The World Bank Report No: ISR16398

Implementation Status & Results Local Sustainable Development (P101426)

Operation Name: Lake Titicaca Local Sustainable Development (P101426) Project Stage: Implementation Seq.No: 14 Status: ARCHIVED Archive Date: 07-Nov-2014 Country: Bolivia Approval FY: 2008 Product Line:IBRD/IDA Region: LATIN AMERICA AND CARIBBEAN Lending Instrument: Specific Investment Loan Implementing Agency(ies): Fondo de Inversion Productiva y Social Key Dates Board Approval Date 20-Dec-2007 Original Closing Date 30-Jun-2013 Planned Mid Term Review Date 17-Dec-2013 Last Archived ISR Date 17-Mar-2014 Public Disclosure Copy Effectiveness Date 01-Dec-2008 Revised Closing Date 02-Feb-2015 Actual Mid Term Review Date 19-Dec-2013

Project Development Objectives Project Development Objective (from Project Appraisal Document) The objective of the Project is to contribute to local sustainable development in the Recipient's side of the Lake Titicaca watershed.

Has the Project Development Objective been changed since Board Approval of the Project?

Yes No

Component(s)

Component Name Component Cost Basic Services 9.00 Tourism Support 7.00 Technical Assistance 4.00

Overall Ratings Previous Rating Current Rating Progress towards achievement of PDO Unsatisfactory Unsatisfactory Overall Implementation Progress (IP) Unsatisfactory Unsatisfactory Overall Risk Rating High

Implementation Status Overview The project is expected to disburse less than half of the loan on goods and works that will contribute to the overall objectives. It will however not reach its development objectives.

The project was envisioned to undertake projects to improve tourism and basicservices in the Lake Titicaca Region including docks, rural water supply, solid waste management Public Disclosure Copy systems, urban water supply, drainage and wastewater treatment, tourist centers and signage for tourist areas. The implementation was delayed initially due to institutional deficiencies of the executing agency at the beginning of the project. A restructuring was undertaken to transfer the responsibility to FPS with a focus on the execution of the works. Under the new structure delays were encountered in contracting the pre-investment studies for the large urban water projects which did not allow these project which represent the

Page 1 of 6 The World Bank Report No: ISR16398

largest portion of the loan to be executed in the time period of the project. In addition some of the other projects encountered delays in finalizing project preparation including identifying land acquisition and compensation arrangements, finalizing designs, identifying interested contractors and reaching community consensus. As of January 2014 an additional set of projects were considered in order to replace those that have had encountered these impediments in the design and bidding. These include drainage works, equipment for solid waste management systems, ecological sanitation facilities and rural water supply projects.

To date the project has completed investments in signage in tourist areas; and rural water supply projects in two areas (Laja and ). 4 landfills (Copacabana, Tiwanacu, and Tiquina) are under construction. In addition, rural water supply projects (in Achacachi and Santiago de Huata); ecological sanitation latrines (in Achacachi, , Santiago de Huata, and Huatajata) have recently been contracted. Additionally, equipment for solid waste management (Achacachi, Tiwanacu, Copacabana and Tiquina) and one urban drainage project (in Viacha) are in the stage of contract award. No other equipment or works are expected to be procured. For all works that would extend after that project closing date, local financing will be provided to cover that portion of the works.

It is expected that a total of between 45 and 50% of the loan will be disbursed before the end of the closing date. In total, the project has disbursed 27% of the loan including the works executed and the previously executed pre-investment studies, small tourism activities and management costs. This represents and increase from 19% reported in the last ISR. Public Disclosure Copy

Locations Country First Administrative Division Location Planned Actual Bolivia Departamento de Viacha

Bolivia Departamento de La Paz Tito Yupamqui

Bolivia Departamento de La Paz Tiahuanaco

Bolivia Departamento de La Paz Taraco

Bolivia Departamento de La Paz Tacanoca

Bolivia Departamento de La Paz Isla del Sol

Bolivia Departamento de La Paz San Pedro

Bolivia Departamento de La Paz Puerto Perez

Bolivia Departamento de La Paz

Bolivia Departamento de La Paz

Bolivia Departamento de La Paz Isla Pariti

Bolivia Departamento de La Paz Nina Chiri

Bolivia Departamento de La Paz Masaya

Bolivia Departamento de La Paz Isla de la Luna

Bolivia Departamento de La Paz Lacaya Public Disclosure Copy Bolivia Departamento de La Paz Kallutaca

Page 2 of 6 The World Bank Report No: ISR16398

Country First Administrative Division Location Planned Actual Bolivia Departamento de La Paz

Bolivia Departamento de La Paz

Bolivia Departamento de La Paz Desaguadero

Bolivia Departamento de La Paz Copacabana

Bolivia Departamento de La Paz Catavi

Bolivia Departamento de La Paz Carabuco

Public Disclosure Copy Bolivia Departamento de La Paz

Bolivia Departamento de La Paz Aygachi

Bolivia Departamento de La Paz Avicaya

Bolivia Departamento de La Paz

Bolivia Departamento de La Paz Achacachi

Results

Project Development Objective Indicators Indicator Name Core Unit of Measure Baseline Current End Target Urban Environmental Sustainability Index for Text Value Copacabana # 4 2 key communities Achacachi # 3 2 Tiquina # 4 2 Tiwanaku # 4 2 Viacha - 4 2 Date 20-Nov-2007 01-Nov-2012 02-Feb-2015 Comments Will not update this indicator until the end of the project due to the effort needed in measuring it.

Intermediate Results Indicators Public Disclosure Copy

Page 3 of 6 The World Bank Report No: ISR16398

Indicator Name Core Unit of Measure Baseline Current End Target Number of rural towns provided woth improved Text Value 0 20 20 water and sanitation services Date 20-Nov-2007 30-Sep-2014 02-Feb-2015 Comments 20 completed (Laja and Puerto Perez). An additional 5 are scheduled to be completed under the project. Number of Tourism Studies - COMPLETED Text Value 0 3 3 Date 20-Nov-2007 30-Sep-2014 02-Feb-2015 Comments

Public Disclosure Copy New piped household water connections that Number Value 0.00 0.00 are resulting from the project intervention Date 20-Nov-2007 30-Sep-2012 02-Feb-2015 Comments All connections in the rural Target not able to be water supply projects are determined as the designs communal. None of the were not finalized for the urban water supply projects household water supply in will be completed. urban areas. Number of other water service providers that Number Value 0.00 2.00 6.00 the project is supporting Date 20-Nov-2007 01-Nov-2012 02-Feb-2015 Comments Puerto Perez, Laja Puerto Perez, Laja, Tiwanacu, Copacabana, Achacachi and Tiquina. Number of people in rural areas provided with Number Value 0.00 0.00 access to Improved Water Sources under the Date 20-Nov-2007 30-Sep-2014 02-Feb-2015 project Comments Populations of Puerto Perez Completed- (both Puerto Population estimates will be and Laja were targeted. Perez and Laja) confirmed for Laja and Puerto Perez as part of project closure. Number of people in urban areas provided with Number Value 0.00 0.00 access to Improved Sanitation under the Date 20-Nov-2007 01-Nov-2012 02-Feb-2015 project Comments No sanitation facilities have Population target will be been completed. confirmed as part of project closure. Number of people in urban areas provided with Number Value 0.00 0.00 52000.00 access to regular solid waste collection under Date 20-Nov-2007 30-Sep-2014 02-Feb-2015 the project Comments All projects are under

Public Disclosure Copy construction.

Page 4 of 6 The World Bank Report No: ISR16398

Number of cities with adequate solid waste Text Value 0 4 3 services Date 20-Nov-2007 01-Nov-2012 02-Feb-2015 Comments All projects are under construction. Number of urban communities provided with Text Value 0 0 3-5 adequate wastewater services Date 20-Nov-2007 01-Nov-2012 02-Feb-2015 Comments None will be realized as designs were not complete. Direct project beneficiaries Number Value 0.00 Date 20-Nov-2007 01-Nov-2012 02-Feb-2015 Public Disclosure Copy Comments Population of water supply Numbers will be updated and projects of Puerto Perez and confirmed before project Laja have benefited. closure based on projected projects accounting for design changes. Female beneficiaries Percentage Value 0.00 Sub Type Supplemental Communities with improved tourism Number Value 0.00 0.00 31.00 infrastructure Date 20-Nov-2007 21-Jun-2013 02-Feb-2015 Comments Note that many communities have benefited from improved signage but they have not been counted here.

Data on Financial Performance (as of 29-Sep-2014)

Financial Agreement(s) Key Dates Project Ln/Cr/Tf Status Approval Date Signing Date Effectiveness Date Original Closing Date Revised Closing Date P101426 IDA-43790 Effective 20-Dec-2007 11-Feb-2008 01-Dec-2008 30-Jun-2013 02-Feb-2015

Disbursements (in Millions) Project Ln/Cr/Tf Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P101426 IDA-43790 Effective XDR 12.80 12.80 0.00 3.46 9.34 27.00

Disbursement Graph Public Disclosure Copy

Page 5 of 6 The World Bank Report No: ISR16398 Public Disclosure Copy

Key Decisions Regarding Implementation The project is planning for closure in February 2, 2015 as planned. A date of October 31, 2014 has been set as a deadline for all bidding processes to be completed, and counterpart funding confirmed. After that time, it is planned that the remaining portion of the loan will be canceled and these resources will be used for other investments in Bolivia.

Restructuring History Level two Approved on 16-Sep-2010, Level two Approved on 18-Jun-2012

Related Projects There are no related projects. Public Disclosure Copy

Page 6 of 6