A6120 Outer Ring Improvements Roundhay Park

Sub-carriageway ducts to be installed off-peak under single lane closures. Wherever possible, where multiple ducts e.g.. lighting and UTMC cross adjacent these will be installed under the same closure , in a combined trench where possible or by separate resources when there is sufficient safe ty zone between them. Main drainage crossings also installed – Not shown for clarity

Drawing Title Notes UTMC duct crossing Drawing Number E17015/SK/PH-1B/1 Rev 0 Outline Phasing Plan Enabling Works – Off peak Street lighting duct crossing Issue Date 01/10/2018 NPG Diversion duct crossing Drawn By Rob Evans

A6120 Outer Ring Road Improvements Roundhay Park Lane

Pedestrian route to be maintained Pedestrian route to be maintained by constructing verge half and half. by constructing verge half and half. Pedestrian route diverted into Pedestrian route diverted into carriageway within TM off-peak carriageway within TM off-peak when works dictate access is when works dictate access is required to full width of verge. required to full width of verge.

Pedestrian routes to be maintained on existing footway which is to be re-surfaced only. Pedestrian route to be moved on to carriageway within TM off-peak to facilitate surfacing operations.

Drawing Title Key Under Construction TM Limit Drawing Number E17015/SK/PH-1B/2 Rev 0 Outline Phasing Plan Stage 1 – – Peak Time Arrangement Completed Movement Issue Date 01/10/2018 Temporary Surfacing Pedestrian Route Drawn By Rob Evans A6120 Outer Ring Road Improvements Roundhay Park Lane

Pedestrian route to be maintained Pedestrian route to be maintained by constructing verge half and half. by constructing verge half and half. Pedestrian route diverted into Pedestrian route diverted into carriageway within TM off-peak carriageway within TM off-peak when works dictate access is when works dictate access is required to full width of verge. required to full width of verge.

Traffic heading north up Harrogate Road wishing to turn south down A61 Scott Hall Road will be diverted around .

Drawing Title Key Under Construction TM Limit Drawing Number E17015/SK/PH-1B/3 Rev 0 Outline Phasing Plan Stage 1 – – Off-Peak Typical Arrangement Completed Traffic Movement Issue Date 01/10/2018 Temporary Surfacing Pedestrian Route Drawn By Rob Evans A6120 Outer Ring Road Improvements Roundhay Park Lane

Pedestrian route to be maintained by constructing verge half and half. Pedestrian route diverted into Pedestrian route to be maintained by carriageway within TM off-peak constructing verge half and half where when works dictate access is there is full depth construction. Overlay required to full width of verge. Pedestrian route to be maintained areas to be constructed off-peak. by constructing new route prior to Pedestrian route diverted into removal of existing route carriageway within TM off-peak when works dictate access is required to full width of verge.

Pedestrian route to be maintained Pedestrian route to be maintained by constructing verge half and half. by constructing verge half and half. Pedestrian route diverted into Pedestrian route diverted into carriageway within TM off-peak carriageway within TM off-peak when works dictate access is when works dictate access is required to full width of verge. required to full width of verge.

Drawing Title Key Under Construction TM Limit Drawing Number E17015/SK/PH-1B/4 Rev 0 Outline Phasing Plan Stage 2 – – Peak Time Arrangement Completed Traffic Movement Issue Date 01/10/2018 Temporary Surfacing Pedestrian Route Drawn By Rob Evans A6120 Outer Ring Road Improvements Roundhay Park Lane

Pedestrian route to be maintained by constructing verge half and half. Pedestrian route diverted into Pedestrian route to be maintained by carriageway within TM off-peak constructing verge half and half where when works dictate access is there is full depth construction. Overlay required to full width of verge. Pedestrian route to be maintained areas to be constructed off-peak. by constructing new route prior to Pedestrian route diverted into removal of existing route carriageway within TM off-peak when works dictate access is required to full width of verge.

Sand Hill Lane is a one-way street. Access to be maintained during tie-in works. Pedestrian route to be maintained Pedestrian route to be maintained by constructing verge half and half. by constructing verge half and half. Pedestrian route diverted into Pedestrian route diverted into carriageway within TM off-peak carriageway within TM off-peak when works dictate access is when works dictate access is required to full width of verge. required to full width of verge.

Drawing Title Key Under Construction TM Limit Drawing Number E17015/SK/PH-1B/5 Rev 0 Outline Phasing Plan Stage 2 – – Off-Peak Typical Arrangement Completed Traffic Movement Issue Date 01/10/2018 Temporary Surfacing Pedestrian Route Drawn By Rob Evans A6120 Outer Ring Road Improvements Roundhay Park Lane

Pedestrian route to be maintained by constructing verge half and half where there is full depth construction. Overlay areas to be constructed off-peak. Pedestrian route diverted into Pedestrian route to be maintained carriageway within TM off-peak when by constructing verge half and half. works dictate access is required to full Signalised pedestrian route Pedestrian route diverted into width of verge. to be maintained using carriageway within TM off-peak Pedestrian route to be maintained either new signals or when works dictate access is by constructing new route prior to temporary signal set. required to full width of verge. removal of existing route

South roundabout will be operating on new traffic signal controller prior to commencing build out in Harrogate Road. Temporary poles will be required in island and on build-out.

Drawing Title Key Under Construction TM Limit Drawing Number E17015/SK/PH-1B/6 Rev 0 Outline Phasing Plan Stage 3 – – Peak Time Arrangement Completed Traffic Movement Issue Date 01/10/2018 Temporary Surfacing Pedestrian Route Drawn By Rob Evans A6120 Outer Ring Road Improvements Roundhay Park Lane

Pedestrian route to be maintained by constructing verge half and half where there is full depth construction. Overlay areas to be constructed off-peak. Pedestrian route diverted into Pedestrian route to be maintained carriageway within TM off-peak when by constructing verge half and half. works dictate access is required to full Signalised pedestrian route Pedestrian route diverted into width of verge. to be maintained using carriageway within TM off-peak Pedestrian route to be maintained either new signals or when works dictate access is by constructing new route prior to temporary signal set. required to full width of verge. removal of existing route

South roundabout will be operating on new traffic signal controller prior to commencing build out in Harrogate Road. Temporary poles will be required in island and on build-out.

Drawing Title Key Under Construction TM Limit Drawing Number E17015/SK/PH-1B/7 Rev 0 Outline Phasing Plan Stage 3 – – Off-Peak Typical Arrangement Completed Traffic Movement Issue Date 01/10/2018 Temporary Surfacing Pedestrian Route Drawn By Rob Evans A6120 Outer Ring Road Improvements Roundhay Park Lane

Pedestrian route to be maintained by constructing new route prior to removal of existing route

Drawing Title Key Under Construction TM Limit Drawing Number E17015/SK/PH-1B/8 Rev 0 Outline Phasing Plan Stage 4 – – Peak Time Arrangement Completed Traffic Movement Issue Date 01/10/2018 Temporary Surfacing Pedestrian Route Drawn By Rob Evans A6120 Outer Ring Road Improvements Roundhay Park Lane

Pedestrian route to be maintained by constructing new route prior to removal of existing route

C

Drawing Title Key Under Construction TM Limit Drawing Number E17015/SK/PH-1B/9 Rev 0 Outline Phasing Plan Stage 4 – – Off-Peak Typical Arrangement Completed Traffic Movement Issue Date 01/10/2018 Temporary Surfacing Pedestrian Route Drawn By Rob Evans A6120 Outer Ring Road Improvements Roundhay Park Lane

Final surface course tie-ins will be carried out using a combination of single way working and road closures off-peak. Short term road closures will be required as providing acceptable lateral safety zones will leave insufficient space to maintain traffic flows past works.

Drawing Title Key Under Construction TM Limit Drawing Number E17015/SK/PH-1B/10 Rev 0 Outline Phasing Plan Stage 5 – Surface Course, Anti-skid & Road Markings Completed Traffic Movement Issue Date 01/10/2018 Temporary Surfacing Pedestrian Route Drawn By Rob Evans