February-2021 Executive Summary on Power Sector

Total Page:16

File Type:pdf, Size:1020Kb

February-2021 Executive Summary on Power Sector भारत सरकार Government of India वि饍युत मंत्रालय Ministry of Power के न्द्रीय वि饍युत प्राधिकरण Central Electricity Authority Executive Summary on Power Sector February-2021 Executive Summary for the Month of February-2021 Contents SN Section A - Highlights of Power Sector Page 1 Electricity Generation for Feb-2021 (BU) 1A & 1B 2 Generating Capacity Addition for Feb-2021 (MW) 2 3 List of Projects Commissioned in Feb-2021 3 4 All India Installed Capacity (MW) Region-wise as on 28-02-2021 3 5 All India Installed Capacity (MW) Sector-wise as on 28-02-2021 4 6 Transmission Lines Added during Feb-2021 (Ckms) 5 7 Transformation Capacity Addition during Feb-2021 (MVA) 6 8 Power Supply Position (Energy & Peak) in Feb-2021 7 9 Peak Shortage of Power Supply (MW) in Different Regions 8-9 10 All India PLF Sector-wise for Feb-2021 10 11 T & D and AT & C Losses (%) 12 All India Village Electrification 11 13 Average cost of Power & Average Realisation 14 All India Coal consumption for Power Generation (MT) Section B - Capacity Addition 1 Capacity Addition Targets and Achievements in 12th Plan, 2017-18 , 2018-19 and 2019-20 12 2 Capacity Addition Targets & Achievements during Feb-2021 13 3 Installed Capacity in various Regions including their shares. 14-19 Section C - Transmission Lines 1 Programme and Achievements of Transmission Lines in Feb-2021 20 2 List of Transmission Lines Commissioned during Feb-2021 Section D - Sub Stations Programme and Achievements of Sub-Stations in Feb-2021 1 21 2 List of Sub Stations commissioned during Feb-2021 Section E - Electricity Generation 1 Electricity Generation (MU) Targets and Achievements for 2020-21 22 Section F - Power supply position 1 Power Supply Position (Provisional) for Feb-2021 23 2 Peak Demand and Peak Met (Provisional) for Feb-2021 24 3 Power Supply Position (Revised) for Jan-2021 25 4 Peak Demand and Peak Met (Revised) for Jan-2021 26 5 Notified Power cuts / Restrictions on Industries during Feb-2021 27 6 Power Supply to Agricultural Sector during Feb-2021 28 Section G - Growth of Power Sector 1 Growth of Installed Capacity since 6th Plan 29 2 Growth of Transmission Sector since 6th Plan 30 3 All India Yearly Coal consumption for Power Generation (Utilities) 4 All India Annual Per Capita Consumption of Electricity since 2006 31 5 Average cost of power supply & Average realisation (Paisa/kWh) 6 Growth of Rural Electrification & Pump Sets Energisation 32 Section H - Rate of sale of power 1 Rate of sale of power 33-46 2 Outstanding dues of Power Utilities Payable to CPSUs on Monthly basis 47 ABBREVIATION Sr.No Short Form Full Form 1 Ach Achievements 2 ACS Average Cost of Supply Average Revenue 3 ARR Realization Aggregate Technical 4 AT&C and Commercial 5 BU Billion Units Central Electricity 6 CEA Authority 7 CKMs Circuit Kilo Meters Central Public Sector 8 CPSUs Undertakings Damodar valley 9 DVC Corporation High Voltage Direct 10 HVDC Current Transmission Independent Power 11 IPP Producer 12 IR Inter Regional 13 kV Kilo Volts 14 kWh Kilo Watt Hours 15 MT Million Tonnes 16 MU Million Units 17 MVA Mega Volt Ampere 18 MW Mega Watt 19 NA Not Applicable 20 PLF Plant Load Factor Renewable Energy 21 RES Sources State Load Dispatch 22 SLDC Centre Transmission and 23 T&D Distribution 24 UTL. Utilities 25 w.r.t With Respect To Section A - Highlights of Power Sector SN Contents Page 1 Electricity Generation (Conventional Sources) for Feb-2021 (BU) 1 2 Generating Capacity Addition for Feb-2021 (MW) 2 3 List of Projects Commissioned in Feb-2021 3 4 All India Installed Capacity (MW) Region-wise as on 28-02-2021 3 5 All India Installed Capacity (MW) Sector-wise as on 28-02-2021 4 6 Transmission Lines Added during Feb-2021 (Ckms) 5 7 Transformation Capacity Addition during Feb-2021 (MVA) 6 8 Power Supply Position (Energy & Peak) in Feb-2021 7 9 Peak Shortage of Power Supply (MW) in Different Regions 8-9 10 All India PLF Sector-wise for Feb-2021 10 11 T & D and AT & C Losses (%) 12 All India Village Electrification 11 13 Average cost of Power & Average Realisation 14 All India Coal consumption for Power Generation (MT) 1. Electricity Generation for Feb-2021 (BU) Achievement Targets Achievement* % Change of Type Achievement Feb-20 Feb-21 Feb-21 w.r.t. Feb-2020 Thermal 89.300 95.764 91.034 1.9 Nuclear 3.172 2.929 2.649 -16.5 Hydro 8.435 7.047 7.251 -14.0 Bhutan Import 0.068 0.237 0.123 80.9 All India 100.98 105.98 101.06 0.1 *Provisional 101.08 101.06 101.06 101.04 101.02 101.00 BU 100.98 100.98 100.96 100.94 100.92 Feb-20 Feb-21 Electricity Generation During Apr-19 to Feb-20 & Apr-20 to Feb-21 (BU) Type Apr-19 to Feb-20 Apr-20 to Feb-21* % Change w.r.t Apr-19 to Feb-20 Thermal 959.935 925.143 -3.62 Nuclear 42.418 39.812 -6.14 Hydro 146.679 141.859 -3.29 Bhutan Import 5.688 8.664 52.32 All India 1,154.72 1,115.48 -3.40 * Provisional 1,400.00 1,154.72 1,200.00 1,115.48 1,000.00 800.00 BU 600.00 400.00 200.00 0.00 Apr-19 to Feb-20 Apr-20 to Feb-21* 1A Electricity Generation (Including Hydro as conventional) Feb-2021* Feb-2020 % Growth Generation from Growth in Growth in Growth in Generation from Renewable Generation from Generation from Conventional Total* Total Conventional Renewable Total Sources* Conventional Sources Renewable Sources Sources* Generation Generation Generation (BU) (BU) (BU) (BU) (BU) (BU) (%) (%) (%) 101.06 10.919 111.98 100.98 11.246 112.221 0.08 -2.91 -0.22 Note: * Tentative Electricity Generation (Including Hydro as Renewable Energy Sources) Feb-2021* Feb-2020 % Growth Generation from Growth in Growth in Growth in Generation from Renewable Generation from Generation from Conventional Total* Total Conventional Renewable Total Sources* Conventional Sources Renewable Sources Sources* Generation Generation Generation (BU) (BU) (BU) (BU) (BU) (BU) (%) (%) (%) 93.81 18.170 111.98 92.54 19.681 112.221 1.37 -7.68 -0.22 Note: * Tentative All India Generation From Renewables (All Figures are in MU) Source-Wise All India For the Month of Cummulative for the period Sl.No. Generation from Renewables Jan-2021 Jan-2020 Apr-20 to Jan-21 Apr-19 to Jan-20 1 Wind 3562.30 3319.95 53745.27 57721.89 2 Solar 4865.41 4612.72 48212.20 39407.14 3 Biomass 339.05 273.21 2876.69 2347.05 4 Bagasse 2005.00 1906.91 7965.38 7741.14 5 Small Hydro 574.17 562.16 9342.72 8255.16 6 Others 164.50 23.95 1285.88 300.26 Total : 11510.43 10698.90 123428.14 115772.64 Note: 1) All figures are provisional 1B 2. Generating Capacity Addition for Feb-2021 (MW) Achievement Targets Achievement % Achivement Type Feb-20 Feb-21 w.r.t. Feb-2020 Thermal 0 250 1300 NA Hydro 300 0 150 NA Nuclear 0 0 0 NA All India 300 250 1450 NA NA- Not Applicable 1600 1,450.0 1400 1200 1000 800 600 400 300.0 200 0 Feb-20 1 Feb-21 Generating Capacity Addition during Apr-19 to Feb-20 & Apr-20 to Feb-21 Apr-19 to Feb-20 Apr-20 to Feb-21 % Change w.r.t Previous Year Thermal 5445.00 3336.15 -38.7 Hydro 300.00 510.00 NA Nuclear 0.00 0.00 NA All India 5745.00 3846.15 -33.1 NA- Not Applicable 7000.00 6000.00 5000.00 4000.00 3000.00 2000.00 1000.00 0.00 Apr-19 to Feb-20 Apr-20 to Feb-21 2 3. List of Projects Commissioned During Feb-2021 1 Thermal i) Neyveli New TPP Unit 2 Thermal (Lignite), Central Sector of 500 MW was commissioned on 03.02.2021 in Tamil Nadu ii) Gadarwara STPP Unit 2 Thermal (Coal), Central Sector of 800 MW was commissioned on 16.02.2021 in Madhya Pradesh 2 Hydro Kameng HEP Unit 4 , Hydro, Central Sector of 150 MW was commissioned on 11.02.2021 in Arunachal Pradesh. 3 Nuclear NIL 4. All India Installed Capacity (MW) Region-wise as on 28-02-2021 Thermal Nuclear Hydro RES** Grand Total Region Coal Lignite Gas Diesel Total Northern 54097.79 1580.00 5781.26 0.00 61459.05 1620.00 20288.77 18259.23 101627.05 Western 74295.12 1400.00 10806.49 0.00 86501.61 1840.00 7562.50 28630.62 124534.73 Southern 44634.52 3640.00 6491.80 433.66 55199.99 3320.00 11774.83 44094.34 114389.16 Eastern 27287.05 0.00 100.00 0.00 27387.05 0.00 4639.12 1581.90 33608.07 North-East 770.02 0.00 1776.96 36.00 2582.98 0.00 1944.00 369.17 4896.14 Islands 0.00 0.00 0.00 40.05 40.05 0.00 0.00 35.22 75.27 ALL INDIA 201084.50 6620.00 24956.51 509.71 233170.72 6780.00 46209.22 92970.48 379130.41 ** RES as on 28.02.2021 400000.00 Total = 379130.413 379130.41 350000.00 300000.00 250000.00 233170.72 200000.00 150000.00 92970.48 100000.00 46209.22 54932 50000.00 6780.00 0.00 Thermal Nuclear Hydro RES Total Captive Thermal Nuclear Hydro RES Total Captive Note: Captive Genaration is not included in the Total *Captive Power capacity as on 31.03.2018 3 5.
Recommended publications
  • PUBLIC ADDRESS SYSTEM for PFBR BHAVINI, Kalpakkam
    BHARATIYA NABHIKIYA VIDYUT NIGAM LIMITED (A Government of India Enterprise) Kalpakkam – 603 102, Kancheepuram District, Tamil Nadu. Tender No - BHAVINI/IT/08/111/10 Name of Work PUBLIC ADDRESS SYSTEM FOR PFBR BHAVINI, Kalpakkam. BHARATIYA NABHIKIYA VIDYUT NIGAM LIMITED (A Government of India Enterprise) Kalpakkam - 603 102, Kancheepuram Dist. (TN) Tender No: BHAVINI /IT/08/111/10 Submission of Tender upto Opening of Tender Date Tim e Date Time 03.12.2008 14:00 hrs 03.12.2008 15:00 hrs Important Notes: • Tender forms shall be signed at the appropriate places by the intending tenderers. • The tenderer shall submit their offer in original Tender documents without changing the Tender format which satisfies each and every condition laid down in the tender documents, failing which the tender is liable to be rejected. • Contractor shall furnish the unconditional bid undertaking failing which their tender shall be considered incomplete and liable for rejection summarily. • This tender document should be returned with all papers intact without detaching any part of it. Tender Issued to M/s. …………………………………………………. By …………………………………………………… BHARATIYA NABHIKIYA VIDYUT NIGAM LIMITED (A Government of India Enterprise) Kalpakkam Name of the work: Design, material, construction features, engineering, manufacture, packing, transportation, delivery, unloading, safe storage, installation, testing, commissioning, training, documentation & guarantee of Public Address system for 500MWe Prototype Fast Breeder Reactor(PFBR) BHAVINI, Kalpakkam, Kancheepuram District,
    [Show full text]
  • List of Abbreviations
    LIST OF ABBREVIATIONS S. No. 1. A&N Andaman & Nicobar 2. ACO Assistant Committee Officer 3. AEES Atomic Energy Education Society 4. AeBAS Aadhaar enabled Biometric Attendance System 5. AIIMS All India Institute of Medical Sciences 6. AIU Association of Indian Universities 7. AMC Annual Maintenance Contract 8. ARO Assistant Research Officer 9. ASEAN Association of South-East Asian Nations 10. ASGP Association of Secretaries-General of Parliaments 11. ASI Archaeological Survey of India 12. ASSOCHAM Associated Chambers of Commerce and Industry of India 13. ATNs Action Taken Notes 14. ATRs Action Taken Reports 15. AWS Automatic Weather Station 16. AYCL Andrew Yule & Company Ltd. 17. AYUSH Ayurvedic, Yoga and Naturopathy, Unani, Siddha and Homeopathy 18. BCD Basic Customs Duty 19. BEML Bharat Earth Movers Limited 20. BHAVINI Bhartiya Nabhikiya Vidyut Nigam Ltd. 21. BHEL Bharat Heavy Electricals Ltd. 22. BHMRC Bhopal Memorial Hospital & Research Centre 23. BIOS Bills Information Online System 24. BIS Bureau of Indian Standards 25. BMRCL Bangalore Metro Rail Corporation Ltd. 26. BOAT Board of Apprentice Ship Training 27. BOB Bank of Baroda 28. BPCL Bharat Petroleum Corporation Limited 29. BPST Bureau of Parliamentary Studies and Training 30. BRO Border Roads Organisation 31. BSF Border Security Force 32. BSNL Bharat Sanchar Nigam Limited 33. C&AG Comptroller & Auditor General 34. CARA Central Adoption Resource Authority 35. CAT Central Administrative Tribunal 36. CBI Central Bureau of Investigation 37. CBRN Chemical Biological Radiological Nuclear 38. CBDT Central Board of Direct Taxes 39. CCL Child Care Leave 40. CCRYN Central Council for Research in Yoga and Naturopathy 41. CCS Central Civil Services 42.
    [Show full text]
  • Expenditure Budget Vol. I, 2015-2016
    Expenditure Budget Vol. I, 2015-2016 49 STATEMENT 14 PLAN INVESTMENT IN PUBLIC ENTERPRISES (In crores of Rupees) Actuals 2013-2014 Budget 2014-2015 Revised 2014-2015 Budget 2015-2016 S.No. Name of Enterprise/Undertaking Total Plan Budget Support Total Plan Budget Support Total Plan Budget Support Total Plan Budget Support Outlay Outlay Outlay Outlay Equity Loans Equity Loans Equity Loans Equity Loans Ministry of Agriculture 24.66 ... 24.66 ... ... ... 10.00 ... 10.00 12.00 ... 12.00 Department of Agriculture and Cooperation 24.66 ... 24.66 ... ... ... 10.00 ... 10.00 12.00 ... 12.00 1. Land Development Banks 24.66 ... 24.66 ... ... ... 10.00 ... 10.00 12.00 ... 12.00 Department of Atomic Energy 5068.14 329.60 ... 8320.62 371.00 422.00 6860.73 158.50 319.00 10045.92 418.00 422.00 2. Bharatiya Nabhikiya Vidyut Nigam Limited 289.60 289.60 ... 440.00 40.00 400.00 354.63 ... 300.00 440.00 40.00 400.00 (BHAVINI) 3. Electonics Corporation of India Limited 39.28 ... ... 27.50 ... ... 27.50 ... ... 25.00 ... ... 4. Indian Rare Earths Limited 22.09 ... ... 65.70 ... ... 67.80 ... ... 65.14 ... ... 5. Nuclear Power Corporation of India Limited 4675.73 ... ... 7446.42 181.00 22.00 6227.50 72.50 19.00 9095.00 178.00 22.00 (NPCIL) 6. Uranium Corporation of India Limited 41.44 40.00 ... 341.00 150.00 ... 183.30 86.00 ... 420.78 200.00 ... Ministry of Ayurveda, Yoga and Naturopathy, ... ... ... 8.60 8.60 ... ... ... ... ... ... ... Unani, Siddha and Homoeopathy (AYUSH) 7. Homeopathic Medicines Pharmaceutical Co.
    [Show full text]
  • Expenditure Budget Vol. I, 2013-2014 53 STATEMENT 15 RESOURCES of PUBLIC ENTERPRISES (In Crores of Rupees) Revised 2012-2013 Budget 2013-2014 S.No
    Expenditure Budget Vol. I, 2013-2014 53 STATEMENT 15 RESOURCES OF PUBLIC ENTERPRISES (In crores of Rupees) Revised 2012-2013 Budget 2013-2014 S.No. Name of Enterprise/Undertaking Internal Bonds/ E.C.B/ Others Total Internal Bonds/ E.C.B/ Others Total Resources Debentures Suppliers Resources Debentures Suppliers Credit Credit Department of Atomic Energy 2707.55 2927.00 ... 110.00 5744.55 3534.30 4257.68 ... 207.08 7999.06 1. Bharatiya Nabhikiya Vidyut Nigam Limited (BHAVINI) ... ... ... 60.00 60.00 ... 7.68 ... 107.08 114.76 2. Electonics Corporation of India Limited 44.00 ... ... ... 44.00 36.50 ... ... ... 36.50 3. Indian Rare Earths Limited 122.05 ... ... ... 122.05 100.30 ... ... ... 100.30 4. Nuclear Power Corporation of India Limited (NPCIL) 2523.00 2927.00 ... 50.00 5500.00 3130.50 4250.00 ... 100.00 7480.50 5. Uranium Corporation of India Limited 18.50 ... ... ... 18.50 267.00 ... ... ... 267.00 Ministry of Chemicals and Fertilisers 2971.75 ... ... ... 2971.75 2770.71 ... ... ... 2770.71 Department of Fertilisers 2971.75 ... ... ... 2971.75 2770.71 ... ... ... 2770.71 6. Fertilizer Corporation of India (FAGMIL) 11.11 ... ... ... 11.11 44.05 ... ... ... 44.05 7. Krishak Bharti Cooperative Ltd. 522.00 ... ... ... 522.00 927.00 ... ... ... 927.00 8. National Fertilizers Ltd. 2087.94 ... ... ... 2087.94 803.20 ... ... ... 803.20 9. Projects and Development (India) Ltd. 5.57 ... ... ... 5.57 18.17 ... ... ... 18.17 10. Rashtriya Chemicals and Fertilizers Ltd. 345.13 ... ... ... 345.13 978.29 ... ... ... 978.29 Ministry of Civil Aviation -161.93 ... 508.59 2741.56 3088.22 1230.49 ... 539.27 1895.64 3665.40 11.
    [Show full text]
  • Quality Assurance in BHAVINI
    Prabhat Kumar Indian Society for Proc. National Seminar on Non-Destructive Testing Non-Destructive Evaluation Hyderabad Chapter Dec. 7 - 9, 2006, Hyderabad Quality Assurance in BHAVINI Prabhat Kumar Project Director, PFBR & Director (Construction), BHAVINI Kalpakkam – 603 102, India 1. Abstract: Fast Breeder Test Reactor (FBTR) operating at IGCAR since 1985 is testimony of maturity India has attained in Fast Breeder Technology. The reactor has operated exceedingly well thus established the competence of Indian engineers in handling this difficult technology where large quantity of sodium is used for cooling of reactors. INDIA took quantum leap from 40 MWe FBTR to launch of 500 MWe Fast Breeder Reactor. This was possible with strong R&D backbone that DAE has established and manufacturing infrastructure that Indian Industries have developed. Competence of Indian scientists and engineers is second to none in taking on any challenge. Quality of construction presently in progress at PFBR is the outcome of this technological excellence Indians have attained at all fronts. The First of its type technology for PFBR has many first of its type materials to be processed, several new manufacturing techniques to be used, and novel construction techniques to be deployed besides commissioning challenges to be met for the first commercial fast breeder reactor. Being commercial venture, the first of its type Fast Breeder Reactor itself has requirement of meeting time and cost targets in parallel to meeting technological challenges. At BHAVINI R&D and construction professionals work together in mission mode to accomplish the technological needs within stringent time and cost targets. PFBR is thus a role model in handling new technologies where experts have been drawn from different organizations to work together with their organizational backing to work in mission mode and to take fast Breeder technology to success.
    [Show full text]
  • Executive Summary
    Report No. 21 of 2015 (Volume I) EXECUTIVE SUMMARY I Introduction 1. This Report includes important audit findings noticed as a result of test check of accounts of records of Central Government Companies and Corporations conducted by the officers of the Comptroller and Auditor General of India under Section 619(3) of the Companies Act, 1956 or the statutes governing the particular Corporations. 2. The Report contains 31 individual observations relating to 28 PSUs under 7 Ministries/Departments. The draft observations were forwarded to the Secretaries of the concerned Ministries/Departments under whose administrative control the PSUs are working to give them an opportunity to furnish their replies/comments in each case within a period of six weeks. Replies to 15 observations were not received even as this Report was being finalised. Earlier, the draft observations were sent to the Managements of the PSUs concerned, whose replies have been suitable incorporated in the report. 3. The paragraphs included in this Report relate to the PSUs under the administrative control of the following Ministries/Departments of the Government of India: Ministry/Department (Number of Number of Number of paragraphs PSUs involved paragraphs in respect of which Ministry/Department’s reply was awaited 1. Atomic Energy 3 1 (BHAVINI, NPCIL and UCIL) 2. Civil Aviation 8 7 (AAI, AICL, ACIL and AIL) 3. Coal 3 1 (BCCL and SECL) 4. Commerce and Industry 5 1 (NINL, MMTC, PEC, STC and STCL) 5. Consumer Affairs, Food and Public 5 1 Distribution (CWC and FCI) 6. Development of North Eastern 1 0 Region (NERAMAC) 7.
    [Show full text]
  • PHYSICAL and FINANCIAL PERFORMANCE of POWER GENERATING Psus – a HORIZONTAL STUDY
    PHYSICAL AND FINANCIAL PERFORMANCE OF 17 POWER GENERATING PSUs - A HORIZONTAL STUDY MINISTRY OF POWER MINISTRY OF NEW AND RENEWABLE ENERGY DEPARTMENT OF ATOMIC ENERGY COMMITTEE ON PUBLIC UNDERTAKINGS (2012-2013) SEVENTEENTH REPORT (FIFTEENTH LOK SABHA) LOK SABHA SECRETARIAT NEW DELHI CPU. No. 950 17 SEVENTEENTH REPORT COMMITTEE ON PUBLIC UNDERTAKINGS (2012-2013) (FIFTEENTH LOK SABHA) PHYSICAL AND FINANCIAL PERFORMANCE OF POWER GENERATING PSUs – A HORIZONTAL STUDY MINISTRY OF POWER MINISTRY OF NEW AND RENEWABLE ENERGY DEPARTMENT OF ATOMIC ENERGY (Action taken by the Government on the Observations/Recommendations contained in the Thirty-fourth Report of the Committee on Public Undertakings (Fourteenth Lok Sabha) on Physical and Financial Performance of Power Generating PSUs – A Horizontal Study) Presented to Lok Sabha on 21.03.2013 Laid on the Table of Rajya Sabha on 21.03.2013 LOK SABHA SECRETARIAT NEW DELHI March 2013 / Phalguna 1934 (S) CONTENTS Page No. COMPOSITION OF THE COMMITTEE (2012-13) (iii) INTRODUCTION (v) CHAPTER I Report 6 CHAPTER II Observations/Recommendations which have 15 been accepted by Government CHAPTER III Observations/Recommendations which the 46 Committee do not desire to pursue in view of the Government Replies CHAPTER IV Observations/Recommendations in respect of 48 which replies of the Government have not been accepted by the Committee and which require reiteration CHAPTER V Observations/Recommendations in respect of 64 which final replies of the Government are still awaited APPENDIX Minutes of the Sitting of the Committee held on 66 19.3.2013 ANNEXURES I Annexure to the reply of Recommendation No. 24 68 II Analysis of the action taken by Government on 79 the Observations / Recommendations contained in the Thirty-fourth Report of COPU (Fourteenth Lok Sabha) on Physical and Financial Performance of Power Generating PSUs - A Horizontal Study (i) COMMITTEE ON PUBLIC UNDERTAKINGS (2012 – 2013) Chairman Shri Jagdambika Pal Members, Lok Sabha 2.
    [Show full text]
  • Human Reliability Program in Industries of National Importance Jointly Organised by Nias, India and Texas A&M University, Usa
    M. Sai Baba Sunil S. Chirayath SUMMARY OF THE MEETINGS ON HUMAN RELIABILITY PROGRAM IN INDUSTRIES OF NATIONAL IMPORTANCE JOINTLY ORGANISED BY NIAS, INDIA AND TEXAS A&M UNIVERSITY, USA NATIONAL INSTITUTE OF ADVANCED STUDIES Bengaluru, India January 2021 Report NIAS/NSE/U/MR/02/2021 Summary of the Meetings on Human Reliability Program in Industries of National Importance Jointly organised by NIAS, India and Texas A&M University, USA M. Sai Baba Sunil S. Chirayath NATIONAL INS TITUTE OF TEXAS A&M UNIVERS ITY USA ADVANCED STUDIES Bengaluru, India © National Institute of Advanced Studies, January 2021 Published by National Institute of Advanced Studies Indian Institute of Science Campus Bengaluru - 560 012 Tel: 2218 5000, Fax: 2218 5028 E-mail: [email protected] NIAS Report: NIAS/NSE/U/MR/02/2021 Typeset & Printed by Aditi Enterprises [email protected] Preface Human Reliability (to describe human performance) is widely used in fields requiring high standards of safety, such as aviation, petroleum and chemical processes, and nuclear industries. Human behavior always poses an inherent risk through our actions or inactions. Introducing errors into the operation of a system or process. Human factors can either positively or negatively affect the performance in workplace. Although human errors can be minimized through education and training/retraining programs, there are some human actions (insider actions) that could be intentional, which compromise the safety and security at the workplace due to ideological, economic, political, or personal motivations. A Human Reliability Program (HRP) could ensure that individuals who occupy positions with access to critical assets/operations/sites meet the highest standards so that they adhere to safety and security rules and regulations (reliability), ensure confidence in individuals based on their character (trustworthiness) and their physical and mental stability.
    [Show full text]
  • ANNUAL REPORT 2018 an OVERVIEW L Central Vigilance Commission Is the Apex Integrity Institution of India, Created in 1964 to Address Governmental Corruption
    ANNUAL REPORT 01.01.2018 to 31.12.2018 CENTRAL VIGILANCE COMMISSION Annual Report 2018 i Shri K.V. Chowdary Central Vigilance Commissioner Dr. T.M. Bhasin Shri Sharad Kumar Vigilance Commissioner Vigilance Commissioner ii Annual Report 2018 The 55th Annual Report of the Central Vigilance Commission is prepared under Section 14 of the CVC Act, 2003 for submission to the President of India. The report highlights the work done by the Central Vigilance Commission during the year ending 31st December, 2018 in fulfilling its mandate under the CVC Act, 2003. (K.V. CHOWDARY) CENTRAL VIGILANCE COMMISSIONER (Dr. T.M. BHASIN) (SHARAD KUMAR) VIGILANCE COMMISSIONER VIGILANCE COMMISSIONER New Delhi Dated: the 6th June, 2019 Annual Report 2018 iii ACKNOWLEDGEMENT The Central Vigilance Commission thanks the Government of India, its Ministries/Departments, Public Sector Undertakings, Public Sector Banks and other organizations, the team of Chief Vigilance Officers, Central Bureau of Investigation, Law Officers, the Whistle Blowers and all others connected with the Commission for their cooperation and assistance. iv Annual Report 2018 CONTENTS Chapter Description Pages 1 Mandate of the Commission 1-9 2 Commission’s Activities during 2018 11-29 3 Superintendence over Vigilance Administration 31-45 4 Non-Compliance of Commission’s advice and other Areas of Concern 47-92 5 Chief Technical Examiners’ Organisation 95-98 6 Superintendence over Central Bureau of Investigation 101-113 7 Preventive Vigilance and Systemic Improvements 115-141 8 Participative Vigilance
    [Show full text]
  • TENDER DOCUMENT for INDIGENOUS SUPPLY Tender No: BHAVINI/CMM/ TECH/1/80/2018/10002549
    BHARATIYA NABHIKIYA VIDYUT NIGAM LIMITED (A Government of India Enterprise) Kalpakkam – 603 102. Kancheepuram Dt. (TN) TENDER DOCUMENT FOR INDIGENOUS SUPPLY Tender No: BHAVINI/CMM/ TECH/1/80/2018/10002549 Downloading of Tender starts from - 27.06.2018 Last date for downloading of Tender up to - 31.07.2018 Date of Pre-bid meeting at 11.00 Hours - 23.07.2018 Due date for submission of tender in online up to 15.00 Hours - 31.07.2018 Date and time for opening of tender on 31.07.2018 at 15.30 Hours Your bid must be submitted in E-mode at our BHAVINI E-Tendering Web site i.e., https:\\bhavini.etenders.in . On or before the due date and time mentioned above. COST OF TENDER DOCUMENT Rs. 590/- (inclusive of Tax) BHARATIYA NABHIKIYA VIDYUT NIGAM LIMITED (A Government of India Enterprise) Kalpakkam – 603 102, Kancheepuram Dt. (TN) PUBLIC TENDER DOCUMENT FOR SUPPLY (PACKAGE) Tender No: BHAVINI/CMM/ TECH/1/80/2018/10002549 Downloading of Tender starts from - 27.06.2018 Last date for downloading of Tender up to - 31.07.2018 Date of Pre-bid meeting at 11.00 Hours - 23.07.2018 Due date for submission of tender in online up to 15.00 Hours - 31.07.2018 Date and time for opening of tender on 31.07.2018 at 15.30 Hours Your bid must be submitted in E-mode at our BHAVINI E-Tendering Web site i.e., https:\\bhavini.etenders.in . On or before the due date and time mentioned above. BHARATIYA NABHIKIYA VIDYUT NIGAM LIMITED (A Government of India Enterprise) Kalpakkam – 603 102, Kancheepuram Dt.
    [Show full text]
  • DEPARTMENT of ATOMIC ENERGY DEMAND NO. 3 Atomic Energy
    Notes on Demands for Grants, 2021-2022 9 DEPARTMENT OF ATOMIC ENERGY DEMAND NO. 3 Atomic Energy (In ` crores) Actual 2019-2020 Budget 2020-2021 Revised 2020-2021 Budget 2021-2022 Revenue Capital Total Revenue Capital Total Revenue Capital Total Revenue Capital Total Gross 15416.36 9463.73 24880.09 15797.10 10894.60 26691.70 15225.28 7512.44 22737.72 16392.20 11403.20 27795.40 Recoveries -109.56 -1388.24 -1497.80 -99.74 -1550.10 -1649.84 -99.74 -1550.10 -1649.84 -106.17 -1527.43 -1633.60 Receipts -3577.60 ... -3577.60 -6812.92 ... -6812.92 -6812.92 ... -6812.92 -7896.91 ... -7896.91 Net 11729.20 8075.49 19804.69 8884.44 9344.50 18228.94 8312.62 5962.34 14274.96 8389.12 9875.77 18264.89 A. The Budget allocations, net of recoveries and receipts, are given below: CENTRE'S EXPENDITURE Establishment Expenditure of the Centre 1. Secretariat 60.10 ... 60.10 66.00 ... 66.00 65.52 ... 65.52 69.25 ... 69.25 2. Atomic Energy Regulatory Board 73.60 ... 73.60 84.77 ... 84.77 75.79 ... 75.79 89.74 ... 89.74 3. Atomic Research Centres 3.01 Bhabha Atomic Research Centre 2544.67 ... 2544.67 2836.00 ... 2836.00 2376.09 ... 2376.09 2935.97 ... 2935.97 -45.52 ... -45.52 -30.50 ... -30.50 -30.50 ... -30.50 -30.50 ... -30.50 Net 2499.15 ... 2499.15 2805.50 ... 2805.50 2345.59 ... 2345.59 2905.47 ... 2905.47 3.02 Indira Gandhi Centre for Atomic Research, 460.61 ..
    [Show full text]
  • Nuclear 2013
    Venue: Hilton Mumbai International Airport Hotel India with its three stage nuclear program based on a closed fuel cycle and vast thorium reserves is striving to reach 20GW nuclear capacity by 2020. IAEA Director General, Yukiya Amano said, "For rapidly developing economy such as India, Nuclear power can make a vitally important contribution to growth and improve energy security.“ India views nuclear energy as an essential element of its national energy mix and is committed to taking decisive steps forward with 7 plants under construction and more than 60 plants are planned or being proposed. 3rd India Nuclear Energy Summit will welcome nuclear community to join this forum where the most prominent industry leaders and government officials will be providing informative and inspiring discussions pertaining to India's current needs, revealing technologies that can assist in achieving India’s ambitious future. Chairman of the 3rd India Nuclear Energy Summit Strategic Advisor Endorser Mr. A.K. Anand, Former Director - Reactor Projects Group, Bhabha Atomic Research Center (BARC) Confirmed Speakers Mr. Arun Srivastava, Mr. Anand Ghare, Secretary, Atomic Energy Commission & Member, Former Senior Executive Director, Projects Strategic Planning Group, Scientific Officer-H, Nuclear Power Corporation of India Limited Department of Atomic Energy (DAE) (NPCIL) Mr. S. Duraisamy, Mr. Dr. K.C. Pillai, Vice-Chairman, Former Head – Health Physics Division Atomic Energy Regulatory Board Bhabha Atomic Research Centre (AERB) (BARC) Mr. Preman Dinaraj, Mr. K.J. Sebastian, Director, Finance, Nuclear Power Corporation of Managing Director, India Limited (NPCIL) Power Age Engineering Consultants Chairman, NPCIL-NALCO Power Company (PAEC) Mr. Dr. Prabhat Kumar, Mr.
    [Show full text]