given to H088 Parsons Effectiveness have been met a developer interested in this site, Workshop as the site is not in the control planning consent has previously been of a developer, there is no granted and the landowner is willing to planning consent and believe divest the site for development. The that there is a physical Council is satisfied that this meets the constraint on the site. Tests of Effectiveness as set out in PAN 2/2010. SC215 / Depot Site Balfron HfS do not agree that Tests of This site is currently being marketed by H083 Effectiveness have been met the Council and a planning brief has been as the site is not in the control prepared. The Council is satisfied that this of a developer and there is no meets the Tests of Effectiveness as set planning consent. out in PAN2/2010. SC267 / South of HfS do not agree that Tests of Pre-application enquires are ongoing and H152 Fisher Effectiveness have been met the landowner is willing to divest the site Place as the site is not in the control for development. The Council is working of a developer, there is no with the developer to overcome the planning consent and believe access constraint. The Council is satisfied that there is a physical that this meets the Tests of Effectiveness constraint on the site in terms as set out in PAN 2/2010. of access. SC268 / South of HfS do not agree that Tests of Pre-application enquires are ongoing and H153 A81 Effectiveness have been met the landowner is willing to divest the site as the site is not in the control for development. It is an allocated site of a developer, there is no and it is not considered that there is a planning consent and believe physical constraint that cannot be that there is a physical overcome. The Council is satisfied that constraint on the site. this meets the Tests of Effectiveness as set out in PAN 2/2010. S041/ Touchill HfS do not agree that the Pre-application enquires are ongoing. The H072 Farm Tests of Effectiveness have landowner is willing to divest the site, it is been met as the site is an allocated site with an implemented constrained by lack of consent. The Council is satisfied that this progress. meets the Tests of Effectiveness as set out in PAN 2/2010. SC201A / Former SRI Stirling HfS do not agree that the This site features in the SHIP and is part H052 Tests of Effectiveness have of a disposal programme by the NHS. The been met as the site is not in Council is satisfied that this meets the the control of the Council or Tests of Effectiveness as set out in PAN an RSL. 2/2010. SC212 / East Fallin Fallin HfS do not agree that the Pre-application enquires are ongoing on H077 Tests of Effectiveness have this site. This legal constraint is not been met as there is an considered to be an ownership constraint ownership constraint due to a as the site is being actively marketed for legal covenant. residential use. The Council is satisfied that this meets the Tests of Effectiveness as set out in PAN 2/2010.

6

5. Statistical Analysis

Table 1 Effective/Established Land Supply - by Sub Area (Excluding Small Sites) Effective Land Non effective Land Established land Number of sites Sub Area Supply (2019/20 - supply (post 2027) supply in audit 2026/27) Core Area 3807 3292 7099 48 Rural Area 363 21 384 30 Total 4170 3313 7483 78 Table 1 / Chart 1 illustrate the breakdown of the land supply by sub area for audit sites. This does not include any output from small sites. The 2019 audit comprises 78 sites, expected to deliver 3,313 units by the end of the plan period in 2027. Not all sites are expected to deliver fully within the effective period till 2027. Strategic sites such as Durieshill and South Stirling Gateway are expected to deliver beyond this point.

7

Table 2 Established Land Supply - Planning Status (Excluding Small Sites) Planning Under Full Established Sub Area Permission In Proposal Construction Permission Land Supply Principle Core Area 317 628 89 6065 7099 Rural Area 83 68 0 233 384 Total 400 696 89 6298 7483 The established land supply of 7,483 units is broken down by planning status and sub area in Table 2 / Chart 2. It highlights that approximately 15% of the land supply is under construction or benefits from planning permission. The relatively high percentage of units classed as 'Proposal' is due in part to 3,300 units expected from strategic sites at Durieshill and South Stirling Gateway, however, planning applications are currently under consideration for both sites.

8

Table 3 Effective land Supply - Brownfield/greenfield split (Excluding Small Sites) Sub Brownfield Conversion Total Brownfield Greenfield Mixed sites Area New Build Core Area 977 10 987 2813 7 Rural Area 128 17 145 160 58 Total 1105 27 1132 2973 65 Total Effective 4170 Land Supply Table 3 / Chart 3 illustrates that approximately 28% of the effective land supply is expected to be delivered on brownfield land, which is land that has previously been developed and includes conversions. Greenfield land is land that has not previously been developed. The Council supports the reuse of brownfield land, however it is recognised in the Spatial Strategy for the LDP that there is a need for controlled greenfield expansion to accommodate the Housing Land Requirement. As only 28% of the supply is expected on brownfield land, this continues to highlight that there are few remaining brownfield sites suitable for housing development.

9

Table 4 Effective Land Supply - Market Tenure (Excludes Small Sites) Sub Area Market Affordable Total Core Area 2663 1144 3807 Rural Area 303 60 363 Total 2966 1204 4170 Table 4 / Chart 4 show that as a proportion of development, there is a difference between the percentage of affordable housing to be delivered in the Core and Rural areas. The higher percentage of affordable units to be delivered in the Core Area is reflective of the Council's commitment to the Regeneration areas within Stirling and the Eastern Villages.

10

Table 5 Five Year Programmed Output (Excluding Small Sites) Programmed Output Total Sub Area 2019/20 2020/21 2021/22 2022/23 2023/24 2019/24

Core Area 179 478 651 634 586 2528

Rural Area 49 61 60 147 38 355

Total 228 539 711 781 624 2883

Within the Effective Land Supply of 4,170 units, as shown in Table 1, 2,883 units are expected to be delivered within the next 5 years on audit sites, as shown in Table 5 / Chart 5. This output is added to the ouput expected from small sites to calculate the 5 year supply, as shown in Table 9. The 5 year output rises from 2020/201 as this is when completions are expected to begin to be delivered from Strategic Sites.

11

Table 6 Five Year Programmed Output by Market Tenure (Excludes Small Sites) Programmed Output Total Tenure 2019/20 2020/21 2021/22 2022/23 2023/24 2019/24 Market 114 233 573 559 497 1976 Affordable 114 306 138 222 127 907

Total 228 539 711 781 624 2883 Within the first 5 years of the effective supply it is expected that there will be 2,883 units completed across the plan area on audit sites, 907 of which are forecast to be affordable. The affordable element represents almost 31% of the 5 year supply. This is due in part to a commitment to accelerate the build out of the Masterplan and the policy requirement for sites for which detailed plans are not yet available. Raploch is a key regeneration priority for the Council.

12

Table 7a Programmed V Actual Completions (All Sites) 2018/2019 2018/2019 Monitoring Category Programmed Actual Difference Completions Completions

Core Area 185 89 -96 Local Development Plan

Rural Area 34 22 -12

More than 4 10 units Windfall 49 -18 Small sites less than 4 21 units Total 268 142 -126

The 2018/2019 audit has performed slightly less than expected in the 2017/2018 audit. Tables and Charts 7a and 7b show that across all sites there were 126 units not delivered as expected. This is largely due to sites at Raploch not delivering as fast as expected. It is expected that there will be 35 units per annum from small sites and windfall contributing towards the land supply. This year 31 such units were delivered.

Table 7b Programmed V Actual Completions By Tenure 2018/19 2018/2019 Tenure Programmed Actual Difference Completions Completions Market 151 117 -34 Affordable 117 25 -92 Total 268 142 -126

13

Table 8 Programmed V Actual Completions 10 Year Trend (Excluding Small Sites) 2009/10 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 Anticipated 306 363 291 263 215 387 337 218 179 233 Actual 290 353 311 223 307 304 336 214 192 121 Difference -16 -10 20 -40 92 -83 -1 -4 13 -112

When small sites are excluded, allocated LDP sites have performed broadly in line with expectations over the last 10 years, with deviations being due to some sites delivering quicker or slower than anticipated.

14

Table 9 Five Year Effective Land Supply 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 Actual Completions Programmed Completions 344 306 247 319 322 368 234 205 142 263 574 746 816 659 540 464 388 Total Completions 2487 5 Year Effective Programming 3058 Housing Supply Target 7072 5 Year Effective Supply Target 2866 Completions and Programmed 6937 Years Gain/ Completions For LDP Period 5.3 192 Supply Shortfall Predicted Gain/Shortfall Units -135

SPP requires that planning authorities maintain a 5 year supply of Effective Land at all times. The precise method of calculation is disputed, with varying approaches being demonstrated across Scotland, at both local and national level, and the private sector. At the time of publication there was no finalised guidance from the Scottish Government in place. However, as set out in section 2 of this document the Council has adopted the compound approach to calculating the 5 year supply. Table 9 demonstrates that Stirling Council is maintaining a 5 year supply of housing land as required by SPP, with evidence of a 5.3 years supply.

15 Appendix A: Schedule of Sites

16 Appendix A: Schedule of Sites

KH Parsons Workshop, Balfron SC112 / H088 Actions Required to Deliver this site Landowner to release the site for development.

Site Details

Audit Status Planning Status Local Ward LDP Sub Monitoring Type Land and Area Development Type 5 year effective Proposal 2 - Forth and Rural LDP Brownfield New build Endrick Site Site Developer (s) X / Y Co- Latest Approval Expiry Date Area Density ordinates 0.28 67.86 Hugh Parsons 254777 / 06/00133/OUT 15/02/2010 - 688640 -

Programming

Total Capacity Total Remaining 5 Year Effective Remaining Effective Non-Effective (2019/20 – 2023/24) (2024/25 – 2026/27) (Post 2027) 19 19 19 0 0 Total Completions First Year in Currently In Established First Year in Effective Currently in Effective Established Supply Supply Since Supply Supply Since 0 2007 2007 2007 2014

2019/20 2020/21 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 Post 2027

Total 0 0 0 13 6 0 0 0 0 Affordable 0 0 0 6 0 0 0 0 0

Market 0 0 0 7 6 0 0 0 0

Completions

Pre 2010 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 Total 0 0 0 0 0 0 0 0 0 0 Af 0 0 0 0 0 0 0 0 0 0 Mkt 0 0 0 0 0 0 0 0 0 0

Tests of Effectiveness

Ownership Physical Contamination Deficit Funding Marketability Infrastructure Land Use Yes Yes Yes Yes Yes Yes Yes

17 Appendix A: Schedule of Sites

15-23 Buchanan Street, Balfron SC176 / H091 Actions Required to Deliver this site Continue buid out of site.

Site Details

Audit Status Planning Status Local Ward LDP Sub Monitoring Type Land and Area Development Type 5 year effective Under Construction 2 - Forth and Rural LDP Brownfield New build Endrick Site Site Developer (s) X / Y Co- Latest Approval Expiry Date Area Density ordinates 0.29 13.79 Cadder Investments 254638 / 17/00900/FUL 23/04/2021 - 688522 -

Programming

Total Capacity Total Remaining 5 Year Effective Remaining Effective Non-Effective (2019/20 – 2023/24) (2024/25 – 2026/27) (Post 2027) 4 4 4 0 0 Total Completions First Year in Currently In Established First Year in Effective Currently in Effective Established Supply Supply Since Supply Supply Since 0 2010 2010 2010 2014

2019/20 2020/21 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 Post 2027

Total 2 2 0 0 0 0 0 0 0 Affordable 0 0 0 0 0 0 0 0 0

Market 2 2 0 0 0 0 0 0 0

Completions

Pre 2010 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 Total 0 0 0 0 0 0 0 0 0 0 Af 0 0 0 0 0 0 0 0 0 0 Mkt 0 0 0 0 0 0 0 0 0 0

Tests of Effectiveness

Ownership Physical Contamination Deficit Funding Marketability Infrastructure Land Use Yes Yes Yes Yes Yes Yes Yes

18 Appendix A: Schedule of Sites

Depot Site, Balfron SC215 / H083 Actions Required to Deliver this site Site being marketed by Council. Planning brief prepared to support this.

Site Details

Audit Status Planning Status Local Ward LDP Sub Monitoring Type Land and Area Development Type 5 year effective Proposal 2 - Forth and Rural LDP Brownfield New build Endrick Site Site Developer (s) X / Y Co- Latest Approval Expiry Date Area Density ordinates 1.13 8.85 Stirling Council 254573 / - - - 688960 -

Programming

Total Capacity Total Remaining 5 Year Effective Remaining Effective Non-Effective (2019/20 – 2023/24) (2024/25 – 2026/27) (Post 2027) 10 10 10 0 0 Total Completions First Year in Currently In Established First Year in Effective Currently in Effective Established Supply Supply Since Supply Supply Since 0 2013 2013 2013 2013

2019/20 2020/21 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 Post 2027

Total 0 0 0 10 0 0 0 0 0 Affordable 0 0 0 0 0 0 0 0 0

Market 0 0 0 10 0 0 0 0 0

Completions

Pre 2010 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 Total 0 0 0 0 0 0 0 0 0 0 Af 0 0 0 0 0 0 0 0 0 0 Mkt 0 0 0 0 0 0 0 0 0 0

Tests of Effectiveness

Ownership Physical Contamination Deficit Funding Marketability Infrastructure Land Use Yes Yes Yes Yes Yes Yes Yes

19 Appendix A: Schedule of Sites

4 Inverallan Road, SC108 / H005 Actions Required to Deliver this site Site is non effective. Candidate for removal from next LDP.

Site Details

Audit Status Planning Status Local Ward LDP Sub Monitoring Type Land and Area Development Type Non effective Proposal 3 - and Core LDP Brownfield New build Bridge of Allan Site Site Developer (s) X / Y Co- Latest Approval Expiry Date Area Density ordinates 0.16 75.00 Gateway Builders 278772 / 10/00544/FUL 28/10/2013 - 697530 -

Programming

Total Capacity Total Remaining 5 Year Effective Remaining Effective Non-Effective (2019/20 – 2023/24) (2024/25 – 2026/27) (Post 2027) 12 12 0 0 12 Total Completions First Year in Currently In Established First Year in Effective Currently in Effective Established Supply Supply Since Supply Supply Since 0 2007 2007 2007 0

2019/20 2020/21 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 Post 2027

Total 0 0 0 0 0 0 0 0 12 Affordable 0 0 0 0 0 0 0 0 0

Market 0 0 0 0 0 0 0 0 12

Completions

Pre 2010 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 Total 0 0 0 0 0 0 0 0 0 0 Af 0 0 0 0 0 0 0 0 0 0 Mkt 0 0 0 0 0 0 0 0 0 0

Tests of Effectiveness

Ownership Physical Contamination Deficit Funding Marketability Infrastructure Land Use No Yes Yes Yes Yes Yes Yes

20 Appendix A: Schedule of Sites

Sunnylaw, Bridge of Allan SC259 / H135 Actions Required to Deliver this site Submission of a planning application.

Site Details

Audit Status Planning Status Local Ward LDP Sub Monitoring Type Land and Area Development Type 5 year effective Proposal 3 - Dunblane and Core LDP Greenfield New build Bridge of Allan Site Site Developer (s) X / Y Co- Latest Approval Expiry Date Area Density ordinates 1.15 3.48 - 279300 / - - - 698373 -

Programming

Total Capacity Total Remaining 5 Year Effective Remaining Effective Non-Effective (2019/20 – 2023/24) (2024/25 – 2026/27) (Post 2027) 4 4 4 0 0 Total Completions First Year in Currently In Established First Year in Effective Currently in Effective Established Supply Supply Since Supply Supply Since 0 2017 2017 2017 2017

2019/20 2020/21 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 Post 2027

Total 0 0 0 4 0 0 0 0 0 Affordable 0 0 0 0 0 0 0 0 0

Market 0 0 0 4 0 0 0 0 0

Completions

Pre 2010 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 Total 0 0 0 0 0 0 0 0 0 0 Af 0 0 0 0 0 0 0 0 0 0 Mkt 0 0 0 0 0 0 0 0 0 0

Tests of Effectiveness

Ownership Physical Contamination Deficit Funding Marketability Infrastructure Land Use Yes Yes Yes Yes Yes Yes Yes

21 Appendix A: Schedule of Sites

South of Fisher Place, Buchlyvie SC267 / H152 Actions Required to Deliver this site Council to work with landowner and developer to bring forward the site for development.

Site Details

Audit Status Planning Status Local Ward LDP Sub Monitoring Type Land and Area Development Type 5 year effective Proposal 2 - Forth and Rural LDP Greenfield New build Endrick Site Site Developer (s) X / Y Co- Latest Approval Expiry Date Area Density ordinates 0.75 20.00 Mr Scoobie 257176 / - - - 693819 -

Programming

Total Capacity Total Remaining 5 Year Effective Remaining Effective Non-Effective (2019/20 – 2023/24) (2024/25 – 2026/27) (Post 2027) 15 15 15 0 0 Total Completions First Year in Currently In Established First Year in Effective Currently in Effective Established Supply Supply Since Supply Supply Since 0 2018 2018 2018 2018

2019/20 2020/21 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 Post 2027

Total 0 0 0 15 0 0 0 0 0 Affordable 0 0 0 5 0 0 0 0 0

Market 0 0 0 10 0 0 0 0 0

Completions

Pre 2010 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 Total 0 0 0 0 0 0 0 0 0 0 Af 0 0 0 0 0 0 0 0 0 0 Mkt 0 0 0 0 0 0 0 0 0 0

Tests of Effectiveness

Ownership Physical Contamination Deficit Funding Marketability Infrastructure Land Use Yes Yes Yes Yes Yes Yes Yes

22 Appendix A: Schedule of Sites

Hayford Mills Phase 2, SC115 / H011 Actions Required to Deliver this site Start on site.

Site Details

Audit Status Planning Status Local Ward LDP Sub Monitoring Type Land and Area Development Type 5 year effective FUL 5 - Core LDP Brownfield New build

Site Site Developer (s) X / Y Co- Latest Approval Expiry Date Area Density ordinates 0.72 52.78 Hayford Estates Ltd 277555 / 14/00035/FUL 02/05/2020 - 690800 -

Programming

Total Capacity Total Remaining 5 Year Effective Remaining Effective Non-Effective (2019/20 – 2023/24) (2024/25 – 2026/27) (Post 2027) 38 38 38 0 0 Total Completions First Year in Currently In Established First Year in Effective Currently in Effective Established Supply Supply Since Supply Supply Since 0 2007 2007 2007 2013

2019/20 2020/21 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 Post 2027

Total 0 6 32 0 0 0 0 0 0 Affordable 0 0 0 0 0 0 0 0 0

Market 0 6 32 0 0 0 0 0 0

Completions

Pre 2010 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 Total 0 0 0 0 0 0 0 0 0 0 Af 0 0 0 0 0 0 0 0 0 0 Mkt 0 0 0 0 0 0 0 0 0 0

Tests of Effectiveness

Ownership Physical Contamination Deficit Funding Marketability Infrastructure Land Use Yes Yes Yes Yes Yes Yes Yes

23 Appendix A: Schedule of Sites

Polmaise Road, Cambusbarron SC276 / H159 Actions Required to Deliver this site Decision to be made on MSC application.

Site Details

Audit Status Planning Status Local Ward LDP Sub Monitoring Type Land and Area Development Type 5 year effective Proposal 5 - Stirling West Core LDP Greenfield New build

Site Site Developer (s) X / Y Co- Latest Approval Expiry Date Area Density ordinates 13.58 18.41 Hallam Land Management Ltd & CEG Land 278166 / PPA-390-2046 04/09/2021 Promotions Ltd 891968 - -

Programming

Total Capacity Total Remaining 5 Year Effective Remaining Effective Non-Effective (2019/20 – 2023/24) (2024/25 – 2026/27) (Post 2027) 250 250 173 77 0 Total Completions First Year in Currently In Established First Year in Effective Currently in Effective Established Supply Supply Since Supply Supply Since 0 2017 2017 2017 2017

2019/20 2020/21 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 Post 2027

Total 0 35 58 40 40 40 37 0 0 Affordable 0 20 28 0 0 0 0 0 0

Market 0 15 30 40 40 40 37 0 0

Completions

Pre 2010 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 Total 0 0 0 0 0 0 0 0 0 0 Af 0 0 0 0 0 0 0 0 0 0 Mkt 0 0 0 0 0 0 0 0 0 0

Tests of Effectiveness

Ownership Physical Contamination Deficit Funding Marketability Infrastructure Land Use Yes Yes Yes Yes Yes Yes Yes

24 Appendix A: Schedule of Sites

Berryhills, Cowie SC209 / H074 Actions Required to Deliver this site MSC application to be submitted.

Site Details

Audit Status Planning Status Local Ward LDP Sub Monitoring Type Land and Area Development Type 5 year effective Proposal 7 - Core LDP Greenfield New build

Site Site Developer (s) X / Y Co- Latest Approval Expiry Date Area Density ordinates 21.25 23.53 Taylor Wimpey Homes 283297 / PPA-390-2056 - Omnivale 689214 -

Programming

Total Capacity Total Remaining 5 Year Effective Remaining Effective Non-Effective (2019/20 – 2023/24) (2024/25 – 2026/27) (Post 2027) 500 500 168 144 188 Total Completions First Year in Currently In Established First Year in Effective Currently in Effective Established Supply Supply Since Supply Supply Since 0 2013 2013 2013 2013

2019/20 2020/21 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 Post 2027

Total 0 24 48 48 48 48 48 48 188 Affordable 0 10 10 10 10 10 10 10 55

Market 0 14 38 38 38 38 38 38 133

Completions

Pre 2010 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 Total 0 0 0 0 0 0 0 0 0 0 Af 0 0 0 0 0 0 0 0 0 0 Mkt 0 0 0 0 0 0 0 0 0 0

Tests of Effectiveness

Ownership Physical Contamination Deficit Funding Marketability Infrastructure Land Use Yes Yes Yes Yes Yes Yes Yes

25 Appendix A: Schedule of Sites

Station Road, Cowie SC210 / H075 Actions Required to Deliver this site Planning application to be submitted.

Site Details

Audit Status Planning Status Local Ward LDP Sub Monitoring Type Land and Area Development Type 5 year effective Proposal 7 - Bannockburn Core LDP Greenfield New build

Site Site Developer (s) X / Y Co- Latest Approval Expiry Date Area Density ordinates 3.27 15.29 Cala Homes 283325 / - - - 689533 -

Programming

Total Capacity Total Remaining 5 Year Effective Remaining Effective Non-Effective (2019/20 – 2023/24) (2024/25 – 2026/27) (Post 2027) 50 50 50 0 0 Total Completions First Year in Currently In Established First Year in Effective Currently in Effective Established Supply Supply Since Supply Supply Since 0 2013 2013 2013 2013

2019/20 2020/21 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 Post 2027

Total 0 0 0 24 26 0 0 0 0 Affordable 0 0 0 12 0 0 0 0 0

Market 0 0 0 12 26 0 0 0 0

Completions

Pre 2010 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 Total 0 0 0 0 0 0 0 0 0 0 Af 0 0 0 0 0 0 0 0 0 0 Mkt 0 0 0 0 0 0 0 0 0 0

Tests of Effectiveness

Ownership Physical Contamination Deficit Funding Marketability Infrastructure Land Use Yes Yes Yes Yes Yes Yes Yes

26 Appendix A: Schedule of Sites

Ochilview, Cowie SC211 / H076 Actions Required to Deliver this site Planning application to be submitted.

Site Details

Audit Status Planning Status Local Ward LDP Sub Monitoring Type Land and Area Development Type 5 year effective Proposal 7 - Bannockburn Core LDP Greenfield New build

Site Site Developer (s) X / Y Co- Latest Approval Expiry Date Area Density ordinates 4.23 18.91 Ogilvie Homes 284269 / - - - 6889301 -

Programming

Total Capacity Total Remaining 5 Year Effective Remaining Effective Non-Effective (2019/20 – 2023/24) (2024/25 – 2026/27) (Post 2027) 80 80 60 20 0 Total Completions First Year in Currently In Established First Year in Effective Currently in Effective Established Supply Supply Since Supply Supply Since 0 2013 2013 2013 2013

2019/20 2020/21 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 Post 2027

Total 0 0 20 20 20 20 0 0 0 Affordable 0 0 5 5 5 5 0 0 0

Market 0 0 15 15 15 15 0 0 0

Completions

Pre 2010 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 Total 0 0 0 0 0 0 0 0 0 0 Af 0 0 0 0 0 0 0 0 0 0 Mkt 0 0 0 0 0 0 0 0 0 0

Tests of Effectiveness

Ownership Physical Contamination Deficit Funding Marketability Infrastructure Land Use Yes Yes Yes Yes Yes Yes Yes

27 Appendix A: Schedule of Sites

St Margarets, Cowie SC265 / H146 Actions Required to Deliver this site Decision to be made on application.

Site Details

Audit Status Planning Status Local Ward LDP Sub Monitoring Type Land and Area Development Type 5 year effective Proposal 7 - Bannockburn Core LDP Brownfield New build

Site Site Developer (s) X / Y Co- Latest Approval Expiry Date Area Density ordinates 0.60 36.67 Stirling Council 283657 / - - - 689476 -

Programming

Total Capacity Total Remaining 5 Year Effective Remaining Effective Non-Effective (2019/20 – 2023/24) (2024/25 – 2026/27) (Post 2027) 22 22 22 0 0 Total Completions First Year in Currently In Established First Year in Effective Currently in Effective Established Supply Supply Since Supply Supply Since 0 2017 2017 2017 2017

2019/20 2020/21 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 Post 2027

Total 0 11 11 0 0 0 0 0 0 Affordable 0 11 11 0 0 0 0 0 0

Market 0 0 0 0 0 0 0 0 0

Completions

Pre 2010 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 Total 0 0 0 0 0 0 0 0 0 0 Af 0 0 0 0 0 0 0 0 0 0 Mkt 0 0 0 0 0 0 0 0 0 0

Tests of Effectiveness

Ownership Physical Contamination Deficit Funding Marketability Infrastructure Land Use Yes Yes Yes Yes Yes Yes Yes

28 Appendix A: Schedule of Sites

Moray Street, SC027 / H096 Actions Required to Deliver this site Continue build out of site.

Site Details

Audit Status Planning Status Local Ward LDP Sub Monitoring Type Land and Area Development Type 5 year effective Under Construction 1 - Trossachs Rural LDP Greenfield New build and Teith Site Site Developer (s) X / Y Co- Latest Approval Expiry Date Area Density ordinates 1.97 28.43 Rural Stirling Housing Assoication 272723 / 17/00941/FUL 26/02/2021 - 701795 -

Programming

Total Capacity Total Remaining 5 Year Effective Remaining Effective Non-Effective (2019/20 – 2023/24) (2024/25 – 2026/27) (Post 2027) 56 6 6 0 0 Total Completions First Year in Currently In Established First Year in Effective Currently in Effective Established Supply Supply Since Supply Supply Since 50 1995 1995 1999 1999

2019/20 2020/21 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 Post 2027

Total 6 0 0 0 0 0 0 0 0 Affordable 6 0 0 0 0 0 0 0 0

Market 0 0 0 0 0 0 0 0 0

Completions

Pre 2010 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 Total 0 0 0 20 30 0 0 0 0 0 Af 0 0 0 20 30 0 0 0 0 0 Mkt 0 0 0 0 0 0 0 0 0 0

Tests of Effectiveness

Ownership Physical Contamination Deficit Funding Marketability Infrastructure Land Use Yes Yes Yes Yes Yes Yes Yes

29 Appendix A: Schedule of Sites

Whitecross, Dunblane SC245 / H133 Actions Required to Deliver this site Submission of a planning application.

Site Details

Audit Status Planning Status Local Ward LDP Sub Monitoring Type Land and Area Development Type Effective Proposal 3 - Dunblane and Core LDP Greenfield New build Bridge of Allan Site Site Developer (s) X / Y Co- Latest Approval Expiry Date Area Density ordinates 0.29 27.59 Messrs Andrew Fleming and Sons 278896 / - - - 702336 -

Programming

Total Capacity Total Remaining 5 Year Effective Remaining Effective Non-Effective (2019/20 – 2023/24) (2024/25 – 2026/27) (Post 2027) 8 8 0 8 0 Total Completions First Year in Currently In Established First Year in Effective Currently in Effective Established Supply Supply Since Supply Supply Since 0 2014 2014 2014 2014

2019/20 2020/21 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 Post 2027

Total 0 0 0 0 0 8 0 0 0 Affordable 0 0 0 0 0 3 0 0 0

Market 0 0 0 0 0 5 0 0 0

Completions

Pre 2010 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 Total 0 0 0 0 0 0 0 0 0 0 Af 0 0 0 0 0 0 0 0 0 0 Mkt 0 0 0 0 0 0 0 0 0 0

Tests of Effectiveness

Ownership Physical Contamination Deficit Funding Marketability Infrastructure Land Use Yes Yes Yes Yes Yes Yes Yes

30 Appendix A: Schedule of Sites

Hillside, Dunblane SC261 / H137 Actions Required to Deliver this site Start on site.

Site Details

Audit Status Planning Status Local Ward LDP Sub Monitoring Type Land and Area Development Type 5 year effective Proposal 3 - Dunblane and Core LDP Greenfield New build Bridge of Allan Site Site Developer (s) X / Y Co- Latest Approval Expiry Date Area Density ordinates 0.96 18.75 Dandara 277550 / - - Arnbathie Developments Ltd 700302 -

Programming

Total Capacity Total Remaining 5 Year Effective Remaining Effective Non-Effective (2019/20 – 2023/24) (2024/25 – 2026/27) (Post 2027) 15 15 15 0 0 Total Completions First Year in Currently In Established First Year in Effective Currently in Effective Established Supply Supply Since Supply Supply Since 0 2017 2017 2017 2017

2019/20 2020/21 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 Post 2027

Total 0 15 0 0 0 0 0 0 0 Affordable 0 0 0 0 0 0 0 0 0

Market 0 15 0 0 0 0 0 0 0

Completions

Pre 2010 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 Total 0 0 0 0 0 0 0 0 0 0 Af 0 0 0 0 0 0 0 0 0 0 Mkt 0 0 0 0 0 0 0 0 0 0

Tests of Effectiveness

Ownership Physical Contamination Deficit Funding Marketability Infrastructure Land Use Yes Yes Yes Yes Yes Yes Yes

31 Appendix A: Schedule of Sites

Barbush, Dunblane SC262 / H138 Actions Required to Deliver this site Start on site.

Site Details

Audit Status Planning Status Local Ward LDP Sub Monitoring Type Land and Area Development Type 5 year effective FUL 3 - Dunblane and Core LDP Brownfield New build Bridge of Allan Site Site Developer (s) X / Y Co- Latest Approval Expiry Date Area Density ordinates 3.55 22.25 Gladman 278632 / 18/00764/MSC 18/06/2024 - 702742 -

Programming

Total Capacity Total Remaining 5 Year Effective Remaining Effective Non-Effective (2019/20 – 2023/24) (2024/25 – 2026/27) (Post 2027) 79 79 79 0 0 Total Completions First Year in Currently In Established First Year in Effective Currently in Effective Established Supply Supply Since Supply Supply Since 0 2017 2017 2017 2017

2019/20 2020/21 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 Post 2027

Total 9 35 35 0 0 0 0 0 0 Affordable 0 26 0 0 0 0 0 0 0

Market 9 9 35 0 0 0 0 0 0

Completions

Pre 2010 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 Total 0 0 0 0 0 0 0 0 0 0 Af 0 0 0 0 0 0 0 0 0 0 Mkt 0 0 0 0 0 0 0 0 0 0

Tests of Effectiveness

Ownership Physical Contamination Deficit Funding Marketability Infrastructure Land Use Yes Yes Yes Yes Yes Yes Yes

32 Appendix A: Schedule of Sites

Major Growth Area, Durieshill SC074 / H057 Actions Required to Deliver this site Decision to be made on application.

Site Details

Audit Status Planning Status Local Ward LDP Sub Monitoring Type Land and Area Development Type 5 year effective Proposal 7 - Bannockburn Core LDP Greenfield New build

Site Site Developer (s) X / Y Co- Latest Approval Expiry Date Area Density ordinates 244.79 10.21 Springfield Homes 281503 / - - - 687601 -

Programming

Total Capacity Total Remaining 5 Year Effective Remaining Effective Non-Effective (2019/20 – 2023/24) (2024/25 – 2026/27) (Post 2027) 2500 2500 325 300 1875 Total Completions First Year in Currently In Established First Year in Effective Currently in Effective Established Supply Supply Since Supply Supply Since 0 2006 2006 2006 2006

2019/20 2020/21 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 Post 2027

Total 0 50 75 100 100 100 100 100 1875 Affordable 0 25 25 25 25 25 25 25 475

Market 0 25 50 75 75 75 75 75 1400

Completions

Pre 2010 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 Total 0 0 0 0 0 0 0 0 0 0 Af 0 0 0 0 0 0 0 0 0 0 Mkt 0 0 0 0 0 0 0 0 0 0

Tests of Effectiveness

Ownership Physical Contamination Deficit Funding Marketability Infrastructure Land Use Yes Yes Yes Yes Yes Yes Yes

33 Appendix A: Schedule of Sites

East Fallin, Fallin SC212 / H077 Actions Required to Deliver this site Planning application to be submitted.

Site Details

Audit Status Planning Status Local Ward LDP Sub Monitoring Type Land and Area Development Type 5 year effective Proposal 7 - Bannockburn Core LDP Greenfield New build

Site Site Developer (s) X / Y Co- Latest Approval Expiry Date Area Density ordinates 24.50 16.33 - 284237 / - - - 691668 -

Programming

Total Capacity Total Remaining 5 Year Effective Remaining Effective Non-Effective (2019/20 – 2023/24) (2024/25 – 2026/27) (Post 2027) 400 400 55 105 240 Total Completions First Year in Currently In Established First Year in Effective Currently in Effective Established Supply Supply Since Supply Supply Since 0 2013 2013 2013 2013

2019/20 2020/21 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 Post 2027

Total 0 0 0 20 35 35 35 35 240 Affordable 0 0 0 10 10 10 10 0 0

Market 0 0 0 10 25 25 25 35 240

Completions

Pre 2010 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 Total 0 0 0 0 0 0 0 0 0 0 Af 0 0 0 0 0 0 0 0 0 0 Mkt 0 0 0 0 0 0 0 0 0 0

Tests of Effectiveness

Ownership Physical Contamination Deficit Funding Marketability Infrastructure Land Use Yes Yes Yes Yes Yes Yes Yes

34 Appendix A: Schedule of Sites

Falcon House, Fallin SC251 / H158 Actions Required to Deliver this site Site is non effective. Candidate for removal from next LDP.

Site Details

Audit Status Planning Status Local Ward LDP Sub Monitoring Type Land and Area Development Type Non effective Proposal 7 - Bannockburn Core LDP Brownfield New build

Site Site Developer (s) X / Y Co- Latest Approval Expiry Date Area Density ordinates 0.58 41.38 Falcon Electrical Engineering 284268 / 09/00677/FUL 19/06/2017 - 691276 -

Programming

Total Capacity Total Remaining 5 Year Effective Remaining Effective Non-Effective (2019/20 – 2023/24) (2024/25 – 2026/27) (Post 2027) 24 24 0 0 24 Total Completions First Year in Currently In Established First Year in Effective Currently in Effective Established Supply Supply Since Supply Supply Since 0 2014 2014 2014 0

2019/20 2020/21 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 Post 2027

Total 0 0 0 0 0 0 0 0 24 Affordable 0 0 0 0 0 0 0 0 0

Market 0 0 0 0 0 0 0 0 24

Completions

Pre 2010 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 Total 0 0 0 0 0 0 0 0 0 0 Af 0 0 0 0 0 0 0 0 0 0 Mkt 0 0 0 0 0 0 0 0 0 0

Tests of Effectiveness

Ownership Physical Contamination Deficit Funding Marketability Infrastructure Land Use No Yes Yes Yes Yes Yes Yes

35 Appendix A: Schedule of Sites

Former Fallin Local Office, Fallin SC273 / - Actions Required to Deliver this site Continue build out of site

Site Details

Audit Status Planning Status Local Ward LDP Sub Monitoring Type Land and Area Development Type 5 year effective Under Construction 7 - Bannockburn Core Windfall Brownfield Conversion

Site Site Developer (s) X / Y Co- Latest Approval Expiry Date Area Density ordinates 0.03 133.33 Stirling Council 283483 / 17/00224/FUL 18/05/2020 - 691765 -

Programming

Total Capacity Total Remaining 5 Year Effective Remaining Effective Non-Effective (2019/20 – 2023/24) (2024/25 – 2026/27) (Post 2027) 4 4 4 0 0 Total Completions First Year in Currently In Established First Year in Effective Currently in Effective Established Supply Supply Since Supply Supply Since 0 2017 2017 2017 2017

2019/20 2020/21 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 Post 2027

Total 4 0 0 0 0 0 0 0 0 Affordable 4 0 0 0 0 0 0 0 0

Market 0 0 0 0 0 0 0 0 0

Completions

Pre 2010 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 Total 0 0 0 0 0 0 0 0 0 0 Af 0 0 0 0 0 0 0 0 0 0 Mkt 0 0 0 0 0 0 0 0 0 0

Tests of Effectiveness

Ownership Physical Contamination Deficit Funding Marketability Infrastructure Land Use Yes Yes Yes Yes Yes Yes Yes

36 Appendix A: Schedule of Sites

Menzies Terrace, SC218 / H098 Actions Required to Deliver this site Submission of a planning application.

Site Details

Audit Status Planning Status Local Ward LDP Sub Monitoring Type Land and Area Development Type 5 year effective Proposal 2 - Forth and Rural LDP Greenfield New build Endrick Site Site Developer (s) X / Y Co- Latest Approval Expiry Date Area Density ordinates 4.10 9.76 Ecovillage Enterprises 261672 / - - Rural Stirling Housing Association 687140 -

Programming

Total Capacity Total Remaining 5 Year Effective Remaining Effective Non-Effective (2019/20 – 2023/24) (2024/25 – 2026/27) (Post 2027) 40 40 32 8 0 Total Completions First Year in Currently In Established First Year in Effective Currently in Effective Established Supply Supply Since Supply Supply Since 0 2013 2013 2013 2014

2019/20 2020/21 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 Post 2027

Total 0 0 9 15 8 8 0 0 0 Affordable 0 0 0 15 0 0 0 0 0

Market 0 0 9 0 8 8 0 0 0

Completions

Pre 2010 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 Total 0 0 0 0 0 0 0 0 0 0 Af 0 0 0 0 0 0 0 0 0 0 Mkt 0 0 0 0 0 0 0 0 0 0

Tests of Effectiveness

Ownership Physical Contamination Deficit Funding Marketability Infrastructure Land Use Yes Yes Yes Yes Yes Yes Yes

37 Appendix A: Schedule of Sites

Blairessan, SC246 / H102 Actions Required to Deliver this site Continue build out of site.

Site Details

Audit Status Planning Status Local Ward LDP Sub Monitoring Type Land and Area Development Type 5 year effective Under Construction 2 - Forth and Rural LDP Greenfield New build Endrick Site Site Developer (s) X / Y Co- Latest Approval Expiry Date Area Density ordinates 3.51 10.54 MacTaggart and Mickel 252133 / 18/00139/FUL 25/05/2021 Rural Stirling Housing Association 686314 -

Programming

Total Capacity Total Remaining 5 Year Effective Remaining Effective Non-Effective (2019/20 – 2023/24) (2024/25 – 2026/27) (Post 2027) 37 23 23 0 0 Total Completions First Year in Currently In Established First Year in Effective Currently in Effective Established Supply Supply Since Supply Supply Since 14 2014 2014 2014 2014

2019/20 2020/21 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 Post 2027

Total 23 0 0 0 0 0 0 0 0 Affordable 0 0 0 0 0 0 0 0 0

Market 23 0 0 0 0 0 0 0 0

Completions

Pre 2010 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 Total 0 0 0 0 0 0 0 0 0 14 Af 0 0 0 0 0 0 0 0 0 12 Mkt 0 0 0 0 0 0 0 0 0 2

Tests of Effectiveness

Ownership Physical Contamination Deficit Funding Marketability Infrastructure Land Use Yes Yes Yes Yes Yes Yes Yes

38 Appendix A: Schedule of Sites

Former Killearn Hotel, Killearn SC289 / - Actions Required to Deliver this site Start on site.

Site Details

Audit Status Planning Status Local Ward LDP Sub Monitoring Type Land and Area Development Type 5 year effective FUL 2 - Forth and Rural Windfall Brownfield Mixture Endrick Site Site Developer (s) X / Y Co- Latest Approval Expiry Date Area Density ordinates 0.34 41.18 APSIS Solutions 252273 / 17/00529/FUL 02/08/2022 Convey Prenty Architects 685935 -

Programming

Total Capacity Total Remaining 5 Year Effective Remaining Effective Non-Effective (2019/20 – 2023/24) (2024/25 – 2026/27) (Post 2027) 14 14 14 0 0 Total Completions First Year in Currently In Established First Year in Effective Currently in Effective Established Supply Supply Since Supply Supply Since 0 2019 2019 2019 2019

2019/20 2020/21 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 Post 2027

Total 0 0 14 0 0 0 0 0 0 Affordable 0 0 0 0 0 0 0 0 0

Market 0 0 14 0 0 0 0 0 0

Completions

Pre 2010 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 Total 0 0 0 0 0 0 0 0 0 0 Af 0 0 0 0 0 0 0 0 0 0 Mkt 0 0 0 0 0 0 0 0 0 0

Tests of Effectiveness

Ownership Physical Contamination Deficit Funding Marketability Infrastructure Land Use Yes Yes Yes Yes Yes Yes Yes

39 Appendix A: Schedule of Sites

Lampson Road, Killearn SC290 / - Actions Required to Deliver this site Council to work with RSHA to deliver the development.

Site Details

Audit Status Planning Status Local Ward LDP Sub Monitoring Type Land and Area Development Type 5 year effective Proposal 2 - Forth and Rural Windfall Greenfield New build Endrick Site Site Developer (s) X / Y Co- Latest Approval Expiry Date Area Density ordinates 0.00 Rural Stirling Housing Assoication 0 / 0 - - - -

Programming

Total Capacity Total Remaining 5 Year Effective Remaining Effective Non-Effective (2019/20 – 2023/24) (2024/25 – 2026/27) (Post 2027) 9 12 12 0 0 Total Completions First Year in Currently In Established First Year in Effective Currently in Effective Established Supply Supply Since Supply Supply Since 0 2019 2019 2019 2019

2019/20 2020/21 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 Post 2027

Total 0 12 0 0 0 0 0 0 0 Affordable 0 12 0 0 0 0 0 0 0

Market 0 0 0 0 0 0 0 0 0

Completions

Pre 2010 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 Total 0 0 0 0 0 0 0 0 0 0 Af 0 0 0 0 0 0 0 0 0 0 Mkt 0 0 0 0 0 0 0 0 0 0

Tests of Effectiveness

Ownership Physical Contamination Deficit Funding Marketability Infrastructure Land Use Yes Yes Yes Yes Yes Yes Yes

40 Appendix A: Schedule of Sites

Burnside, SC223 / H103 Actions Required to Deliver this site Decision to be made on application.

Site Details

Audit Status Planning Status Local Ward LDP Sub Monitoring Type Land and Area Development Type 5 year effective Proposal 2 - Forth and Rural LDP Greenfield New build Endrick Site Site Developer (s) X / Y Co- Latest Approval Expiry Date Area Density ordinates 1.54 20.13 Cala Homes 265127 / - - - 694390 -

Programming

Total Capacity Total Remaining 5 Year Effective Remaining Effective Non-Effective (2019/20 – 2023/24) (2024/25 – 2026/27) (Post 2027) 31 30 30 0 0 Total Completions First Year in Currently In Established First Year in Effective Currently in Effective Established Supply Supply Since Supply Supply Since 0 2014 2014 2017 2017

2019/20 2020/21 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 Post 2027

Total 0 0 0 30 0 0 0 0 0 Affordable 0 0 0 10 0 0 0 0 0

Market 0 0 0 20 0 0 0 0 0

Completions

Pre 2010 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 Total 0 0 0 0 0 0 0 0 0 0 Af 0 0 0 0 0 0 0 0 0 0 Mkt 0 0 0 0 0 0 0 0 0 0

Tests of Effectiveness

Ownership Physical Contamination Deficit Funding Marketability Infrastructure Land Use Yes Yes Yes Yes Yes Yes Yes

41 Appendix A: Schedule of Sites

Touchill Farm, Plean SC041 / H072 Actions Required to Deliver this site Council to work with landowner to deliver the development.

Site Details

Audit Status Planning Status Local Ward LDP Sub Monitoring Type Land and Area Development Type 5 year effective FUL 7 - Bannockburn Core LDP Greenfield New build

Site Site Developer (s) X / Y Co- Latest Approval Expiry Date Area Density ordinates 6.89 24.24 Strawson Holdings Ltd 283234 / 16/00731/FUL 05/01/2020 - 687090 -

Programming

Total Capacity Total Remaining 5 Year Effective Remaining Effective Non-Effective (2019/20 – 2023/24) (2024/25 – 2026/27) (Post 2027) 167 167 85 82 0 Total Completions First Year in Currently In Established First Year in Effective Currently in Effective Established Supply Supply Since Supply Supply Since 0 1989 1989 1989 2012

2019/20 2020/21 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 Post 2027

Total 0 0 15 35 35 43 39 0 0 Affordable 0 0 0 0 0 10 9 0 0

Market 0 0 15 35 35 33 30 0 0

Completions

Pre 2010 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 Total 0 0 0 0 0 0 0 0 0 0 Af 0 0 0 0 0 0 0 0 0 0 Mkt 0 0 0 0 0 0 0 0 0 0

Tests of Effectiveness

Ownership Physical Contamination Deficit Funding Marketability Infrastructure Land Use Yes Yes Yes Yes Yes Yes Yes

42 Appendix A: Schedule of Sites

Main Street 1, Plean SC044 / H073 Actions Required to Deliver this site Submission of planning application.

Site Details

Audit Status Planning Status Local Ward LDP Sub Monitoring Type Land and Area Development Type Non effective Proposal 7 - Bannockburn Core LDP Greenfield New build

Site Site Developer (s) X / Y Co- Latest Approval Expiry Date Area Density ordinates 0.83 19.28 Stewart Milne 283624 / 15/00104/FUL 12/06/2017 - 686685 -

Programming

Total Capacity Total Remaining 5 Year Effective Remaining Effective Non-Effective (2019/20 – 2023/24) (2024/25 – 2026/27) (Post 2027) 16 16 0 0 16 Total Completions First Year in Currently In Established First Year in Effective Currently in Effective Established Supply Supply Since Supply Supply Since 0 2002 2002 2007 2007

2019/20 2020/21 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 Post 2027

Total 0 0 0 0 0 0 0 0 16 Affordable 0 0 0 0 0 0 0 0 0

Market 0 0 0 0 0 0 0 0 16

Completions

Pre 2010 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 Total 0 0 0 0 0 0 0 0 0 0 Af 0 0 0 0 0 0 0 0 0 0 Mkt 0 0 0 0 0 0 0 0 0 0

Tests of Effectiveness

Ownership Physical Contamination Deficit Funding Marketability Infrastructure Land Use Yes Yes Yes Yes Yes Yes Yes

43 Appendix A: Schedule of Sites

East Plean, Plean SC252 / H069 Actions Required to Deliver this site Decision to be made on applications.

Site Details

Audit Status Planning Status Local Ward LDP Sub Monitoring Type Land and Area Development Type 5 year effective Proposal 7 - Bannockburn Core LDP Greenfield New build

Site Site Developer (s) X / Y Co- Latest Approval Expiry Date Area Density ordinates 5.95 84.03 Story Homes 283796 / - - Persimmon 686906 -

Programming

Total Capacity Total Remaining 5 Year Effective Remaining Effective Non-Effective (2019/20 – 2023/24) (2024/25 – 2026/27) (Post 2027) 500 500 187 150 163 Total Completions First Year in Currently In Established First Year in Effective Currently in Effective Established Supply Supply Since Supply Supply Since 0 2014 2014 2017 2017

2019/20 2020/21 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 Post 2027

Total 0 30 59 28 70 50 50 50 163 Affordable 0 29 0 15 15 15 15 15 21

Market 0 1 59 13 55 35 35 35 142

Completions

Pre 2010 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 Total 0 0 0 0 0 0 0 0 0 0 Af 0 0 0 0 0 0 0 0 0 0 Mkt 0 0 0 0 0 0 0 0 0 0

Tests of Effectiveness

Ownership Physical Contamination Deficit Funding Marketability Infrastructure Land Use Yes Yes Yes Yes Yes Yes Yes

44 Appendix A: Schedule of Sites

Dalnair House, Rural SC132 / H116 Actions Required to Deliver this site Continue build out of site.

Site Details

Audit Status Planning Status Local Ward LDP Sub Monitoring Type Land and Area Development Type 5 year effective Under Construction 2 - Forth and Rural LDP Brownfield Mixture Endrick Site Site Developer (s) X / Y Co- Latest Approval Expiry Date Area Density ordinates 3.06 10.46 Corum Properties 248257 / 18/00090/MSC 16/05/2018 - 686135 -

Programming

Total Capacity Total Remaining 5 Year Effective Remaining Effective Non-Effective (2019/20 – 2023/24) (2024/25 – 2026/27) (Post 2027) 32 24 24 0 0 Total Completions First Year in Currently In Established First Year in Effective Currently in Effective Established Supply Supply Since Supply Supply Since 8 2008 2008 2008 2014

2019/20 2020/21 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 Post 2027

Total 10 14 0 0 0 0 0 0 0 Affordable 0 0 0 0 0 0 0 0 0

Market 10 14 0 0 0 0 0 0 0

Completions

Pre 2010 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 Total 0 0 0 0 0 0 0 0 0 8 Af 0 0 0 0 0 0 0 0 0 0 Mkt 0 0 0 0 0 0 0 0 0 8

Tests of Effectiveness

Ownership Physical Contamination Deficit Funding Marketability Infrastructure Land Use Yes Yes Yes Yes Yes Yes Yes

45 Appendix A: Schedule of Sites

Craigforth, Rural SC149 / H119 Actions Required to Deliver this site Site is non effective. Candidate for removal from next LDP.

Site Details

Audit Status Planning Status Local Ward LDP Sub Monitoring Type Land and Area Development Type Non effective Proposal 4 - Core LDP Brownfield New build

Site Site Developer (s) X / Y Co- Latest Approval Expiry Date Area Density ordinates 2.28 3.51 Prudential Corportate Property 277467 / 13/00803/FUL 24/02/2017 - 694863 -

Programming

Total Capacity Total Remaining 5 Year Effective Remaining Effective Non-Effective (2019/20 – 2023/24) (2024/25 – 2026/27) (Post 2027) 8 8 0 0 8 Total Completions First Year in Currently In Established First Year in Effective Currently in Effective Established Supply Supply Since Supply Supply Since 0 2008 2008 2012 2019

2019/20 2020/21 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 Post 2027

Total 0 0 0 0 0 0 0 0 8 Affordable 0 0 0 0 0 0 0 0 0

Market 0 0 0 0 0 0 0 0 8

Completions

Pre 2010 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 Total 0 0 0 0 0 0 0 0 0 0 Af 0 0 0 0 0 0 0 0 0 0 Mkt 0 0 0 0 0 0 0 0 0 0

Tests of Effectiveness

Ownership Physical Contamination Deficit Funding Marketability Infrastructure Land Use No Yes Yes Yes Yes Yes Yes

46 Appendix A: Schedule of Sites

Land at Wester Cambushinne Farmhouse, Rural SC175 / H124 Actions Required to Deliver this site Site is non effective. Candidate for removal from next LDP.

Site Details

Audit Status Planning Status Local Ward LDP Sub Monitoring Type Land and Area Development Type Non effective Proposal 3 - Dunblane and Rural LDP Brownfield Mixture Bridge of Allan Site Site Developer (s) X / Y Co- Latest Approval Expiry Date Area Density ordinates 0.93 6.45 Guy Spurway 279080 / 12/00740/FUL 15/01/2016 - 706659 -

Programming

Total Capacity Total Remaining 5 Year Effective Remaining Effective Non-Effective (2019/20 – 2023/24) (2024/25 – 2026/27) (Post 2027) 6 6 0 0 6 Total Completions First Year in Currently In Established First Year in Effective Currently in Effective Established Supply Supply Since Supply Supply Since 0 2010 2010 2010 0

2019/20 2020/21 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 Post 2027

Total 0 0 0 0 0 0 0 0 6 Affordable 0 0 0 0 0 0 0 0 0

Market 0 0 0 0 0 0 0 0 6

Completions

Pre 2010 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 Total 0 0 0 0 0 0 0 0 0 0 Af 0 0 0 0 0 0 0 0 0 0 Mkt 0 0 0 0 0 0 0 0 0 0

Tests of Effectiveness

Ownership Physical Contamination Deficit Funding Marketability Infrastructure Land Use No Yes Yes Yes Yes Yes Yes

47 Appendix A: Schedule of Sites

Fairfield Farm, Rural SC184 / H126 Actions Required to Deliver this site Start on site.

Site Details

Audit Status Planning Status Local Ward LDP Sub Monitoring Type Land and Area Development Type 5 year effective FUL 2 - Forth and Rural LDP Brownfield Conversion Endrick Site Site Developer (s) X / Y Co- Latest Approval Expiry Date Area Density ordinates 0.28 17.86 Mr and Mrs David Steel 263831 / 18/00447/FUL 30/08/2021 - 695712 -

Programming

Total Capacity Total Remaining 5 Year Effective Remaining Effective Non-Effective (2019/20 – 2023/24) (2024/25 – 2026/27) (Post 2027) 5 5 5 0 0 Total Completions First Year in Currently In Established First Year in Effective Currently in Effective Established Supply Supply Since Supply Supply Since 0 2011 2011 2011 2013

2019/20 2020/21 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 Post 2027

Total 0 0 2 3 0 0 0 0 0 Affordable 0 0 0 0 0 0 0 0 0

Market 0 0 2 3 0 0 0 0 0

Completions

Pre 2010 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 Total 0 0 0 0 0 0 0 0 0 0 Af 0 0 0 0 0 0 0 0 0 0 Mkt 0 0 0 0 0 0 0 0 0 0

Tests of Effectiveness

Ownership Physical Contamination Deficit Funding Marketability Infrastructure Land Use Yes Yes Yes Yes Yes Yes Yes

48 Appendix A: Schedule of Sites

Lower Canglour Farm, Rural SC236 / H151 Actions Required to Deliver this site Continue build out of site.

Site Details

Audit Status Planning Status Local Ward LDP Sub Monitoring Type Land and Area Development Type 5 year effective Under Construction 5 - Stirling West Rural LDP Brownfield Conversion

Site Site Developer (s) X / Y Co- Latest Approval Expiry Date Area Density ordinates 0.06 66.67 Mr J Versel 278385 / 12/00826/FUL 28/02/2016 - 686799 -

Programming

Total Capacity Total Remaining 5 Year Effective Remaining Effective Non-Effective (2019/20 – 2023/24) (2024/25 – 2026/27) (Post 2027) 4 2 2 0 0 Total Completions First Year in Currently In Established First Year in Effective Currently in Effective Established Supply Supply Since Supply Supply Since 2 2013 2013 2013 2013

2019/20 2020/21 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 Post 2027

Total 1 1 0 0 0 0 0 0 0 Affordable 0 0 0 0 0 0 0 0 0

Market 1 1 0 0 0 0 0 0 0

Completions

Pre 2010 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 Total 0 0 0 0 0 2 0 0 0 0 Af 0 0 0 0 0 0 0 0 0 0 Mkt 0 0 0 0 0 2 0 0 0 0

Tests of Effectiveness

Ownership Physical Contamination Deficit Funding Marketability Infrastructure Land Use Yes Yes Yes Yes Yes Yes Yes

49 Appendix A: Schedule of Sites

Hill O Drip Farm, Rural SC255 / H154 Actions Required to Deliver this site Start on site.

Site Details

Audit Status Planning Status Local Ward LDP Sub Monitoring Type Land and Area Development Type 5 year effective FUL 1 - Trossachs Rural LDP Brownfield Conversion and Teith Site Site Developer (s) X / Y Co- Latest Approval Expiry Date Area Density ordinates 0.75 13.33 Bobby Haliday Architects 276623 / 17/00681/FUL 03/10/2021 - 695600 -

Programming

Total Capacity Total Remaining 5 Year Effective Remaining Effective Non-Effective (2019/20 – 2023/24) (2024/25 – 2026/27) (Post 2027) 10 10 10 0 0 Total Completions First Year in Currently In Established First Year in Effective Currently in Effective Established Supply Supply Since Supply Supply Since 0 2015 2015 2015 2015

2019/20 2020/21 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 Post 2027

Total 0 0 0 6 4 0 0 0 0 Affordable 0 0 0 0 0 0 0 0 0

Market 0 0 0 6 4 0 0 0 0

Completions

Pre 2010 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 Total 0 0 0 0 0 0 0 0 0 0 Af 0 0 0 0 0 0 0 0 0 0 Mkt 0 0 0 0 0 0 0 0 0 0

Tests of Effectiveness

Ownership Physical Contamination Deficit Funding Marketability Infrastructure Land Use Yes Yes Yes Yes Yes Yes Yes

50 Appendix A: Schedule of Sites

Kilearn Hospital, Rural SC270 / H157 Actions Required to Deliver this site Planning application to be submitted.

Site Details

Audit Status Planning Status Local Ward LDP Sub Monitoring Type Land and Area Development Type 5 year effective Proposal 2 - Forth and Rural LDP Brownfield New build Endrick Site Site Developer (s) X / Y Co- Latest Approval Expiry Date Area Density ordinates 10.89 6.43 - 250998 / - - - 684827 -

Programming

Total Capacity Total Remaining 5 Year Effective Remaining Effective Non-Effective (2019/20 – 2023/24) (2024/25 – 2026/27) (Post 2027) 70 70 70 0 0 Total Completions First Year in Currently In Established First Year in Effective Currently in Effective Established Supply Supply Since Supply Supply Since 0 2017 2017 2019 2019

2019/20 2020/21 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 Post 2027

Total 0 0 15 35 20 0 0 0 0 Affordable 0 0 0 0 0 0 0 0 0

Market 0 0 15 35 20 0 0 0 0

Completions

Pre 2010 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 Total 0 0 0 0 0 0 0 0 0 0 Af 0 0 0 0 0 0 0 0 0 0 Mkt 0 0 0 0 0 0 0 0 0 0

Tests of Effectiveness

Ownership Physical Contamination Deficit Funding Marketability Infrastructure Land Use Yes Yes Yes Yes Yes Yes Yes

51 Appendix A: Schedule of Sites

Gartcarron Filters, Rural SC272 / - Actions Required to Deliver this site Start on site.

Site Details

Audit Status Planning Status Local Ward LDP Sub Monitoring Type Land and Area Development Type 5 year effective FUL 2 - Forth and Rural Windfall Brownfield Mixture Endrick Site Site Developer (s) X / Y Co- Latest Approval Expiry Date Area Density ordinates 0.43 11.63 Property Mastery Academy 266720 / 17/00138/FUL 27/04/2020 - 686041 -

Programming

Total Capacity Total Remaining 5 Year Effective Remaining Effective Non-Effective (2019/20 – 2023/24) (2024/25 – 2026/27) (Post 2027) 5 5 5 0 0 Total Completions First Year in Currently In Established First Year in Effective Currently in Effective Established Supply Supply Since Supply Supply Since 0 2017 2017 2017 2017

2019/20 2020/21 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 Post 2027

Total 0 5 0 0 0 0 0 0 0 Affordable 0 0 0 0 0 0 0 0 0

Market 0 5 0 0 0 0 0 0 0

Completions

Pre 2010 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 Total 0 0 0 0 0 0 0 0 0 0 Af 0 0 0 0 0 0 0 0 0 0 Mkt 0 0 0 0 0 0 0 0 0 0

Tests of Effectiveness

Ownership Physical Contamination Deficit Funding Marketability Infrastructure Land Use Yes Yes Yes Yes Yes Yes Yes

52 Appendix A: Schedule of Sites

South of Easter Row, Rural SC274 / - Actions Required to Deliver this site Site is non-effective. Candidate for removal from HLA once Planning Permission Expires.

Site Details

Audit Status Planning Status Local Ward LDP Sub Monitoring Type Land and Area Development Type Non effective FUL 3 - Dunblane and Rural Windfall Brownfield New build Bridge of Allan Site Site Developer (s) X / Y Co- Latest Approval Expiry Date Area Density ordinates 0.26 15.38 Kier Estate 266720 / 16/00439/FUL 12/06/2020 - 686041 -

Programming

Total Capacity Total Remaining 5 Year Effective Remaining Effective Non-Effective (2019/20 – 2023/24) (2024/25 – 2026/27) (Post 2027) 4 4 0 0 4 Total Completions First Year in Currently In Established First Year in Effective Currently in Effective Established Supply Supply Since Supply Supply Since 0 2017 2017 2017 0

2019/20 2020/21 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 Post 2027

Total 0 0 0 0 0 0 0 0 4 Affordable 0 0 0 0 0 0 0 0 0

Market 0 0 0 0 0 0 0 0 4

Completions

Pre 2010 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 Total 0 0 0 0 0 0 0 0 0 0 Af 0 0 0 0 0 0 0 0 0 0 Mkt 0 0 0 0 0 0 0 0 0 0

Tests of Effectiveness

Ownership Physical Contamination Deficit Funding Marketability Infrastructure Land Use No Yes Yes Yes Yes Yes Yes

53 Appendix A: Schedule of Sites

Mains of Boquhapple, Rural SC277 / - Actions Required to Deliver this site Continue build out of site

Site Details

Audit Status Planning Status Local Ward LDP Sub Monitoring Type Land and Area Development Type 5 year effective Under Construction 1 - Trossachs Rural Windfall Brownfield New build and Teith Site Site Developer (s) X / Y Co- Latest Approval Expiry Date Area Density ordinates 0.00 W S Dunsire 700048 / 15/00345/FUL 21/08/2020 - -

Programming

Total Capacity Total Remaining 5 Year Effective Remaining Effective Non-Effective (2019/20 – 2023/24) (2024/25 – 2026/27) (Post 2027) 8 6 6 0 0 Total Completions First Year in Currently In Established First Year in Effective Currently in Effective Established Supply Supply Since Supply Supply Since 2 2018 2018 2018 2018

2019/20 2020/21 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 Post 2027

Total 4 2 0 0 0 0 0 0 0 Affordable 0 0 0 0 0 0 0 0 0

Market 4 2 0 0 0 0 0 0 0

Completions

Pre 2010 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 Total 0 0 0 0 0 0 0 0 0 2 Af 0 0 0 0 0 0 0 0 0 0 Mkt 0 0 0 0 0 0 0 0 0 2

Tests of Effectiveness

Ownership Physical Contamination Deficit Funding Marketability Infrastructure Land Use Yes Yes Yes Yes Yes Yes Yes

54 Appendix A: Schedule of Sites

Cauldbarns Farm, Rural SC278 / - Actions Required to Deliver this site Continue build out of site.

Site Details

Audit Status Planning Status Local Ward LDP Sub Monitoring Type Land and Area Development Type 5 year effective Under Construction 5 - Stirling West Rural Windfall Brownfield New build

Site Site Developer (s) X / Y Co- Latest Approval Expiry Date Area Density ordinates 0.52 13.46 The Stafford Trust 279156 / 14/00729/PPP 18/08/2020 - 266125 -

Programming

Total Capacity Total Remaining 5 Year Effective Remaining Effective Non-Effective (2019/20 – 2023/24) (2024/25 – 2026/27) (Post 2027) 7 7 7 0 0 Total Completions First Year in Currently In Established First Year in Effective Currently in Effective Established Supply Supply Since Supply Supply Since 0 2018 2018 2018 2018

2019/20 2020/21 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 Post 2027

Total 2 5 0 0 0 0 0 0 0 Affordable 0 0 0 0 0 0 0 0 0

Market 2 5 0 0 0 0 0 0 0

Completions

Pre 2010 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 Total 0 0 0 0 0 0 0 0 0 0 Af 0 0 0 0 0 0 0 0 0 0 Mkt 0 0 0 0 0 0 0 0 0 0

Tests of Effectiveness

Ownership Physical Contamination Deficit Funding Marketability Infrastructure Land Use Yes Yes Yes Yes Yes Yes Yes

55 Appendix A: Schedule of Sites

Station House, Rural SC279 / - Actions Required to Deliver this site Start on site.

Site Details

Audit Status Planning Status Local Ward LDP Sub Monitoring Type Land and Area Development Type 5 year effective FUL 2 - Forth and Rural Windfall Brownfield New build Endrick Site Site Developer (s) X / Y Co- Latest Approval Expiry Date Area Density ordinates 1.25 3.20 Mr J Steel 266435 / 16/00570/FUL 24/10/2020 - 695741 -

Programming

Total Capacity Total Remaining 5 Year Effective Remaining Effective Non-Effective (2019/20 – 2023/24) (2024/25 – 2026/27) (Post 2027) 4 4 4 0 0 Total Completions First Year in Currently In Established First Year in Effective Currently in Effective Established Supply Supply Since Supply Supply Since 0 2018 2018 2018 2018

2019/20 2020/21 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 Post 2027

Total 0 2 2 0 0 0 0 0 0 Affordable 0 0 0 0 0 0 0 0 0

Market 0 2 2 0 0 0 0 0 0

Completions

Pre 2010 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 Total 0 0 0 0 0 0 0 0 0 0 Af 0 0 0 0 0 0 0 0 0 0 Mkt 0 0 0 0 0 0 0 0 0 0

Tests of Effectiveness

Ownership Physical Contamination Deficit Funding Marketability Infrastructure Land Use Yes Yes Yes Yes Yes Yes Yes

56 Appendix A: Schedule of Sites

Blane Smithy, Rural SC281 / - Actions Required to Deliver this site Continue build out on site.

Site Details

Audit Status Planning Status Local Ward LDP Sub Monitoring Type Land and Area Development Type 5 year effective Under Construction 2 - Forth and Rural Windfall Greenfield New build Endrick Site Site Developer (s) X / Y Co- Latest Approval Expiry Date Area Density ordinates 0.84 5.95 Mr and Mrs John and Lillian McVicar 250672 / 17/00186/FUL 14/12/2020 - 685430 -

Programming

Total Capacity Total Remaining 5 Year Effective Remaining Effective Non-Effective (2019/20 – 2023/24) (2024/25 – 2026/27) (Post 2027) 5 5 5 0 0 Total Completions First Year in Currently In Established First Year in Effective Currently in Effective Established Supply Supply Since Supply Supply Since 0 2018 2018 2018 2018

2019/20 2020/21 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 Post 2027

Total 1 4 0 0 0 0 0 0 0 Affordable 0 0 0 0 0 0 0 0 0

Market 1 4 0 0 0 0 0 0 0

Completions

Pre 2010 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 Total 0 0 0 0 0 0 0 0 0 0 Af 0 0 0 0 0 0 0 0 0 0 Mkt 0 0 0 0 0 0 0 0 0 0

Tests of Effectiveness

Ownership Physical Contamination Deficit Funding Marketability Infrastructure Land Use Yes Yes Yes Yes Yes Yes Yes

57 Appendix A: Schedule of Sites

Gogar Mains, Rural SC282 / - Actions Required to Deliver this site Start on site.

Site Details

Audit Status Planning Status Local Ward LDP Sub Monitoring Type Land and Area Development Type 5 year effective FUL 4 - Stirling North Rural Windfall Brownfield New build

Site Site Developer (s) X / Y Co- Latest Approval Expiry Date Area Density ordinates 0.65 12.31 Mr Alistair Snowie 283709 / 17/00724/FUL 31/01/2021 - 696268 -

Programming

Total Capacity Total Remaining 5 Year Effective Remaining Effective Non-Effective (2019/20 – 2023/24) (2024/25 – 2026/27) (Post 2027) 8 8 8 0 0 Total Completions First Year in Currently In Established First Year in Effective Currently in Effective Established Supply Supply Since Supply Supply Since 0 2018 2018 2018 2018

2019/20 2020/21 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 Post 2027

Total 0 4 4 0 0 0 0 0 0 Affordable 0 0 0 0 0 0 0 0 0

Market 0 4 4 0 0 0 0 0 0

Completions

Pre 2010 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 Total 0 0 0 0 0 0 0 0 0 0 Af 0 0 0 0 0 0 0 0 0 0 Mkt 0 0 0 0 0 0 0 0 0 0

Tests of Effectiveness

Ownership Physical Contamination Deficit Funding Marketability Infrastructure Land Use Yes Yes Yes Yes Yes Yes Yes

58 Appendix A: Schedule of Sites

Kings Park Farm, Rural SC283 / - Actions Required to Deliver this site Start on site.

Site Details

Audit Status Planning Status Local Ward LDP Sub Monitoring Type Land and Area Development Type 5 year effective FUL 5 - Stirling West Core Windfall Brownfield Mixture

Site Site Developer (s) X / Y Co- Latest Approval Expiry Date Area Density ordinates 0.49 14.29 Cramond Select Homes 278703 / 17/00632/FUL 26/04/2021 - 693578 -

Programming

Total Capacity Total Remaining 5 Year Effective Remaining Effective Non-Effective (2019/20 – 2023/24) (2024/25 – 2026/27) (Post 2027) 7 7 7 0 0 Total Completions First Year in Currently In Established First Year in Effective Currently in Effective Established Supply Supply Since Supply Supply Since 0 2018 2018 2018 2018

2019/20 2020/21 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 Post 2027

Total 0 7 0 0 0 0 0 0 0 Affordable 0 0 0 0 0 0 0 0 0

Market 0 7 0 0 0 0 0 0 0

Completions

Pre 2010 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 Total 0 0 0 0 0 0 0 0 0 0 Af 0 0 0 0 0 0 0 0 0 0 Mkt 0 0 0 0 0 0 0 0 0 0

Tests of Effectiveness

Ownership Physical Contamination Deficit Funding Marketability Infrastructure Land Use Yes Yes Yes Yes Yes Yes Yes

59 Appendix A: Schedule of Sites

Park of Keir, Rural SC284 / - Actions Required to Deliver this site Conclusion of S75 Agreement.

Site Details

Audit Status Planning Status Local Ward LDP Sub Monitoring Type Land and Area Development Type 5 year effective Proposal 3 - Dunblane and Core Windfall Greenfield New build Bridge of Allan Site Site Developer (s) X / Y Co- Latest Approval Expiry Date Area Density ordinates 0.00 Park of Keir Partnership 278274 / - - - 698971 -

Programming

Total Capacity Total Remaining 5 Year Effective Remaining Effective Non-Effective (2019/20 – 2023/24) (2024/25 – 2026/27) (Post 2027) 19 19 15 4 0 Total Completions First Year in Currently In Established First Year in Effective Currently in Effective Established Supply Supply Since Supply Supply Since 0 2018 2018 2018 2018

2019/20 2020/21 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 Post 2027

Total 0 0 0 5 10 4 0 0 0 Affordable 0 0 0 0 0 0 0 0 0

Market 0 0 0 5 10 4 0 0 0

Completions

Pre 2010 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 Total 0 0 0 0 0 0 0 0 0 0 Af 0 0 0 0 0 0 0 0 0 0 Mkt 0 0 0 0 0 0 0 0 0 0

Tests of Effectiveness

Ownership Physical Contamination Deficit Funding Marketability Infrastructure Land Use Yes Yes Yes Yes Yes Yes Yes

60 Appendix A: Schedule of Sites

Strewiebank Farm, Rural SC285 / - Actions Required to Deliver this site Continue build out of site.

Site Details

Audit Status Planning Status Local Ward LDP Sub Monitoring Type Land and Area Development Type 5 year effective Under Construction 2 - Forth and Rural Windfall Brownfield Mixture Endrick Site Site Developer (s) X / Y Co- Latest Approval Expiry Date Area Density ordinates 0.71 8.45 Mr F Hillhouse 264354 / 14/00206/FUL 23/07/2021 - 695363 -

Programming

Total Capacity Total Remaining 5 Year Effective Remaining Effective Non-Effective (2019/20 – 2023/24) (2024/25 – 2026/27) (Post 2027) 6 6 6 0 0 Total Completions First Year in Currently In Established First Year in Effective Currently in Effective Established Supply Supply Since Supply Supply Since 0 2019 2019 2019 2019

2019/20 2020/21 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 Post 2027

Total 0 3 3 0 0 0 0 0 0 Affordable 0 0 0 0 0 0 0 0 0

Market 0 3 3 0 0 0 0 0 0

Completions

Pre 2010 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 Total 0 0 0 0 0 0 0 0 0 0 Af 0 0 0 0 0 0 0 0 0 0 Mkt 0 0 0 0 0 0 0 0 0 0

Tests of Effectiveness

Ownership Physical Contamination Deficit Funding Marketability Infrastructure Land Use Yes Yes Yes Yes Yes Yes Yes

61 Appendix A: Schedule of Sites

Gartur House, Rural SC286 / - Actions Required to Deliver this site Start on site.

Site Details

Audit Status Planning Status Local Ward LDP Sub Monitoring Type Land and Area Development Type 5 year effective FUL 5 - Stirling West Rural Windfall Brownfield Mixture

Site Site Developer (s) X / Y Co- Latest Approval Expiry Date Area Density ordinates 3.30 2.73 Juniper Projects Ltd 276456 / 18/00318/FUL 08/11/2021 Scott Allan 692154 -

Programming

Total Capacity Total Remaining 5 Year Effective Remaining Effective Non-Effective (2019/20 – 2023/24) (2024/25 – 2026/27) (Post 2027) 9 9 9 0 0 Total Completions First Year in Currently In Established First Year in Effective Currently in Effective Established Supply Supply Since Supply Supply Since 0 2019 2019 2019 2019

2019/20 2020/21 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 Post 2027

Total 0 4 5 0 0 0 0 0 0 Affordable 0 0 0 0 0 0 0 0 0

Market 0 4 5 0 0 0 0 0 0

Completions

Pre 2010 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 Total 0 0 0 0 0 0 0 0 0 0 Af 0 0 0 0 0 0 0 0 0 0 Mkt 0 0 0 0 0 0 0 0 0 0

Tests of Effectiveness

Ownership Physical Contamination Deficit Funding Marketability Infrastructure Land Use Yes Yes Yes Yes Yes Yes Yes

62 Appendix A: Schedule of Sites

Moor Road, Rural SC287 / - Actions Required to Deliver this site Start on site.

Site Details

Audit Status Planning Status Local Ward LDP Sub Monitoring Type Land and Area Development Type 5 year effective FUL 2 - Forth and Rural Windfall Greenfield New build Endrick Site Site Developer (s) X / Y Co- Latest Approval Expiry Date Area Density ordinates 0.14 28.57 Mosaic Architecture and Design 255905 / 16/00798/FUL 26/11/2021 Ewan Buchanan 678636 -

Programming

Total Capacity Total Remaining 5 Year Effective Remaining Effective Non-Effective (2019/20 – 2023/24) (2024/25 – 2026/27) (Post 2027) 4 4 4 0 0 Total Completions First Year in Currently In Established First Year in Effective Currently in Effective Established Supply Supply Since Supply Supply Since 0 2019 2019 2019 2019

2019/20 2020/21 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 Post 2027

Total 0 1 3 0 0 0 0 0 0 Affordable 0 0 0 0 0 0 0 0 0

Market 0 1 3 0 0 0 0 0 0

Completions

Pre 2010 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 Total 0 0 0 0 0 0 0 0 0 0 Af 0 0 0 0 0 0 0 0 0 0 Mkt 0 0 0 0 0 0 0 0 0 0

Tests of Effectiveness

Ownership Physical Contamination Deficit Funding Marketability Infrastructure Land Use Yes Yes Yes Yes Yes Yes Yes

63 Appendix A: Schedule of Sites

East of Rochoill, Rural SC288 / - Actions Required to Deliver this site Start on site.

Site Details

Audit Status Planning Status Local Ward LDP Sub Monitoring Type Land and Area Development Type 5 year effective FUL 2 - Forth and Rural Windfall Greenfield New build Endrick Site Site Developer (s) X / Y Co- Latest Approval Expiry Date Area Density ordinates 0.42 11.90 Enspire Architects 266369 / 17/00428/FUL 20/12/2021 Gary Neill 694519 -

Programming

Total Capacity Total Remaining 5 Year Effective Remaining Effective Non-Effective (2019/20 – 2023/24) (2024/25 – 2026/27) (Post 2027) 5 5 5 0 0 Total Completions First Year in Currently In Established First Year in Effective Currently in Effective Established Supply Supply Since Supply Supply Since 0 2019 2019 2019 2019

2019/20 2020/21 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 Post 2027

Total 0 2 3 0 0 0 0 0 0 Affordable 0 0 0 0 0 0 0 0 0

Market 0 2 3 0 0 0 0 0 0

Completions

Pre 2010 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 Total 0 0 0 0 0 0 0 0 0 0 Af 0 0 0 0 0 0 0 0 0 0 Mkt 0 0 0 0 0 0 0 0 0 0

Tests of Effectiveness

Ownership Physical Contamination Deficit Funding Marketability Infrastructure Land Use Yes Yes Yes Yes Yes Yes Yes

64 Appendix A: Schedule of Sites

Braehead 1, Stirling SC047 / H023 Actions Required to Deliver this site Council to explore how development can be brought forward on this site.

Site Details

Audit Status Planning Status Local Ward LDP Sub Monitoring Type Land and Area Development Type Non effective Proposal 6 - Core LDP Greenfield New build

Site Site Developer (s) X / Y Co- Latest Approval Expiry Date Area Density ordinates 7.36 20.38 Stirling Council 280498 / - - - 692058 -

Programming

Total Capacity Total Remaining 5 Year Effective Remaining Effective Non-Effective (2019/20 – 2023/24) (2024/25 – 2026/27) (Post 2027) 150 150 0 0 150 Total Completions First Year in Currently In Established First Year in Effective Currently in Effective Established Supply Supply Since Supply Supply Since 0 2002 2002 2002 0

2019/20 2020/21 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 Post 2027

Total 0 0 0 0 0 0 0 0 150 Affordable 0 0 0 0 0 0 0 0 150

Market 0 0 0 0 0 0 0 0 0

Completions

Pre 2010 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 Total 0 0 0 0 0 0 0 0 0 0 Af 0 0 0 0 0 0 0 0 0 0 Mkt 0 0 0 0 0 0 0 0 0 0

Tests of Effectiveness

Ownership Physical Contamination Deficit Funding Marketability Infrastructure Land Use Yes No No No Yes No No

65 Appendix A: Schedule of Sites

Area 8 Raploch Schools, Stirling SC049 / H061 Actions Required to Deliver this site Start on site.

Site Details

Audit Status Planning Status Local Ward LDP Sub Monitoring Type Land and Area Development Type 5 year effective FUL 4 - Stirling North Core LDP Brownfield New build

Site Site Developer (s) X / Y Co- Latest Approval Expiry Date Area Density ordinates 6.10 34.59 Robertsons Homes 278412 / 18/00127/MSC 31/05/2023 CREHA 694748 -

Programming

Total Capacity Total Remaining 5 Year Effective Remaining Effective Non-Effective (2019/20 – 2023/24) (2024/25 – 2026/27) (Post 2027) 211 211 211 0 0 Total Completions First Year in Currently In Established First Year in Effective Currently in Effective Established Supply Supply Since Supply Supply Since 0 2002 2002 2002 2016

2019/20 2020/21 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 Post 2027

Total 20 77 77 37 0 0 0 0 0 Affordable 20 77 39 0 0 0 0 0 0

Market 0 0 38 37 0 0 0 0 0

Completions

Pre 2010 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 Total 0 0 0 0 0 0 0 0 0 0 Af 0 0 0 0 0 0 0 0 0 0 Mkt 0 0 0 0 0 0 0 0 0 0

Tests of Effectiveness

Ownership Physical Contamination Deficit Funding Marketability Infrastructure Land Use Yes Yes Yes Yes Yes Yes Yes

66 Appendix A: Schedule of Sites

Riverbank Works, Stirling SC054 / H028 Actions Required to Deliver this site Site is non effective. Candidate for removal from next LDP.

Site Details

Audit Status Planning Status Local Ward LDP Sub Monitoring Type Land and Area Development Type Non effective Proposal 4 - Stirling North Core LDP Brownfield New build

Site Site Developer (s) X / Y Co- Latest Approval Expiry Date Area Density ordinates 3.35 23.88 Taylor Wimpey Homes 280549 / - - - 695302 -

Programming

Total Capacity Total Remaining 5 Year Effective Remaining Effective Non-Effective (2019/20 – 2023/24) (2024/25 – 2026/27) (Post 2027) 80 80 0 0 80 Total Completions First Year in Currently In Established First Year in Effective Currently in Effective Established Supply Supply Since Supply Supply Since 0 2003 2003 2003 0

2019/20 2020/21 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 Post 2027

Total 0 0 0 0 0 0 0 0 80 Affordable 0 0 0 0 0 0 0 0 20

Market 0 0 0 0 0 0 0 0 60

Completions

Pre 2010 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 Total 0 0 0 0 0 0 0 0 0 0 Af 0 0 0 0 0 0 0 0 0 0 Mkt 0 0 0 0 0 0 0 0 0 0

Tests of Effectiveness

Ownership Physical Contamination Deficit Funding Marketability Infrastructure Land Use No No Yes Yes Yes Yes Yes

67 Appendix A: Schedule of Sites

Forthside Phase 2, Stirling SC067B / H034 Actions Required to Deliver this site Council to work with landowner to bring forward rest of site for development.

Site Details

Audit Status Planning Status Local Ward LDP Sub Monitoring Type Land and Area Development Type 5 year effective FUL 4 - Stirling North Core LDP Brownfield New build

Site Site Developer (s) X / Y Co- Latest Approval Expiry Date Area Density ordinates 1.92 59.38 Stirling Council 279915 / 15/00790/FUL 26/10/2019 - 693735 -

Programming

Total Capacity Total Remaining 5 Year Effective Remaining Effective Non-Effective (2019/20 – 2023/24) (2024/25 – 2026/27) (Post 2027) 114 40 40 0 0 Total Completions First Year in Currently In Established First Year in Effective Currently in Effective Established Supply Supply Since Supply Supply Since 74 2009 2009 2009 2017

2019/20 2020/21 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 Post 2027

Total 0 0 0 20 20 0 0 0 0 Affordable 0 0 0 0 0 0 0 0 0

Market 0 0 0 20 20 0 0 0 0

Completions

Pre 2010 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 Total 0 3 71 0 0 0 0 0 0 0 Af 0 0 14 0 0 0 0 0 0 0 Mkt 0 3 57 0 0 0 0 0 0 0

Tests of Effectiveness

Ownership Physical Contamination Deficit Funding Marketability Infrastructure Land Use Yes Yes Yes Yes Yes Yes Yes

68 Appendix A: Schedule of Sites

Area 7 Craigforth Cresecent, Stirling SC075 / H063 Actions Required to Deliver this site Further exploratory work requried.

Site Details

Audit Status Planning Status Local Ward LDP Sub Monitoring Type Land and Area Development Type Non effective PPP 4 - Stirling North Core LDP Greenfield New build

Site Site Developer (s) X / Y Co- Latest Approval Expiry Date Area Density ordinates 2.61 34.10 Stirling Council 278351 / 16/00771/PPP 31/01/2021 - 694352 -

Programming

Total Capacity Total Remaining 5 Year Effective Remaining Effective Non-Effective (2019/20 – 2023/24) (2024/25 – 2026/27) (Post 2027) 89 89 0 0 89 Total Completions First Year in Currently In Established First Year in Effective Currently in Effective Established Supply Supply Since Supply Supply Since 0 2002 2002 2002 0

2019/20 2020/21 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 Post 2027

Total 0 0 0 0 0 0 0 0 89 Affordable 0 0 0 0 0 0 0 0 89

Market 0 0 0 0 0 0 0 0 0

Completions

Pre 2010 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 Total 0 0 0 0 0 0 0 0 0 0 Af 0 0 0 0 0 0 0 0 0 0 Mkt 0 0 0 0 0 0 0 0 0 0

Tests of Effectiveness

Ownership Physical Contamination Deficit Funding Marketability Infrastructure Land Use Yes Yes No Yes Yes Yes Yes

69 Appendix A: Schedule of Sites

Kildean Auction Market, Stirling SC126 / H054 Actions Required to Deliver this site Continue build out of site.

Site Details

Audit Status Planning Status Local Ward LDP Sub Monitoring Type Land and Area Development Type 5 year effective Under Construction 4 - Stirling North Core LDP Brownfield New build

Site Site Developer (s) X / Y Co- Latest Approval Expiry Date Area Density ordinates 9.57 26.54 Barrat Homes 278205 / 18/00123/MSC 18/05/2023 Stirling Council 695207 -

Programming

Total Capacity Total Remaining 5 Year Effective Remaining Effective Non-Effective (2019/20 – 2023/24) (2024/25 – 2026/27) (Post 2027) 254 37 37 0 0 Total Completions First Year in Currently In Established First Year in Effective Currently in Effective Established Supply Supply Since Supply Supply Since 217 2007 2007 2007 2013

2019/20 2020/21 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 Post 2027

Total 37 0 0 0 0 0 0 0 0 Affordable 0 0 0 0 0 0 0 0 0

Market 37 0 0 0 0 0 0 0 0

Completions

Pre 2010 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 Total 0 0 0 0 0 0 63 51 56 47 Af 0 0 0 0 0 0 12 8 0 0 Mkt 0 0 0 0 0 0 51 43 56 47

Tests of Effectiveness

Ownership Physical Contamination Deficit Funding Marketability Infrastructure Land Use Yes Yes Yes Yes Yes Yes Yes

70 Appendix A: Schedule of Sites

Former MFI, Stirling SC133 / H142 Actions Required to Deliver this site Decision to be made on application.

Site Details

Audit Status Planning Status Local Ward LDP Sub Monitoring Type Land and Area Development Type 5 year effective Proposal 6 - Stirling East Core LDP Brownfield New build

Site Site Developer (s) X / Y Co- Latest Approval Expiry Date Area Density ordinates 0.83 36.14 Allan Water Developments 279650 / 13/00410/FUL 15/08/2016 - 691207 -

Programming

Total Capacity Total Remaining 5 Year Effective Remaining Effective Non-Effective (2019/20 – 2023/24) (2024/25 – 2026/27) (Post 2027) 30 30 30 0 0 Total Completions First Year in Currently In Established First Year in Effective Currently in Effective Established Supply Supply Since Supply Supply Since 0 2017 2017 2017 2017

2019/20 2020/21 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 Post 2027

Total 0 0 0 10 20 0 0 0 0 Affordable 0 0 0 0 0 0 0 0 0

Market 0 0 0 10 20 0 0 0 0

Completions

Pre 2010 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 Total 0 0 0 0 0 0 0 0 0 0 Af 0 0 0 0 0 0 0 0 0 0 Mkt 0 0 0 0 0 0 0 0 0 0

Tests of Effectiveness

Ownership Physical Contamination Deficit Funding Marketability Infrastructure Land Use Yes Yes Yes Yes Yes Yes Yes

71 Appendix A: Schedule of Sites

21 Dumbarton Road East, Stirling SC135 / H036 Actions Required to Deliver this site Site is non effective. Candidate for removal from next LDP.

Site Details

Audit Status Planning Status Local Ward LDP Sub Monitoring Type Land and Area Development Type Non effective FUL 4 - Stirling North Core LDP Brownfield New build

Site Site Developer (s) X / Y Co- Latest Approval Expiry Date Area Density ordinates 0.05 120.00 Mr Mark Crawford 279580 / 16/00266/FUL 04/10/2019 - 693207 -

Programming

Total Capacity Total Remaining 5 Year Effective Remaining Effective Non-Effective (2019/20 – 2023/24) (2024/25 – 2026/27) (Post 2027) 6 6 0 0 6 Total Completions First Year in Currently In Established First Year in Effective Currently in Effective Established Supply Supply Since Supply Supply Since 0 2008 2008 2008 0

2019/20 2020/21 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 Post 2027

Total 0 0 0 0 0 0 0 0 6 Affordable 0 0 0 0 0 0 0 0 0

Market 0 0 0 0 0 0 0 0 6

Completions

Pre 2010 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 Total 0 0 0 0 0 0 0 0 0 0 Af 0 0 0 0 0 0 0 0 0 0 Mkt 0 0 0 0 0 0 0 0 0 0

Tests of Effectiveness

Ownership Physical Contamination Deficit Funding Marketability Infrastructure Land Use No Yes Yes Yes Yes Yes Yes

72 Appendix A: Schedule of Sites

32 Baker Street, Stirling SC136 / H037 Actions Required to Deliver this site Start on site.

Site Details

Audit Status Planning Status Local Ward LDP Sub Monitoring Type Land and Area Development Type 5 year effective FUL 4 - Stirling North Core LDP Brownfield New build

Site Site Developer (s) X / Y Co- Latest Approval Expiry Date Area Density ordinates 0.23 43.48 - 279555 / 18/00015/FUL 20/03/2021 - 693575 -

Programming

Total Capacity Total Remaining 5 Year Effective Remaining Effective Non-Effective (2019/20 – 2023/24) (2024/25 – 2026/27) (Post 2027) 10 6 6 0 0 Total Completions First Year in Currently In Established First Year in Effective Currently in Effective Established Supply Supply Since Supply Supply Since 4 2010 2010 2010 2018

2019/20 2020/21 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 Post 2027

Total 0 6 0 0 0 0 0 0 0 Affordable 0 0 0 0 0 0 0 0 0

Market 0 6 0 0 0 0 0 0 0

Completions

Pre 2010 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 Total 0 0 0 0 4 0 0 0 0 0 Af 0 0 0 0 0 0 0 0 0 0 Mkt 0 0 0 0 4 0 0 0 0 0

Tests of Effectiveness

Ownership Physical Contamination Deficit Funding Marketability Infrastructure Land Use Yes Yes Yes No Yes Yes Yes

73 Appendix A: Schedule of Sites

Area 6 Gowanhill Gardens, Stirling SC145 / H066 Actions Required to Deliver this site Start on site.

Site Details

Audit Status Planning Status Local Ward LDP Sub Monitoring Type Land and Area Development Type 5 year effective FUL 4 - Stirling North Core LDP Brownfield New build

Site Site Developer (s) X / Y Co- Latest Approval Expiry Date Area Density ordinates 3.24 23.15 Robertsons Homes 278790 / 18/00127/MSC 31/05/2023 Stirling Council 694372 Forth Housing Association

Programming

Total Capacity Total Remaining 5 Year Effective Remaining Effective Non-Effective (2019/20 – 2023/24) (2024/25 – 2026/27) (Post 2027) 75 35 35 0 0 Total Completions First Year in Currently In Established First Year in Effective Currently in Effective Established Supply Supply Since Supply Supply Since 0 2008 2008 2008 2013

2019/20 2020/21 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 Post 2027

Total 35 0 0 0 0 0 0 0 0 Affordable 35 0 0 0 0 0 0 0 0

Market 0 0 0 0 0 0 0 0 0

Completions

Pre 2010 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 Total 0 0 0 0 0 0 0 0 0 0 Af 0 0 0 0 0 0 0 0 0 0 Mkt 0 0 0 0 0 0 0 0 0 0

Tests of Effectiveness

Ownership Physical Contamination Deficit Funding Marketability Infrastructure Land Use Yes Yes Yes Yes Yes Yes Yes

74 Appendix A: Schedule of Sites

Area 9 Kildean, Stirling SC146 / H067 Actions Required to Deliver this site Start on site.

Site Details

Audit Status Planning Status Local Ward LDP Sub Monitoring Type Land and Area Development Type 5 year effective FUL 4 - Stirling North Core LDP Brownfield New build

Site Site Developer (s) X / Y Co- Latest Approval Expiry Date Area Density ordinates 0.80 20.00 Robertsons Homes 278670 / 18/00127/MSC 31/05/2023 Forth Housing Association 694924 -

Programming

Total Capacity Total Remaining 5 Year Effective Remaining Effective Non-Effective (2019/20 – 2023/24) (2024/25 – 2026/27) (Post 2027) 16 16 16 0 0 Total Completions First Year in Currently In Established First Year in Effective Currently in Effective Established Supply Supply Since Supply Supply Since 0 2008 2008 2008 2014

2019/20 2020/21 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 Post 2027

Total 0 16 0 0 0 0 0 0 0 Affordable 0 16 0 0 0 0 0 0 0

Market 0 0 0 0 0 0 0 0 0

Completions

Pre 2010 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 Total 0 0 0 0 0 0 0 0 0 0 Af 0 0 0 0 0 0 0 0 0 0 Mkt 0 0 0 0 0 0 0 0 0 0

Tests of Effectiveness

Ownership Physical Contamination Deficit Funding Marketability Infrastructure Land Use Yes Yes Yes Yes Yes Yes Yes

75 Appendix A: Schedule of Sites

Former Bolt Works Sunnyside, Stirling SC163 / H041 Actions Required to Deliver this site Site appears to have stalled. Site is non effective. Candidate for removal from next LDP.

Site Details

Audit Status Planning Status Local Ward LDP Sub Monitoring Type Land and Area Development Type Non effective Proposal 5 - Stirling West Core LDP Brownfield New build

Site Site Developer (s) X / Y Co- Latest Approval Expiry Date Area Density ordinates 0.05 80.00 Mr Brian Reid 279335 / 09/00266/FUL 11/06/2014 - 691716 -

Programming

Total Capacity Total Remaining 5 Year Effective Remaining Effective Non-Effective (2019/20 – 2023/24) (2024/25 – 2026/27) (Post 2027) 4 4 0 0 4 Total Completions First Year in Currently In Established First Year in Effective Currently in Effective Established Supply Supply Since Supply Supply Since 0 2009 2009 2009 0

2019/20 2020/21 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 Post 2027

Total 0 0 0 0 0 0 0 0 4 Affordable 0 0 0 0 0 0 0 0 0

Market 0 0 0 0 0 0 0 0 4

Completions

Pre 2010 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 Total 0 0 0 0 0 0 0 0 0 0 Af 0 0 0 0 0 0 0 0 0 0 Mkt 0 0 0 0 0 0 0 0 0 0

Tests of Effectiveness

Ownership Physical Contamination Deficit Funding Marketability Infrastructure Land Use No Yes Yes Yes Yes Yes Yes

76 Appendix A: Schedule of Sites

70-76 Murray Place, Stirling SC170 / - Actions Required to Deliver this site Start on site.

Site Details

Audit Status Planning Status Local Ward LDP Sub Monitoring Type Land and Area Development Type 5 year effective FUL 4 - Stirling North Core Windfall Brownfield Conversion

Site Site Developer (s) X / Y Co- Latest Approval Expiry Date Area Density ordinates 0.03 200.00 McEachern Architects 279669 / 18/00646/FUL 20/11/2021 Farcastle Ltd 693561 -

Programming

Total Capacity Total Remaining 5 Year Effective Remaining Effective Non-Effective (2019/20 – 2023/24) (2024/25 – 2026/27) (Post 2027) 6 6 6 0 0 Total Completions First Year in Currently In Established First Year in Effective Currently in Effective Established Supply Supply Since Supply Supply Since 0 2010 2019 2010 2019

2019/20 2020/21 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 Post 2027

Total 0 3 3 0 0 0 0 0 0 Affordable 0 0 0 0 0 0 0 0 0

Market 0 3 3 0 0 0 0 0 0

Completions

Pre 2010 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 Total 0 0 0 0 0 0 0 0 0 0 Af 0 0 0 0 0 0 0 0 0 0 Mkt 0 0 0 0 0 0 0 0 0 0

Tests of Effectiveness

Ownership Physical Contamination Deficit Funding Marketability Infrastructure Land Use Yes Yes Yes Yes Yes Yes Yes

77 Appendix A: Schedule of Sites

Ministry of Defence Site, Stirling SC198 / H049 Actions Required to Deliver this site Council to work with MOD to bring the site forward for development. Forthside Masterplan currently under

preperation.

Site Details

Audit Status Planning Status Local Ward LDP Sub Monitoring Type Land and Area Development Type Effective Proposal 6 - Stirling East Core LDP Brownfield New build

Site Site Developer (s) X / Y Co- Latest Approval Expiry Date Area Density ordinates 14.00 17.86 Ministry of Defence 280502 / - - - 693290 -

Programming

Total Capacity Total Remaining 5 Year Effective Remaining Effective Non-Effective (2019/20 – 2023/24) (2024/25 – 2026/27) (Post 2027) 250 250 0 150 100 Total Completions First Year in Currently In Established First Year in Effective Currently in Effective Established Supply Supply Since Supply Supply Since 0 2013 2013 2013 2013

2019/20 2020/21 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 Post 2027

Total 0 0 0 0 0 50 50 50 100 Affordable 0 0 0 0 0 10 10 10 32

Market 0 0 0 0 0 40 40 40 68

Completions

Pre 2010 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 Total 0 0 0 0 0 0 0 0 0 0 Af 0 0 0 0 0 0 0 0 0 0 Mkt 0 0 0 0 0 0 0 0 0 0

Tests of Effectiveness

Ownership Physical Contamination Deficit Funding Marketability Infrastructure Land Use Yes Yes No Yes Yes Yes Yes

78 Appendix A: Schedule of Sites

Viewforth, Stirling SC199 / H050 Actions Required to Deliver this site Council is working to bring forward the site for development and CDF proposals will free up part of

the existing site for redevelopment.

Site Details

Audit Status Planning Status Local Ward LDP Sub Monitoring Type Land and Area Development Type 5 year effective Proposal 5 - Stirling West Core LDP Brownfield New build

Site Site Developer (s) X / Y Co- Latest Approval Expiry Date Area Density ordinates 9.47 8.45 Stirling Council 279662 / - - - 692798 -

Programming

Total Capacity Total Remaining 5 Year Effective Remaining Effective Non-Effective (2019/20 – 2023/24) (2024/25 – 2026/27) (Post 2027) 80 80 61 19 0 Total Completions First Year in Currently In Established First Year in Effective Currently in Effective Established Supply Supply Since Supply Supply Since 0 2013 2013 2013 2014

2019/20 2020/21 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 Post 2027

Total 0 0 0 20 41 19 0 0 0 Affordable 0 0 0 20 22 0 0 0 0

Market 0 0 0 0 19 19 0 0 0

Completions

Pre 2010 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 Total 0 0 0 0 0 0 0 0 0 0 Af 0 0 0 0 0 0 0 0 0 0 Mkt 0 0 0 0 0 0 0 0 0 0

Tests of Effectiveness

Ownership Physical Contamination Deficit Funding Marketability Infrastructure Land Use Yes Yes Yes Yes Yes Yes Yes

79 Appendix A: Schedule of Sites

Former Stirling Royal Infirmary Site, Stirling SC201A / H052 Actions Required to Deliver this site Council to work with NHSFV to bring forward site for development.

Site Details

Audit Status Planning Status Local Ward LDP Sub Monitoring Type Land and Area Development Type 5 year effective Proposal 5 - Stirling West Core LDP Brownfield New build

Site Site Developer (s) X / Y Co- Latest Approval Expiry Date Area Density ordinates 1.60 25.63 NHSFV 279755 / 13/00505/PPP 26/06/2017 Stirling Council 692094 -

Programming

Total Capacity Total Remaining 5 Year Effective Remaining Effective Non-Effective (2019/20 – 2023/24) (2024/25 – 2026/27) (Post 2027) 41 41 41 0 0 Total Completions First Year in Currently In Established First Year in Effective Currently in Effective Established Supply Supply Since Supply Supply Since 0 2013 2013 2013 2013

2019/20 2020/21 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 Post 2027

Total 0 0 0 21 20 0 0 0 0 Affordable 0 0 0 10 0 0 0 0 0

Market 0 0 0 11 20 0 0 0 0

Completions

Pre 2010 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 Total 0 0 0 0 0 0 0 0 0 0 Af 0 0 0 0 0 0 0 0 0 0 Mkt 0 0 0 0 0 0 0 0 0 0

Tests of Effectiveness

Ownership Physical Contamination Deficit Funding Marketability Infrastructure Land Use Yes Yes Yes Yes Yes Yes Yes

80 Appendix A: Schedule of Sites

Area 23 Kildean Hospital, Stirling SC202 / H053 Actions Required to Deliver this site Site is non effective. Candidate for removal at next LDP.

Site Details

Audit Status Planning Status Local Ward LDP Sub Monitoring Type Land and Area Development Type Non effective Proposal 4 - Stirling North Core LDP Brownfield New build

Site Site Developer (s) X / Y Co- Latest Approval Expiry Date Area Density ordinates 1.52 19.74 Raploch URC 278582 / - - - 694925 -

Programming

Total Capacity Total Remaining 5 Year Effective Remaining Effective Non-Effective (2019/20 – 2023/24) (2024/25 – 2026/27) (Post 2027) 30 30 0 0 30 Total Completions First Year in Currently In Established First Year in Effective Currently in Effective Established Supply Supply Since Supply Supply Since 0 2012 2012 2012 0

2019/20 2020/21 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 Post 2027

Total 0 0 0 0 0 0 0 0 30 Affordable 0 0 0 0 0 0 0 0 0

Market 0 0 0 0 0 0 0 0 30

Completions

Pre 2010 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 Total 0 0 0 0 0 0 0 0 0 0 Af 0 0 0 0 0 0 0 0 0 0 Mkt 0 0 0 0 0 0 0 0 0 0

Tests of Effectiveness

Ownership Physical Contamination Deficit Funding Marketability Infrastructure Land Use No Yes Yes Yes Yes Yes No

81 Appendix A: Schedule of Sites

South Stirling Gateway, Stirling SC203 / H055 Actions Required to Deliver this site Decision to be made on applications and address wider site issues.

Site Details

Audit Status Planning Status Local Ward LDP Sub Monitoring Type Land and Area Development Type 5 year effective Proposal 6 - Stirling East Core LDP Greenfield New build

Site Site Developer (s) X / Y Co- Latest Approval Expiry Date Area Density ordinates 46.00 17.39 Tulloch Homes representing a variety of land owners 280895 / - - - 689456 -

Programming

Total Capacity Total Remaining 5 Year Effective Remaining Effective Non-Effective (2019/20 – 2023/24) (2024/25 – 2026/27) (Post 2027) 800 800 311 210 279 Total Completions First Year in Currently In Established First Year in Effective Currently in Effective Established Supply Supply Since Supply Supply Since 0 2013 2013 2013 2013

2019/20 2020/21 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 Post 2027

Total 0 48 96 97 70 70 70 70 279 Affordable 0 20 20 30 30 30 20 20 30

Market 0 28 76 67 40 40 50 50 249

Completions

Pre 2010 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 Total 0 0 0 0 0 0 0 0 0 0 Af 0 0 0 0 0 0 0 0 0 0 Mkt 0 0 0 0 0 0 0 0 0 0

Tests of Effectiveness

Ownership Physical Contamination Deficit Funding Marketability Infrastructure Land Use Yes Yes Yes Yes Yes Yes Yes

82 Appendix A: Schedule of Sites

Newpark Farm, Stirling SC205 / H058 Actions Required to Deliver this site Continue build out of site.

Site Details

Audit Status Planning Status Local Ward LDP Sub Monitoring Type Land and Area Development Type 5 year effective Under Construction 5 - Stirling West Core LDP Greenfield New build

Site Site Developer (s) X / Y Co- Latest Approval Expiry Date Area Density ordinates 8.60 21.51 Ogilvie Homes 278936 / 15/00669/FUL 23/07/2022 - 690931 -

Programming

Total Capacity Total Remaining 5 Year Effective Remaining Effective Non-Effective (2019/20 – 2023/24) (2024/25 – 2026/27) (Post 2027) 185 185 185 0 0 Total Completions First Year in Currently In Established First Year in Effective Currently in Effective Established Supply Supply Since Supply Supply Since 0 2013 2013 2013 2013

2019/20 2020/21 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 Post 2027

Total 35 52 52 46 0 0 0 0 0 Affordable 10 12 0 24 0 0 0 0 0

Market 25 40 52 22 0 0 0 0 0

Completions

Pre 2010 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 Total 0 0 0 0 0 0 0 0 0 0 Af 0 0 0 0 0 0 0 0 0 0 Mkt 0 0 0 0 0 0 0 0 0 0

Tests of Effectiveness

Ownership Physical Contamination Deficit Funding Marketability Infrastructure Land Use Yes Yes Yes Yes Yes Yes Yes

83 Appendix A: Schedule of Sites

Cultenhove Regeneration Areas, Stirling SC206 / H059 Actions Required to Deliver this site Continue build out of site.

Site Details

Audit Status Planning Status Local Ward LDP Sub Monitoring Type Land and Area Development Type 5 year effective Under Construction 5 - Stirling West Core LDP Brownfield New build

Site Site Developer (s) X / Y Co- Latest Approval Expiry Date Area Density ordinates 7.10 17.46 Stirling Council 279039 / 17/00542/FUL 14/12/2020 Forth Housing Association 691242 -

Programming

Total Capacity Total Remaining 5 Year Effective Remaining Effective Non-Effective (2019/20 – 2023/24) (2024/25 – 2026/27) (Post 2027) 124 80 80 0 0 Total Completions First Year in Currently In Established First Year in Effective Currently in Effective Established Supply Supply Since Supply Supply Since 44 2013 2013 2013 2013

2019/20 2020/21 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 Post 2027

Total 35 15 30 0 0 0 0 0 0 Affordable 35 0 0 0 0 0 0 0 0

Market 0 15 30 0 0 0 0 0 0

Completions

Pre 2010 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 Total 0 0 0 0 0 16 6 22 0 0 Af 0 0 0 0 0 16 6 22 0 0 Mkt 0 0 0 0 0 0 0 0 0 0

Tests of Effectiveness

Ownership Physical Contamination Deficit Funding Marketability Infrastructure Land Use Yes Yes Yes Yes Yes Yes Yes

84 Appendix A: Schedule of Sites

Cornton Regeneration Areas, Stirling SC207 / H060 Actions Required to Deliver this site Planning application to be submitted.

Site Details

Audit Status Planning Status Local Ward LDP Sub Monitoring Type Land and Area Development Type 5 year effective Proposal 4 - Stirling North Core LDP Brownfield New build

Site Site Developer (s) X / Y Co- Latest Approval Expiry Date Area Density ordinates 0.00 0.00 Stirling Council 279558 / 16/00296/FUL 11/08/2019 Forth Housing Association 695335 -

Programming

Total Capacity Total Remaining 5 Year Effective Remaining Effective Non-Effective (2019/20 – 2023/24) (2024/25 – 2026/27) (Post 2027) 100 52 24 0 28 Total Completions First Year in Currently In Established First Year in Effective Currently in Effective Established Supply Supply Since Supply Supply Since 48 2013 2013 2013 2013

2019/20 2020/21 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 Post 2027

Total 0 24 0 0 0 0 0 0 28 Affordable 0 24 0 0 0 0 0 0 28

Market 0 0 0 0 0 0 0 0 0

Completions

Pre 2010 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 Total 0 0 0 0 0 9 16 0 10 13 Af 0 0 0 0 0 9 16 0 10 13 Mkt 0 0 0 0 0 0 0 0 0 0

Tests of Effectiveness

Ownership Physical Contamination Deficit Funding Marketability Infrastructure Land Use Yes Yes Yes Yes Yes Yes Yes

85 Appendix A: Schedule of Sites

Stirling Ice Rink, Stirling SC227 / H128 Actions Required to Deliver this site Submission of a planning application.

Site Details

Audit Status Planning Status Local Ward LDP Sub Monitoring Type Land and Area Development Type 5 year effective Proposal 5 - Stirling West Core LDP Brownfield New build

Site Site Developer (s) X / Y Co- Latest Approval Expiry Date Area Density ordinates 0.60 33.33 Stirling Council 279158 / - - - 692049 -

Programming

Total Capacity Total Remaining 5 Year Effective Remaining Effective Non-Effective (2019/20 – 2023/24) (2024/25 – 2026/27) (Post 2027) 20 20 20 0 0 Total Completions First Year in Currently In Established First Year in Effective Currently in Effective Established Supply Supply Since Supply Supply Since 0 2012 2012 2012 2016

2019/20 2020/21 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 Post 2027

Total 0 0 20 0 0 0 0 0 0 Affordable 0 0 0 0 0 0 0 0 0

Market 0 0 20 0 0 0 0 0 0

Completions

Pre 2010 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 Total 0 0 0 0 0 0 0 0 0 0 Af 0 0 0 0 0 0 0 0 0 0 Mkt 0 0 0 0 0 0 0 0 0 0

Tests of Effectiveness

Ownership Physical Contamination Deficit Funding Marketability Infrastructure Land Use Yes Yes Yes Yes Yes Yes Yes

86 Appendix A: Schedule of Sites

Milne Park Road, Stirling SC229 / H130 Actions Required to Deliver this site Submission of a planning application.

Site Details

Audit Status Planning Status Local Ward LDP Sub Monitoring Type Land and Area Development Type 5 year effective Proposal 7 - Bannockburn Core LDP Brownfield New build

Site Site Developer (s) X / Y Co- Latest Approval Expiry Date Area Density ordinates 0.66 60.61 D. Roy Civil Engineering Limited 281114 / - - - 689900 -

Programming

Total Capacity Total Remaining 5 Year Effective Remaining Effective Non-Effective (2019/20 – 2023/24) (2024/25 – 2026/27) (Post 2027) 40 40 30 10 0 Total Completions First Year in Currently In Established First Year in Effective Currently in Effective Established Supply Supply Since Supply Supply Since 0 2013 2013 2013 2014

2019/20 2020/21 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 Post 2027

Total 0 0 0 10 20 10 0 0 0 Affordable 0 0 0 0 10 0 0 0 0

Market 0 0 0 10 10 10 0 0 0

Completions

Pre 2010 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 Total 0 0 0 0 0 0 0 0 0 0 Af 0 0 0 0 0 0 0 0 0 0 Mkt 0 0 0 0 0 0 0 0 0 0

Tests of Effectiveness

Ownership Physical Contamination Deficit Funding Marketability Infrastructure Land Use Yes Yes Yes Yes Yes Yes Yes

87 Appendix A: Schedule of Sites

Area 22 Drip Road Frontage, Stirling SC239 / H131 Actions Required to Deliver this site Start on site.

Site Details

Audit Status Planning Status Local Ward LDP Sub Monitoring Type Land and Area Development Type 5 year effective FUL 4 - Stirling North Core LDP Brownfield New build

Site Site Developer (s) X / Y Co- Latest Approval Expiry Date Area Density ordinates 0.30 56.67 Robertsons Homes 279139 / 18/00127/MSC 31/05/2023 Stirling Council 694650 -

Programming

Total Capacity Total Remaining 5 Year Effective Remaining Effective Non-Effective (2019/20 – 2023/24) (2024/25 – 2026/27) (Post 2027) 17 17 17 0 0 Total Completions First Year in Currently In Established First Year in Effective Currently in Effective Established Supply Supply Since Supply Supply Since 0 2013 2013 2014 2014

2019/20 2020/21 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 Post 2027

Total 0 17 0 0 0 0 0 0 0 Affordable 0 17 0 0 0 0 0 0 0

Market 0 0 0 0 0 0 0 0 0

Completions

Pre 2010 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 Total 0 0 0 0 0 0 0 0 0 0 Af 0 0 0 0 0 0 0 0 0 0 Mkt 0 0 0 0 0 0 0 0 0 0

Tests of Effectiveness

Ownership Physical Contamination Deficit Funding Marketability Infrastructure Land Use Yes Yes Yes Yes Yes Yes Yes

88 Appendix A: Schedule of Sites

Catherine Street, Stirling SC258 / H134 Actions Required to Deliver this site Continue build out of site.

Site Details

Audit Status Planning Status Local Ward LDP Sub Monitoring Type Land and Area Development Type 5 year effective Under Construction 6 - Stirling East Core LDP Brownfield New build

Site Site Developer (s) X / Y Co- Latest Approval Expiry Date Area Density ordinates 0.38 28.95 Stirling Council 280427 / 17/00920/FUL 15/02/2021 - 690460 -

Programming

Total Capacity Total Remaining 5 Year Effective Remaining Effective Non-Effective (2019/20 – 2023/24) (2024/25 – 2026/27) (Post 2027) 11 11 11 0 0 Total Completions First Year in Currently In Established First Year in Effective Currently in Effective Established Supply Supply Since Supply Supply Since 0 2017 2017 2017 2017

2019/20 2020/21 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 Post 2027

Total 4 7 0 0 0 0 0 0 0 Affordable 4 7 0 0 0 0 0 0 0

Market 0 0 0 0 0 0 0 0 0

Completions

Pre 2010 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 Total 0 0 0 0 0 0 0 0 0 0 Af 0 0 0 0 0 0 0 0 0 0 Mkt 0 0 0 0 0 0 0 0 0 0

Tests of Effectiveness

Ownership Physical Contamination Deficit Funding Marketability Infrastructure Land Use Yes Yes Yes Yes Yes Yes Yes

89 Appendix A: Schedule of Sites

South of A81, Strathblane and SC268 / H153 Actions Required to Deliver this site Council to work with landowner to bring forward the site for development.

Site Details

Audit Status Planning Status Local Ward LDP Sub Monitoring Type Land and Area Development Type 5 year effective Proposal 2 - Forth and Rural LDP Greenfield New build Endrick Site Site Developer (s) X / Y Co- Latest Approval Expiry Date Area Density ordinates 1.16 17.24 - 256314 / - - - 679002 -

Programming

Total Capacity Total Remaining 5 Year Effective Remaining Effective Non-Effective (2019/20 – 2023/24) (2024/25 – 2026/27) (Post 2027) 20 20 20 0 0 Total Completions First Year in Currently In Established First Year in Effective Currently in Effective Established Supply Supply Since Supply Supply Since 0 2017 2017 2017 2017

2019/20 2020/21 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 Post 2027

Total 0 0 0 20 0 0 0 0 0 Affordable 0 0 0 6 0 0 0 0 0

Market 0 0 0 14 0 0 0 0 0

Completions

Pre 2010 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 Total 0 0 0 0 0 0 0 0 0 0 Af 0 0 0 0 0 0 0 0 0 0 Mkt 0 0 0 0 0 0 0 0 0 0

Tests of Effectiveness

Ownership Physical Contamination Deficit Funding Marketability Infrastructure Land Use Yes Yes Yes Yes Yes Yes Yes

90 Appendix A: Schedule of Sites

Norrieston Glebe, Thornhill SC064 / H111 Actions Required to Deliver this site Council to explore how development can be brought forward on the remainder of this site.

Site Details

Audit Status Planning Status Local Ward LDP Sub Monitoring Type Land and Area Development Type Non effective Proposal 1 - Trossachs Rural LDP Greenfield New build and Teith Site Site Developer (s) X / Y Co- Latest Approval Expiry Date Area Density ordinates 0.57 24.56 Stirling Council 266915 / 14/00364/FUL 14/08/2017 - 699933 -

Programming

Total Capacity Total Remaining 5 Year Effective Remaining Effective Non-Effective (2019/20 – 2023/24) (2024/25 – 2026/27) (Post 2027) 14 6 0 0 6 Total Completions First Year in Currently In Established First Year in Effective Currently in Effective Established Supply Supply Since Supply Supply Since 8 2000 2000 2008 0

2019/20 2020/21 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 Post 2027

Total 0 0 0 0 0 0 0 0 6 Affordable 0 0 0 0 0 0 0 0 0

Market 0 0 0 0 0 0 0 0 6

Completions

Pre 2010 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 Total 0 0 0 0 0 0 0 8 0 0 Af 0 0 0 0 0 0 0 8 0 0 Mkt 0 0 0 0 0 0 0 0 0 0

Tests of Effectiveness

Ownership Physical Contamination Deficit Funding Marketability Infrastructure Land Use No Yes Yes Yes Yes Yes Yes

91 Appendix A: Schedule of Sites

Burnside Works, Thornhill SC225 / H109 Actions Required to Deliver this site Future development unclear. Candidate for removal at next LDP.

Site Details

Audit Status Planning Status Local Ward LDP Sub Monitoring Type Land and Area Development Type Non effective Proposal 1 - Trossachs Rural LDP Brownfield New build and Teith Site Site Developer (s) X / Y Co- Latest Approval Expiry Date Area Density ordinates 0.60 8.33 Robert Dykes and Son 266308 / - - - 700057 -

Programming

Total Capacity Total Remaining 5 Year Effective Remaining Effective Non-Effective (2019/20 – 2023/24) (2024/25 – 2026/27) (Post 2027) 5 5 0 0 5 Total Completions First Year in Currently In Established First Year in Effective Currently in Effective Established Supply Supply Since Supply Supply Since 0 2013 2013 2013 0

2019/20 2020/21 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 Post 2027

Total 0 0 0 0 0 0 0 0 5 Affordable 0 0 0 0 0 0 0 0 0

Market 0 0 0 0 0 0 0 0 5

Completions

Pre 2010 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 Total 0 0 0 0 0 0 0 0 0 0 Af 0 0 0 0 0 0 0 0 0 0 Mkt 0 0 0 0 0 0 0 0 0 0

Tests of Effectiveness

Ownership Physical Contamination Deficit Funding Marketability Infrastructure Land Use No Yes Yes Yes Yes Yes Yes

92 Appendix A: Schedule of Sites

East of 39 Kersie Road, SC109 / H081 Actions Required to Deliver this site Planning application to be submitted.

Site Details

Audit Status Planning Status Local Ward LDP Sub Monitoring Type Land and Area Development Type 5 year effective Proposal 7 - Bannockburn Core LDP Greenfield New build

Site Site Developer (s) X / Y Co- Latest Approval Expiry Date Area Density ordinates 0.66 7.58 Donnie Allan 285294 / 06/00624/OUT 05/04/2010 - 691132 -

Programming

Total Capacity Total Remaining 5 Year Effective Remaining Effective Non-Effective (2019/20 – 2023/24) (2024/25 – 2026/27) (Post 2027) 5 5 5 0 0 Total Completions First Year in Currently In Established First Year in Effective Currently in Effective Established Supply Supply Since Supply Supply Since 0 2007 2007 2007 2013

2019/20 2020/21 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 Post 2027

Total 0 0 0 0 5 0 0 0 0 Affordable 0 0 0 0 0 0 0 0 0

Market 0 0 0 0 5 0 0 0 0

Completions

Pre 2010 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 Total 0 0 0 0 0 0 0 0 0 0 Af 0 0 0 0 0 0 0 0 0 0 Mkt 0 0 0 0 0 0 0 0 0 0

Tests of Effectiveness

Ownership Physical Contamination Deficit Funding Marketability Infrastructure Land Use Yes Yes Yes Yes Yes Yes Yes

93 Appendix A: Schedule of Sites

Throsk, Throsk SC213 / H080 Actions Required to Deliver this site Planning application to be submitted.

Site Details

Audit Status Planning Status Local Ward LDP Sub Monitoring Type Land and Area Development Type 5 year effective Proposal 7 - Bannockburn Core LDP Greenfield New build

Site Site Developer (s) X / Y Co- Latest Approval Expiry Date Area Density ordinates 5.70 13.16 Donnie Allan 285122 / - - - 691256 -

Programming

Total Capacity Total Remaining 5 Year Effective Remaining Effective Non-Effective (2019/20 – 2023/24) (2024/25 – 2026/27) (Post 2027) 75 75 75 0 0 Total Completions First Year in Currently In Established First Year in Effective Currently in Effective Established Supply Supply Since Supply Supply Since 0 2013 2013 2013 2013

2019/20 2020/21 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 Post 2027

Total 0 0 20 49 6 0 0 0 0 Affordable 0 0 0 19 0 0 0 0 0

Market 0 0 20 30 6 0 0 0 0

Completions

Pre 2010 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 Total 0 0 0 0 0 0 0 0 0 0 Af 0 0 0 0 0 0 0 0 0 0 Mkt 0 0 0 0 0 0 0 0 0 0

Tests of Effectiveness

Ownership Physical Contamination Deficit Funding Marketability Infrastructure Land Use Yes Yes Yes Yes Yes Yes Yes

94

Appendix B: Sites Completed 1st July 2018 – 30th June 2019

95 Appendix B: Sites Completed 1st July 2018 – 30th June 2019

Site Name Settlement HLA Ref / Total Completions Developer(s) LDP Ref Area 4B Stirling SC144B / 94 Cruden Homes Glendevon H147 Stirling Council Forth Housing Association South of North Rural SC242 / 5 Mr David Doll H150 McKeown Farmhouse - - 17 Gladstone Stirling SC271 / - 4 The Place Leadership Factory - - Wellington Stirling SC275 / - 4 Campbell House Properties - - / / / / / / / / / / / /

96