<<

Inuvik to Highway: Monitoring Plan

January 2014

Prepared by: Government of the Department of Transportation , NT

Inuvik to Tuktoyaktuk Highway: Permafrost Monitoring Plan Executive Summary January 2014

Executive Summary

The Inuvik to Tuktoyaktuk Highway (ITH) is a Government of the Northwest Territories (GNWT) 138 kilometre all-season highway project which has been planned, designed and will be constructed and operated to minimize disturbance to the active layer, underlying permafrost and ground ice features in the project area. The GNWT has significant experience constructing, maintaining, operating and monitoring highways built on terrain underlain by ice rich permafrost.

The ITH Permafrost Monitoring Plan (PEMP) was developed to guide monitoring efforts aimed at ensuring protection of active layer and permafrost conditions along the highway embankment, at watercourse crossing structures, in the exploited burrow sources and along temporary winter access roads. The PEMP also describes approaches that will be taken to effectively monitor the areas impacted by the ITH project.

The PEMP describes visual and ground temperature monitoring activities that will be conducted regularly throughout the summer and fall seasons and during operations. These monitoring activities will assist in adaptively managing the design and construction elements aimed at protecting ground thermal conditions. The monitoring efforts will also assist in identifying specific areas where mitigative or restorative efforts will be required. This plan contributes to the adaptive management approach for the project committed to by the GNWT in the regulatory framework.

Innovative remote and ground sensing techniques will be tested for broader application along the ITH and to other northern transportation infrastructure projects. Information and data collected under the PEMP will add value to broad regional permafrost-related studies in progress by the climate science, geoscience and transportation infrastructure research community.

i

Inuvik to Tuktoyaktuk Highway: Permafrost Monitoring Plan Executive Summary January 2014

ii

Inuvik to Tuktoyaktuk Highway: Permafrost Monitoring Plan Table of Contents January 2014

Table of Contents

1 INTRODUCTION ...... 1-1 1.1 PURPOSE ...... 1-1 1.2 TIMING OF CONSTRUCTION ...... 1-2 1.3 DOT STAFF AND CONTRACTOR TRAINING ...... 1-2 1.4 LESSONS LEARNED FROM TUKTOYAKTUK TO SOURCE 177 ACCESS ROAD DESIGN AND CONSTRUCTION ...... 1-2

2 MONITORING ...... 2-1 2.1 BORROW SOURCES ...... 2-1 2.2 WINTER ACCESS ROADS ...... 2-1 2.3 HIGHWAY EMBANKMENT...... 2-1 2.4 WATERCOURSE CROSSING STRUCTURES ...... 2-2 2.5 ANALYSIS ...... 2-2 2.6 REPORTING ...... 2-2

Appendices

APPENDIX A ITH Construction Atlas

iii

Inuvik to Tuktoyaktuk Highway: Permafrost Monitoring Plan Table of Contents January 2014

iv

Inuvik to Tuktoyaktuk Highway: Permafrost Monitoring Plan Abbreviations January 2014

Abbreviations

AANDC ...... Aboriginal Affairs and Northern Development DOT ...... Department of Transportation GNWT ...... Government of the Northwest Territories ILA ...... Land Administration ITH ...... Inuvik to Tuktoyaktuk Highway NWTWB ...... Northwest Territories Water Board NWT ...... Northwest Territories PEMP ...... Permafrost Management Plan PMP ...... Pit Management Plans QA/QC ...... Quality Assurance/Quality Control

v

Inuvik to Tuktoyaktuk Highway: Permafrost Monitoring Plan Abbreviations January 2014

vi

Inuvik to Tuktoyaktuk Highway: Permafrost Monitoring Plan Section 1: Introduction January 2014

1 INTRODUCTION

1.1 Purpose

In January 2014 the Government of the Northwest Territories (GNWT) Department of Transportation (DOT) will begin construction of a 138 kilometre all-season highway from Inuvik to Tuktoyaktuk in the Inuvialuit Settlement Region of the Northwest Territories (NWT). The GNWT has significant experience constructing, maintaining, operating and monitoring highways built on terrain underlain by ice rich permafrost.

The Inuvik to Tuktoyaktuk Highway (ITH) is being constructed through terrain underlain with continuous ice rich permafrost. The ITH design and construction plan is based on keeping the permafrost in a stable, frozen state. The ITH project comprises: construction of the highway embankment; construction of 68 watercourse crossing structures; development of the borrow sources; and construction of temporary winter access roads. The ITH Construction Atlas is provided in Appendix A.

The development of a Permafrost Monitoring Plan (PEMP) was a condition of Water License N7L1-1835 issued for the Inuvik to Tuktoyaktuk Highway (ITH) project by the Northwest Territories Water Board (NWTWB) on December 12, 2013.

Condition Part C # 7 of NWTWB Licence N7L1-1835 states:

“The Licensee shall within thirty (30) days of License issuance submit to the Board for approval a Permafrost Monitoring Plan. The plan shall address monitoring of active layer and near-surface permafrost impacts from the winter road construction to aggregate sources, as well as, the all-weather highway and watercourse crossings. The implementation of this plan shall inform the overall Adaptive management program of the project”.

The ITH PEMP was developed to guide monitoring efforts aimed at ensuring protection of active layer and permafrost conditions in the project area and along the highway embankment, at watercourse crossing structures, in the exploited borrow sources and along temporary winter access roads. The PEMP describes the approaches that will be taken to effectively monitor the areas impacted by the ITH project.

The PEMP will assist in adaptively managing the design and construction elements directed specifically at protecting ground thermal conditions in the project area and identifying specific sites where mitigative or restorative efforts may be required. Information and data collected under the PEMP will also add value to broader regional permafrost-related studies in progress by the climate science, geoscience and transportation infrastructure research community.

1-1

Inuvik to Tuktoyaktuk Highway: Permafrost Monitoring Plan Section 1: Introduction January 2014

1.2 Timing of Construction

The majority of new construction activities will be conducted during late fall and winter when the active layer is frozen. Winter construction avoids damaging the natural ground surface and erosion of permafrost terrain. Overland travel is not permitted during summer months, with the exception of on previously constructed embankment and within the approved granular sources.

1.3 DOT Staff and Contractor Training

The PEMP will be reviewed with DOT Staff and the Contractor that will undertake the construction of the ITH. The purpose of this review is to ensure DOT Staff and the Contractor understand the intent of the PEMP and how to implement it, and to obtain feedback on possible improvements. In turn the contractor will be responsible for educating highway construction crews on the content of the plan and the importance of correct implementation .

1.4 Lessons Learned from Tuktoyaktuk to Source 177 Access Road Design and Construction

Valuable lessons have been learned from previously constructed roads in similar locations and conditions, particularly the . The construction of the access road from Tuktoyaktuk to Borrow Source 177 provided valuable lessons that were incorporated into the design and will be used in the construction of the ITH. Lessons learned related to active layer and permafrost protection, are provided below:

• the nature of the ice-rich terrain is such that all initial embankment construction must be carried out in the winter when the active layer is fully frozen; • the borrow sources will be mainly developed during the winter and overburden cover restored after extraction to minimize impacts to the ground thermal regimes in the borrow sources; • geotextile placed on the original ground increases roadbed stability and improves embankment integrity; • thermal modelling is an effective tool to ensure that embankment heights and profiles have been designed to insulate the ground from thaw penetration and to promote the agradation of permafrost into the embankment; • effective maintenance of the highway embankment during and post construction will assist in the preserving permafrost conditions along the right of way; and • the use of a ‘fill only’ design section with no cuts to the natural ground or stripping maintains the insulation value of the vegetative mat and organic soil to preserve the underlying permafrost. This intact vegetation cover provides excellent active layer and permafrost protection.

1-2

Inuvik to Tuktoyaktuk Highway: Permafrost Monitoring Plan Section 2: Monitoring January 2014

2 MONITORING

2.1 Borrow Sources

ITH embankment construction will require materials extracted from borrow sources located in proximity to the right of way. The Pit Development Plans approved by the Inuvialuit Land Administration (ILA) for work in ILA borrow sources, and by Aboriginal Affairs and Northern Development Canada (AANDC) for Crown granular sources clearly define the measures to be taken to protect permafrost and ground ice encountered during material extraction activities. These measures include covering any ice-rich material so that there is no unintended thaw flows and erosion as a result of permafrost degradation.

For the term of the land use permits the developed borrow sources will be visually monitored throughout the summer and fall seasons to ensure that there is no erosion resulting from degradation of permafrost.

2.2 Winter Access Roads

Water will be extracted from authorized lakes proximal to the borrow sources and right of way to assist in the construction and thickening of winter access roads. The land use permits issued for winter access road construction and operation by ILA and AANDC clearly define the conditions and specific measures to be taken to protect surface vegetation, surface soils and permafrost during winter construction activities.

For the term of the land use permits all of the winter access road alignments will be visually monitored throughout the summer and fall seasons , to ensure that there is no significant scarring of the surface that could lead to erosion of the active layer, which could in turn result in degradation of the underlying permafrost.

2.3 Highway Embankment

The highway embankment will be constructed during the winter when the active layer is frozen as directed in the land use permits issued by the ILA and AANDC. The embankment is being constructed with a volume of material and resulting embankment height and slope that is designed to protect the integrity of the underlying permafrost.

The embankment will be visually monitored throughout the summer and fall seasons during construction and during highway operations, to ensure that there is no significant erosion resulting from degradation of permafrost. In addition ground temperature sensors will be installed at strategic locations along and adjacent to the right of way. These sensors will record ground temperatures at various depths to confirm overall ground temperature regimes, depth of the active layer and temperature of the permafrost. These temperature readings will occur during construction and into the operational phase of the highway. This quantitative temperature data will be shared with scientists and permafrost engineers who are

2-1

Inuvik to Tuktoyaktuk Highway: Permafrost Monitoring Plan Section 2: Monitoring January 2014

undertaking ongoing regional assessments of permafrost, geomorphic, hydrologic and related climate conditions in the NWT and .

2.4 Watercourse Crossing Structures

Water course crossing structures along the ITH right of way will consist of single span bridges or culverts. All watercourse crossings will be constructed in the winter unless open water is encountered, in which case watercourse crossings will be constructed in accordance with the summer watercourse crossing methods identified in the Sediment and Erosions Control Plan. To ensure that the drainage system is functioning as designed and to ensure that there is no significant degradation of the underlying permafrost crossing structures and bridge abutments will be subject to ongoing visual inspections. In addition instrumentation will be installed at bridge abutments to record ground temperatures at various depths to confirm ground temperature regimes depth of the active layer and temperature of the permafrost. These temperature readings will be taken during construction and into the operational phase of the highway.

2.5 Analysis

Quality assurance and quality control (QA/QC) of visual and quantitative monitoring results will be maintained through appropriate training of DOT staff and contractor staff, periodic verification of field observations and monthly review of monitoring results. Metadata and reporting standards will be established so the data can be integrated with existing permafrost data from the region. The ITH project team will continue to work closely with the geoscience and engineering community to investigate and test innovative means of monitoring permafrost and ground thermal conditions throughout the project area. These may include remote sensing geophysical survey techniques to track ground subsidence and any changes in the depth of the active layer. There is broad interest in the research community to evaluate the performance and effects of the ITH, and of natural processes and changing climatic conditions, on regional thermal regimes, hydrology and geomorphic events in the project area.

The ITH represents a strategic platform to support research initiatives which in cooperation will improve ITH permafrost monitoring efforts. Analysis may include integration of ITH PEMP ground temperature data and field observations into existing Geographic Information System (GIS) – based studies.

2.6 Reporting

An annual report of all permafrost monitoring activities will be prepared for the period of construction.. Reports will provide results of permafrost monitoring activities, indicate if any issues were identified, and describe corrective actions to address these issues. The reports will also provide updates on relevant permafrost monitoring work being carried out in the project area by other parties.

Data will be provided to the NWTWB in tabular format and copies of reports prepared in hard copy and electronic format (PDF).

2-2

Inuvik to Tuktoyaktuk Highway: Permafrost Monitoring Plan Appendix A: ITH Construction Atlas January 2014

APPENDIX A ITH Construction Atlas

Inuvik to Tuktoyaktuk Highway: Permafrost Monitoring Plan Appendix A: ITH Construction Atlas January 2014

±

! Tuktoyaktuk

KM 134.2 (!

177

KM 112.1 (! r e v 1 i R

e i (! z KM 105.6 n e k 170 c a Husky M Lakes

173/305 174

H o l 3 m e s

C r e e k

309 Old Man Parsons (! Lake Lake KM 70.7

Husky Lakes (! 5 KM 61.7

312 West

PW19A

PW18 314/325

M i d d le C h a n n e l KM 30.9 (! KM 30.2 (! GSC4

E GSC3 a s t C h a n n 4 e l

PW11 Noel Sitidgi PW10 Lake Lake

(! Proposed Pullout Location

Highway Alignment I401A

Map Frame Proposed Borrow Source 2 Canadian Landmark

0 5 10 15 Inuvik ! Kilometres Metres - 1:375,000

123510689-145

o h

PREPARED BY t

e

p

j

INUVIK - TUKTOYAKTUK GEOTECHNIOCAL INVESTIGATIONS PROGRAM :

y

B

3

1

0 2

Project

, 3

Location 1

PREPARED FOR r e

NU b m

Construction Plan Overview Atlas e t

YT p

e

S

NWT : d

Index e

i f

! FIGURE NO. i

d

o

M

t

Acknowledgements: Original Drawing by Jacques Whitford - AXYS Ltd. s

INDEX a L 566000 568000 570000 572000 574000 576000 578000 580000 582000 584000 586000 588000

Kilometre Post

Proposed Pullout Location 7690000 7690000

Summer Camp

Winter Camp

Winter Camp/Summer Storage 7688000 7688000 Bridge Crossing 120

Bridge Size Culvert Crossing

Culvert Crossing KP 119

7686000 Constructed Alignment 7686000 KP 118 39d Year One Winter Road Winter Camp 1 119 (Operation) Year One Contigency (Winter) KP 117

Year One Winter Access Trail 39c 7684000 7684000 KP 116 Year One Water Access (Winter) 177 39b

Tuktoyaktuk to Source 177 Road KP 115 Tuk 1 Year 1 Water Withdrawal Lake KP 114 7682000 Inuvik, 7(1)a Private Lands 7682000

Inuvik, 7(1)b Private Lands KP 113

Tuktoyaktuk, 7(1)a Private Lands 39a KM 112.1 Tuktoyaktuk, 7(1)b Private Lands 7680000 7680000 KP 112 0 1,000 2,000 3,000 4,000

KP 111 Metres - 1:100,000 KP 110 123510689-149 KP 108 KP 107 KP 110

7678000 A2a 7678000 KP 109 KM 105.6

KP 105 A2 7676000 7676000 KP 104

KP 103 A3 Tuk 3 (105)

7674000 Winter Camp 2 KP 102 7674000 (Year 1 and Year 2 Tuk 4 Operation) KP 101 170

KP 100 7672000 7672000 A8

End of Construction Year One 7670000 7670000 7668000 7668000 7666000 7666000 7664000 7664000

Year 2 174 7662000 7662000 173/305 Winter Camp 1 (Year 1 Move and Year 2 & 3 Operational) 7660000 7660000 7658000 7658000 7656000 7656000

566000 568000 570000 572000 574000 576000 578000 580000 582000 584000 586000 588000

PREPARED BY INUVIK - TUKTOYAKTUK HIGHWAY CONSTRUCTION PLAN

NU PREPARED FOR Project Location Year One (North) NWT FIGURE NO. YT Acknowledgements: Original Drawing by KAVIK-STANTEC LTD: Base Data: Government of Canada DISCLAIMER: All locations are approximate, please refer to the Highway Final Design for specific locations. of 05

01 Last Modified:September 13,2013 By: jpetho 542000 544000 546000 548000 550000 552000 554000 556000 558000 560000 562000 564000

> Kilometre Post 7618000 7618000 Q Summer Camp Q Winter Camp ± R Winter Camp/Summer Storage GSC4

7616000 !( Proposed Pullout Location 7616000

!C Bridge Crossing Winter Camp 1 (Alternate) QR (Year 1 Move and Year 2 Operational) !(GF Bridge Size Culvert Crossing

!( Culvert Crossing 38 (Jimmy Lake) 7614000 QR 7614000 Constructed Alignment Winter Camp 1 GSC3 Year One Winter Access Trail (Year 1 Move and Year 2 Operational) Year One Contigency 7612000 7612000 Year One Winter Road

Year One Water Access (Winter)

Year 1 Water Withdrawal Lake

7610000 Administration Boundary 7610000 End of Construction Inuvik, 7(1)a Private Lands KP 20 Year One > Inuvik, 7(1)b Private Lands

KP 19 !( 14 Tuktoyaktuk, 7(1)a Private Lands > 7608000 7608000

Tuktoyaktuk, 7(1)b Private Lands KP 18 > 0 1,000 2,000 3,000 4,000 13a Inuvik 6 !(GF Metres - 1:100,000 >KP 17 123510689-150 7606000 7606000 KP 16 > Inuvik 5 PW11 KP 15 Inuvik 4 > Winter Camp 2 QR 7604000 (Alternate) 7604000 KP 14 > !( 13 !( QR Winter Camp 2 12bKP 13 Inuvialuit Settlement Region > (Year 1 & 2 Operation) 12a PW10 !( 7602000 7602000 KP 12 > 12 !(GF KP 11 > KP 11

7600000 KP 10 7600000 > !(GF11 !( 10 KP 9 > 9 !(GF 8 ! 7598000 C 7598000 >KP 8 Summer Camp Q!( KP 7 7 > 6 !( KP 6 7596000 > 7596000 KP 5 KP 5 > 5a !( 5 !(GF

7594000 >KP 4 7594000 4 !( GF Winter Camp 1 KP 3 (Year 1 & 2 Operation) > 3 Q !C I401A KP 2 2 !( 7592000 > 7592000 !(GF1 KP 1 KP 1 >

!( 0 >KP 0 7590000 7590000 7588000 7588000

7586000 Gwich'in Settlement Area 7586000 7584000 7584000 Inuvik

7582000 542000 544000 546000 548000 550000 552000 554000 556000 558000 560000 562000 564000 7582000

PREPARED BY INUVIK - TUKTOYAKTUK HIGHWAY CONSTRUCTION PLAN

NU PREPARED FOR Project Location Year One (South) NWT FIGURE NO. YT Acknowledgements: Original Drawing by KAVIK-STANTEC LTD: Base Data: Government of Canada DISCLAIMER: All locations are approximate, please refer to the Highway Final Design for specific locations. of 05

02 Last Modified: September20, 2013 By: cthibodeau >

> 556000 558000 560000 562000 564000 566000 568000 570000 572000 574000 576000 578000 KP 103 > 0 0

0 > Kilometre Post 0 0 0 4 4

7 KP 102 7 6 6 7 Winter Camp 2 > 7 ! Bridge Crossing R" C (Year 1 and Year 2 ± Operation) !( Bridge Size Culvert Crossing KP 101 GF > KP 101 !( Culvert Crossing 170 0 0 0 0

0 KP 100 KP 100 0 2 2 7 7

6 > 6 7 Q Summer Camp 7 Summer Q Camp R Winter Camp/Summer Storage KP 99 " > (! Proposed Pullout Location KP 98 0 0 0 0

0 > 0 0 0

7 Constructed Alignment 7 6 6 7 !( 7 A9 Year Two Winter Road >KP 97

Year Two Winter Access Trail KP 96 A10 !( > 0 0

0 Year Two Water Access (Winter) 0 0 0

8 A11 8

6 !(KP 95 6 6 6 7 > 7 Year 2 Water Withdrawal Lake A12 !(GF

Inuvik, 7(1)a Private Lands KP 94 > Inuvik, 7(1)b Private Lands 0 0 0 0 0 KP 86 0 6 KP 93 6 6 6 6 6

7 Tuktoyaktuk, 7(1)a Private Lands > 7

Tuktoyaktuk, 7(1)b Private Lands KP 91 KP 92 > 0 1,000 2,000 3,000 4,000 !( 35a A13

0 ! 0 0 C 0 0 > 0 4 Metres - 1:100,000 KP 91 4 6 6 6 6

7 123510689-151 7

>KP 90 KP 89 34e > KP 85 !( Year 2 KP 88 0 0 0 0

0 > 0

2 174 173/305 2 6 6

6 !( 6 7 7 KP 87 34c Winter Camp 1 R > (Year 1 Move and " Year 2 & 3 Operational) KP 86 KP 82A !(>

0 KP 85 34b 0 0 0

0 >!( 0 0 0 6 6 6 6

7 KP 82B 34a2 7 >KP 84

>KP 83 0 0 0 0 0 > 0 8 KP 82 8 5 5

6 !( 6 7 Q 34a 7 KP 81 Summer Camp > E nd KP 80 o > f C

0 Y o 0 0 n 0 0 e s 0 6 a 6 5 r tr 5 6 u 6 7 Tw c 7 o ti on 0 0 0 0 0 0 4 4 5 5 6 6 7 7

309 0 0 0 0 0 0 2 2 5 5 6 6 7 R" 7 Winter Camp 2 (Year 2 Move and Year 3 Operation) 0 0 0 0 0 0 0 0 5 5 6 6 7 7 0 0 0 0 0 0 8 8 4 4 6 6 7 7 0 0 0 0 0 0 6 6 4 4 6 6 7 7 0 0 0 0 0 0 4 4 4 4 6 6 7 7 0 0 0 0 0 0 2 2 4 4 6 6 7 7 312 West R" Winter Camp 1 0 0 0 0 0 0

0 (Year 2 Move and 0 4 4 6 6

7 Year 3 & 4 Operation) 7

556000 558000 560000 562000 564000 566000 568000 570000 572000 574000 576000 578000

o h

PREPARED BY t

e

p

j

INUVIK - TUKTOYAKTUK HIGHWAY CONSTRUCTION PLAN :

y

B

3

1

0

2

,

9

1

PREPARED FOR r e

PNWU 19A b

Project m

e t

Location p

e

S

: d

Year Two (North) e

i f

FIGURE NO. i d

NWT o

M

YT t

Acknowledgements: Original Drawing by KAVIK-STANTEC LTD: Base Data: Government of Canada DISCLAIMER: All locations are approximate, please refer to the Highway Final Design for specific locations. s of 05 a

03 L Winter Camp 1 (Year 2 Move and Year 3 & 4 Operation)

544000 546000 548000 550000 552000 554000 556000 558000 560000 562000 564000 566000 568000 570000 572000 574000

> Kilometre Post PW19A 0 0 0 0 0 0 6 6

3 R" 3 6 Q Summer Camp 6 7 Camp 3 7 (Year 2 Move and R" Winter Camp/Summer Storage Year 3 Operational) ± 0 0

0 Proposed Pullout Location 0 0 (! 0 4 4 3 3 6 6 7 7 !C Bridge Crossing

!(GF Bridge Size Culvert Crossing 0 0 0 0 0 0 2 2

3 !( 3

6 Culvert Crossing 6 7 7

Constructed Alignment

0 Year Two Water Access (Winter) 0 0 0 0 0 0 0 3 3 6 6 7 Year Two Winter Road 7

Year Two Winter Access Trail 0 0 0 0 0 0

8 Year 2 Water Withdrawal Lake 8 2 2 6 6 7 7 Inuvik, 7(1)a Private Lands PW18 Winter Camp 2 314/325 (Year 2 and Inuvik, 7(1)b Private Lands

0 Year 3 Operational) 0 0 0

0 KP 40 R 0 6 End of Construction " 6 2 > 2 6 6 7 Tuktoyaktuk, 7(1)a Private Lands Year Two R" 7 KP 39 Tuktoyaktuk, 7(1)b Private Lands > 0 0

0 0 1,250 2,500 3,750 5,000 KP 38 0 0 0 4 4

2 > 2 6 6 7 7 Metres - 1:130,000 KP 37 123510689-152 > 22b !(

0 KP 36 0 0 0 0 0

2 > 2 2 2 6 6 7 7 KP 35 > Summer Camp Q KP 34 0 0

0 > 0 0 0 0 0 2 2 6 6 7 KP 33 7 > 35 KP 32

0 > 0 0 !( 0

0 22a 0

8 GF 8 1 1 6 6 7 KP 31 7 (!> 37 KM 30.9 (!> 0 KM 30.2 0 0 29B KP 30 0 0 !( GSC4 0 6 6

1 21a 1 6 6 7 7 29A >KP 29 KP 28 Winter Camp 1 (Alternate) !(>R" (Year 1 Move and KP 27 !( GF Year 2 Operational) 0 !( GF 21 0 0 KP 26 !( > 28 (Jimmy Lake) 0 0 !( 0

4 20a 4

1 > 1

6 ! 19 6

7 C 7 18a 20 R >KP 25 18 Winter Camp 1 " 17a (Year 1 Move and !(GF GSC3 KP 24 Year 2 Operational)

0 > 0 0 0 0 0

2 !( 2

1 17 1 6 6

7 KP 23 !( KP 24 7 > 16 15C !( 15B >GF 0 0

0 15A KP 22 0 0 0 0 0

1 KP 21 1 6 6 7 > 7

KP 20 > 0 0 0 0 0 0 8 8 0 0

6 >KP 19 6 7 7

>KP 18 0 0

0 Q Summer Camp 0

0 > 0 6 6 0 0

6 KP 17 6 7 KP 16 7 > PW11 KP 15

0 > 0 0 0 0 0 4 4

0 Camp 2 (Alternate) 0 6 R 6 7 KP 14 " 7 > R Camp 2 KP 13 " (Year 1 and 2)

0 > 0 0 0 0 0

2 PW10 2 0 0 6 6 7 KP 12 7 >

KP 11 > 0 0 0 0 0 0 0 0 0 0 6 6

7 KP 10 7 >

KP 9 > 0 0 0 0 0 0 8 8 9 9

5 KP 8 5 7 > 7

KP 7 > 0 0 0 0 0 0 6 6

9 KP 6 9 5 5 7 > 7

>KP 5 0 0 0 0 0 0

4 KP 4 4 9 9 5 5

7 > 7

KP 3 > 0 0

0 I401A 0 0 0

2 KP 2 2 9 9 5 5

7 > 7 (Year 2 Operation) KP 1 > 0 0 0 0 0 0 0 0 9 9 5 5 7 7

544000 546000 548000 550000 552000 554000 556000 558000 560000 562000 564000 566000 568000 570000 572000 574000

n

w o

PREPARED BY r

b

d

INUVIK - TUKTOYAKTUK HIGHWAY CONSTRUCTION PLAN :

y

B

3

1

0

2

Navy ,

0

2

PREPARED FOR r e NU Pit b

Project m

e t

Location p

e

S

: d

Year Two (South) e

i f

FIGURE NO. i d

NWT o

M

YT t

Acknowledgements: Original Drawing by KAVIK-STANTEC LTD: Base Data: Government of Canada DISCLAIMER: All locations are approximate, please refer to the Highway Final Design for specific locations. s of 05 a

04 L >

> 548000 550000 552000 554000 556000 558000 560000 562000 564000 566000 568000 570000 572000 574000 0 0 0 0 0 0

4 >4 6 6 6 6 7 > Kilometre Post 7 KM90 > KM89 R Winter Camp/Summer Storage >

Proposed Pullout Location KM88 0 (! 0 0 0

0 > 0

2 174 2 6 6 6 6 7 ! Bridge Crossing 7 C Winter Camp 1 KM87 R > (Year 1 Move and !( GF Bridge Size Culvert Crossing Year 2 & 3 Operational) KM86 > !( Culvert Crossing 0 KM85 0 0 0 0 > 0 0 ± 0 6 6 6 6 7 Constructed Alignment > KM84 7

Source 177 Access >KM83

Year Three Winter Road 0 0

0 KP 78 0 0 0

8 >KM82 8 5 5 6 6 7 Year Two Water Access (Winter) 7 KM81 > Year 3 Water Withdrawal Lake KM79 KM80 KM78 >!( !( > Inuvik, 7(1)a Private Lands > GF 0 0

0 KP 77 KM77 33a 0

0 33b 0 6 6

5 > 5 6 6

7 Inuvik, 7(1)b Private Lands 7

KM76 Tuktoyaktuk, 7(1)a Private Lands >

Tuktoyaktuk, 7(1)b Private Lands 0 0

0 KM75 0 0 0

4 > 4 5 0 1,000 2,000 3,000 4,000 5 6 6

7 KM73 7 > 11BC > Metres - 1:110,000 KM74 123510689-153 KM72 309 > 0 0 0 0 0 0 2 2 5 5

6 KM71 6 7 R KP 70 > 7 KM 70.7 !( KM70 Winter Camp 2 > (Year 2 Move and 0 0

0 Year 3 Operation) 0 0 0 0 0

5 KM69 5 6 6 7 > 7

KM68 >! KM67 C 31 0 0

0 > 0 0 0 8 8 4 4

6 KM66 6 7 > 7

KM65 >

KM64 0 0 0 0

0 > 0 6 6 4 4 6 6 7 7 KM63 >

KM62 > 0 0 0 0

0 !( 0 4 > KM 61.7 4 4 4 6 6 7 KM61 7 > KP 61 KM60

KM59 > 0 0 0 0 0 0 2 2 4 4 6 6 7 KM58 7 312 West >

R KM57 30a Winter Camp 1 >

0 !C 0 0 (Year 2 Move and > 0 0 KM56 0 0 0 4 4

6 Year 3 & 4 Operation) 6 7 !(GF29a 7 KM55 > KP 55 KM54 > 0 0 0 0 0 0

8 !( 28a 8 3 3

6 KP 54 6 7 KM53 7 >

KM52 >

0 PW19A 0 0 0

0 KM51 0

6 R 6 3 > 3 6 6 7 Winter Camp 3 KP 50B 7 (Year 2 Move and Year 3 Operation) >!( KM50 27c KM49 0 !( 0 0 KP 50A 0

0 27b2 > 0 4 4 3 3 6 6 7 7

>!( 27b KM48

> KM47 0 0 0 0 0 0

2 27a !( 2 3 3 6 6 7 KM46 7 > KP 45 > 26 !( KM45 0 0 0 0 0 0 0 0 3 KM44 3 6 6 7 > 7 25 !( KM43 > KP 42 !( 24b 0 0

0 !( 0 0 0

8 KM42 GF24a 8 2 2 6 6

7 > 7 KP 41 KM41 314/325 > PW18 Winter Camp 2 0 0

0 R 0 0 (Year 2 and ! 0 6 C 6 2 > 2 6 Year 3 Operation) 6 7 23a 7 KM40

>KM39 0

KM38 0 0

> 4 2 6 7

548000 550000 552000 554000 556000 558000 560000 562000 564000 566000 568000 570000 572000 574000 u

a

e

d

o

b i

PREPARED BY h

> T

C

INUVIK - TUKTOYAKTUK HIGHWAY CONSTRUCTION PLAN :

y B

PW13

3

1

0

2

,

0

2

PREPARED FOR r e

NU b

Project m

e t

Location p

e

S

: d

Year Three (North, South) e

i f

FIGURE NO. i d

NWT o

M

YT t

Acknowledgements: Original Drawing by KAVIK-STANTEC LTD: Base Data: Government of Canada DISCLAIMER: All locations are approximate, please refer to the Highway Final Design for specific locations. s of 05 a

05 L