Nunavik Land Claims Agreement Implementation Report Fiscal Years from 2011-2012 to 2014-2015 For information regarding reproduction rights, please contact Indigenous and Northern Affairs at:

[email protected]

www.canada.ca/indigenous-northern-affairs

1-800-567-9604 TTY only 1-866-553-0554

QS-6354-100-BB-A1 Catalogue: R1-63 ISSN: 2369-0364

© Her Majesty the Queen in Right of Canada, represented by the Minister of Indigenous and Northern Affairs, 2017

This Publication is also available in French under the title: Accord sur les revendications territoriales des Inuit du – Rapport du Comité de mise en œuvre - Exercices financiers de 2011-2012 à 2014-2015

Photo Credits:

b Table of Contents Foreword 2 General Overview of NILCA 3 Funding the Agreement 4 Implementing the Agreement 5 Implementation Committee 5 5 Government of 7 Makivik Corporation 10 Institutions of Public Government 12 Web Links 16 Annex A: Summary of Funding 17 Annex B: Overview of NILCA Area 18

1 Foreword As required by Article 23.3.3 (e) of the Nunavik The Implementation Committee would like to Inuit Land Claims Agreement (NILCA), the take this opportunity to recognize the strong Implementation Committee (IC) is pleased to communication between the various stake- present its second report on the implementation holders in the last few years, which has led to a of the Agreement. successful implementation process. It is hoped that this precedent foreshadows continued Exceptionally, the IC has decided to combine good relations between the parties heading into two reporting periods (2011-2013 and 2013-2015) the future. into one volume in order to cover this period in a timely manner. The good working relationship between the Nunavik Institutions of Public Government (IPGs) This report provides readers with an overview of and those from the surrounding treaty the Agreement, its funding and the various activ- has also aided in a successful implementation ities undertaken by the different bodies during process since 2011. this reporting period.

Natalie Neville Sam Silverstone William MacKay Appointed by Appointed by Appointed by the the Government of Canada Makivik Corporation Government of Nunavut

2 General Overview of NILCA On 1, 2006 Makivik Corporation, the Nunavik Marine ) as well as a portion Government of Nunavut (GN) and the Govern- of northern and an area offshore ment of Canada signed the Nunavik Inuit Land from Labrador. Claims Agreement (NILCA). The agreement Pursuant to the NILCA, Nunavik Inuit own, either came into force on July 10, 2008 following the solely or jointly, a total of 7,530 islands which adoption by the Parliament of Canada of the constitute an approximate area of 8,051 km Nunavik Inuit Land Claims Agreement Act (S.C. squared. 1 2008, c.2). This Agreement is a treaty and is constitutionally protected within the meaning of Finally, the NILCA contains separate overlap section 25 of the Constitution Act of 1982. agreements between Nunavik Inuit and Nunavut Inuit, the of Eeyou Istchee, The NILCA addresses the use and ownership of and Labrador Inuit. lands and resources in James Bay, , and (known as the 1 These figures were provided by Makivik Corporation.

3 Funding the Agreement The Government of Canada is responsible for transferred a total amount of $45,396,153 to the funding Institutions of Public Government (IPGs) parties (signatories and IPGs) involved in the and activities related to the implementation of implementation of the NILCA. Payments were the NILCA. made on time according to final schedules and funds and were distributed as shown in the pie During the reporting period, the Department of chart below. Indigenous and Northern Affairs Canada (INAC)

Overall Funding for Fiscal Years from 2011-2012 to 2014-2015

Grant to Makivik Corporation / Nunavik Inuit Trust (Article 16) Grant to Makivik Corporation / Nunavik Inuit Trust (Article 23) Grant to Government of Nunavut Contributions to IPGs

4 Implementing the Agreement Implementation Committee Departments/Organizations that are involved, on a regular basis, in the fulfillment of Cana- The NILCA (Article 23) provides for the es- da’s obligations towards this Agreement are: tablishment of an implementation committee Indigenous and Northern Affairs Canada, Parks responsible for overseeing, monitoring and Canada, Environment Canada, and Fisheries and reporting on the implementation of the Agree- Oceans Canada. These Departments play key ment, and making recommendations to the roles in the day-to-day implementation activi- parties for future planning periods following ties of the NILCA, namely in terms of funding, the initial ten-year period. The Implementation coordinating and participating in meetings and/ Committee (IC) of the NILCA is composed of or IPGs, and sharing expertise on different issues three senior officials, one from Canada, one from raised by the implementation of the negotiated Nunavut, and one from Makivik Corporation. agreement. Apart from the production of this report, the IC Apart from funding, the Government of Canada undertook several actions/activities during the participates actively in the implementation of reporting period, as it: the NILCA through an interdepartmental cau- ÊÊ Improved the funding agreement as the cus. This Interdepartmental Caucus provides a mechanism to transfer funds to the IPGs; structured forum to help ensure collaborative, ÊÊ Created a permanent Terms of Reference for consistent and effective fulfillment of imple- the committee so that their responsibilities mentation activities undertaken across different and procedures are clear; federal organizations. Generally, the Interdepart- ÊÊ Began the process of the Implementation mental Caucus meets twice a year and these Plan renewal; regular meetings often coincide with upcoming Implementation Committee meetings. These ÊÊ Coordinated to ensure that issues that arise meetings allow members of federal departments are properly reviewed and resolved, including creating working groups where necessary to with implementation responsibilities to discuss study specific issues. implementation-related matters, to propose that certain issues be referred to the Implementation Government of Canada Committee for further discussions and finally, to As a signatory to the NILCA, the Government consult with Canada’s representative on the IC of Canada has implementation obligations about committee business before IC meetings. under the provisions in the NILCA. Federal

5 During the reporting period, the Government (TMNP) and will seek the views of Makivik. of Canada, via its departments/organizations, There will be a general consultation process contributed to the effective implementation that will solicit views from the public and key of the Agreement by undertaking several stakeholders. actions/activities: ÊÊ Due to a fire in the Pavilion for the Parc Na- tional Kuururjuaq in 2014, Parks Canada has Indigenous and Northern Affairs Canada secured interim office space in the Communi- ÊÊ Participated in the NILCA Implementation ty Centre through a lease arrangement with Committee to ensure proper and timely the Northern Village of . implementation of the NILCA; ÊÊ Parks Canada continues to base its oper- ÊÊ Funded and assisted in resolving funding and ations in the summer out of the Torngat related matters for the IPGs; Mountains Base Camp and Research Station ÊÊ Participated jointly with other signatories in located at Saglek outside the park but the implementation of the overlap arrange- adjacent to the southern boundary. ments contained in Articles 27, 28 and 29 of ÊÊ In addition, Parks Canada contracted 9 the NILCA; Nunavik Inuit cultural performers who also ÊÊ Monitored members’ appointments to the enriched the general visitor experience and IPGs as well as members’ appointments to in 2011 and 2014 provided special experienc- the Implementation Committee; es and programming for the Students on Ice which was hosted by Parks Canada in the ÊÊ Worked closely with their partners to collect Torngat Mountains National Park. These el- nominations and processes all Ministerial ders and cultural performers worked with the appointments to the IPGs. Six appointments Kangidluasuk Student Program which hosts were made to the IPGs between April 1, 2012 Inuit youth from Nunavik and and March 31, 2015; at Base Camp for 2-3 weeks. Seventeen ÊÊ Through the Nunavut Contaminated Sites Nunavik Inuit youth have participated in this Program, worked on remediating the Cape program during this time. The connection Dorset 2 site, located on Nottingham Island. between Inuit elders and youth in the Torn- Community consultations were held in gat Mountains has been showcased through and in January 2013 presenting the poetry in 2 books: A Gift of Words (2013) and draft Remedial Action Plan, in order to seek Their Working Hands, Their Golden Words – input from residents on the plan. Inuit Elders to Inuit Youth (2014). Parks Canada ÊÊ Providing opportunities for safety training workshops in Kangiqsualujjuaq to Torngat Mountains National Park of Canada help Nunavik Inuit qualify for employment as ÊÊ Parks Canada is beginning a new manage- bear guards in the park. ment planning process with a final manage- ÊÊ Collaborating with Nunavik Parks on ways to ment plan due in December 2016. As part of cooperate on communication and emergency this process, Parks Canada will be collaborat- response and to promote the Torngat Moun- ing with the Cooperative Management Board tains National Park and the Parc National (CMB) for Torngat Mountains National Park Kuururjuaq as one destination.

6 Fisheries and Oceans Canada EC has collaborated actively in the work of the NMRWB by making EC’s expertise available to ÊÊ Community consultations to obtain detailed samples from and Ivujivik com- the NMRWB and by providing technical support munity hunts (July) and inform on research for questions related to migratory birds and activities and to outline research results species at risk. (February 2012). More specifically, EC worked with the NMRWB on: ÊÊ Advice provided to Wildlife Board on accept- ÊÊ The development of the Peregrine Falcon able harvest levels of beluga in the NMR. Management Plan and the Recovery Strategy ÊÊ Tissue sampling program (collect skin sample for the Red Knot; and tooth from harvested beluga whales and ÊÊ The presentation to the NMRWB of avifauna other mammals) from all Nunavik communi- monitoring in the Nunavik marine and coastal ties supported. region; ÊÊ Genetic analyses of the samples obtained ÊÊ The preparation of the implementation of the from Nunavik hunter tissue sampling pro- 2nd Québec Breeding Bird Atlas in Nunavik. gram were analyzed at the DFO genetics laboratory. EC also kept the NMRWB informed of its decisions and activities concerning Polar Bear ÊÊ Large programs that explored the ecology of beluga, and bowhead whales from the management in Canada and in the NMR con- perspective of traditional knowledge were cerning, in particular: completed in 2013, and a study partially ÊÊ The development of the Polar Bear Manage- supported by the Nunavik Marine Region ment Plan; Wildlife Board (NMRWB) that examined ÊÊ The implementation of Total Allowable Take ecology from the perspective of by Inuit in the NMR, and; Inuit Traditional Ecological Knowledge was initiated in 2013/2014 and completed in 2015. ÊÊ Polar Bear population management in Canada and internationally. ÊÊ Deployment and recovery of hydrophones to monitor ship noise and marine mammal Since 2014, EC is also involved in the formulation vocalizations in Hudson Strait. Presentation of the Land Use Plan at the invitation of the Nun- of results to National Marine Mammal Peer avik Marine Region Planning Commission. Review meeting. ÊÊ Presented several research results to partner Government of Nunavut entities. The GN has several implementation obligations Environment Canada under the NILCA, many of which are on an as needed basis, for example, activities associated During the reporting period, Environment with nominating members to NILCA IPGs, new Canada (EC) worked closely with NILCA’s IPGs consultation requirements, and potential travel on the implementation of the wildlife manage- and translation costs related to obligations. ment regime and the impact review process Legal obligations include land titles registration, for proposed development projects in the surveys and the potential for dispute resolu- Nunavik Marine Region as specified under the tion costs. Environmental obligations include Agreement. 7 licensing, harvesting related information collec- Land and Resources: tion, enforcement of wildlife legislation, general With the jurisdictional responsibility to protect environmental monitoring and land use planning the land and people of the territory, the GN has a where it overlaps and affects both jurisdictions, very real and tangible interest in the outcome of enforcement of development project certificates Land Use Planning (Article 6) and the Develop- and related activities, and activities associated ment Impact (Article 7) process. with the future appropriate permanent wildlife and land and water management regimes for ÊÊ The GN Department of the Environment makes appointments for the GN representa- the Areas of Equal Use and Occupancy between tive to the NMRPC (Nunavik Marine Region the NLCA and the NILCA. Finally, there are other Planning Commission) and the NMRIRB obligations related to places names, archaeolog- (Nunavik Marine Region Impact Review ical and ethnographic resources and legislation, Board) ongoing, including involvement in the resource royalty related activities (calculations, chair appointment process for each IPGs. proposals, legislation, etc). ÊÊ The GN Minister and GN departments will be Department of Executive involved in the development of, review and and Intergovernmental Affairs implementation and monitoring of future land use plan. EIA holds the transboundary claims files and works to coordinate and monitor implementa- ÊÊ The GN Minister and GN departments tion of the NILCA by government departments. are also involved in screening, reviewing, monitoring, decisions and amendments of ÊÊ Costs related to implementation manage- development project proposals. ment include ongoing membership on the Implementation Committee and related ÊÊ The GN will also work with its partners to activities. develop a general environmental monitoring plan for the NMR. Department of Environment Wildlife Management Division: Protected Areas: Under the NILCA, the responsibility for manage- Article 11 of the NILCA assigns the Department ment of terrestrial species is shared between the of Environment the responsibility for the estab- GN Department of Environment, the NMRWB, lishment of a Protected Area Impact and Benefit and the Local Nunavimmi Umajutvijiit Kata- Agreement and joint management committee juaqatigininga (LNUKs)/ Regional Nunavimmi for territorial parks and other areas of particular Umajutvijiit Katajuaqatigininga (RNUKs). These significance for ecological, cultural, archaeolog- organizations work collectively and inde- ical, research or similar reasons under shared pendently on their respective responsibilities as jurisdiction or solely under the jurisdiction of the outlined in the NILCA. In the GN, responsibility territorial government. for wildlife management initiatives falls to the ÊÊ No Protected Areas are currently planned Wildlife Division of the Department of Environ- for the NMR Settlement Area; therefore no ment. This division participates in the decision activities have been undertaken during the making process by bringing the Department’s reporting period. management recommendations forward to the

8 NMRWB. The division is responsible for licensing, developing regulations and legislation that information collection (harvesting, sampling, are consistent with the NILCA. etc.), enforcement of wildlife legislation and ÊÊ The Land Titles Office administers the Land wildlife monitoring. The GN Department of Titles Act (Nunavut) and provides guaran- Environment may also seek advice from the teed titles under a modern legal regime. NMRWB on wildlife management issues. The GN ÊÊ Pursuant to Article 20 of NILCA, the GN Environment Minister can refer matters to the and Makivik Corporation share title in NMRWB where appropriate. all archaeological specimens discovered ÊÊ The Wildlife Division has increased contact, in the Nunavik Marine Region after July most recently on legislation and regulations, 2008. The GN retains title in all specimens and will be building on that relationship. recovered prior to July 2008. In 2014, the Avataq Cultural Institute, which has been ÊÊ The Department of the Environment makes designated by Makivik as its repository for appointments for the GN representative archaeological specimens, requested that all to the NMRWB ongoing, including jointly specimens from the Nunavik Marine Region appointing the chair. be transferred to it. The Department of Department of Justice Justice assisted the GN in entering into an amended agreement with Avataq respecting Legal obligations include land titles registration, sur- this transfer. veys and the potential for dispute resolution costs. Department of Culture and Heritage ÊÊ The Legal and Constitutional Law Division provided legal advice to other GN depart- ÊÊ The Department of Culture and Heritage ments about their NILCA obligations during worked with the Inuit of Nunavik to im- the period in question. plement Article 20 (Archaeology) and 21 (Ethnographic Resources and Archival ÊÊ The Legislative Drafting Division assisted Records), including the drafting of a Place government departments and agencies in Names Policy.

Funding to the Government of Nunavut during reporting period 2

2011-2012 2012-2013 2013-2014 2014-2015

Grant to Government of Nunavut $392,609 $392,013 $415,745 $422,210

2 This amount includes Final Domestic Demand Implicit Price Index (FDDIPI) as prescribed in the text of the Agreement

9 Makivik Corporation ÊÊ The system automatically generates the entry and access permit as well as a release During the reporting period, Makivik Corporation of liability waiver that proponents must sign; undertook a number of activities respecting ÊÊ Future development will involve the process- the NILCA and the NILCA Implementation Plan ing of land use licenses / leases along with in addition to participating in meetings of the payment of fees (if required). Scheduled to NILCA Implementation Committee to work with be up on the web in 2016. the other parties to ensure the effective and timely implementation of the various provisions Place Names: of NILCA. Makivik, through its appointed mem- ÊÊ Place names in the offshore region, both bers, also participated in the Torngat Mountains traditional island names as well as feature National Park Cooperative Management Board names (cliffs, bays, etc.) have been compiled (2 members and support staff) pursuant to in a database and will be submitted to the Article 4 of the Nunavik Inuit Parks Impacts Geographic Names Board of Canada (GNBC and Benefits Agreement (PIBA) for the Torngat Nunavut region); Mountains National Park. ÊÊ After data collection / interviews and verifi- cation, names were assembled with support- Makivik Corporation is in charge of monitoring ing documentation into a geodatabase; and supervising the entry and access provisions of Article 12 of NILCA and oversees any access ÊÊ The GNBC requires various other attributes in or land use requests from government or private the digital geodatabase prior to submission to the toponymist and a funding submission sector. Makivik is also in the process of research- to the GN Department of Language, Culture, ing and establishing Inuit place names for the and Youth (CLEY) will be submitted in early Nunavik Marine Region. In this regard, Makivik 2016 to continue the work on the geodata- has undertaken the following actions/activities base prior to submission. during this period: Makivik provided investment and administrative Entry and Access: advice to the Nunavik Inuit Trust. In addition, ÊÊ Makivik reviews and processes 5 to 10 entry Makivik has been responsible for ensuring applica- and access applications per year; tion of the priority provisions respecting contracts ÊÊ About 50% of the entry and access appli- and employment under Article 13 of NILCA. cations are from Government and 50% of With respect to the three overlap arrangements the applications are from non-government between Nunavik Inuit and other Aboriginal entities / private companies (tourism opera- groups contained in the NILCA, Makivik contin- tors for example). ues to participate in the implementation of these Land Administration: overlap arrangements as contained in Articles ÊÊ Makivik developed an online entry and 27 (Nunavut), 28 (Crees) and 29 (Labrador Inuit) access application that allows users to apply of the NILCA and ensures that Nunavik Inuit for entry and access via an online application maintain participation through representation form; on the respective management boards of these overlap arrangements.

10 During this period, Makivik undertook extensive institutions created by the NILCA. In addition, discussions with Canada regarding the proposed Makivik has raised with Canada and Nunavut its federal Funding Arrangement template and mu- concern over various provisions of the Nunavut tually acceptable amendments were made which Wildlife Act and new Nunavut Wildlife Regula- adequately respect the provisions of NILCA, tions due to potential conflicts of certain provi- while at the same time assuring the necessary sions of this statute and regulations with various transparency and accountability for implemen- wildlife provisions of the NILCA. In this regard, tation funding of the three institutions of public Makivik will participate in a working group government created by virtue of the NILCA; the established by Nunavut to review this legislation NMRWB, the NMRPC, and the NMRIRB. and regulations in order to avoid conflicts with the NILCA. Makivik also tracked and reviewed the progress of the major use and occupancy mapping Makivik has also begun to participate during this project undertaken by the NMRPC. In this regard, period in discussions with the other Implemen- Makivik assisted the Implementation Committee tation Committee parties concerning the next in ensuring adequate funding was provided to ten-year period of the Implementation Plan, as the NMPRC to complete this use and occupancy contemplated by Article 23 (Implementation) mapping project in accordance with the project- of the NILCA. This process will probably extend ed deadlines for delivery of this work. over a two-year period leading up to the actual commencement of the next ten-year period. Makivik generally provides assistance and advice, as requested, to the three management

Funding to Makivik Corporation and Nunavik Inuit Trust during reporting period 3,4

2011-2012 2012-2013 2013-2014 2014-2015 Grant to Makivik Corporation / Nunavik Inuit Trust (Article 16) $6,790,890 $6,790,890 $6,790,890 $6,790,890 Grant to Makivik Corporation / Nunavik Inuit Trust (Article 23) $1,420,943 4 N/A N/A N/A

3 This amount includes Final Domestic Demand Implicit Price Index (FDDIPI) as prescribed in the text of the Agreement 4 Under the Agreement the last payment was on the third anniversary of the signing of the Agreement

11 Institutions of Public Government ÊÊ Following a request from the RNUK to hunt bowhead whales in the NMR, in 2014 the Nunavik Marine Region Wildlife Board NMRWB established a TAT for bowhead The NMRWB is an Institution of Public Govern- whales that was accepted and implemented by the DFO Minister; ment created under Chapter 5 of the NILCA. ÊÊ The NMRWB approved access to the NMR for During the reporting period, the NMRWB has un- wildlife research projects, primarily for migra- dertaken several activities related to its mandate. tory bird studies on the offshore islands, as Such activities have included: well as beluga, fish and shrimp surveys; Ê The NMRWB held its first public hearing Ê ÊÊ The NMRWB collaborated with the Nunavut regarding establishing a Total Allowable Take Wildlife Management Board to establish a To- (TAT) and Non-Quota Limitations (NQL) for tal Allowable Take / Total Allowable Harvest Southern Hudson Bay polar bear within the for the two species of shrimp fished in the Nunavik Marine Region (NMR) (held Febru- NMR and Nunavut Settlement Area; ary 2014); ÊÊ The NMRWB approved research funding ÊÊ NMRWB staff held workshops in each Nun- for projects proposed in the NMR that best avik community with relevant organizations reflect the board’s mandate. Between 2011- and individuals (LNUKs and key hunters) 2015, the board supported eight projects. regarding beluga management. Based on Research funded included; surveys for ringed these consultations and the best available seal and SHB polar bear, research on polar information from Nunavik Inuit knowledge bear predation of Common eiders and Inuit and scientific studies, the NMRWB decided knowledge of walrus, monitoring of invasive on a new beluga management system, species, survey of subsistence harvest of including TAT for Eastern Hudson Bay beluga migratory birds, Inuit participation in the and NQLs, which was accepted by the Breeding Bird Atlas, and community Department of Fisheries and Oceans (DFO) based monitoring of the sea ice, wildlife Minister in the summer of 2014; entrapments and oceanography. Two of ÊÊ In collaboration with researchers from Trent these projects did not proceed as anticipated University, the NMRWB is conducting a Nun- - the polar bear survey and survey of Inuit avik Inuit Knowledge of polar bears study to subsistence harvesting of migratory birds - inform the Board’s public hearings regarding and therefore did not end up expending the polar bears.; allocated funding; ÊÊ The NMRWB established a TAT, and NQLs, ÊÊ Completed the first website of the NMRWB, and approved a management plan for 2013- in the summer of 2012 and currently working 16, for in the NMR. In 2014 Makivik an improved version for launch in 2016. and DFO proposed a flex-quota system for narwhal, which was approved by the NMRWB;

12 Funding to NMRWB during reporting period 5

2011-2012 2012-2013 2013-2014 2014-2015

NMRWB $2,564,571 $2,617,581 $2,682,284 $2,700,128

5 This amount includes Final Domestic Demand Implicit Price Index (FDDIPI) as prescribed in the text of the Agreement

Nunavik Marine Region »» Phase II oversaw the completion of the Planning Commission interview sessions on the Ungava Coast (Kangiqsualujjuaq, , , The NMRPC is an Institution of Public Govern- Quaqtaq, , and Salluit); ment created under Chapter 6 of the NILCA. »» Phase III oversaw the completion of the During the reporting period, the NMRPC has un- Verification Tour for the Ungava Coast dertaken several activities related to its mandate. which included returning to the com- Such activities have included: munities of Kangiqsualujjuaq, Kuujjuaq, , , Quaqtaq, Kangirsuk, ÊÊ Discussed and mandated a chairperson to Kangiqsujuaq, and Salluit with completed finalize the arrangements for the production map biographies to hand-back and verify of a website for the NMRPC. The website is the data-collection for each community; to include resolutions of meetings, public notices and decisions, among including a »» Phase IV oversaw the completion of the series of maps related to the Nunavik Marine interview sessions on the Hudson Coast as Region. The website went live in early 2013; well as residents from Nunavik. The communities interviewed included Ivu- ÊÊ A Data Gap Analysis of current information jivik, , , , , available for the Nunavik Marine Region Kuujjuaraapik and ; (NMR). The analysis led to the proposal of the Nunavik-wide Use and Occupancy »» Phase V is the Verification and Hand- Mapping exercise; back Tour for the Hudson Coast (Ivujivik, Akulivik, Umiujaq, Puvirnituq, Inukjuak, ÊÊ The Nunavik-wide Use and Occupancy Map- Kuujjuaraapik, Chisasibi) and is currently ping Exercise was undertaken in five Phases: scheduled for completion in March 2016; »» Phase I oversaw the development of the » Important additional funding was granted communications strategy and the com- » during the reporting period to assist in pletion of research design, methodology completion of the project. testing and two single-community pilot map surveys (Tasiujaq and Aupaluk); ÊÊ A Data Compilation Initiative to give an overview of the available datasets for the

13 land-use activities of the NMRPC was under- ÊÊ The preliminary stages of the development taken and completed. It will form the basis of of engagement procedures for Overlap the Land-Use Plan currently in development Agreements with Adjacent Jurisdictions; for the NMR; ÊÊ The Land-Use Plan for the NMR is currently ÊÊ The preliminary stages of the Marine Protect- in its formulation stages. ed Areas Project were undertaken.

Funding to NMRPC during reporting period 6,7,8

2011-2012 2012-2013 2013-2014 2014-2015

NMRPC $513,880 $524,502 $654,258 7 $1,141,042 8

6 This amount includes Final Domestic Demand Implicit Price Index (FDDIPI) as prescribed in the text of the Agreement 7 Includes an additional $121,500 from Canada and $21,380 from Makivik Corporation to do the Use and Occupancy Mapping project 8 Includes an additional $600,000 to the base funding to do the Use and Occupancy Mapping project

Nunavik Marine Region potential to impact the NMR. These include Impact Review Board projects and activities such as: The NMRIRB is an Institution of Public Govern- »» The Baffinland Mary River Iron Mine ment created under Chapter 7 of the NILCA. Project; » The Canadian Royalties Nunavik Nickel During the reporting period, the NMRIRB has un- » Project; dertaken several activities related to its mandate. Such activities have included: »» The Oceanic Iron Ore Hopes Advance Bay Project; ÊÊ Discussed and mandated a chairperson to finalize the arrangements for the production »» The Fiber Submarine Cable Project; of a website for the NMRIRB. The website »» Research and exploration activities as well is to include resolutions of meetings, public as tourist ventures. notices and decisions, among including a series of maps related to the Nunavik Marine ÊÊ The development of coordination strategies Region. The website went live in early 2013; with the RNUKs and LNUKs with regard to project monitoring in the NMR; ÊÊ The development of the internal Impact Review Process with clear-cut timelines and ÊÊ The creation of a Cumulative Impacts Assess- coordination procedures for cross-jurisdic- ment Tool for interactive engagement with tional activities; regard to potential and current development projects in the NMR. Additional funding was ÊÊ The Screening and Review of multiple granted to help complete this project. projects and activities that have had the

14 Funding to NMRIRB during reporting period 9,10

2011-2012 2012-2013 2013-2014 2014-2015

NMRIRB $354,540 $361,868 $720,339 10 $373,280

9 This amount includes Final Domestic Demand Implicit Price Index (FDDIPI) as prescribed in the text of the Agreement 10 Includes an additional $314,375 to the base funding to conduct hearings necessary to fulfill mandate, as well as an additional $19,200 to complete the Interactive map and Cumulative Impacts Assessment Tool

15

Web Links Nunavik Inuit Land Claims Agreement: http://www.aadnc-INAC.gc.ca/eng/1320425236476/1320425393532

Nunavik Inuit Land Claims Agreement – Implementation Plan: http://www.aadnc-INAC.gc.ca/eng/1293723055236/1293723175703

Nunavik Marine Region Wildlife Board: http://nmrwb.ca/

Nunavik Marine Region Impact Review Board: http://www.nmrirb.ca/

Nunavik Marine Region Planning Commission: http://www.nmrpc.ca/

16 Annex A: 11 Summary of Funding ,12,13,14

2011-2012 2012-2013 2013-2014 2014-2015

Grant to Makivik Corporation / Nunavik Inuit Trust (Article 16) $6,790,890 $6,790,890 $6,790,890 $6,790,890

Grant to Makivik Corporation / Nunavik Inuit Trust (Article 23) $1,420,943 N/A N/A N/A

Grant to Government of Nunavut $392,609 $392,013 $415,745 $422,210

NMRWB $2,564,571 $2,617,581 $2,682,284 $2,700,128 Contributions to IPGs NMRIRB $354,540 $361,868 $720,339 12 $373,280

NMRPC $513,880 $524,502 $654,258 13 $1,141,042 14

11 This amount includes Final Domestic Demand Implicit Price Index (FDDIPI) as prescribed in the text of the agreement 12 Includes an additional $314,375 to the base funding to conduct hearings necessary to fulfill mandate, as well as an additional $19,200 to complete the Interactive map and Cumulative Impacts Assessment Tool 13 Includes an additional $121,500 from Canada and $21,380 from Makivik Corporation to do the Use and Occupancy Mapping project 14 Includes an additional $600,000 to the base funding to finalize the use of occupancy plan

17

Annex B: OverviewAnnex of B: Overview NILCA of NILCA Area

18

20

NCR#7707805 - v5 19 20