In the Name of God
National Iranian Oil Company Public Relations Title: Investment Opportunities in National Iranian Oil Company Written and Edited by: Corporate planning directorate - Deputy of Investment and Development
Publisher: Department of Research and Publications
Design: Tarhesadeh.com Print: Ideh Novin Farda 1000 Issues Revised Ed.: 2013, Tehran “ All rights reserved to National Iranian Oil Company ”
Address: 3rd Headquarter of National Iranian Oil Company, Roudsar St., Hafez St., Tehran, Iran P.O.Box: 15875-1863, Tel: (+9821) 88946390 www.nioc.ir INVESTMENT OPPORTUNITIES in National Iranian Oil Company
In the name of God National Iranian Oil Company, with a huge amount of hydrocarbon reserves, ranks among the world’s largest oil companies. By March 2011, the oil and gas NIOC reserves are estimated to be 155 billion barrels and 34 trillion cubic meters respectively. Since 1951, NIOC has been directing and making policies for exploration, drilling, production, research and development, refining, distribution and export of oil, gas and petroleum products. With advances in technology and increasing complexities of economic and political relations, NIOC has risen to a privileged status. Now, NIOC plays a key role in national and regional policies and aims to cooperate with industrial countries in terms of energy supply and stabilizing the global oil market. NIOC, in line with the short, mid and long term plans, now aims to embark on joint ventures by foreign investors and international companies in oil and gas industry. This leaflet contains the major ready-for-investment projects. A summary of the most significant ready-for-investment projects comes as follows: Page Project 4 Oil & Gas Fields Development Plans (Preference is given to common fields) 10 Oil Fields Development Plans 28 Gas Fields Development Plans 42 Oil & Gas Exploration Blocks Projects 60 Gas Gathering, Compressor & Injection Stations Projects 76 Construction, Development & Commissioning of Desalting Plants 80 Construction of Gas Production Facilities, New Gas and NGL Plants 86 Aghajari Production Optimization and Surface Facilities Renovation (POSFR) 92 Crude Oil & Gas Export Pipelines and Pump Stations 98 Construction and Completion of Crude Oil Storage Tanks and pipelines 110 Gas Liquefaction and Sweetening Projects (LNG Production) 114 Other Projects 126 Power Supply Projects 130 Operational Tugboats and Marine Vessels Supply 134 Main Projects Under Investigation INVESTMENT Oil & Gas Fields Development OPPORTUNITIES Plans (preference is given to common fields) in National Iranian Oil Company 1 Final Development of Arash oil/gas field 2 Farzam oil field development, Siri district 3 Development of Salman field-Faraghan gas reservoir, Development of Salman field -Dalan and Kangan gas reservoirs + Development of Salman field-Shoeyba oil reservoir Oil & Gas Total project / 1
INVESTMENT Oil & Gas Fields Development OPPORTUNITIES Plans (preference is given to common fields) in National Iranian Oil Company
1 Further Development of Arash oil / gas field
Total Production Objectives Cost 1 Estimation 6,000 bpd (jointly with Saudi billion USD Arabia and Kuwait) Iranian Project Offshore Oil Client Company
6 Oil & Gas Total project / 2
INVESTMENT Oil & Gas Fields Development OPPORTUNITIES Plans (preference is given to common fields) in National Iranian Oil Company
2 Farzam oil field development, Siri district
Total Production Objectives Cost 140 Estimation 4,000 bpd production million USD (Common with the UAE) Iranian Project Offshore Oil Client Company
7 Oil & Gas Total project / 3
INVESTMENT Oil & Gas Fields Development OPPORTUNITIES Plans (preference is given to common fields) in National Iranian Oil Company 3 Development of Salman field-Faraghoun gas reservoir, Development of Salman field \ Dalan and Kangan gas reservoirs (990 million USD credit) + Development of Salman field-Shoeyba oil reservoir
Total Production Objectives Cost 2000 Estimation 1) 200 million cfpd of natural million USD gas; 2) maintaining production of 500 cfpd of natural gas; 3) 15 Iranian to 20,000 bpd gas condensates Project Offshore Oil (Jointly with the UAE) Client Company
8
INVESTMENT Oil Fields OPPORTUNITIES Development Plans in National Iranian Oil Company 1 South Azadegan oil field development (phase 2) 2 East Asalouyeh oil field development 3 Rig, Shorom, Doudro (Roshd) oil fields development (early production) 4 Soroush oil field development (phase 2), Bahregan district 5 Mahshahr oil field development, Bahregan district 6 Development of heavy oil reservoir of Ferdowsi field 7 Yadavaran oil field development (phases 2 & 3) 8 Khayam oil field development 9 Sousangerd oil field development 10 Masjed Soleiman oil field development (phase 2), Description and early production 11 Development of siri (Alvand, Dena) & Taftan oil fields 12 Development of Bangestan reservoir, Ahwaz oil field 13 Rag sefid oil field development 14 Development and completion of Cheshmeh-Khosh oil field (Bangstan) Oil Total project / 4
INVESTMENT Oil Fields OPPORTUNITIES Development Plans in National Iranian Oil Company
1 South Azadegan oil field development (phase 2)
Total Production Objectives Cost 6 Estimation Increasing production upto billion USD 600,000 bpd Petroleum Project Engineering and Client Development Company 13 Oil Total project / 5
INVESTMENT Oil Fields OPPORTUNITIES Development Plans in National Iranian Oil Company
2 Development and Description of East Asalouyeh oil field
Total Production Objectives Cost 66 Estimation Early production of 4000 bpd; million USD production upto 10,000-15,000 bpd Iranian Central Project Oil Fields Client Company
14 Oil Total project / 6
INVESTMENT Oil Fields OPPORTUNITIES Development Plans in National Iranian Oil Company
3 Rig, Shorom, Doudro (Roshd) oil fields development (early production)
Total 54+1500 Production Objectives Cost Estimation million Euro billion Rials Phase 1: 8,000 bpd production Phase 2: Increasing production upto 35,000 bpd Iranian Central Project Oil Fields Client Company
15 Oil Total project / 7
INVESTMENT Oil Fields OPPORTUNITIES Development Plans in National Iranian Oil Company
4 Soroush oil field development(phase 2), Bahregan district
Total Production Objectives Cost 570 Estimation Increasing production upto 25,000 million USD bpd Iranian Project Offshore Oil Client Company
16 Oil Total project / 8
INVESTMENT Oil Fields OPPORTUNITIES Development Plans in National Iranian Oil Company
5 Mahshahr oil field development, Bahregan district
Total Production Objectives Cost 72 Estimation 10,000 bpd million USD
Iranian Project Offshore Oil Client Company
17 Oil Total project / 9
INVESTMENT Oil Fields OPPORTUNITIES Development Plans in National Iranian Oil Company
6 Development of heavy oil reservoir of Ferdowsi field
Total Production Objectives Cost 3.13 Estimation Description of oil reservoir of billion USD Ferdowsi field (PEDEC is negotiating with Petronas and Petropars in Petroleum Malaysia for finance.) Project Engineering and Client Development Company 18 Oil Total project / 10
INVESTMENT Oil Fields OPPORTUNITIES Development Plans in National Iranian Oil Company
7 Yadavaran oil field development (phases 2 & 3)
Total Production Objectives Cost 7 Estimation Increasing production upto 300,000 billion USD bpd Petroleum Project Engineering and Client Development Company 19 Oil Total project / 11
INVESTMENT Oil Fields OPPORTUNITIES Development Plans in National Iranian Oil Company
8 Khayam oil field development
Total Production Objectives Cost 350 Estimation Increasing production upto 17,000 million USD bpd Iranian Central Project Oil Fields Client Company
20 Oil Total project / 12
INVESTMENT Oil Fields OPPORTUNITIES Development Plans in National Iranian Oil Company
9 Sousangerd oil field development
Total Production Objectives Cost 500 Estimation Early production of 10,000 bpd / million Euro Future development: Increasing production upto 30,000 bpd Arvandan Oil Project & Gas Client Company
21 Oil Total project / 13
INVESTMENT Oil Fields OPPORTUNITIES Development Plans in National Iranian Oil Company
10 Masjed Soleiman oil field development (Description and early production of phase 2)
Total Production Objectives Cost 100 Estimation Early production of 6,000 bpd million USD Petroleum Project Engineering and Client Development Company 22 Oil Total project / 14
INVESTMENT Oil Fields OPPORTUNITIES Development Plans in National Iranian Oil Company
11 Development of Siri (Alvand, Dena) and Taftan oil fields
Total Production Objectives Cost 1. 5 Estimation Increasing production upto 25,000 billion USD bpd Iranian Project Offshore Oil Client Company
23 Oil Total project / 15
INVESTMENT Oil Fields OPPORTUNITIES Development Plans in National Iranian Oil Company
12 Development of Ahwaz oil field- Bangestan reservoir
Total Production Objectives Cost 1.173 Estimation Increasing production upto billion USD 220,000 bpd National Project Iranian South Client Oil Company
24 Oil Total project / 16
INVESTMENT Oil Fields OPPORTUNITIES Development Plans in National Iranian Oil Company
1323 Rag Sefidoil field Development
517.5 Production Objectives Increasing production upto million USD 180,000 bpd National Project Iranian South Client Oil Company
25 Oil Total project / 17
INVESTMENT Oil Fields OPPORTUNITIES Development Plans in National Iranian Oil Company
14 Development and completion of Cheshmeh-Khosh oil field(Bangestan)
650 Production Objectives 30,000 bpd upto 80,000 bpd million USD
Iranian Central Project Oil Fields Client Company
26
INVESTMENT Gas Fields OPPORTUNITIES Development Plans in National Iranian Oil Company 1 Development of Zireh gas field, Bushehr 2 Halegan gas field development, Sepid Baghenoun field development, construction of Halegan gas refinery 3 Development of Karoun field- Bangestan gas reservoir - 88304 4 Development of Pazanan field-Khami gas reservoir - 83307 5 Aghajari field-Khalij gas reservoir development (phase 1) - 83302 6 Karanj gas field-Khami reservoir development (phase 1) - 83305 7 Development of West Namak Gas field 8 Development of Kish Gas field (phases 2 & 3) 9 Development of Tous Gas field (phase 1) 101 Development of Sorou Gas field (phase 1) 111 Development of South Gasho Gas field and its refinery Gas Total project / 18
INVESTMENT Gas Fields OPPORTUNITIES Development Plans in National Iranian Oil Company
1 Development of Zireh gas field, Bushehr
Total Production Objectives Cost 38+432 Estimation 1.5 million cubic meters per million USD billion Rials day of natural gas production and transfer of gas to Kangan Iranian Central processing facilities Project Oil Fields Client Company
30 Gas Total project / 19
INVESTMENT Gas Fields OPPORTUNITIES Development Plans in National Iranian Oil Company 2 Halegan gas field development, Sepid Baghenoun field development, construction of Halegan gas refinery
Total Production Objectives Cost 732.6+2591 Estimation million USD billion Rials Production 17 million cubic meters of sour gas per day (12.5 million from Halegan and Iranian Central 4.5 million from Sefid Baghoun) Project Oil Fields and 10,000 barrels of gas Client Company condensates; refining capacity: 17 million cubic meters per day 31 Gas Total project / 20
INVESTMENT Gas Fields OPPORTUNITIES Development Plans in National Iranian Oil Company
3 Development of Karoun field- Bangestan gas reservoir - 88304
Total Production Objectives Cost 84.5 Estimation 120 million cfpd of natural gas and million USD 14400 gas condensates barrels National Project Iranian South Client Oil Company
32 Gas Total project / 21
INVESTMENT Gas Fields OPPORTUNITIES Development Plans in National Iranian Oil Company
4 Development of Pazanan field- Khami gas reservoir - 83307
Total Production Objectives Cost 105 Estimation 200 million cfpd of natural million USD gas and 28,000 barrels of gas condensates National Project Iranian South Client Oil Company
33 Gas Total project / 22
INVESTMENT Gas Fields OPPORTUNITIES Development Plans in National Iranian Oil Company 5 Aghajari field-Khalij gas reservoir development (phase 1) - 83302
Total Production Objectives Cost 8.2 Estimation Production and injection of 40 million USD million cfpd of natural gas in Aghajari field-Asmari reservoir National Project Iranian South Client Oil Company
34 Gas Total project / 23
INVESTMENT Gas Fields OPPORTUNITIES Development Plans in National Iranian Oil Company
6 Karanj gas field-Khami reservoir development (phase 1) - 83305
Total Production Objectives Cost 43 Estimation 116 million cfpd of natural gas million Rials and 4500 gas condensate barrels National Project Iranian South Client Oil Company
35 Gas Total project / 24
INVESTMENT Gas Fields OPPORTUNITIES Development Plans in National Iranian Oil Company
7 West Namak gas field development
Total Production Objectives Cost 47.68+545.7 Estimation million USD billion Rials Production of 1.5 million cmpd natural gas and transfer to Sarkhoun processing unit Iranian Central Project Oil Fields Client Company
36 Gas Total project / 25
INVESTMENT Gas Fields OPPORTUNITIES Development Plans in National Iranian Oil Company
8 Kish gas field development(phases 2,3)
Total Production Objectives Cost 4.4 Estimation 2 billion cfpd billion USD Petroleum Project Engineering and Client Development Company 37 Gas Total project / 26
INVESTMENT Gas Fields OPPORTUNITIES Development Plans in National Iranian Oil Company
9 Tous gas field development(Phase 1)
Total Cost 59+900 Estimation million USD billion Rials
Iranian Central Project Oil Fields Client Company
38 Gas Total project / 27
INVESTMENT Gas Fields OPPORTUNITIES Development Plans in National Iranian Oil Company
10 Sorou gas field development(phase 1)
Total Production Objectives Cost 53.5+10 Estimation million USD billion Rials Production of 2.8 million cmpd of natural gas at end of the fifth five- year development plan of Iran Iranian Central Project Oil Fields Client Company
39 Gas Total project / 28
INVESTMENT Gas Fields OPPORTUNITIES Development Plans in National Iranian Oil Company
11 South Gasho gas field and its refinery development
Total Production Objectives Cost 861+6675 Estimation million USD billion Rials Production of 14.2 million cmpd natural gas, construction of a refinery with capacity of 14.2 million cmpd Iranian Central Project Oil Fields Client Company
40
INVESTMENT Oil & Gas Exploration Blocks OPPORTUNITIES Projects in National Iranian Oil Company 1 Hormozgan Block, Fars Zone 2 Lark (Hormoz Strait) Block, Persian Gulf Zone 3 Bastaneh Block, Fars Zone 4 Fino Block, Fars Zone 5 Kelato Block, Fars Zone 6 Dahno Block, Fars Zone 7 Lar Block, Fars Zone 8 Jahrom Block, Fars Zone 9 Kazeroun Block, Fars Zone 10 Taybad Block, Tabas Zone 11 Shiraz Block, Fars Zone 12 Sepidan Block, Fars Zone 13 Sina Block, Persian Gulf Zone 14 Kermanshah Block, Lorestan Zone 15 Drilling, seismic imaging, construction of roads and cellar (during 5th FYDP) Oil & Gas Total project / 29
INVESTMENT Oil & Gas Exploration Blocks OPPORTUNITIES Projects in National Iranian Oil Company
1 Hormozgan Block, Fars Zone
Total Production Objectives Cost 100 Estimation Exploration and Development million USD
Project Exploration Client Management
45 Oil & Gas Total project / 30
INVESTMENT Oil & Gas Exploration Blocks OPPORTUNITIES Projects in National Iranian Oil Company
2 Lark (Hormoz Strait) Block, Persian Gulf Zone
Total Production Objectives Cost 250 Estimation Exploration and Development million USD
Project Exploration Client Management
46 Oil & Gas Total project / 31
INVESTMENT Oil & Gas Exploration Blocks OPPORTUNITIES Projects in National Iranian Oil Company
3 Bastaneh Block, Fars Zone
Total Production Objectives Cost 100 Estimation Exploration and Development million USD
Project Exploration Client Management
47 Oil & Gas Total project / 32
INVESTMENT Oil & Gas Exploration Blocks OPPORTUNITIES Projects in National Iranian Oil Company
4 Fino Block, Fars Zone
Total Production Objectives Cost 100 Estimation Exploration and Development million USD
Project Exploration Client Management
48 Oil & Gas Total project / 33
INVESTMENT Oil & Gas Exploration Blocks OPPORTUNITIES Projects in National Iranian Oil Company
5 Kelato Block, Fars Zone
Total Production Objectives Cost 100 Estimation Exploration and Development million USD
Project Exploration Client Management
49 Oil & Gas Total project / 34
INVESTMENT Oil & Gas Exploration Blocks OPPORTUNITIES Projects in National Iranian Oil Company
6 Dahno Block, Fars Zone
Total Production Objectives Cost 100 Estimation Exploration and Development million USD
Project Exploration Client Management
50 Oil & Gas Total project / 35
INVESTMENT Oil & Gas Exploration Blocks OPPORTUNITIES Projects in National Iranian Oil Company
7 Lar Block, Fars Zone
Total Production Objectives Cost 100 Estimation Exploration and Development million USD
Project Exploration Client Management
51 Oil & Gas Total project / 36
INVESTMENT Oil & Gas Exploration Blocks OPPORTUNITIES Projects in National Iranian Oil Company
8 Jahrom Block, Fars Zone
Total Production Objectives Cost 100 Estimation Exploration and Development million USD
Project Exploration Client Management
52 Oil & Gas Total project / 37
INVESTMENT Oil & Gas Exploration Blocks OPPORTUNITIES Projects in National Iranian Oil Company
9 Kazeroun Block, Fars Zone
Total Production Objectives Cost 100 Estimation Exploration and Development million USD
Project Exploration Client Management
53 Oil & Gas Total project / 38
INVESTMENT Oil & Gas Exploration Blocks OPPORTUNITIES Projects in National Iranian Oil Company
10 Taybad Block, Tabas Zone
Total Production Objectives Cost 100 Estimation Exploration and Development million USD
Project Exploration Client Management
54 Oil & Gas Total project / 39
INVESTMENT Oil & Gas Exploration Blocks OPPORTUNITIES Projects in National Iranian Oil Company
11 Shiraz Block, Fars Zone
Total Production Objectives Cost 100 Estimation Exploration and Development million USD
Project Exploration Client Management
55 Oil & Gas Total project / 40
INVESTMENT Oil & Gas Exploration Blocks OPPORTUNITIES Projects in National Iranian Oil Company
12 Sepidan Block, Fars Zone
Total Production Objectives Cost 100 Estimation Exploration and Development million USD
Project Exploration Client Management
56 Oil & Gas Total project / 41
INVESTMENT Oil & Gas Exploration Blocks OPPORTUNITIES Projects in National Iranian Oil Company
13 Sina Block, Persian Gulf Zone
Total Production Objectives Cost 250 Estimation Exploration and Development million USD
Project Exploration Client Management
57 Oil & Gas Total project / 42
INVESTMENT Oil & Gas Exploration Blocks OPPORTUNITIES Projects in National Iranian Oil Company
14 Kermanshah Block, Lorestan Zone
Total Production Objectives Cost 100 Estimation Exploration and Development million USD
Project Exploration Client Management
58 Oil & Gas Total project / 43
INVESTMENT Oil & Gas Exploration Blocks OPPORTUNITIES Projects in National Iranian Oil Company
15 Drilling, seismic, construction of roads and cellar (during the 5th FYDP)
Total Production Objectives Cost 10 0 Estimation Exploration objectives of oil and million USD gas fields
Project Exploration Client Management
59 INVESTMENT Gas Gathering, Compressor & OPPORTUNITIES Injection Stations Projects in National Iranian Oil Company 1 Upgrading of machinery of Gachsaran compressor station - 86306 2 Construction of pipelines and extended gas injection station in Koupal field (phase 1)- 85405 23 Gathering of excess natural gas of stages 2 and 3 of Gachsaran 4 - 84306 4 Gathering of excess natural gas of stage 2 of Maroun stations 1, 2 & 6 - 88312 5 Substitution of old Ingersolrand compressors and electrical rotator in Ahwaz and Maroun gas compressor stations - 88310 6 Construction of and compressor station in Varavi gas field 67 Construction of and compressor station in Kangan gas field 8 Construction of liquid separation plant in Tabnak gas field 9 Construction of associated gas gathering station in Rag-Sefid field (phase 1) 10 Construction of gas compressor station in Homa gas field 11 Gathering gases of Haft Shahidan production unit - 86316 12 Gas injection in Karanj field (phase 3) Gas Total project / 44
INVESTMENT Gas Gathering, Compressor & OPPORTUNITIES Injection Stations Projects in National Iranian Oil Company
1 Upgrading of machinery of Gachsaran compressor station - 86306
Total Production Objectives Cost 351 Estimation Just project finance billion Rials National Project Iranian South Client Oil Company
63 Gas Total project / 45
INVESTMENT Gas Gathering, Compressor & OPPORTUNITIES Injection Stations Projects in National Iranian Oil Company
2 Construction of pipelines and extended gas injection station in Koupal field- 85405
Total Production Objectives Cost 663.4 Estimation Just project finance billion Rials National Project Iranian South Client Oil Company
64 Gas Total project / 46
INVESTMENT Gas Gathering, Compressor & OPPORTUNITIES Injection Stations Projects in National Iranian Oil Company
3 Gathering of excess natural gas of stages 2 and 3 of Gachsaran 4 - 84306
Total Production Objectives Cost 217 Estimation billion Rials To prevent flaring of 20 million cfd associated gases of Gachsaran compressor station National Project Iranian South Client Oil Company
65 Gas Total project / 47
INVESTMENT Gas Gathering, Compressor & OPPORTUNITIES Injection Stations Projects in National Iranian Oil Company
4 Gathering of excess natural gas of stage 2 of Maroun stations 1, 2 & 6 - 88312
Total Production Objectives Cost 605.6 Estimation billion Rials To prevent flaring of 54 million cfd associated gases National Project Iranian South Client Oil Company
66 Gas Total project / 48
INVESTMENT Gas Gathering, Compressor & OPPORTUNITIES Injection Stations Projects in National Iranian Oil Company
5 Substitution of old Ingersolrand compressors and electrical rotator in Ahwaz and Maroun gas compressor stations
Total 241.7 Cost Estimation billion Rials
National Project Iranian South Client Oil Company
67 Gas Total project / 49
INVESTMENT Gas Gathering, Compressor & OPPORTUNITIES Injection Stations Projects in National Iranian Oil Company
6 Construction of compressor station in Varavi gas field
Total 64.672 + 465465 Production Objectives Cost Estimation million usd million Rials For maintaining gas production at 10 million cubic meters per day IranianCentral Project Oil Fields Client Company
68 Gas Total project / 50
INVESTMENT Gas Gathering, Compressor & OPPORTUNITIES Injection Stations Projects in National Iranian Oil Company
7 Construction of compressor station in Kangan gas field
Total 309+1040 Production Objectives Cost Estimation million USD billion Rials For maintaining gas production at 68 million cubic meters per day Iranian Central Project Oil Fields Client Company
69 Gas Total project / 51
INVESTMENT Gas Gathering, Compressor & OPPORTUNITIES Injection Stations Projects in National Iranian Oil Company
8 Construction of liquid separation plant in Tabnak gas field
Total Cost 61.15+116.9 Estimation million USD billion Rials
Iranian Central Project Oil Fields Client Company
70 Gas Total project / 52
INVESTMENT Gas Gathering, Compressor & OPPORTUNITIES Injection Stations Projects in National Iranian Oil Company
9 Construction of associated gas gathering station in Rag-Sefid field (phase 1)
Total Production Objectives Cost 232.5 Delivering 180 million cfd for NGL Estimation billion Rials 2400 National Project Iranian South Client Oil Company
71 Gas Total project / 53
INVESTMENT Gas Gathering, Compressor & OPPORTUNITIES Injection Stations Projects in National Iranian Oil Company
10 Construction of gas compressor station in Homa gas field
Total Production Objectives Cost 128+704.5 For maintaining gas production at Estimation million USD billion Rials 10 million cubic meters per day Iranian Central Project Oil Fields Client Company
72 Gas Total project / 54
INVESTMENT Gas Gathering, Compressor & OPPORTUNITIES Injection Stations Projects in National Iranian Oil Company
11 Gathering gases of Haft Shahidan production unit - 86316
Total Cost 430.8 Estimation million USD National Project Iranian South Client Oil Company
73 Gas Total project / 55
INVESTMENT Gas Gathering, Compressor & OPPORTUNITIES Injection Stations Projects in National Iranian Oil Company
12 Gas injection in Karanj field(phase 3)
Total Cost 191 Estimation million USD National Project Iranian South Client Company
74
Construction, Development & INVESTMENT OPPORTUNITIES Commissioning of Desalting Plants in National Iranian Oil Company
1 Increasing the capacity of Ahwaz 2 Bangestan desalting plant - 88221 2 Equiping desalting plant of Rag-Sefid 1 - 88220 3 Construction of desalting plant of Koupal field and completing surface facilities Oil & Gas Total project / 56
Construction, Development & INVESTMENT OPPORTUNITIES Commissioning of Desalting Plants in National Iranian Oil Company
1 Increasing the capacity of Ahwaz 2 Bangestan desalting plant - 88221
Total Production Objectives Cost 169 Estimation With a capacity of 55,000 bpd, billion Rials Just project finance National Project Iranian South Client Oil Company
77 Oil & Gas Total project / 57
Construction, Development & INVESTMENT OPPORTUNITIES Commissioning of Desalting Plants in National Iranian Oil Company
2 Equiping desalting plant of Rag-Sefid 1 - 88220
Total Cost 193.5 Estimation billion Rials National Project Iranian South Client Oil Company
78 Oil & Gas Total project / 58
Construction, Development & INVESTMENT OPPORTUNITIES Commissioning of Desalting Plants in National Iranian Oil Company
3 Construction of desalting plant of Koupal field and completing processing facilities
Total Production Objectives Cost 27.8+553.2 Estimation million USD billion Rials With a capacity of 95,000 bpd
National Project Iranian South Client Oil Company
79 Construction of Gas Production INVESTMENT OPPORTUNITIES Facilities, New Gas and NGL Plants in National Iranian Oil Company 1 Construction of Karoun Bangestan NGL 1700, Masjed Soleiman - 87308 2 Construction of Pazanan Khami gas and NGL plant 1900, Aghajari - 83308 3 Construction of gas and NGL plant 2400 - 90306 4 Substitution of 5 turbo compressors in gas and NGL plants 900 and 1000 Gas Total project / 59
Construction of Gas Production INVESTMENT OPPORTUNITIES Facilities, New Gas and NGL Plants in National Iranian Oil Company
1 Construction of Karoun Bangestan gas and NGL plant 1700, Masjed Soleiman - 87308
Total Production Objectives Cost 3476.8 Production of 159 million cfd Estimation billion Rials natural gas for injection to southern oil fields (146 million cfd National sweet gas) Project Iranian South Client Oil Company
82 Gas Total project / 60
Construction of Gas Production INVESTMENT OPPORTUNITIES Facilities, New Gas and NGL Plants in National Iranian Oil Company
2 Construction of Pazanan Khami gas and NGL plant 1900, Aghajari - 83308
Total Production Objectives Cost 1388.9 Estimation 11,180 bpd of ethane for billion Rials petrochemical delivery, 19,730 bpd of naphtha, 152.2 million cfpd of National light gas, and 10.11 million cfpd of Project Iranian South acid gas Client Oil Company
83 Gas Total project / 61
Construction of Gas Production INVESTMENT OPPORTUNITIES Facilities, New Gas and NGL Plants in National Iranian Oil Company
3 Construction of gas and NGL plant 2400 - 90306
Total Production Objectives Cost 2701 Estimation Capacity:180 million cfpd of feed billion Rials gas National Project Iranian South Client Oil Company
84 Gas Total project / 62
Construction of Gas Production INVESTMENT OPPORTUNITIES Facilities, New Gas and NGL Plants in National Iranian Oil Company
4 Substitution of 5 turbo compressors in the gas and NGL plants 900 and 1000
Total Cost 1211 Estimation billion Rials National Project Iranian South Client Oil Company
85 Aghajari Production Optimization and INVESTMENT OPPORTUNITIES Surface Facilities Renovation (POSFR) in National Iranian Oil Company 1 Construction of gas and NGL plant 1800 in Aghajari - 90303 2 Construction of CFU 100 - 90304 3 Construction of processing facilities of Aghajari field - 90202 4 Construction of associated gases gathering station in Aghajari field - 90302 Oil & Gas Total project / 63
Aghajari Production Optimization and INVESTMENT OPPORTUNITIES Surface Facilities Renovation (POSFR) in National Iranian Oil Company
1 Construction of gas and NGL plant 1800 in Aghajari - 90303
Total Cost 202+686 Estimation million USD billion Rials
National Project Iranian South Client Oil Company
88 Oil & Gas Total project / 64
Aghajari Production Optimization and INVESTMENT OPPORTUNITIES Surface Facilities Renovation (POSFR) in National Iranian Oil Company
2 Construction of CFU 100 - 90304
Total Cost 127.3 + 617.7 Estimation million USD billion Rials
National Project Iranian South Client Oil Company
89 Oil & Gas Total project / 65
Aghajari Production Optimization and INVESTMENT OPPORTUNITIES Surface Facilities Renovation (POSFR) in National Iranian Oil Company
3 Construction of processing facilities of Aghajari field- 90202
Total Cost 152.8+3405 Estimation million USD billion Rials
National Project Iranian South Client Oil Company
90 Oil & Gas Total project / 66
Aghajari Production Optimization and INVESTMENT OPPORTUNITIES Surface Facilities Renovation (POSFR) in National Iranian Oil Company
4 Construction of associated gases gathering station in Aghajari field- 90302
Total Cost 59.15+870 Estimation million USD billion Rials
National Project Iranian South Client Oil Company
91 INVESTMENT Crude Oil & Gas Export Pipelines OPPORTUNITIES and Pump Stations in National Iranian Oil Company 1 Construction of pump station (shared for light and heavy oil) in Karoun West and Omidiyeh; and Bahregan metering station 2 Construction of North Dezful crude oil pipeline and Azar and Changuleh oil fields pipelines 3 Construction of the new Golkhari-Gachsaran pipeline 4 Construction of 42", 48", 42" crude oil export pipline in way of Ahwaz, Omidiyeh, Goureh, Genaveh Oil Total project / 67
INVESTMENT Crude Oil & Gas Export Pipelines OPPORTUNITIES and Pump Stations in National Iranian Oil Company 1 Construction of pump station (shared for light and heavy oil) in Karoun West and Omidiyeh; and Bahregan metering station
Total Production Objectives Cost 114 Estimation Transfer of 1 million barrels of crude million USD oil from Azadegan, Yadavaran, Band- Karkheh and Azar oil fields; ( light oil is Petroleum transferred to Gonaveh and heavy oil to Project Engineering and Bahregansar) Client Development Company 94 Oil Total project / 68
INVESTMENT Crude Oil & Gas Export Pipelines OPPORTUNITIES and Pump Stations in National Iranian Oil Company
2 Construction of North Dezful crude oil pipeline and Azar and Changuleh oil fields pipelines
Total 12.19+314 Production Objectives Cost Construction of 55 kilometers 20” pipeline for Estimation million USD billion Rials transferring Cheshmeh Khosh - Sabzab crude oil; supply of two pumps (30,000 bpd) for Dehloran production unit; construction of 16” pipeline with a length of 58 km for transferring Dehloran’s crude Iranian Central oil to Cheshmeh Khosh; construction of facilities for Project Oil Fields receiving and pumping Azar oil field’s crude oil in Client Cheshmeh Khosh with a capacity of 65,000 bpd; Company Increasing the capacity of phase 2 of receiving and pumping oil in Sabzab pump station; and Azar oil field storage capacity for three days 95 Oil Total project / 69
INVESTMENT Crude Oil & Gas Export Pipelines OPPORTUNITIES and Pump Stations in National Iranian Oil Company
3 Construction of the new Golkhari-Gachsaran pipeline
Total Cost 93 Estimation billion Rials National Project Iranian South Client Oil Company
96 Oil Total project / 70
INVESTMENT Crude Oil & Gas Export Pipelines OPPORTUNITIES and Pump Stations in National Iranian Oil Company
4 Construction of 42”, 48”, 42” crude oil export pipline in way of Ahwaz, Omidiyeh, Goureh, Genaveh
Total Cost 3531 Estimation billion Rials
National Project Iranian South Client Oil Company
97 Construction and Completion of INVESTMENT OPPORTUNITIES Crude Oil Storage Tanks and pipelines in National Iranian Oil Company 1 Metal storage tanks of Kharg Island 2 Cathodic protection for crude oil storage tanks of Kharg Oil Terminal 3 Omidiyeh concrete storage tanks 4 Construction of storage tanks and underground storage, delivery and export of crude oil (oil swap) in Jask
4/1 Construction of Neka storage tanks 4/2 Construction of Neka-Jask pipeline 4/3 Construction of Goureh-Jask pipeline 5 Construction of storage tanks and underground storage facilities 6 Construction of four tanks in North Oil Terminal Oil Total project / 71
Construction and Completion of INVESTMENT OPPORTUNITIES Crude Oil Storage Tanks and pipelines in National Iranian Oil Company
1 Metal storage tanks of Kharg Island
Total Production Objectives Cost 700 Estimation Construction of a storage tank billion Rials with a capacity of 4 million barrels, just project finance Iranian Oil Project Terminals Client Company
100 Oil Total project / 72
Construction and Completion of INVESTMENT OPPORTUNITIES Crude Oil Storage Tanks and pipelines in National Iranian Oil Company
2 Cathodic protection for crude oil storage tanks of Kharg Oil Terminal
Total Production Objectives Cost 15.8 Estimation Cathodic protection for storage tanks million USD with a capacity of 24 million barrels and related pipelines, just project Iranian Oil finance Project Terminals Client Company
101 Oil Total project / 73
Construction and Completion of INVESTMENT OPPORTUNITIES Crude Oil Storage Tanks and pipelines in National Iranian Oil Company
3 Omidiyeh concrete storage tanks
Total Production Objectives Cost 45 Estimation Completion of unfinished operations for million USD construction of 4 storage tanks with a capacity of 3 million barrels, just project Petroleum finance Project Engineering and Client Development Company 102 Oil Total project / 74
Construction and Completion of INVESTMENT OPPORTUNITIES Crude Oil Storage Tanks and pipelines in National Iranian Oil Company
4 Construction of storage tanks and underground storage, delivery and export of crude oil (oil swap) in Jask
Iranian Oil Terminals Production Objectives Project Company Client (International Affairs Construction of a terminal for Management) export and transfer of crude oil, and increasing storage capacity
103 Oil Total project / 75
Construction and Completion of INVESTMENT OPPORTUNITIES Crude Oil Storage Tanks and pipelines in National Iranian Oil Company
4/1 Construction of Neka storage tanks
Total Production Objectives Cost 500 Estimation With a storage capacity of 5 million USD million barrels Iranian Oil Project Terminals Client Company
104 Oil Total project / 76
Construction and Completion of INVESTMENT OPPORTUNITIES Crude Oil Storage Tanks and pipelines in National Iranian Oil Company
4/2 Construction of Neka-Jask pipeline
National Iranian Production Objectives Project Oil Refining and Client Distribution Company (Iranian Oil Terminals Swap and transportation of the Middle Company) Asia crude oil
105 Oil Total project / 77
Construction and Completion of INVESTMENT OPPORTUNITIES Crude Oil Storage Tanks and pipelines in National Iranian Oil Company
4/3 Construction of Goureh-Jask pipeline
National Iranian Oil Refining and Production Objectives Project Distribution Company Client (Iranian Oil Terminals Swap and transportation of the Middle Company) Asia’s crude oil
106 Oil Total project / 78
Construction and Completion of INVESTMENT OPPORTUNITIES Crude Oil Storage Tanks and pipelines in National Iranian Oil Company
5 Construction of storage tanks and underground storage facilities
Total Production Objectives Cost study of phase 1 has done as Estimation research funds Passive defense of storage facilities
Iranian Oil Terminals Project Company Client (International Affairs Management)
107 Oil Total project / 79
Construction and Completion of INVESTMENT OPPORTUNITIES Crude Oil Storage Tanks and pipelines in National Iranian Oil Company
6 Construction of four tanks in North Oil Terminal
Total Production Objectives Cost 220 Estimation Increasing storage capacity (600,000 billion Rials barrels) for swap
Iranian Oil Project Terminals Client Company
108
Gas Liquefaction and Sweetening INVESTMENT OPPORTUNITIES Projects (LNG Production) in National Iranian Oil Company 1 Construction of the liquefaction unit in Iran LNG Plant; related to South Pars gas field development plan (shared field) 2 Construction of the sweetening unit in Iran LNG Plant; related to South Pars gas field development plan (shared field) Gas Total project / 80
Gas Liquefaction and Sweetening INVESTMENT OPPORTUNITIES Projects (LNG Production) in National Iranian Oil Company
1 Construction of the liquefaction unit in Iran LNG Plant; related to South Pars gas field development plan(shared field)
Total Production Objectives Cost 1.1 Estimation 10 million tons LNG per year billion USD
Iran Liquefied Project Natural Gas Client Company
112 Gas Total project / 81
Gas Liquefaction and Sweetening INVESTMENT OPPORTUNITIES Projects (LNG Production) in National Iranian Oil Company
2 Construction of the sweetening unit in Iran LNG Plant; related to South Pars gas field development plan(shared field)
Total Production Objectives Cost 540 Estimation 10 million tons LNG per year million Euro Iran Liquefied Project Natural Gas Client Company
113 INVESTMENT Other Projects OPPORTUNITIES in National Iranian Oil Company 1 Construction of sewage system, pumping and centralized water sewage plant in Pars 1 Special Zone
2 Construction of second runway of Persian Gulf International Airport 3 Construction of the servicing port of Site 2 of Pars-Kangan 4 Improvement of fuel export and receiving system (bunkering) in Kharg Island 5 Construction of new crude oil pump stations 6 Supply of a drilling rig (through BOO contract) 7 3D Seismic pinaging from Gachsaran, Chaligar and Garangan and karoun fields 8 Equipping delivery spots with Automatic smart metering systems 9 3D Seismic from Sarkan and Maleh kouh fields Oil & Gas Total project / 82
INVESTMENT Other Projects OPPORTUNITIES in National Iranian Oil Company
1 Construction of sewage system, pumping and centralized sewage plant in Pars 1 Special Zone
Total Production Objectives Cost 130 Estimation Gathering and treatment of both million USD industrial and non-industrial wastewater of downstream industries and service Pars Special sector of Pars Special Zone Project Economic Client Energy Zone
116 Oil & Gas Total project / 83
INVESTMENT Other Projects OPPORTUNITIES in National Iranian Oil Company
2 Construction of second runway of Persian Gulf International Airport
Total Cost 40 Estimation million USD Pars Special Project Economic Client Energy Zone
117 Oil & Gas Total project / 84
INVESTMENT Other Projects OPPORTUNITIES in National Iranian Oil Company
3 Construction of the servicing port of Site 2 of Pars-Kangan
Total Production Objectives Cost 650 Estimation Includes marine transportation, service million USD support facilities for development phases of South Pars (especially new phases)
Project Pars Oil & Gas Client Company
118 Oil & Gas Total project / 85
INVESTMENT Other Projects OPPORTUNITIES in National Iranian Oil Company
4 Improvement of fuel export and receiving system (bunkering) in Kharg Island
Total Production Objectives Cost 8.9 Estimation Increasing fuel supply for ships million USD Iranian Oil Project Terminals Client Company
119 Oil & Gas Total project / 86
INVESTMENT Other Projects OPPORTUNITIES in National Iranian Oil Company
5 Construction of new crude oil pump stations
Total Production Objectives Cost 2257 Estimation Three pump stations of Ahwaz- billion Rials Omidiyeh-Goureh National Project Iranian South Client Oil Company
120 Oil & Gas Total project / 87
INVESTMENT Other Projects OPPORTUNITIES in National Iranian Oil Company
6 Supply of a drilling rig (offshore rig is preferred) after signing up a contract with investors for hiring a rig through BOO contracts (preference is given to drilling operations aimed at maintaining production of production companies and drilling operations in exploration and appraisal wells) onshore rigs offshore rigs Total Production Objectives Cost 25 15 0 Estimation Executing drilling projects million USD million USD (development, exploration, appraisal, workover) Production and Project Client development companies
121 Oil & Gas Total project / 88
INVESTMENT Other Projects OPPORTUNITIES in National Iranian Oil Company
7 3D seismic of Gachsaran, Chelinger, Garangan and Karoun fields
Total Production Objectives Cost 60+380 2 Estimation million USD billion Rials 3D seismic in 2000 km
National Project Iranian South Client Oil Company
122 Oil & Gas Total project / 89
INVESTMENT Other Projects OPPORTUNITIES in National Iranian Oil Company
8 Equipping delivery spots with automatic smart metering systems
Total Cost 350 Estimation million Euro Petroleum Project Engineering and Client Development Company 123 Oil & Gas Total project / 90
INVESTMENT Other Projects OPPORTUNITIES in National Iranian Oil Company
9 3D seismic from Sarkan and Maleh kouh fields
Total Cost 82 Estimation million Euro
Iranian Central Project Oil Fields Client Company
124
INVESTMENT Power Supply Projects OPPORTUNITIES (Through BOO Contracts) in National Iranian Oil Company 1 Construction of a 492-megawatt power plant for oil fields of Karoun West Zone (Azadegan,Darkhovein, Yadavaran and Jofeir) 2 Construction of three combined cycle power plants for new pump stations in Ahwaz, Omidiyeh and Goureh Oil & Gas Total project / 91
INVESTMENT Power Supply Projects OPPORTUNITIES (Through BOO Contracts) in National Iranian Oil Company
1 Construction of a 492-megawatt power plant for oil fields ofKaroun West Zone (Azadegan, Darkhovein, Yadavaran and Jofeir)
Total Cost 320 Estimation million Euro Petroleum Project Engineering and Client Development Company 128 Oil & Gas Total project / 92
INVESTMENT Power Supply Projects OPPORTUNITIES (Through BOO Contracts) in National Iranian Oil Company
2 Construction of three combined cycle power plants for new pump stations in Ahwaz, Omidiyeh and Goureh
Total Cost Estimation
National Project Iranian South Client Oil Company
129 INVESTMENT Operational Tugboats and OPPORTUNITIES Marine Vessels Supply in National Iranian Oil Company
1 Supply of a special marine vessel for LNG transportation after signing up LNG transportation long term contracts with investors - related to South Pars gas field development (shared field) and construction of Iran LNG Plant 2 Supply of six operational five-extenguisher tugboats 3 Buying 2 marine ambulances Oil & Gas Total project / 93
INVESTMENT Operational Tugboats and OPPORTUNITIES Marine Vessels Supply in National Iranian Oil Company 1 Supply of a special marine vessel for LNG transportation after signing up LNG transportation long term contracts with investors - related to South Pars gas field development (shared field) and construction of Iran LNG Plant
Iran Liquefied Production Objectives Project Natural Gas Client Company 7 tankers for shipping LNG produced by Iran LNG Plant
131 Oil & Gas Total project / 94
INVESTMENT Operational Tugboats and OPPORTUNITIES Marine Vessels Supply in National Iranian Oil Company
2 Supply of six operational five- extenguisher tugboats
Total Production Objectives Cost 90 Estimation 7 tankers for shipping LNG million USD produced by Iran LNG Plant Iranian Oil Project Terminals Client Company &
132 Oil & Gas Total project / 95
INVESTMENT Operational Tugboats and OPPORTUNITIES Marine Vessels Supply in National Iranian Oil Company
3 Buying 2 Marine ambulances
Total Cost 36 Estimation million USD
Iranian Oil Khazar Oil and Project Terminals Gas Exploration Client Company & Company
133 INVESTMENT Main Projects Under OPPORTUNITIES Investigation in National Iranian Oil Company 1 Development of Dalan/Kangan gas reservoir in Reshadat field (shared field) 2 Development of Dalan/Kangan gas reservoir in Balal field, eastern cape of South Pars, (shared field) 3 Forouzan oil field development phase 2, (shared field) 4 Namak Kangan gas field development, Bushehr 5 Development of Ghar gas reservoir in Bahregansar field 6 Development of Salakh gas field, Qeshm 7 Shakheh oil field development 8 Vizenhar oil field development 9 Alborz oil field development, Qom 10 Development of gas Jurassic horizon of Azadegan oil field 11 Development of gas Jurassic horizon of Darkhovein oil field Oil & Gas Total project / 96
INVESTMENT Main Projects Under OPPORTUNITIES Investigation in National Iranian Oil Company
1 Development of Dalan/Kangan gas reservoir in Reshadat field(shared field)
Total Production Objectives Cost 120 0 Estimation Possibility of 2.3 trillion cubic feet of million USD natural gas (shared with Qatar)
Iranian Project Offshore Oil Client Company
136 Oil & Gas Total project / 97
INVESTMENT Main Projects Under OPPORTUNITIES Investigation in National Iranian Oil Company
2 Development of Dalan/Kangan gas reservoir in Balal field, eastern cape of South Pars, (shared field)
Total Production Objectives Cost 720 -1200 Estimation Equivalent to 3.31 times of a standard million USD phase of South Pars (shared with Qatar)
Iranian Project Offshore Oil Client Company
137 Oil & Gas Total project / 98
INVESTMENT Main Projects Under OPPORTUNITIES Investigation in National Iranian Oil Company
3 Forouzan oil field development(phase 2) (shared field)
Total Production Objectives Cost 800 Estimation 250 million cfpd of natural gas and million USD 65,000 bpd of crude oil (shared with Saudi Arabia) Iranian Project Offshore Oil Client Company
138 Oil & Gas Total project / 99
INVESTMENT Main Projects Under OPPORTUNITIES Investigation in National Iranian Oil Company
4 Namak Kangan gas field development, Bushehr
Total Production Objectives Cost 40 Estimation 1.5 million cubic meters per day of million USD natural gas
Iranian Central Project Oil Fields Client Company
139 Oil & Gas Total project / 100
INVESTMENT Main Projects Under OPPORTUNITIES Investigation in National Iranian Oil Company
5 Development of Ghar gas reservoir in Bahregansar field
Total Production Objectives Cost 250 Estimation 0.52 billion cfpd million USD
Iranian Project Offshore Oil Client Company
140 Oil & Gas Total project / 101
INVESTMENT Main Projects Under OPPORTUNITIES Investigation in National Iranian Oil Company
6 Development of Salakh gas field, Qeshm
Total Production Objectives Cost 225 Estimation 3.3 million cubic meters of natural gas million USD
Iranian Central Project Oil Fields Client Company
141 Oil & Gas Total project / 102
INVESTMENT Main Projects Under OPPORTUNITIES Investigation in National Iranian Oil Company
7 Shakheh oil field development
Total Production Objectives Cost 15.6+180 Estimation million USD billion Rials 5,000 bpd
Iranian Central Project Oil Fields Client Company
142 Oil & Gas Total project / 103
INVESTMENT Main Projects Under OPPORTUNITIES Investigation in National Iranian Oil Company
8 Vizenhar oil field development
Total Production Objectives Cost 14 +114 Increasing production to 5,000 bpd Estimation million USD billion Rials
Iranian Central Project Oil Fields Client Company
143 Oil & Gas Total project / 104
INVESTMENT Main Projects Under OPPORTUNITIES Investigation in National Iranian Oil Company
9 Alborz oil field development, Qom
Total Production Objectives Cost 55+123 Estimation million USD billion Rials 2,000 bpd
Iranian Central Project Oil Fields Client Company
144 Oil & Gas Total project / 105
INVESTMENT Main Projects Under OPPORTUNITIES Investigation in National Iranian Oil Company
10 Development of gas Jurassic horizon of Azadegan oil field
Total Cost 60 Estimation million USD
Arvandan Project Oil & Gas Client Company
145 Oil & Gas Total project / 106
INVESTMENT Main Projects Under OPPORTUNITIES Investigation in National Iranian Oil Company
11 Development of gas Jurassic horizon of Darkhovein oil field
Total Cost 60 Estimation million USD
Arvandan Project Oil & Gas Client Company
146