<<

Citizen's Report

District Six Tentative Work Program Fiscal Year 2021 - 2025

Miami-Dade County

Prepared by FDOT - District 6 - 10/10/2019 Data Reading the

Citizen’sCounty: Dade Report ( 87 ) FDOT HIGHWAY SYSTEM: 01 INTRASTATE INTERSTATE PROJECT MANAGER 251688.1 SR 836/I-395 FROM WE ST OF I-95 TO MACARTHUR C SWY BRIDGE PM: PERDOMO, MARIA City: MIAMI Work Mix: Bridge-Replace And Add Lanes Extra Description: SEE ALSO 6141902 & 6141919/ULTIMATE IMPROV. CONTRACT #E6J53 R/W EST=ALT. #E-2/PH32 IN 2011 FOR DESIGN BUILD PACKAGE 4B-02 = PROPERTY MGMT SERVICES/PH4302=BNIR IN 2011 FOR ADVANCE R/W PARCELS. 32-02=CAR CNT BDT36 32-03=GC STATE FUND SEE MORE NOTES Cont. Class: Design Build ON WP45 REGARDING PH 57 & FLAGGING. FHWA OVST (PODI). PROJECT IS P3 & LET W/429300-2, 423126-1 & 423126-2

Phase Fund Code FY 2021 FY 2022 5 Year Total Construction ACID $92,340 $92,340 CEI ACNP $513,000 $513,000 ACSU $3,872,138 $3,872,138 SA $18,468 $619,408 $637,876 Total For Project 251688.1 $4,495,946 $619,408 $5,115,354

TYPE OF WORK 414964.1 SR 9A/I-95 FROM S OF MIAMI GARDENSIdentifies DRIVE the TO major B ROWARD COUNTY LINE PM: WANG, BAOYING PROJECT COST PROJECTWork Mix: Pd&E/Emo Study categoryExtra Description: of work effort SEE 95 EXPRESS UNDER 4154561 PD & E STUDY TO SUPPORT MULTIMODAL EFFORTS REMINDER: REQUEST A PH 57 TO BE ADDED IN THE AMOUNT OF $1MFunded IN THE SAME in the YR (ORTWP B4) PH 52 IS ALLOCATED PER H. HARTMANN ON 9/8/16. PHASECont. Class: Misc - No Letting on a particular item segment. BEING Phase Fund Code FY 2021 FY 2024 5 Year Total FUNDEDPDE ACNP $4,000,000 $4,000,000 P.E. ACFP $20,130,000 $20,130,000 DESCRIPTION SA $10,000 $10,000 ProvidesTotal theFor Project from 414964.1 and to $4,000,000 $20,140,000 $24,140,000 as well as the name of the road, bridge, transit operation,414964.7 airport,SR etc. 9A/I-95 FROM US-1 /SOUTH DIXIE HIGHWAY TO S OUTH OF NW 62ND STREET PM: WANG, BAOYING City: MIAMI Work Mix: Pd&E/Emo Study Extra Description: PD&E STUDY SWAT PROJECT MPO PRIORITY ID# 25/FY 21 MPO PRIORITY PROJECTS LISTING MPO RESOLUTION #17-14/LRTP PRIORITY #2 REFER TO 432639-6 FOR LIMIT SPLIT Cont. Class: Misc - No Letting

Phase Fund Code FY 2022 FY 2024 5 Year Total PDE ACFP $6,700,000 $6,700,000 P.E. ACFP $10,340,000 $10,340,000 Total For Project 414964.7 $6,700,000 $10,340,000 $17,040,000

October. 10 2019 Page 2 of 151 County: Miami Dade ( 87 )

HIGHWAY SYSTEM: 01 INTRASTATE INTERSTATE

251688.1 SR 836/I-395 FROM WE ST OF I-95 TO MACARTHUR C SWY BRIDGE PM: PERDOMO, MARIA City: MIAMI Work Mix: Bridge-Replace And Add Lanes Extra Description: SEE ALSO 6141902 & 6141919/ULTIMATE IMPROV. CONTRACT #E6J53 R/W EST=ALT. #E-2/PH32 IN 2011 FOR DESIGN BUILD PACKAGE 4B-02 = PROPERTY MGMT SERVICES/PH4302=BNIR IN 2011 FOR ADVANCE R/W PARCELS. 32-02=CAR CNT BDT36 32-03=GC STATE FUND SEE MORE NOTES Cont. Class: Design Build ON WP45 REGARDING PH 57 & FLAGGING. FHWA OVST (PODI). PROJECT IS P3 & LET W/429300-2, 423126-1 & 423126-2

Phase Fund Code FY 2021 FY 2022 5 Year Total Construction ACID $92,340 $92,340 CEI ACNP $513,000 $513,000 ACSU $3,872,138 $3,872,138 SA $18,468 $619,408 $637,876 Total For Project 251688.1 $4,495,946 $619,408 $5,115,354

414964.1 SR 9A/I-95 FROM S OF MIAMI GARDENS DRIVE TO B ROWARD COUNTY LINE PM: WANG, BAOYING

Work Mix: Pd&E/Emo Study Extra Description: SEE 95 EXPRESS UNDER 4154561 PD & E STUDY TO SUPPORT MULTIMODAL EFFORTS REMINDER: REQUEST A PH 57 TO BE ADDED IN THE AMOUNT OF $1M IN THE SAME YR (OR B4) PH 52 IS ALLOCATED PER H. HARTMANN ON 9/8/16. Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2024 5 Year Total PDE ACNP $4,000,000 $4,000,000 P.E. ACFP $20,130,000 $20,130,000 SA $10,000 $10,000 Total For Project 414964.1 $4,000,000 $20,140,000 $24,140,000

414964.7 SR 9A/I-95 FROM US-1 /SOUTH DIXIE HIGHWAY TO S OUTH OF NW 62ND STREET PM: WANG, BAOYING City: MIAMI Work Mix: Pd&E/Emo Study Extra Description: PD&E STUDY SWAT PROJECT MPO PRIORITY ID# 25/FY 21 MPO PRIORITY PROJECTS LISTING MPO RESOLUTION #17-14/LRTP PRIORITY #2 REFER TO 432639-6 FOR LIMIT SPLIT Cont. Class: Misc - No Letting

Phase Fund Code FY 2022 FY 2024 5 Year Total PDE ACFP $6,700,000 $6,700,000 P.E. ACFP $10,340,000 $10,340,000 Total For Project 414964.7 $6,700,000 $10,340,000 $17,040,000

October. 10 2019 Page 2 of 151 HIGHWAY SYSTEM: 01 INTRASTATE INTERSTATE

414964.8 SR 9A/I-95 FROM SOUT H OF NW 62ND STREET TO NO RTH OF NW 151 STREET PM: WANG, BAOYING City: MIAMI - NORTH MIAMI Work Mix: Pd&E/Emo Study Extra Description: PD&E STUDY MPO PRIORITY ID# 25/FY 21 MPO PRIORITY PROJECTS LISTING MPO RESOLUTION #17-14/LRTP PRIORITY #2 REFER TO 432639- 6 FOR LIMIT SPLIT Cont. Class: Misc - No Letting

Phase Fund Code FY 2022 FY 2024 5 Year Total PDE ACFP $3,700,000 $3,700,000 P.E. ACFP $5,720,000 $5,720,000 Total For Project 414964.8 $3,700,000 $5,720,000 $9,420,000

415456.7 SR 9A/I-95 EXPRESS L ANES ITS OPERATIONS CONSU LTANT CONTRACT PM: MOTTA, ALEJANDRO City: MIAMI - NORTH MIAMI Work Mix: Technical Assistance Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 5 Year Total Capital Improvement/Operating TOBD $3,528,565 $3,528,565 Total For Project 415456.7 $3,528,565 $3,528,565

415456.9 SR 9A/I-95 EXPRESS F HP ENHANCED ENFORCEMENT PM: RODRIGUEZ, JAVIER Work Mix: Other Its Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 5 Year Total Capital Improvement/Operating TOBD $625,000 $380,000 $370,000 $1,375,000 Total For Project 415456.9 $625,000 $380,000 $370,000 $1,375,000

423126.2 SR 9A/I-95 SOUTHBOUN D RAMP TO WESTBOUND SR 83 6 PM: PERDOMO, MARIA City: MIAMI

Work Mix: Interchange Improvement Extra Description: CNT# E6J53; P3 & LET W/251688-1, 423126-1 & 423126-2 FHWA OVERSIGHT (PODI). Cont. Class: Design Build

Phase Fund Code FY 2021 5 Year Total CEI STED $2,220,004 $2,220,004 Total For Project 423126.2 $2,220,004 $2,220,004

October. 10 2019 Page 3 of 151 HIGHWAY SYSTEM: 01 INTRASTATE INTERSTATE

423452.3 SR 9A/I-95 FROM N.W. 155TH STREET TO N.W. 170 TH STREET PM: SCHOT, KEVIN Work Mix: Landscaping Extra Description: THIS REQUEST IS FOR A NEW LANDSCAPE PROJECT WHOSE FUNDING HAS BEEN REQUESTED PREVIOUSLY BUT HAS NOT BEEN AVAILABLE. PROJECT LIMITS INCLUDE A MAJOR INTERCHANGE AT I-95, SR 826, SR-7, AND FL TPK. THIS MAJOR INTERSECTION IS ONE OF THREE IN THE I-95 CORRIDOR Cont. Class: District Let THAT, WHEN COMPLETED, WILL FINISH ALL SIGNIFICANT LANDSCAPING ON I-95. G/W 428358-1;251684-6

Phase Fund Code FY 2023 5 Year Total P.E. DDR $500,000 $500,000 DIH $30,000 $30,000 Total For Project 423452.3 $530,000 $530,000

428358.5 SR 9A/I-95 FROM N. O F BISCAYNE CANAL TO SR 86 0/MIAMI GARDEN DR PM: GARGANTA, NATALIE Work Mix: Widen/Resurface Exist Lanes Extra Description: I-95 WIDENING TO PROVIDE AUXILARY LANES FROM BISCAYNE RIVER CANAL TO MIAMI GARDENS DRIVE MPO PRIORITY ID# 13/FY 21 MPO PRIORITY PROJECTS LISTING PHASE 32-01 = GEOTECH, 32-02 = INHOUSE SUPPORT AECOM ($300K) PHASE 32-03 = DRAINAGE AECOM ($150K) Cont. Class: Tallahassee Let CONTRACT C9J68 FHWA IDENTIFIED AS OVERSIGHT (PODI) 6/15/2018 FY19.

Phase Fund Code FY 2021 5 Year Total P.E. DS $220,000 $220,000 Total For Project 428358.5 $220,000 $220,000

429047.1 SR 93/I-75 FROM NW 1 78 STREET TO NW 202 STREE T PM: SCHOT, KEVIN

Work Mix: Landscaping Extra Description: STAND ALONE LANDSCAPING CONTRACT#: E6M81 (LEAD) LET W/4290472 NOTE: MEGA MALL INFLUENCE FOLLOW CST OF D6 FM 4326871 & D4 FM 4307637. FM 4217078 (D6 IMPACTS) PER LANDSCAPE GAMING MTG HELD 10/10/16 NOTE: BDI CONTRACT PER LEIGH,APPR. BY ANGELA MATIYOW Cont. Class: District Let 1-11-18

Phase Fund Code FY 2021 5 Year Total Construction DDR $1,115,380 $1,115,380 CEI DDR $136,126 $136,126 DIH $44,118 $44,118 DS $108,062 $108,062 Total For Project 429047.1 $1,403,686 $1,403,686

October. 10 2019 Page 4 of 151 HIGHWAY SYSTEM: 01 INTRASTATE INTERSTATE

429047.2 SR 93/I-75 FROM NW 1 62 STREET TO NW 178 STREE T PM: SCHOT, KEVIN

Work Mix: Landscaping Extra Description: NOTE: MEGA MALL INFLUENCE FOLLOW CST OF D6 FM 4326871 & D4 FM 4307637. FM 4217078 (D6 IMPACTS) PER LANDSCAPE GAMING MTG HELD 10/10/16 CNT# E6M81 LET W/4290471 (LEAD) Cont. Class: District Let

Phase Fund Code FY 2021 5 Year Total Construction DDR $699,456 $699,456 CEI DIH $27,702 $27,702 DS $162,108 $162,108 Total For Project 429047.2 $889,266 $889,266

429300.2 SR 9A/I-95 FROM NW 8 STREET TO NW 29 STREET PM: PERDOMO, MARIA City: MIAMI Work Mix: Rigid Pavement Reconstruction Extra Description: CONCRETE PAVEMENT PROJECT (SECTION #1 SOUTH PORTION) #E6J53 SECTION #2 NORTH PORTION SPLIT TO SEGMENT 3 (4293003) INCLUDES CONCRETE PAVEMENT RAMPS 87270173, 87270174, 87270176, 87270223, 87270507 AND 87270600.FHWA OVERSIGHTPODI P3 & LET WITH Cont. Class: Design Build 251688-1, 423126-1 & 423126-2

Phase Fund Code FY 2021 5 Year Total CEI ACNP $447,565 $447,565 SA $149,999 $149,999 Total For Project 429300.2 $597,564 $597,564

430291.4 ITS EQUIPMENT REPLAC EMENT - CONSULTANTS /GRAN TS PM: BRAVO, S/, D

Work Mix: Its Communication System Extra Description: Cont. Class: Design Build

Phase Fund Code FY 2021 5 Year Total CEI DS $112,860 $112,860 DSBD $193,914 $193,914 Total For Project 430291.4 $306,774 $306,774

October. 10 2019 Page 5 of 151 HIGHWAY SYSTEM: 01 INTRASTATE INTERSTATE

430291.5 ITS EQUIPMENT REPLAC EMENT - CONSULTANTS /GRAN TS PM: BRAVO, S/DUNCAN, D

Work Mix: Its Communication System Extra Description: Cont. Class: Design Build

Phase Fund Code FY 2021 FY 2022 5 Year Total CEI DS $1,295,127 $1,295,127 DSBD $454,896 $454,896 Capital Improvement/Operating DITS $6,833,000 $6,833,000 DSBD $2,400,000 $2,400,000 Total For Project 430291.5 $9,233,000 $1,750,023 $10,983,023

430291.6 ITS EQUIPMENT REPLAC EMENT - CONSULTANTS /GRAN TS PM: BRAVO, S/DUNCAN, D

Work Mix: Its Communication System Extra Description: Cont. Class: Design Build

Phase Fund Code FY 2022 FY 2023 5 Year Total CEI DS $325,143 $325,143 DSBD $330,786 $330,786 Capital Improvement/Operating DITS $1,671,000 $1,671,000 DSBD $1,700,000 $1,700,000 Total For Project 430291.6 $3,371,000 $655,929 $4,026,929

430291.7 ITS EQUIPMENT RE PLACEMENT - CONSULTANTS / GRANTS PM: BRAVO, S/DUNCAN, D

Work Mix: Its Communication System Extra Description: Cont. Class: Design Build

Phase Fund Code FY 2023 FY 2024 5 Year Total CEI DS $261,045 $261,045 Capital Improvement/Operating DITS $1,305,355 $1,305,355 Total For Project 430291.7 $1,305,355 $261,045 $1,566,400

October. 10 2019 Page 6 of 151 HIGHWAY SYSTEM: 01 INTRASTATE INTERSTATE

430291.8 ITS EQUIPMENT REPLA CEMENT - CONSULTANTS /GRA NTS PM: BRAVO, S/DUNCAN, D Work Mix: Its Communication System Extra Description: Cont. Class: Design Build

Phase Fund Code FY 2024 FY 2025 5 Year Total CEI DS $274,798 $274,798 Capital Improvement/Operating DITS $1,334,487 $1,334,487 Total For Project 430291.8 $1,334,487 $274,798 $1,609,285

430291.9 ITS EQUIPMENT REPLAC EMENT - CONSULTANTS /GRAN TS PM: BRAVO, S/DUNCAN, D Work Mix: Its Communication System Extra Description: Cont. Class: Design Build

Phase Fund Code FY 2025 5 Year Total CEI DS $133,424 $133,424 Capital Improvement/Operating DITS $1,237,061 $1,237,061 Total For Project 430291.9 $1,370,485 $1,370,485

430444.3 SR 907/ALTON ROAD FR OM 43 ST TO WESTBND SR 11 2/I-195/JULIA TUTTLE CSWY PM: GOMEZ, HUMBERTO City: MIAMI BEACH Work Mix: Traffic Ops Improvement Extra Description: WIDEN ON-RAMP FROM SOUTHBOUND SR 907/ALTON ROAD TO WESTBOUND SR 112/I-195. CNT# T6522 APPROVED BY SCOPING COMMITTEE ON 5-24-17 PH56-01 = LUMPSUM W/THE CITY OF MIAMI BEACH FOR VALVE AND MANHOLE ADJUSTMENTS Cont. Class: Tallahassee Let

Phase Fund Code FY 2021 FY 2023 5 Year Total Construction DDR $3,006,225 $3,006,225 LF $7,000 $7,000 Incentive DS $200,000 $200,000 CEI DIH $87,210 $87,210 DS $376,542 $376,542 Total For Project 430444.3 $3,476,977 $200,000 $3,676,977

434676.1 SR 9A/I-95 EXPRESS O PERATIONS & MAINTENANCE I NCIDENT MGMT/RD RANGERS PM: DARDES, CARLOS Work Mix: Other Its Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 5 Year Total Capital Improvement/Operating TOBD $3,258,748 $3,023,980 $2,271,708 $8,554,436 Total For Project 434676.1 $3,258,748 $3,023,980 $2,271,708 $8,554,436

October. 10 2019 Page 7 of 151 HIGHWAY SYSTEM: 01 INTRASTATE INTERSTATE

434676.2 I-95 EXPRESS LANES I NCIDENT MANAGEMENT ROAD R ANGER SERVICE PATROLS PM: DARDES, CARLOS

Work Mix: Other Its Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2024 FY 2025 5 Year Total Capital Improvement/Operating TOBD $4,123,900 $4,123,900 $8,247,800 Total For Project 434676.2 $4,123,900 $4,123,900 $8,247,800

436199.1 SR 93/I-75 EXPRESS L ANES TOLLING AND OPERATIO NS PM: MOTTA, ALEJANDRO

Work Mix: Technical Assistance Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 5 Year Total Capital Improvement/Operating TOBG $688,591 $688,591 Total For Project 436199.1 $688,591 $688,591

436202.1 SR 9A/I-95 EXPRESS O PERATIONS & MAINTENANCE PM: MOTTA, ALEJANDRO Work Mix: Other Its Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 5 Year Total Capital Improvement/Operating TOBD $1,600,000 $1,600,000 $3,200,000 Total For Project 436202.1 $1,600,000 $1,600,000 $3,200,000

436202.2 I-95 EXPRESS LANES I NFRASTRUCTURE MAINTENANCE & REPAIRS PM: MOTTA, ALEJANDRO Work Mix: Other Its Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2023 FY 2024 FY 2025 5 Year Total Capital Improvement/Operating TOBD $1,680,000 $1,680,000 $1,680,000 $5,040,000 Total For Project 436202.2 $1,680,000 $1,680,000 $1,680,000 $5,040,000

October. 10 2019 Page 8 of 151 HIGHWAY SYSTEM: 01 INTRASTATE INTERSTATE

436204.1 SR 93/I-75 EXPRESS L ANES ITS MAINTENANCE OF T OLLING EQUIPMENT PM: MOTTA, ALEJANDRO Work Mix: Other Its Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 5 Year Total Capital Improvement/Operating TOBG $400,000 $400,000 $800,000 Total For Project 436204.1 $400,000 $400,000 $800,000

436204.2 I-75 EXPRESS LANES I NFRASTRUCTURE MAINTENANCE & REPAIRS PM: MOTTA, ALEJANDRO Work Mix: Other Its Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2023 FY 2024 FY 2025 5 Year Total Capital Improvement/Operating TOBG $420,000 $420,000 $420,000 $1,260,000 Total For Project 436204.2 $420,000 $420,000 $420,000 $1,260,000

436210.1 SR 93/I-75 EXPRESS L ANES INCIDENT MANAGMNT/RO AD RANGER SERVICE PATROLS PM: DARDES, CARLOS

Work Mix: Other Its Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 5 Year Total Capital Improvement/Operating TOBD $713,005 $713,005 TOBG $1,089,125 $964,125 $2,053,250 Total For Project 436210.1 $1,089,125 $964,125 $713,005 $2,766,255

436210.2 I-75 EXPRESS LANES I NCIDENT MANAGMENT ROAD RA NGER SERVICE PATROLS PM: DARDES, CARLOS

Work Mix: Other Its Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2024 FY 2025 5 Year Total Capital Improvement/Operating TOBG $618,600 $618,600 $1,237,200 Total For Project 436210.2 $618,600 $618,600 $1,237,200

October. 10 2019 Page 9 of 151 HIGHWAY SYSTEM: 01 INTRASTATE INTERSTATE

436213.1 SR 93/I-75 EXPRESS L ANES FHP ENHANCED ENFORCE MENT PM: RODRIGUEZ, JAVIER Work Mix: Other Its Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 5 Year Total Capital Improvement/Operating TOBG $225,000 $185,000 $171,000 $581,000 Total For Project 436213.1 $225,000 $185,000 $171,000 $581,000

436213.2 I-75 EXPRESS LANES F HP ENHANCED ENFORCEMENT PM: DARDES, CARLOS Work Mix: Other Its Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2024 FY 2025 5 Year Total Capital Improvement/Operating TOBG $232,000 $232,000 $464,000 Total For Project 436213.2 $232,000 $232,000 $464,000

441834.1 SR 93/I-75 FRONTAGE RDS FROM E OF HIALEAH GDN S BLVD TO W 23RD AVE PM: FUNTANELLAS, IVETTE City: HIALEAH

Work Mix: Resurfacing Extra Description: RRR PROJECT CNT# T6491 INCLUDES TWO SEGMENTS (MATCH 4390881 & 4307951) FRONTAGE RD (NW 138 ST/W 84 ST) (87075703) CRACK RATING = 6.5 FRONTAGE RD (NW 138 ST/W 84 ST)(87075704) CRACK RATING = 6.0 CONSULT: GOAL ASSOCIATES. ***SEE Cont. Class: Tallahassee Let WP45**

Phase Fund Code FY 2021 5 Year Total Incentive DS $200,000 $200,000 Total For Project 441834.1 $200,000 $200,000

441836.1 SR 93/I-75 RAMPS AT NW 138 STREET PM: DE LA CRUZ, JOAQUIN City: HIALEAH Work Mix: Resurfacing Extra Description: RRR PROJECT/I-75 EXIT 2 INCLUDES 4 RAMPS (MATCH FM 439088-1) EXISTING BRIDGES 870604 AND 870605 TO REMAIN / NB OFF RAMP (87075600) CRACK RATING = 6.5 / SB ON RAMP(87075601) CRACK RATING = 6.0 / NB ON RAMP CRACK RATING (87075602) = 6.0 & & SB Cont. Class: District Let OFF RAMP (87075603) CRACK RATING (87075602) = 6.0 AND SB OFF RAMP (87075603) CRACK RATING = 5.5

Phase Fund Code FY 2021 FY 2023 5 Year Total P.E. DIH $30,000 $30,000 DS $154,000 $154,000 Construction DDR $1,447,113 $1,447,113 CEI DIH $21,620 $21,620 DS $183,770 $183,770 Total For Project 441836.1 $184,000 $1,652,503 $1,836,503

October. 10 2019 Page 10 of 151 HIGHWAY SYSTEM: 01 INTRASTATE INTERSTATE

441967.1 SR 112/I 195 OVER WE STSHORE WATERWAY BRIDGE# 870314 PM: COELLO, GEIDY City: MIAMI Work Mix: Bridge-Repair/Rehabilitation Extra Description: CNT# E6M50 Cont. Class: District Let

Phase Fund Code FY 2021 5 Year Total Construction BRRP $926,478 $926,478 CEI BRRP $205,200 $205,200 DIH $20,520 $20,520 Total For Project 441967.1 $1,152,198 $1,152,198

443894.1 SR 9A/I-95 RAMPS AT SR90/SW 8 STREET AND SW 7 STREET PM: GOMEZ, HUMBERTO City: MIAMI

Work Mix: Rigid Pavement Rehabilitation Extra Description: FY2018 RESURFACING PROJECT. RAMPS 87270168, 87270169, 87270170, 87270171, & 87270501. RIGID PAVEMENT REHABILITATION PROJECT. LEAD STRUNG W/4439421 & 4438901 APPROVED INTERSTATE PROJECT FOR FY2023 Cont. Class: Tallahassee Let

Phase Fund Code FY 2021 FY 2023 5 Year Total P.E. ACNP $320,000 $320,000 Construction ACNP $1,287,621 $1,287,621 CEI ACNP $155,461 $155,461 Total For Project 443894.1 $320,000 $1,443,082 $1,763,082

443896.1 SR 9A/I-95 RAMPS SOU THBOUND OFF RAMP TO SW 25 ROAD PM: GOMEZ, HUMBERTO

Work Mix: Rigid Pavement Rehabilitation Extra Description: FY2018 RESURFACING PROJECT RAMPS 87270004, 87270166, 87270167, 87270500, RIGID PAVEMENT REHABILITATION PROJECT. PH32-02 = SAFETY COMPONENT, PH52-02 = SAFETY COMPONENT B/C: 11.4/ NPV: $3,210,630/SHSP: INTERSECTION CRASHES SAFETY COMPONENT RDWY#87270166 Cont. Class: Tallahassee Let FROM BMP 0.00 TO EMP 0.178 ***SEE WP45*** SAFETY SHAREPOINT #D6-217

Phase Fund Code FY 2021 FY 2023 5 Year Total P.E. ACID $82,702 $82,702 ACNP $405,000 $405,000 Construction ACNP $2,190,893 $2,190,893 ACSS $279,379 $279,379 DS $57,183 $57,183 CEI ACNP $387,317 $387,317 ACSS $55,876 $55,876 Total For Project 443896.1 $487,702 $2,970,648 $3,458,350

October. 10 2019 Page 11 of 151 HIGHWAY SYSTEM: 01 INTRASTATE INTERSTATE

443942.1 SR 9A/I-95 (SHOULDER S ONLY) FROM SOUTH DIXIE HIGHWAY TO SW 8TH STREET PM: GOMEZ, HUMBERTO City: MIAMI Work Mix: Rigid Pavement Rehabilitation Extra Description: 2018 RESURFACING PROJECTS STRUNG W/4438901 & 4438941 (LEAD) REHAB ASPHALT SHOULDERS APPROVED INTERSTATE PROJECT FOR FY2023 Cont. Class: Tallahassee Let

Phase Fund Code FY 2021 FY 2023 5 Year Total P.E. ACNP $285,000 $285,000 Construction ACNP $449,712 $449,712 CEI ACNP $88,931 $88,931 Total For Project 443942.1 $285,000 $538,643 $823,643

444622.1 SR 112/I-195/JULIA T UTTLE CSWY FR E. OF SR-5/ BISCAYNE BLV TO ALTON RD PM: WANG, BAOYING City: MIAMI BEACH - MIAMI

Work Mix: Miscellaneous Construction Extra Description: 2018 MPO PRIORITY #2/3 INSIDE SHOULDER WIDENING & IMPROVEMENTS FROM JUST EAST OF BISCAYNE BLV ON/OFF RAMPS TO ALTON ROAD ON/OFF RAMPS O&M UNFUNDED Cont. Class: Tallahassee Let

Phase Fund Code FY 2022 FY 2023 5 Year Total Construction GFSU $5,917,860 $5,917,860 Incentive SA $220,000 $220,000 CEI GFSU $183,495 $183,495 SU $1,093,540 $1,093,540 Total For Project 444622.1 $6,101,355 $1,313,540 $7,414,895

444800.1 SR 9A/I-95 SOUTHBOUN D SOUTH OF NW 6 STREET OV ERHEAD SIGN 87S051 PM: OROZCO, PABLO City: MIAMI Work Mix: Overhead Signing Extra Description: LEFT TURN OF I-95 OVERHEAD SIGN 875051 Cont. Class: District Let

Phase Fund Code FY 2021 FY 2024 5 Year Total P.E. DDR $60,000 $60,000 DIH $8,000 $8,000 Construction DDR $447,957 $447,957 CEI DDR $77,770 $77,770 DIH $16,665 $16,665 Total For Project 444800.1 $68,000 $542,392 $610,392

October. 10 2019 Page 12 of 151 HIGHWAY SYSTEM: 01 INTRASTATE INTERSTATE

444801.1 SR 913 RAMP WESTBOUN D TO I-95 NORTHBOUND BRID GE# 870162 PM: OROZCO, PABLO City: MIAMI Work Mix: Bridge - Painting Extra Description: BRIDGE SUPERSTRUCTURE AND SUBSTRUCTURE REHABILITATION INCLUDING BRIDGE PAINTING PH52 = LEAD STRUNG W/4448021 Cont. Class: Tallahassee Let

Phase Fund Code FY 2022 FY 2024 5 Year Total P.E. BRRP $380,000 $380,000 DIH $57,000 $57,000 Construction BRRP $4,300,681 $4,300,681 CEI BRRP $888,800 $888,800 DIH $88,880 $88,880 Total For Project 444801.1 $437,000 $5,278,361 $5,715,361

444802.1 SR 913 RAMP WESTBOUN D TO US-1 SOUTHBOUND BRID GE# 870163 PM: OROZCO, PABLO City: MIAMI Work Mix: Bridge - Painting Extra Description: BRIDGE SUPERSTRUCTURE AND SUBSTRUCTURE REHABILITATION INCLUDING BRIDGE PAINTING PH52 = STRUNG W/4448011 (LEAD) Cont. Class: Tallahassee Let

Phase Fund Code FY 2022 FY 2024 5 Year Total P.E. BRRP $100,000 $100,000 DIH $17,000 $17,000 Construction BRRP $1,406,526 $1,406,526 CEI BRRP $272,195 $272,195 DIH $25,553 $25,553 Total For Project 444802.1 $117,000 $1,704,274 $1,821,274

445745.1 SR 985/SW 107 AVENUE AND SW 24 STREET PM: SOLAUN, JUDY Work Mix: Intersection Improvement Extra Description: B/C: 7.5/NPV: $2,984,655/SHSP: INTERSECTION CRASHES PROVIDE AN ADDITIONAL WB LEFT TURN LANE.PROVIDE A SB OVERLAP PHASE. REPLACE MAST ARM ON SOUTHBOUND APPROACH FOR OVERLAP PHASE. INSTALL SIGNAL AHEAD WARNING SIGNS SAFETY SHAREPOINT #D6-212 Cont. Class: Tallahassee Let

Phase Fund Code FY 2021 FY 2023 5 Year Total P.E. ACSS $109,026 $109,026 SA $15,000 $15,000 Construction ACSS $366,867 $366,867 SA $72,228 $72,228 CEI ACSS $67,728 $67,728 SA $9,729 $9,729 Total For Project 445745.1 $124,026 $516,552 $640,578

October. 10 2019 Page 13 of 151 HIGHWAY SYSTEM: 01 INTRASTATE INTERSTATE

445763.1 SR 9A/I-95 AUDIBLE P AVEMENT MARKINGS FROM MP 0.00 TO 11.31 PM: FUNTANELLAS, IVETTE City: MIAMI - NORTH MIAMI Work Mix: Signing/Pavement Markings Extra Description: SR 9A/I-95 FROM MP 0.00 TO MP 11.31, MP 7.265 TO MP 10.892 & MP 10.892 TO MP 11.310 NORTHBOUND ONLY TO PROVIDE AUDIBLE PAYMENT MARKINGS ON ROADWAY EDGE LINES B/C:27.9 / NPV: $14,465,464/ SHSP - LANE DEPARTURE CRASHES SAFETY SHAREPOINT #D6-215 Cont. Class: Tallahassee Let LEAD STRUNG W/445764-1 CNT#

Phase Fund Code FY 2022 5 Year Total Construction ACSS $534,757 $534,757 SA $141,240 $141,240 CEI ACSS $94,160 $94,160 SA $43,173 $43,173 Total For Project 445763.1 $813,330 $813,330

446193.1 SR 9A/I-95 NB FLYOVE R RAMP OVER NW 17 & NW 20 ST - BRIDGE # 870724 PM: OROZCO, PABLO

Work Mix: Bridge-Rehab And Add Lanes Extra Description: Cont. Class: District Let

Phase Fund Code FY 2023 FY 2025 5 Year Total P.E. BRRP $90,000 $90,000 Construction BRRP $1,017,016 $1,017,016 CEI BRRP $223,080 $223,080 Total For Project 446193.1 $90,000 $1,240,096 $1,330,096

446480.1 SR 826, SR 934 & I-7 5 WRONG WAY DRIVING COUNT ER MEASURES PM: ARVELO, ANA City: HIALEAH - MEDLEY - MIAMI GARDENS - MIAMI LAKES - DORAL

Work Mix: Its Freeway Management Extra Description: SCOPE: INSTALL WRONG WAY DRIVING COUNTERMEASURES ON LIMITED ACCESS FACILITIES EXIT RAMPS TO MEET REQUIREMENTS IN ROADWAY DESIGN BULLETIN 19-03. MAIN IMPROVEMENT INCLUDE THE INSTALLATION OF LIGHT EMITTING DIODE (LED) WRONG WASY SIGNS INTEGRATED Cont. Class: Tallahassee Let BACK TO THE TRAFFIC MANAGMENT CENTER (TMC) AT 52 EXIT RAMPS ALONG SR 826, SR 934 & I-75. ***WP45***

Phase Fund Code FY 2021 5 Year Total Construction ACID $1,600,560 $1,600,560 CEI ACID $17,460 $17,460 SA $313,855 $313,855 Total For Project 446480.1 $1,931,875 $1,931,875

FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total HIGHWAY SYSTEM: 01 Total $43,011,047 $30,162,221 $16,841,965 $52,395,059 $9,959,879 $152,370,171 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

October. 10 2019 Page 14 of 151 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

249943.3 MIAMI-DADE COUNTYWDE CONTAMINATION ASSESSMENT & REMEDIATION PM: GOMEZ, MAURICIO Work Mix: Environmental Test/Mitigate Extra Description: PH32/02=CNT# BDL07/CB&I; PH32/03=CNT# BDT36/CB&I PH32/04=CNT# BDT37/NORTHSTAR CNT GROUP; PH32/05=CNT#BDY80/ CB&I;PH32/06=CNT# BDY81/NOVA CONSULT. PHC2/01=CNT#BDT37/NORTHSTAR CNT GRP; PHC2/02=BDY80/CB&I PH32-05/CNT# Cont. Class: Misc - No Letting BDY80/CONSULT: APTIM PH32-06/CNT# BDY81/CONSULT: NOVA

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total PDE DIH $50,000 $50,000 $50,000 $50,000 $50,000 $250,000 P.E. DDR $800,000 $400,000 $400,000 $400,000 $2,000,000 Total For Project 249943.3 $850,000 $450,000 $450,000 $450,000 $50,000 $2,250,000

250113.5 SERVICE PATROLS PM: DARDES, CARLOS

Work Mix: Service Patrol/Fhp Extra Description: Cont. Class: District Let

Phase Fund Code FY 2021 FY 2022 FY 2023 5 Year Total Capital Improvement/Operating DSPC $2,528,528 $2,596,798 $2,669,508 $7,794,834 Total For Project 250113.5 $2,528,528 $2,596,798 $2,669,508 $7,794,834

250113.7 SERVICE PATROLS PM: DARDES, CARLOS

Work Mix: Service Patrol/Fhp Extra Description: Cont. Class: District Let

Phase Fund Code FY 2024 FY 2025 5 Year Total Capital Improvement/Operating DSPC $2,746,924 $2,818,344 $5,565,268 Total For Project 250113.7 $2,746,924 $2,818,344 $5,565,268

251156.3 PORT OF MIAMI TUNNEL FROM PORT OF MIAMI TO SR 836/I-395 PM: SALAZAR, LEONARD City: MIAMI Work Mix: New Road Construction Extra Description: SEG.3 FOR GROWTH MANAGEMENT/32-06 PRC JOB/FHWA OVST.#E6F67 PH32 STIPENDS = SEQ. 2 - MIAMI ACCESS TUNNEL; SEQ. 3 - MIAMI MOBILITY GROUP AND SEQ. 4 - FCC CONSTRUCTION S.A./ MORGAN STANLEY. PH.82 OPERATION/MAINTENANCE & PH.52 SEQ. 01 AVAILABILITY Cont. Class: Design Build PAYMENT,SEQ.02 GEOTECH RESERVE,SEQ.03 MILESTONE PAYMENTS;PH.3201 GMR 12/13-41/42=FINANCIAL SERVICES S/A WP45

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total Construction GMR $24,337,594 $25,356,701 $24,712,049 $24,508,307 $26,018,150 $124,932,801 LF $2,934,702 $3,022,745 $3,113,427 $3,206,829 $3,303,033 $15,580,736 Capital Improvement/Operating DI $19,729,048 $21,726,272 $23,323,165 $23,248,265 $88,026,750 STED $19,434,977 $19,434,977 Total For Project 251156.3 $46,707,273 $48,108,494 $49,551,748 $51,038,301 $52,569,448 $247,975,264

October. 10 2019 Page 15 of 151 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

251156.4 PORT OF MIAMI TUNNEL MIAMI-DADE COUNTY MPO PR IORITY PM: SALAZAR, LEONARD City: MIAMI Work Mix: Funding Action Extra Description: 2018 TPO PRIORITY #9 Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total Admin DDR $17,000,000 $17,000,000 $17,000,000 $17,000,000 $17,000,000 $85,000,000 Total For Project 251156.4 $17,000,000 $17,000,000 $17,000,000 $17,000,000 $17,000,000 $85,000,000

405574.1 MIAMI-DADE COUNTYWDE AGREEMENT-TRAFFIC SIGNAL S MAINTENANCE & OPERATION PM: RODRIGUEZ, CHERIE Work Mix: Traffic Signals Extra Description: TRAFFIC SIGNAL MAINTENANCE & OPERATION Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total Capital Improvement/Operating DDR $2,986,281 $3,090,729 $3,199,450 $3,311,200 $3,427,000 $16,014,660 DITS $3,851,796 $3,954,218 $4,090,458 $4,184,667 $4,279,000 $20,360,139 Total For Project 405574.1 $6,838,077 $7,044,947 $7,289,908 $7,495,867 $7,706,000 $36,374,799

405575.8 SR 9336/PALM DRIVE F ROM SR 997/KROME AVE TO S R 5/US 1 (TRUCK BYPASS) PM: QUINTELA, RAUL City: FLORIDA CITY Work Mix: Widen/Resurface Exist Lanes Extra Description: KROME AVENUE TRUCK BY PASS - LET W/4055756 (LEAD) & 4055757 PD & E PERFORMED UNDER FM #405575-2 CNT# T6450 Cont. Class: Tallahassee Let

Phase Fund Code FY 2021 5 Year Total Incentive DDR $60,000 $60,000 Total For Project 405575.8 $60,000 $60,000

405575.9 SR 997/KROME AVENUE FROM SW 312ST/CAMPBELL DR TO SW 296 ST (TRUCKBYPS) PM: BARRERA, JOSE City: HOMESTEAD

Work Mix: Add Lanes & Rehabilitate Pvmnt Extra Description: KROME AVENUE TRUCK BY PASS (LET W/427369-1 LEAD) CNT# T6424 PD & E PERFORMED UNDER FM #405575-2 NOTE: SIS BEING VERIFIED / PH52-01=CNT# C9L15 NOTE: 30 DAY AD APPROVED BY BRIAN BLANCHARD 10-10-16 NOTE: PER LEIGH CANN 12-14-16, CHANGED BACK TO 60 DAY Cont. Class: Tallahassee Let AD PH61-01 = MATERIALS TESTING PH62-61 = MATERIALS LAB

Phase Fund Code FY 2022 5 Year Total Incentive DDR $200,000 $200,000 Total For Project 405575.9 $200,000 $200,000

October. 10 2019 Page 16 of 151 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

410646.4 SR 934/NE/NW 79 ST F ROM WEST OF I-95(13 CT.) TO END OF SR 934/1 WAY PR PM: BENITEZ, AURALIZ City: MIAMI Work Mix: Pd&E/Emo Study Extra Description: PD&E STUDY CONTINUATION OF SEGMENT 2 REMINDER: REQUEST A PH 57 TO BE ADDED IN THE AMOUNT OF $1M IN THE SAME YR (OR B4) PH 52 IS ALLOCATED PER H. HARTMANN ON 9/8/16. Cont. Class: Misc - No Letting

Phase Fund Code FY 2023 5 Year Total RW Land DDR $4,664,300 $4,664,300 RW Support DDR $739,000 $739,000 DIH $144,000 $144,000 Total For Project 410646.4 $5,547,300 $5,547,300

410646.5 SR 934/NE/NW 79 ST F ROM WEST OF I-95(13 CT.) TO END OF SR 934/1 WAY PR PM: RAGHUNANDAN, RYAN City: MIAMI

Work Mix: Add Lanes & Reconstruct Extra Description: LCDA = 06/2020 Cont. Class: Tallahassee Let

Phase Fund Code FY 2021 5 Year Total P.E. ACSU $150,000 $150,000 DDR $300,000 $300,000 Total For Project 410646.5 $450,000 $450,000

410646.6 SR 934/NE/NW 81/82 S T FROM WEST OF I-95(13 CT .) TO END OF SR 934/1 WAY PM: RAGHUNANDAN, RYAN City: MIAMI

Work Mix: Road Reconstruction - 2 Lane Extra Description: CONVERT 81ST/82ND STREET TO A TWO-LANE, TWO WAY FACILITY. SPLIT OUT FROM SEG 5 DURING FY2021-2025 DEVELOPMENT CYCLE NOTE: FEDERAL FUNDS ADDED NOT SIS FACILITY PER SIS MAP PER S. YEE FONG 7/25/19 Cont. Class: Tallahassee Let

Phase Fund Code FY 2021 5 Year Total P.E. ACSU $150,000 $150,000 DDR $300,000 $300,000 Total For Project 410646.6 $450,000 $450,000

418423.6 SR 826/PALMETTO EXPY FROM SR 968/W FLAGLER ST TO S OF NW 154 STREET PM: WANG, BAOYING City: HIALEAH - MEDLEY - MIAMI LAKES Work Mix: Pd&E/Emo Study Extra Description: PD & E STUDY FOR THE SR 826 'ULTIMATE' Cont. Class: Tallahassee Let

Phase Fund Code FY 2023 5 Year Total PDE DDR $6,000,000 $6,000,000 DIH $600,000 $600,000 Total For Project 418423.6 $6,600,000 $6,600,000

October. 10 2019 Page 17 of 151 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

423251.2 SR 25/OKEECHOBEE RD FROM BROWARD COUNTY LINE TO WEST OF HEFT PM: RIVEROL, ELSA Work Mix: Add Lanes & Reconstruct Extra Description: PROVIDE INTERSECTION IMPROVEMENTS AT KROME AVENUE AND AT NW 154 STREET. PROVIDE ACCESS MODIFICATIONS IN ORDER TO PROVIDE ADEQUATE ACCELERATION AND DECELERATION LANES IN ALL DIRECTIONS MPO PRIORITY ID# 9/FY 22 MPO PRIORITY PROJECTS LISTING SEE Cont. Class: Tallahassee Let MORE COMMENTS WP45

Phase Fund Code FY 2021 FY 2022 FY 2024 5 Year Total RW Land DDR $1,751,030 $1,751,030 RW Support DDR $34,000 $34,000 DIH $10,000 $10,000 Construction DI $46,981,648 $46,981,648 Incentive DS $3,000,000 $3,000,000 CEI DDR $66,110 $66,110 DI $1,948,196 $1,948,196 DIH $169,840 $169,840 Total For Project 423251.2 $1,795,030 $49,165,794 $3,000,000 $53,960,824

October. 10 2019 Page 18 of 151 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

423251.3 SR 25/OKEECHOBEE RD FROM EAST OF NW 87 AVE TO NW 79 AVE (CONCRETE) PM: WANG, BAOYING

Work Mix: Add Lanes & Reconstruct Extra Description: PROVIDE ONE ADDITIONAL THROUGH LANE IN EACH DIRECTION AND PROVIDE MORE AMPLE INTERSECTION TURNING RADIUS TO FACILITATE OPERATIONS AT INTERSECTIONS AT NW 95 STREET AND AT NW 79 AVE MPO PRIORITY ID# 9/FY 22 MPO PRIORITY PROJECTS LISTING LET Cont. Class: Tallahassee Let W/4365651 PH56-01 = TOWN OF MEDLEY ***SEE WP45**

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2025 5 Year Total RW Land BNIR $2,000,000 $4,000,000 $7,444,364 $13,444,364 DI $6,605,018 $6,605,018 DSBD $6,000,000 $1,394,982 $7,394,982 GFSN $260,961 $260,961 SN $369 $250,000 $50,000 $300,369 RW Support ACNP $496,416 $496,416 BNIR $200,000 $200,000 DDR $38,936 $38,936 DIH $50,000 $50,000 $44,000 $144,000 DS $14,986 $14,986 DSBD $160,808 $160,808 SN $361,064 $361,064 Construction ACNP $7,648,199 $7,648,199 DI $13,182,574 $13,182,574 LF $20,000 $20,000 STED $20,592,000 $20,592,000 CEI ACNP $3,294,376 $3,294,376 Total For Project 423251.3 $8,983,540 $12,700,000 $7,738,364 $44,737,149 $74,159,053

October. 10 2019 Page 19 of 151 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

423251.4 SR 25/OKEECHOBEE RD FROM E. OF NW 116 WAY TO E. OF NW 87 AVE(CONCRETE) PM: WANG, BAOYING City: HIALEAH GARDENS Work Mix: Add Lanes & Rehabilitate Pvmnt Extra Description: DEPRESS OKEECHOBEE RD MAINLINE UNDER NW 87 AVE & PROVIDEA SERVICE RD FOR THE LOCAL MOVEMENTS TO NW 87 AVE, REALIGN NW 103 FURTHER TO THE NORTH, PROVIDE NW 87 AVE SB LEFT TURN FLYOVER RAMP. PROVIDE NW 87 AVENUE NB LEFT TURN FLYOVER RAMP Cont. Class: Tallahassee Let RELOCATE THE NW 105 WAY BRIDGE FURTHER W. OF NW 106 ST. SEE WP45 FOR MORE COMMENTS / CNT#T6529 LEAD LET W/423251-8

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total RW Land ACNP $354,975 $69,480 $424,455 BNIR $12,512,720 $20,000,000 $5,000,000 $37,512,720 DDR $380,520 $380,520 SN $150,000 $150,000 RW Support ACNP $926,582 $251,715 $1,178,297 BNIR $360,318 $393,285 $416,000 $1,169,603 DIH $300,000 $400,000 $160,000 $860,000 Construction CFA $245,160,436 $245,160,436 DS $4,741,342 $4,741,342 LF $45,000 $45,000 SA $500,000 $500,000 CEI ACNP $17,219,180 $17,219,180 DIH $504,568 $504,568 DIS $11,440,000 $11,440,000 DS $1,029,600 $1,029,600 Total For Project 423251.4 $14,454,595 $21,495,000 $5,726,000 $45,000 $280,595,126 $322,315,721

423251.5 SR 25/OKEECHOBEE RD FROM E. OF NW 107 AVE TO E. OF NW 116 WAY(CNCRETE) PM: RIVEROL, ELSA City: HIALEAH GARDENS Work Mix: Add Lanes & Rehabilitate Pvmnt Extra Description: ELEVATE THROUGH LANES ALONG OKEECHOBEE RD OVER NW 116 WAY CONSTRUCT NW 116 WAY SOUTHBOUND LEFT TURN FLYOVER, CONSTRUCT SR 25 EASTBOUND NEW OFF RAMP FOR LOCAL ACCESS TO NW 116 WAY, CONSTRUCT NEW BRIDGE CROSSING OVER THE MIAMI CANAL FROM NW S. Cont. Class: Tallahassee Let RIVERDRIVE TO ACCESS OKEECHOBEE RD, PROVIDE INTERSEC. IMPROV. SEE WP45 SCREEN/MORE SCOPE B.WANG 1-25-16*

Phase Fund Code FY 2021 FY 2022 5 Year Total RW Support BNIR $300,000 $300,000 Construction ACNP $27,098,686 $27,098,686 DDR $850,000 $850,000 DS $700,000 $700,000 LF $743,701 $743,701 STED $82,120,000 $82,120,000 CEI ACNP $3,003,500 $3,003,500 DIH $665,978 $665,978 STED $7,000,000 $7,000,000 Total For Project 423251.5 $300,000 $122,181,865 $122,481,865

October. 10 2019 Page 20 of 151 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

423251.7 SR 25/OKEECHOBEE ROA D CORRIDOR REVIEW/PRELIMI NARY ENGINEERING PM: WANG, BAOYING City: HIALEAH GARDENS Work Mix: Preliminary Engineering Extra Description: PHASE 32-01 = AECOM/GC CONTRACT C9J68 DRAINAGE PHASE 32-02 = HDR/GC CONTRACT C9J67 Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 5 Year Total P.E. DS $300,000 $300,000 Total For Project 423251.7 $300,000 $300,000

424407.1 SR 968/SW 1ST STREET AT MIAMI RIVER (BRIDGE # 870660) PM: GOMEZ, HUMBERTO City: MIAMI Work Mix: Bridge Replacement Extra Description: NOTE: WORK MIX CHANGED FROM PD&E/EMO STUDY TO BRIDGE/ T-6433 REPLACEMENT ON 3-4-13 (OK PER H. DESDUNES) FROM WEST OF SW 5TH AVENUE TO SW 2ND AVENUE (PER G1 MEETING HELD 7/30/13) PH 32-02 = CONTROL SURVEY NEW BRIDGE# 871183. PH 56-01 = LUMP Cont. Class: Tallahassee Let SUM UTILITY-MDWASD $19,030 CK RECD #00656096 FHWA FULL OVERSIGHT (PODI).

Phase Fund Code FY 2022 5 Year Total Incentive ACBR $4,200,000 $4,200,000 Total For Project 424407.1 $4,200,000 $4,200,000

424407.2 SR 968/SW 1 STREET A T SW SOUTH RIVER DRIVE PM: SCHOT, KEVIN

Work Mix: Landscaping Extra Description: STANDALONE LANDSCAPING PROJECT MMOA WITH THE CITY OF MIAMI FOR ADDITIONAL ITEMS INCLUDING PLANTING AND IRRIGATION Cont. Class: District Let

Phase Fund Code FY 2023 5 Year Total Construction DS $389,729 $389,729 CEI DIH $6,486 $6,486 DS $77,832 $77,832 Total For Project 424407.2 $474,047 $474,047

October. 10 2019 Page 21 of 151 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

427369.1 SR 997/KROME AVENUE FROM SW 296 STREET TO S O F SW 232 STREET PM: BARRERA, JOSE Work Mix: Add Lanes & Reconstruct Extra Description: THIS PROJECT SPLIT OUT FROM 249614-4 (3 SEGMENTS) #T-6424 32-01=AERIALS/ROOKS C-8Z12, 32-02=SURVEY/ATKINS C-9705, 32- 03=CONTROL SURVEY & ROW MAPS/CSA CENTRAL, 32-04=TRIANGLE (SEE 4349301-6 FOR INTERIM RESURFACING) PH52-01=CNT# C9H49 56- Cont. Class: Tallahassee Let 01=MDWASD LUMP SUM UTILITY $6,160 CK RECD DATED 8-18-16 LEAD LET WITH 405575-9. ** SEE WP45 MORE COMMENTS **

Phase Fund Code FY 2021 FY 2022 FY 2023 5 Year Total RW Land DDR $4,199,073 $4,199,073 DS $1,000,000 $1,000,000 DSBD $3,343,801 $3,343,801 RW Support DDR $249,736 $249,736 DS $116,118 $116,118 Incentive ACNP $820,000 $820,000 DDR $980,000 $980,000 Total For Project 427369.1 $7,908,728 $1,800,000 $1,000,000 $10,708,728

427369.2 SR 997/KROME AVENUE FROM SW 232 STREET TO S O F SW 184TH ST/EUREKA DR. PM: WANG, BAOYING

Work Mix: Add Lanes & Reconstruct Extra Description: PRJT SPLIT OUT FROM FM 2496144 IN 3 SEGMNTS CNT#T6422 (LEAD) 32-01=AERIALS/ROOKS C-8Z12, 32-02=SURVEY/ATKINS C-9705, 32-03=ROW MAPS/BISCAYNE C9771 AUTOCAD CIVIL 3D PILOT PROJECT PH 32-05 & 52-02=SAFETY ADD ON APPRVD JULY 2016 SCOPING AT SW 192 STREET Cont. Class: Tallahassee Let TO INSTALL A TRAFFIC SIGNAL & FLASHING BEACONS RECONSTRUCT NW CORNER TURN APRON & SIGNING SEE WP45 MORE ++

Phase Fund Code FY 2021 5 Year Total RW Support BNIR $89,032 $89,032 DDR $300,000 $300,000 DS $67,635 $67,635 Incentive DDR $540,000 $540,000 DSBD $680,000 $680,000 Total For Project 427369.2 $1,676,667 $1,676,667

427369.3 SR 997/KROME AVENUE FROM SW 184 STREET TO SOU TH OF SW 136 STREET PM: PERDOMO, MARIA

Work Mix: Add Lanes & Reconstruct Extra Description: PRJT SPLIT OUT FROM 2496144 (3 SEGMNTS) T-6422 LT W/4273692 32-01 = AERIALS/ROOKS C-8Z12, 32-02=SURVEY/ATKINS C-9705, 32-03 = DESIGN/JACOBS C-9F61, 32-04=SURVEY & ROW MAPS C-9771 (SEE 4349301-6 FOR INTERIM RESURFACING) - LET W/427369-2 NOTE: 30 DAY Cont. Class: Tallahassee Let AD APPROVED BY BRIAN BLANCHARD 10-10-16 NOTE: PER LEIGH CANN 12-14-16, CHANGED BACK TO 60 DAY AD

Phase Fund Code FY 2021 5 Year Total Incentive DDR $220,000 $220,000 DSBD $680,000 $680,000 Total For Project 427369.3 $900,000 $900,000

October. 10 2019 Page 22 of 151 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

427518.2 SR 860/MIAMI GARDENS /NW 183 ST FROM E OF NW 5 7 AVE TO W OF NW 27 AVE PM: DE LA CRUZ, JOAQUIN City: MIAMI GARDENS Work Mix: Resurfacing Extra Description: RESURFACING CNT#T6486 (LEAD) LET W/4401811 APPROVED BY SCOPING COMMITTEE ON 7/27/16 / CANDIDATE #8 NOTE: EXCEPTION @ SR 847/NW 47TH AVENUE. SEE FM 430637-1 STRUNG W/440181-1 & 427518-3 PH32-02 = SAFETY (M. LEON)/PH32-03 = SAFETY LIGHTING Cont. Class: Tallahassee Let PH52 = SAFETY (M. LEON) UNDER 42751835201

Phase Fund Code FY 2021 FY 2022 5 Year Total Construction ACSS $167,738 $167,738 DDR $3,455,707 $3,455,707 LF $15,000 $15,000 SA $894,649 $894,649 Incentive SA $355,000 $355,000 CEI DDR $574,560 $574,560 DIH $161,082 $161,082 DS $97,436 $97,436 Total For Project 427518.2 $5,366,172 $355,000 $5,721,172

427518.3 SR 860/NW 183 STREET FROM WEST OF NW 57 AVE T O EAST OF NW 57 AVE PM: DE LA CRUZ, JOAQUIN Work Mix: Intersection Improvement Extra Description: MODIFY MEDIAN OPENING WEST OF NW 183 ST AND NW 57 AVE TO WESTBOUNTDIRECTIONAL MEDIAN OPENING. EXTEND EASTBOUND DUAL LEFT TURN LANES AT NW 183 STREET AND NW 57 AVENUE. LIGHTING IMPROVEMENTS B/C-32.2, NPV-$6,766,549,SHSP-INTERSECTION CRASHES, Cont. Class: Tallahassee Let SHAREPOINT# D6-205 DESIGN BEING ADDED UNDER SEG. 2 SEQ.02

Phase Fund Code FY 2021 FY 2022 5 Year Total Construction ACSS $224,734 $224,734 SA $123,631 $123,631 Incentive SA $15,000 $15,000 CEI ACSS $42,792 $42,792 SA $8,208 $8,208 Total For Project 427518.3 $399,365 $15,000 $414,365

October. 10 2019 Page 23 of 151 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

427521.2 SR 922/NE 125 ST FRO M SR 915/NE 6 AVENUE TO N E 7 AVENUE PM: RAGHUNANDAN, RYAN City: NORTH MIAMI Work Mix: Intersection Improvement Extra Description: B/C RATIO=2.3,NPV=1,003,049,SHSP=INTERS.CRASHES CNT#T6494 PROVIDE LEFT TURN ON EB AND WB APPROACHES, BACKPLATES, ELIMINATE ON-STREET PARKING. PROVIDE COUNTDOWN PEDESTRIAN HEAD AND SIGNAL TIMING IMPROVEMENTS. SAFETY APPROVED 9/17/13 BY JOE SANTOS. Cont. Class: Tallahassee Let PD&E STUDY UNDER 427521-1 LEAD PROJECT STRUNG W/4399761, 4399762

Phase Fund Code FY 2021 FY 2022 FY 2023 5 Year Total P.E. SA $10,000 $10,000 $20,000 RW Support SA $15,000 $15,000 Construction ACSS $3,073,138 $3,073,138 LF $5,405 $5,405 SA $10,000 $10,000 CEI ACSS $496,030 $496,030 DIH $162,150 $162,150 Total For Project 427521.2 $25,000 $20,000 $3,736,723 $3,781,723

428358.1 SR 826/PALMETTO EXPY - SR 826 EASTBOUND RAMP TO SR 9A/I-95 NORTHBOUND PM: BENITEZ, AURALIZ City: MIAMI GARDENS

Work Mix: Interchange Ramp (New) Extra Description: GOLDEN GLADES I/NEW RAMPS PH.1(INTERIM); LEAD LETTING/T-6413 NEW TWO (2) LANE RAMP FOR DIRECT SYSTEM TO SYSTEM CONNECTION FROM EASTBOUND SR 826 PALMETTO EXPRESSWAY TO NORTHBOUND I-95 PH31/32 FOR RFP PACKAGE IN 2014;PHASE 32-02=SURVEY/PHOTOGRAM Cont. Class: Tallahassee Let PH22-02= TPK TO PROGRAM AND FUND SA; SEE 4370531 SEE ALSO 4184231 & TPK FM#4233732/FHWA OVERSIGHT SEE WP45

Phase Fund Code FY 2021 FY 2022 5 Year Total RW Land DSBD $648,100 $200,000 $848,100 RW Support BNIR $50,000 $50,000 DIH $130,000 $50,000 $180,000 DS $32,000 $32,000 Total For Project 428358.1 $828,100 $282,000 $1,110,100

428358.4 GOLDEN GLADES INTERC HANGE VARIOUS RAMP IMPROV EMENTS PM: RAGHUNANDAN, RYAN City: MIAMI GARDENS Work Mix: Interchange Ramp (New) Extra Description: GOLDEN GLADES INTERCHANGE RAMPS RECONSTRUCTION SR 7/US 441 NORTHBOUND RECONSTRUCTION AND REALIGNMENT (INCLUDING CONNECTING RAMPS) SR 9 REALIGNMENT AND SR 826 CONNECTOR WIDENING/BRIDGE REPLACEMENT 870348 MOVED FROM SEG7 PER FABIANA 3- Cont. Class: Tallahassee Let 22-17 & ROADWAY ID'S S/B SAME FOR 437053-1 PH56-01 = REIMBURSABLE W/FPL PH60-96 = DIST. MATERIALS LAB

Phase Fund Code FY 2021 5 Year Total P.E. DDR $300,000 $300,000 DS $400,000 $400,000 Total For Project 428358.4 $700,000 $700,000

October. 10 2019 Page 24 of 151 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

428358.8 SR 826 CONNECTOR AT GOLDEN GLADES INTERCHG AN D VARIOUS RAMPS PM: BENITEZ, AURALIZ City: MIAMI GARDENS Work Mix: Add Lanes & Reconstruct Extra Description: RECONSTRUCTION OF SR 826 CONNECTOR TO NW 2ND AVENUE. T-6413 IMPROVEMENTS TO NW 2ND AVENUE AND NW 167TH STREET INTERSECT. REALIGNMENT OF SR 7/US 441 INTERNAL RAMPS WITHIN GGI. RECONSTRUCTION OF RAMP FROM SR 826 WESTBOUND TO I-95 SB. TO BE LET WITH Cont. Class: Tallahassee Let 428358-1 (LEAD)FHWA ID.OVST (PODI)6/15/2018 PH 57 = SEQ 01 FLAGGING (GEOTECH) & SEQ 02 RAILROAD

Phase Fund Code FY 2021 5 Year Total RW Land DDR $700,000 $700,000 DSBD $910,300 $910,300 RW Support DDR $80,212 $80,212 DS $28,555 $28,555 DSBD $56,652 $56,652 Total For Project 428358.8 $1,775,719 $1,775,719

428358.9 GOLDEN GLADES INTERC HANGE ENGINEERING SUPPORT PM: GONZALEZ, FABIANA Work Mix: Preliminary Engineering Extra Description: PH32-01 = OWNER REP Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 5 Year Total P.E. DIH $10,000 $10,000 Total For Project 428358.9 $10,000 $10,000

429185.2 SR 9/NW 27 AVENUE FR OM NW 39 STREET TO S OF N W 79 STREET PM: WANG, BAOYING

Work Mix: Resurfacing Extra Description: RESURFACING CNT# T6504 SCOPING COMMITTEE APPROVED ON 7/27/16 / CANDIDATE #11 CC=7 PER PRODUCTION 081616 (TV) FM 438076-1 SMART PLAN Cont. Class: Tallahassee Let

Phase Fund Code FY 2021 FY 2022 FY 2023 5 Year Total Construction DDR $1,564,026 $1,564,026 SA $3,773,508 $3,773,508 Incentive SA $360,000 $360,000 CEI DIH $151,632 $151,632 DS $608,634 $608,634 Total For Project 429185.2 $5,337,534 $760,266 $360,000 $6,457,800

October. 10 2019 Page 25 of 151 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

429185.3 SR 9/NW 27 AVENUE FR OM S OF SR 934/NW 79 ST T O N OF SR 932/NW 103 ST PM: FUNTANELLAS, IVETTE Work Mix: Drainage Improvements Extra Description: SCOPING COMMITTEE APPROVAL 10-12-16 CONTRACT #T6523 DRAINAGE IMPROVEMENTS TO INCLUDE RECONSTRUCTION OF 7-FEET AVERAGE PAVEMENT SILVER ALONG THE EDGE OF PAVEMENT, RECON- STRUCTION PEDESTRIAN RAMPS, SIDEWALKS, CURB & GUTTER, DRIVE- Cont. Class: Tallahassee Let WAYS, REGRADING OF SODDED UTILITY STRIPS, ADD NEW INLETS & FRENCH DRAINS, RESTORATION PAVEMENT MARKINGS & TRAFFIC LOOPS

Phase Fund Code FY 2021 5 Year Total Incentive DS $100,000 $100,000 Total For Project 429185.3 $100,000 $100,000

429186.3 SR 817/NW 27 AVENUE FROM SOUTH OF NW 203 ST T O NW 215 ST/COUNTY LINE PM: GOMEZ, HUMBERTO City: MIAMI GARDENS

Work Mix: Resurfacing Extra Description: NOTE: REVISIT PROJECT AFTER JULY 1ST 2018 TO POSSIBLY STRING WITH NEW SEGMENT 4 SAFETY PROJECT AS APPROVED IN SCOPING COMMITTEE. CNT#T6518 (LEAD) LET W/4291864 & 4291865 PH32-02 = SAFETY LIGHTING PH 56-01 = MDWSD LUMP SUM FOR VALVE AND Cont. Class: Tallahassee Let MANHOLE

Phase Fund Code FY 2022 5 Year Total Construction ACSS $48,013 $48,013 DDR $802,401 $802,401 DS $649,448 $649,448 LF $4,000 $4,000 SA $403,306 $403,306 CEI DDR $252,720 $252,720 DIH $63,180 $63,180 Total For Project 429186.3 $2,223,068 $2,223,068

429186.4 SR 817/NW 27 AVENUE @ NW 207 STREET PM: GOMEZ, HUMBERTO City: MIAMI GARDENS

Work Mix: Intersection Improvement Extra Description: NEW SAFETY PROJECT - APPROVED FINAL SCOPING MEETING 7-25-17 B/C = 12.3, NPV = $5,653,755.12 CNT#T6518 LET W/4291863 (LEAD) & 4291865 Cont. Class: Tallahassee Let

Phase Fund Code FY 2021 FY 2022 5 Year Total Construction ACSS $313,317 $313,317 DS $25,650 $25,650 CEI ACSS $61,560 $61,560 DS $10,530 $10,530 SA $10,260 $10,260 Total For Project 429186.4 $410,787 $10,530 $421,317

October. 10 2019 Page 26 of 151 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

429186.5 SR 817/NW 27 AVE AT NW 195TH BLOCK PM: GOMEZ, HUMBERTO City: MIAMI GARDENS Work Mix: Intersection Improvement Extra Description: SR 817/NW 27 AVE AT 1224' NORTH OF NW 191 STREET (WALMART NORTHEND ENTRANCE) INSTALL A TRAFFIC SIGNAL AT THE NORTHEND OF WALMART. PROVIDE HIGH EMPHASIS CROSSWALKS AND COUNTDOWN TYPE PEDESTRIAN SIGNALS ON ALL LEGS. B/C-2.3, NPV $422,293 SHSP- Cont. Class: Tallahassee Let VULNARABLE ROAD USERS & INTERSECTION CRASHES. SHAREPOINT#D6-203 CNT#T6518 LET W/4291863 (LEAD) & 4291864

Phase Fund Code FY 2021 FY 2022 5 Year Total RW Land ACSS $100,000 $100,000 SA $50,000 $50,000 $100,000 RW Support ACSS $36,000 $36,000 SA $44,000 $45,000 $89,000 Construction ACSS $904,246 $904,246 CEI ACSS $150,469 $150,469 SA $31,590 $31,590 Total For Project 429186.5 $230,000 $1,181,305 $1,411,305

429193.1 SR 907/ALTON ROAD FR OM MICHIGAN AVENUE TO S O F ED SULLIVAN DR/43 ST PM: GARGANTA, NATALIE City: MIAMI BEACH

Work Mix: Flexible Pavement Reconstruct. Extra Description: LEAVE REMAINING HSP FUNDS ON 32-02 PER A. ARVELO FUNDS WILL BE AUTH IN STAGES/32-05 = ADA ENG.CNT#T6398 (LEAD)STRUNG W/4291931/ 32-01 = C9042/METRIC RESURF./32-06 = EAC CONSULT 32-02 = C9042/METRIC SAFETY DESIGN ON 429193-2 32-03 = C9007/KEITH Cont. Class: Tallahassee Let & SCHNARS (GC) LANDSCAPING SEG. 2 SAFETY 32-04 = C9A45/CSA(DRAIN. REPORT) 32-07=AECOM (GEC) C-9J68

Phase Fund Code FY 2021 FY 2025 5 Year Total Construction DDR $11,407,077 $11,407,077 DS $674,652 $674,652 LF $3,129,672 $3,129,672 SA $5,602,980 $5,602,980 CEI DDR $3,493,776 $3,493,776 DIH $102,960 $102,960 ENV DS $25,000 $25,000 Total For Project 429193.1 $25,000 $24,411,117 $24,436,117

429193.3 SR 907/ALTON ROAD FR OM N. OF WEST 48 STREET T O E. OF ALLISON ROAD PM: SCHOT, KEVIN City: MIAMI BEACH Work Mix: Landscaping Extra Description: STANDALONE LANDSCAPING PROJECTW/IRRIGATION SYSTEM REQUIRED MMOA AMENDMENT W/CITY FOLLOWING FM 4304442 (CST PROJECT) Cont. Class: District Let

Phase Fund Code FY 2025 5 Year Total P.E. DIH $20,000 $20,000 DS $250,000 $250,000 Total For Project 429193.3 $270,000 $270,000

October. 10 2019 Page 27 of 151 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

429193.4 SR 907/ALTON ROAD FR OM S OF 43 STREET TO N OF WEST 48 STREET PM: SCHOT, KEVIN City: MIAMI BEACH Work Mix: Landscaping Extra Description: STANDALONE LANDSCAPING PROJECTW/IRRIGATION SYSTEM REQUIRES MMOA WITH THE CITY FOLLOWING FM 4304441 (CST PROJECT) Cont. Class: District Let

Phase Fund Code FY 2025 5 Year Total P.E. DIH $20,000 $20,000 DS $150,000 $150,000 Total For Project 429193.4 $170,000 $170,000

429193.5 SR 907/ALTON ROAD FR OM MICHIGAN AVENUE TO S O F 43 STREET PM: SCHOT, KEVIN City: MIAMI BEACH

Work Mix: Landscaping Extra Description: STANDALONE LANDSCAPING PROJECT W/IRRIGATION SYSTEM REQUIRES MMOA WITH THE CITY FOLLOWING FM 4291931 (CST PROJECT) Cont. Class: District Let

Phase Fund Code FY 2025 5 Year Total P.E. DIH $20,000 $20,000 DS $80,000 $80,000 Total For Project 429193.5 $100,000 $100,000

429300.4 SR 925/NW 3RD COURT & NW 3RD AVENUE FROM NW 1 ST STREET TO NW 8TH ST PM: WANG, BAOYING City: MIAMI

Work Mix: Resurfacing Extra Description: PAVEMENT RECONSTRUCTION PROJECT WHICH INCLUDES PORTION OF RAMPS 87270173, 87270503, AND 87270504. SB SIDE (NW 3RD COURT) CRACK AND RIDE DEFICIENT AND THE NB SIDE (NW 3RD AVE) RIDE IS DEFICIENT ON THE I-95 FRONTAGE ROADS. CNT# Cont. Class: Tallahassee Let T6469 PH 56-01 = MDWASA-CHECK REC'D 7/23/2019 $14,520 XENIA R.

Phase Fund Code FY 2021 5 Year Total Incentive DDR $220,000 $220,000 Total For Project 429300.4 $220,000 $220,000

October. 10 2019 Page 28 of 151 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

429341.2 SR 994/QUAIL ROOST/S W 186 ST FROM EAST OF HEF T TO US 1/S. DIXIE HWY PM: RIVEROL, ELSA

Work Mix: Resurfacing Extra Description: RESURFACING CNT# T6506 APPROVED BY SCOPING COMMITTEE ON 7/27/16 / CANDIDATE #5 TO BE LET WITH 429341-4 (DESIGN TO BE ADV. WITH SEGMENT 4) PH56-01 = LUMP SUM JPA VALVE AND MANHOLE ADJUSTMENT PAYMENT CHK# 00704467 RECV 8/1/19 FROM Cont. Class: Tallahassee Let MDWS IN THE AMT OF $16,885.

Phase Fund Code FY 2021 FY 2023 5 Year Total Construction DDR $852,755 $852,755 LF $16,885 $16,885 SA $513,000 $513,000 Incentive SA $120,000 $120,000 CEI DIH $70,794 $70,794 DS $239,863 $239,863 Total For Project 429341.2 $1,693,297 $120,000 $1,813,297

429341.3 SR 994/QUAIL ROOST F ROM WEST OF SW 127 AVE TO WEST OF SW 113 AVE PM: RIVEROL, ELSA

Work Mix: Resurfacing Extra Description: RESURFACING CNT# T6506 APPROVED BY SCOPING COMMITTEE ON 7/27/16 / CANDIDATE #6 ** NOTE: JULY 1ST ADD PH 52-02 FOR TRAFFIC SIGNAL ON QUAIL ROOST AT SW 200 ST (MP 5.304 TO 5.403 W/IN PROJECT LIMITS) APPROVED BY SCOPING COMMITTEE OCTOBER Cont. Class: Tallahassee Let 2016. TO BE LET WITH 429341-5/DESIGN TO BE ADVERTISED W/SEGMENT 5

Phase Fund Code FY 2021 FY 2023 5 Year Total Construction ACSS $163,478 $163,478 DDR $179,304 $179,304 DS $1,357,783 $1,357,783 LF $28,380 $28,380 SA $1,183,608 $1,183,608 Incentive SA $200,000 $200,000 CEI DDR $365,256 $365,256 DIH $90,288 $90,288 DS $32,011 $32,011 Total For Project 429341.3 $3,400,108 $200,000 $3,600,108

October. 10 2019 Page 29 of 151 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

429341.4 SR 994/QUAIL ROOST A T HOMESTEAD AVENUE PM: RIVEROL, ELSA Work Mix: Intersection Improvement Extra Description: NEW SAFETY PROJECT (SEE SCOPING COMMITTEE MEETING 6-14-17) B/C = 11.9 TO BE LET WITH 429341-2 (DESIGN TO BE ADV. WITH SEGMENT 2) CNT# T6506 Cont. Class: Tallahassee Let

Phase Fund Code FY 2021 5 Year Total Construction ACSS $59,323 $59,323 DS $5,130 $5,130 CEI ACSS $8,208 $8,208 DIH $7,182 $7,182 DS $10,260 $10,260 Total For Project 429341.4 $90,103 $90,103

429341.5 SR 994/QUAIL ROOST A T SW 122 AVENUE & SW 117 AVENUE PM: RIVEROL, ELSA

Work Mix: Intersection Improvement Extra Description: NEW SAFETY PROJECT (SEE SCOPING COMMITTEE MEETING 7-17-17) B/C = 5.1 (117 AVENUE) AND B/C = 4.8 (SW 122 AVENUE) TO BE LET WITH 429341-3/DESIGN TO BE ADVERTISED W/SEGMENT 3 CNT# T6506 Cont. Class: Tallahassee Let

Phase Fund Code FY 2021 FY 2023 5 Year Total Construction ACSS $377,172 $377,172 DS $72,603 $72,603 Incentive DS $25,000 $25,000 CEI ACSS $50,274 $50,274 DIH $18,468 $18,468 DS $10,260 $10,260 Total For Project 429341.5 $528,777 $25,000 $553,777

429341.7 SR 994/QUAIL ROOST D R FROM MIAMI-DADE TRANSIT BUSWAY TO US-1 PM: CARTAYA, NILIA Work Mix: Pedestrian Safety Improvement Extra Description: DFA WITH MIAMI-DADE COUNTY THE LIMITS OF THIS PROJECT WERE REMOVED FROM 429341-2 AND ABSORBED BY MIAMI-DADE COUNTY. THE SCOPE WILL BE COMPLETED VIA THE SMART PLAN SOUTH COORIDOR PROJECT. Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2021 5 Year Total JPA/LAP Construction DDR $274,577 $274,577 Total For Project 429341.7 $274,577 $274,577

October. 10 2019 Page 30 of 151 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

429345.3 SR 969/MILAM DAIRY R D/NW 72 AVE FROM N OF W F LAGLER ST TO S OF NW 7 ST PM: RIVEROL, ELSA Work Mix: Resurfacing Extra Description: RESURFACING CNT# T6524 SCOPING COMMITTEE APPROVED ON 7/27/16 / CANDIDATE #9 INCLUDES BRIDGE 870655 OVER TAMIAMI CANAL PH56-01 = MDWSD LUMPSUM FOR VALVE AND MANHOLE Cont. Class: Tallahassee Let

Phase Fund Code FY 2021 5 Year Total Construction DS $38,792 $38,792 LF $20,000 $20,000 SA $546,247 $546,247 CEI DIH $75,924 $75,924 DS $124,146 $124,146 Total For Project 429345.3 $805,109 $805,109

429346.4 SR 916/NW/NE 135 ST FROM NW 6 AVE TO SR 5/US- 1/BISCAYNE BOULEVARD PM: SCHOT, KEVIN City: NORTH MIAMI

Work Mix: Landscaping Extra Description: STANDALONE LANDSCAPE FOLLOWING FM 429346-1 (RRR) CNT# E6M55 Cont. Class: District Let

Phase Fund Code FY 2023 5 Year Total Construction DDR $973,354 $973,354 CEI DDR $73,002 $73,002 DIH $77,832 $77,832 DS $146,003 $146,003 Total For Project 429346.4 $1,270,191 $1,270,191

October. 10 2019 Page 31 of 151 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

430444.1 SR 907/ALTON ROAD FR OM S. OF 43RD STREET TO N . OF WEST 48TH STREET PM: GOMEZ, HUMBERTO City: MIAMI BEACH

Work Mix: Flexible Pavement Reconstruct. Extra Description: CONTRACT #T-6397 ORIGINAL PROJECT LIMITS SPLIT TO NEW SEGMENT 2 ON 7-27-16 AS RECOMMENDED BY CONST. AND APPROVED BY H. DESDUNES 3-22-16 PHASE 32-02 & 56-01 = UTILITY JPA WITH CITY OF MIAMI BEACH PH 32 = $386,772 CHECK REC'D DATED 2-9-17 PH 52-03 = Cont. Class: Tallahassee Let LFA FOR ITS PAY ITEMS (DDR/LF SPLIT)

Phase Fund Code FY 2021 FY 2025 5 Year Total RW Land DDR $2,000,000 $2,000,000 RW Support DDR $100,000 $100,000 DIH $50,000 $50,000 Construction DDR $11,043,403 $11,043,403 DS $321,859 $321,859 LF $1,576,361 $1,576,361 SA $3,395,195 $3,395,195 CEI DDR $2,116,400 $2,116,400 DIH $221,848 $221,848 ENV DS $25,000 $25,000 Total For Project 430444.1 $2,175,000 $18,675,066 $20,850,066

430637.1 SR 847/NW 47 AVENUE FROM SR 860/NW 183 STREET TO N. OF NW 199 STREET PM: FUENTES, KARINA Work Mix: Add Lanes & Reconstruct Extra Description: NOTE: BRIDGE WIDENING FOR BRIDGE #870053 MPO #2 CNT# T-6427 STUDY EXTENDS APPROX 1000' INTO BROWARD COUNTY DUE TO LOGICAL TERMINUS/ PD&E FOR 2L TO 4L (SEE ALSO 4309071) PH 32-01=STRUCTURES DESIGN; MAIN DESIGN=IN-HOUSE 60 DAY AD PH 32-02=ROW Cont. Class: Tallahassee Let CONTROL MAPS, PH 32-03=DRAINAGE ANALYSIS/C9330 ****SEE NEW SEGMENT 3/LIMITS SPLIT 7-12-16 PER MARCH SCOPING

Phase Fund Code FY 2021 5 Year Total Incentive DDR $1,120,000 $1,120,000 Total For Project 430637.1 $1,120,000 $1,120,000

430637.2 SR 847/NW 47 AVE FRO M SR 860/NW 183 STREET TO PREMIER PKWY (BROWARD) PM: SCHOT, KEVIN City: MIAMI GARDENS

Work Mix: Landscaping Extra Description: STAND ALONE LANDSCAPING TO FOLLOW NEW ROADWAY CONSTRUCTION PRIOR TO TURNING ROADWAY OVER TO THE COUNTY CNT# E6M51 Cont. Class: District Let

Phase Fund Code FY 2021 5 Year Total Construction DS $513,143 $513,143 CEI DIH $60,534 $60,534 DS $87,210 $87,210 Total For Project 430637.2 $660,887 $660,887

October. 10 2019 Page 32 of 151 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

430637.3 SR 847/NW 47 AVENUE FROM N. OF NW 199 STREET TO PREMIER PKY (BROWARD) PM: FUENTES, KARINA City: MIAMI GARDENS Work Mix: Add Lanes & Reconstruct Extra Description: ORIGINAL LIMITS SPLIT FROM SEGMENT 1 ON 7-12-16 CNT#T-6442 PER KARINA FUENTES APPROVED BY SCOPING COMMITTEE ON 3-16-16 TO REDUCE CONSTRUCTION TIME & MINIMIZE IMPACTS TO THE PUBLIC SEG. 1 ENDS AT N. OF 206 TERRACE. STUDY EXTENDS APPROX 1000' INTO Cont. Class: Tallahassee Let BROWARD CO. DUE TO LOGICAL TERMINUS/PD&E FOR 2L TO 4L (SEE ALSO 4309071). PH 56=MIAMI DADE WATER/CK RECD. SEE WP45

Phase Fund Code FY 2021 5 Year Total Incentive SU $790,000 $790,000 Total For Project 430637.3 $790,000 $790,000

430813.2 SR A1A/COLLINS AVE A ND INDIAN CREEK DR FROM 5 800 BLOCK TO SR 907/63 ST PM: ARVELO, ANA City: MIAMI BEACH

Work Mix: Resurfacing Extra Description: RIDE ONLY PROJECT Cont. Class: Tallahassee Let

Phase Fund Code FY 2022 5 Year Total Construction DDR $696,920 $696,920 CEI DDR $116,125 $116,125 DIH $43,173 $43,173 Total For Project 430813.2 $856,218 $856,218

430817.3 SR 7/US 441/NW 7 AVE FROM LITTLE RIVER DR TO SOUTH OF NW 117 STREET PM: GARGANTA, NATALIE Work Mix: Resurfacing Extra Description: DESIGNED IN HOUSE CONTRACT T6460 (LET WITH LEAD PROJECT 430817-4) PHASE 56-01 = LUMP SUM UTILITY W/MDWASD FOR VALVE & MANHOLE ADJUSTMENTS. CHECK RECEIVED #00659803 DATED 12-5-17. NOTE: GAME CANIDATE PHASE 56 ON JULY 1ST 2018 COMPLETE STREETS Cont. Class: Tallahassee Let PROJECT

Phase Fund Code FY 2021 FY 2022 5 Year Total Incentive DDR $240,000 $240,000 CEI DDR $420,661 $420,661 Total For Project 430817.3 $420,661 $240,000 $660,661

430817.4 SR 7/US 441/NW 7 AVE FROM S. OF NW 117 STREET TO S. OF BISCAYNE CANAL PM: GARGANTA, NATALIE City: NORTH MIAMI

Work Mix: Resurfacing Extra Description: DESIGNED IN HOUSE. CONTRACT T6460 (LET WITH 430817-3) D6-152 & D6-153/NEW SAFETY APPRVD SCOPING COMMITTEE 8-12-16 SAFETY PROJECT APPROVED BY C.O. ON 10-6-16 PH 56-01 = MDWASA COMPLETE STREETS PROJECT Cont. Class: Tallahassee Let

Phase Fund Code FY 2021 FY 2022 5 Year Total Incentive DDR $340,000 $340,000 CEI ACSS $88,906 $88,906 DDR $551,318 $551,318 Total For Project 430817.4 $640,224 $340,000 $980,224

October. 10 2019 Page 33 of 151 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

430949.2 SR A1A/COLLINS AVE F ROM NORTH OF HAULOVER INL ET TO SOUTH OF BAYVIEW DR PM: FUNTANELLAS, IVETTE City: SUNNY ISLES Work Mix: Resurfacing Extra Description: CNT# **SEE WP45** DO NOT FEDERALIZE** APPROVED BY SCOPING COMMITTEE ON 7/27/16/CANDIDATE #4 NOTE: ADDT'L SCOPE MAY BE ADDED TO PROJECT AT A LATER DATE (PARTIAL RECST FOR BASE CLEARANCE, WIDENING FOR BIKE LANES, CONSTRUCT NEW DRAINAGE SYSTEM, Cont. Class: District Let CONSTRUCT NEW SIDEWALK, RECONSTRUCT LIGHT SYSTEM & UPGRADE OF ROADSIDE GUARDRAIL)

Phase Fund Code FY 2021 FY 2022 FY 2023 5 Year Total P.E. DIH $5,000 $5,000 $10,000 RW Land DS $991,600 $400,000 $1,391,600 RW Support DDR $15,000 $15,000 DIH $2,000 $1,000 $3,000 DS $25,000 $25,000 Construction DDR $5,037,581 $5,037,581 DS $100,000 $100,000 LF $7,000 $7,000 Incentive DS $330,000 $330,000 CEI DDR $781,326 $781,326 DIH $148,473 $148,473 Total For Project 430949.2 $1,123,600 $6,395,380 $330,000 $7,848,980

431433.3 TRAFFIC OPERATIONS P USH BUTTON - ROADS MIAMI- DADE COUNTY PM: KHAN, SAUD

Work Mix: Miscellaneous Construction Extra Description: CNT# E6M53 Cont. Class: District Let

Phase Fund Code FY 2021 5 Year Total Construction DS $1,000,000 $1,000,000 CEI DIH $147,744 $147,744 DS $184,680 $184,680 Total For Project 431433.3 $1,332,424 $1,332,424

431433.5 MIAMI-DADE PEDESTRIA N & BICYCLE SAFETY PUSHBU TTON CONTRACT PM: KHAN, SAUD Work Mix: Miscellaneous Construction Extra Description: CNT#E6M00 Cont. Class: District Let

Phase Fund Code FY 2021 5 Year Total CEI DIH $147,744 $147,744 Total For Project 431433.5 $147,744 $147,744

October. 10 2019 Page 34 of 151 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

431433.7 MIAMI-DADE PEDESTRIA N & BICYCLE SAFETY PUSHBU TTON CONTRACT PM: KHAN, SAUD Work Mix: Miscellaneous Construction Extra Description: Cont. Class: District Let

Phase Fund Code FY 2021 5 Year Total Construction DS $1,000,000 $1,000,000 CEI DIH $116,451 $116,451 DS $180,000 $180,000 Total For Project 431433.7 $1,296,451 $1,296,451

431433.8 TRAFFIC OPERATIONS P USHBUTTON SIGNALS IN MIAM I-DADE COUNTY PM: KHAN, SAUD

Work Mix: Miscellaneous Construction Extra Description: NEW PROJECT # FM 446263-1 Cont. Class: District Let

Phase Fund Code FY 2023 5 Year Total Construction DS $1,000,000 $1,000,000 CEI DS $180,001 $180,001 Total For Project 431433.8 $1,180,001 $1,180,001

431434.3 TRAFFIC OPERATIONS P USH BUTTON - SIGNALS MIAM I-DADE COUNTY PM: KHAN, SAUD

Work Mix: Miscellaneous Construction Extra Description: CNT# E6M54 Cont. Class: District Let

Phase Fund Code FY 2021 5 Year Total CEI DIH $147,744 $147,744 Total For Project 431434.3 $147,744 $147,744

431434.5 TRAFFIC OPERATIONS P USHBUTTON SIGNALS IN MIAM I-DADE COUNTY PM: KHAN, SAUD Work Mix: Miscellaneous Construction Extra Description: Cont. Class: District Let

Phase Fund Code FY 2021 FY 2023 5 Year Total Construction DS $1,000,000 $1,000,000 CEI DIH $109,782 $109,782 DS $180,001 $180,001 Total For Project 431434.5 $109,782 $1,180,001 $1,289,783

October. 10 2019 Page 35 of 151 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

432639.1 SR 826/PALMETTO EXPY FROM US-1/S. DIXIE HWY T O SR 836/DOLPHIN XWAY PM: QUINTELA, RAUL City: PINECREST Work Mix: Prelim Eng For Future Capacity Extra Description: PH2201=PLANNING STUDY AND CONCEPTUAL ENGINEERING TO EVALUATE EXPRESS LANES ALTERNATIVES ON SR 826 FROM SR 836 TO US-1 PH2202= ACTUAL PD&E STUDY WORK MIX CHANGE REQUEST FROM L. CANN ON 8/12/19 FROM 9980 TO 9982 APPROV. BY CO & B. CASKEY Cont. Class: Design Build

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 5 Year Total P.E. ACNP $8,000,000 $8,000,000 RW Land ACNP $16,748,070 $32,500,000 $1,000,000 $50,248,070 BNIR $30,000,000 $30,000,000 RW Support ACNP $1,065,000 $1,900,000 $1,277,795 $4,242,795 Construction ACNP $117,609,135 $117,609,135 DI $44,440,000 $44,440,000 DSBD $408,839,865 $408,839,865 STED $38,885,000 $38,885,000 CEI ACNP $64,606,592 $64,606,592 Total For Project 432639.1 $25,813,070 $34,400,000 $32,277,795 $674,380,592 $766,871,457

432748.4 SR 933/NW 12 AVENUE FROM S. OF NW 20 STREET T O N. OF NW 29 STREET PM: DE LA CRUZ, JOAQUIN City: MIAMI

Work Mix: Resurfacing - Ride Only Extra Description: RIDE ONLY PRJT RIDE RATING = 4.8 / RIDE 3.9 NOTE: BDI CONTRACT PER LEIGH,APPR. BY ANGELA MATIYOW 1-11-18 PH32-02=SAFETY DESIGN AT VARIOUS LOCATIONS. SEE WP45 FOR VARIOUS INTERSECTIONS/CST & ROW DONE UNDER 432748-5. LEAD STRUNG W/432748-5 & Cont. Class: Tallahassee Let 4425381

Phase Fund Code FY 2021 FY 2022 FY 2023 5 Year Total RW Land DS $180,100 $180,100 RW Support DDR $20,000 $20,000 DIH $10,000 $8,000 $18,000 DS $8,000 $8,000 Construction DDR $1,261,693 $1,261,693 DS $5,000 $5,000 SA $372,367 $372,367 Incentive SA $80,000 $80,000 CEI DDR $205,335 $205,335 DIH $64,233 $64,233 Total For Project 432748.4 $210,100 $1,924,628 $80,000 $2,214,728

October. 10 2019 Page 36 of 151 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

432748.5 SR 933/NW 12 AVENUE AT VARIOUS LOCATIONS PM: DE LA CRUZ, JOAQUIN City: MIAMI Work Mix: Intersection Improvement Extra Description: SR 933/NW 12 AVE @ NW 20 AVE (BMP 2.976-3.052) SR 933/NW 12 AVE @ NW 22 ST (MP 3.204) SR 933/NW 12 AVE FROM NW 23 ST TO NW 24 ST (MP 3.272-3.336) SR 933/NW 12 AVE @ NW 28 ST (MP 3.522) SR 933/NW 12 AVE @ NW 29 ST (MP 3.591) B/C-6.1, NPV-$3,623,045.92, & SHSP- Cont. Class: Tallahassee Let INTRSEC. CRASHES &VULINE

Phase Fund Code FY 2022 FY 2023 5 Year Total Construction ACSS $324,588 $324,588 Incentive SA $16,000 $16,000 CEI ACSS $46,535 $46,535 SA $12,636 $12,636 Total For Project 432748.5 $383,759 $16,000 $399,759

433264.2 SR 94/KENDALL DR/SW 88 ST FROM E. OF SW 132 A VE TO SW 122 AVE PM: FUNTANELLAS, IVETTE

Work Mix: Resurfacing Extra Description: THIS PROJECT IS BEING SPLIT WITH FM 4332643 CNT# T6473 BDID APPROVED BY CARLA PERRY 1-30-17 NOTE: REF FM 4377841 KENDALL BRT PHASE 56-01 = LUMP SUM UTILITY W/MDWASD Cont. Class: Tallahassee Let

Phase Fund Code FY 2021 5 Year Total Incentive SA $100,000 $100,000 Total For Project 433264.2 $100,000 $100,000

433264.3 SR 94/KENDALL DR/SW 88 ST FROM E. OF SW 150 A VE TO E. OF SW 132 AVE PM: FUNTANELLAS, IVETTE Work Mix: Resurfacing Extra Description: THIS PROJECT IS A SPLIT FM 4332642. LEAD LET W/4332644 ALSO SEE PLANNING STUDY FM 434845-3 AND BRT STUDY FM 4377841 PHASE 52-02 = SAFETY PROJECT D6-148 APPROVED BY C.O. 10-6-16 SAFETY LOCATION IS KENDALL DR. AT SW 147 AVENUE. B/C = 19.7 NPV = $141,733.45/SHSP = Cont. Class: Tallahassee Let INTERSECTION CRASHES OFFSET EB & WB LEFT TURN LANES & REALIGN (T6505) *SEE WP45*

Phase Fund Code FY 2021 FY 2022 5 Year Total Construction ACSS $114,723 $114,723 DDR $1,264,982 $1,264,982 SA $4,616,107 $4,616,107 Incentive SA $390,000 $390,000 CEI ACSS $162,107 $162,107 DDR $560,197 $560,197 DIH $149,796 $149,796 DS $10,260 $10,260 Total For Project 433264.3 $6,878,172 $390,000 $7,268,172

October. 10 2019 Page 37 of 151 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

433264.4 SR 94/KENDALL DR/SW 88 ST MEDIAN MOD. BETWEEN SW 149 AVE & SW 147 AVE PM: FUNTANELLAS, IVETTE Work Mix: Intersection Improvement Extra Description: NEW SAFETY PROJECT (SEE SCOPING COMMITTEE MEETING 6-14-17) B/C = 19.2 (SW 149 AVE TO SW 147 AVE), NPV = $141,503.29 TO BE LET WITH 4332643 CNT #T6505 Cont. Class: Tallahassee Let

Phase Fund Code FY 2021 FY 2022 5 Year Total Construction GFSA $12,686 $12,686 LF $5,000 $5,000 SA $286,266 $286,266 Incentive SA $10,000 $10,000 CEI ACSS $18,468 $18,468 DIH $8,208 $8,208 Total For Project 433264.4 $330,628 $10,000 $340,628

433455.3 SR 5/US-1/S. DIXIE H WY FROM RIVIERA DR. TO SW 27 AVE (WITH EXCEPTION) PM: DE LA CRUZ, JOAQUIN City: MIAMI - CORAL GABELS

Work Mix: Resurfacing Extra Description: EXCEPTION FROM PONCE DE LEON BLVD (MP 5.054) TO SW 37 AVENUE /DOUGLAS ROAD (MP 5.395) CONTRACT T6465 PH 56-01 = UTILITY W/MDWASD FOR MANHOLE/VALVE ADJUSTMENTS CHK# 00684064 RECIEVED ON 10/16/2018 FOR $14,355 FOR MDWS PH 56-02 = ILLUMINATION Cont. Class: Tallahassee Let AGREEMENT/FPL

Phase Fund Code FY 2021 5 Year Total Incentive DDR $170,000 $170,000 Total For Project 433455.3 $170,000 $170,000

434768.3 SR 932/NW 103 STREET /49 STREET FROM WEST 3 AV ENUE TO EAST 10 AVENUE PM: RIVEROL, ELSA City: HIALEAH Work Mix: Resurfacing Extra Description: RESURFACING CNT# APPROVED BY SCOPING COMMITTEE ON 7/27/16 / CANDIDATE #13 LEAD PROJET STRUNG W/4347684. Cont. Class: Tallahassee Let

Phase Fund Code FY 2022 FY 2023 5 Year Total Construction DDR $1,198,207 $1,198,207 DS $1,144,633 $1,144,633 SA $2,886 $2,886 Incentive SA $140,000 $140,000 CEI DIH $74,763 $74,763 DS $226,395 $226,395 SA $57,915 $57,915 Total For Project 434768.3 $2,704,799 $140,000 $2,844,799

October. 10 2019 Page 38 of 151 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

434768.4 SR 932/NW 103 STREET /W 49 ST AND LEJEUNE ROAD /E. 8TH AVENUE PM: RIVEROL, ELSA Work Mix: Intersection Improvement Extra Description: NEW SAFETY PROJECT TO BE LET WITH SEGMENT 3. CNT# APPROVED SCOPING COMMITTEE. B/C=15.6, NPV = $9,930,341 SCOPE: MODIFY LEFT TURN PHASING FOR NB & SB APPROACHES TO PROTECTED ONLY PHASING. INSTALL BACKPLATES & ADDITIONAL SIG- NAL HEAD PER LANE Cont. Class: Tallahassee Let ON ALL APPROACHES. MODIFY LANE CONFIG. OF SB EXCLUSIVE RIGHT TURN LANE TO A SHARED THROUGH & RIGHT. --

Phase Fund Code FY 2021 FY 2022 FY 2023 5 Year Total RW Land DDR $100,000 $100,000 DS $800,000 $800,000 RW Support DIH $25,000 $5,000 $30,000 DS $60,000 $40,000 $100,000 Construction ACSS $637,041 $637,041 DS $61,706 $61,706 Incentive SA $40,000 $40,000 CEI ACSS $81,224 $81,224 DIH $22,113 $22,113 DS $10,530 $10,530 Total For Project 434768.4 $885,000 $957,614 $40,000 $1,882,614

435506.3 SR 90 ASCT PILOT PRO JECT OPERATION OF M-D COU NTY TRAF SIGNAL FACILITY PM: MOTTA, ALEJANDRO

Work Mix: Traffic Signal Update Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 5 Year Total Capital Improvement/Operating DS $600,000 $600,000 Total For Project 435506.3 $600,000 $600,000

435506.4 DISTRICTWIDE ACTIVE ARTERIAL MANAGEMENT SERVI CES PM: MOTTA, ALEJANDRO

Work Mix: Traffic Signal Update Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total Capital Improvement/Operating DS $630,000 $630,000 $630,000 $630,000 $2,520,000 Total For Project 435506.4 $630,000 $630,000 $630,000 $630,000 $2,520,000

October. 10 2019 Page 39 of 151 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

435760.1 SR 826/PALMETTO EXPY FROM I-75 TO N.OF CANAL C-8 BRDG(APPROX NW 162ST) PM: QUINTELA, RAUL City: HIALEAH - MIAMI LAKES Work Mix: Add Lanes & Reconstruct Extra Description: WIDENING OF THE MAINLINE INCLUDING MILLING & RESURFACING THE MAINLINE & WIDENING OF EXISTING BRDG OVER NW 157 ST. PROJECT INCLUDES NEW BRAIDED RAMP FROM EB I-75 TO NB SR 826 & MODS. TO NW 154 ST INTERCHG & NEW SB SR 826/PALMETTO Cont. Class: Tallahassee Let RAMP TO NW 154 ST & I-75 THAT INCLUDES NEW 2 LANE BDG OVER NW 154. *SEE WP45*REMINDER: NEED TO ADD RAMPS. LET W/435760-2 T6468

Phase Fund Code FY 2021 FY 2022 5 Year Total P.E. DIH $50,000 $10,000 $60,000 RW Land ACNP $2,000,000 $2,000,000 DDR $50,000 $50,000 DSBD $2,000,000 $2,000,000 RW Support DIH $40,000 $40,000 DSBD $200,000 $200,000 Total For Project 435760.1 $4,340,000 $10,000 $4,350,000

435760.2 SR 826/PALMETTO EXPY FROM N.OF CANAL C-8 BRDG (162ST) TO E.OF NW 67 AVE PM: QUINTELA, RAUL City: MIAMI LAKES

Work Mix: Add Lanes & Reconstruct Extra Description: RECONSTRUCT ROADWAY TO ADD EXPRESS LANES PROJECT INCLUDES INGRESS/EGRESS TO EXPRESS LANES. RECONSTRUCT INTCHG AT NW 67 AVENUE (SINGLE POINT URBAN INTERCHANGE). REMINDER: RAMPS HAVE YET TO BE ADDED IN LOCATION SCREENS ONLY THE MAINLINE. PH56-01 Cont. Class: Tallahassee Let = MDWASA LET W/435760-1 (LEAD) PER MEETING 7-18-16

Phase Fund Code FY 2021 FY 2022 5 Year Total P.E. DIH $30,000 $10,000 $40,000 RW Land ACNP $3,239,053 $3,239,053 DSBD $760,947 $760,947 RW Support DIH $30,000 $30,000 DSBD $300,000 $300,000 Total For Project 435760.2 $4,360,000 $10,000 $4,370,000

October. 10 2019 Page 40 of 151 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

435760.3 SR 826/PALMETTO EXPY FROM E. OF NW 67 AVE TO E. OF NW 57 AVE PM: QUINTELA, RAUL Work Mix: Add Lanes & Reconstruct Extra Description: RECONSTRUCT ROADWAY TO ADD EXPRESS LANES & RECONSTRUCT INTERCHANGE AT NW 57 AVENUE. REMINDER: RAMPS HAVE YET TO BE ADDED IN LOCATION SCREENS ONLY THE MAINLINE LET W/435760-4 AND 435760-5 PER MEETING 7-18-16 PH56-01 = MDWASA Cont. Class: Tallahassee Let

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 5 Year Total P.E. DIH $30,000 $10,000 $10,000 $10,000 $60,000 RW Land ACNP $1,565,316 $1,000,000 $2,565,316 BNIR $12,000,000 $7,560,649 $19,560,649 DDR $700,000 $700,000 DSBD $7,174,754 $7,174,754 RW Support BNIR $103,279 $307,114 $200,000 $610,393 DDR $14,719 $14,719 DI $342,886 $342,886 DIH $104,000 $100,000 $100,000 $304,000 DSBD $789,492 $789,492 Total For Project 435760.3 $9,781,560 $13,760,000 $8,570,649 $10,000 $32,122,209

435760.4 SR 826/PALMETTO EXPY FROM E. OF NW 57 AVE TO E. OF NW 42 AVE PM: QUINTELA, RAUL City: MIAMI GARDENS

Work Mix: Add Lanes & Reconstruct Extra Description: ADD EXPRESS LANES AND RECONSTRUCT NW 47 AVENUE INTERCHANGE AND NW 42 AVENUE OVERPASS REMINDER: RAMPS HAVE YET TO BE ADDED IN LOCATION SCREENS ONLY THE MAINLINE PH56-01 = MDWASA LET W/435760-3 AND 435760-5 PER MEETING 7-18-16 LNSDSCAPE Cont. Class: Tallahassee Let DISPOSITION PLAN FOR ALL SEGMENTS ON THIS FM

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 5 Year Total P.E. DIH $30,000 $10,000 $10,000 $10,000 $60,000 RW Land DDR $1,500,000 $1,500,000 $839,384 $3,839,384 RW Support DDR $576,460 $220,000 $100,000 $896,460 DIH $100,000 $200,000 $140,000 $440,000 Total For Project 435760.4 $2,206,460 $1,930,000 $1,089,384 $10,000 $5,235,844

October. 10 2019 Page 41 of 151 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

435760.5 SR 826/PALMETTO EXPY FROM E. OF NW 42 AVE TO E. OF NW 32 AVE PM: QUINTELA, RAUL City: MIAMI GARDENS Work Mix: Add Lanes & Reconstruct Extra Description: ADD EXPRESS LANES AND RECONSTRUCT NW 37 AVENUE INTERCHANGE AND NW 32ND AVENUE OVERPASS. REMINDER: RAMPS HAVE YET TO BE ADDED IN LOCATION SCREENS ONLY THE MAINLINE PH32-02 = APPROX.(130) TEST HOLES LET W/435760-3 AND 435760-4 PER MEETING 7-18-16 Cont. Class: Tallahassee Let PH56-01 = MDWASA /PH56-02 = CITY OF NORTH MIAMI BEACH

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 5 Year Total P.E. DIH $30,000 $10,000 $10,000 $10,000 $60,000 RW Land DDR $1,042,635 $500,000 $1,542,635 DS $1,500,000 $1,500,000 RW Support DDR $905,305 $300,000 $100,950 $1,306,255 DIH $100,000 $100,000 $80,000 $280,000 Total For Project 435760.5 $2,077,940 $410,000 $2,190,950 $10,000 $4,688,890

435760.6 SR 826/PALMETTO EXPY FROM E. OF NW 32 AVE TO W. OF NW 17 AVE PM: QUINTELA, RAUL City: MIAMI GARDENS

Work Mix: Add Lanes & Reconstruct Extra Description: ADD EXPRESS LANES AND RECONSTRUCT NW 27 AVE INTERCHANGE (SINGLE POINT URBAN INTERCHANGE) & NW 22 AVENUE OVERPASS TO JUST WEST OF NW 17 AVENUE PH32-02 = APPROX.(200) TEST HOLES REMINDER: RAMPS HAVE YET TO BE ADDED IN LOCATION SCREENS ONLY THE Cont. Class: Tallahassee Let MAINLINE PH56-01 = MDWASA/PH56-02 COMB LET W/428358-3 PER MEETING 7-18-16

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 5 Year Total P.E. DIH $30,000 $10,000 $10,000 $10,000 $60,000 RW Land ACNP $1,559,854 $3,657,706 $5,217,560 BNIR $3,549,404 $1,342,294 $4,000,000 $8,891,698 DI $5,015,763 $5,015,763 DSBD $3,100,000 $3,100,000 RW Support ACNP $1,334,668 $1,334,668 BNIR $100,000 $100,000 DI $200,000 $200,000 DIH $184,000 $200,000 $200,000 $584,000 DSBD $436,587 $436,587 Total For Project 435760.6 $10,194,513 $10,425,763 $4,310,000 $10,000 $24,940,276

435760.7 SR 826/PALMETTO EXPW Y EAST/WEST CORRIDOR PREL IMINARY ENGINEERING PM: QUINTELA, RAUL City: HIALEAH - MIAMI LAKES

Work Mix: Preliminary Engineering Extra Description: GEC (AECOM) SERVICES TO INCLUDE PLANS REVIEWS, MEETINGS, CREATION OF MASTER PLANS, AND PROJECT COORDINATION. PH32/SEQ 01= AECOM PH32/SEQ 02 = HDR OWNERS REP Cont. Class: Misc - No Letting

Phase Fund Code FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total P.E. DS $250,000 $125,000 $125,000 $500,000 CEI DS $250,000 $125,000 $125,000 $250,000 $750,000 Total For Project 435760.7 $500,000 $250,000 $250,000 $250,000 $1,250,000

October. 10 2019 Page 42 of 151 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

435843.1 SR 112/I-195 FRONTAG E RD & RAMP REALIGNMENT ( MIAMI DESIGN DISTRICT) PM: RAGHUNANDAN, RYAN City: MIAMI

Work Mix: New Road Construction Extra Description: REALIGNMENT OF THE I-195 WESTBOUND ON-RAMP FROM NE T-6443 MIAMI AVE & NW/NE 38 ST & EXTENSION OF THE I-195 OFF- RAMP/ FRONTAGE ROAD: NE 37 STREET FROM NE MIAMI AVE TO NE 1 AVE NOTE: AUTOCADD PILOT CONTRACT E6J50 PHASE 56-01 Cont. Class: Tallahassee Let = LUMP SUM UTILITY AGREEMENT W/MIAMI DADE WATER & SEWER FOR $3,520 (CHECK REC'D DATED 10-20-15).

Phase Fund Code FY 2022 5 Year Total Construction ACNP $4,953,218 $4,953,218 DI $52,650 $52,650 LF $3,520 $3,520 Incentive DDR $320,000 $320,000 CEI DDR $431,730 $431,730 DIH $168,480 $168,480 Total For Project 435843.1 $5,929,598 $5,929,598

436200.1 SR 826/PALMETTO EXPY EXPRESS LANES TOLLING & RAMP SIGNALING OPERATION PM: MOTTA, ALEJANDRO

Work Mix: Technical Assistance Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 5 Year Total Capital Improvement/Operating TOBI $2,169,178 $2,169,178 Total For Project 436200.1 $2,169,178 $2,169,178

436203.1 SR 826/PALMETTO EXPY ITS CONTRACT FOR MAINTEN ANE OF TOLLING EQUIPMENT PM: MOTTA, ALEJANDRO

Work Mix: Other Its Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 5 Year Total Capital Improvement/Operating TOBI $1,000,000 $1,000,000 $2,000,000 Total For Project 436203.1 $1,000,000 $1,000,000 $2,000,000

436203.2 SR 826 EXPRESS LANES INFRASTRUCTURE MAINTENAN CE & REPAIRS PM: MOTTA, ALEJANDRO Work Mix: Other Its Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2023 FY 2024 FY 2025 5 Year Total Capital Improvement/Operating TOBI $1,050,000 $1,050,000 $1,050,000 $3,150,000 Total For Project 436203.2 $1,050,000 $1,050,000 $1,050,000 $3,150,000

October. 10 2019 Page 43 of 151 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

436209.1 SR 826/PALMETTO EXPY INCIDENT MANAGEMENT ROAD RANGER SERVICE PATROLS PM: DARDES, CARLOS Work Mix: Other Its Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 5 Year Total Capital Improvement/Operating TOBI $3,007,603 $3,125,511 $2,866,179 $8,999,293 Total For Project 436209.1 $3,007,603 $3,125,511 $2,866,179 $8,999,293

436209.2 SR 826 EXPRESS LANES INCIDENT MANAGEMENT ROAD RANGER SERVICE PATROLS PM: DARDES, CARLOS Work Mix: Other Its Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2024 FY 2025 5 Year Total Capital Improvement/Operating TOBI $3,505,300 $3,505,300 $7,010,600 Total For Project 436209.2 $3,505,300 $3,505,300 $7,010,600

436212.1 SR 826/PALMETTO EXPR ESSWAY FHP ENHANCED ENFOR CEMENT PM: RODRIGUEZ, JAVIER

Work Mix: Other Its Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 5 Year Total Capital Improvement/Operating TOBI $450,000 $375,000 $365,000 $1,190,000 Total For Project 436212.1 $450,000 $375,000 $365,000 $1,190,000

436212.2 SR 826 EXPRESS LANES FHP ENHANCED ENFORCEMENT PM: DARDES, CARLOS

Work Mix: Other Its Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2024 FY 2025 5 Year Total Capital Improvement/Operating TOBI $463,500 $463,500 $927,000 Total For Project 436212.2 $463,500 $463,500 $927,000

October. 10 2019 Page 44 of 151 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

436355.2 SR 976/SW 40 ST FROM EAST OF SW 117 AVENUE TO EAST OF SW 102 AVENUE PM: GOMEZ, HUMBERTO Work Mix: Resurfacing Extra Description: LEAD TO BE STRUNG W/437923-1 (SAFETY) CNT# T6475 Cont. Class: Tallahassee Let

Phase Fund Code FY 2022 5 Year Total Incentive DS $145,000 $145,000 Total For Project 436355.2 $145,000 $145,000

436355.3 SR 976/BIRD ROAD/SW 40 STREET FROM SW 114 AVE NUE TO SW 102 AVENUE PM: DOMINGUEZ, MARIO Work Mix: Drainage Improvements Extra Description: TO BE STRUNG W/436355-2 (LEAD) & 437923-1 DRAINAGE IMPROVEMENTS TO MITIGATE FLOODING CNT# T6475 Cont. Class: Tallahassee Let

Phase Fund Code FY 2022 5 Year Total Incentive SA $60,000 $60,000 Total For Project 436355.3 $60,000 $60,000

436426.1 SR 948/NW 36 ST FROM SR 826/PALMETTO EXPY TO SR 5/ US1 PM: CASTRO, CARLOS City: VIRGINIA GARDENS - DORAL

Work Mix: Modal Systems Planning Extra Description: STUDY RECOMMENDED FROM THE 2014 LISTENING SESSION PLANNING STUDY IS TO DEVELOP AND EVALUATE IMPROVEMENTS TO ADDRESS THE EXISTING AND FUTURE MOBILITY OPERATIONS AND MULTIMODAL NEEDS ALONG THE STUDIED CORRIDOR. POTENTIAL SWAT** Cont. Class: Misc - No Letting

Phase Fund Code FY 2022 FY 2025 5 Year Total PDE ACFP $1,500,000 $1,500,000 DIH $15,000 $15,000 P.E. ACFP $5,550,000 $5,550,000 Total For Project 436426.1 $1,515,000 $5,550,000 $7,065,000

October. 10 2019 Page 45 of 151 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

436479.1 SR 934/NW 74 ST. FRO M E. OF SR 826/PALMETTO E XPWY TO E. OF NW 69 AVE. PM: GOMEZ, HUMBERTO City: MEDLEY Work Mix: Intersection Improvement Extra Description: SHORT TERM IMPROVEMENT AT VARIOUS LOCATIONS ALONG SR 934/ NW 74 STREET FROM SR 826/PALMETTO EXPRESSWAY TO US 27/SR 25 OKEECHOBEE ROAD, STRATEGIC INTERMODAL SYSTEM CONNECTOR, NATIONAL HIGHWAY CONNECTOR. THE PLANNING STUDY IS BEING Cont. Class: Tallahassee Let COMPLETED UNDER FM 432639-4-22-01 (FREIGHT). PH56-01/PH56-02 CK HAS YET TO BE RECV. PEND PAYMENT FROM TOWN OF MEDLEY.

Phase Fund Code FY 2021 FY 2022 5 Year Total RW Land ACNP $3,034,418 $3,034,418 SA $100,000 $500,000 $600,000 Construction ACNP $4,350,988 $4,350,988 DS $316,156 $316,156 LF $913,837 $913,837 Incentive DS $320,000 $320,000 CEI ACNP $534,056 $534,056 DS $90,000 $90,000 Total For Project 436479.1 $4,364,411 $5,795,044 $10,159,455

436525.1 SR 826/SUNNY ISLES B LVD OVER INTRACOASTAL WTW Y BASCULE BR 870592/0593 PM: COELLO, GEIDY City: SUNNY ISLES Work Mix: Bridge-Repair/Rehabilitation Extra Description: SUPERSTRUCTURE REHABILITATION/DRIVES/BEARINGS/LOCKS TENDERHOUSE VIBRATION STUDY CONTRACT E-6L44 BASCULE BRIDGE NUMBERS 870592 AND 870593 Cont. Class: District Let

Phase Fund Code FY 2021 5 Year Total Construction BRRP $8,608,689 $8,608,689 CEI BRRP $1,642,626 $1,642,626 DIH $71,820 $71,820 ENV BRRP $50,000 $50,000 Total For Project 436525.1 $10,373,135 $10,373,135

436525.2 SR 826/SUNNY ISLES B LVD FROM NE 35 AVENUE TO SR A1A/COLLINS AVE PM: FUNTANELLAS, IVETTE City: SUNNY ISLES

Work Mix: Resurfacing Extra Description: RESURFACING CNT# E6L44 APPROVED BY SCOPING COMMITTEE ON 7/27/16 / CANDIDATE #7 INCLUDES: SR 826 WB & RAMPS 87170360, 87170362, 87170363, 87170364 AND 87170366. RAMP 87170361 ADDED NOTE: LIMITS EXTENDED TO THE WEST TO Cont. Class: District Let INCLUDE A MAST ARM (SEE EMAIL DATED 1-11-18 FROM I.F.) EXCEPTION FROM RESURFACING

Phase Fund Code FY 2021 5 Year Total Construction DDR $2,130,726 $2,130,726 DS $203,271 $203,271 CEI DDR $35,910 $35,910 DIH $114,742 $114,742 DS $418,608 $418,608 Total For Project 436525.2 $2,903,257 $2,903,257

October. 10 2019 Page 46 of 151 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

436526.1 SR 934/NE 79 ST OVER INTRACOASTAL CANAL 4 BRD GS: 870082;-554;-085;551 PM: OROZCO, PABLO City: MIAMI BEACH - MIAMI - NORTH BAY

Work Mix: Bridge-Repair/Rehabilitation Extra Description: GENERATOR, HYDRAULIC SPAN PUMNPS, CYLINDERS, NEW PLC, LOCKS, DRIVES, FENDER LADDER, SEWAGE SYSTEM, RELAY BACKUP SYSTEM, BIKE TREATMENT PH52 = CNT#6K68 LEAD STRUNG W/4448041 Cont. Class: District Let

Phase Fund Code FY 2021 FY 2022 5 Year Total P.E. BRRP $15,000 $15,000 Construction BRRP $6,264,343 $6,264,343 CEI BRRP $1,174,095 $1,174,095 DIH $73,710 $73,710 Total For Project 436526.1 $15,000 $7,512,148 $7,527,148

436539.1 SR 856/WM LEHMAN CSW AY OVER INTRACOASTAL CANA L BRIDGES 870606 & 870607 PM: COELLO, GEIDY City: AVENTURA - SUNNY ISLES Work Mix: Bridge - Painting Extra Description: PAINTING/SUPERSTRUCTURE REPAIRS/BEARINGS/JOINTS CNT#E6L94 Cont. Class: District Let

Phase Fund Code FY 2021 5 Year Total Construction BRRP $2,738,305 $2,738,305 CEI BRRP $561,222 $561,222 DIH $30,780 $30,780 Total For Project 436539.1 $3,330,307 $3,330,307

October. 10 2019 Page 47 of 151 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

436565.1 SR 25/OKEECHOBEE RD. & SR 826/PALMETTO EXPRES SWAY INTERCHANGE PM: RIVEROL, ELSA City: MEDLEY

Work Mix: Interchange Ramp (New) Extra Description: PD & E AND IMR WILL EVALUATE OPERATIONAL AND CAPACITY IMPROVEMENTS OF THREE (3) RAMPS, WHICH WERE REQUESTED BY THE CITY OF HIALEAH WHICH INCLUDES THE SR 826 INTERCHANGE AT OKEECHOBEE. LET W/ 4232513 PH56-01 = MDWSD REIMBURSABLE CONCRETE Cont. Class: Tallahassee Let RESURFACING FY2024- CONCRETE LENGTH: 0.889 MI

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 5 Year Total RW Land BNIR $1,600,000 $406,288 $2,006,288 DDR $1,000,000 $1,000,000 RW Support DDR $200,000 $62,435 $262,435 DIH $10,000 $15,000 $5,000 $30,000 DS $10,000 $10,000 Construction ACNP $49,047,095 $49,047,095 DDR $1,270,273 $1,270,273 DI $18,926,746 $18,926,746 DS $200,000 $200,000 CEI ACNP $8,027,086 $8,027,086 Total For Project 436565.1 $1,410,000 $1,677,435 $421,288 $77,271,200 $80,779,923

436877.1 SR 997/KROME AVENUE FROM SR 5/US-1 TO SR 25/O KEECHOBEE ROAD (FHP) PM: FERNANDEZ, ARNALDO City: FLORIDA CITY - HOMESTEAD Work Mix: Traffic Ops Improvement Extra Description: PROJECT IS FOR THE PURPOSE OF TEMPORARILY PROVIDING FOUR ADDITIONAL TROOPERS ON SR 997/KROME AVE TO DETER HEAD ON CRASHES & ENFORCE TRAFFIC LAWS ESTABLISHED UNDER CHAPTER 316 OF THE FLORIDA STATUTES. TROOPERS WILL PATROL 36.705 MILES OF THE SR Cont. Class: Extern Mngd(Not Lap) 997 CORRIDOR DAILY FOR DURATION OF RECONSTRUCTION PROJECTS. CONTRACT BDY82

Phase Fund Code FY 2021 5 Year Total JPA/LAP Construction DS $254,000 $254,000 Total For Project 436877.1 $254,000 $254,000

437782.1 SR 968/FLAGLER ST FR OM SR 821/HEFT TO SR 5/BI SCAYNE BLVD (BRT STUDY) PM: CARTAYA, NILIA City: MIAMI - SWEETWATER

Work Mix: Pd&E/Emo Study Extra Description: BUS RAPID TRANSIT (BRT) ALONG SR 968/FLAGLER ST. FRM SR 821 /HOMESTEAD EXT. OF FLORIDA'S TRPKE (HEFT) TO SR 5/US-1/ BISCAYNE BLVD. THIS PD&E IS TO BE GAMED USING THE MPO EST. OF $3M AS PER MPO RESOLUTION # 01-15 PH32-02 = GANNETT MPO PRIORITY ID# 2/FY 22 Cont. Class: Misc - No Letting MPO PRIORITY PRJTS LISTING CNT#C9P09/PH22-01 CNT#C9R18 PH22-02=BRT/GEC PGM SPT

Phase Fund Code FY 2021 FY 2022 5 Year Total P.E. DDR $250,000 $250,000 $500,000 SU $2,315,000 $2,315,000 Total For Project 437782.1 $2,565,000 $250,000 $2,815,000

October. 10 2019 Page 48 of 151 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

437784.1 SR 94/KENDALL DR FRO M SR 997/KROME AVE TO SR 5/S DIXIE HWY (BRT STUDY) PM: CARTAYA, NILIA Work Mix: Pd&E/Emo Study Extra Description: BUS RAPID TRANSIT (BRT) STUDY NOTE:THIS PD&E IS TO BE GAMED USING THE MPO ESTIMATE OF $3M AS PER MPO RESOLUTION # 01-15 MPO PRIORITY ID# 1/FY 22 MPO PRIORITY PROJECTS LISTING CNT# C9R18/PH22-01/ PH32-02 = GANNETT CNT#C9Q50/PH22-02 = Cont. Class: Misc - No Letting BRT/GEC PROGRAM SUPPORT

Phase Fund Code FY 2021 FY 2022 5 Year Total PDE SU $1,875,000 $1,875,000 P.E. DDR $250,000 $250,000 $500,000 SU $5,650,000 $5,650,000 Total For Project 437784.1 $7,775,000 $250,000 $8,025,000

437915.1 SR 5/BISCAYNE BLVD. FROM SE 2ND STREET TO NE 11TH TERRACE PM: BARRERA, JOSE City: MIAMI Work Mix: Intersection Improvement Extra Description: SAFETY PROJECT TO INSTALL GUIDE SIGNS, REPLACE CNT# T-6447 EXISTING GUIDE SIGNS @ INTERCT W/NE 5 ST WITH SIGNS MOUNTED ON A TRUSS. AT SE 2ND ST, IMPROVE TURNING RADIUS BY WIDENING INTO THE MEDIAN. INSTALL LANE CONFIG. SIGNS SUPPLEMENTED W/ ARROW Cont. Class: Tallahassee Let PAVEMENT MARKINGS ALONG THE CORRIDOR. B/C = 41.5, NPV=$2,974,590.54, SHSP=INTERS. CRASHES (D6-096). **SEE WP45

Phase Fund Code FY 2021 5 Year Total Incentive SA $105,000 $105,000 Total For Project 437915.1 $105,000 $105,000

437923.1 SR 976/SW 40 STREET FROM SW 11500 BLOCK TO SW 107 AVENUE PM: GOMEZ, HUMBERTO

Work Mix: Intersection Improvement Extra Description: SAFETY PRJ AT SW 11500 BLOCK TO MODIFY EB LEFT CNT# T6475 TURN OPERATION TO PROTECTED ONLY. PROVIDE A WB U-TURN LANE. INSTALL PEDESTRIAN WARNING SIGNS, MODIFY MEDIAN OPENINGS AT SW 114 AVE & SW 113 AVE TO NB DIRECTIONAL ONLY.AT SW 112 AVE INSTALL Cont. Class: Tallahassee Let BACKPLATES, REMOVE NIGHTTIME FLASHING OPERATIONS AND INSTALL PEDESTRIAN WARNING SIGNS. SEE WP45 SCREEN MORE SCOPE

Phase Fund Code FY 2022 5 Year Total Incentive DS $65,000 $65,000 Total For Project 437923.1 $65,000 $65,000

438028.1 SR 25/US 27/OKEECHOB EE RD FROM NW 72 AVE/W 16 AVE TO SE 4 AVE/E DR. PM: YEE FONG, SHEREEN City: HIALEAH - MIAMI SPRINGS Work Mix: Transportation Planning Extra Description: TO SOUTHEAST OF 4365651 THIS NEW STUDY WAS RECOMMENDED FROM THE 2015 PLANNING LISTENING SESSION. THE STUDY WILL DEVELOP AND EVALUATE IMPROVEMENTS TO ADDRESS THE EXISTING AND FUTURE MOBILITY OPERATIONS AND MULTIMODAL NEEDS ALONG THE CORRIDOR. Cont. Class: Studies

Phase Fund Code FY 2021 5 Year Total PDE DDR $500,000 $500,000 DIH $45,000 $45,000 Total For Project 438028.1 $545,000 $545,000

October. 10 2019 Page 49 of 151 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

438034.1 SR 997/KROME AVENUE FROM SW 296 STREET TO SW 232 STREET PM: SCHOT, KEVIN Work Mix: Landscaping Extra Description: STANDALONE LANDSCAPING Cont. Class: District Let

Phase Fund Code FY 2022 5 Year Total Construction DDR $1,013,559 $1,013,559 CEI DIH $76,869 $76,869 DS $179,010 $179,010 Total For Project 438034.1 $1,269,438 $1,269,438

438034.2 SR 997/KROME AVENUE FROM SW 232 STREET TO SW 184TH STREET PM: SCHOT, KEVIN

Work Mix: Landscaping Extra Description: STANDALONE LANDSCAPING LET W/438034-3 CNT# E6M56 Cont. Class: District Let

Phase Fund Code FY 2021 FY 2022 5 Year Total Construction DS $884,697 $884,697 CEI DIH $43,092 $43,092 DS $131,625 $131,625 Total For Project 438034.2 $927,789 $131,625 $1,059,414

438034.3 SR 997/KROME AVENUE FROM SW 184 STREET TO SW 136 STREET PM: SCHOT, KEVIN Work Mix: Landscaping Extra Description: STANDALONE LANDSCAPING LET W/ 438034-2 (LEAD) CNT# E6M56 Cont. Class: District Let

Phase Fund Code FY 2021 FY 2022 5 Year Total Construction DDR $803,262 $803,262 CEI DDR $125,307 $125,307 DIH $40,014 $40,014 Total For Project 438034.3 $843,276 $125,307 $968,583

October. 10 2019 Page 50 of 151 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

438034.4 SR 997/KROME AVENUE FROM SW 136 STREET TO SW 88 STREET PM: SCHOT, KEVIN Work Mix: Landscaping Extra Description: STANDALONE LANDSCAPING CNT#E6L99 BDID APPROVED BY CARLA PERRY 7-12-16 Cont. Class: District Let

Phase Fund Code FY 2021 5 Year Total Construction DDR $702,560 $702,560 DS $20,000 $20,000 CEI DDR $159,030 $159,030 DIH $54,378 $54,378 Total For Project 438034.4 $935,968 $935,968

438076.1 SR 9/NW 27 AVE FROM MIA INTRMDAL CTR TO NW 21 5 ST/UNITY STN(PTC STUDY) PM: CARTAYA, NILIA City: HIALEAH - MIAMI GARDENS - OPA-LOCKA Work Mix: Pd&E/Emo Study Extra Description: PREMIUM TRANSIT CORRIDOR(PTC): SR 9/SR 817/NW 27 AVE FROM MIA INTRMDAL CTR TO NW 215 ST. AT UNITY STN PH32-02/GANNETT NOTE:THIS PD&E STUDY IS TO BE GAMED USING THE MPO EST OF $3M MPO PRIORITY ID# 1/FY 21 MPO PRIORITY PROJECTS LISTING CNT# Cont. Class: Misc - No Letting C9Q20/PH22-02 = PTC/GEC PGM SUPPORT/MPO RESOL.#26-16 DESCRIPTION UPDATED APPROVED PER MEETING HELD ON 5/2/16.

Phase Fund Code FY 2021 FY 2022 5 Year Total P.E. DDR $250,000 $250,000 $500,000 SU $6,575,011 $6,575,011 Total For Project 438076.1 $6,825,011 $250,000 $7,075,011

438314.1 ITS FIELD EQUIPMENT COMMUNICATIONS SERVICES PM: MOTTA, ALEJANDRO

Work Mix: Dynamic Message Sign Extra Description: PAYMENT OF UTILITY BILLS (ELECTRIC, TELEPHONE, ETC.) FOR SPECIALIZED ITS EQUIPMENT ON VARIOUS ROADWAYS VIA TR 51 DISBURSEMENTS (NO ENCUMBRANCE AND NO CONTRACT NUMBER.) Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total Capital Improvement/Operating DS $365,000 $365,000 $365,000 $365,000 $365,000 $1,825,000 Total For Project 438314.1 $365,000 $365,000 $365,000 $365,000 $365,000 $1,825,000

438314.2 ITS FIELD EQUIPMENT ELECTRIC SERVICES PM: MOTTA, ALEJANDRO

Work Mix: Dynamic Message Sign Extra Description: PAYMENT OF UTILITY BILLS (ELECTRIC, TELEPHONE, ETC.) FOR SPECIALIZED ITS EQUIPMENT ON VARIOUS ROADWAYS VIA TR 51'S DISBURSEMENTS (NO ENCUMBRANCE AND NO CONTRACT NUMBER.) Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total Capital Improvement/Operating DS $235,000 $235,000 $235,000 $235,000 $235,000 $1,175,000 Total For Project 438314.2 $235,000 $235,000 $235,000 $235,000 $235,000 $1,175,000

October. 10 2019 Page 51 of 151 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

438314.3 I-95 TOLLING FIELD E QUIPMENT ELECTRIC SERVICE S PM: MOTTA, ALEJANDRO Work Mix: Dynamic Message Sign Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total Capital Improvement/Operating TOBD $20,000 $20,000 $20,000 $20,000 $20,000 $100,000 Total For Project 438314.3 $20,000 $20,000 $20,000 $20,000 $20,000 $100,000

438314.4 SR 826 TOLLING FIELD EQUIPMENT ELECTRIC SERVI CES PM: MOTTA, ALEJANDRO Work Mix: Dynamic Message Sign Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total Capital Improvement/Operating TOBI $15,000 $15,000 $15,000 $15,000 $15,000 $75,000 Total For Project 438314.4 $15,000 $15,000 $15,000 $15,000 $15,000 $75,000

438314.5 I-75 TOLLING ITS FIE LD EQUIPMENT ELECTRIC SER VICES PM: MOTTA, ALEJANDRO

Work Mix: Dynamic Message Sign Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total Capital Improvement/Operating TOBG $15,000 $15,000 $15,000 $15,000 $15,000 $75,000 Total For Project 438314.5 $15,000 $15,000 $15,000 $15,000 $15,000 $75,000

438521.1 SR 953/NW 42 AVENUE WITH SR 948/NW 36 STREET AND SR 25/OKEECHOBEE ROAD PM: JEFFRIES, KEN City: HIALEAH - MIAMI SPRINGS - MIAMI

Work Mix: Transportation Planning Extra Description: STUDY RECOMMENDED FROM THE 2015 PLANNING LISTENING SESSION THE STUDY WILL DEVELOP AND EVALUATE IMPROVEMENTS TO ADDRESS THE EXISTING AND FUTURE MOBILITY OPERATIONS ALONG THE CORRIDOR. Cont. Class: Studies

Phase Fund Code FY 2024 5 Year Total PDE DS $500,000 $500,000 Total For Project 438521.1 $500,000 $500,000

October. 10 2019 Page 52 of 151 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

438864.1 SR 860/MIAMI GDNS/NW 183 ST FROM I-75/SR 93 T O SR 823/RED RD/NW 57 AVE PM: FUENTES, KARINA Work Mix: Transportation Planning Extra Description: STUDY WAS PROGRAMMED IN FY16 WITH ADVERTISEMENT IN NOVEMBER 2015 AND EXECUTION BY MAY 2016. PROJECT WILL EVALUATE THE EXISTING AND FUTURE OPERATIONAL CONDITIONS OF THE CORRIDOR. THE STUDY WILL IDENTIFY ANY OPERATIONAL DEFICIENCIES AND WILL Cont. Class: Studies PROPOSE IMPROVEMENTS TO ADDRESS THEM CNT#C9P89

Phase Fund Code FY 2021 5 Year Total P.E. DIH $75,000 $75,000 Total For Project 438864.1 $75,000 $75,000

439522.1 SR 916/NW 135 STREET BETWEEN CAIRO LANE & SES AME STREET PM: RAGHUNANDAN, RYAN City: OPA-LOCKA

Work Mix: Pedestrian Safety Improvement Extra Description: MID-BLOCK PEDESTRIAN CROSSING CNT#E6M02 APPROVED BY SCOPING COMMITTEE (MAY 2016) TO BE DESIGNED IN-HOUSE Cont. Class: District Let

Phase Fund Code FY 2021 5 Year Total P.E. DIH $5,000 $5,000 Construction DDR $317,741 $317,741 CEI DIH $41,040 $41,040 DS $41,040 $41,040 Total For Project 439522.1 $404,821 $404,821

439913.1 SR 5/US 1 AT SW 112 AVENUE PM: RIVEROL, ELSA City: CUTLER BAY Work Mix: Intersection Improvement Extra Description: D6-135/NEW SAFETY PROJECT APPRV SCOPING ON 7-26-16 CNT#T6452 TO INSTALL BACKPLATES ON NB & SB APPROACHES, PROVIDE A 2ND SB LEFT TURN LANE & MODIFY OPERATION TO PROTECTED ONLY LEFT TURN PHASING. MODIFY LANE CONFIGURATION FOR SB RIGHT TURN LN Cont. Class: Tallahassee Let FM RIGHT TURN ONLY TO SHARED THROUGH & RIGHT. EXTEND MERGE LANE ON SB APPROACH. **SEE WP45 SCREEN MORE. 52-02=LIGHTING

Phase Fund Code FY 2021 FY 2022 5 Year Total RW Land DDR $40,000 $40,000 Construction ACSS $918,082 $918,082 Incentive SA $54,000 $54,000 CEI ACSS $129,276 $129,276 DIH $33,858 $33,858 DS $20,520 $20,520 Total For Project 439913.1 $1,141,736 $54,000 $1,195,736

October. 10 2019 Page 53 of 151 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

439916.1 SR 989/ALLAPATTAH RO AD AT SW 211 STREET PM: WANG, BAOYING Work Mix: Intersection Improvement Extra Description: D6-139/NEW SAFETY PRJCT APPRV SCOPING ON 7-26-16 (LEAD)T6452 TO PROVIDE AN ADD'L NORTHBOUND LEFT TURN LANE. OFFSET SB APPROACH. EXTEND NB RIGHT TURN LANE & WB LEFT TURN LANE INSTALL BACKPLATES ON ALL APPROACHES. PROVIDE HIGH EMPHASIS Cont. Class: Tallahassee Let CROSSWALKS & MILL & RESURFACE ALL LEGS. PH 32 APPRV $309,485 NOTE: BDI CONTRACT PER LEIGH ** SEE WP45 SCREEN MORE SCOPE.

Phase Fund Code FY 2021 FY 2022 5 Year Total Construction ACSS $981,433 $981,433 DS $270,773 $270,773 LF $7,000 $7,000 Incentive SA $66,000 $66,000 CEI ACSS $143,640 $143,640 DIH $43,092 $43,092 Total For Project 439916.1 $1,445,938 $66,000 $1,511,938

439918.1 SR 90/SW 8TH STREET AT SW 137 AVENUE PM: RAGHUNANDAN, RYAN

Work Mix: Intersection Improvement Extra Description: D6-141/NEW SAFETY PROJECT APPRVD SCOPING ON 7-26-16 (T ) TO PROVIDE TRIPLE EASTBOUND LEFT TURN LANES. INSTALL BACK- PLATES ON EASTBOUND AND WESTBOUND APPROACHES. MILL AND RESURFACE ALL LEGS. B/C = 6 AND NPV = $772,428 Cont. Class: Tallahassee Let

Phase Fund Code FY 2021 FY 2022 5 Year Total Construction ACSS $1,767,576 $1,767,576 DS $41,040 $41,040 Incentive DS $100,000 $100,000 CEI ACSS $310,374 $310,374 SA $20,520 $20,520 Total For Project 439918.1 $2,139,510 $100,000 $2,239,510

439919.1 SR 7/NW 2ND AVENUE F ROM NW 7 AVENUE TO NW 179 TH STREET PM: FUNTANELLAS, IVETTE City: MIAMI GARDENS

Work Mix: Intersection Improvement Extra Description: D6-142/NEW SAFETY PROJECT APPRVD SCOPING ON 7-26-16 (T ) PROJECT APPROVED BY C.O. ON 10-6-16 WITH ACNP FUNDS UNTIL HSP IS AVAILABLE FOR THE CONST. PHASES IN FY 18/19 PH 56 = VALVE/MANHOLE ADJUSTMENTS CNT# T6474 Cont. Class: Tallahassee Let

Phase Fund Code FY 2021 5 Year Total Incentive SA $100,000 $100,000 Total For Project 439919.1 $100,000 $100,000

October. 10 2019 Page 54 of 151 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

439920.1 SR-7/NW 2ND AVE FROM S. OF NW 183RD ST TO S. OF NW 188TH ST PM: RIVEROL, ELSA City: MIAMI GARDENS Work Mix: Intersection Improvement Extra Description: D6-159/NEW SAFETY PROJECT APPRVD SCOPING ON 7-26-16 (T ) SR 860 MIAMI GARDENS DRIVE/NW 183RD ST & NW 2ND AVE: INSTALL BACKPLATES. MIAMI GARDENS DR FM NW 1 AVE TO N. MIAMI AVE: PROVIDE DIRECTIONAL MEDIAN. INSTALL BACKPLATES ON EB & WB Cont. Class: Tallahassee Let APPROACHES & HIGH EMPHASIS CROSSWALKS. SR 7/NW 2 AVE AT NW 187 ST: MODIFY MEDIAN OPENING. B/C=6.46 & NPV=$3,585,559

Phase Fund Code FY 2021 FY 2022 5 Year Total RW Land DDR $124,000 $124,000 Construction ACSS $757,657 $757,657 DDR $30,512 $30,512 CEI ACSS $128,071 $128,071 SA $10,260 $10,260 Total For Project 439920.1 $922,429 $128,071 $1,050,500

439923.1 SR 916/NE 135 STREET AT NE 12TH AVENUE PM: GOMEZ, HUMBERTO City: NORTH MIAMI

Work Mix: Intersection Improvement Extra Description: D6-145/NEW SAFETY PROJECT APPRVD SCOPING ON 7-26-16 (T6466) TO INSTALL BACKPLATES WITH RETRO-REFLECTIVE TAPE BORDER ON ALL APPROACHES. ELIMINATE FLASHING OPERATION. INSTALL FLUORESCENT YELLOW-GREEN PEDESTRIAN WARNING SIGNS WITH SUPPLEMENTAL Cont. Class: Tallahassee Let PLAQUE FACING ALL APPROACHES.PROVIDE PEDESTRIAN COUNTDOWN SIGNAL HEADS. ** SEE WP45 SCREEN MORE COMMENTS **

Phase Fund Code FY 2021 FY 2022 5 Year Total Construction ACSS $279,057 $279,057 DDR $87,210 $87,210 LF $2,500 $2,500 CEI ACSS $49,052 $49,052 DIH $36,936 $36,936 DS $10,260 $10,260 Total For Project 439923.1 $415,963 $49,052 $465,015

439924.1 SR 973/SW 87 AVENUE FROM SW 27 STREET TO SW 2 0 TERRACE PM: ARVELO, ANA Work Mix: Intersection Improvement Extra Description: D6-147/NEW SAFETY PROJECT APPRVD SCOPING ON 7-26-16 (T6488) SR 973 AT SW 24 ST/CORAL WAY: INSTALL BACKPLATES WITH RETRO- REFLECTIVE TAPE BORDER ON ALL APPROACHES. EXTEND THE SB & EB LEFT TURN LANES. PROVIDE 4 FT OFFSET BETWEEN THE EB & WB Cont. Class: Tallahassee Let LEFT TURN LANES. INSTALL FLUORESCENT YELLOW-GREEN PEDESTRIAN WARNING SIGNS. ** SEE WP45 SCREEN MORE COMMENTS **

Phase Fund Code FY 2021 FY 2022 5 Year Total Construction ACSS $1,039,323 $1,039,323 Incentive SA $70,000 $70,000 CEI ACSS $121,994 $121,994 DIH $70,794 $70,794 Total For Project 439924.1 $1,232,111 $70,000 $1,302,111

October. 10 2019 Page 55 of 151 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

439976.1 SR 909/WEST DIXIE HW Y FROM NE 119 STREET TO N OF NE 124 STREET PM: DE LA CRUZ, JOAQUIN City: NORTH MIAMI Work Mix: Resurfacing Extra Description: NOTE: BDI CONTRACT PER LEIGH,APPR. BY ANGELA MATIYOW 1-11-18 RESURFACING APPROVED BY SCOPING COMMITTEE ON 7/27/16 /CANDIDATE #10 INCLUDES BRIDGE 870799 OVER BISCAYNE CANAL PROJECT STRUNG W/4275212 (LEAD), 4399762 PH32-02=SAFETY LIGHTING (440179.1) Cont. Class: Tallahassee Let

Phase Fund Code FY 2023 5 Year Total Construction ACSS $18,532 $18,532 DDR $1,222,915 $1,222,915 CEI DIH $13,783 $13,783 DS $165,393 $165,393 Total For Project 439976.1 $1,420,623 $1,420,623

439976.2 SR 909/WEST DIXIE HW Y AT NE 119 STREET AND NE 124 STREET PM: DE LA CRUZ, JOAQUIN City: NORTH MIAMI Work Mix: Intersection Improvement Extra Description: NEW SAFETY PROJECT (SEE SCOPING COMMITTEE MEETING 6-14-17) B/C = 5.1 (NE 119 ST) AND B/C = 85 (NE 124 ST) PROJECT STRUNG W/4275212 (LEAD), 4399761 NOTE: BDI CONTRACT PER LEIGH,APPR. BY ANGELA MATIYOW 1-11-18 Cont. Class: Tallahassee Let

Phase Fund Code FY 2023 5 Year Total Construction ACSS $65,572 $65,572 DS $5,405 $5,405 CEI ACSS $15,468 $15,468 DIH $10,810 $10,810 DS $10,810 $10,810 Total For Project 439976.2 $108,065 $108,065

439981.1 SR 924/NW 119 STREET /GRATIGNY RD FROM NW 27 A VE TO W. OF NW 7 AVE PM: GOMEZ, HUMBERTO

Work Mix: Resurfacing Extra Description: RESURFACING CNT# APPROVED BY SCOPING COMMITTEE ON 7/27/16 / CANDIDATE #12 INCLUDES BRIDGE 870621 OVER RIO VISTA CANAL LET WITH: 4399812 AND 441963-1 PH56-01 = LUMPSUM W/MDWSD FOR VALVE AND MANHOLE Cont. Class: Tallahassee Let

Phase Fund Code FY 2022 FY 2023 5 Year Total Construction DDR $820,406 $820,406 LF $15,000 $15,000 SA $2,948,400 $2,948,400 Incentive SA $200,000 $200,000 CEI DDR $59,019 $59,019 DIH $115,830 $115,830 DS $481,170 $481,170 Total For Project 439981.1 $4,439,825 $200,000 $4,639,825

October. 10 2019 Page 56 of 151 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

439981.2 SR 924/NW 119 STREET AT NW 27 AVENUE AND NW 1 7 AVENUE PM: GOMEZ, HUMBERTO Work Mix: Intersection Improvement Extra Description: NEW SAFETY PROJECT APPROVED BY FINAL SCOPING MEETING 7-25-17 LET WITH 439981-1 (LEAD) AND 441963-1 Cont. Class: Tallahassee Let

Phase Fund Code FY 2022 FY 2023 5 Year Total Construction ACSS $193,723 $193,723 Incentive SA $20,000 $20,000 CEI ACSS $47,385 $47,385 DIH $11,583 $11,583 DS $10,530 $10,530 Total For Project 439981.2 $263,221 $20,000 $283,221

439984.1 SR 5/US-1 AT SW 136T H STREET PM: GOMEZ, HUMBERTO Work Mix: Intersection Improvement Extra Description: D6-150/NEW SAFETY PROJECT APPRVD SCOPING ON 8-12-16 (T6500) TO INSTALL BACK-PLATES AND AN ADDITIONAL SIGNAL HEAD ON NORTHBOUND & SOUTHBOUND APPROACHES. SAFETY PROJECT APPROVED BY C.O. 10-6-16. CONSULT: HBC. NOTE: SCOPE TRANSFERRED TO Cont. Class: Tallahassee Let MIAMI-DADE COUNTY; FM 439984-2

Phase Fund Code FY 2021 5 Year Total Construction ACSS $295,853 $295,853 CEI ACSS $37,965 $37,965 DIH $41,040 $41,040 DS $10,260 $10,260 Total For Project 439984.1 $385,118 $385,118

439984.2 SR 5/US-1 AT SW 136T H STREET PM: CARTAYA, NILIA

Work Mix: Intersection Improvement Extra Description: DFA WITH MIAMI-DADE COUNTY THE SCOPE AND LIMITS OF THIS PROJECT, ORIGINALLY ON 439984-1 WILL BE TRANSFERRED TO MIAMI-DADE COUNTY. THE PROJECT WILL BE COMPLETED VIA THE SMART PLAN SOUTH COORIDOR PROJECT. Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2021 5 Year Total JPA/LAP Construction DDR $290,729 $290,729 Total For Project 439984.2 $290,729 $290,729

October. 10 2019 Page 57 of 151 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

439985.1 SR 860/MIAMI GARDENS DRIVE AND NW 67 AVENUE PM: ARVELO, ANA Work Mix: Intersection Improvement Extra Description: D6-151/NEW SAFETY PROJECT APPRVD SCOPING ON 8-12-16 (T6501) TO MILL AND RESURFACE INTERSECTION AND INSTALL BACKPLATES ON ALL APPROACHES. NEW SAFETY PROJECT APPROVED C.O. 10-6-16 BDID APPROVED BY CARLA PERRY 1-30-17. B/C RATIO 1.5 SHSP INTERSECTION Cont. Class: Tallahassee Let CRASHES. NPV $659,341 **SEE WP45*** PH52-02 = LIGHTING RETROFITS

Phase Fund Code FY 2021 5 Year Total Construction ACSS $731,151 $731,151 DS $30,000 $30,000 LF $2,310 $2,310 SA $61,560 $61,560 CEI ACSS $121,068 $121,068 DIH $67,716 $67,716 Total For Project 439985.1 $1,013,805 $1,013,805

439986.1 SR 5/US-1 FROM BAILE S ROAD TO SW 214 STREET PM: BENITEZ, LOLA

Work Mix: Intersection Improvement Extra Description: D6-154/NEW SAFETY PROJECT APPRVD SCOPING ON 8-12-16 (T ) SAFETY PROJECT APPROVED BY C.O. ON 10-6-16. SCOPE TO INCLUDE MILLING AND RESURFACING SEGMENT & INSTALLATION OF BACKPLATES B/C = 7.8, NPV = $19,643,658 52-02 = ADA RAMPS PH32-02 = APPROX. (40) Cont. Class: Tallahassee Let TEST HOLES/CNT#C9T21/CONSULT: WANTMAN

Phase Fund Code FY 2021 FY 2022 5 Year Total Construction ACSS $2,042,575 $2,042,575 LF $17,000 $17,000 SA $399,464 $399,464 Incentive SA $160,000 $160,000 CEI ACSS $388,623 $388,623 SA $30,780 $30,780 Total For Project 439986.1 $2,878,442 $160,000 $3,038,442

440176.1 SR 989/SW 112AVE SIG NALIZED INTERS.LIGHTING F M JUST S.OF US1 TO 248 ST PM: MARCHANT, PATRICK

Work Mix: Lighting Extra Description: SAFETY SHAREPOINT# D6-180 CNT#T6452 PEDESTRIAN LIGHTING RETROFIT (7 INTERSECTIONS) MP 0.409 TO 2.901 (87015000) NOTE: LET WITH 439913-1 AND 439916-1(LEAD/ADV 439916-1) Cont. Class: Tallahassee Let

Phase Fund Code FY 2021 FY 2022 5 Year Total Construction ACSS $354,692 $354,692 Incentive SA $20,000 $20,000 CEI ACSS $33,858 $33,858 DIH $10,260 $10,260 SA $9,870 $9,870 Total For Project 440176.1 $408,680 $20,000 $428,680

October. 10 2019 Page 58 of 151 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

440176.2 SR 994/QUAIL ROOST D R SIGNALIZED INT. LIGHTIN G FM SW 113 AVE TO BUSWAY PM: MARCHANT, PATRICK

Work Mix: Lighting Extra Description: SAFETY SHAREPOINT# D6-181 PEDESTRIAN LIGHTING RETROFIT (10 INTERSECTIONS) MP 6.837 TO 7.952 (87091000) NOTE: 3 INTERSECTIONS OVERLAP WITH 429341-3 LET W/429341-2 THRU SEGMENT 5 CNT# T6506 Cont. Class: Tallahassee Let

Phase Fund Code FY 2021 FY 2023 5 Year Total Construction ACSS $248,768 $248,768 Incentive ACSS $15,000 $15,000 CEI ACSS $36,936 $36,936 DIH $10,260 $10,260 Total For Project 440176.2 $295,964 $15,000 $310,964

440177.1 SR 934/NW 81/NW 82ST SIGNALIZED INTERS.LIGHTI NG FM NW 79ST TO NE 10AVE PM: MARCHANT, PATRICK City: MIAMI Work Mix: Lighting Extra Description: SAFETY SHAREPOINT #D6-182 CNT#T6479 PEDESTRIAN LIGHTING RETROFITS (11 INTERSECTIONS) MP 0.251 TO 3.079 (87080001) STRUNG W/ 4401791, 4402811, 4401792 & 4401811 (LEAD) Cont. Class: Tallahassee Let

Phase Fund Code FY 2021 5 Year Total Construction ACSS $235,042 $235,042 CEI ACSS $51,300 $51,300 DIH $24,624 $24,624 Total For Project 440177.1 $310,966 $310,966

440177.2 SR 934/NW 79 STREET AT NW 22ND AVENUE PM: MARCHANT, PATRICK

Work Mix: Lighting Extra Description: PROJECT STRUNG W/445167-1 (LEAD) & 445168-1 CNT# T6497 INSTALL NEW LIGHTING BC-118.1, NPV-$6,545,055, SHSP-INTERSECTION CRASHES SHAREPOINT# D6-201 MP 36.970 TO 36.971 (87080900) Cont. Class: Tallahassee Let

Phase Fund Code FY 2021 5 Year Total Construction ACSS $61,597 $61,597 CEI ACSS $8,415 $8,415 DIH $3,078 $3,078 Total For Project 440177.2 $73,090 $73,090

October. 10 2019 Page 59 of 151 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

440179.1 SR 909/W.DIXIE HWY S IGNALIZED INTERS.LIGHTNG FRM NE 8 AVE TO NE 159 ST PM: MARCHANT, PATRICK City: SOUTH MIAMI - CORAL GABELS Work Mix: Lighting Extra Description: SAFETY SHAREPOINT #D6-183 CNT# T6527 PEDESTRIAN LIGHTING RETROFIT (13 INTERSECTIONS) MP 0.995 TO 3.505 (87190000) LEAD PROJECT STRUNG W/440179-2 Cont. Class: Tallahassee Let

Phase Fund Code FY 2022 5 Year Total Construction ACSS $377,048 $377,048 CEI ACSS $69,498 $69,498 SA $10,530 $10,530 Total For Project 440179.1 $457,076 $457,076

440179.2 SR 915/NE 6 AVE SIGN ALIZED INTERS.LIGHTING FR OM NE 123 ST TO NE 177 ST PM: MARCHANT, PATRICK City: NORTH MIAMI BEACH - NORTH MIAMI

Work Mix: Lighting Extra Description: SAFETY SHAREPOINT #D6-184 CNT# T6527 PEDESTRIAN LIGHTING RETROFIT (10 INTERSECTIONS) MP 2.220 TO 5.613(87034000) PROJECT STRUNG W/440179-1(LEAD) Cont. Class: Tallahassee Let

Phase Fund Code FY 2022 5 Year Total Construction ACSS $353,367 $353,367 CEI ACSS $44,226 $44,226 SA $18,954 $18,954 Total For Project 440179.2 $416,547 $416,547

440181.1 SR 860/NW 184ST SIGN ALIZED INTRSC.LIGHTNG FM NW 27 AVE TO W.DIXIE HWY PM: MARCHANT, PATRICK City: MIAMI GARDENS - NORTH MIAMI BEACH Work Mix: Lighting Extra Description: SAFETY SHAREPOINT #D6-185 CNT# T6486 LET W/4275182 (LEAD) PEDESTRIAN LIGHTING RETROFITS (28 INTERSECTIONS) MP 3.019 TO 9.214 (87026000) Cont. Class: Tallahassee Let

Phase Fund Code FY 2021 FY 2022 5 Year Total Construction ACSS $496,068 $496,068 Incentive ACSS $30,000 $30,000 CEI ACSS $71,820 $71,820 DIH $13,338 $13,338 Total For Project 440181.1 $581,226 $30,000 $611,226

October. 10 2019 Page 60 of 151 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

440182.1 SR 90/SW 8 ST SIGNAL IZED INTERS.LIGHTING FROM SW 132 AVE TO SW 70 AVE PM: MARCHANT, PATRICK Work Mix: Lighting Extra Description: SAFETY SHAREPOINT #D6-186 CNT#T6480 (LEAD) PEDESTRIAN LIGHTING RETROFITS (22 INTERSECTIONS) MP 4.458 TO 10.782 (87120000) STRUNG W/4401831 Cont. Class: Tallahassee Let

Phase Fund Code FY 2021 5 Year Total Construction ACSS $418,870 $418,870 CEI ACSS $77,976 $77,976 DIH $47,196 $47,196 SA $8,208 $8,208 Total For Project 440182.1 $552,250 $552,250

440183.1 SR 90/SW 8TH ST SIGN ALIZED INTER.LIGHTING FM SW 62 AVE TO BRICKELL AVE PM: MARCHANT, PATRICK City: MIAMI - CORAL GABELS Work Mix: Lighting Extra Description: SAFETY SHAREPOINT #D6-187 CNT# T6480 PEDESTRIAN LIGHTING RETROFITS (22 INTERSECTIONS) MP 11.572 TO 18.040 (87120000) STRUNG W/4401821 (LEAD) Cont. Class: Tallahassee Let

Phase Fund Code FY 2021 5 Year Total Construction ACSS $287,610 $287,610 CEI ACSS $77,976 $77,976 DIH $47,196 $47,196 SA $8,208 $8,208 Total For Project 440183.1 $420,990 $420,990

440190.1 SR 5/US 1 SIGNALIZED INTERSECTION LIGHTING FR OM SE 1 ST TO NE 21 ST PM: MARCHANT, PATRICK City: MIAMI

Work Mix: Lighting Extra Description: SAFETY SHAREPOINT# D6-168 CNT#T6447 PEDESTRIAN LIGHTING RETROFITS (20 INTERSECTIONS) MP 10.900 TO 12.579 (87030000) STRUNG W/4379151(LEAD) Cont. Class: Tallahassee Let

Phase Fund Code FY 2021 5 Year Total Incentive ACSS $45,000 $45,000 Total For Project 440190.1 $45,000 $45,000

October. 10 2019 Page 61 of 151 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

440281.1 SR 826/NE 163 ST SIG NALIZED INTERS. LIGHTING FRM NW 2 AVE TO NE 35 AVE PM: MARCHANT, PATRICK City: NORTH MIAMI BEACH Work Mix: Lighting Extra Description: SAFETY SHAREPOINT #D6-188 CNT# T6479 PEDESTRIAN LIGHTING RETROFITS (21 INTERSECTIONS-REVISED 20) MP 0.474 TO 4.935 (87170000) (SEE 440304-1 OVERLAP OF ONE INTERSECTION-MOVED $30K HSP TO 440304-1-52-02 ON 9-5-17) STRUNG W/4401771 (LEAD), 4401792 Cont. Class: Tallahassee Let

Phase Fund Code FY 2021 5 Year Total P.E. DIH $10,000 $10,000 Construction ACSS $554,150 $554,150 CEI ACSS $64,638 $64,638 DIH $35,910 $35,910 DS $17,442 $17,442 Total For Project 440281.1 $682,140 $682,140

440604.1 SR 922/NE 125 STREET AT NE 10 AVENUE PM: GOMEZ, HUMBERTO City: NORTH MIAMI Work Mix: Traffic Signals Extra Description: INTERSECTION IMPROVEMENT AND TRAFFIC SIGNAL UPGRADE APPROVED BY SCOPING COMMITTEE CNT# E6M37 Cont. Class: District Let

Phase Fund Code FY 2021 5 Year Total CEI DS $76,191 $76,191 Total For Project 440604.1 $76,191 $76,191

440668.1 SW 312 STREET/CAMPBE LL DRIVE FROM SR 997/KROM E AVENUE TO SR 5/US-1 PM: SCHOT, KEVIN City: HOMESTEAD Work Mix: Landscaping Extra Description: STANDALONE LANDSCAPE PROJECT FOLLOWS ROADWAY PROJECT 405575-6 TPO PRIORITY# Cont. Class: District Let

Phase Fund Code FY 2022 5 Year Total Construction SU $187,734 $187,734 CEI SU $55,809 $55,809 Total For Project 440668.1 $243,543 $243,543

October. 10 2019 Page 62 of 151 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

440683.1 NE 203 STREET FROM S R 5/US-1 TO WEST DIXIE HI GHWAY PM: GONZALEZ, FABIANA City: AVENTURA Work Mix: Landscaping Extra Description: STANDALONE LANDSCAPE PROJECT/ FOLLOWS FM 4335112 NOTE: CONVERT TO FEDERAL FUNDS AFTER JULY 1ST, 2018 (LOCAL RDWAY) THI Cont. Class: District Let

Phase Fund Code FY 2022 FY 2025 5 Year Total P.E. DIH $10,000 $10,000 DS $70,000 $70,000 Construction DS $922,234 $922,234 CEI DIH $6,864 $6,864 DS $164,736 $164,736 Total For Project 440683.1 $80,000 $1,093,834 $1,173,834

441646.1 CITY OF SUNNY ISLES BCH - GOVERNMNT CTR/BEACH ACCESS PEDESTRIAN BRIDGE PM: NUNEZ, XIOMARA Work Mix: Pedestrian/Wildlife Overpass Extra Description: MUNICIPALITY: CITY OF SUNNY ISLES BEACH GOVERNMENT CENTER/BEACH ACCESS PEDESTRIAN BRIDGE FY17 TPO RANK #2 /D6 RANK #7 Cont. Class: Local Agcy Pgm (Lap)

Phase Fund Code FY 2021 5 Year Total JPA/LAP Construction LF $3,500,000 $3,500,000 TALU $500,000 $500,000 CEI TALT $5,000 $5,000 JPA/LAP CEI LF $550,000 $550,000 Total For Project 441646.1 $4,555,000 $4,555,000

441672.1 SR 90/SW 8TH STREET AT SW 17 AVENUE AND SW 7T H ST AT SW 17 AVENUE PM: FUNTANELLAS, IVETTE City: MIAMI

Work Mix: Intersection Improvement Extra Description: NEW SAFETY PROJECT PRESENTED AT SCOPING COMMITTEE 7-17-17 (HCL) B/C = 5.8, NPV = $2,714,117 T6526 NOTE: 2 PARCELS AT SW 7TH STREET AND SW 17 AVENUE D/W CONSULTANT ASA CONTRACT C9T01 CNT# T6526 Cont. Class: Tallahassee Let

Phase Fund Code FY 2021 5 Year Total Construction ACSA $47,329 $47,329 ACSS $367,494 $367,494 CEI ACSS $65,667 $65,667 SA $10,260 $10,260 Total For Project 441672.1 $490,750 $490,750

October. 10 2019 Page 63 of 151 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

441812.1 SR 5/SOUTH DIXIE HIG HWAY FROM CARD SOUND RD T O S OF SW 336 STREET PM: WANG, BAOYING City: FLORIDA CITY Work Mix: Resurfacing Extra Description: RRR PROJECT CRACK RATING = 6.5 (RT) / RIDE RATING = 6.7 (RT) LET W/ 4418271 /CNT# T6496 PH56-01 = LUMPSUM W/FL. CITY FOR VALVE AND MANHOLE Cont. Class: Tallahassee Let

Phase Fund Code FY 2021 FY 2022 5 Year Total Construction DDR $514,175 $514,175 LF $5,000 $5,000 SA $2,462,400 $2,462,400 Incentive SA $200,000 $200,000 CEI DDR $357,869 $357,869 DIH $105,678 $105,678 Total For Project 441812.1 $3,445,122 $200,000 $3,645,122

441827.1 SR 5/SOUTH DIXIE HIG HWAY FROM N OF SW 336 STR EET TO S OF SW 304 STREET PM: GOMEZ, HUMBERTO City: FLORIDA CITY - HOMESTEAD

Work Mix: Resurfacing Extra Description: RRR PROJECT: EXCEPTION FROM N. OF SE 6 AVE TO N. OFCAMPBELL DR/SW 312 ST (SEE FM 4055756) CNT# T6496 CRACK RATING = 6.5 (RT) / RIDE RATING = 6.7 (RT) LEAD PROJECT LET W/ 4418121 **SEE WP45** PH52-02=SAFETY BC-21.3, NPV-$12,041,399.20 & SHSP Cont. Class: Tallahassee Let INTERSECTION CRASHES, SHAREPOINT# D6-202 PH32-02= SAFETY PH32-03 = TESTHOLES

Phase Fund Code FY 2021 FY 2022 5 Year Total Construction ACSS $497,505 $497,505 DDR $2,422,302 $2,422,302 LF $5,000 $5,000 SA $1,126,448 $1,126,448 Incentive SA $260,000 $260,000 CEI ACSS $101,147 $101,147 DDR $448,848 $448,848 DIH $112,860 $112,860 Total For Project 441827.1 $4,714,110 $260,000 $4,974,110

October. 10 2019 Page 64 of 151 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

441830.1 SR 826 FRONTAGE ROAD S FROM OKEECHOBEE ROAD TO NW 103 STREET PM: WANG, BAOYING City: HIALEAH Work Mix: Resurfacing Extra Description: RRR PROJECT CNT#T6520 STRUNG W/4418311 (LEAD) & 4418321 INCLUDES THE WEST FRONTAGE ROAD (NW 77 AVENUE) AND THE EAST FRONTAGE ROAD (WEST 20TH AVENUE) WEST FRONTAGE RD (NW 77 AVENUE)(87260152) CRACK RATING = 6.0 EAST FRONTAGE RATING (W 20TH Cont. Class: Tallahassee Let AVE) (87260151) CRACK RATING = 5.0

Phase Fund Code FY 2021 FY 2024 5 Year Total P.E. DIH $25,000 $25,000 DS $176,000 $176,000 Construction DS $1,975,544 $1,975,544 Incentive DS $120,000 $120,000 CEI DIH $201,758 $201,758 DS $213,312 $213,312 Total For Project 441830.1 $201,000 $2,510,614 $2,711,614

441831.1 SR 826 FRONTAGE ROAD S FROM NW 103 STREET TO N W 122 STREET PM: WANG, BAOYING City: HIALEAH Work Mix: Resurfacing Extra Description: RRR PROJECT LEAD CNT#T6520 STRUNG W/4418301 & 4418321 INCLUDES THE WEST FRONTAGE ROAD (WEST 20TH AVENUE WEST) AND THE EAST FRONTAGE ROADS (WEST 20TH AVENUE EAST) INCLUDES EXISTING BRIDGES 870569 AND 870570 TO REMAIN W.FRONTAGE RD (W 20 Cont. Class: Tallahassee Let AVE WEST)(87260521) CRACK RATING = 6.0 E.FRONTAGE RD (W 20 AVE EAST) (87260298) CRACK RATING = 6.5

Phase Fund Code FY 2021 FY 2024 5 Year Total P.E. DDR $132,160 $132,160 DIH $35,000 $35,000 GFSA $164,840 $164,840 Construction SA $3,108,889 $3,108,889 Incentive SA $180,000 $180,000 CEI DDR $38,885 $38,885 DIH $38,885 $38,885 DS $299,970 $299,970 Total For Project 441831.1 $332,000 $3,666,629 $3,998,629

October. 10 2019 Page 65 of 151 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

441832.1 SR 826 FRONTAGE ROAD FROM NW 122 STREET TO NW 138 STREET PM: RAGHUNANDAN, RYAN City: HIALEAH Work Mix: Resurfacing Extra Description: RRR PROJECT/CNT#T6528 STANDALONE PROJECT INCLUDES EAST FRONTAGE ROAD (WEST 20TH AVENUE EAST) ONLY E. FRONTAGE RD (W 20 AVE EAST)(87260522) CRACK RATING = 6.0 Cont. Class: Tallahassee Let

Phase Fund Code FY 2021 FY 2022 5 Year Total P.E. DIH $20,000 $20,000 Construction ACSA $355,982 $355,982 GFSA $1,537,835 $1,537,835 Incentive GFSA $100,000 $100,000 CEI DIH $143,419 $143,419 SA $215,865 $215,865 Total For Project 441832.1 $2,013,817 $359,284 $2,373,101

441886.1 SR A1A/COLLINS AVENU E AT 36TH, 83RD AND 87TH STREETS PM: BARRERA, JOSE City: MIAMI BEACH

Work Mix: Pedestrian Safety Improvement Extra Description: PROJECT APPROVED BY SCOPING COMMITTEE ON 6-28-17 INSTALL OVERHEAD RECTANGULAR RAPID FLASHING BEACON CROSSWALK ON SR A1A/COLLINS AVENUE AT 36TH, 83RD AND 87TH STREETS PH56-01 = LUMPSUM W/CITY OF BAL HARBOUR PH56-02 = LUMPSUM W/CITY OF MIAMI Cont. Class: District Let BEACH

Phase Fund Code FY 2021 FY 2022 FY 2023 5 Year Total RW Support DIH $10,000 $10,000 DS $15,000 $15,000 Construction DDR $695,773 $695,773 LF $11,000 $11,000 CEI DDR $103,776 $103,776 DIH $5,405 $5,405 Total For Project 441886.1 $25,000 $11,000 $804,954 $840,954

441960.1 SR886 PORT BLVD OVER INTERCOASTAL WATERWAY BR IDGES 875000/875001 PM: OROZCO, PABLO City: MIAMI

Work Mix: Bridge-Repair/Rehabilitation Extra Description: Cont. Class: District Let

Phase Fund Code FY 2022 5 Year Total Construction BRRP $1,585,818 $1,585,818 CEI BRRP $358,020 $358,020 DIH $18,543 $18,543 Total For Project 441960.1 $1,962,381 $1,962,381

October. 10 2019 Page 66 of 151 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

441961.1 SR 994/QUAIL ROOST D R./SW 200 ST OVER CANAL C -102 BRIDGE#870628 PM: COELLO, GEIDY Work Mix: Bridge-Repair/Rehabilitation Extra Description: CNT# E6M47 Cont. Class: District Let

Phase Fund Code FY 2021 5 Year Total Construction BRRP $460,674 $460,674 CEI BRRP $102,600 $102,600 DIH $5,130 $5,130 Total For Project 441961.1 $568,404 $568,404

441963.1 SR 924/GRATIGNY/NW 1 19 ST OVER RIO VISTA CANA L BRIDGE 870621 PM: GOMEZ, HUMBERTO

Work Mix: Bridge-Repair/Rehabilitation Extra Description: LET W/439981-1 (LEAD) AND 439981-2. Cont. Class: Tallahassee Let

Phase Fund Code FY 2022 FY 2023 5 Year Total Construction BRRP $403,915 $403,915 Incentive BRRP $20,000 $20,000 CEI BRRP $91,611 $91,611 DIH $13,689 $13,689 Total For Project 441963.1 $509,215 $20,000 $529,215

441965.1 SR 856 RAMP NB A1A T O SR 856 (BRIDGE 870603) PM: COELLO, GEIDY City: SUNNY ISLES Work Mix: Bridge-Repair/Rehabilitation Extra Description: Cont. Class: District Let

Phase Fund Code FY 2021 FY 2023 5 Year Total P.E. BRRP $185,000 $185,000 DIH $10,000 $10,000 Construction BRRP $1,999,217 $1,999,217 CEI BRRP $415,104 $415,104 DIH $49,726 $49,726 Total For Project 441965.1 $195,000 $2,464,047 $2,659,047

October. 10 2019 Page 67 of 151 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

442120.1 GOLDEN GLADES INTERC HANGE COMMUNICATIONS CONS ULTANT CONTRACT PM: BURGHER, TISH City: HIALEAH - MIAMI GARDENS - MIAMI LAKES Work Mix: Transportation Planning Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 5 Year Total P.E. DIH $20,000 $20,000 Total For Project 442120.1 $20,000 $20,000

442537.1 SR 25/NW 36 STREET B ETWEEN NW 20 AVENUE AND N W 19 AVENUE PM: BARRERA, JOSE City: MIAMI Work Mix: Pedestrian Safety Improvement Extra Description: INSTALL OVERHEAD PEDESTRIAN HYBRID BEACON ON SR 25/NW 36 ST BETWEEN NW 20 AVENUE AND NW 19 AVENUE APPRV BY SCOPING COMMITTEE NOTE: LEAD TO BE LET WITH 4425391, 4425401/ CNT# E6M84 TO BE CREATED 7-1-18 FOR SR915/NE 6 AVE N. OF NE 150 STREET Cont. Class: District Let (RAMON SIERRA TO REQUEST IN PSEE)

Phase Fund Code FY 2021 5 Year Total Construction DDR $363,761 $363,761 LF $5,000 $5,000 CEI DDR $53,352 $53,352 DIH $22,572 $22,572 Total For Project 442537.1 $444,685 $444,685

442538.1 SR 933/NW 12 AVENUE AT NW 19 STREET (TRAFFIC SIGNAL) PM: BARRERA, JOSE City: MIAMI

Work Mix: Pedestrian Safety Improvement Extra Description: INSTALL A FULL TRAFFIC SIGNAL ON SR 933/NW 12 AVENUE AT NW 19 STREET. APPROVED BY SCOPING COMMITTEE NOTE: TO BE LET WITH 4327485 & 4327484 (LEAD) TO BE CREATED 7-1-18 FOR SR915/NE 6 AVE N. OF NE 150 STREET (RAMON SIERRA TO REQUEST IN PSEE) Cont. Class: Tallahassee Let

Phase Fund Code FY 2021 FY 2022 FY 2023 5 Year Total RW Support DIH $12,000 $12,000 DS $7,000 $7,000 Construction DDR $577,571 $577,571 LF $4,000 $4,000 Incentive DDR $24,000 $24,000 CEI DDR $69,498 $69,498 DIH $18,954 $18,954 Total For Project 442538.1 $19,000 $670,023 $24,000 $713,023

October. 10 2019 Page 68 of 151 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

442539.1 SR 944/NW 54 STREET AT NW 14 AVENUE PM: BARRERA, JOSE City: MIAMI Work Mix: Pedestrian Safety Improvement Extra Description: INSTALL OVERHEAD RECTANGULAR RAPID FLASHING BEACON CROSSWALK ON SR 944/NW 54 STREET AT NW 14 AVENUE APPRV BY SCOPING COMMITTEE NOTE: TO BE LET WITH 4425371 (LEAD), 4425401 / CNT# E6M84 TO BE CREATED 7-1-18 FOR SR915/NE 6 AVE N. OF NE 150 STREET Cont. Class: District Let (RAMON SIERRA TO REQUEST IN PSEE)

Phase Fund Code FY 2021 5 Year Total Construction DDR $399,872 $399,872 DS $10,000 $10,000 LF $7,000 $7,000 CEI DDR $53,352 $53,352 DIH $22,572 $22,572 Total For Project 442539.1 $492,796 $492,796

442541.1 SR 973/SW 87 AVENUE AT SW 28TH STREET (TRAFFI C SIGNAL) PM: ARVELO, ANA Work Mix: Pedestrian Safety Improvement Extra Description: INSTALL FULL TRAFFIC SIGNAL ON SR 973/SW 87 AVENUE AT SW 28TH STREET. APPROVED BY SCOPING COMMITTEE NOTE: TO BE LET WITH FM 439924-1/SW 87 AVENUE FROM SW 27 ST. TO 20 TERRACE & POSSIBLY TO BE LET W/NEW PROJECT TO BE CREATED 7012018 FOR SR 968 W. Cont. Class: Tallahassee Let FLAGLER ST & 79 AVE-R. SIERRA CNT# T6488 STRUNG W/4399241 (LEAD)

Phase Fund Code FY 2021 FY 2022 5 Year Total Construction DDR $705,812 $705,812 Incentive DS $50,000 $50,000 CEI DDR $98,496 $98,496 DIH $31,806 $31,806 Total For Project 442541.1 $836,114 $50,000 $886,114

443432.1 SR A1A/MACARTHUR CAU SEWAY FROM SR-5/BISCAYNE BLV TO SR 907/ALTON RD PM: FUENTES, KARINA City: MIAMI

Work Mix: Bike Path/Trail Extra Description: MACARTHUR CAUSEWAY BICYCLE FACILITY IMPROVEMENTS CNT# E6M36 Cont. Class: District Let

Phase Fund Code FY 2022 5 Year Total Construction DDR $592,656 $592,656 CEI DDR $78,975 $78,975 DIH $57,260 $57,260 Total For Project 443432.1 $728,891 $728,891

October. 10 2019 Page 69 of 151 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

443853.1 SR 953/EAST 8 AVENUE AT EAST 32ND STREET PM: DE LA CRUZ, JOAQUIN City: HIALEAH Work Mix: Intersection Improvement Extra Description: STANDALONE SAFETY PROJECT OFFEST NORTHBOUND AND SOUTHBOUND LEFT TURN LANES B/C-1.9, NPV-$335,588, SHSP-INTERSECTIONS CRASHES, SHAREPOINT # D6-207 CNT# T6502 Cont. Class: Tallahassee Let

Phase Fund Code FY 2021 5 Year Total Construction ACSS $420,837 $420,837 SA $149,513 $149,513 CEI ACSS $73,995 $73,995 SA $34,761 $34,761 Total For Project 443853.1 $679,106 $679,106

443855.1 SR 915/NE 6 AVENUE F ROM SOUTH OF NE 147 ST TO NORTH OF NE 154 ST PM: WANG, BAOYING City: NORTH MIAMI Work Mix: Intersection Improvement Extra Description: STANDALONE SAFETY PROJECT, SHAREPOINT# D6-204 INSTALL A MIDBLOCK PEDESTRIAN CROSSING CONTROLLED BY A PEDESTRIAN HYBRID BEACON (HAWK) AND LIGHTING IMPROVEMENTS WITHIN THE AREA OF THE CROSSING. B/C-2.6, NPV-$446,857, SHSO-VULNARABLE ROAD USERS Cont. Class: Tallahassee Let *PH 52-02: TRAFFIC SIGNALS APPROVED BY SCOPING COMM. 4/15/19

Phase Fund Code FY 2021 FY 2022 FY 2023 5 Year Total RW Land ACSA $185,500 $185,500 ACSS $14,500 $14,500 SA $132,552 $132,552 RW Support ACSA $81,780 $81,780 ACSS $14,500 $14,500 SA $125,000 $125,000 Construction ACSS $854,423 $854,423 SA $1,017,104 $1,017,104 CEI ACSS $67,332 $67,332 SA $23,166 $23,166 Total For Project 443855.1 $296,280 $280,718 $1,938,859 $2,515,857

October. 10 2019 Page 70 of 151 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

443857.1 SR 976/SW 40 STREET AT SR 826/PALMETTO SOUTHB OUND OFF RAMP PM: ARVELO, ANA

Work Mix: Intersection Improvement Extra Description: RECONSTRUCT/TIGHTEN RADIUS AT THE NORTHWEST CORNER OF SB OFF RAMP, INSTALL MAST ARMS FOR SOUTHBOUND AND WESTBOUND APPROACHES. B/C-36.2 NPV-$20,906,755. SHSP-INTERSECTION CRASHES SHAREPOINT# D6-208 Cont. Class: Tallahassee Let

Phase Fund Code FY 2022 5 Year Total Construction ACSS $486,519 $486,519 SA $17,466 $17,466 CEI ACSS $86,954 $86,954 SA $33,696 $33,696 Total For Project 443857.1 $624,635 $624,635

443890.1 SR970/SR5/DOWNTOWN D ISTRIBUTOR RAMPS FROM S.M IAMI AVE. TO SE 2 AVE. PM: SOLAUN, JUDY City: MIAMI

Work Mix: Rigid Pavement Rehabilitation Extra Description: FY 2018 RESURFACING PROJECT RAMPS 87006000, 87006047, 87006048, 87270506. RIGID PAVEMENT RHABILITATION PROJECT. STRUNG W/4439421 & 4438941 (LEAD) Cont. Class: District Let

Phase Fund Code FY 2021 FY 2024 5 Year Total P.E. SA $287,500 $287,500 Construction DDR $1,155,757 $1,155,757 CEI DDR $207,757 $207,757 DIH $60,194 $60,194 DS $27,775 $27,775 Total For Project 443890.1 $287,500 $1,451,483 $1,738,983

443899.1 SR A1A/HARDING AVENU E/ABBOTT AVE. FROM N. OF 96 ST. TO INDIAN CREEK DR PM: FUNTANELLAS, IVETTE City: BAL HARBOUR - MIAMI BEACH - SURFSIDE

Work Mix: Resurfacing Extra Description: FY2018 MILLING AND RESURFACING PROJECT. Cont. Class: Tallahassee Let

Phase Fund Code FY 2023 5 Year Total Construction DDR $1,438,474 $1,438,474 NHRE $3,035,272 $3,035,272 CEI DDR $878,988 $878,988 DIH $37,835 $37,835 Total For Project 443899.1 $5,390,569 $5,390,569

October. 10 2019 Page 71 of 151 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

443902.1 SR A1A/COLLINS AVENU E FROM NORTH OF 26 ST. TO 44 ST./INDIAN CREEK DR. PM: SOLAUN, JUDY Work Mix: Resurfacing Extra Description: FY2018 RESURFACING & MILLING Cont. Class: District Let

Phase Fund Code FY 2021 FY 2023 FY 2024 5 Year Total P.E. DIH $20,000 $20,000 GFSA $380,000 $380,000 SA $41,000 $41,000 Construction DDR $2,217,201 $2,217,201 Incentive DDR $200,000 $200,000 CEI DDR $313,490 $313,490 DIH $21,620 $21,620 Total For Project 443902.1 $441,000 $2,552,311 $200,000 $3,193,311

443903.1 SR 932/NW-NE 103 STR EET FROM EAST OF NW 6 AVE TO EAST OF NE 2 AVE PM: SOLAUN, JUDY

Work Mix: Resurfacing - Ride Only Extra Description: 2018 RESURFACING PROJECT RIDE-ONLY PROJECT, MILLING AND RESURFACING. Cont. Class: District Let

Phase Fund Code FY 2021 FY 2023 5 Year Total P.E. DDR $240,000 $240,000 DIH $15,000 $15,000 Construction DDR $1,258,803 $1,258,803 CEI DDR $204,679 $204,679 DIH $16,215 $16,215 Total For Project 443903.1 $255,000 $1,479,697 $1,734,697

443905.1 SR 90/US 41/SW 7 STR EET FROM BRICKELL AVENUE TO WEST OF SW 2 AVENUE PM: SOLAUN, JUDY

Work Mix: Resurfacing Extra Description: 2018 RESURFACING PROJECT MILLING AND RESURFACING. ALSO SEE PD&E STUDY FM 432639-6. Cont. Class: District Let

Phase Fund Code FY 2022 FY 2024 5 Year Total P.E. DDR $205,000 $205,000 DIH $10,000 $10,000 Construction DDR $1,070,648 $1,070,648 CEI DDR $181,062 $181,062 DIH $16,665 $16,665 Total For Project 443905.1 $215,000 $1,268,375 $1,483,375

October. 10 2019 Page 72 of 151 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

443906.1 SR 852/COUNTY LINE R OAD FROM EAST OF NW 27 AV E TO WEST OF NW 1700 BLK PM: SOLAUN, JUDY

Work Mix: Resurfacing Extra Description: 2018 RESURFACING PROJECT MILLING AND RESURFACING. Cont. Class: District Let

Phase Fund Code FY 2021 FY 2023 5 Year Total P.E. DIH $15,000 $15,000 GFSA $260,000 $260,000 Construction DDR $1,535,933 $1,535,933 CEI DDR $250,043 $250,043 DIH $10,810 $10,810 Total For Project 443906.1 $275,000 $1,796,786 $2,071,786

443907.1 SR 994/QUAIL ROOST D RIVE FROM EAST OF KROME A VE TO WEST OF SW 137 AVE PM: SOLAUN, JUDY

Work Mix: Resurfacing Extra Description: 2018 RESURFACING PROJECT MILLING AND RESURFACING. BRIDGE 870628 (CANAL C-102). Cont. Class: Tallahassee Let

Phase Fund Code FY 2021 FY 2023 FY 2024 5 Year Total P.E. DIH $30,000 $30,000 GFSA $690,000 $690,000 Construction DDR $123,109 $123,109 SA $4,456,162 $4,456,162 CEI DDR $751,393 $751,393 DIH $38,885 $38,885 Total For Project 443907.1 $720,000 $4,579,271 $790,278 $6,089,549

443908.1 SR 5/US 1/S DIXIE HI GHWAY FROM SOUTH OF SW 10 0 ST TO SOUTH OF SW 88 ST PM: SOLAUN, JUDY Work Mix: Resurfacing Extra Description: 2018 RESURFACING PROJECT MILLING AND RESURFACING. Cont. Class: District Let

Phase Fund Code FY 2021 5 Year Total P.E. DDR $320,000 $320,000 DIH $20,000 $20,000 Total For Project 443908.1 $340,000 $340,000

October. 10 2019 Page 73 of 151 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

443909.1 SR 934/NW 74 ST/W-E 21 ST FROM EAST OF W 4 AV E TO E 4 AVE PM: SOLAUN, JUDY Work Mix: Resurfacing Extra Description: 2018 RESURFACING PROJECT MILLING AND RESURFACING. Cont. Class: District Let

Phase Fund Code FY 2022 FY 2024 FY 2025 5 Year Total P.E. DDR $340,000 $340,000 DIH $15,000 $15,000 Construction DDR $1,783,616 $1,783,616 CEI DDR $22,220 $276,261 $298,481 DIH $22,220 $22,220 Total For Project 443909.1 $355,000 $1,828,056 $276,261 $2,459,317

443910.1 SR 25/US 27/NW 36 ST REET FROM EAST OF NW 7 AV E TO WEST OF N MIAMI AVE PM: SOLAUN, JUDY Work Mix: Resurfacing Extra Description: 2018 RESURFACING PROJECT EXCEPTIONS AT NW 3 AVE AND NW 1 AVE, SEE FPID 439922-1. MILLING AND RESURFACING. Cont. Class: District Let

Phase Fund Code FY 2021 FY 2023 5 Year Total P.E. DDR $180,000 $180,000 DIH $10,000 $10,000 Construction DDR $860,404 $860,404 CEI DDR $145,470 $145,470 DIH $16,215 $16,215 Total For Project 443910.1 $190,000 $1,022,089 $1,212,089

443911.1 SR 5/US 1/BISCAYNE B LVD. FROM SOUTH OF NE 5 S TREET TO NE 11 STREET PM: SOLAUN, JUDY Work Mix: Resurfacing - Ride Only Extra Description: 2018 RESURFACING PROJECT RIDE-ONLY PROJECT, MILLING AND RESURFACING. PRIORITY 11 2018 Cont. Class: Tallahassee Let

Phase Fund Code FY 2022 FY 2024 5 Year Total P.E. DDR $320,000 $320,000 DIH $20,000 $20,000 Construction NHRE $1,673,572 $1,673,572 CEI DDR $279,710 $279,710 DIH $33,330 $33,330 Total For Project 443911.1 $340,000 $1,986,612 $2,326,612

October. 10 2019 Page 74 of 151 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

443912.1 SR 5/US 1/BISCAYNE B LVD. FROM NE 105 STREET T O NE 123 STREET PM: SOLAUN, JUDY Work Mix: Resurfacing Extra Description: 2018 RESURFACING PROJECT MILLING AND RESURFACING. LEAD STRUNG W/4446361 & 4439351 Cont. Class: District Let

Phase Fund Code FY 2022 FY 2024 5 Year Total P.E. DDR $550,000 $550,000 DIH $30,000 $30,000 Construction DDR $2,915,540 $2,915,540 CEI DDR $466,620 $466,620 DIH $38,885 $38,885 Total For Project 443912.1 $580,000 $3,421,045 $4,001,045

443913.1 SR 886/PORT BOULEVAR D FROM BISCAYNE BLVD. TO PORT MIAMI PM: SOLAUN, JUDY Work Mix: Rigid Pavement Rehabilitation Extra Description: 2018 RESURFACING PROJECT RIGID PAVEMENT REHABILITATION PROJECT. BRIDGES 8750000 AND 875001 (INTRACOASTAL WATERWAY). Cont. Class: District Let

Phase Fund Code FY 2021 5 Year Total P.E. DDR $415,000 $415,000 DIH $20,000 $20,000 Total For Project 443913.1 $435,000 $435,000

443914.1 SR 9/SR 817/NW 27 AV ENUE FROM NORTH OF NW 135 ST TO BURLINGTON ST PM: SOLAUN, JUDY

Work Mix: Resurfacing Extra Description: 2018 RESURFACING PROJECT MILLING AND RESURFACING. BRIDGE 870090 (OPA-LOCKA CANAL). Cont. Class: District Let

Phase Fund Code FY 2021 FY 2023 5 Year Total P.E. DDR $260,000 $260,000 DIH $13,000 $13,000 Construction DDR $1,369,230 $1,369,230 CEI DDR $192,418 $192,418 DIH $16,215 $16,215 Total For Project 443914.1 $273,000 $1,577,863 $1,850,863

October. 10 2019 Page 75 of 151 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

443916.1 SR 5/US 1/S DIXIE HW Y. FROM NORTH OF SW 80 ST . TO SOUTH OF RIVIERA DR. PM: BARRERA, JOSE City: SOUTH MIAMI - CORAL GABELS Work Mix: Resurfacing Extra Description: 2018 RESURFACING PROJECT MILLING AND RESURFACING. SAFETY SHAREPOINT #D6-218 BRIDGE 870019 (CORAL GABLES CANAL/C-3) B/C: 14.7 / NPV: $2,411,619,85. PROVIDE PROTECTED PERMISSIVE LEFT TURN PHASING FOR SOUTHBOUND APPROACH. UPGRADE CROSSWALK TO HIGH Cont. Class: Tallahassee Let EMPHASIS CROSSWALK AND INSTALL PEDESTRIAN WARNING

Phase Fund Code FY 2022 FY 2023 FY 2024 5 Year Total Construction DDR $4,885,713 $4,885,713 Incentive SA $360,000 $360,000 CEI DDR $711,298 $711,298 DIH $42,120 $42,120 Total For Project 443916.1 $4,927,833 $711,298 $360,000 $5,999,131

443917.1 SR 90/SW 8TH STREET FROM EAST OF SW 42 AVENUE TO WEST OF SW 27 AVE PM: DE LA CRUZ, JOAQUIN City: MIAMI - CORAL GABELS

Work Mix: Resurfacing Extra Description: 2018 RESURFACING PROJECT MILLING AND RESURFACING Cont. Class: Tallahassee Let

Phase Fund Code FY 2021 FY 2022 FY 2023 5 Year Total P.E. DIH $5,000 $5,000 $10,000 Construction DDR $746,907 $746,907 SA $1,579,500 $1,579,500 CEI SA $428,090 $428,090 Total For Project 443917.1 $5,000 $2,331,407 $428,090 $2,764,497

443918.1 SR 90/SW 8TH STREET FROM WEST OF SW 57 AVENUE TO WEST OF SW 42 AVENUE PM: DE LA CRUZ, JOAQUIN Work Mix: Resurfacing Extra Description: 2018 RESURFACING PROJECT MILLING AND RESURFACING Cont. Class: Tallahassee Let

Phase Fund Code FY 2021 FY 2022 FY 2023 5 Year Total P.E. DIH $5,000 $5,000 $10,000 Construction DDR $1,691,357 $1,691,357 SA $645,679 $645,679 CEI SA $31,590 $373,874 $405,464 Total For Project 443918.1 $5,000 $2,373,626 $373,874 $2,752,500

October. 10 2019 Page 76 of 151 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

443919.1 SR 90/SW 8TH STREET FROM WEST OF SW 74 COURT TO WEST OF SW 57 AVENUE PM: BARRERA, JOSE Work Mix: Resurfacing Extra Description: 2018 RESURFACING PROJECT EXCEPTION AT SW 67 AVENUE MILLING AND RESURFACING CNT# Cont. Class: Tallahassee Let

Phase Fund Code FY 2022 FY 2023 5 Year Total Construction SA $2,729,142 $2,729,142 CEI DIH $35,431 $35,431 SA $52,650 $363,734 $416,384 Total For Project 443919.1 $2,817,223 $363,734 $3,180,957

443926.1 SR 934/71 STREET FRO M BAY DRIVE EAST TO COLLI NS AVENUE PM: SOLAUN, JUDY

Work Mix: Resurfacing - Ride Only Extra Description: 2018 RESURFACING PROJECT RIDE-ONLY PROJECT, MILLING AND RESURFACING BRIDGE 870709 (INDIAN CREEK WATERWAY) Cont. Class: Tallahassee Let

Phase Fund Code FY 2022 FY 2024 5 Year Total P.E. DDR $220,000 $220,000 DIH $20,000 $20,000 Construction DDR $1,137,087 $1,137,087 NHRE $90,000 $90,000 CEI DDR $187,759 $187,759 DIH $18,453 $18,453 Total For Project 443926.1 $240,000 $1,433,299 $1,673,299

443927.1 SR 953/LEJEUNE ROAD FROM NORTH OF NW 79 ST TO SOUTH OF NW 103 ST PM: BARRERA, JOSE Work Mix: Resurfacing Extra Description: 2018 RESURFACING PROJECT MILLING AND RESURFACING Cont. Class: District Let

Phase Fund Code FY 2021 FY 2023 5 Year Total P.E. DIH $20,000 $20,000 GFSA $425,000 $425,000 Construction DDR $2,568,424 $2,568,424 CEI DDR $351,325 $351,325 DIH $19,458 $19,458 Total For Project 443927.1 $445,000 $2,939,207 $3,384,207

October. 10 2019 Page 77 of 151 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

443931.1 SR A1A/COLLINS AVENU E FROM 44 ST TO 4700 BLOC K PM: SOLAUN, JUDY Work Mix: Resurfacing Extra Description: AND SR A1A/INDIAN CREEK DRIVE FROM 41 ST TO 44 ST 2018 RESURFACING PROJECT MILLING AND RESURFACING Cont. Class: District Let

Phase Fund Code FY 2022 FY 2024 5 Year Total P.E. DDR $250,000 $250,000 DIH $20,000 $20,000 Construction DDR $1,338,977 $1,338,977 CEI DDR $214,779 $214,779 DIH $22,220 $22,220 Total For Project 443931.1 $270,000 $1,575,976 $1,845,976

443932.1 SR 915/NE 6 AVENUE F ROM SOUTH OF NE 123 ST TO NORTH OF NE 145 ST PM: SOLAUN, JUDY Work Mix: Resurfacing Extra Description: EXCEPTION FROM NE 124 ST TO NE 129 ST, MATCH FM 427521-2. EXCEPTION AT NE 135 ST, MATCH FM 429346-2. 2018 RESURFACING PROJECT MILLING AND RESURFACING. LEAD PROJECT GOES WITH FM 443933-1 & 443935-1 Cont. Class: District Let

Phase Fund Code FY 2021 FY 2023 5 Year Total P.E. DIH $20,000 $20,000 GFSA $320,000 $320,000 Construction DDR $1,814,518 $1,814,518 CEI DDR $292,219 $292,219 DIH $27,025 $27,025 Total For Project 443932.1 $340,000 $2,133,762 $2,473,762

443933.1 SR 922/NW-NE 125 STR EET FROM WEST OF NW 1 AVE NUE TO NE 5 AVENUE PM: SOLAUN, JUDY Work Mix: Resurfacing - Ride Only Extra Description: RIDE-ONLY PROJECT, MILLING AND RESURFACING 2018 RESURFACING PROJECT BRIDGE 870671 (BISCAYNE CANAL, C-8) PROJECT GOES WITH FM 443932-1 & 443935-1 Cont. Class: District Let

Phase Fund Code FY 2021 FY 2023 5 Year Total P.E. DDR $250,000 $250,000 DIH $15,000 $15,000 Construction DDR $1,400,479 $1,400,479 CEI DDR $227,167 $227,167 DIH $16,215 $16,215 Total For Project 443933.1 $265,000 $1,643,861 $1,908,861

October. 10 2019 Page 78 of 151 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

443935.1 SR 922/NE 123 STREET FROM W OF BISCAYNE BLVD. TO E OF N BAYSHORE DR. PM: SOLAUN, JUDY Work Mix: Resurfacing - Ride Only Extra Description: 2018 RESURFACING PROJECT RIDE-ONLY PROJECT, MILLING AND RESURFACING PROJECT GOES WITH FM 443932-1 (LEAD) & 444636-1 Cont. Class: District Let

Phase Fund Code FY 2022 FY 2024 5 Year Total P.E. DDR $315,000 $315,000 DIH $20,000 $20,000 Construction DDR $1,664,845 $1,664,845 CEI DDR $269,222 $269,222 DIH $22,220 $22,220 Total For Project 443935.1 $335,000 $1,956,287 $2,291,287

443936.1 SR 909/W DIXIE HIGHW AY FROM SOUTH OF NE 129 S T. TO NORTH OF NE 151 ST. PM: SOLAUN, JUDY Work Mix: Resurfacing Extra Description: EXCEPTION AT NE 135 ST, MATCH FM 429346-2 2018 RESURFACING PROJECT MILLING AND RESURFACING Cont. Class: District Let

Phase Fund Code FY 2021 FY 2023 5 Year Total P.E. DIH $30,000 $30,000 GFSA $600,000 $600,000 Construction SA $3,719,002 $3,719,002 CEI DDR $603,655 $603,655 DIH $27,025 $27,025 Total For Project 443936.1 $630,000 $4,349,682 $4,979,682

443937.1 SR 817/NW 27 AVENUE FROM BURLINGTON STREET TO NW 165 TERRACE PM: SOLAUN, JUDY Work Mix: Resurfacing Extra Description: 2018 RESURFACING PROJECT MILLING AND RESURFACING BRIDGE 870151 (BISCAYNE CANAL/C-8) Cont. Class: District Let

Phase Fund Code FY 2021 FY 2023 5 Year Total P.E. DIH $24,000 $24,000 GFSA $470,000 $470,000 SA $60,000 $60,000 Construction DDR $2,800,655 $2,800,655 CEI DDR $367,540 $367,540 DIH $21,620 $21,620 Total For Project 443937.1 $554,000 $3,189,815 $3,743,815

October. 10 2019 Page 79 of 151 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

443939.1 SR 817/NW 27 AVENUE FROM NW 168 TERRACE TO SO UTH OF NW 187 STREET PM: SOLAUN, JUDY Work Mix: Resurfacing Extra Description: 2018 RESURFACING PROJECT MILLING AND RESURFACING Cont. Class: District Let

Phase Fund Code FY 2021 FY 2023 5 Year Total P.E. DDR $390,000 $390,000 DIH $20,000 $20,000 Construction DDR $2,062,975 $2,062,975 CEI DDR $277,817 $277,817 DIH $21,620 $21,620 Total For Project 443939.1 $410,000 $2,362,412 $2,772,412

443940.1 SR 9/NW 27 AVENUE FR OM NORTH OF NW 116 ST TO SOUTH OF NW 122 ST PM: GOMEZ, HUMBERTO Work Mix: Resurfacing Extra Description: 2018 RESURFACING PROJECT MILLING AND RESURFACING. Cont. Class: District Let

Phase Fund Code FY 2022 5 Year Total Construction DDR $758,049 $758,049 CEI DDR $114,057 $114,057 DIH $11,406 $11,406 DS $15,795 $15,795 Total For Project 443940.1 $899,307 $899,307

443980.1 SR-932/NW 103 ST. FR OM NW 80 CT. TO NW 77 AVE PM: SOLAUN, JUDY City: HIALEAH GARDENS Work Mix: Traffic Ops Improvement Extra Description: UPGRADE SIGNAL TO MAST ARMS AND INCLUDE AN EASTBOUND LEFT TURN PHASE. INCLUDE OVERHEAD DIRECTIONAL SIGNS FOR NORTHBOUND APROACH. Cont. Class: District Let

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 5 Year Total P.E. DDR $130,000 $130,000 DIH $5,000 $5,000 RW Land DDR $107,892 $107,892 RW Support DDR $25,462 $25,462 DIH $20,000 $20,000 Construction DDR $421,091 $421,091 CEI DDR $74,274 $74,274 DIH $6,054 $6,054 Total For Project 443980.1 $135,000 $153,354 $6,054 $495,365 $789,773

October. 10 2019 Page 80 of 151 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

443986.1 SR 915/NE 6TH AVE FR OM NE 113TH ST TO NE 121S T ST PM: WANG, BAOYING City: BISCAYNE PARK

Work Mix: Sidewalk Extra Description: VILLAGE OF BISCAYNE PARK PH32-01 = CNT# NEW/CONSULT: RIBBECK ENG. Cont. Class: District Let

Phase Fund Code FY 2022 5 Year Total Construction DDR $1,822,338 $1,822,338 CEI DDR $326,430 $326,430 DIH $97,929 $97,929 Total For Project 443986.1 $2,246,697 $2,246,697

444444.2 SR-90/US HWY-41/TAMI AMI TRAIL FROM STRUCTURE S-333 TO STRUCTURE S-334 PM: HERNANDEZ, FELIX Work Mix: Flexible Pavement Reconstruct. Extra Description: FOR MP 13.850 TO 14.818; MP 18.039 TO 22.239 AND MP 23.750 TO 24.420; MITIGATE GROWTH AND SPREAD OF ALGAE BLOOMS PH32-07 = TESTHOLES PH32-02 THRU 06 = STIPENDS CC CHANGED FROM 1 (TALLY) TO 9 (DB) 9/12/19 PER REQUEST FROM PRODUCTION Cont. Class: Design Build

Phase Fund Code FY 2021 5 Year Total P.E. ACNP $1,190,000 $1,190,000 DS $257,287 $257,287 Construction ACNP $38,810,000 $38,810,000 PLH $51,970,000 $51,970,000 CEI ACNP $3,244,000 $3,244,000 PLH $8,030,000 $8,030,000 Total For Project 444444.2 $103,501,287 $103,501,287

444450.1 SR 972/SW 13TH ST/SW 3RD AVE/CORAL WAY @ SW 1 5TH RD PM: GARGANTA, NATALIE City: MIAMI

Work Mix: Roundabout Extra Description: 3D DESIGN MODEL W/PROJ DELIVER Cont. Class: District Let

Phase Fund Code FY 2021 FY 2022 FY 2023 5 Year Total RW Support DDR $20,000 $8,114 $28,114 DIH $2,000 $8,000 $10,000 RW Land DDR $1,100,207 $1,100,207 Construction DDR $2,132,377 $2,132,377 CEI DDR $301,813 $301,813 DIH $107,792 $107,792 Total For Project 444450.1 $22,000 $1,116,321 $2,541,982 $3,680,303

October. 10 2019 Page 81 of 151 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

444636.1 SR 5/US 1 AT NORTHEA ST 123RD STREET PM: IGLESIAS, DANIEL Work Mix: Traffic Ops Improvement Extra Description: CAPACITY IMPROVEMENT TO ADD WB DUAL LEFT TURN LANES, EB DUAL LEFT TURN LANES, EXTEND WB RIGHT TURN LANE, MODIFY WB BUS BAY AND MODIFY MEDIAN OPENINGS STRUNG W/4439121 (LEAD) & 4439351 Cont. Class: Tallahassee Let

Phase Fund Code FY 2021 FY 2022 FY 2023 5 Year Total P.E. DDR $130,000 $130,000 DIH $10,000 $10,000 RW Land DDR $67,418 $67,418 RW Support DIH $10,000 $10,000 DS $44,027 $44,027 Construction DDR $952,718 $952,718 CEI DDR $21,620 $21,620 DIH $124,806 $124,806 DS $181,017 $181,017 Total For Project 444636.1 $140,000 $121,445 $1,280,161 $1,541,606

444798.1 SR 90/US 41 OVER SPI LLWAY 12-B BRIDGE# 870028 PM: OROZCO, PABLO

Work Mix: Bridge-Repair/Rehabilitation Extra Description: BRIDGE SUPERSTRUCTURE AND SUBSTRUCTURE REHABILITATION LET WITH 444799-1 (LEAD) Cont. Class: District Let

Phase Fund Code FY 2021 FY 2023 5 Year Total P.E. BRRP $45,000 $45,000 DIH $5,000 $5,000 Construction BRRP $298,356 $298,356 CEI BRRP $70,265 $70,265 DIH $27,025 $27,025 Total For Project 444798.1 $50,000 $395,646 $445,646

October. 10 2019 Page 82 of 151 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

444799.1 SR 90/US 41 OVER SPI LLWAY 12-D BRIDGE# 870031 PM: OROZCO, PABLO Work Mix: Bridge-Repair/Rehabilitation Extra Description: BRIDGE SUPERSTRUCTURE AND SUBSTRUCTURE REHABILITATION LEAD PROJECT GOES WITH 444798-1 Cont. Class: District Let

Phase Fund Code FY 2021 FY 2023 5 Year Total P.E. BRRP $45,000 $45,000 DIH $5,000 $5,000 Construction BRRP $347,001 $347,001 CEI BRRP $76,751 $76,751 DIH $32,430 $32,430 Total For Project 444799.1 $50,000 $456,182 $506,182

444803.1 SR 25/US 27/OKEECHOB EE ROAD DEPRESSED SECTION 87W001 PM: OROZCO, PABLO City: MIAMI SPRINGS Work Mix: Bridge - Painting Extra Description: DEPRESSED SECTION REHABILITATION INCLUDING RAIL BRIDGE PAINTING Cont. Class: District Let

Phase Fund Code FY 2022 FY 2024 5 Year Total P.E. BRRP $150,000 $150,000 DIH $17,000 $17,000 Construction BRRP $1,327,645 $1,327,645 CEI BRRP $277,750 $277,750 DIH $25,553 $25,553 Total For Project 444803.1 $167,000 $1,630,948 $1,797,948

444804.1 SR 934/NE 79 ST OVER INTRACOASTAL CANAL FENDE R BRIDGE# 870085 & 870551 PM: OROZCO, PABLO City: MIAMI BEACH - NORTH BAY Work Mix: Bridge-Repair/Rehabilitation Extra Description: BRIDGE FENDER SYSTEM REPLACEMENT PH52 = CNT#6K68 STRUNG W/4365261 (LEAD) Cont. Class: District Let

Phase Fund Code FY 2022 5 Year Total Construction BRRP $2,951,822 $2,951,822 CEI BRRP $589,680 $589,680 DIH $10,530 $10,530 Total For Project 444804.1 $3,552,032 $3,552,032

October. 10 2019 Page 83 of 151 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

445023.1 I-95 EXPRESS LANES T OLLING & RAMP SIGNALING O PERATIONS PM: MOTTA, ALEJANDRO Work Mix: Other Its Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total Capital Improvement/Operating TOBD $3,312,564 $3,279,472 $3,151,371 $3,103,299 $12,846,706 Total For Project 445023.1 $3,312,564 $3,279,472 $3,151,371 $3,103,299 $12,846,706

445023.2 I-95 EXPRESS LANES I NCIDENT RESPONSE VEHICLE SERVICES PM: MOTTA, ALEJANDRO Work Mix: Other Its Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total Capital Improvement/Operating TOBD $498,080 $498,080 $498,080 $498,080 $1,992,320 Total For Project 445023.2 $498,080 $498,080 $498,080 $498,080 $1,992,320

445023.3 SR 826 EXPRESS LANES TOLLING & RAMP SIGNALING OPERATIONS PM: MOTTA, ALEJANDRO

Work Mix: Other Its Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total Capital Improvement/Operating TOBI $1,949,018 $1,875,562 $1,800,168 $1,725,000 $7,349,748 Total For Project 445023.3 $1,949,018 $1,875,562 $1,800,168 $1,725,000 $7,349,748

445023.4 SR 826 EXPRESS LANES INCIDENT RESPONSE VEHICL E SERVICES PM: MOTTA, ALEJANDRO

Work Mix: Other Its Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total Capital Improvement/Operating TOBI $332,060 $332,060 $332,060 $332,060 $1,328,240 Total For Project 445023.4 $332,060 $332,060 $332,060 $332,060 $1,328,240

October. 10 2019 Page 84 of 151 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

445023.5 I-75 EXPRESS LANES T OLLING & RAMP SIGNALING O PERATIONS PM: MOTTA, ALEJANDRO Work Mix: Other Its Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total Capital Improvement/Operating TOBG $400,683 $400,000 $400,000 $400,000 $1,600,683 Total For Project 445023.5 $400,683 $400,000 $400,000 $400,000 $1,600,683

445023.6 I-75 EXPRESS LANES I NCIDENT RESPONSE VEHICLE SERVICE PM: MOTTA, ALEJANDRO Work Mix: Other Its Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total Capital Improvement/Operating TOBG $332,060 $332,060 $332,060 $332,060 $1,328,240 Total For Project 445023.6 $332,060 $332,060 $332,060 $332,060 $1,328,240

445025.1 I-95 EXPRESS LANES F HP ENHANCED ENFORCEMENT PM: DARDES, CARLOS

Work Mix: Other Its Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2024 FY 2025 5 Year Total Capital Improvement/Operating TOBD $644,000 $644,000 $1,288,000 Total For Project 445025.1 $644,000 $644,000 $1,288,000

445167.1 SR 25/US 27/OKEECHOB EE RD/NW 36TH STREET FROM W. 18 AVE TO NE 2ND AVE PM: MARCHANT, PATRICK City: HIALEAH - MIAMI SPRINGS - MIAMI

Work Mix: Lighting Extra Description: 16 INTERSECTIONS LEAD STRUNG W/4451681 & 4401772 CNT# T6497 PER J. SANTOS EMAIL DATED 3/8/19:BC = 33 NPV = $32,727,399 Cont. Class: Tallahassee Let

Phase Fund Code FY 2021 5 Year Total Construction ACSS $398,643 $398,643 CEI ACSS $78,489 $78,489 SA $114,399 $114,399 Total For Project 445167.1 $591,531 $591,531

October. 10 2019 Page 85 of 151 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

445168.1 SR 934/E. 25TH STREE T FROM PALM AVENUE TO NE 5TH AVENUE PM: MARCHANT, PATRICK City: HIALEAH - MIAMI Work Mix: Lighting Extra Description: 25 INTERSECTIONS STRUNG W/ 4451671 (LEAD) & 4401772 CNT# T6497 PER J. SANTOS EMAIL DATED 3/8/19:BC = 47 NPV = $45,200,234 Cont. Class: Tallahassee Let

Phase Fund Code FY 2021 5 Year Total Construction ACSS $458,213 $458,213 CEI ACSS $98,496 $98,496 SA $54,378 $54,378 Total For Project 445168.1 $611,087 $611,087

445746.1 SR 932/NW 103RD STRE ET AND NW 32 AVENUE PM: SOLAUN, JUDY

Work Mix: Intersection Improvement Extra Description: B/C: 3.9/NPV:$4,801,857/SHSP: INTERSECTION CRASHES OFFSET EASTBOUND AND WESTBOUND LEFT TURN LANES. ADD AN EXCLUSIVE RIGHT TURN LANE ON EASTBOUND APPROACH. PROVIDE TURNING GUIDLINES PAVEMENT MARKINGS. SAFETY SHAREPOINT #D6-213 Cont. Class: Tallahassee Let

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 5 Year Total P.E. ACSS $249,195 $249,195 SA $38,000 $38,000 RW Land ACSS $196,924 $196,924 SA $400,000 $100,000 $500,000 RW Support ACSS $180,000 $180,000 SA $100,000 $26,676 $126,676 Total For Project 445746.1 $287,195 $376,924 $500,000 $126,676 $1,290,795

445747.1 SR 852/NW 215 STREET AND NW 2 AVENUE PM: SOLAUN, JUDY Work Mix: Intersection Improvement Extra Description: B/C: 16.2/NPV: $6,453,327/SHSP: INTERSECTION CRASHES WIDEN TO ADD AN ADDITIONAL WB RIGHT TURN LANE. PROVIDE BACKPLATES AND ADDITIONAL SIGNAL HEAD ON THE NEW MAST ARM FOR ON EASTBOUND APPROACH SAFETY SHAREPOINT #D6-214 Cont. Class: Tallahassee Let

Phase Fund Code FY 2021 FY 2023 5 Year Total P.E. ACSA $10,000 $10,000 ACSS $63,833 $63,833 Construction ACSS $438,592 $438,592 CEI ACSS $43,182 $43,182 SA $5,405 $5,405 Total For Project 445747.1 $73,833 $487,179 $561,012

October. 10 2019 Page 86 of 151 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

445764.1 SR 5/US 1/OVERSEAS H WY FROM MP 0.00 TO 13.55 PM: FUNTANELLAS, IVETTE Work Mix: Signing/Pavement Markings Extra Description: SR 5/US 1/OVERSEAS HWY FROM MP 0.00 TO 13.55 INSIDE SHOULDER NORTHBOUND AND FROM MP 0.265 TO MP 1.790, MP 2.915 TO 3.405, MP 3.535 TO 13.550 OUTSIDE SHOULDER SOUTHBOUND. PROVIDE GROUND IN RUMBLE STRIPS ON THE INSIDE AND OUTSIDE SHOULDERS/SAFETY Cont. Class: Tallahassee Let SHAREPOINT #D6-216/STRUNG W/4457631(LEAD) B/C: 68/NPV: $13,289,271/SHSP: LANE DEPARTURE CRASHES

Phase Fund Code FY 2022 5 Year Total Construction ACSS $194,797 $194,797 CEI ACSS $29,345 $29,345 SA $6,318 $6,318 Total For Project 445764.1 $230,460 $230,460

445804.1 SR 994/SW 200 ST/QUA IL ROOST DRIVE FROM SW 13 7 AVE TO SW 127 AVE PM: BENITEZ, HONG Work Mix: Pd&E/Emo Study Extra Description: *CREATED FY2021 FOR SEPTEMBER 2020 EXECUTION* PROJECT REPLACES FM 443915-1 Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2023 5 Year Total PDE DDR $540,000 $540,000 DIH $50,000 $50,000 P.E. DDR $600,000 $600,000 DIH $50,000 $50,000 Total For Project 445804.1 $590,000 $650,000 $1,240,000

445987.1 SR 9336/SW 392 ST FR OM EVERGLADES NATIONAL PA RK TO SW 192 AVE PM: SOLAUN, JUDY Work Mix: Resurfacing Extra Description: 2019 RRR CANDIDATE #C-1 Cont. Class: District Let

Phase Fund Code FY 2021 FY 2023 5 Year Total P.E. SN $1,220,000 $1,220,000 Construction DDR $5,775,515 $5,775,515 DS $169,985 $169,985 CEI DDR $556,715 $556,715 DIH $59,455 $59,455 Total For Project 445987.1 $1,220,000 $6,561,670 $7,781,670

October. 10 2019 Page 87 of 151 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

445989.1 SR 9336/SW 192 AVE F ROM 376 ST TO S OF SW 344 ST PM: SOLAUN, JUDY Work Mix: Resurfacing Extra Description: 2019 RRR CANDIDATE #C-2 Cont. Class: District Let

Phase Fund Code FY 2021 FY 2023 5 Year Total P.E. DIH $20,000 $20,000 GFSA $450,000 $450,000 Construction DDR $2,378,200 $2,378,200 CEI DDR $190,256 $190,256 DIH $21,620 $21,620 DS $40,538 $40,538 Total For Project 445989.1 $470,000 $2,630,614 $3,100,614

445990.1 SR 976/SW 40 ST/BIRD ROAD FROM EAST OF SW 87 AVE TO WEST OF SR 826 PM: SOLAUN, JUDY

Work Mix: Resurfacing Extra Description: Cont. Class: District Let

Phase Fund Code FY 2022 FY 2024 5 Year Total P.E. DDR $380,000 $380,000 DIH $30,000 $30,000 Construction DDR $2,333,100 $2,333,100 CEI DDR $305,525 $305,525 DIH $38,885 $38,885 Total For Project 445990.1 $410,000 $2,677,510 $3,087,510

445991.1 SR 976/SW 40 ST/BIRD ROAD FROM E OF SR 826 TO SW 58 AVE PM: SOLAUN, JUDY

Work Mix: Resurfacing Extra Description: Cont. Class: District Let

Phase Fund Code FY 2022 FY 2024 5 Year Total P.E. DDR $625,000 $625,000 DIH $45,000 $45,000 Construction DDR $3,777,400 $3,777,400 CEI DDR $555,500 $555,500 DIH $72,215 $72,215 Total For Project 445991.1 $670,000 $4,405,115 $5,075,115

October. 10 2019 Page 88 of 151 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

445992.1 SR 9336/SW 344 ST/ P ALM DRIVE FROM SW 192 AVE TO W OF SR 5/US-1 PM: SOLAUN, JUDY Work Mix: Resurfacing Extra Description: EXCEPTION AT KROME AVENUE 2019 RRR CANDIDATE #C-3 Cont. Class: District Let

Phase Fund Code FY 2021 FY 2023 5 Year Total P.E. DIH $20,000 $20,000 GFSA $430,000 $430,000 Construction DDR $2,270,100 $2,270,100 CEI DDR $181,608 $181,608 DIH $37,835 $37,835 DS $27,025 $27,025 Total For Project 445992.1 $450,000 $2,516,568 $2,966,568

445993.1 SR 932/NW 103 ST/W 4 9 ST FROM WEST OF NW 82 A VE TO EAST OF W 6 AVE PM: SOLAUN, JUDY

Work Mix: Resurfacing Extra Description: Cont. Class: District Let

Phase Fund Code FY 2022 FY 2024 5 Year Total P.E. DDR $950,000 $950,000 DIH $65,000 $65,000 Construction DDR $6,443,800 $6,443,800 CEI DDR $777,700 $777,700 DIH $83,325 $83,325 Total For Project 445993.1 $1,015,000 $7,304,825 $8,319,825

445995.1 SR 913/SW/SE 26 ROAD FROM SW 1 AVE TO RICKENB ACKER CAUSEWAY PM: SOLAUN, JUDY

Work Mix: Resurfacing Extra Description: Cont. Class: District Let

Phase Fund Code FY 2022 FY 2024 5 Year Total P.E. DDR $165,000 $165,000 DIH $15,000 $15,000 Construction DDR $1,011,010 $1,011,010 CEI DDR $161,095 $161,095 DIH $22,220 $22,220 Total For Project 445995.1 $180,000 $1,194,325 $1,374,325

October. 10 2019 Page 89 of 151 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

445996.1 SR 5/US 1/BISCAYNE B LV FROM NE 61 ST TO NE 6 AVE PM: SOLAUN, JUDY Work Mix: Resurfacing Extra Description: Cont. Class: District Let

Phase Fund Code FY 2022 FY 2024 5 Year Total P.E. DDR $400,000 $400,000 DIH $30,000 $30,000 Construction DDR $2,444,200 $2,444,200 CEI DDR $394,405 $394,405 DIH $27,775 $27,775 Total For Project 445996.1 $430,000 $2,866,380 $3,296,380

445997.1 SR 916/NW 138 ST FRO M NW 67 AVE TO NW 57 AVE PM: SOLAUN, JUDY Work Mix: Resurfacing Extra Description: Cont. Class: District Let

Phase Fund Code FY 2022 FY 2024 FY 2025 5 Year Total P.E. DDR $225,000 $225,000 DIH $20,000 $20,000 Construction DDR $1,333,200 $1,333,200 CEI DDR $212,212 $212,212 DIH $38,885 $38,885 Total For Project 445997.1 $245,000 $1,372,085 $212,212 $1,829,297

445998.1 SR 972/CORAL WAY/SW 3 AVE FROM WEST OF SW 12 AVE TO BRICKELL AVE PM: SOLAUN, JUDY Work Mix: Resurfacing Extra Description: EXCEPTION AT SW 15 ROAD (BMP 4.102 TO EMP 4.323) Cont. Class: District Let

Phase Fund Code FY 2022 FY 2024 5 Year Total P.E. DDR $450,000 $450,000 DIH $35,000 $35,000 Construction DDR $2,888,600 $2,888,600 CEI DDR $399,960 $399,960 DIH $44,440 $44,440 Total For Project 445998.1 $485,000 $3,333,000 $3,818,000

October. 10 2019 Page 90 of 151 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

445999.1 SR 7/US 441/NW 8 AVE /NW 7 AVE FROM N OF NW 3 ST TO S OF NW 8 ST PM: SOLAUN, JUDY Work Mix: Resurfacing Extra Description: Cont. Class: District Let

Phase Fund Code FY 2022 FY 2024 5 Year Total P.E. DDR $125,000 $125,000 DIH $15,000 $15,000 Construction DDR $555,500 $555,500 CEI DDR $86,658 $86,658 DIH $72,771 $72,771 Total For Project 445999.1 $140,000 $714,929 $854,929

446000.1 SR 90/TAMIAMI TRAIL/ SW 8 ST FROM BEACOM BLVD TO SW 4 AVE PM: SOLAUN, JUDY Work Mix: Resurfacing Extra Description: Cont. Class: District Let

Phase Fund Code FY 2022 FY 2024 FY 2025 5 Year Total P.E. DDR $500,000 $500,000 DIH $30,000 $30,000 Construction DDR $1,328,950 $1,328,950 SA $1,670,750 $1,670,750 CEI DDR $503,360 $503,360 DIH $55,550 $55,550 Total For Project 446000.1 $530,000 $3,055,250 $503,360 $4,088,610

446001.1 SR 976/BIRD ROAD/SW 40 ST FROM E OF LAGUNA ST TO WEST OF SW 38 AVE PM: SOLAUN, JUDY

Work Mix: Resurfacing Extra Description: Cont. Class: District Let

Phase Fund Code FY 2022 FY 2024 5 Year Total P.E. DDR $125,000 $125,000 DIH $15,000 $15,000 Construction DDR $499,950 $499,950 CEI DDR $87,769 $87,769 DIH $77,392 $77,392 Total For Project 446001.1 $140,000 $665,111 $805,111

October. 10 2019 Page 91 of 151 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

446002.1 SR 953/LEJEUNE RD/SW 42 AVE FROM S DIXIE HIGH WAY TO S OF ALTARA AVE PM: SOLAUN, JUDY Work Mix: Resurfacing Extra Description: Cont. Class: District Let

Phase Fund Code FY 2022 FY 2024 5 Year Total P.E. DDR $125,000 $125,000 DIH $15,000 $15,000 Construction DDR $611,050 $611,050 CEI DDR $99,990 $99,990 DIH $80,048 $80,048 Total For Project 446002.1 $140,000 $791,088 $931,088

446189.1 SR112-W 41ST STREET OVER INDIAN CREEK WATERWA Y - BRIDGE # 870055 PM: OROZCO, PABLO Work Mix: Bridge-Repair/Rehabilitation Extra Description: Cont. Class: District Let

Phase Fund Code FY 2024 5 Year Total P.E. BRRP $50,000 $50,000 Total For Project 446189.1 $50,000 $50,000

446190.1 SR 9 - NW 27TH AVENU E OVER MIAMI RIVER - BRID GE # 870731 & 870763 PM: OROZCO, PABLO Work Mix: Bridge-Repair/Rehabilitation Extra Description: Cont. Class: District Let

Phase Fund Code FY 2024 5 Year Total P.E. BRRP $260,000 $260,000 Total For Project 446190.1 $260,000 $260,000

446263.1 TRAFFIC OPERATIONS P USH-BUTTON ROADS MIAMI DA DE COUNTY PM: KHAN, SAUD

Work Mix: Miscellaneous Construction Extra Description: PREVIOUS PROJECT FM 431433-8 Cont. Class: District Let

Phase Fund Code FY 2021 5 Year Total Construction DS $1,000,000 $1,000,000 CEI DS $180,000 $180,000 Total For Project 446263.1 $1,180,000 $1,180,000

October. 10 2019 Page 92 of 151 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

446263.3 TRAFFIC OPERATIONS P USH-BUTTON ROADS MIAMI DA DE COUNTY PM: KHAN, SAUD Work Mix: Miscellaneous Construction Extra Description: Cont. Class: District Let

Phase Fund Code FY 2025 5 Year Total Construction DS $1,000,000 $1,000,000 CEI DS $180,000 $180,000 Total For Project 446263.3 $1,180,000 $1,180,000

446264.1 TRAFFIC OPERATIONS P USH-BUTTONS SIGNALS MIAMI -DADE COUNTY PM: KHAN, SAUD Work Mix: Miscellaneous Construction Extra Description: PREVIOUS PROJECT # FM 431434-5 Cont. Class: District Let

Phase Fund Code FY 2021 5 Year Total Construction DS $1,000,000 $1,000,000 CEI DS $180,000 $180,000 Total For Project 446264.1 $1,180,000 $1,180,000

446482.1 I-95 OFF RAMPS/I-395 /I-195/SR 856/SR 826 @ VA RIOUS LOCATIONS PM: ARVELO, ANA City: AVENTURA - MIAMI BEACH - MIAMI - NORTH MIAMI - SUNNY ISLES Work Mix: Its Freeway Management Extra Description: SCOPE: INSTALL WRONG WAY DRIVING COUNTERMEASURES ON LIMITED ACCESS FACILITIES EXIT RAMPS TO MEET REQUIREMENTS IN ROADWAY DESIGN BULLETIN 19-03. MAIN IMPROVEMENT INCLUDE THE INSTALLATION OF LIGHT EMITTING DIODE (LED) WRONG WASY SIGNS INTEGRATED Cont. Class: Tallahassee Let BACK TO THE TRAFFIC MANAGMENT CENTER (TMC) AT 38 EXIT RAMPS ALONG I-95,I-395, SR 856, SR 826 ***WP45***

Phase Fund Code FY 2021 5 Year Total Construction ACID $1,169,640 $1,169,640 CEI SA $242,115 $242,115 Total For Project 446482.1 $1,411,755 $1,411,755

446605.1 DISTRICTWIDE PUSHBUT TON FOR TRAFFIC SIGNAL MA ST ARM PM: OROZSCO, PABLO

Work Mix: Miscellaneous Construction Extra Description: SR-A1A/COLLINS AVE. & 75 ST.; SR-A1A/COLLINS AVE. & 8 ST; SR-A1A/ABBOTT AVE. & INDIAN CREEK DR; SR-A1A/COLLINS AVE. @ 65 ST; Cont. Class: District Let

Phase Fund Code FY 2021 5 Year Total Construction BRRP $434,000 $434,000 CEI BRRP $78,120 $78,120 DIH $20,000 $20,000 Total For Project 446605.1 $532,120 $532,120

October. 10 2019 Page 93 of 151 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

446605.3 DISTRICTWIDE PUSHBUT TON FOR TRAFFIC SIGNAL MA ST ARM PM: OROZSCO, PABLO Work Mix: Miscellaneous Construction Extra Description: SR-934/NORMANDY DR & RU VERSAILLES DR. SR-985 (NW 107 AVE) & SR-836 ON/OFF RAMPS Cont. Class: District Let

Phase Fund Code FY 2021 5 Year Total Construction BRRP $368,000 $368,000 CEI BRRP $66,240 $66,240 DIH $20,000 $20,000 Total For Project 446605.3 $454,240 $454,240

446872.1 SR 924/NW 119TH ST F ROM SR-9A/I-95 NB OFF-RAM P TO SR-909/W. DIXIE HWY PM: SCHOT, KEVIN

Work Mix: Landscaping Extra Description: STANDALONE LANDSCAPE PROJECT - NO IRRIGATION CNT# E6M88 Cont. Class: District Let

Phase Fund Code FY 2021 5 Year Total Construction DDR $275,000 $275,000 CEI DDR $61,250 $61,250 DIH $10,000 $10,000 Total For Project 446872.1 $346,250 $346,250

FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total HIGHWAY SYSTEM: 03 Total $416,170,062 $445,285,910 $236,049,195 $901,065,684 $471,501,216 $2,470,072,067 HIGHWAY SYSTEM: 06 NON-INTRASTATE OFF STATE HIWAY

251271.6 NORTH BEACH CORRIDOR -VARIOUS BIKE PATH LINKS , ADA ACCESS, SIDEWALK + PM: NUNEZ, XIOMARA Work Mix: Bike Path/Trail Extra Description: EXTEND ADA ACCESS, SIDEWALK, LANDSCAPE AND IRRIGATION IMPROVEMENTS, LINK BIKE FACILITIES MUNICIPALITY: CITY OF MIAMI BEACH CNT# Cont. Class: Local Agcy Pgm (Lap)

Phase Fund Code FY 2024 5 Year Total JPA/LAP Construction TALU $291,760 $291,760 CEI SA $5,000 $5,000 Total For Project 251271.6 $296,760 $296,760

October. 10 2019 Page 94 of 151 HIGHWAY SYSTEM: 06 NON-INTRASTATE OFF STATE HIWAY

405575.6 SR998/SW 312 ST/CAMP BELL DR FROM SR997/KROME AVE TO SR5/US1(TRKBYPASS) PM: BARRERA, JOSE City: HOMESTEAD

Work Mix: Flexible Pavement Reconstruct. Extra Description: KROME AVENUE TRUCK BY PASS - LET W/4055757 & 4055758 PD & E PERFORMED UNDER FM #405575-2 LEAD PROJECT T-6450 NOTE: LOCAL ROAD TO BE TRANSFERRED TO STATE - NEW SIS NOTE: EXCEPTION GRANTED BY TREY TILLANDER ON 11-10-15 FROM REQUIREMENTS- Cont. Class: Tallahassee Let PROGRAM MGMT BULLETIN #15-03 DATED 9-21-15. SEE WP45 FOR PH 56* PH52-01=CNT# C9L89

Phase Fund Code FY 2021 5 Year Total RW Land ACNP $5,539,439 $5,539,439 SU $1,824,294 $1,824,294 Incentive SU $980,000 $980,000 Total For Project 405575.6 $8,343,733 $8,343,733

405575.7 SW 336 ST/DAVIS PKWY FROM W. OF SR 997/KROME AVE TO US1 (TRUCK BYPASS) PM: QUINTELA, RAUL City: FLORIDA CITY

Work Mix: Flexible Pavement Reconstruct. Extra Description: KROME AVENUE TRUCK BY PASS - LET W/4055756 (LEAD) & 4055758 PD & E PERFORMED UNDER FM #405575-2 CNT# T6450 NOTE: EXCEPTION GRANTED BY TREY TILLANDER ON 11-10-15 FROM REQUIREMENTS-PROGRAM MGMT BULLETIN #15-03 DATED 9-21-15. PH56-01/CITY OF Cont. Class: Tallahassee Let FLORIDA CITY $146,981 (REIMBURSE) TO THEIR FACILITY RELOCATION DESIGN & CST.

Phase Fund Code FY 2021 5 Year Total Incentive SA $300,000 $300,000 Total For Project 405575.7 $300,000 $300,000

439088.1 HIALEAH GARDENS BOUL EVARD FROM W. 80TH STREET TO NW 138 STREET PM: RAGHUNANDAN, RYAN City: HIALEAH Work Mix: Add Turn Lane(S) Extra Description: ADD NORTHBOUND LEFT TURN LANE @ NW 138 ST & HIALEAH GRDNS BLVD, ADD SB LEFT LANE AT W 84 ST & HIALEAH GRDNS BLVD, ADD NB RIGHT TURN LANE AT W 84 ST & HIALEAH GRDNS BLVD, MILLING AND RESURFACING ALONG THE PROJECT LIMITS, INSTALL ITS ADMS Cont. Class: Tallahassee Let SIGNS AS PER SCOPE (APPROX. CONST.$1,228,220). AS OF 7-18-17 (60% PLANS/EST. = $2,150,366 PER C.ALFARO). CONTRACT# T6464

Phase Fund Code FY 2021 5 Year Total Incentive SA $160,000 $160,000 Total For Project 439088.1 $160,000 $160,000

443861.1 GOLDEN GLADES BICYCL E-PED CONNECTOR TO SUNSHI NE STATE INDUSTRIAL PARK PM: CARTAYA, NILIA

Work Mix: Bike Path/Trail Extra Description: DESIGN/CST (1) KISS & RIDE TERMINAL FACILITY & (2) COVERED PEDESTRAIN & BICYCLE OVERPASS CONNECTING THE TERMINAL TO THE EXISTING TRI-RAIL STATION AND GOLDEN GLADES MULTIMODAL TRANSPORTATION FACILITY. INCLUDES LAND ACQUISITION. APPROX. MP Cont. Class: Extern Mngd(Not Lap) SFRC IS SX 1027.21 (+/- 0.005)

Phase Fund Code FY 2023 5 Year Total Construction CIGP $3,484,050 $3,484,050 LFP $3,484,050 $3,484,050 Total For Project 443861.1 $6,968,100 $6,968,100

October. 10 2019 Page 95 of 151 HIGHWAY SYSTEM: 06 NON-INTRASTATE OFF STATE HIWAY

444805.1 NW 87 AVENUE NORTHBO UND & SOUTHBOUND OVER I-7 5 BRIDGE# 870600 & 871001 PM: OROZCO, PABLO Work Mix: Bridge - Painting Extra Description: BRIDGE SUPERSTRUCTURE AND SUBSTRUCTURE REHABILITATION INCLUDING BRIDGE PAINTING Cont. Class: District Let

Phase Fund Code FY 2022 5 Year Total Construction BRRP $1,269,277 $1,269,277 CEI BRRP $294,840 $294,840 DIH $26,325 $26,325 Total For Project 444805.1 $1,590,442 $1,590,442

446298.1 SAFE RTS. TO SCHOOL - CAROL CITY MIDDLE SCHOO L PM: NUNEZ, XIOMARA

Work Mix: Pedestrian Safety Improvement Extra Description: FY20 SAFE ROUTES TO SCHOOL TPO PRIORITY #8 SCHOOL: CAROL CITY MIDDLE SCHOOL SCOPE: ADDING CROSSWALKS, ENHANCING EXISTING CROSSWALKS, FIL ING SIDEWALK GAPS, ADDING PEDESTRIAN SIGNANGE, ADDING SCHOOL ZONE SIGNAGE, UPGRADING ADA RAMPS. Cont. Class: Local Agcy Pgm (Lap) B/C:3153.41/SHSP:

Phase Fund Code FY 2025 5 Year Total P.E. SU $162,435 $162,435 Total For Project 446298.1 $162,435 $162,435

446300.1 SAFE RTS. TO SCHOOL - HIALEAH SENIOR HIGH SCH OOL PM: NUNEZ, XIOMARA Work Mix: Pedestrian Safety Improvement Extra Description: FY20 SAFE ROUTES TO SCHOOL TPO PRIORITY #8 SCHOOL: HIALEAH SENIOR HIGHSCHOOL SCOPE: ADDING CROSSWALKS, ENHANCING EXISTING CROSSWALKS, FILLING SIDEWALK GAPS, ADDING PEDSTRAIN SIGNAGE, ADDING SCHOOL ZONE SINAGE, UPGRADING ADA RAMPS. Cont. Class: Local Agcy Pgm (Lap) B/C:1045.52/SHSP:__

Phase Fund Code FY 2025 5 Year Total P.E. SU $169,125 $169,125 Total For Project 446300.1 $169,125 $169,125

446303.1 SAFE RTS. TO SCHOOL - GEORGIA JONES-AYERS MID DLE PM: NUNEZ, XIOMARA

Work Mix: Pedestrian Safety Improvement Extra Description: FY20 SAFE ROUTES TO SCHOOL TPO PRIORITY #8 SCHOOL: GEORGIA JONES-AYERS MIDDLE B/C: 4467.09/SHSP: SCOPE: INSTALL SCHOOL ZONE SIGNAGE INSTALL/UPGRADE TO HIGH EMPHASIS CROSSWALK, INSTALL ADA RAMPS, INSTALL 15 MPH SCHOOL SIGN FLASHING Cont. Class: Local Agcy Pgm (Lap) BEACON ASSEMBLY. INSTALL/UPGRADE DETECTABLE WARNING SURFACE. ADDING CROSSWALKS, ENHANCING EXISTING

Phase Fund Code FY 2023 5 Year Total P.E. SU $277,207 $277,207 Total For Project 446303.1 $277,207 $277,207

FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total HIGHWAY SYSTEM: 06 Total $8,803,733 $1,590,442 $7,245,307 $296,760 $331,560 $18,267,802 HIGHWAY SYSTEM: 08 TRANSIT

October. 10 2019 Page 96 of 151 HIGHWAY SYSTEM: 08 TRANSIT

405133.4 MDT - FTA SEC 5307 M ETRORAIL & METROMOVER GUI DEWAY BRIDGE INSPECTNS PM: FREEMAN, RAYMOND Work Mix: Fixed Guideway Improvements Extra Description: CAPITALIZATION OF TRANSIT BRIDGE (GUIDEWAY) INSPECTION CONTINUES PROJECT FM# 4051333. BRIDGE INSPECTION IS REQUIRED BY 335.074 FTA Transfer Not Shown F.S. ****SEE WP45**** FTA TRANSFER. TOLL REVENUE CREDIT PROVIDES LOCAL MATCH MPO PRIORITY LISTING# 24/MPO RESOL.#31-15 Cont. Class: Extern Mngd(Not Lap) TEMP. FTA GRANT# 1089-2019-8/EXECUTED BY DTPW:9/6/16 PER E. CARSON EMAIL.

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total Capital Improvement/Operating LF $250,000 $250,000 $250,000 $250,000 $250,000 $1,250,000 SU $1,000,000 $1,000,000 $1,000,000 $1,000,000 $1,000,000 $5,000,000 Total For Project 405133.4 $1,250,000 $1,250,000 $1,250,000 $1,250,000 $1,250,000 $6,250,000

417917.4 MDT - SOUTH MIAMI-DA DE TRANSITWAY ROUTES: DAD ELAND TO FLORIDA CITY PM: FREEMAN, RAYMOND Work Mix: Urban Corridor Improvements Extra Description: MDT -TRANSIT CORRIDOR PROGRAM/OPERATING ASSISTANCE FOR SOUTH MIAMI-DADE BUSWAY ROUTES.100% STATE PARTICIPATION RATE FROM DADELAND SOUTH METRORAIL STATION TO FLORIDA CITY PER RESOLUTION R-457-16; Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2021 5 Year Total Capital Improvement/Operating DPTO $467,012 $467,012 Total For Project 417917.4 $467,012 $467,012

417917.5 MDT - SOUTH MIAMI-DA DE TRANSITWAY ROUTES: DAD ELAND TO FLORIDA CITY PM: FREEMAN, RAYMOND

Work Mix: Urban Corridor Improvements Extra Description: MDT -TRANSIT CORRIDOR PROGRAM/OPERATING ASSISTANCE FOR SOUTH MIAMI-DADE BUSWAY ROUTES.100% STATE PARTICIPATION RATE FROM DADELAND SOUTH METRORAIL STATION TO FLORIDA CITY PER RESOLUTION R-457-16; Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2022 5 Year Total Capital Improvement/Operating DPTO $959,888 $959,888 Total For Project 417917.5 $959,888 $959,888

420452.2 SOUTH FLA COMMUTER S ERVICES IN MIAMI-DADE COU NTY - TDM OUTREACH PM: FREEMAN, RAYMOND

Work Mix: Commuter Trans. Assistance Extra Description: SFCS - TRANSPORTATION DEMAND MANAGEMENT OUTREACH SERVICES IN MIAMI DADE COUNTY. LOCALIZED TDM OUTREACH AND SPECIAL PROJECT SUPPORT. FUNDING SUPPORTS FOUR (4) OUTREACH PERSONNEL. CONTINUATION FROM FM 4204521. Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total Planning SU $50,000 $50,000 $50,000 $50,000 $50,000 $250,000 Total For Project 420452.2 $50,000 $50,000 $50,000 $50,000 $50,000 $250,000

October. 10 2019 Page 97 of 151 HIGHWAY SYSTEM: 08 TRANSIT

420462.5 MDT - 95 EXPRESS DAD E BROWARD EXPRESS (MIAMI CBD) PM: FREEMAN, RAYMOND Work Mix: Urban Corridor Improvements Extra Description: OPERATING ASSISTANCE TO CONTINUE MDTA 95 EXPRESS BUS SERVICE (SEE ALSO 4154561 FOR ROADWAY & 4242191) **WP45** STATE PART. RATE: 100% UNDER TRANSIT CORRIDOR PROGRAM EST. COST: MIAMI TO SHERIDAN ST. - $1.8 M/YEAR MIAMI TO BROWARD BLVD - $2.1 Cont. Class: Extern Mngd(Not Lap) M/YEAR PH.84, SEQ.01=MDT GRANT (CONTINUES SEGMENT 1)

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total Capital Improvement/Operating TOBD $800,000 $800,000 $800,000 $800,000 $800,000 $4,000,000 Total For Project 420462.5 $800,000 $800,000 $800,000 $800,000 $800,000 $4,000,000

420462.9 SOUTH FLA COMMUTER S ERVICES IN MIAMI-DADE I-9 5 EXPRESS CALL CENTER PM: FREEMAN, RAYMOND

Work Mix: Commuter Trans. Assistance Extra Description: SOUTH FLORIDA COMMUTER SERVICES, 95 EXPRESS CALL CENTER Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total Planning TOBD $200,000 $200,000 $138,029 $138,029 $138,029 $814,087 Total For Project 420462.9 $200,000 $200,000 $138,029 $138,029 $138,029 $814,087

422239.2 SOUTH FLA COMMUTER S ERVICES IN MIAMI-DADE COU NTY - OPERATIONS PM: FREEMAN, RAYMOND

Work Mix: Commuter Trans. Assistance Extra Description: MIAMI-DADE (D6) SHARE OF REGIONAL TDM PROJECT CONTINUES FM 4222391 LF=TMI AGREEMENT W/CITY OF MIAMI BEACH (COMB) PH12- 01=WIRE TRNFER (LF) RECIEVED IN THE AMT OF $19,871.28 FOR CITY OF MIA BCH PER C. HENRIQUES EMAIL DATED 10/23/2018. Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 5 Year Total Planning DDR $84,475 $84,475 Total For Project 422239.2 $84,475 $84,475

422239.5 SOUTH FLA COMMUTER S ERVICES IN MIAMI-DADE COU NTY - OPERATIONS PM: FREEMAN, RAYMOND Work Mix: Commuter Trans. Assistance Extra Description: COMMUTER ASSISTANCE PROGRAM FUNDING FOR THE SOUTH FLORIDA COMMUTER SERVICES CONTRACT FOR D4/D6. FUNDING IS FOR OPERATIONS IN MIAMI DADE AND MONROE SPR = 100% Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 5 Year Total Planning CM $35,000 $35,000 $70,000 Total For Project 422239.5 $35,000 $35,000 $70,000

October. 10 2019 Page 98 of 151 HIGHWAY SYSTEM: 08 TRANSIT

422242.2 SOUTH FLA COMMUTER S ERVICES IN MIAMI-DADE COU NTY - MARKETING PM: FREEMAN, RAYMOND Work Mix: Commuter Trans. Assistance Extra Description: SFCS - MARKETING SERVICES (CREATIVE), MEDIA ADVERTISING SVCS (PRINITING, INTERNET, RADIO, TV-CABLE), PRINTING/ PRODUCTION OF MATERIALS TO PROMOTE TDM ALTERNATIVE MODES OF TRANSPORTATION IN MIAMI-DADE COUNTY. CONTINUATION OF FM 4222421 Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total Planning SU $1,412,401 $1,412,401 $1,318,668 $1,318,668 $1,318,668 $6,780,806 Total For Project 422242.2 $1,412,401 $1,412,401 $1,318,668 $1,318,668 $1,318,668 $6,780,806

422529.3 MDT - KENDALL CRUISE R (ROUTE 288) FROM DADELA ND NORTH TO SW 162 AVE PM: FREEMAN, RAYMOND Work Mix: Urban Corridor Improvements Extra Description: ENHANCED BUS SERVICE ALONG KENDALL DRIVE (SR 94) TO SW 162 AVENUE. LIMITED STOP SERVICE WITH SOME BUS RAPID TRANSIT (BRT) QUALITIES. TRANSIT CORRIDOR PROGRAM FUNDING. STATE PARTICIPATION RATE 100% CNT# AQQ61 MPO PRIORITY LISTING# 28 Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2021 5 Year Total Capital Improvement/Operating DPTO $165,000 $165,000 Total For Project 422529.3 $165,000 $165,000

422529.4 MDT - KENDALL CRUISE R (ROUTE 288) FROM DADELA ND NORTH TO SW 162 AVE PM: FREEMAN, RAYMOND

Work Mix: Urban Corridor Improvements Extra Description: ENHANCED BUS SERVICE ALONG KENDALL DRIVE (SR 94) TO SW 162 AVENUE. LIMITED STOP SERVICE WITH SOME BUS RAPID TRANSIT (BRT) QUALITIES. TRANSIT CORRIDOR PROGRAM FUNDING. STATE PARTICIPATION RATE 100% CNT# AQQ61 MPO PRIORITY LISTING# 28 Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2023 5 Year Total Capital Improvement/Operating DPTO $550,000 $550,000 Total For Project 422529.4 $550,000 $550,000

422529.5 MDT - KENDALL CRUISE R (ROUTE 288) FROM DADELA ND NORTH TO SW 162 AVE PM: FREEMAN, RAYMOND

Work Mix: Urban Corridor Improvements Extra Description: ENHANCED BUS SERVICE ALONG KENDALL DRIVE (SR 94) TO SW 162 AVENUE. LIMITED STOP SERVICE WITH SOME BUS RAPID TRANSIT (BRT) QUALITIES. TRANSIT CORRIDOR PROGRAM FUNDING. STATE PARTICIPATION RATE 100% CNT# AQQ61 Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2024 5 Year Total Capital Improvement/Operating DDR $428,896 $428,896 Total For Project 422529.5 $428,896 $428,896

October. 10 2019 Page 99 of 151 HIGHWAY SYSTEM: 08 TRANSIT

424147.4 DTPW CANOPY FOR ELEV ATORS AT DADELAND NORTH M ETRORAIL STATION PM: FREEMAN, RAYMOND Work Mix: Intermodal Hub Capacity Extra Description: CONSTRUCTION OF A PROPOSED NEW CANOPY AT THE DADELAND NORTH METRORAIL STATION Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2023 5 Year Total Capital Improvement/Operating DPTO $595,856 $595,856 Total For Project 424147.4 $595,856 $595,856

430953.2 MDT - FLAGLER MAX (R OUTE 51) FROM WEST MIAMI- DADE TO DOWNTOWN PM: FREEMAN, RAYMOND Work Mix: Urban Corridor Improvements Extra Description: MDT - FLAGLER MAX BUS ROUTE (#51) TRANSIT CORRIDOR PROGRAM OPERATING ASSISTANCE. 100% STATE PARTICIPATION RATE CONTINUATION OF FM# 4222201 & 430953-1 MPO PRIORITY LISTING# 21 Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2021 5 Year Total Capital Improvement/Operating DPTO $510,000 $510,000 Total For Project 430953.2 $510,000 $510,000

430953.3 MDT - FLAGLER MAX (R OUTE 51) FROM WEST MIAMI- DADE TO DOWNTOWN PM: FREEMAN, RAYMOND

Work Mix: Urban Corridor Improvements Extra Description: MDT - FLAGLER MAX BUS ROUTE (#51) TRANSIT CORRIDOR PROGRAM OPERATING ASSISTANCE. 100% STATE PARTICIPATION RATE CONTINUATION OF FM# 4222201 & 430953-1 MPO PRIORITY LISTING# 21 Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2023 5 Year Total Capital Improvement/Operating DPTO $633,635 $633,635 Total For Project 430953.3 $633,635 $633,635

431077.2 MDT - SR 836 EBS PAR K AND RIDE LOT AT SW 8 ST AND SW 147 AVE PM: FREEMAN, RAYMOND

Work Mix: Park And Ride Lots Extra Description: MDT - INTERMODAL PROGRAM FUNDING TO CONSTRUCT A PARK AND RIDE FACILITY THAT INCLUDES APPROX. 350 PARKING SPACES, BUS TERMINAL W. BUS BAYS AND PASSENGER LOUNGE. STRUNG W/ 4310771 & 4310773 ***WP45*** MPO PRIORITY LISTING# 18 CNT# Cont. Class: Extern Mngd(Not Lap) G0173 NOTE: DTPW REQUESTED $891,640 IN FUNDING FROM SAID ITEM

Phase Fund Code FY 2022 FY 2023 5 Year Total Capital Improvement/Operating DPTO $1,250,000 $1,250,000 $2,500,000 LF $1,250,000 $1,250,000 $2,500,000 Total For Project 431077.2 $2,500,000 $2,500,000 $5,000,000

October. 10 2019 Page 100 of 151 HIGHWAY SYSTEM: 08 TRANSIT

432934.1 MDT - 95 EXPRESS DAD E/BROWARD CIVIC CENTER PM: FREEMAN, RAYMOND Work Mix: Urban Corridor Improvements Extra Description: MDT - I-95 DADE/BROWARD I-95 EXPRESS (CIVIC CENTER) WILL PROVIDE ADDITIONAL SERVICE TO CIVIC CENTER FROM THE BROWARD BOULEVARD AND SHERIDAN STREET PARK AND RIDE STATIONS. STATE PARTICIPATION RATE 100% MPO PRIORITY LIST #36 (PAGE 12 OF 18) PER Cont. Class: Extern Mngd(Not Lap) THE REQUEST OF MDT DATED 08/29/12 FUNDS PGM IN OUTER YEARS FROM 4204625

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total Capital Improvement/Operating TOBD $450,000 $450,000 $450,000 $450,000 $450,000 $2,250,000 Total For Project 432934.1 $450,000 $450,000 $450,000 $450,000 $450,000 $2,250,000

434897.3 MIAMI-DADE COUNTY - TPO FTA SECTION 5305(D) M ETRO PLANNING PM: DUBE/FREEMAN

Work Mix: Pto Studies Extra Description: FTA SECTION 5305 (D) FUNDING TO SUPPORT TRANSIT PLANNING ACTIVITIES BY MIAMI-DADE MPO. INCLUDES VARIOUS STUDIES DESCRIBED IN THE UPWP AND ANNUAL UPDATES TO THE TIP AND LRTP FOR FY 20/21 MATCHES = 80F/10S/10L Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2021 5 Year Total Planning DDR $167,780 $167,780 DU $1,342,240 $1,342,240 LF $167,780 $167,780 Total For Project 434897.3 $1,677,800 $1,677,800

434897.4 MIAMI-DADE COUNTY - TPO FTA SECTION 5305(D) M ETRO PLANNING PM: DUBE/FREEMAN Work Mix: Pto Studies Extra Description: FTA SECTION 5305 (D) FUNDING TO SUPPORT TRANSIT PLANNING ACTIVITIES BY MIAMI-DADE MPO. INCLUDES VARIOUS STUDIES DESCRIBED IN THE UPWP AND ANNUAL UPDATES TO THE TIP AND LRTP FOR FY 21/22 MATCHES = 80F/10S/10L Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2022 5 Year Total Planning DDR $172,813 $172,813 DU $1,382,507 $1,382,507 LF $172,813 $172,813 Total For Project 434897.4 $1,728,133 $1,728,133

434897.5 MIAMI-DADE COUNTY - TPO FTA SECTION 5305(D) M ETRO PLANNING PM: DUBE/FREEMAN

Work Mix: Pto Studies Extra Description: FTA SECTION 5305 (D) FUNDING TO SUPPORT TRANSIT PLANNING ACTIVITIES BY MIAMI-DADE MPO. INCLUDES VARIOUS STUDIES DESCRIBED IN THE UPWP AND ANNUAL UPDATES TO THE TIP AND LRTP FOR FY 22/23 MATCHES = 80F/10S/10L Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2023 5 Year Total Planning DPTO $177,998 $177,998 DU $1,423,982 $1,423,982 LF $177,998 $177,998 Total For Project 434897.5 $1,779,978 $1,779,978

October. 10 2019 Page 101 of 151 HIGHWAY SYSTEM: 08 TRANSIT

434897.6 MIAMI-DADE COUNTY - TPO FTA SECTION 5305(D) M ETRO PLANNING PM: DUBE/FREEMAN

Work Mix: Pto Studies Extra Description: FTA SECTION 5305 (D) FUNDING TO SUPPORT TRANSIT PLANNING ACTIVITIES BY MIAMI-DADE MPO. INCLUDES VARIOUS STUDIES DESCRIBED IN THE UPWP AND ANNUAL UPDATES TO THE TIP AND LRTP FOR FY 23/24 MATCHES = 80F/10S/10L Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2024 5 Year Total Planning DDR $183,338 $183,338 DU $1,466,702 $1,466,702 LF $183,338 $183,338 Total For Project 434897.6 $1,833,378 $1,833,378

434897.7 MIAMI-DADE COUNTY - TPO FTA SECTION 5305(D) M ETRO PLANNING PM: DUBE/FREEMAN

Work Mix: Pto Studies Extra Description: FTA SECTION 5305 (D) FUNDING TO SUPPORT TRANSIT PLANNING ACTIVITIES BY MIAMI-DADE MPO. INCLUDES VARIOUS STUDIES DESCRIBED IN THE UPWP AND ANNUAL UPDATES TO THE TIP AND LRTP FOR FY 24/25 MATCHES = 80F/10S/10L Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2025 5 Year Total Planning DPTO $188,838 $188,838 DU $1,510,703 $1,510,703 LF $188,838 $188,838 Total For Project 434897.7 $1,888,379 $1,888,379

436695.2 CITY OF MIAMI - TROL LEY VEHICLES PURCHASE PM: FREEMAN, RAYMOND Work Mix: Purchase Vehicles/Equipment Extra Description: TRANSIT CORRIDOR PROGRAM FUNDS PROVIDED TO PURCHASE ADDITIONAL TROLLEY VEHICLES. STATE PARTICIPATION RATE = 50% Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2021 5 Year Total Capital Improvement/Operating DDR $354,000 $354,000 LF $354,000 $354,000 Total For Project 436695.2 $708,000 $708,000

436695.3 CITY OF MIAMI - TROL LEY VEHICLES PURCHASE PM: FREEMAN, RAYMOND Work Mix: Purchase Vehicles/Equipment Extra Description: TRANSIT CORRIDOR PROGRAM FUNDING TO CITY OF MIAMI TROLLEY FOR THE PURCHASE OF SIX REPLACEMENT TROLLEYS. STATE PARTICIPATION RATE = 100% Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2022 5 Year Total Capital Improvement/Operating DPTO $1,180,000 $1,180,000 Total For Project 436695.3 $1,180,000 $1,180,000

October. 10 2019 Page 102 of 151 HIGHWAY SYSTEM: 08 TRANSIT

436695.4 CITY OF MIAMI - TROL LEY VEHICLES PURCHASE PM: FREEMAN, RAYMOND Work Mix: Purchase Vehicles/Equipment Extra Description: TRANSIT CORRIDOR PROGRAM FUNDS PROVIDED TO PURCHASE ADDITIONAL TROLLEY VEHICLES. STATE PARTICIPATION RATE = 100% Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2023 5 Year Total Capital Improvement/Operating DPTO $1,020,450 $1,020,450 Total For Project 436695.4 $1,020,450 $1,020,450

436695.5 CITY OF MIAMI - TROL LEY VEHICLES REPLACEMENT PM: FREEMAN, RAYMOND Work Mix: Purchase Vehicles/Equipment Extra Description: TRANSIT CORRIDOR PROGRAM FUNDS PROVIDED FOR THE PURCHASE OF 10 REPLACEMENT TROLLEY VEHICLES. STATE PARTICIPATION RATE = 100% Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2024 5 Year Total Capital Improvement/Operating DDR $1,841,311 $1,841,311 Total For Project 436695.5 $1,841,311 $1,841,311

436704.2 MDT - STATE TRANSIT BLOCK GRANT PM: FREEMAN, RAYMOND

Work Mix: Operating For Fixed Route Extra Description: STATE PUBLIC TRANSIT BLOCK GRANT FUNDS FOR THE OPERATIONS OF MDT FIXED ROUTE BUS SERVICE STATE PARTICIPATION RATE = 50% Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2021 5 Year Total Capital Improvement/Operating DDR $12,352,031 $12,352,031 DPTO $9,955,819 $9,955,819 LF $22,307,850 $22,307,850 Total For Project 436704.2 $44,615,700 $44,615,700

436704.3 MDT - STATE TRANSIT BLOCK GRANT PM: FREEMAN, RAYMOND

Work Mix: Operating For Fixed Route Extra Description: STATE PUBLIC TRANSIT BLOCK GRANT FUNDS FOR THE OPERATIONS OF MDT FIXED ROUTE BUS SERVICE STATE PARTICIPATION RATE = 50% Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2022 5 Year Total Capital Improvement/Operating DDR $15,134,690 $15,134,690 DPTO $8,288,552 $8,288,552 LF $23,423,242 $23,423,242 Total For Project 436704.3 $46,846,484 $46,846,484

October. 10 2019 Page 103 of 151 HIGHWAY SYSTEM: 08 TRANSIT

436704.4 MDT - STATE TRANSIT BLOCK GRANT PM: FREEMAN, RAYMOND Work Mix: Operating For Fixed Route Extra Description: STATE PUBLIC TRANSIT BLOCK GRANT FUNDS FOR THE OPERATIONS OF MDT FIXED ROUTE BUS SERVICE STATE PARTICIPATION RATE = 50% Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2023 5 Year Total Capital Improvement/Operating DDR $6,879,048 $6,879,048 DPTO $17,715,356 $17,715,356 LF $24,594,404 $24,594,404 Total For Project 436704.4 $49,188,808 $49,188,808

436704.5 MDT - STATE TRANSIT BLOCK GRANT PM: FREEMAN, RAYMOND

Work Mix: Operating For Fixed Route Extra Description: STATE PUBLIC TRANSIT BLOCK GRANT FUNDS FOR THE OPERATIONS OF MDT FIXED ROUTE BUS SERVICE STATE PARTICIPATION RATE = 50% Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2024 5 Year Total Capital Improvement/Operating DDR $11,124,082 $11,124,082 DPTO $14,700,043 $14,700,043 LF $25,824,125 $25,824,125 Total For Project 436704.5 $51,648,250 $51,648,250

436704.6 MDT - STATE TRANSIT BLOCK GRANT PM: FREEMAN, RAYMOND

Work Mix: Operating For Fixed Route Extra Description: STATE PUBLIC TRANSIT BLOCK GRANT FUNDS FOR THE OPERATIONS OF MDT FIXED ROUTE BUS SERVICE STATE PARTICIPATION RATE = 50% Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2025 5 Year Total Capital Improvement/Operating DDR $11,329,242 $11,329,242 DPTO $14,481,041 $14,481,041 LF $25,810,283 $25,810,283 Total For Project 436704.6 $51,620,566 $51,620,566

October. 10 2019 Page 104 of 151 HIGHWAY SYSTEM: 08 TRANSIT

436886.1 MDT - FTA SECTION 53 39 BUS AND BUS FACILITIES PM: FREEMAN, RAYMOND

Work Mix: Capital For Fixed Route Extra Description: FTA SECTION 5339 GRANT FUND FOR THE PURCHASE OF BUSES FEDERAL PASS THROUGH - FEDERAL 80%/LF 20% Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2025 5 Year Total Capital Improvement/Operating FTA $7,000,000 $7,000,000 LF $1,750,000 $1,750,000 Total For Project 436886.1 $8,750,000 $8,750,000

438942.1 MDT - BEACH CONNECTI ON SOUTH - EXPRESS BUS SE RVICE PM: FREEMAN, RAYMOND

Work Mix: Urban Corridor Improvements Extra Description: Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2021 5 Year Total Capital Improvement/Operating DPTO $750,000 $750,000 LF $750,000 $750,000 Total For Project 438942.1 $1,500,000 $1,500,000

438943.2 MDT- 95 EXPRESS DADE /BROWARD EXPRESS (RTE 196 SHERIDAN ST TO DOWNTOWN) PM: FREEMAN, RAYMOND Work Mix: Purchase Vehicles/Equipment Extra Description: CAPTIAL GRANT FOR BUS REPLACEMENTS OPERATING FUNDS ON 420462-5 Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2022 5 Year Total Capital Improvement/Operating DSBD $4,480,000 $4,480,000 Total For Project 438943.2 $4,480,000 $4,480,000

440450.1 DTPW - SOUTH DADE TR ANSITWAY (T-WAY) SERVICE IMPROVEMENT PROJECT PM: FREEMAN/NUNEZ

Work Mix: Purchase Vehicles/Equipment Extra Description: COUNTY INCENTIVE GRANT PROGRAM (CIGP)/MIAMI DADE DTPW SUBMITTED AN APPLICATION FOR CIGP FUNDS TO PURCHASE TWENTY TWO (22) SIXTY-FOOT COMPRESSED NATURAL GAS (CNG) BUSES TO INCREASE SERVICE FREQUENCY FOR ROUTES 38 (FY 21) AND ROUTE 34 (FY 22). LOCAL Cont. Class: Extern Mngd(Not Lap) FUND MATCH: CHARTER COUNTY TRANSPORTATION SALES SURTAX BOND PROCEEDS

Phase Fund Code FY 2021 FY 2022 5 Year Total Capital Improvement/Operating CIGP $4,793,029 $4,833,138 $9,626,167 LF $4,793,029 $4,833,138 $9,626,167 Total For Project 440450.1 $9,586,058 $9,666,276 $19,252,334

October. 10 2019 Page 105 of 151 HIGHWAY SYSTEM: 08 TRANSIT

440856.1 DTPW - SMART PLAN CO RRIDORS T.R.I.P. CAPITAL EXPENDITURES PM: CARTAYA, NILIA Work Mix: Transit Improvement Extra Description: 2018 TPO PRIORITY #8 TRIP PRIORITY #1 APPROVED 7/1/16 BY SEFTC CORRIDORS INCLUDE: NW 27TH AVENUE, KENDALL DRIVE, BEACH TRANSIT CONNECTOR, EAST-WEST 836, SOUTH DADE TRANSIT WAY, COASTAL LINK. Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total Capital Improvement/Operating TRIP $34,354 $903,221 $2,048,089 $2,271,843 $2,837,006 $8,094,513 TRWR $664,593 $1,937,647 $1,926,975 $1,703,221 $1,138,058 $7,370,494 Total For Project 440856.1 $698,947 $2,840,868 $3,975,064 $3,975,064 $3,975,064 $15,465,007

440922.1 DTPW - FTA SECTION 5337 PM: FREEMAN, RAYMOND

Work Mix: Capital For Fixed Route Extra Description: FY 2021 FTA SECTION 5337 GRANT AWARD TO DTPW. FTA = $31,000,000 LF = $7,750,000 TDC'S TO PROVIDE LOCAL MATCH Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2021 5 Year Total Capital Improvement/Operating FTA $32,000,000 $32,000,000 LF $8,000,000 $8,000,000 Total For Project 440922.1 $40,000,000 $40,000,000

440923.1 DTPW - FTA SECTION 5 339 PM: FREEMAN, RAYMOND

Work Mix: Capital For Fixed Route Extra Description: FY 2021 FTA SECTION 5339 GRANT AWARD TO DTPW FTA = $6,000,000 LF = $1,500,000 TRC'S PROVIDE LOCAL MATCH Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2021 5 Year Total Capital Improvement/Operating FTA $7,000,000 $7,000,000 LF $1,750,000 $1,750,000 Total For Project 440923.1 $8,750,000 $8,750,000

440924.1 DTPW - FTA SECTION 5 307 PM: FREEMAN, RAYMOND

Work Mix: Capital For Fixed Route Extra Description: FY 21 FTA SECTION 5307 STATE OF GOOD REPAIR GRANT AWARD TO DTPW FTA = $55,000,000 LF = $13,750,000 TDC'S PROVIDE LOCAL MATCH Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2021 5 Year Total Capital Improvement/Operating FTA $56,000,000 $56,000,000 LF $14,000,000 $14,000,000 Total For Project 440924.1 $70,000,000 $70,000,000

October. 10 2019 Page 106 of 151 HIGHWAY SYSTEM: 08 TRANSIT

440932.1 DTPW - FTA SECTION 5 337 PM: FREEMAN, RAYMOND Work Mix: Capital For Fixed Route Extra Description: FY 22 FTA SECTION 5337 CAPITOL GRANT - STATE OF GOOD REPAIR TO MIAMI DADE DEPT. OF TRANSPORTATION & PUBLIC WORKS (DTPW) FTA = $31,000,000 LF = 7,750,000 Cont. Class: Misc - No Letting

Phase Fund Code FY 2022 5 Year Total Capital Improvement/Operating FTA $32,000,000 $32,000,000 LF $8,000,000 $8,000,000 Total For Project 440932.1 $40,000,000 $40,000,000

442445.1 DTPW - FTA SECTION 5 307 FEDERAL FORMULA FUNDI NG PM: FREEMAN, RAYMOND

Work Mix: Capital For Fixed Route Extra Description: DTPW - FTA FORMULA FUNDING (SECTION 5307) FOR STATE FISCAL YEAR 22. FTA=80%/LF=20% TOLL REVENUE CREDITS PROVIDE LOCAL FUND MATCH Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2022 5 Year Total Capital Improvement/Operating FTA $56,000,000 $56,000,000 LF $14,000,000 $14,000,000 Total For Project 442445.1 $70,000,000 $70,000,000

442446.1 DPTW - FTA SECTION 5 339 BUS AND BUS FACILITES PM: FREEMAN, RAYMOND

Work Mix: Capital For Fixed Route Extra Description: DTPW - FTA SECTION 5339 BUS AND BUS FACILITIES FOR STATE FISCAL YEAR 22. TOLL REVENUE CREDITS WILL BE USED FOR LOCAL FUND MATCH. FTA=80%/LF=20% Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2022 5 Year Total Capital Improvement/Operating FTA $7,000,000 $7,000,000 LF $1,750,000 $1,750,000 Total For Project 442446.1 $8,750,000 $8,750,000

442448.1 DTPW - FTA SECTION 5 307 FEDERAL FORMULA FUNDI NG PM: FREEMAN, RAYMOND

Work Mix: Capital For Fixed Route Extra Description: DTPW FTA SECTION 5307 FEDERAL FORMULA FUNDING FOR STATE FISCAL YEAR 23. TOLL REVENUE CREDITS TO BE USED FOR LOCAL FUND MATCH FTA=80%/LF=20% Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2023 5 Year Total Capital Improvement/Operating FTA $56,000,000 $56,000,000 LF $14,000,000 $14,000,000 Total For Project 442448.1 $70,000,000 $70,000,000

October. 10 2019 Page 107 of 151 HIGHWAY SYSTEM: 08 TRANSIT

442449.1 DTPW-FTA SECTION 533 7 FEDERAL FORMULA FUNDING CAPITAL FOR FIXED ROUTE PM: FREEMAN, RAYMOND Work Mix: Capital For Fixed Route Extra Description: DTPW FTA SECTION 5337 CAPITAL FOR FIXED ROUTE FOR STATE FISCAL YEAR 23 FTA=80%/LF=20%/TOLL REVENUE CREDITS WILL BE USED FOR LOCAL FUNDS MATCH Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2023 5 Year Total Capital Improvement/Operating FTA $32,000,000 $32,000,000 LF $8,000,000 $8,000,000 Total For Project 442449.1 $40,000,000 $40,000,000

442450.1 DPTW-FTA SECTION 533 9 FEDERAL FORMULA FUNDING FOR CAPITAL FIXED ROUTE PM: FREEMAN, RAYMOND

Work Mix: Capital For Fixed Route Extra Description: DTPW FTA SECTION 5337 CAPITAL FOR FIXED ROUTE FOR STATE FISCAL YEAR 23 FTA=80%/LF=20%TOLL REVENUE CREDITS WILL BE USED FOR LOCAL TOLL REVENUE CREDITS WILL BE USED FOR LOCAL FUNDS MATCH Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2023 5 Year Total Capital Improvement/Operating FTA $7,000,000 $7,000,000 LF $1,750,000 $1,750,000 Total For Project 442450.1 $8,750,000 $8,750,000

442497.1 STRATEGIC MIAMI AREA RAPID TRANSIT (SMART PLA N) PRIORITY PROJECTS PM: CARTAYA, NILIA

Work Mix: Preliminary Engineering Extra Description: 2018 TPO PRIORITY #1 Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total P.E. SU $26,820,646 $32,985,918 $31,682,883 $30,000,799 $33,014,687 $154,504,933 Total For Project 442497.1 $26,820,646 $32,985,918 $31,682,883 $30,000,799 $33,014,687 $154,504,933

442497.2 STRATEGIC MIAMI AREA RAPID TRANSIT (SMART PLA N) PRIORITY PROJECTS (2) PM: CARTAYA, NILIA

Work Mix: Preliminary Engineering Extra Description: 2018 TPO PRIORITY #4 ADVANCEMENT & DEVELOPMENT OF PROJECTS TO SUPPORT INITIATIVES SUCH AS: FIRST AND LAST MILE, COMPLETE STREETS, & CONNECTED AND AUTONOMOUS VEHICLE (CAV) Cont. Class: Misc - No Letting

Phase Fund Code FY 2025 5 Year Total P.E. SU $1,000,000 $1,000,000 Total For Project 442497.2 $1,000,000 $1,000,000

October. 10 2019 Page 108 of 151 HIGHWAY SYSTEM: 08 TRANSIT

443988.1 MIAMI-DADE DTPW I-75 EXPRESS BUS SERVICE PM: FREEMAN, RAYMOND Work Mix: Transit Service Demonstration Extra Description: 2018 TPO PRIORITY #2 I-75 EXPRESS BUS SERVICE - PALMETTO (NW MIAMI-DADE) EXPRESS ROUTE C STATE PARTICIPATION RATE = 100% Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total Capital Improvement/Operating TOBD $1,090,000 $1,140,000 $1,200,000 $1,260,000 $1,320,000 $6,010,000 Total For Project 443988.1 $1,090,000 $1,140,000 $1,200,000 $1,260,000 $1,320,000 $6,010,000

444082.1 MIAMI-DADE DTPW - MI DTOWN/DESIGN DISTRICT RAI L STATION OPERATIONS PM: FREEMAN, RAYMOND Work Mix: Operating For Fixed Route Extra Description: 2018 TPO PRIORITY #3 DTPW - TRI-RAIL SERVICE MIAMI-MIDTOWN/DESIGN DISTRICT STATE PARTICIPATION IS 50% TPO DEMONSTRATION PROJECT Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2021 FY 2022 5 Year Total Capital Improvement/Operating DPTO $350,000 $350,000 $700,000 LF $350,000 $350,000 $700,000 Total For Project 444082.1 $700,000 $700,000 $1,400,000

444352.1 CITY OF DORAL - FIU/ PANTHER STATION TROLLEY R OUTE PM: FREEMAN, RAYMOND Work Mix: Transit Service Demonstration Extra Description: 2018 TPO PRIORITY #3 CITY OF DORAL - FIU/PANTHER STATION TROLLEY ROUTE CO AWARDED STATE FUNDS THROUGH THE SERVICE DEVELOPMENT PROGRAM - TPO DEMOMSTRATION PROJECT. STATE PARTICIPATION = 50% Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2021 5 Year Total Capital Improvement/Operating DPTO $260,000 $260,000 LF $260,000 $260,000 Total For Project 444352.1 $520,000 $520,000

444353.1 CITY OF MIAMI - FLAG AMI TROLLEY ROUTE PM: FREEMAN, RAYMOND

Work Mix: Transit Service Demonstration Extra Description: 2018 TPO PRIORITY #3 CITY OF MIAMI - FLAGAMI TROLLEY ROUTE CO AWARDED STATE FUNDS THROUGH THE SERVICE DEVELOPMENT PROGRAM - TPO DEMONSTRATION PROJECT. STATE PARTICIPATION = 50% Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2021 5 Year Total Capital Improvement/Operating CM $600,000 $600,000 LF $600,000 $600,000 Total For Project 444353.1 $1,200,000 $1,200,000

October. 10 2019 Page 109 of 151 HIGHWAY SYSTEM: 08 TRANSIT

444354.1 TOWN OF CUTLER BAY - CUTLER BAY EXPRESS PM: FREEMAN, RAYMOND Work Mix: Transit Service Demonstration Extra Description: 2018 TPO PRIORITY #3 TOWN OF CUTLER BAY - CUTLER BAY EXPRESS CO AWARDED STATE FUNDS THROUGH THE SERVICE DEVELOPMENT PROGRAM. TPO SERVICE DEMONSTRATION PROJECT. STATE PARTICIPATION = 50%. Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2021 5 Year Total Capital Improvement/Operating DPTO $192,500 $192,500 LF $192,500 $192,500 Total For Project 444354.1 $385,000 $385,000

444355.1 TOWN OF MEDLEY - CEN TRAL COMMUTER ROUTE PM: FREEMAN, RAYMOND

Work Mix: Transit Service Demonstration Extra Description: 2018 TPO PRIORITY #3 TOWN OF MEDLEY - CENTRAL COMMUTER ROUTE CO AWARDED STATE FUNDS THROUGH THE SERVICE DEVELOPMENT PROGRAM. TPO SERVICE DEMONSTRATION PROJECT. STATE PARTICIPATION = 50% Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2021 5 Year Total Capital Improvement/Operating DPTO $35,000 $35,000 LF $35,000 $35,000 Total For Project 444355.1 $70,000 $70,000

444356.1 VILLAGE OF PINECREST - ON-DEMAND TRANSIT CIRC ULATOR PM: FREEMAN, RAYMOND

Work Mix: Transit Service Demonstration Extra Description: 2018 TPO PRIORITY #3 VILLAGE OF PINECREST - ON-DEMAND TRANSIT CIRCULATOR CO AWARDED STATE FUNDS THROUGH THE SERVICE DEVELOPMENT PROGRAM. TPO SERVICE DEMOMONSTRATION PROJECT. STATE PARTICIPATION = 50% Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2021 5 Year Total Capital Improvement/Operating DPTO $96,221 $96,221 LF $96,221 $96,221 Total For Project 444356.1 $192,442 $192,442

444357.1 CITY OF CORAL GABLES - FLEX ROUTE VIA ELECTRI C VEHICLES PM: FREEMAN, RAYMOND

Work Mix: Transit Service Demonstration Extra Description: 2018 TPO PRIORITY #3 CITY OF CORAL GABLES - FLEX ROUTE VIA ELECTRONIC VEHICLES CO AWARDED STATE FUNDS THROUGH SERVICE DEVELOPMENT PROGRAM. TPO SERVICE DEMONSTRATION PROJECT. STATE PARTICIPATION = 50% Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2021 5 Year Total Capital Improvement/Operating DPTO $209,733 $209,733 LF $209,733 $209,733 Total For Project 444357.1 $419,466 $419,466

October. 10 2019 Page 110 of 151 HIGHWAY SYSTEM: 08 TRANSIT

444358.1 MIAMI SHORES VILLAGE - SMART SHUTTLE SERVICE PM: FREEMAN, RAYMOND Work Mix: Transit Service Demonstration Extra Description: 2018 TPO PRIORITY #3 MIAMI SHORES VILLAGE - SMART SHUTTLE SERVICE CO AWARDED STATE FUNDS TO SERVICE DEVELOPMENT PROGRAM. TPO SERVICE DEMONSTRATION PROJECT. STATE PARTICIPATION = 50% Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2021 5 Year Total Capital Improvement/Operating DPTO $39,780 $39,780 LF $39,780 $39,780 Total For Project 444358.1 $79,560 $79,560

444360.1 NORTH BAY VILLAGE CO NNECTOR PM: FREEMAN, RAYMOND

Work Mix: Transit Service Demonstration Extra Description: 2018 TPO PRIORITY #3 NORTH BAY VILLAGE - NORTH BAY VILLAGE CONNECTOR CO AWARDED STATE FUNDS TO SERVICE DEVELOPMENT PROGRAM. TPO SERVICE DEMONSTRATION PROJECT. STATE PARTICIPATION = 50% Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2021 5 Year Total Capital Improvement/Operating DPTO $50,000 $50,000 LF $50,000 $50,000 Total For Project 444360.1 $100,000 $100,000

444361.1 VILLAGE OF PALMETTO BAY - ON-DEMAND EXPRESS S ERVICE PM: FREEMAN, RAYMOND

Work Mix: Transit Service Demonstration Extra Description: 2018 TPO PRIORITY #3 VILLAGE OF PALMETTO BAY - ON-DEMAND EXPRESS SERVICE CO AWARDED STATE FUNDS TO SERVICE DEVELOPMENT PROGRAM TPO SERVICE DEMONSTRATION PROJECT. STATE PARTICIPATION = 50% Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2021 5 Year Total Capital Improvement/Operating DPTO $175,000 $175,000 LF $175,000 $175,000 Total For Project 444361.1 $350,000 $350,000

444362.1 VILLAGE OF PALMETTO BAY - NEW TRANSIT FACILIT Y (LEASE) PM: FREEMAN, RAYMOND

Work Mix: Transit Service Demonstration Extra Description: 2018 TPO PRIORITY #3 VILLAGE OF PALMETTO BAY - NEW TRANSIT FACILITY CO AWARDED STATE FUNDS TO SERVICE DEVELOPMENT PROGRAM TPO SERVICE DEMONSTRATION PROJECT. STATE PARTICIPATION = 50% Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2021 5 Year Total Capital Improvement/Operating DPTO $50,000 $50,000 LF $50,000 $50,000 Total For Project 444362.1 $100,000 $100,000

October. 10 2019 Page 111 of 151 HIGHWAY SYSTEM: 08 TRANSIT

444901.2 DTPW - OPERATING AS SISTANCE FOR ROUTES ON TH E SOUTH DADE TRANSITWAY PM: FREEMAN, RAYMOND Work Mix: Operating For Fixed Route Extra Description: 2019 TPO PRIORITY #1 OPERATING ASSISTANCE PROVIDED TO MIAMI-DADE DTPW FOR THE FIVE BUS ROUTES RUNNING ON THE SOUTH DADE TRANSITWAY. STATE PARTICIPATION IS 100% Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2025 5 Year Total Capital Improvement/Operating DPTO $1,000,000 $1,000,000 Total For Project 444901.2 $1,000,000 $1,000,000

445024.1 MDT-95 EXPRESS DADE/ BROWARD EXPRESS (RTE 195 BROWARD BLVD TO DOWNTOWN) PM: FREEMAN, RAYMOND Work Mix: Purchase Vehicles/Equipment Extra Description: CAPTIAL GRANT FOR BUS REPLACEMENTS OPERATING FUNDS ON 420462-5 Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2022 5 Year Total Capital Improvement/Operating DSBD $5,040,000 $5,040,000 Total For Project 445024.1 $5,040,000 $5,040,000

445157.1 MIAMI-DADE DTPW - FT A SECTION 5307 - URBANIZE D AREA FORMULA PROGRAM PM: FREEMAN, RAYMOND

Work Mix: Transit Improvement Extra Description: FTA SECTION 5307 - URBANIZED AREA FORMULA PROGRAM TRANSPORTATION DEVELOPMENT CREDITS (TDCA) WILL PROVIDE THE LOCAL MATCH (LF). Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2024 5 Year Total Capital Improvement/Operating FTA $56,000,000 $56,000,000 LF $14,000,000 $14,000,000 Total For Project 445157.1 $70,000,000 $70,000,000

445159.1 MIAMI-DADE DTPW - FT A SECTION 5339 - BUS AND BUS FACILITIES PM: FREEMAN, RAYMOND

Work Mix: Capital For Fixed Route Extra Description: FTA SECTION 5339 - BUS AND BUS FACILITIES TRANSPORTATION DEVELOPMENT CREDITS (TDC) WILL PROVIDE THE LOCAL MATCH (LF). Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2024 5 Year Total Capital Improvement/Operating FTA $7,000,000 $7,000,000 LF $1,750,000 $1,750,000 Total For Project 445159.1 $8,750,000 $8,750,000

October. 10 2019 Page 112 of 151 HIGHWAY SYSTEM: 08 TRANSIT

445164.1 MIAMI-DADE DTPW - FT A SECTION 5337 - STATE OF GOOD REPAIR PM: FREEMAN, RAYMOND Work Mix: Capital For Fixed Route Extra Description: FTA SECTION 5337 - STATE OF GOOD REPAIR TRANSPORTATION DEVELOPMENT CREDITS (TDC) WILL PROVIDE THE LOCAL MATCH (LF). Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2024 5 Year Total Capital Improvement/Operating FTA $32,000,000 $32,000,000 LF $8,000,000 $8,000,000 Total For Project 445164.1 $40,000,000 $40,000,000

446613.1 DTPW - FTA SECTION 5 307 PM: FREEMAN, RAYMOND

Work Mix: Capital For Fixed Route Extra Description: TDC TO PROVIDE THE LOCAL MATCH Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2025 5 Year Total Capital Improvement/Operating FTA $56,000,000 $56,000,000 LF $14,000,000 $14,000,000 Total For Project 446613.1 $70,000,000 $70,000,000

446614.1 DTPW - FTA SECTION 5 337 PM: FREEMAN, RAYMOND

Work Mix: Capital For Fixed Route Extra Description: FTA SECTION 5337 - STATE OF GOOD REPAIR TRANSPORTATION DEVELOPMENT CREDITS (TDC) WILL PROVIDE THE LOCAL MATCH (LF). Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2025 5 Year Total Capital Improvement/Operating FTA $32,000,000 $32,000,000 LF $8,000,000 $8,000,000 Total For Project 446614.1 $40,000,000 $40,000,000

446615.1 DTPW - FTA SECTION 5 339 PM: FREEMAN, RAYMOND

Work Mix: Capital For Fixed Route Extra Description: FTA SECTION 5339 - BUS AND BUS FACILITIES TRANSPORTATION DEVELOPMENT CREDITS (TDC) WILL PROVIDE THE LOCAL MATCH (LF). Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2025 5 Year Total Capital Improvement/Operating FTA $7,000,000 $7,000,000 LF $1,750,000 $1,750,000 Total For Project 446615.1 $8,750,000 $8,750,000

October. 10 2019 Page 113 of 151 HIGHWAY SYSTEM: 08 TRANSIT

446651.1 CITY OF MIAMI - LIBE RTY CITY TROLLEY ROUTE PM: FREEMAN, RAYMOND Work Mix: Transit Service Demonstration Extra Description: CITY OF MIAMI - LIBERTY CITY TROLLEY ROUTE STATE PARTICIPATION IS 50% ; LOCAL PARTICIPATION IS 50% Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2021 5 Year Total Capital Improvement/Operating DPTO $1,000,500 $1,000,500 LF $1,000,500 $1,000,500 Total For Project 446651.1 $2,001,000 $2,001,000

446653.1 CITY OF MIAMI BEACH - SOUTH BEACH TROLLEY SER VICE ROUTE PM: FREEMAN, RAYMOND

Work Mix: Transit Service Demonstration Extra Description: CITY OF MIAMI BEACH - SOUTH BEACH TROLLEY SERVICE ROUTE STATE PARTICIPATION RATE IS 25% Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2021 5 Year Total Capital Improvement/Operating DPTO $1,250,000 $1,250,000 LF $3,751,450 $3,751,450 Total For Project 446653.1 $5,001,450 $5,001,450

446660.1 TOWN OF MIAMI LAKES - MIAMI LAKES FREEBEE PUB LIC TRANSIT SERVICE EXPAN PM: FREEMAN, RAYMOND

Work Mix: Transit Service Demonstration Extra Description: 2019 TPO PRIORITY #4 SMART PLAN DEMONSTRATION PROJECT TOWN OF MIAMI LAKES - MIAMI LAKES FREEBEE PUBLIC TRANSIT SERVICE EXPANSION TO ADD VEHICLE, SERVICE HOURS AND EXPAND ROUTES. STATE PARTICIPATION 50% / LOCAL PARTICIPATION 50% Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2021 5 Year Total Capital Improvement/Operating DPTO $171,730 $171,730 LF $171,730 $171,730 Total For Project 446660.1 $343,460 $343,460

446661.1 CITY OF MIAMI - PURC HASE REPLACEMENT TROLLEYS PM: FREEMAN, RAYMOND

Work Mix: Purchase Vehicles/Equipment Extra Description: CITY OF MIAMI - PURCHASE REPLACEMENT TROLLEYS TRANSIT COORIDOR PROGRAM AWARD STATE PARTICIPATION 100% Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2025 5 Year Total Capital Improvement/Operating DPTO $1,338,300 $1,338,300 Total For Project 446661.1 $1,338,300 $1,338,300

October. 10 2019 Page 114 of 151 HIGHWAY SYSTEM: 08 TRANSIT

446682.1 DTPW - FLORIDA CITY PARK AND RIDE EXPANSION A T SW 344TH STREET PM: FREEMAN, RAYMOND Work Mix: Park And Ride Lots Extra Description: 2019 TPO PRIORITY #4 FLORIDA CITY PARK AND RIDE FACILITY EXPANSION CENTRAL OFFICE PARK AND RIDE LOT PROGRAM AWARD FOR FY2021 PARTICIPATION IS 50/50 - STATE/LOCAL Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2021 5 Year Total Capital Improvement/Operating DPTO $1,569,900 $1,569,900 LF $1,569,900 $1,569,900 Total For Project 446682.1 $3,139,800 $3,139,800

446684.1 SR 836/DOLPHIN EXPRE SSWAY EXPRESS TRANSPORTAT ION SERVICE - LINE B PM: FREEMAN, RAYMOND

Work Mix: Operating For Fixed Route Extra Description: 2019 TPO PRIORITY #1 SR 836/DOLPHIN EXPRESSWAY EXPRESS TRANSPORTATION SERVICE - LINE B FIXED ROUTE ALONG SR836 FROM MIAMI INTERMODAL STATION TO PANTHER STATION (SW 109TH AVENUE/SW 8 STREET) Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2022 FY 2023 FY 2024 5 Year Total Capital Improvement/Operating CM $505,000 $505,000 $505,000 $1,515,000 LF $505,000 $505,000 $505,000 $1,515,000 Total For Project 446684.1 $1,010,000 $1,010,000 $1,010,000 $3,030,000

446686.1 DTPW - PANTHER STATI ON TO DOLPHIN STATION EXP RESS SERVICE PM: FREEMAN, RAYMOND

Work Mix: Operating For Fixed Route Extra Description: 2019 TPO PRIORITY #4 FIXED ROUTE FROM SW 109TH AVE TO NW 122 AVE/NW 12 ST Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2022 5 Year Total Capital Improvement/Operating DPTO $145,000 $145,000 LF $145,000 $145,000 Total For Project 446686.1 $290,000 $290,000

446687.1 SURFSIDE/BAL HARBOU R/BAY HARBOR ON-DEMAND SE RVICES CONNECTION PM: FREEMAN, RAYMOND

Work Mix: Operating For Fixed Route Extra Description: 2019 TPO PRIORITY #4 FIRST-LAST MILE ON DEMAND TRANSIT SERVICE PROVIDING CONNECTIVITY TO FURTURE NE COORIDOR STATION Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2021 5 Year Total Capital Improvement/Operating DPTO $150,000 $150,000 LF $150,000 $150,000 Total For Project 446687.1 $300,000 $300,000

October. 10 2019 Page 115 of 151 HIGHWAY SYSTEM: 08 TRANSIT

446692.1 FIU - PANTHER STATIO N ON-DEMAND REPONSIVE SER VICE PM: FREEMAN, RAYMOND Work Mix: Operating For Fixed Route Extra Description: 2019 TPO PRIORITY #4 FIRST-LAST MILE ON-DEMAND TRANSIT SERVICE PROVIDING CONNECT- IVITY TO A 2-MILE SERVICE AREA AROUND FIU/PANTHER STATION. Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2021 5 Year Total Capital Improvement/Operating DPTO $202,500 $202,500 LF $202,500 $202,500 Total For Project 446692.1 $405,000 $405,000

446693.1 DTPW - ROUTE ALONG I -75 BTW HIALEAH GARDENS & MIAMI GARDENS PARK/RIDE PM: FREEMAN, RAYMOND

Work Mix: Operating For Fixed Route Extra Description: 2019 TPO PRIORITY #4 FIXED ROUTE ALONG I-75 PROVIDING CONNECTIVITY BETWEEN HIALEAH GARDENS TO MIAMI GARDENS PARK AND RIDE; PASSING BY ATLIS BONTERRA APARTMENTS AND INDUSTRIAL PARK Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2022 FY 2023 5 Year Total Capital Improvement/Operating CM $200,000 $200,000 $400,000 LF $200,000 $200,000 $400,000 Total For Project 446693.1 $400,000 $400,000 $800,000

446695.1 CITY OF HIALEAH - T RI-RAIL/METRORAIL TRANSFE R STATION PM: FREEMAN, RAYMOND

Work Mix: Capital For Fixed Route Extra Description: 2019 TPO PRIORITY #4 CITY OF HIALEAH SERVICE GAP AREA TO PROVIDE FIRST/LAST MILE SERVICE TO METRORAIL/TRI-RAIL TRANSFER STATION. Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2021 5 Year Total Capital Improvement/Operating DPTO $75,000 $75,000 LF $75,000 $75,000 Total For Project 446695.1 $150,000 $150,000

446696.1 DTPW - WEST DADE CIR CULATOR ON-DEMAND SERVICE AT KENDALL COORIDOR PM: FREEMAN, RAYMOND

Work Mix: Operating For Fixed Route Extra Description: 2019 TPO PRIORITY #4 ADDRESSING SERVICE GAP IN WESTERN REGION OF UNINCORPORATED MIAMI-DADE BETWEEN SW 26 ST AND SW 120 ST (NORTH/SOUTH) AND SW 137 AVE AND SW 157 AVE (EAST/WEST) Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2021 5 Year Total Capital Improvement/Operating DPTO $675,000 $675,000 LF $675,000 $675,000 Total For Project 446696.1 $1,350,000 $1,350,000

FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total HIGHWAY SYSTEM: 08 Total $227,678,217 $234,714,968 $217,293,371 $214,754,395 $226,663,693 $1,121,104,644

October. 10 2019 Page 116 of 151 HIGHWAY SYSTEM: 09 AVIATION

423290.2 MIAMI INT'L AIRPORT CONCOURSE H INTERNALIZATI ON PM: CAYUBIT, SUNSHINE

Work Mix: Aviation Capacity Project Extra Description: A380 MODIFICATION AT CONCOURSE H, PFL 0005468 AIRPORT SITE# 3333*A CNT# ARK81 Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2021 5 Year Total Capital Improvement/Operating DPTO $2,500,000 $2,500,000 LF $2,500,000 $2,500,000 Total For Project 423290.2 $5,000,000 $5,000,000

425873.2 MIAMI EXECUTIVE AIRP ORT AIRFIELD ROTATING BEA CON PM: CAYUBIT, SUNSHINE

Work Mix: Aviation Capacity Project Extra Description: RELOCATION OF AIRFIELD ROTATING BEACON AIRPORT SITE# 33251*A JACIP UPIN# PFL 0000963 Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2023 5 Year Total Capital Improvement/Operating DPTO $427,371 $427,371 LF $106,843 $106,843 Total For Project 425873.2 $534,214 $534,214

429271.1 MIAMI INT'L AIRPORT PERIMETER ROAD WIDENING & REALIGNMENT PM: CAYUBIT, SUNSHINE Work Mix: Aviation Capacity Project Extra Description: MPO PRIORITY ID# 9/FY 21 MPO PRIORITY PROJECTS LISTING CNT#G0E79 Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2021 5 Year Total Capital Improvement/Operating DDR $72,056 $72,056 DPTO $480,785 $480,785 LF $552,841 $552,841 Total For Project 429271.1 $1,105,682 $1,105,682

431127.3 MIAMI HOMESTEAD GENE RAL OVERHAUL SEGMENTED CI RCLE PM: CAYUBIT, SUNSHINE

Work Mix: Aviation Safety Project Extra Description: RE-ESTABLISH, UPGRADE AND OVERHAUL SEGMENT CIRCLE. THIS IS TO MEET FAA REQUIREMENT TO UPGRADE/IMPROVE SEGMENT CIRCLES NON- TOWERED AIRPORTS AIRPORT SITE# 32421*A JACIP UPIN# Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2023 5 Year Total Capital Improvement/Operating DPTO $400,000 $400,000 LF $100,000 $100,000 Total For Project 431127.3 $500,000 $500,000

October. 10 2019 Page 117 of 151 HIGHWAY SYSTEM: 09 AVIATION

431130.6 MIAMI EXECUTIVE AIRP ORT PAVE SHOULDERS FOR RU NWAY 9L/27R PM: CAYUBIT, SUNSHINE Work Mix: Aviation Preservation Project Extra Description: ADDING PAVE SHOULDER TO THE PRIMARY RUNWAY 9R/27L. THIS WILL INCREASE RUNWAY CAPACITY SERVING THE MAJORITY OF BASED AIRCRAFT OPERATIONS. AIRPORT SITE#33251*A JACIP UPIN#PFL0000963 Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2023 5 Year Total Capital Improvement/Operating DPTO $1,600,000 $1,600,000 LF $400,000 $400,000 Total For Project 431130.6 $2,000,000 $2,000,000

431229.2 MIAMI INT'L AIRPORT CENTRAL BASE PAVEMENT REH ABILITATION PM: CAYUBIT, SUNSHINE

Work Mix: Aviation Preservation Project Extra Description: Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2021 5 Year Total Capital Improvement/Operating DPTO $1,726,262 $1,726,262 LF $1,726,262 $1,726,262 Total For Project 431229.2 $3,452,524 $3,452,524

436693.1 MIAMI INT'L AIRPORT TERMINAL HARDSTAND & GSE FACILITY PM: CAYUBIT, SUNSHINE

Work Mix: Aviation Security Project Extra Description: Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2021 FY 2022 5 Year Total Capital Improvement/Operating GMR $3,000,000 $5,500,000 $8,500,000 LF $3,000,000 $5,500,000 $8,500,000 Total For Project 436693.1 $6,000,000 $11,000,000 $17,000,000

438612.1 DADE-COLLIER AIRPORT POWER DISTRIBUTION & AIR FIELD LIGHT FEEDER PM: CAYUBIT, SUNSHINE

Work Mix: Aviation Capacity Project Extra Description: AIRPORT FULL NAME: DADE-COLLIER TRAINING AND TRANSITION APT Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2023 5 Year Total Capital Improvement/Operating DDR $37,613 $37,613 DPTO $167,387 $167,387 LF $51,250 $51,250 Total For Project 438612.1 $256,250 $256,250

October. 10 2019 Page 118 of 151 HIGHWAY SYSTEM: 09 AVIATION

438618.1 MIAMI INT'L AIRPORT TERMINAL E THRU F CONNECT OR PM: CAYUBIT, SUNSHINE Work Mix: Aviation Preservation Project Extra Description: Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2023 5 Year Total Capital Improvement/Operating DIS $4,000,000 $4,000,000 LF $4,000,000 $4,000,000 Total For Project 438618.1 $8,000,000 $8,000,000

438806.1 MIAMI OPA LOCKA EXEC UTIVE AIRPORT BLAST FENCE PM: CAYUBIT, SUNSHINE

Work Mix: Aviation Capacity Project Extra Description: AIRPORT SITE ID: 3339*A JACIP UPIN: PFL0010445 Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2021 5 Year Total Capital Improvement/Operating DDR $210,000 $210,000 LF $52,500 $52,500 Total For Project 438806.1 $262,500 $262,500

438808.1 MIAMI OPA LOCKA EXEC UTIVE APT UPGRADE 9R/27L TO NON-PRECISION RUNWAY PM: CAYUBIT, SUNSHINE

Work Mix: Aviation Safety Project Extra Description: AIRPORT SITE ID: 3339*A JACIP UPIN: PFL0010444 Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2021 5 Year Total Capital Improvement/Operating DPTO $950,000 $950,000 LF $237,500 $237,500 Total For Project 438808.1 $1,187,500 $1,187,500

438809.1 MIAMI OPA LOCKA EXEC UTIVE APT NEW PARALLEL TA XIWAY PM: CAYUBIT, SUNSHINE

Work Mix: Aviation Safety Project Extra Description: AIRPORT SITE ID: 3339*A JACIP UPIN: PFL0010428 Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2021 5 Year Total Capital Improvement/Operating DPTO $700,000 $700,000 LF $175,000 $175,000 Total For Project 438809.1 $875,000 $875,000

October. 10 2019 Page 119 of 151 HIGHWAY SYSTEM: 09 AVIATION

438810.1 MIAMI HOMESTEAD GENE RAL X51 WIDEN BLDG 6 PARK ING LOT - ROADWAY ACCESS PM: CAYUBIT, SUNSHINE Work Mix: Aviation Capacity Project Extra Description: AIRPORT SITE ID: 32421*A LOC ID: X51 JACIP UPIN: PFL0009083 Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2021 5 Year Total Capital Improvement/Operating DPTO $900,000 $900,000 LF $225,000 $225,000 Total For Project 438810.1 $1,125,000 $1,125,000

439492.1 MIAMI INT'L AIRPORT FEDERAL INSPECTION STN RE FURBISHMENT PM: CAYUBIT, SUNSHINE

Work Mix: Aviation Preservation Project Extra Description: UPIN# PFL0011473 APT SITE ID# 3333*A Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2022 FY 2023 5 Year Total Capital Improvement/Operating DDR $577,216 $1,290,353 $1,867,569 DPTO $8,132,771 $1,709,647 $9,842,418 LF $8,709,987 $3,000,000 $11,709,987 Total For Project 439492.1 $17,419,974 $6,000,000 $23,419,974

442409.1 MIAMI OPA LOCKA EXEC UTIVE APT WIDEN TAXIWAY P TO PROVIDE ADG IV PM: CAYUBIT, SUNSHINE Work Mix: Aviation Capacity Project Extra Description: AIRPORT SITE#3339*A JACIP UPIN# PFL0010459 Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2023 5 Year Total Capital Improvement/Operating DPTO $210,000 $210,000 LF $52,500 $52,500 Total For Project 442409.1 $262,500 $262,500

442410.1 MIAMI INT'L AIRPORT NEW WAREHOUSE AND APRON E XPANSION PM: CAYUBIT, SUNSHINE Work Mix: Aviation Capacity Project Extra Description: PSEE REQUEST SUBMITTED 9/19/17 AIRPORT SITE#333*A JACIP UPIN# Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2023 5 Year Total Capital Improvement/Operating DDR $4,734,614 $4,734,614 DPTO $3,107,756 $3,107,756 LF $7,842,370 $7,842,370 Total For Project 442410.1 $15,684,740 $15,684,740

October. 10 2019 Page 120 of 151 HIGHWAY SYSTEM: 09 AVIATION

443530.1 MIAMI INT'L AIRPORT CONSOLIDATED OFFICE COMPL EX PM: CAYUBIT, SUNSHINE Work Mix: Aviation Capacity Project Extra Description: CAPACITY PROJECT Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2021 5 Year Total Capital Improvement/Operating DDR $1,000,000 $1,000,000 DPTO $950,000 $950,000 LF $1,950,000 $1,950,000 Total For Project 443530.1 $3,900,000 $3,900,000

443531.1 MIAMI INT'L AIRPORT TERMINAL WIDE FACADE RENO VATION PM: CAYUBIT, SUNSHINE

Work Mix: Aviation Preservation Project Extra Description: PRESERVATION PROJECT Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2021 5 Year Total Capital Improvement/Operating DDR $2,000,000 $2,000,000 DPTO $8,573,738 $8,573,738 LF $10,573,738 $10,573,738 Total For Project 443531.1 $21,147,476 $21,147,476

FY 2021 FY 2022 FY 2023 5 Year Total HIGHWAY SYSTEM: 09 Total $44,055,682 $28,419,974 $33,237,704 $105,713,360

October. 10 2019 Page 121 of 151 HIGHWAY SYSTEM: 10 RAIL

433511.2 NE 203 STREET INTERS ECTION IMPROVEMENTS BETWN SR 5/US-1 & W. DIXIE HWY PM: ARVELO/QUERO City: AVENTURA

Work Mix: Rail Capacity Project Extra Description: ELEVATING WB NE 203 STREET OVER THE FEC RAILROAD TRACK AND WEST DIXIE HIGHWAY. INCLUDES WIDENING ROADWAY ALONG SB & EB NE 203 STREET INCLUDING THE BRIDGE. UPDATING PEDESTRIAN RAMPS, SIGNAGE, PAVEMENT MARKINGS, AND LIGHTING TO MEET THE CURRENT Cont. Class: District Let STANDARDS. INCLUDES DRAINAGE IMPROVEMENTS AND REPLACEMENT OF OVERHEAD SIGN STRUCTURES. PD&E UNDER 433511-1

Phase Fund Code FY 2021 5 Year Total RW Land DDR $2,303,217 $2,303,217 GMR $1,872,929 $1,872,929 SIWR $752,513 $752,513 Construction DPTO $25,881,878 $25,881,878 GMR $11,997,676 $11,997,676 CEI DIH $513,000 $513,000 DPTO $483,000 $483,000 GMR $5,920,446 $5,920,446 Total For Project 433511.2 $49,724,659 $49,724,659

FY 2021 5 Year Total HIGHWAY SYSTEM: 10 Total $49,724,659 $49,724,659 HIGHWAY SYSTEM: 11 SEAPORT

433363.1 PORT OF MIAMI CRUISE TERMINAL IMPROVEMENTS PM: CAYUBIT, SUNSHINE

Work Mix: Seaport Capacity Project Extra Description: SEQ 01 = FY 2014 FSTED ALLOCATION CHANGE CONTRACT CLASS 4 TO 2 2015-03-27 SEQ 02 = PFS0001776 ($2.75M) FROM FM 431761-1-94-02 & FM 431764-1-94-03 FY 2017 FSTED ALLOCATION POM CRUISE TERMINAL IMPROVEMENTS ***SEE WP 45 FOR SCOPE OF WORK FOR SEQ 02 FY Cont. Class: Extern Mngd(Not Lap) 2017 FUNDING***

Phase Fund Code FY 2021 5 Year Total Capital Improvement/Operating LF $4,250,000 $4,250,000 PORT $4,250,000 $4,250,000 Total For Project 433363.1 $8,500,000 $8,500,000

438029.1 PORT OF MIAMI PASSEN GER BOARDING BRIDGES PM: CAYUBIT, SUNSHINE

Work Mix: Seaport Capacity Project Extra Description: SEACIP# PFS0002495 Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2021 5 Year Total Capital Improvement/Operating DPTO $2,300,000 $2,300,000 LF $2,300,000 $2,300,000 Total For Project 438029.1 $4,600,000 $4,600,000

FY 2021 5 Year Total HIGHWAY SYSTEM: 11 Total $13,100,000 $13,100,000 October. 10 2019 Page 122 of 151 HIGHWAY SYSTEM: 13 NON-SYSTEM SPECIFIC

250610.5 MIAMI DADE COUNTY LA NDSCAPE JPA PM: SCHOT, KEVIN

Work Mix: Landscaping Extra Description: Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2023 FY 2024 FY 2025 5 Year Total JPA/LAP Construction DS $500,000 $500,000 $500,000 $1,500,000 Total For Project 250610.5 $500,000 $500,000 $500,000 $1,500,000

252094.1 METROPOLITAN PLANNIN G ORGANIZATION (MPO) SUPP ORT PM: THOMAS, CURLENE

Work Mix: Modal Systems Planning Extra Description: EXPRESSWAY/HOV PLANNING & ANALYSIS I-95/SR826/SR836/SR874/I-75 CORRIDORS INCLUDES LOCAL GOVERNMENT COORDINATION PH 12- 01 = CNT: C6031/CONSULT: VANASSE HANGEN BRUSTLIN PH 12-01 = CNT: C7723/CONSULT: VANASSE HANGEN BRUSTLIN PH 12-02 = CNT: Cont. Class: Extern Mngd(Not Lap) C6031/CONSULT: URS ***SEE WP45***

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total Planning D $400,000 $525,000 $400,000 $300,000 $450,000 $2,075,000 Total For Project 252094.1 $400,000 $525,000 $400,000 $300,000 $450,000 $2,075,000

252180.2 TRANSPORTATION SYSTE M PLANNING & STATISTICS S UPPORT PM: LYN, NEIL

Work Mix: Transportation Statistics Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total Planning D $500,000 $500,000 $500,000 $500,000 $2,000,000 Total For Project 252180.2 $500,000 $500,000 $500,000 $500,000 $2,000,000

416660.4 MIAMI DADE COUNTY - LUDLAM TRAIL FROM NW 7 ST REET TO SW 40 STREET PM: NUNEZ/GEHRKE

Work Mix: Bike Path/Trail Extra Description: SUNTRAIL ID# THIS LUDLUM TRAIL SEGMENT A, PHASE II PROJECT IS PART OF THE SUNTRAIL PROGRAM. PROJECT LENGTH: 0.86 MILES AND 10.4 ACRES Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2024 5 Year Total Construction TLWR $8,000,000 $8,000,000 Total For Project 416660.4 $8,000,000 $8,000,000

October. 10 2019 Page 123 of 151 HIGHWAY SYSTEM: 13 NON-SYSTEM SPECIFIC

416660.6 LUDLAM TRAIL CORRIDO R SEGMENT B PHASE 1 PM: NUNEZ, XIOMARA Work Mix: Bike Path/Trail Extra Description: MUNICIPALITY: MIAMI DADE PARK AND RECREATION OPEN SPACES LUDLAM TRAIL CORRIDOR SEGMENT B PHASE 1 FUNDING REQUEST IS FOR DESIGN OF .91 MILES OF A SHARED-USE PATH AND GREENWAY TRAIL PROJECT. FY17 TPO RANK #10 /FDOT RANK #12 Cont. Class: Local Agcy Pgm (Lap)

Phase Fund Code FY 2024 5 Year Total P.E. LF $80,000 $80,000 SA $5,000 $5,000 TALU $627,531 $627,531 Total For Project 416660.6 $712,531 $712,531

428044.1 PLEMO OPERATING FUND NON-PROJECT SPECIFIC CON SULTANT TASKS PM: HUYNH, DAT

Work Mix: Transportation Planning Extra Description: PROJECT TO PROVIDE OPERATING FUNDS FOR NON-PROJECT **WP45** SPECIFIC PLEMO CONSULTANT WORK TASKS FOR PLANNING, PROJECT DEVELOPMENT, AND ENVIRONMENTAL WORK ACTIVITIES. FY17 12-01 FOR PLANNING / 12-02 FOR GIS & 12-03 FOR SCANNING EFFORTS FOR C. Cont. Class: Misc - No Letting JAMES/12-01 = AECOM 12-03 = STANTEC FY18/12-02 - FLP (APPROV. FROM H. DESDUNES) **WP45**

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total Planning D $244,383 $244,383 $244,383 $244,383 $244,383 $1,221,915 Total For Project 428044.1 $244,383 $244,383 $244,383 $244,383 $244,383 $1,221,915

432400.2 MIAMI-DADE COUNTYWDE GMX DOCUMENTS REVIEW PM: JEFFRIES, KEN Work Mix: Transportation Statistics Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total PDE DIH $10,000 $10,000 $10,000 $10,000 $10,000 $50,000 Total For Project 432400.2 $10,000 $10,000 $10,000 $10,000 $10,000 $50,000

432590.3 DISTRICTWIDE PLANNIN G CONSULTANT SUPPORT PM: JEFFRIES, KEN Work Mix: Transportation Planning Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 5 Year Total PDE DDR $300,000 $300,000 $300,000 $150,000 $1,050,000 DIH $10,000 $10,000 $10,000 $10,000 $40,000 Total For Project 432590.3 $310,000 $310,000 $310,000 $160,000 $1,090,000

October. 10 2019 Page 124 of 151 HIGHWAY SYSTEM: 13 NON-SYSTEM SPECIFIC

432590.4 DISTRICTWIDE PLANNIN G CONSULTANT SUPPORT PM: JEFFRIES, KEN Work Mix: Transportation Planning Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2024 FY 2025 5 Year Total PDE DDR $150,000 $300,000 $450,000 DIH $10,000 $10,000 $20,000 Total For Project 432590.4 $160,000 $310,000 $470,000

435501.5 DTPW - UNDERLINE PHA SE 6 PM: NUNEZ, XIOMARA

Work Mix: Bike Path/Trail Extra Description: MUNICIPALITY: DTPW STRUNG W/445793-1 THE INTENT OF THIS PROJECT IS TO CREATE A SAFE, OFF-ROAD PEDESTRIAN AND BICYCLE TRAIL FROM SW 42 AVENUE TO GRANADA BOULEVARD. THE PROJECT ALSO ALIGNS WITH THE MIAMI-DADE 2040 LONG RANGE TRANSPORTATION Cont. Class: Extern Mngd(Not Lap) PLAN, THE PARKS, RECREATION AND OPEN SPACES DEPARTMENT SYSTEM MASTER PLAN THE CITY OF MIAMI

Phase Fund Code FY 2024 5 Year Total JPA/LAP Construction LF $8,600,000 $8,600,000 SU $500,000 $500,000 CEI SA $5,000 $5,000 JPA/LAP CEI LF $500,000 $500,000 Total For Project 435501.5 $9,605,000 $9,605,000

438662.1 CITY OF CORAL GABLES - ALHAMBRA CIRCLE BIKE L ANES PM: NUNEZ, XIOMARA

Work Mix: Bike Lane/Sidewalk Extra Description: MUNICIPALITY: CITY OF CORAL GABLES FY15 TPO RANK #2 /FDOT RANK #8 Cont. Class: Local Agcy Pgm (Lap)

Phase Fund Code FY 2021 5 Year Total JPA/LAP Construction TALU $597,670 $597,670 CEI TALT $5,000 $5,000 JPA/LAP CEI LF $89,651 $89,651 Total For Project 438662.1 $692,321 $692,321

October. 10 2019 Page 125 of 151 HIGHWAY SYSTEM: 13 NON-SYSTEM SPECIFIC

438667.1 BLACK CREEK TRAIL SE GMENT B PHASE I PM: NUNEZ, XIOMARA Work Mix: Bike Path/Trail Extra Description: MIAMI DADE COUNTY PARKS, RECREATION, AND OPEN SPACES MPO PRIORITY ID# 22/FY 21 MPO PRIORITY PROJECTS LISTING MPO RESOLUTION #17-14/LRTP PRIORITY #2 FY15 TPO RANK #5 /FDOT RANK #4 Cont. Class: Local Agcy Pgm (Lap)

Phase Fund Code FY 2022 5 Year Total JPA/LAP Construction LF $114,257 $114,257 TALU $628,412 $628,412 CEI SA $5,000 $5,000 JPA/LAP CEI LF $68,554 $68,554 Total For Project 438667.1 $816,223 $816,223

439334.3 MIAMI-DADE MPO FY 20 20/2021-2021/2022 UPWP PM: THOMAS, CURLENE

Work Mix: Transportation Planning Extra Description: Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2021 FY 2022 5 Year Total Planning PL $2,203,342 $2,203,342 $4,406,684 Total For Project 439334.3 $2,203,342 $2,203,342 $4,406,684

439334.4 MIAMI-DADE MPO FY 20 22/2023-2023/2024 UPWP PM: THOMAS, CURLENE

Work Mix: Transportation Planning Extra Description: Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2023 FY 2024 5 Year Total Planning PL $2,203,342 $2,203,342 $4,406,684 Total For Project 439334.4 $2,203,342 $2,203,342 $4,406,684

439334.5 MIAMI-DADE MPO FY 20 24/2025-2025/2026 UPWP PM: THOMAS, CURLENE Work Mix: Transportation Planning Extra Description: Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2025 5 Year Total Planning PL $2,203,342 $2,203,342 Total For Project 439334.5 $2,203,342 $2,203,342

October. 10 2019 Page 126 of 151 HIGHWAY SYSTEM: 13 NON-SYSTEM SPECIFIC

439898.1 BISCAYNE TRAIL SEGME NT D PHASE II FROM SW 117 AVE TO SW 137 AVE PM: NUNEZ, XIOMARA Work Mix: Bike Path/Trail Extra Description: 2018 TPO PRIORITY #5 SUNTRAIL ID# 6999991 AWARDED DURING FY2018 APPLICATION CYCLE Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2024 5 Year Total Construction LF $264,866 $264,866 TLWR $1,254,731 $1,254,731 Total For Project 439898.1 $1,519,597 $1,519,597

441639.1 SNAPPER CREEK TRAIL SEGMENT B PHASE 1 PM: NUNEZ, XIOMARA

Work Mix: Bike Path/Trail Extra Description: MUNICIPALITY: MIAMI DADE PARK AND RECREATION OPEN SPACES FOR DESIGN, CONSTRUCTION AND CONSTRUCTION ENGINEERING AND INSPECTION OF A 12'WIDE SHARE USED PATH ALONG THE NORTH SIDE OF THE CANAL AND WEST SIDE OF SW 67 AVENUE FY17 TPO RANK #11 Cont. Class: Local Agcy Pgm (Lap) /FDOT RANK #9

Phase Fund Code FY 2024 5 Year Total JPA/LAP Construction LF $108,089 $108,089 TALT $357,964 $357,964 CEI SA $5,000 $5,000 JPA/LAP CEI SA $17,924 $17,924 TALT $27,654 $27,654 Total For Project 441639.1 $516,631 $516,631

441640.1 CITY OF CORAL GABLES - LAST MILE TRANSIT STOP IMPROVEMENTS PM: NUNEZ, XIOMARA Work Mix: Sidewalk Extra Description: MUNICIPALITY: CITY OF CORAL GABLES LAST MILE TRANSIT STOP IMPROVEMENTS PROGRAM IS FOCUSED ON BRINGING EACH OF THE ONE HUNDRED SEVEN (107) BUD STOPS ON LOCAL CORAL GABELS STREETS INTO COMPLIANCE WITH THE ADA ACT IN ADDITION TO MAKING OTHER Cont. Class: Local Agcy Pgm (Lap) IMPROVEMENTS TO ENCOURAGE MASS TRANSIT RIDERSHIP FY17 TPO RANK #9 /FDOT RANK #2

Phase Fund Code FY 2022 5 Year Total JPA/LAP Construction LF $669,680 $669,680 TALT $6,537 $6,537 TALU $993,463 $993,463 CEI SA $5,000 $5,000 JPA/LAP CEI LF $164,485 $164,485 Total For Project 441640.1 $1,839,165 $1,839,165

October. 10 2019 Page 127 of 151 HIGHWAY SYSTEM: 13 NON-SYSTEM SPECIFIC

441647.1 TOWN OF MIA LAKES - NW 79TH COURT TRANSPORTAT ION IMPROVEMENTS PROJECT PM: NUNEZ, XIOMARA Work Mix: Bike Lane/Sidewalk Extra Description: MUNICIPALITY: TOWN OF MIAMI LAKES NW 79TH COURTH TRANSPORTATION IMPROVEMENTS PROJECT FY17 TPO RANK #1 /D6 RANK #4 Cont. Class: Local Agcy Pgm (Lap)

Phase Fund Code FY 2021 FY 2023 5 Year Total P.E. LF $205,000 $205,000 JPA/LAP Construction LF $612,000 $612,000 TALU $1,000,000 $1,000,000 CEI TALU $5,000 $5,000 JPA/LAP CEI LF $77,000 $77,000 Total For Project 441647.1 $205,000 $1,694,000 $1,899,000

443866.1 NW 59 AVENUE ROADWAY EXTENSION AND REDEVELOPM ENT PM: NUNEZ, XIOMARA Work Mix: Miscellaneous Construction Extra Description: DESIGN/ CONSTRUCT BRIDGE AND ROADWAY IMPROVEMENT EXTENDING NW 59TH AVENUE TO NW 151ST STREET. INCLUDES LAND ACQUISITION OF: (1) 5.86 ACRE PARCEL FROM MIAMI-DADE AVIATION DEPARTMENT AND (2) ROADWAY ACCESS POINT ON NW 151ST STREET. CONSTRUCT A Cont. Class: Extern Mngd(Not Lap) BRIDGE EXTENDING NW 59 AVE OVER C-8 (CANAL #870609). JPA WITH CITY OF MIAMI LAKES

Phase Fund Code FY 2021 5 Year Total Construction CIGP $2,474,000 $2,474,000 LFP $2,474,000 $2,474,000 Total For Project 443866.1 $4,948,000 $4,948,000

444194.1 SNAPPER CREEK TRAIL SEGMENT A SW 107 AVENUE G AP PM: NUNEZ, XIOMARA

Work Mix: Bike Path/Trail Extra Description: MUNICIPALITY: MDPROS FY25 TPO RANK #9 /D6 RANK #4 THE SEGMENT A TRAIL MEANDERS MAINLY WITHIN THE SNAPPER CREEK (C-2) CANAL RIGHT-OF-WAY WITH ADDITIONAL SEGMENTS LOCATED W/IN STREET RIGHT-OF-WAY. THE TRAIL PROVIDES A ROUTE OF TRAVEL FROM THE Cont. Class: Local Agcy Pgm (Lap) C-4 CANAL NEAR FLORIDA INTERNATIONAL UNIVERSITY (FIU) TO KENDALL DRIVE. THE TRAIL RUNS CONTINUOUS

Phase Fund Code FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total P.E. LF $182,167 $183,259 $365,426 JPA/LAP Construction LF $356,771 $113,648 $470,419 SU $500,000 $500,000 TALU $256,675 $256,675 JPA/LAP CEI LF $82,389 $82,389 TALT $103,838 $103,838 Total For Project 444194.1 $182,167 $183,259 $939,160 $474,161 $1,778,747

October. 10 2019 Page 128 of 151 HIGHWAY SYSTEM: 13 NON-SYSTEM SPECIFIC

444195.1 PEDESTRIAN AND BICYC LE SAFETY EDUCATION FOR H IGH SCHOOL STUDENTS PM: YEE-FONG/NUNEZ Work Mix: Public Information/Education Extra Description: THE PROPOSED AIMS TO COLLABORATE W/AND BUILD ON WALK SAFE & BIKE-SAFE PROGRAMS AT THE UNIVERSITY OF MIAMI BY FOCUSING THE EDUCATION & TRAINING ACTIVITIES ON HIGH SCHOOL STUDENTS WHICH WERE NOT INCLUDED IN BIKE-SAFE AND WALK-SAFE Cont. Class: Local Agcy Pgm (Lap) PROGRAMS. THE PROPOSED PROGRAM WILL CONSIST OF EVIDENCE BASED EDUCATIONAL & TRAINING CURRICULA TO TEACH PEDESTRAIN &

Phase Fund Code FY 2024 5 Year Total Planning LF $76,788 $76,788 TALU $76,788 $76,788 Total For Project 444195.1 $153,576 $153,576

444196.1 MIAMI BEACH HIGH SCH OOL PEDESTRIAN ENHANCEMEN TS PM: NUNEZ, XIOMARA Work Mix: Pedestrian Safety Improvement Extra Description: THE CITY OF MIAMI BEACH IS REQUESTING FUNDS TO ENHANCE TRANSPORTATION ALTERNATIVES & SAFETY NEAR MIAMI BEACH SENIOR HIGHSCHOOL. THIS APPLICATION IS INTENDED TO ENHANCE THE EXISTING PEDESTRAIN & BICYCLE NETWORK TO PROMOTE THE USE OF Cont. Class: Local Agcy Pgm (Lap) BICYCLING AND WALKING AS A VIABLE METHOD OF TRANSPORTATION TO THE SCHOOL. THIS PROJECT WILL ADD SIGNAGE, RESTORE

Phase Fund Code FY 2022 FY 2024 5 Year Total P.E. LF $48,729 $48,729 JPA/LAP Construction TALU $218,794 $218,794 CEI SA $5,000 $5,000 JPA/LAP CEI LF $40,000 $40,000 Total For Project 444196.1 $48,729 $263,794 $312,523

444197.1 NORTH BAY VILLAGE - TREASURE ISLAND ADA IMPRO VEMENTS PM: NUNEZ, XIOMARA Work Mix: Sidewalk Extra Description: MUNICIPALITY - NORTH BAY VILLAGE IN JANUARY 2018. THE VILLAGE COMPLETED AN ADA SELF EVALUATION AND TRANSITION PLAN. THE VILLAGE IS REQUESTING $150K TO IMPLEMENT SOME OF THE URGENT RECOMMENDATIONS FROM THE ADA PLAN. Cont. Class: Local Agcy Pgm (Lap)

Phase Fund Code FY 2022 FY 2024 5 Year Total Planning LF $7,650 $7,650 P.E. LF $23,000 $23,000 JPA/LAP Construction LF $31,000 $31,000 TALU $153,000 $153,000 CEI SA $5,000 $5,000 JPA/LAP CEI LF $15,300 $15,300 Total For Project 444197.1 $30,650 $204,300 $234,950

October. 10 2019 Page 129 of 151 HIGHWAY SYSTEM: 13 NON-SYSTEM SPECIFIC

444299.1 SNAKE CREEK TRAIL EX TENSION TO GREYNOLDS PARK PM: NUNEZ, XIOMARA Work Mix: Bike Path/Trail Extra Description: PLANNED IMPROVEMENTS INCLUDE DESIGNATING S. GLADES DR. (NE 165TH STREET) AS A ONE-WAY, WESTBOUND ROADWAY FROM NE 21 AV. TO NE 19TH AV. AND WIDENING THE EXISTING BIKE LANE ON THE NORTH SIDE OF S. GLADES DR. TO CREATE A TWO-WAY CYCLE TRACK; WIDENING Cont. Class: Local Agcy Pgm (Lap) THE EXISTING BICYCLE LANE ON THE NORTH SIDE OF S. GLADES DR. FROM NE 19 AV. TO MIAMI DR. TO CREATE A ONE

Phase Fund Code FY 2022 FY 2024 5 Year Total P.E. LF $138,830 $138,830 SA $5,000 $5,000 JPA/LAP Construction LF $173,588 $173,588 TALU $403,072 $403,072 CEI SA $5,000 $5,000 JPA/LAP CEI LF $55,374 $55,374 Total For Project 444299.1 $143,830 $637,034 $780,864

444489.1 DISTRICTWIDE RIGHT O F WAY MAP UPDATES AND DEV ELOPMENT PM: ALBURY, CRISTINA Work Mix: Preliminary Engineering Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 5 Year Total P.E. DS $489,600 $489,600 $489,600 $489,600 $1,958,400 Total For Project 444489.1 $489,600 $489,600 $489,600 $489,600 $1,958,400

445154.1 SAFE RTS. SCHOOL WES T MIAMI MIDDLE SCHOOL PM: NUNEZ, XIOMARA

Work Mix: Pedestrian Safety Improvement Extra Description: 2018 TPO PRIORITY #6 SRTS PROJECT FOR THE FOLLOWING SCHOOL: WEST MIAMI MIDDLE SCOPE: ADDING CROSSWALKS, ENHANCING EXISTING CROSSWALKS, ADDING PEDESTRAIN SINAGE, FILLING SIDEWALK GAPS, ADDING SCHOOL ZONE SIGNAGE, UPGRADING ADA PUSHBUTTONS AND Cont. Class: Local Agcy Pgm (Lap) RAMPS. FDOT RANK # 5

Phase Fund Code FY 2022 FY 2024 5 Year Total P.E. SA $36,286 $36,286 JPA/LAP Construction SU $156,437 $156,437 CEI SU $5,000 $5,000 JPA/LAP CEI SU $31,286 $31,286 Total For Project 445154.1 $36,286 $192,723 $229,009

October. 10 2019 Page 130 of 151 HIGHWAY SYSTEM: 13 NON-SYSTEM SPECIFIC

445155.1 SAFE RTS. SCHOOL - O LYMPIA HEIGHTS ELEMENTARY PM: NUNEZ, XIOMARA Work Mix: Pedestrian Safety Improvement Extra Description: 2018 TPO PRIORITY #6 SAFE ROUTES TO SCHOOL PROJECT FOR THE FOLLOWING SCHOOLS; OLYMPIA HEIGHTS ELEMENTARY SCOPE: ADD CROSSWALKS, ENHANCING EXISTING CROSSWALKS, ADDING PEDESTRIAN SIGNAGE, FILLING SIDEWALK GAPS, ADDING SCHOOL ZONE SINAGE, Cont. Class: Local Agcy Pgm (Lap) UPDRADING ADA PUSH BUTTONS.

Phase Fund Code FY 2023 FY 2025 5 Year Total P.E. SU $15,616 $15,616 JPA/LAP Construction SU $63,087 $63,087 CEI SU $3,000 $3,000 JPA/LAP CEI SU $12,617 $12,617 Total For Project 445155.1 $15,616 $78,704 $94,320

445156.1 SAFE RTS. SCHOOL - M IAMI EDISON HIGH SCHOOL PM: NUNEZ, XIOMARA Work Mix: Pedestrian Safety Improvement Extra Description: TPO PRIORITY #6 SRTS PROJECT FOR MIAMI EDISON HIGH SCHOOL SCOPE: ADDING CROSSWALKS, ENHANCING EXISTING CROSSWALKS, ADDING PEDESTRIAN SIGNAGE, FILLING SIDEWALK GAPS, ADDING SCHOOL ZONE SINAGE, UPDRADING ADA PUSH BUTTONS. Cont. Class: Local Agcy Pgm (Lap)

Phase Fund Code FY 2023 FY 2025 5 Year Total P.E. SU $10,326 $10,326 JPA/LAP Construction SU $36,346 $36,346 CEI SU $1,500 $1,500 JPA/LAP CEI SU $8,827 $8,827 Total For Project 445156.1 $10,326 $46,673 $56,999

445163.1 SAFE RTS. SCHOOL - N ORLAND ELEMENTARY SCHOOL PM: NUNEZ, XIOMARA

Work Mix: Pedestrian Safety Improvement Extra Description: TPO PRIORITY #6 SRTS PROJECT FOR NORLAND ELEMENTARY SCHOOL SCOPE: ADDING CROSSWALKS, ENHANCING EXISTING CROSSWALKS, ADDING PEDESTRIAN SIGNAGE, FILLING SIDEWALK GAPS, ADDING SCHOOL ZONE SINAGE, UPDRADING ADA PUSH BUTTONS. Cont. Class: Local Agcy Pgm (Lap)

Phase Fund Code FY 2023 FY 2025 5 Year Total P.E. SU $47,729 $47,729 JPA/LAP Construction SU $208,648 $208,648 CEI SU $6,000 $6,000 JPA/LAP CEI SU $41,730 $41,730 Total For Project 445163.1 $47,729 $256,378 $304,107

October. 10 2019 Page 131 of 151 HIGHWAY SYSTEM: 13 NON-SYSTEM SPECIFIC

445165.1 SAFE RTS. SCHOOL - N ORLAND MIDDLE SCHOOL PM: NUNEZ, XIOMARA Work Mix: Pedestrian Safety Improvement Extra Description: TPO PRIORITY #6 SRTS PROJECT FOR NORLAND MIDDLE SCHOOL SCOPE: ADDING CROSSWALKS, ENHANCING EXISTING CROSSWALKS, ADDING PEDESTRIAN SIGNAGE, FILLING SIDEWALK GAPS, ADDING SCHOOL ZONE SINAGE, UPDRADING ADA PUSH BUTTONS. Cont. Class: Local Agcy Pgm (Lap)

Phase Fund Code FY 2023 FY 2025 5 Year Total P.E. SU $30,654 $30,654 JPA/LAP Construction SU $133,277 $133,277 CEI SU $4,000 $4,000 JPA/LAP CEI SU $26,655 $26,655 Total For Project 445165.1 $30,654 $163,932 $194,586

446052.1 DPTW - SMART TRAIL A LONG NW 12 STREET PM: NUNEZ, XIOMARA

Work Mix: Bike Path/Trail Extra Description: MUNICIPALITY: DTPW FY25 TPO RANK #9/D6 RANK #18 CONSTRUCTION OF AN OFF ROAD PATH ALONG NW 12 STREET TO CONNECT TO THE DOLPHIN PARK AND RIDE STATION & SUBSEQUENTLY THE DOLPHIN MALL Cont. Class: Local Agcy Pgm (Lap)

Phase Fund Code FY 2025 5 Year Total P.E. TALT $231,018 $231,018 Total For Project 446052.1 $231,018 $231,018

446053.1 CITY OF MIAMI - I-39 5 PEDESTRIAN BAYWALK CONN ECTION PM: NUNEZ, XIOMARA

Work Mix: Pedestrian/Wildlife Overpass Extra Description: FY2025 TPO RANK #9 / MUNICIPALITY: CITY OF MIAMI THE PROJECT WIL BE AN APPROX. 540 FEET OVER THE WATER 16 TO 20 FOOT WIDE PEDESTRIAN BRIDGE/BAYWALK CONNECTION FROM THE EXISTING PEREZ ART MUSEUM (PAMM) AND MAURICE A. FERRE PARK BAYWALK IN THE Cont. Class: Local Agcy Pgm (Lap) SOUTH TO THE FDOT PROPERTY LINE UNDER 7-395 ABUTTING THE RESORTS WORLD MIAMI LLC PARCEL TO THE

Phase Fund Code FY 2021 FY 2023 5 Year Total P.E. LF $533,622 $533,622 JPA/LAP Construction LF $2,294,204 $2,294,204 TALT $873,956 $873,956 TALU $126,044 $126,044 JPA/LAP CEI LF $440,518 $440,518 Total For Project 446053.1 $533,622 $3,734,722 $4,268,344

October. 10 2019 Page 132 of 151 HIGHWAY SYSTEM: 13 NON-SYSTEM SPECIFIC

446054.1 MIAMI SHORES - SR 91 5/NE 6TH AVENUE PEDESTRIA N PROMENADE PM: NUNEZ, XIOMARA Work Mix: Bike Lane/Sidewalk Extra Description: MUNICIPALITY: MIAMI SHORES FY25 TPO RANK #9 /D6 RANK #14 EXPANSION OF THE ESISTING SIDEWALK TO A WIDE MULTI-PURPOSE PATH FACILITY OF 10 FEET IN WIDTH ON BOTH SIDES OF NE 6TH AVENUE, BETWEEN NE 96TH STREET AND 107TH STREET Cont. Class: Local Agcy Pgm (Lap)

Phase Fund Code FY 2023 FY 2025 5 Year Total P.E. LF $72,141 $72,141 JPA/LAP Construction LF $34,523 $34,523 TALT $345,231 $345,231 JPA/LAP CEI LF $21,361 $21,361 TALT $30,424 $30,424 Total For Project 446054.1 $72,141 $431,539 $503,680

446055.1 CITY OF MIAMI - MIAM I RIVER GREENWAY FROM NW 22 AVENUE TO NW 19 AVENUE PM: NUNEZ, XIOMARA Work Mix: Bike Lane/Sidewalk Extra Description: MUNICIPALITY: CITY OF MIAMI FY25 TPO RANK #9 /D6 RANK #10 THE PROJECT WILL PROVIDE FOR A PUBLICLY ACCESSIBLE PATHWAY FOR BICYCLISTS AND PEDESTRIANS IN CONCERT W/THE ROADWAY RECONSTRUCTION OF NW NORTH RIVER DRIVE. THIS PUBLIC PEDESTRIAN AND Cont. Class: Local Agcy Pgm (Lap) BICYCLE TRAIL ALONG THE HISTORIC MIAMI RIVER WILL CONNECT DIVERSE MULTICULTURAL NEIGHBORHOODS, PUBLIC

Phase Fund Code FY 2023 FY 2025 5 Year Total P.E. LF $412,812 $412,812 JPA/LAP Construction LF $2,005,733 $2,005,733 TALU $1,000,000 $1,000,000 JPA/LAP CEI LF $269,177 $269,177 Total For Project 446055.1 $412,812 $3,274,910 $3,687,722

446056.1 DTPW - COMMODORE TRA IL MISSING LINK PM: NUNEZ, XIOMARA

Work Mix: Bike Path/Trail Extra Description: MUNICIPALITY: DTPW FY25 TPO RANK #9 /D6 RANK #7 ROAD DIET AND BUFFERED BIKE LANES ON SOUTH MIAMI AVENUE. THIS PROJECT IS INTENDED TO IMPROVE SAFETY AND CONNECTIVITY FOR BICYCLISTS THAT USE THE COMMODORE TRAIL FOR COMMUTING AND RECREATIONAL Cont. Class: Local Agcy Pgm (Lap) PURPOSES TODAY

Phase Fund Code FY 2025 5 Year Total P.E. TALT $104,508 $104,508 Total For Project 446056.1 $104,508 $104,508

October. 10 2019 Page 133 of 151 HIGHWAY SYSTEM: 13 NON-SYSTEM SPECIFIC

446057.1 TOWN OF MIAMI LAKES - FAIRWAY DRIVE BIKE LANE S & CROSSWALK IMPROVEMNTS PM: NUNEZ, XIOMARA Work Mix: Bike Lane/Sidewalk Extra Description: MUNICIPALITY: TWN OF MIA LAKES FY25 TPO RANK #9/D6 RANK #8 THIS PROJECT INCLUDES THE DESIGN, PERMITTING, & CONSTRUCTION BIKE LANES AND CROSSWALKS IMPROVEMENTS FOR ENHANCED PEDESTRIAN AND BICYCLE SAFETY-RELATED INFRASTRUCTURE IN COMPLIANCE Cont. Class: Local Agcy Pgm (Lap) WITH THE AMERICANS WITH DISABILITIES ACT.

Phase Fund Code FY 2023 FY 2025 5 Year Total P.E. LF $119,000 $119,000 JPA/LAP Construction LF $156,000 $156,000 TALT $350,274 $350,274 TALU $529,726 $529,726 JPA/LAP CEI LF $25,000 $25,000 TALT $20,000 $20,000 Total For Project 446057.1 $119,000 $1,081,000 $1,200,000

446059.1 MDPROS - LUDLAM TRAI L ACCESS & TRAILHEAD IMPR OVMNTS AT A.D BARNES PARK PM: NUNEZ, XIOMARA

Work Mix: Pedestrian/Wildlife Overpass Extra Description: MUNICIPALITY: MDPROS FY25 TPO RANK #9 /D6 RANK #12 WORK WILL INCLUDE AN APPROXIMATELY 10-FOOT WIDE, 100-FOOT LONG PRE- FABRICATED PEDESTRIAN BRIDGE AND APPROACHES ACROSS CORAL GABLES (C-3) CANAL TO EXISTING PARK PATHS WITH RECONSTRUCTION OF Cont. Class: Local Agcy Pgm (Lap) APPROXIMATELY 22 LF OF EXISTING ASPHALT PARK PATH ON THE SOUTH END OF BRIDGE.

Phase Fund Code FY 2025 5 Year Total P.E. TALT $454,827 $454,827 Total For Project 446059.1 $454,827 $454,827

446064.1 CITY OF DORAL - CITY WIDE SIDEWALK, CURB RAMP & CROSSWLK IMPROVEMENTS PM: NUNEZ, XIOMARA

Work Mix: Sidewalk Extra Description: MUNICIPALITY: CITY OF DORAL FY25 TPO RANK #9 /D6 RANK #16 CITYWIDE SIDEWALK, CURB RAMP, AND CROSSWALK IMPROVEMENTS PHASE II Cont. Class: Local Agcy Pgm (Lap)

Phase Fund Code FY 2021 5 Year Total JPA/LAP Construction LF $400,000 $400,000 TALT $1,000,000 $1,000,000 JPA/LAP CEI LF $115,000 $115,000 Total For Project 446064.1 $1,515,000 $1,515,000

October. 10 2019 Page 134 of 151 HIGHWAY SYSTEM: 13 NON-SYSTEM SPECIFIC

446069.1 MDPROS - SNAKE CREEK TRAIL ACCESS AND PATH IM PROVEMENTS PM: NUNEZ, XIOMARA

Work Mix: Bike Path/Trail Extra Description: MUNICIPALITY: MDPROS FY25 TPO RANK #9 /D6 RANK #13 WORK AT THE MIAMI GARDENS DR. AND S. GLADES DR. INTERSECTION WILL INCLUDE APPROXIMATELY 350 LF OF IMPROVEMENTS INCLUDING SIDEWALK WIDENING, A REBUILT TRAIL CONNECTION PAVEMENT MARKINGS, Cont. Class: Local Agcy Pgm (Lap) HIGH EMPHASIS CROSSWALKS REGULATORY AND WAYFINDING SIGNS, BOLLARDS, ADA TACTILE WARNING STRIPS

Phase Fund Code FY 2025 5 Year Total P.E. TALT $173,962 $173,962 Total For Project 446069.1 $173,962 $173,962

446070.1 CITY OF HOMESTEAD - DOWNTOWN PEDESTRIAN ACCE SS PM: NUNEZ, XIOMARA Work Mix: Sidewalk Extra Description: MUNICIPALITY: CITY OF HOMESTEAD FY25 TPO RANK #9 / D6 RANK #17 RENOVATE THE EXISTING PATHWAYS ALONG KROME AVENUE FROM NW 40 ST TO SOUTH FLAGGER DRIVE. THE PROJECT WILL CONSIST OF CONSTRUCTING APPROXIMATELY 3800 LF OF 6-10 FOOT PATHWAYS THAT RUNS Cont. Class: Local Agcy Pgm (Lap) THROUGH DOWNTOWN HOMESTEAD

Phase Fund Code FY 2025 5 Year Total JPA/LAP Construction TALT $900,000 $900,000 JPA/LAP CEI TALT $100,000 $100,000 Total For Project 446070.1 $1,000,000 $1,000,000

446071.1 DTPW - HIGHLIGHTING BIKE LANES ON MULTILANE R OADS PM: NUNEZ, XIOMARA

Work Mix: Bike Lane/Sidewalk Extra Description: MUNICIPALITY: DTPW FY25 TPO RANK #9 / D6 RANK #20 IMPROVE THE VISIBILITY OF THE BIKE LANE SPACE BY INSTALLING GREEN PAINT AT CONFLICT POINTS ALONG SEVERAL MULTILANE ROADS SW 72 STREET FROM SW 147 AVENUE TO SW 118 AVENUE; SW 216 STREET FROM SW 112 Cont. Class: Local Agcy Pgm (Lap) AVENUE

Phase Fund Code FY 2025 5 Year Total P.E. TALT $51,987 $51,987 Total For Project 446071.1 $51,987 $51,987

446124.4 PUBLIC COMMUNICATION FOR OKEECHOBEE ROAD RECO NSTRUCTION PM: BURGHER, TISH Work Mix: Public Information/Education Extra Description: PUBLIC COMMUNICATION FOR RECONSTRUCTION OF SR25/US27/OKEECHOBEE ROAD Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total CEI DIH $20,000 $20,000 $20,000 $20,000 $20,000 $100,000 DS $200,000 $300,000 $300,000 $300,000 $300,000 $1,400,000 Total For Project 446124.4 $220,000 $320,000 $320,000 $320,000 $320,000 $1,500,000

October. 10 2019 Page 135 of 151 HIGHWAY SYSTEM: 13 NON-SYSTEM SPECIFIC

446297.1 SAFE RTS. TO SCHOOL - NORTH MIAMI SENIOR HIGH SCHOOL PM: NUNEZ, XIOMARA Work Mix: Pedestrian Safety Improvement Extra Description: FY20 SAFE ROUTES TO SCHOOL TPO PRIORITY #8 SCHOOL: NORTH MIAMI SENIOR HIGHSCHOOL **SEE WP45** SCOPE: ADDING CROSSWALKS, ENHANCING EXISTING CROSSWALKS, FILLING SIDEWALK GAPS, ADDING PEDESTRIAN SIGNAGE, ADDING ZONE SIGNAGE, UPGRADING Cont. Class: Local Agcy Pgm (Lap) ADA RAMPS. B/C:743.84/SHSP:

Phase Fund Code FY 2025 5 Year Total P.E. SU $106,778 $106,778 Total For Project 446297.1 $106,778 $106,778

446299.1 SAFE RTS. TO SCHOOL - RUBEN DARIO MIDDLE SCHO OL PM: NUNEZ, XIOMARA

Work Mix: Pedestrian Safety Improvement Extra Description: FY20 SAFE ROUTES TO SCHOOL TPO PRIORITY #8 SCHOOL: RUBEN DARIO MIDDLE SCHOOL SCOPE: ADDING CROSSWALKS, ENHANCING EXISTING CROSSWALKS, FILLING SIDEWALK GAPS, ADDING PEDESTRIAN SIGNAGE, ADDING SCHOOL ZONE SINAGE, UPGRADING ADA RAMPS Cont. Class: Local Agcy Pgm (Lap) B/C:436.48 /SHSP:__

Phase Fund Code FY 2025 5 Year Total P.E. SU $60,411 $60,411 Total For Project 446299.1 $60,411 $60,411

446302.1 SAFE RTS. TO SCHOOL - MIAMI JACKSON SENIOR HI GHSCHOOL PM: NUNEZ, XIOMARA Work Mix: Pedestrian Safety Improvement Extra Description: FY20 SAFE ROUTES TO SCHOOL TPO PRIORITY #8 SCHOOL: MIAMI JACKSON SENIOR HIGHSCHOOL SCOPE: INSTALL STANDARD CROSSWALK (EAST SIDEWALK) INSTALL 15 MPH SCHOOL ZONE FLASHING BEACON ASSEMBLIES (NORTH BOUND) - INSTALL END SCHOOL SPEED Cont. Class: Local Agcy Pgm (Lap) LIMIT SIGN S5-3 9 SOUTHBOUND) ADDING CROSSWALKS ENHANCING EXISTING CROSSWALKS, FILLING

Phase Fund Code FY 2025 5 Year Total P.E. SU $156,882 $156,882 Total For Project 446302.1 $156,882 $156,882

446744.1 RICKENBACKER TO VIZC AYA METRORAIL STATION/UND ERLINE TRAIL CONNECTOR PM: FREEMAN, RAYMOND

Work Mix: Bike Path/Trail Extra Description: 2019 TPO PRIORITY #5 Cont. Class: Local Agcy Pgm (Lap)

Phase Fund Code FY 2021 FY 2024 5 Year Total P.E. CM $200,000 $200,000 JPA/LAP Construction SU $500,000 $500,000 Total For Project 446744.1 $200,000 $500,000 $700,000

October. 10 2019 Page 136 of 151 HIGHWAY SYSTEM: 13 NON-SYSTEM SPECIFIC

446745.1 DTPW - COMPLETE STRE ETS PUSHBUTTON PM: TBD Work Mix: Miscellaneous Construction Extra Description: 2019 TPO PRIORITY #5 Cont. Class: Local Agcy Pgm (Lap)

Phase Fund Code FY 2022 FY 2023 5 Year Total JPA/LAP Construction SU $1,200,000 $700,000 $1,900,000 Total For Project 446745.1 $1,200,000 $700,000 $1,900,000

446747.1 MIAMI SPRINGS - OKEE CHOBEE STATION SMART TRAI L CONNECTOR PM: NUNEZ, XIOMARA Work Mix: Bike Path/Trail Extra Description: 2019 TPO PRIORITY #5 Cont. Class: Local Agcy Pgm (Lap)

Phase Fund Code FY 2021 FY 2023 5 Year Total P.E. CM $300,000 $300,000 JPA/LAP Construction CM $600,000 $600,000 SU $1,400,000 $1,400,000 Total For Project 446747.1 $300,000 $2,000,000 $2,300,000

446748.1 BIKE BOULEVARD DEMO PROJECT - MODEL CITY/BROW NSVILLE PM: NUNEZ, XIOMARA

Work Mix: Bike Path/Trail Extra Description: 2019 TPO PRIORITY #5 Cont. Class: Local Agcy Pgm (Lap)

Phase Fund Code FY 2022 FY 2024 5 Year Total P.E. SU $300,000 $300,000 JPA/LAP Construction CM $300,000 $300,000 SU $500,000 $500,000 Total For Project 446748.1 $300,000 $800,000 $1,100,000

446824.1 UNIVERSITY OF MIAMI - BIKE SAFE MIDDLE SCHOOL CLUBS PM: YEE FONG, SHEREEN

Work Mix: Public Information/Education Extra Description: SCHOOL: UNIVERSITY OF MIAMI FY25 TPO RANK #9 IMPLEMENT THE BIKESAFE HIGH SCHOOL CLUB IN MIAMI-DADE COUNTY WITH MECHANICAL WORKSHOPS, TECHNICAL ASSISTANCES PARK TRAIL RIDES, AND COMMUNITY INVOLVEMENT. Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2021 5 Year Total Planning TALU $538,080 $538,080 Total For Project 446824.1 $538,080 $538,080

FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total HIGHWAY SYSTEM: 13 Total $12,809,348 $9,199,375 $13,997,584 $28,931,671 $12,685,395 $77,623,373

October. 10 2019 Page 137 of 151 HIGHWAY SYSTEM: 15 MULTIMODAL FACILITY

251684.6 GOLDEN GLADES MULTI- MODAL TERMINAL PM: QUINTELA, RAUL

Work Mix: Intermodal Hub Capacity Extra Description: SPLIT OUT FROM SEGMENT 1 CONTRACT E-6L38 FHWA IDENTIFIED AS OVERSIGHT (PODI) SEG.1 & 6 SEE WP45. MPO PRIORITY LISTING# 10 DESIGN/BUILD APPROVAL REC'D FROM C.DRUMMOND 1/22/17 EMAIL PHASE 32-03 THRU 32-07 = STIPEND AGREEMENTS PHASE 32-08 Cont. Class: Design Build = SURVEY C9J68, 32-09 = CCEI FOR MIKHAIL

Phase Fund Code FY 2021 5 Year Total CEI SU $629,968 $629,968 Total For Project 251684.6 $629,968 $629,968

251684.7 GOLDEN GLADES MULTIM ODAL TRANSIT FACILITY ITS COMPONENTS PM: CARTAYA, NILIA Work Mix: Preliminary Engineering Extra Description: 2018 TPO PRIORITY #12 Cont. Class: Design Build

Phase Fund Code FY 2024 5 Year Total P.E. SU $2,025,000 $2,025,000 Total For Project 251684.7 $2,025,000 $2,025,000

406800.2 MIAMI INTERMODAL CTR (MIC) MIC CENTRAL STATIO N PM: ALVAREZ, TERESA

Work Mix: Intermodal Hub Capacity Extra Description: ROW=SEGMENT 1; PH.58 INCLUDES VESTIBULE ($2.776M DDR) 5202/8=CAR CLEANUP W/SHAW ENVIRO;01=WEST CONCOURSE W/TURNER 5203=EAST CONCOURSE;5207=PUMP STN CNT# T-6248 5204=WATER MAIN,SEWER CAPACITY,UNDERGROUND PUMP VAULTS *SPECIAL Cont. Class: Extern Mngd(Not Lap) NOTE: TIFI PH 52, F 08/09=STTF LOAN (SEE 4083232)* PH58=MDT AGRMT/CNT#AP762 PH57=CNT#APZ31 FHWA OVRSIGH(GMP#6C)

Phase Fund Code FY 2021 5 Year Total CEI DIH $120,000 $120,000 Total For Project 406800.2 $120,000 $120,000

408323.2 MIAMI INTERMODAL CTR (MIC) FDOT/DISTRICT 6 LO AN REPAYMENT PM: CARTAYA, NILIA Work Mix: Funding Action Extra Description: STTF LOAN REPAYMENT **CENT.OFC MUST APPROVE FUND CHANGES** LF = CUSTOMER FACILITY CHARGES & MISCELLANEOUS RENTAL FEES ANNUAL SERVICING FEE PAID FROM; SEE ITEM COMMENTS FOR SEQ.99 SEQ.01 LF/DDR=$19.5 (LF)JOINT DEVELOPMENT, $6.75M (DDR) SEQ.02 Cont. Class: Misc - No Letting LFNE/DDR PROGRAMMED=$95M RCF LAND REPAYMENTS SEQ.03 DDR PROGRAMMED=$136,519,251 SCETS LOAN REPAYMENT

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total Admin DDR $1,750,000 $1,750,000 $2,000,000 $2,000,000 $2,000,000 $9,500,000 Total For Project 408323.2 $1,750,000 $1,750,000 $2,000,000 $2,000,000 $2,000,000 $9,500,000

October. 10 2019 Page 138 of 151 HIGHWAY SYSTEM: 15 MULTIMODAL FACILITY

408324.1 MIAMI INTERMODAL CTR (MIC) RENTAL CAR FACILIT Y (RCF) TIFIA LOAN REPAYM PM: CARTAYA, NILIAA Work Mix: Funding Action Extra Description: TIFIA REPAYMENT SET UP FOR 30 YEARS - BEGINNING IN FY 12/13 MIC PROJECT LFNE = CUSTOMER FACILITY CHARGES; AMOUNT COULD FLUCTUATE DEPENDING UPON RENTAL CAR FACILITY TRANSACTIONS. *PAYMENTS TO BE MADE FROM WELLS FARGO ACCOUNT & NOT STTF* Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total Admin LFNE $19,942,044 $19,420,455 $21,386,232 $20,764,208 $20,339,600 $101,852,539 Total For Project 408324.1 $19,942,044 $19,420,455 $21,386,232 $20,764,208 $20,339,600 $101,852,539

435381.1 MDT - PALMETTO INTER MODAL TERMINAL PM: FREEMAN, RAYMOND Work Mix: Intermodal Hub Capacity Extra Description: 2018 TPO PRIORITY #11 EXPANSION OF PALMETTO METRORAIL STATION ONTO ADJACENT PROPERTY TO ALLOW ADDITIONAL PARK AND RIDE, TRANSIT HUB FACILITIES PROJECT INCLUDES PLANNING, DESIGN & R/W Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2021 FY 2022 FY 2024 5 Year Total Capital Improvement/Operating DDR $41,034 $8,534,610 $8,575,644 DPTO $383,895 $383,895 LF $1,784,185 $255,586 $2,039,771 TRIP $1,111,501 $1,111,501 TRWR $631,650 $255,586 $887,236 Total For Project 435381.1 $3,568,370 $383,895 $9,045,782 $12,998,047

437947.1 FREIGHT VILLAGE ANAL YSIS STUDY COUNTYWIDE PM: CASTRO, CARLOS

Work Mix: Modal Systems Planning Extra Description: THIS STUDY IS TO FOCUS ON IDENTIFICATION OF THE MOST APPROPRIATE AND EFFICIENT LOCATION FOR ONE (OR A NETWORK OF) FREIGHT VILLAGES AND HOW THEIR ESTABLISHMENT WILL AFFECT THE REGIONAL AND STATEWIDE FREIGHT TRANSPORTATION SYSTEM. Cont. Class: Misc - No Letting

Phase Fund Code FY 2023 5 Year Total PDE DIH $20,000 $20,000 DS $450,000 $450,000 Total For Project 437947.1 $470,000 $470,000

437950.1 DISTRICT INTERMODAL LOGISTIC CENTER (ILC) DEV ELOPMENT PM: CASTRO, CARLOS

Work Mix: Modal Systems Planning Extra Description: ANALYSIS OF EXISTING, DEVELOPING, AND PLANNED INTERMODAL LOGISTICS CENTERS (ILC) AND OTHER EFFORTS NECESSARY FOR INCREASING THEIR DEVELOPMENT Cont. Class: Misc - No Letting

Phase Fund Code FY 2022 5 Year Total PDE DIH $20,000 $20,000 DS $300,000 $300,000 Total For Project 437950.1 $320,000 $320,000

October. 10 2019 Page 139 of 151 HIGHWAY SYSTEM: 15 MULTIMODAL FACILITY

439982.1 MIAMI INTERMODAL CEN TER - PROPERTY MANAGEMENT PM: DUBE/FREEMAN Work Mix: Intermodal Hub Capacity Extra Description: PROVIDE STATE FUNDS UNDER INTERMODAL PROGRAM TO MIAMI DADE DEPARTMENT OF TRANSPORTATION & PUBLIC WORKS FOR THE MAINTENANCE COSTS OF THE MIAMI INTERMODAL CENTER SEQ 02 = PROFORMA REIMBURSEMENTS SEQ 03 = AMTRAK CAM COST Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total Capital Improvement/Operating DPTO $603,100 $345,508 $352,418 $78,920 $80,498 $1,460,444 Total For Project 439982.1 $603,100 $345,508 $352,418 $78,920 $80,498 $1,460,444

FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total HIGHWAY SYSTEM: 15 Total $26,613,482 $22,219,858 $24,208,650 $33,913,910 $22,420,098 $129,375,998 HIGHWAY SYSTEM: 16 OFF STATE HWY SYS/OFF FED SYS

251265.7 BISCAYNE TRAIL SEG D , SW 328 ST/SW 117 AVE TO HOMESTEAD BAYFRONT PARK PM: NUNEZ, XIOMARA Work Mix: Bike Path/Trail Extra Description: MUNICIPALITY: MIAMI DADE PARKS AND RECREATION DESIGN BEING DONE UNDER 251265-4 Cont. Class: Local Agcy Pgm (Lap)

Phase Fund Code FY 2021 5 Year Total JPA/LAP Construction TALU $1,845,000 $1,845,000 CEI ACSA $5,000 $5,000 JPA/LAP CEI LF $120,000 $120,000 Total For Project 251265.7 $1,970,000 $1,970,000

435505.1 CITY OF MIAMI GARDEN S NW 199 ST/BETTY FERGUSO N RECREATION COMPLEX PM: NUNEZ, XIOMARA Work Mix: Bike Path/Trail Extra Description: MUNICIPALITY: CITY OF MIAMI GARDENS FOR A BICYCLE/PEDESTRIAN SAFETY ENHANCEMENT PROJECT Cont. Class: Local Agcy Pgm (Lap)

Phase Fund Code FY 2024 5 Year Total JPA/LAP Construction LF $108,448 $108,448 TALT $623,822 $623,822 TALU $376,178 $376,178 CEI SA $5,000 $5,000 JPA/LAP CEI LF $110,844 $110,844 Total For Project 435505.1 $1,224,292 $1,224,292

October. 10 2019 Page 140 of 151 HIGHWAY SYSTEM: 16 OFF STATE HWY SYS/OFF FED SYS

439894.1 SAFE RTS.TO SCHOOL C ARRIE MEEK/WESTVW,FLAGAMI , H.O. SIBLEY & SHADOWLWN PM: NUNEZ, XIOMARA

Work Mix: Sidewalk Extra Description: SAFE ROUTES TO SCHOOL - P. MEEK/WESTVIEW K-8, FLAGAMI ELEMENTARY, HUBERT O. SIBLEY K-8 CENTER AND SHADOW- LAWN ELEMENTARY LOCATED IN CITY OF MIAMI MUNICIPALITY - MIAMI DADE COUNTY DEPT. OF TRANSPORTATION AND PUBLIC WORKS MPO PRIORITY Cont. Class: Local Agcy Pgm (Lap) ID# 11/FY 21 MPO PRIORITY PROJECTS LISTING

Phase Fund Code FY 2021 5 Year Total JPA/LAP Construction LF $89,465 $89,465 SR2T $490,282 $490,282 CEI SR2T $10,000 $10,000 JPA/LAP CEI SR2T $96,845 $96,845 Total For Project 439894.1 $686,592 $686,592

439895.1 SAFE RTS.TO SCHOOL B UNCHE PK ELM, MIA GDN ELM , MYRTLE GRV K8 & TWIN LK PM: NUNEZ, XIOMARA

Work Mix: Sidewalk Extra Description: SAFE ROUTES TO SCHOOL - BUNCHE PARK ELEMENTARY, MIAMI GARDENS ELEMENTARY, MYRTLE GROVE K-8 CENTER LOCATED IN MIAMI GARDENS AND NORTH TWIN LAKES WHICH IS LOCATED IN THE CITY OF HIALEAH. MUNICIPALITY: DTPW MPO PRIORITY ID# 11/FY 22 MPO PRIORITY Cont. Class: Local Agcy Pgm (Lap) PROJECTS LISTING

Phase Fund Code FY 2021 5 Year Total JPA/LAP Construction LF $41,040 $41,040 SR2T $246,239 $246,239 CEI SR2T $10,000 $10,000 JPA/LAP CEI SR2T $43,092 $43,092 Total For Project 439895.1 $340,371 $340,371

439896.1 SAFE RTS.TO SCHOOL F LORIDA CITY ELEMENTARY AN D ROBERT R. MOTON ELEM. PM: NUNEZ, XIOMARA Work Mix: Sidewalk Extra Description: SAFE ROUTES TO SCHOOL - FLORIDA CITY ELEMENTARY AND ROBERT R. MOTON ELEMENTARY LOCATED IN FLORIDA CITY AND PERRINE MUNICIPALITY - MIAMI DADE COUNTY DEPT. OF TRANSPORTATION AND PUBLIC WORKS MPO PRIORITY ID# 11/FY 22 MPO PRIORITY PROJECTS Cont. Class: Local Agcy Pgm (Lap) LISTING

Phase Fund Code FY 2021 5 Year Total JPA/LAP Construction LF $48,256 $48,256 SR2T $289,532 $289,532 CEI SR2T $10,000 $10,000 JPA/LAP CEI SR2T $50,669 $50,669 Total For Project 439896.1 $398,457 $398,457

October. 10 2019 Page 141 of 151 HIGHWAY SYSTEM: 16 OFF STATE HWY SYS/OFF FED SYS

439897.1 SAFE RTS. TO SCHOOL NORMAN S. EDELCUP K8 CENT ER PM: NUNEZ, XIOMARA Work Mix: Sidewalk Extra Description: SAFE ROUTES TO SCHOOL - NORMAN S. EDELCUP K8 CENTER LOCATED IN SUNNY ISLES BEACH MUNICIPALITY - DTPW MPO PRIORITY ID# 11/FY 22 MPO PRIORITY PROJECTS LISTING NOTE: THE ROADWAY PORTION OF THIS SRTS IS THE ONLY PORTION THAT IS BEING FUNDED THROUGH THIS Cont. Class: Local Agcy Pgm (Lap) PRGM.

Phase Fund Code FY 2022 FY 2024 5 Year Total P.E. SR2T $34,475 $34,475 JPA/LAP Construction LF $7,770 $7,770 SR2T $155,393 $155,393 CEI SR2T $10,000 $10,000 JPA/LAP CEI SR2T $24,475 $24,475 Total For Project 439897.1 $34,475 $197,638 $232,113

440837.1 CITY OF MIAMI - MIAM I RIVER GREENWAY CURTIS P ARK EAST PM: NUNEZ, XIOMARA

Work Mix: Sidewalk Extra Description: MUNICIPALITY - CITY OF MIAMI 440837-2 = SUNTRAIL Cont. Class: Local Agcy Pgm (Lap)

Phase Fund Code FY 2023 5 Year Total JPA/LAP Construction LF $1,200,000 $1,200,000 TALT $1,000,000 $1,000,000 CEI SA $5,000 $5,000 JPA/LAP CEI LF $110,797 $110,797 Total For Project 440837.1 $2,315,797 $2,315,797

440841.1 CITY OF MIAMI BEACH - NORTHSHORE OPEN SPACE B EACHWALK PM: NUNEZ, XIOMARA Work Mix: Bike Path/Trail Extra Description: MUNICIPALITY: CITY OF MIAMI BEACH Cont. Class: Local Agcy Pgm (Lap)

Phase Fund Code FY 2022 5 Year Total JPA/LAP Construction LF $1,930,000 $1,930,000 TALT $1,000,000 $1,000,000 CEI SA $5,000 $5,000 JPA/LAP CEI LF $125,000 $125,000 Total For Project 440841.1 $3,060,000 $3,060,000

October. 10 2019 Page 142 of 151 HIGHWAY SYSTEM: 16 OFF STATE HWY SYS/OFF FED SYS

440842.1 MDPROS - BLACK CREEK TRAIL SEGMENT B PHASE II PM: NUNEZ, XIOMARA Work Mix: Bike Path/Trail Extra Description: MUNICIPALITY: MIAMI DADE COUNTY PARKS RECREATION AND OPEN SPACES DEPARTMENT DESIGN BEING COMPLETED UNDER 438667-1 Cont. Class: Local Agcy Pgm (Lap)

Phase Fund Code FY 2022 5 Year Total JPA/LAP Construction LF $131,102 $131,102 TALU $1,000,000 $1,000,000 CEI SA $5,000 $5,000 JPA/LAP CEI LF $130,880 $130,880 Total For Project 440842.1 $1,266,982 $1,266,982

440843.1 CITY OF MIAMI SHORES - MULTIMODAL MOBILITY IM PROVEMENTS PM: NUNEZ, XIOMARA

Work Mix: Bike Path/Trail Extra Description: MUNICIPALITY - CITY OF MIAMI SHORES Cont. Class: Local Agcy Pgm (Lap)

Phase Fund Code FY 2023 5 Year Total JPA/LAP Construction LF $70,182 $70,182 TALU $631,513 $631,513 CEI TALU $5,000 $5,000 JPA/LAP CEI TALU $73,916 $73,916 Total For Project 440843.1 $780,611 $780,611

440845.1 VILLAGE OF VIRGINIA GARDENS - COMMUNITY BICYC LE AND PEDESTRIAN IMPROV. PM: NUNEZ, XIOMARA

Work Mix: Bike Path/Trail Extra Description: MUNICIPALITY: VILLAGE OF VIRGINIA GARDENS Cont. Class: Local Agcy Pgm (Lap)

Phase Fund Code FY 2022 5 Year Total JPA/LAP Construction LF $207,113 $207,113 TALT $577,024 $577,024 TALU $422,976 $422,976 CEI SA $5,000 $5,000 JPA/LAP CEI LF $150,886 $150,886 Total For Project 440845.1 $1,362,999 $1,362,999

October. 10 2019 Page 143 of 151 HIGHWAY SYSTEM: 16 OFF STATE HWY SYS/OFF FED SYS

440846.1 NORTH BAY VILLAGE - BAYWALK PLAZA AREA PHASE I PM: NUNEZ, XIOMARA Work Mix: Bike Lane/Sidewalk Extra Description: MUNICIPALITY: NORTH BAY VILLAGE Cont. Class: Local Agcy Pgm (Lap)

Phase Fund Code FY 2023 5 Year Total JPA/LAP Construction LF $1,097,822 $1,097,822 TALT $966,938 $966,938 CEI SA $5,000 $5,000 JPA/LAP CEI TALT $33,062 $33,062 Total For Project 440846.1 $2,102,822 $2,102,822

440849.1 TOWN OF MIAMI LAKES - GREEN 2.0 PM: NUNEZ, XIOMARA

Work Mix: Bike Path/Trail Extra Description: MUNICIPALITY: TOWN OF MIAMI LAKES Cont. Class: Local Agcy Pgm (Lap)

Phase Fund Code FY 2023 5 Year Total JPA/LAP Construction LF $44,826 $44,826 TALU $541,494 $541,494 CEI SA $5,000 $5,000 JPA/LAP CEI LF $98,880 $98,880 Total For Project 440849.1 $690,200 $690,200

441234.1 SAFE RTS.SCHOOL;RAIN BW PK,GLDN GLDS,LK STVNS ELE,NO.CO.K-8,BENFRNK K-8 PM: NUNEZ, XIOMARA

Work Mix: Pedestrian Safety Improvement Extra Description: SAFE ROUTES TO SCHOOL PROJECTS FOR THE FOLLOWING SCHOOLS RAINBOW PARK ELEMENTARY, GOLDEN GLADES ELEMENTARY, LAKE STEVENS ELEMENTARY, NORTH COUNTY K-8 & BENJAMIN FRANKLIN K-8 Cont. Class: Local Agcy Pgm (Lap)

Phase Fund Code FY 2022 5 Year Total JPA/LAP Construction SR2T $1,191,174 $1,191,174 CEI SR2T $10,000 $10,000 JPA/LAP CEI SR2T $178,676 $178,676 Total For Project 441234.1 $1,379,850 $1,379,850

October. 10 2019 Page 144 of 151 HIGHWAY SYSTEM: 16 OFF STATE HWY SYS/OFF FED SYS

441235.1 SAFE RTS.SCHOOL;NORW OOD,DANTE ,CHRLS H ADLEY,MAE WALTERS,REEVES PM: NUNEZ, XIOMARA Work Mix: Pedestrian Safety Improvement Extra Description: SAFE ROUTES TO SCHOOL PROJECTS FOR THE FOLLOWING SCHOOLS NORWOOD ELEMENTARY, DANTE FASCELL ELEMENTARY, CHARLES HADLEY ELEMENTARY, MAE M WALTERS ELEMENTARY & REEVES HENRY ELEMEN. Cont. Class: Local Agcy Pgm (Lap)

Phase Fund Code FY 2022 FY 2024 5 Year Total P.E. SR2T $215,081 $215,081 JPA/LAP Construction SR2T $932,206 $932,206 CEI SR2T $10,000 $10,000 JPA/LAP CEI SR2T $139,831 $139,831 Total For Project 441235.1 $215,081 $1,082,037 $1,297,118

441637.1 VILLAGE OF PALMETTO BAY - SW 82 AVENUE COMMUT ER ACCESS PM: NUNEZ, XIOMARA

Work Mix: Bike Lane/Sidewalk Extra Description: MUNICIPALITY: VILLAGE OF PALMETTO BAY ADDING BICYCLE LANES TO INCLUDE CURBING, SIDEWALK UPGRADES, ADA COMPLIANCE, STRIPING/PAVEMENT MARKINGS, AND DRAINAGE INFRASTRUCTURE. FY17 TPO RANK #13/FDOT RANK #14 Cont. Class: Local Agcy Pgm (Lap)

Phase Fund Code FY 2021 FY 2024 5 Year Total P.E. LF $303,106 $303,106 JPA/LAP Construction LF $1,316,146 $1,316,146 SA $56,464 $56,464 TALT $550,227 $550,227 TALU $393,309 $393,309 CEI SA $5,000 $5,000 JPA/LAP CEI LF $241,685 $241,685 Total For Project 441637.1 $303,106 $2,562,831 $2,865,937

October. 10 2019 Page 145 of 151 HIGHWAY SYSTEM: 16 OFF STATE HWY SYS/OFF FED SYS

441638.1 MIAMI SHORES - MULTI MODAL MOBILITY IMPROVEMEN TS PM: NUNEZ, XIOMARA

Work Mix: Signing/Pavement Markings Extra Description: MUNICIPALITY: MIAMI SHORES PROVIDE ENHANCED SAFETY AND MOBILITY FOR PEDESTRIANS AND BICYCLISTS BY IMPLEMENTING NEIGHBORHOOD GREENWAYS, SHARED LANE MARKINGS, HIGH-EMPHASIS TEXTURED INTERSECTIONS, AND BICYCLE AND PEDESTRAIN CROSSING Cont. Class: Local Agcy Pgm (Lap) IMPROVEMENTS FY17 TPO RANK #12 /FDOT RANK #6

Phase Fund Code FY 2021 FY 2024 5 Year Total P.E. LF $79,405 $79,405 JPA/LAP Construction LF $44,603 $44,603 TALU $418,363 $418,363 CEI SA $5,000 $5,000 JPA/LAP CEI TALT $9,284 $9,284 TALU $41,186 $41,186 Total For Project 441638.1 $79,405 $518,436 $597,841

441641.1 ROBERTA HUNTER PARK - SOUTH DADE TRAIL CONNEC TION PM: NUNEZ, XIOMARA

Work Mix: Bike Path/Trail Extra Description: MUNICIPALITY: MIAMI DADE PARKS AND RECREATION OPEN SPACES SOUTH DADE TRAIL CONNECTION, WHICH INCLUDES A TRAIL CONNECTION, COLORED PAVEMENT, PAVEMENT MARKINGS, REGULATORY AND WAYFINDING SIGNAGE, A BIKE SIGNAL, CURBING AND DRAINAGE BIKE RACKS AND Cont. Class: Local Agcy Pgm (Lap) A BIKE REPAIR STATION AND TRASH RECEPTACLE FY17 TPO RANK #8 /D6 RANK #10

Phase Fund Code FY 2024 5 Year Total JPA/LAP Construction LF $139,354 $139,354 TALT $304,755 $304,755 CEI SA $5,000 $5,000 JPA/LAP CEI TALU $43,446 $43,446 Total For Project 441641.1 $492,555 $492,555

441642.1 CITY OF DORAL - BICY CLE/PEDESTRIAN BRIDGE OVE R DORAL BLVD PM: NUNEZ, XIOMARA

Work Mix: Pedestrian/Wildlife Overpass Extra Description: MUNICIPALITY - CITY OF DORAL TURNPIKE TRAIL BICYCLE/PEDSTRIAN BRIDGE OVER DORAL BLVD FY17 TPO RANK #6 /D6 RANK #8 Cont. Class: Local Agcy Pgm (Lap)

Phase Fund Code FY 2022 5 Year Total JPA/LAP Construction LF $1,433,360 $1,433,360 TALT $1,000,000 $1,000,000 CEI SA $5,000 $5,000 Total For Project 441642.1 $2,438,360 $2,438,360

October. 10 2019 Page 146 of 151 HIGHWAY SYSTEM: 16 OFF STATE HWY SYS/OFF FED SYS

441643.1 TOWN OF MIAMI LAKES - 59TH AVENUE TRANSPORTAT ION IMPROVEMENTS PROJECT PM: NUNEZ, XIOMARA Work Mix: Bike Lane/Sidewalk Extra Description: MUNICIPALITY: TOWN OF MIAMI LAKES 59TH AVENUE TRANSPORTATION IMPROVEMENTS PROJECT FY17 TPO RANK #5 /D6 RANK #3 Cont. Class: Local Agcy Pgm (Lap)

Phase Fund Code FY 2022 FY 2024 5 Year Total P.E. LF $173,000 $173,000 JPA/LAP Construction LF $372,000 $372,000 TALT $1,000,000 $1,000,000 CEI SA $5,000 $5,000 JPA/LAP CEI LF $65,000 $65,000 Total For Project 441643.1 $173,000 $1,442,000 $1,615,000

444295.1 SAFE RTS. SCHOOL - B OB EDUCATION CENTE R PM: NUNEZ, XIOMARA Work Mix: Pedestrian Safety Improvement Extra Description: SAFE ROUTES TO SCHOOL PROJECT FOR THE FOLLOWING SCHOOL: BOB GRAHAM EDUCATION CENTER FDOT RANK #1 Cont. Class: Local Agcy Pgm (Lap)

Phase Fund Code FY 2021 FY 2023 5 Year Total P.E. SR2T $61,267 $61,267 JPA/LAP Construction SR2T $160,762 $160,762 CEI SR2T $5,000 $5,000 JPA/LAP CEI SR2T $24,114 $24,114 Total For Project 444295.1 $61,267 $189,876 $251,143

444296.1 SAFE RTS. SCHOOL - O JUS ELEMENTARY PM: NUNEZ, XIOMARA

Work Mix: Pedestrian Safety Improvement Extra Description: SAFE ROUTES TO SCHOOL PROJECT FOR THE FOLLOWING SCHOOL: OJUS ELEMENTARY FDOT RANK# 2 Cont. Class: Local Agcy Pgm (Lap)

Phase Fund Code FY 2021 FY 2023 5 Year Total P.E. SA $102,740 $102,740 JPA/LAP Construction SR2T $362,005 $362,005 CEI SR2T $5,000 $5,000 JPA/LAP CEI SR2T $72,401 $72,401 Total For Project 444296.1 $102,740 $439,406 $542,146

October. 10 2019 Page 147 of 151 HIGHWAY SYSTEM: 16 OFF STATE HWY SYS/OFF FED SYS

445158.1 SAFE RTS. SCHOOL - S EMINOLE ELEMENTARY PM: NUNEZ, XIOMARA Work Mix: Pedestrian Safety Improvement Extra Description: 2018 TPO PRIORITY #6 SRTS PROJECT FOR THE FOLLOWING SCHOOL: SEMINOLE ELEMENTARY SCOPE: ADDING CROSSWALKS, ENHANCING EXISTING CROSSWALKS, ADDING PEDESTRIAN SIGNAGE, FILLING SIDEWALK GAPS, ADDING SCHOOL ZONE SINAGE, UPDRADING ADA PUSH Cont. Class: Local Agcy Pgm (Lap) BUTTONS. FDOT RANK# 3

Phase Fund Code FY 2022 FY 2024 5 Year Total P.E. SA $101,007 $101,007 JPA/LAP Construction LF $80,740 $80,740 SU $376,784 $376,784 CEI SU $9,500 $9,500 JPA/LAP CEI SU $91,504 $91,504 Total For Project 445158.1 $101,007 $558,528 $659,535

445160.1 SAFE RTS. SCHOOL - MANDARIN LAKES K-8 PM: NUNEZ, XIOMARA

Work Mix: Pedestrian Safety Improvement Extra Description: 2018 TPO PRIORITY #6 SRTS PROJECT FOR THE FOLLOWING SCHOOL: MANDARIN LAKES K-8 SCOPE: ADDING CROSSWALKS, ENHANCING EXISTING CROSSWALKS, ADDING PEDESTRIAN SIGNAGE, FILLING SIDEWALK GAPS, ADDING SCHOOL ZONE SINAGE, UPDRADING ADA PUSH BUTTONS. FDOT Cont. Class: Local Agcy Pgm (Lap) RANK# 4

Phase Fund Code FY 2022 FY 2024 5 Year Total P.E. SA $28,176 $28,176 JPA/LAP Construction SU $182,634 $182,634 CEI SU $6,000 $6,000 JPA/LAP CEI SU $22,177 $22,177 Total For Project 445160.1 $28,176 $210,811 $238,987

445161.1 SAFE RTS. SCHOOL - A IRBASE K-8 CENTER PM: NUNEZ, XIOMARA

Work Mix: Pedestrian Safety Improvement Extra Description: 2018 TPO PRIORITY #6 SRTS PROJECT FOR THE FOLLOWING SCHOOL: AIRBASE K-8 CENTER SCOPE: ADDING CROSSWALKS, ENHANCING EXISTING CROSSWALKS, ADDING PEDESTRIAN SIGNAGE, FILLING SIDEWALK GAPS, ADDING SCHOOL ZONE SINAGE, UPDRADING ADA PUSH BUTTONS. FDOT Cont. Class: Local Agcy Pgm (Lap) RANK# 6

Phase Fund Code FY 2022 FY 2024 5 Year Total P.E. SA $9,241 $9,241 JPA/LAP Construction SU $36,210 $36,210 CEI SU $2,000 $2,000 JPA/LAP CEI SU $7,242 $7,242 Total For Project 445161.1 $9,241 $45,452 $54,693

October. 10 2019 Page 148 of 151 HIGHWAY SYSTEM: 16 OFF STATE HWY SYS/OFF FED SYS

445162.1 SAFE RTS. SCHOOL - E VERGLADES K-8 PM: NUNEZ, XIOMARA Work Mix: Pedestrian Safety Improvement Extra Description: 2018 TPO PRIORITY #6 SRTS PROJECT FOR THE FOLLOWING SCHOOL: EVERGLADES K-8 SCOPE: ADDING CROSSWALKS, ENHANCING EXISTING CROSSWALKS, ADDING PEDESTRIAN SIGNAGE, FILLING SIDEWALK GAPS, ADDING SCHOOL ZONE SINAGE, UPDRADING ADA PUSH BUTTONS. FDOT Cont. Class: Local Agcy Pgm (Lap) RANK# 7

Phase Fund Code FY 2022 FY 2024 5 Year Total P.E. SA $55,405 $55,405 JPA/LAP Construction SU $247,028 $247,028 CEI SU $6,000 $6,000 JPA/LAP CEI SU $49,406 $49,406 Total For Project 445162.1 $55,405 $302,434 $357,839

445743.1 SAFE RTS. TO SCHOOL MIAMI CENTRAL HIGHSCHOOL PM: NUNEZ, XIOMARA Work Mix: Pedestrian Safety Improvement Extra Description: FY 19 SAFE ROUTES TO SCHOOL SHAREPOINT# D6-209 SCHOOLS: MIAMI CENTRAL SENIOR H.S. SCOPE INCLUDES PROVING PEDESTRIAN CROSSWALKS, PEDESTRIAN SIGNS, COVERING GAPS IN SIDEWALK, PEDESTRIAN CURB RAMPS AND DETECTABLE WARNING SURFACES. B/C: Cont. Class: Local Agcy Pgm (Lap) 912.46/SHSP: VULNERABLE ROD USERS

Phase Fund Code FY 2024 5 Year Total P.E. SR2T $139,009 $139,009 Total For Project 445743.1 $139,009 $139,009

445766.1 SAFE RTS. TO SCHOOL MIAMI NORTHWESTERN SENIOR HIGHSCHOOL PM: NUNEZ, XIOMARA

Work Mix: Pedestrian Safety Improvement Extra Description: FY19 SAFE ROUTES TO SCHOOL SCOPE INCLUDES PROVING PEDESTRAIN CROSSWALKS, PEDESTRIAN SIGNS, COVERING GAPS IN SIDEWALK, PEDESTRIAN CURB RAMPS & DETECTABLE WARNING SURFACES. B/C: 743.84/SHSP: VULNERABLE ROD USERS SHAREPOINT# D6-211 Cont. Class: Local Agcy Pgm (Lap)

Phase Fund Code FY 2024 5 Year Total P.E. SR2T $150,059 $150,059 Total For Project 445766.1 $150,059 $150,059

446777.1 RR CROSSING #628343V AT NW 62ND ST/EAST 17TH ST - (SFRTA) PM: QUERO, ANA Work Mix: Rail Safety Project Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 5 Year Total Construction RHP $383,291 $383,291 Total For Project 446777.1 $383,291 $383,291

October. 10 2019 Page 149 of 151 HIGHWAY SYSTEM: 16 OFF STATE HWY SYS/OFF FED SYS

446778.1 RR CROSSING #628378W AT NW RIVER DRIVE - (SFR TA) PM: QUERO, ANA Work Mix: Rail Safety Project Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 5 Year Total Construction RHP $403,542 $403,542 Total For Project 446778.1 $403,542 $403,542

446779.1 RR CROSSING #631077 AT SW 56 ST - (CSX) PM: QUERO, ANA Work Mix: Rail Safety Project Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 5 Year Total Construction RHP $375,807 $375,807 Total For Project 446779.1 $375,807 $375,807

446780.1 RR CROSSING #631078L AT SW 87 AVE - (CSX) PM: QUERO, ANA

Work Mix: Rail Safety Project Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 5 Year Total Construction RHP $386,152 $386,152 Total For Project 446780.1 $386,152 $386,152

446781.1 RR CROSSING #631079T AT SW 72ND ST - (CSX) PM: QUERO, ANA

Work Mix: Rail Safety Project Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 5 Year Total Construction RHP $82,826 $82,826 Total For Project 446781.1 $82,826 $82,826

FY 2021 FY 2022 FY 2023 FY 2024 5 Year Total HIGHWAY SYSTEM: 16 Total $5,573,556 $10,124,576 $6,518,712 $8,926,082 $31,142,926 Miami Dade Total $847,539,786 $781,717,324 $555,392,488 $1,240,283,561 $743,561,841 $4,168,495,000

October. 10 2019 Page 150 of 151 Total Total 5 Year Program: $286,817,066

Glossary of Terms and Accronyms

Box Funds for supplementals, overruns, litigation, AC conversions Capital Improvement / Capital Improvements and/or Operating Costs Operating CEI Construction Engineering Inspection Design Build Includes all phases, let as one contract for PE, Construction. Let in the District District Contract Contracts let in the District Extern Mngd (Not LAP) Joint Particiapation Agreement - Interagency method to exchange funds FM # Financial Management Number, aka Financial Project ID Force Account Force account / external JPA Joint Particiapation Agreement - Interagency method to exchange funds Local Agcy Pgm (LAP) Local Agency Program - Interagency method to exchange funds PD&E Project Development and Environmental (studies) PE Preliminary Engineering PTO Public Transportation R/W Right of Way ROW Right of Way ROW Adv. Acq. Advanced Acquisition of Right of Way only. SA Supplemental Agreement To Be Let Contract let in Tallahassee

October. 10 2019 Page 51 of 51 This page intentionally left blank.

October. 10 2019 Page 151 of 152 Citizen's Report

District Six Tentative Work Program Fiscal Year 2021 - 2025

Districtwide

Prepared by FDOT - District 6 - 10/10/2019 Data County: Districtwide ( 99 )

HIGHWAY SYSTEM: 01 INTRASTATE INTERSTATE

433534.1 ITS OPERATIONS HARDW ARE/SOFTWARE AND REPLACEM ENT EQUIPMENT PM: MOTTA, ALEJANDRO Work Mix: Traffic Management Centers Extra Description: SPLIT OUT FROM 417740-3-93-01 FY 14 ONWARD WITH STATE FUNDS TO ENABLE CLOSE OF FED FUNDED PREDECESSOR PROJECT ON FAP # ITS6- 015. Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total Capital Improvement/Operating DITS $125,000 $125,000 $125,000 $125,000 $125,000 $625,000 Total For Project 433534.1 $125,000 $125,000 $125,000 $125,000 $125,000 $625,000

FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total HIGHWAY SYSTEM: 01 Total $125,000 $125,000 $125,000 $125,000 $125,000 $625,000 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

248594.1 DISTRICTWIDE ROW MAP PREPARATION PM: ALBURY, CRISTINA Work Mix: Preliminary Engineering Extra Description: ESTABLISH RIGHT-OF-WAY ON EXISTING ROADWAYS Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total P.E. DIH $170,000 $170,000 $170,000 $170,000 $170,000 $850,000 Total For Project 248594.1 $170,000 $170,000 $170,000 $170,000 $170,000 $850,000

249726.6 DISTRICTWIDE MISC ST UDIES & RCI DATA COLLECTI ON CONSULTANT PM: LU, JINYAN

Work Mix: Transportation Statistics Extra Description: BDID GROUP CODE ADDED 5-10-16 (LEIGH/APPROVED CARLA PERRY) Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 5 Year Total P.E. DS $320,000 $320,000 Total For Project 249726.6 $320,000 $320,000

249726.7 DISTRICTWIDE TRAFFIC OPERATIONS STUDIES CONSU LTANT PM: MAAROUF, KHALIL

Work Mix: Transportation Statistics Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2022 5 Year Total P.E. DS $100,000 $100,000 Total For Project 249726.7 $100,000 $100,000

October. 10 2019 Page 2 of 51 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

249726.8 DISTRICTWIDE MISC. S TUDIES & RCI DATA COLLECT ION PM: LU, JINYAN

Work Mix: Traffic Engineering Study Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total P.E. DS $400,000 $400,000 $350,000 $350,000 $1,500,000 Total For Project 249726.8 $400,000 $400,000 $350,000 $350,000 $1,500,000

249726.9 DISTRICTWIDE TRAFFIC OPERATIONS STUDIES CONSU LTANT PM: MAAROUF, KHALIL_

Work Mix: Traffic Engineering Study Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2024 FY 2025 5 Year Total P.E. DS $75,000 $300,000 $375,000 Total For Project 249726.9 $75,000 $300,000 $375,000

249796.8 DISTRICTWIDE TRAFFIC OPERATIONS SAFETY STUDIE S CONSULTANTS PM: LEON, MISLEIDYS Work Mix: Safety Project Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 5 Year Total P.E. DS $275,000 $275,000 $275,000 $825,000 Total For Project 249796.8 $275,000 $275,000 $275,000 $825,000

249796.9 DISTRICTWIDE TRAFFIC OPERATIONS STUDIES CONS ULTANT PM: LLERENA, XAVIEL Work Mix: Safety Project Extra Description: THE WORD 'SAFETY' WAS REMOVED FROM DESCR PER ARNIE 111215 NOTE: BDI CONTRACT PER LEIGH,APPR. BY ANGELA MATIYOW 1-11-18 Cont. Class: Misc - No Letting

Phase Fund Code FY 2022 5 Year Total P.E. DS $100,000 $100,000 Total For Project 249796.9 $100,000 $100,000

October. 10 2019 Page 3 of 51 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

250084.4 TRANSPORTATION SYSTE MS MGMT AND OPS. CONULTAN T CONTINUING CONTRACT PM: DIAZ, YAMILET Work Mix: Corridor/Subarea Planning Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total P.E. DS $500,000 $1,000,000 $1,000,000 $1,000,000 $1,000,000 $4,500,000 Total For Project 250084.4 $500,000 $1,000,000 $1,000,000 $1,000,000 $1,000,000 $4,500,000

250093.4 DISTRICTWIDE TRAFFIC OPERATIONS STUDIES CONSU LTANT PM: PIERRE-LOUIS, RONALD Work Mix: Corridor/Subarea Planning Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2022 5 Year Total P.E. DS $100,000 $100,000 Total For Project 250093.4 $100,000 $100,000

250093.5 DISTRICTWIDE TRAFFIC OPERATIONS STUDIES CONSU LTANT PM: MAAROUF, KHALIL

Work Mix: Corridor/Subarea Planning Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2024 FY 2025 5 Year Total P.E. DS $75,000 $300,000 $375,000 Total For Project 250093.5 $75,000 $300,000 $375,000

250115.7 ITS TECHNICAL CONSUL TANT SERVICES PM: BRAVO, SERGIO

Work Mix: Traffic Ops Improvement Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total P.E. DS $300,000 $300,000 $300,000 $300,000 $1,200,000 Total For Project 250115.7 $300,000 $300,000 $300,000 $300,000 $1,200,000

October. 10 2019 Page 4 of 51 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

250604.1 DISTRICTWIDE VALUE E NGINEERING CONSULTANT PM: MASON, CALVIN Work Mix: Preliminary Engineering Extra Description: FUNDS SPLIT OUT FROM 6119900 1636=MOSELAND ALTOBELLI ASSOC., INC.=02 1657=VENTRY ENGINEERING=03 1693=STATEWIDE MASTER (FOUR CONSULTANTS) =04 SEQ. 07 = CONTRACT C9040/HDR Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total P.E. DDR $56,308 $87,867 $144,175 DIH $50,000 $50,000 $50,000 $50,000 $50,000 $250,000 DS $150,000 $93,692 $62,133 $150,000 $150,000 $605,825 Total For Project 250604.1 $200,000 $200,000 $200,000 $200,000 $200,000 $1,000,000

250608.2 DISTRICTWIDE AERIAL PHOTOGRAPHY PM: MARRERO, VICTOR

Work Mix: Preliminary Engineering Extra Description: NEW CONTRACT TO BEGIN IN FY 15/16 PER GAMING MEETING ON 7-15-13 PHASE 32-01 = CONTRACT C9149/AERIAL (FEB. 2015 TO FEB. 2020) PHASE 32-02 = NEW CONTRACT Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total P.E. DS $250,000 $300,000 $600,000 $600,000 $300,000 $2,050,000 Total For Project 250608.2 $250,000 $300,000 $600,000 $600,000 $300,000 $2,050,000

250610.4 DISTRICTWIDE LANDSCA PE DESIGN CONSULTANT & JP A PM: SCHOT, KEVIN

Work Mix: Landscaping Extra Description: FUNDS TO BE USED FOR VARIOUS LANDSCAPING PROJECTS. PH58-01 = RAAM: DOT R/W AESTHETIC MAINTENANCE MIAMI DADE PH58-02 = RAAM FDOT LANDSCAPE REPLACEMENT W/CO Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2021 FY 2022 5 Year Total JPA/LAP Construction DS $500,000 $500,000 $1,000,000 CEI DIH $5,000 $5,000 Total For Project 250610.4 $505,000 $500,000 $1,005,000

250621.1 D/W PROPERTY MGT. BY DIST. R/W ADMIN. PM: CASALS, ALEX

Work Mix: Right Of Way Activities Extra Description: DISPOSAL OF SURPLUS PROPERTY, APPRL REVIEW, SALE OR LEASING, LEGAL CLAIM, EXPERT WITNESS FUNDS SEQ. 3 = JOINT PUBLIC/PRIVATE DEV. CONTRACT. PH 43 WAS USED TO PAY UNSUCCESSFUL BIDDERS' APPRAISAL FEES PH 4B - LENGTH OF CONTRACT: 200 DAYS CNT DMS73 EXEC Cont. Class: Misc - No Letting 091808 4302=PBSJ

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total RW Support DIH $550,000 $500,000 $500,000 $500,000 $500,000 $2,550,000 DS $100,000 $100,000 $100,000 $100,000 $100,000 $500,000 Total For Project 250621.1 $650,000 $600,000 $600,000 $600,000 $600,000 $3,050,000

October. 10 2019 Page 5 of 51 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

250622.4 D/W PD&E CONSULTANT SUPPORT PM: BENITEZ, HONG Work Mix: Pd&E/Emo Study Extra Description: PH22-02/CONSULT: GANNETT CONTRACT# C9783 Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total PDE DIH $50,000 $50,000 $50,000 $50,000 $200,000 DS $100,000 $350,000 $350,000 $350,000 $350,000 $1,500,000 Total For Project 250622.4 $150,000 $400,000 $400,000 $400,000 $350,000 $1,700,000

250622.5 D/W PD&E CONSULTANT SUPPORT PM: BENITEZ, HONG

Work Mix: Pd&E/Emo Study Extra Description: PH 22-01/CONSULT: STANTEC CONTRACT# C9764 Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total PDE DIH $50,000 $50,000 $50,000 $50,000 $50,000 $250,000 DS $100,000 $350,000 $350,000 $350,000 $350,000 $1,500,000 Total For Project 250622.5 $150,000 $400,000 $400,000 $400,000 $400,000 $1,750,000

250626.1 DISTRICTWIDE TRAFFIC OPERATIONS PM: MEITIN, OMAR

Work Mix: Traffic Ops Improvement Extra Description: GENERAL WORK Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 5 Year Total P.E. DIH $950,000 $950,000 $1,000,000 $1,000,000 $3,900,000 Total For Project 250626.1 $950,000 $950,000 $1,000,000 $1,000,000 $3,900,000

250629.5 D/W TRAFFIC OPS PUSH BUTTON DESIGN CONSULTANT PM: SIERRA, RAMON

Work Mix: Traffic Ops Improvement Extra Description: PH32-01 = CNT#C9V87/CONSULT: TRACE Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 5 Year Total P.E. DS $340,000 $340,000 Total For Project 250629.5 $340,000 $340,000

October. 10 2019 Page 6 of 51 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

250629.6 DISTRICTWIDE TRAFFIC OPS PUSHBUTTON DESIGN CO NSULTANT PM: SIERRA, RAMON Work Mix: Traffic Ops Improvement Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total P.E. DIH $18,000 $18,000 $18,000 $18,000 $72,000 DS $300,000 $300,000 $300,000 $300,000 $300,000 $1,500,000 Total For Project 250629.6 $318,000 $318,000 $318,000 $318,000 $300,000 $1,572,000

250629.8 DISTRICTWIDE TRAFFIC OPS PUSH-BUTTON DESIGN C ONSULTANT PM: LU, JINYAN

Work Mix: Traffic Ops Improvement Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total P.E. DS $300,000 $300,000 $300,000 $300,000 $300,000 $1,500,000 Total For Project 250629.8 $300,000 $300,000 $300,000 $300,000 $300,000 $1,500,000

250633.3 DISTRICTWIDE CONSTRU CTABILITY REVIEW CONSULTA NT PM: DUBROVSKY, MIKHAIL Work Mix: Preliminary Engineering Extra Description: CONSTRUCTABILITY REVIEWS PM'D BY DOT CEI UNIT. Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 5 Year Total P.E. DS $300,000 $300,000 $300,000 $900,000 CEI DS $50,000 $50,000 $100,000 Total For Project 250633.3 $350,000 $350,000 $300,000 $1,000,000

250633.4 DISTRICTWIDE CONSTRU CTABILITY REVIEW CONSULTA NT PM: WYNN, ISAAC Work Mix: Preliminary Engineering Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2023 FY 2024 FY 2025 5 Year Total P.E. DS $700,000 $700,000 $700,000 $2,100,000 CEI DS $50,000 $50,000 $50,000 $150,000 Total For Project 250633.4 $750,000 $750,000 $750,000 $2,250,000

October. 10 2019 Page 7 of 51 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

250635.3 D/W CULTURAL RESOURC E ASSESSMENT CONSULTANT PM: CULHANE/CONDELL Work Mix: Environmental Test/Mitigate Extra Description: PH-C2 & PH-62: FOR ARCHEOLOGICAL MONITORING Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 5 Year Total PDE DIH $30,000 $30,000 $30,000 $30,000 $120,000 ENV DS $100,000 $100,000 Total For Project 250635.3 $130,000 $30,000 $30,000 $30,000 $220,000

250647.2 DISTRICTWIDE REPAIR/ REHAB PLANS PREPARATION PM: OROZCO, PABLO Work Mix: Bridge-Repair/Rehabilitation Extra Description: ROADWAY ID AND BRIDGE NUMBERS TO BE ASSIGNED WHEN TASK WORK ORDERS ARE ISSUES/ PH 32-01 = C9332/TRANS SYSTEMS, PH 32-02 = C9331/BCC ENG. PH 32-03 = C9B58/HDR ENG, PH 32-04 = C9B57/HARDESTY&HANOVER Cont. Class: Misc - No Letting

Phase Fund Code FY 2023 5 Year Total P.E. BRRP $100,000 $100,000 Total For Project 250647.2 $100,000 $100,000

250649.2 DISTRICTWIDE PERMITS CONSULTANT PM: DOMINGUEZ, MARIO Work Mix: Environmental Permits Acq Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total PDE DIH $20,000 $20,000 $20,000 $20,000 $20,000 $100,000 DS $350,000 $400,000 $400,000 $400,000 $400,000 $1,950,000 Total For Project 250649.2 $370,000 $420,000 $420,000 $420,000 $420,000 $2,050,000

250650.4 DISTRICTWIDE TRAFFIC OPERATIONS - SAFETY STUD IES CONSULTANT PM: SOTOLONGO, ISIS Work Mix: Traffic Engineering Study Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 5 Year Total P.E. DS $125,000 $125,000 Total For Project 250650.4 $125,000 $125,000

October. 10 2019 Page 8 of 51 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

250650.5 DISTRICTWIDE TRAFFIC OPERATIONS - SAFETY STUD IES CONSULTANT PM: SOTOLONGO, ISIS Work Mix: Traffic Engineering Study Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total P.E. DS $200,000 $200,000 $200,000 $200,000 $200,000 $1,000,000 Total For Project 250650.5 $200,000 $200,000 $200,000 $200,000 $200,000 $1,000,000

250654.1 DISTRICTWIDE COMMUNI TY SAFETY PM: SARMIENTO, CARLOS Work Mix: Safety Project Extra Description: NHTS, COMMUNITY TRAFFIC SAFETY PROGRAM Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total P.E. NHTS $30,000 $30,000 $30,000 $30,000 $30,000 $150,000 Total For Project 250654.1 $30,000 $30,000 $30,000 $30,000 $30,000 $150,000

250662.5 DISTRICTWIDE TRAFFIC OPERATIONS SAFETY STUDIE S CONSULTANT PM: CHOW, LEEFANG

Work Mix: Traffic Engineering Study Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total P.E. DS $300,000 $300,000 $300,000 $300,000 $300,000 $1,500,000 Total For Project 250662.5 $300,000 $300,000 $300,000 $300,000 $300,000 $1,500,000

250668.2 DISTRICTWIDE MITIGAT ION SITE MAINTENANCE PM: DEANGELO, JACQUELYN

Work Mix: Environmental Test/Mitigate Extra Description: SPLIT OUT FROM SEQ 1 --- FYS 2011 THRU 2015 C2= PILOT PROJECT FOR SEAGRASS MITIGATION CNT:BDW12/CONSULT: METRIC ENGINEERING Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total PDE DIH $25,000 $50,000 $25,000 $25,000 $25,000 $150,000 DS $100,000 $150,000 $200,000 $200,000 $100,000 $750,000 Total For Project 250668.2 $125,000 $200,000 $225,000 $225,000 $125,000 $900,000

October. 10 2019 Page 9 of 51 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

250673.1 DISTRICTWIDE PUBLIC INVOLVEMENT CONSULTANT PM: BURGHER, TISH Work Mix: Preliminary Engineering Extra Description: SEQ 1 - CNT BB528 SEQ 2 - CNT BD507 SEQ 3 - CNT BDC44 SEQ 4 - CNT BDS55:060 060311 PER C.GUIDRY EMAIL OF 063011 SEQ 5 CNT BDC44/PROG 08 (S.A. TO SUPPORT TRAF OPS W/PUBLIC INVOLVEMENT ACTIVITIES/TRAF OPS SAFETY PROJECTS Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total P.E. DIH $80,000 $80,000 $80,000 $80,000 $80,000 $400,000 Total For Project 250673.1 $80,000 $80,000 $80,000 $80,000 $80,000 $400,000

250676.3 DISTRICTWIDE CONSTRU CTION ENGINEERING INSPECT ION CONSULTANT SURVEYS PM: DUBROVSKY, MIKHAIL Work Mix: Special Surveys Extra Description: NOTE: BDI CONTRACT PER LEIGH,APPR. BY ANGELA MATIYOW 1-11-18 Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 5 Year Total CEI DS $100,000 $100,000 $100,000 $100,000 $400,000 Total For Project 250676.3 $100,000 $100,000 $100,000 $100,000 $400,000

250676.4 DISTRICTWIDE CONSTRU CTION ENGINEERING INSPECT ION CONSULTANT SURVEYS PM: DUBROVSKY, MIKHAIL

Work Mix: Special Surveys Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2024 FY 2025 5 Year Total CEI DS $100,000 $100,000 $200,000 Total For Project 250676.4 $100,000 $100,000 $200,000

250678.2 DISTRCT WORK PROGRAM /FEDERAL AID/BUDGET STAF F ACTIVITIES PM: LUCERO, MICHAEL

Work Mix: Transportation Planning Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total Admin D $500,000 $500,000 $500,000 $500,000 $500,000 $2,500,000 Total For Project 250678.2 $500,000 $500,000 $500,000 $500,000 $500,000 $2,500,000

October. 10 2019 Page 10 of 51 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

250680.2 DISTRICTWIDE ENVIRON MENTAL COMPLIANCE CONSULT ANT PM: DOMINGUEZ, MARIO Work Mix: Environmental Permits Acq Extra Description: CNT# BDZ39 CECOS Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total PDE DIH $15,000 $10,000 $10,000 $10,000 $10,000 $55,000 DS $50,000 $150,000 $100,000 $100,000 $300,000 $700,000 Total For Project 250680.2 $65,000 $160,000 $110,000 $110,000 $310,000 $755,000

250686.2 DISTRICTWIDE MISC. L OCATION SURVEY CONSULTANT PM: MARRERO, VICTOR

Work Mix: Preliminary Engineering Extra Description: PHASE 32-01 = ATKINS CONTRACT C9705 - EXPIRES JUNE 2017 PHASE 32-02 = F.R. ALEMAN CONTRACT C9699 - EXPIRES JUNE 2017 PHASE 32-03 = CARDNO C9J66 - EXPIRES JUNE 2020 PHASE 32-04 = MASER Cont. Class: Misc - No Letting

Phase Fund Code FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total P.E. DS $950,000 $750,000 $750,000 $750,000 $3,200,000 Total For Project 250686.2 $950,000 $750,000 $750,000 $750,000 $3,200,000

250686.3 DISTRICTWIDE MISC. L OCATION SURVEY CONSULTANT PM: MARRERO, VICTOR Work Mix: Preliminary Engineering Extra Description: TO BE ADOPTED JULY 1ST 2014 AND FUTURE YEARS GAMED BDID CONTRACT FOR $1.5M (5 YEARS) APPRVD BY C. PERRY 4-27-14 DECEMBER 2014 ADV. AND JUNE 2015 PSU OFFICE EXECUTION PHASE 32-01 = CONTRACT C9K68 (ZURWELLE) EXPIRES JUNE 2020 Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total P.E. DS $200,000 $200,000 $200,000 $200,000 $200,000 $1,000,000 Total For Project 250686.3 $200,000 $200,000 $200,000 $200,000 $200,000 $1,000,000

250693.2 D/W ENVIRONMENTAL DA TA & REPORT CONSULTANT PM: KELLEY/JUNGMAN

Work Mix: Research Extra Description: PH22-01 = CNT:C9F13/CONSULT: STANTEC PH22-02 = CNT:C9P87/CONSULT: AECOM PH22-03 = CNT:C9W59/CONSULT: STANTEC Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total PDE DIH $30,000 $30,000 $30,000 $30,000 $30,000 $150,000 DS $900,000 $900,000 $1,800,000 Total For Project 250693.2 $30,000 $930,000 $930,000 $30,000 $30,000 $1,950,000

October. 10 2019 Page 11 of 51 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

250693.3 D/W ENVIRONMENTAL DA TA & REPORT CONSULTANT PM: KELLEY/JUNGMAN Work Mix: Research Extra Description: CONTRACT - 1 REPLACES 250693-2-22-04 Cont. Class: Misc - No Letting

Phase Fund Code FY 2023 FY 2024 FY 2025 5 Year Total PDE DS $150,000 $450,000 $450,000 $1,050,000 Total For Project 250693.3 $150,000 $450,000 $450,000 $1,050,000

250693.4 D/W ENVIRONMENTAL DA TA & REPORT CONSULTANT PM: KELLEY/JUNGMAN Work Mix: Research Extra Description: CONTRACT - 2 REPLACES 250693-2-22-05 Cont. Class: Misc - No Letting

Phase Fund Code FY 2023 FY 2024 FY 2025 5 Year Total PDE DIH $10,000 $10,000 $10,000 $30,000 DS $150,000 $450,000 $450,000 $1,050,000 Total For Project 250693.4 $160,000 $460,000 $460,000 $1,080,000

250697.1 DISTRICTWIDE TITLE S EARCH PM: ALBURY, CRISTINA Work Mix: Preliminary Engineering Extra Description: JOB#1552=86/87 PHASE 3B-01, 3B-02 & 3B-03 (CONTRACTS CLOSED) PHASE 3B-04 = CONTRACT DNY87/AMERICAN GOVT. MAY 2016 TO 2019 PHASE 3B-05 = CONTRACT DNY88/PARAMOUNT JUNE 2016 TO MAY 2019 PHASE 3B-06 = NEW CONTRACT PHASE 3B-07 = NEW CONTRACT Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total P.E. DS $167,646 $167,646 $167,646 $167,646 $167,646 $838,230 Total For Project 250697.1 $167,646 $167,646 $167,646 $167,646 $167,646 $838,230

250697.2 DISTRICTWIDE TITLE S EARCH PM: ALBURY, CRISTINA

Work Mix: Preliminary Engineering Extra Description: PHASE 32-01 = CONTRACT DN092/JGS PROPERTIES PHASE 32-02 = CONTRACT DO471/PERFORMANCE PROPERTY MGMT. PHASE 32-03 = CONTRACT DO771/JGS PROPERTIES PHASE 32-04 = NEW CONTRACT PHASE 32-05 = NEW CONTRACT Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total P.E. DS $75,000 $75,000 $75,000 $75,000 $75,000 $375,000 Total For Project 250697.2 $75,000 $75,000 $75,000 $75,000 $75,000 $375,000

October. 10 2019 Page 12 of 51 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

250711.7 DISTRICTWIDE MISC. C ONSTRUCTION ENGINEERING I NSPECTION CONSULTANT PM: DUBROVSKY, MIKHAIL Work Mix: Inspect Construction Projs. Extra Description: PHASE 62-01 = NEW CONTRACT JUNE 2019 PHASE 62-02 = NEW CONTRACT NOVEMBER 2019 PHASE 62-03 = NEW CONTRACT JUNE 2020 PHASE 62- 03,04 & 05 REPLACED WITH FM 445958-1, SEG 2 & 3 Cont. Class: Misc - No Letting

Phase Fund Code FY 2022 FY 2023 5 Year Total CEI DS $900,000 $300,000 $1,200,000 Total For Project 250711.7 $900,000 $300,000 $1,200,000

250711.9 017 D-WIDE MISC.CONS TRUCTION ENGINEERING INSP ECTION CONSULTANT 2 PM: DUBROVSKY, MIKHAIL Work Mix: Inspect Construction Projs. Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 5 Year Total CEI DS $384,100 $112,000 $496,100 Total For Project 250711.9 $384,100 $112,000 $496,100

250723.3 DISTRICTWIDE UTILITY COORDINATION CONSULTANT PM: ALBURY, TIM

Work Mix: Preliminary Engineering Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total P.E. DS $100,000 $500,000 $600,000 $600,000 $600,000 $2,400,000 Total For Project 250723.3 $100,000 $500,000 $600,000 $600,000 $600,000 $2,400,000

250723.4 CONTINUING UTILITY L OCATING SERVICES PM: IGLESIAS, DANIEL

Work Mix: Preliminary Engineering Extra Description: FUNDS FROM 250723-2-32-05 Cont. Class: Misc - No Letting

Phase Fund Code FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total P.E. DIH $5,000 $5,000 $5,000 $5,000 $20,000 DS $300,000 $300,000 $300,000 $300,000 $1,200,000 Total For Project 250723.4 $305,000 $305,000 $305,000 $305,000 $1,220,000

October. 10 2019 Page 13 of 51 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

250723.5 CONTINUING UTILITY L OCATING SERVICES PM: IGLESIAS, DANIEL Work Mix: Preliminary Engineering Extra Description: FUNDS FROM 250723-2-32-06 Cont. Class: Misc - No Letting

Phase Fund Code FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total P.E. DIH $5,000 $5,000 $5,000 $5,000 $20,000 DS $300,000 $300,000 $300,000 $300,000 $1,200,000 Total For Project 250723.5 $305,000 $305,000 $305,000 $305,000 $1,220,000

250724.2 D/W STRUCTURAL PROJE CTS MINOR DESIGN CONSULTA NTS PM: ZHANG, HAILING

Work Mix: Preliminary Engineering Extra Description: PHASE 32-01 = CONTRACT C9F93/TRANSYSTEMS (S/B AT $1.5M FY18) PHASE 32-02 = NEW CONTRACT IN FY 17/18 Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total P.E. DIH $10,000 $10,000 $10,000 $10,000 $10,000 $50,000 DS $550,000 $450,000 $450,000 $550,000 $450,000 $2,450,000 Total For Project 250724.2 $560,000 $460,000 $460,000 $560,000 $460,000 $2,500,000

250730.2 DISTRICTWIDE MATERIA LS TESTING/ GEOTECHNICAL SUPPORT PM: ARCALAS, RON

Work Mix: Inspect Construction Projs. Extra Description: INDEFINITE TERM PROJECT CONSISTING OF MATLS TESTING SVCES WITH 5 YEAR CONTRACTS. GEOTECHNICAL SUPPORT FOR PRECONST. & CONST. PROJECTS. MIKHAIL DUBROVSKY WORKS W/D-4 (M. PATEL) PH 32-01 = C9827/GEOSOL (CONTRACT ENDS OCT. 2017) PH 32-02 = C9F24/HR Cont. Class: Misc - No Letting (CONTRACT ENDS MAY 2019) PH 32-03 = C9Q52/GEOSOL (CONTRACT ENDS JULY 2021)

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 5 Year Total P.E. DS $300,000 $300,000 $300,000 $300,000 $1,200,000 Total For Project 250730.2 $300,000 $300,000 $300,000 $300,000 $1,200,000

250730.3 DISTRICTWIDE MATERIA LS TESTING/ GEOTECHNICAL SUPPORT PM: ARCALAS, RON Work Mix: Inspect Construction Projs. Extra Description: CONTRACT APPROVED BY CARLA PERRY AS BDID ON 6-16-17 Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 5 Year Total P.E. DS $100,000 $100,000 Total For Project 250730.3 $100,000 $100,000

October. 10 2019 Page 14 of 51 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

250730.4 DISTRICTWIDE MATERIA LS TESTING/GEOTECHNICAL S UPPORT PM: ARCALAS, RON Work Mix: Inspect Construction Projs. Extra Description: INDEFINITE TERM PROJECT CONSISTING OF MATLS TESTING SVCES WITH 5 YEAR CONTRACTS. GEOTECHNICAL SUPPORT FOR PRECONST. & CONST. PROJECTS. MIKHAIL DUBROVSKY WORKS W/D-4 (M. PATEL) Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total P.E. DS $300,000 $300,000 $300,000 $300,000 $300,000 $1,500,000 Total For Project 250730.4 $300,000 $300,000 $300,000 $300,000 $300,000 $1,500,000

250730.5 DISTRICTWIDE MATERIA LS TESTING/GEOTECHNICAL S UPPORT PM: ARCALAS, RON Work Mix: Inspect Construction Projs. Extra Description: INDEFINITE TERM PROJECT CONSISTING OF MATERIALS TESTING SERVICES WITH 5 YEAR CONTRACTS. GEOTECHICAL SERVICES FOR PRE- CONSTRUCTION PROJECTS AND PROJECTS UNDER CONSTRUCTION. Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total P.E. DS $300,000 $300,000 $300,000 $300,000 $300,000 $1,500,000 Total For Project 250730.5 $300,000 $300,000 $300,000 $300,000 $300,000 $1,500,000

250741.1 D/W IN HOUSE CONSULT ANT MANAGEMENT SUPPORT PM: SOLAUN, JUDY

Work Mix: Preliminary Engineering Extra Description: SUPPORT FOR D/W MINOR PROJECT CONSULTANT CONTRACTS AND MISCELLANEOUS NON PROJECT ACTIVITIES Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total P.E. DIH $500,000 $500,000 $500,000 $500,000 $500,000 $2,500,000 Total For Project 250741.1 $500,000 $500,000 $500,000 $500,000 $500,000 $2,500,000

250742.1 DISTRICTWIDE PD&E PR OJECT MGT PM: HUYNH, DAT

Work Mix: Preliminary Engineering Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total PDE DIH $300,000 $300,000 $300,000 $300,000 $300,000 $1,500,000 Total For Project 250742.1 $300,000 $300,000 $300,000 $300,000 $300,000 $1,500,000

October. 10 2019 Page 15 of 51 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

250743.1 D/W IN HOUSE ROADWAY DESIGN SUPPORT PM: IGLESIAS, DANIEL Work Mix: Preliminary Engineering Extra Description: SUPPORT FOR IN HOUSE DESIGN MISCELLANEOUS NON PROJECT ACTIVITIES Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total P.E. DIH $120,000 $100,000 $100,000 $100,000 $100,000 $520,000 Total For Project 250743.1 $120,000 $100,000 $100,000 $100,000 $100,000 $520,000

250747.1 DISTRICTWIDE ENGINEE RING SUPPORT SERVICES PM: IGLESIAS, DANIEL Work Mix: Preliminary Engineering Extra Description: TSD DIRECTOR=SEQ.02 Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total P.E. DIH $2,000,000 $2,000,000 $2,000,000 $2,000,000 $2,000,000 $10,000,000 Total For Project 250747.1 $2,000,000 $2,000,000 $2,000,000 $2,000,000 $2,000,000 $10,000,000

250759.1 DISTRICTWIDE PROJECT MANAGEMENT PD&E SCOPING UNIT & SUPPORT PM: BENITEZ, HONG

Work Mix: Pd&E/Emo Study Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 5 Year Total PDE DIH $50,000 $50,000 $50,000 $50,000 $200,000 Total For Project 250759.1 $50,000 $50,000 $50,000 $50,000 $200,000

250790.2 D/W LAP CONSULTANT-L AP PROJECTS PM: NUNEZ, XIOMARA

Work Mix: Preliminary Engineering Extra Description: PD&E AND DESIGN FOR ELIGIBLE LAP PROJECTS. 32-02 = CONSUL-TECH C-8286 32-03 = KEITH & SCHNARS C-9007 Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total P.E. DIH $160,000 $160,000 $160,000 $160,000 $160,000 $800,000 Total For Project 250790.2 $160,000 $160,000 $160,000 $160,000 $160,000 $800,000

October. 10 2019 Page 16 of 51 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

405610.9 DISTRICTWIDE PUSHBUT TON LANDSCAPING CONTRACTO R PM: SCHOT, KEVIN Work Mix: Landscaping Extra Description: D/W LANDSCAPING PUSHBUTTON CONTRACT CNT# Cont. Class: District Let

Phase Fund Code FY 2022 5 Year Total Construction DS $923,684 $923,684 CEI DDR $42,120 $42,120 DIH $148,473 $148,473 DS $185,328 $185,328 Total For Project 405610.9 $1,299,605 $1,299,605

406486.1 D/W RIGHT-OF-WAY DON ATIONS AND DEDICATIONS PM: CASALS, ALEX Work Mix: Right Of Way Activities Extra Description: IN-HOUSE CHARGES FOR ROW DONATIONS/DEDICATIONS THROUGH PERMIT PROCESS 3201=250696-4 D/W FOR SURVEY & MAPS. PH31 = ROW ENGINEERING PH41 = ROW ADMIN Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total P.E. DIH $10,000 $10,000 $10,000 $10,000 $10,000 $50,000 RW Support DIH $60,000 $60,000 $60,000 $60,000 $60,000 $300,000 Total For Project 406486.1 $70,000 $70,000 $70,000 $70,000 $70,000 $350,000

409521.7 DISTRICTWIDE TRAFFIC OPERATIONS STUDIES CONSU LTANT PM: MOTTA, ALEJANDRO Work Mix: Traffic Ops Improvement Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total P.E. DS $300,000 $300,000 $300,000 $300,000 $300,000 $1,500,000 Total For Project 409521.7 $300,000 $300,000 $300,000 $300,000 $300,000 $1,500,000

409521.8 DISTRICTWIDE TRAFFIC OPERATIONS STUDIES CONSU LTANT PM: RODRIGUEZ, CHERIE

Work Mix: Traffic Ops Improvement Extra Description: 2 - MISC. INFO Cont. Class: Misc - No Letting

Phase Fund Code FY 2023 5 Year Total P.E. DS $350,000 $350,000 Total For Project 409521.8 $350,000 $350,000

October. 10 2019 Page 17 of 51 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

410265.2 DISTRICTWIDE ASBESTO S & LEAD ABATEMENT SUPERV ISION & INSPECTNS PM: OROZCO, PABLO Work Mix: Inspect Construction Projs. Extra Description: SPLIT OUT FROM SEGMENT 1 FY13 AND LATER Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total CEI BRRP $650,000 $300,000 $300,000 $300,000 $300,000 $1,850,000 Total For Project 410265.2 $650,000 $300,000 $300,000 $300,000 $300,000 $1,850,000

410993.1 DISTRICTWIDE STRUCTU RES DESIGN AND REVIEW CON SULTANT PM: ZHANG, HAILING Work Mix: Preliminary Engineering Extra Description: PH 32-01 = C7969/AECOM (CLOSED) PH 32-02 = C8J62/TRANSYSTEMS (CLOSED) PH 32-03 = C8Y13/EAC (CLOSED) PH 32-04 = C9H45/EAC (EXPIRES 11-20-19) PCR S/B $1.5M FY 18 PH 32-05 = NEW CONTRACT DEFER FY 17/18 FUNDING 1 YR TO 18/19 PER EMAIL HAILING ZHANG/PRODUCTION 5-10 Cont. Class: Misc - No Letting -17

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total P.E. DIH $10,000 $10,000 $10,000 $10,000 $10,000 $50,000 DS $550,000 $450,000 $450,000 $550,000 $2,000,000 Total For Project 410993.1 $10,000 $560,000 $460,000 $460,000 $560,000 $2,050,000

411433.2 DISTRICTWIDE DRAINAG E DESIGN AND PLAN REVIEW CONSULTANT PM: DOMINGUEZ, MARIO

Work Mix: Preliminary Engineering Extra Description: NEW SEG 2 FY16 ONWARD CREATED PER RICHARDS REPORT/GAMING MEETINGS NOTES PER L.PALMBERG EMAIL OF 080813 Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total P.E. DIH $40,000 $25,000 $15,000 $25,000 $105,000 DS $400,000 $400,000 $300,000 $400,000 $400,000 $1,900,000 Total For Project 411433.2 $440,000 $425,000 $315,000 $425,000 $400,000 $2,005,000

414052.3 DISTRICTWIDE TRAFFIC OPERATIONS SAFETY STUDIE S CONSULTANT PM: CHOW, LEEFANG Work Mix: Transportation Statistics Extra Description: PH32-01 = CNT# C9U18/CONSULT: MCMAHON Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 5 Year Total P.E. DS $200,000 $200,000 Total For Project 414052.3 $200,000 $200,000

October. 10 2019 Page 18 of 51 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

414052.4 DISTRICTWIDE TRAFFIC OPS SAFETY STUDIES CONSU LTANT PM: CHOW, LEEFANG Work Mix: Traffic Ops Improvement Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total P.E. DS $300,000 $300,000 $300,000 $200,000 $1,100,000 Total For Project 414052.4 $300,000 $300,000 $300,000 $200,000 $1,100,000

415239.4 DISTRICTWIDE PLANS R EVIEW CONSULTANT AND SUPP ORT SERVICES PM: DEFRANT, JACQUES Work Mix: Preliminary Engineering Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 5 Year Total P.E. DS $400,000 $400,000 $300,000 $1,100,000 Total For Project 415239.4 $400,000 $400,000 $300,000 $1,100,000

415239.5 DISTRICTWIDE PLANS R EVIEW & SUPPORT SERVICES CONSULTANT PM: DEFRANT, JACQUES

Work Mix: Traffic Ops Improvement Extra Description: DISTRICTWIDE PLANS REVIEW & SUPPORT SERVICES CONSULTANT Cont. Class: Misc - No Letting

Phase Fund Code FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total P.E. DS $400,000 $400,000 $400,000 $300,000 $1,500,000 Total For Project 415239.5 $400,000 $400,000 $400,000 $300,000 $1,500,000

416487.1 DISTRICTWIDE ETDM CO NSULTANT PM: THOMAS, CURLENE

Work Mix: Pd&E/Emo Study Extra Description: PH 22-01 = CNT:C8B44/CONSULT: URS PH 22-02 = CNT:C8V22/CONSULT: CORRADINO GRP PH 22-03 = CNT:C9015/CONSULT: URS PH 22-04 = CNT:C9897/CONSULT: URS Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total PDE DIH $10,000 $10,000 $10,000 $10,000 $10,000 $50,000 DS $300,000 $300,000 $300,000 $300,000 $300,000 $1,500,000 Total For Project 416487.1 $310,000 $310,000 $310,000 $310,000 $310,000 $1,550,000

October. 10 2019 Page 19 of 51 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

417026.1 DISTRICTWIDE R/W ADV ANCED ACQ. SUPPORT PM: CASALS, ALEX Work Mix: Right Of Way Activities Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total RW Support DIH $10,000 $10,000 $10,000 $10,000 $10,000 $50,000 Total For Project 417026.1 $10,000 $10,000 $10,000 $10,000 $10,000 $50,000

418064.1 DISTRICTWIDE (ADA) C OMPLIANCE CONSULTANT PM: GEHRKE, TIFFANY Work Mix: Sidewalk Extra Description: DESIGN PLANS, STUDY UPDATES, COORDINATION WITH PROJECT MGRS AND REVIEW OF DESIGN PLANS PH32-03: CURLENE THOMAS/CNT# C9M59 PH32-01: KEN JEFFRIES/CNT#C9896 Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total P.E. DS $250,000 $250,000 $250,000 $250,000 $250,000 $1,250,000 Total For Project 418064.1 $250,000 $250,000 $250,000 $250,000 $250,000 $1,250,000

423448.1 DISTRICTWIDE ROW MON UMENTATION CONSULTANT CON TRACT PM: ALBURY, CRISTINA

Work Mix: Preliminary Engineering Extra Description: 32-01 = CONTRACT C8P66/TRIANGLE (CLOSED) 32-02 = CONTRACT C9D05/MANUEL G. VERA (10/2013 TO 10/2018) 32-03 = NEW CONTRACT IN FY 18/19 32-04 = NEW CONTRACT IN FY 23/24 Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total P.E. DS $300,000 $300,000 $300,000 $300,000 $300,000 $1,500,000 Total For Project 423448.1 $300,000 $300,000 $300,000 $300,000 $300,000 $1,500,000

425402.1 DISTRICTWIDE LANDSCA PE DESIGN CONSULTANT PM: SCHOT, KEVIN

Work Mix: Landscaping Extra Description: PH 32-01 = CNT: C8V83/C9007 - KEITH & SCHNARS PH 32-02 = CNT: C9931/KEITH & SCHNARS PH 32-03 = CNT: C9930/MILLER LEGG PH 32-04 = CNT: C9070/CHEN MOORE PH 32-05 = CNT: C9071/WANTMAN GROUP PH 32-06 = CNT: **SEE WP45** Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total P.E. DIH $20,000 $20,000 $20,000 $20,000 $20,000 $100,000 DS $500,000 $300,000 $100,000 $900,000 Total For Project 425402.1 $520,000 $320,000 $120,000 $20,000 $20,000 $1,000,000

October. 10 2019 Page 20 of 51 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

425402.2 DISTRICTWIDE LANDSCA PE DESIGN CONSULTANT PM: SCHOT, KEVIN Work Mix: Landscaping Extra Description: FUNDS FROM FM 425402-1-32-08 Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total P.E. DS $150,000 $150,000 $200,000 $150,000 $50,000 $700,000 Total For Project 425402.2 $150,000 $150,000 $200,000 $150,000 $50,000 $700,000

425402.3 DISTRICTWIDE LANDSCA PE DESIGN CONSULTANT PM: SCHOT, KEVIN Work Mix: Landscaping Extra Description: FUNDS ADDED FROM 425402-1-32-09 Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total P.E. DS $150,000 $150,000 $200,000 $150,000 $150,000 $800,000 Total For Project 425402.3 $150,000 $150,000 $200,000 $150,000 $150,000 $800,000

427849.1 D/W PROPERTY MGMT. A SBESTOS CONSULT ABATEMNT AND DEMOLITION SERVICES PM: CASALS, ALEX

Work Mix: Right Of Way Activities Extra Description: FOR USE IN UPCOMING FUTURE DISTRICTWIDE ASBESTOS, ABATEMENT AND DEMOLITION SERVICES FOR MIAMI-DADE AND MONROE BRIDGES Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total RW Support DIH $5,000 $5,000 $5,000 $5,000 $5,000 $25,000 DS $25,000 $25,000 $25,000 $25,000 $25,000 $125,000 Total For Project 427849.1 $30,000 $30,000 $30,000 $30,000 $30,000 $150,000

429285.3 TRAFFIC ENGINEERING STUDIES & ENGINEERING REV IEWS CONSULTANT PM: LU, JINYAN

Work Mix: Preliminary Engineering Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 5 Year Total P.E. DS $400,000 $400,000 $300,000 $1,100,000 Total For Project 429285.3 $400,000 $400,000 $300,000 $1,100,000

October. 10 2019 Page 21 of 51 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

429285.4 TRAFFIC ENGINEERING STUDIES & ENGINEERING REV IEWS CONSULTANT PM: LU, JINYAN Work Mix: Traffic Ops Improvement Extra Description: 2 - MISC. INFO Cont. Class: Misc - No Letting

Phase Fund Code FY 2023 FY 2024 FY 2025 5 Year Total P.E. DS $200,000 $400,000 $400,000 $1,000,000 Total For Project 429285.4 $200,000 $400,000 $400,000 $1,000,000

429286.4 TRAFFIC ENGINEERING SUPPORT SERVICES CONSULTA NT PM: HIJAR, JULIO Work Mix: Preliminary Engineering Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 5 Year Total P.E. DS $500,000 $100,000 $600,000 Total For Project 429286.4 $500,000 $100,000 $600,000

429286.6 TRAFFIC ENGINEERING SUPPORT SERVICES CONSULTA NT PM: HIJAR, JULIO

Work Mix: Traffic Ops Improvement Extra Description: 2 - MISC. INFO Cont. Class: Misc - No Letting

Phase Fund Code FY 2022 FY 2023 FY 2024 5 Year Total P.E. DS $500,000 $500,000 $500,000 $1,500,000 Total For Project 429286.6 $500,000 $500,000 $500,000 $1,500,000

429286.7 TRAFFIC ENGINEERING SUPPORT SERVICES CONSULTA NT PM: HIJAR, JULIO

Work Mix: Traffic Ops Improvement Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2025 5 Year Total P.E. DS $500,000 $500,000 Total For Project 429286.7 $500,000 $500,000

October. 10 2019 Page 22 of 51 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

429536.5 DISTRICTWIDE (ADA) P USHBUTTON CONSTRUCTION PM: GEHRKE/GERSHANOVICH Work Mix: Pedestrian Safety Improvement Extra Description: Cont. Class: District Let

Phase Fund Code FY 2021 5 Year Total Construction DS $685,487 $685,487 CEI DIH $101,101 $101,101 DS $123,120 $123,120 Total For Project 429536.5 $909,708 $909,708

429536.6 DISTRICTWIDE (ADA) P USHBUTTON CONSTRUCTION PM: GEHRKE/GERSHANOVICH

Work Mix: Pedestrian Safety Improvement Extra Description: Cont. Class: District Let

Phase Fund Code FY 2023 5 Year Total Construction DS $685,487 $685,487 CEI DIH $101,000 $101,000 DS $118,910 $118,910 Total For Project 429536.6 $905,397 $905,397

429536.7 DISTRICTWIDE (ADA) P USHBUTTON CONSTRUCTION PM: GEHRKE/GERSHANOVICH Work Mix: Pedestrian Safety Improvement Extra Description: Cont. Class: District Let

Phase Fund Code FY 2025 5 Year Total Construction DS $685,487 $685,487 CEI DIH $101,101 $101,101 DS $91,102 $91,102 Total For Project 429536.7 $877,690 $877,690

October. 10 2019 Page 23 of 51 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

430161.4 CONSTRUCTION FINAL E STIMATES CONTRACT SUPPORT PM: WYNN, ISAAC

Work Mix: Inspect Construction Projs. Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 5 Year Total CEI ACSA $100,000 $100,000 SA $280,000 $380,000 $380,000 $360,000 $1,400,000 Total For Project 430161.4 $380,000 $380,000 $380,000 $360,000 $1,500,000

430161.5 CONSTRUCTION FINAL E STIMATES CONTRACT SUPPORT PM: WYNN, ISAAC

Work Mix: Inspect Construction Projs. Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2025 5 Year Total CEI SA $380,000 $380,000 Total For Project 430161.5 $380,000 $380,000

431635.5 DISTRICTWIDE TRAFFIC OPS PUSHBUTTON DESIGN CO NSULT CONTINUING CONTRACT PM: SIERRA, RAMON

Work Mix: Traffic Ops Improvement Extra Description: 2-MISC.INFO PH32-01 = CNT#CA044/CONSUL: TINDALE-OLIVER Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 5 Year Total P.E. DIH $18,000 $18,000 $36,000 DS $500,000 $500,000 $500,000 $1,500,000 Total For Project 431635.5 $518,000 $500,000 $518,000 $1,536,000

431635.7 TRAFFIC OPERATIONS P USHBUTTON MISC. CONSTRUCT ION IN MIAMI-DADE COUNTY PM: KHAN, SAUD

Work Mix: Miscellaneous Construction Extra Description: Cont. Class: District Let

Phase Fund Code FY 2021 5 Year Total Construction DS $1,000,000 $1,000,000 CEI DIH $106,704 $106,704 DS $180,000 $180,000 Total For Project 431635.7 $1,286,704 $1,286,704

October. 10 2019 Page 24 of 51 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

431635.8 TRAFFIC OPERATIONS P USHBUTTON MISC. CONSTRUCT ION IN MIAMI-DADE COUNTY PM: KHAN, SAUD Work Mix: Miscellaneous Construction Extra Description: Cont. Class: District Let

Phase Fund Code FY 2022 5 Year Total Construction DS $1,000,000 $1,000,000 CEI DIH $180,000 $180,000 DS $180,000 $180,000 Total For Project 431635.8 $1,360,000 $1,360,000

431635.9 TRAFFIC OPERATIONS P USH-BUTTON MISC. CONSTRUC TION IN MIAMI-DADE COUNTY PM: KHAN, SAUD

Work Mix: Miscellaneous Construction Extra Description: NEW PROJECT CREATED FM 446261-1 Cont. Class: District Let

Phase Fund Code FY 2023 5 Year Total Construction DS $1,000,000 $1,000,000 CEI DS $180,001 $180,001 Total For Project 431635.9 $1,180,001 $1,180,001

432413.1 DISTRICTWIDE SCOPING UNIT TRAFFIC SAFETY REVI EWS PM: BENITEZ, HONG

Work Mix: Pd&E/Emo Study Extra Description: FUNDING TO REVIEW NUMEROUS DISTRICTWIDE TRAFFIC SAFETY STUDY PROJECT IS TO BE STRUNG TO GEC CNTS IN CONSULTANT MGMT. SEQ 01 = CONSULT: KEITH & SHNARS/CNT#C9007/EXEC:11/05/2010 SEQ 02 = CONSULT: AECOM/CNT#C9015/EXEC:12/20/2010 SEQ 03 = CONSULT: Cont. Class: Misc - No Letting AECOM/CNT#C968/EXEC: 06/12/15 SEQ 04 = CONSULT: HDR/CNT#C9J67/EXEC: 05/15/2015

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total PDE DS $200,000 $200,000 $200,000 $200,000 $200,000 $1,000,000 Total For Project 432413.1 $200,000 $200,000 $200,000 $200,000 $200,000 $1,000,000

432950.2 DISTRICTWIDE PROGRAM MANAGEMENT CONTRACT ADMI N SUPPORT PM: NUNEZ, XIOMARA

Work Mix: Preliminary Engineering Extra Description: CONTINUING SERVICES CONTRACT Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total P.E. DDR $900,000 $900,000 DS $900,000 $900,000 $900,000 $900,000 $3,600,000 Total For Project 432950.2 $900,000 $900,000 $900,000 $900,000 $900,000 $4,500,000

October. 10 2019 Page 25 of 51 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

434664.1 DISTRICTWIDE TRAFFIC OPERATIONS SAFETY STUDIE S CONSULTANTS PM: LEON, MISLEIDYS Work Mix: Safety Project Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 5 Year Total P.E. DS $200,000 $200,000 $400,000 Total For Project 434664.1 $200,000 $200,000 $400,000

434664.2 DISTRICTWIDE TRAFFIC OPERATIONS SAFETY STUDIE S CONSULTANT PM: LEON, MISLEIDYS Work Mix: Safety Project Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2023 FY 2024 FY 2025 5 Year Total P.E. DIH $5,000 $5,000 DS $300,000 $200,000 $200,000 $700,000 Total For Project 434664.2 $305,000 $200,000 $200,000 $705,000

435201.3 TRAFFIC ENGINEERING DATA COLLECTION - CONTINU ING SERVICES CONTRACT PM: LU, JINYAN Work Mix: Traffic Control Devices/System Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 5 Year Total P.E. DS $250,000 $250,000 Total For Project 435201.3 $250,000 $250,000

435201.4 DISTRICT 6 SIGNAL RE TIMING SERVICES-CONTINUIN G CONTRACT PM: HERNANDEZ, ISABEL

Work Mix: Traffic Control Devices/System Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 5 Year Total P.E. DITS $1,232,000 $1,232,000 $2,464,000 Total For Project 435201.4 $1,232,000 $1,232,000 $2,464,000

October. 10 2019 Page 26 of 51 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

435201.5 DISTRICTWIDE TRAFFIC ENGINEERING DATA COLLECT ION CONTRACT CONTRACT PM: LU, JINYAN Work Mix: Traffic Control Devices/System Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 5 Year Total P.E. DS $500,000 $500,000 $500,000 $1,500,000 Total For Project 435201.5 $500,000 $500,000 $500,000 $1,500,000

435201.6 DISTRICT SIX SIGNAL RETIMING SERVICES CONTINU ING CONTRACT PM: RODRIGUEZ, CHERIE Work Mix: Traffic Ops Improvement Extra Description: 2 - MISC. INFO Cont. Class: Misc - No Letting

Phase Fund Code FY 2023 FY 2024 FY 2025 5 Year Total P.E. DITS $1,232,000 $1,232,000 $1,232,000 $3,696,000 Total For Project 435201.6 $1,232,000 $1,232,000 $1,232,000 $3,696,000

435573.3 DISTRICTWIDE PEDESTR IAN & BICYCLE SAFETY PROG RAM CONSULTANT PM: SIERRA, RAMON

Work Mix: Traffic Engineering Study Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total P.E. DS $300,000 $300,000 $300,000 $300,000 $300,000 $1,500,000 Total For Project 435573.3 $300,000 $300,000 $300,000 $300,000 $300,000 $1,500,000

439218.1 DISTRICTWIDE GENERAL ENGINEERING CONSULTANT F OR MODAL PM: CARTAYA, NILIA

Work Mix: Preliminary Engineering Extra Description: PH 32/SEQ 01 = TRANSIT PH 32/SEQ 05 = GENERAL SUPP. PH 32/SEQ 02 = AVIATION PH 32/SEQ 06 = PRODUCTION SUPP PH 32/SEQ 03 = SEAPORT PH 37/SEQ 01 = RAIL INSPECTION PH 32/SEQ 04 = FREIGHT **FOR PHASES PRIOR TO THE TENTATIVE, SEE WP-45** REPLACEMENT Cont. Class: Misc - No Letting CONTRACT ON 439218-2

Phase Fund Code FY 2021 5 Year Total P.E. DS $1,000,000 $1,000,000 Total For Project 439218.1 $1,000,000 $1,000,000

October. 10 2019 Page 27 of 51 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

439218.2 DISTRICTWIDE GENERAL ENGINEERING CONSULTANT F OR MODAL PM: CARTAYA, NILIA Work Mix: Preliminary Engineering Extra Description: PH 22-01 = GENERAL MODAL SUPPORT (OVERLAP) PH 32-01 = TRANSIT PH 32-02 = AVIATION PH 32-03 = SEAPORT PH 32-04 = FREIGHT PH 37-01 = RAIL INSPECTION Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 5 Year Total PDE DS $50,000 $50,000 P.E. DS $1,000,000 $1,000,000 $1,000,000 $3,000,000 Total For Project 439218.2 $50,000 $1,000,000 $1,000,000 $1,000,000 $3,050,000

439491.1 DISTRICTWIDE PROGRAM MANAGEMENT ACTIVITIES PM: LUCERO, MICHAEL Work Mix: Preliminary Engineering Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 5 Year Total P.E. DIH $500,000 $500,000 $500,000 $1,500,000 Total For Project 439491.1 $500,000 $500,000 $500,000 $1,500,000

441940.1 ITS PROGRAM AVL SYST EM TO MANAGE D6 INCIDENT MANAGMENT FLEET PM: DARDES, CARLOS Work Mix: Other Its Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 5 Year Total Capital Improvement/Operating DS $127,020 $127,020 $127,020 $381,060 Total For Project 441940.1 $127,020 $127,020 $127,020 $381,060

444437.1 DISTRICTWIDE TRAFFIC OPERATIONS STUDIES CONSU LTANT PM: PATULOT, ARTHURO

Work Mix: Safety Project Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2024 5 Year Total P.E. DS $350,000 $350,000 Total For Project 444437.1 $350,000 $350,000

October. 10 2019 Page 28 of 51 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

444438.1 DISTRICTWIDE TRAFFIC OPERATIONS SAFETY STUDIE S CONSULTANTS PM: LEON, MISLEIDYS Work Mix: Safety Project Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2024 FY 2025 5 Year Total P.E. DS $300,000 $275,000 $575,000 Total For Project 444438.1 $300,000 $275,000 $575,000

445958.1 DISTRICTWIDE MISC. C ONSTRUCTION ENGINEERING I NSPECTION CONSULTANT PM: DUBROVSKY, MIKHAIL Work Mix: Inspect Construction Projs. Extra Description: NEW PROJECT REPLACED FM 250711-7-62-03 Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 5 Year Total CEI DS $1,400,000 $1,200,000 $1,200,000 $600,000 $4,400,000 Total For Project 445958.1 $1,400,000 $1,200,000 $1,200,000 $600,000 $4,400,000

445958.2 DISTRICTWIDE MISC. C ONSTRUCTION ENGINEERING I NSPECTION CONSULTANT PM: DUBROVSKY, MIKHAIL

Work Mix: Inspect Construction Projs. Extra Description: NEW PROJECT REPLACED FM 250711-7-62-04 Cont. Class: Misc - No Letting

Phase Fund Code FY 2025 5 Year Total CEI DS $600,000 $600,000 Total For Project 445958.2 $600,000 $600,000

445960.1 DISTRICTWIDE MISC. C ONSTRUCTION ENGINEERING I NSPECTION CONSULTANTAI PM: DUBROVSKY, MIKHAIL

Work Mix: Inspect Construction Projs. Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 5 Year Total CEI DS $800,000 $600,000 $1,400,000 Total For Project 445960.1 $800,000 $600,000 $1,400,000

October. 10 2019 Page 29 of 51 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

445960.2 DISTRICTWIDE MISC. C ONSTRUCTION ENGINEERING I NSPECTION CONSULTANT PM: DUBROVSKY, MIKHAIL Work Mix: Inspect Construction Projs. Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2022 FY 2023 FY 2024 5 Year Total CEI DS $400,000 $800,000 $300,000 $1,500,000 Total For Project 445960.2 $400,000 $800,000 $300,000 $1,500,000

445960.3 DISTRICTWIDE MISC. C ONSTRUCTION ENGINEERING I NSPECTION CONSULTANT PM: DUBROVSKY, MIKHAIL Work Mix: Inspect Construction Projs. Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2024 FY 2025 5 Year Total CEI DS $500,000 $800,000 $1,300,000 Total For Project 445960.3 $500,000 $800,000 $1,300,000

445963.1 DISTRICTWIDE DRAINAG E PUSHBUTTON PM: DOMINGUEZ, MARIO

Work Mix: Drainage Improvements Extra Description: CNT# E6L97 FUNDS CONSOLIDATED - FM 432695-3 AND SEGMENT 4 Cont. Class: District Let

Phase Fund Code FY 2021 5 Year Total CEI DDR $186,732 $186,732 Total For Project 445963.1 $186,732 $186,732

445963.2 DISTRICTWIDE DRAINAG E PUSHBUTTON PM: DOMINGUEZ, MARIO

Work Mix: Drainage Improvements Extra Description: FUNDS CONSOLIDATED FROM FM 425865-5 AND SEGMENT 6 Cont. Class: District Let

Phase Fund Code FY 2022 5 Year Total Construction DDR $1,000,000 $1,000,000 CEI DDR $189,540 $189,540 DIH $171,639 $171,639 Total For Project 445963.2 $1,361,179 $1,361,179

October. 10 2019 Page 30 of 51 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

445963.3 DISTRICTWIDE DRAINAG E PUSHBUTTON PM: DOMINGUEZ, MARIO Work Mix: Drainage Improvements Extra Description: FUNDS ADDED FROM DELETION OF FM 425865-8 Cont. Class: District Let

Phase Fund Code FY 2024 5 Year Total Construction DDR $1,000,000 $1,000,000 CEI DDR $179,982 $179,982 DIH $181,093 $181,093 Total For Project 445963.3 $1,361,075 $1,361,075

446015.1 DISTRICTWIDE TRAFFIC ENGINEERING DATA COLLECT ION CONTRACT PM: LU, JINYAN

Work Mix: Traffic Control Devices/System Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2024 FY 2025 5 Year Total P.E. DS $500,000 $500,000 $1,000,000 Total For Project 446015.1 $500,000 $500,000 $1,000,000

446120.1 017 D-WIDE MISC. CON STRUCTION ENGENEERING INS PECTION CONSULTANT 2 PM: DUBROVSKY, MIKHAIL

Work Mix: Inspect Construction Projs. Extra Description: NEW PROJECT REPLACED FM 250711-9 Cont. Class: Misc - No Letting

Phase Fund Code FY 2023 FY 2024 FY 2025 5 Year Total CEI DS $600,000 $1,400,000 $1,200,000 $3,200,000 Total For Project 446120.1 $600,000 $1,400,000 $1,200,000 $3,200,000

446140.1 DISTRICWIDE MISC. CO NSTRUCTION ENGINEERING IN SPECTION CONSULTANT PM: DUBROVSKY, MIKHAIL Work Mix: Inspect Construction Projs. Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2023 FY 2024 FY 2025 5 Year Total CEI DS $700,000 $700,000 $700,000 $2,100,000 Total For Project 446140.1 $700,000 $700,000 $700,000 $2,100,000

October. 10 2019 Page 31 of 51 HIGHWAY SYSTEM: 03 INTRASTATE STATE HIGHWAY

446444.1 DISTRICTWIDE PUSHBUT TON LANDSCAPING CONTRACTO R PM: SCHOT, KEVIN Work Mix: Landscaping Extra Description: D/W LANDSCAPING PUSHBUTTON CONTRACT CNT# Cont. Class: District Let

Phase Fund Code FY 2024 5 Year Total P.E. DS $40,000 $40,000 Construction DS $999,900 $999,900 CEI DIH $156,651 $156,651 DS $201,091 $201,091 Total For Project 446444.1 $1,397,642 $1,397,642

FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total HIGHWAY SYSTEM: 03 Total $28,529,910 $35,032,450 $34,083,064 $32,521,363 $27,462,336 $157,629,123 HIGHWAY SYSTEM: 06 NON-INTRASTATE OFF STATE HIWAY

444825.1 DISTRICT 6 SCHOOL ZO NE IMPLEMENTATION PLAN PM: LU, JINYAN

Work Mix: Traffic Control Devices/System Extra Description: PH 93 = FUNDING OVER A 3YR PERIOD FOR PURCHASE OF SCHOOL ZONE TRAFFIC CONTROL DEVICES WHICH MEETS THE NEW MUTCD STANDARDS. Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 5 Year Total Capital Improvement/Operating RED $1,060,300 $1,060,300 $2,120,600 Total For Project 444825.1 $1,060,300 $1,060,300 $2,120,600

FY 2021 FY 2022 5 Year Total HIGHWAY SYSTEM: 06 Total $1,060,300 $1,060,300 $2,120,600 HIGHWAY SYSTEM: 08 TRANSIT

418051.3 MDT - DADE/MONROE EX PRESS BUS ROUTE FROM FL C ITY TO MARATHON (MM50) PM: FREEMAN, RAYMOND

Work Mix: Commuter Trans. Assistance Extra Description: MDT OPERATING ASSISTANCE FOR BUS ROUTE SERVING SOUTH MIAMI DADE COUNTY AND NORTHERN MONROE COUNTY. BUS ROUTE PROVIDES ACCESS TO EMPLOYMENT OPPORTUNITIES FOR MIAMI DADE COUNTY RESIDENTS IN MONROE COUNTY AND ACCESS TO TRANSIT FOR MONROE Cont. Class: Extern Mngd(Not Lap) COUNTY RESIDENTS. 50% STATE PARTICIPATION RATE

Phase Fund Code FY 2021 5 Year Total Capital Improvement/Operating DPTO $1,604,253 $1,604,253 LF $900,000 $900,000 Total For Project 418051.3 $2,504,253 $2,504,253

October. 10 2019 Page 32 of 51 HIGHWAY SYSTEM: 08 TRANSIT

418051.4 MDT - DADE/MONROE EX PRESS BUS SERVICE PM: FREEMAN, RAYMOND

Work Mix: Commuter Trans. Assistance Extra Description: MDT OPERATING ASSISTANCE FOR BUS ROUTE SERVING SOUTH MIAMI DADE COUNTY AND NORTHERN MONROE COUNTY. BUS ROUTE PROVIDES ACCESS TO EMPLOYMENT OPPORTUNITIES FOR MIAMI DADE COUNTY RESIDENTS IN MONROE COUNTY AND ACCESS TO TRANSIT FOR MONROE Cont. Class: Extern Mngd(Not Lap) COUNTY RESIDENTS. 50% STATE PARTICIPATION RATE

Phase Fund Code FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total Capital Improvement/Operating DPTO $900,000 $900,000 $900,000 $900,000 $3,600,000 LF $900,000 $900,000 $900,000 $900,000 $3,600,000 Total For Project 418051.4 $1,800,000 $1,800,000 $1,800,000 $1,800,000 $7,200,000

420452.3 SOUTH FLA COMMUTER S ERVICES DISTRICTWIDE TDM OUTREACH PM: FREEMAN, RAYMOND

Work Mix: Commuter Trans. Assistance Extra Description: SOUTH FLORIDA COMMUTER SERVICES - TRANSPORTATION DEMAND MANAGEMENT OUTREACH ACTIVITIES IN MIAMI-DADE AND MONROE. PARTICIPATION = 100% Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 5 Year Total Planning DPTO $75,000 $75,000 Total For Project 420452.3 $75,000 $75,000

422239.4 SOUTH FLA COMMUTER S ERVICES IN MIAMI-DADE COU NTY - OPERATIONS PM: FREEMAN, RAYMOND Work Mix: Commuter Trans. Assistance Extra Description: COMMUTER ASSISTANCE PROGRAM FUNDING FOR THE SOUTH FLORIDA COMMUTER SERVICES CONTRACT FOR D4/D6. FUNDING IS FOR OPERATIONS IN MIAMI DADE AND MONROE STATE PARTICIPATION RATE = 100% Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total Planning DDR $388,000 $592,396 $592,396 $592,396 $2,165,188 DPTO $472,475 $472,475 Total For Project 422239.4 $388,000 $472,475 $592,396 $592,396 $592,396 $2,637,663

422242.4 SOUTH FLORIDA COMMUT ER SERVICES - SOUTH FLORI DA VANPOOL MARKETING PM: FREEMAN, RAYMOND

Work Mix: Commuter Trans. Assistance Extra Description: CNT# BE581 Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total Planning SU $75,000 $75,000 $75,000 $75,000 $75,000 $375,000 Total For Project 422242.4 $75,000 $75,000 $75,000 $75,000 $75,000 $375,000

FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total HIGHWAY SYSTEM: 08 Total $3,042,253 $2,347,475 $2,467,396 $2,467,396 $2,467,396 $12,791,916 HIGHWAY SYSTEM: 13 NON-SYSTEM SPECIFIC

October. 10 2019 Page 33 of 51 HIGHWAY SYSTEM: 13 NON-SYSTEM SPECIFIC

249943.5 DISTRICTWIDE CONTAMI NATION ASSESSMENT & REMED IATION PM: GOMEZ, MAURICIO Work Mix: Environmental Test/Mitigate Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2025 5 Year Total P.E. DDR $200,000 $200,000 DIH $10,000 $10,000 Total For Project 249943.5 $210,000 $210,000

249943.6 DISTRICTWIDE CONTAMI NATION ASSESSMENT & REMED IATION PM: GOMEZ, MAURICIO

Work Mix: Environmental Test/Mitigate Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2025 5 Year Total P.E. DDR $200,000 $200,000 DIH $10,000 $10,000 Total For Project 249943.6 $210,000 $210,000

250115.6 DISTRICTWIDE ITS TEC HNICAL CONSULTANT CONTRAC T PM: BRAVO, SERGIO

Work Mix: Traffic Management Centers Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 5 Year Total P.E. DS $300,000 $100,000 $400,000 Total For Project 250115.6 $300,000 $100,000 $400,000

250604.3 DISTRICTWIDE COST RI SK ANALYSIS CONSULTANT PM: MASON, CALVIN

Work Mix: Preliminary Engineering Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2025 5 Year Total P.E. DIH $10,000 $10,000 DS $50,000 $50,000 Total For Project 250604.3 $60,000 $60,000

October. 10 2019 Page 34 of 51 HIGHWAY SYSTEM: 13 NON-SYSTEM SPECIFIC

250605.3 DISTRICTWIDE MISCEL LANEOUS PE DESIGN CONSULT ANT PM: WANG/PULIDO Work Mix: Preliminary Engineering Extra Description: PH32/01= CNT# /CONSULT: CH PEREZ PH32/02= CNT# /CONSULT: LOCHNER Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 5 Year Total P.E. DS $20,000 $20,000 Total For Project 250605.3 $20,000 $20,000

250605.4 DISTRICTWIDE MISCELL ANEOUS MINOR DESIGN CONSU LTANT PM: WANG/PULIDO Work Mix: Preliminary Engineering Extra Description: FOR BDI PROJECTS Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 5 Year Total P.E. DS $10,000 $10,000 Total For Project 250605.4 $10,000 $10,000

250621.2 D/W PROPERTY MGT. BY DIST. R/W ADMIN. PM: CASALS, ALEX

Work Mix: Right Of Way Activities Extra Description: 08/09 OPERATING BUDGET FUNDS REDUCE IN YEARS 2012 TO 2017 TO 477,870/ FUNDS TO 250621-4 FY18 INCREASED PER AT 18-028 TO $665 ADDING $45K FROM D7 TO D6 FOR GIS SERVICES/RWMS FACE LIFT) UNDER CNT C9J67 PER EMAIL DATED 9/1/17 FROM S. PEREZ/M. TIPTON Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total RW Support DS $620,000 $620,000 $620,000 $620,000 $620,000 $3,100,000 Total For Project 250621.2 $620,000 $620,000 $620,000 $620,000 $620,000 $3,100,000

250635.4 DISTRICTWIDE CULTURA L RESOURCE ASSESSMENT CON SULTANT PM: CULHANE/CONDELL

Work Mix: Environmental Test/Mitigate Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total PDE DIH $10,000 $10,000 $10,000 $10,000 $10,000 $50,000 DS $100,000 $400,000 $400,000 $400,000 $200,000 $1,500,000 Total For Project 250635.4 $110,000 $410,000 $410,000 $410,000 $210,000 $1,550,000

October. 10 2019 Page 35 of 51 HIGHWAY SYSTEM: 13 NON-SYSTEM SPECIFIC

250635.5 DISTRICTWIDE CULTURA L RESOURCE ASSESSMENT CON SULTANT PM: CULHANE/CONDELL Work Mix: Environmental Test/Mitigate Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 5 Year Total PDE DIH $10,000 $10,000 $10,000 $10,000 $40,000 DS $100,000 $400,000 $400,000 $400,000 $1,300,000 Total For Project 250635.5 $110,000 $410,000 $410,000 $410,000 $1,340,000

250635.6 DISTRICTWIDE CULTURA L RESOURCE ASSESSMENT CON SULTANT PM: CULHANE/CONDELL

Work Mix: Environmental Test/Mitigate Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2025 5 Year Total PDE DIH $10,000 $10,000 DS $100,000 $100,000 Total For Project 250635.6 $110,000 $110,000

250649.3 DISTRICTWIDE ENVIRON MENTAL PERMITS PM: DOMINGUEZ, MARIO

Work Mix: Environmental Permits Acq Extra Description: NOTE: FM CREATED FOR PAYMENT OF ENVIRONMENTAL PERMITS UTILIZING A PCARD CNT# C9846 Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total PDE DS $50,000 $50,000 $50,000 $50,000 $50,000 $250,000 Total For Project 250649.3 $50,000 $50,000 $50,000 $50,000 $50,000 $250,000

250673.3 DISTRICTWIDE PUBLIC INVOLVEMENT CONSULTANT PM: BURGHER, TISH

Work Mix: Preliminary Engineering Extra Description: NEW CONTRACT IN FY 13/14 (APRIL 2014) PHASE 32-01 = CONTRACT BDX85/INFINITE SOURCE COMMUNICATIONS CONTRACTS END NOVEMBER 1, 2017 PHASE 32-02 = CONTRACT BE413/INFINITE (6-28-17 TO 6-27-20) PHASE 32-03 = NEW CONTRACT IN FY 2020 Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total P.E. DIH $20,000 $50,000 $50,000 $120,000 DS $400,000 $400,000 $550,000 $400,000 $150,000 $1,900,000 Total For Project 250673.3 $420,000 $450,000 $600,000 $400,000 $150,000 $2,020,000

October. 10 2019 Page 36 of 51 HIGHWAY SYSTEM: 13 NON-SYSTEM SPECIFIC

250696.3 DISTRICTWIDE ROW PUB LIC RECORDS SEARCH PM: ALBURY, CRISTINA Work Mix: Preliminary Engineering Extra Description: CORELOGIC - SINGLE SOURCE Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total RW Support DS $2,000 $2,000 $2,000 $2,000 $2,000 $10,000 Total For Project 250696.3 $2,000 $2,000 $2,000 $2,000 $2,000 $10,000

250696.5 DISTRICTWIDE MISC. L OCATION SURVEY CONSULTANT PM: MARRERO, VICTOR Work Mix: Preliminary Engineering Extra Description: PHASE 32-01 = CONTRACT C9698 (C.H. PEREZ) PHASE 32-02 = CONTRACT C9C43 (MANUEL G. VERA) PHASE 32-03 = CONTRACT C9C44 (CSA CENTRAL) PHASE 32-04 = CONTRACT /CONSULT: KEITH & ASSOC. PHASE 32-05 = CONTRACT C9Z25/CONSULT: BISCAYNE Cont. Class: Misc - No Letting

Phase Fund Code FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total P.E. DS $1,050,000 $1,050,000 $700,000 $700,000 $3,500,000 Total For Project 250696.5 $1,050,000 $1,050,000 $700,000 $700,000 $3,500,000

250696.6 DISTRICTWIDE ROW MAP PING & SURVEY PM: ALBURY, CRISTINA

Work Mix: Preliminary Engineering Extra Description: PHASE 32-01 = CONTRACT C9J19 (MASER) PHASE 32-02 = CONTRACT C9M04 (BISCAYNE) PHASE 32-03 = CONTRACT C9M05 (MANUEL VERA) Cont. Class: Misc - No Letting

Phase Fund Code FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total P.E. DS $1,050,000 $1,050,000 $600,000 $750,000 $3,450,000 Total For Project 250696.6 $1,050,000 $1,050,000 $600,000 $750,000 $3,450,000

250747.3 D/W DESIGN OFFICE EN GINEERING SUPPORT SERVICE S PM: ALBURY, TIM

Work Mix: Geographic Info. Systems Extra Description: OPERATING ASSISTANCE (PGM IS) CONSOLIDATION OF FM 250747-2-32-01 ($125,611), 250747-2-32-02 ($115,883) AND 413221-2-32-02 ($231K) TO TOTAL $472,494 EA FY. Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total P.E. DS $472,494 $472,494 $472,494 $472,494 $236,247 $2,126,223 Total For Project 250747.3 $472,494 $472,494 $472,494 $472,494 $236,247 $2,126,223

October. 10 2019 Page 37 of 51 HIGHWAY SYSTEM: 13 NON-SYSTEM SPECIFIC

250747.4 D/W DESIGN OFFICE EN GINEERING SUPPORT SERVICE S PM: ALBURY, TIM Work Mix: Geographic Info. Systems Extra Description: OPERATING ASSISTANCE (PGM IS) CONSOLIDATION OF FM 250747-2-32-01 ($125,611), 250747-2-32-02 ($115,883) AND 413221-2-32-02 ($231K) TO TOTAL $472,494 EA FY. Cont. Class: Misc - No Letting

Phase Fund Code FY 2025 5 Year Total P.E. DS $236,247 $236,247 Total For Project 250747.4 $236,247 $236,247

250753.2 DISTRICTWIDE OPERATI ONS DIVISION SUPPORT/OPER . BUDGET PM: ESPINO, BARBARA Work Mix: Funding Action Extra Description: OPERATING BUDGT FOR EDMS SCANNING SUPPORT/OPERATIONS SUPPORT PHASE 62-02 FOR TIM ALBURY GIS APPROVED BY DISTRICT CONST. SEE EMAIL BARBARA ESPINO PEREZ 7-23-14 Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 5 Year Total CEI D $47,058 $47,058 DS $47,058 $47,058 $47,058 $141,174 Total For Project 250753.2 $47,058 $47,058 $47,058 $47,058 $188,232

250759.3 DISTRICTWIDE RESURFA CING SCOPING REPORTS PM: MASON, CALVIN Work Mix: Pd&E/Emo Study Extra Description: PD & E PH 22-01 = CONSULT: ALEMAN /CNT# C9D86 EXE: 1/22/2014 PH 22-02 = CONSULT: HDR ENGINEERING /CNT# C9U47 EXEC:5/2/17 PH 22-03 = CONSULT: GOAL ASSOC./CNT# CA354 EXEC: 3/27/19 NOTE: BDI CONTRACT PER LEIGH,APPR. BY ANGELA MATIYOW 1-11-18 Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total PDE DIH $50,000 $50,000 $50,000 $50,000 $50,000 $250,000 DS $800,000 $800,000 $950,000 $650,000 $900,000 $4,100,000 Total For Project 250759.3 $850,000 $850,000 $1,000,000 $700,000 $950,000 $4,350,000

252071.1 TRANSPORTATION STATI STICS SUPPORT #1 PM: LEON, PAOLA

Work Mix: Transportation Statistics Extra Description: DESIGN TRAFFIC DATA COLLECTION CNT# C7640 ROADWAY & TRAFFIC CHARACTERISTICS INVENTORY. SEQ 01 = C3875/TRANSPORT ANALYSIS/C6652/FR ALEMAN/ C7640/TRANSPORT ANALYSIS/C8B59/URS/C8133/CROSSROADS SEQ 02= C4223/DAVID PLUMMER Cont. Class: Misc - No Letting & ASSOC./C5638/TRANSPORT ANALYSIS/C6269/FR ALEMAN/C6652/FR ALEMAN ***SEE WP45***

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total Planning D $500,000 $500,000 $422,000 $500,000 $500,000 $2,422,000 Total For Project 252071.1 $500,000 $500,000 $422,000 $500,000 $500,000 $2,422,000

October. 10 2019 Page 38 of 51 HIGHWAY SYSTEM: 13 NON-SYSTEM SPECIFIC

403487.1 HPR PROGRAM TRANSPOR TATION PLANNING ACTIVITIE S PM: HUYNH, DAT Work Mix: Transportation Planning Extra Description: FPS#1=CORR.STDY. FIHS MASTER PLANS/ACTION PLANS FPS#2=GROWTH MANAGEMENT COMPREHENSIVE PL REVIEW FPS#3=ARTL.CORR.STDY.MODAL SYSTEMS PLANNING CONTRACT#BDC70 FPS#4=WRK PRGM/TIP DEV-EXPWY/HOV PL.&ANALYSIS I-95/I-75 Cont. Class: Misc - No Letting CORR FPS#5=PLANNING SUPPORT/FPS#6=SYSTEMS PL.MODEL PL DEV FPS#7=MPO SUPPORT/FPS#8=AIR QU.BIKE/PED,LOS,SCEN HWY

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total Planning D $49,431 $64,877 $67,748 $72,000 $76,654 $330,710 HP $1,032,504 $1,031,480 $1,103,940 $1,064,000 $1,080,000 $5,311,924 Total For Project 403487.1 $1,081,935 $1,096,357 $1,171,688 $1,136,000 $1,156,654 $5,642,634

403488.1 HPR PROGRAM DATA COL LECTION ACTIVITIES PM: HUYNH, DAT Work Mix: Transportation Statistics Extra Description: FPS#1=DESIGN TRAF DATA COLL./RDWY & TRAFFIC CHARC INVENTORY FPS#2=CONSULTANT SUPPORT FPS#3=RAIL HWY CROSSING INVENTORY FPS#4=MAPPING/FPS#5=VEHICLE CLASSIFICATION/FPS#6=HWY CLASSIF FPS#7=DESIGN TRAF FORECAST/FPS#8=DATA Cont. Class: Misc - No Letting ANALYSIS,RDWY CLASS, FPS#8=DATA ANALYSIS, ROADWAY CLASS,PAVEMENT MAN,TELEMETRY SY

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total Planning D $19,595 $28,199 $22,595 $23,960 $23,960 $118,309 HP $440,130 $499,478 $388,274 $390,000 $400,000 $2,117,882 Total For Project 403488.1 $459,725 $527,677 $410,869 $413,960 $423,960 $2,236,191

403489.1 HPR PROGRAM SYSTEMS PLANNING ACTIVITIES PM: HUYNH, DAT

Work Mix: Transportation Planning Extra Description: FPS#1=BIKE/PED PLANNING - CONSULTANT SUPPORT FPS#2=PAVEMENT SURVEY - SPECIAL SURVEYS FPS#3=SCENIC HWY COORDINATION Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total Planning D $53,904 $37,200 $47,427 $49,453 $52,595 $240,579 HP $573,863 $552,326 $622,722 $655,060 $671,242 $3,075,213 Total For Project 403489.1 $627,767 $589,526 $670,149 $704,513 $723,837 $3,315,792

407347.3 DISTRICTWIDE COMMUNI CATION PROGRAMS & SPECIAL PROJECTS PM: BURGHER, TISH Work Mix: Transportation Planning Extra Description: TRAFFIC OPS TO SUPPORT ALL TRAFFIC IMPROVEMENT PROJECTS FOR FY 20/21. Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 5 Year Total P.E. DIH $5,000 $5,000 DS $300,000 $300,000 Total For Project 407347.3 $305,000 $305,000

October. 10 2019 Page 39 of 51 HIGHWAY SYSTEM: 13 NON-SYSTEM SPECIFIC

407347.4 DISTRICTWIDE COMMUNI CATION PROGRAMS & SPECIAL PROJECTS PM: BURGHER, TISH Work Mix: Transportation Planning Extra Description: TRAFFIC OPS TO SUPPORT ALL TRAFFIC IMPROVEMENT PROJECTS FOR FY 21/22. Cont. Class: Misc - No Letting

Phase Fund Code FY 2022 FY 2023 FY 2024 5 Year Total P.E. DIH $5,000 $5,000 $5,000 $15,000 DS $350,000 $350,000 $350,000 $1,050,000 Total For Project 407347.4 $355,000 $355,000 $355,000 $1,065,000

407347.5 DISTRICTWIDE COMMUNI CATION PROGRAMS & SPECIAL PROJECTS PM: BURGHER, TISH

Work Mix: Transportation Planning Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2025 5 Year Total P.E. DIH $5,000 $5,000 DS $350,000 $350,000 Total For Project 407347.5 $355,000 $355,000

408199.1 TRANSPORTATION STATI STICS SUPPORT #3 PM: LYN, NEIL

Work Mix: Urban Corridor Improvements Extra Description: SEQ 01 = CNT# C7721/PARSONS/C8J88/BURN & MCDONNELL SEQ 02 = CNT# C8T89/FTE SEQ 03 = CNT# C9617/CALTRAN SEQ 04 = CNT# C9J86/CTS ENGINEERING INC SEQ 05 = Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total Planning D $422,200 $350,000 $350,000 $500,818 $442,857 $2,065,875 Total For Project 408199.1 $422,200 $350,000 $350,000 $500,818 $442,857 $2,065,875

413221.1 TRANSPORTATION SYSTE MS GIS DATA DEVELOPMENT A ND MAPPING PM: LEON, PAOLA

Work Mix: Transportation Statistics Extra Description: GIS APPLICATIONS FOR MAPPING PRODUCE GRAPHICS FOR SLDS, FUNCTIONAL CLASS, WORK PROGRAM AND OTHERS. PH 12-01 = CNT:C8D22/CONSULT: BURNS & MCDONNELL PH 12-01 = CNT:C8383/CONSULT: F.R. ALEMAN PH 12-02 = CNT C8O60/CONSULT: MARLIN Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total Planning D $400,000 $500,000 $420,857 $500,000 $500,000 $2,320,857 Total For Project 413221.1 $400,000 $500,000 $420,857 $500,000 $500,000 $2,320,857

October. 10 2019 Page 40 of 51 HIGHWAY SYSTEM: 13 NON-SYSTEM SPECIFIC

414753.3 DISTRICTWIDE TRAFFIC STUDIES - FIU PM: HERNANDEZ, ISABEL Work Mix: Traffic Engineering Study Extra Description: THIS SEGMENT A BREAKOUT FROM 414753-1-32-02 Cont. Class: Misc - No Letting

Phase Fund Code FY 2022 FY 2023 5 Year Total P.E. DITS $500,000 $500,000 $1,000,000 DS $265,000 $265,000 Total For Project 414753.3 $765,000 $500,000 $1,265,000

414753.4 DISTRICTWIDE TRAFFIC STUDIES - FIU PM: CARRERO-VILA, RODNEY

Work Mix: Traffic Engineering Study Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total P.E. DS $260,000 $210,000 $210,000 $210,000 $210,000 $1,100,000 Total For Project 414753.4 $260,000 $210,000 $210,000 $210,000 $210,000 $1,100,000

421053.3 DISTRICTWIDE INTERMO DAL SYSTEMS PLANNING PM: YEE FONG, SHEREEN Work Mix: Transportation Planning Extra Description: $100K SEQ 02 FY18 = FOR WK RELATED TO AMERICAN DREAM MALL INCLUDING THE SIMR,PD&E RE-EVAL. & REVIEWS PER K. JEFFRIES &L. CANN EMAIL 8/8/17. CNT# C9A19 CONSULT: RS&H Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 5 Year Total Planning D $415,714 $500,000 $500,000 $1,415,714 Total For Project 421053.3 $415,714 $500,000 $500,000 $1,415,714

421053.4 DISTRICTWIDE COMPLET E STREETS CONTRACT PM: GEHRKE, TIFFANY

Work Mix: Transportation Planning Extra Description: PH12-01/CNT# C9095 PH11/FM 442671-1 FOR TRACKING OF IN-HOUSE HOURS Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total Planning D $450,000 $500,000 $500,000 $400,000 $500,000 $2,350,000 Total For Project 421053.4 $450,000 $500,000 $500,000 $400,000 $500,000 $2,350,000

October. 10 2019 Page 41 of 51 HIGHWAY SYSTEM: 13 NON-SYSTEM SPECIFIC

421053.5 DISTRICTWIDE SYSTEMS PLANNING PM: YEE FONG, SHEREEN Work Mix: Transportation Planning Extra Description: CONTINUATION OF 421053-3 Cont. Class: Misc - No Letting

Phase Fund Code FY 2024 FY 2025 5 Year Total Planning D $500,000 $500,000 $1,000,000 Total For Project 421053.5 $500,000 $500,000 $1,000,000

421054.1 DISTRICTWIDE GENERAL PLANNING CONSULTANT PM: JEFFRIES, KEN Work Mix: Transportation Planning Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 5 Year Total Planning D $477,143 $117,857 $400,000 $192,039 $1,187,039 Total For Project 421054.1 $477,143 $117,857 $400,000 $192,039 $1,187,039

421054.2 DISTRICTWIDE GENERAL PLANNING CONSULTANT PM: JEFFRIES, KEN

Work Mix: Transportation Planning Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2024 FY 2025 5 Year Total Planning D $200,000 $300,000 $500,000 Total For Project 421054.2 $200,000 $300,000 $500,000

425144.2 DISTRICTWIDE GENERAL CONSULTANT ENGINEERING S ERVICES CONTRACT #1 PM: ALBURY, TIM

Work Mix: Preliminary Engineering Extra Description: PHASE 32-01 = CONTRACT #C9J67/HDR (GEC) (5-15-15 TO 5-14-20) PHASE 32-02 = CONTRACT# C9J67/NEW CNT PHASE 32-03 = CONTRACT #C9J67/HDR (GEC) PHASE 62-01 = CONTRACT C9J67 FOR CONSTRUCTION SUPPORT TASK Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total P.E. DIH $15,000 $15,000 $15,000 $15,000 $15,000 $75,000 Total For Project 425144.2 $15,000 $15,000 $15,000 $15,000 $15,000 $75,000

October. 10 2019 Page 42 of 51 HIGHWAY SYSTEM: 13 NON-SYSTEM SPECIFIC

425144.3 DISTRICTWIDE GENERAL CONSULTANT ENGINEERING S ERVICES CONTRACT #2 PM: ALBURY, TIM Work Mix: Preliminary Engineering Extra Description: PH32-01 = CONTRACT C9J68/AECOM/ 4D DEVELOPMENT OF GGI MOT MASTER PLAN PH32-02 = GEC SUPPORT FOR PAVEMENT DESIGN REVIEWS Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total P.E. DIH $15,000 $15,000 $15,000 $15,000 $15,000 $75,000 Total For Project 425144.3 $15,000 $15,000 $15,000 $15,000 $15,000 $75,000

425144.4 DISTRICTWIDE GENERAL CONSULTANT ENGINEERING S ERVICES CONTRACT #1 PM: ALBURY, TIM Work Mix: Preliminary Engineering Extra Description: PREVIOUS CONTRACT UNDER 425144-2-32-01: #C9J67/HDR (GEC) Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total P.E. DIH $15,000 $15,000 $15,000 $15,000 $15,000 $75,000 DS $2,400,000 $2,400,000 $2,400,000 $2,400,000 $9,600,000 Total For Project 425144.4 $2,415,000 $15,000 $2,415,000 $2,415,000 $2,415,000 $9,675,000

425144.5 DISTRICTWIDE GENERAL CONSULTANT ENGINEERING S ERVICES CONTRACT #2 PM: ALBURY, TIM Work Mix: Preliminary Engineering Extra Description: PREVIOUS CONTRACT UNDER 425144-3-32-01: #C9J68/AECOM (GEC) Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total P.E. DIH $15,000 $15,000 $15,000 $15,000 $15,000 $75,000 DS $2,400,000 $2,400,000 $2,400,000 $2,400,000 $9,600,000 Total For Project 425144.5 $2,415,000 $15,000 $2,415,000 $2,415,000 $2,415,000 $9,675,000

428345.4 D/W NPDES PUSH BUTTO N DRAINAGE & TECH CONSULT SERVICE PM: DOMINGUEZ, MARIO

Work Mix: Drainage Improvements Extra Description: NOTE: GEC CAN'T BE UTILIZED FOR PH72. Cont. Class: District Let

Phase Fund Code FY 2021 FY 2022 5 Year Total P.E. DS $200,000 $200,000 $400,000 Total For Project 428345.4 $200,000 $200,000 $400,000

October. 10 2019 Page 43 of 51 HIGHWAY SYSTEM: 13 NON-SYSTEM SPECIFIC

428345.5 DISTRICTWIDE NPDES PUSHBUTTON DRAINAGE & TEC H CONSULTANT SERVICES PM: DOMINGUEZ, MARIO Work Mix: Drainage Improvements Extra Description: NOTE: GEC CAN'T BE UTILIZED FOR PH72 Cont. Class: District Let

Phase Fund Code FY 2023 FY 2024 FY 2025 5 Year Total P.E. DS $200,000 $200,000 $200,000 $600,000 Total For Project 428345.5 $200,000 $200,000 $200,000 $600,000

431868.1 DISTRICTWIDE PUBLIC INFORMATION SERVICES ON D IST 6 CONSTRUCTION PROJS PM: MCLENDON, KATHY Work Mix: Public Information/Education Extra Description: FY13 FUNDS # $ 350K DS MOVED FROM 40830216202. # BDW10 Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total CEI DIH $5,000 $5,000 $5,000 $5,000 $5,000 $25,000 DS $400,000 $300,000 $300,000 $350,000 $400,000 $1,750,000 Total For Project 431868.1 $405,000 $305,000 $305,000 $355,000 $405,000 $1,775,000

431868.2 DISTRICTWIDE PUBLIC INFORMATION SERVICES ON D IST 6 CONSTRUCTION PROJS PM: MCLENDON, KATHY Work Mix: Public Information/Education Extra Description: CONTRACT # BDW11 PH62-03 CNT# TBD /CNSLT: TBA PH62-02 CNT# TBD /CNSLT: TBA Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total CEI DIH $20,000 $20,000 $20,000 $20,000 $20,000 $100,000 DS $350,000 $300,000 $300,000 $250,000 $350,000 $1,550,000 Total For Project 431868.2 $370,000 $320,000 $320,000 $270,000 $370,000 $1,650,000

431868.3 DISTRICTWIDE PUBLIC COMMUNICATION SERVICES FO R MISC CONSTRUCTION PROJS PM: MCLENDON, KATHY

Work Mix: Public Information/Education Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total CEI DIH $20,000 $20,000 $20,000 $20,000 $20,000 $100,000 DS $200,000 $300,000 $300,000 $300,000 $300,000 $1,400,000 Total For Project 431868.3 $220,000 $320,000 $320,000 $320,000 $320,000 $1,500,000

October. 10 2019 Page 44 of 51 HIGHWAY SYSTEM: 13 NON-SYSTEM SPECIFIC

432451.3 DISTRICTWIDE AVIATIO N/SEAPORT CONSULTANT SERV ICES PM: CAYUBIT, SUNSHINE Work Mix: Pto Studies Extra Description: REPLACEMENT OF CONTRACT C-9T67 Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total Planning D $150,000 $150,000 $150,000 $150,000 $350,000 $950,000 Total For Project 432451.3 $150,000 $150,000 $150,000 $150,000 $350,000 $950,000

432451.4 DISTRICTWIDE MODAL D EVELOPMENT CONSULTANT SER VICES PM: RICHARDSON, DIONNE Work Mix: Pto Studies Extra Description: REPLACEMENT OF CONTRACT C-9I19 Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 5 Year Total Planning D $100,000 $100,000 $100,000 $300,000 Total For Project 432451.4 $100,000 $100,000 $100,000 $300,000

432793.1 DISTRICTWIDE LOCATIO N SURVEY SUPPORT PM: MARRERO, VICTOR

Work Mix: Preliminary Engineering Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total P.E. DIH $300,000 $300,000 $300,000 $300,000 $300,000 $1,500,000 Total For Project 432793.1 $300,000 $300,000 $300,000 $300,000 $300,000 $1,500,000

433056.3 DISTRICTWIDE MODAL T RANSIT CONSULTANT SERVICE S PM: FREEMAN, RAYMOND

Work Mix: Pto Studies Extra Description: PH12-01 = CNT# CA243/CONSULT: MARLIN Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total Planning D $150,000 $150,000 $150,000 $150,000 $150,000 $750,000 Total For Project 433056.3 $150,000 $150,000 $150,000 $150,000 $150,000 $750,000

October. 10 2019 Page 45 of 51 HIGHWAY SYSTEM: 13 NON-SYSTEM SPECIFIC

433056.4 DISTRICTWIDE MODAL R AIL CONSULTANT SERVICES PM: QUERO, ANA Work Mix: Pto Studies Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total Planning D $150,000 $150,000 $150,000 $150,000 $150,000 $750,000 Total For Project 433056.4 $150,000 $150,000 $150,000 $150,000 $150,000 $750,000

433891.3 TRANSPORTATION RESIL IENCE PM: JUNGMAN, ANDREW Work Mix: Corridor/Subarea Planning Extra Description: D6 ASSIGNMENT FOR TRACKING THE ALLOCATION OF RESOURCES FOR STAFF TIME IN CONJUNCTIONS W/ FHWA PILOT GRANT AWARDED TO THE BROWARD MPO IN COORDINATION W/THE MIAMI DADE MPO AND THE PALM BEACH MPO TO CONDUCT THE SOUTH FLORIDA CLIMATE AND Cont. Class: Misc - No Letting EXTREME WEATHER VULNERABILITY ASSESSMENT AND ADAPTATION PILOT PROJECT.

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total PDE DDR $50,000 $25,000 $25,000 $25,000 $25,000 $150,000 DIH $10,000 $10,000 $10,000 $10,000 $10,000 $50,000 Total For Project 433891.3 $60,000 $35,000 $35,000 $35,000 $35,000 $200,000

434665.1 ITS OPERATIONS CONSU LTANTS PM: MOTTA, ALEJANDRO

Work Mix: Traffic Management Centers Extra Description: NEW PROJECT MOVED FROM 417740.1.82.03 FOR NEW CONTRACT AND NEW PROJECT LIFE-SPAN PER EMAIL A. FERNANDEZ 072913 Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total Capital Improvement/Operating DITS $2,986,961 $3,061,489 $3,144,169 $3,321,550 $3,417,307 $15,931,476 DSBD $886,956 $909,088 $933,639 $959,573 $987,236 $4,676,492 Total For Project 434665.1 $3,873,917 $3,970,577 $4,077,808 $4,281,123 $4,404,543 $20,607,968

434673.1 DISTRICTWIDE NOISE A ND AIR QUALITY ASSESSMENT S PM: MCMULLEN, ROBERT Work Mix: Pd&E/Emo Study Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 5 Year Total PDE DIH $20,000 $20,000 $20,000 $20,000 $80,000 DS $250,000 $250,000 $250,000 $170,000 $920,000 Total For Project 434673.1 $270,000 $270,000 $270,000 $190,000 $1,000,000

October. 10 2019 Page 46 of 51 HIGHWAY SYSTEM: 13 NON-SYSTEM SPECIFIC

434673.2 DISTRICTWIDE NOISE A ND AIR QUALITY ASSESSMENT S PM: MCMULLEN, ROBERT Work Mix: Pd&E/Emo Study Extra Description: CONTRACT #1 REPLACES 434673-1-22-02 Cont. Class: Misc - No Letting

Phase Fund Code FY 2024 FY 2025 5 Year Total PDE DIH $10,000 $10,000 $20,000 DS $50,000 $125,000 $175,000 Total For Project 434673.2 $60,000 $135,000 $195,000

434673.3 DISTRICTWIDE NOISE A ND AIR QUALITY ASSESSMENT S PM: MCMULLEN, ROBERT

Work Mix: Pd&E/Emo Study Extra Description: CONTRACT #2 REPLACES 434673-1-22-03 Cont. Class: Misc - No Letting

Phase Fund Code FY 2024 FY 2025 5 Year Total PDE DIH $10,000 $10,000 $20,000 DS $50,000 $125,000 $175,000 Total For Project 434673.3 $60,000 $135,000 $195,000

435140.2 DISTRICTWIDE FREIGHT CONSULTANT SERVICES PM: CASTRO, CARLOS

Work Mix: Pto Studies Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 5 Year Total Planning D $150,000 $150,000 $150,000 $150,000 $600,000 Total For Project 435140.2 $150,000 $150,000 $150,000 $150,000 $600,000

435140.3 MODAL INSPECTIONS CO NSULTANT SERVICES PM: CARTAYA, NILIA

Work Mix: Pto Studies Extra Description: PH12-01 = CNT#CA293/CONSULT: RENAISSANCE PH12-02 = CNT#CA293/CONSULT: TINDALE-OLIVER Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 5 Year Total Planning D $927,800 $500,000 $500,000 $1,927,800 DS $72,200 $500,000 $500,000 $1,072,200 Total For Project 435140.3 $1,000,000 $1,000,000 $1,000,000 $3,000,000

October. 10 2019 Page 47 of 51 HIGHWAY SYSTEM: 13 NON-SYSTEM SPECIFIC

435140.4 MODAL INSPECTIONS CO NSULTANT SERVICES PM: CARTAYA, NILIA Work Mix: Pto Studies Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2024 FY 2025 5 Year Total Planning D $500,000 $500,000 $1,000,000 Total For Project 435140.4 $500,000 $500,000 $1,000,000

435140.5 DISTRICTWIDE FREIGHT CONSULTANT SERVICES PM: CASTRO, CARLOS Work Mix: Pto Studies Extra Description: CONTINUATION OF 435140-2-12-01 CNT# ; CONSULTANT: Cont. Class: Misc - No Letting

Phase Fund Code FY 2025 5 Year Total Planning D $150,000 $150,000 Total For Project 435140.5 $150,000 $150,000

435755.1 DISTRICTWIDE CONGEST ED CORRIDOR MASTER PLAN PM: JEFFRIES, KEN

Work Mix: Transportation Planning Extra Description: PLANNING STUDY TO EVALUATE CONGESTED CORRIDORS IN BOTH MIAMI-DADE AND MONROE COUNTIES. Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 5 Year Total Planning D $300,000 $300,000 $300,000 $300,000 $1,200,000 Total For Project 435755.1 $300,000 $300,000 $300,000 $300,000 $1,200,000

439031.2 TRAFFIC OPERATIONS C ONSULTANT SUPPORT SERVICE S PM: MOTTA, ALEJANDRO

Work Mix: Funding Action Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 5 Year Total Capital Improvement/Operating DS $497,131 $497,131 Total For Project 439031.2 $497,131 $497,131

October. 10 2019 Page 48 of 51 HIGHWAY SYSTEM: 13 NON-SYSTEM SPECIFIC

439031.3 TRAFFIC OPERATIONS C ONSULTANT SUPPORT SERVICE S PM: MOTTA, ALEJANDRO Work Mix: Funding Action Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total Capital Improvement/Operating DS $497,131 $497,131 $497,131 $497,131 $1,988,524 Total For Project 439031.3 $497,131 $497,131 $497,131 $497,131 $1,988,524

444626.1 REGIONAL PLANNING CO UNCIL SUPPORT PM: YEE FONG, SHEREEN Work Mix: Transportation Planning Extra Description: JPA WITH THE REGIONAL PLANNING COUNCIL GENERAL PLANNING SUPPORT FOR VARIOUS PLANNING ACTIVITIES Cont. Class: Extern Mngd(Not Lap)

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total Planning DS $50,000 $50,000 $50,000 $50,000 $50,000 $250,000 Total For Project 444626.1 $50,000 $50,000 $50,000 $50,000 $50,000 $250,000

445680.1 TRAFFIC OPERATIONS E NGINEERING CONSULTANT SUP PORT PM: SIERRA, RAMON

Work Mix: Preliminary Engineering Extra Description: Cont. Class: Misc - No Letting

Phase Fund Code FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total P.E. DDR $210,000 $210,000 DS $210,000 $210,000 $210,000 $210,000 $840,000 Total For Project 445680.1 $210,000 $210,000 $210,000 $210,000 $210,000 $1,050,000

FY 2021 FY 2022 FY 2023 FY 2024 FY 2025 5 Year Total HIGHWAY SYSTEM: 13 Total $21,727,084 $20,060,677 $25,067,054 $23,112,136 $23,328,476 $113,295,427

October. 10 2019 Page 49 of 51 HIGHWAY SYSTEM: 15 MULTIMODAL FACILITY

438822.1 DISTRICTWIDE FREIGHT MOBILITY OPTIMIZATION ST UDY PM: CASTRO, CARLOS

Work Mix: Pto Studies Extra Description: PLANNING LEVEL STUDY TO ASSESS STRATEGIES FOR OPTIMIZING FREIGHT MOBILITY WITHIN THE DISTRICT. POTENTIAL STRATEGIES TO CONSIDER MAY INCLUDE TRUCK WAYFINDING SIGNAGE, TRUCK PARKING, INTERSECTION SIGNAL TIMING, INTERSECTION GEOMETRY AND FREIGHT Cont. Class: Studies ROUTE DESIGNATIONS.

Phase Fund Code FY 2024 5 Year Total PDE DIH $55,000 $55,000 DS $300,000 $300,000 Total For Project 438822.1 $355,000 $355,000

FY 2024 5 Year Total HIGHWAY SYSTEM: 15 Total $355,000 $355,000 Districtwide Total $54,484,547 $58,625,902 $61,742,514 $58,580,895 $53,383,208 $286,817,066

October. 10 2019 Page 50 of 51 Total Total 5 Year Program: $286,817,066

Glossary of Terms and Accronyms

Box Funds for supplementals, overruns, litigation, AC conversions Capital Improvement / Capital Improvements and/or Operating Costs Operating CEI Construction Engineering Inspection Design Build Includes all phases, let as one contract for PE, Construction. Let in the District District Contract Contracts let in the District Extern Mngd (Not LAP) Joint Particiapation Agreement - Interagency method to exchange funds FM # Financial Management Number, aka Financial Project ID Force Account Force account / external JPA Joint Particiapation Agreement - Interagency method to exchange funds Local Agcy Pgm (LAP) Local Agency Program - Interagency method to exchange funds PD&E Project Development and Environmental (studies) PE Preliminary Engineering PTO Public Transportation R/W Right of Way ROW Right of Way ROW Adv. Acq. Advanced Acquisition of Right of Way only. SA Supplemental Agreement To Be Let Contract let in Tallahassee

October. 10 2019 Page 51 of 51