<<

VALLEY & SPRUCE PROJECT

INITIAL STUDY AND MITIGATED NEGATIVE DECLARATION

Prepared for: City of Rialto

December 2017

VALLEY & SPRUCE PROJECT

INITIAL STUDY AND MITIGATED NEGATIVE DECLARATION

Prepared For:

City of Rialto 150 . Palm Avenue Rialto, CA 92376

Prepared By:

Kimley-Horn and Associates, Inc. 401 B Street, Suite 600 San Diego, California 92101

December 2017

095894012 Copyright © 2017 Kimley-Horn and Associates, Inc.

TABLE OF CONTENTS . Initial Study ...... 1 II. Description of Proposed Project ...... 2 III. Required Permits ...... 8 IV. Environmental Factors Potentially Affected ...... 9 . Determination ...... 9 VI. Environmental Evaluation ...... 10 1. Aesthetics ...... 10 2. Agricultural and Forestry Resources ...... 14 3. Air Quality ...... 17 4. Biological Resources ...... 24 5. Cultural Resources ...... 29 6. Geology and Soils ...... 34 7. Greenhouse Gas Emissions ...... 39 8. Hazards and Hazardous Materials ...... 41 9. Hydrology and Water Quality ...... 44 10. Land Use and Planning ...... 48 11. Mineral Resources ...... 50 12. Noise ...... 52 13. Population and Housing ...... 65 14. Public Services ...... 67 15. Recreation ...... 70 16. Transportation/Traffic ...... 71 17. Tribal Cultural Resources ...... 88 18. Utilities and Service Systems ...... 90 19. Mandatory Findings of Significance ...... 96 VII. Preparers...... 98 VIII. References ...... 98

Valley & Spruce Project| i

LIST OF FIGURES Figure 1: Regional Location Map ...... 4 Figure 2: Project Vicinity Map ...... 5 Figure 3: Site Plan ...... 6 Figure 4: Conceptual Landscape Plan ...... 7 Figure 5: Maximum Truck Traffic Vibration Levels vs. Distance ...... 62

LIST OF TABLES Table 1: Attainment Status of the South Coast Air Basin ...... 18 Table 2: SCAQMD Daily Emissions Thresholds ...... 18 Table 3: Construction Emissions Summary and Significance Evaluation ...... 19 Table 4: Operational Emissions Summary and Significance Evaluation ...... 20 Table 5: Health Risk Results – Valley and Spruce Avenue Warehouse ...... 22 Table 6: CNDDB Species Habitat Assessment Results ...... 25 Table 7: GHG Emissions Summary and Significance Evaluation ...... 40 Table 8: Existing (Ambient) Short-Term Noise Level Measurements1,3 ...... 55 Table 9: Existing (Ambient) Long-Term (24-hour) Noise Level Measurements1 ...... 55 Table 10: Construction Equipment Noise Levels ...... 56 Table 11: Summary of Project Onsite Operations Maximum Noise Levels ...... 58 Table 12: Traffic Noise Levels – 2019 Project Contributions ...... 59 Table 13: Caltrans Vibration Damage Potential Threshold Criteria ...... 60 Table 14: Caltrans Vibration Annoyance Potential Criteria ...... 60 Table 15: FTA Vibration Annoyance Potential Criteria ...... 60 Table 16: Construction Equipment Vibration Levels ...... 63 Table 17: City of Rialto Roadway Capacity ...... 72 Table 18: Summary of Intersection Operations, Existing Conditions ...... 74 Table 19: Summary of Roadway Analysis, Existing Conditions ...... 75 Table 20: Summary of Intersection Operation, Opening Year (2019) Existing Plus Growth ...... 76 Table 21: Summary of Roadway Analysis, Opening Year (2019) Existing Plus Growth ...... 77 Table 22: Summary of Intersection Operation, Opening Year (2019) - Cumulative Without Project .. 78 Table 23: Summary of Roadway Analysis, Opening Year (2019) - Cumulative Without Project ...... 79 Table 24: Summary of Project Trip Generation ...... 80

Valley & Spruce Project| ii

Table 25: Summary of Intersection Operation, Opening Year (2019) - Existing Plus Growth ...... 81 Table 26: Summary of Roadway Analysis, Opening Year (2019) – Existing Plus Growth Plus Project 82 Table 27: Summary of Intersection Operation, Opening Year (2019) Cumulative Plus Project ...... 83 Table 28: Summary of Roadway Analysis, Opening Year (2019) Cumulative Plus Project ...... 84 Table 29: Peak Hour Link Analysis, Opening Year (2019) Cumulative Plus Project ...... 85 Table 30: Estimated Wastewater Generation ...... 92 Table 31: WVWD Minimum Three Year Supply 2016-2018 ...... 94 Table 32: WVWD Water Supply and Demands Estimates for years 2020-2040 ...... 94

APPENDICES . Air Quality, Greenhouse Gas and Health Risk Assessment Study B. Biotic Resources Report . Cultural Resource Study Findings Memorandum . Geotechnical Investigation . Phase I Environmental Site Assessment . Hydrology Calculations . Water Quality Management Plan . Noise & Vibration Study I-1. Traffic Impact Study I-2. Email Correspondence with County of San Bernardino Dated 8/14/2017 Regarding Traffic Study Scoping

Valley & Spruce Project| iii

I. Initial Study

Background and Project Description

Project Title Valley & Spruce Project

Lead Agency Name and Address City of Rialto 150 S. Palm Avenue Rialto, CA 92376

Contact Person and Phone Number Gina Gibson-Williams, Planning Manager (909) 820-2535

Project Location The Valley & Spruce Project is located in the City of Rialto north of Interstate 10 (I-10) and west of Interstate 215 (I-215), as depicted in Figure 1, Regional Location Map. The overall Project site is located on approximately 16.91 acres at the southeast corner of Valley Boulevard and Spruce Avenue, as depicted in Figure 2, Project Vicinity Map.

Project Applicant PDC OC/IE LLC

General Plan Designation The City’s General Plan land use designation for the Project site is Business Park, Specific Plan Overlay (Gateway Specific Plan Area).

Zoning The current zoning for the Project site is Gateway Specific Plan (Industrial Park (I-P)).

Project Setting The Project site is located in a predominately industrial and commercial area. The land uses surrounding the Project site consist of a mix of uses including industrial, commercial, residential, a major transportation corridor, and schools. Immediately south of the proposed Project site is the Interstate 10 (I-10) and the Union Pacific Rail Yard, to the east and west are commercial, warehousing, and industrial uses, to the northwest are residential uses and a school, and to the north and northeast are an auto sales yard, vacant property, and a school.

Valley & Spruce Project| 1

II. Description of Proposed Project The proposed Valley & Spruce Project (proposed Project) is comprised of one 404,837 sf warehouse distribution building with approximately 5,000 sf of office space and associated parking and landscaping on approximately 16.9 acres as shown in Figure 3, Site Plan and Figure 4, Conceptual Landscape Plan. The proposed project would require a Precise Plan of Design (PPD); a Variance to allow for a maximum building height of 47 feet; a Tentative Parcel Map (TPM) to allow for parcel consolidation; and a Conditional Development Permit (CDP) to allow for site development within 300 feet of a of public education facility. For additional information regarding the requested land use entitlements, please reference Section III, Required Permits. The industrial warehouse building would be one level and would include 49 dock doors and two drive thru doors on the southern side of the building. South of the building, adjacent to the dock doors, would be 69 trailer parking spaces. Surface parking totaling 220 standard stalls and 5 dedicated ADA stalls, would be located on both the eastern, western and southern sides of the building. Landscaping in the amount of 91,026 sf is anticipated for the site. Roadway frontage improvements including sidewalk, curb and gutter improvements would be provided along Spruce Avenue, Valley Boulevard and Cactus Avenue as well as the removal or relocation of existing street lights and power poles along Spruce Avenue and Cactus Avenue. The proposed industrial warehouse Project is currently planned as a “speculative building.” Therefore, the future tenants of the building are not currently known. Without knowing the future tenants, an exact number of future employees or hours of operation cannot be determined. Therefore, this Initial Study and associated technical reports use approximate potential on-site employees, hours of operation, and vehicular traffic generation based on the Project’s proposed square footage and use as warehouse distribution buildings. In an abundance of caution, this Initial Study and the associated technical reports have assumed uses and intensities that may be greater than what might actually be expected at buildout and operation, resulting in a possible conservative/worst-case estimation of impacts.

Access and Parking Vehicular access provisions for the Project site would consist of four full movement driveways, two would be located on Cactus Avenue and two on Spruce Avenue. No access is proposed on Valley Boulevard. The south driveways on both Spruce Avenue and Cactus Avenue would be for trucks and passenger vehicles and the north driveways on Spruce Avenue and Cactus Avenue would be for passenger vehicles. All Project driveways would be unsignalized. Street improvements would be provided along Spruce Avenue, Valley Boulevard and Cactus Avenue to include improvements to curbs, gutters, sidewalks, street lights, traffic signal equipment and signing and striping as required. The proposed Project is expected to also include the relocation of the existing traffic signal at the intersection of Cactus Avenue and Valley Boulevard as well as a new traffic signal at the intersection of Spruce Avenue and Valley Boulevard.

Landscaping Proposed landscaping would cover approximately 12.4 percent or 91,026 sf of the site. Landscaping would be installed in all areas not devoted to buildings, parking, traffic and specific user requirements, in accordance with the City’s Municipal Code Section 18.61.250 and Section 18.61.270 which specify landscape design guidelines. Setbacks would be 25 feet along Valley Boulevard, Cactus Avenue and Spruce Avenue. There would be no setback on the southern portion of the site, adjacent to I-10.

Construction and Phasing Construction of the proposed Project is expected to commence in August 2018 with a construction duration of approximately 9 months and would be completed in one phase. Total grading for the proposed Project is estimated to require 91,555 cubic yards (cy) of cut and 91,555 cy of fill; earthwork would balance on-site and no import or export of soils is required.

Valley & Spruce Project| 2

Existing Project Site The Project site is located on Assessor Parcel No. (APN) 0253-251-01, 0253-251-02, 0253-251-03, 0253-251-04 and 0253-251-07. The Project site is currently a largely disturbed area comprised of disked non-native grassland vegetation with small developed patches comprised of sidewalks and cement pads. A former storage yard occupied the site until it was demolished/removed in September 2017. No structures are currently located on the site. There is existing utility access (water, sewer, electricity, gas) to the Project site.

Valley & Spruce Project| 3 Project Site

Rialto, CA

Source: Google Maps, 2017

FIGURE 1: Regional Location Map Valley & Spruce Project Rialto, CA Valley Blvd

Project Location Spruce Ave S Cactus Ave

10

Source: Google Earth, 2017

FIGURE 2: Project Vicinity Map Valley & Spruce Project Rialto, CA SIT E AREA In s .f . 736,753 s.f. In acres 16.9 ac BUILDING AREA Office 5,000 s.f. Warehouse 399,837 s.f. TOTAL 404,837 s.f. COVERAGE 54.9% s.f. AUTO PARKING REQUIRED Office: 1/250 s.f. 20 stalls Whse: 1st 10k @ 1/1,000 s.f. 10 stalls above 10k @ 1/2,000 s.f. 195 stalls TOTAL 225 stalls AUTO PARKING PROV IDED Standard (9 'x 20') 220 stalls Handicap (9 'x 20') 5 stalls TOTAL 225 stalls TRAILER PARKING PROV IDED FIGURE 3 - Site Plan Trailer (10' x 55') 69 stalls AXIM UM BUILDING HEIGHT ALLOWED Valley & Spruce Project Height - 35' (variance required) ANDSCAPE REQUIREM ENT Percentage - 10% Rialto, CA In s .f . 73,675 s.f. LANDSCAPE PROV IDED Percentage - 12.4% in s.f. 91,026 SETBACKS Valley Blvd. - 25' (Major Arterial) Spruce Ave. - 25' (Collector St.) Cactus Ave. - 25' (Collector St.) Side / Rear - 0 ZONING ORDINANCE FOR CITY Zoning Designation - Gatew ay Specific Plan Industrial Park (I- P) PLANTING LEGEND TREES SHRUBS GROUNDCOVER SYMBOL BOTANICAL/COMMON NAME SIZE QTY WUCOLS REMARKS SYMBOL BOTANICAL/COMMON NAME SIZE QTY WUCOLS REMARKS SYMBOL BOTANICAL/COMMON NAME SIZE SPACING WUCOLS REMARKS

Arbutus unedo 5 Gal 191 L Acacia redolens 'Low Boy' 1 Gal 6' .C. L Strawberry Tree Acacia Cercidium 'Desert Museum' 36" Box 22 L Multi Blue Palo Verde Calliandra californica 5 Gal 50 L Baccharis pilularis 1 Gal 24" O.C. L Baja Fairy Duster Coyote Bush

Lavendula 'Goodwin Creek Grey' 1 Gal 115 L Chilopsis linearis 24" Box 18 L Multi Carex praegracilis Seed Hydro- L Lavender Seed Desert Willow Cluster Field Sedge Leptospermum s. 'Ruby Glow' 5 Gal 298 L Lantana montevidensis 1 Gal 24" O.C. L New Zealand Tea Tree Purple and White Lantana Chitalpa tashkentensis 24" Box 52 L Standard Leucophyllum f. 'Green Cloud' Chitalpa 5 Gal 164 L Texas Ranger Leymus c. 'Canyon Prince' 1 Gal 24" O.C. L California Rye Grass Rhamnus californica 5 Gal 143 L Coffeeberry Cupaniopsis anacardioides 24" Box 22 M Standard Rosa californica 2 Gal 30" O.C. L Carrotwood California Wild Rose PLANTING LEGEND Rosmarinus o. 'Tuscan Blue' 5 Gal 123 L Rosemary SHRUBS GROUNDCOVER TREES Rosmarinus o. 'Prostratus' 1 Gal 30" O.C. L Salvia greggii SYMBOL BOTANICAL/COMMON NAME SIZE QTY WUCOLS REMARKS SYMBOL BOTANICAL/COMMON NAME SIZE5 Gal QTY201 WUCOLSL REMARKS SYMBOL BOTANICAL/COMMONProstrate Rosemary NAME SIZE SPACING WUCOLS REMARKS Heteromeles arbutifolia 15 Gal 12 L Multi Autumn Sage Toyon Arbutus unedo 5 Gal 191 L Acacia redolens 'Low Boy' 1 Gal 6' O.C. L Senna artemisioides Strawberry Tree 5 Gal 337 L Acacia Cercidium 'Desert Museum' 36" Box 22 L Multi Feathery Cassia BlueProsopis Palo Verde chiliensis 36" Box 2 M Standard Calliandra californica 5 Gal 50 L Baccharis pilularis 1 Gal 24" O.C. L Chilean Mesquite Sambucus mexicana Baja Fairy Duster 5 Gal 55 L Coyote Bush Mexican Elderberry Tristania conferta 15 Gal 17 M Standard Lavendula 'Goodwin Creek Grey' 1 Gal 115 L Chilopsis linearis 24" Box 18 L Multi Carex praegracilis Seed Hydro- L Brisbane Box LavenderWestingia fruticosa Seed Desert Willow 5 Gal 584 L Cluster Field Sedge LeptospermumCoast Rosemary s. 'Ruby Glow' 5 Gal 298 L Lantana montevidensis 1 Gal 24" O.C. L New Zealand Tea Tree Purple and White Lantana Chitalpa tashkentensis 24" Box 52 L Standard ACCENTSLeucophyllum f. 'Green Cloud' Chitalpa 5 Gal 164 L Texas Ranger Leymus c. 'Canyon Prince' 1 Gal 24" O.C. L SYMBOL BOTANICAL/COMMON NAME SIZE QTY WUCOLS REMARKS California Rye Grass Rhamnus californica Agave villmoriniana 5 Gal 143 L Coffeeberry 5 Gal 13 L Cupaniopsis anacardioides 24" Box 22 M Standard Agave Rosa californica 2 Gal 30" O.C. L Carrotwood Rosmarinus o. 'Tuscan Blue' California Wild Rose Anigozanthos flavidus 5 Gal5 Gal 12355 L L RosemaryKangaroo Paw Rosmarinus o. 'Prostratus' 1 Gal 30" O.C. L Salvia greggii Dasylerion wheeleri 5 Gal5 Gal 20124 L L Prostrate Rosemary Heteromeles arbutifolia 15 Gal 12 L Multi AutumnDesert Sage Spoon Toyon Senna artemisioides Hesperaloe parviflora 5 Gal5 Gal 337106 L L FeatheryRed Yucca Cassia Prosopis chiliensis 36" Box 2 M Standard Chilean Mesquite Muhlenbergia rigens Sambucus mexicana 5 Gal5 Gal55 173 L M Deergrass Mexican Elderberry Tristania conferta 15 Gal 17 M Standard Pennisetum s. 'Cupreum' 5 Gal 240 L Westingia fruticosa Brisbane Box Purple Fountain Grass 5 Gal 584 L Coast Rosemary

ACCENTS SYMBOL BOTANICAL/COMMON NAME SIZE QTY WUCOLS REMARKS

Agave villmoriniana 5 Gal 13 L Agave

Anigozanthos flavidus 5 Gal 55 L Kangaroo Paw

Dasylerion wheeleri 5 Gal 24 L Desert Spoon

Hesperaloe parviflora 5 Gal 106 L Red Yucca

Muhlenbergia rigens 5 Gal 173 M Deergrass

Pennisetum s. 'Cupreum' 5 Gal 240 L Purple Fountain Grass

N

0 20' 40' 80'

N Valley Blvd. & Spruce Ave. PDC OC/IE LPIV, LLC 711 FEE ANA STREET PLACENTIA, CA 92870 714.986.2400 FAX 714.986.2408 17-050 0 20' 40' 80' 09.13.17 Rialto, California FIGURE 4 - Conceptual Landscape Plan Valley & Spruce Project Valley Blvd. & Spruce Ave. PDC OC/IE LPIV, LLC 711 FEE ANA STREET PLACENTIA, CA 92870 714.986.2400 FAX 714.986.2408 Rialto,17-050 CA 09.13.17 Rialto, California

III. Required Permits The City of Rialto (City) is the Lead Agency under CEQA and is responsible for reviewing and approving this Initial Study. As part of the proposed Project’s implementation, the City will also consider the following discretionary approvals: ▪ Precise Plan of Design (PPD) ▪ Variance (for building height) ▪ Tentative Parcel Map (TPM) ▪ Conditional Development Permit (CDP) The PPD package is comprised of the following components: site plan, floor plan, roof plan, elevation plan, conceptual grading plan, preliminary Water Quality Management Plan, color elevations, color and materials board, and conceptual landscape plan. The Gateway Specific Plan designates a maximum building height of 35 feet per Section 18.35.030 of the Gateway Specific Plan. The requested building height variance to increase the maximum building height from 35 feet to a maximum building height of 47 feet would allow the Applicant to construct a state of the art industrial building which would be competitive in the marketplace and attract quality tenancy for the life of the asset. The TPM would allow for the consolidation of five parcels into one parcel. The CDP would allow for site development within 300 feet of a public education facility as the proposed Project site is located less than 300 feet southwest of Joe Baca Middle School and less than 300 feet south of Ruth Grimes Elementary School, per the requirements set forth in Section 18.35.020(C) of the Gateway Specific Plan. Additional permits may be required upon review of construction documents. Other permits required for the proposed Project may include the issuance of encroachment permits for new driveways, sidewalks, and utilities, walls, fences, security and parking area lighting; building permits; and permits for new utility connections. These additional permits are considered ministerial, and thus issuance of these permits would not trigger the need to further comply with CEQA. Development of the proposed Project does not require the issuance of any discretionary permits from any other federal, State, or local agency.

Valley & Spruce Project | 8

IV. Environmental Factors Potentially Affected The environmental factors checked below would be potentially affected by this project, involving at least one impact that is a "Potentially Significant Impact" or “Less Than Significant Impact with Mitigation Incorporated” as indicated by the checklist on the following pages. Aesthetics Agricultural and Forestry Air Quality Resources Biological Resources Cultural Resources Geology/Soils Greenhouse Gas Emissions Hazards and Hazardous Hydrology/Water Quality Materials Land Use/Planning Mineral Resources Noise Population/Housing Public Services Recreation Transportation/Traffic Tribal Cultural Resources Utilities/Service Systems Mandatory Findings of Significance V. Determination On the basis of this evaluation: I find that the proposed Project COULD NOT have a significant effect on the environment, and a NEGATIVE DECLARATION will be prepared. I find that although the proposed Project could have a significant effect on the environment, there will not be a significant effect in this case because revisions in the project have been made by or agreed to by the project proponent. A MITIGATED NEGATIVE DECLARATION will be prepared. I find that the proposed Project MAY have a significant effect on the environment, and an ENVIRONMENTAL IMPACT REPORT is required. I find that the proposed Project MAY have a "potentially significant impact" or "potentially significant unless mitigated" impact on the environment, but at least one effect 1) has been adequately analyzed in an earlier document pursuant to applicable legal standards, and 2) has been addressed by mitigation measures based on the earlier analysis as described on attached sheets. An ENVIRONMENTAL IMPACT REPORT is required, but it must analyze only the effects that remain to be addressed. I find that although the proposed Project could have a significant effect on the environment, because all potentially significant effects (a) have been analyzed adequately in an earlier EIR or NEGATIVE DECLARATION pursuant to applicable standards, and (b) have been avoided or mitigated pursuant to that earlier EIR or NEGATIVE DECLARATION, including revisions or mitigation measures that are imposed upon the proposed Project, nothing further is required. I find that although the proposed Project could have a significant effect on the environment, because all potentially significant effects (a) have been analyzed adequately in an earlier EIR or NEGATIVE DECLARATION pursuant to applicable standards, (b) none of the conditions described in Guidelines Section 15162 for a Subsequent EIR or Section 15163 for a Supplemental EIR have occurred and (c) only minor technical changes or additions to the previous environmental documents are necessary.

Signature Date Gina Gibson-Williams, Planning Manager For: City of Rialto

Valley & Spruce Project | 9

VI. Environmental Evaluation This section evaluates the potential environmental effects of the proposed Project using the environmental checklist from the State CEQA Guidelines as amended. The definitions of the response column headings include: A. “Potentially Significant Impact” is appropriate if there is substantial evidence that an effect may be significant after the implementation of feasible mitigation measures. B. “Less than Significant With Mitigation Incorporated” applies where the incorporation of mitigation measure has reduced an effect from “Potentially Significant Impact” to a “Less Than Significant Impact.” C. “Less Than Significant Impact” applies where the project creates no significant impacts, only Less than Significant Impacts. D. “No Impact” applies where the project does not create an impact in that category. 1. Aesthetics Less Than Potentially Significant Less than Significant with Mitigation Significant No Issues Impact Incorporated Impact Impact Would the project: a. Have a substantial adverse effect on a scenic

vista? b. Substantially damage scenic resources, including, but not limited to trees, rock

outcroppings, and historic buildings within a State-designated scenic highway? c. Substantially degrade the existing visual character or quality of the site and its surroundings? d. Create a new source of substantial light or glare which would adversely affect day or nighttime views in the area?

Discussion a) Have a substantial adverse effect on a scenic vista? Less Than Significant Impact. The proposed Project would not have a substantial adverse effect on a scenic vista. The applicant proposes the construction of one distribution warehouse building that would be a maximum of 47 feet in height. Development of the Project site would convert the mostly undeveloped land to an industrial use consistent with pertinent planning documents and adjacent surrounding land uses. The Project site is located at an elevation of approximately 1,077 feet above mean sea level (msl) and is in an area with flat topography. The land uses surrounding the Project site consist of a mix of uses including industrial, commercial, residential, a major transportation corridor, and schools. Immediately south of the proposed Project site is the Interstate 10 (I-10) and the Union Pacific Rail Yard, to the east and west are commercial, warehousing, and industrial uses, to the northwest are residential uses and a school, and to the north and northeast are an auto sales yard, vacant property, and a school. None of these areas, including the Project site contain any landforms that would be considered scenic.

Valley & Spruce Project | 10

The City of Rialto General Plan encourages the protection of scenic resources and views of the San Gabriel and San Bernardino Mountains, and the La Loma Hills, Jurupa Hills, Box Spring Mountains, Moreno Valley, and Riverside by limiting building heights. The General Plan lists two pertinent policies and they are as follows: Policy 2-14.1: Protect views of the San Gabriel and San Bernardino Mountains by ensuring that building heights are consistent with the scale of surrounding, existing development; and Policy 2-14.2: Protect views of the La Loma Hills, Jurupa Hills, Box Spring Mountains, Moreno Valley, and Riverside by ensuring that building heights are consistent with the scale of surrounding, existing development. The La Loma Hills, Jurupa Hills, Box Spring Mountains, Moreno Valley, and Riverside are located in a southerly direction from the Project site. Views of these areas from the proposed Project site and surrounding roadways are heavily obscured by intervening urban development including, structures, landscaping, and overhead utility lines. Implementation of the proposed Project would not result in a degradation of views to these areas. Impacts in this regard would be less than significant. The San Gabriel and San Bernardino Mountains are located approximately 15 miles to the north and east of the proposed Project site. Although partially obscured by intervening urban development including structures, landscaping, and overhead utilities, views of the San Gabriel and San Bernardino Mountains are afforded from the Project site and from Valley Boulevard, from Spruce Avenue, and Cactus Avenue. Views of the mountains from I-10, adjacent to the southern Project boundary are extremely limited. These views are from motorists traveling along the freeway at highway speed and the views are compromised and heavily obscured due to blocking objects including tall trees and vegetation on the southern Project boundary, and existing urban development. Therefore, although the proposed Project would result in a change to the visual environment and reduce the availability of some distant views, this change would not substantially affect the aesthetic nature of the proposed Project site, area, or the views from the proposed Project area. In addition, while the proposed Project would change the visual character of the site and alter views from some surrounding areas, these changes would not be considered to have a significant impact on a scenic vista. Because the views of the distant locations are already compromised, the further reduction in viewing opportunities are considered less than significant. No mitigation is required. b) Substantially damage scenic resources, including, but not limited to, trees, rock outcroppings, and historic buildings within a State scenic highway? No Impact. There are no State or County designated scenic highways proximate to the Project site.1 There are also no historically significant buildings on the site. The Project site does not contain any rock out-crops, but does have landscape trees scattered intermittently throughout the site. There also are thirteen trees within the eastern portion of the Project site. These trees would be removed as part of the proposed Project, but the trees along the southern Project boundary would remain. The City of Rialto does not have a preservation ordinance regarding the removal of trees on private property, therefore, the proposed Project would not conflict with

1 California Department of Transportation. Official Designated Scenic Highways. Available at: http://www.dot.ca.gov/hq/LandArch/16_livability/scenic_highways/index.htm. Accessed September 7, 2017

Valley & Spruce Project | 11

any regulations regarding removal of the trees located on-site. Additionally, the trees located on the Project site do not constitute a significant scenic or visual resource. Therefore, the proposed Project would not damage any scenic resources, including trees, rock outcroppings, or historic buildings and is not located near a State scenic highway. Impacts would not occur and mitigation is not required. c) Substantially degrade the existing visual character or quality of the site and its surroundings? Less than Significant Impact. The Project site is located in a predominately industrial and commercial area. The land uses surrounding the Project site consist of a mix of uses including industrial, commercial, residential, a major transportation corridor, and schools. Immediately south of the proposed Project site is the Interstate 10 (I-10) and the Union Pacific Rail Yard, to the east and west are commercial, warehousing, and industrial uses, to the northwest are residential uses and a school, and to the north and northeast are an auto sales yard, vacant property, and a school. The proposed Project would change the site appearance from a vacant parcel to one with a modern warehouse distribution facility. The aesthetic appearance of the site would be consistent with the intent of the Gateway Specific Plan, which zones the Project site as I-P (Industrial Park). As such, the proposed Project would be consistent with the existing and planned development. In addition, the proposed Project would conform to design guidelines intended to create a uniform and consistent theme within the overall plan area. Therefore, although the visual characteristics of the site would change, the proposed Project would be consistent with the surrounding areas, the intent of the Gateway Specific Plan, and with adopted development regulations. The proposed Project would not substantially impact or degrade the visual quality of the Project site or its surroundings. Impacts in this regard would be less than significant and no mitigation is required. Construction of the proposed Project may create temporary aesthetic nuisances associated with construction activities including demolition, grading, and construction and the presence of debris, equipment, and truck traffic. The visual impact associated with the construction of the proposed Project would be characteristic of a typical construction site of this scale. The temporary nature of these activities, would cease upon completion of construction, and would not result in a substantial degradation to the Project site or surrounding area. In addition, no significant aesthetic resources would be altered or destroyed as a result of construction- related activities. For these reasons, the short-term construction impacts of the proposed Project would be less than significant impact in relation to changing the visual character of the Project site and its surroundings. No mitigation is required. d) Create a new source of substantial light or glare which would adversely affect day or nighttime views in the area? Less Than Significant Impact. The existing sources of light and glare within the existing developed portion of the proposed Project and from the surrounding areas is consistent with a predominately urbanized area. Sources of glare during the day come from vehicle windshields, and windows on businesses and homes; and nighttime light comes from sources in the surrounding, commercial and industrial buildings, homes, schools, streets, intersections, and vehicles. The proposed Project would introduce new sources of light needed to illuminate the outside of the warehouse, building entrance areas, the parking lots, and vehicles on-site. Additionally, the proposed Project would create new sources of glare from reflection off windows and walls on new buildings, and reflection from windshields of vehicles and from new surface parking lots. The City of Rialto General Plan encourages the reduction of light and glare through the incorporation of the following policy: Policy 2-14.3: Ensure use of building materials that do not produce glare, such as polished metals or reflective windows.

Valley & Spruce Project | 12

As discussed above, the proposed Project would introduce additional nighttime lighting on the Project site, which would be visible from the surrounding area. The lighting used for the proposed Project would be consistent with the existing sources of nighttime lighting in the area from the surrounding uses and street lighting along Valley Boulevard, and at the intersections with Cactus Avenue and Spruce Avenue. As part of the lighting plan for the proposed Project, the lighting for the warehouse distribution building would be designed in accordance with the City’s Zoning Code and would comply with all applicable development standards. New sources of lighting would be shielded to minimize uplighting and to prevent light from shining directly onto adjacent properties. In addition, the proposed Project would not use building materials (i.e., reflective glass) or lighting that would cause a substantial new source of glare. Incorporation of these design features would ensure that the introduction of the new sources of light and glare associated within the proposed Project would be less than significant. No mitigation would be required. Cumulative Impacts The potential aesthetic impacts related to views and aesthetics are generally site specific. As discussed above, project-related impacts to scenic vistas would be less than significant, and the proposed Project would not result in any impacts to on-site visual resources because there are none. In addition, the proposed Project would also be consistent with the land use and development regulations contained in pertinent planning documents. Lighting and sources of glare, while not always site-specific, would be consistent with the majority of the surrounding urban area and would be used during similar hours as surrounding uses. Therefore, while the proposed Project in conjunction with past, present, and reasonably foreseeable development would change the appearance of the site and surrounding area, all development projects would be expected to be conditioned to follow applicable local planning and design guidelines regarding building design including materials, coloration, and landscaping as specified in Sections 18.61.060, 18.61.080 through 18.61.100, 18.61.120 through 18.61.140, 18.61.220, 18.61.250, and 18.61.270 of the City’s Municipal Code regarding lighting standards and limitation. Therefore, aesthetic impacts are not expected to be cumulatively considerable and impacts would be less than significant.

Valley & Spruce Project | 13

2. Agricultural and Forestry Resources Less Than Significant Potentially with Less than Significant Mitigation Significant No Issues Impact Incorporated Impact Impact In determining whether impacts to agricultural resources are significant environmental effects, lead agencies may refer to the California Agricultural Land Evaluation and Site Assessment Model (1997) prepared by the California Dept. of Conservation as an optional model to use in assessing impacts on agriculture and farmland. In determining whether impacts to forest resources, including timberland, are significant environmental effects, lead agencies may refer to information compiled by the California Department of Forestry and Fire Protection regarding the state’s inventory of forest land, including the Forest and Range Assessment Project and the Forest Legacy Assessment project; and forest carbon measurement methodology provided in Forest Protocols adopted by the California Air Resources Board. Would the project: a. Convert Prime Farmland, Unique Farmland, or Farmland of Statewide Importance (Farmland), as shown on the maps prepared pursuant to the

Farmland Mapping and Monitoring Program of the California Resources Agency, to non-agricultural use? b. Conflict with existing zoning for agricultural use, or

a Williamson Act contract? c. Conflict with existing zoning for, or cause rezoning of, forest land (as defined in Public Resources Code Section 12220(g)), timberland (as defined

by Public Resources Code Section 4526), or timberland zoned Timberland Production (as defined by Government Code Section 51104(g))? d. Result in the loss of forest land or conversion of

forest land to non-forest use? e. Involve other changes in the existing environment which, due to their location or nature, could result

in conversion of Farmland, to non-agricultural use or conversion of forest land to non-forest use?

Valley & Spruce Project | 14

Discussion a) Convert Prime Farmland, Unique Farmland, or Farmland of Statewide Importance (Farmland), as shown on the maps prepared pursuant to the Farmland Mapping and Monitoring Program of the California Resources Agency, to non-agricultural use? No Impact. The proposed Project site and surrounding areas are not designated as Prime Farmland, Unique Farmland, or Farmland of Statewide Importance on the State of California Important Farmland Map2. The proposed Project site, however, is designated as Urban and Built-Up Land. Therefore, the proposed Project would not result in a conversion of documented agricultural lands to non-agricultural use. No impact would occur and no mitigation is required. b) Conflict with existing zoning for agricultural use, or a Williamson Act contract? No Impact. The proposed Project site is not zoned for agricultural use, is not under a Williamson Act contract as shown on the 2015-2016 Williamson Act Contract Map, and as discussed above, is designated as Urban and Built-Up Land3. Based on the City of Rialto Zoning Ordinance, the Project site is within the boundaries of the Gateway Specific Plan and is zoned I-P (Industrial Park)4. Therefore, the proposed Project would not conflict with a Williamson Act Contract and would not conflict within the existing zoning. No impact would occur and no mitigation is required. c) Conflict with existing zoning for, or cause rezoning of, forest land (as defined in Public Resources Code section 12220(g)), timberland (as defined by Public Resources Code Section 4526), or timberland zoned Timberland Production (as defined by Government Code section 51104(g))? No Impact. The proposed Project site is within the boundaries of the Gateway Specific Plan and is zoned I-P (Industrial Park). The proposed Project site is not currently zoned as forest land, timberland, or timberland zoned for production. Therefore, improvements planned as part of the proposed Project would not conflict with existing zoning or require the rezoning. Therefore, no impact would result and no mitigation is required. d) Result in the loss of forest land or conversion of forest land to non-forest use? No Impact. The proposed Project site does not contain forest land. Therefore, no impact would occur in regard to changing forest land to a non-forest use. No mitigation is required. e) Involve other changes in the existing environment which, due to their location or nature, could result in conversion of Farmland, to non-agricultural use or conversion of forest land to non- forest use? No Impact. The proposed Project site does not contain any land used for or designated as agricultural or forest land. Therefore, no impact would occur in this regard and no mitigation is required.

2 California Department of Conservation, State of California Important Farmland Map. Available at: http://www.conservation.ca.gov/dlrp/fmmp. Accessed September 5, 2017. 3 California Department of Conservation, State of California – San Bernardino County Williamson Act FY 2015/2016. Available at: ftp://ftp.consrv.ca.gov/pub/dlrp/wa/SanBernardino_so_15_16_WA.pdf. Accessed September 5, 2017. 4 City of Rialto, 2013. City of Rialto Official Zoning Map. Available at: http://yourrialto.com/wp- content/uploads/2015/06/Zoning-Map-July-2013.pdf. Accessed September 5, 2017.

Valley & Spruce Project | 15

Cumulative Impacts The proposed Project would have no impact on agricultural and forestry resources. Therefore, the proposed Project would not contribute to a cumulatively considerable impact.

Valley & Spruce Project | 16

3. Air Quality Less Than Significant Potentially with Less than Significant Mitigation Significant No Issues Impact Incorporated Impact Impact Where available, the significance criteria established by the applicable air quality management or air

pollution control district may be relied upon to make the following determinations. Would the project: a. Conflict with or obstruct implementation of the

applicable air quality plan? b. Violate any air quality standard or contribute substantially to an existing or projected air quality violation? c. Result in a cumulatively considerable net increase of any criteria pollutant for which the project region is non-attainment under an applicable

federal or State ambient air quality standard (including releasing emissions which exceed quantitative thresholds for ozone precursors)? d. Expose sensitive receptors to substantial

pollutant concentrations? e. Create objectionable odors affecting a substantial

number of people?

Discussion An Air Quality, Greenhouse Gas and Health Risk Assessment Study for the proposed Project was prepared by Entech Consulting Group (October 2017). The report is provided in Appendix A; the results and conclusions of the report are summarized herein. The Project site is located within the South Coast Air Basin (SoCAB) within the City of Rialto, which is under the jurisdiction of the South Coast Air Quality Management District (SCAQMD). The SCAQMD is the agency principally responsible for comprehensive air pollution control in the SoCAB, which includes all of Orange County and the urbanized portions of , Riverside, and San Bernardino Counties. The SCAQMD develops rules and regulations; establishes permitting requirements for stationary sources; inspects emissions sources; and enforces such measures through educational programs or fines, when necessary. Air quality impacts were assessed in accordance with methodologies recommended by California Air Resources Board (CARB) and the SCAQMD. Where criteria air pollutant quantification was required, emissions were modeled using the California Emissions Estimator Model (CalEEMod). The attainment status for SoCAB is included Table 1: Attainment Status of the South Coast Air Basin. Areas that meet ambient air quality standards are classified as attainment areas, while areas that do not meet these standards are classified as nonattainment areas. Areas for which there is insufficient data available are designated unclassified. As shown in the table, the region is designated as a nonattainment area for the federal ozone, PM10 and PM2.5 standards and is also a nonattainment area for the state standards for state ozone, PM10, and PM2.5 standards.

Valley & Spruce Project | 17

Table 1: Attainment Status of the South Coast Air Basin

Criteria Pollutant Federal Designation State Designation Ozone Nonattainment Nonattainment

PM10 Nonattainment Nonattainment

PM2.5 Nonattainment Nonattainment Carbon Monoxide Maintenance Attainment Nitrogen Dioxide Maintenance Attainment Sulfur Dioxide Attainment Attainment Lead Attainment Attainment Sulfates No Standard Attainment Hydrogen Sulfide No Standard Unclassified* Visibility Reducing Particles No Standard Unclassified* Sources: EPA website, http://www.epa.gov/oaqps001/greenbk/index.html, December 2014. and CARB website, http://www.arb.ca.gov/desig/adm/adm.htm, August 2014. *If there is inadequate or inconclusive data to make a definitive attainment designation, districts are considered “unclassified.”

To determine whether a project would create potential air quality impacts, the City uses SCAQMD Air Quality Thresholds. The screening thresholds for construction and daily operations are shown in Table 2: SCAQMD Daily Emissions Thresholds.

Table 2: SCAQMD Daily Emissions Thresholds

Thresholds (lbs/day) Pollutant Construction Operations Volatile Organic Compounds (VOC) 75 55 Nitrogen Oxides (NOx) 100 55 Particulate Matter (PM10) 150 150 Particulate Matter (PM2.5) 55 55

Sulfur Oxides (SOx) 150 150

Carbon Monoxide (CO) 550 550 Lead (Pb) 3 3 Source: South Coast AQMD web page, www.aqmd.gov

a) Conflict with or obstruct implementation of the applicable air quality plan? Less Than Significant Impact. The SCAQMD drafted the 2016 Air Quality Management Plan (AQMP). The 2016 AQMP establishes a program of rules and regulations directed at reducing air pollutant emissions and achieving state and national air quality standards. The primary purpose of an air quality plan is to bring an area that does not attain federal and State air quality standards into compliance with the requirements of the federal Clean Air Act and California Clean Air Act. In addition, air quality plans are developed to ensure that an area maintains a healthful level of air quality based on the national ambient air quality standards (NAAQS) and the California ambient air quality standards (CAAQS).

Valley & Spruce Project | 18

The SCAQMD’s CEQA Handbook identifies two key indicators of consistency with the AQMP: 1) Whether a project will result in an increase in the frequency or severity of existing air quality violations or cause or contribute to new violations, or delay timely attainment of air quality standards or the interim emission reductions specified in the AQMP. 2) Whether a project will exceed the assumptions in the AQMP based on the year of project buildout and phase. Construction associated with the proposed Project would generate short-term emissions of criteria air pollutants. The criteria pollutants of primary concern within the Project area include ozone-precursor pollutants and particulate matter. The construction emissions result from site grading, road paving, and motor vehicle exhaust associated with construction equipment and worker trips. Emissions of airborne particulate matter are largely dependent on the amount of ground disturbance associated with site preparation activities as well as weather conditions and the appropriate application of water. Construction-generated emissions are short term and of temporary duration, lasting only as long as construction activities occur, but would be considered a significant air quality impact if the volume of pollutants generated exceeds the SCAQMD’s threshold of significance. The duration of construction activities associated with the proposed Project is estimated to last approximately 9 months. Construction-generated emissions associated with the proposed Project were calculated using the CARB-approved CalEEMod computer program. As shown in Table 3: Construction Emissions Summary and Significance Evaluation, all criteria pollutant emissions would remain below their respective thresholds. While impacts would be considered less than significant, the proposed Project would be subject to SCAQMD Rules 402, 403, and 1113 to further reduce specific construction-related emissions.

Table 3: Construction Emissions Summary and Significance Evaluation

Criteria Unmitigated Mitigated Threshold Significance Pollutants (lbs/day) (lbs/day) (lbs/day) ROGs (VOCs) 38.36 38.36 75 LTSM NOx 68.0 68.0 100 LTSM CO 40.0 40.0 550 LTSM SOx 0.07 0.07 150 LTSM Total PM10 21.1 10.2 150 LTSM Total PM2.5 12.6 6.6 55 LTSM Notes: 1) lbs/day are winter or summer maxima for planned land use 2) Total PM10/PM2.5 comprises fugitive dust plus engine exhaust 3) Mitigated emissions for PM10 and PM2.5 incorporate Rule 402 4) LTSM – Less Than Significant with Mitigation Sources: SCAQMD 2015a, CalEEMod version 2016.3.1

Once operational, Project-generated emissions would be associated with motor vehicle use and area sources, such as the use of landscape maintenance equipment and architectural coatings. As shown in Table 4: Operational Emissions Summary and Significance Evaluation, estimated long-term operational emissions attributable to the proposed Project would not exceed SCAQMD thresholds for any criteria air pollutants.

Valley & Spruce Project | 19

Table 4: Operational Emissions Summary and Significance Evaluation

Criteria Unmitigated Threshold Significance Pollutants (lbs/day) (lbs/day) ROGs (VOCs) 8.6 55 LTS NOx 23.9 55 LTS CO 56.8 550 LTS SOx 0.2 150 LTS Total PM10 13.7 150 LTS Total PM2.5 4.1 55 LTS Notes: 1) lbs/day are winter or summer maxima for planned land use 2) Total PM10/PM2.5 comprises fugitive dust plus engine exhaust 3) LTS – Less Than Significant 4) Sources: SCAQMD 2015a, CalEEMod version 2016.3.1

As shown in Table 3 and Table 4 above, the proposed Project would not exceed the short-term construction standards or long-term operational standards. Therefore, the proposed Project would not violate any air quality standards and would not have an impact based on criterion 1 above.

The AQMP contains air pollutant reduction strategies based on SCAG’s latest growth forecasts, which were defined in consultation with local governments and with reference to local general plans. The proposed Project is consistent with the land use designation and development density presented in the City of Rialto’s General Plan and the Gateway Specific Plan, therefore, would not exceed the population or job growth projections used by the SCAQMD to develop the AQMP. No impact would occur based on criterion 2 above. b) Violate any air quality standard or contribute substantially to an existing or projected air quality violation? Less Than Significant Impact. As described above, the Air Quality Study determined that emissions associated with the construction and operations of the facility would be below the significance thresholds for all pollutants. Therefore, implementation of the proposed Project would not violate an air quality standard or contribute to an existing or projected air quality violation. No mitigation is required. c) Result in a cumulatively considerable net increase of any criteria pollutant for which the project region is non-attainment under an applicable federal or State ambient air quality standard (including releasing emissions which exceed quantitative thresholds for ozone precursors)? Less Than Significant Impact. California has 35 specific air districts, which are each responsible for ensuring that the criteria pollutants are below the NAAQS and CAAQS. Air basins that exceed either the NAAQS or the CAAQS for any criteria pollutants for set periods are designated as “non-attainment areas” for that pollutant. The cumulative setting for air quality includes Rialto and the SoCAB. The SoCAB is designated as a nonattainment area for state standards of ozone, PM10, and PM2.5. Cumulative growth in population and vehicle use could inhibit efforts to improve regional air quality and attain the ambient air quality standards. The SCAQMD’s approach to assessing cumulative impacts is based on the AQMP forecasts of attainment of ambient air quality standards in accordance with the requirements of the federal and California Clean Air Acts. The AQMP is designed to assist the region in attaining the applicable state and national

Valley & Spruce Project | 20

ambient air quality standards and is intended to bring the SoCAB into attainment for all criteria pollutants. Since the construction and operational emission calculated for the proposed Project do not exceed the applicable SCAQMD daily significance thresholds, the proposed Project would be consistent with the AQMP and cumulative impacts would not be significant. d) Expose sensitive receptors to substantial pollutant concentrations? Less Than Significant Impact. Some land uses are considered more sensitive to air pollution than others due to the types of population groups or activities involved. Sensitive population groups include children, the elderly, the acutely ill, and the chronically ill. Residential areas are considered to be sensitive receptors to air pollution because residents (including children and elderly) tend to be at home for extended periods of time, resulting in sustained exposure to any pollutants present. The nearest sensitive receptors to the Project site are the residences located approximately 190 feet northwest of the Project site. In order to identify impacts to sensitive receptors, the SCAQMD recommends addressing Localized Significance Thresholds (LSTs) for construction. LSTs were developed by SCAQMD to assist lead agencies in analyzing localized impacts associated with individual projects. The Air Quality Study included a mobile source Health Risk Assessment (HRA). The operational phase mobile source HRA was conducted based on the CARB July 23rd, 2015 Risk Management Guidance for Stationary Sources of Air Toxics, the SCAQMD Risk Assessment Procedures, and the Office of Environmental Health Hazard Assessment’s (OEHHA) Health Risk Assessment Guidance for Analyzing Cancer Risks from Mobile Source Diesel Idling Emissions for CEQA Air Quality Analysis (August 2003). Consistent with the SCAQMD guidelines, the HRA was conducted per the current OEHHA’s Air Toxics Hot Spots Program Guidance Manual for the Preparation of HRAs using the Hotspots Analysis and Reporting Program, Version 2 (HARP2). Carbon Monoxide Hotspots The proposed Project is anticipated to generate 1,441 daily trips. A CO “hot spots” analysis is not needed to determine whether the change in the level of service (LOS) of an intersection in the proposed Project would have the potential to result in exceedances of the CAAQS or NAAQS. An adverse CO concentration, known as a “hot spot”, would occur if an exceedance of the state one-hour standard of 20 ppm or the eight-hour standard of 9 ppm were to occur. At the time of the 1993 Handbook, the SCAG was designated nonattainment under the California AAQS and National AAQS for CO. It has long been recognized that CO hotspots are caused by vehicular emissions, primarily when idling at congested intersections. However, vehicle emissions standards have become increasingly stringent in the last twenty years. Currently, the allowable CO emissions standard in California is a maximum of 3.4 grams/mile for passenger cars (there are requirements for certain vehicles that are more stringent). With the turnover of older vehicles, introduction of cleaner fuels and implementation of increasingly sophisticated and efficient emissions control technologies, CO concentration in the SCAB is now designated as attainment. Also, CO concentrations in the Project vicinity have steadily declined. Similar considerations are also employed by other Air Districts when evaluating potential CO concentration impacts. More specifically, the Bay Area Air Quality Management District (BAAQM) concludes that under existing and future vehicle emission rates, a given project would have to increase traffic volumes at a single intersection by more than 44,000 vehicles per hour- or 24,000 vehicles per hour where vertical and/or horizontal air does not mix to generate a significant CO impact. The proposed Project would not produce this volume of

Valley & Spruce Project | 21

traffic required to generate a CO “hot spot”. Therefore, CO “hotspots:” are not an environmental impact of concern for the proposed Project. Localized air quality impacts related to mobile-source emissions would therefore be less than significant. Construction-Related Diesel Particulate Matter The HRA analyzed the on-site and off-site impacts from the diesel trucks accessing the warehouse development on nearby residential and worker receptors. As diesel particulate matter (DPM) is the only toxic air contaminants (TAC) emitted from the trucks, the HRA only examined cancer and chronic health risks. Acute risks were not estimated as DPM does not have short-term toxicity values. Downwind concentrations of air pollutants were estimated using the Environmental Protection Agency’s (EPA’s) AERMOD air dispersion computer model. The air dispersion modeling methodology is based on generally accepted modeling practices of the SCAQMD. The HRA followed the OEHHA and SCAQMD’s techniques to calculate the health risk impacts at all receptors including the nearby residential, sensitive, and off-site worker receptors. Ruth Grimes Elementary School was included in the analysis as an elementary school since it is near one of the truck routes. DPM increases non-cancer health risk due to long-term (chronic) exposures. The Chronic non- cancer Hazard Index (HI) is the sum of the individual substance chronic hazard indices for all TACs affecting the same target organ system. The chronic non-cancer HI estimates for all receptor types used the OEHHA Derived calculation method. As shown in Table 5: Health Risk Results – Valley and Spruce Avenue Warehouse, the HRA for the proposed Project found that at all receptor types, the predicted HIC is less than the SCAQMD significance threshold. The HRA predicted that the cancer risk for the Proposed would not exceed the SCAQMD’s cancer risk health risk significance threshold for either sensitive receptors in the residential areas immediately adjacent to the Proposed Project or along the expected travel routes of the Proposed Project’s truck traffic, and for worker receptors located in the vicinity of the Proposed Project.

Table 5: Health Risk Results – Valley and Spruce Avenue Warehouse

SCAQMD Impact Health Risk Impact Significance Significant Receptor Type Parameter (Dimensionless) Threshold (Yes/No) (Dimensionless) Resident 6.1 in a million 10 in a million No MICR Worker 1.9 in a million 10 in a million No Sensitive 5.4 in a million 10 in a million No Resident 0.0014 1 No Chronic non- Worker 0.0061 1 No cancer HI Sensitive 0.0012 1 No Notes: 1) Maximum Individual Cancer Risk (MICR) Total PM10/PM2.5 comprises fugitive dust plus engine exhaust 2) Chronic Hazard Index (HI)

Valley & Spruce Project | 22

e) Create objectionable odors affecting a substantial number of people? No Impact. The proposed Project is a warehouse use and would not include any of the land uses that have been identified by the SCAQMD as odor sources. Therefore, there would be no impacts from the proposed Project.

Cumulative Impacts No single project is sufficient in size to, by itself, result in nonattainment of ambient air quality standards. Instead, a project’s individual emissions contribute to existing cumulatively significant adverse air quality impacts. The SCAQMD developed the operational thresholds of significance based on the level above which a project’s individual emissions would result in a cumulatively considerable contribution to the Basin’s existing air quality conditions. Therefore, a project that exceeds the SCAQMD operational thresholds would also be a cumulatively considerable contribution to a significant cumulative impact. As described in this section, the proposed Project’s operational emissions would not exceed thresholds. Therefore, the proposed Project would not result in a cumulatively considerable contribution to significant cumulative air quality impacts.

Valley & Spruce Project | 23

4. Biological Resources Less Than Significant Potentially with Less than Significant Mitigation Significant No Issues Impact Incorporated Impact Impact Would the project: a. Have a substantial adverse effect, either directly or through habitat modifications, on any species identified as a candidate, sensitive, or special

status species in local or regional plans, policies, or regulations, or by the California Department of Fish and Wildlife or .S. Fish and Wildlife Service? b. Have a substantial adverse effect on any riparian habitat or other sensitive natural community identified in local or regional plans, policies, regulations or by the California Department of Fish and Game or US Fish and Wildlife Service? c. Have a substantial adverse effect on federally protected wetlands as defined by Section 404 of the Clean Water Act (including, but not limited to,

marsh, vernal pool, coastal, etc.) through direct removal, filling, hydrological interruption, or other means? d. Interfere substantially with the movement of any native resident or migratory fish or wildlife species or with established native resident or migratory wildlife corridors, or impede the use of native wildlife nursery sites? e. Conflict with any local policies or ordinances protecting biological resources, such as a tree preservation policy or ordinance? f. Conflict with the provisions of an adopted Habitat Conservation Plan, Natural Community

Conservation Plan, or other approved local, regional, or State habitat conservation plan?

Discussion A Biotic Resources Report was prepared for the proposed Project by Rocks Biological Consulting (September 2017). The Biotic Resources Report is included as Appendix B and the results are summarized herein. a) Have a substantial adverse effect, either directly or through habitat modifications, on any species identified as a candidate, sensitive, or special status species in local or regional plans, policies, or regulations, or by the California Department of Fish and Wildlife or the USFWS? Less than Significant Impact with Mitigation Incorporated. The California Department of Fish and Wildlife (CDFW) and the U.S. Fish and Wildlife Service (USFWS) may list species as threatened or endangered under the California Endangered Species Act (CESA) or Federal Endangered Species Act (FESA), respectively. The USFWS can designate critical habitat that identifies specific areas that are essential to the conservation of a listed species.

Valley & Spruce Project | 24

As a part of the Biotic Resources Report prepared for the project, a query of the CDFW’s California Natural Diversity Database (CNDDB) found historical occurrences of five special- status plant species and six special-status wildlife species within 1 mile of the Project site. The proposed Project has low potential to support burrowing owl as discussed below. The proposed Project is within the County of San Bernardino’s Burrowing Owl Overlay Zone (Biotic Resources Overlay Map, County of San Bernardino 2012). The CNDDB results, habitat assessment, and potential for occurrence for each species are included in Table 6, CNDDB Species Habitat Assessment Results, below.

Table 6: CNDDB Species Habitat Assessment Results

Potential to Occur Species Status Habitat Description within Project Area Marsh sandwort (Arenaria FE; SE; CRPR Perennial stoloniferous None. No suitable paludicola) 1B.1 herb. Blooms May-Aug. habitat present Marshes and swaps within Project site. (freshwater or brackish). Elevation 10-560 feet. Salt Marsh bird’s beak FE; SE; CRPR Hemiparastic annual None. No suitable (Chloropyron maritimum ssp. 1B.1 herb. Blooms March- habitat present Maritimum) October. Coastal dunes within Project site. and coastal salt marsh. Elevation 0-100 feet. Mesa horkelia (Horkelia cuneata CPPR 1B.1 Perennial herb. Blooms None. No suitable var. puberula) February – September. habitat present Maritime chaparral, within Project site. cismontane woodland, and coastal scrub. Elevation 230-2,657 feet. Parish’s bush-mallow CRPR 1A Perennial deciduous None. No suitable (Malacothamnus parishii) shrub. Blooms June-July. habitat present Chaparral and coastal within Project site. scrub. Elevation 1,000- 1,493 feet Pringle’s monardella CRPR 1A Annual herb. Blooms None. No suitable (Monardella pringlei) May-June. Coastal scrub. habitat present Elevation 985-1,315 feet. within Project site. California glossy snake (Arizona SSC Found in arid scrub, rocky None. No suitable elegans occidentalis) washes, grasslands, and habitat present chaparral. within Project site. Burrowing owl (Athene SSC Found in grasslands and Low. Suitable cunicularia) open scrub from coast to habitat is present foothills. Strongly on site, no BUOW associated with California or sign observed. ground squirrel and other fossorial mammal burrows. Crotch bumble bee (Bombus CNDDB: G3: Found in open grasslands None. Suitable

Valley & Spruce Project | 25

Table 6: CNDDB Species Habitat Assessment Results

Potential to Occur Species Status Habitat Description within Project Area crotchii) S1 and scrub habitats habitat not present within Project site. San Bernardino kangaroo rat FE; SSC Found on the gentle None. Suitable (Dipodomys merriami parvus) slopes of alluvial fans, on habitat not flood plains, along present within washes, and on adjacent Project site. upland areas, including alluvial sage scrub, coastal sage scrub, and chaparral. Pocketed free-tailed bat SSC Rugged cliffs, rocky None. Suitable (Nyctinomops femorosaccus) outcrops, and slopes in habitat not desert shrub and pine present within oak forests. Project site. Delhi Sands flower-loving fly FE Found in sandy areas None. Suitable (Rhaphiomidas terminatus composed of Delhi Fine habitat not abdominalis) Sands, stabilized by present within sparse native vegetation. Project site. Notes: CNDDB Rank G-Global Rank 3- Vulnerable, at moderate risk of extinction due to very restricted range, relatively few populations (often 80 or fewer), recent and widespread declines, or other factors S – State Rank 1- Critically imperiled, at very high risk of extinction due to extreme rarity (often 5 or fewer populations), very steep declines, or other factors CRPR – California Rare Plant Rank 1A- Plants presumed extirpated in California and either rare or extinct elsewhere 1B – Plants rare, threatened, or endangered in California and elsewhere 0.1 – Seriously threatened in California (over 80% of occurrences threatened/high degree and immediacy of threat 0.2 FE: Federally-listed endangered under the Endangered Species Act SSC: Species of Special Concern per the CDFW

Delhi Fine Sands soils are not present on the Project site according to the Natural Resources Conservation Service (NRCS) soils map (USDA 2016) for the site and field investigation during the site visit. Disking has greatly disturbed the site leaving very few possible nectar sources for the Delhi Sands flower-loving fly. This, in combination with the lack of Delhi Fine Sands, leads to the conclusion that there is no potential for this species to occur on site. Alluvial fan scrub habitat is not present on the Project site. Disking has greatly disturbed the site and made the soils on site loose and unstable. Two small potentially suitable burrows for San Bernardino kangaroo rat were observed near the southeast corner of the developed storage lot where the soil was slightly more compacted. However, no small mammal sign was observed and the burrows appeared inactive. This leads to the conclusion that there is no potential for San Bernardino kangaroo rat to occur on site.

Valley & Spruce Project | 26

No burrowing owl individuals or burrowing owl sign were observed on the Project site. The previous disking on site has made the soil loose and unstable. No suitable burrows were observed on site. Based on these conditions, the Project site has a low potential to support burrowing owl. However, as identified in in Mitigation Measure BIO-1, a pre-construction burrowing owl survey is required prior to site disturbance to ensure impacts on burrowing owls are reduced to a less than significant level. Mitigation Measure BIO-1 Burrowing Owl Pre-Construction Survey: A qualified biologist will conduct a preconstruction presence/absence survey for burrowing owl(s) within 30 days of scheduled site disturbance. Project site disturbance may proceed once the qualified biologist confirms no burrowing owl(s) or sign (molted feathers, cast pellets, prey remains, eggshell fragments, or excrement) are present on site. If burrowing owl(s) or sign are observed during the pre-construction presence/absence survey, the qualified biologist will monitor the burrow(s) for up to two weeks to determine if the burrow(s) are occupied. If the burrow(s) are occupied, the qualified biologist will coordinate burrowing owl avoidance and/or passive relocation in conjunction with CDFW. If the qualified biologist confirms at the expiration of the two-week period that there is no burrowing owl onsite, construction/site disturbance activities may commence. In addition, the Project site is a largely disturbed area comprised of disked non-native grassland vegetation with small developed patches comprised of sidewalks and cement pads. A former storage yard occupies approximately 2.8 acres of the site (this facility was demolished/removed in September 2017 following the site visit for the biotic resources report). No natural habitat remains. Impacts on native vegetation communities or habitats would be less than significant. b) Have a substantial adverse effect on any riparian habitat or other sensitive natural community identified in local or regional plans, policies, regulations or by the California Department of Fish and Wildlife (CDFW) or U.S. Fish and Wildlife Service? No Impact. The Project site is a largely disturbed area comprised of disked non-native grassland vegetation with small developed patches comprised of sidewalks and cement pads. A former storage yard occupied the site until it was demolished/removed in September 2017. No structures are currently located on the site. There are no native habitats on site. There are no USGS-designated blue line streams or associated jurisdictional features on the Project site. No areas of ponded water were observed on site, and no evidence of vernal pools or fairy shrimp habitat was observed on the parcel. There is a concrete-lined channel (maintained by Caltrans) is present offsite within 50 feet of the Project site to the south side of the project boundary along I-10. This channel conveys water from outside of the Project boundaries. This feature may be considered jurisdictional by regulatory agencies, but it will not be impacted by the Project. No impacts to riparian habitat or other sensitive natural community would occur as a result of the proposed Project; no mitigation is required. c) Have a substantial adverse effect on federally protected wetlands as defined by Section 404 of the Clean Water Act (including, but not limited to, marsh, vernal pool, coastal, etc.) through direct removal, filling, hydrological interruption, or other means? No Impact. As discussed above in threshold 4.b, the Project site does not contain potential jurisdictional features, including federally protected wetlands and other features that carry water. Therefore, no impacts would occur and no mitigation is required. d) Interfere substantially with the movement of any native resident or migratory fish or wildlife species or with established native resident or migratory wildlife corridors, or impede the use of native wildlife nursery sites? Less Than Significant Impact with Mitigation Incorporated.

Valley & Spruce Project | 27

Wildlife Corridors: The Project site is located in a predominately industrial and commercial area and is not suitable as a wildlife movement corridor. Construction of the proposed Project would not impact a wildlife corridor. Therefore, there would be no impact to migratory wildlife or corridors and no mitigation is required. Nesting Birds: The Project site has the potential to impact active bird nests if vegetation is removed or ground disturbing activities occur during the nesting season (January 15 to August 31). Impacts on nesting birds are prohibited by the Migratory Bird Treaty Act (MBTA) and California Fish and Game Code (CFGC). With the implementation of Mitigation Measure BIO- 2, impacts on nesting birds would be less than significant. Mitigation Measure  BIO-2 Nesting Bird Pre-Construction Survey: Vegetation clearing and ground disturbing activities should be conducted outside of the nesting season (January 15 to August 31). If these activities occur during nesting season, then a qualified biologist will conduct a nesting bird survey within three days prior to any disturbance of the site, including tree and shrub removal, disking, demolition activities, and grading. If active nests are identified, the biologist shall establish suitable buffers around the nests depending on the level of activity within the buffer and species detected, and the buffer areas shall be avoided until the nests are no longer occupied and the juvenile birds can survive independently from the nests. Raptor species will have an avoidance buffer of 500 feet and other bird species will have an avoidance buffer of 300 feet. These buffers may be reduced in consultation with the CDFW. If active nests are not identified, vegetation clearing and ground disturbing activities may be commenced. e) Conflict with any local policies or ordinances protecting biological resources, such as tree preservation policy/ordinance? No Impact. The proposed Project would not conflict with any local policies or ordinances protecting biological resources, as the site has been disturbed and there are no identified biological resources that are subject to such regulation; no impact would occur and no mitigation is required. f) Conflict with the provisions of an adopted Habitat Conservation Plan, Natural Community Conservation Plan, or other approved local, regional, or State habitat conservation plan? No Impact. The Project site is not subject to a conservation plan; no plans have been adopted in the area of the Project site. No impact relative to adopted habitat conservation or other approved local, regional or State plans would occur.

Cumulative Impacts Mitigation measures have been identified above (Mitigation Measures BIO-1 and BIO 2) that would serve to reduce the severity of biological impacts. Similar to the proposed Project, all cumulative projects would be subject to individual project review and conformance with conservation plans and standard provisions for compliance with state and federal protection laws. Since project-related impacts would be minimized by mitigation and cumulative projects would also be required to follow suit, the cumulative impact from other past, present, and reasonably foreseeable projects, would be expected to be less than significant. Therefore, cumulative impacts would be less than significant.

Valley & Spruce Project | 28

5. Cultural Resources Less Than Significant Potentially with Less than Significant Mitigation Significant No Issues Impact Incorporated Impact Impact Would the project: a. Cause a substantial adverse change in the significance of a historical resource as defined in Section 15064.5? b. Cause a substantial adverse change in the significance of an archaeological resource pursuant to Section 15064.5? c. Directly or indirectly destroy a unique paleontological resource or site or unique geologic feature? d. Disturb any human remains, including those

interred outside of formal cemeteries?

Discussion A Cultural Resource Study Findings Memorandum for the proposed Project was prepared by ASM in October 2017. The report evaluated cultural and tribal resources on the Project site and in surrounding areas. The Cultural Resources Study Findings Memorandum is provided in Appendix C; the results and conclusions of the study related to Tribal Cultural Resources are summarized herein. a) Cause a substantial adverse change in the significance of a historical resource? No Impact. The Cultural Resources Study Findings Memorandum for the proposed Project site included a records search at the South Central Coastal Information Center (SCCIC), a search of the Sacred Lands File of the California Native American Heritage Commission (NAHC), a pedestrian survey of accessible portions of the Project area, and review of aerial photographs and topographic maps to determine the presence or absence of historical resources. The Cultural Resources Study Findings Memorandum was completed in compliance with California Environmental Quality Act (CEQA) requirements and has been included to this Initial Study as Appendix C to address the potential environmental impacts of the proposed Project pursuant to the required provisions of CEQA, Public Resources Code Section 21000 et seq., and State CEQA Guidelines Section 15063. The SCCIC and NAHC records searches provide a listing of, and information about previous cultural resource studies that have been conducted in a designated radius to a particular location. The records searches show studies that have been conducted as well as a separate data set that shows instances where physical cultural resource(s) have been located. The purpose of the searches is to provide information regarding the presence or absence of historic and archaeological resources that have been located in an area surrounding a particular Project site. Both records searches conducted for the proposed Project used a radius of 1-mile from the proposed Project site. The records search identified 36 previous cultural resource studies that had been conducted within a 1.0-mile radius from the Project site between 1976 and 2015. One of these studies, SB-01772 occurred in 1988, and involved a survey encompassing the entire proposed Project site. A second record, SB-07960 occurred in 2010 and covered the area needed for a pipeline adjacent to Valley Boulevard along the northern Project boundary.

Valley & Spruce Project | 29

The records search also indicated there were a total of 45 physical cultural resources previously recorded within the 1-mile of the Project site. None of these resources were located within the proposed Project site. Two of these sites are prehistoric sites, with the remaining 43 consisting of historic resources. Of the 43 historic resources, four sites contained refuse scatters, one is a railroad, one is a water conveyance system, and the remaining 39 are various types of structures, mostly single family residential. The majority of the documented resources are greater than 0.3 mile from the proposed Project. Only two, both historic refuse scatters, have been documented adjacent the proposed Project site. One of these, P-36-008927, was recorded just north of proposed Project within Valley Boulevard, and the other, P-36-006868, was within the vacant lot across Valley Boulevard at the northwestern corner of the intersection of Valley Boulevard and Cactus Avenue. The Project does not propose any construction activity within either of these locations. As discussed above, historic aerials for various years from 1938 through 2012, were evaluated and historic topographic maps from various years from1896 through 1985, were analyzed to evaluate changes to the site during that time. The aerials and topographic maps show that the site once contained numerous structures and had roads that bisected the site from east to west along the southern boundary and a north to south road that bisected the parcel. It is unknown when the structures were constructed, but three structures appear to have been built prior to 1943. Over the years, the aerial photos indicate that numerous structures in various locations had been built, but were later removed. The 1938 aerial photo shows the Project site is planted in what appeared to be citrus groves, but that most had been removed by 1948. In 1955, State Routes 70 and 99 appear at the southern edge of the proposed Project area. By 1994, many of the previous structures had been removed and by 2002 the central portion of the site was paved. That paving remains to date and is currently used for equipment and storage. The pedestrian survey conducted for the proposed Project found the area to be significantly disturbed from agricultural and residential uses, as well as more recent disking and other surface-disturbing activities. These activities appear to have occurred across the entirety of the western and eastern parcels that are separated by the concrete pad. These areas appeared to be recently disked with little surface vegetation being present. In addition, there were several areas containing modern dumped construction materials and other refuse. Several stands of trees are found in areas where structures appeared in the historical images; however, the structures are now absent and only the concrete foundations and multiple piles of rubble remain. The northeastern corner of the eastern parcel evidences a low brick wall painted white that was likely associated with the nearby newer concrete foundation. Some degraded bricks and several trees were found, but no artifacts were found in this area. Various posts are located within the proposed Project site evidencing the prior presence of various forms of fencing. The pedestrian survey located four highly degraded concrete foundations with three concrete basins and an historic artifact scatter near the western edge of the western parcel. The location, referred to as Valley-1, has been heavily impacted and damaged by disking, which has resulted in most of the artifacts being highly fragmented and mixed with modern and historic materials. While no clearly intact deposits were found, one concentration of artifacts surrounding one of the foundations, comprising primarily soda bottle fragments was located. Analysis of historic aerials and topographic maps show this portion of the proposed Project site was likely in use sometime between 1948 and 1966 and the artifacts are likely from that time frame as well. The number of soda bottles might suggest some sort of a retail or restaurant establishment, but the site generally lacks the number or types of other artifacts

Valley & Spruce Project | 30

such as serving style glassware or dishware, that would be expected to be found. The bottles may have simply been collected and then left behind by prior inhabitants of the site. The Valley-1 site is a late historic refuse scatter that has sustained very heavy damage and has lost integrity; no evidence of any intact surface or subsurface deposits was identified. As such, Valley-1 is not recommended as eligible for listing in the California Register of Historical Resources (CRHR) as it fails to meet the criteria for listing and does not have the potential to yield information important to understanding the history of the proposed Project area. As discussed above, no historic resources were identified within the Project site that would require any further consideration under CEQA; the proposed Project would not impact any known historical structures. Therefore, no impacts would occur and mitigation is not required. b) Cause a substantial adverse change in the significance of an archaeological resource? Less Than Significant Impact with Mitigation Incorporated. The Project site has been previously disturbed and the surrounding area is predominately urbanized with industrial, commercial and residential uses located in the vicinity of the Project site. No archaeological resources have been recorded on the Project site, and due to the level of past disturbance, it is not anticipated that archaeological sites would be found. Because the proposed Project involves development of a site that has been so heavily disturbed, it is not anticipated that intact subsurface archaeological resources would be encountered during excavation and grading activities. Although the potential for disturbance of undiscovered resources during grading and excavation activities is considered low, CUL-1 is required to reduce this potential impact to a level considered less than significant. Mitigation Measure CUL-1 Cultural Resources Monitoring: Prior to beginning project construction, the project applicant shall retain an archaeological monitor to monitor initial ground- disturbing activities in an effort to identify any unknown archaeological resources. Any newly discovered cultural resource deposits shall be subject to a cultural resources evaluation. These actions, as well as final mitigation and disposition of the resources, shall be subject to the approval of the City of Rialto. c) Directly or indirectly destroy a unique paleontological resource or site or unique geologic feature? Less than Significant Impact with Mitigation Incorporated. No paleontological resources are known to be on or adjacent to the Project site. It is assumed that if these resources were located in these areas, they would have been discovered during original or subsequent ground disturbing activities. Should evidence of paleontological resources be encountered during grading and construction, operations would be required to cease, and the City of Rialto would be required to be contacted for determination of appropriate procedures. Compliance with the City’s standard conditions would preclude significant impacts to paleontological resources. While fossils are not expected to be discovered during construction, it is possible that significant fossils could be discovered during excavation activities, even in areas with a low likelihood of occurrence. Fossils encountered during excavation could be inadvertently damaged. If a unique paleontological resource is discovered, the impact to the resource could be substantial. To reduce this potentially significant impact to a less than significant level, all construction related impacts of fossils or fossil-bearing deposits shall be monitored in accordance with Mitigation Measure CUL-2, to the satisfaction of the City Planning Director.

Valley & Spruce Project | 31

Mitigation Measure CUL-2 Prior to the issuance of any grading permits, or any permit authorizing ground disturbance, the project applicant shall, to the satisfaction of the City Planning Director, demonstrate that a qualified paleontological monitor has been retained to be present during brushing and clearing, excavation, or any mass grading activities. In the event that fossils or fossil-bearing deposits are discovered during construction, excavations within 50 feet of the find shall be temporarily halted or diverted. The paleontologist shall document the discovery as needed in accordance with Society of Vertebrate Paleontology standards, evaluate the potential resource, and assess the significance of the find under the criteria set forth in CEQA Guidelines Section 15064.5. The paleontologist shall notify the appropriate agencies to determine procedures that would be followed before construction is allowed to resume at the location of the find. If in consultation with the paleontologist, City staff and the project applicant determine that avoidance is not feasible, the paleontologist shall prepare an excavation plan for reducing the effect of the project on the qualities that make the resource important. The plan shall be submitted to the City for review and approval and the project applicant shall implement the approval plan. d) Disturb any human remains, including those interred outsides of formal cemeteries? Less Than Significant Impact with Mitigation Incorporated. The Project site is not located within a known or suspected cemetery and there are no known human remains within the Project site. However, this does not preclude finding human remains during project-related ground disturbance. In compliance with State regulations, should any human remains be encountered during construction activities, State Health and Safety Code Section 7050.5 states that no further disturbances shall occur in the immediate area until the County Coroner has made the necessary findings as to origin and disposition pursuant to California Public Resources Code Section 5097.98. In addition, in accordance with State and local guidelines, if the Coroner determines the remains to be of a Native American, the Coroner shall contact the Native American Heritage Commission within 24 hours for identification of the most likely descendent of the deceased Native American. Additionally, if the remains are determined to be Native American, the City would work with local Native American representatives to ensure that the remains and any associated artifacts are treated in a respectful and dignified manner. Despite the applicable regulatory framework and the relatively low likelihood of discovery, it remains possible that the proposed Project would discover human remains during subsurface activities, which could then result in the remains being inadvertently damaged. To reduce this potentially significant impact to a less than significant level, all construction related impacts of human remains shall be monitored in accordance with Mitigation Measure CUL-3 and to the satisfaction of the City Planning Director. Mitigation Measure CUL-3 Prior to the issuance of any grading permits, or any permit authorizing ground disturbance, the project applicant shall, to the satisfaction of the City Planning Director, demonstrate that the following note is included on any grading plans: If human skeletal remains are uncovered during construction, the contractor (depending on the project component) shall immediately halt work within 50 feet of the find, contact the San Bernardino County coroner to evaluate the remains, and follow the procedures and protocols set forth in Section 15064.5(e)(1) of the CEQA Guidelines. If the County Coroner determines that the remains are Native American, the County Coroner shall contact the NAHC, in accordance with Health

Valley & Spruce Project | 32

and Safety Code Section 7050.5, subdivision (c), and Public Resources Code 5097.98 (as amended by AB 2641). Per Public Resources Code 5097.98, the contractor shall ensure that the immediate vicinity, according to generally accepted cultural or archaeological standards or practices, where the human remains are located, is not damaged or disturbed by further development activity until the contractor has discussed and conferred, as prescribed in this section (California Public Resources Code Section 5097.98), with the most likely descendants regarding their recommendations, if applicable, taking into account the possibility of multiple human remains.

Cumulative Impacts The proposed Project would result in no impacts to historical, known archaeological or paleontological resources, or known human remains. The chances of cumulative impacts occurring as a result of Project implementation plus implementation of other projects in the region is not likely since proposed Projects would be subject to individual project-level environmental review. Since there would be no project-related impacts and due to existing laws and regulations in place to protect cultural resources and prevent significant impact to paleontological resources, the potential incremental effects of the proposed Project would not be cumulatively considerable.

Valley & Spruce Project | 33

6. Geology and Soils Less Than Significant Potentially with Less than Significant Mitigation Significant No Issues Impact Incorporated Impact Impact Would the project: a. Expose people or structures to potential substantial adverse effects, including the risk of loss, injury, or death involving: i. Rupture of a known earthquake fault, as delineated on the most recent Alquist-Priolo Earthquake Fault Zoning Map issued by the State Geologist for the area or based on other substantial evidence of a known fault? Refer to Division of Mines and Geology Special Publication 42.

ii. Strong seismic ground shaking?

iii. Seismic-related ground failure, including

liquefaction?

iv. Landslides? b. Result in substantial soil erosion or the loss of

topsoil? c. Be located on a geologic unit or soil that is unstable, or that would become unstable as a result of the project, and potentially result in on- or off-site landslide, lateral spreading, subsidence, liquefaction or collapse? d. Be located on expansive soil, as defined in Table 18- 1-B of the Uniform Building Code (1994), creating substantial risks to life or property? e. Have soils incapable of adequately supporting the use of septic tanks or alternative waste water

disposal systems where sewers are not available for the disposal of waste water?

Discussion A Geotechnical Investigation was prepared for the proposed Project by Southern California Geotechnical. (September 2017). The report is provided in Appendix D; the results and conclusions of the report are summarized herein. a) Expose people or structures to potential substantial adverse effects, including the risk of loss, injury, or death involving: i. Rupture of a known earthquake fault, as delineated on the most recent Alquist-Priolo Earthquake Fault Zoning Map issued by the State Geologist for the area or based on other substantial evidence of a known fault? Refer to Division of Mines and Geology Special Publication 42. Less Than Significant Impact.

Valley & Spruce Project | 34

The Alquist-Priolo Earthquake Fault Zoning Act (Act) was passed in 1972 to address the hazard of surface faulting to structures for human occupancy. The Act’s main purpose is to prevent the construction of buildings used for human occupancy on the surface trace of active faults. The Act requires the State Geologist to establish regulatory zones, known as “Alquist-Priolo (AP) Earthquake Fault Zones” around the surface traces of active faults and to issue appropriate maps. If an active fault is found, a structure for human occupancy cannot be placed over the trace of the fault and must be set back from the fault (typically 50 feet). Based on the Geotechnical Investigation the proposed Project site is not located within an AP Earthquake Fault Zone and no evidence of faulting was observed during the investigation. Therefore, the potential for damage due to direct fault rupture is considered to be low. The possibility of significant fault rupture on the Project site is considered to be less than significant and no mitigation is required. ii. Strong seismic ground shaking? Less Than Significant Impact. The Project site is located in an area of high regional seismicity and numerous faults capable of producing significant ground motions are located in the region. The closest known active earthquake fault to the proposed Project is the San Jacinto fault located approximately 3.5 miles northeast.5 The Cucamonga fault and the San Andreas fault are also located in the regional vicinity and ground shaking originating from these or other faults in the region could subject the proposed Project site to strong ground motions and impact the proposed Project. The proposed Project would be required to be constructed in conformance with the California Building Code (CBC), City regulations, and other applicable standards. Conformance with standard engineering practices and design criteria would reduce the effects of seismic ground shaking to a less than significant level. No mitigation is required. iii. Seismic-related ground failure, including liquefaction? Less than Significant Impact. Liquefaction is the loss of strength that generally occurs as a “quicksand” type of ground failure caused by strong ground shaking. Liquefaction generally occurs in cohesionless, saturated soils when the pore-water pressure induced in the soil by a seismic event becomes equal to or exceeds the overburden pressure. The primary factors influencing liquefaction potential include groundwater, soil type, relative density of the sandy soils, confining pressure, and the intensity and duration of ground shaking. The potential for liquefaction generally occurs during strong ground shaking within relatively loose sediments where the groundwater is usually less than 50-feet. Although the California Geological Survey has not yet conducted detailed seismic hazard mapping in the area, the San Bernardino County Official Land Use Plan, General Plan, Geologic Hazard Overlay does not show the proposed Project within an area susceptible to liquefaction (San Bernardino County, 1994). Based on the listed mapping, and the subsurface conditions encountered during the geotechnical investigation from the boring locations, impacts from liquefaction are considered less than significant. iv. Landslides? No Impact. Landslides are mass movements of the ground that include rock falls, relatively shallow slumping and sliding of soil, and deeper rotational or transitional movement of soil or

5Caltech, 2017. – Southern California Earthquake Data Center - San Jacinto Fault Zone. Available at: http://scedc.caltech.edu/significant/index.html. Accessed October 5, 2017.

Valley & Spruce Project | 35

rock. The Project site is relatively flat and, according to the San Bernardino County Geologic Hazard Overlay Map, is not located within an area susceptible to landslides6 (San Bernardino County, 1994). Therefore, there would be no impact from landslides on the proposed Project and no mitigation is required. b) Result in substantial soil erosion or the loss of topsoil? Less Than Significant Impact. Grading during the construction phase of the proposed Project would displace soils and temporarily increase the potential for soils to be subject to wind and water erosion. However, erosion and loss of topsoil would be controlled using standard erosion control practices during construction. Accordingly, the proposed Project would be required to prepare a SWPPP under the National Pollutant Discharge Elimination System (NPDES) General Construction Permit to implement BMPs to minimize stormwater runoff during construction. Adherence to the SWPPP with the recommendations of the Water Quality Management Plan prepared for the proposed Project would reduce possible impacts related to the erosion to less than significant. No mitigation is required. c) Be located on a geologic unit or soil that is unstable, or that would become unstable as a result of the project, and potentially result in on- or off-site landslide, lateral spreading, subsidence, liquefaction or collapse? Less Than Significant Impact with Mitigation Incorporated. The Project site is not identified as being located on a geologic unit or soil that has been identified as being unstable or having the potential to result in on-site or off-site landslide, lateral spreading, subsidence, liquefaction or collapse. The Geotechnical Investigation for the proposed Project site found impacts due to liquefaction to be less than significant. There would be no impacts from landslides because the proposed Project site is flat and is not located near any areas with steep topography that would be susceptible to landslides. The proposed Project site consists of undocumented fill materials extending to depths of 2.5 to 4.5 feet below the surface of the site that overlay alluvial materials. The fill soils generally possess variable densities and strengths, and it is not known where the soil originated, when it was placed, or if it was compacted. Based on the results of laboratory testing, the fill materials possess unfavorable consolidation and collapse characteristics and the existing fill soils are not considered suitable, in their present condition, to support the foundation loads of the proposed Project. The alluvial soils generally possess more favorable consolidation/collapse characteristics. Soil remedial grading would be required to remove the artificial fill materials so they could be replaced with a proper compacted structural fill. The Geotechnical Investigation stated that removal and recompaction of the artificial fill and near-surface native soils would be estimated to result in an average shrinkage of 10 to 15 percent. This estimate is based on the results of dry density testing performed on small- diameter samples of the soils from the boring locations. Due to settlement and machinery working, minor ground subsidence is expected to occur in the soils below the zone of removal. The subsidence is estimated to be plus or minus 0.1±. The actual amount of subsidence is expected to be variable and will be dependent on the type of machinery used, repetitions of use, and dynamic effects.

6 San Bernardino County, 1994 – San Bernardino County Land Use Plan – General Plan – Geologic Hazard Overlays. Available at: http://cms.sbcounty.gov/lus/planning/zoningoverlaymaps/geologichazardmaps.aspx Accessed October 5, 2017.

Valley & Spruce Project | 36

The Geotechnical Investigation includes recommendations to ensure that soils are made appropriate for development of the proposed Project on the Project site. The recommendations, including overexcavation of soils so that a uniform blanket of structural fill can be created to support the proposed structure, are included as a part of mitigation measure GEO -1, below. Implementation of mitigation that incorporates compliance with the recommendation of the Geotechnical Investigation would reduce impacts associated with consolidation and collapse to less than significance. Mitigation Measure GEO-1: Prior to issuance of a grading permit, the developer shall, to the satisfaction of the City Public Works Director, show that precise grading plan(s) include(s) all recommendations contained in the geotechnical investigation report prepared for the proposed Project. The performance standard for this measure is to assure that all recommended grading and structures for the project conform to City standards. d) Be located on expansive soil, as defined in Table 18-1-B of the California Building Code (2013), creating substantial risks to life or property? Less Than Significant Impact. Boring logs were taken from eight locations on the proposed Project site including four boring logs in the eastern half and four in the western half. Soils from the boring logs were classified using the Unified Soil Classification System (USCS) in accordance with ASTM-D2488, soil densities were determined using ASTM D-2937, consolidation potential was tested using ASTM D-2435, and maximum dry density and optimum moisture content was tested per ASTM D-1557. The near-surface soils generally consist of sands and silty sand with no appreciable clay content and were visually classified as non-expansive. The soils do not require special design considerations required related to expansive soils. In addition, the proposed Project would be required conform to the California Building Code, city regulations, and other applicable construction and design standards. Conformance with standard engineering practices, design criteria would ensure impacts related to expansive soil potential remain less than significant. e) Have soils incapable of adequately supporting the use of septic tanks or alternative wastewater disposal systems where sewers are not available for the disposal of wastewater? No Impact. The proposed Project does not include the implementation of septic tanks or alternative wastewater disposal systems. Therefore, no impact would occur and no mitigation is required.

Cumulative Impacts The potential cumulative impact related to earth and geology is typically site specific. The analysis herein determined that the proposed Project would not result in any significant impacts related to landform modification, grading, or the destruction of a geologically significant landform or feature with implementation of mitigation. Moreover, existing State and local laws and regulations are in place to protect people and property from substantial adverse geological and soils effects, including fault rupture, strong seismic ground shaking, seismic-induced ground failure (including liquefaction), and landslides. Existing laws and regulations also protect people and property from adverse effects related to soil erosion, expansive soils, loss of topsoil, development on an unstable geologic unit or soil type that could result in on- or off-site landslides, lateral spreading, subsidence, liquefaction, or collapse. These existing laws and regulations, along with mitigation assigned to the proposed Project, would render potentially adverse geological and soil effects of the proposed Project to a level considered less than significant. Moreover, these existing laws and regulations also ensure that past, present, and reasonably foreseeable future projects in the

Valley & Spruce Project | 37

City of Rialto and surrounding region do not result in substantial adverse geological and soils effects. As a result, the existing legal and regulatory framework would ensure that the incremental geological and soils effects of the proposed Project would not result in greater adverse cumulative effects when considered together with the effects of other past, present, and reasonably foreseeable future projects in the region. The impacts of the proposed project-related to geology and soils would be less than cumulatively considerable.

Valley & Spruce Project | 38

7. Greenhouse Gas Emissions Less Than Significant Potentially with Less than Significant Mitigation Significant No Issues Impact Incorporated Impact Impact Would the project: a. Generate greenhouse gas emissions, either directly or indirectly, that may have a significant impact on the environment? b. Conflict with an applicable plan, policy or regulation adopted for the purpose of reducing the emissions of greenhouse gases?

Discussion Certain gases in the earth’s atmosphere, classified as greenhouse gases (GHGs), play a critical role in determining the earth’s surface temperature. Emissions of GHGs contributing to global climate change are attributable in large part to human activities associated with transportation, industrial/manufacturing, utility, residential, commercial, and agricultural emissions sectors. California is a significant emitter of CO2e in the world. The State of California has adopted various administrative initiatives and legislation relating to climate change, much of which set aggressive goals for GHG emissions reductions statewide. The SCAQMD has formed a GHG CEQA Significance Threshold Working Group to provide guidance to local lead agencies on determining significance for GHG emissions in their CEQA documents. For all industrial projects, the SCAQMD adopted a screening threshold of 10,000 MTCO2-eq per year. SCAQMD concluded that projects with emissions less than the screening threshold would not result in a significant cumulative impact. As the proposed Project involves the construction of a new warehouse, the 10,000 MTCO2-eq per year industrial screening threshold has been selected as the significance threshold. An Air Quality, Greenhouse Gas and Health Risk Assessment Study for the Valley and Cactus Avenue Warehouse Project was prepared by Entech Consulting Group (October 2017). The report is provided in Appendix A; the results and conclusions of the report are summarized herein. a) Generate greenhouse gas emissions, either directly or indirectly, that may have a significant impact on the environment? Less than Significant Impact.

GHGs, primarily carbon dioxide (CO2), methane (CH4), and nitrous (N2O) oxide, collectively reported as CO2e, are directly emitted from stationary source combustion of natural gas in equipment such as water heaters, boilers, process heaters, and furnaces. GHGs are also emitted from mobile sources such as on-road vehicles and off-road construction equipment burning fuels, such as gasoline, diesel, biodiesel, propane, or natural gas (compressed or liquefied). Indirect GHG emissions result from electric power generated elsewhere (i.e., power plants) used to operate process equipment, lighting, and utilities at a facility. Also, included in GHG quantification is electric power used to pump the water supply (e.g., aqueducts, wells, pipelines) and the disposal and decomposition of municipal waste in landfills (CARB 2008). Using CalEEMod, direct on-site and off-site GHG emissions were estimated for construction and operation. Indirect off-site GHG emissions were estimated to account for electric power used by the proposed Project, water conveyance, and solid waste disposal. In 2015, the SCAQMD officially adopted an industrial facility mass emissions threshold of 10,000 MT CO2e/yr.

Valley & Spruce Project | 39

Table 7: GHG Emissions Summary and Significance Evaluation shows unmitigated GHG emissions and evaluates these emissions against SCAQMD significance thresholds. Off-site traffic impacts are included in these emissions estimates, along with construction emissions amortized over 30 years. Peak daily traffic volumes were used in estimating the annual emissions. Therefore, there is a chance this will result in an overestimation of the GHG emissions. As shown in Table 7, mitigated GHG emissions are below the proposed GHG significance threshold for industrial land use projects, i.e., LST. Since the proposed Project would not exceed these thresholds, the proposed Project would not be required to implement mitigation measures to reduce GHG emissions and would have a less than significant impact.

Table 7: GHG Emissions Summary and Significance Evaluation

Unmitigated Threshold GHGs Significance MT/yr MT/yr

CO2 9,567.22 — —

CH4 8.0 — —

N2O 0.14 — —

CO2e 9,809.8 10,000.0 LTS Notes: Comprises annual operational emissions and construction emissions amortized over 30 years LTS – Less Than Significant Sources: SCAQMD 2008a, CalEEMod version 2016.3.1

b) Conflict with an applicable plan, policy or regulation adopted for the purpose of reducing the emissions of greenhouse gases? Less than Significant Impact.

SCAQMD’s screening thresholds are 10,000 MT/year CO2e for industrial projects. The industrial screening threshold was used for the proposed Project. At a screening level of 9,809.8 metric tons of CO2e each year (Table 7), the Project's GHG emissions level falls below the SCAQMD screening threshold of 10,000 metric tons per year of CO2e for industrial projects. Therefore, as the project’s emissions do not exceed SCAQMD’s screening thresholds, the proposed Project is consistent with the applicable plan, policy or regulation adopted for the purpose of reducing the emissions of greenhouse gases. Therefore, impacts are less than significant and no mitigation is required.

Cumulative Impacts GHG impacts are recognized as exclusively cumulative impacts; there are no non-cumulative GHG emission impacts from a climate change perspective. As discussed above, the Project’s emissions would be below the SCAQMD’s threshold for of 10,000 MT per year of CO2e for an industrial project and would not conflict with applicable plans. Thus, the proposed Project’s cumulative contribution of GHG emissions would be less than significant.

Valley & Spruce Project | 40

8. Hazards and Hazardous Materials Less Than Significant Potentially with Less than Significant Mitigation Significant No Issues Impact Incorporated Impact Impact Would the project: a. Create a significant hazard to the public or the environment through the routine transport, use, or disposal of hazardous materials? b. Create a significant hazard to the public or the environment through reasonably foreseeable upset

and accident conditions involving the release of hazardous materials into the environment? c. Emit hazardous emissions or handle hazardous or acutely hazardous materials, substances, or waste

within one-quarter mile of an existing or proposed school? d. Be located on a site which is included on a list of hazardous materials sites compiled pursuant to Government Code Section 65962.5 and, as a result, would it create a significant hazard to the public or the environment? e. For a project located within an airport land use plan or, where such a plan has not been adopted, within two miles of a public airport or public use airport, would the project result in a safety hazard for people residing or working in the project area? f. For a project within the vicinity of a private airstrip, would the project result in a safety hazard for people residing or working in the project area? g. Impair implementation of or physically interfere with an adopted emergency response plan or emergency evacuation plan? h. Expose people or structures to a significant risk of loss, injury or death involving wildland fires, including where wildlands are adjacent to urbanized areas or where residences are intermixed with wildlands?

Discussion A Phase I Environmental Site Assessment was prepared for the proposed Project by ATC Group Services LLC. (October 2017) and is provided as Appendix E; the results of the report is summarized herein. a) Create a significant hazard to the public or the environment through the routine transport, use, or disposal of hazardous materials? Less Than Significant Impact. Per the Phase I Environmental Site Assessment (ESA), the Project site was used for agricultural purposes between at least the late 1930s and the late 1970s suggesting the possible presence of environmentally persistent pesticides and herbicides on the property. However, ATC concluded that the former application of pesticides for agricultural purposes generally does not require a remedial response in most jurisdictions and therefore is not

Valley & Spruce Project | 41

considered to represent a Recognized Environmental Condition (REC). In addition, ATC conducted a non-comprehensive visual review of suspect asbestos containing materials (ACM) and lead based paint (LBP) at the site. Suspect ACMs and LBP were observed at the site consisting of several debris piles, which appeared to be primarily concrete and a stucco dumpster enclosure, located in the east-central portion of the former storage yard. No structures were observed on the site during the September 27, 2017 site visit for the Phase I ESA. ATC did not identify any RECs associated with the site and did not recommend any additional investigation. Once the proposed Project is constructed, hazardous materials would be limited to those associated with a warehouse facility. These include cleaners, paints, solvents; and fertilizers and pesticides for site landscaping. Because these materials are used in very limited quantities, they are not considered a hazard to the public. Adherence to federal, State, and local health and safety requirements regarding these substances would preclude potential impacts. No mitigation is required. b) Create a significant hazard to the public or the environment through reasonably foreseeable upset and accident conditions involving the release of hazardous materials into the environment? Less Than Significant Impact. The proposed Project anticipated to be built speculatively and is not anticipated to result in releases of hazardous materials into the environment. The proposed facility would be expected to use limited hazardous materials and substances which would be limited to cleaners, paints, solvents; and fertilizers and pesticides for site landscaping. All materials and substances would be subject to applicable health and safety requirements. A less than significant impact would occur and no mitigation is required. c) Emit hazardous emissions or handle hazardous or acutely hazardous materials, substances, or waste within one-quarter mile of an existing or proposed school? Less Than Significant Impact. The Project site is located approximately 350 feet south of Ruth Grimes Elementary School, a public elementary school, at 1609 S. Spruce Avenue, Rialto. Joe Baca Middle School is located approximately 150 feet northeast of the Project site at 1640 S. Lilac Avenue, Rialto. Although the proposed industrial warehouse is speculative in nature, the specific use that would occupy the industrial building would comply with the allowable uses identified in the Gateway Specific Plan. Furthermore, allowable land uses would comply with all applicable local, State and Federal hazardous materials regulations. As such, there will be no significant impact. d) Be located on a site which is included on a list of hazardous materials sites compiled pursuant to Government Code Section 65962.5 and, as a result, would it create a significant hazard to the public or the environment? No Impact. The Project site is not included on a hazardous site list compiled pursuant to California Government Code Section 65962.5.7 In addition, a Phase I Environmental Site Assessment was prepared for the Project site by ATC in October 2017 and according to that report, there was no Recognized Environmental Condition (REC)s (as defined by ASTM Practice E 1527-13)

7 California, State of, Department of Toxic Substances Control, DTSC's Hazardous Waste and Substances Site List - Site Cleanup (Cortese List). Available at: http://www.dtsc.ca.gov/SiteCleanup/Cortese_List.cfm. Accessed October 9, 2017.

Valley & Spruce Project | 42

identified in association with the Project site that required additional investigation. No significant adverse impacts relative to hazardous materials sites would result with project implementation. No mitigation is required. e) For a project located within an airport land use plan or, where such a plan has not been adopted, within two miles of a public airport or public use airport, would the project result in a safety hazard for people residing or working in the project area? No Impact. The proposed Project is not located within the vicinity of a public use airport and would not create a safety hazard for people residing or working in the project area. No impacts would occur and no mitigation is required. f) For a project within the vicinity of a private airstrip, would the project result in a safety hazard for people residing or working in the project area? No Impact. The proposed Project is not located within the vicinity of a private airstrip and would not result in a safety hazard for people residing or working in the project area. No impacts would occur and no mitigation is required. g) Impair implementation of or physically interfere with an adopted emergency response plan or emergency evacuation plan? No impact. The proposed Project would not impair or physically interfere with an adopted emergency response or evacuation plan. Primary access to all major roads would be maintained during construction of the proposed Project. Therefore, no associated impacts would occur. h) Expose people or structures to a significant risk of loss, injury or death involving wildland fires, including where wildlands are adjacent to urbanized areas or where residences are intermixed with wildlands? No Impact. The proposed Project would not expose people or structures to a risk of loss, injury or death involving wildland fires. The Project site is in a developed urban area and it is not adjacent to any wildland areas. The proposed Project is not located in a fire hazard zone in the City’s General Plan (2010). Therefore, no impact would occur in regard to wildland fires and no mitigation is required.

Cumulative Impacts The incremental effects of the proposed Project related to hazards and hazardous materials, if any, are anticipated to be minimal, and any effects would be site-specific. Therefore, the proposed Project would not result in incremental effects to hazards or hazardous materials that could be compounded or increased when considered together with similar effects from other past, present, and reasonably foreseeable probable future projects. The proposed Project would not result in cumulatively considerable impacts to or from hazards or hazardous materials.

Valley & Spruce Project | 43

9. Hydrology and Water Quality Less Than Significant Potentially with Less than Significant Mitigation Significant No Issues Impact Incorporated Impact Impact Would the project: a. Violate any water quality standards or waste

discharge requirements? b. Substantially deplete groundwater supplies or interfere substantially with groundwater recharge such that there would be a net deficit in aquifer volume or a lowering of the local groundwater

table level (e.g., the production rate of pre-existing nearby wells would drop to a level which would not support existing land uses or planned uses for which permits have been granted)? c. Substantially alter the existing drainage pattern of the site or area, including through the alteration of the course of a stream or river, in a manner which would result in substantial erosion or siltation on- or off-site? d. Substantially alter the existing drainage pattern of the site or area, including through the alteration of the course of a stream or river, or substantially

increase the rate or amount of surface runoff in a manner which would result in flooding on- or off- site? e. Create or contribute runoff water which would exceed the capacity of existing or planned storm

water drainage systems or provide substantial additional sources of polluted runoff? f. Otherwise substantially degrade water quality? g. Place housing within a 100-year flood hazard area as mapped on a federal Flood Hazard Boundary

or Flood Insurance Rate Map or other flood hazard delineation map? h. Place within a 100-year flood hazard area structures which would impede or redirect flood flows? i. Expose people or structures to a significant risk of loss, injury or death involving flooding, including

flooding as a result of the failure of a levee or dam? . Inundation by seiche, tsunami, or mudflow?

Valley & Spruce Project | 44

Discussion Preliminary Hydrology Calculations were prepared for the proposed Project by Thienes Engineering (September 2017) and are provided as Appendix F. A Water Quality Management Plan was prepared for the proposed Project and is provided as Appendix G. The results and conclusions of both reports are summarized herein. a) Violate any water quality standards or waste discharge requirements? Less Than Significant Impact. The Project site is a largely disturbed area comprised of disked non-native grassland vegetation with small developed patches comprised of sidewalks and cement pads. A former storage yard occupied the site until it was demolished/removed in September 2017. No structures are currently located on the site. The site generally surface drains southerly to the Caltrans maintained concrete channel (I-10 Drainage Channel) adjacent to I -10. The southwest portion of the proposed building, the westerly parking lot and the west portion of the truck yard are proposed to drain southerly to catch basins in the proposed truck yard. Runoff would discharge offsite via a storm drain connection to the southerly existing I-10 Drainage Channel. The north portion of the proposed building and the northerly landscape adjacent to Valley Boulevard would drain easterly and then southerly, via a proposed storm drain to catch basins in the proposed truck yard. These catch basins would also accept runoff from the southeast portion of the building and the easterly parking lot. Runoff would then be conveyed westerly via the proposed storm drain, then southerly to the existing I-10 Drainage Channel. A proposed underground infiltration basin in the truck yard would be utilized to reduce the proposed condition discharge to below existing condition discharge. Runoff tributary to the truck yard would be temporarily detained before it is discharged to the existing I-10 Drainage Channel. Also, runoff from the southeasterly and southwesterly self-treating landscape areas would drain offsite without being routed to the proposed underground infiltration basin. The Project site is currently accepting northerly offsite flows via three 24-inch pipes across Valley Blvd. Under proposed conditions, this offsite flow will be intercepted by a 42-inch storm drain and conveyed easterly to the existing 42-inch storm drain in Cactus Avenue. Similarly, street flow from the easterly half of Spruce Avenue would be intercepted by a proposed catch basin and conveyed via the proposed storm drain to the existing 45-inch storm drain in Spruce Avenue, which drains to the existing I-10 Drainage Channel. The proposed Project will meet stormwater treatment requirements in the San Bernardino MS4 Permit; and therefore, impacts to water quality as a result of the proposed Project would be less than significant. The majority of the site drains to a proposed underground infiltration basin will meet the performance criteria for low impact design (LID) BMP Design and infiltrate the Design Capture Volume (DCV). The DCV will infiltrate, and flows greater than the DCV will drain directly to the onsite storm drain system that conveys runoff to the I-10 Drainage Channel. In addition to the underground infiltration basin, two small landscape areas are designed to be self-treating and will directly discharge to the I-10 Drainage Channel. To minimize water quality impacts during construction of the proposed Project, construction activities would be required to comply with a Stormwater Pollution Prevention Plan (SWPPP) consistent with the General Permit for Stormwater Discharge Associated with Construction Activity (Construction Activity General Permit). The SWPPP would incorporate Best Management Practices (BMPs) such as gravel bags, silt fence, and fiber rolls. Preparation and implementation of a SWPPP would reduce potential impacts to water quality during construction to a less than significant level. No mitigation is required.

Valley & Spruce Project | 45

b) Substantially deplete groundwater supplies or interfere substantially with groundwater recharge such that there would be a net deficit in aquifer volume or a lowering of the local groundwater table level (e.g., the production rate of pre-existing nearby wells would drop to a level which would not support existing land uses or planned uses for which permits have been granted)? No Impact. The proposed Project does not propose to use groundwater. Although the proposed Project would result in additional impervious surfaces on site, the proposed Project would construct an underground infiltration facility which would detain and treat water prior to discharging into the public storm drain system. Therefore, the proposed Project would not significantly impact local groundwater recharge. No impacts would occur in this regard and no mitigation is required. c) Substantially alter the existing drainage pattern of the site or area, including through the alteration of the course of stream or river, in a manner which would result in substantial erosion or siltation on- or off-site? No Impact. The proposed Project would not substantially alter the existing drainage patterns of the site or vicinity. The proposed Project would continue to drain to the I-10 Drainage Channel adjacent to I-10. The proposed Project proposes to use an underground infiltration facility and self-treating landscape areas to treat stormwater runoff prior to discharge into the existing I- 10 Drainage Channel. The Project site does not contain any streams or rivers; therefore, none would be altered by the proposed Project. Therefore, no impact would occur and no mitigation is required. d) Substantially alter the existing drainage pattern of the site or area, including through the alteration of the course of a stream or river, or substantially increase the rate or amount of surface runoff in a manner which would result in flooding on- or off-site? Less Than Significant Impact. Refer to response VI.9(c) above. The proposed Project would not substantially alter existing drainage patterns of the site or Project vicinity. The proposed Project does not include any streams or rivers. On-site surface run-off would be directed to the on-site underground infiltration facility. The proposed underground infiltration facility would also minimize the potential for flooding to occur on site or off site. Impacts would be less than significant and no mitigation is required. e) Create or contribute runoff water which would exceed the capacity of existing or planned stormwater drainage systems or provide substantial additional sources of polluted runoff? Less Than Significant Impact. The proposed Project discharges stormwater to the existing Caltrans owned and maintained I-10 Drainage Channel. In existing condition, the Project site’s 100-year peak flow is 39.3 cfs. The proposed Project will detain increase flows to existing condition using the truck yard for detention storage. The proposed Project will not release more stormwater than existing conditions. In addition, the proposed Project would be required to prepare a SWPPP under the National Pollutant Discharge Elimination System (NPDES) General Construction Permit to implement BMPs to minimize stormwater runoff during construction. Adherence with the recommendations of the Water Quality Management Plan prepared for the proposed Project, and preparation of a SWPPP would reduce possible impacts related to the stormwater drainage system to less than significant. No mitigation is required.

Valley & Spruce Project | 46

f) Otherwise substantially degrade water quality? Less Than Significant Impact. Water quality impacts other than those described in Response V.9(a) above are not anticipated with implementation of the proposed Project. Impacts resulting from the proposed Project would be less than significant and no mitigation is required. g) Place housing within a 100-year flood hazard area as mapped on a federal Flood Hazard Boundary or Flood Insurance Rate Map or other flood hazard delineation map? No Impact. The proposed Project is not within a 100-year floodplain and does not propose housing. Therefore, no flood-related impacts would occur in this regard and no mitigation is required. h) Place within a 100-year flood hazard area structures which would impede or redirect flood flows? No Impact. The proposed Project is not within a 100-year floodplain. Therefore, no flood-related impacts would occur in this regard and no mitigation is required. i) Expose people or structures to a significant risk of loss, injury or death involving flooding, including flooding as a result of the failure of a levee or dam? No Impact. The City of Rialto General Plan (2010) Flood Hazard Zones shows that the proposed Project is outside of the 500-year floodplain. The closest dam or levee is the Lytle Creek Levee located over 6 miles north of the Project site. Given the distance from the Lytle Creek Levee, resultant flooding from the unlikely failure of the levee would not expose people or structures to a significant risk of loss, injury, or death. The closest dams to the Project site are the Wiggins Number 2 Dam and the Little Mountain Dam, both over 10 miles east of the site. The proposed Project is not within the flood inundation zones of these dams pursuant to dam inundation boundary files available from the State of California Emergency Management Agency.8 No associated flood hazard impacts would occur. j) Inundation by seiche, tsunami, or mudflow? No Impact. The proposed Project is located approximately 40 miles east of the Pacific Ocean. There is no risk of exposure to inundation by seiche or tsunami. The proposed Project is relatively flat so the potential for a mudflow is unlikely. Therefore, no impact would occur and no mitigation is required.

Cumulative Impacts The potential impacts related to hydrology and storm water runoff are typically site specific and site specific BMPs are implemented at the proposed Project level. The analysis above determined that the implementation of the proposed Project would not result in significant impacts. Therefore, the proposed Project would have no impact under most hydrology criteria, and therefore could not contribute toward a cumulative impact. In regards, to proposed Project impacts that would be considered less than significant, such impacts are not expected to result in compounded or increased impacts when considered together with similar effects from other past, present, and reasonably foreseeable probable future projects, as other projects would be subject to similar laws and requirements regarding hydrology practices. Potential impacts are considered less than cumulative considerable.

8 http://myplan.calema.ca.gov. Accessed October 9, 2017.

Valley & Spruce Project | 47

10. Land Use and Planning Less Than Significant Potentially with Less than Significant Mitigation Significant No Issues Impact Incorporated Impact Impact Would the project: a. Physically divide an established community?

b. Conflict with any applicable land use plan, policy, or regulation of an agency with jurisdiction over the project (including, but not limited to the

general plan, specific plan, local coastal program, or zoning ordinance) adopted for the purpose of avoiding or mitigating an environmental effect? c. Conflict with any applicable habitat conservation

plan or natural community conservation plan?

Discussion a) Physically divide an established community? No Impact. Projects that are typically considered to have the potential to divide an established community include the construction of a new freeways, highways, or roads, or other uses that physically separate an existing or established neighborhood. The proposed Project does not include the construction of public roadways, structures, or other improvements that would be located between existing neighborhoods. Therefore, the proposed Project would not physically divide or separate neighborhoods within an established community. The Project site is bound by Valley Boulevard to the north, Spruce Avenue to the west, Interstate 10 (I-10) to the south and Cactus Avenue to the east. The Project site is located in a predominately industrial and commercial area. The land uses surrounding the Project site consist of a mix of uses including industrial, commercial, residential, a major transportation corridor, and schools. Immediately south of the proposed Project site is the Interstate 10 (I-10) and the Union Pacific Rail Yard, to the east and west are commercial, warehousing, and industrial uses, to the northwest are residential uses and a school, and to the north and northeast are an auto sales yard, vacant property, and a school. As discussed above, the proposed Project is predominantly surrounded by industrial and commercial uses and would not physically separate and residential areas. Accordingly, the proposed Project would generally blend in with the surrounding uses and would not physically divide an established community. Therefore, no impacts would occur and no mitigation is required. b) Conflict with any applicable land use plan, policy, or regulation of an agency with jurisdiction over the project (including, but not limited to the general plan, specific plan, local coastal program, or zoning ordinance) adopted for the purpose of avoiding or mitigating an environmental effect? No Impact. The City of Rialto General Plan land use designation for the proposed Project site is Business Park with a Specific Plan Overlay (Gateway Specific Plan Area). According to the General Plan, the Gateway Specific Plan area is identified as a Redevelopment Area. In part, the focus of this area is to reduce visual blight, efficiently use underutilized properties, and to relieve traffic

Valley & Spruce Project | 48

congestion.9 Accordingly, one of the objectives of the Gateway Specific Plan is to create an attractive entry to the City by upgrading the Gateway and encouraging development on vacant land. The Gateway Specific Plan incorporates a mix of uses, which includes Industrial Park uses on the Project site. The zoning for the Gateway Specific Plan area and the Project site is I-P (Industrial Park). The I-P designation allows for contractor and general trade office and storage; minor assembly, fabrication, adjustment or repair or previously manufactured items; printing and publishing; warehousing and storage in an enclosed building; wholesale and distribution facilities; and accessory buildings used ancillary to permitted uses10. Although the proposed industrial warehouse is speculative in nature, the specific use that would occupy the industrial building would comply with the allowable uses identified in the Gateway Specific Plan. Furthermore, allowable land uses would comply with all applicable local, State and Federal hazardous materials regulations. The proposed Project is consistent with the pertinent land use planning and policy documents, including the General Plan, Zoning (with the variance to allow a structure height of 47 feet), and the Gateway Specific Plan. Therefore, the proposed Project would have no impact on a plan, policy, or regulation adopted for the purpose of avoiding or mitigating an environmental effect. c) Conflict with any applicable habitat conservation plan or natural community conservation plan? No Impact. The Project site is not located within an area designated as a habitat conservation area or subject to a natural community conservation plan. Therefore, the proposed Project would not conflict either type of plan, impacts would not occur, and no mitigation is required.

Cumulative Impacts The proposed Project does not conflict with any applicable land use regulations, land use policies, or land use planning documents. The proposed Project does not propose any new roadways or other significant infrastructure improvements that would restrict access, require a diversion of existing travel routes, or otherwise divide an established community. Therefore, the proposed Project would not contribute towards any cumulative impacts in these regards. The proposed Project would not result in an impact on any sensitive plant or animal species covered by a habitat conservation plan or natural community conservation plan, nor does it hinder the implementation or establishment of such plans. For these reasons, the proposed Project would not contribute to a cumulative impact or result in land use conflicts. Therefore, taken with past, present and reasonably foreseeable Projects impacts are not considered cumulatively considerable, and no mitigation is required.

9 Rialto, City of, 2010 – General Plan – Available at: http://yourrialto.com/wp-content/uploads/2016/08/General-Plan-Update- 2010.pdf Accessed September 6, 2017. 10 Rialto, City of, 2017 – Zoning- Available at: https://library.municode.com/ca/rialto/codes/code_of_ordinances?nodeId=TIT18ZO_CH18.35INPAZO Accessed September 6, 2017.

Valley & Spruce Project | 49

11. Mineral Resources Less Than Significant Potentially with Less than Significant Mitigation Significant No Issues Impact Incorporated Impact Impact Would the project: a. Result in the loss of availability of a known mineral resource that would be of value to the region and the residents of the State? b. Result in the loss of availability of a locally- important mineral resource recovery site

delineated on a local general plan, specific plan or other land use plan?

Discussion a) Result in the loss of availability of a known mineral resource that would be of value to the region and the residents of the State? Less Than Significant Impact. The proposed Project site does not have history of known mining or quarry operations. The Surface Mining and Reclamation Act of 1975 (SMARA) requires the State Geologist to classify land in California according to its potential to contain mineral resources. The City of Rialto General Plan shows the Mineral Lands Classification (MLC) maps of the proposed Project site based the SMARA. According to the General Plan, the majority of the proposed Project site is classified as MRZ-2, which is defined as areas where geologic data indicate that significant PCC-Grade aggregate resources are present. The northeast corner of the Project site, adjacent to the intersection of Cactus Avenue and Valley Boulevard, is classified as MRZ-3, which is defined as areas containing known or inferred mineral occurrences of undetermined mineral resource significance11. The Department of Conservation, Division of Oil, Gas, and Geothermal Resources (DOGGR) addresses the needs of state and local governments, and the oil and gas industry by regulating statewide oil and gas activities with uniform laws and regulations. DOGGR maintains a mapping system that shows the location of all oil and gas wells within the state. According to the DOGGR mapping system, the two closest wells that were used for oil and gas production are approximately 1.5 miles to the southwest of the proposed Project. One of the wells has been plugged and the other is buried. DOGGR does not map any wells on the proposed Project site12 and there is no known history of oil or gas wells having been drilled within the Project site. Although the proposed Project site has been mapped within a MRZ-2, the site does not have history of aggregate resource mining. In addition, the site is designated for industrial uses and use of the site for mining would be inconsistent with pertinent planning and policy documents and due to the proximity of adjacent land uses, the site is not conducive for use

11 Rialto, City of, 2010 – General Plan – Available at: http://yourrialto.com/wp-content/uploads/2016/08/General-Plan-Update- 2010.pdf Accessed September 6, 2017. 12 California Department of Conservation, Division of Oil, Gas, and Geothermal Resources. Available at: http://www.conservation.ca.gov/dog/Pages/Wellfinder.aspx. Accessed September 6, 2017.

Valley & Spruce Project | 50

as a mine. Therefore, impacts related to the loss of availability of a known mineral resource would be considered less than significant and no mitigation is required. b) Result in the loss of availability of a locally-important mineral resource recovery site delineated on a local general plan, specific plan or other land use plan? Less Than Significant Impact. The proposed Project site has not been used for mineral resource recovery and is not delineated as a mineral resource recovery site on any land use plans. Additionally, the proposed Project site is not currently used (or planned for use) as a mineral resource recovery site. Therefore, no impacts to mineral resources in this regard would be less than significant and mitigation is not required.

Cumulative Impacts The proposed Project would not result in direct or indirect permanent or temporary impacts related to mineral resources. Implementation of the proposed Project would not result in the loss of an area that is designated for mineral resource extraction and would not result in the inability to use any other areas for such purpose. Therefore, the proposed Project would not result in incremental effects to the loss of mineral resources that could be compounded or increased when considered together with similar effects from other past, present, and reasonably foreseeable future projects. Thus, no cumulative impacts related to mineral resources would occur.

Valley & Spruce Project | 51

12. Noise Less Than Significant Potentially with Less than Significant Mitigation Significant No Issues Impact Incorporated Impact Impact Would the project: a. Exposure of persons to or generation of noise levels in excess of standards established in the

local general plan or noise ordinance, or applicable standards of other agencies? b. Exposure of persons to or generation of excessive groundborne vibration or groundborne noise levels? c. A substantial permanent increase in ambient noise levels in the project vicinity above levels existing without the project? d. A substantial temporary or periodic increase in ambient noise levels in the project vicinity above levels existing without the project? e. For a project located within an airport land use plan or, where such a plan has not been adopted, within two miles of a public airport or public use

airport, would the project expose people residing or working in the project area to excessive noise levels? f. For a project within the vicinity of a private airstrip, would the project expose people residing

or working in the project area to excessive noise levels?

Discussion A Noise and Vibration Study was prepared for the proposed Project by Entech Consulting Group (December 2017). The Noise and Vibration Study is included as Appendix H and the results are summarized herein. Noise is generally defined as loud, unpleasant, unexpected, or undesired sound that is typically associated with human activity and that interferes with or disrupts normal activities. The human environment is generally characterized by a certain consistent noise level that varies by area. This is called ambient, or background noise. Although exposure to high noise levels has been demonstrated to cause hearing loss, the principal human response to environmental noise is annoyance. The response of individuals to similar noise events is diverse and influenced by the type of noise, perceived importance of the noise and its appropriateness in the setting; time of day and type of activity during which the noise occurs, and sensitivity of the individual. Sound is a physical phenomenon consisting of minute vibrations that travel through a medium, such as air, and are sensed by the human ear. Sound is generally characterized by several variables, including frequency and intensity. Frequency describes the sound’s pitch and is measured in cycles per second, or hertz (Hz). Intensity describes the sound’s loudness and is measured in decibels (dB). A sound level of 0 dB is approximately the threshold of human hearing and is barely audible under extremely quiet listening conditions. Normal speech has a sound level of approximately 60 dB. Sound levels above about 120 dB begin to be felt inside the human ear

Valley & Spruce Project | 52

as discomfort and eventually as pain at still higher levels. The minimum change in the sound level of individual events that an average human ear can detect is about 3 dB. Decibels are measured using a logarithmic scale; thus, the average person perceives a change in sound level of about 10 dB as a doubling (or halving) of the sound’s loudness. This relation holds true for sounds of any loudness. Because community noise fluctuates over time, a single measure called the Equivalent Sound Level (Leq) is often used to describe the time-varying character of community noise. The Leq is the energy-averaged A-weighted sound level during a measured time interval, and is equal to the level of a continuous steady sound containing the same total acoustical energy over the averaging time period as the actual time-varying sound. Another sound measure known as the Community Noise Equivalent Level (CNEL) is an adjusted average A-weighted sound level for a 24-hour day. It is calculated by adding a 5 dB adjustment to sound levels during evening hours (7:00 p.m. to 10:00 p.m.) and a 10 dB adjustment to sound levels during nighttime hours (10:00 p.m. to 7:00 a.m.). These adjustments compensate for the increased sensitivity to noise during the typically quieter evening and nighttime hours. The CNEL is used by the State of California and the City to evaluate land use compatibility with respect to transportation noise. The noise standards identified in the City of Rialto General Plan Noise Element (2010) serve as guidelines to evaluate the acceptability of the transportation noise level impacts. These standards are used to assess the long-term traffic noise impacts on land uses. According to the City’s Land Use Compatibility for Community Noise Exposure, noise-sensitive land uses such as residences and schools are normally acceptable with exterior noise levels below 60 dBA CNEL and conditionally acceptable with noise levels below 70 dBA CNEL. Industrial, Manufacturing, Utilities, and Agriculture land uses are normally acceptable with exterior noise levels below 75 dBA CNEL and conditionally acceptable with exterior noise levels below 80 dBA CNEL. These guidelines also include a maximum exterior noise level of 65 dBA CNEL for noise-sensitive receptors. In addition, the City’s Code of Ordinances include requirements that pertain to noise during construction and operation. 9.50.060 Exemptions The following activities and noise sources shall be exempt from the provisions of this chapter (9.50): (O) Sounds generated in commercial and industrial zones that are necessary and incidental to the uses permitted therein. 9.50.070 Disturbances from Construction Activity The City of Rialto has set exterior noise limits to control noise impacts associates with the construction of the proposed Project. According to Section 9.50.070 of the City’s Municipal Code, Disturbances from Construction Activity, the appropriate construction hours are as follows: October 1st through April 30th: ▪ Monday through Friday: 7:00 a.m. to 5:30 p.m. ▪ Saturday: 8:00 a.m. to 5:00 p.m. ▪ Sundays and State Holidays: No permissible hours May 1st through September 30th: ▪ Monday through Friday: 6:00 a.m. to 7:00 p.m. ▪ Saturday: 8:00 a.m. to 5:00 p.m. ▪ Sundays and State Holidays: No permissible hours

Valley & Spruce Project | 53

The hours above shall apply to all persons that are engaged in any work of construction, erection, alternation, repair, addition, movement, demolition, or improvement to any building or structure. In community noise assessment, changes in noise levels greater than 3 dBA are often identified as “barely perceptible” while changes of 5 dBA are “ready perceptible”. In the range of 1 dBA to 3 dBA, people who are very sensitive to noise may perceive a slight change in noise level. In laboratory testing situations, humans are able to detect noise level changes of slightly less than 1 dBA. However, in a community situation the noise exposure is extended over a long time period, and changes in noise levels occur over years rather than the immediate comparison made in a laboratory situation. Therefore, the level at which changes in community noise levels become discernible is likely to be some value greater than 1 dBA, and 3 dBA appears to be appropriate for most people. For purposes of this Initial Study, noise impacts are considered significant if the project increases noise levels by 3 dBA, or if the predicted exterior noise levels exceed the City of Rialto Noise Element criteria. In addition, noise level increases and impacts attributable to development of the proposed Project are estimated by comparing the “with Project” traffic volume to the “without Project” traffic volume. For purposes of this Initial Study, roadway noise impacts would be considered significant if the proposed Project increases noise levels for a noise sensitive land use by 3 dBA and if: (1) the existing noise levels already exceeds the 65 dBA CNEL residential standard, or (2) the Project increase noise levels from below the 65 dBA CNEL standard to above 65 dBA CNEL.

Existing Noise Environment The City is impacted by various noise sources. Mobile sources of noise, especially cars and trucks, are the most common and significant sources of noise in most communities. Other sources of noise are the various land uses throughout the City that generate stationary-source noise. The Project site is a largely disturbed area comprised of disked non-native grassland vegetation with small developed patches comprised of sidewalks and cement pads. A former storage yard occupied the site until it was demolished/removed in September 2017. No structures are currently located on the site. The Project site is located in a predominately industrial and commercial area. Immediately south of the proposed Project site is the Interstate 10 (I-10) and the Union Pacific Rail Yard, to the east and west are commercial, warehousing, and industrial uses, to the northwest are residential uses and a school, and to the north and northeast are an auto sales yard, vacant property, and a school. In order to quantify existing ambient noise levels in the Project area, Entech conducted one long- term 24-hour measurement and three short-term measurements on September 19 and 20, 2017. Noise monitoring locations were selected based on residential and school properties in close proximity to the proposed Project site. Noise measurement locations 1 through 3 were monitored for a period of 20 minutes. Site 1 is located near 1609 S Spruce Avenue, north of the proposed Project site. Site 2 is located at 10057 Claremont Avenue, northwest of the proposed Project site. Site 3 is located across the street from the Joe Baca Middle School east of the proposed Project site.

Valley & Spruce Project | 54

Table 8: Existing (Ambient) Short-Term Noise Level Measurements1,3

Noise Monitoring Time of Primary Noise Noise Levels Noise Levels Description 3 Location Measurement Source (Leq dBA) (Leq CNEL) ID2,3 1 1609 S Spruce Avenue 10:46 Traffic 54.2 63.3 2 10057 Claremont Avenue 11:10 Traffic 57.3 60.3 3 Across from Joe Baca Middle School 11:42 Traffic 67.7 60.3 1) Noise measurement taken on September 19th, 2017. 2) See Figure 4 of Appendix H for the location of the monitoring sites, and Appendix A (of Appendix H) for Field Monitoring Forms. 3) Taken with LxT Type 1 noise meter.

Table 9: Existing (Ambient) Long-Term (24-hour) Noise Level Measurements1

Noise Hourly Noise Levels (1hr-Leq) 24-hour Monitoring Noise Description Location Daytime Daytime Nighttime Nighttime Levels ID2,3 Minimum Maximum Minimum Maximum (CNEL) A Vacant lot North of Project Site on Cactus Avenue 58.9 66.2 50.6 63.8 64 1) Noise measurement taken on September 19th and 20th, 2017 2) See Figure 4 of Appendix H for the location of the monitoring sites, and Appendix A (of Appendix H) for Field Monitoring Forms. 3) Taken with LxT Type 1 noise meter.

a) Exposure of persons to or generation of noise levels in excess of standards established in the local general plan or noise ordinance, or applicable standards of other agencies? Less Than Significant with Mitigation Incorporated.

Construction The assessment of the construction noise impacts must be relatively general at this phase because many of the decisions affecting noise will be at the discretion of the contractor. However, an assessment based on the type of equipment expected to be used by the contractor can provide a reasonable estimate of potential noise impacts and the need for noise mitigation. A worst-case construction noise scenario was developed to estimate the loudest activities that would be occurring at the Project site. Pile driving and blasting activities are not anticipated, therefore, the loudest construction activities are centered around movement of heavy construction equipment during excavation, grading operations and the erection of buildings. Noise levels were estimated based on a worst-case scenario which assumed all pieces of equipment would be operating simultaneously during each construction phase. The calculated noise level was then compared to the respective local noise regulation to determine if construction would cause a short-term noise impact at nearby residential land uses and schools. Construction of the proposed Project is expected to occur over a nine (9) month period. Receiver distance to the construction activity along with the construction equipment operating at maximum load will have the greatest influence on construction noise levels experienced at residential land uses and schools.

Valley & Spruce Project | 55

Construction of the proposed Project would include site preparation, building construction, and paving. Construction activities, such as movement of equipment and workers, would also cause increased noise along access routes to and from the site. Construction noise would be acoustically dispersed throughout the Project site and would not be concentrated in one area near adjacent sensitive uses. The U.S Environmental Protection Agency (U.S. EPA) has compiled data regarding the noise generating characteristics of specific types of construction equipment. As shown in Table 10: Construction Equipment Noise Levels, noise levels generated by heavy construction for various construction phases can range from 81-88 dBA, when measured at 50 feet. However, these noise levels would diminish rapidly with distance from the construction site at a rate approximately 6 dBA per doubling of distance. For example, a noise level of 68 dBA at 50 feet from the noise source to the receptor would be reduced to 62 dBA at 100 feet from the source to the receptor, and would be further reduced by another 6 dBA to 56 dBA at 200 feet from the source to the receptor.

Table 10: Construction Equipment Noise Levels

1 Construction Activity Noise Level at 50 Feet (dBA, Leq) Demolition 88 Ground Clearing 84 Grading/Excavation 88 Foundations 81 Erection 82 Finishing 88 1 Average noise levels correspond to a distance of 50 feet from the noisiest piece of equipment Associated with a given phase of construction and 200 feet from the rest of the equipment associated with that phase. Source: USEPA, Noise from Construction Equipment and Operations, Building Equipment, and Home Appliances, Table 1-b Domestic Housing, 1971, An overall demolition/grading noise level of 88 dBA at 50 feet was used as the worst-case maximum exterior noise level. The nearest sensitive land use is the Joe Baca Middle School, which is 150 feet from the eastern property boundary of the Project site. Using a drop-off rate of 6 dBA per doubling of distance, the noise level at 150 feet is estimated to be 76 dBA Leq, at 200 feet 70 dBA Leq and at 400 feet 64 dBA Leq. This noise level impact is a worst-case scenario. Construction noise is of short-term duration and will not present any long-term impacts on the Project site or the surrounding area. The mitigation measures below will be employed as applicable and will serve to reduce the construction noise impacts to the nearby sensitive receptors. Mitigation Measures NOI-1a During all Project site excavation and grading on-site, the construction contractors shall equip all construction equipment, fixed or mobile, with properly operating and maintained mufflers, consistent with the manufacturers’ standards. The construction contractors shall place all stationary construction equipment so that emitted noise is directed away from the noise sensitive receptors (residences) nearest the Project site. This measure shall be implemented to the satisfaction of the City Public Works Director or his designee. NOI-1b The construction contractor shall locate equipment staging in areas that will create the greatest distance between construction-related noise sources and noise sensitive receptors nearest the Project site during all project construction.

Valley & Spruce Project | 56

This measure shall be implemented to the satisfaction of the City Public Works Director or his designee. NOI-1c The construction contractor shall limit all construction activities to be performed within the permitted hours for construction work pursuant to Section 9.50.070 of the City Municipal Code unless otherwise permitted by the City of Rialto. This measure shall be implemented to the satisfaction of the City Public Works Director or his designee. NOI-1d To the extent feasible, the construction contractor shall restrict all haul routes during construction to avoid passing sensitive land uses or residential dwellings. The haul route(s) shall be submitted to and approved by the City Public Works Director or his designee prior to the start of grading. On-Site Operations Stationary noise sources associated with operation of the Project would include, but not be limited to, idling trucks, delivery truck activities, parking, forklifts with backup alarms, as well as loading and unloading of dry goods. The greatest loading dock-related noise levels would be related to truck access and back-up alarms. Trucks accessing the Project Site would be a combination of heavy- and medium-duty trucks with noise levels ranging from 71 to 79 dBA Leq at 50 feet (Caltrans Technical Noise Supplement, October 1998). Back-up safety alarms would generate a single event noise level of approximately 79 dBA Leq at 50 feet (per regulations set by OSHA). This reference noise level and the ambient noise levels will be used to predict the project noise levels from the proposed Project utilizing noise propagation formulas. Parking Areas Typical parking lot activities such as people conversing, doors slamming or vehicles idling generate noise levels of approximately 60 dBA to 70 dBA Lmax at 50 feet. The closest noise- sensitive land use to the proposed parking areas would be the Joe Baca Middle School, which is 150 feet from the eastern property boundary of the Project site. At this distance, maximum noise levels from parking lot activities could range up to approximately 52 dBA Lmax at the school property boundary. The Ruth Grimes Elementary School is located 350 feet from the northern property boundary of the project site. At this distance, maximum noise levels from parking lot activities could range up to approximately 44 dBA Lmax at the school property boundaries respectively. These activities would be expected to occur sporadically throughout the day, as visitors and staff arrive and leave the parking lot areas. Such activities spread out over the Project site parking areas would not result in an increase above existing ambient noise levels as measured at any off-site sensitive land use. Therefore, project-related parking lot activities would not result in exposure of persons to noise levels in excess of existing noise levels. HVAC & Ventilation Systems Details pertaining to mechanical ventilation systems were not available; therefore, a reference noise level for typical rooftop mechanical ventilation systems was used. Noise levels from typical rooftop mechanical ventilation equipment are anticipated to range up to approximately 60 dBA Leq at a distance of 25 feet. The closest sensitive receptor is the Joe Baca Middle School located to the northeast of the project site, approximately 150 feet from the nearest location where rooftop ventilation equipment would be placed. At this distance, noise generated by the rooftop mechanical ventilation equipment would attenuate to 44 dBA Leq. The distance from the Ruth Grimes Elementary School to the rooftop ventilation equipment is 350 feet. At this distance, the noise generated by the rooftop mechanical ventilation equipment would attenuate to 37 dBA Leq. Thus, noise levels from rooftop mechanical

Valley & Spruce Project | 57

equipment operation would be well below the City’s noise performance standard of 65 dBA Leq for any receiving noise sensitive residential land uses..

Loading Dock & Delivery Operations As stated previously, stationary noise sources associated with operation of the Project would include, but not be limited to, idling trucks, delivery truck activities, parking, forklifts with backup alarms, as well as loading and unloading of dry goods. The greatest loading dock- related noise levels would be related to truck access and back-up alarms. The associated reference noise level that would represent loading dock and delivery operations is 79 dBA Leq at 50 feet. The loading docks are located closest to the I-10 freeway and are shielded by the warehouse building. The distance to the loading docks from the Joe Baca Middle School property boundary is 700 feet and from the Ruth Grimes elementary school property boundary is 850 feet. At these distances, the maximum noise levels from loading/unloading activities could range up to approximately 56 and 54 dBA Leq respectively. Therefore, when averaged over an hour or a 24-hour period, these operational noise levels would not exceed the City’s noise performance standard of 65 dBA Leq as measured at the nearby receiving noise sensitive land uses in the project vicinity. Therefore, the proposed Project would result in a less than significant impact. For additional detail, please see below Table 11: Summary of Project Onsite Operations Maximum Noise Levels for a summary of the maximum noise levels for the project’s onsite operations.

Table 11: Summary of Project Onsite Operations Maximum Noise Levels

Ruth Grimes Elementary Joe Baca Middle School School Maximum dBA Noise Source from Operation Significant? Distance from Noise at Distance from Noise at Permitted Sensitive Sensitive Sensitive Sensitive Receptor Receptor Receptor Receptor Parking Areas +/-150' 52 dBA Leq +/-350' 44 dBA Leq 65 dBA Leq No HVAC & Ventilation Systems +/-150' 44 dBA Leq +/-350' 37 dBA Leq 65 dBA Leq No Loading Dock & Delivery Options +/-700' 56 dBA Leq +/-850' 54 dBA Leq 65 dBA Leq No Source: Entech, 2017.

Operations – Off-site Traffic Noise Noise level increases and impacts attributable to development of the proposed Project are estimated by comparing the “with Project” traffic volume to the “without Project” traffic volume. Roadway noise impacts would be considered significant if the proposed Project increases noise levels for a noise sensitive land use by 3 dBA CNEL and if: (1) the existing noise levels already exceed the 65 dBA CNEL residential standard, or (2) the proposed Project increases noise levels from below the 65 dBA CNEL standard to above 65 dBA CNEL. To assess the off-site noise level impacts associated with the development of the proposed Project, noise levels were developed for the following traffic scenarios:

Valley & Spruce Project | 58

▪ Existing: This scenario refers to the current noise conditions, without construction of the proposed Project ▪ Year (2019 With/Without Project): This scenario refers to the background noise conditions at future year 2019 with and without the proposed Project. This corresponds to the completion of the Project’s buildout. The nearest sensitive land uses that can potentially be affected by project-related traffic are the residential areas and the Ruth Grimes Elementary School located north of the Project site near W. Pomona and S. Cactus Avenue, the residential areas near Claremont and Portola Avenue and the Joe Baca Middle School. As shown in Table 12: Traffic Noise Levels – 2019 Project Contributions, the development of proposed Project will increase off-site noise levels by less than 3.0 dBA, which is considered “barely perceptible and is therefore, “insignificant” in terms of community noise impacts. The proposed Project’s contributions to off-site roadway noise increases will not cause any significant impacts to any existing or future sensitive noise receptors.

Table 12: Traffic Noise Levels – 2019 Project Contributions

2019 With Change in Noise Receiver Location Existing 2019 No Project Impact Project Levels 1 61.5 61.6 62.1 0.5 No 2 59.5 59.6 60.2 0.6 No 3 59.9 60.1 60.6 0.5 No 4 61.8 62 62.5 0.5 No 5 58 58.1 58.5 0.4 No 6 50.9 51 51.4 0.4 No 7 52.1 52.2 52.6 0.4 No 8 56.9 57.1 57.2 0.1 No 9 57.3 57.5 57.6 0.1 No 10 61.3 61.5 61.6 0.1 No 11 58.3 58.5 58.6 0.1 No I-1 (Elementary School) 57 57.2 57.6 0.4 No I-2 (Middle School) 57.5 57.7 58 0.3 No 1According to the City of Rialto Valley and Cactus Avenue Traffic Impact Analysis by Kimley Horn 2017.

b) Exposure of persons to or generation of excessive groundborne vibration or groundborne noise levels? Determination: Less Than Significant. There are no state vibration standards applicable to the proposed Project. In addition, the California Department of Transportation’s (Caltrans) Transportation and Construction Vibration Guidance Manual (2013), does not provide official Caltrans standards for vibration. However, this manual provides guidelines that can be used as screening tools for assessing the potential for adverse vibration effects related to structural damage and human perception. The manual is meant to provide guidance related to vibration issues associated with the construction, operation, and maintenance of Caltrans projects. The vibration criteria established by Caltrans for assessing structural damage and human perception are shown in Table 13: Caltrans Vibration Damage Potential Threshold Criteria and Table 14: Caltrans Vibration Annoyance Potential Criteria.

Valley & Spruce Project | 59

Table 13: Caltrans Vibration Damage Potential Threshold Criteria

Maximum PPV (in/sec) Structure and Condition Infrequent Sources Infrequent Sources Extremely fragile historic buildings, ruins, ancient 0.12 0.08 monuments Fragile buildings 0.2 0.1 Historic and some old buildings 0.5 0.25 Older residential structures 0.5 0.3 New residential structures 1.0 0.5 Modern industrial/commercial buildings 2.0 0.5 Source: Caltrans, 2006. Table 14: Caltrans Vibration Annoyance Potential Criteria

Maximum PPV (in/sec) Structure and Condition Continuous / Frequent Infrequent Sources Intermittent Sources Barely perceptible 0.035 0.019 Distinctly perceptible 0.24 0.08 Strongly perceptible 0.9 0.10 Severe 2.0 0.4-0.6 Source: Caltrans, 2006. Table 15: FTA Vibration Annoyance Potential Criteria

Maximum PPV (in/sec) Structure and Condition Infrequent Sources Continuous / Frequent Intermittent Sources Barely perceptible 0.035 0.019 Distinctly perceptible 0.24 0.08 Strongly perceptible 0.9 0.10 Severe 2.0 0.4-0.6 Source: Caltrans, 2006. The County of San Bernardino’s General Plan (Section 83.01.090) includes vibration standards and requirements that are applicable to the proposed Project. (a) Vibration standard. No ground vibration shall be allowed that can be felt without the aid of instruments at or beyond the lot line, nor shall any vibration be allowed which produces a particle velocity greater than or equal to two-tenths (0.2) inches per second measured at or beyond the lot line. (b) Vibration measurement. Vibration velocity shall be measured with a seismograph or other instrument capable of measuring and recording displacement and frequency, particle velocity, or acceleration. Readings shall be made at points of maximum vibration along any lot line next to a parcel within a residential, commercial and industrial land use-zoning district. (c) Exempt vibrations. The following sources of vibration shall be exempt from the regulations of this Section.

Valley & Spruce Project | 60

(1) Motor vehicles not under the control of the subject use. (2) Temporary construction, maintenance, repair, or demolition activities between 7:00 AM and 7:00 PM, except Sundays and Federal holidays. Groundborne vibration levels resulting from construction activities within the Project area were estimated using the data published by the FTA in its Transit Noise and Vibration Impact Assessment Manual (FTA, 2006). Potential vibration levels resulting from construction activities of the proposed Project are identified at the nearest off-site sensitive receptor location and compared to the FTA damage criteria as shown previously in Table 13. As a conservative measure, vibration vs. distance curve obtained from the Caltrans Transportation and Construction Vibration Guidance Manual will be used to represent worst- case vibration levels from truck traffic at the nearest receiver locations along Cactus Avenue. These vibration levels will be compared to the Caltrans and FTA vibration annoyance criteria as shown previously in Table 14 and Table 15 for Continuous Sources. These criteria will be utilized to evaluate the level of significance associated with vibration effects from continuous truck traffic.

Operational Vibration The proposed Project will increase truck traffic within the Project area. Per the Caltrans Transportation Noise and Vibration Manual traffic, including heavy trucks, traveling on roadways rarely generates vibration amplitudes high enough to cause structural or cosmetic damage. However, a qualitative analysis was provided in this study to evaluate the likelihood of vibration impacts from the proposed Project. The Caltrans Noise and Vibration Manual provides a collection of measure vibration data for truck passbys. This data demonstrates that truck passbys can be characterized by a peak in vibration that are considerably higher than those generated by automobiles for a few seconds. Vibration from these trucks drop off dramatically with distance. As truck volumes increase, more peaks will occur but not necessarily higher peaks. Vibration wavefronts emanating from several trucks closely together may either cancel or partially cancel (destructive interference), or reinforce or partially reinforce (constructive interference) each other, depending on their phases and frequencies. Since traffic vibrations can be considered random, the probabilities of total destructive or constructive interference are extremely small. Coupled with the fact that two trucks cannot occupy the same space, and the rapid drop-off rates, it is understandable that two or more trucks normally do not contribute significantly to each other's peaks. In order to predict the maximum highway truck traffic vibrations from the proposed Project, the curve in Figure 5: Maximum Truck Traffic Vibration Levels vs. Distance was used which compiles the highest measured vibrations available from previous studies to demonstrate possible vibration levels from truck traffic. Figure 5 provides the maximum highway truck traffic vibrations vs. distance from the centerline of the nearest freeway lane. The graph indicates that the highest traffic generated vibrations measured on freeway shoulders (5 m from center line of nearest lane) have never exceeded 2.0 mm/s or (0.08 in/sec) with the worst combinations of heavy trucks. This amplitude coincides with the maximum recommended “safe amplitude” for historical buildings. The graph illustrates the rapid attenuation of vibration amplitudes, which dip below the threshold of perception for most people at about 45 m (150 ft). Based on Figure 5, the maximum worse-case vibration that would be experience at the homes along Cactus Avenue within 15m (50 feet) of the centerline of the nearest travel lane would be 0.08 mm/s or (0.0032 in/sec).

Valley & Spruce Project | 61

Figure 5: Maximum Truck Traffic Vibration Levels vs. Distance Caltrans and FTA provide a range of perceptible annoyance levels and the predicted vibration level falls well below the distinctly perceptible level of 0.08 PPV (in/sec). Further, this worse- case vibration noise level is below the FTA damage criteria of 0.3 PPV (in/sec). It is expected that actual vibration levels within the Project area from truck traffic will be lower than this worst-case level when soil type and pavement conditions are considered. On this basis, the potential for the proposed Project to result in exposure of persons to, or generation of, excessive ground-borne vibration is determined to be less than significant. Construction Vibrational Impacts Construction activity can result in varying degrees of ground vibration, depending on the equipment and methods used, distance to the affected structures and soil type. It is expected that ground-borne vibration from Project construction activities would cause only intermittent, localized intrusion. The proposed Project’s construction activities most likely to cause vibration impacts are: ▪ Heavy Construction Equipment: Although all heavy mobile construction equipment has the potential of causing at least some perceptible vibration while operating close to building, the vibration is usually short-term and is not of sufficient magnitude to cause building damage. It is not expected that heavy equipment such as large bulldozers would operate close enough to any residences to cause a vibration impact. ▪ Trucks: Trucks hauling building materials to construction sites can be sources of vibration intrusion if the haul routes pass through residential neighborhoods on streets with bumps or potholes. Repairing the bumps and potholes generally eliminates the problem. Ground-borne vibration levels resulting from construction activities occurring within the Project site was estimated by data published by the FTA. Construction activities that would occur within the Project site are expected to include grading and excavation, which would have the potential to generate low levels of ground-borne vibration. Using the vibration source level of construction equipment provided on Table 16: Construction Equipment Vibration

Valley & Spruce Project | 62

Levels, and the construction vibration assessment methodology published by the FTA, it is possible to estimate the Project vibration impacts. Table 16 presents the expected Project related vibration levels at 150 feet at the Joe Baca Middle School property boundary.

Table 16: Construction Equipment Vibration Levels

Large Bulldozer Reference Distance to Property Peak Vibration Noise Receiver Vibration Level Significant Impact Line PPV (in/sec) at 50ft PPV (in/sec) at 25ft Joe Baca Middle 150 feet 0.089 0.015 No School along W. Valley Blvd Avenue

Based on the reference vibration levels provided by the FTA, a large bulldozer represents the peak source of vibration with a reference level of 0.089 (in/sec) at a distance of 25 feet. At 150 feet, construction vibration levels are expected to approach 0.015 (in/sec). Using the construction vibration assessment annoyance criteria provided by the FTA for infrequent events, as shown in Table 15, the proposed Project site will not include nor require equipment, facilities, or activities that would result in a perceptible human response (annoyance). Further, impacts at the Project site of the closest sensitive receptor are unlikely to be sustained during the entire construction period, but will occur rather only during the times that heavy construction equipment is operating proximate to the Project site perimeter. Moreover, construction at the Project site will be restricted to daytime hours consistent with City of Rialto Municipal Code (Ord. 1417 § 1 (part), 2008), thereby eliminating potential vibration impact during the sensitive nighttime hours, unless otherwise permitted by the City of Rialto. On this basis, the potential for the proposed Project to result in exposure of persons to, or generation of, excessive ground-borne vibration is determined to be less than significant. c) A substantial permanent increase in ambient noise levels in the project vicinity above levels existing without the project? Less Than Significant. Future development generated by the proposed Project would result in additional traffic on adjacent roadways, thereby increasing vehicular noise in the vicinity of existing land uses. As shown in Table 12, noise levels range from 51 dBA to 61.6 dBA for 2019 No Project. These levels do not exceed the City’s residential noise standards of 65 dBA CNEL. To determine significance, a 3 dBA increase was used as a threshold. This level of noise is considered a just-perceivable difference. As shown in Table 12, the noise levels range from 51.4 dBA to 62.5 dBA for 2019 With Project. The maximum increase in noise would be 0.6 dBA, which would occur among the residences approximately 65 feet north of Valley Boulevard between Portola Avenue and Claremont Avenue. Since the proposed Project would not increase noise levels above 3 dBA along the roadway segments analyzed, a less than significant impact would occur. d) Substantial temporary or periodic increase in ambient noise levels in the project vicinity above levels existing without the project? Less Than Significant with Mitigation Incorporated. Existing ambient traffic noise levels are documented in Table 12. As shown in the table, existing traffic-generated noise levels on Project-vicinity roadways currently ranges from 50.9

Valley & Spruce Project | 63

to 61.8 dBA CNEL. As discussed above in threshold 12 (a), noise levels generated by heavy construction for various construction phases can range from 81-88 dBA, when measured at 50 feet from the source. An overall demolition/grading noise level of 88 dBA at 50 feet was used as the worst-case maximum exterior noise level. The nearest sensitive land use is the Joe Baca Middle School, which is 150 feet from the eastern property boundary of the Project site. Using a drop-off rate of 6 dBA per doubling of distance, the noise level at 150 feet is estimated to be 76 dBA Leq, at 200 feet 70 dBA Leq and at 400 feet 64 dBA Leq. This noise level impact is a worst-case scenario. Construction noise is of short-term duration and will not present any long-term impacts on the Project site or the surrounding area. As previously discussed, Mitigation Measures NOI-1a through 1d would be implemented as applicable to reduce the construction noise impacts to the nearby sensitive receptor. Based on this, the impact would be less than significant. e) For a project located within an airport land use plan or, where such a plan has not been adopted, within two miles of a public airport or public use airport, would the project expose people residing or working in the project area to excessive noise levels? No Impact. The proposed Project is not located within the vicinity of a public airport and, therefore, there is no impact surrounding the proposed Project concerning airport noise. f) For a project within the vicinity of a private airstrip, would the project expose people residing or working in the project area to excessive noise levels? No Impact. The proposed Project is not located within the vicinity of a private airstrip and, therefore, there is no impact surrounding the proposed Project concerning airport noise.

Cumulative Impacts As discussed above, all noise impacts can be mitigated to a less than significant level. Construction noise impacts are by nature localized. The distance of separation among the proposed Project and other cumulative projects would be such that the temporary noise and vibration effects of the proposed Project would not be compounded or increased by similar noise or vibration effects from other cumulative projects. Therefore, cumulative impacts relative to temporary and permanent noise generation associated with the proposed Project would not be cumulatively considerable, and thus, less than significant.

Valley & Spruce Project | 64

13. Population and Housing Less Than Significant Potentially with Less than Significant Mitigation Significant No Issues Impact Incorporated Impact Impact Would the project: a. Induce substantial population growth in an area, either directly (for example, by proposing new homes and businesses) or indirectly (for example, through extension of roads or other infrastructure)? b. Displace substantial numbers of existing housing, necessitating the construction of replacement housing elsewhere? c. Displace substantial numbers of people, necessitating the construction of replacement housing elsewhere?

Discussion a) Induce substantial population growth in an area, either directly (for example, by proposing new homes and businesses) or indirectly (for example, through extension of roads or other infrastructure)? Less than Significant. The proposed Project would result in the construction of a single industrial warehouse building with associated parking and approximately 5,000 sf of office space. The proposed Project does not involve any residential development. Roadways adjacent to the proposed Project include Cactus Avenue to the east, I-10 to the south, Spruce Avenue to the west, and Valley Boulevard to the north. The proposed Project would result in the construction of an approximate 404,837 sf structure that would require onsite infrastructure improvements. The proposed Project would result in the construction of four driveways to access the site, two via Cactus Avenue and two via Spruce Avenue, but there is no proposal to widen or extend these or any other roadway to any other areas. In addition, infrastructure (water, sewer, electrical) is located in the immediate vicinity of the proposed Project and these services would be extended to the site to serve the proposed Project. The proposed Project would not result in the extension of infrastructure beyond areas currently served. Unemployment in San Bernardino County is currently 5.9 percent, within the Riverside-San Bernardino-Ontario Municipal Service Area (MSA) it is 6.1 percent,13 and within the City of Rialto unemployment is 5.6 percent.14 The proposed Project would create new jobs and increase demand for new employees. By providing jobs, the proposed Project is expected to benefit the local community while having little effect on population growth. The growth that

13 California Employment Development Department, Riverside-San Bernardino-Ontario Metropolitan Statistical Area (MSA), July 2017 – Preliminary. Available at: http://www.labormarketinfo.edd.ca.gov/file/lfmonth/rive$pds.pdf Accessed September 6, 2017 14 California Employment Development Department, Labor Force and Unemployment Rate for Cities and Census Designated Places, http://www.labormarketinfo.edd.ca.gov/data/labor-force-and-unemployment-for-cities-and-census- areas.html, accessed September 6, 2017.

Valley & Spruce Project | 65

would occur as a result of the proposed Project is accounted for in the City General Plan, as envisioned in the Gateway Specific Plan, which designated the largely undeveloped site for use as an Industrial Park. Given the need for jobs to meet existing population, and the relatively small number of jobs created by the proposed Project compared to those on a regional basis, the proposed Project would not induce substantial population growth. Accordingly, although the proposed Project would create job opportunities, an industrial project such as this is not considered inherently growth inducing. Therefore, the proposed Project would not result in any adverse change in the population, housing, or employment projections developed by or for the City of Rialto. Impacts in this regard would be less than significant and no mitigation is required. b) Displace substantial numbers of existing housing, necessitating the construction of replacement housing elsewhere? No Impact. The Project site is currently a largely disturbed area comprised of disked non-native grassland vegetation with small developed patches comprised of sidewalks and cement pads. A former storage yard occupied the site until it was demolished/removed in September 2017. No structures are currently located on the site. The Project site does not contain any housing and as such, the construction of substantial replacement housing would not be required. Therefore, impacts would be less than significant and no mitigation is required. c) Displace substantial numbers of people, necessitating the construction of replacement housing elsewhere? No Impact. The proposed Project consists of the construction of one industrial warehouse building on a site that is vacant and largely disturbed. As the Project site does not include housing, the construction of replacement housing would not be required; therefore, no mitigation is required.

Cumulative Impacts The proposed Project would not result in direct or indirect permanent or temporary impacts related to population or housing. Therefore, the proposed Project would not result in incremental effects to population and housing that could be compounded or increased when considered together with similar effects from other past, present, and reasonably foreseeable probable future projects. As a result, no cumulative impacts related to population and housing would occur.

Valley & Spruce Project | 66

14. Public Services Less Than Significant Potentially with Less than Significant Mitigation Significant No Issues Impact Incorporated Impact Impact Would the project: a. Would the project result in substantial adverse physical impacts associated with the provision of new or physically altered governmental facilities, need for new or physically altered governmental facilities, the construction of which could cause significant environmental impacts, in order to maintain acceptable service ratios, response times or other performance objectives for any of the public services: i. Fire protection? ii. Police protection? iii. Schools? iv. Parks? v. Other public facilities?

Discussion d) Would the project adversely impact: i. Fire protection? Less Than Significant Impact. The City of Rialto Fire Department (RFD) provides fire protection services for the City. The RFD service area includes fire protection for over 100,000 residents in a 22-square mile area. The RFD is led by a Division Chief (although the position is currently vacant), three Battalion Chiefs, an EMS Coordinator, and Assistant Fire Marshall. The Rialto Fire Department deploys from four fire stations, Stations 201, 202, 203, and 204, staffed by 24 hours per day by career firefighters. The RFD staffs one battalion chief, three engine companies, one truck company and four paramedic ambulances each day. On- duty personnel also provide staffing for a Hazardous Materials unit and an Urban Search and Rescue unit. Station 201, which also houses the administrative office at 131 South Willow Avenue is the closest to the proposed Project site and is approximately 2.0 miles north of the Project site. 15 The Fire stations and their complement of personnel is as follows: Fire Station 201 - 131 South Willow Avenue: (1) Captain, (1) Engineer, (3) Firefighter/Paramedics, (2) Ambulance Operator/Paramedics, and (2) Ambulance Operator/Emergency Medical Technicians.

15 Rialto, City of, 2017 – City of Rialto Fire Department. Available at: http://yourrialto.com/residents/fire-department/. Accessed September 6, 2017.

Valley & Spruce Project | 67

Fire Station 202 - 1700 North Riverside Avenue: (1) Captain, (1) Engineer, (2) Firefighter/Paramedics, and (1) Firefighter. Fire Station 203 – 1550 North Ayala Drive: (1) Captain, (1) Engineer, (3) Firefighter/Paramedics. Fire Station 204 – 3288 N. Alder Avenue: (1) Captain, (1) Engineer, (1) Firefighter/Paramedic. Development of the proposed Project would incrementally increase the demand for fire protection services; however, the proposed Project is not expected to substantially increase service demand such that a new fire station would need to be constructed. However, according to the Rialto Fire Department Strategic Plan 2016-2020, which was written and published prior to the proposal to construct the proposed Project, the RFD had plans to construct Fire Station 205 at the approximate location of Valley Boulevard and Lilac Avenue. This station would be approximately 0.25 miles from the proposed Project. In order to address the potential increases in demand for fire service calls, the proposed Project would be required to pay fees based on the City of Rialto Development Fee Schedule. Fees are paid on a project-by-project basis to ensure a proportionate fair share is contributed toward facilities, equipment, and personnel that would be needed over time to accommodate the additional demand from the proposed Project. Therefore, upon payment of fee’s, impacts would be considered less than significant and no mitigation is required. ii. Police protection? Less Than Significant Impact. Police protection services would be provided by the City of Rialto Police Department. The proposed Project would be within the South Area Command in Area 3, which covers the City south of Foothill Boulevard and West of Lilac Avenue. The closest police station is located at 128 N. Willow Avenue in the City of Rialto, approximately 2.0 miles north of the Project site. Currently, the Rialto Police Department consists of a total of 106 Sworn staff and 39.5 non-sworn16, who would serve the needs of the proposed Project and future workers. Although a new industrial warehouse building would be constructed and operate on the Project site, the proposed Project is in a currently developed area and is currently served by the Police Department. Because of this, and because law enforcement personnel already patrol the Project vicinity and surrounding areas, the proposed Project is not anticipated to increase response times to the Project site or surrounding areas. As a means to provide adequate funding for police services, the City has established development impact fees that are charged to all new developments within the City of Rialto. The fees are designed to cover the added expense to police services resulting from new development. The development impact fees levied on the proposed Project, based on the City of Rialto Development Fee Schedule, would help the City provide for infrastructure, equipment, and staffing. The proposed Project does not propose or

16 City of Rialto, 2017 – City of Rialto Police Department. – Organizational Chart. Available at: http://www.rialtopd.com/index.php/divisions-1/department-organizational-chart Accessed October 6, 2017.

Valley & Spruce Project | 68

require new or physically altered police protection facilities. Therefore, impacts would be less than significant and no mitigation is required. iii. Schools? No Impact. The proposed Project is a non-residential land use. Implementation of the proposed Project would not directly result in an increased population in the City and would therefore not increase the need for the construction of additional school facilities. The Rialto Unified School District would require development fees be paid by the applicant. Upon payment of the required fees, no significant impact to school services or facilities would occur and no mitigation is required. iv. Parks? Less than Significant Impact. The City has established park development fees to offset the costs associated with increased maintenance and the addition of park facilities resulting from new development. The City’s park development fees are generated based on the type of land use. Residential uses are required to pay a park development fee; however, commercial and industrial uses are not obligated to contribute to park development fees. The proposed Project does not have a residential component. As such, the proposed Project would not create a significant increased demand or need for the construction of park facilities. Therefore, the impact would be less than significant and no mitigation is required. v. Other public facilities? No Impact. The City requires that certain types of development pay impact fees to compensate for additional services provided by public facilities as a result of implementation of their project. The City of Rialto requires development fees for libraries, open space, and general facilities. The proposed Project would be subject to open space and general facilities developer fees based on the square footage of the proposed Project; however, the Project would not be subject to library facility fees. The proposed Project does not include residential uses and would not result in a direct increase in population within the City or surrounding area. Therefore, based on the payment of required developer fees and the nominal impacts to the City’s population, impacts to other public facilities would be less than significant and no mitigation is required.

Cumulative Impacts The proposed Project would not result in a significant cumulative impact to public services or facilities. The proposed Project would not result in growth beyond what has been planned in the Gateway Specific Plan. Similar to the proposed Project, future projects would be required to compensate the City for potential increases in demand for public services. It is expected that impacts of future projects also would be reduced to less than significance by payment of fees and compensation for the provision of services. Therefore, the proposed Project would not result in substantial incremental effects to public services and facilities when taken in sum with other past, present, and reasonably foreseeable projects. Therefore, the proposed Project would not result in cumulatively considerable impacts to public services or facilities.

Valley & Spruce Project | 69

15. Recreation Less Than Significant Potentially with Less than Significant Mitigation Significant No Issues Impact Incorporated Impact Impact a. Would the project increase the use of existing neighborhood and regional parks or other recreational facilities such that substantial physical deterioration of the facility would occur or be accelerated? b. Does the project include recreational facilities or require the construction or expansion of

recreational facilities which might have an adverse physical effect on the environment?

Discussion a) Would the project increase the use of existing neighborhood and regional parks or other recreational facilities such that substantial physical deterioration of the facility would occur or be accelerated? No Impact. The proposed Project does not include development of any residences, which would directly increase population and result in increased demand for parks and recreational facilities. Accordingly, implementation of the proposed Project would not generate an increase in demand on existing public or private parks or other recreational facilities that could result in increased physical deterioration of the facility. Based on the City of Rialto Development Fee Schedule, and because the proposed Project consists of an industrial use, the proposed Project would not be subject to a park development fee. Therefore, no impact to existing recreational facilities would occur and no mitigation is required. b) Does the project include recreational facilities or require the construction or expansion of recreational facilities which might have an adverse physical effect on the environment? No Impact. As discussed above, the proposed Project consists of an industrial development and does not include any residential use that would increase the demand on and increase the deterioration of an existing park or recreational facility. In addition, the proposed Project site is not identified in the Rialto General Plan as a park or open space resource. The proposed Project does not include the construction of recreational facilities, nor would it require the construction or expansion of recreational facilities. Therefore, the proposed Project would not have an adverse physical effect on the environment from providing recreational resources and no impact would occur. No mitigation is required.

Cumulative Impacts The proposed Project would not result in an increased use of recreational facilities or require construction or expansion of existing recreational facilities. Therefore, take in sum with past, present, and reasonably foreseeable projects, no cumulative impacts on recreational facilities would result from implementation of the proposed Project.

Valley & Spruce Project | 70

16. Transportation/Traffic Less Than Significant Potentially with Less than Significant Mitigation Significant No Issues Impact Incorporated Impact Impact Would the project: a. Conflict with an applicable plan, ordinance or policy establishing measures of effectiveness for the performance of the circulation system, taking into account all modes of transportation including mass transit and non-motorized travel and relevant components of the circulation system, including but not limited to intersections, streets, highways and freeways, pedestrian and bicycle paths, and mass transit? b. Conflict with an applicable congestion management program, including, but not limited to level of service standards and travel demand measures, or other

standards established by the county congestion management agency for designated roads or highways? c. Result in a change in air traffic patterns, including either an increase in traffic levels or a change in location that results in substantial safety risks? d. Substantially increase hazards due to a design feature (e.g., sharp curves or dangerous intersections) or incompatible uses (e.g., farm equipment)? e. Result in inadequate emergency access? f. Conflict with adopted policies, plans, or programs regarding public transit, bicycle, or pedestrian facilities, or otherwise decrease the performance or safety of such facilities? A Traffic Impact Study (TIS) and Update was prepared by Kimley-Horn and Associates (October 2017) to assess the potential traffic impacts of the proposed Project. The findings of the TIS are summarized in this Initial Study; the traffic study is provided as Appendix I.

Discussion a) Conflict with an applicable plan, ordinance or policy establishing measures of effectiveness for the performance of the circulation system, taking into account all modes of transportation including mass transit and non-motorized travel and relevant components of the circulation system, including but not limited to intersections, streets, highways and freeways, pedestrian and bicycle paths, and mass transit? Less Than Significant Impact with Mitigation Incorporated. The traffic study was prepared in consultation with City of Rialto staff through the Scoping Letter Agreement process and included coordination with County of San Bernardino staff. Peak hour intersection operations at signalized and unsignalized intersections were evaluated using the methods prescribed in the Highway Capacity Manual (HCM) 2010, consistent with the requirements of the City of Rialto Traffic Study Guidelines. The traffic study area includes nine intersections as identified below.

Valley & Spruce Project | 71

▪ Cedar Avenue at Valley Boulevard ▪ Cedar Avenue at I-10 Westbound Ramps ▪ Cedar Avenue at I-10 Eastbound Ramps ▪ Spruce Avenue at Valley Boulevard ▪ Cactus Avenue at Valley Boulevard ▪ Lilac Avenue at Valley Boulevard ▪ Riverside Avenue at Valley Boulevard ▪ Riverside Avenue at I-10 Westbound Ramps ▪ Riverside Avenue at I-10 Eastbound Ramps Roadway segments were evaluated by comparing the traffic volume on a roadway segment to the daily capacity of that segment, to determine the volume-to-capacity (v/c) ratio. Daily capacity is based on the roadway classification, as shown in Table 17: City of Rialto Roadway Capacity, below.

Table 17: City of Rialto Roadway Capacity

(2) No. of Two-Way Traffic Volume (ADT) Roadway Classification Lanes Service Level C Service Level D Service Level E

Local 2 2,500-2,799 2,800-3,099 3,100 +

Collector (60' or 64') 2 9,900-11,199 11,200-12,499 12,500 +

Industrial (45') 2 9,900-11,199 11,200-12,499 12,500 +

Arterial(3) 2 14,400-16,199 16,200-17,999 18,000 +

Secondary Highway 4 16,900-19,399 19,400-21,999 22,000 +

Modified Arterial (100') 4 26,200-29,599 29,600-32,999 33,000 +

Arterial (120') 6 38,700-44,099 44,100-49,499 49,500 +

Notes: (1) All capacity figures are based on optimum conditions and are intended as guidelines for planning purposes only (2) Maximum two-way ADT values are based on the 1999 Modified Highway Capacity Manual Level of Service Tables. (3) Two-lane roads designated as future arterials that conform to arterial design standards for vertical and horizontal alignments are analyzed as arterials. Source: City of Rialto Traffic Impact Analysis Report Guidelines and Requirements (2013) The traffic study area includes six roadway segments as identified below. ▪ Cedar Avenue a. Valley Boulevard to I-10 Westbound Ramps ▪ Valley Boulevard a. Cedar Avenue to Spruce Avenue b. Spruce Avenue to Cactus Avenue

Valley & Spruce Project | 72

c. Cactus Avenue to Lilac Avenue d. Lilac Avenue to Riverside Avenue ▪ Riverside Avenue a. Valley Boulevard to I-10 Westbound Ramps Traffic conditions within the study area were analyzed for the following scenarios: ▪ Existing Conditions ▪ Project Opening Year (2019) – Existing Plus Growth ▪ Project Opening Year (2019) – Existing Plus Growth Plus Project ▪ Project Opening Year (2019) – Cumulative Without Project ▪ Project Opening Year (2019) – Cumulative Plus Project Significance Criteria The City of Rialto, per the City of Rialto 2010 General Plan Update, establishes minimum Level of Service standards. Per Policy 4-1.20 of the General Plan document, the City requires that signalized intersections operate at LOS D or better during the morning and evening peak hours. The one exception is Riverside Avenue from the Metrolink tracks to the City’s southern border, for which the Level of Service standard is LOS E. The City’s Traffic Study Guidelines require new development to mitigate impacts that cause the Level of Service to fall below an acceptable LOS, or that cause the peak hour delay to increase as follows: ▪ LOS A/B – by 10.0 seconds ▪ LOS C – by 8.0 seconds ▪ LOS D – by 5.0 seconds ▪ LOS E – by 2.0 seconds ▪ LOS F – by 1.0 second The City’s traffic study guidelines require unsignalized intersections to operate with no vehicular movement having an average delay exceeding 120 seconds during the morning and evening peak hours. The minimum acceptable LOS for roadway segments in the City of Rialto is LOS D, except for Riverside Avenue south of the Metrolink tracks all the way to the City’s southern border, which can operate at LOS E. The City’s traffic study guidelines require that a roadway segment must be mitigated if the segment exceeds 1,500 feet and the V/C ratio exceeds 1.0, even if improved intersection at the ends of the segment do not exceed LOS D. Existing Conditions Existing morning and evening peak hour turning movement volumes and daily roadway volumes were collected in May 2017. Vehicle classifications were included, and application of Passenger Car Equivalents (PCE) were used in the traffic analysis to address the impacts of truck traffic on intersection and roadway operation. The PCE volumes were developed by applying a PCE factor of 1.5 for 2-axle trucks, 2.0 for 3-axle trucks, and 3.0 for trucks with 4 or more axles. Peak Hour Operations As identified in Table 18: Summary of Intersection Operations, Existing Conditions all traffic study area intersections are currently operating at an acceptable LOS during both the morning

Valley & Spruce Project | 73

and evening peak hours except the intersection of Spruce Avenue at Valley Boulevard, which operates at LOS E during both peak hours. Daily Capacity As identified in Table 19: Summary of Roadway Analysis, Existing Conditions, all traffic study area roadway segments currently carry volumes within their capacity the segment of Cedar Avenue between Valley Boulevard and I-10 Westbound Ramps.

Table 18: Summary of Intersection Operations, Existing Conditions

Traffic Peak Existing Conditions # Intersection Control Hour Delay LOS AM 27.4 C 1 Cedar Avenue at Valley Boulevard S PM 31.0 C AM 38.7 D 2 Cedar Avenue at I-10 WB Ramps S PM 25.1 C AM 32.3 C 3 Cedar Avenue at I-10 EB Ramps S PM 28.7 C AM 46.1 E 4 Spruce Avenue at Valley Boulevard U PM 48.6 E AM 19.7 B 5 Cactus Avenue at Valley Boulevard S PM 14.0 B AM 20.1 C 6 Lilac Avenue at Valley Boulevard S PM 10.3 B AM 56.2 E 7 Riverside Avenue at Valley Boulevard S PM 38.5 D AM 22.7 C 8 Riverside Avenue at I-10 WB Ramps S PM 20.6 C AM 23.5 C 9 Riverside Avenue at I-10 EB Ramps S PM 26.3 C Notes: Bold and shaded values indicate intersections operating at unacceptable level of service. LOS E is acceptable for intersections along Riverside Avenue south of the Metrolink tracks to the City’s southern border. At a signalized intersection, delay refers to the average control delay for the entire intersection, measured in seconds per vehicle. At a two-way stop-controlled intersection, delay refers to the average vehicle delay on the worst movement. Delay values are based on the methodology outlined in the 2010 HCM. S = Signalized, U = Unsignalized Source: Kimley-Horn, 2017.

Valley & Spruce Project | 74

Table 19: Summary of Roadway Analysis, Existing Conditions

Existing Conditions Roadway Roadway Segment Daily Capacity ADT w/ Classification LOS PCE Cedar Valley Boulevard to I-10 WB Ramps Arterial (120’) 41,249 59,096 F Avenue Cedar Avenue to Spruce Avenue Modified Arterial 32,999 22,167 A Valley Spruce Avenue to Cactus Avenue Modified Arterial 32,999 16,166 A Boulevard Cactus Avenue to Lilac Avenue Modified Arterial 32,999 18,771 A Lilac Avenue to Riverside Avenue Modified Arterial 32,999 23,525 B Riverside Valley Boulevard to I-10 WB Ramps Arterial (120’) 55,439 53,916 E Avenue Notes: PCE = Passenger Car Equivalent, ADT = Average Daily Traffic, LOS = Level of Service Bold and shaded values indicate intersections operating at unacceptable level of service. LOS E is acceptable for intersections along Riverside Avenue south of the Metrolink tracks to the City’s southern border. Daily capacity for Riverside Avenue is based on LOS E. Source: Kimley-Horn, 2017.

Project Opening Year (2019) Conditions The proposed Project’s Opening Year (the year the Project would be constructed and occupied) is anticipated to be 2019. Based on consultation with City staff, an ambient growth rate of 2.0 percent per year was applied to existing peak hour traffic volumes to develop Existing Plus Growth forecasts. Peak Hour Operations Results of the intersection LOS analysis conducted for the morning and evening peak hours for the Project Opening Year (2019) Conditions are shown in Table 20: Summary of Intersection Operation, Opening Year (2019) Existing Plus Growth. Review of this table indicates that, with the addition of ambient growth traffic, the following intersection would operate at an unacceptable Level of Service: ▪ #4 – Spruce Avenue at Valley Boulevard: AM – LOS F, PM – LOS F Daily Capacity Results of the roadway segment LOS analysis conducted for the Project Opening Year (2019) Conditions are shown in Table 21: Summary of Roadway Analysis, Opening Year (2019) Existing Plus Growth. Review of this table indicates that the following roadway segments, with the addition of ambient growth traffic, would carry traffic volumes in excess of their daily capacity: ▪ Cedar Avenue: Valley Boulevard to I-10 WB Ramps ▪ Riverside Avenue: Valley Boulevard to I-10 WB Ramps

Valley & Spruce Project | 75

Table 20: Summary of Intersection Operation, Opening Year (2019) Existing Plus Growth

Opening Year (2019) Traffic Peak # Intersection Conditions Control Hour Delay LOS AM 28.0 C 1 Cedar Avenue at Valley Boulevard S PM 33.0 C AM 44.1 D 2 Cedar Avenue at I-10 WB Ramps S PM 27.3 C AM 35.9 D 3 Cedar Avenue at I-10 EB Ramps S PM 30.9 C AM 52.8 F 4 Spruce Avenue at Valley Boulevard U PM 56.2 F AM 20.0 C 5 Cactus Avenue at Valley Boulevard S PM 14.2 B AM 20.6 C 6 Lilac Avenue at Valley Boulevard S PM 10.5 B AM 64.3 E 7 Riverside Avenue at Valley Boulevard S PM 41.6 D AM 23.9 C 8 Riverside Avenue at I-10 WB Ramps S PM 21.7 C AM 24.2 C 9 Riverside Avenue at I-10 EB Ramps S PM 27.4 C Notes: Bold and shaded values indicate intersections operating at unacceptable level of service. LOS E is acceptable for intersections along Riverside Avenue south of the Metrolink tracks to the City’s southern border. At a signalized intersection, delay refers to the average control delay for the entire intersection, measured in seconds per vehicle. At a two-way stop-controlled intersection, delay refers to the average vehicle delay on the worst movement. Delay values are based on the methodology outlined in the 2010 HCM. S = Signalized, U = Unsignalized Source: Kimley-Horn, 2017.

Valley & Spruce Project | 76

Table 21: Summary of Roadway Analysis, Opening Year (2019) Existing Plus Growth

Opening Year (2019) Roadway Daily Conditions Roadway Segment Classification Capacity ADT w/ LOS PCE Cedar Valley Boulevard to I-10 WB Ramps Arterial (120’) 41,249 61,483 F Avenue Cedar Avenue to Spruce Avenue Modified Arterial 32,999 23,063 A Valley Spruce Avenue to Cactus Avenue Modified Arterial 32,999 16,819 A Boulevard Cactus Avenue to Lilac Avenue Modified Arterial 32,999 19,529 A Lilac Avenue to Riverside Avenue Modified Arterial 32,999 24,475 B Riverside Valley Boulevard to I-10 WB Ramps Arterial (120’) 55,439 56,094 F Avenue Notes: PCE = Passenger Car Equivalent, ADT = Average Daily Traffic, LOS = Level of Service Bold and shaded values indicate intersections operating at unacceptable level of service. LOS E is acceptable for intersections along Riverside Avenue south of the Metrolink tracks to the City’s southern border. Daily capacity for Riverside Avenue is based on LOS E. Source: Kimley-Horn, 2017.

Cumulative Conditions In addition to ambient growth to reach Project Opening Year (2019), traffic volumes from area cumulative projects were added to existing volumes. Cumulative Projects consist of any project that has been approved but is not yet constructed/ occupied, and projects that are in various stages of the application and approval process, but have not yet been approved. A total of 27 cumulative projects were identified and included in the analysis. Four of the cumulative projects are located in the City of Rialto; 7 are located in the City of Colton; 2 are located in the City of Riverside; 5 are located in the City of Jurupa Valley; 1 is located in the City of Fontana; 6 are located in the County of San Bernardino; and 2 are located in the County of Riverside. Trip Generation, Trip Distribution, and Assignment Trip generation and distribution assumptions for the cumulative projects were derived from approved traffic studies, where available; and were estimated when approved studies were not available. Peak Hour Operations Results of the intersection LOS analysis conducted for the morning and evening peak hours for the Project Opening Year (2019) Conditions are shown in Table 22: Summary of Intersection Operation, Opening Year (2019) - Cumulative Without Project. Review of this table indicates that, with the addition of Cumulative Projects traffic, the following intersections would operate at an unacceptable Level of Service: ▪ #2 – Cedar Avenue at I-10 WB Ramps: AM – LOS E ▪ #4 – Spruce Avenue at Valley Boulevard: AM – LOS F, PM – LOS F

Valley & Spruce Project | 77

Daily Capacity Results of the roadway segment LOS analysis conducted for the Project Opening Year (2019) Conditions are shown in Table 23: Summary of Roadway Analysis, Opening Year (2019) - Cumulative Without Project. Review of this table indicates that the following roadway segments would continue to carry traffic volumes in excess of their daily capacity: ▪ Cedar Avenue: Valley Boulevard to I-10 WB Ramps ▪ Riverside Avenue: Valley Boulevard to I-10 WB Ramps

Table 22: Summary of Intersection Operation, Opening Year (2019) - Cumulative Without Project

Opening Year (2019) Traffic Peak Cumulative # Intersection Control Hour Conditions Delay LOS AM 28.6 C 1 Cedar Avenue at Valley Boulevard S PM 33.9 C AM 71.2 E 2 Cedar Avenue at I-10 WB Ramps S PM 49.1 D AM 54.3 D 3 Cedar Avenue at I-10 EB Ramps S PM 43.6 D AM 58.3 F 4 Spruce Avenue at Valley Boulevard U PM 62.2 F AM 19.9 B 5 Cactus Avenue at Valley Boulevard S PM 14.1 B AM 20.6 C 6 Lilac Avenue at Valley Boulevard S PM 10.4 B AM 69.8 E 7 Riverside Avenue at Valley Boulevard S PM 48.0 D AM 38.3 D 8 Riverside Avenue at I-10 WB Ramps S PM 26.2 C AM 35.9 D 9 Riverside Avenue at I-10 EB Ramps S PM 43.8 D Notes: Bold and shaded values indicate intersections operating at unacceptable level of service. LOS E is acceptable for intersections along Riverside Avenue south of the Metrolink tracks to the City’s southern border. At a signalized intersection, delay refers to the average control delay for the entire intersection, measured in seconds per vehicle. At a two-way stop-controlled intersection, delay refers to the average vehicle delay on the worst movement. Delay values are based on the methodology outlined in the 2010 HCM. S = Signalized, U = Unsignalized Source: Kimley-Horn, 2017.

Valley & Spruce Project | 78

Table 23: Summary of Roadway Analysis, Opening Year (2019) - Cumulative Without Project

Opening Year (2019) Cumulative Roadway Daily Roadway Segment Conditions Classification Capacity ADT w/ LOS PCE Cedar Valley Boulevard to I-10 WB Ramps Arterial (120’) 41,249 63,297 F Avenue Cedar Avenue to Spruce Avenue Modified Arterial 32,999 23,526 B Valley Spruce Avenue to Cactus Avenue Modified Arterial 32,999 17,282 A Boulevard Cactus Avenue to Lilac Avenue Modified Arterial 32,999 19,992 A Lilac Avenue to Riverside Avenue Modified Arterial 32,999 24,938 B Riverside Valley Boulevard to I-10 WB Ramps Arterial (120’) 55,439 59,217 F Avenue Notes: PCE = Passenger Car Equivalent, ADT = Average Daily Traffic, LOS = Level of Service Bold and shaded values indicate intersections operating at unacceptable level of service. LOS E is acceptable along Riverside Avenue south of the Metrolink tracks to the City’s southern border. Daily capacity for Riverside Avenue is based on LOS E. Source: Kimley-Horn, 2017.

Project Traffic Project Trip Generation

Trip generation estimates for the proposed Project are based on daily and peak hourly trip generation rates obtained from the Institute of Transportation Engineers (ITE) Trip Generation Manual (9th Edition). ITE trip generation estimates for the proposed Project are based on the trip generation rates for ITE Land Use: Warehouse (Land Use 150). The Project is estimated to generate 2,414 Passenger Car Equivalent (PCE) vehicle trips on a daily basis, with 206 trips in the morning peak hour, and 215 trips in the evening peak hour. The resulting trip generation estimates for the proposed Project are summarized in Table 24: Summary of Project Trip Generation.

Valley & Spruce Project | 79

Table 24: Summary of Project Trip Generation Trip Generation Rates1 AM Peak Hour PM Peak Hour ITE Land Use ITE Code Unit Daily In Out Total In Out Total Warehousing 150 KSF 3.560 0.237 0.063 0.300 0.080 0.240 0.320 Project Trip Generation AM Peak Hour PM Peak Hour Project Land Use Quantity Unit Daily In Out Total In Out Total Warehousing 404.837 KSF 1,441 96 26 122 32 97 129 Passenger Vehicles (60%) 865 58 16 74 19 58 77 Trucks (40%) 576 38 10 48 13 39 52 AM Peak Hour PM Peak Hour Daily Veh PCE Vehicle Type Daily In Out Total In Out Total (Mix) 2 Factor 2- Axle Trucks 12 (0.8%) 1.5 18 1 0 1 0 1 1 3-Axle Trucks 161 (11.2%) 2.0 322 22 6 28 7 22 29 4+Axle Trucks 403 (28%) 3.0 1,209 81 22 103 27 81 108 Total Truck PCE Trips 1,549 104 28 132 34 104 138 Total Project PCE Trips 2,414 162 44 206 53 162 215 1 Source: Institute of Transportation Engineers (ITE) Trip Generation Manual, 9th Edition 2 Source: City of Rialto Traffic Impact Analysis Report Guidelines and Requirements, December 2013 Source: Kimley-Horn, 2017.

Trip Distribution and Assignment Trip distribution assumptions for the Project trips were developed considering the proposed site uses, and the routes to and from the freeway system for the warehouse trucks. Trip distribution assumptions are shown on Figure 7 in the traffic study. Trip distribution percentages at each study intersection were applied to the Project trip generation to determine the Project trips through each intersection. The resulting Project related peak hour trips at the study intersections are shown on Figure 8 in the traffic study. Project Opening Year (2019) plus Project As identified in Table 25: Summary of Intersection Operation, Opening Year (2019) - Existing Plus Growth, all traffic study area intersections would continue to operate at an acceptable LOS with the addition of the proposed Project except the following intersection:

▪ #4 – Spruce Avenue at Valley Boulevard: AM – LOS F, PM – LOS F This intersection would have a Project impact that would be considered a significant impact based on the significance criteria for an unsignalized intersection. As identified in Table 26: Summary of Roadway Analysis, Opening Year (2019) – Existing Plus Growth Plus Project , the following roadway segments would carry traffic volumes in excess of their daily capacity: ▪ Cedar Avenue: Valley Boulevard to I-10 WB Ramps ▪ Riverside Avenue: Valley Boulevard to I-10 WB Ramps These roadway segments would have a Project impact that would be considered a significant impact based on the significance criteria for roadways.

Valley & Spruce Project | 80

Table 25: Summary of Intersection Operation, Opening Year (2019) - Existing Plus Growth

Opening Year Opening Year Traffic Peak (2019) (2019) Plus Project Project Sig Int. # Intersection Control Hour Conditions Conditions Impact Impact? Delay LOS Delay LOS AM 28.0 C 28.2 C 0.2 No 1 Cedar Avenue at Valley Boulevard S PM 33.0 C 34.0 C 1.0 No AM 44.1 D 45.9 D 1.8 No 2 Cedar Avenue at I-10 WB Ramps S PM 27.3 C 32.2 C 4.9 No AM 35.9 D 40.0 D 4.1 No 3 Cedar Avenue at I-10 EB Ramps S PM 30.9 C 31.7 C 0.8 No AM 52.8 F 84.6 F 31.8 No 4 Spruce Avenue at Valley Boulevard U PM 56.2 F 193.5 F 137.3 Yes AM 20.0 B 21.6 C 1.6 No 5 Cactus Avenue at Valley Boulevard S PM 14.2 B 17.2 B 3.0 No AM 20.6 C 20.6 C 0.0 No 6 Lilac Avenue at Valley Boulevard S PM 10.5 B 10.4 B -0.1 No AM 64.3 E 63.5 E -0.8 No 7 Riverside Avenue at Valley Boulevard S PM 41.6 D 44.8 D 3.2 No AM 23.9 C 24.3 C 0.4 No 8 Riverside Avenue at I-10 WB Ramps S PM 21.7 C 21.8 C 0.1 No AM 24.2 C 24.3 C 0.1 No 9 Riverside Avenue at I-10 EB Ramps S PM 27.4 C 27.8 C 0.4 No Notes: Bold and shaded values indicate intersections operating at LOS E or F or significant impact to intersection per City standards. LOS E is acceptable for intersections along Riverside Avenue south of the Metrolink tracks to the City’s southern border. At a signalized intersection, delay refers to the average control delay for the entire intersection, measured in seconds per vehicle. At a two-way stop-controlled intersection, delay refers to the average vehicle delay on the worst movement. Delay values are based on the methodology outlined in the 2010 HCM. S = Signalized, U = Unsignalized Source: Kimley-Horn, 2017.

Valley & Spruce Project | 81

Table 26: Summary of Roadway Analysis, Opening Year (2019) – Existing Plus Growth Plus Project

Opening Year (2019) Opening Year (2019) Plus Project Roadway Daily Conditions Roadway Segment Conditions Classification Capacity ADT w/ ADT w/ LOS LOS PCE PCE Cedar Valley Boulevard to I-10 WB Ramps Arterial (120’) 41,249 61,483 F 62,938 F Avenue Cedar Avenue to Spruce Avenue Modified Arterial 32,999 23,063 A 24,734 B Valley Spruce Avenue to Cactus Avenue Modified Arterial 32,999 16,819 A 18,027 A Boulevard Cactus Avenue to Lilac Avenue Modified Arterial 32,999 19,529 A 20,143 A Lilac Avenue to Riverside Avenue Modified Arterial 32,999 24,475 B 25,089 B Riverside Valley Boulevard to I-10 WB Ramps Arterial (120’) 55,439 56,094 F 56,534 F Avenue Notes: PCE = Passenger Car Equivalent, ADT = Average Daily Traffic, LOS = Level of Service Bold and shaded values indicate intersections operating at unacceptable level of service. LOS E is acceptable for intersections along Riverside Avenue south of the Metrolink tracks to the City’s southern border. Daily capacity for Riverside Avenue is based on LOS E. Source: Kimley-Horn, 2017.

Project Opening Year (2019) Cumulative plus Project As identified in Table 27: Summary of Intersection Operation, Opening Year (2019) Cumulative Plus Project , all traffic study area intersections would continue to operate at an acceptable LOS with the addition of the proposed Project except the following intersections:

▪ #2 – Cedar Avenue at I-10 WB Ramps (signalized): AM – LOS E ▪ #4 – Spruce Avenue at Valley Boulevard (unsignalized): AM – LOS F, PM – LOS F The following intersections would experience a significant impact due to the Project, based on the significance criteria established by the City: ▪ #2 – Cedar Avenue at I-10 WB Ramps: PM – LOS D, Impact > 5.0 seconds ▪ #3 – Cedar Avenue at I-10 EB Ramps: PM – LOS D, Impact > 5.0 seconds ▪ #4 – Spruce Avenue at Valley Boulevard: PM – LOS F, Delay > 120 seconds (critical movement) ▪ #7 – Riverside Avenue at Valley Boulevard: AM – LOS E, Impact > 2.0 seconds As identified in Table 28: Summary of Roadway Analysis, Opening Year (2019) Cumulative Plus Project , the following roadway segments would carry traffic volumes in excess of their daily capacity: ▪ Cedar Avenue: Valley Boulevard to I-10 WB Ramps ▪ Riverside Avenue: Valley Boulevard to I-10 WB Ramps These roadway segments would have a Project impact that would be considered a significant impact based on the significance criteria for roadways.

Valley & Spruce Project | 82

Table 27: Summary of Intersection Operation, Opening Year (2019) Cumulative Plus Project

Opening Year Opening Year Traffic Peak (2019) (2019) Plus Project Project Sig Int. # Intersection Control Hour Conditions Conditions Impact Impact? Delay LOS Delay LOS AM 28.6 C 28.9 C 0.3 No 1 Cedar Avenue at Valley Boulevard S PM 33.9 C 37.7 D 3.8 No AM 71.2 E 73.0 E 1.8 No 2 Cedar Avenue at I-10 WB Ramps S PM 49.1 D 58.2 E 9.1 Yes AM 54.3 D 59.2 E 4.9 Yes 3 Cedar Avenue at I-10 EB Ramps S PM 43.6 D 45.2 D 1.6 No AM 58.3 F 95.2 F 36.9 No 4 Spruce Avenue at Valley Boulevard U PM 62.2 F 227.1 F 164.9 Yes AM 19.9 B 21.6 C 1.7 No 5 Cactus Avenue at Valley Boulevard S PM 14.1 B 17.1 B 3.0 No AM 20.6 C 20.7 C 0.1 No 6 Lilac Avenue at Valley Boulevard S PM 10.4 B 10.4 B 0.0 No AM 69.8 E 74.7 E 4.9 Yes 7 Riverside Avenue at Valley Boulevard S PM 48.0 D 50.2 D 2.2 No AM 38.3 D 39.7 D 1.4 No 8 Riverside Avenue at I-10 WB Ramps S PM 26.2 C 26.3 C 0.1 No AM 35.9 D 36.2 D 0.3 No 9 Riverside Avenue at I-10 EB Ramps S PM 43.8 D 45.2 D 1.4 No Notes: Bold and shaded values indicate intersections operating at LOS E or F or significant impact to intersection per City standards. LOS E is acceptable for intersections along Riverside Avenue south of the Metrolink tracks to the City’s southern border. At a signalized intersection, delay refers to the average control delay for the entire intersection, measured in seconds per vehicle. At a two-way stop-controlled intersection, delay refers to the average vehicle delay on the worst movement. Delay values are based on the methodology outlined in the 2010 HCM. S = Signalized, U = Unsignalized Source: Kimley-Horn, 2017.

Valley & Spruce Project | 83

Table 28: Summary of Roadway Analysis, Opening Year (2019) Cumulative Plus Project

Opening Year (2019) Opening Year (2019) Cumulative Plus Roadway Daily Cumulative Conditions Roadway Segment Project Conditions Classification Capacity ADT w/ ADT w/ LOS LOS PCE PCE Cedar Valley Boulevard to I-10 WB Ramps Arterial (120’) 41,249 63,297 F 64,752 F Avenue Cedar Avenue to Spruce Avenue Modified Arterial 32,999 23,526 B 25,197 B Valley Spruce Avenue to Cactus Avenue Modified Arterial 32,999 17,282 A 18,490 A Boulevard Cactus Avenue to Lilac Avenue Modified Arterial 32,999 19,992 A 20,606 A Lilac Avenue to Riverside Avenue Modified Arterial 32,999 24,938 B 25,552 B Riverside Valley Boulevard to I-10 WB Ramps Arterial (120’) 55,439 59,217 F 59,657 F Avenue Notes: PCE = Passenger Car Equivalent, ADT = Average Daily Traffic, LOS = Level of Service Bold and shaded values indicate intersections operating at unacceptable level of service. LOS E is acceptable for intersections along Riverside Avenue south of the Metrolink tracks to the City’s southern border. Daily capacity for Riverside Avenue is based on LOS E. Source: Kimley-Horn, 2017. The proposed Project’s impact would be considered significant for the following intersections: ▪ #2 – Cedar Avenue at I-10 Westbound Ramps ▪ #3 – Cedar Avenue at I-10 Eastbound Ramps ▪ #4 – Spruce Avenue at Valley Boulevard ▪ #7 – Riverside Avenue at Valley Boulevard Off-site mitigation improvements were identified to mitigate the Project’s significant impacts at the four study intersections. Off-site mitigation improvements were identified to mitigate the deficiency on one roadway segment: ▪ Cedar Avenue: Valley Boulevard to I-10 Westbound Ramps A Peak Hour Link Analysis (PHLA) evaluates volumes against theoretical capacity of a roadway to determine if the roadway capacity itself is exceeded or if intersection operations along the roadway dictate operations. A PHLA was conducted for the roadway segment of Riverside Avenue between Valley Boulevard and I-10 Westbound Ramps, as it would exceed its daily capacity, to determine if the segments would have enough hourly capacity during the morning and evening peak hours. An hourly capacity of 1,600 vehicles per hour for a single lane was assumed. As shown in Table 29: Peak Hour Link Analysis, Opening Year (2019) Cumulative Plus Project , Riverside Avenue capacity would indicate operations at LOS A during the peak hours under Opening Year 2019 Cumulative Plus Project Conditions. Thus, the intersections along Riverside Avenue dictate operations of the roadway segment. As such, no significant impact is determined to occur from a roadway segment capacity analysis at this location and no mitigation is required.

Valley & Spruce Project | 84

Table 29: Peak Hour Link Analysis, Opening Year (2019) Cumulative Plus Project

AM Peak PM Peak Roadway # Roadway Segment Capacity PCE PCE Classification Lanes V/C LOS V/C LOS Volume Volume Riverside Valley Boulevard to Northbound 3 4,800 1,434 0.299 A 2,228 0.464 A Avenue I-10 WB Ramps Southbound 3 4,800 2,180 0.454 A 1,746 0.364 A Source: Kimley-Horn, 2017.

Mitigation Measures TRAF-1 Cedar Avenue at I-10 Westbound Ramps: The SANBAG Development Mitigation Nexus Study (June 2016) identifies the Cedar Avenue and I-10 interchange as a needed improvement project. This mitigation measure would add a second westbound right-turn lane. This improvement is consistent with the proposed improvements to the Cedar Avenue / I-10 Interchange Improvement project. This improvement would more than offset the project-related incremental delay. The Cedar Avenue / I-10 interchange is outside the City of Rialto and is included in the SANBAG Development Mitigation Nexus Study. The development obligation is met with the payment of the development impact fee (DIF). TRAF-2 Cedar Avenue at I-10 Eastbound Ramps: The SANBAG Development Mitigation Nexus Study (June 2016) identifies the Cedar Avenue and I-10 interchange as a needed improvement project. This mitigation measure would add a second eastbound left-turn lane. This improvement is consistent with the proposed improvements to the Cedar Avenue / I-10 Interchange Improvement project. This improvement would more than offset the project-related incremental delay. The Cedar Avenue / I-10 interchange is outside the City of Rialto and is included in the SANBAG Development Mitigation Nexus Study. The development obligation is met with the payment of the development impact fee (DIF). TRAF-3 Spruce Avenue at Valley Boulevard: Signalization. This improvement is identified in the City of Rialto 2013 Nexus Study Updated. This improvement would more than offset the project-related incremental delay. Since this intersection serves as an access point to the site, the project will construct the traffic signal. TRAF-4 Riverside Avenue at Valley Boulevard: Provide an eastbound right-turn overlap from Valley Boulevard onto southbound Riverside Avenue. This improvement would more than offset the project-related incremental delay. The project will contribute a fair-share basis to this improvement. TRAF-5 Cedar Avenue between Valley Boulevard and I-10 Westbound Ramps: The SANBAG Development Mitigation Nexus Study (June 2016) identifies the Cedar Avenue and I-10 interchange as a needed improvement project. Currently, the Cedar/I-10 Interchange Improvements project includes improvements at the interchange intersections along Cedar Avenue, as well as widening of Cedar Avenue. The widening associated with the interchange project would mitigate the impact at this location. The Cedar Avenue / I-10 interchange is outside the City of Rialto and is included in the SANBAG Development Mitigation Nexus Study. The development obligation is met with the payment of the development impact fee (DIF).

Valley & Spruce Project | 85

With implementation of Mitigation Measures TRAF-1 through TRAF-5, the proposed Project would have a less than significant impact to the intersections of Spruce Avenue at Valley Boulevard and Riverside Avenue at Valley Boulevard. b) Conflict with an applicable congestion management program, including, but not limited to level of service standards and travel demand measures, or other standards established by the county congestion/management agency for designated roads or highways? Less Than Significant Impact. The purpose of the Congestion Management Program (CMP) is to develop a coordinated approach to managing and decreasing traffic congestion by linking the various transportation, land use, and air quality planning programs throughout the County, consistent with that of SANBAG. The CMP requires review of substantial individual projects, which might on their own impact the CMP transportation system. Specifically, the CMP Traffic Impact Analysis measures impacts of a project on the CMP Highway System. Compliance with the CMP requirements ensures a city’s eligibility to compete for State gas tax funds for local transportation projects.

The CMP requires that a Traffic Impact Analysis include analysis of any CMP arterial monitoring intersection where the Project will add 50 or more trips during either the AM or PM weekday peak hour; and any freeway monitoring location where the Project will not add 150 or more trips, in either direction, during either the AM or PM peak hour. The proposed Project would not add 50 or more trips during either the AM or PM weekday peak hour to a designated CMP intersection; and would not add 150 or more trips to any freeway mainline location, in either direction, during either the AM or PM peak hour. Therefore, the proposed Project would not exceed a level of service standard established by the CMP for designated roads or highways. c) Result in a change in air traffic patterns, including either an increase in traffic levels or a change in location that results in substantial safety risks? No Impact. The proposed Project would not include any aviation components or structures where height would be an aviation concern. No traffic impacts would occur and no mitigation is required. d) Substantially increase hazards due to a design feature (e.g., sharp curves or dangerous intersections) or incompatible uses (e.g., farm equipment)? No Impact. The Project site driveways and proposed Project improvements would be designed to provide adequate sight distance for drivers entering and exiting the Project site. The roadway infrastructure surrounding the Project site would be developed and/or expanded consistent with City standards. The proposed Project would not introduce any new design features that would create hazards to traffic. No significant impacts would occur and no mitigation is required. e) Result in inadequate emergency access? No Impact. Vehicular access provisions for the Project site would consist of the following: ▪ Two full-movement driveways on Spruce Avenue. ▪ Two full-movement driveways on Cactus Avenue. ▪ Passenger vehicles and trucks would access the site via the south driveways on either Spruce Avenue or Cactus Avenue. ▪ Passenger vehicles would access the site via the north driveways on either Spruce Avenue or Cactus Avenue.

Valley & Spruce Project | 86

The cumulative intersection analysis for the With Project condition indicates that all Project driveways will operate at acceptable Level of Service during both peak hour periods. Constructed roadways and driveways are required to meet access standards of Rialto Fire Department. Compliance with the Fire Department requirements would ensure impacts remain less than significant.

f) Conflict with adopted policies, plans, or programs regarding public transit, bicycle, or pedestrian facilities, or otherwise decrease the performance or safety of such facilities? No Impact. The main alternative transportation mode available to the Project would be bus transit. Bus routes in the City of Rialto are provided via the OmniTrans transit lines, which serve several San Bernardino cities in the area. The nearest bus stops in the Project vicinity are located at the intersections of Riverside Avenue at Valley Boulevard and Cedar Avenue at Valley Boulevard. OmniTrans Route 22 operates between the City of Rialto and the City of Colton via Riverside Avenue. OmniTrans Route 29 operates between the City of Fontana and the Bloomington area, traveling along Valley Boulevard and Cedar Avenue, approximately one- half mile from the Project site. There are no planned or existing designated bicycle routes in the study area. The proposed Project would not conflict with adopted policies, plans, or programs regarding alternative modes of transportation. No impact would result.

Cumulative Impacts The traffic study addresses both the Project-specific and the Project’s contribution to cumulative impacts. The Project would have a significant impact to the intersections of Spruce Avenue at Valley Boulevard and Riverside Avenue at Valley Boulevard that can be mitigated to a less than significant level.

Valley & Spruce Project | 87

17. Tribal Cultural Resources Less Than Significant Potentially with Less than Significant Mitigation Significant No Issues Impact Incorporated Impact Impact Would the project cause a substantial adverse change in the significance of a tribal cultural resource, defined in Public Resources Code section 21074 as either a site, feature, place, cultural landscape that is geographically defined in terms of the size and scope of the landscape, sacred place, or object with cultural value to a California Native American tribe, and that is: a. Listed or eligible for listing in the California Register of Historical Resources, or in a local register of historical resources as defined in Public Resources Code section 5020.1(), or b. A resource determined by the lead agency, in its discretion and supported by substantial evidence, to be significant pursuant to criteria set forth in subdivision (c) of Public Resources Code Section 5024.1. In applying the criteria set forth in subdivision (c) of Public Resources Code Section 5024.1, the lead agency shall consider the significance of the resource to a California Native American tribe.

Discussion A Cultural Resource Study Findings Memorandum (September 2017) was prepared for the proposed Project to evaluate cultural and tribal resources on the Project site and in surrounding areas. The report is provided in Appendix C; the results and conclusions of the report related to Tribal Cultural Resources are summarized herein. a) Listed or eligible for listing in the California Register of Historical Resources, or in a local register of historical resources as defined in Public Resources Code section 5020.1(k). As discussed above in Section VI. (5) Cultural Resources, the proposed Project would result in no impact or a less than significant impact with mitigation incorporated to sites that are listed or eligible for listing in the California Register of Historic Resources. Less Than Significant Impact. b) A resource determined by the lead agency, in its discretion and supported by substantial evidence, to be significant pursuant to criteria set forth in subdivision (c) of Public Resources Code Section 5024.1. In applying the criteria set forth in subdivision (c) of Public Resources Code Section 5024.1, the lead agency shall consider the significance of the resource to a California Native American tribe. Less Than Significant Impact. Tribal cultural resources as defined in Public Resources Code section 5020.1(k) have not been previously identified within the proposed Project site. The proposed Project site is undeveloped and does not contain any existing structures or extant historical tribal cultural resources with the potential for inclusion on the California Register of Historical Resources or a local register. A Cultural Resource Study Findings Memorandum was prepared by ASM Affiliates in September 2017 for the proposed Project and is provided as Appendix C. In accordance with Assembly Bill (AB) 52, and the California Tribal Consultation guidelines, ASM sent a request to the NAHC to search their Sacred Lands File (SLF) to ascertain whether their files contained

Valley & Spruce Project | 88

any information relating to the presence of Native American cultural resources within the Project area. The other intent of this contact is to determine the appropriate native groups that are traditionally and culturally affiliated with the Project area so they may be provided the opportunity to provide input. In response to the ASM letter, NAHC responded on September 27, 2017 and indicated they lacked documentation that tribal resources exist in the Project area. It should be noted, however, that the absence of specific site information in the SLF does not indicate the absence of Native American cultural resources within the proposed Project site. The NAHC, did provide a list of 18 tribes who may be culturally affiliated with the proposed Project site. Per the City’s standard practice and in accordance with Assembly Bill 52 (AB 52), including Section 21080.3.1(d), the City circulated letters via certified mail on November 13, 2017 to the following eleven (11) tribes to request comments and input on the proposed Project and the potential to affect Tribal and Cultural Resources. ▪ Agua Caliente Band of Cahuilla Indians ▪ Morongo Band of Mission Indians ▪ Agua Caliente Band of Cahuilla Indians – ▪ Ramona Band of Cahuilla Mission Indians THPO ▪ San Fernando Band of Mission Indians ▪ Gabrieleño Band of Mission Indians – ▪ San Manuel Band of Mission Indians Kizh Nation ▪ Serrano Nation of Mission Indians ▪ Gabrieleño /Tongva Nation ▪ Soboba Band of Luiseno Indians ▪ Gabrieleño/Tongva San Gabriel Band of Mission Indians ▪ Agua Caliente Band of Cahuilla Indians – THPO

On November 16, 2017, the City received a response letter from the Gabrieleño Band of Mission Indians – Kizh Nation to request additional consultation. The City has reached out to the tribe to initiate tribal consultation and is currently trying to identify potential next steps. Upon confirmation of the request(s) by the Gabrieleño Band of Mission Indians – Kizh Nation, the City will use commercial reasonable efforts to put a mitigation measure in place in addition to Mitigation Measures CUL-1, CUL-2, and CUL-3 already provided in the Cultural Resources section, to satisfy the requirement or requirements set forth by the Gabrieleño Band of Mission Indians – Kizh Nation. Cumulative Impacts The proposed Project would result in less than significant impacts to tribal cultural resources. The chances of cumulative impacts occurring as a result of Project implementation plus implementation of other projects in the region is not likely since all past, present, and reasonably foreseeable project would be have been or will be subject to individual project-level environmental review. Since there would be no project-related impacts, and because existing laws and regulations are in place to protect tribal cultural resources and prevent significant impact to such resources, the potential incremental effects of the proposed Project would not be cumulatively considerable.

Valley & Spruce Project | 89

18. Utilities and Service Systems Less Than Significant Potentially with Less than Significant Mitigation Significant No Issues Impact Incorporated Impact Impact Would the project: a.Exceed wastewater treatment requirements of the

applicable Regional Water Quality Control Board? b. Require or result in the construction of new water or wastewater treatment facilities or expansion of

existing facilities, the construction of which could cause significant environmental effects? c. Require or result in the construction of new storm water drainage facilities or expansion of existing facilities, the construction of which could cause significant environmental effects? d. Have sufficient water supplies available to serve the project from existing entitlements and resources, or are new or expanded entitlements needed? e. Result in a determination by the wastewater treatment provider which serves or may serve the project that it has adequate capacity to serve the project’s projected demand in addition to the provider’s existing commitments? f. Be served by a landfill with sufficient permitted capacity to accommodate the project’s solid waste disposal needs? g. Comply with federal, State, and local statutes and

regulations related to solid waste?

Discussion Rialto Water Services (RWS) provides water and wastewater services to 100,000 people in the Inland Empire in partnership with Veolia North America (VNA). In 2012, the City of Rialto agreed to a 30-year concession agreement to accelerate delivery of a capital improvement projects. The City turned over management of the water and wastewater systems to VNA in order to implement $41 million in capital and efficiency improvements within a five-year period. In 2013, VNA partnered with Table Rock Capital (TRC) to facilitate the financing of the agreement which involved an upfront $35 million payment to begin improvements.17 These agreements allow the City to retain full ownership of water and wastewater systems, retain all water rights and supply, and to maintain the rate-setting authority associated with the facilities, while Veolia North America delivers all water and wastewater services, including billing and customer service, and oversees

17 Veolia North America, 2017. Rialto, Calif. Available at: https://www.veolianorthamerica.com/en/case-studies/rialto-california Accessed October 10, 2017.

Valley & Spruce Project | 90

the improvement program to upgrade aging facilities including seismic retrofits, and improving water supply and wastewater capacity.18 a) Exceed wastewater treatment requirements of the applicable Regional Water Quality Control Board? Less Than Significant Impact. The proposed Project is within the jurisdiction of the Santa Ana RWQCB and is subject to the waste discharge requirements of the MS4 Permit for San Bernardino and Riverside counties and the proposed permit for San Bernardino County. As discussed above, in Section VI. (9) Hydrology and Water Quality, the proposed Project would be required to implement a Storm Water Pollution Prevention Plan (SWPPP) that would require the use of Best Management Practices (BMPs) to ensure water quality is not degraded. This may also include the filing of a NPDES permit and other applicable permits. Implementation of these measures would ensure that storm water flowing from the proposed Project site would not result in an exceedance of any wastewater treatment requirements of the Santa Ana Regional Water Quality Control Board (RWQCB). Impacts in this regard would be considered less than significant. The proposed Project also would be required to abide by all applicable Santa Ana RWQCB requirements, including payment of fees to offset cost of wastewater infrastructure, such that the proposed Project would not exceed wastewater treatment standards. As discussed above, wastewater conveyance is handled by Veolia North America (VNA) utilizing infrastructure previously management by RWS. Wastewater is processed at the Wastewater Treatment Plant (WTP) located at 501 E. Santa Ana Avenue. Locally, wastewater would flow from the Project site into existing sewer mains and flow southeast to the treatment plant. The proposed Project would abide by all required regulations regarding wastewater discharge into this system. Doing so would ensure that the proposed Project’s does not violate any wastewater treatment requirements. This includes causing an exceedance of the treatment capacity of the WTP, which discussed in additional detail below. Prior to VNA assuming management of the wastewater system, the City of Rialto General Plan (2010) estimated the life expectancy of the sewer system outside of expansion needs was 50 to 100 years. Construction of the original WTP was in 1956 and over the years the WTP has been expanded and upgraded to its current treatment capacity of between 12 mgd. The General Plan does note that there are upgrades and some maintenance that is required to the 263-mile collection system and 6 lift stations.19 The maintenance and upgrades are expected to accommodate growth as it occurs within planning areas such as within the Gateway Specific Plan Area. In addition, through the RWS agreement with VNA, VNA is responsible for managing maintenance and planned upgrades to ensure adequate wastewater treatment is available to serve future demand within the City. The City of Rialto produces around 7-8 million gallons of sewage on a daily basis.20 Therefore, considering the treatment capacity 12 mgd and existing flows, the WTP operates on average at 66.6 percent of daily capacity. The RWQCB requires treatment plant expansions when a

18 City of Rialto, 2017 – Rialto Water Services, Part of a Unique Concession Agreement. Available at: http://rialtowater.com/about-us/ Accessed October 9, 2017. 19 Veolia North America, 2017. Rialto, Calif. Available at: https://www.veolianorthamerica.com/en/case-studies/rialto-california Accessed October 10, 2017. 20 City of Rialto, 2017b. Rialto Wastewater – Did You Know? Available at: http://rialtowater.com/about-us/wastewater/ Accessed October 10, 2017

Valley & Spruce Project | 91

plant reaches 75 percent capacity. As indicated in Table 30: Estimated Wastewater Generation, below, the proposed Project is projected to generate 4,572.5 gallons of effluent on a daily basis. The additional 4,498.4 gpd of wastewater generated by the proposed Project would result in the treatment facility operating at approximately 66.7 percent of the plant's current daily capacity.

Table 30: Estimated Wastewater Generation

Wastewater Generation, Gallons per Day (gpd) Land Use Area (sf) Per Unita Total Warehouse 399,837 0.01 gpd per sq. ft. 3,998.4 gpd Office 5,000 0.1 gpd per sq. ft. 500 gpd Total 4,498.4 gpd a. Per Unit Generation Factors from City of San Bernardino Municipal Water Department – Sewage Flow Guide for Domestic Waste Discharge

Therefore, the available capacity is sufficient to accommodate the treatment requirements of the proposed Project. In addition, because the system is managed by a city-wide management plan which will provide for maintenance and needed system improvements, the proposed Project will not violate any standards set forth by the RWQCB. Impacts are less than significant and no mitigation is required. b) Require or result in the construction of new water or wastewater treatment facilities or expansion of existing facilities, the construction of which could cause significant environmental effects? Less Than Significant Impact. As discussed above, sewer lines are already in place to serve the proposed Project and expansion of these lines beyond the scope of the proposed Project site or construction of a new or expanded wastewater treatment facilities as a result of the proposed Project would not be required. As discussed above, expansion of the existing WTP and associated infrastructures was already planned and are not a result of the increased demand from proposed Project. Therefore, the proposed would not require the construction of new wastewater facilities which could cause significant environmental effects. Impacts would not occur, and no mitigation is required. c) Require or result in the construction of new storm water drainage facilities or expansion of existing facilities, the construction of which could cause significant environmental effects? Less Than Significant Impact. Implementation of the proposed Project would require the construction of new storm drainage facilities to control storm water run-off. Stormwater facilities would tie into existing stormwater drainage facilities within existing City of Rialto right-of-way’s. Storm drainage facilities have been designed to provide for an adequate volume of on-site detention, and infiltration in landscaped areas so that all water discharged from the site is properly treated and will not negatively affect off-site or downstream flows. As described in Section 9, Hydrology and Water quality, the majority of the Project site drains to a proposed underground infiltration basin in the proposed truck yard, which would infiltrate or drain to the onsite storm drain system that conveys runoff to the I-10 Drainage Channel. In addition to the underground infiltration basin, two small landscape areas are designed to be self-treating and would directly discharge to the I-10 Drainage Channel.

Valley & Spruce Project | 92

The underground infiltration facility would be designed and utilized to satisfy stormwater quality measures prior to being discharged to downstream waters. The proposed Project’s storm water facilities would be designed to limit the release of storm water to pre- development conditions. The new storm drain facilities would be constructed within the footprint of the proposed Project site and within areas proposed for disturbance. No off-site areas or areas outside the scope of the proposed Project as evaluated within the various section of this Initial Study would occur and all impacts are disclosed. Therefore, implementation of the stormwater drainage system for the proposed Project would not result in significant environmental effects either on the Project site or at any off-site location. Impacts would be less than significant and no mitigation is required. d) Have sufficient water supplies available to serve the project from existing entitlements and resources, or are new or expanded entitlements needed? Less Than Significant Impact. The City of Rialto is provided water service by three different water agencies: City of Rialto municipal water system through its water system operator (Veolia, through Rialto Water Services), the West Valley Water District (WVWD), and the Fontana Union Water Company (FUWC). Each agency has its own water supply and resources, and must meet its demands through those resources. 21 The proposed Project is within the WVWD service areas. In June 2016, the 2015 San Bernardino Valley Regional Urban Water Management Plan (UWMP) was published. The UWMP was prepared for the WVWD and nine other water suppliers including (San Bernardino Valley Municipal Water District, East Valley Water District, City of Loma Linda, City of Redlands, City of San Bernardino Municipal Water Department, Yucaipa Valley Water District, City of Colton, City of Rialto, and Riverside Highland Water Company).19 WVWD’s service area is approximately 31 square miles, serving portions of the Cities of Rialto, Fontana, Colton, and Jurupa Valley, and unincorporated areas of San Bernardino County. WVWD utilizes water from five groundwater basins and treats surface water from Lytle Creek and SWP water at its 14.4-mgd Oliver P. Roemer Water Filtration Facility to serve over 19,000 water service connections.19 The 2015 UWMP projected demand for raw and potable water for five year increments based on land use between 2020 to 2040 for the WVWD service area. For year 2020, Commercial uses are expected to use 1,730 acre feet of water per year (afy). This is contrasted by a total demand within the WVWD of 20,799 afy. Of this amount, commercial uses represent approximately 8.3%. The balance of the 19,069 afy, would be used by a combination of uses including single family, multi-family, institutional, industrial, agricultural irrigation, landscape irrigation, fire service, and hydrant. These uses account for the remaining 91.7% of potable water demand. The estimated water use for commercial uses through 2040 in five-year increments are as follows: year 2025 – (8.3%), year 2030 – (8.4%), year 2035 – (8.4%), and year 2040 – (8.4%).19 The UWMP Act requires a retailer to quantify the minimum water supply available during the next three years. Using this criterion, for the years 2016 to 2018, assuming those years repeated the driest three-year historic sequence for each water supply source, WVWD estimated the minimum water supply for these years. These supplies are based on the

21 San Bernardino Valley Municipal Water District, et al., 2016. 2015 San Bernardino regional Urban Water Management Plan, Available at: https://wvwd.org/DocumentCenter/View/1261. Accessed October 10, 2017.

Valley & Spruce Project | 93

anticipated reliability of imported State Water Project water from Valley District, local surface water, and local groundwater, and are shown in Table 31: WVWD Minimum Three Year Supply 2016-2018.

Table 31: WVWD Minimum Three Year Supply 2016-2018

Year 2016 2017 2018 Available Water Supply 33,030 33,030 33,030 Source: 2015 San Bernardino Valley Regional Urban Water Management Plan Note: Units in Acre-feet per year

WVWD estimated water supply and water demand at five year increments from 2020-2040. Table 32: WVWD Water Supply and Demands Estimates for years 2020-2040, which is shown below.

Table 32: WVWD Water Supply and Demands Estimates for years 2020-2040

2020 2025 2030 2035 2040 Supply Total 36,400 41,900 45,400 48,400 48,400 Demand Total 20,799 22,256 23,802 25,492 27,312 Difference 15,601 19,644 21,598 22,908 21,088 Source: 2015 San Bernardino Valley Regional Urban Water Management Plan Note: Units in Acre-feet per year

Based on this analysis, it is anticipated that the WVWD will can meet the potable water demands for the existing and future 20-year projected planned growth within the WVWD’s service area. This conclusion is true under normal, single-dry and multiple-dry year conditions. In addition, because total water demand for the foreseeable future is approximately 50% of the projected total supply, the increased demand as whole as well as from the proposed Project would be met. Potable water would be supplied using imported water supplies, local surface and groundwater supplies and through recycling and water conservation. Therefore, adequate water supplies would be available to serve proposed Project, impacts would be less than significant, and mitigation is not required. e) Result in a determination by the wastewater treatment provider which serves or may serve the project that it has adequate capacity to serve the project’s projected demand in addition to the provider’s existing commitments? Less Than Significant Impact. Refer to response VI.18(a) and (b) above. The wastewater infrastructure needed to serve the proposed Project is already in place and the WTP has adequate capacity to serve the proposed Project’s increased demand. Impacts would be less than significant and no mitigation is required. f) Be served by a landfill with sufficient permitted capacity to accommodate the project’s solid waste disposal needs? Less Than Significant Impact. Implementation of the proposed Project would be expected to generate additional waste during the temporary, short-term construction phase, as well as the operational phase, but it would not be expected to result in inadequate landfill capacity. The City of Rialto’s Waste Management Office oversees the City’s trash and recycling services, which are provided by Burrtec Waste Industries. Solid waste would be disposed of at the Mid-Valley Sanitary Landfill located approximately 5.5. miles north of the proposed Project site. The landfill has a maximum throughput of 7,500 tons per day. This landfill has a maximum permitted capacity

Valley & Spruce Project | 94

of approximately 101.3 million cubic yards, and the landfill has a remaining capacity of approximately 67.5 million cubic yards.22 The landfill has an expected operational life through 2033 with the potential for vertical, or downward expansion.23 Landfill capacity is expected to decrease over time with future growth and development throughout San Bernardino County and surrounding Inland Empire areas. Waste reduction and recycling programs and regulations are expected to reduce this demand and extend the life of existing landfills. The proposed Project complies with the land use and zoning designated in the Gateway Specific Plan. Furthermore, the Specific Plan projected that build out would result in an estimated net increase in solid waste disposal of 16,615 tons per year. This increase would represent approximately 0.61 percent of Mid-Valley Landfill’s daily permitted capacity. This nominal incremental increase in solid waste disposal disposed of at Mid-Valley Landfill would not be considered cumulative considerable. Therefore, impacts would be less than significant and no mitigation is required. g) Comply with federal, State, and local statutes and regulations related to solid waste? Less Than Significant Impact. Refer to response VI.18 (f) above. The Mid-Valley Landfill has been constructed to meet all required local, State, and federal rules and regulations. The proposed Project would not compromise the City’s compliance with federal, State and local statues and regulations related to solid waste. Impacts would be less than significant and no mitigation is required.

Cumulative Impacts The proposed Project would have a less than significant impact with respect to utilities/service systems. The proposed Project would require water and wastewater infrastructure, as well as solid waste disposal for building facility operation. Development of public utility infrastructure is part of an extensive planning process involving utility providers and jurisdictions with discretionary review authority. The coordination process associated with the preparation of development and infrastructure plans is intended to ensure that adequate resources are available to serve both individual projects and cumulative demand for resources and infrastructure as a result of cumulative growth and development in the area. Individual projects are subject to review for utility capacity to avoid unanticipated interruptions in service or inadequate supplies. Coordination with the utility companies would allow for the provision of utility service to the proposed Project and other developments. The proposed Project and other planned projects are subject to connection and service fees to assist in facility expansion and service improvements triggered by an increase in demand. Because of the utility planning and coordination activities described above, the proposed Project taken in sum with past, present, and reasonably foreseeable projects would not result in significant cumulative utility impacts.

22 California, State of, Department of Resources Recycling and Recovery (CalRecycle) Available at: http://www.calrecycle.ca.gov/SWFacilities/Directory/36-AA-0055/Detail, accessed October 10, 2017 23 Ibid. p 4.16-15 and 16.

Valley & Spruce Project | 95

19. Mandatory Findings of Significance

Less Than Potentially Significant Less than Significant with Mitigation Significant No Issues Impact Incorporated Impact Impact Would the project: a. Does the project have the potential to degrade the quality of the environment, substantially reduce the habitat of a fish or wildlife species, cause a fish or wildlife population to drop below self- sustaining levels, threaten to eliminate a plant or animal community, reduce the number or restrict the range of a rare or endangered plant or animal or eliminate important examples of the major periods of California history or prehistory? b. Does the project have impacts that are individually limited, but cumulatively considerable? ("Cumulatively considerable" means that the incremental effects of a project are considerable when viewed in connection with the effects of past projects, the effects of other current projects, and the effects of probable future projects)? c. Does the project have environmental effects which will cause substantial adverse effects on human beings, either directly or indirectly?

Discussion a) Does the project have the potential to degrade the quality of the environment, substantially reduce the habitat of a fish or wildlife species, cause a fish or wildlife population to drop below self-sustaining levels, threaten to eliminate a plant or animal community, reduce the number or restrict the range of a rare or endangered plant or animal or eliminate important examples of the major periods of California history or prehistory? Less Than Significant Impact with Mitigation Incorporated. As described throughout the Initial Study, the proposed Project would not result in any significant impacts to the environment that cannot be mitigated to a less than significant level through the application of uniformly applied mitigation and development policies and/or standards. The proposed Project would be required to implement a range of standard and uniformly applied development policies and standards, as well as implement mitigation measures identified in the analysis herein, which would reduce impacts to a less than significant level. b) Does the project have impacts which are individually limited, but cumulatively considerable (Cumulatively considerable means the projects incremental effects are considerable when compared to the past, present, and future effects of other projects)? Less Than Significant Impact with Mitigation Incorporated. The proposed Project would result in significant impacts in the following areas: biological resources, cultural resources, geology and soils, noise and transportation/traffic. A Mitigation Monitoring and Reporting Program has been prepared for each of these environmental issue areas in order to reduce impacts to less than significant levels. Standard conditions would also be imposed upon the project. Other new development projects within the City would also be subject to these requirements.

Valley & Spruce Project | 96

All other impacts of the proposed Project were determined either to have no impact or to be less than significant, without the need for mitigation. Cumulatively, the proposed Project would not result in any significant impacts that would substantially combine with impacts of other current or probable future impacts. Therefore, the proposed Project, in conjunction with other future projects, would not result in any cumulatively considerable impacts. c) Does the project have environmental effects which will have substantial adverse effects on human beings, directly or indirectly? Less Than Significant Impact. As discussed in the respective sections, the proposed Project would have no potentially significant impacts. Therefore, impacts related to adverse effects on human beings would be less than significant.

Valley & Spruce Project | 97

VII. P e p a r e r s

City of Rialto (Lead Agency) 150 S. Palm Avenue Rialto, CA 92376 Gina Gibson-Williams, Planning Manager

Kimley-Horn and Associates, Inc. 401 B Street, Suite 600 San Diego, California 92101 (619) 234-9411 Karina Fidler, AICP, Project Manager

VIII. R e f e r e n c e s ASM Affiliates, Cultural Resource Study Findings Memo for the Valley & Spruce Project, City of Rialto, San Bernardino County, California, September 2017. ATC Group Services LLC, Phase I Environmental Site Assessment Of I-10 Logistics Center SWC of Valley Boulevard and Cactus Avenue Rialto, California 92316. October 2017. California Institute of Technology, 2017. Southern California Earthquake Data Center - San Jacinto Fault Zone, Available: http://scedc.caltech.edu/significant/index.html. Accessed October 5, 2017. California Standard Specifications, July 1992. California, State of, Department of Conservation. California Important Farmland Finder. Available at: http://maps.conservation.ca.gov/ciff/ciff.html. Accessed September 5, 2017. California, State of, Department of Conservation. Division of Oil, Gas, and Geothermal Resources. Available at: http://www.conservation.ca.gov/dog/Pages/Wellfinder.aspx. Accessed September 6, 2017. California, State of, Department of Conservation, San Bernardino County Williamson Act FY 2015/2016. Available at: ftp://ftp.consrv.ca.gov/pub/dlrp/wa/SanBernardino_so_15_16_WA.pdf. Accessed September 5, 2017. California, State of, Employment Development Department, Labor Force and Unemployment Rate for Cities and Census Designated Places, http://www.labormarketinfo.edd.ca.gov/data/labor-force-and- unemployment-for-cities-and-census-areas.html. Accessed September 6, 2017. California, State of, Employment Development Department, Riverside-San Bernardino-Ontario Metropolitan Statistical Area (MSA), July 2017 – Preliminary. Available at: http://www.labormarketinfo.edd.ca.gov/file/lfmonth/rive$pds.pdf. Accessed September 6, 2017. California, State of, Governor’s Office of Emergency Services, Hazard Mitigation Planning Division, http://myplan.calema.ca.gov. Accessed October 9, 2017. California, State of, Department of Resources Recycling and Recovery (CalRecycle) http://www.calrecycle.ca.gov/SWFacilities/Directory/36-AA-0055/Detail. Accessed October 10, 2017.

Valley & Spruce Project | 98

California, State of, Department of Toxic Substances Control. DTSC's Hazardous Waste and Substances Site List - Site Cleanup (Cortese List). Available at: http://www.dtsc.ca.gov/SiteCleanup/Cortese_List.cfm. Accessed October 9, 2017. California, State of, Department of Transportation. Official Designated Scenic Highways. Available at: http://www.dot.ca.gov/hq/LandArch/scenic_highways/index.htm. Accessed September 7, 2017. Entech Consulting Group, Air Quality, Greenhouse Gas and Health Risk Assessment Study for the Valley and Spruce Project, City of Rialto. October 2017. Entech Consulting Group, Noise & Vibration Study for the Valley and Spruce Project, City of Rialto. December 2017. Kimley-Horn and Associates, Traffic Impact Study for the Proposed Valley and Cactus Warehouse in The City of Rialto. October 2017. Rialto, City of, Development Code. 2010. Rialto, City of, Final Environmental Impact Report for Rialto Gateway Area, SCH #88090526. January 1990. Rialto, City of, Fire Department. Available at: http://yourrialto.com/residents/fire-department/. Accessed September 6, 2017. Rialto, City of, Police Department. Organizational Chart. Available: http://www.rialtopd.com/index.php/divisions-1/department-organizational-chart. Accessed October 6, 2017. Rialto, City of, Specific Plan for Rialto Gateway Area. January 1990. Rialto, City of, Wastewater – Did You Know? Available: http://rialtowater.com/about-us/wastewater/ Accessed October 10, 2017. Rialto, City of, Water Services Department, Part of a Unique Concession Agreement. Available: http://rialtowater.com/about-us/. Accessed October 9, 2017. Rialto, City of, Zoning Map. 2013. Rocks Biological Consulting, Valley & Spruce Project Biotic Resources Report. September 20, 2017. San Bernardino Valley Municipal Water District, 2015 San Bernardino regional Urban Water Management Plan, Available at: https://wvwd.org/DocumentCenter/View/1261. Accessed October 10, 2017. Southern California Geotechnical, Geotechnical Investigation Proposed Commercial/Industrial Building, SEC Valley Boulevard and Spruce Avenue Rialto, California. September 13, 2017. Thienes Engineering, Inc., Preliminary Hydrology Calculations for Valley Boulevard Between Spruce Avenue and Cactus Avenue, Rialto, California. September 22, 2017. Thienes Engineering, Inc., Water Quality Management Plan for Valley Blvd. and Spruce Ave., Valley Boulevard, Rialto, California 92316. September 20, 2017.

Veolia North America, 2017. Rialto, Calif. Available: https://www.veolianorthamerica.com/en/case- studies/rialto-california. Accessed October 10, 2017.

Valley & Spruce Project | 99