Great Western Zone : TOC Consultation 04

Total Page:16

File Type:pdf, Size:1020Kb

Great Western Zone : TOC Consultation 04 Network Rail EAS - Section 7 Data freeze: EAS_V4_3_2021 HS1 Route Version 4.3 Week 37 Possession RefLOR Possession Possession Blocked Line Protection Start End Traffic Remarks Work Type Location from Location to Type P2020/2940044 SO110 Fawkham Jn Hook Green Up Waterloo BLOCKED To 15/12/20 15/12/20 W2020/6797756 SO400 Connection A/C Electric 0055 Tue 0510 Tue (4 hrs) OHL Work SO460 Down Waterloo Trains 0m0ch and 0m0ch Connection P2020/2955463 SO110 Fawkham Jn Hook Green Up Waterloo BLOCKED To 16/12/20 16/12/20 W2020/7295972 SO400 Connection A/C Electric 0055 Wed 0510 Wed (4 hrs) OHL Work SO460 Down Waterloo Trains 0m0ch and 0m0ch Connection P2020/2940121 SO110 Fawkham Jn Hook Green Up Waterloo BLOCKED To 17/12/20 17/12/20 W2020/6797817 SO400 Connection A/C Electric 0055 Thu 0510 Thu (4 hrs) OHL Work SO460 Down Waterloo Trains 0m0ch and 0m0ch Connection P2020/2939962 EA1320 St. Pancras Dock Jn South Maintenance Sidings 14/12/20 14/12/20 W2020/7258524 LN115 International Siding Possession 0025 Mon 0440 Mon (5 hrs) S&T Work LN3201 0m0ch and 0m0ch SO400 Silo Curve Jn Cedar Jn Silo Curve Protected 14/12/20 14/12/20 Path 0025 Mon 0440 Mon (4 hrs) St. Pancras York Way North Jn East Coast Protected 14/12/20 14/12/20 International Mainline Path 0025 Mon 0440 Mon (4 hrs) Connection York Way North St. Pancras North London Protected 14/12/20 14/12/20 Jn International Incline Path 0025 Mon 0440 Mon (4 hrs) SUPERSEDED BY CPPP Electronic Copy - Uncontrolled when printed Page1 of 143 Network Rail EAS - Section 7 Data freeze: EAS_V4_3_2021 HS1 Route Version 4.3 Week 37 - Continued Possession RefLOR Location from Location to Blocked Line Protn Type Start End Traffic Remarks Work Type P2020/2761699 LN101 Copenhagen Jn Camden Road North London Possession 13/12/20 13/12/20 TRAINS TO START/TERMINATE AT FINSBURY W2020/6764088 LN3214 Central Jn Incline 0200 Sun 0845 Sun PARK Litter / Graffiti Clearance SO400 LNER REQUIRE A MINIMUM OF 2 LONG 0m0ch and 0m22ch Kings Cross Finsbury Park All Lines Possession 13/12/20 13/12/20 PLATFORMS FOR STABLING W2020/7252389 0200 Sun 0845 Sun Rail Testing and Lubrication OPEN ACCESS REQUIRE 1 PLATFORM FOR 0m0ch and 2m14ch Kings Cross Kings Cross Station Platforms 1 to 11 Possession 13/12/20 13/12/20 STABLING W2020/6766815 Station inc 0200 Sun 0845 Sun Major Projects Platform 0 PLATFORMS 0, 3, 4, AND 5 TO BE KEPT CLEAR OF 0m0ch and 2m16ch Route Boundary York Way North Jn ECML Connect Possession 13/12/20 13/12/20 STOCK W2020/7084268 LNE Route - HS1 Line 0200 Sun 0845 Sun Patrolling / CTRL 0m0ch and 1m40ch Canal Tunnels Jn Belle Isle Jn Down and Up BLOCKED To 13/12/20 13/12/20 W2020/7084017 Canal Tunnel Electric Trains 0200 Sun 0845 Sun S&C Maintenance 1m40ch and 2m10ch W2020/7104892 S&T Work 0m0ch and 2m0ch W2020/7046225 Off Track Work 0m0ch and 0m47ch W2020/7237972 Litter / Graffiti Clearance 0m0ch and 1m35ch W2020/7237133 OLE Maintenance 0m46ch and 2m16ch W2020/7159168 Technical Inspection 0m0ch and 2m0ch W2020/6753686 Welding and Grinding 0m0ch and 0m62ch W2020/6329481 Survey Work 0m15ch and 0m62ch P2019/2434247 EA1390 Renwick Road Jn Freightliner Depot Down Goods BLOCKED To 29/12/19 21/05/21 NO ACCESS AVAILABLE TO ELECTRIC TRAINS VIA SO420 East End GF Electric Trains 0001 Sun 0002 Fri THE DOWNS GOODS TO THE UP TILBURY/EXCHANGE SDGS SUPERSEDED BY CPPP Electronic Copy - Uncontrolled when printed Page2 of 143 Network Rail EAS - Section 7 Data freeze: EAS_V4_3_2021 HS1 Route Version 4.3 Week 37 - Continued Possession RefLOR Location from Location to Blocked Line Protn Type Start End Traffic Remarks Work Type P2020/2687765 EA1370 Barking Barking Platforms 7-8 Possession 13/12/20 13/12/20 RAIL REPLACEMENT ROAD SERVICE TO W2020/6756318 EA1380 0035 Sun 1425 Sun OPERATE BETWEEN GRAYS, PURFLEET, Major Projects EA1390 RAINHAM AND UPMINSTER 7m65ch and 10m26ch SO420 Barking Station Grays Down T&H/Down Possession 13/12/20 13/12/20 W2020/7101421 Jn Tilbury 0035 Sun 1425 Sun NO ACCESS TO/FROM EAST HAM CS FOR ARL S&T Points 9m16ch and 9m54ch Barking Tilbury Barking Tilbury Line Up Possession 13/12/20 13/12/20 NO ACCESS TO/FROM RIPPLE LANE, DAGENHAM W2020/7154511 Line Jn Jn West Tilbury/Fenchurch 0035 Sun 1425 Sun DOCK AND PURFLEET SIDINGS Structures Examination Street 7m42ch and 8m11ch Barking Tilbury Ripple Lane East Jn Down Goods Possession 13/12/20 13/12/20 FREIGHT SERVICES TO BE RE-TIMED OR NOT TO W2020/7027893 Line Jn East (Down 0035 Sun 1425 Sun RUN Tilbury/Goods) Remove Rail Defects 13m12ch and 19m70ch Upney Jn Down and Up Possession 13/12/20 13/12/20 LTS CYCLIC TYPE 5 Connecting Line 0035 Sun 1425 Sun Barking Tilbury Barking Down Fenchurch Possession 13/12/20 13/12/20 Line Jn West Street/Tilbury 0035 Sun 1425 Sun Freightliner Depot Dagenham Dock FMC Connecting Possession 13/12/20 13/12/20 East End GF Line 0035 Sun 1425 Sun Down Ripple Lane Chord Up Ripple Lane Chord Grays Barking Station Jn Up Tilbury/Up T&H Possession 13/12/20 13/12/20 0035 Sun 1425 Sun Renwick Road Jn Freightliner Depot Exchange Sidings Possession 13/12/20 13/12/20 East End GF 1-3 0035 Sun 1425 Sun Ripple Lane East Barking Tilbury Line Up Goods Possession 13/12/20 13/12/20 Jn (Up Tibury) Jn East 0035 Sun 1425 Sun Freightliner Depot Freightliner Depot Sidings 1-3 Sidings 13/12/20 13/12/20 West End GF East End GF Possession 0035 Sun 1425 Sun Ripple Lane Ripple Lane Down Through Sidings 13/12/20 13/12/20 Sidings Possession 0035 Sun 1425 Sun Stora Sidings H7 & H8 Ripple Lane West Ripple Lane West Sidings 1-4 Sidings 13/12/20 13/12/20 Yard Yard Possession 0035 Sun 1425 Sun Barking Upney Jn Down and Up Possession 13/12/20 13/12/20 Main 0100 Sun 0600 Sun Upminster Grays Up & Down Possession 13/12/20 13/12/20 Ockendon/Third 0100 Sun 0600 Sun SUPERSEDEDLine BY CPPP Electronic Copy - Uncontrolled when printed Page3 of 143 Network Rail EAS - Section 7 Data freeze: EAS_V4_3_2021 HS1 Route Version 4.3 Week 37 - Continued Possession RefLOR Location from Location to Blocked Line Protn Type Start End Traffic Remarks Work Type P2020/2948826 SO130 Ashford Ashford Platforms 3 - 6 BLOCKED To 13/12/20 13/12/20 ASHFORD UP AND DOWN EAST AND WEST JN W2020/7281034 SO470 A/C Electric 0055 Sun 0700 Sun BLOCKED TO AC ELECTRIC TRAFFIC OHL Work SO480 Trains 0m0ch and 0m0ch Ashford East Jn Ashford East Jn Down CTRL BLOCKED To 13/12/20 13/12/20 SUB SECTIONS 715 COMPLETE & 716 COMPLETE Chord A/C Electric 0055 Sun 0700 Sun ARE NOT AVAILABLE TO AC ELECTRIC TRAFFIC Up CTRL Chord Trains DUE TO HS1 SWITCHING Ashford West Jn Ashford West Jn Down CTRL BLOCKED To 13/12/20 13/12/20 PLATFORMS 5 & 6 AVAILABLE TO DC TRAFFIC Chord A/C Electric 0055 Sun 0700 Sun Up CTRL Chord Trains DOLLAND MOOR FREIGHT CHORD BLOCKED TO Dollands Moor Dollands Moor Up Freight Chord BLOCKED To 13/12/20 13/12/20 AC ELECTRIC TRAFFIC (part) A/C Electric 0055 Sun 0700 Sun SUB SECTION 718F IS NOT AVAILABLE TO AC Trains ELECTRIC TRAFFIC DUE TO HS1 SWITCHING P2020/2948830 SO130 Ashford Ashford Platforms 3 - 6 BLOCKED To 14/12/20 14/12/20 ASHFORD UP AND DOWN EAST AND WEST JN W2020/7281099 SO470 A/C Electric 0020 Mon 0455 Mon BLOCKED TO AC ELECTRIC TRAFFIC OHL Work SO480 Trains 0m0ch and 0m0ch Ashford East Jn Ashford East Jn Down CTRL BLOCKED To 14/12/20 14/12/20 SUB SECTIONS 715 COMPLETE & 716 COMPLETE Chord A/C Electric 0020 Mon 0455 Mon ARE NOT AVAILABLE TO AC ELECTRIC TRAFFIC Up CTRL Chord Trains DUE TO HS1 SWITCHING Ashford West Jn Ashford West Jn Down CTRL BLOCKED To 14/12/20 14/12/20 PLATFORMS 5 & 6 AVAILABLE TO DC TRAFFIC Chord A/C Electric 0020 Mon 0455 Mon Up CTRL Chord Trains DOLLAND MOOR FREIGHT CHORD BLOCKED TO Dollands Moor Dollands Moor Up Freight Chord BLOCKED To 14/12/20 14/12/20 AC ELECTRIC TRAFFIC (part) A/C Electric 0020 Mon 0455 Mon SUB SECTION 718F IS NOT AVAILABLE TO AC Trains ELECTRIC TRAFFIC DUE TO HS1 SWITCHING SUPERSEDED BY CPPP Electronic Copy - Uncontrolled when printed Page4 of 143 Network Rail EAS - Section 7 Data freeze: EAS_V4_3_2021 HS1 Route Version 4.3 Week 38 Possession RefLOR Possession Possession Blocked Line Protection Start End Traffic Remarks Work Type Location from Location to Type P2020/2816092 LN3201 St. Pancras Dock Jn South Maintenance Possession 20/12/20 20/12/20 PLATFORMS 5-7/DN CTRL - BUFFER STOPS TO LN3213 International Siding 0015 Sun 0730 Sun AF046 SO400 PLATFORMS 8-10/UP CTRL - BUFFER STOPS TO SO410 York Way North Jn East Coast Possession 20/12/20 20/12/20 AF048 Mainline 0015 Sun 0730 Sun PLATFORMS 11-13/CTRL RELIEF - BUFFER STOPS Connection TO PTS 2040 York Way South Jn CTRL Relief Possession 20/12/20 20/12/20 Down CTRL 0015 Sun 0730 Sun OHL ISOLATION TO BE GIVEN UP BY 0700 TO ALLOW TRAINS TO PAN UP. York Way South St. Pancras Up CTRL Possession 20/12/20 20/12/20 Jn International 0015 Sun 0730 Sun POSSESSION TO BE TAKEN AFTER THE PASSAGE OF 1J78.
Recommended publications
  • Data Classification – Track & Civil
    Division / Business Unit: Corporate Services & Safety Function: Engineering (Track & Civil) Document Type: Work Instruction Data Classification – Track & Civil EGW-10-04 Applicability ARTC Network Wide SMS Publication Requirement Internal / External Primary Source EGH-10-03 Data Management Guideline No. 3 – Track & Civil Equipment Document Status Version Date Prepared by Reviewed by Endorsed Approved # Reviewed 1.1 08 Sep 20 Assurance Engineer & Stakeholders Manager General Manager Level Crossing Standards Technical Standards Performance Manager 16/09/2020 (Interstate Network) Amendment Record Amendment Date Clause Description of Amendment Version # Reviewed 1.0 27 Feb 19 First issue of Work Instruction 1.1 08 Sep 20 Revision to level crossings including licences EGI and functions descriptions table; Inclusion of Track EGI TR0005 - Track Loops; Adjusted size definition for T&C small culverts undertrack; Added enhanced definition with regards to KM change anomalies; And, detailed method to define gauge variations on track equipment in areas where there are many different tracks with different gauge variations in close proximity. Nameplate details also removed from this document and are now defined in a standalone document EGW- 10-17. © Australian Rail Track Corporation Limited (ARTC) Disclaimer This document has been prepared by ARTC for internal use and may not be relied on by any other party without ARTC’s prior written consent. Use of this document shall be subject to the terms of the relevant contract with ARTC. ARTC and its employees shall have no liability to unauthorised users of the information for any loss, damage, cost or expense incurred or arising by reason of an unauthorised user using or relying upon the information in this document, whether caused by error, negligence, omission or misrepresentation in this document.
    [Show full text]
  • Joint Performance Improvement Update
    Joint Performance Improvement Update Issued 28 February 2018 This report gives progress on the joint improvement plan for Govia Thameslink Railway (GTR) and Network Rail with punctuality data by route, as well as the main operational issues in the period (there are 13, 4-week reporting periods per year), and planned customer improvements. PPM* statistics and delay responsibility by route – Period 11 (to 3 February 2018) Gatwick Express Great Northern Southern Thameslink *The public performance measure (PPM) data above shows the percentage of trains which arrive at their terminating station within five minutes of the planned arrival time. It combines figures for punctuality and reliability into a single performance measure. A summary of key issues affecting performance in this period GTR’s PPM in Period 11 was 82.9 per cent, a rise of six percentage points from Period 10. This lifted the Moving Annual Average (MMA) to 81.3 per cent, maintaining the steady improvement achieved through 2017. Within the GTR total, Southern’s PPM increased by almost seven percentage points to 80.9 per cent, edging its MMA up to 79.7 per cent. On Southern, the period’s most disruptive incidents were a points failure near London Victoria (1,700 delay minutes and 32 cancellations), an incident at Durrington-on-Sea (1,066 delay minutes and 44 cancellations), and a track fault near Portsmouth (558 delay minutes and 39 cancellations). Thameslink’s PPM of 89.0 per cent was also an improvement over the previous period’s 85.4 per cent. A loss of power to the track at City Thameslink station caused 1,250 delay minutes and 153 cancellations.
    [Show full text]
  • GTR 18Th SA Decision Letter
    OFFICE OF RAIL AND ROAD Jonathan Rodgers Senior Executive, Access and Licensing Telephone: 0207 282 3775 E-mail: jonathan. [email protected]. uk 22 February 2018 Andriana Shiakallis Tom Causebrook Customer Manager Access Contract Manager Network Rail Infrastructure Limited Govia Thameslink Railway Limited Cotton Centre 1st and 2nd Floor Monument Place Tooley Street 24 Monument Place London Bridge London SE12QG EC3R 8AJ Dear Andriana and Tom Eighteenth supplemental agreement to the track access contract between Network Rail Infrastructure Limited and Govia Thameslink Railway Limited (GTR) 1. We have today approved the above supplemental agreement submitted to us formally on 22 February 2018. 2. The purpose of this agreement is to obtain contingent access rights allowing GTR to operate weekday preview passenger train services ahead of the May Timetable change. The services will use the new Canal Tunnel infrastructure between St Pancras and London Bridge. Two services a day will run from Cambridge to Brighton and back and two services a day will run from Peterborough to Horsham and back. Both services will be weekdays only. 3. As no other operator will be using the Canal Tunnels and the full May 2018 access rights application (which will include firm rights for these services) is currently in consultation, we advised the parties that a consultation was not necessary for this application. Head Office: One Kemble Street, London WC2B 4AN T: 020 7282 2000 www.orr.gov.uk 4. Our own review did not identify any issues and we are satisfied that approval is in accordance with our statutory duties under section 4 of the Railways Act 1993.
    [Show full text]
  • A Review of the Thameslink Programme
    The Institution of Railway Signal Engineers Inc Australasian Section Incorporated A Review of the Thameslink Programme Georgina Hartwell MEng (Hons) AMIRSE MIET Network Rail Consulting SUMMARY The aim of this paper is to provide a project description and update to Network Rail’s Thameslink Programme in London. It discusses the history behind the programme and key design considerations. The paper then goes on to look at the reasons behind the decision to implement ATO over ETCS Level 2, before explaining some of the supporting projects and work-streams. In order to successfully commission ATO, a migration strategy and comprehensive set of system proving is required; testing activities are discussed in the paper. Finally, examples of best practice and lessons learned are given, before highlighting key considerations to be made by other high capacity infrastructure projects. 1 INTRODUCTION 3 WHAT IS THAMESLINK? Opened in 1988, the Thameslink route runs along the 3.1 Three Stages North – South plane of London, connecting services KO0 was completed in March 2009 and saw the number through the heart of the city. It currently covers 68 stations and 225km of track, with the majority of services running of trains per hour (tph) through the core area increase from Bedford to Brighton via London Bridge. The route from 8 to 15 in the peak. serves two airports, London Luton and London Gatwick, KO1 was completed in December 2011, introducing 12 as well as King’s Cross St Pancras where connections to car trains across the whole route, along with an increased Eurostar services can be made.
    [Show full text]
  • At London Bridge Station the Railway Nights for 4 Consecutive Nights
    THE THAMESLINK PROGRAMME ISSUE 5 FEBRUARY/MARCH 2014 FREE! EVERYONE GETS HOME SAFE EVERY DAY! ALTERING LAYOUTS AT any station been installed by Balfour Beatty’s whilst it’s still operational and moving civil team based at New Cross Gate thousands of people around every day to get cables to track level to feed the is extremely demanding therefore it is new signalling systems. no surprise that the complex redevel- As well as the cable routes, major opment of London Bridge station is a modifications have been made to the real challenge for those working on the existing 1974 Westpac signalling project. with over 1000 wires to change over London Bridge station has approx- during the commissioning which MAKING imately 52 million people travelling will keep the system running until through it every year during which the new electronic Westlock system Railway Systems and Civils project becomes live in December 2014. teams from Network Rail, Costain, Bal- And finally, before the platforms four Beatty, Siemens and others not can be opened the track needs to be mentioned are working tirelessly to laid, so during the first week of Feb- redevelop. ruary the team have seen the first Prior to the start of the main works ballast trains arrive during mid week TRACKS at London Bridge station the Railway nights for 4 consecutive nights. Each Systems team diverted all the signal- night 420t of ballast has been deliv- AT LONDON BRIDGE ling and communication cables (around ered by train and then during the 60km of multi-core cable) off the foot- day it’s been dozered and compacted Ballast being bridge to allow the Costain station dropped in the team to start demolition.
    [Show full text]
  • Joint Performance Improvement Update
    Joint Performance Improvement Update Issued 30 March 2018 This report gives progress on the joint improvement plan for Govia Thameslink Railway (GTR) and Network Rail with punctuality data by route, as well as the main operational issues in the period (there are 13, 4-week reporting periods per year), and planned customer improvements. PPM* statistics and delay responsibility by route – Period 12 (to 3 March 2018) Gatwick Express Great Northern Southern Thameslink *The public performance measure (PPM) data above shows the percentage of trains which arrive at their terminating station within five minutes of the planned arrival time. It combines figures for punctuality and reliability into a single performance measure. A summary of key issues affecting performance in this period In period 12, GTR’s PPM was 79.32% with the main incidents affecting performance being the severe winter weather in the Sussex area at the end of February/beginning of March, and also a track defect at City Thameslink on 14 February and a signalling fault near Sutton on 12 February. The PPM for each of the brands for this period was: Gatwick Express 71.30%, Great Northern 79.25%, Southern 77.91% and Thameslink 84.35%. Delivering improvements for passengers Thameslink Class 700s There are 71 class 700 trains in regular service between Brighton and London Bridge or Bedford; between Wimbledon, Sutton, St Albans and Luton; on the Sevenoaks route and between Horsham / Littlehampton and London. Since 26 February, we have been operating preview services through the canal tunnels at Kings Cross between Cambridge and Brighton, and between Peterborough and Horsham.
    [Show full text]
  • Thameslink Programme Baseline Evaluation Report
    Thameslink Programme Evaluation: Baseline Report Department for Transport March 2018 Thameslink Programme Evaluation: Baseline Report Quality information AECOM ref. no.: 60518666 Prepared by Checked by Approved by Jameel Hayat Richard Redfern Richard Redfern AECOM AECOM AECOM March 2018 Final Report to DfT Prepared for: Department for Transport AECOM | Ipsos MORI 2/162 Thameslink Programme Evaluation: Baseline Report Prepared for: Department for Transport Prepared by: Jameel Hayat E: [email protected] AECOM Limited Aldgate Tower 2 Leman Street London E1 8FA aecom.com Prepared in association with: Ipsos MORI © 2018 AECOM Limited. All Rights Reserved. This document has been prepared by AECOM Limited (“AECOM”) for sole use of our client (the “Client”) in accordance with generally accepted consultancy principles, the budget for fees and the terms of reference agreed between AECOM and the Client. Any information provided by third parties and referred to herein has not been checked or verified by AECOM, unless otherwise expressly stated in the document. No third party may rely upon this document without the prior and express written agreement of AECOM. Prepared for: Department for Transport AECOM | Ipsos MORI 3/162 Thameslink Programme Evaluation: Baseline Report Table of Contents Executive Summary .............................................................................................................. 9 1. Introduction ...............................................................................................................
    [Show full text]
  • 13 14 Calculating and Sharing Train Occupancy in Real Time
    CALCULATING AND SHARING TRAIN OCCUPANCY IN REAL TIME GOVIA THAMESLINK RAILWAY CASE STUDY 13 14 KNOWING WHICH CARRIAGES ARE FULL IS THE KEY TO REDUCING STATION DWELL TIMES AND IMPROVING THE PASSENGER EXPERIENCE. GOVIA THAMESLINK RAILWAY WORKED WITH CACI AND THE UNIVERSITY OF SOUTHAMPTON, AND USED WORLD-LEADING TECHNOLOGY TO PROVE THE CONCEPT ON THE GATWICK EXPRESS. SUMMARY Knowing where there’s space on a train – before it arrives in the station – makes a huge difference to passenger experience and operational efficiency alike. For the passenger, the experience of a crowded carriage is much the same whether the train is completely full, or there are seats elsewhere. And for the rail operator, the chance to direct waiting passengers to the best points on the platform can help to reduce station dwell times, as passengers board and alight more easily. These were the issues Govia Thameslink Railway (GTR) hoped to address when it won funding from the Rail Safety and Standards Board (RSSB) for a research project into understanding real-time passenger numbers aboard the Gatwick Express. It could then apply this knowledge to deliver reliability across its network – most notably the fast-moving Thameslink service. But to prove its concept, GTR needed to tackle two key issues in real time: the actual number of passengers, and the real composition of the train. We’ve proved you can know the exact train composition – and how many passengers are aboard – at any given time. That’s powerful information to keep our customers informed and happy, and our trains running on time. Stewart Wells, Customer Information Projects Manager, Govia Thameslink Railway.
    [Show full text]
  • Public Meeting #2 Summary Report
    Public Meeting #2 Summary Report Metrolinx GO Expansion Program 04-Nov-2020 Prepared by: Revision 00 04-Nov-2020 Metrolinx GO Expansion Program Public Meeting #2 Summary Report Authorization X X Sabriya Jahangir Yulia Pak Environmental Planner Consultation Specialist X X Amber Saltarelli Andrew Gillespie Environmental Lead Program Manager REVISION HISTORY Revision Date Purpose of Submittal Comments 00 04-Nov-20 Final Submission to Metrolinx. N/A This submission was completed and reviewed in accordance with the Quality Assurance Process for this Project. Revision 00 04-Nov-2020 Metrolinx GO Expansion Program Public Meeting #2 Summary Report Table of Contents 1 Introduction .......................................................................................................................................... 1 1.1 GO Expansion .................................................................................................................................. 1 1.2 Scope of the GO Expansion Program .............................................................................................. 2 GO Rail Network Electrification TPAP Addendum Project .................................................... 2 Scarborough Junction Grade Separation TPAP .................................................................... 4 Stouffville Rail Corridor Grade Separations TPAP ................................................................ 4 New Track & Facilities TPAP ................................................................................................
    [Show full text]
  • Railfuture Autumn 2013 Rail Users Conference
    ISSUE163 September 2014 Internet at www.railfuture.org.uk www.railfuture.org.uk/east html THE CLASS 377, ARRIVING 2017; BETWEEN KING'S LYNN, CAMBRIDGE & KING'S CROSS Yes, it is official; the Class 377, electric units, now running on Thameslink to Bedford from Brighton, will be transferring in 2017 to the Cambridge Cruiser service from King's Cross station (not Thameslink) through to King's Lynn. Compared with the current rolling stock this means air-conditioned, double glazed, quieter journeys on most of these services. Significant on a route containing no fewer than nine tunnels, especially when the 'hopper' windows are open. Read more inside on this and GTR, the new franchisee replacing First Capital Connect. 1 What an amalgam; the constituent parts of Govia Thameslink Railway (GTR), as the franchise is to be known from 14 September this year. For many years members of the Branch attended at least twice a year the meetings of the Thameslink 2000 Consortium; an important grouping of local authorities plus pressure groups such as ours. It kept the burning flame of the idea in the sight of all MPs and Ministers, stressing the importance of the project to the entire South-East economy, not just to London. We like to think it ensured the scheme remained regionally based rather than defaulting to just a metro-style line, like Crossrail. Obviously we were successful even if the title 'Thameslink' had to drop the suffix 2000! How time flies! So let us not forget this amazingly stubborn work by the Consortium. After all these years it is more than a pleasure to now see all the parts of Thameslink coming together in 2018.
    [Show full text]
  • ESC 250 Turnouts and Special Trackwork
    Technical Note – TN 003: 2018 For queries regarding this document [email protected] www.transport.nsw.gov.au Technical Note – TN 003: 2018 Issue date: 23 August 2018 Effective date: 23 August 2018 Subject: Turnout speeds and crossing selection This technical note is issued by the Asset Standards Authority (ASA) as an update to ESC 250 Turnouts and Special Trackwork, version 4.8 to restrict the design speed through higher speed turnouts and crossovers, provide restrictions on the use of certain crossing types and correct some typographical errors. Higher speed turnouts, when used in a crossover or a reversing curve situation without transitions, can result in higher maintenance requirements and increased passenger discomfort. Swing nose and spring wing crossings are permitted to be used with tangential turnouts, but due to whole-of-life costs considerations, restrictions on their use have been expanded. The updates include amendments to Section 6.1.5 as follows: 1. Section 6.1.5 Crossings Replace the contents of Section 6.1.5 with the following: The selection of turnouts is dependent upon the criteria for crossing rates and crossing types. For crossing rate see Section 6.1.5.1 and for crossing type see Section 6.1.5.2. 1.1. Section 6.1.5.1 Selection of crossing rate The selection of the crossing rate shall be based on the geometric design of the turnout and the associated limiting speeds of the mainline and turnout roads. Turnout speeds shall be determined by applying design standards for track geometry detailed in ESC 210 Track Geometry and Stability.
    [Show full text]
  • Thameslink-East Coast Tunnel Link Work Starts
    Welcome [email protected] Search site resources Log out Front page News & analysis Intelligence & resources Agenda & monitors Subscribe About News Analysis Thameslink-East Coast tunnel link work starts Canal Tunnels: Network Rail Posted 11/09/13 installing track, signalling, power and safety systems Network Rail has announced what it describes as the first stage of work to connect two new Thameslink rail tunnels to the national network. The Canal Tunnels in north London will connect the core Thameslink route to the East Coast Main Line ready for completion of the Thameslink Programme when direct train services between Sussex/Kent and Cambridge/Peterborough will be introduced. Although the tunnels were built between 2004 and 2006 as part of the redevelopment of St Pancras station to accommodate High Speed 1, delays progressing what was called Thameslink 2000 mean they continue to lie idle. RELATED ARTICLES However, as the introduction of trains moves closer, Network Rail says the first stage of connecting the tunnels to operational lines, including track work on the East Coast London Bridge platforms demolished for Thameslink Main Line, near the tunnels' entrances, will take place over the weekend of 14 and 15 Bombardier secures second Thameslink train order September 2013. The infraco is currently installing track, signalling, power and safety Thameslink train depots to be built by Volker systems in the tunnels. Siemens awarded £1.6bn Thameslink train... Thameslink rolling stock deal finalised - almost Between October 2011 and January 2012 Balfour Beatty Rail constructed a new Thameslink KO2 at risk from train deal delay Canal Tunnel Junction which involved the installation of two new turnouts from the London Bridge Thameslink rebuild enters next phase existing Thameslink lines to the Canal Tunnels.
    [Show full text]