Reconstruction of the road Roskovec Poshnje
albaniandf.org/2021/03/09/reconstruction-of-the-road-roskovec-poshnje-2/
March 9, 2021
CONTRACT AWARD NOTICE
Employer: Albanian Development Fund (ADF)
Project: Regional and Local Roads Connectivity Project (RLRCP)
Contract title: “Reconstruction of the road Roskovec Poshnje”
Country: Albania
Loan No.: IBRD loan 8850-AL
RFB No: RLRCP/1/1.11/2020
Issued on: March 09, 2021
I. The selection method used: Request for Bids (RFB) as specified in the World Bank’s “Procurement Regulations for IPF Borrowers” July 2016, as amended.
II. The Bidders who submitted a Bid and the bid prices as read out and as evaluated:
No. Name of Bidder Bid price as read Bid price as out, ALL, net of corrected (if any), VAT ALL, net of VAT
1. “Alb-Star” shpk 610,806,155 732,967,386
2. “Avtomagistrali – Tcherno More 579,859,450 695,831,340 JSC – Schumen”
3. “Cemil Ozgur Insaat Sanayi Ve 515,180,060 618,216,072 Ticaret AS”
4. “Gener 2” shpk 756,046,835 907,256,202
5. “Green Line General Trading and 489,777,115 587,732,538 Contracting CO.W.LL”
6. “Rawafed Al-Torok Contracting 581,835,850 698,203,020 Establishment”
7. “Salillari” shpk 571,031,410 685,237,692
8. “Trace Group Hold plc” 775,273,258 930,327,910
1/5 9. JV “4 A-M” shpk & “Makimsan 473,213,798 567,856,558 Asfalt Taahhut Insaat Sanayi Ve Ticaret AS”
10. JV “G.P.G. Company” shpk & 461,899,170 554,279,004 “Gjikuria” shpk
11. JV “Trema Engineering 2” shpk & 468,182,056 561,818,467 “Starbag AG”
III. The Bidders whose Bids were rejected and the reasons therefor:
IV. The Bidder submitting the successful Bid: JV “G.P.G. Company” shpk & “Gjikuria” shpk
V. The Contract price: 554,279,004 ALL (VAT included).
VI. The duration and summary scope of the contract: The construction period is 12 months. This project lies in the central-southern area of Albania. This segment has the number Sh-73 and connects the national road SH-4 with the city of Berat. This project includes the districts of Fier and Berat. The population under this project is 50,000 inhabitants.
The road to be reconstructed is 13,019 km long; it starts at the Patos Intersection of the district and district of Fier and ends at the Intersection of this road with the Berat- Lushnje road. This whole segment crosses Roskovec, Strume, Kutalli, Rerez until the roundabout of Poshnja.