Venjar–Sørli Project

Supplier meeting 2017-02-02 Lien - Andersen Venjar – Sørli Project • The project is part of the InterCity section between and – construction of new double tracks • Construction completed in 2024 • Venjar – Langset

• Kleverud – Sørli

2 Venjar – Langset Project It has been decided to implement the project with the following construction contracts: • An execution contract for substructure/ground works and technical railway installations Venjar – North • An execution contract for substructure/ground works and technical railway installations Eidsvoll North – Langset • Extension of the interlocking system on the • An EPC contract for new signalling system on the Line

3

IC Venjar – Langset milestones

4

Investments Venjar – Langset Duration Contract Constructio Proj. No: Project name Line section (number of signing n start years) Preparatory work all disciplines Dovre Line ongoing VE Venjar – Eidsvoll Gardermoen/ 2018 2018 5 Dovre lines EL Eidsvoll – Langset Dovre Line 2018 2018 5

Signalling system Eidsvoll – Langset Dovre Line 2021 2021 3 Signalling system Gardermoen Line Gardermoen Line 2017 2020 4

5 Railway power supply & overhead contact line

Delivery of the railway power supply including: • New switching post Eidsvoll • Number of switches 7 x 1p and 11 x 2p.

Delivery of the overhead contact line system including: • Auto transformers (AT) x 4 • Overhead contact line for all new and temporary tracks, approx. 21 km

6 Electrical power supply 50 Hz 22 kV high voltage distribution network: • Transformers 22 kV x 6 • High voltage switchgear x 6 • High voltage cables approx. 10 km

7 Low voltage power supply 50 Hz system

• Equipment in technical buildings, prefabricated kiosks and radio kiosks • Backup power supply and emergency power supply systems • Power supply for signalling system, telecom system • Power supply for disconnector switches • Point heaters • Pumping system • Fire alarm system • Control, regulation and monitoring systems (SRO) • Lighting equipment • Ventilation

8 Telecommunications Several of the installations in the points below are supplied as part of the frame contract with the contractor. • Cable system for transport network, access network, tunnels, external parties and local networks • Radio installation • Radio masts • Transmission system • Telecom room and access control

9 Kleverud – Sørli Project

Contract strategy

• Preparatory works • EPC contracts • An interdisciplinary EPC contract for Kleverud – Tangen which includes the Hestnes tunnel and Tangenvika railway bridge. Includes technical railway work for the entire Kleverud – Sørli section, excluding signalling. • EPC contract for substructure/ground works for Tangen – Sørli, including the new Tangen Station. • An EPC contract for new signalling system.

10 IC Kleverud – Sørli milestones

11

Investments Kleverud – Sørli

Duration Contract Constructio Proj. No: Project name Line section (number of signing n start years) Preparatory work all disciplines Dovre Line 2017 KS-01 EPC contract Kleverud – Sørli Dovre Line 2018 2018 5 KS-02 EPC contract Tangen – Sørli Dovre Line 2019 2019 4 Thales subcontracts under framework Dovre Line 2021 2022 2 agreement

12 Railway power supply & overhead contact line Delivery of the railway power supply includes the following: • Section limitation switch gear x 2 Delivery of the overhead contact line system includes the following: • Auto transformers (AT) x 6 • Overhead contact line/AT for all new and temporary tracks, approx. 36 km • Switch gear, cables and connections to switch gear x 26

13 Electrical power supply 50 Hz 22 kV high voltage power supply : • Transformers 22/11kV x 8 • High voltage switch gear x 7 • High voltage cables approx.18 km

14 Low voltage power supply 50 Hz

• Equipment in technical buildings, prefabricated kiosks and radio kiosks • Backup power supply and emergency power supply systems • Power supply for signalling system, telecom system • Power supply for disconnector switches • Point heaters • Pumping system • Fire alarm system • Control, regulation and monitoring systems (SRO) • Lighting equipment • Ventilation • Hestnes Tunnel – emergency lighting and emergency concept

15

Telecommunications Several of the installations in the points below are supplied as part of the frame contract with the contractor.

• Cable system for transport network, access network, tunnels, external parties and local network • Radio installation in tunnel • Radio masts • Transmission system • Passenger Information System (PIS system) • Camera surveillance system (CCTV system) • Hearing induction loop • Ticketing system • Telecom room (construction client and external) and access control • Telecom centre at Espa

16 Tangen Station Installations at the new Tangen Station, including parking spaces with electric vehicle charging sockets, lighting, snow melting system, heating system, passenger information system and ticketing system.

17

18 Thank you for your attention!