Future Railway Power Supply

Bane NOR Energi, Planning dept. Nils Grønneberg 2017-02-02 Bane NOR Energi’s assignment

Ensure an adequate and stable railway power supply at the correct voltage and frequency.

Sounds simple…

…but we can’t do it without a lot of help from others!

We will see a number of projects in the next few years, which directly affect our railway power supply.

2 Railway network undergoing development

The section maps of the future will look different.

NTP 2018 – 2029 is aggressive: • More people to travel by train • Environmentally-friendly transport • Significant increase in capacity • Higher frequency of departures • Significant reduction of travel time

This means: • More sections • New tracks on the sections • More double track • Electrification

3 Consequences for railway power supply

Factors with a direct effect: • Increase in passenger traffic – new timetables • Increase in freight traffic • New rolling stock • Increasing power required • Modernisation of overhead contact line system (with autotransformers)

Action by Bane NOR: • New systems must be constructed • Existing systems must be upgraded • Maintenance must be intensified • New studies, master plans and analyses of load flow and stability

4

Bane NOR power system study

National overview of the power systems.

• Overarching report A shared starting point PSSP Referrals References

• Describes the current system

• Results and recommendations from section-based studies, simulations, analyses and Section-based studies measurements.

• Overall plans

5

Major projects A selection of projects:

• New double track for towards Tønsberg • New double track for Farriseidet – Porsgrunn • , – Ski • Electrification of Trønder and Meråker lines – near , Sandvika – Hønefoss • New double track for Line, Kleverud – Sørli • Upgrade of overhead contact line on Line • Double track for Østfold Line – western route • Upgrade of Østfold Line – eastern route • Upgrade of , north • Introduction of new rolling stock to the Gjøvik Line • Boost with mobile static converters

6

Studies for new major projects A selection of studies:

• Double track for , Narvik – Kiruna • Double track for Sørlandet Line, Nærbø – Sandnes • Double track for Dovre Line,

• Double track for Vestfold Line, Tønsberg – Larvik • Grenland Line, Porsgrunn – Skorstøl • Double track for Line, Arna –

• Kongsberg Line, Hokksund – Kongsberg • Linking of Gjøvik Line to Dovre Line • Electrification of Røros Line, Hamar – – Støren • Electrification of Solør Line, Hamar – Elverum – Kongsvinger

7

Typical procurements – Bane NOR Energi Studies and master plans

• Calculations and financial uncertainty analyses • Network analyses (stability, resonance) • Concept development • RAMS analyses • Planning processes • Site plans • Noise calculations and noise plan • Surveys, environmental and biological diversity • Risk analyses

• Preliminary inspections and site assessments

8

Typical procurements – Bane NOR Energi Detailed planning phase

• Concept development, system definition • Tender documents and specifications: - earthwork - building requirements - electrotechnical requirements • Consultancy services • General project assistance • Acquisition of land

9 Typical procurements – Bane NOR Energi Implementation phase/construction phase

• EPC contracts for converter stations • Assistance of construction client • Site assessments • Supply (and development) of converters • Supply of transformers • Supply of high-voltage breaker systems • Supply of protection and control equipment

• Revisions • Transport, lifting, installation, fitting • Inspections • etc.

10