Quick viewing(Text Mode)

City of Surprise

City of Surprise

CITY OF SURPRISE

SPA-1 Water Reclamation Facility Basin #2 Floating Cover

Technical Specifications Volume 2 of 3

March 2015

Prepared by

Hilts Consulting Group, Inc. 7835 Westpark Dr. Riverside, CA 92506

and

Brown and Caldwell 201 East Washington Street, Suite 500 Phoenix, Arizona 85004

SECTION 01015

CONTRACTOR'S USE OF PREMISES

The existing Water Reclamation Facility is currently and continuously receiving and treating wastewater, and those functions shall not be interrupted except as specified herein. Basin #1 shall remain in service during the execution of this contract. The Contractor shall coordinate the work to avoid any interference with normal operation of plant equipment and processes.

The Owner's operating personnel will be responsible for operating the existing treatment plant throughout the execution of this contract. Facilities and in the treatment plant must be available to plant personnel at all times for use, maintenance, and repair. If it is necessary in the course of operating the plant, for the Contractor to move his equipment, materials, or any material included in the work, he shall do so promptly and place that equipment or material in an area which does not interfere with the plant operation. The Contractor shall not adjust or operate serviceable or functioning equipment or systems except as specifically required by this contract.

The existing treatment plant will remain in operation throughout the execution of this contract. The Contractor shall schedule and conduct his work to minimize necessary shutdowns and interference with normal plant operations and maintenance.

The Contractor shall notify the Construction Manager 1 week in advance for requested outages or tie-in to existing facilities. The Contractor shall be responsible for providing whatever temporary piping, pumping, power, and control facilities as are required to maintain continuous plant operation and complete treatment except as otherwise specified. The integrity of existing plant utilities shall be maintained by the Contractor at all times.

**END OF SECTION**

01015-1

SECTION 01050

SURVEY INFORMATION

The Owner has established reference benchmarks and baselines as shown on the Drawings. From the information provided, the Contractor shall develop and make such additional surveys as are needed for construction, such as control lines, slope stakes, batter boards, stakes for pipe locations and other working points, lines, and elevations. Survey work shall be performed under the supervision of a licensed land surveyor or registered civil engineer in the State of Arizona. Contractor shall reestablish reference benchmarks and survey control monuments destroyed by his operations at no cost to the Owner.

**END OF SECTION**

01050-1

SECTION 01060

SAFETY AND HEALTH

PART 1--GENERAL

1.01 GENERAL

Portions of the existing plant are exposed to wastewaters of varying degrees of treatment. The Contractor certifies that he is experienced and qualified to anticipate and meet the safety and health requirements of this project.

Workmen involved in the removal, renovation, or installation of equipment within the treatment plant may be exposed to disease-producing organisms in wastewater. The Contractor shall require his personnel to observe proper hygienic precautions.

Solvents, gasoline, and other hazardous materials enter the plant with incoming sewage, and, therefore, certain areas are hazardous to open flame, sparks, or unventilated occupancy. The Contractor shall take measures to assure his personnel observe proper safety precautions when working in these areas.

1.02 SAFETY AND HEALTH REGULATIONS

The Contractor shall comply with Safety and Health Regulations for Construction, promulgated by the Secretary of Labor under Section 107 of the Contract Work Hours and Safety Standards Act, as set forth in Title 29, C.F.R. Copies of these regulations may be obtained from Labor Building, 14th and Constitution Avenue N.W., Washington, DC 20013.

The Contractor shall also comply with the provisions of the Federal Occupational Safety and Health Act, as amended.

1.03 CONTRATOR REQUIREMENTS

A. RESPONSIBILITIES:

Any Contractor and Subcontractor working on the Owner’s property is responsible for the safety and health training of their respective employees and holding to a safety standard that is equal to or more stringent than the City of Surprise public works safety program. They are also responsible for reporting any incident, spill, or accident immediately.

B. PROCEDURE:

Before the start of any work, the Construction Manager will meet with the Contractor to review and document needs related to the work including Maintenance of Plant Operations

01060-1

(MOPO), safety, hours of access, trash collection and removal, dust control, reclaimed water usage, hazardous chemicals, and incident reporting.

1.04 SUBMITTALS

The Contractor shall submit a Health and Safety Plan at the Pre-Construction conference in accordance with Section 01300.

PART 2--NOT USED

PART 3--NOT USED

**END OF SECTION**

01060-2

SECTION 01071

STANDARD REFERENCES

The following documents referenced in the documents are available for public viewing at the websites below:

City of Surprise Water and Wastewater Facility Guidelines http://www.surpriseaz.gov/index.aspx?NID=2711

City of Surprise Engineering Development Standards http://www.surpriseaz.gov/index.aspx?NID=1645

Wherever used in the project manual, the following abbreviations will have the meanings listed:

AA Aluminum Association Incorporated P.O. Box 753 Waldorf, MD 20604 AABC Associated Air Balance Council 1518 K Street N.W. Washington, DC 20005 AAMA American Architectural Manufacturers Association 1540 East Dundee Road, Suite 310 Palatine, IL 60067 AASHTO American Association of State Highway and Transportation Officials 444 North Capitol Street, N.W., Suite 249 Washington, DC 20001 ABMA American Bearing Manufacturers Association 1200 19th Street N.W., Suite 300 Washington, DC 20036 ACI American Concrete Institute 22400 West Seven Mile Road P.O. Box 19150, Redford Station Detroit, MI 48219 AEIC Association of Edison Illuminating Companies 600 North 18th Street P.O. Box 2641 Birmingham, AL 35291 AGA American Gas Association ATTN: Records 1515 Wilson Boulevard Arlington, VA 22209

01071-1

AGMA American Gear Manufacturer's Association, Inc. 1500 King Street, Suite 201 Alexandria, VA 22314 AHA American Hardboard Association 1210 West Northwest Highway Palatine, IL 60067 AISC American Institute of Steel Construction One East Wacker Drive, Suite 3100 Chicago, IL 60601 AISI American Iron and Steel Institute 1101 Seventeenth Street, NW, Suite 1300 Washington, DC 20036 AITC American Institute of Timber Construction 7012 South Revere Parkway, Suite 140 Englewood, CO 80112 ALSC American Lumber Standard Committee P.O. Box 210 Germantown, MD 20875 AMCA Air Movement and Control Association, Inc. 30 West University Drive Arlington Heights, IL 60004 ANSI American National Standards Institute 11 West 42nd Street, 13th Floor New York, NY 10036 APA American Plywood Association 7011 South 19th Street Tacoma, WA 98466 API American Petroleum Institute 1220 "L" Street N.W. Washington, DC 20005 ARI Air-Conditioning and Refrigeration Institute 4301 North Fairfax Drive, Suite 425 Arlington, VA 22203 ASCE American Society of Civil Engineers United Engineering Center 345 East 47th Street New York, NY 10017 ASCII American Standard Code for Information Interchange United States of America Standards Institute 10 East 40th Street New York, NY 10016 ASE Code American Standard Safety Code for Elevators, Dumbwaiter and Escalators American National Standards Institute 1430 Broadway New York, NY 10018

01071-2

ASHRAE American Society of Heating, Refrigeration and Air Conditioning Engineers, Inc. 1791 Tullie Circle, NE Atlanta, GA 30329 ASME American Society of Mechanical Engineers 345 East 47th Street New York, NY 10017 ASTM American Society for Testing and Materials 100 Barr Harbor Drive West Conshohocken, PA 19428 AWPA American Wood-Preservers' Association 9549 Old Fredrick Road Ellicott City, MD 21042 or P.O. Box 286 Woodstock, MD 21163-0286 AWS American Society 550 NW LeJeune Road P.O. Box 351040 Miami, FL 33135 AWWA American Water Works Association 6666 West Quincy Avenue Denver, CO 80235 BOCA Building Officials and Code Administrators, International, Inc. 4051 West Flossmoor Road Country Club Hills, IL 60478 CALTEST Materials Manual, State of California, Business and Transportation Agency Department of Public Works State of California, Department of Transportation 6002 Folsom Boulevard Sacramento, CA 95819 CALTRANS Standard Specifications, State of California, Department of Transportation State of California, Business and Transportation Agency P.O. Box 1499 Sacramento, CA 95807 CBM Certified Ballast Manufacturers 2120 Keith Building Cleveland, OH 44115 CMAA Crane Manufacturers Association of America, Inc. (Formerly called: Overhead Electrical Crane Institute) (OECI) 8720 Red Oak Boulevard, Suite 201 Charlotte, NC 28217 CRSI Concrete Reinforcing Steel Institute 933 N Plum Grove Road Schaumburg, IL 60173

01071-3

CSA Canadian Standards Association 178 Rexdale Boulevard Rexdale, Ontario, M9W IR3, Canada DEMA Diesel Engine Manufacturer's Association 30200 Detroit Road Cleveland, OH 44145 DHI Door and Hardware Institute 14170 Newbrook Drive Chantilly, VA 22021 DIS Division of Industrial Safety California Department of Industrial Relations 2422 Arden Way Sacramento, CA 95825 EEI Edison Electric Institute 90 Park Avenue New York, NY 10016 EIA Electronic Industries Association Order from: Global Engineering Documents 18201 McDurmott West Irvine, CA 92714 EJMA Expansion Joint Manufacturers Association 25 North Broadway Tarrytown, NY 10591 ESO Electrical Safety Orders California Administrative Code, Title 8, Chap. 4, Subarticle 5 Office of Procurement, Publications Section P.O. Box 20191 8141 Elder Creek Road Sacramento, CA 95820 FEDSPEC Federal Specifications General Services Administration Specification and Consumer Information Distribution Branch Washington Navy Yard, Bldg. 197 Washington, DC 20407 FEDSTDS Federal Standards (see FEDSPECS) FM Factory Mutual Engineering and Research Corporation 1151 Boston-Providence Turnpike P.O. Box 9102 Norwood, MA 02062 HEI Heat Exchange Institute 1300 Sumner Avenue Cleveland, OH 44115

01071-4

HI Hydraulic Institute 9 Sylvan Way, Suite 180 Parsippany, NJ 07054 HPVA Hardwood Plywood & Veneer Association 1825 Michael Faraday Drive P.O. Box 2789 Reston, VA 22090-2789 IAPMO International Association of Plumbing and Mechanical Officials 20001 Walnut Drive S Walnut, CA 91789 ICCO International Conference Council 3060 Saturn Street, Suite 100 Brea, California 92821 IBC International Building Code Published by ICC ICEA Insulated Cable Engineers Association P.O. Box 440 South Yarmouth, MA 02664 IEEE Institute of Electrical and Electronics Engineers 445 Hoes Lane P.O. Box 1331 Piscataway, NJ 08855 IES Illuminating Engineering Society of North America 120 Wall Street New York, NY 10017 ISA Instrument Society of America 67 Alexander Drive P.O. Box 12277 Research Triangle Park, NC 27709 JIC Joint Industrial Council 7901 West Park Drive McLean, VA 22101 MAG Maricopa Association of Governments 302 N. First Avenue, Suite 300 Phoenix, Arizona 85003 MFMA Metal Framing Manufacturers Association 401 N. Michigan Avenue Chicago, IL 60611 MILSPEC Military Specifications Naval Publications and Forms Center 5801 Tabor Avenue Philadelphia, PA 19120 MSS Manufacturers Standardization Society of the Valve & Fittings Industry, Inc. 127 Park Street, N.E. Vienna, VA 22180

01071-5

NAAMM National Association of Architectural Metal Manufacturers 11 South La Salle Street, Suite 1400 Chicago, IL 60603 NACE National Association of Corrosion Engineers 1440 South Creek Drive Houston, TX 77084 NBC National Building Code Published by BOCA NEC National Electric Code National Fire Protection Association One Batterymarch Park P.O. Box 9101 Quincy, MA 02269 NELMA Northeastern Lumber Manufacturers Association, Inc. P.O. Box 87A Cumberland Center, ME 04021 NEMA National Electrical Manufacturer's Association 2101 L Street, NW, Suite 300 Washington, DC 20037 NESC National Electric Safety Code American National Standards Institute 1430 Broadway New York, NY 10018 NFOR National Forest Products Association (Formerly National Lumber Manufacturer's Association) 1111 19 Street NW, Suite 700 Washington, DC 20036 NFPA National Fire Protection Association One Batterymarch Park P.O. Box 9101 Quincy, MA 02269 NHLA National Hardwood Lumber Association 6830 Raleigh LaGrange P.O. Box 34518 Memphis, TN 38184-0518 NSF National Sanitation Foundation 3475 Plymouth Road P.O. Box 130140 Ann Arbor, MI 48113 OSHA Occupational Safety and Health Act U.S. Department of Labor Occupational and Health Administration San Francisco Regional Office 450 Golden Gate Avenue, Box 36017 San Francisco, CA 94102

01071-6

PCI Precast/Prestressed Concrete Institute 175 West Jackson Blvd., Suite 1859 Chicago, IL 60604 PPIC The Plumbing & Piping Industry Council, Inc. 510 Shatto Place, Suite 402 Los Angeles, CA 90020 RIS Redwood Inspection Service California Redwood Association 405 Enfrente Dr., Suite 200 Novato, CA 94949 RMA Rubber Manufacturers Association 1400 K Street NW, Suite 900 Washington, DC 20005 SAE Society of Automotive Engineers, Inc. 400 Commonwealth Drive Warrendale, PA 15096 SAMA Scientific Apparatus Makers Association One Thomas Circle Washington, DC 20005 SBC Standard Building Code Published by SBCCI SBCCI Southern Building Code Congress International Inc. 900 Montclair Road Birmingham, AL 35213 SCMA Southern Cypress Manufacturers Association 400 Penn Center Boulevard, Suite 530 Pittsburg, PA 15235 SDI Steel Door Institute 30200 Detroit Road Cleveland, OH 44145 SMACNA and Air Conditioning Contractors National Association, Inc. P.O. Box 221230 Chantilly, VA 22021 SPI Society of the Plastics Industry, Inc. 1275 K Street NW, Suite 400 Washington, DC 20005 SPIB Southern Pine Inspection Bureau 4709 Scenic Highway Pensacola, FL 32504 SSPC Society for Protective Coatings 40 24th Street, 6th Floor Pittsburgh, PA 15222 SSPWC Standard Specifications for Public Works Construction Building News, Inc. 3055 Overland Avenue Los Angeles, CA 90034

01071-7

TEMA Tubular Exchanger Manufacturer's Association 25 North Broadway Tarrytown, NY 10591 TPI Truss Plate Institute 583 D'Onofrio Drive, Suite 200 Madison, WI 53719 UL Underwriters Laboratories Inc. 333 Pfingsten Road Northbrook, IL 60062 UMC Uniform Mechanical Code Published by ICBO UPC Uniform Plumbing Code Published by IAPMO USBR Bureau of Reclamation U.S. Department of Interior Engineering and Research Center Denver Federal Center, Building 67 Denver, CO 80225 WCLIB West Coast Lumber Inspection Bureau 6980 SW Varns St. P.O. Box 23145 Portland, OR 97223 WWPA Western Wood Products Association (Formerly called: West Coast Lumbermen's Association (WCLA)) Yeon Building 522 SW 5th Avenue Portland, OR 97204

**END OF SECTION**

01071-8

SECTION 01300

SUBMITTALS

1.0 GENERAL

Submittals covered by these requirements include manufacturers' information, shop drawings, test procedures, test results, samples, requests for substitutions, and miscellaneous work- related submittals. Submittals shall also include, but not be limited to, all product data sheets, product information, fabricated items, mechanical, electrical and electronic equipment and systems, materials, reinforcing steel, fabricated items, and piping and conduit details. The Contractor shall furnish all drawings, specifications, descriptive data, certificates, samples, tests, methods, schedules, and manufacturer's installation and other instructions as specifically required in the contract documents to demonstrate fully that the materials and equipment to be furnished and the methods of work comply with the provisions and intent of the contract documents.

2.0 CONTRACTOR'S RESPONSIBILITIES

The Contractor shall be responsible for the accuracy and completeness of the information contained in each submittal and shall assure that the material, equipment or method of work shall be as described in the submittal. The Contractor shall verify that all features of all products conform to the specified requirements. Submittal documents shall be clearly edited to indicate only those items, models, or series of equipment, which are being submitted for review. All extraneous materials shall be crossed out or otherwise obliterated. The Contractor shall ensure that there is no conflict with other submittals and notify the Construction Manager in each case where his submittal may affect the work of another contractor or the Owner. The Contractor shall coordinate submittals among his subcontractors and suppliers including those submittals.

The Contractor shall coordinate submittals with the work so that work will not be delayed. Contractor shall coordinate and schedule different categories of submittals, so that one will not be delayed for lack of coordination with another. No extension of time will be allowed because of failure to properly schedule submittals. The Contractor shall not proceed with work related to a submittal until the submittal process is complete. This requires that submittals for review and comment shall be returned to the Contractor stamped "No Exceptions Taken" or "Make Corrections Noted."

The Contractor shall certify on each submittal document that he has reviewed the submittal, verified field conditions, and complied with the contract documents.

The Contractor may authorize in writing a material or equipment supplier to deal directly with the Construction Manager or with the Owner with regard to a submittal. These dealings shall be limited to contract interpretations to clarify and expedite the work.

01300-1 3.0 CATEGORIES OF SUBMITTALS

A. GENERAL:

Submittals fall into two general categories; submittals for review and comment, and submittals which are primarily for information only. Submittals which are for information only are generally specified as PRODUCT DATA in Part 2 of applicable specification sections.

At the beginning of work, the Construction Manager will furnish the Contractor lists of those submittals specified in the project manual. Two separate lists will be provided: submittals for review and comment and product data (submittals) for information only.

B. SUBMITTALS FOR REVIEW AND COMMENT:

All submittals except where specified to be submitted as product data for information only shall be submitted by the Contractor to the Construction Manager for review and comment.

C. SUBMITTALS (PRODUCT DATA) FOR INFORMATION ONLY:

Where specified, the Contractor shall furnish submittals (product data) to the Construction Manager for Information only. Submittal requirements for operation and maintenance manuals are included in this category.

4.0 TRANSMITTAL PROCEDURE

A. GENERAL:

Unless otherwise specified, submittals regarding material and equipment shall be accompanied by Transmittal Form 01300-A at the end of this section. A separate form shall be used for each specific item, class of material, equipment, and items specified in separate, discrete sections, for which the submittal is required. Submittal documents common to more than one piece of equipment shall be identified with all the appropriate equipment numbers. Submittals for various items shall be made with a single form when the items taken together constitute a manufacturer's package or are so functionally related that expediency indicates checking or review of the group or package as a whole.

A unique number, sequentially assigned, shall be noted on the transmittal form accompanying each item submitted. Original submittal numbers shall have the following format: “SPECIFICATION NUMBER” - "XXX"; where "XXX" is the sequential number assigned by the Contractor. Resubmittals shall have the following format: "XXX-Y"; where "XXX" is the originally assigned submittal number and "Y" is a sequential letter assigned for resubmittals, i.e., A, B, or C being the 1st, 2nd, and 3rd resubmittals, respectively. Submittal 15050-25B, for example, is the second resubmittal of submittal 25 from specification section 15050.

01300-2 B. DEVIATION FROM CONTRACT:

If the Contractor proposes to provide material, equipment, or method of work which deviates from the project manual, he shall indicate so under "deviations" on the transmittal form accompanying the submittal copies.

C. SUBMITTAL COMPLETENESS:

Submittals which do not have all the information required to be submitted, including deviations, are not acceptable and will be returned without review.

5.0 REVIEW PROCEDURE

A. GENERAL:

Submittals are specified for those features and characteristics of materials, equipment, and methods of operation which can be selected based on the Contractor's judgment of their conformance to the specified requirements. Other features and characteristics are specified in a manner which enables the Contractor to determine acceptable options without submittals. The review procedure is based on the Contractor's guarantee that all features and characteristics not requiring submittals conform as specified. Review shall not extend to means, methods, techniques, sequences or procedures of construction, or to verifying quantities, dimensions, weights or gages, or fabrication processes (except where specifically indicated or required by the project manual) or to safety precautions or programs incident thereto. Review of a separate item, as such, will not indicate approval of the assembly in which the item functions.

When the contract documents require a submittal, the Contractor shall submit the specified information as follows:

1. 3 hard or electronic PDF copies of all submitted information shall be transmitted with submittals for review and comment.

2. Unless otherwise specified, 2 hard or electronic PDF copies of all submitted information shall be transmitted with submittals (Product Data) for information only.

B. SUBMITTALS FOR REVIEW AND COMMENT:

Unless otherwise specified, within 14 calendar days after receipt of a submittal for review and comment, the Construction Manager shall review the submittal and return 1 copies of the marked-up reproducible original noted in 1 above. The reproducible original will be retained by the Construction Manager. The returned submittal shall indicate one of the following actions:

1. If the review indicates that the material, equipment or work method complies with the project manual, submittal copies will be marked "NO

01300-3 EXCEPTIONS TAKEN." In this event, the Contractor may begin to implement the work method or incorporate the material or equipment covered by the submittal.

2. If the review indicates limited corrections are required, copies will be marked "MAKE CORRECTIONS NOTED." The Contractor may begin implementing the work method or incorporating the material and equipment covered by the submittal in accordance with the noted corrections. Where submittal information will be incorporated in O&M data, a corrected copy shall be provided.

3. If the review reveals that the submittal is insufficient or contains incorrect data, copies will be marked "AMEND AND RESUBMIT." Except at his own risk, the Contractor shall not undertake work covered by this submittal until it has been revised, resubmitted and returned marked either "NO EXCEPTIONS TAKEN" or "MAKE CORRECTIONS NOTED."

4. If the review indicates that the material, equipment, or work method does not comply with the project manual, copies of the submittal will be marked "REJECTED - SEE REMARKS." Submittals with deviations which have not been identified clearly may be rejected. Except at his own risk, the Contractor shall not undertake the work covered by such submittals until a new submittal is made and returned marked either "NO EXCEPTIONS TAKEN" or "MAKE CORRECTIONS NOTED."

C. SUBMITTALS (PRODUCT DATA) FOR INFORMATION ONLY:

Such information is not subject to submittal review procedures and shall be provided as part of the work under this contract and its acceptability determined under normal inspection procedures.

6.0 EFFECT OF REVIEW OF CONTRACTOR'S SUBMITTALS

Review of contract drawings, methods of work, or information regarding materials or equipment the Contractor proposes to provide, shall not relieve the Contractor of his responsibility for errors therein and shall not be regarded as an assumption of risks or liability by the Construction Manager or the Owner, or by any officer or employee thereof, and the Contractor shall have no claim under the contract on account of the failure, or partial failure, of the method of work, material, or equipment so reviewed. A mark of "NO EXCEPTIONS TAKEN" or "MAKE CORRECTIONS NOTED" shall mean that the Owner has no objection to the Contractor, upon his own responsibility, using the plan or method of work proposed, or providing the materials or equipment proposed.

01300-4 01300-A. SUBMITTAL TRANSMITTAL FORM SUBMITTAL TRANSMITTAL

Submittal Description: Submittal No:1

Spec Section:

Routing Sent Received OWNER: Contractor/CM PROJECT: CM/Engineer Engineer/CM CONTRACTOR: CM/Contractor

We are sending you Attached Under separate cover via ______Submittals for review and comment Product data for information only

Remarks:

Review Section Review Reviewer comments Item Copies Date No. Description actiona initials attached

aNote: NET = No exceptions taken; MCN = Make corrections noted; A&R = Amend and resubmit; R = Rejected Attach additional sheets if necessary.

Contractor Certify either A or B: A. We have verified that the material or equipment contained in this submittal meets all the requirements, including coordination with all related work, specified (no exceptions). B. We have verified that the material or equipment contained in this submittal meets all the requirements specified except for the attached deviations. No. Deviation

Certified by: Contractor's Signature

**END OF SECTION**

1See paragraph 01300-4.0 A, Transmittal Procedure.

01300-5

SECTION 01310

CONSTRUCTION SCHEDULE

PART 1--GENERAL

1.01 SCOPE

This section specifies reports and schedules for planning and monitoring the progress of the work.

1.02 DESCRIPTION

The Contractor shall provide a graphic construction schedule indicating the various subdivisions of the work and the dates of commencing and finishing each. The schedule shall show the time allowed for testing and for other procedures which must be completed prior to the work being put into operation. Contractor shall provide a 3-week look ahead schedule at each progress meeting.

1.03 SUBMITTAL PROCEDURES

Within 14 days after the date of the Notice to Proceed, the Contractor shall submit in accordance with Section 01300, a construction schedule conforming to paragraph 01310-1.02. The submittal shall consist of a reproducible original and two copies.

Within 7 calendar days after receipt of the submittal, the Construction Manager shall review the submitted schedule and return one copy of the marked up original to the Contractor. If the Construction Manager finds that the submitted schedule does not comply with specified require- ments, the corrective revisions will be noted on the submittal copy returned to the Contractor.

1.04 SCHEDULE REVISIONS

Revisions to the accepted construction schedule may be made only with the written approval of the Contractor and Construction Manager.

1.05 PROJECT STATUS UPDATE

Project status review and update shall be provided each month with the pay application. The submittal shall consist of two copies.

PART 2--NOT USED

PART 3--NOT USED

**END OF SECTION**

01310-1

SECTION 01380

PHOTOGRAPHS

PART 1--GENERAL

1.01 PRECONSTRUCTION PHOTOGRAPHS

The Contractor shall provide preconstruction photographs prior to commencement of work on the site. The photographs shall be minimum 35-mm film size or electronic jpeg files with an index print, and shall indicate on the front of each print the date, name of work, and the location where the photograph was taken. Before construction may start, 4-inch by 6-inch prints glossy prints of each exposure, together with the negative, or electronic jpeg files on a CD with an index print, clearly depicting preconstruction conditions must be delivered to the Construction Manager. Preconstruction photographs shall be taken at locations to be designated by the Construction Manager.

1.02 CONSTRUCTION PHOTOGRAPHS

The Contractor shall provide construction photographs showing the progress of the work. The photographs shall be taken of such subjects as may be directed, shall be minimum 35-mm film size or electronic jpeg files on a CD with an index print, and shall indicate on the front of each print the date, job title and brief description of the photograph including the location where the photograph was taken. Starting one week after the date of the preconstruction photographs and continuing as long as the work is in progress, a minimum of 28 weekly photographs shall be taken.

Upon acceptance of the work, a minimum of 24 color exposure photographs shall be made of the work where directed by the Construction Manager. 4-inch by 6-inch prints of each exposure, together with the negatives or electronic jpeg files on a CD with an index print, shall be delivered to the Construction Manager within 10 days following each set of exposures.

PART 2--NOT USED

PART 3--NOT USED

**END OF SECTION**

01380-1

SECTION 01500

CONTRACTOR'S UTILITIES

PART 1--GENERAL

1.01 DESCRIPTION

This section describes the responsibilities of the Contractor with regard to temporary power, telephone service, water, sanitary facilities, barriers, fencing, protection of Work, water control, access roads, parking, progress cleaning, project signage, and buildings. This Section also describes the Contractor’s responsibility for overall safety of project activities.

1.02 POWER

The Contractor shall provide power for construction at the site. The Contractor shall make arrangements with the electrical utility and with the Construction Manager for power takeoff points, voltage and phasing requirements, transformers and metering and shall pay the costs and fees arising there from. The Contractor shall provide the special connections required for their work.

1.03 TELEPHONE

The Contractor shall provide telephone service at the construction site. Radio-telephone service is not acceptable as a substitute for telephone service. Cellular telephones are acceptable.

1.04 SANITARY FACILITIES

The Contractor shall provide toilet and wash-up facilities for his work force at the site of work. The facilities shall comply with applicable laws, ordinances, and regulations pertaining to the public health and sanitation of dwellings and camps, in conformance with OSHA CFR 1926.5.

1.05 WATER

The Contractor shall provide water for construction at the site. For conservation reasons, water flooding of trenches for backfilling using potable water is discouraged. The Contractor shall request water using form provided by City of Surprise. City of Surprise must approve form prior to water use.

1.06 SECURITY

The Contractor shall provide security and facilities to protect Work, and existing facilities, from unauthorized entry, vandalism, or theft. The Contractor is responsible for any losses that occur.

PART 2--NOT USED

PART 3--NOT USED

01500-1

**END OF SECTION**

01500-2

SECTION 01560

ENVIRONMENTAL CONTROLS

PART 1--GENERAL

1.01 SITE MAINTENANCE

The Contractor shall keep the work site clean and free from rubbish and debris. Materials and equipment shall be removed from the site when they are no longer necessary. Upon completion of the work and before final acceptance, the work site shall be cleared of equipment, unused materials, and rubbish to present a clean and neat appearance.

1.02 AIR POLLUTION CONTROL

The Contractor shall not discharge or cause to be discharged any smoke, dust, and other contaminants into the atmosphere that violate the regulations of any legally constituted authority. The Contractor shall also abate dust nuisance by cleaning, sweeping, and sprinkling with water, or other means as necessary. The use of water, in amounts which result in mud on public streets, is not acceptable as a substitute for sweeping or other methods.

1.03 NOISE CONTROL

Work hours are to be between 5:00 a.m. and 4:30 p.m. unless otherwise approved by the Construction Manager. Noise from Contractor's operations shall not exceed limits established by applicable laws or regulations and in no event shall exceed 86 dBA at a distance of 50 feet from the noise source.

1.04 BARRIERS

The Contractor shall provide barriers to prevent unauthorized entry to construction areas. The Contractor shall take all necessary measures to protect existing facilities and adjacent properties from damage resulting from construction operations.

The Contractor shall take measures to protect plant life that has been designated to remain and shall be responsible for the replacement of such plant life if damaged during construction activities.

The Contractor shall take all reasonable measures to protect non-Contractor vehicles, materials stored onsite and structures from damage.

PART 2--NOT USED

PART 3--NOT USED

**END OF SECTION**

01560-1

SECTION 01700

RESTORATION OF IMPROVEMENTS

PART 1--GENERAL

1.01 STRUCTURES

The Contractor shall take all precautions necessary to protect the integrity and usefulness of all existing plant facilities. If necessary, the Contractor may, with the approval of the Construction Manager, remove such existing structures, including curbs, gutters, pipelines and utility poles as may be necessary for the performance of the work, and shall rebuild the structures thus removed in as good a condition as found with the requirements specified. Contractor shall also repair existing structures which may be damaged as a result of the work under this contract.

1.02 ROADS AND STREETS

Unless otherwise specified, roads and streets in which the surface is removed, broken, or damaged, or in which the ground has caved or settled during the work under this contract, shall be resurfaced and brought to the original grade and section. Roadways used by the Contractor shall be cleaned and repaired. Before resurfacing material is placed, edges of pavements shall be trimmed back far enough to provide clean, solid, vertical faces, and shall be free of loose material. All paved surfaces shall be cut with a pavement saw. Rough cuts are not allowed. Repair work shall conform to the paving specifications.

1.03 CULTIVATED AREAS AND OTHER SURFACE IMPROVEMENTS

Cultivated or planted areas and other surface improvements which are damaged by actions of the Contractor shall be restored as nearly as possible to their original condition. Restoration shall take place within 1 week or sooner as directed by the Construction Manager.

Existing guard posts, barricades, and fences shall be protected and replaced if damaged.

1.04 PROTECTION OF EXISTING INSTALLATIONS

The Contractor shall protect all existing operating facilities and structures from damages. However, if damage occurs, the Contractor shall immediately correct or replace existing equipment, controls, systems, structures, or facilities which are damaged in any way as a result of the Contractor’s operations.

PART 2--NOT USED

PART 3--NOT USED

**END OF SECTION**

01700-1

SECTION 01720

RECORD DRAWINGS

PART 1--GENERAL

Record drawings refer to those documents maintained and annotated by the Contractor during construction and are defined as (1) a neatly and legibly marked set of contract drawings showing the final location of piping, equipment, electrical conduits, outlet boxes and cables; (2) additional documents such as schedules, lists, drawings, and electrical and instrumentation diagrams included in the specifications; and (3) Contractor layout and installation drawings.

Unless otherwise specified, record drawings shall be full size and maintained in a clean, dry, and legible condition. Record documents shall not be used for construction purposes and shall be available for review by the Construction Manager during normal working hours at the Contractor's field office. At the completion of the work, prior to final payment, all record drawings shall be submitted to the Construction Manager.

Marking of the drawings shall be kept current and shall be done at the time the material and equipment are installed. Annotations to the record documents shall be made with an erasable colored pencil conforming to the following color code:

Additions - Red Deletions - Green Comments - Blue Dimensions - Graphite*

*Legibly mark to record actual depths, horizontal and vertical location of underground raceways, cables, and appurtenances referenced to permanent surface improvements.

If the Contractor opts to use electronic record files, the above requirements shall be met within the electronic documentation. This includes, but is not limited to, the requirement that the annotation color code be maintained in the electronic files such that when printed in color, the annotation colors are legible and distinguishable.

PART 2--NOT USED

PART 3--NOT USED

**END OF SECTION**

01720-1

SECTION 01730

OPERATING AND MAINTENANCE INFORMATION

PART 1--GENERAL

1.01 SCOPE

Operation and maintenance (O&M) instructions shall be provided in accordance with this section and as required in the technical sections of this project manual. O&M information shall be provided for each maintainable piece of equipment, equipment assembly or subassembly, and material provided or modified under this contract. O&M instruction shall also be provided by the Contractor for the overall O&M of the system.

O&M instructions must be submitted, reviewed and accepted by the Construction Manager before on-site training may start. O&M instructions specific to individual equipment shall be submitted to the Construction Manager for review and approval following the Construction Manager’s approval of the equipment submittal/shop drawing. The O&M manuals shall be submitted to the City at least 30 days prior to on-site training, or at the completion time stated per Part 1.04.

1.02 TYPES OF INFORMATION REQUIRED

A. GENERAL:

O&M information shall contain the names, addresses, and telephone numbers of the manufacturer, the nearest representative of the manufacturer, and the nearest supplier of the manufacturer's equipment and parts. Each O&M manual shall include the following general information: 1. Date O&M issued.

2. Neatly typewritten table of contents for each volume, arranged in systematic order.

3. Identify the Contractor, name of the Engineer, address, and telephone number.

4. List each product required to be included, indexed to content of volume.

a. List, with each product, name, address and telephone number of:

i. Subcontractor or installer ii. Maintenance contractor, as appropriate iii. Identify area of responsibility of each iv. Local source of supply for parts and replacement and list of recommended spare parts

01730-1

5. Identify each product by the product name and other identifying symbols as set forth in the contract documents, including nameplate information and serial numbers for each item of equipment furnished.

6. Include only product data sheets, which are pertinent to specific product.

a. Annotate each sheet to:

i. Clearly identify specific product or part installed ii. Clearly identify data applicable to installation iii. Delete references to inapplicable information

7. Supplement product data with drawings as necessary to clearly illustrate:

a. Relations of component parts of equipment and systems b. Control and flow diagrams

8. Coordinate drawings with information in the project record documents to assure correct illustration of completed installation.

9. Include appendix with written description of Start-up procedures.

10. Provide additional written text, as required to supplement product data for a job- specific installation. Organize in a consistent format under separate headings for different procedures. Provide logical sequence of instructions for each procedure.

11. Provide a copy of each warranty, bond, and service contract issued. Provide an information sheet for the Owner, giving:

a. Proper procedures in event of failure b. Instances, which might void warranties or bonds c. Life of all bonds and warranties d. Start and end date of warranty period

In addition, one or more of the following items of information shall be provided as applicable.

B. OPERATING INSTRUCTIONS:

Specific instructions, procedures, and illustrations shall be provided for the following phases of operations:

1. SAFETY PRECAUTIONS: List personnel hazards for equipment and list safety precautions for all operating conditions.

2. OPERATOR PRESTART: Provide requirements to set up and prepare each system for use.

01730-2

3. START-UP, SHUTDOWN, AND POST SHUTDOWN PROCEDURES: Provide a control sequence for each of these operations.

4. NORMAL OPERATIONS: Provide control diagrams with data to explain operation and control of systems and specific equipment.

5. EMERGENCY OPERATIONS: Provide emergency procedures for equipment malfunctions to permit a short period of continued operation or to shut down the equipment to prevent further damage to systems and equipment. Include emergency shutdown instructions for fire, explosion, spills, or other foreseeable contingencies. Provide guidance on emergency operations of all utility systems including valve locations and portions of systems controlled.

6. OPERATOR SERVICE REQUIREMENTS: Provide instructions for services to be performed by the operator such as lubrication, adjustments, and inspection.

7. ENVIRONMENTAL CONDITIONS: Provide a list of environmental conditions (temperature, humidity, seasonal fluctuations in flow and other relevant data) which are best suited for each product or piece of equipment and describe conditions under which equipment should not be allowed to run.

C. PREVENTIVE MAINTENANCE:

The following information shall be provided for preventive and scheduled maintenance to minimize corrective maintenance and repair:

1. LUBRICATION DATA: Provide lubrication data, other than instructions for lubrication in accordance with paragraph 1.02-B6.

a. A table showing recommended lubricants for specific temperature ranges and applications;

b. Charts with a schematic diagram of the equipment showing lubrication points, recommended types and grades of lubricants, and capacities; and

c. A lubrication schedule showing service interval frequency.

2. PREVENTIVE MAINTENANCE PLAN AND SCHEDULE: Provide manufacturer's schedule for routine preventive maintenance, inspections, tests, and adjustments required to ensure proper and economical operation and to minimize corrective maintenance and repair. Provide manufacturer's projection of preventive maintenance man-hours on a daily, weekly, monthly, and annual basis including craft requirements by type of craft.

01730-3

D. CORRECTIVE MAINTENANCE:

Manufacturer's recommendations shall be provided on procedures and instructions for correcting problems and making repairs.

1. TROUBLESHOOTING GUIDES AND DIAGNOSTIC TECHNIQUES: Provide step-by-step procedures to promptly isolate the cause of typical malfunctions. Describe clearly why the checkout is performed and what conditions are to be sought. Identify tests or inspections and test equipment required to determine whether parts and equipment may be reused or requires replacement.

2. WIRING DIAGRAMS AND CONTROL DIAGRAMS: Wiring diagrams and control diagrams shall be point-to-point drawings of wiring and control circuits including factory-field interfaces. Provide a complete and accurate depiction of the actual job-specific wiring and control work. On diagrams, number electrical and electronic wiring and pneumatic control tubing and the terminals for each type identically to actual installation numbering.

3. MAINTENANCE AND REPAIR PROCEDURES: Provide instructions and list tools required to restore product or equipment to proper condition or operating standards.

4. REMOVAL AND REPLACEMENT INSTRUCTIONS: Provide step-by- step procedures and list required tools and supplies for removal, replacement, disassembly, and assembly of components, assemblies, subassemblies, accessories, and attachments. Provide tolerances, dimensions, settings, and adjustments required. Instructions shall include a combination of test and illustrations.

5. SPARE PARTS AND SUPPLY LISTS: Provide lists of spare parts and supplies required for maintenance and repair to ensure continued service or operation without unreasonably delays. Special consideration is required for facilities at remote locations. List spare parts and supplies that have a long lead time to obtain.

6. CORRECTIVE MAINTENANCE PERSONNEL HOURS: Provide manufacturer's projection of corrective maintenance personnel-hours including craft requirements by type of craft. Corrective maintenance that requires participation of the equipment manufacturer shall be identified and tabulated separately.

E. APPENDICES:

The following information shall be provided; include information not specified in the preceding paragraphs but pertinent to the maintenance or operation of the product or equipment.

1. PARTS IDENTIFICATION: Provide identification and coverage for all parts of each component, assembly, subassembly, and accessory of the end items subject to replacement. Include special hardware requirements, such as requirement to use high-strength bolts and nuts. Identify parts by make, model, serial number, and source of supply to allow reordering without further identification. Provide clear and legible illustrations, drawings, and exploded views

01730-4 to enable easy identification of the items. When illustrations omit the part numbers and description, both the illustrations and separate listing shall show the index, reference, or key number which will cross-reference the illustrated part to the listed part. Parts shown in the listings shall be grouped by components, assemblies, and subassemblies. Provide description of unit and component parts as follows: a. Function, normal operating characteristics, and limiting conditions

b. Performance curves, engineering data, and tests

c. Complete nomenclature and part number of replaceable parts

d. Life of all bonds and warranties (start and end dates)

e. Predicted life of parts subject to wear.

f. Original manufacturer’s parts list, illustrations, assembly drawings, and diagrams required for maintenance.

2. WARRANTY INFORMATION: List and explain in a spreadsheet the various warranties and include the servicing and technical precautions prescribed by the manufacturers or contract documents to keep warranties in force.

3. PERSONNEL TRAINING REQUIREMENTS: Provide information available from the manufacturers to use in training designated personnel to operate and maintain the equipment and systems properly.

4. TESTING EQUIPMENT AND SPECIAL TOOL INFORMATION: Provide information on test equipment required to perform specified tests and on special tools needed for the operation, maintenance, and repair of components.

F. ELECTICAL AND ELECTRONIC SYSTEMS:

The following information shall be provided for all electrical and electronic system contents, as appropriate:

1. DESCRIPTION OF SYSTEM AND COMPONENT PARTS:

a. Function, normal operating characteristics, and limiting conditions b. Performance curves, engineering data, and tests c. Complete nomenclature and part number of replacement parts

2. CIRCUIT DIRECTORIES OF PANELBOARDS:

a. Electrical service b. Controls c. Communications

01730-5

d. As installed color-coded wiring diagrams

3 OPERATING PROCEDURES:

a Routing and normal operating instructions b. Sequences required c. Special operating instructions

4. MAINTENANCE PROCEDURES:

a. Routine maintenance b. Guide to “troubleshooting” c. Disassembly, repair, and assembly d. Adjustment and checking

5. MANUFACTURER’S PRINTED OPERATING AND MAINTENANCE INSTRUCTIONS

1.03 TRANSMITTAL PROCEDURE

Unless otherwise specified, O&M manuals, information, and data shall be transmitted in accordance with Section 01300 accompanied by Transmittal Form 01730-A and Equipment Record Forms 01730-B and/or 01730-C, as appropriate, all as specified in Section 01999. The transmittal form shall be used as a checklist to ensure the manual is complete. Only complete sets of O&M instructions will be reviewed for acceptance.

Six hard copies and one electronic copy on compact disc in pdf format of the specified O&M information shall be provided. For ease of identification, each manufacturer's brochure and manual shall be appropriately labeled with the equipment name and equipment number as it appears in the project manual. The information shall be organized in the binders in numerical order by the equipment numbers assigned in the project manual. The binders shall be provided with a table of contents and tab sheets to permit easy location of desired information. Binders shall be heavy, 3-ring style, 3-inch maximum, suitable for bookshelf storage. White, 8-1/2 inch x 11 inch, 20 lb minimum paper shall be used for typed pages.

If manufacturers' standard brochures and manuals are used to describe O&M procedures, such brochures and manuals shall be modified to reflect only the model or series of equipment used on this project. Extraneous material shall be crossed out neatly or otherwise annotated or eliminated. Text shall be manufacturer’s printed data, or neatly typewritten. Drawings shall be bound in with the text with a reinforced punched binder tab. Larger drawings shall be folded to the size of text pages. Provide a flyleaf for each separate product or piece of operating equipment. Provide a typed description of the product and major component parts of the equipment. Provide indexed tabs. The cover of each volume shall include the title of the project, identity of each separate structure as applicable, and general subject matter covered in the manual.

01730-6

1.04 PAYMENT

Acceptable O&M information for the project must be delivered to the Construction Manager prior to the project being 65 percent complete. Progress payments for work in excess of 65 percent completion will not be made until the specified acceptable O&M information has been delivered to the Construction Manager.

1.05 FIELD CHANGES

Following the acceptable installation and operation of an equipment item, the item's instructions and procedures shall be modified and supplemented by the Contractor to reflect any field changes or information requiring field data.

PART 2--NOT USED

PART 3--NOT USED

**END OF SECTION**

01730-7

SECTION 01800

ENVIRONMENTAL CONDITIONS

PART 1--GENERAL

This section describes the environmental conditions which have been observed at the site of the work and which may reasonably be anticipated throughout the life of the project.

The site of the work is at an elevation of 1140 feet above mean sea level. Climate conditions are described as follows:

Description Range of Conditions Winter Several days each year have frost, with occasional rain and very rare occasions of snowfall. Most days are sunny and are mild. Summer Sunny and hot, with a late season thunder storm. Relative humidity, percent Average outdoors 21 to 39 Air temperature, degrees F Outdoors 8 to 117 Barometric pressure, inches, mercury 30

Additional conditions which may be applicable are specified in other sections.

PART 2--NOT USED

PART 3--NOT USED

**END OF SECTION**

01800-1

SECTION 01999

REFERENCE FORMS

The forms listed below and included in this section are referenced from other sections of the project manual:

Form No. Title

01300-A Submittal Transmittal Form

01660-A Equipment Test Report Form

01730-A Operation and Maintenance Transmittal Form 01730-B Equipment Record Form 01730-C Equipment Record Form

09900-A Coating System Inspection Checklist

11000-A Manufacturer's Installation Certification Form

16000-A Wire and Cable Resistance Test Data Form

01999-1

01300-A. SUBMITTAL TRANSMITTAL FORM: SUBMITTAL TRANSMITTAL

Submittal Description: Submittal No:1

Spec Section:

Routing Sent Received OWNER: Contractor/CM PROJECT: CM/Engineer Engineer/CM CONTRACTOR: CM/Contractor

We are sending you Attached Under separate cover via ______Submittals for review and comment Product data for information only

Remarks:

Review Section Review Reviewer comments Item Copies Date No. Description actiona initials attached

aNote: NET = No exceptions taken; MCN = Make corrections noted; A&R = Amend and resubmit; R = Rejected Attach additional sheets if necessary.

Contractor Certify either A or B: A. We have verified that the material or equipment contained in this submittal meets all the requirements, including coordination with all related work, specified (no exceptions). B. We have verified that the material or equipment contained in this submittal meets all the requirements specified except for the attached deviations. No. Deviation

Certified by: Contractor's Signature

1See paragraph 01300-4.0 A, Transmittal Procedure.

01999-2

Page 1 of 3

01660-A. EQUIPMENT TEST REPORT FORM: NOTE: This example equipment test report is provided for the benefit of the Contractor and is not specific to any piece of equipment to be installed as a part of this project. The example is furnished as a means of illustrating the level of detail required for the preparation of equipment test report forms for this project.

CITY OF SAMPLE

EXAMPLE WATER TREATMENT PLANT STAGE IV EXPANSION PROJECT

ABC Construction Company, Inc., General Contractor XYZ Engineering, Inc., Construction Manager

EQUIPMENT TEST REPORT

Equipment Name: Sludge Pump 2 Equipment Number: P25202 Specification Ref: 11390 Location: East Sedimentation Basin Gallery

Contractor Construction Manager Verified Date Verified Date PREOPERATIONAL CHECKLIST Mechanical Lubrication Alignment Anchor bolts Seal water system operational Equipment rotates freely Safety guards Valves operational Hopper purge systems operational Sedimentation tank/hopper clean O&M manual information complete Manufacturer's installation certificate complete Electrical (circuit ring-out and high-pot tests) Circuits: Power to MCC 5 Control to HOA

01999-3

Page 2 of 3

Contractor Construction Manager Verified Date Verified Date Indicators at MCC: Red (running) Green (power) Amber (auto) Indicators at local control panel Wiring labels complete Nameplates: MCC Control station Control panel Equipment bumped for rotation Piping Systems Cleaned and flushed: Suction Discharge Pressure tests Temporary piping screens in place Instrumentation and Controls Flowmeter FE2502F calibration Calibration Report No. Flow recorder FR2502G calibrated against transmitter VFD speed indicator calibrated against independent reference Discharge overpressure shutdown switch calibration Simulate discharge overpressure Shutdown FUNCTIONAL TESTS

Mechanical Motor operation temperature satisfactory Pump operating temperature satisfactory Unusual noise, etc? Pump operation: 75 gpm/50 psig Measurement: Flow Pressure: Test gage number: Alignment hot Dowelled in Remarks:

01999-4

Page 3 of 3

Contractor Construction Manager

Verified Date Verified Date Electrical Local switch function: Runs in HAND No control power in OFF Timer control in AUTO Overpressure protection switch PS2502C functional in both HAND and AUTO Overpressure protection switch PS2502C set at 75 psig PLC 2500 set at 24-hour cycle, 25 min ON OPERATIONAL TEST 48-hour continuous test. Pump cycles as specified, indicators functional, controls functional, pump maintains capacity, overpressure protection remains functional, hour meter functional

RECOMMENDED FOR BENEFICIAL OCCUPANCY

Construction Manager Date

ACCEPTED FOR BENEFICIAL OCCUPANCY

Owner's Representative Date

01999-5

01730-A. OPERATION AND MAINTENANCE TRANSMITTAL FORM:

Date: Submittal No:2 To: Contract No: Spec. Section: Submittal Description: From: Attention: Contractor Construction manager Checklist Satisfactory N/A Accept Deficient 1. Table of contents 2. Equipment record forms 3. Manufacturer information 4. Vendor information 5. Safety precautions 6. Operator prestart 7. Start-up, shutdown, and post shutdown procedures 8. Normal operations 9. Emergency operations 10. Operator service requirements 11. Environmental conditions 12. Lubrication data 13. Preventive maintenance plan and schedule 14. Troubleshooting guides and diagnostic techniques 15. Wiring diagrams and control diagrams 16. Maintenance and repair procedures 17. Removal and replacement instructions 18. Spare parts and supply list 19. Corrective maintenance man-hours 20. Parts identification 21. Warranty information 22. Personnel training requirements 23. Testing equipment and special tool information

Remarks:

Contractor's Signature

2See paragraph 01300-4.0 A, Transmittal Procedure. 01999-6

01730-B. EQUIPMENT RECORD FORM:

EQUIP DESCRIP EQUIP LOC EQUIP NO. SHOP DWG NO. DATE INST COST MFGR MFGR CONTACT MFGR ADDRESS PHONE VENDOR VENDOR CONTACT VENDOR ADDRESS PHONE

MAINTENANCE REQUIREMENTS D W M Q S A Hours

LUBRICANTS: RECOMMENDED: ALTERNATIVE: MISC. NOTES:

RECOMMENDED SPARE PARTS ELECTRICAL NAMEPLATE DATA PART NO QUAN PART NAME COST EQUIP MAKE SERIAL NO. ID NO. MODEL NO. FRAME NO. HP V AMP HZ PH RPM SF DUTY CODE INSL. CL DES TYPE NEMA DES C AMB TEMP RISE RATING MISC. MECHANICAL NAMEPLATE DATA EQUIP MAKE SERIAL NO. ID NO. MODEL NO. FRAME NO. HP RPM CAP SIZE TDH IMP SZ BELT NO. CFM PSI ASSY NO. CASE NO. MISC

01999-7

01730-C. EQUIPMENT RECORD FORM:

EQUIP DESCRIP EQUIP LOC EQUIP NO. SHOP DWG NO. DATE INST COST MFGR MFGR CONTACT MFGR ADDRESS PHONE VENDOR VENDOR CONTACT VENDOR ADDRESS PHONE

MAINTENANCE REQUIREMENTS D W M Q S A Hours

01999-8

11000-A. MANUFACTURER'S INSTALLATION CERTIFICATION FORM:

Contract No: Specification section:

Equipment name:

Contractor:

Manufacturer of equipment item:

The undersigned manufacturer of the equipment item described above hereby certifies that he has checked the installation of the equipment and that the equipment, as specified in the project manual, has been provided in accordance with the manufacturer's recommendations, and that the trial operation of the equipment item has been satisfactory.

Comments:

Date Manufacturer

Signature of Authorized Representative

Date Contractor

Signature of Authorized Representative

01999-9

11000-B. MANUFACTURER'S INSTRUCTION CERTIFICATION FORM:

Contract No: Specification section: ______

Equipment name:

Contractor:

Manufacturer of equipment item:

The undersigned manufacturer certifies that a service engineer has instructed the wastewater treatment plant operating personnel in the proper maintenance and operation of the equipment designated herein.

Operations Check List (check appropriate spaces) Start-up procedure reviewed Shutdown procedure reviewed Normal operation procedure reviewed Others:

Maintenance Check List (check appropriate spaces) Described normal oil changes (frequency) Described special tools required Described normal items to be reviewed for wear Described preventive maintenance instructions Described greasing frequency Others:

Date Manufacturer

Signature of Authorized Representative

Date Signature of Owner’s Representative

Date Signature of Contractor’s Representative

01999-10

16000-A. WIRE AND CABLE RESISTANCE TEST DATA FORM:

Wire or Cable No.: Temperature, oF

Insulation resistance, Location of Test megohms 1.

2.

3.

4.

5.

6.

7 .

CERTIFIED Date Contractor's Representative

WITNESSED Date Owner's Representative

01999-11

SECTION 02010

DEMOLITION

PART 1 - GENERAL

1.01 DESCRIPTION

A. This Section includes demolition of existing improvements in accordance with the Drawings and as specified in this Section.

1.02 REFERENCES

A. This section contains references to the following documents. They are a part of this section as specified and modified. Where a referenced document contains references to other standards, those documents are included as references under this section as if referenced directly. In the event of conflict between the requirements of this section and those of the listed documents, the requirements of this section shall prevail.

B. Unless otherwise specified, references to documents shall mean the documents in effect at the time of Advertisement for Bids or Invitation to Bid (or on the effective date of the Agreement if there were no Bids). If referenced documents have been discontinued by the issuing organization, references to those documents shall mean the replacement documents issued or otherwise identified by that organization or, if there are no replacement documents, the last version of the document before it was discontinued. Where document dates are given in the following listing, references to those documents shall mean the specific document version associated with that date, regardless of whether the document has been superseded by a version with a later date, discontinued or replaced.

C. Except as otherwise indicated in this Section, the Contractor shall comply with the latest edition of the Uniform Standard Specifications and Details for Public Works Constructions by the Maricopa Association of Governments (MAG).

1.03 SUBMITTALS

A. Submittals shall be made in accordance with Specifications Section 01300, Submittals, and the following special provisions provided herein.

B. At least 5 days in advance of cutting operations, the Contractor shall submit a proposed schedule and methods for demolition Work.

02010-1 PART 2- PRODUCTS (Not Used)

PART 3 - EXECUTION

3.01 GENERAL

A. The Contractor shall perform the demolition required for joining and tying in new Work to existing facilities or improvements. Items removed temporarily for the convenience of the Contractor shall be replaced to the satisfaction of the Construction Manager.

1. Existing utilities, piping systems, and electrical and mechanical equipment to remain in place shall be adequately supported, protected, and maintained until Work is complete.

2. Features or items that are damaged by the Contractor during the course of Work shall be repaired and restored to a state equal or superior to that which existed before beginning of the Work, as judged by the Construction Manager.

3.02 WORK TO BE ACCOMPLISHED BEFORE DEMOLITION

A. The Contractor shall not begin demolition until the Construction Manager has reviewed and accepted the Contractor's proposed schedule and methods of performing the demolition Work.

B. The Contractor shall obtain and verify measurements for modification Work and shall establish exact layouts, locations, lines, and elevations of Work in relation to existing conditions.

C. Prior to commencing cutting operations in an area, the Contractor shall verify that:

1. All utilities and piping in the area are located.

2. Piping and utilities to remain in service are rerouted or supported and protected.

3. Affected electrical equipment and circuits are de-energized and locked out.

4. Affected telephone and communication lines are disconnected.

5. Affected piping is isolated, drained, flushed, or purged, and all valves to lines are locked out.

02010-2 3.03 DEMOLITION, SALVAGE, AND DISPOSAL

A. Piping, electrical and mechanical equipment and other items obstructing the new construction shall be carefully removed. Items designated as being salvageable in the Contract Documents shall be turned over to Construction Manager. The Contractor shall transport and store salvageable items on the premises as directed by Construction Manager. Items that are not designated to be salvaged shall be immediately disposed of and hauled off the site in a lawful manner.

B. Unless otherwise shown on the Drawings, piping that will be disconnected as a part of the Work shall be removed if it is aboveground and abandoned in place if it is buried. Above ground lines that enter the ground shall be cut off a minimum of 30 inches below grade and removed. The ends of abandoned-in-place lines shall be closed with welded or threaded caps, flanges, or concrete plugs. The supports for aboveground lines that are no longer required shall be removed. Lines that enter structures and are designated to be removed shall be flanged at both ends of the penetration through the structure.

C. Construction Manager shall be immediately advised if utilities that are not shown on the Drawings are encountered during demolition operations. The utilities shall not be disturbed until specific instructions are received from Construction Manager.

D. Bituminous paving shall be saw cut full depth and in straight lines along the boundaries of removal before removing material.

E. Unless otherwise indicated on the Drawings or Specifications, score lines shall be cut in straight lines at least 1½-inch deep along the boundaries of removal before breaking out concrete, masonry, or non-bituminous paving. The area to be removed shall be neatly separated from adjoining surfaces.

1. Unless otherwise shown on the Drawings, curbs, gutters, and paving in the way of the excavations shall have score lines saw cut in straight segments or may be removed to the nearest construction joint, expansion joint, or similar line to make the removal as neat as practicable.

2. Asphalt pavement shall be removed to clean, straight lines by saw cutting edges.

3. Where only the surface of existing bituminous pavement is to be removed, the method of removal shall be approved by the Construction Manager, and a minimum laying depth of 1 inch new pavement material shall be provided at the join line. Where bituminous pavement adjoins a trench, the edges adjacent to the trench shall be trimmed to neat straight lines before resurfacing to ensure that all areas to be resurfaced are accessible to the rollers used to compact the subgrade or paving materials.

02010-3 4. Unless otherwise shown on the Drawings, existing reinforcing shall not be cut and shall be preserved undamaged for tying into new Work.

5. Unless shown on the Drawings or specifically approved by Construction Manager, overcutting will not be allowed. Surfaces to be removed shall be scored or cut only to the extent of the removal.

F. New Work shall be joined to existing facilities or improvements as inconspicuously as practicable.

G. Material that has been removed or demolished shall be immediately disposed of off the site in a lawful manner. While being handled and loaded, debris shall be moistened with water to settle dust. Upon completion of demolition Work, the premises shall be left neat, clean, and in a condition to receive subsequent Work.

**END OF SECTION**

02010-4 SECTION 02200

EARTHWORK PART 1--GENERAL

1.01 DESCRIPTION

A. SCOPE:

This section specifies earthwork which consists of excavation, filling, grading, and disposal of excess material for pipeline installation.

B. DEFINITIONS:

1. COMPACTION: The degree of compaction is specified as percent compaction. Maximum or relative densities refer to dry soil densities obtainable at optimum moisture content.

2. EXCAVATION SLOPE: Excavation slope shall be defined as an inclined surface formed by removing material from below existing grade.

1.02 QUALITY ASSURANCE

A. REFERENCES:

This section contains references to the following documents. They are a part of this section as specified and modified. Where a referenced document contains references to other standards, those documents are included as references under this section as if referenced directly. In the event of conflict between the requirements of this section and those of the listed documents, the requirements of this section shall prevail.

Unless otherwise specified, references to documents shall mean the documents in effect at the time of Advertisement for Bids or Invitation to Bid (or on the effective date of the Agreement if there were no Bids). If referenced documents have been discontinued by the issuing organization, references to those documents shall mean the replacement documents issued or otherwise identified by that organization or, if there are no replacement documents, the last version of the document before it was discontinued. Where document dates are given in the following listing, references to those documents shall mean the specific document version associated with that date, whether or not the document has been superseded by a version with a later date, discontinued or replaced.

02200-1 Reference Title ASTM C136 Standard Method for Sieve Analysis of Fine and Coarse Aggregates ASTM D1556 Test Method for Density of Soil in Place by the Sand- Cone Method ASTM D1557 Test Methods for Moisture-Density Relations of Soils and Soil-Aggregate Mixtures Using 10-lb (4.5-kg) Rammer and 18-in. (457-mm) Drop ASTM D2419 Standard Test Method for Sand Equivalent Value of Soils and Fine Aggregate ASTM D3017 Test Method for Moisture Content of Soil and Soil- Aggregate in Place by Nuclear Methods (Shallow Depth)

B. TESTS:

The Construction Manager will take samples and perform moisture content, gradation, compaction, and density tests during placement of backfill materials to check compliance with these specifications. The Contractor shall remove surface material at locations designated by the Construction Manager and provide such assistance as necessary for sampling and testing. The Construction Manager may direct the Contractor to construct inspection trenches in compacted or consolidated backfill to determine that the Contractor has complied with these specifications.

Tests will be made by the Construction Manager in accordance with the following:

Test Standard Procedure Moisture content ASTM D3017 Gradation ASTM C136 Density in-place ASTM D1556 Moisture-density relationships ASTM D1557

1.03 SUBMITTALS

Samples of fill materials to be used shall be submitted 2 weeks in advance of use. Samples shall consist of 0.5 cubic feet of each type of material.

02200-2 PART 2--MATERIALS

2.01 FILL MATERIALS

A. TYPE A:

Type A material shall be a clean gravel-sand mixture free from organic matter and shall conform to the following gradation:

U.S. standard sieve size Percent by weight passing 3/4 inch 100 3/8 inch 70-100 No. 4 55-100 No. 10 35-95 No. 20 20-80 No. 40 10-55 No. 100 0-2

B. TYPE B:

Type B material shall be a select granular material free from organic matter and of such size and gradation that the specified compaction can be readily attained. Material shall have a sand equivalent value determined in accordance with ASTM D2419 of not less than 20 and shall conform to the following gradation:

U.S. standard sieve size Percent by weight passing 3 inch 100 No. 4 35-100 No. 30 20-100

The coefficient of uniformity shall be 3 or greater.

The material may be an imported quarry waste, clean natural sand or gravel, select trench excavation or a mixture thereof.

C. TYPE C:

Type C material shall be unclassified material which is free from peat, wood, roots, bark, debris, garbage, rubbish or other extraneous material. The maximum size of stone shall not exceed 6 inches. If the material excavated from the site meets these requirements, it may be classified as Type C.

02200-3 D. TYPE D:

Type D material shall be granular material commonly known as pea gravel and shall conform to the following gradation:

U.S. standard sieve size Percent by weight passing 1/4 inch 100 No. 8 0-5

E. TYPE E:

Type E material shall be crushed rock commonly known as drain rock and shall conform to the following gradation:

U.S. standard sieve size Percent by weight passing 1-1/2 inch 100 3/4 inch 30-75 1/2 inch 15-55 1/4 inch 0-5

Type E material shall be composed of hard, durable, sound pieces having a specific gravity of not less than 2.65.

PART 3--EXECUTION

3.01 GENERAL

A. CONTROL OF WATER:

The Contractor shall keep excavations reasonably free from water during construction. The static water level shall be drawn down a minimum of 1 foot below the bottom of excavations to maintain the undisturbed state of natural soils and allow the placement of any fill to the specified density. Disposal of water shall not damage property or create a public nuisance. The Contractor shall have on hand pumping equipment and machinery in good working condition for emergencies and shall have workmen available for its operation. Dewatering systems shall operate continuously until backfill has been completed to 1 foot above the normal static groundwater level.

Groundwater shall be controlled to prevent softening of the bottom of excavations, or formation of "quick" conditions. Dewatering systems shall not remove natural soils. The Contractor shall control surface runoff to prevent entry or collection of water in excavations.

02200-4 Release of groundwater to its static level shall be controlled to prevent disturbance of the natural foundation soils or compacted fill and to prevent flotation or movement of structures or pipelines.

B. OVEREXCAVATION:

Where the undisturbed condition of natural soils is inadequate for support of the planned construction, the Construction Manager will direct the Contractor to overexcavate to adequate supporting soils. The excavated space shall be filled to the specified elevation with backfill. The overexcavated space under footings may be filled with concrete. The quantity and placement of such material will be paid for as extra work.

C. SURPLUS MATERIAL:

Unless otherwise specified, surplus excavated material shall be disposed of off site in accordance with applicable ordinances and environmental requirements.

D. HAULING:

When hauling is done over highways or city streets, the loads shall be trimmed and the vehicle shelf areas shall be cleaned after each loading. The loads shall be watered after trimming to eliminate dust.

E. FINISH GRADING:

Finished surfaces shall be smooth, compacted and free from irregularities. The degree of finish shall be that normally obtainable with a blade-grader.

Finished grade shall be as specified by the contours plus or minus 0.10 foot except where a local change in elevation is required to match sidewalks, curbs, manholes and catch basins, or to ensure proper drainage. Allowance for topsoil and grass cover, and subbase and pavement thickness shall be made so that the specified thickness of topsoil can be applied to attain the finished grade.

When the work is an intermediate stage of completion, the lines and grades shall be as specified plus or minus 0.5 foot to provide adequate drainage.

If the soil is to be cultivated or straw is to be incorporated into the surface, rocks larger than 2-1/2 inches in maximum dimension, roots and other debris on the surface of the slope shall be removed and disposed of prior to cultivation or placement of straw.

F. CONTROL OF EROSION:

The Contractor shall maintain earthwork surfaces true and smooth and protected from erosion. Where erosion occurs, the Contractor shall provide fill or shall excavate as necessary to return earthwork surfaces to the grade and finish specified.

02200-5 3.02 CLASSIFICATION OF FILL

Fill material shall be placed in horizontal layers and compacted with power operated tampers, rollers, idlers, or vibratory equipment. Material type, maximum layer depth, relative compaction, and general application are specified in Table A. Unless otherwise specified, fill classes shall be used where specified in Table A under general application.

Table A, Fill Classifications

Maximum Minimum uncompressed relative Fill Material layer depth, compaction, class type inches percent General application A1 A 8 95 Bedding for pipe, initial and subsequent pipeline backfill; slabs on grade (other than specified for Class E1) B1 B 8 95 Structure and subsequent pipeline backfill C1 C 8 90-95 Subsequent pipeline backfill; compaction as specified D1 D - 95 Bedding for pipe, initial and subsequent pipeline backfill E1a E 8 - Fill under slabs for structures with pressure relief valves

aCompaction of layers shall be accomplished in two passes of equipment with complete coverage across the width of the field.

3.03 EARTHWORK FOR STRUCTURES

NOT USED

3.04 EARTHWORK FOR PIPELINES AND CONDUITS

A. GENERAL:

Earthwork for pipelines and conduits is specified in paragraph 02200-3.02, Table A; in the standard details; and in the following paragraphs.

B. PIPELINE EXCAVATION:

The bottom of the trench shall be carried to the specified lines and grades with proper allowance for pipe thickness and for bedding as specified.

C. PIPELINE BACKFILL:

1. BEDDING: The Contractor shall not proceed with backfill placement in excavated areas until the subgrade has been inspected by the Construction Manager. All pipe shall

02200-6 have a minimum thickness of bedding material below the barrel of the pipe as specified. Bedding material shall be placed in the bottom of the trench, leveled and compacted. Bell holes shall be excavated at each pipe joint to permit proper inspection and uniform bearing of pipe on bedding material.

After the pipe has been laid to alignment and grade, unless otherwise specified, additional bedding material shall be placed in layers the full width of the trench and compacted up to the specified level. Bedding shall be placed simultaneously on both sides of the pipe, keeping the level of backfill the same on each side. The material shall be carefully placed and compacted around the pipe to ensure that the pipe barrel is completely supported and that no voids or uncompacted areas are left beneath the pipe. Contractor shall use particular care in placing material on the underside of the pipe to prevent lateral movement during backfilling.

2. INITIAL BACKFILL: After pipe has been properly bedded, Contractor shall place and compact initial backfill as specified. Initial backfill, where specified below the springline of the pipe, shall be placed and compacted in accordance with paragraph 02200-3.04 C.1 for additional bedding material.

3. SUBSEQUENT BACKFILL:

a. GENERAL: Backfill material, placement and compaction above the pipe zone shall be as specified. Backfill above the pipe zone shall not commence until pipe zone backfill has been inspected and accepted by the Construction Manager.

b. IMPROVED AREAS: Unless otherwise specified, select granular backfill (Class A or B) shall be used under all paved and unpaved roadways and paved and unpaved roadway shoulders, roadway embankments, and in all public right-of-ways and easements. The trench shall be backfilled to an elevation which will permit the placement of the specified surface or paving. Other surfaces shall be restored, including compaction, to the condition existing prior to construction including restoration of yard areas.

c. UNIMPROVED AREAS: Class C1 backfill shall be used for all trenches in pastureland, cultivated land, undeveloped land, and for other unimproved areas where specified. Class C1 backfill shall not be used in any public right-of-way. Trench operation which meets the requirements of Type C material may be used. The Contractor shall maximize the use of fine-grained materials (e.g., sand, silty sand, sandy silt) as Class C1 backfill.

For Class C1 backfill, the trench above the pipe zone shall be backfilled to within 12 inches of original ground surface. The top 12 inches of soil shall be removed and stored in such a manner that it will not become mixed with unsatisfactory soils. After the trench has been backfilled, the stored topsoil shall be replaced at a uniform depth in its original area compacted to its original condition. The Contractor shall leave the backfilled trench neatly mounded not more than 6 inches above existing grade for the full width of the Class C1 backfill area.

02200-7 3.05 SUBGRADE FOR PAVEMENT

The prepared subgrade shall be scarified to a depth of at least 12 inches and recompacted to at least 95 percent of the maximum density.

**END OF SECTION**

02200-8 SECTION 02773

GEOTEXTILE

PART 1 GENERAL

1.01 DESCRIPTION

A. This Section includes furnishing and installing geotextile as shown on the Drawings and specified in this Section.

1.02 REFERENCES

A. This section contains references to the following documents. They are a part of this section as specified and modified. Where a referenced document contains references to other standards, those documents are included as references under this section as if referenced directly. In the event of conflict between the requirements of this section and those of the listed documents, the requirements of this section shall prevail.

B. Unless otherwise specified, references to documents shall mean the documents in effect at the time of Advertisement for Bids or Invitation to Bid (or on the effective date of the Agreement if there were no Bids). If referenced documents have been discontinued by the issuing organization, references to those documents shall mean the replacement documents issued or otherwise identified by that organization or, if there are no replacement documents, the last version of the document before it was discontinued. Where document dates are given in the following listing, references to those documents shall mean the specific document version associated with that date, regardless of whether the document has been superseded by a version with a later date, discontinued or replaced.

C. Except as otherwise indicated in this Section, the Contractor shall comply with the latest edition of the Uniform Standard Specifications and Details for Public Works Constructions by the Maricopa Association of Governments (MAG).

Reference Title ASTM D4491 Standard Test Methods for Water Permeability of Geotextiles by Permittivity ASTM D4533 Standard Test Method for Trapezoidal Tearing Strength of Geotextiles ASTM D4632 Standard Test Method for Grab Breaking Load and Elongation of Geotextiles ASTM D4833 Standard Test Method for Index Puncture of Geomembranes and Related Products0

02773-1 Reference Title ASTM D5261 Standard Test Method for Measuring Mass Per Unit Area of Geotextiles ASTM G53 Operating Light and Water Exposure Apparatus (Fluorescent UV- Fluorescent UV-Condensation Type) for Exposure of Nonmetallic Materials

1.03 SUBMITTALS

A. Submittals shall be made in accordance with Specifications Section 01300, Submittals, and the following special provisions provided herein.

B. The Contractor shall submit the following items for review and approval:

1. Geotextile manufacturer’s product data sheets.

2. Geotextile installation and weld seaming procedure.

3. Geotextile manufacturer name quality assurance certified test reports.

4. Samples:

a. Prior to ordering geotextile material, four 12-inch by 12-inch geotextile material samples.

b. Four 12-inch by 12-inch geotextile welded seam samples.

1.04 QUALITY ASSURANCE

A. The materials supplied under these Specifications shall be first quality products designed and manufactured specifically for the purposes of this Work.

B. Certified test report(s) by the manufacturer shall be submitted prior to ordering the products.

C. The Contractor shall be responsible for field handling, storing, deploying, seaming or connecting, temporary restraining against wind, and other site aspects of the geotextile material.

D. The Contractor shall be trained and qualified to install geotextiles.

02773-2 1.05 DELIVERY, STORAGE AND HANDLING

A. Delivery, storage, and handling shall be in accordance with the following special requirements:

1. Geotextiles shall be supplied in rolls wrapped in impermeable and opaque protective covers. Geotextile rolls shall be marked or tagged with the following information:

a. Manufacturers name.

b. Product identification.

c. Lot number.

d. Roll number.

e. Roll dimensions.

2. During shipment and storage, geotextile rolls shall be protected from ultraviolet light exposure, precipitation, or other inundation, mud, dirt, dust, puncture, cutting or any other damaging or deleterious condition.

3. For long-term outdoor storage of geotextile rolls, the material shall be placed on pallets, or dunnage, off the ground and covered with a light- colored, heat reflective, opaque cover.

PART 2 PRODUCTS

2.01 NONWOVEN GEOTEXTILE

A. The geotextile shall be nonwoven polypropylene filaments, formed into a stable network by needle . The geotextile shall be inert to commonly encountered chemicals and hydrocarbons and shall also be resistant to mildew, rot, ultraviolet light exposure, insects, and rodents.

B. The geotextile shall be colored (not white) to avoid "snow blindness" of the installation and inspection personnel.

C. The geotextile shall contain a UV inhibitor.

D. The geotextile weight at specific locations and uses shall be as specified on the Drawings.

E. The minimum average roll value (MARV), in the weakest principal direction, for properties of any individual roll tested from a particular shipment shall be equal to or in excess of the values listed below:

02773-3 Property Test Method Value Weight ASTM D5261 12 oz/sq. yd. Grab Tensile Strength ASTM D4632 300 lbs. Grab Tensile Elongation ASTM D4632 50% Puncture Strength ASTM D4833 175 lbs. Trapezoid Tear Strength ASTM D4533 115 lbs. Water Flow Rate ASTM D4491 60 gpm/sq ft UV Resistance ASTM G53 70% strength retained @ 500 hours MARV is based on typical values minus 2 standard deviations

F. During manufacturing, the manufacturer shall test the geotextile material at a frequency of not less than every 50,000 sf of geotextile material produced. The manufacturer shall certify that the physical properties of the finished geotextile material meets or exceeds these project specifications and submit certified test reports to validate conformance.

G. Geotextile Manufacturers:

a. Agru America, Inc.

b. American Engineering Fabrics

c. GSE Lining Technology, Inc.

d. Propex Geotextile Systems

e. SKAPS Industries

f. TenCate Geosynthetics North America

g. US Fabrics, Inc.

h. Or approved equal.

PART 3 EXECUTION

3.01 PROTECTION

A. The Contractor shall take all necessary precautions to protect the soil subgrade from damage during placement of geotextile.

02773-4 B. Damaged areas shall be repaired or removed and replaced at Construction Manager’s direction.

3.02 GEOTEXTILE INSTALLATION

A. Prior to installation of the geotextile, the Contractor shall inspect the soil subgrade or concrete surface which the geotextile shall be placed. All foreign matter and protrusions which may damage the geotextile shall be removed, as directed by Construction Manager.

B. The Contractor shall handle all geotextile in such a manner to prevent damage and in accordance with the following minimum requirements:

1. To protect against wind, all geotextiles shall be weighted with sandbags or the equivalent. Sandbags losing their contents shall be removed from construction area and replaced. Spillage shall be immediately cleaned up.

2. Care shall be taken to protect other geosynthetic materials from damage that could be caused by the cutting of the geotextile fabric.

3. Geotextile shall be deployed in a manner to avoid wrinkles. Any wrinkles shall be removed by repositioning the geotextile prior to anchoring or seaming adjacent edges.

4. Any cuts to the geotextile shall be made with a geotextile cutter and done in a manner to prevent damage to the adjacent geosynthetic materials.

5. An examination of the geotextile surface after installation shall be conducted to ensure that no potentially harmful foreign objects are present above or below the geotextile. Any foreign objects so encountered shall be removed by the Contractor.

6. Geotextile shall not be exposed to sunlight or ultra-violet rays prior to installation. Additionally, to minimize exposure at the site, the geotextile shall not be placed, and exposed to sunlight and ultra-violet rays for more than 7 calendar days in advance of the time it will be covered by the composite drainage course material.

C. No wheeled vehicles will be permitted on the geotextile.

3.03 GEOTEXTILE SEAMING

A. Geotextile shall be overlapped a minimum of 6 inches and heat welded 3 inch wide by continuous, unless otherwise shown on the Drawings.

02773-5 3.04 GEOTEXTILE REPAIRS

A. Holes or tears in the geotextile shall be repaired with a patch made from the same geotextile material, and shall be a minimum of 6 inches larger in all directions than the area to be repaired, and shall be continuously heat welded all around.

B. Care shall be taken to remove any soil or other material that may have penetrated the torn geotextile.

**END OF SECTION**

02773-6 SECTION 02774

HDPE LINER

PART 1 GENERAL

1.01 DESCRIPTION

A. This Section includes furnishing and installing materials for modifications to the existing high density polyethylene (HDPE) geomembrane liner and appurtenant Work as shown on the Drawings and specified in this Section.

B. Reservoir is currently lined with an existing 60-mil HDPE liner.

1.02 REFERENCES

A. This section contains references to the following documents. They are a part of this section as specified and modified. Where a referenced document contains references to other standards, those documents are included as references under this section as if referenced directly. In the event of conflict between the requirements of this section and those of the listed documents, the requirements of this section shall prevail.

B. Unless otherwise specified, references to documents shall mean the documents in effect at the time of Advertisement for Bids or Invitation to Bid (or on the effective date of the Agreement if there were no Bids). If referenced documents have been discontinued by the issuing organization, references to those documents shall mean the replacement documents issued or otherwise identified by that organization or, if there are no replacement documents, the last version of the document before it was discontinued. Where document dates are given in the following listing, references to those documents shall mean the specific document version associated with that date, regardless of whether the document has been superseded by a version with a later date, discontinued or replaced.

C. Except as otherwise indicated in this Section, the Contractor shall comply with the latest edition of the Uniform Standard Specifications and Details for Public Works Constructions by the Maricopa Association of Governments (MAG).

Reference Title ASTM D1004 Test Method for Initial Tear Resistance of Plastic Film and Sheeting ASTM D1238 Standard Test Method for Flow Rates of Thermoplastics by Plastometer ASTM D1505 Test Method for Density of Plastics by the Density-Gradient Technique ASTM D1603 Test Method for Carbon Black in Olefin Plastics

02774-1 Reference Title ASTM D3895 Standard Test Method for Oxidative-Induction Time of Polyolefins by Differential Scanning Calorimetry ASTM D4833 Standard Test Method for Index Puncture Resistance of Geotextiles, Geomembranes, and Related Products ASTM D5199 Standard Test Method for Measuring Nominal Thickness of Geotextiles and Geomembranes ASTM D5397 Standard Test Method for Evaluation of Stress Crack Resistance of Polyolefin Geomembranes Using Notched Constant Tensile Load Test ASTM D5596 Standard Test Method for Microscopic Evaluation of the Dispersion of Carbon Black in Polyolefin Geosynthetics ASTM D5994 Standard Test Method for Measuring Thickness of Textured Geomembranes ASTM D6392 Standard Test Method for Determining the Integrity of Non-reinforced Geomembrane Seams Produced Using Thermo-Fusion Methods ASTM D6693 Standard Test Method for Determining Tensile Properties of Nonreinforced Polyethylene and Nonreinforced Flexible Polypropylene Gemembranes

1.03 SUBMITTALS

A. Submittals shall be made in accordance with Specifications Section 01300, Submittals, and the following special provisions provided herein.

B. Shop Drawings:

1. Contractor shall submit information for proposed details, seaming procedures, or methods of construction to perform required repairs.

2. The Contractor shall provide all additional details required but not provided in the Drawings or Specifications. Those details provided by the Contractor shall be subject to the review and approval of Construction Manager prior to commencement of Work.

C. The Contractor shall submit the Manufacturer name and qualifications of HDPE geomembrane materials.

D. Material Certifications:

1. The Contractor shall submit written certification that the resin used for the HDPE geomembrane liner material and all required appurtenances complies with the material requirements stated in this Section.

02774-2 2. The Contractor shall submit written statement certifying that no recycled polymer and no more than 10% rework of the same type of material is added to the resin.

3. The Contractor shall submit the manufacturer’s product data sheet(s) indicating the material(s) proposed for conformance with the material requirements stated in this Section.

E. Material Safety Data Sheets (MSDS):

1. Material Safety Data Sheets for all cleaners, solvents, caulks, adhesives, and other chemicals proposed for use shall be submitted to Construction Manager for review.

2. A copy of all Material Safety Data Sheets shall be posted on the Contractor's job bulletin board at all times.

1.04 REGULATORY REQUIREMENTS

A. The Contractor shall obtain permits and comply with all regulations from all regulatory agencies as required for the use of solvents, adhesives, and other chemicals.

B. The Contractor shall ensure that their employees, subcontractors, and others exposed to solvents, adhesives, and other chemicals comply with limitations for exposure and handling in accordance with OSHA, and other regulatory agencies’ regulations.

1.05 QUALIFICATIONS

A. Master Seamer

1. The Contractor shall provide a minimum of one master seamer for the HDPE geomembrane liner repair Work.

2. The master seamer shall have not less than 1 million feet of HDPE geomembrane liner seaming work using the same types of seaming procedures proposed for this Project.

1.06 QUALITY ASSURANCE

A. Quality Assurance Plan:

1. The Contractor shall thoroughly review and comprehend the Drawings and Specifications prior to the development of the job specific Quality Assurance Plan. The Contractor's Quality Assurance Plan shall be in accordance with the Specifications. Any deviations or conflicts with the Specifications shall be clearly marked, immediately brought to Construction Manager’s attention, and shall not be used without the Construction Manager’s prior written consent.

02774-3 2. The Contractor's quality assurance plan shall state how the following items shall be accomplished and shall include sample forms to be used to document each quality assurance activity. The major heading and subheadings list those tasks, as a minimum, which shall be included in the Quality Assurance Plan. The Contractor

a. Material storage and handling

b. Deployment and installation

c. Seaming

d. Seam testing samples

B. Field Seaming Demonstration:

1. The Contractor shall conduct a field demonstration utilizing the seaming procedures, equipment, calibration procedures, and all other aspects of the proposed seaming methods.

2. The Contractor shall conduct on site seam strength tests in compliance with the requirements stated in this Section.

3. The Contractor shall provide seaming demonstration for each type of seaming method proposed (e.g., wedge welder, extrusion, etc.).

4. At least two 10-foot long demonstration seams shall be made.

5. Samples may be taken from the demonstration seams and tested by Construction Manager.

1.07 DELIVERY, STORAGE, AND HANDLING

A. Each roll of HDPE geomembrane material delivered to the site shall be labeled by the manufacturer and shall include the manufacturer’s name, product identification, material thickness, roll length, roll width, and roll number. Each HDPE geomembrane material roll shall be wrapped in cardboard or other suitable material and enclosed in an opaque, light-reflective airtight bag to protect and prevent damage during shipment and storage.

B. Each roll of HDPE geomembrane material shall be adequately packaged and protected to prevent damage to the material and facilitate off-loading.

C. On-site storage shall protect the HDPE geomembrane material from punctures, abrasions and excessive dirt and moisture. The storage area shall be level, smooth, dry, free draining, and adequately protected. HDPE geomembrane materials shall not be stored on wooden pallets.

02774-4 1.08 PROJECT/SITE CONDITIONS

A. Safety Requirements

1. Construction personnel shall be trained in and be instructed on the use of barrier creams or gloves as necessary, for working with the solvents and cleaning agents. All used cloths impregnated with solvent shall be kept separately in metal containers with close-fitting lids suitable for use as necessary and in compliance with the requirements of the International Fire Code (IFC) and local Fire Marshal requirements. Construction personnel at the site will not be permitted to have open flames within 50 feet of any open solvent container and will be required to wear and be trained in the use of appropriate approved breathing apparatus, where necessary.

PART 2 PRODUCTS

2.01 MANUFACTURERS

A. The HDPE geomembrane liner material shall be manufactured by an experienced firm regularly engaged in manufacturing HDPE geomembrane liner material for a minimum period of 5 years immediately prior to the award of the contract and which has produced a minimum of 10 million square feet of HDPE geomembrane liner materials.

B. HDPE geomembrane liner material manufacturer shall be:

1. Agru America, Inc.

2. GSE Lining Technology, Inc.

3. Or approved equal.

2.02 MATERIALS

A. All HDPE geomembrane liner material and HDPE accessories shall be provided from a single HDPE manufacturer.

B. All HDPE geomembrane liner accessories shall be the same HDPE resin as the HDPE geomembrane liner material.

C. HDPE Lining Resin:

1. Resin shall be new, first quality, compounded and manufactured specifically for producing HDPE geomembrane liner material.

2. Natural resin (without carbon black) shall meet the following minimum requirements:

02774-5 Property Test Test Method Value Density ASTM D1505 0.932 g/cm3 Melt Flow Index ASTM D1238 ≤ 1.0 g/10 min. OIT ASTM D3895 100 min. (1 atm/200°C)

D. HDPE Geomembrane Lining Rolls

1. Geomembrane liner material shall be smooth both sides, high density polyethylene (HDPE) geomembrane material produced from specially formulated, virgin polyethylene resin. Polyethylene resin shall be specially designed for flexible geomembrane applications.

2. HDPE geomembrane liner material shall contain approximately 97.5% polyethylene, 2.5% carbon black, and trace amounts of antioxidants and heat stabilizers. No other additives, fillers, or extenders shall be utilized. HDPE geomembrane liner material shall have mechanical properties, environmental stress crack resistance, dimensional stability, and thermal aging characteristics for the applications shown on the Drawings. The HDPE geomembrane liner material shall be a flexible, durable, watertight product free of pinholes, blisters, and contaminates and shall be subjected to a water environment.

3. HDPE geomembrane liner material shall contain a minimum of 2.0% carbon black, in accordance with ASTM D1603. Carbon black dispersion (to near spherical agglomerates) shall be in accordance with ASTM D5596, where 9 of 10 views shall be category 1 or 2 and no more than 1 view category 3.

4. HDPE geomembrane liner material shall be free of holes, pinholes as verified by on-line electrical detection, bubbles, blisters, excessive contamination by foreign matter, and nicks and cuts on roll edges.

5. HDPE geomembrane liner material is to be supplied in roll form. Each roll is to be identified with labels indicating roll number, thickness, length, width, and material manufacturer.

6. HDPE geomembrane liner material produced at the factory shall be inspected prior to shipment for compliance with the physical property requirements this Section. All HDPE geomembrane liner material shall be tested by an acceptable method of inspecting for pinholes.

Property Test Test Test Method Frequency Value (min.) Thickness ASTM D5199 Every roll 60 mil (min. avg.) 54 mil (min.) Density ASTM D1505 200,000 lb. 0.94 g/cm3

02774-6 Property Test Test Test Method Frequency Value (min.) Tensile Properties ASTM D6693 20,000 lb. (ea. direction) Type IV dumbell 2 in./min. Strength at Break 243 lb./in. Strength at Yield 130 lb./in. Elongation at Break G.L. 2.0 in. 700% Elongation at Yield G.L. 1.3 in. 13 % Tear Resistance ASTM D1004 45,000 lb. 42 lb. Puncture Resistance ASTM D4833 45,000 lb. 119 lb. Carbon Black Content ASTM D1603 20,000 lb. 2.0% Notched Constant ASTM D5397 200,000 lb. 400 hr. Tensile Load Appendix Oxidative Induction ASTM D3895, 200,000 lb. > 100 min. Time 200°C (nominal) O2, 1 atm

7. The HDPE geomembrane material manufacturer shall certify that the physical properties of the finished materials meet or exceed the Specifications and submit certified test reports to validate conformance

E. HDPE Embedment Strip

1. HDPE embedment strip material shall be made from same type resin as the HDPE geomembrane liner material.

2. Additives shall be thoroughly dispersed.

3. Materials shall be free of contamination by moisture or foreign matter.

F. HDPE Extrudate Rod

1. HDPE extrudate material shall be made from same type resin as the HDPE geomembrane liner material.

2. Additives shall be thoroughly dispersed.

3. Materials shall be free of contamination by moisture or foreign matter.

G. Patches

1. Patches shall be the same material as the HDPE geomembrane liner material.

02774-7 2.03 EQUIPMENT

A. Welding equipment and accessories shall meet the following requirements:

1. Gauges showing temperatures in apparatus.

2. An adequate number of welding apparatus shall be available to avoid delaying Work.

3. Power source must be capable of providing constant voltage under combined line load.

PART 3 EXECUTION

3.01 PREPARATION

A. Protection:

1. Under no circumstances shall the HDPE geomembrane liner be subjected to rough treatment or have sandbags, equipment, or other material dragged across its surface. Neither materials nor workers shall slide down slopes on top of the HDPE geomembrane liner. All scuffed surfaces resulting from abuse of any kind by the Contractor, Construction Manager personnel overseeing the Work, or others, shall be repaired by the Contractor in accordance with the Specifications.

2. All persons walking on the HDPE geomembrane liner material shall wear smooth rubber-soled shoes. Shoes with patterns in relief (like those popularly known as "sneakers") that could pick up rocks and debris will not be permitted.

3. The Contractor shall protect the existing reservoir liner material by deploying a 22 ounce nonwoven geotextile in all high foot traffic areas. This provision shall be included in the Contractor’s Quality Assurance Plan.

4. Scissors used in the Work shall have blades with rounded points. Marking pens or pencils used for identifying areas requiring Work shall not contain wax, oil, or grease.

5. No wheeled vehicles will be permitted on the HDPE geomembrane liner. Miscellaneous equipment with rubber pneumatic tires with an effective contact pressure on the HDPE geomembrane liner less than 6 pounds per square inch may be permitted, with the prior written approval from Construction Manager.

02774-8 6. The Contractor shall make all reasonable efforts to protect the existing HDPE liner material from pinholes, cuts, abrasions, and other damage.

7. All large tools are to have smooth base plates or shoes.

8. Smoking is not permitted on the HDPE geomembrane liner.

9. The existing HDPE geomembrane liner materials, connections/seals to structures, anchorage, penetrations, and other ancillary liner items shall be protected at all times performing the Work. Protection shall include existing floating cover removal, sediment removal, liner cleaning, and new composite geomembrane liner and new geomembrane floating cover installation.

3.02 INSTALLATION

A. Field Seaming:

1. All field seaming shall be performed by or under the direct supervision of the on-site master seamer.

2. Seams shall be welded along the entire panel edges and patches.

3. To the maximum extent possible, orient seams shall be oriented parallel to slope (e.g., down slope), not across slope. Minimize number of field seams in corners, odd-shaped geometric locations and outside corners.

4. Adjacent panels at seams shall be aligned and overlapped a minimum of 6 inches, as shown on the Drawings, and consistent with the requirements of the welding equipment.

5. All seams (field and factory) shall be staggered a minimum of 12 inches to ensure that no more than three layers of material meet at a joint.

6. Machine-made heat seams shall be used on all field seams wherever practical.

7. All machine heat seaming equipment shall be equipped with gauges which monitor voltage and temperature.

8. Field seams shall not be made if the ambient temperature or humidity would result in inferior seams.

9. HDPE geomembrane material overlap contact surfaces of material to be seamed shall be wiped clean with a cloth until all foreign matter, dust, and dirt has been removed. Only clean, white, lint-free, cotton cloths shall be used in the Work. Cleaning of contact surfaces shall not be completed more than 10 minutes ahead of seaming. When conditions are adverse to

02774-9 proper workmanship, such as high heat or winds, or when other conditions increase the probability of dirt or other foreign material being deposited on the contact surfaces, the time between cleaning and seaming shall be reduced as necessary to produce acceptable seams.

10. Hot Wedge Welding:

a. Welding apparatus shall be a self-propelled device equipped with an electronic controller which displays applicable temperatures.

b. Clean seam area of dust, mud, moisture and debris immediately ahead of hot wedge welder.

c. Protect against moisture build-up between sheets.

11. Extrusion Welding:

a. Hot-air tack adjacent pieces together using procedures that do not damage the geomembrane.

b. Clean geomembrane surfaces by disc grinder or equivalent.

c. Purge welding apparatus of heat-degraded extrudate before welding.

12. HDPE geomembrane liner materials to be joined in the field shall be lapped. After the initial seal of the lap joint has been made, all exposed free edges of the liner material shall be resealed, using the same procedure, to eliminate all free edges. The top edge of all seams shall be fully bonded. Loose edges will not be allowed on the top side of the HDPE geomembrane liner.

13. Butt joints shall be used only where lap joints are not possible and as approved by Construction Manager. Butt joints shall be formed using joint cover strips made from the same HDPE liner material, continuous in length, and as shown on the Drawings. The joint cover strip shall be centered over the butt joint and shall be installed in accordance with the same procedures for lap joints specified herein.

14. Care shall be taken to avoid fishmouths, pleats, folds, and tucks in seams. Any such defects shall be prevented by tugging on the seam just completed in the opposite direction from which the seam is progressing, during the seaming process. The Contractor’s seaming crew shall give continuous attention to the elimination of all such defects to prevent their occurrence. Regardless of the location or cause of such defects, they shall be slit out far enough from the seam to dissipate the defect. The slit edges shall then be lapped and field seamed. Wherever the lap width is less than 4-inches,

02774-10 the defect shall be repaired with a joint cover strip made from the same HDPE geomembrane liner material.

B. HDPE Embedment Strip

1. HDPE embedment strip shall be installed as shown on the Drawings.

2. HDPE embedment strip shall be adequately support from concrete forms or falsework to ensure the proper location and straight alignment.

3. HDPE embedment strip shall be completely embedded in concrete. Air voids and gaps under the embedment strip shall not be permitted and shall be removed during the placement of concrete.

4. Screw holes or other temporary means to support the HDPE embedment strip during installation and concrete placement shall be sealed with HDPE extrusion bead. The extrusion bead shall be ground smooth with top of HDPE embedment strip.

5. HDPE embedment strip ends shall be cut square at end splices and at 45 degree angle for square corner splices. HDPE embedment strip splices shall be joined with a HDPE extrusion bead across the full width of the HDPE embedment strip. The extrusion bead shall be ground smooth with top of HDPE embedment strip.

3.03 REPAIRS

A. All punctures, cuts, tears, abrasions, and similar damage or abuse to the HDPE geomembrane liner material shall be repaired to the satisfaction of Construction Manager.

B. Damaged HDPE geomembrane shall be removed and replaced with acceptable HDPE geomembrane if damage cannot be repaired to the satisfaction of Construction Manager.

C. Patches shall be cut from flat, unwrinkled parent material of the material being patched, and shall be free of defects, field seams, and factory seams. Patches shall be of sufficient size to extend a minimum of 6 inches in all directions beyond the limits of any puncture, cut, tear, or abrasion. Patches over fishmouths, pleats, folds, and tucks shall extend a minimum of 6 inches each side of the defect.

D. All patches shall be neat in appearance with corners rounded to a minimum 1-inch radius.

E. Patches shall be applied as specified previously for extrusion welding. The parent material shall be carefully pulled and held flat in the area to be patched as to provide an acceptable surface to receive the patch.

02774-11 3.04 QUALITY ASSURANCE / QUALITY CONTROL

A. The Contractor’s Quality Assurance / Quality Control testing shall keep pace with the deployment and seaming operations to identify all problems at the earliest possible point in time.

B. All HDPE geomembrane panels and seams will be examined by Construction Manager for defects, holes, blisters, undispersed raw materials, and any sign of contamination by foreign matter. The HDPE geomembrane surface shall be clean at the time of examination. Each suspect location shall be repaired and all repairs shall be non-destructively tested.

C. Construction Manager and Contractor shall visually inspect all material to be included in the Work, and compare panel identification numbers with those on the certifications provided by the manufacturer to assure delivery of the appropriate material. Damage to HDPE geomembrane liner during installation shall be repaired in accordance with this Section. If Construction Manager determines that any damage cannot adequately be repaired, the damaged material shall be removed and replaced.

D. Prior to installation of the HDPE geomembrane at the site, the Contractor shall provide Construction Manager with copies of manufacturer material certifications and a copy of quality control test results for all panels to be supplied, verifying conformance with this Section. The location of any defects and repairs and all necessary retesting results shall be documented.

E. The Contractor shall conduct both destructive and non-destructive testing on seams during the HDPE geomembrane installation, as part of the Construction Quality Control Program.

F. Equipment Calibration Trial Seams

1. The seaming equipment shall be calibrated in accordance with the Contractor’s quality assurance plan; but shall not be less than at the beginning of each shift, every 4 hours, and any significant environmental changes.

2. Calibration trial seam samples shall be collected and tested in accordance with the provisions stated herein (peel strength and bonded strength). The calibration seam verification testing may be performed by on-site personnel. The Contractor shall submit the daily calibration test results to Construction Manager as part of the final quality assurance report.

3. Calibration trial seam samples shall be performed under the same surface preparation, environmental conditions (temperature, humidity, wind), and underlying substrate support.

02774-12 4. For each calibration trial seam sample, a minimum of (6) 1-inch wide by 6-inch long test coupons shall be cut for on-site testing. Three coupons shall be tested for peel strength and three coupons for bonded shear strength in accordance with the provisions herein.

5. No production welding shall be performed until all calibration trial field seams are tested and pass. Testing of the calibration trial seams shall be performed in the presence of Construction Manager.

G. Seam Testing:

1. The Contractor shall conduct calibration trial seams and destructive seam tests performed, at their own expense. All testing shall be performed to ensure that seams meet the minim strength requirements stated herein.

2. Peel Strength

a. Peel strength test samples shall be tested in accordance with ASTM D6392.

b. Minimum peel strength for fusion welds is 98 pounds per inch seam width.

c. Minimum peel strength for extrusion welds is 78 pounds per inch seam width.

d. The material break shall occur in the geomembrane liner material (film tearing bond, FTB), rather than peel separation in the plane of the seam.

3. Bonded Shear strength

a. Bonded shear strength test samples shall be tested in accordance with ASTM D6392.

b. Minimum bonded shear strength for fusion and extrusion welds is 121 pounds per inch seam width.

4. Test results not meeting these requirements shall be cause for rejection of the seam from which the test sample was taken.

H. Destructive Field Seams Test Samples:

1. Destructive field seam samples shall be cut from the installed HDPE geomembrane at a minimum frequency of one sample per 500 linear feet of seam, excluding repair seam length. A minimum of one seam sample shall be obtained for each seaming machine/operator combination for each day, or as directed by Construction Manager. The cutout sections shall be 12 inches wide by 36 inches long with the seam centered lengthwise. A 1- inch wide specimen shall be cut from each end of the sample, and these

02774-13 two specimens shall be tested for peel strength in the field in accordance with this Section. The remaining sample shall be cut into parts and distributed as follows:

a. 12-inch by 12-inch sample for Contractor field testing.

b. 12-inch by 12-inch sample for Contractor independent laboratory testing.

2. A minimum of (3) test specimens for each of the above tests (peel strength and bonded shear strength) shall be taken from each seam test sample.

3. All seam test samples shall be provided by the Contractor at their expense.

4. Destructive field seam test samples shall be numbered, dated, and identified as to the personnel making the seam from which the sample is taken, the seaming method being used, and the temperature and weather conditions at the time of seaming. Each test sample shall be keyed to its general location on the seam from which it is taken by appropriate notes or markings on a drawing, furnished by the Contractor, for future reference.

5. The 12-inch by 12-inch laboratory sample will provide (3) specimens for shear testing and (3) specimens for peel testing. Specimens that will be subject to peel and shear testing shall be selected alternately from the sample. The laboratory shall report the locus of break code for each specimen according to the definitions in accordance with ASTM D 6392. The laboratory sample will be considered acceptable only if all 10 specimens meet the minimum requirements. The specimen will be considered a failure if any of the following occur:

a. In the shear test, the bond of the seam fails or the material breaks at a stress lower than specified.

b. In the peel test, the two sheets comprising the seam separate at a peak stress lower than specified. Complete peel separation of the seam is allowable.

c. In the shear or peel test, locus of break codes AD, AD-BRK, BRK, and SE are reported.

6. If a sample fails destructive testing, the welding path must be retraced to intermediate locations at least 10-feet in each direction from the location of the sample that failed the test, and a second sample shall be taken for an additional field test. If the tracking samples pass, the seam must be reconstructed between the location of the two tracking samples and the original sampled location. If the tracking sample fails, this process must be repeated. The seam between two passing test locations shall be capped,

02774-14 the cap seams shall be nondestructively tested, and shall include one field peel and shear test location along the reconstructed seam.

I. If any test results (calibration trial seam samples or destructive field seam test samples) are not satisfactory, Construction Manager, at their discretion, may require that additional sampling and testing be done at the Contractor’s expense.

J. In addition to all sampling and testing described above, Construction Manager may, at their discretion, require the Contractor to provide Construction Manager with additional samples of any field or factory seam, for testing by the Construction Manager, at the Owner’s expense.

K. The testing laboratory and the Contractor shall certify all test results. Five copies of the certification and test results shall be submitted to Construction Manager.

L. Vacuum Box Testing:

1. The Contractor shall perform field vacuum box tests on all field and factory T-seams and all repairs and patches.

2. Vacuum box testing shall be performed in accordance with ASTM D5641.

3. Vacuum box testing shall be performed after all cap strips and patches have been applied.

4. The vacuum box apparatus shall be a rigid housing with a transparent window on top to allow observance of the seam wile under test. The seal to the liner shall be a gasket-type seal capable of a tight seal without leaks under the required test pressure.

5. A soap solution shall be applied to the tested area prior to the placement of the vacuum box apparatus.

6. The vacuum box shall be capable of holding a vacuum pressure of not less than 4 psi without any time limitations.

7. The vacuum box shall maintain a vacuum over the seam portion being tested for a minimum of 10 seconds, during which time the seam shall be examined for the formation of bubbles, which is indicative of a leak.

8. Vacuum testing shall be performed by the Contractor in the presence of Construction Manager during daylight hours.

M. Air Pressure Testing

1. The Contractor shall perform air pressure testing for the entire length of all dual seam wedge welds.

02774-15 2. Air pressure testing shall be performed in accordance with ASTM D5820.

3. Air pressure testing shall be performed at a minimum pressure of 30 psi and held a minimum of 5 minutes. Air pressure reduction shall not exceed 3 psi.

N. Testing:

1. The Contractor shall perform nondestructive, spark testing for the entire length of the extrusion welds where vacuum box testing cannot be performed.

2. Spark testing shall be performed in accordance with ASTM D6365 and as stated herein.

3. Equipment for spark testing shall include, but not be limited to, hand-held holiday spark tester and conductive wand that generated a high voltage.

4. Testing procedure performed by the Contractor shall include placing a copper wire within the material overlap beneath the extrusion seam prior to welding.

5. A trial seam containing a non-welded segment shall be subject to a calibration test to ensure that such defect (non-welded segment) will be identified under the planned machine settings and procedures.

6. Upon completion of the extrusion weld, enable the spark tester and hold the wand approximately 1-inch above the extrusion weld passing slowly over the entire weld length.

7. If there is no spark, the extrusion weld is considered satisfactory. A spark indicates a defect in the seam area. The defect area shall be marked, repaired, and retested until a passing test result is obtained.

3.05 CLEANING

A. Cleanup within the reservoir shall be an ongoing responsibility of the Contractor throughout the course of the Work. Care shall be taken to insure that no dirt, scrap material, trash, tools, or other unwanted materials are trapped beneath the existing or new HDPE geomembrane liner material.

**END OF SECTION**

02774-16 SECTION 02778

FLEXIBLE GEOMEMBRANE FLOATING COVER AND BAFFLES

PART 1 - GENERAL

1.01 DESCRIPTION

A. This Section includes furnishing and installing a new weight tensioned Ethylene Interpolymer Alloy (EIA) flexible geomembrane floating cover and baffles and appurtenances as shown on the Drawings and specified in this Section.

1.02 REFERENCES

A. This section contains references to the following documents. They are a part of this section as specified and modified. Where a referenced document contains references to other standards, those documents are included as references under this section as if referenced directly. In the event of conflict between the requirements of this section and those of the listed documents, the requirements of this section shall prevail.

B. Unless otherwise specified, references to documents shall mean the documents in effect at the time of Advertisement for Bids or Invitation to Bid (or on the effective date of the Agreement if there were no Bids). If referenced documents have been discontinued by the issuing organization, references to those documents shall mean the replacement documents issued or otherwise identified by that organization or, if there are no replacement documents, the last version of the document before it was discontinued. Where document dates are given in the following listing, references to those documents shall mean the specific document version associated with that date, regardless of whether the document has been superseded by a version with a later date, discontinued or replaced.

C. Except as otherwise indicated in this Section, the Contractor shall comply with the latest edition of the Uniform Standard Specifications and Details for Public Works Constructions by the Maricopa Association of Governments (MAG).

Reference Title ASTM A276 Standard Specification for Bars and Shapes ASTM D696 Standard Test Method for Coefficient of Linear Thermal Expansion of Plastics Between −30°C and 30°C with a Vitreous Silica Dilatometer ASTM D741 Methods of Measuring Dimensions of Rigid Rods Used in Electrical Insulation ASTM D751 Standard Test Methods for Coated Fabrics

02778 - 1 Reference Title ASTM D1204 Standard Test Method for Linear Dimensional Changes of Nonrigid Thermoplastic Sheeting or Film at Elevated Temperature ASTM D2000 Standard Classification System for Rubber Products in Automotive Applications ASTM D2136 Test Method for Coated Fabrics-Low-Temperature Bend Test ASTM D3389 Standard Test Method for Coated Fabrics Abrasion Resistance (Rotary Platform Abrader) ASTM D4833 Standard Test Method for Index Puncture Resistance of Geomembranes and Related Products ASTM F405 Standard Specification for Corrugated Polyethylene (PE) Pipe and Fittings ASTM G153 Standard Practice for Operating Enclosed Carbon Arc Light Apparatus for Exposure of Nonmetallic Materials FTMS 101C, Federal Test Method Standard, Puncture Resistance and Elongation Test Method 2031

1.03 SUBMITTALS

A. Submittals shall be made in accordance with Specifications Section 01300, Submittals, and the following special provisions provided herein.

B. The Contractor shall submit the following with their bid:

1. Proposed EIA flexible geomembrane manufacturer name and qualifications

2. Proposed fabricator name and qualifications

3. Installation Contractor qualifications

C. Liner Protection Plan

1. The Contractor shall submit, for the Construction Manager’s approval, a written plan which addresses the Contractor’s measures to protect the existing geomembrane liner prior to starting Work.

2. The protection plan shall address, as a minimum, the Contractor’s proposed method to protect the existing geomembrane liner, the stockpile and storage locations of materials within the basin, methods for moving and deploying materials, methods of providing ingress and egress, etc.

02778 - 2 D. Shop Drawings:

1. The Contractor shall submit, for the Construction Manager’s approval, shop drawings showing the floating cover panel layout with proposed size, number, position, weight, and sequence of placing all factory fabricated panels; the overlap and direction of all factory joints on each panel; and location and overlap of all field joints.

2. If the Contractor proposes alternate design details, seaming procedures or methods of construction which are different than those shown on the Drawings and stated in the Specifications, the Contractor shall submit complete shop drawings and other pertinent information shall be submitted to the Construction Manager for approval. Such proposed alternates shall not be used unless approved in writing by the Construction Manager prior to the Contractor starting that portion of Work.

3. Approval of any alternate design, method, or procedure proposed by the Contractor may be granted only if, in the Construction Manager’s sole opinion, such proposal will produce an end result equal to or better than the design, method, or procedure shown in the Drawings and Specifications.

4. The Contractor shall provide all additional details required but not provided in the Drawings or Specifications. Those details provided by the Contractor shall be subject to the review and approval of the Construction Manager prior to commencement of Work.

E. Procedures:

1. Contractor’s thermal seaming procedures including surface preparation, cleaning, prewelding procedures, and testing.

2. Contractor’s extrusion welding procedures including surface preparation, cleaning, prewelding procedures, and testing.

3. Contractor’s procedures for application of EIA sealant including surface preparation, cleaning, and application procedures.

F. Product Information:

1. EIA flexible geomembrane floating cover material product data.

2. EIA extrusion weld rod material product data.

3. EIA adhesive material product data and application recommendations.

4. EIA sealant material product data and application recommendations.

5. Check valve manufacturer product data and written installation instructions.

02778 - 3 G. Samples

1. Prior to ordering materials, Contractor shall submit the following material samples to the Construction Manager for approval.

a. EIA flexible geomembrane floating cover material, four 8-inch by 10-inch.

2. EIA textured walkway, four 4-inch by textured walkway full width.

H. Material Safety Data Sheets (MSDS):

1. Material Safety Data Sheets for all cleaners, solvents, caulks, adhesives, and other chemicals proposed for use shall be submitted to the Construction Manager for review.

2. A copy of all Material Safety Data Sheets shall be posted on the Contractor's job bulletin board at all times.

I. Certified Testing Laboratories:

1. The name of Contractor’s proposed independent, certified testing laboratory shall be submitted to the Construction Manager for approval a minimum of 10 working days prior to any material testing.

2. The laboratory shall be certified by the Geosynthetic Research Institute (GRI).

J. Manufacturer’s Quality Assurance Plan:

1. The Contractor shall submit the reinforced flexible geomembrane manufacturer’s quality assurance plan for the Construction Manager’s review and approval.

2. Prior to the Contractor’s submittal to the Construction Manager, the Contractor shall have reviewed and approved the manufacturer’s quality assurance plan.

3. The manufacturer’s quality assurance plan shall be approved in writing by the Construction Manager prior to manufacturing EIA flexible geomembrane floating cover materials.

K. Fabricator’s Quality Assurance Plan:

1. The Contractor shall submit the reinforced flexible geomembrane fabricator’s quality assurance plan for the Construction Manager’s review and approval.

2. Prior to the Contractor’s submittal to the Construction Manager, the Contractor shall have reviewed and approved the fabricator’s quality assurance plan.

02778 - 4 3. The fabricator’s quality assurance plan shall be approved in writing by the Construction Manager prior to fabricating the reinforced flexible geomembrane floating cover material into panels.

4. Prior to installation of the panels, the fabricator shall provide the Construction Manager written certification that the factory seams were inspected and tested in accordance with these Specifications.

L. Contractor’s Quality Assurance Plan:

1. Prior to installing EIA flexible geomembrane floating cover materials, the Contractor shall submit a Project-specific quality assurance plan covering installation for the Construction Manager's review and approval.

2. The Contractor’s quality assurance plan shall be approved in writing by the Construction Manager prior to starting any on-site EIA flexible geomembrane floating cover installation Work.

M. Operations and Maintenance Manual

1. The Contractor shall submit floating cover and baffles operations and maintenance manual to the Construction Manager for review and approval.

1.04 REGULATORY REQUIREMENTS

A. The Contractor shall obtain permits and comply with all regulations from all regulatory agencies as required for the use of solvents, adhesives, and other chemicals.

B. The Contractor shall ensure that their employees, subcontractors, and others exposed to solvents, adhesives, and other chemicals comply with limitations for exposure and handling in accordance with OSHA, and other regulatory agencies’ regulations.

1.05 QUALIFICATIONS

A. Specialty Installation Contractor:

1. The Work shall be performed by a specialty installation contractor who has been regularly engaged in the installation of reinforced flexible geomembrane floating covers for a minimum period of 4 years immediately prior to the bid opening date and shall have installed not less than 1 million square feet of EIA and/or reinforced flexible geomembrane material. Other relevant experience may be considered, in which case the Construction Manager’s opinion as to the acceptability of all experience shall be final and conclusive.

2. With their bid, the Contractor shall provide to the Construction Manager the Contractor’s representative experience consisting of not less than five (5) projects of EIA and/or reinforced flexible geomembrane fabrication

02778 - 5 projects and indicating the project name, project description project address, contact person, and telephone number.

B. Project Manager:

1. The Contractor shall assign to the Project a project manager who has been regularly engaged in the installation of reinforced flexible geomembrane floating covers for a minimum period of 3 years immediately prior to the bid opening date and shall have installed not less than 1 million square feet of EIA and/or reinforced flexible geomembrane material.

C. Superintendent:

1. The Contractor shall assign, exclusively to the project, a superintendent who has served in a similar capacity for not less than 2 years immediately prior to the bid opening date and has not less than 1 million square feet of experience in the installation of EIA and/or reinforced flexible geomembrane floating covers.

2. The only experience of the superintendent that will be considered as qualifying is on projects where the superintendent was full time at the point of installation directly overseeing and supervising the labor and the Work. Time spent in a field office does not qualify.

3. If the superintendent is deemed not qualified by the Construction Manager, the Contractor shall not employ such superintendent on this Project. Any superintendent employed by the Contractor shall be discharged if his performance on the Work is determined by the Construction Manager to be unsatisfactory.

4. Any superintendent substituted for a superintendent originally assigned by the Contractor shall meet the same minimum requirements specified herein.

D. Quality Assurance Manager

1. The Contractor shall assign, exclusively to the Project, a quality assurance manager who has served in a similar capacity on at least three prior reinforced flexible geomembrane installations involving a total of not less than 1 million square feet.

E. Fabricator

1. Individual sheets of reinforced EIA flexible geomembrane material shall be factory-fabricated into large panels by an experienced fabricator regularly engaged in fabricating EIA and/or reinforced flexible geomembrane for a minimum period of 5 years immediately prior to award of the Contract and fabricated not less than 1,000,000 square feet of reinforced EIA flexible geomembrane prefabricated panels. Other experience relevant to fabrication which does not meet the above requirements may be considered.

02778 - 6 The Construction Manager's opinion as to the acceptability of all experience shall be final and conclusive

2. With their bid, the Contractor shall provide to the Construction Manager the Fabricator’s representative experience consisting of not less than five (5) projects of EIA and/or reinforced flexible geomembrane fabrication projects and indicating the project name, project description project address, contact person, and telephone number.

F. EIA Flexible Geomembrane Material Manufacturer

1. EIA flexible geomembrane materials shall be manufactured by an experienced firm regularly engaged in manufacturing reinforced EIA flexible geomembrane material sheeting for a minimum period of 2 years immediately prior to the award of the Contract and which has produced a minimum of 10,000,000 square feet of reinforced EIA flexible geomembrane materials.

2. With their bid, the Contractor shall provide to the Construction Manager the Manufacturer’s representative experience consisting of not less than five (5) projects of EIA flexible geomembrane projects and indicating the project name, project description project address, contact person, and telephone number.

1.06 QUALITY ASSURANCE

A. Quality Assurance Plan:

1. The Contractor shall thoroughly review and comprehend the Project Drawings and Specifications prior to the development of the job specific Quality Assurance Plan. The Contractor's Quality Assurance Plan shall be in accordance with the Drawings and Specifications. Any deviations or conflicts with the Drawings or Specifications shall be clearly marked, immediately brought to the Construction Manager’s attention, and shall not be used without the Construction Manager’s prior written consent.

2. The Contractor's quality assurance plan shall state how the following items shall be accomplished and shall include sample forms to be used to document each quality assurance activity. The major headings and subheadings list those tasks, as a minimum, which shall be included in the Quality Assurance Plan. The Contractor shall include any additional pertinent information and topics.

3. Materials:

a. Monitor and document the unloading, handling, and on-site storage of fabricated panels and other materials.

b. Monitor material, process, and equipment certifications required by the Specifications to ensure their adequacy and timely submittal. The Construction Manager shall be notified of any deviations.

02778 - 7 c. Label, package and ship test samples to the independent testing laboratory for Specifications compliance testing.

4. Deployment/Installation:

a. Evaluate and document the suitability of weather conditions to insure proper installation.

b. Monitor and document placement and condition of all panels while being placed.

c. Monitor and document the proper installation of panels in accordance with approved shop drawings.

d. Perform overall visual observations of entire geomembrane surface to locate and document all damage and defects.

e. Monitor and record the repair of all damage, defects, and all destructive testing.

5. Seaming:

a. Monitor and document trial seaming procedure and test results to evaluate seaming personnel and equipment.

b. Monitor and document seaming procedures.

c. Devise seam identification numbering system unique to each seam such that the seam location, seaming crew, equipment used, date, time, and weather conditions are properly documented.

d. Include a list of all equipment, with pertinent technical information, to be used for seaming.

e. Describe in detail each seaming procedure the Contractor proposes to use in executing the Work. Each seaming procedure shall be approved by the Construction Manager prior to use. The seaming procedures shall include cleaning of geomembrane material to be seamed, cleaners/solvents, preheating, adhesives, seaming temperatures, seaming rate, and dwell pressure.

f. Indicate adverse weather or other conditions that could limit or halt seaming operations.

g. Describe measures to account for and compensate for temperature changes in ambient air or material that may affect seam quality.

h. Describe equipment calibration frequency and procedure.

6. Seam Testing Samples:

a. Monitor and document nondestructive testing of seams.

02778 - 8 b. Select locations for destructive seam samples, when selection is not made by the Construction Manager.

c. Monitor and document the cutting of seam test samples and patching of test sample holes, if required.

d. Utilizing the test seam identification numbering system, document the location, seaming crew, equipment used, date, time, and weather conditions for each test sample.

e. Label, package, and ship test samples to independent testing laboratory for Specifications compliance testing.

f. Interpret all laboratory test results on material and seam compliance with Specifications.

g. Distribute 5 copies to the Construction Manager of the certified laboratory test results with interpretation to the Construction Manager.

h. Monitor and document the repair of all rejected seams.

i. Monitor and document destructive and nondestructive testing of repaired seams.

B. Field Seaming Demonstration:

1. Following the submittal of the Quality Assurance Plan and prior to the Construction Manager's approval, the Contractor shall conduct a field demonstration utilizing the seaming procedures, equipment usage, calibration procedures, and all other aspects of the proposed seaming methods.

2. The Contractor shall conduct on site seam strength tests in compliance with the requirements stated in this Section.

3. The Contractor shall provide seaming demonstration for each type of seaming method proposed (e.g., hot air, wedge welder, adhesive, etc.).

4. At least four 10-foot long demonstration seams shall be made for each type of panel-to-panel seaming system proposed.

5. Each demonstration seam shall include a tee joint where three layers of material are bonded together.

6. Samples may be taken from the demonstration seams and tested by the Construction Manager.

7. Approval of the Quality Assurance Plan will be contingent upon the results of the demonstration test samples.

02778 - 9 C. Execution of the Quality Assurance Plan:

1. Upon the Construction Manager’s written approval of the Contractor's Quality Assurance Plan, the Contractor shall implement and continuously monitor the Quality Assurance Plan, as described above, through an active and ongoing Quality Assurance Program.

2. The Construction Manager will continuously monitor the Contractor's approved Quality Assurance Program for compliance.

3. The Contractor's quality assurance manager shall report directly to off-site senior management, shall be completely independent from the on-site installation personnel, and shall have no production responsibilities that could infringe upon the execution of the Contractor’s Quality Assurance Plan.

4. The Quality Assurance Program shall include, but not necessarily be limited to, the above specified items and the following items:

a. Review of all Drawings and Specifications for clarity, completeness, and to acquire a thorough knowledge of Project materials and construction procedure requirements.

b. Review, revise as deemed necessary, and approve the reinforced flexible geomembrane manufacturer’s quality assurance plan.

c. Review, revise as deemed necessary, and approve the reinforced flexible geomembrane fabricator's quality assurance plan.

d. Continuous review and revision, as necessary, of the quality assurance plan for thoroughness, adequacy, and feasibility.

e. Use special Project specific and task specific forms or logs for monitoring all activities involved with the Quality Assurance Plan. Project specific forms shall include the Project name and minimum test values for each specific test (e.g., shear, peel, etc.).

f. Maintain logs summarizing all daily activities.

g. Interpret all laboratory test results on materials and seams for compliance with Specifications.

h. Distribute 5 copies of certified laboratory test results with interpretation to the Construction Manager.

D. Quality Assurance Final Report: At the completion of the floating cover installation and prior to final acceptance of all Work by the Construction Manager, a final quality assurance report shall be submitted to the Construction Manager. The Contractor shall submit to the Construction Manager a report at the 90% completion prior to the issuance of the final report. The Contractor shall positively address all of the Construction Manager’s comments prior to the issuance of the

02778 - 10 final report. The quality assurance report shall include, but not necessarily be limited to, the following items:

1. A brief description of the Project, including the Project name, type of facility, location, design Construction Manager, material supplier(s), shop fabricator(s), subcontractors, and the Contractor’s project manager and superintendent.

2. Detailed description of basin reinforced flexible geomembrane floating cover system, including, area, and type of reinforced flexible geomembrane materials installed.

3. Copy of basin floating cover Drawings and Specifications with as-built mark ups.

4. Record of daily activities, including all special problems and associated resolutions encountered during the Project.

5. Copies of all field and laboratory, destructive and nondestructive test results, with interpretations.

6. Copies of all standard forms and logs completed as part of the Quality Assurance Plan.

7. Copy of approved shop drawings and Contractor provided details.

8. Copy of quality assurance record drawings indicating panel numbers, seam identification numbers, seaming dates, location of defects, type of defect, repairs, repair dates, location of all samples.

9. Statement from the Contractor certifying the floating cover has been installed in accordance with Project Drawings and Specifications.

10. The Contractor's, fabricator's, and manufacturer's approved quality assurance plans.

1.07 DELIVERY, STORAGE, AND HANDLING

A. Delivery, storage, and handling shall be in accordance with the following special requirements:

1. Packing and Shipping:

a. Each factory-fabricated panel shall be individually packaged. Floating cover panels shall be rolled onto pipes with an outside diameter not less than 6 inches and shall be rolled in a manner that keeps the material properly aligned. Each rolled panel shall be wrapped in cardboard or other suitable material and enclosed in an opaque, light-reflective airtight bag to protect and prevent damage during shipment and storage. Each roll enclosure shall be prominently marked in the same fashion as the panel within.

02778 - 11 2. Storage and Protection:

a. Packaged factory-fabricated panel rolls shall be stored in their original unopened condition, on a flat and clean surface, in a dry free draining area, and protected from direct sunlight under an opaque, light colored heat-reflective cover.

b. Sand for sand-filled tubes shall be stored on a clean, paved area or tarpaulin to prevent contamination, and shall be covered with a tarpaulin and maintained in a dry condition until used.

1.08 PROJECT/SITE CONDITIONS

A. Safety Requirements

1. Construction personnel shall be trained in and be instructed on the use of barrier creams or gloves as necessary, for working with the solvents and cleaning agents. All used cloths impregnated with solvent shall be kept separately in metal containers with close-fitting lids suitable for use as necessary and in compliance with the requirements of the International Fire Code (IFC) and local Fire Marshal. Construction personnel at the site will not be permitted to have open flames within 50 feet of any open solvent container and will be required to wear and be trained in the use of appropriate approved breathing apparatus, where necessary.

1.09 OPERATIONS AND MAINTENANCE MANUAL

A. The Contractor shall prepare and submit to a site-specific operations and maintenance manual for the operation, maintenance, and repair of the floating cover and appurtenances for the Construction Manager’s approval. The general requirements for the operation and maintenance manual, including content, format, and submittals of the technical manuals shall be in accordance with these Specifications and the AWWA California-Nevada Section Reservoir Floating Cover Guidelines. The manual shall include catalog cuts of all electrical and mechanical equipment furnished and/or installed by the Contractor.

1.010 GUARANTEE AND WARRANTY

A. Prior to manufacturing the reinforced EIA flexible geomembrane material, the Contractor shall submit a written material warranty from the manufacturer for Construction Manager’s review and approval.

B. The reinforced EIA flexible geomembrane material shall be warranted in writing by the manufacturer against manufacturing defects or workmanship and against deterioration due to ozone, ultraviolet rays, or other than normal weather aging. Vandalism, acts of animals, and acts of God are excluded. The warranty shall be limited to the replacement of material only. Installation labor is not included in the material warranty.

C. The reinforced EIA flexible geomembrane material warranty shall be for a total of 20 years. Material warranty may be prorated.

02778 - 12 D. The reinforced EIA flexible geomembrane material warranty period shall not commence until the material has been installed by the Contractor and accepted by the Owner.

E. The reinforced EIA flexible geomembrane material manufacturer shall perform site inspections during fabrication and onsite installation to verify the material has not been damaged as a result of the fabrication or installation and no part of the material warranty has been voided.

F. The Contractor shall warrant and guarantee that all Work shall be free of deficiencies and defects for a period of 2 years after the date of final acceptance of the Work by the Owner.

G. The warranties and guarantees specified herein may not be the only warranties and guarantees involved in the Contract, and are in addition to those specified in the Contract documents.

PART 2 - PRODUCTS

2.01 MATERIALS

A. Floating Cover and Baffle Reinforced Flexible Geomembrane:

1. The floating cover and baffle reinforced flexible geomembrane material shall be manufactured from a composition of high quality ingredients and shall be an Ethylene Interpolymer Alloy (EIA) fabric reinforced material.

2. The Owner may, at its discretion, have a representative at the manufacturer’s facility during the production of the EIA flexible geomembrane material for the Project. The Contractor shall notify the Construction Manager no less than 2 weeks in advance of starting manufacturing so that shop inspection may be arranged.

3. The flexible geomembrane material shall consist of thoroughly bonded, reinforced EIA sheeting. All reinforced flexible geomembrane materials shall be uniform in color, thickness, size, and surface texture. The fabric shall be totally encapsulated. The reinforced flexible geomembrane shall be a balanced sheet with the fabric approximately centered in the geomembrane. The material shall be a flexible, durable, watertight product free of pinholes, blisters, and contaminates and shall not delaminate in a water environment.

4. All floating cover geomembrane material and geomembrane floating cover accessories shall be provided from a single EIA reinforced flexible geomembrane material supplier.

5. The finished color of the EIA reinforced flexible geomembrane material sheet shall be tan top side/ black bottom side. The color shall not vary between sheets.

02778 - 13 6. Unless otherwise indicated, all EIA material used in the floating cover appurtenances shall be the same type of EIA reinforced flexible geomembrane material as that used for the floating cover geomembrane.

7. The material manufacturer shall certify in writing prior to manufacturing material that the EIA reinforced flexible geomembrane material has the following material property values:

Property Test Floating Cover & Method Baffle Material Test Value Base Fabric Type Polyester Base Fabric Weight 6.5 oz./sq. yd. Thickness ASTM D751 45 mils ± 10% (nominal) Finished Coated Weight ASTM D751 42.0 ± 2.0 oz./sq. yd. Tear Strength ASTM D7513 40 lbs. / 55 lbs. (minimum) Trapezoidal Tear Break Yield Strength ASTM D751 550 lbs. / 550 lbs. (minimum) Grab Method Elongation at Yield ASTM D751 20% (minimum) Grab Method Low Temperature Resistance ASTM D2136 Pass at -30ºF 4 hrs., 1/8 in. , Dimensional Stability ASTM D1204 0.5% (maximum) 212°F, 1 hr., each direction Hydrostatic Resistance ASTM D751 800 psi (minimum) Method A Procedure 1 Blocking Resistance ASTM D751 #2 Rating (maximum) 180°F Adhesion – Ply ASTM D751 15 lbs./in. (minimum) Type A, 2 in. min. Adhesion – Heat Welded Seam ASTM D751 40 lbs./2 in. (minimum) Dead Load Seam Strength ASTM D751 240 lbs./in. @ 70°F (minimum) 4 hrs. 120 lbs./in. @ 160°F

02778 - 14 Property Test Floating Cover & Method Baffle Material Test Value Bonded Seam Strength ASTM D751 550 lbs. (minimum) Procedure A Grab Test Abrasion Resistance ASTM D3389 2,000 cycles (minimum) H-18 wheel, minimum before 1kg. load fabric exposure 50mg/100 cycles max. weight loss Weathering Resistance ASTM G153 8,000 hrs. (minimum) no appreciable change or stiffening or cracking of coating Water Absorption ASTM D471 0.025 kg/m2 at 70ºF (maximum) Section 12 0.14 kg/m2 at 212ºF 7 days Wicking ASTM D751 1/8 in. (maximum) Bursting Strength ASTM D751 750 lbs. (minimum) Ball Tip Puncture Resistance ASTM D4833 275 lbs. (minimum) Puncture Resistance FTMS 101C 350 lbs. (minimum) Method 2031 Coefficient of Thermal ASTM D696 8x10-6 in/in/ºF Expansion/Contraction Environmental/Chemical ASTM D741 NSF 61 approved Resistance 7 day total immersion with exposed edges

8. During manufacturing, the material manufacturer shall test the EIA reinforced flexible geomembrane material at a frequency of not less than every 50,000 sf of geomembrane produced. The manufacturer shall certify that the physical properties of the finished sheet meet or exceed the specifications and submit certified test reports to validate conformance.

9. Reinforced flexible geomembrane material shall be:

a. 8142 XR-5 PW, manufactured by Seaman Corporation

b. Or approved equal.

02778 - 15 B. Use of EIA: Unless otherwise indicated, all EIA material used in the floating cover and appurtenances shall be the same type of reinforced EIA as that used for the floating cover geomembrane. Exposed surfaces or outside surfaces of floating cover appurtenances shall be same color as floating cover material topside.

C. Floats:

1. Floats shall be rigid, extruded, closed-cell, polyethylene foam planks weighing 2.3 pounds per cubic foot ±10%. The floats shall be:

a. Ethafoam 220 by Dow Chemical Company,

b. Polyplank PLK 220 by Pregis Corp.,

c. Or approved equal.

2. Individual float dimensions from the factory shall be minimum 2-inch thickness by the full width specified for the application shown on the Drawings by maximum length commercially available.

3. Built-up floats for the total finished thickness specified on the Drawings shall be achieved by laminating individual float layers. Vertical joints in individual float layers shall be staggered a minimum 12 inches. Each layer shall be fully heat-bonded to the adjacent layers.

4. Polyethylene foam floats shall be fully encased in the same reinforced geomembrane material as that used for the floating cover geomembrane, unless noted otherwise.

D. Hatches

1. Access hatch frames and covers shall be fabricated from aluminum. Reference Section 05500, Miscellaneous Metals, for additional requirements.

E. Batten Bars

1. Batten bars shall be fabricated from stainless steel in accordance with ASTM A276, Type 316L, unless otherwise shown on the Drawings.

2. Reference Section 05500, Miscellaneous Metals, for additional requirements.

F. Sand-Filled Tubes:

1. Sand-filled tubes shall be fabricated from the same reinforced geomembrane floating cover material.

2. Sand-filled tubes shall be of sufficient length and lay-flat width to produce the finished length and diameter shown on the Drawings. The overall tube length shall include extra material required to seal the ends of the tube.

02778 - 16 3. Sand-filled tubes shall be filled with dry, even graded #12 silica sand with minimum 90% passing a No. 12 sieve, minimum 95% retained on a No. 16 sieve, and no more than 1% passing a No. 30 sieve.

4. Attachment

a. Stainless steel grommets shall be installed in the attachment tabs material as shown on the Drawings. Holes in the attachment tabs shall be punched using spur-setting dies with cutter to properly suit the grommet size. The grommets shall be seated so that the entire rim is firmly gripping the geomembrane material all the way around the grommet. No loose or sharp edges around the grommet shall be permitted. Grommets shall be manufactured by:

(1) Stimpson Co.

(2) Rome Fastener Corp.

(3) Or approved equal.

b. Attachment straps shall be black, double-face weave, medium weight or heavier, dacron webbing with black Delrin (Acetal) standard cam buckles as shown on the Drawings. Ends of the dacron webbing shall be heat seared to prevent raveling.

c. The webbing and cam buckle assembly shall have compatible components and shall be capable of supporting a sustained 100 pound tensile load without the webbing pulling out of the buckle.

d. Dacron webbing shall be sewn to the attachment end of the cam buckle with #207 or stronger, bonded, silicone treated, black, polyester thread.

G. Flexible Drain Pipe

1. Flexible drain pipe shall be corrugated, perforated polyethylene in accordance with ASTM F405.

2. Flexible drain pipe fittings shall be in accordance with ASTM F405.

3. Pipe fittings (tees, couplings, etc.) shall be snap style fittings.

4. Flexible pipe shall be manufactured by”

a. Advanced Drainage Systems, Inc. (ADS),

b. Hancor, Inc.,

c. Or equal.

02778 - 17 H. Rainwater Removal Sumps

1. Sump Cans

a. Sump cans shall be industrial rated, molded, black polyethylene cans.

b. Sump cans shall be UV stable and UV resistant and rated for outdoor exposure.

I. Walkways

1. Walkways shall be manufactured from potable grade, EIA floating cover material.

2. The top of the walkways shall provide a non-slip walking surface. Textured surface material shall be fully bonded and integral with the floating cover material. Roughened or abraded surface of standard EIA geomembrane material shall not be acceptable.

3. The walkway exposed top surface shall be the same color as the floating cover topside.

4. Walkway material shall at a minimum be the same thickness as the floating cover material.

5. Walkway minimum width shall be as stated on the Drawings.

J. Rope:

1. Rope shall be 100% Dacron or 3 strand, twisted, polypropylene.

2. Rope shall be suitable for marine use.

3. Rope size shall be as shown on the Drawings.

K. Rubber Gaskets:

1. Rubber gaskets shall be black neoprene rubber.

2. Rubber gaskets shall have a durometer Shore A hardness of 35 ± 5, in accordance with ASTM D2000.

L. Accessories:

1. All accessories, hose clamps, and other miscellaneous hardware required for the floating cover shall be stainless steel, Type 316 or Type 316L, if welding is required.

02778 - 18 M. Rainwater Enhancement Sand-Filled Tubes:

1. In addition to the permanent sand-filled tubes shown on the Drawings, the Contractor shall furnish 3-inch diameter by 8-foot long sand-filled tubes.

2. Quantity of rainwater enhancement sand-filled tubes shall be as stated on the Drawings.

3. The rainwater enhancement sand-filled tubes shall not be initially installed on the floating cover but shall be neatly stored and protected on pallets at the site to the satisfaction of the Construction Manager. The rainwater enhancement sand-filled tubes shall be deployed on the floating cover on an as-needed basis at field-determined locations. These tubes shall be used to direct ponded rainwater to rainwater collection troughs and to remove incidental slack in the floating cover.

N. Sandbags:

1. Sandbags shall contain a minimum of 40 pounds and a maximum of 60 pounds of sand. The sand gradation shall be 100% passing a No. 8 sieve.

2. Double bags shall be utilized. Both bags shall be made of 6-mil minimum solid (non-woven) polyethylene with ultraviolet inhibitors (UVI) sufficient to guarantee a minimum life of 12 months. Each bag shall be tied off separately. Wire ties will be permitted on the inner bag. Twine or black nylon cable ties with a minimum tensile strength of 30 pounds, shall be used on the outer bag.

O. Patches:

1. Structural patches shall be the same reinforced geomembrane floating cover material.

2. Non-structural patches shall be 40-mil unreinforced EIA material, same color as the geomembrane floating cover material.

P. Cleaning Solvents:

1. Solvents for cleaning contact surfaces of factory and field joints and other surfaces shall be suitable for the intended use, subject to the approval of the Construction Manager.

2. Solvents for cleaning contact surfaces of field joints and other surfaces shall satisfy the recommendations of the EIA reinforced flexible geomembrane material manufacturer, subject to the approval of the Construction Manager.

Q. EIA Extrusion Weld Rod

1. EIA extrusion weld rod shall be the same formulation as the EIA geomembrane floating cover material.

02778 - 19 2. EIA extrusion weld rod shall be the same color as the EIA geomembrane floating cover material.

3. Extrusion weld rod material shall be produced by the same manufacturer as the EIA geomembrane floating cover material.

R. EIA Adhesive

1. EIA adhesive shall be a 2-part polyurethane based adhesive specifically formulated for use with EIA geomembrane materials.

2. Color shall be clear to slight yellow.

3. Adhesive shall be minimum 10½% solids.

4. Product shall be XP 500:501, manufactured by Seaman Corp., or approved equal.

S. EIA Sealant

1. EIA sealant shall be the same formulation as the EIA geomembrane floating cover material.

2. EIA sealant shall be the same color as the EIA geomembrane floating cover material.

3. EIA sealant shall be shall be produced by the same manufacturer as the EIA geomembrane floating cover material.

T. Maintenance Repair Materials

1. In addition to the materials required by the Contractor to perform the Work, the Contractor shall provide the following materials to the Construction Manager for future maintenance tasks:

a. Three hundred (300) 12-inch by 12-inch, patches, same composition and color as floating cover material.

b. One roll stock wide by 100-foot long roll, reinforced EIA floating cover material, same composition and color as floating cover material. 2.02 FABRICATION

A. Fabricators shall be one of the following:

1. Colorado Linings

2. EC Applications, Inc.

3. Field Lining Systems, Inc.

02778 - 20 4. Lange Containment Systems, Inc.

5. Layfield Environmental Corporation

6. MPC Containment Systems

7. Or approved equal

B. The factory seams shall be machine-made with hot air welding, hot wedge welding, or RF welding techniques. The fabricator shall perform 100% continuous visual inspection of each linear foot of seam as it is produced.

C. The surface of the welded areas must be dry and clean. Pressure must be applied to the full width of the seam on the top and bottom surface while the welded area is still in a melt-type condition. On a hot air welder, the bottom surface must be flat to insure that the entire seam is welded properly. Enough heat shall be applied in the hot air welding process that a visible bead is extruded from both edges being welded. The bead insures that the material is in a melt condition and a successful chemical bond between the two surfaces is accomplished.

D. Floating cover factory seams shall be fully bonded on the top side so that no loose edge is present on the top side of the fabricated panel.

E. Baffle factory seams shall be fully bonded on both sides so that no loose edge is present on either side of the fabricated panel.

F. All factory-fabricated panels shall be fabricated such that the materials are rolled. Accordion folded panels shall not be permitted. Roll widths shall be not less than 24 feet nominal width. “Wall papering” the installation with manufacturers roll stock material shall not be permitted.

G. Factory-fabricated sections or panels shall be given prominent, unique indelible identifying markings in accordance with the approved panel layout drawing and shall indicate the proper direction for unrolling to facilitate their layout and positioning in the field.

H. Horizontal factory-made and field-made seams will not be permitted on the basin slope, except for factory roll stock splices, which shall be offset by at least 5 feet from such splices in adjacent roll stock in the same panel. Rollstock splices will not be permitted on either outside edge of a panel. Roll stock splices shall only be permitted in the center rolls of fabricated panels.

I. All factory seams shall be staggered as required to ensure that no more than 3 layers of geomembrane meet at a joint.

J. Where 3 layers of reinforced flexible geomembrane floating cover material occur at a "T" joint (factory rollstock splices), care shall be taken to seal the small leak path that would otherwise occur along the edge of the middle layer. The area shall be

02778 - 21 solvent wiped and sealed with a high-solids adhesive and then covered with a 4 inch round 40-mil unreinforced EIA patch. The center of the patch shall be placed at the intersection of the edges of the top and middle layers of the reinforced flexible geomembrane.

K. Fishmouths, pleats, folds, wrinkles, and similar defects shall not be permitted in any seams.

L. Treatment of exposed the fabric shall be as stated in part 3 and as shown on the Drawings.

M. The Contractor may have portions of the floating cover and appurtenances fabricated in the factory. The factory fabrication may include, but not necessarily be limited to, sand tubes, straps, and float wrap. Factory seams for all such items shall comply with the requirements shown on the Drawings.

N. Equipment Calibration:

1. The seaming equipment shall be calibrated in accordance with the fabricator’s quality assurance plan by testing trial seam samples, but shall not be less than at the beginning of each shift, every 4 hours, and at any significant environmental changes.

2. Shop seam samples shall be collected and tested in accordance with the Quality Control provisions stated in Part 3 - Execution. The shop seam verification testing shall be performed by in-house personnel or independent laboratory. The Contractor shall submit the daily calibration test results to the Construction Manager as part of the final quality assurance report. No shop seaming shall be performed until all test samples have been tested and passed.

O. All factory fabricated panel seams shall be probe and air lance tested in accordance with the Quality Control provisions stated in Part 3 - Execution.

P. Factor seam samples shall be collected and tested in accordance with the Quality Control provisions stated in Part 3 - Execution. The shop seam destructive testing shall be performed by independent laboratory.

PART 3 - EXECUTION

3.01 PREPARATION

A. Protection:

1. Under no circumstances shall the geomembrane floating cover or the existing geomembrane liner be subjected to rough treatment or have

02778 - 22 sandbags, equipment, or other material dragged across or thrown upon its surface. Neither materials nor workers or others shall slide down slopes on top of the geomembrane floating cover or the existing geomembrane liner.

2. Scuffed surfaces resulting from abuse or inadvertent damage of any kind by the Contractor's employees, or inadvertent damage caused by the Construction Manager personnel overseeing the Work, shall be repaired in accordance with the Specifications.

3. All persons walking on the geomembrane floating cover material and the existing composite geomembrane liner shall wear smooth, rubber-soled shoes. Shoes with patterns in relief (like those popularly known as "sneakers") that could pick up rocks and debris will not be permitted.

4. The Contractor shall protect the geomembrane floating cover and existing composite geomembrane liner by deploying a 22 ounce nonwoven geotextile in all high foot traffic areas. This provision shall be included in the Contractor’s Protection Plan.

5. No wheeled vehicles will be permitted on the existing geomembrane liner or on the geomembrane floating cover material. Miscellaneous equipment with pneumatic tires may be permitted with prior written approval from the Construction Manager.

6. Scissors and utility knives used in the Work shall have blades with rounded points. Marking pens or pencils used for identifying areas requiring work shall not contain wax, oil, or grease.

7. Tarpaulins of EIA material, about 10 feet by 10 feet in size, shall be spread out on the existing geomembrane liner or geomembrane floating cover material as a work area for storing soiled rags, tools, gasoline-driven equipment, or aggressive chemicals. Under no circumstances shall gasoline-driven engines or cans of gasoline or solvents be placed directly on the existing geomembrane liner or geomembrane floating cover material or be stored within the basin overnight.

8. The Contractor shall take all precautionary measures required to protect the geomembrane floating cover and existing geomembrane liner. This shall include, but not be limited to, the geomembrane material itself, all field and factory seams, attachment at anchor curb at top of slope, and underwater seals to structures.

B. Cleaning of the Basin Geomembrane Liner:

1. Prior to placement of geomembrane baffles or floating cover panel materials on the existing HDPE geomembrane liner, loose particles shall be removed from the geomembrane liner by blowing with compressed air. Blowing shall be performed with an air compressor and suitable lengths of air hose.

2. Accumulations of loose particles shall be removed with brooms and vacuums.

02778 - 23 3. Cleaning of large areas far in advance of panel placement is not acceptable. The underlying material shall be cleaned no more than 2 days in advance of material deployment. This timeframe may be shortened, as determined by the Construction Manager, under less than ideal weather conditions.

4. The Contractor shall conduct his Work to minimize the movement of fugitive dusts from the site boundaries by using suitable Reasonably Available Control Measures (RACM).

3.02 INSTALLATION

A. Panels:

1. The Contractor shall identify and repair any damage or defects to panels that occurred during shipping, unloading, storage, and installation.

2. Reinforced flexible geomembrane floating cover panels shall be carefully placed on the bottom and slopes of the basin in accordance with approved shop drawings, and in such a manner as to assure minimum handling.

3. During installation of the geomembrane floating cover, the Construction Manager shall have complete authority to order an immediate stoppage of the Work because of inclement weather, the use of improper installation procedures, or any other reason which may result in a defective floating cover installation.

4. Seaming shall keep pace with the placement and spreading of panels such that panels will not be laid out unless they can be seamed the same day.

5. Reinforced flexible geomembrane floating cover panels shall be deployed in sufficient time to allow panels to shrink, as a result of panel stretch during the manufacturing and/or fabrication process, prior to field seaming. The Contractor shall account for the panel stretch during the manufacturing process when ordering panel lengths.

6. Prior to backfilling perimeter anchorage trenches the Contractor shall straighten and pull taut, in both directions to remove wrinkles as much as possible. If seaming equipment lifts the material off the substrate and leaves slack material along the seam, wherever possible the wrinkle so formed shall also be pulled out before backfilling trench or seamed to adjacent panels. The Contractor shall continuously make every effort to remove all wrinkles in the floating cover.

B. Temporary Anchorage:

1. Sandbags shall be used as necessary to hold the geomembrane floating cover material in position during installation in order to protect it from damage or displacement due to wind.

2. During any discontinuity of the Work exceeding 4 hours in length, the leading (unseamed) edges of all panels shall be secured with sandbags at not more than 3 feet on center. The Contractor shall be responsible for

02778 - 24 maintaining closer spacing as necessary to protect the Work during all weather conditions.

3. Sandbags placed on slope shall be tied off at the top of slope to prevent their shifting or sliding down the slope.

4. Bags that are split, torn, or otherwise losing their contents shall immediately be removed from the basin area, and any spillage shall immediately be cleaned up.

C. Heat Seaming:

1. Machine-made heat seams shall be used on all field seams, wherever practical.

2. Machine-made heat seams shall be made using hot air or hot wedge welding equipment. All machine heat seaming equipment shall be equipped with gauges that monitor voltage and temperature.

3. Hand-held heat seaming equipment may be used where machine-made heat seams are not practical and for miscellaneous seaming as approved by the Construction Manager.

4. All seaming shall comply with these Specifications and the Contractor's Quality Assurance Plan.

5. Contact surfaces of geomembrane material to be seamed shall be cleaned with water and wiped dry with a cloth until all foreign matter, dust, dirt, and water has been removed. Only clean, colorfast, lint-free, cotton cloths shall be used in the Work. Cleaning of the contact surfaces shall not be completed more than 10 minutes ahead of seaming. When conditions are adverse to proper workmanship such as high winds, or other conditions increase the probability of dirt or other foreign material being deposited on the contact surfaces, the time between cleaning and seaming shall be reduced as necessary to produce acceptable seams.

6. The Contractor shall follow immediately behind the heat seaming equipment, while the material is still hot from the initial seam, bonding the top edge of the seam. The top edge of the seam shall be “stitched” by manually the seam area with firm pressure with a 2-inch wide roller. Joints where 3 layers of reinforced flexible geomembrane meet shall also be stitched to seal the potential leak path along the edge of the middle layer.

7. In the event a floating cover reinforced flexible geomembrane panel has been laid out and not seamed for a period of 3 days or more, the contact surfaces shall be solvent scoured and buffed to ensure a positive bond at the seam. The scouring procedure shall consist of hand buffing the contact surfaces with stainless steel scouring pads soaked in solvent to effectively penetrate and remove the oxidation layer. This scouring

02778 - 25 procedure shall be applicable to all panel-to-panel seams, patches, and seams for attachment of accessories.

8. Care shall be taken to avoid damaging the existing geomembrane liner with the seaming equipment. The Contractor shall take the necessary precautionary measures to ensure the geomembrane floating cover is not bonded to the underlying existing geomembrane liner during the seaming process.

D. Adhesive Seaming:

1. Adhesive may be used to make seams where heat seaming is impractical and for minor repairs and only in those instances approved by the Construction Manager.

2. Adhesive seaming shall comply with the manufacturer’s written recommendations and procedures and the Contractor’s approved Quality Control Plan.

3. Use of adhesives and solvents shall be in compliance with the applicable regulatory requirements.

4. Contact surfaces of reinforced flexible geomembrane material to be seamed shall be cleaned, abraded, and prepared in accordance with the manufacturer’s written recommendations and procedures.

5. The use and application of adhesive shall be performed in accordance with the manufacturer’s written recommendations and procedures.

6. Care shall be taken to avoid damaging the existing geomembrane liner with the seaming equipment. The Contractor shall take the necessary precautionary measures to ensure the geomembrane floating cover is not bonded to the underlying existing composite geomembrane liner during the seaming process.

E. Joinings:

1. Panels to be joined in the field shall be lapped as shown on the Drawings. After the initial seal of the lap joint has been made, all exposed free edges of the geomembrane floating cover shall be resealed, using hand-held equipment, to eliminate all free edges. The top edge of all seams shall be fully bonded. Loose edges will not be allowed on the top side of the floating cover.

2. Butt joints shall be used only where lap joints are not possible and as approved by the Construction Manager. Butt joints shall be formed using joint cover strips made from the same reinforced flexible geomembrane floating cover material, continuous in length, and as shown on the Drawings. The joint cover strip shall be centered over the butt joint and shall be fully bonded across its entire width. Butt joints shall be installed in accordance with the same procedures for lap joints specified herein.

02778 - 26 3. All seams, field and factory, shall be staggered a minimum of 12 inches to ensure that no more than 3 layers of material meet at a joint.

4. Lap joints that cross rainwater collection troughs made in the field shall be reinforced with a joint cover strip, made from the same reinforced flexible geomembrane floating cover material, as shown on the Drawings.

5. The doubler along the centerline of the rainwater collection trough shall be reinforced flexible geomembrane floating cover material. The doubler shall stop and start each side of the joint cover strips and shall be seamed all around on sides and ends. Care shall be taken to extrude air from beneath the doubler before closing the last seam.

6. Longitudinal seams (field or factory seams) on the floor of the basin and parallel with rainwater collection troughs shall not be permitted within 5 feet from the outermost edge of the rainwater collection trough.

7. Where 3 layers of material occur at a “T” joint (field seams, factory seams, and rollstock splices), care shall be taken to seal the small leak path that would otherwise occur along the edge of the middle layer. The upper layer shall be heated and rolled to conform or “step-down” and seal the leak path. In addition, the area shall be solvent wiped and sealed with a high-solids adhesive and then covered with a 40-mil minimum unreinforced EIA material patch as shown on the Drawings. The center of the patch shall be placed at the intersection of the edges of the top and middle layers of the reinforced flexible geomembrane material.

8. Seam preparation shall be in accordance with the requirements stated herein, the manufacturer’s printed recommendations, and the applicable regulatory requirements.

9. Care shall be taken to avoid fishmouths, wrinkles, pleats, folds, and tucks in seams. Any such defects shall be prevented by tugging on the seam just completed in the opposite direction from which the seam is progressing, during the seaming process. The Contractor’s seaming crew shall give continuous attention to the elimination of all such defects to prevent their occurrence. Regardless of the location or cause of such defects, they shall be slit out far enough from the seam to dissipate the defect. The slit edges shall then be lapped and field seamed. Wherever the lap width is less than 2½ inches, the defect shall be repaired with a joint cover strip made from the same reinforced geomembrane floating cover material.

10. Field seams shall not be made if the ambient temperature or humidity would result in inferior seams.

11. Where reinforced flexible geomembrane floating cover material has been cut and thus exposes the fabric, the cut edge, if exposed to view after installation, shall be shall be solvent wiped and sealed with a high-solids adhesive. Specifically, the acceptable treatment options for the cut and exposed fabric at the various locations shall conform to the following table:

02778 - 27 Treatment Location of exposed fabric No EIA EIA Strip Weld Sealant Extrusion Treatment Joint Cover Factory seams in floating cover • (outside rainwater collection trough) Factory seams in floating cover • (inside rainwater collection trough) Field seams in floating cover • (outside rainwater collection trough) Field seams in floating cover • (inside rainwater collection trough Rainwater collection trough float • wrap Sand tubes • Doubler strip in rainwater collection • • troughs Joint cover strip in rainwater • • collection troughs Structural patches • • Non structural patches • Cut edges at hatches and vents • Factory and field seams in baffles •

F. Anchorage and Fastenings:

1. Floating cover shall be anchored at the top of slope as shown on the Drawings.

2. Baffles shall be anchored to concrete curb on basin floor and side slopes as shown on the Drawings and shall be installed on the anchor studs by either of the following methods:

a. Anchor bolt holes shall be neatly punched using a tool that removes the material to form a neat hole 1/8-inch less in diameter than the penetrating stud diameter. The geomembrane floating cover material shall be forced over the stud in such a manner to prevent damage to the cover or the stud.

b. The geomembrane floating cover material forced onto the anchor studs using a pipe section with an inside diameter slightly larger than the anchor stud diameter (½-inch, schedule 40 pipe for ½-inch anchor studs), thus punching the geomembrane floating cover material around the anchor stud. This method will result in no

02778 - 28 removal of geomembrane floating cover material at the anchor bolts.

c. Oversized, cut, or irregular shaped holes will not be allowed.

d. Anchor bolt holes created by any other means shall not be accepted, unless specifically approved by the Construction Manager.

G. Rainwater Collection Troughs:

1. Sand filled tubes shall be placed with end-to-end gaps, as shown on the Drawings.

2. Sand filled tubes and flexible drain pipe shall be securely attached to reinforced flexible geomembrane tabs with webbing and buckles, as shown on the Drawings.

H. Hatches

1. Hatches shall be installed as shown on the Drawings.

2. Hatches shall be installed in floating cover material deployed on and conforming to the reservoir floor and side slopes. Floating cover material shall be smooth, without wrinkles or extra material.

3. After installation, the top of studs attaching the hatch frame to the wrapped floats shall be trimmed such that no more than ½ inch of stud projection past the nuts.

I. Rainwater Removal Sumps

1. Rainwater removal sumps shall be installed as shown on the Drawings.

J. Walkways

1. Walkways shall be laid flat and parallel to the slope. Puckered or skewed walkways shall not be acceptable.

2. Walkway material shall be lapped and seamed with adjacent floating cover panels.

K. Rope

1. The rope shall be installed in the baffle hems, as shown on the Drawings, such that the rope hem is installed snug to the attachment bar.

L. Sand-Filled Tubes

1. After installation of sand-filled tubes on reinforced flexible geomembrane floating cover, all sand tubes shall be punctured with an awl on both sides at 12 inches on center to create “dimensionless” holes to allow saturation of

02778 - 29 the sand when the tubes are submerged in rainwater. The use of a blade for this purpose is not permitted. This Work shall be witnessed by the Construction Manager.

3.03 REPAIRS

A. Punctures, cuts, tears, abrasions, and similar damage of abuse to the reinforced flexible geomembrane floating cover material shall be repaired to the satisfaction of the Construction Manager.

B. All repairs shall be considered either structural or non-structural.

1. Non-structural repairs shall be defined as pinholes and abrasions to the surface coating where the reinforcing is intact and has not been cut or otherwise damaged.

2. Structural repairs shall be defined as all other defects.

C. Non-structural repairs shall be performed using EIA patches as described in Part 2. Patches shall be cut from flat unwrinkled material. Patches shall be of sufficient size to extend a minimum of 2 inches beyond the limits of any puncture, pinhole, or abrasion.

D. Patches for structural repairs shall be cut from flat, unwrinkled floating cover material, and shall be free of defects, field seams, and factory seams. Patches shall be of sufficient size to extend a minimum of 3 inches in all directions beyond the limits of any puncture, cut, tear, or abrasion.

E. All patches shall be neat in appearance with corners rounded to a minimum 1-inch radius.

F. Patches shall be applied as specified previously for heat seaming or adhesive seaming. The parent material shall be carefully pulled and held flat in the area to be patched as to provide an acceptable surface to receive the patch.

G. All patches shall be fully bonded across their entire width.

3.04 QUALITY ASSURANCE / QUALITY CONTROL

A. The Contractor’s Quality Assurance / Quality Control testing shall keep pace with the deployment and seaming operations to identify all problems at the earliest possible point in time.

B. Equipment Calibration

1. The seaming equipment shall be calibrated by testing trial seam samples in accordance with the Contractor’s quality assurance plan; but shall not be less than at the beginning of each shift, every 4 hours, and any significant environmental changes.

2. Field seam samples shall be collected and tested in accordance with the provisions stated herein. The field seam calibration verification testing

02778 - 30 may be performed by on-site personnel. The Contractor shall submit the daily calibration test results to the Construction Manager as part of the final quality assurance report.

3. The testing equipment shall be calibrated at least once every 12 months by an independent testing agency certified to conduct such calibration and a label attesting to such calibration shall be affixed to the testing equipment.

4. No daily field seaming shall be performed until all the equipment calibration samples have been tested and passed.

C. Seam Testing:

1. The Contractor shall have tests performed, at their own expense, by a GRI-certified testing laboratory.

2. All testing shall be performed to ensure that all shop seams and field seams meet the requirements stated herein.

3. Adhesion Test:

a. Factory and field test samples shall be tested for peel strength in accordance with the requirements of ASTM D751, Type A.

b. A minimum of 5 test specimens shall be tested from each test sample.

c. A seam shall be deemed acceptable if all the specimens from each test seam sample location satisfy all of the following requirements:

(1) Value equal to or greater than 40 pounds per 2-inch seam width, and

(2) Failure by delamination from the fabric rather than in the plane of the seam.

4. Bonded Seam Strength Test:

a. Specimens from factory or field seam test sample shall be 4 inches wide, with a length equal to the specified seam width plus 9 inches.

b. Factory and field test samples shall be tested in accordance with the requirements of ASTM D751, Procedure A, Grab Test Method.

c. A minimum of 5 test specimens shall be shall be tested from each test sample.

d. A seam shall be deemed acceptable if all the specimens from each test seam sample location have a test value equal to or greater than 550 pounds.

02778 - 31 5. Dead Load Seam Strength Test:

a. Factory and field test samples shall be tested in accordance with the requirements of ASTM D751, 4 hour test.

b. A minimum of 5 test specimens shall be shall be tested from each test sample.

c. A seam shall be deemed acceptable if all the specimens from each test seam sample location shall have a dead load seam strength value equal to or greater than:

(1) 240 pounds per inch seam width tested at 70ºF.

(2) 120 pounds per inch seam width tested at 160ºF

6. Test results not meeting the above requirements shall be cause for rejection of the seam from which the test sample was taken.

D. Test Samples:

1. Samples of factory and field seams shall measure not less than 14 inches wide by 60 inches long with the seam parallel to the long side, and down the middle of the sample.

2. A minimum of 5 test specimens shall be taken from each test sample for each of the above tests.

3. All test samples shall be provided by the Contractor at their expense.

4. Field and factory seam samples shall be numbered, dated, and identified as to the personnel making the seam from which the sample is taken, the seaming method being used, and the temperature and weather conditions at the time of seaming. Each test sample shall be keyed to its general location on the seam from which it is taken by appropriate notes or markings on a drawing, furnished by the Contractor, for future reference.

E. Testing of Factory Seams During Fabrication

1. The Contractor shall require the fabricator to provide and test samples of factory fabricated seams taken from the fabricated panels at the factory.

2. Factory fabricated seam samples shall be tested by a GRI-accredited independent laboratory.

3. One test sample per 5,000 linear feet of rollstock-to-rollstock shop seams, or one test sample per panel, whichever yields the greater number of samples, is required. Each sample shall be tested for all of the above tests.

4. The certified test results of specimens from each sample shall be submitted to the Construction Manager for review and approval prior to installation of panels represented by that sample.

02778 - 32 5. Patching of sampled seams may be done in the field after installation of the affected panel, at the Contractor’s option.

6. If any test results are not satisfactory, the Construction Manager may, at their discretion, require that additional sampling and testing be done at the Contractor’s expense.

F. Testing of Field Seams During Field Installation:

1. The Contractor shall provide and test samples of field panel to panel seams taken from installed floating cover panels.

2. Field seam samples shall be tested by a GRI-accredited independent laboratory.

3. One test sample per 500 feet of panel-to-panel field seam shall be tested for the above tests.

4. If any test results are not satisfactory, the Construction Manager, at their discretion, may require that additional sampling and testing be done at the Contractor’s expense.

G. In addition to all sampling and testing described above, the Construction Manager may, at their discretion, require the Contractor to provide the Construction Manager with additional samples of any field or factory seam, for testing by the Construction Manager, at the Construction Manager’s expense.

H. The testing laboratory and the Contractor shall certify all test results. The Contractor shall submit copies of the certifications and test results to the Construction Manager.

I. Probe and Air-Lance Testing:

1. Prior to performing air lance testing, the Contractor shall check all seams and patches with a metal probe (such as a wire 1/16 inch maximum diameter with the point slightly rounded) for loose or unbounded edges.

2. All factory seams, field seams, joint cover strips, doublers, and patches shall be air-lance tested. Air-lance tests shall be performed in the field by the Contractor in the presence of the Construction Manager during daylight hours. Leak paths, unbounded areas, or suspect areas revealed by these inspections shall be marked and repaired.

3. The air-lance shall have a 1/8-inch diameter orifice. Pressure at the orifice shall be between 60 and 80 psi. The jet of air shall be directed at the edge of seams and patches to effect the lifting of unbonded edges. The air-lance testing shall be done in a manner so as to allow the Contractor’s Quality Assurance/Quality Control personnel sufficient time to observe and document any leaks or suspect areas. All defects found during probing shall not be repaired until the defect is tested by air-lancing.

02778 - 33 4. Field probing and air-lance tests of factory seams shall be required, even though those seams have previously been probed and air-lance tested in the factory.

3.05 CLEANUP

A. Cleanup within and around the basin shall be an ongoing responsibility of the Contractor throughout the course of the Work. Particular care shall be taken to ensure that no dirt, scrap material, trash, tools, or other unwanted materials are trapped between the existing composite geomembrane liner and the floating cover.

3.06 OWNER TRAINING

A. After completion of all operational testing and when the basin is in service, the Contractor shall provide training to the Owner’s personnel. The training shall include basic maintenance and repair procedures for the floating cover, including cleaning and patching. The training shall take place on the in-service floating cover to simulate the actual field conditions under which future maintenance and repairs would be performed.

3.07 FLOATING COVER CLEANING

A. Upon completion of construction, testing, commissioning, and basin filling, the Contractor shall perform and entire floating cover cleaning, including rainwater collection trough flush.

3.08 POST-CONSTRUCTION REPAIRS

A. In addition to any other requirement specified in the Contract Documents, after the 23rd month of the 24-month guarantee period, and prior to the end of said guarantee period, the Contractor shall contact the Owner and arrange a joint inspection of the floating cover. The Contractor shall make repairs and adjustments to the floating cover or its appurtenances as required to correct defects or problems which are evident or discovered during said inspection, or are otherwise covered under the guarantee or any warranty, and which have been determined by the Owner to be necessary. The guarantee shall continue in effect until this joint inspection is conducted and all required repairs and adjustments discovered are made, or until the end of the 24th month, whichever is later.

**END OF SECTION**

02778 - 34 SECTION 02780

BASIN STARTUP

PART 1 GENERAL

1.01 DESCRIPTION

A. This section describes the tasks associated with the startup of the reservoir that are to be performed at the completion of the floating cover.

B. The tasks to be performed in this section are to be performed by the Contractor and/or Owner, as identified herein.

1.02 REFERENCES

A. This section contains references to the following documents. They are a part of this section as specified and modified. Where a referenced document contains references to other standards, those documents are included as references under this section as if referenced directly. In the event of conflict between the requirements of this section and those of the listed documents, the requirements of this section shall prevail.

B. Unless otherwise specified, references to documents shall mean the documents in effect at the time of Advertisement for Bids or Invitation to Bid (or on the effective date of the Agreement if there were no Bids). If referenced documents have been discontinued by the issuing organization, references to those documents shall mean the replacement documents issued or otherwise identified by that organization or, if there are no replacement documents, the last version of the document before it was discontinued. Where document dates are given in the following listing, references to those documents shall mean the specific document version associated with that date, regardless of whether the document has been superseded by a version with a later date, discontinued or replaced.

C. Except as otherwise indicated in this Section, the Contractor shall comply with the latest edition of the Uniform Standard Specifications and Details for Public Works Constructions by the Maricopa Association of Governments (MAG).

PART 2 PRODUCTS – Not Used

02780-1 PART 3 EXECUTION

3.01 INITIAL FILL, OPERATIONAL TESTING, AND WATER QUALITY TESTING

A. At the completion of the floating cover work the initial fill and disinfection process shall commence.

B. Contractor shall provide written notification and request to Construction Manager for reservoir disinfection and fill water 30 days prior to starting this Work. Owner will provide fill water and control the filling operations.

C. The basin fill and disinfection shall be performed by the Owner.

D. During the disinfection and fill period, the Contractor shall have personnel on site to perform any necessary adjustments to the floating cover, rainwater collection troughs, pump assemblies, etc. The Contractor shall deploy supplemental rainwater enhancement sand tubes, as necessary to facilitate drainage and minimize localized ponding areas.

E. The Contractor shall demonstrate and verify, to the satisfaction of Construction Manager, that the floating cover, baffles, and all appurtenances, including rainwater removal pumps are functioning properly.

F. Throughout the disinfection and fill period, Owner will be engaged in water quality testing for various contaminants, including those chemicals or substances that are constituents of any product or material used in the fabrication or installation of the geomembrane baffles and geomembrane floating cover.

G. In the event water quality testing result do not comply with drinking water standards, the Contractor shall be required to drain the reservoir and perform any repairs or modifications deemed necessary by Construction Manager to rectify defects or unsatisfactory conditions observed during testing. The Contractor shall be responsible for all costs associated with the subsequent disinfection Work and basin fill water.

H. The Contractor shall anticipate up to 20 work days for fill and disinfection.

3.02 WORK ACCEPTANCE

A. Final acceptance of Work will be given after completion of all said repairs or modifications.

**END OF SECTION**

02780-2 SECTION 03250

CONCRETE ANCHORS

PART 1 GENERAL

1.01 SUMMARY

A. This Section includes furnishing and installing concrete anchors as shown on the Drawings and specified in this Section.

1.02 REFERENCES

A. This section contains references to the following documents. They are a part of this section as specified and modified. Where a referenced document contains references to other standards, those documents are included as references under this section as if referenced directly. In the event of conflict between the requirements of this section and those of the listed documents, the requirements of this section shall prevail.

B. Unless otherwise specified, references to documents shall mean the documents in effect at the time of Advertisement for Bids or Invitation to Bid (or on the effective date of the Agreement if there were no Bids). If referenced documents have been discontinued by the issuing organization, references to those documents shall mean the replacement documents issued or otherwise identified by that organization or, if there are no replacement documents, the last version of the document before it was discontinued. Where document dates are given in the following listing, references to those documents shall mean the specific document version associated with that date, regardless of whether the document has been superseded by a version with a later date, discontinued or replaced.

C. Except as otherwise indicated in this Section, the Contractor shall comply with the latest edition of the Uniform Standard Specifications and Details for Public Works Constructions by the Maricopa Association of Governments (MAG).

D. American Concrete Institute (ACI)

1. ACI 318, Building Code Requirements for Structural Concrete

2. ACI 318, Building Code Requirements for Structural Concrete and Commentary

3. ACI 355.2, Qualification of Post-Installed Mechanical Anchors in Concrete and Commentary

03250-1 E. American National Standards Institute/NSF International (ANSI/NSF)

1. ANSI/NSF 61, Drinking Water System Components - Health Effect

F. International Code Council (ICC)

1. Evaluation Services (ICC-ES)

2. International Building Code (IBC), latest edition

1.03 SUBMITTALS

A. Submittals shall be made in accordance with the Specifications Section 01300, Submittals, and the following special provisions provided herein.

B. The Contractor shall submit Material Safety Data Sheets (MSDS) for each proposed product.

C. Manufacturer's Instructions: Manufacturer's printed instructions for shipping, storing, mixing and application of the adhesive shall be submitted prior to delivery of the product.

D. Installation Instructions: Manufacturer's printed instructions for all phases of installation including hole size, preparation, placement, and procedures. Specific instruction for safe handling and installation of all concrete anchors to personnel handling and installing concrete anchors.

E. Certification of special inspector(s) proposed for concrete anchors, where required by ICC Evaluation Report.

1.04 QUALITY ASSURANCE

A. Manufacturer’s Service for Adhesive Anchors:

1. The concrete anchor manufacturer shall provide jobsite training of Contractor’s personnel for safe and proper installation, handling, and storage of adhesive system.

2. Training shall be at the Contractor’s expense. The Contractor shall coordinate training with concrete anchor manufacturer, and Construction Manager shall be notified of training schedule and sessions.

1.05 DELIVERY, STORAGE AND HANDLING

A. Materials shall be delivered in sealed containers with labels legible and intact. Each container shall be clearly marked with the following information:

1. Name of manufacturer

03250-2 2. Manufacturer's product identification

3. Manufacturer's instructions for mixing, installation, and application

4. Warning for handling and toxicity

5. Manufacturer's batch numbers

B. Materials shall be stored at temperatures between 40°F and 100°F, unless specifically stipulated otherwise by the manufacturer.

C. Materials shall be handled safely and in a manner that will avoid breaking container seals.

D. The Contractor shall heed the manufacturer's label warnings.

E. The Contractor shall store adhesive components as recommended by the manufacturer and approved by Construction Manager, and shall store and handle adhesive components in accordance with the requirements of the UFC and all health, safety, and environmental regulations.

PART 2 PRODUCTS

2.01 GENERAL

A. Stainless steel studs, bolts, nuts, and washers shall be stamped indicating the type of stainless steel.

B. Concrete anchors shall be Type 316 stainless steel, unless noted otherwise on the Drawings.

2.02 CONCRETE ADHESIVE ANCHORS

A. Concrete adhesive anchors shall be Type 316 stainless steel studs, bolts, nuts, and washers.

B. Adhesive for anchorage and doweling in hardened concrete shall be 2-component, insensitive to moisture, and be designed for installation in adverse environments.

C. Adhesive anchors shall be pre-proportioned adhesive system or an adhesive capsule system.

D. Stainless steel fasteners shall conform to the requirements of ASTM A193, Grade B8MA or B8MNA Type 316 or 316N or ASTM F593 Type 316. Stainless steel nuts shall conform to ASTM A194, Type 316 or ASTM F594, Type 316.

03250-3 E. Studs and nuts shall be Type 316 stainless steel threaded rod free of grease, oil, or other deleterious material

F. Studs embedded end shall have a 45° point.

G. The cure temperature, pot life, and workability of adhesive shall be compatible for intended use and anticipated environmental conditions.

H. Acceptable Products:

1. Hilti, Inc., HIT HY-200 Adhesive Anchors

2. Hilti, Inc., HIT RE 500-SD Adhesive Anchor,

3. Simpson Strong-Tie, Inc., SET-XP Epoxy Adhesive Anchor,

4. Or approved equal.

2.03 EXPANSION ANCHORS

A. Mechanical expansion anchors shall be used for the installation of comparatively light metal accessories such as handrails and etc. that are not required to be installed before the concrete is placed or as specified by the engineer. Mechanical anchors shall be wedge type stud anchor systems.

B. Drop-in anchors will not be permitted in applications to resist seismic or wind loading.

C. Expansion anchors will not be permitted in applications that will be subjected to vibrations or impact loads and shall not be used in concrete masonry.

D. Acceptable Products:

1. Hilti, Inc., Kwik Bolt TZ,

2. ITW Ramset / Red Head, Trubolt Plus Stainless Steel Seismic Anchor,

3. Simpson Strong Tie, Inc., Strong Bolt 2 Wedge Anchor,

4. Or approved equal.

2.04 ANTI GALLING COMPOUND

A. All threaded portions of stainless steel bolts, studs, and cap screws shall be coated with an NSF 61 certified thread lubricant anti galling compound.

B. Acceptable Products:

1. Laco, Slic-Tite;

03250-4 2. Hercules, Real-Tuff;

3. Or approve equal.

PART 3 EXECUTION

3.01 GENERAL

A. Dispensing, Metering, or Mixing Adhesive Components: The Contractor shall use portable, automatic metering and mixing device or machine capable of maintaining prescribed mix ratio within deviation of 5% or less, by volume. Dispensing equipment shall be as recommended by the manufacturer and approved by Construction Manager.

B. The Contractor shall install anchors in accordance with the manufacturer's printed recommendations.

C. The Contractor shall dispense components through a specially designed static mixing nozzle that thoroughly mixes components and places mixed components at base of predrilled hole.

D. Mixing nozzles shall have non-removable internal static mixer required to ensure proper blending of components.

3.02 PREPARATION OF CONCRETE SURFACES

A. Concrete surfaces shall be prepared in accordance with the requirements of the applicable ICC Evaluation Report.

B. Holes for all studs shall be accurately located and drilled by using templates and jigs.

C. Drilling Equipment:

1. Drilling for holes shall be electric or pneumatic rotary type with medium or light impact.

2. The Contractor shall use bit diameter in accordance with the manufacturer’s instructions and the applicable ICC Evaluation Report.

3. Hollow shall be provided with flushing air systems.

4. Where edge distances are less than 2 inches, the Contractor shall use lighter impact equipment to prevent micro cracking and concrete spalling during drilling process.

03250-5 5. Obstructions in Drill Path:

a. When existing reinforcing steel is encountered during drilling and when approved by Construction Manager, the Contractor shall enlarge the hole by 1/8-inch, core through the existing reinforcing steel at the larger diameter, and resume drilling at original hole diameter.

b. Misdrilled holes shall be filled with adhesive, as specified in this Section, so as not to entrap or create air pockets.

6. Holes shall be made free of dust and loose materials by the use of moisture free and clean compressed air or other acceptable and approved means.

7. Anchor embedment depth and spacing shall be as shown on the Drawings.

3.03 INSTALLATION

A. Concrete anchors shall be installed in accordance with the manufacturer's printed recommendations and the requirements of the applicable ICC Evaluation Report. Manufacturer's recommended drills and equipment shall be used. Hole diameter is critical to installation; only drills recommended by the anchor manufacturer shall be used.

B. Anchor shall be dry and grease-free.

C. Turn and agitate anchor immediately following placement to ensure the absence of voids and to ensure that adhesive makes contact with all surfaces.

D. An anchor shall not be installed closer than 6 times its diameter to either an edge of concrete or 12 times its diameter to another anchor, unless specifically shown on the Drawings.

E. Adhesive anchoring system shall not be used when temperature of concrete is outside the ranges recommended by the manufacturer.

F. Specific manufacturer-safe handling practices shall be followed when handling and/or installing all concrete anchors.

G. Concrete shall be dry at the time of adhesive anchor placement.

H. After anchor stud installation and prior to assembly, all threaded portions of stainless steel bolts, studs, and cap screws shall be coated with a thread lubricant

I. Concrete adhesive anchors installation torque shall be in accordance with the provisions stated on the Drawings. In no case shall the torque exceed the manufacturer’s installation recommendations.

03250-6 J. Concrete expansion anchors installation torque shall be in accordance with the manufacturer’s installation recommendations.

K. Concrete screw anchors shall be installed in accordance with the manufacturer’s installation recommendations.

3.04 CURING

A. Adhesive materials shall be protected from temperature extremes in accordance with the applicable ICC Evaluation Report.

B. The temperature of the base materials shall not exceed the range permitted in the applicable ICC Evaluation Report.

3.05 FIELD QUALITY CONTROL

A. Construction Manager will inspect concrete surfaces prior to application.

B. The Contractor shall engage the services of a testing agency to provide special inspection services when required by applicable International Code Council (ICC) Evaluation Reports. Special inspection personnel shall be certified for the specific application. Special inspection personnel shall be an independent commercial testing firm approved by Construction Manager.

3.06 CLEANUP

A. Concrete surfaces beyond the limits of the adhesive shall be protected against spillage.

B. Adhesive applied or spilled beyond desired areas shall be immediately removed. Cleanup shall be performed with material designated by the adhesive manufacturer.

**END OF SECTION**

03250-7

SECTION 03300

CAST-IN-PLACE CONCRETE

PART 1 GENERAL

1.01 DESCRIPTION

A. This Section includes all Work associated with cast-in-place concrete and required accessories as shown on the Drawings and specified in this Section.

1.02 REFERENCES

A. This section contains references to the following documents. They are a part of this section as specified and modified. Where a referenced document contains references to other standards, those documents are included as references under this section as if referenced directly. In the event of conflict between the requirements of this section and those of the listed documents, the requirements of this section shall prevail.

B. Unless otherwise specified, references to documents shall mean the documents in effect at the time of Advertisement for Bids or Invitation to Bid (or on the effective date of the Agreement if there were no Bids). If referenced documents have been discontinued by the issuing organization, references to those documents shall mean the replacement documents issued or otherwise identified by that organization or, if there are no replacement documents, the last version of the document before it was discontinued. Where document dates are given in the following listing, references to those documents shall mean the specific document version associated with that date, regardless of whether the document has been superseded by a version with a later date, discontinued or replaced.

C. Except as otherwise indicated in this Section, the Contractor shall comply with the latest edition of the Uniform Standard Specifications and Details for Public Works Constructions by the Maricopa Association of Governments (MAG).

1.03 SUBMITTALS

A. Submittals shall be made in accordance with Specifications Section 01300, Submittals, and the following special provisions provided herein.

B. Concrete mix designs shall be prepared and stamped by Arizona professional civil or structural engineer. Mix design shall show the ingredients of the mix and shall include:

1. Type, brand, source, and amounts of cement, pozzolans, admixtures, or other additives

03300-1 2. Source and amounts of water and aggregates

3. Sieve analysis of coarse and fine aggregates

4. Combined grading of each mix design

5. Specific gravity of all materials

6. Concrete Admixtures: Material specifications and instructions for use

7. Identify off-site batch plant supplier and plant location

C. Test Reports and Certifications: The following reports and certifications shall be submitted.

1. Mill certificates and certified test reports showing physical and chemical analysis for reinforcing steel

2. Concrete delivery ticket with the information stated in ASTM C94 Section 16, furnished before unloading at the site.

D. Concrete Procedures

1. Procedure for placement of concrete

2. Procedure for curing concrete

E. Materials Testing Laboratory

1. The name and qualifications of the Contractor proposed materials testing laboratory shall be submitted to Construction Manager for approval a minimum of 10 working days prior to any material testing.

2. The materials testing laboratory shall be independent commercial testing firm approved Construction Manager.

1.04 DELIVERY, STORAGE, AND HANDLING

A. Reinforcing steel shall be tagged showing quantity, grade, size, and piece mark identifying location. Unidentified reinforcing steel will be rejected.

B. Storage and Protection: Reinforcing steel shall be stored off the ground and protected from deleterious materials.

03300-2 PART 2 PRODUCTS

2.01 CONCRETE

A. Concrete shall be in accordance with the provisions stated in MAG Section 725, concrete class AA, except as modified in this section.

B. Concrete shall be in accordance with ASTM C94 and these Specifications. If a conflict exists between ASTM C94 and these Specifications, these Specifications shall govern.

C. Portland cement shall be in accordance with ASTM C150, type V low-alkali. Fly ash, if used, shall not exceed 20%, as a percentage by weight of total cementitious material. Additional cement may be used to obtain a high-early-strength concrete

D. Water shall be in accordance with ASTM C94, and shall be clean and free from objectionable quantities of organic matter, alkali, salts, and other impurities that might reduce the strength, durability, or quality of the concrete. Water shall contain no more than 650 parts per million of chlorides as Cl nor more than 1000 parts per million of sulfates as SO4.

E. Concrete shall have a combined aggregate grading as follows:

Sieve Size Percent passing 1½” 100 1” 95 - 100 ¾” 77 – 93 3/8” 50 – 70 No.4 39 – 51 No.8 31 – 41 No.16 22 – 32 No.30 12 – 22 No.50 3 – 15 No.100 0 – 5 No.200 0 - 2

F. Aggregate shall not originate from sources susceptible to producing reactive or degenerative rock products.

G. Concrete Admixtures:

1. Concrete shall contain an air-entraining admixture in accordance with ASTM C260. The air-entraining agent shall be added to provide 4.5% ± 1% air entrainment in the concrete as discharged from the mixer.

03300-3 2. Concrete shall contain a water-reducing admixture in accordance with ASTM C494, Type A or Type D.

3. Concrete admixtures shall be added to the concrete mix in accordance with the manufacturer's printed recommendations to achieve optimum performance.

H. Concrete ultimate compressive strength at 28 days shall be not less than 4,000 psi.

I. Concrete shall contain a minimum cement content of 600 pounds per cubic yard of concrete (6½ sack mix).

J. Water-cement ratio shall not exceed 0.45. Water-cement ratio shall be determined by weight of water and Portland cement or weight of water and Portland cement plus pozzolan.

K. Concrete slump shall not exceed 4 inches.

2.02 REINFORCING STEEL

A. Concrete reinforcing steel materials shall be in accordance with the provisions stated in MAG Section 727, except as modified in this section.

B. Deformed reinforcing bars shall be in accordance with ASTM A615, Grade 60. Deformed reinforcing steel to be welded shall be in accordance with ASTM A706, Grade 60.

C. Accessories:

1. Tie wire shall be 16 or heavier, black, soft annealed, unless noted otherwise.

2. Reinforcement support cement mortar cubes (dobes) shall be of the same strength and density as the concrete in the Section being placed. Plastic supports and plastic-tipped supports shall not be used.

D. All reinforcing steel shall be fabricated in accordance with ACI 315 and ACI 318, except as noted on the Drawings or within these Specifications.

E. All reinforcing steel shall be bent cold.

2.03 CONCRETE BONDING AGENT

A. Products:

1. Intralock, manufactured by W.R. Meadows

2. Armatec 110 Epocem, manufactured by Sika

03300-4 3. Daraweld C, manufactured by W.R. Grace

4. Or approved equal.

2.04 CONCRETE SLURRY

A. Concrete slurry shall be in accordance with the provisions stated in MAG Section 725, Concrete Class C, except as modified in this section.

B. Concrete slurry shall be in accordance with the provisions stated above in Paragraph 2.01, Concrete, with the following exceptions noted below:

1. Concrete slurry shall have a combined aggregate grading as follows:

Sieve Size Percent passing ¾” 100 3/8” 90 - 100 No.4 60 - 80 No.8 50 - 70 No.16 33 - 53 No.30 19 - 35 No.50 5 – 15 No.100 2 – 7 No.200 0 - 4

2. Concrete slurry ultimate compressive strength at 28 days shall be not less than 2,000 psi.

3. Concrete shall contain a minimum cement content of 420 pounds per cubic yard of concrete (4½ sack mix).

4. Water-cement ratio shall not exceed 0.50. Water-cement ratio shall be determined by weight of water and Portland cement or weight of water and Portland cement plus pozzolan.

5. Concrete slump shall not exceed 8 inches.

2.05 CURING MATERIALS

A. Concrete curing materials shall be in accordance with the provisions stated in MAG Section 726.

B. Absorptive Cover: AASHTO M182, Class 2, burlap cloth made from jute or kenaf.

03300-5 C. Moisture-Retaining Cover: ASTM C171, polyethylene film or white burlap- polyethylene sheet.

D. Curing Compound: ASTM C309, Type 1, Class B, clear, waterborne, membrane- forming compound.

2.06 EXPANSION JOINTS

A. Bond Breaker Tape

1. Bond breaker tape shall be an adhesive-backed glazed butyl or polyethylene tape which will satisfactorily adhere to the premolded joint material or concrete surface as required.

2. Bond breaker tape shall be the same width as the joint.

B. Premolded Joint Filler

1. Expansion joint filler material shall conform to the joint dimensions and material type designated on the Drawings.

2. Sponge Rubber: Sponge rubber filler shall be of the preformed, non- extruding, resilient, non-bituminous type in accordance with the requirements of ASTM D1752, Type I.

3. Bituminous expansion joint filler shall consist of strips of preformed, non- extruding, resilient, bituminous-fiber-type material in accordance with ASTM D1751.

C. Joint Sealant

1. Joint sealant shall conform to the requirements of ASTM C920, Type M, Grade P, Class 25, Use T.

2. Joint sealant shall have a Shore “A” hardness range of 25 to 35 in accordance with ASTM D2240.

3. Approved Products:

a. Sika, Sika Flex 2C NS/SL

b. Or approved equal.

2.07 NONSHRINK GROUT

A. Nonshrink grout shall be a cementitious, inorganic, nonmetallic, nonstaining, nonshrinking, premixed grout requiring only the addition of water. Nonshrink

03300-6 grout shall not require mortar cap or other protection following placement and curing.

B. Nonshrink grouts shall be in accordance with ASTM C1107 except that the compressive strength shall be not less than 5,000 psi in 7 days and not less than 7,000 psi in 28 days.

C. Products:

1. Master Flow 713, manufactured by Master Builders Company

2. Five Star Grout, manufactured by US Grout Corporation

3. Or approved equal.

PART 3 EXECUTION

3.01 GENERAL

A. The term concrete and the provisions stated in part 3, Execution shall to structural concrete and slurry concrete, except where specifically noted otherwise.

3.02 PREPARATION

A. Prior to placing concrete, reinforcing steel and embedded items shall be thoroughly cleaned of dirt, loose mill scale, excessive rust, oil, and other foreign substances that may reduce the bond between reinforcing steel and concrete.

B. Immediately before placing concrete, the surfaces upon or against which the concrete is to be placed shall be clean and free of standing water, mud, debris, loose material, oil, objectionable coatings; and other materials which could adversely effect the concrete quality. Surfaces shall be moistened with water immediately prior to placing concrete.

C. Surfaces of forms and embedded items that have been encrusted with dried mortar or grout from concrete previously placed shall be cleaned.

D. Reinforcing steel concrete cover shall be as indicated on the Drawings. When reinforcing steel concrete cover is not specified, reinforcing steel shall be placed not closer than:

1. 2 inches to formed concrete surfaces in contact with water, ground, or air

2. 3 inches to concrete surfaces placed directly against the earth

03300-7 E. Reinforcing steel shall be placed accurately in the position with the spacing shown on the Drawings and shall be securely fastened in position to prevent displacement during concrete placement.

F. Before new concrete is placed against hardened concrete, the bonding surface of the hardened concrete shall be roughened to a ¼-inch amplitude using blasting, or high-pressure water blasting. Concrete bonding agent shall be applied in accordance with the manufacture’s printed instructions. Fresh concrete may be green-cut with water blasting and hand tools to remove laitance and spillage and to expose sound aggregate. Cleaning, roughening, or cutting shall be performed without damage to embedded items or coatings.

G. The prepared surfaces of hardened concrete shall be kept thoroughly wet during the 24-hour period immediately prior to the placement of the new concrete. Wetting shall be accomplished by continuous sprinkling, by covering exposed surfaces with wet burlap, or by packing holes with burlap and keeping the burlap wet.

H. Embedded items shall be adequately secured in place against displacement during concrete placement with templates or other approved methods. Embedded items shall be kept clear of the reinforcement. Embedded items shall have a minimum 2 inches cover from the nearest outer surface of concrete unless otherwise required by the Drawings.

3.03 BATCHING AND MIXING OF MATERIALS

A. Cast-in-place concrete shall be produced at a single off-site batch plant. Only one concrete supplier will be approved.

B. The quantities of cement, pozzolanic materials and aggregates entering each batch of concrete shall be determined by automatic weighing. The quantity of water shall be determined by weighing or volumetric measurement.

C. Dispensers for admixtures shall have the capacity of the full quantity of the properly diluted solution required for each batch. Admixtures shall be added to the premeasured water for the batch or shall be discharged into the batch by flowing automatically and uniformly into the stream of mixing water from beginning to end of its flow into the mixer.

D. Transit Mixing

1. Transit mixers shall be in accordance with ASTM C94.

2. Truck mixers and their operation shall ensure concrete is discharged uniformly.

03300-8 3. Truck mixers shall be equipped with approved revolution counters by which the number of revolutions of the drum or blades may readily be verified. The water-tank system of the truck shall be equipped with gauges that permit accurate determination of the tank contents.

E. The methods and equipment used to transport concrete to the site and transportation elapse time shall not cause segregation of coarse aggregate or slump loss in excess of 1 inch when measured at the point of discharge. Only agitating equipment shall be used to transport concrete.

3.04 CONCRETE PLACEMENT

A. Concrete mixing, transportation, and placement on site shall be within 90 minutes after the water has been added to the cement and aggregates, and prior to stiffening or initial set. When air temperature is between 85ºF and 90ºF, mixing, delivery, and placement time shall be reduce to 75 minutes. When air temperature is above 90ºF, mixing, delivery, and placement time shall be reduced to 60 minutes.

B. Concrete chutes shall maintain a minimum slope to enable a consistent and steady flow of concrete.

C. Concrete pumps shall be operated only by experienced operators.

D. Concrete placement shall be performed to prevent concrete mix segregation and without high velocity.

E. Free fall of concrete shall not exceed 4 feet. The horizontal movement of concrete shall not exceed 5 feet. Concrete shall not be dropped through reinforcement. Mortar shall not accumulate on form surfaces above the placed concrete.

F. Consolidation

1. All concrete shall be consolidated with internal vibrators having a frequency of at least 7000 vibrations per minute. The number of vibrators employed shall be sufficient to consolidate the concrete within 15 minutes after concrete is deposited in forms.

2. Concrete shall be consolidated by vibration to the maximum practicable density. The concrete shall be free from pockets of coarse aggregate and entrapped air and shall close snugly against the surfaces of forms and embedded materials. In consolidating each layer of concrete, the vibrator shall be operated at regular and frequent intervals and in as nearly a vertical position as practicable.

3. The vibrating head shall penetrate into the preceding layer and then be withdrawn at a slow rate. The top part of each layer shall be re-vibrated

03300-9 systematically at the latest time the concrete can be made plastic by means of vibration. Concrete shall not be placed until the previous layer has been vibrated. The vibrating head shall not contact the surfaces of the forms. The use of vibrators for shifting or dragging concrete will not be permitted.

G. Horizontal construction joints shall be straight and level.

H. Vertical construction joints shall be straight and plumb.

I. Weather

1. Concrete placement will not be permitted during rainfall or when rain appears imminent. If rain should fall subsequent to placement, the concrete shall be completely protected until curing is complete.

2. Concrete shall not be placed on frozen ground nor mixed or placed when the temperature is 40°F or less and dropping, and the possibility of freezing is indicated by U.S. Weather Bureau frost warnings.

J. Protection

1. When concrete slab or other unformed concrete is placed under warm, dry, dusty, or windy conditions, concrete surfaces shall be protected from rapid drying by use of windbreaks, shading, fogging with properly designed nozzles, or a combination of these methods. Dust control shall be provided in the surrounding areas during placement.

2. Hot weather procedures provided in ACI 305R shall be used when ambient conditions dictate.

3. Cold weather procedures provided in ACI 306R shall be used when ambient conditions dictate.

4. Concrete shall be protected against damage until final acceptance by Construction Manager.

3.05 FINISHING CONCRETE SURFACES

A. Formed surfaces shall conform accurately to the shape, alignment, grades, and sections shown on the Drawings. Surfaces shall be free from fins, bulges, ridges, honeycombing, or roughness of any kind and shall present a finished, smooth, continuous, hard surface.

B. A steel-trowel finish shall be provided on unformed concrete surfaces unless otherwise specified. The addition of water to the surface during the finishing operation and dusting of dry cement or sand on the surface to absorb excess moisture shall not be permitted.

03300-10 C. At locations subject to light traffic, and locations indicated on the Drawings, a broom finish shall be provided. Upon completing the steel trowel finish, the concrete surface shall be roughened by drawing a broom over the surface.

D. Unless otherwise shown on the Drawings, exposed horizontal surfaces (e.g., floors, walkways, and roofs) shall be sloped a minimum of 1/8-inch per foot to drain water.

E. Concrete shall be cured by any of the following methods:

1. Curing compound, in accordance with the manufacturer’s written recommendations

2. Water spray, minimum 14 days

3. Curing blanket, minimum 4-mils thickness

4. Wet burlap mat, minimum 14 days

F. Special care shall be taken to prevent concrete from drying out during the curing period and to avoid damaging surfaces.

3.06 GROUTING

A. Concrete surface shall be roughened by abrasive blasting or other approved means to an amplitude of approximately 1/8-inch and to remove all laitance and unsound material. After roughening, the surface shall be cleaned using oil-free compressed air or water.

B. The concrete surface shall be saturated per the manufacturer’s recommendations prior to grouting.

C. Water content of the grout shall not exceed the maximum or less than the minimum stipulated by the manufacturer's printed instructions. Consistency of the grout shall be the minimum that will reliably result in complete filling of the joint space to be grouted.

D. The exposed surfaces of newly placed grout shall be protected from drying by using wet burlap, wet sand, plastic sheeting, or a water soaker hose and shall be kept continuously moist for 7 days. After 7 days and while the surface is still damp, 2 coats of curing compound shall be applied to prevent moisture loss.

3.07 PROTECTION

A. Concrete surfaces shall be protected from rapid drying. Contractor shall provide protective measures as required.

03300-11 B. Hot weather concrete procedures per ACI 350R shall be used when ambient conditions dictate.

C. Cold weather concrete procedures per ACI 306R shall be used when ambient conditions dictate.

D. Concrete shall not be loaded until concrete has attained 85% of the minimum specified design compressive strength or a minimum of 14 calendar days.

1. Contractor may consider temporary supports to prevent loading concrete prior to obtaining required strength. All temporary supports shall be provided at no additional cost to Construction Manager and shall be subject to Construction Manager approval.

3.08 JOINTS

A. General

1. Concrete placement shall not commence until after the joint preparation has been inspected and approved by the Construction Manager.

2. Joints shall be accurately located and constructed to produce straight joints and shall be vertical or horizontal.

B. Installation

1. Filler shall be cut to the size and shape of the joint surface to be covered and securely held in place.

2. Joints between portions of the joint filler shall be sufficiently tight to prevent mortar from seeping through.

3. The edges of joint filler shall be placed flush with the finished surface of the concrete or to the bottom edge of the chamfers, except where polyurethane sealant is required to be placed, in which case the edge of the joint material shall be trimmed in accordance with details shown on the Drawings.

C. Sealant

1. All expansion joints shall be filled with joint sealant and shall be provided with tapered grooves as shown on the Drawings.

2. The material used for forming the tapered grooves shall be left in place in the groove until after all forms have been removed and the floors or other adjacent areas have been cleaned and swept. After the forms have been removed from the grooves, all laitance and fins shall be removed and the grooves shall be sandblasted.

03300-12 3. Surfaces to accept sealant shall be cleaned and primed in accordance with the sealant manufacturer's printed recommendations.

4. The sealant shall be placed in accordance with the printed recommendations of the manufacturer; special care shall be taken to properly mix the sealant before its application.

3.09 FIELD QUALITY CONTROL

A. Tolerances shall be in accordance with ACI 117.

B. The Contractor shall engage the services of an independent commercial testing firm to perform material tests for material compliance with these Specifications.

1. Concrete compressive strength tests representing concrete that has been placed shall attain the following 28-day strength: The average of all sets of 3 consecutive strength tests shall be equal to or greater than the specified 28-day strength. Not more than 10 percent of the tests shall be less than the specified 28-day strength. No individual test shall be more than 500 psi below the specified 28-day strength.

2. Testing Frequency: One set of test cylinders for each 50 cubic yards of concrete or one set of test cylinders for each day of concrete placement, whichever results in more test cylinders.

3. Concrete that is represented by compressive strength tests and that fails to meet the requirements of this Section shall be removed from the Work.

4. Compressive strength will be determined by testing fabricated 6-inch by 12-inch cylinders that have been cured in accordance with ASTM C31. The cylinders will be tested in accordance with ASTM C39.

5. Each set of concrete compressive strength tests shall consist of minimum (5) test cylinders. Each set of test cylinders shall consist of (1) 7-day test, (1) 14-day test, (2) 28-day tests, and (1) spare cylinder.

C. Field Inspection

1. Concrete shall not be placed until all formwork, installation of embedded items, and preparation of surfaces have been inspected and approved by Construction Manager.

2. Concrete finishing and repairs shall be performed in the presence of Construction Manager.

**END OF SECTION**

03300-13

SECTION 05500

MISCELLANEOUS METALS

PART 1 GENERAL

1.01 DESCRIPTION

A. This Section includes furnishing and installing miscellaneous metal work as indicated in the Contract Documents and specified in this Section.

1.02 REFERENCES

A. This section contains references to the following documents. They are a part of this section as specified and modified. Where a referenced document contains references to other standards, those documents are included as references under this section as if referenced directly. In the event of conflict between the requirements of this section and those of the listed documents, the requirements of this section shall prevail.

B. Unless otherwise specified, references to documents shall mean the documents in effect at the time of Advertisement for Bids or Invitation to Bid (or on the effective date of the Agreement if there were no Bids). If referenced documents have been discontinued by the issuing organization, references to those documents shall mean the replacement documents issued or otherwise identified by that organization or, if there are no replacement documents, the last version of the document before it was discontinued. Where document dates are given in the following listing, references to those documents shall mean the specific document version associated with that date, regardless of whether the document has been superseded by a version with a later date, discontinued or replaced.

C. Except as otherwise indicated in this Section, the Contractor shall comply with the latest edition of the Uniform Standard Specifications and Details for Public Works Constructions by the Maricopa Association of Governments (MAG).

Reference Title ASTM A36 Standard Specification for Carbon ASTM A53 Standard Specification for Pipe, Steel, Black and Hot-Dipped, Zinc-Coated, Welded and Seamless ASTM A108 Standard Specification for Steel Bar, Carbon and Alloy, Cold-Finished ASTM A123 Standard Specification for Zinc (Hot-Dip Galvanized) Coatings on Iron and Steel Products

05500-1 Reference Title ASTM A143 Standard Practice for Safeguarding Against Embrittlement of Hot-Dip Galvanized Structural Steel Products and Procedure for Detecting Embrittlement ASTM A153 Standard Specification for Zinc Coating (Hot-Dip) on Iron and Steel Hardware ASTM A167 Standard Specification for Stainless and Heat-Resisting Chromium-Nickel Steel Plate, Sheet, and Strip ASTM A193 Standard Specification for Alloy-Steel and Stainless Steel Bolting for High Temperature or High Pressure Service and Other Special Purpose Applications ASTM A194 Standard Specification for Carbon and Alloy Steel Nuts for Bolts for High Pressure or High Temperature Service, or Both ASTM A276 Standard Specification for Stainless Steel Bars and Shapes ASTM A307 Standard Specification for Bolts, Studs, and Threaded Rod 60,000 PSI Tensile Strength ASTM A283 Standard Specification for Low and Intermediate Tensile Strength Carbon Steel Plates ASTM A312 Standard Specification for Seamless, Welded, and Heavily Cold Worked Austenitic Stainless Steel Pipes ASTM A380 Standard Practice for Cleaning, Descaling, and Passivation of Stainless Steel Parts, Equipment, and Systems ASTM A384 Standard Practice for Safeguarding Against Warpage and Distortion During Hot-Dip Galvanizing of Steel Assemblies ASTM A500 Standard Specification for Cold-Formed Welded and Seamless Carbon Steel Structural Tubing in Rounds and Shapes ASTM A554 Standard Specification for Welded Stainless Steel Mechanical Tubing ASTM A563 Standard Specification for Carbon and Alloy Steel Nuts ASTM A564 Standard Specification for Hot-Rolled and Cold-Finished Age-Hardening Stainless Steel Bars and Shapes ASTM A780 Standard Practice for Repair of Damaged and Uncoated Areas of Hot-Dip Galvanized Coatings ASTM A992 Standard Specification for Structural Steel Shapes ASTM A1008 Standard Specification for Steel, Sheet, Cold-Rolled, Carbon, Structural, High-Strength Low-Alloy, High-Strength Low-Alloy with Improved Formability, Solution Hardened, and Bake Hardenable ASTM B209 Standard Specification for Aluminum and Aluminum-Alloy Sheet and Plate

05500-2 Reference Title ASTM B221 Standard Specification for Aluminum and Aluminum-Alloy Extruded Bars, Rods, Wire, Profiles, and Tubes ASTM F436 Standard Specification for Hardened Steel Washers ASTM F593 Standard Specification for Stainless Steel Bolts, Hex Cap Screws, and Studs ASTM F594 Standard Specification for Stainless Steel Nuts ASTM D7091 Standard Practice for Nondestructive Measurement of Dry Film Thickness of Nonmagnetic Coatings Applied to Ferrous Metals and Nonmagnetic, Nonconductive Coatings Applied to Non-Ferrous Metals AWS A5.4 Specification for Stainless Steel for Shielded Metal AWS A5.9 Specification for Bare Stainless Steel Welding Electrodes and Rods AWS B2.1 Specification for Welding Procedure and Performance Qualification AWS D1.1 Structural Welding Code - Steel AWS D1.2 Structural Welding Code - Aluminum AWS D1.6 Structural Welding Code - Stainless Steel AWS D10.4 Recommended Practices for Welding Austenitic Chromium – Nickel Stainless Steel Pipe and Tubing AWS D10.12 Guide for Welding Mild Steel Pipe SSPC SP-3 Power Tool Cleaning SSPC SP-5 White Metal Blast Cleaning

1.03 SUBMITTALS

A. Submittals shall be made in accordance with the Specifications Section 01300, Submittals, and the following special provisions provided herein.

B. Shop Drawings

1. Before beginning fabrication of structural steel, the Contractor shall submit complete shop and erection drawings showing details of methods, materials, tolerances on adjustable connections, and finishes. Shop drawings shall give complete information necessary for the fabrication and erection of the component parts of the structure including the location, type, and size of all welds and bolts. Drawings shall clearly distinguish between shop or field welds and bolts.

2. Separate plans for the setting of anchors and bearing plates, prepared in coordination with concrete placement drawings, shall be submitted and approved prior to the placement of concrete.

05500-3 C. Weld Procedure Qualifications

1. Welding Procedure Specifications (WPS) shall be submitted per AWS D1.6, or AWS D1.2 as applicable. Pre-qualified procedure may be submitted. The WPS forms shall be per AWS.

2. Welder, Welding Operator, and/or Tack welder Qualification Test Records shall be submitted on Form NE-4 of AWS D1.1 for approval for all welding personnel proposed for employment on the project.

3. Test shall be in accordance with AWS D1.1 and shall be made using the positions to be used in the work.

4. Construction Manager may require additional test plates as the work progresses and may demend the removal from the Project of any welder whose work is not satisfactory, regardless of the quality of the test welds.

D. Pre-fabricated Access Hatch

1. Product information.

2. Shop fabrication drawings.

E. Prior to the start of fabrication, the Contractor shall establish and submit an identification system for marking of material ordered to special requirements and for field identification of assemblies and assembly components.

1.04 QUALITY ASSURANCE

A. Welder Qualifications: Welding welder qualification requirements and welding procedures shall be in accordance with AWS D1.1.

1. In lieu of performing welding operator or tack welder qualification tests, the Contractor may employ personnel possessing a current AWS certification in accordance with AWS D1.1.

B. Records of steel manufacturer shall be kept, materials shall be properly identified, and shop fabrication records shall show that the proper material was incorporated into each item. Such records shall be available to Construction Manager upon request.

1.05 DELIVERY, STORAGE, AND HANDLING

A. Erection and identification marks shall be applied to the members by painting or other suitable means, unless otherwise specified or approved by Construction Manager.

05500-4 B. The Contractor shall take reasonable care in the proper handling and storage of articles or materials during erection operations to avoid accumulation of dirt and foreign matter. The Contractor shall remove from the articles or materials, dust, dirt, or other foreign matter that accumulates during construction. Coated surfaces shall be protected from abrasion or other damage during handling, storing, and erecting.

C. Materials taken from stock shall comply with the appropriate ASTM standards, including the applicable test reports, prepared at the mill where the material was manufactured, or at a testing laboratory approved by Construction Manager.

PART 2 PRODUCTS

2.01 MATERIALS

A. Carbon Steel

1. Carbon steel bars, shapes, and plates shall be in accordance with ASTM A36, ASTM A108, ASTM A283, or ASTM A992 with a minimum yield of 36 ksi.

2. Hollow steel sections (HSS) (square, round, and rectangular) shall be in accordance with ASTM A500 Grade B or ASTM A1085.

3. Pipe (including handrails, pipe columns, and light standards) shall be in accordance with ASTM A53, Grade B or ASTM A108.

4. Light gauge galvanized sheet metal shall be in accordance with ASTM A446 Grade A with a G90 coating, cold rolled.

5. Cold-rolled sheet metal shall be in accordance with ASTM A366, commercial quality.

B. Stainless Steel

1. Unless otherwise shown on the drawings, materials in contact with water, intermittently or continuously, or in a wet or moist environment shall be stainless steel.

a. Stainless steel bars and shapes shall be in accordance with ASTM A276 Type 316 Condition A, or Type 316L Condition A where welding is required, unless otherwise specified or shown on the drawings.

b. Stainless steel plate, sheet, and strip shall be in accordance with ASTM A167 Type 316 No. 1 finish, or Type 316L No. 1 finish

05500-5 when welding is required, unless otherwise specified or shown on the drawings.

c. Pipe shall be in accordance with ASTM A312 Type 316L.

d. Tubing specified by outer diameter and thickness shall be in accordance with ASTM A554 Grade MT316L.

2. Where age-hardened stainless steel is shown on the drawings, the steel shall be in accordance with ASTM A564 Type 630, cold finished. Heat- treatment or age-hardening shall be conducted at 900 F, except bolts and shafts, which shall be age-hardened at 1150° F.

3. Spring nuts, bolts, and other materials shall not be fabricated using powder metalurgy (PM) methods.

C. Aluminum

1. Aluminum bars, plate, and shapes shall be in accordance with ASTM B221 Alloy 6061 or Alloy 6063. Temper designation shall be as shown in the drawings.

2. Aluminum plate shall be in accordance with ASTM B209 Alloy 5052 or Alloy 6061.

D. Fasteners

1. Threads for bolts and nuts shall be in accordance with ANSI B1.1.

a. Threads for bolts 1 inch and less in diameter shall be coarse-thread series and threads for bolts 1-1/8 inches and greater in diameter shall be the 8-pitch thread series.

b. The fit shall be Class 2 free fit; except that Class 3 medium fit shall be provided in holes tapped for studs.

2. Unless otherwise shown on the drawings, bolts shall have heavy hexagon heads and heavy hexagon nuts.

3. The lengths of studs and bolts, excluding anchor bolts, shall provide a projection of not less than 1/4 inch nor more than 1/2 inch through the nut when it is drawn tight; however, in exposed locations the projection shall be not more than 1/4 inch.

05500-6 4. Carbon Steel Fasteners, Anchor Bolts, Machine Bolts, and Threaded Rods

a. Anchor bolts, machine bolts, and threaded rods shall be heavy hex and in accordance with ASTM A307 Grade A, with Supplement S- 1 where welding is required, unless otherwise shown.

b. Nuts shall be in accordance with ASTM A563 Grade A, heavy hex.

c. Hardened washers shall be in accordance with ASTM F436, Type 3.

5. Stainless Steel Fasteners

a. Except as otherwise specified or shown on the drawings, stainless steel fasteners shall be used where the material will be immersed in water, intermittently or continuously, or in moist-environment installations.

(1) Type 316 or 316N stainless steel fasteners shall be in accordance with ASTM A193 Grade B8MA, or Grade B8MNA for bolting and stud material, and ASTM A194 Grade 8MA or Grade 8MNA for nuts. Fasteners for age- hardened stainless steel shall be manufactured in accordance with ASTM F593 and ASTM F594 Type 630.

(2) Stainless steel washers shall conform to ASTM F844 except that they shall be punched from steel conforming to ASTM 167 Type 316 or machined from bar stock conforming to ASTM A276 Type 316.

(3) Stainless steel fasteners shall be Type 316 or 316N unless otherwise shown on the drawings. An anti-galling compound shall be applied in the fastener threads in accordance with the manufacturer’s printed instructions.

6. Insulating Washers

a. Insulating washers shall be black, nylon material.

b. Insulating washers shall be shoulder washers or flat washers with full, depth unthreaded sleeve spacers.

E. Electrodes

1. Electrodes for welding carbon steel shall be in accordance with AWS D1.1 except that electrodes shall have a minimum yield of 70 ksi. Electrodes for shielded metal arc welding (SMAW) shall be low hydrogen.

05500-7 2. Electrodes for welding stainless steel to stainless steel shall be in accordance with AWS A5.4 or AWS A5.9 Classification E316L/ER316L.

F. Anti-Galling Compound

1. The anti-galling compound to be used on threads of stainless steel fastener assemblies in potable water systems shall be an ANSI/NSF 61-certified compound.

2. Acceptable Products:

a. Laco, Slic-Tite

b. Hercules, Real-Tuff

c. or approved equal

2.02 ACCESS HATCHES

A. Access hatches shall be a pre-assembled roof hatch to the size and dimensions indicated on the Drawings.

B. Hatch cover shall be a single leaf hinged on one side.

C. Cover: Shall be 11 gauge aluminum with a 3” beaded flange with formed reinforcing members. Cover shall have a heavy extruded EPDM rubber gasket bonded to the cover interior to assure a continuous seal when compressed to the top surface of the curb.

D. Cover insulation shall not be provided on roof hatch curb or frame.

E. Lifting mechanisms: Manufacturer shall provide compression spring operators enclosed in telescopic tubes to provide, smooth, easy, and controlled cover operation throughout the entire arc of opening and closing. The upper tube shall be the outer tube to prevent accumulation of moisture, grit, and debris inside the lower tube assembly. The lower tube shall interlock with a flanged support shoe welded to the curb assembly.

F. Hardware:

1. Hinges shall be heavy pintle type.

2. Cover shall be equipped with a spring latch with interior and exterior turn handles.

3. Roof hatch shall be equipped with interior and exterior padlock hasps.

4. The latch strike shall be a stamped component bolted to the curb assembly.

05500-8 5. Cover shall automatically lock in the open position with a rigid hold open arm equipped with a 1 inch diameter red vinyl grip handle to permit easy release for closing.

6. Hardware shall be Type 316 stainless steel.

7. Compression spring tubes shall be an anti-corrosive composite material.

8. Cover hardware shall be bolted into heavy gauge channel reinforcing welded to the underside of the cover.

G. Acceptable Products

1. Type E Roof Hatch manufactured by The Bilco Company

2. Or approved equal.

2.03 FABRICATION OF MISCELLANEOUS METALWORK

A. The Contractor shall take the necessary precautions, as described in ASTM A143 and ASTM A384, during fabrication of articles to be galvanized to properly fabricate and prepare the material to prevent embrittlement, warpage, and distortion.

1. Steel tubing with cover plates welded at both ends or other enclosed assemblies shall have vent and drain holes drilled at locations shown on the assembly fabrication drawings approved by Construction Manager. The holes shall be drilled during fabrication and before galvanizing.

B. Prior to beginning fabrication, the Contractor shall field-verify existing conditions and dimensions and shall be responsible for accuracy and layout of the work.

C. The Contractor shall review the drawings and the approved shop and erection drawings and shall report any discrepancies to the Construction Manager for clarification before starting fabrication.

D. After shop fabrication, stainless steel welds shall be cleaned, pickled, and passivated in accordance with ASTM A380. Contaminated surfaces shall be cleaned in accordance with ASTM A380 as approved by Construction Manager.

2.04 FABRICATION - WELDING PROCESS RESTRICTIONS

A. SMAW will be permitted for manual welding.

B. In automatic welding, both the rate of travel and the rate of deposition of metal shall be controlled automatically.

C. (SAW) will be permitted for automatic or semi-automatic welding.

05500-9 D. Gas metal-arc welding (GMAW) will be permitted for semi-automatic welding, short circuit transfer mode is not allowed.

E. Flux-core arc welding (FCAW) will be permitted only where specifically approved by Construction Manager and provided that auxiliary gas shielding process is used.

2.05 FABRICATION - WELDING OF CARBON STEEL

A. Except for the modifications set forth in this section, the welding of miscellaneous metals or articles fabricated from carbon steel shall be in accordance with AWS D1.1.

1. Electrodes for field welding shall not exceed 3/16 inch.

2. Welding of pipe or tubing shall be in accordance with the recommendations of AWS D10.12.

3. Runoff tabs shall be removed by hand flame-cutting or other means as close to the edge of the finished member as practical, followed by grinding to a smooth surface contiguous with the adjacent metal.

2.06 FABRICATION - WELDING OF STAINLESS STEEL

A. Welding of miscellaneous metal articles fabricated from stainless steel shall be in accordance with the following:

1. Welding on austenitic stainless steel shall be performed by SMAW, GMAW, gas-tungsten arc welding (GTAW), or FCAW process using direct current.

2. Weld procedures shall be qualified in accordance with AWS B2.1.

a. Interpass temperature shall not exceed 350° F.

3. Welding of stainless pipe or tubing shall be in accordance with the recommended practices of AWS D10.4.

4. Stainless steel to carbon steel welds will not require stress-relieving heat treatment.

5. Stress-relieving of austenitic stainless steel, where deemed necessary by Construction Manager, shall be performed at 750 F for 4 hours, plus an additional 1/2 hour for each additional inch over 1/2 inch weld section thickness, or a full solution anneal at 1900 F shall be performed with rapid quench.

05500-10 6. Stainless steel welds shall be deburred and ground smooth using grinding wheels of aluminum oxide. Carborundum or other carbon bearing wheels are not acceptable for use on stainless steel surfaces. Wire brushing of stainless steel surfaces shall be performed only with stainless steel brushes. Grinding wheels and brushes used to clean stainless steel shall not have been used on carbon steel surfaces.

2.07 SHOP FINISHES

A. Galvanizing

1. Miscellaneous metal parts shall be galvanized when shown on the drawings.

2. Galvanizing for shapes, plates, and fabricated items shall be in accordance with ASTM A123 with an average weight per square foot of 2.0 ounces and not less than 1.8 ounces per square foot.

3. Bolts, anchor bolts, and other threaded fasteners required to be galvanized shall, after being properly cleaned, be coated in accordance with ASTM A153 Table 1.

4. Except where otherwise specified, galvanizing shall be performed after fabrication, including cutting, punching, welding, and drilling.

5. Prior to galvanizing, items shall be cleaned to meet SSPC SP-3.

a. Weld flux, weld spatter, minor weld defects, paint, and grease shall be removed.

b. Parts shall be alkaline cleaned and then acid pickled to remove mill scale and surface rust.

6. Galvanizing shall be done after all fabrication is completed.

7. Where galvanized light-gauge sheet goods are specified, upset edges of factory -punched holes need not have the bare edges regalvanized and the galvanized coating adjacent to such die-punched edges need not be repaired.

05500-11 PART 3 EXECUTION

3.01 INSTALLATION

A. Installation and anchorage details for items of miscellaneous metal, regardless of ultimate usage (ornamental, structural, architectural, mechanical, or electrical) shall be as shown on the Drawings. Details not shown on the Contract Drawings shall be developed by the Contractor and indicated on the shop drawings.

B. Anti-galling compound shall be used each time stainless steel fasteners or combination stainless steel and silicon bronze fasteners are assembled or reassembled.

C. Anchor Bolts

1. Anchor bolts shall be accurately set and maintained in position by templates while placing concrete.

2. Anchor bolts shall be cleaned of dirt and other foreign substances prior to placing concrete. Tape or other protection shall be provided to prevent anchor bolt threads from being filled with concrete.

3. Whenever it is impractical to place anchors or anchor bolts required for the installation of comparatively light metal accessories before the concrete is placed, concrete anchors shall be installed in accordance with Section 03250.

3.02 REPAIR OF GALVANIZED SURFACES

A. Galvanized surfaces damaged during fabrication, shipping, erection, or at any time prior to acceptance of the work shall be prepared and recoated according to one of the following methods.

1. The damaged components shall be thoroughly stripped and cleaned of all coating, and new galvanizing shall be applied by the hot-dipped process in accordance with ASTM A123 or ASTM A153 as applicable.

2. The method of repair of damaged areas shall be as approved by Construction Manager. Damaged areas shall be repaired by one of the methods listed below as specified in ASTM A780 with the following modifications:

a. Repair surfaces shall be blasted clean to meet SSPC SP-5 or cleaned by mechanical means to meet SSPC SP-3 and coated immediately before any deterioration (flash-rust) occurs.

b. Sprayed Zinc (Metalizing): 4.0 mils minimum thickness using a wire with at least 98 percent zinc.

05500-12 c. Zinc-Based Solders: 4.0 mils minimum thickness.

3. Dry film thickness shall be verified using a magnetic-type gauge in accordance with ASTM D7091.

4. The finished surface shall be of uniform texture, free of lumps, coarse areas, and loosely adhered areas.

**END OF SECTION**

05500-13

SECTION 07120

FLUID APPLIED MEMBRANE

PART 1 GENERAL

1.01 DESCRIPTION

A. This Section includes furnishing and applying a fluid-applied membrane over concrete, stainless steel, and geomembrane liner surfaces, as shown on the Drawings and specified in this Section.

1.02 REFERENCES

A. This section contains references to the following documents. They are a part of this section as specified and modified. Where a referenced document contains references to other standards, those documents are included as references under this section as if referenced directly. In the event of conflict between the requirements of this section and those of the listed documents, the requirements of this section shall prevail.

B. Unless otherwise specified, references to documents shall mean the documents in effect at the time of Advertisement for Bids or Invitation to Bid (or on the effective date of the Agreement if there were no Bids). If referenced documents have been discontinued by the issuing organization, references to those documents shall mean the replacement documents issued or otherwise identified by that organization or, if there are no replacement documents, the last version of the document before it was discontinued. Where document dates are given in the following listing, references to those documents shall mean the specific document version associated with that date, regardless of whether the document has been superseded by a version with a later date, discontinued or replaced.

C. Except as otherwise indicated in this Section, the Contractor shall comply with the latest edition of the Uniform Standard Specifications and Details for Public Works Constructions by the Maricopa Association of Governments (MAG).

D. Where a date is given for reference standards, the edition of that date shall be used. Where no date is given for reference standards, the latest edition available on the date of Notice Inviting Bids shall be used.

1.03 SUBMITTALS

A. Submittals shall be made in accordance with Specifications Section 01300, Submittals, and the following special provisions provided herein.

07120-1 B. Product Data: Contractor shall submit manufacturer's product data for fluid- applied membrane, primer, and bonding agent.

C. Installation Instructions: Contractor shall submit manufacturer’s printed instructions for installation of products, including preparation, application limitations, and recoating requirements.

D. Certification: Contractor shall submit certification from fluid-applied membrane manufacturer that the fluid-applied membrane materials which will be in contact or may be in contact with potable water are NSF approved for potable water storage.

E. Materials Safety Data Sheets: Contractor shall submit Material Safety Data Sheets (MSDS) for each product.

F. Samples: Submit a sample of the fluid-applied membrane for approval.

1.04 QUALITY ASSURANCE

A. The Contractor shall be trained and approved by the fluid-applied membrane manufacturer.

B. A pre-installation conference shall be held prior to surface preparation and application of fluid-applied membrane to assure proper installation conditions.

C. The fluid-applied membrane material shall be designed and manufactured specifically for reservoirs containing treated (potable) water, shall have been satisfactorily demonstrated by prior use to be suitable for such use, and shall be approved by the National Sanitation Foundation (NSF) and other regulatory agencies having jurisdiction for such use. In lieu of NSF approval, the manufacturer shall provide written certification, from a product certification organization accredited for this purpose by the American National Standards Institute (ANSI) and regularly engaged in testing such products, that the fluid- applied membrane material meets the requirements of NSF for use in potable water.

D. Pre-Application Meeting:

1. The fluid-applied membrane representative shall conduct a pre-application training meeting with Contractor 2 weeks before the start of fluid applied membrane application.

2. Meeting attendees shall include all parties affecting the Work, including Construction Manager, Contractor, applicable subcontractors, Engineer, applicator, and the fluid-applied membrane manufacturer’s representative.

3. The purpose of the meeting is to review environmental requirements, fluid-applied membrane materials, protection of adjacent surfaces, surface

07120-2 preparation, application, curing, field quality control, cleaning, and coordination with other Work.

1.05 DELIVERY, STORAGE, AND HANDLING

A. Deliver materials to site in original unbroken packages bearing manufacturers label showing brand, weight, volume, and batch number.

B. Store materials at site in compliance with manufacturer's printed recommendations. Do not allow materials to freeze in containers.

1.06 CONDITIONS

A. Surfaces that are not required to be coated, but are adjacent to surfaces to be cleaned, abrasive-blasted, and coated shall be protected from these operations.

B. The Contractor shall perform Work only when existing and forecasted weather and temperature conditions are within manufacturer's recommendations for the material and product used.

1.07 GUARANTEE AND WARRANTY

A. Prior to the start of Work, a written material warranty from the fluid-applied membrane manufacturer shall be submitted. The fluid-applied membrane material shall be warranted in writing by the manufacturer against manufacturing defects or workmanship for a period of 2 years commencing at the time of acceptance of the Work.

B. The warranty specified herein is not the only warranty involved in the Contract. It is merely supplemental to the warranty specified elsewhere in the Specifications.

PART 2 PRODUCTS

2.01 MATERIALS

A. Fluid-Applied Membrane:

1. Fluid-applied membrane material shall be a 2-component, high-solids, elastomeric asphalt modified urethane elastomer membrane material. Fluid-applied membrane shall be nontoxic and odorless.

2. Acceptable Products:

a. CIM 1061, manufactured by CIM Industries, Inc.

b. CIM 1000 Trowel Grade, manufactured by CIM Industries, Inc.

07120-3 c. Or equal.

B. Primer:

1. Primer material shall be a two-component, high-solids, epoxy primer.

2. Acceptable Products:

a. CIM 61BG, as manufactured by CIM Industries, Inc.

b. Or approved equal.

C. Bonding Agent:

1. Bonding agent shall be in accordance with the fluid-applied membrane manufacturer’s recommendations.

D. Concrete epoxy adhesive shall be:

1. SikaDur 31, manufactured by Sika Corporation

2. Or equal.

PART 3 EXECUTION

3.01 SURFACE PREPARATION

A. Surfaces to receive the fluid-applied membrane material shall be prepared in accordance with the manufacturer's printed recommendations to achieve the greatest adhesion.

B. Surfaces shall be clean, smooth, and free of any dirt, algae, debris, loose material, release agents or curing compounds.

C. Surfaces shall be hand-sanded or abrasive-blasted to remove surface residue and to scarify the surface.

3.02 EXAMINATION

A. All surfaces to receive the fluid-applied membrane will be inspected and approved by the Engineer at least 1 day prior to commencing Work.

3.03 INSTALLATION

A. Contact bonding surfaces shall be primed with a bonding agent in accordance with the manufacture’s recommendations.

07120-4 B. Mixing shall be in strict accordance with the manufacturer’s recommendations. The components shall be thoroughly mixed and in a manner to prevent air from being drawn into the mixture. The amount of each component shall be accurately measured, not estimated.

C. Thickness and Coats:

1. Unless otherwise noted on the Drawings, fluid-applied membrane shall be applied to achieve a total 60-mil minimum dry thickness applied in a minimum of 2 coats of equal thickness.

2. The surface preparation for the second and subsequent coats shall be in accordance with the manufacturer's printed recommendations before proceeding with the second application.

D. The Contractor shall ensure that the fluid-applied membrane is not penetrated. The fluid-applied membrane shall be kept free of dirt and debris and traffic until water or a protective cover is in place.

E. Application of fluid-applied membrane on non-horizontal surfaces shall begin at the bottom and work towards the top.

F. At vertical surfaces, sloping surfaces, joints, and patches, fluid-applied membrane shall be a chemically thickened material for a trowel application with minimum sag.

G. The Contractor shall protect all studs, threads, and nuts from the application of the fluid-applied membrane. The Contractor shall submit its proposed method of protection and shall test the proposed method on the test area, designated above.

H. The Contractor shall arrange for the presence on-site of the fluid-applied membrane manufacturer's technical representative if quality control or application problems arise, or at the Engineer's request.

3.04 FIELD QUALITY CONTROL

A. The Contractor shall check Work for coverage and thickness.

B. When thickness or integrity is in question, the fluid-applied membrane shall be tested as described below. Use both visual and tactile measurements. Areas suspected of being too thin shall be measured with the gauges to determine the exact thickness.

1. Fluid-applied membrane shall be checked for coverage with a lightly oiled, needle nose depth gauge, taking 4 readings over a one square inch area, every 200 linear feet or fraction thereof. Record the minimum reading. Mark the test areas for repair.

07120-5 2. Test areas shall be patched over with fluid-applied membrane to a 60-mil minimum dry thickness, extending a minimum of 1 inch beyond the test perimeter.

3. When blistering of the fluid-applied membrane occurs, blister heads shall be tested for proper fluid-applied membrane thickness.

3.05 PROTECTION

A. Compressed-air units used in dust-off cleaning, abrasive-blasting, and spray coating operations shall be equipped with oil/water separators to remove all oil and moisture from the air. Separators shall be placed as close as practical to the application equipment.

B. Application equipment shall conform to the requirements and recommendations contained in the manufacturer's printed recommendations and shall be sufficient for surface preparation and coating application.

C. Drop cloths shall be provided, as required, to protect adjacent surfaces from cleaning residue or coating spatter and droppings.

**END OF SECTION**

07120-6 SECTION 11220

FLOATING COVER PUMPS

PART 1 GENERAL

1.01 WORK INCLUDED

A. This Section includes furnishing and installing floating cover pumps and required accessories on Basin #2 as shown on the Drawings and specified in this Section.

B. Work includes replacement of existing pump discharge hoses on Basin #1 existing floating cover. Contractor shall provide and install replacement pump discharge hoses.

1.02 REFERENCES

A. This Section contains references to the following documents. They are a part of this section as specified and modified. Where a referenced document contains references to other standards, those documents are included as references under this section as if referenced directly. In the event of conflict between the requirements of this section and those of the listed documents, the requirements of this section shall prevail.

B. Unless otherwise specified, references to documents shall mean the documents in effect at the time of Advertisement for Bids or Invitation to Bid (or on the effective date of the Agreement if there were no Bids). If referenced documents have been discontinued by the issuing organization, references to those documents shall mean the replacement documents issued or otherwise identified by that organization or, if there are no replacement documents, the last version of the document before it was discontinued. Where document dates are given in the following listing, references to those documents shall mean the specific document version associated with that date, regardless of whether the document has been superseded by a version with a later date, discontinued or replaced.

C. Except as otherwise indicated in this Section, the Contractor shall comply with the latest edition of the Uniform Standard Specifications and Details for Public Works Constructions by the Maricopa Association of Governments (MAG).

1.03 SUBMITTALS

A. Submittals shall be made in accordance with Specifications Section 01300, Submittals, and the following special provisions provided herein.

11220-1 B. Product Data:

1. The Contractor shall submit product data including pump description, manufacturer's pump identification number, electrical data, and related information.

2. Pump performance curve data shall be submitted with the manufacturer's printed recommendations indicating points on the curve and limits for stable operation between which the pumps may be operated without surge, cavitation, and vibration.

3. Electrical and motor data sheets, including wiring and control diagrams, shall be submitted.

4. Manufacturers' assembly and installation instructions and drawings including bill of materials, outline dimensions and shipping weights shall be submitted.

5. Drawings showing dimensions, materials of construction, equipment arrangements, connections, pump base mounting details, and related necessary information as applicable to each type of installation.

C. Operation and Maintenance Data:

1. Manufacturers' printed recommendations for spare parts shall be submitted to the Engineer.

2. Operations and Maintenance manuals shall be provided to Construction Manager for all pumps and motors.

3. The Contractor shall provide training on pump operation to Owner.

1.04 DELIVERY, STORAGE AND HANDLING

A. Delivery, storage, and handling shall be in accordance with the following special requirements:

1. The Contractor shall store rainwater removal pumps neatly on a pallet, off the ground, at the site, as directed by Construction Manager.

2. Spare primary rainwater removal pump shall be stored at the direction of Construction Manager.

1.05 WARRANTY

A. The Contractor shall provide a written warranty from the manufacturer against manufacturer’s defects for a period of 1 year after the date of final acceptance of the Work.

11220-2 B. This warranty is in addition to the requirements specified in the Project Specifications.

PART 2 PRODUCTS

2.01 RAINWATER REMOVAL SUBMERSIBLE PUMPS

A. Rainwater removal submersible pump shall normally operate automatically with the ability to operate manually by local start/stop push button switches at control panel located at the basin perimeter.

B. Design Requirements:

1. Rainwater removal pumps shall be submersible-type pumps according to the following design requirements:

Design Condition Point 1 Point 2

Discharge Flow 80 gpm 70 gpm

TDH 5 ft 15 ft

Flow shall be -0%, +10% at given TDH.

C. Rainwater removal submersible pumps shall be constructed to incorporate the following requirements:

1. Discharge Connection: 2-inch NPT

2. Pump Housing: Stainless steel Type 304

3. Shaft: Stainless steel Type 420

4. Upper Bearings: Single row ball bearing

5. Lower Bearings: Single row ball bearing

6. Shaft Seals: Independent double face seals. Upper seal carbon/carbide. Lower seal /silicon carbide.

7. Impeller: Multivane, open type, polyurethane

8. Diffuser: Nitrile rubber

9. Strainer: Hard EPDM rubber with 3/16 inch x 7/16 inch holes

10. Hardware: Stainless steel Type 304

11220-3 11. Maximum Weight without cable: 35 lbs

12. Maximum O.D.: 7 ¼ inches

D. Pump Motors:

1. Rainwater removal submersible pump shall have a constant-speed submersible motor rated at minimum 1.1 hp, 1-phase, 60 hertz, 115/230 volt, and shall be mounted in the pump. The motor shall be provided with thrust and radial bearings to carry the entire load that may be imposed upon it under all operating conditions.

2. Each motor shall have two seals. Both seals shall operate in an oil-filled chamber. Seals shall have tungsten carbide seal faces.

E. Models / Manufacturers:

1. Ready 8, manufactured by ITT Flygt Corporation,

2. Or equal.

F. The Contractor shall provide a total of 5 submersible rainwater removal pumps. Contractor shall install 4 submersible rainwater removal submersible pumps on floating cover and deliver 1 spare pump to Construction Manager.

G. Pump Hose and Fittings:

1. Pump hose shall be suction hose construction in accordance with this Section.

2. Fittings:

a. Connections at the end of each hose run and hose-to-hose segment connections shall be Type 304 stainless steel cam and groove (male/female) hose couplings.

b. All socket (female) ends shall have Buna-N gaskets.

c. Hose coupling barb ends shall be secured to hose with two low- profile stainless steel hose clamps.

d. All couplings on the floating cover shall be wrapped with straps of floating cover geomembrane material after installation to prevent damage to the floating cover.

e. All stainless steel shall be Type 304.

11220-4 2.02 PUMP DISCHARGE HOSE

A. The flexible hose for the submersible rainwater removal pumps discharge hose shall be suction hose construction of the following materials:

1. Tube - synthetic rubber

2. Carcass - plies of synthetic fabric

3. Cover - synthetic rubber

B. The tube and cover shall be wear resistant and resistant to sunlight, ozone, and moisture.

C. The pump discharge suction hose shall be heavy-duty industrial type with a minimum positive working pressure of 125 psi and a minimum negative working pressure 14 psi.

D. The pump discharge suction hose shall be equipped with Type 304 stainless steel quick-disconnect couplings.

E. Hose size shall be as indicated on the Drawings.

F. Manufacturers:

1. Goodyear, Plicord Water Suction and Discharge, (S&D)

2. Or equal.

PART 3 EXECUTION

3.01 INSTALLATION OF RAINWATER REMOVAL PUMPS

A. The submersible rainwater removal pumps shall be installed in accordance with the manufacturer's printed recommendations, and as shown on the Drawings.

B. The Contractor shall furnish all necessary appurtenances to make the rainwater removal pumps operable such as discharge pipes, stainless steel pipe and fittings, quick disconnect fittings, and discharge hoses.

C. The Contractor shall connect the rainwater removal pumps and control boxes to the electrical power feeds located at the reservoir perimeter road, as shown on the Drawings, and shall be installed in accordance with the manufacturer’s printed recommendations.

D. The Contractor shall install the submersible rainwater removal pump discharge suction hose on the floating cover, as shown on the Drawings.

11220-5 3.02 FLOW TEST

A. After installation, a field flow test for the submersible rainwater removal pumps shall be conducted and will be witnessed by Construction Manager.

B. At least two operating points for the submersible rainwater removal pump shall be verified.

**END OF SECTION**

11220-6 SECTION 15050

PIPING SYSTEMS

PART 1--GENERAL

1.01 DESCRIPTION

A. SCOPE:

This section specifies systems of process piping and general requirements for piping systems. Detailed specifications for the components listed on the Piping System Specification Sheets are found in other sections of Division 15. This section shall be used in conjunction with those sections.

B. DEFINITIONS:

Pressure terms used in Section 15050 and elsewhere in Division 15 are defined as follows:

1. Maximum: The greatest continuous pressure at which the piping system operates.

2. Test: The hydrostatic pressure used to determine system acceptance.

1.02 QUALITY ASSURANCE

A. REFERENCES:

This section contains references to the following documents. They are a part of this section as specified and modified. Where a referenced document contains references to other standards, those documents are included as references under this section as if referenced directly. In the event of conflict between the requirements of this section and those of the listed documents, the requirements of this section shall prevail.

Unless otherwise specified, references to documents shall mean the documents in effect at the time of Advertisement for Bids or Invitation to Bid (or on the effective date of the Agreement if there were no Bids). If referenced documents have been discontinued by the issuing organization, references to those documents shall mean the replacement documents issued or otherwise identified by that organization or, if there are no replacement documents, the last version of the document before it was discontinued. Where document dates are given in the following listing, references to those documents shall mean the specific document version associated with that date, regardless of whether the document has been superseded by a version with a later date, discontinued or replaced.

15050-1 Reference Title AASHTO Metallic (Zinc or Aluminum) Coated Corrugated Steel Culverts M36/M36M and Underdrains ANSI A13.1 Scheme for the Identification of Piping Systems ANSI B1.20.1 Pipe Threads, General Purpose (Inch) ANSI B16.1 Pipe Flanges and Flanged Fittings Class 25, 125, 250, and 800 ANSI B16.3 Malleable Iron Threaded Fittings Class 150 and 300 ANSI B16.5 Pipe Flanges and Flanged Fittings ANSI B16.9 Factory-Made Wrought Steel Buttwelding Fittings ANSI B16.11 Forged Steel Fittings, Socket Welding and Threaded ANSI B16.12 Cast Iron Threaded Drainage Fittings ANSI B16.22 Wrought Copper and Copper Alloy Solder Joint Pressure Fittings ANSI B16.26 Cast Copper Alloy Fittings for Flared Copper Tubes ANSI B31.1 Power Piping ANSI B31.3 Chemical Plant and Petroleum Refinery Piping ASME Section IX Boiler and Pressure Vessel Code; Welding and Qualifications ASTM A47 Malleable Iron ASTM A53 Pipe, Steel, Black and Hot Dipped, Zinc-Coated Welded and Seamless ASTM A74 Cast Iron Soil Pipe and Fittings ASTM A105/A105M , Carbon Steel, for Piping Components ASTM A106 Seamless Carbon Steel Pipe for High-Temperature Service ASTM A126 Standard Specification for Gray Iron Castings for Valves, Flanges, and Pipe Fittings ASTM A197 Cupola Malleable Iron ASTM A234/A234M Pipe Fittings of Wrought Carbon Steel and Alloy Steel for Moderate and Elevated Temperatures ASTM A312/A312M Seamless and Welded Austenitic Stainless Steel Pipe ASTM A403/A403M Wrought Austenitic Stainless Steel Piping Fittings ASTM A536 Ductile Iron Castings ASTM A570/A570M Hot-Rolled Carbon Steel Sheet and Strip, Structural Quality ASTM B88 Seamless Copper Water Tube

15050-2 Reference Title ASTM C76 Reinforced Concrete Culvert, Storm Drain, and Sewer Pipe ASTM C296 Asbestos-Cement Pressure Pipe ASTM C443-REV A Standard Specification for Joints for Circular Concrete Sewer and Culvert Pipe, Using Rubber Gaskets ASTM C564 Rubber Gaskets for Cast Iron Soil Pipe and Fittings ASTM D1248 Polyethylene Plastics Molding and Extrusion Materials ASTM D1784 Rigid Poly (Vinyl Chloride) (PVC) Compounds and Chlorinated Poly(Vinyl Chloride) (CPVC) Compounds ASTM D1785 Poly (Vinyl Chloride) (PVC) Plastic Pipe, Schedules 40, 80, and 120 ASTM D2241 Poly (Vinyl Chloride) (PVC) Plastic Pipe (SDR-PR) ASTM D2513 Thermoplastic Gas Pressure Pipe, Tubing, and Fittings ASTM D2665 Poly (Vinyl Chloride) (PVC) Plastic Drain, Waste, and Vent Pipe and Fittings ASTM D2996 Filament-Wound Reinforced Thermosetting Resin Pipe ASTM D3034 Standard Specification for Type PSM Poly (Vinyl Chloride) (PVC) Sewer Pipe and Fittings ASTM D3261 Butt Fusion Polyethylene (PE) Plastic Fittings for Polyethylene (PE) Plastic Pipe and Tubing ASTM D4174 Cleaning, Flushing, and Purification of Petroleum Fluid Hydraulic Systems ASTM D4101 Propylene Plastic Injection and Extrusion Materials ASTM F441 Chlorinated Poly (Vinyl Chloride) (CPVC) Plastic Pipe, Schedules 40 and 80 AWWA C105 Polyethylene Encasement for Ductile-Iron Piping for Water and Other Liquids AWWA C110 Ductile-Iron and Gray-Iron Fittings, 3 Inch Through 48 Inch, for Water and Other Liquids AWWA C111 Rubber-Gasket Joints for Ductile-Iron and Gray-Iron Pressure Pipe and Fittings AWWA C115 Flanged Ductile-Iron and Gray-Iron Pipe with Threaded Flanges AWWA C151 Ductile-Iron Pipe, Centrifugally Cast in Metal Molds or Sand-Lined Molds, for Water or Other Liquids AWWA C200 Steel Water Pipe 6 Inches and Larger

15050-3 Reference Title AWWA C205 Cement-Mortar Protective Lining and Coating for Steel Water Pipe--4 In. and Larger--Shop Applied AWWA C206 Field Welding of Steel Water Pipe AWWA C207 Steel Pipe Flanges for Waterworks Services--Sizes 4 In. through 144 In. AWWA C208 Dimensions for Fabricated Steel Water Pipe Fittings AWWA C209 Cold-Applied Tape Coating for Special Sections, Connections, and Fittings for Steel Water Pipelines AWWA C210 Liquid Epoxy Coating Systems for the Interior and Exterior of Steel Water Pipe AWWA C214 Tape Coating Systems for the Exterior of Steel Water Pipelines AWWA C301 Prestressed Concrete Pressure Pipe, Steel Cylinder Type, for Water and Other Liquids AWWA C303 Reinforced Concrete Pressure Pipe--Steel Cylinder Type, Pretensioned, for Water and Other Liquids AWWA C600 Installation of Ductile-Iron Water Mains and Their Appurtenances AWWA C651 Disinfecting Water Mains AWWA C900 Polyvinyl Chloride (PVC) Pressure Pipe, 4 Inches Through 12 Inches, for Water AWWA M11 Steel Pipe--A Guide for Design and Installation CISPI 301 Specification Data for Hubless Cast Iron Sanitary System with No-Hub Pipe and Fittings FEDSPEC Coating, Pipe, Thermoplastic Resin or Thermosetting Epoxy L-C-530B(1) MIL-H-13528B Hydrochloric Acid, Inhibited, Rust Removing MIL-STD-810C Environmental Test Methods SAE J1227 Assessing Cleanliness of Hydraulic Fluid Power Components and Systems UPC Uniform Plumbing Code

B. FITTINGS AND COUPLING COMPATIBILITY:

To assure uniformity and compatibility of piping components, fittings and couplings for grooved end piping systems shall be furnished by the same manufacturers.

15050-4 PART 2--PRODUCTS

2.01 PIPING MATERIALS

Unless otherwise specified, piping materials, including pipe, gaskets, fittings, connection and joint assemblies, linings and coatings, shall be selected from those listed on the piping system specification sheets. Piping materials shall conform to detailed specifications for each type of pipe and piping appurtenance specified in other sections of Division 15.

2.02 PIPING IDENTIFICATION

A. PLASTIC CODING MARKERS:

NOT USED

B. PLASTIC TRACER TAPE:

Tracer tape shall be 6 inches wide, colored the same as the background colors as specified in Table A, paragraph 15050-3.06, and made of inert plastic material suitable for direct burial. Tape shall be capable of stretching to twice its original length and shall be as manufactured by Allen Systems, W. H. Brady Co., Seton Name Plate Corporation, Marking Services Inc., or equal.

Two messages shall be printed on the tape. The first message shall read "CAUTION CAUTION CAUTION PIPE BURIED BELOW" with bold letters approximately 2 inches high. The blank shall be filled with the particular system fluid such as chlorine, oxygen or sulfur dioxide. The second message shall read "CALL " with letters approximately 3/4 inch high. Both messages shall be printed at maximum intervals of 2 feet.

2.03 VALVES

Valves of the same size and service shall be provided by a single valve manufacturer. Packing shall be nonasbestos material. Actual length of valves shall be within 1/16 inch (plus or minus) of the manufacturer's specified length. Flanges shall meet the requirement of ANSI B16.5. Push-on and mechanical joints shall meet the requirements of AWWA C111.

2.04 PRODUCT DATA

Product data on piping materials shall be provided in accordance with Section 01300 where specified.

Piping layout drawings shall be transmitted to the Construction Manager a minimum of 2 weeks prior to construction. Drawings shall be original layouts by the Contractor; photocopies of contract drawings are not acceptable.

15050-5 PART 3--EXECUTION

3.01 INSTALLATION

A. LOCATION:

Piping shall be provided as specified except for adjustments to avoid architectural and structural features and shall be coordinated with electrical construction.

B. PIPING SIZES:

Where the size of piping is not specified, the Contractor shall provide piping of the sizes required by UPC. Unless specified otherwise, small piping (less than 1 inch in diameter) required for services not described by UPC shall be 1/2 inch.

C. PIPE SUPPORT, ANCHORAGE AND SEISMIC BRACING:

1. GENERAL: Piping shall be supported by anchor brackets, guides, saddles or hangers. Acceptable types of supports, guides, saddles, hangers and structure attachments for general pipe support, expansion/ contraction and for seismic bracing, as well as anchorage details, are shown on the drawings. Minimum spacing shall be as specified for supports and for seismic bracing. Where a specific type of support or anchorage is indicated on the drawings, then only that type shall be used there. Piping shall be vertically supported by anchor brackets, guides, saddles or hangers and shall be seismically braced where indicated to resist lateral load. Supports shall be provided on each run at each change of direction. Pipe supports shall be hot-dip or mechanically galvanized. Unless otherwise specified, existing pipes and supports shall not be used to support new piping.

D. ANCHORAGE FOR BURIED PIPING:

All plugs, caps, tees and bends in buried pressure piping systems shall be anchored by means of reaction backing or restrained joints as specified.

E. BEDDING AND BACKFILL:

Bedding and backfill for buried piping shall be as specified in specification section 02200 and on contract drawings.

3.02 PIPING IDENTIFICATION

A. PLASTIC TRACER TAPE:

15050-6 A single line of tape as specified in paragraph 15050-2.02 B shall be provided 2.5 feet above the centerline of buried (insert required systems) pipe. For (insert required systems) pipelines buried 8 feet or greater below finished grade, contractor shall provide a second line of tape 12 inches below finished grade, above and parallel to each buried pipe. Tape shall be spread flat with message side up before backfilling.

3.03 VALVE IDENTIFICATION

NOT USED

3.04 TESTING

A. GENERAL:

Upon completion of piping, but prior to application of insulation on exposed piping, the Contractor shall test the piping systems. Pressures, media and test durations shall be as specified in the PIPESPEC. Equipment which may be damaged by the specified test conditions shall be isolated. Testing shall be performed using calibrated test gages and calibrated volumetric measuring equipment to determine leakage rates. Each test gage shall be selected so that the specified test pressure falls within the upper half of the gage's range. Unless otherwise specified, the Contractor shall notify the Construction Manager 24 hours prior to each test.

Unless otherwise specified, testing, as specified herein, shall include existing piping systems which connect with new pipe systems. Existing pipe shall be tested to the nearest existing valve. Any piping which fails the test shall be repaired. Repair of existing piping will be considered and paid for as extra work. B. GAS, AIR, AND VAPOR SYSTEMS:

NOT USED

C. LIQUID SYSTEMS:

Leakage shall be zero at the specified test pressure throughout the specified duration for the following systems: exposed piping, buried insulated piping, and buried or exposed piping carrying liquid chemicals. Unless otherwise specified, leakage from other buried liquid piping systems shall be according to MAG 610.15 for Force main applications and MAG 618.3 for Gravity main applications.

D. CHLORINE AND SULFUR DIOXIDE SYSTEMS:

NOT USED

E. HYDRAULIC AND LUBE OIL SYSTEMS:

NOT USED

15050-7 F. DRAINS:

Drain systems, other than pumped drain systems, shall be tested in accordance with UPC.

3.05 CLEANING AND FLUSHING

A. GENERAL:

Piping systems shall be cleaned following completion of testing and prior to connection to operating, control, regulating or instrumentation equipment. The Contractor may, at his option, clean and test sections of buried or exposed piping systems. Use of this procedure, however, will not waive the requirement for a full pressure test of the completed system. Unless specified otherwise, piping 24 inches in diameter and smaller shall first be cleaned by pulling a tightly fitting cleaning ball or swab through the system. Piping larger than 24 inches in diameter may be cleaned manually or with a cleaning ball or swab.

B. TEMPORARY SCREENS:

NOT USED

C. GAS AND AIR SYSTEMS:

NOT USED

D. LIQUID SYSTEMS:

After completion of cleaning, liquid systems, unless otherwise specified, shall be flushed with clean water. With temporary screens in place, the liquid shall be circulated through the piping system using connected equipment for a minimum period of 15 minutes and until no debris is collected on the screens. Liquid chlorine and sulfur dioxide lines shall be cleaned in accordance with paragraph 15050-3.05 E.

E. CHLORINE AND SULFUR DIOXIDE SYSTEMS:

NOT USED

F. STEAM SYSTEMS:

NOT USED

G. HYDRAULIC AND FLUID POWER OIL SYSTEMS:

NOT USED

H. POTABLE WATER SYSTEMS:

15050-8 Potable water piping systems shall be flushed and disinfected in accordance with AWWA C651.

3.06 PIPING SPECIFICATION SHEETS (PIPESPEC)

Piping and valves for groupings of similar plant processes or types of service lines are specified on individual piping specification sheets (PIPESPECS). Piping services are grouped according to the chemical and physical properties of the fluid conveyed and/or by the temperature or pressure requirements. Each grouping of services (PIPESPEC) is identified by a piping system number. Piping services specified in the PIPESPECS and on the drawings are alphabetically arranged by designated service symbols.

15050-9 3.06 PIPING SPECIFICATION SHEETS--PIPESPEC

Piping Symbol/Service: System--12 FM – Force Main

Test Requirements: Medium: Water; Refer to MAG 610.15 Pressure: 125 psig Duration: 120 minutes

Gasket Requirements: Flange: Compressed gasketing consisting of organic fibers (Kevlar) and neoprene binder Push-on/Mech Cpl: Nitrile or Neoprene

Exposed Pipe and Valves: (See drawings for pipe size and valve type)

(2" and smaller) Pipe: Stainless steel; ASTM A312, Schedule 40S. Ref. spec Section 15067. Conn; threaded, ANSI B1.20.1. Ftgs; ASTM A403, material, ends and wall thickness to match pipe.

Valves: Ball; Jamesbury Fig. 351, Nibco T-580, or equal. Globe; Crane 7TF or 17TF, Lunkenheimer 123 or 214, or equal. Lift check; Crane 27TFE, Lunkenheimer 231, or equal.

Buried and Encased Pipe: (See drawings for pipe size and valve type. Omit coating on encased pipe.)

(6" and smaller) Pipe: PVC; ASTM D1784, Class 12454-B, NSF certified, ASTM D2241, SDR 21. Ref. spec Section 15064. Conn; plain end; solvent weld with threaded or flanged adapters for valves. Ftgs; PVC, Sch. 80, solvent welded socket type.

Valves: None

Remarks:

1. Manual air vents shall be provided at the high points and drains provided at the low points of each reach of pipeline.

15050-10

3.06 PIPING SPECIFICATION SHEETS--PIPESPEC

Piping Symbol/Service: System--24 GM – Gravity Main

Test Requirements: Medium: Refer to MAG 615.11

Pressure: Refer to MAG 615.11

Duration: Refer to MAG 615.11

Gasket Requirements: Flange: Compressed gasketing consisting of organic fibers (Kevlar) and neoprene binder Push-on/Mech Cpl: Nitrile or neoprene

Buried and Encased Pipe and Valves Beyond 5 Feet Outside Building (See drawings for pipe size.)

(Smaller than 8") Pipe: PVC; ASTM D1784, Class 12454-B, ASTM D2665, Sch. 40. Ref. spec Section 15064. Provide magnetic tracer tape. Conn; plain end, solvent weld. Ftgs; PVC, socket type, DWV, ASTM D2665.

Valves: None

(8" and 12") Pipe: PVC; ASTM D3034, SDR 35. Provide magnetic tracer tape. Conn; Push-on with nitrile gasket. Ftgs; PVC or IPS cast iron; ends to match pipe.

Valves: None

Remarks:

**END OF SECTION**

15050-11

SECTION 15064

PLASTIC PIPE

PART 1--GENERAL

1.01 DESCRIPTION

A. SCOPE:

This section specifies polyvinylchloride, chlorinated polyvinylchloride, polyethylene, and polypropylene pipe and fittings.

B. PIPE DESIGNATIONS:

For use in the Piping System Specification Sheets (PIPESPEC) in Section 15050 and in this section, the following plastic pipe designations are defined:

Designation Definition PVC Polyvinylchloride CPVC Chlorinated polyvinylchloride PE Polyethylene PP Polypropylene

1.02 QUALITY ASSURANCE

A. REFERENCES:

This section contains references to the following documents. They are a part of this section as specified and modified. Where a referenced document contains references to other standards, those documents are included as references under this section as if referenced directly. In the event of conflict between the requirements of this section and those of the listed documents, the requirements of this section shall prevail.

Unless otherwise specified, references to documents shall mean the documents in effect at the time of Advertisement for Bids or Invitation to Bid (or on the effective date of the Agreement if there were no Bids). If referenced documents have been discontinued by the issuing organization, references to those documents shall mean the replacement documents issued or otherwise identified by that organization or, if there are no replacement documents, the last version of the document before it was discontinued. Where document dates are given in the following listing, references to those documents shall mean the specific document version associated with that date, regardless of whether the document has been superseded by a version with a later date, discontinued or replaced.

15064-1 Reference Title ASTM D1248 Polyethylene Plastics Molding and Extrusion Materials ASTM D1784 Rigid Poly (Vinyl Chloride) (PVC) Compounds and Chlorinated Poly (Vinyl Chloride) (CPVC) Compounds ASTM D1785 Poly (Vinyl Chloride) (PVC) Plastic Pipe, Schedules 40, 80, and 120 ASTM D2241 Poly (Vinyl Chloride) (PVC) Plastic Pipe (SDR-PR) ASTM D2464 Threaded Poly (Vinyl Chloride) (PVC) Plastic Pipe Fittings, Schedule 80 ASTM D2466 Poly (Vinyl Chloride) (PVC) Plastic Pipe Fittings, Schedule 40 ASTM D2467 Socket-Type Poly (Vinyl Chloride) (PVC) Plastic Pipe Fittings, Schedule 80 ASTM D2564 Solvent Cements for Poly (Vinyl Chloride) (PVC) Plastic Pipe and Fittings ASTM D2657 Heat-Joining Polyolefin Pipe and Fittings ASTM D2665 Poly (Vinyl Chloride) (PVC) Plastic Drain, Waste, and Vent Pipe and Fittings ASTM D3034 Type PSM Poly (Vinyl Chloride) (PVC) Sewer Pipe and Fittings ASTM D4101 Propylene Plastic Injection and Extrusion Materials ASTM F402 Safe Handling of Solvent Cements and Primers Used for Joining Thermoplastic Pipe and Fittings ASTM F437 Threaded Chlorinated Poly (Vinyl Chloride) (CPVC) Plastic Pipe Fittings, Schedule 80 ASTM F438 Socket-Type Chlorinated Poly (Vinyl Chloride) (CPVC) Plastic Pipe Fittings, Schedule 40 ASTM F439 Socket-Type Chlorinated Poly (Vinyl Chloride) (CPVC) Plastic Pipe Fittings, Schedule 80 ASTM F441 Chlorinated Poly (Vinyl Chloride) (CPVC) Plastic Pipe, Schedules 40 and 80 ASTM F477 Elastomeric Seals (Gaskets) for Joining Plastic Pipe ASTM F493 Solvent Cements for Chlorinated Poly (Vinyl Chloride) (CPVC) Plastic Pipe and Fittings

15064-2 PART 2--PRODUCTS

2.01 PVC PIPE

A. PRESSURE PIPE:

PVC material for pipe and fittings shall conform to ASTM D1784, Class 12454-B. Pipe and fittings shall either be in accordance with ASTM D1785 or shall conform to ASTM D2241 for standard dimension ratios: 160 psi pipe--SDR 26; 200 psi pipe--SDR 21; 250 psi--SDR 17. Pressure rating for pipe shall be in excess of test pressure specified in Section 15050. Neoprene gaskets with push-on joints shall conform to ASTM F477.

Schedule 80 PVC socket type fittings shall conform to ASTM D2467. Schedule 40 PVC fittings shall conform to ASTM D2466. PVC solvent weld cement for socket connections shall meet the requirements of ASTM D2564. Schedule 80 PVC threaded fittings shall conform to ASTM D2464. Fittings for gasketed pipe shall be ductile iron or steel push-on IPS-sized pressure fittings rated for use with the specified class of PVC pipe.

B. NONPRESSURE PIPE:

1. GRAVITY SEWER PIPE: PVC material for sewer pipe and fittings shall conform to Class 12454-B, as defined in ASTM D1784. Pipe and fittings shall meet the requirements of ASTM D3034 for SDR 35. Neoprene gaskets with push-on joints shall conform to ASTM F477.

2. DRAIN, WASTE AND VENT PIPE: PVC material for drain waste and vent (DWV) pipe and fittings shall conform to Class 12454-B, ASTM D1784. Pipe and fittings shall conform to ASTM D2665. Unless otherwise specified, connections shall be solvent weld. Connections to traps, closet flanges, and nonplastic pipe shall be with approved adapter type fittings designed for intended use. Solvent weld cement for socket connections shall meet requirements of ASTM D2564.

2.02 CPVC PIPE

NOT USED

2.03 PE PIPE

NOT USED

2.04 PP PIPE

NOT USED

15064-3 2.05 PRODUCT DATA

The following information shall be provided in accordance with Section 01300:

1. Manufacturer's certificates of compliance with the specified standards and Contractor's layout drawings.

PART 3--EXECUTION

3.01 INSTALLATION

PVC pipe 3 inches in diameter and smaller shall be joined by means of socket fittings and solvent welding in conformance with ASTM F402. Solvent-cemented joints shall be made in strict compliance with the manufacturer's/supplier's instructions and recommended procedures. Unless otherwise specified, PVC pipe 4 inches in diameter and greater shall be joined by means of gasketed push-on joints and steel or ductile iron push-on or mechanical joint fittings. Fittings shall be lined and coated as specified in Section 15062. Unless otherwise specified, PVC and CPVC piping exposed to sunlight shall be painted with coating.

Connections to different types of pipe shall be by means of flanges, specified adapters or transition fittings. Where sleeve type couplings are used, both shall be uniformly torqued in accordance with pipe manufacturer's recommendation. Foreign material shall be removed from the pipe interior prior to assembly.

3.02 TESTING

Testing of plastic piping shall be as specified in Section 15050.

**END OF SECTION**

15064-4 SECTION 15067

STAINLESS STEEL PIPING

PART 1--GENERAL

1.01 DESCRIPTION

A. SCOPE:

This section specifies stainless steel pipe and fittings for exposed pump discharge piping as detailed on the contract drawings.

1.02 QUALITY ASSURANCE

A. REFERENCES:

This section contains references to the following documents. They are a part of this section as specified and modified. Where a referenced document contains references to other standards, those documents are included as references under this section as if referenced directly. In the event of conflict between the requirements of this section and those of the listed documents, the requirements of this section shall prevail.

Unless otherwise specified, references to documents shall mean the documents in effect at the time of Advertisement for Bids or Invitation to Bid (or on the effective date of the Agreement if there were no Bids). If referenced documents have been discontinued by the issuing organization, references to those documents shall mean the replacement documents issued or otherwise identified by that organization or, if there are no replacement documents, the last version of the document before it was discontinued. Where document dates are given in the following listing, references to those documents shall mean the specific document version associated with that date, regardless of whether the document has been superseded by a version with a later date, discontinued or replaced.

Reference Title ANSI B16.1 Cast Iron Pipe Flanges and Flanged Fittings Classes 25, 125, 250, and 800 ANSI B16.11.80 Forged Steel Fittings, Socket Welding and Threaded. ANSI B31.1 Power Piping ANSI B36.19M Stainless Steel Pipe ASME Section IX (1989) Boiler and Pressure Vessel Code; Welding and Brazing Qualifications

15067-1 Reference Title ASTM A182/A182M Forged or Rolled Alloy-Steel Pipe Flanges, Forged Fittings, and Valves and Parts for High-Temperature Service ASTM A193/A193M Alloy-Steel and Stainless Steel Bolting Materials for High-Temperature Service ASTM A194/A194M Carbon and Alloy Steel Nuts for Bolts for High Pressure and High-Temperature Service ASTM A240 Heat-Resisting Chromium and Chromium Nickel Stainless Steel Plate, Sheet, and Strip for Pressure Vessels ASTM A276 Stainless and Heat-Resisting Steel Bars and Shapes ASTM A312/A312M Seamless and Welded Austenitic Stainless Steel Pipes ASTM A320/A320M Alloy Steel Bolting Materials for Low-Temperature Service ASTM A403/A403M Wrought Austenitic Stainless Steel Piping Fittings ASTM A409/A409M Welded Large Diameter Austenitic Steel Pipe for Corrosive or High Temperature Service ASTM A480/A480M General Requirements for Flat-Rolled Stainless and Heat-Resisting Steel Plate, Sheet and Strip ASTM A774/A774M As-Welded Wrought Austenitic Stainless Steel Fittings for General Corrosive Service at Low and Moderate Temperatures ASTM A778 Welded, Unannealed Austenitic Stainless Steel Tubular Products

B. QUALIFICATIONS:

All shop fabricated stainless steel pipe and fittings shall be furnished by a single manufac- turer who is experienced and qualified in the manufacture and fabrication of the items to be furnished. The pipe and fittings shall be shop-fabricated and field-installed in accordance with common industrywide practices and methods and shall comply with these specifications.

Only weld procedures which have been qualified under ASME Section IX and only welders who have successfully completed performance qualification tests per ASME Section IX on these qualified procedures shall be utilized.

C. TESTING:

Factory testing shall conform to the requirements of ASTM A312, ASTM A409 HT-0, or ASTM A778, depending on the size and type of stainless steel pipe provided.

15067-2

1.03 SUBMITTALS

The following information shall be provided in accordance with Section 01300:

1. A copy of this specification section, with addendum updates included, and all referenced and applicable sections, with addendum updates included, with each paragraph check-marked to indicate specification compliance or marked to indicate requested deviations from specification requirements. A check mark shall denote full compliance with a paragraph as a whole. If deviations from the specifications are indicated, and therefore requested by the Contractor, each deviation shall be underlined and denoted by a number in the margin to the right of the identified paragraph, referenced to a detailed written explanation of the reasons for requesting the deviation. The Construction Manager shall be the final authority for determining acceptability of requested deviations. The remaining portions of the paragraph not underlined will signify compliance on the part of the Contractor with the specifications. Failure to include a copy of the marked- up specification sections, along with justification(s) for any requested deviations to the specification requirements, with the submittal shall be sufficient cause for rejection of the entire submittal with no further consideration.

2. Shop fabrication drawings showing details of materials, piping, fittings, couplings, dielectric connections, joint locations and details, types and locations of supports.

3. Other data necessary to show conformance of the complete piping system to these specifications.

PART 2--PRODUCTS

2.01 PIPE

Unless otherwise specified, stainless steel pipe 2-1/2 inches and smaller shall be Type 304, seamless, threaded joints conforming to ASTM A312. The minimum wall thickness shall be Schedule 40S.

2.02 FITTINGS

Unless otherwise specified, stainless steel fittings, 2-1/2-inches and smaller, shall be ASTM A403, of the same material and pressure rating as the pipe, threaded long radius with dimensions conforming to ANSI B16.11.

15067-3 Unless otherwise specified, stainless steel fittings, 3-inch and larger, shall be butt-weld type manufactured in accordance with ASTM A774 of the same material and in the same thicknesses as the pipe. Long radius elbows up to 24 inches in diameter shall be smooth flow. All short radius, special radius, and reducing elbows and long radius elbows greater than 24 inches in diameter shall be of mitered construction. Reducers shall be straight tapered, cone type. Tees, crosses, laterals, and wyes shall be shop-fabricated from pipe.

2.03 JOINTS

Stainless steel pipe fabricated into spool pieces shall have shop-welded circumferential butt- weld joints or flanges. Unless otherwise specified, flanged joints shall be Van Stone joints made up of stainless steel slip-on type rolled-angle face rings and ductile iron backup flanges drilled to ANSI B16.1, Class 125 standard. The angle face ring thickness shall be equal to or greater than the wall of the pipe or fitting to which it is welded, and it shall be continuously welded on both sides to the pipe or fitting. The angle leg shall not interfere with the flange bolt holes.

2.04 COUPLINGS

A. GENERAL:

Fabricated stainless steel piping shall be shop-prepared for pipe couplings where specified. Unless otherwise specified, couplings shall be arched-band or grooved type.

B. SLEEVE TYPE:

Sleeve type couplings, where specified, shall be of standard steel construction as specified in paragraph 15085-2.02 A. Pipe shall be plain-end with external weld beads ground smooth to ensure proper gasket seating. For pressure pipe lines, sleeve coupling joints shall be restrained by the use of harness rods connecting across the joint to flange lugs on adjacent flange joints. Where no adjacent flange joints exist, stainless steel harness lugs shall be welded to the pipe to receive the harness rods.

C. ARCHED-BAND TYPE:

Arched-band type couplings shall be stainless steel of the same material and wall thickness as the pipe and shall be Depend-O-Lok type as manufactured by Brico or equal. Couplings shall be Fixed--FxF, Expansion--ExE, or Fixed by Expansion--FxE as specified or as required. The pipe shall be plain-end with external weld beads ground smooth and with S.S. restraining rings shop- welded to the piping for fixed type couplings.

D. GROOVED-END TYPE:

Grooved-end or split type couplings shall be malleable iron or ductile iron as specified in paragraph 15085-2.02 C except that submerged couplings shall be the same material as the pipe. The pipe ends shall be roll-grooved to the coupling manufacturer's specifications. Where roll grooving is impractical, the pipe shall have heavy-wall machine-grooved pipe nipples or machined

15067-4 ring collars fully welded to the pipe or fitting. Nipples shall be taper-bored to the I.D. of the adjoining pipe to allow full-weld penetration. Collars shall be welded on both sides to the piping. Nipples and collars shall be of the same alloy as the piping.

E. EXPANSION TYPE:

NOT USED

2.05 THREADED CONNECTIONS

Threaded pipe, gage, or instrument connections shall be made using stainless steel, 150-pound, threaded half-couplings conforming to ASTM A182 or ASTM A276, shop welded to the pipe at the locations specified.

2.06 GASKETS

Unless otherwise specified, gaskets shall be as specified in the PIPESPECS and in paragraph 15085-2.03. For air lines, gaskets shall be neoprene or EPDM suitable for use at temperatures to 240 degrees F.

2.07 BOLTS

Bolts, nuts, and washers for stainless steel flange assemblies and stainless steel couplings shall be the same material, conforming to ASTM A320 for low-temperature service and ASTM A193 and ASTM A194 for high-temperature service. Bolts, nuts and washers for other couplings shall be as specified in referenced paragraphs for the couplings.

2.08 PIPE SUPPORT SYSTEMS

Unless otherwise specified, all hangers, rods, structural attachments, and other components of support systems for stainless steel pipe shall be of the same materials as the pipe.

2.09 FINISH

After all shop operations have been completed, pipe and fittings shall be pickled and passivated in manufacturer's plant, and scrubbed and washed until discoloration and possible iron picked up from manufacturing process are removed. The standard finish for 16-gage through 8-gage material shall be No. 1 or 2B per ASTM A480; 3/16-inch and heavier plate material shall be No. 1 or better per ASTM A480.

2.10 PRODUCT DATA

The following information and data shall be provided in accordance with Section 01300:

15067-5 1. Certifications specified in the following documents:

ASTM A403, paragraph 14.1 ASTM A774, paragraph 14.1 ASTM A778, paragraph 14.1 ASTM A409, paragraph 17.1

2. Test results specified in paragraph 15067-1.02 C.

3. Names and qualification records of proposed welders.

PART 3--EXECUTION

3.01 PIPE CUTTING, THREADING, AND JOINTING

Pipe cutting, threading, and jointing shall conform to the requirements of ANSI B31.1. All pipe threads shall be lubricated with Teflon tape.

3.02 WELDING

A. GENERAL:

Piping with wall thickness up to 11 gage (0.120 inch) shall be welded with the TIG (GTAW) process. Unless otherwise specified, heavier walls shall be properly beveled and have a root pass with the TIG (GTAW) process followed by subsequent passes with the TIG (GTAW), MIG (GMAW), or Metallic Arc (SMAW) process. Filler wire of ELC grades only shall be added to all welds to provide a cross section at the weld equal to or greater than the parent metal. Weld deposit shall be smooth and evenly distributed and have a crown of no more than 1/16 inch on the I.D. and 3/32 inch on the O.D. of the piping. Concavity, undercut, cracks, or crevices shall not be allowed. Butt welds shall have full penetration to the interior surface, and inert gas shielding shall be provided to the interior and exterior of the joint. Excessive weld deposits, slag, spatter, and projections shall be removed by grinding. Welds on gasket surfaces shall be ground smooth.

B. FIELD WELDING:

Field welding shall be minimized to the greatest extent possible by use of couplings and prefabrication of pipe systems at the factory. Pipe butt welds may be performed at the job site, providing the but welds are performed only with an inert gas shielded process and that other applicable specified welding requirements are rigidly adhered to.

All residue, oxide, and heat stain is to be removed from any type of field weld and the affected areas adjacent by the use of stainless steel wire brushes, followed by cleaning with an agent such as Eutectic Company's "Eucleen," or equal, followed by complete removal of the agent.

15067-6 C. PREPARATION OF SURFACES TO BE WELDED:

Surfaces of joints to be welded shall be free from mill scale, slag, grease, oil, paint, rust, and other foreign material. Joints to be welded shall be wire-brushed with stainless steel wire brushes and precisely fitted before welding.

D. WEATHER CONDITIONS:

Welding shall be done only when the surfaces are completely free of any moisture. Welding of the pipe shall not be done during periods of high winds or rain unless the areas being welded are properly shielded.

E. TACK WELDS, CLIPS, AND OTHER ATTACHMENTS:

Nicks, gouges, notches, and depressions in the base metal in the area of the joint shall be repaired before the joint weld is made. Tack welds, clips, and other attachments shall be removed and defects repaired, except where the tack welds occur within the weld area and these tack welds do not exceed the size of the completed weld. Cracked tack welds shall be removed. Areas to be repaired shall be ground to clean metal and then repaired by building up with weld metal. The repaired areas shall be ground smooth to form a plane surface with the base metal.

F. DEFECTS AND REPAIRS:

Welds with cracks, slag inclusions, porosity, undercutting, incomplete penetration, or which are otherwise deficient in quality or made contrary to any provisions of these specifications shall be removed by chipping or grinding throughout their depth to clean base metal. Calking or peening of welds to correct defects shall not be done. Welds found deficient in dimension but not in quality shall be enlarged by additional welding after thoroughly cleaning the surface of previously deposited metal and the adjoining plate. Weld deposits, slag, weld spatter, and projections into the interior of the pipe shall be removed by grinding.

3.03 MARKING, SHIPPING, AND STORAGE

All pipe, fittings, and fabrications shall be properly marked with type, gage, and heat number. All fabricated piping shall have openings plugged and flanges secured for storage and/or transport after fabrication. All fabricated piping shall be piece-marked with identifying numbers or codes which correspond to the Contractor's layout and installation drawings. The marks will be located on the spools at opposite ends and 180 degrees apart. Pipe spools shall be loaded and blocked and lagged as necessary to ensure protection from damage during shipping. Stainless steel pipe and fittings shall be stored per manufacturer's recommendation. Dents, gouges, and scratches in stainless steel pipe and fittings are not acceptable and are reason for rejecting pipe and fittings.

3.04 FABRICATION/INSTALLATION REQUIREMENTS

The piping supplier during manufacturing, fabricating and handling stages, and the Contractor during handling and installation stages, shall use extreme care to avoid the contact of any

15067-7 ferrous materials with the stainless steel piping. All saws, drills, files, wire brushes, etc. shall be used for stainless steel piping only. Pipe storage and fabrication racks shall be nonferrous or stainless steel or rubber-lined. Nylon slings or straps shall be used for handling stainless steel piping. Contact with ferrous items may cause rusting of iron particles embedded in the piping walls. After installation, the Contractor shall wash and rinse all foreign matter from the piping surface. All welded joints shall be treated with a pickling solution, brushed with stainless steel wire brushes and rinsed clean. If rusting of embedded iron occurs, the Contractor shall pickle the affected surface with Oakite Deoxidizer SS, or equal, scrub with stainless steel brushes, and rinse clean.

3.05 COATINGS

No coating is required.

**END OF SECTION**

15067-8 SECTION 15085

PIPING CONNECTIONS

PART 1--GENERAL

1.01 DESCRIPTION

This section specifies the following methods of connecting metallic piping: flanges, threading, mechanical couplings, equipment connection fittings, dielectric unions, and welding.

1.02 REFERENCES

This section contains references to the following documents. They are a part of this section as specified and modified. Where a referenced document contains references to other standards, those documents are included as references under this section as if referenced directly. In the event of conflict between the requirements of this section and those of the listed documents, the requirements of this section shall prevail.

Unless otherwise specified, references to documents shall mean the documents in effect at the time of Advertisement for Bids or Invitation to Bid (or on the effective date of the Agreement if there were no Bids). If referenced documents have been discontinued by the issuing organization, references to those documents shall mean the replacement documents issued or otherwise identified by that organization or, if there are no replacement documents, the last version of the document before it was discontinued. Where document dates are given in the following listing, references to those documents shall mean the specific document version associated with that date, regardless of whether the document has been superseded by a version with a later date, discontinued or replaced.

Reference Title ANSI Bl.1 Unified Inch Screw Threads (UN and UNR Thread Form) ANSI Bl.20.1 Pipe Threads, General Purpose (Inch) ANSI B16.1 Cast Iron Pipe Flanges and Flanged Fittings ANSI B16.5 Pipe Flanges and Flanged Fittings ANSI B18.2.1 Square and Hex Bolts and Screws Inch Series ANSI B18.2.2 Square and Hex Nuts (Inch Series) ANSI B31.1 Power Piping ANSI B31.3 Chemical Plant and Petroleum Refinery Piping ASME Section IX Boiler and Pressure Vessel Code; Welding and Brazing Procedures, Welders, Brazers, and Welding and Brazing Operators Qualifications ASTM B98 Copper-Silicon Alloy Rod, Bar and Shapes

15085-1 Reference Title ASTM F37 Standard Test Methods for Sealability of Gasket Materials ASTM F104 Standard Classification System for Nonmetallic Gasket Materials ASTM F152 Standard Test Methods for Tension Testing of Nonmetallic Gasket Materials ASTM F593 Stainless Steel Bolts, Hex Cap Screws, and Studs AWWA C111 Rubber-Gasket Joints for Ductile-Iron Pressure Pipe and Fittings AWWA C206 Field Welding of Steel Water Pipe AWWA C207 Steel Pipe Flanges for Waterworks Service-Size 4 in. through 144 in. AWWA C219 Bolted, Sleeve-Type Couplings for Plain-End Pipe AWWA C550 Protective Epoxy Coatings for Valves and Hydrants AWWA C606 Grooved and Shouldered Joints AWWA M11 Steel Pipe-A Guide for Design and Installation NSF 61 Drinking Water System Components - Health Effects

1.03 SUBMITTALS

In addition to the material listed in the detailed specification, the following submittals shall be provided in accordance with Section 01300:

1. For Equipment Connection Fittings used in pumping applications submit thrust rod stretch calculations in accordance with paragraph 2.01D. and dimensional layout data.

PART 2--PRODUCT

2.01 FLANGE ASSEMBLIES

A. FLANGES:

1. GENERAL: Flanges shall either be flat flanges or convoluted ring flanges as specified in the following paragraphs.

2. FLAT FLANGES: Cast iron flanges shall be faced in accordance with ANSI B16.1. Where companion flanges are used, the flanges on pipe shall be refaced to be flush with the companion flange face. Class 150 and Class 300 forged steel flanges shall be raised face conforming to ANSI B16.5. Lightweight slip-on flanges shall be plain face conforming to AWWA C207, Class B and ANSI B16.5. Unless otherwise specified, steel flanges shall be ANSI B16.5, Class 150 or AWWA C207, Class D. Class E AWWA flanges shall be provided where test pressure exceeds 175 psi. Plain faced flanges shall not be bolted to raised face flanges.

15085-2

3. CONVOLUTED RING FLANGES: Convoluted ring flanges shall be ductile iron, forged steel or cast stainless steel, designed to bear on hubs welded to the pipe and shall be as manufactured by Improved Piping Products. The Construction Manager knows of no equal. The flange joints shall be rated for not less than 150 percent of the test pressures listed in Section 15050 and shall conform to the requirements of ANSI B 16.5 and AWWA C207. The flange manufacturer shall be prepared to demonstrate, by certified pressure test that the flanges will meet these requirements.

B. GASKETS:

Gasket material shall be as specified in paragraph 15085-2.03.

Gaskets for plain faced flanges shall be the full face type. Thickness shall be 1/16 inch for pipe 10 inches and less in diameter and 1/8 inch for pipe 12 inches and larger in diameter. Unless otherwise specified, gaskets for raised face flanges shall match the raised face and shall be 1/16 inch thick for pipe 3-1/2 inches and less in diameter and 1/8 inch thick for pipe 4 inches and larger.

C. BOLTS:

Flange assembly bolts shall be ANSI B18.2.1 standard square or hexagon head bolts with ANSI B18.2.2 standard hexagon nuts. Threads shall be ANSI Bl.1, standard coarse thread series; bolts shall be Class 2A, nuts shall be Class 2B. Bolt length shall conform to ANSI B16.5.

Unless otherwise specified, bolts shall be carbon steel machined bolts with hot pressed hexagon nuts. Bolts for submerged service shall be made of Type 316 stainless steel in conformance with ASTM F593, marking F593F. Nuts for submerged service shall be made of copper-silicon alloy bronze conforming to ASTM B98, alloy C65100, designation H04 or alloy C65500, designation H04. Bolts and nuts for buried service shall be made of noncorrosive high- strength, low-alloy steel having the characteristics specified in ANSI/AWWA C111/A21, regardless of any other protective coating. Where washers are required, they shall be of the same material as the associated bolts.

2.02 MECHANICAL COUPLINGS

A. SLEEVE-TYPE COUPLINGS:

Unless otherwise specified, sleeve-type mechanical pipe couplings shall be Smith-Blair Type 411, Dresser Style 38, or equal, with the stop removed from the middle ring. Reducing couplings shall be Smith-Blair Type 415, Dresser Style 62, or equal. Sleeve-type flanged coupling adapters shall be Smith-Blair Type 913, Dresser Style 128, or equal. Insulating couplings shall be Smith-Blair Type 416, Dresser Style 39, or equal.

Bolts for submerged service shall be made of Type 316 stainless steel in conformance with ASTM F593, markingF593F. Nuts for submerged service shall be made of copper-silicon alloy bronze conforming to ASTM B98, alloy C65100, designation H04, or alloy C65500, designation

15085-3 H04. Bolts and nuts for buried service shall be made of noncorrosive high-strength, low-alloy steel having the characteristics specified in ANSI/AWWA C111/A21, regardless of any other protective coating. Where washers are required, they shall be of the same material as the associated bolts.

Gaskets shall be as specified in paragraph 15085-2.03 and AWWA C111.

B. PLAIN END COUPLINGS:

Plain end pipe couplings for pipe sizes 6 inches and smaller shall be Gustin-Bacon 200, Victaulic Style 99, or equal for Schedule 80 pipe and Gustin-Bacon 205, Victaulic Style 90, or equal for lighter weight pipe. Plain end couplings for pipe sizes 8 inches and larger shall be Gustin-Bacon 200, Victaulic Style 99, or equal. Unless otherwise specified, bolts and nuts shall comply with AWWA C606.

Gaskets shall be as specified in paragraph 15085-2.03 and AWWA C606.

C. GROOVED END COUPLINGS:

Grooved end flexible-type couplings shall be Gustin-Bacon 100, Victaulic Style 77, or equal. Grooved end rigid-type couplings shall be Gustin-Bacon 120 Rigi-Grip, Victaulic Style 07 Zero-Flex, or equal. Flexible-type couplings shall be used for all piping greater than 12 inches in diameter; for pipe 12 inches in diameter and less in rack-mounted tunnel piping applications; and for grooved joints adjacent to pump or blower suction and discharge where grooved couplings are used for noise and vibration control. All other applications for piping 12 inches in diameter and less shall utilize rigid-type couplings. Grooved end flanged coupling adapters shall be either Gustin- Bacon 154, Victaulic Style 741, or equal. Snap-joint grooved end couplings shall be Gustin-Bacon 115, Victaulic Style 78, or equal. Cut grooves are not permitted on fabricated or lightwall pipe.

Unless otherwise specified, bolts and nuts shall comply with AWWA C606. Bolts for submerged service shall be Type 316 stainless steel in conformance with ASTM F593, marking F593F. Nuts for submerged service shall be made of copper-silicon alloy bronze conforming to ASTM B98, alloy C65100, designation H04 or alloy C65500, designation H04. Bolts and nuts for buried service shall be made of noncorrosive high-strength, low-alloy steel having the characteristics specified in ANSI/AWWA C111/A21, regardless of any other protective coating. Where washers are required, they shall be of the same material as the associated bolts.

Gaskets shall be as specified in paragraph 15085-2.03 and AWWA C 606.

instructions.

2.03 GASKETS

Gaskets designated in Section 15050 shall be as follows:

1. EPDM: ethylene-propylene-diene-terpolymer.

15085-4

2. Neoprene: neoprene.

3. Nitrile: nitrile (Buna N).

4. Compressed gasketing consisting of organic fibers (Kevlar) and neoprene binder; ASTM F104 (F712400), 2500 psi (ASTM F152), 0.2 ML/HR LEAKAGE FUEL A (ASTM F37).

5. Compressed gasketing consisting of organic fibers (Kevlar) and SBR binder; ASTM F104 (F712400), 2500 PSI (ASTM F152), 0.1 ml/hr leakage Fuel A (ASTM F37).

6. Gylon gasketing, Garlock Style 3500, 2000 psi (ASTM F152), 0.22 ml/hr Fuel A (ASTM F37).

7. Gylon gasketing, Garlock Style 3510, 2000 psi (ASTM F152), 0.04 ml/hr Fuel A (ASTM F37).

8. Gylon gasketing, Garlock Style 3504, 2000 psi (ASTM F152), 0.12 ml/hr Fuel A (ASTM F37).

9. TFE: noncreeping tetrafluoroethylene (TFE) with insert filler.

10. PTFE bonded EPDM: PTFE bonded to EPDM in full-face gasket having concentric-convex molded rings; Garlock Stress Saver 370 or equal.

2.04 THREAD

Pipe thread dimensions and size limits shall conform to ANSI Bl.20.1.

2.05 DIELECTRIC UNIONS

Dielectric unions shall be EPCO, Capitol Manufacturing, or equal.

2.06 COATINGS

Unless otherwise specified, flange assemblies and mechanical type couplings for buried installation shall be field coated with petrolatum based mastic

2.07 PRODUCT DATA

In accordance with Section 01300, the Contractor shall provide for each welder, a welder qualification certificate indicating the welder is certified for pipe welding in accordance with ASME Boiler and Pressure Vessel, Section IX. Each welder's certificate shall be provided to the Construction Manager prior to that welder working on the job.

15085-5

PART 3--EXECUTION

3.01 PIPE CUTTING, THREADING AND JOINTING

Pipe cutting, threading and jointing shall conform to the requirements of ANSI B31.1.

3.02 PIPE WELDING

Pipe shall be welded by ASME-certified welders using shielded metal arc, gas shielded arc or submerged arc welding methods. Welds for piping systems shall be made in accordance with AWWA C206.

3.03 FLEXIBILITY

Unless otherwise specified, piping passing from concrete to earth shall be provided with two pipe couplings or flexible joints (or a single Flexijoint) as specified on the buried pipe within 2 feet of the structure for 2-inch through 6-inch diameter pipe; within 3 feet of the structure for 8-inch through 24-inch diameter pipe; and within one and one-half pipe diameters of the structure for larger pipe. Where required for resistance to pressure, mechanical couplings shall be restrained in accordance with Chapter 13 of AWWA M11, including Tables 13-4, 13-5 and 13-5A, and Figure 13-20.

**END OF SECTION**

15085-6 SECTION 15150

AIR RELEASE AND VACUUM VALVES FOR CLEAN WATER SERVICE

PART 1--GENERAL

1.01 DESCRIPTION

A. SCOPE:

This section specifies air release valves, air and vacuum valves, and combination air valves for clean water service, pumping, and storage applications.

B. TYPES:

1. AIR RELEASE VALVES: Air release valves (ARV) shall have a small venting orifice to vent the accumulation of air and other gases with the line or system under pressure. Size and capacity shall be as specified.

2. AIR AND VACUUM VALVES: Air and vacuum valves (AVV) shall have a large venting orifice to permit the release of air as the line is filling or relieve the vacuum as the line is draining or is under negative pressure. Size and capacity shall be as specified.

3. COMBINATION AIR VALVES: Combination air valves (CAV) shall have operating features of both the air and vacuum valve and the air release valve. They include both single- and dual-body construction. Size and capacity shall be as specified.

4. AIR VALVES FOR VERTICAL TURBINE PUMPS: Air valves for vertical turbine pumps (ATP) shall consist of an air and vacuum valve with throttling device for sizes 3-inch and less, and a dual body construction combination air valve mounted on top of a surge check for sizes 4-inch and larger. Size and capacity shall be as specified.

1.02 REFERENCES

This section contains references to the following documents. They are a part of this section as specified and modified. Where a referenced document contains references to other standards, those documents are included as references under this section as if referenced directly. In the event of conflict between the requirements of this section and those of the listed documents, the requirements of this section shall prevail.

Unless otherwise specified, references to documents shall mean the documents in effect at the time of Advertisement for Bids or Invitation to Bid (or on the effective date of the Agreement if there were no Bids). If referenced documents have been discontinued by the issuing organization, references to those documents shall mean the replacement documents issued or otherwise identified by that organization or, if there are no replacement documents, the

15150-1 last version of the document before it was discontinued. Where document dates are given in the following listing, references to those documents shall mean the specific document version associated with that date, regardless of whether the document has been superseded by a version with a later date, discontinued or replaced.

Reference Title ASTM A126 Gray Iron Castings for Valves, Flanges, and Pipe Fittings ASTM A240 Heat-Resisting Chromium and Chromium Nickel Stainless Steel Plate, Sheet, and Strip for Pressure Vessels

1.03 SCHEDULE

Pressure relief capacity, minimum, Vacuum relief standard cubic capacity, minimum feet/min standard cubic Valve Valve size, System press, at 0.75 psi feet/min at 5 psi Location inches Type psi differentialb differentialb Pump 1/2 AVV 0-10 25 60 Discharge

PART 2--PRODUCTS

2.01 ACCEPTABLE PRODUCTS

Air release and vacuum valves shall be APCO as manufactured by Valve and Primer Corporation, Crispin as manufactured by Multiplex Manufacturing Company, or equal, modified to provide the specified features and to meet the specified operating conditions.

2.02 MATERIALS

Component Material Body, cover Cast iron, ASTM A126, Grade B Float Type 316 SS, ASTM A240 Seat Buna-N or Type 316 SS Trim Type 316 SS, ASTM A240

Materials specified are considered the minimum acceptable for the purposes of durability, strength, and resistance to erosion and corrosion. The Contractor may propose alternative materials for the purpose of providing greater strength or to meet required stress limitations. However, alternative materials must provide at least the same qualities as those specified for the purpose.

15150-2

2.03 CONSTRUCTION

Air release valves shall be float operated, compound lever type, except air release valves less than 1-inch may be simple lever type.

Air and vacuum valves shall be designed to protect the float from direct contact of the rushing air and water to prevent the float from closing prematurely in the valve. The seat shall be fastened into the valve cover, and shall be easily removed if necessary. The float shall be center or peripheral guided for positive shutoff into the seat.

Combination air valves, unless otherwise specified, shall be single-body construction in sizes 1- through 6-inch and dual-body construction in sizes 8-inch and larger. Single-body construction shall be designed to provide all functions within one housing. The body inlet shall be baffled to protect the float and the large and small orifices shall be designed so that during large orifice closure, the small air release orifice will open to allow small amounts of air to escape. Dual- body construction shall combine one air and vacuum valve and one air release valve with interconnecting piping and gate valve.

Air valves for vertical turbine pumps (sizes 3-inch and less) shall be designed and constructed as specified for air and vacuum valves except the discharge orifice shall be fitted with a throttling device to regulate and restrict air venting and establish a pressure loading on the rising column of water on pump start. Unless otherwise specified, air valves, 4-inch and larger, shall be dual body combination air valves except the inlet shall be fitted with a surge check to prevent water column entering the valve on pump start.

Valves shall be suitable for pressures up to 150 psi.

2.04 PRODUCT DATA

The following information shall be provided in accordance with Section 01300:

1. Manufacturer's product data.

2. Applicable O&M instruction manuals.

PART 3--EXECUTION

Air release and vacuum valves shall be installed in accordance with the manufacturer's recommendations. Unless otherwise specified, isolation valves per Section 15050 shall be provided below each air valve.

**END OF SECTION**

15150-3