REVISION DATE REVISION PREPARED APPROVED BGV CHECKED BY INITIALS STATUS SCOPE BY BY Revision CLIENT COMPANY ENTERPRISE: CAMBAMBE HYDROELECTRIC POWER PLANT AREA: ENVIRONMENT TITLE: ENVIRONMENTAL IMPACT STUDY FOR THE REHABILITATION AND EXPANSION OF THE CAMBAMBE HYDROELECTRIC POWER PLANT PREPARED BY: CHECKED BY: INITIALS: APPROVED BY: DATE Sheet of 17/12/2012 DOCUMENT NO. REVISION CLIENT NO. REVISION RESTRICTED ENVIRONMENTAL IMPACT STUDY FOR THE REHABILITATION AND EXPANSION OF THE CAMBAMBE HYDROELECTRIC POWER PLANT Prepared by: DECEMBER 2012 RESTRICTED Project’s Technical Data: Title: Environmental Impact Study for the Rehabilitation and Expansion of the Cambambe Hydroelectric Power Plant Client: Office for the Medium Kwanza Project (GAMEK). Rua do Massangano, s/n, Luanda. Http://www.gamek.com Telephone: +244-222-445072 / 222-675801; Fax: +244-222-447973 E-mail: Consultant: Holísticos, Lda. – Serviços, Estudos & Consultoria. Rua 60, Casa 559, Urbanização Harmonia, Benfica, Luanda. Telephone: +244-222-006938; Fax: +244-222-006435. E-mail:
[email protected] Date: December 2012 RESTRICTED EIA (Environmental Impact Study) for the Rehabilitation and Expansion of the Cambambe Hydroelectric Power Plant CONTENTS Text Box List xii Figure List xii Photo List xv Table List xvii Chart List xxi Attachment List xxi Abbreviations xxiii 1. INTRODUCTION 1- 1 1.1. Background 1-1 1.2. Justification 1-4 1.3. Enterprise Sponsor 1-14 1.4. Scope of the Study 1-16 1.5. EIA’s Targets 1-19 1.6. Localization 1-20 1.7. Work Methodology 1-22 1.8. Areas Affected by the Project 1-23 1.8.1. Regional Coverage Area (AAR) 1-25 1.8.2.