24 Structure Getty

Precast BERGER/ABAM

James

Mark Federal A. Senior T.

G.

S. Glendale, Curd Way,

Josten,

Guarre, Project Vice Engineers Constructors

Center Washington The

Wilfred Senior A. Glendale, Rialto, Precast P. President Manager

E. T.

PCI Niobrara

RE. Curd

RE. California Vice Inc.

Prestressed Operations California Constructors

L. President

DESIGN River

Painter,

Provides Company

Jr.

Tram

AWARD

people-mover

post-tensioning. steep system Museum from structure design

project tors ports and concrete Diego of the

visual the To

tific J. Getty design Paul headquarters in The

p The Paul Los the

solve from laboratories Getty

innovative designers a

construction Museum.

answers arts

an Getty Freeway Sepulveda role recast long, people-mover alongside Angeles, Getty

WINNER

hillside

features,

Guideway an

posed

and and

underground in Trust.

Solution

the

(near curved, underground Center for and Museum, the

supporting humanities.

components Fig. to

construction the

problem for California. the

Concrete design-construction prestressed The Pass the to

several

and is 1 programs U-shaped use

system conservation San

Los

to

precast system,

highlights shows

these main Center a between

This a cultural Diego

the scholarly parking

builders The

of Angeles,

parking plaza This

of an which concrete

unique

precast/prestressed lies and tram article

new facility challenges this Freeway

aerial concrete

was transporting the complex guideway of structure alongside outside administration

of

of

combined research guideway rapidly San cultural of

people-mover view

J.

of the played will

the

devised.

structure a

California),

challenges

presents (Interstate Fernando 1080

Paul dedicated the the

project. feature of next transports

fabrication, structure

guide library, Interstate property, PCI near the a new

for m came

project. prominent to

visitors JOURNAL of (3535 tramway

Getty the the the 405). I. Valley

up

with The

way to scien

The

the visi Paul sup new city San 405 and the

to

in ft)

a a J. r’ ,

geles, the and people Malibu. cated derground Center plaza the lenge beautifully resulted extremely one new overlooking Fig.

dential also May-June

The

The

San existing

the

1.

service

museum

located

on

California

of

The

of

new

site

area

from

presented

Los

Diego in

the

the 1995

The

moving

with

Getty

has restrictions

parking

steep

museum

of

Angeles road the

Pacific

in museum

an Getty

atop

West location

the

limited Freeway

a

Los

entry

(see

Center

and

secluded,

grades.

the

site.

a

an

Center

Coast

Angeles Los

structure

large

will basin

Fig.

adjacent

a

at

logistical

point

on

access

Tram

fire

Angeles. of

to

the

2).

complement

construction

Highway

The

number in

and

the the

quiet

road

at

basin.

Villa

Los

guideway —

next

hillside

an

arrival site

to Getty

chal

resi only This with

An

un

the

lo

of

to

in

is

winds

confronting cided activities configurations. museum would cut, guideway itors conditions, appearance, Systems system driven, supplier.

SYSTEM

After The

up

was

from

the

be Otis

that

air-cushion suppliers

a

Inc.

on

chosen

The and

needed

Southern

aesthetics, competition

contract the

and

a

a

them, -

of pollution-free

dedicated

on

PROCUREMENT

people-mover

Otis

parking

low

Farmington,

With

as

people-mover

that

to

the

supported

system

the California

was

shuttle noise,

vehicle

included

these

Getty

among

vehicle

guideway.

garage a

design-build

Otis

uses

Center

operating

Connecti problems

Trust

and

vehicles.

hillside

system pricing,

vehicle -

Transit

system

system

to

cable-

train

vis

de

the

along

cles, contract Dinwiddie (DCCo). With to BERGER/ABAM guideway tract Federal select the

operate lane pass

the

The

DCCo;

guideway

THE

San

subsystems,

with

section.

the

the

tram

shortlist

Way, in

Diego

Otis

with

guideway

design,

a

DCCo

PEOPLE-MOVER

added

a

system double-lane

Construction fr.

SYSTEM

shuttle

Two

structure.

was

the

Washington,

Freeway,

of

and

would

Otis

to %

project

responsibility

separate

qualified

Engineers

guideway 4

construction

provide

configuration

guideway

contracted

off-center and

then

contractor,

Company

trains

to

blends

the

bidders.

is

subcon

Inc.

design

design

single

vehi

with

to

will

by

on

of

of in 25

a the

tached type along Museum cable support Fig. weight) machine 26 3,

a

guideway.

3.

geared

cable

the

will

Schematic

sheave to

is

room Station.

length 0

located

be

a

tension Miles

drive

drive

driven

Each

outside

network.

of 4

of

As

system

at

the

the

cable

device illustrated

train

the

by

guideway

cable

and

In

entry an

located North

will

supported

turn,

under

elevator-

(tension

drive

in station

be

each

by

in

Fig.

system.

the

at

a a Tension

just

trolled the chine cated 3. module long

8.8 Weight

The

Each

cable

m

outside

and

in

room.

(29

by shuttle

vehicles,

a

train

drive

control

computerized will

ft).

of

A

Vehicles the

will

operation

system

consist

schematic

each room

station

be

is

with

27.4

next

of

will

equipment

shown

area.

will

three,

drawing

a

to be

m

length

be

the

2.24

(90

in

two-

con

Fig.

ma

lo

ft)

of

of

m

high. (7

93 seated tated tion Site challenges the road side. cilitate scar visual views conditions ment from horizontal side follows tical from The long proaching museum supported

is tinuous tions, is is 1080 guideway over

without Vehicle supported on ports control for guideway cle quired for slab

trains support

THE

Site

The ft

This

divided The 26 per 20

a

guideway

4 system. the maintaining the and

aerial of

Conditions grade

that flanked

It

38

smooth

m the that

m m 13 consisting and

Vehicle from

in.)

three-vehicle

the

and

the

total

conditions

guideway

the construction was impact

on

to 800

units.

(3535 a

natural GUIDEWAY

to

drive columns. (86 (63

the

design.

m at

parking

wound

System

subsystems.

profile

wide

guideway interface

the guide into

vertical produced on

directly structure guideway of

305

the

radii

San 17

the

the

is

grade with

(42

m also

numerous length ft).

ft);

Supports

by

7.2 “flying”

the

two

The

supported ft). standing

cable,

(2580

parallel 9 station hillside

guideway, m

Diego

and capacity vegetation

of

ft) At

either

maximum

of The important

four- the

up of rail, percent

with a

guideway

garage (125

The

supports

passenger

beam

average

Interfaces on

the

tall. some

horizontal

train.

of

sidewalls with

curvature

imposed 2.90

is nine

the and a

lateral

construction

ft)

Getty superstructure

power

guideway

sheave is surface for

drilled Freeway. at-grade

rise 800

to

an

the rope

to

on

per

guideway

to At

hillside

64 long

DESIGN minimize

A

the m

(see

station

locations, six-span

sections

curves,

1000

average

on

PCI

a the

will

in

tramway m on

span the brackets

span

to

the

other

m (9

configura vehicle

sheaves

position Trust

guidebeam U-shaped

stations.

Otis

rails,

elevation

columns pier Fig. (2580

JOURNAL

opposite

structure

position

the

supports and

(210

ft unique varying

was

ft),

or

bottom

access vehicle

be

These

length length

align

to 6 to

loca with

vehi pile-

hill

con 4).

dic caps

ver

in.) that sup

not

ap

the and

the fa

ft). 14 on the

or re

ft)

re

is

of is to necessary elements to interface with the Otis vehicle system as structural elements. Added structure beneath the supporting slab would generally be ( eliminated. North In the bypass area, a struc ture to stiffen the cross section would be added beneath the supporting slab. Alternative C — Precast concrete L-beams spanning from column to column with a cast-in-place connect ing slab to form the above U-section. Precast concrete stem beams extend Road ing below the supporting slab would be used in the bypass area. Precast Fig. 4. The site plan. concrete beam components would be designed to support the weight of the connecting slab and associated form- work and construction loads without auxiliary supports. This alternative minimized the amount of cast-in-place shoring and minimized the pick weights of precast concrete elements. Alternative C was chosen by the Getty Trust, the project architect, and the project contractor because of cost, aesthetics, and constructability factors.

Design Criteria The site Guiderail Support for the guideway was within the jurisdiction of the City of , so the Los Angeles De Sheave Support partment of Building and Safety was the approving authority. Early discus sions with the Department of Building Air and Safety indicated that the Depart Cushion ment would be comparing the design for the guideway with the Los Angeles Rope Sheaves Uniform Building Code (LAUBC). Power Rail Post The concerns of the Department cen tered on the seismic design of the Concrete Beam or Pavement guideway structure. This review process presented a Fig. 5. The guideway/vehicle system interfaces. dilemma to the design team because the guideway structure was more like a bridge than a building. The LAUBC quired to guide the propulsion cable way cross sections included those sec grouped this type of structure into the around numerous turns, and the power tions shown in Fig. 6. category of “Other” structures. Guide- rail for supplying electric power to the Alternative A — Precast concrete way design engineers thought it was operating vehicles are secured to the double tees spanning column to col essential to introduce the latest re guideway sidewalls and supporting umn. The stems of these double tees search regarding bridge seismic be slab (see Fig. 5). would be straight; the flanges of the havior and safety into the design of double tees would be curved to make this structure. Therefore, prior to be curved guideway sections. The side- ginning the final design process, a Preliminary Design walls and flying surface would be cast- Getty Center People-Mover Guideway The guideway designer’s initial ef in-place concrete. Multiple double tees Structural Design Specification was fort was to develop alternative guide- would be used in the bypass area. submitted to the Department for ap way cross sections that would meet Alternative B — Cast-in-place U- proval as an acceptable analysis! project design criteria. Alternate guide- section. This section would use the design method. This specification

May-June 1995 27 combined provisions of the LAUBC and California Department of Trans portation (CALTRANS) Bridge De Cast-In-Place Cast-In-Place sign Specification. FlyingSurface Slab Sidewall Seismic design provisions of the Structural Design Specification stated / the following: • Internal seismic forces would be computed using response spectrum analysis methods. • A site-specific response spectra would be used with a return period of 1000 years. A two-thirds vertical Alternative A response would also be imposed on the structure. of the CALTRANS • Design methods Cast-In-Place Bridge Design Specification would FlyingSurface Slab Cast-In-Place used for reinforced and precast be Beam concrete components. The CAL- TRANS methods for seismic design of reinforced concrete components use ultimate loads and ultimate B component design capacities. Alternative • A minimum design base shear force would also be imposed on guideway columns. This minimum force would Cast-In-Place based be computed per the LAUBC, FlyingSurface Slab on rules for “Other” structures in the code. • Effects of vehicle live load would be scaled from results of response spec trum analysis with only dead load mass to account for the added mass. Alternative C This was done because the vehicle will be “secured” to the guideway. Fig. 6. Alternate cross sections considered in designing the guideway structure.

Superstructure Design The single-lane tram guideway su beams were used, depending on the tern to transfer dead load from the perstructure was made from two L overall structure width. Typically, the simple-span, precast concrete ele shaped precast, prestressed concrete single-lane guideway is 4.62 m (15 ft ments to continuous span composite web beams connected with a cast-in- 2 in.) wide and 1.17m (3 ft 10 in.) high. beams. Full-span-length precast con place slab. Web beams were designed The guideway widens to 6.20 m (20 ft crete elements were erected; shores to support the weight of the slab and 4 in.) in the bypass area (see Fig. 7). were installed to just contact the bot its formwork. Web beams were pre Spliced girder construction was tom of these elements. Decks and clo stressed at the plant to support their used in the design to extend the span sure pours between elements were own weight and simple-span applied length of the 1.17 m (3 ft 10 in.) deep cast. Touch shores were removed after loads. channel section to 26 m (86 ft) over a the spans were integrated into continu The guideway design specified that slide area along the tram alignment. ous span units. W30 beams would be used to tie the Two adjacent beam elements were Inserts to support the vehicle guide precast concrete web beams together erected on a shore tower, joined with posts and supports for the rope during casting of the connecting slab. a cast-in-place closure pour. The ele sheaves were cast directly into pre Spans were later post-tensioned into ments were then post-tensioned in the cast concrete L-beams. Over 10,000 four- to six-span continuous structure field to make up the 26 m (86 ft) span. threaded inserts were to be cast into units. The shore tower was removed after these precast concrete components to a Flanged rectangular precast concrete the span was integrated into a contin tolerance of 3 mm (‘/8 in.). The design stem beams, extending below the slab, uous span unit. required formwork adjustments to off were used to stiffen the superstructure Three other long bypass spans were set predicted deflections and cambers in the bypass area. One or two stem designed to use a touch shoring sys as small as 12 mm (1/2 in.).

28 PCI JOURNAL Substructure Design The guideway substructure gener Precast Webs ally consists of 1.07 m (3 ft 6 in.) Cast-In-Place diameter round columns supported on FlyingSurface Slab”\ 1.22 m (4 ft) diameter shafts. The columns support a cross-head element to absorb shear forces from precast Cast-In-PlaceSlab concrete web beam superstructure ele ments (see Fig. 8). The shaft and col Single-Lane Section umn use a common reinforcing steel cage to achieve ductility requirements with a minimum amount of reinforcing Precast Webs

steel. Foundation shafts are generally Cast-in-Place designed to resist horizontal shear and FlyingSwlace Slab moment forces associated with hinging (yielding) of the base column section. In the bypass area, dual columns and shafts are used. These columns are Cast-In-PlaceSlab connected with a cross-head element to transfer shears from precast con Bypass-Area Section crete L and stem beams to supporting columns. Careful attention was paid Fig. 7. Cross section of the superstructure. during the design phase to the ductility requirements of the joints between cross-heads and columns. Site Logistics and Planning In areas where the guideway is sup The site conditions were the major ported close to the ground without factor driving construction sequences columns, multiple shafts are used. Shaft and methods. The guideway alignment moments and shears were designed to roughly follows the contours of a resist the maximum elastic seismic steep hillside, passing over several en shears and moments from response vironmentally sensitive areas that spectrum analysis. The guideway super could not be disrupted by construction structure is connected to the substruc activities. While the vertical gradient ture through bearings and large steel bar of the guideway along its final path of lugs that were cast directly into the travel is approximately a constant 7 cross-head elements (see Fig. 9). percent, the slopes and cross slopes of The completed tram. guideway the hillside at the foundations are as structure survived the January 17, steep as 1:1 in some locations. Creat 1994, 6.8 magnitude Northridge earth ing access for drilling 1.22 m (48 in.) quake without damage (see Fig. 10). diameter-deep caissons and erecting During the earthquake, measured hori large precast concrete elements was of zontal accelerations within 20 miles primary importance. (32 km) of the epicenter ranged from A series of narrow access roads was 0.24g to 1.82g. The Getty site is 10 planned to provide access for caisson miles (16 km) from the epicenter of drilling. These roads were limited to Fig. 8. Typical guideway substructure. the earthquake. areas where partial canyon fills were already planned; hence, regrading and THE GUIDEWAY revegetation after construction was a ments from the nearby parallel perma feasible alternative. It was not possi nent roadway had several drawbacks. CONSTRUCTION ble, however, to construct a road wide This road was the only access to the Initial guideway construction docu enough to allow a suitable erection top of the hill where the main building ments were issued to a select shortlist crane to travel around cross-heads that construction was underway. Constant, of qualified bidders in the summer of topped support columns. Several sec heavy construction traffic needed to be 1992. Final guideway construction tions of the alignment were over sensi maintained almost the entire day. Only documents were bid in September and tive areas that could not be disturbed brief time windows were available to October 1992. A. T. Curd Construc with access roads, so all construction block this road with precast component tors of Glendale, California, was se had to be reached over the top with erection activities. Also, the size and lected to be the guideway construction large cranes. number of erection cranes required subcontractor. Erection of precast concrete ele would be significantly larger if erec

May-June1995 29 transfer superstructure tion place Fig. cision lem cast quested elements. cross-head use ments. passed the cross-heads support stead general (see guideway sequencing way to guideway 30

The

The

2. 3. 4. 5. 1.

the

beams

a

9.

took was

concrete

in

The The The The The

Fig.

narrow

cross-heads of

entry

Multiple key

to

guideway

the This

earthquake

columns

by

areas

that

the

cast-in-place place

convert

on-grade The on-grade

first 14

last at

at

(see

bypass to

11).

design

in

the

station

guideway

the

the allowed

were

access

spans the

solving

cross-head

the

for to

guideway

steel

from

Fig.

11

16

support

After uphill downhill

this

for

was

designer

following

the

overall

area

to

erected

spans to

spans

shear

guideway guideway

of

12).

lugs

road the

the

pier.

the

precast

divided provide

the

original

contractor’s end

elevated cross-head

the

main

erection

and

contractor

alongside column,

contractor

forces end elements access

of construction

of

modify just

crane

order:

bearings

road.

elevated

elevated

concrete

into

between adjacent for

cast-in-

before

guide-

from

prob

crane

pre

had ele

five

de

the the

the

re in

to

the

were

guideway

the

roads. station road, Column struction Foundation road for the series tions crane large Special plished cent road ticipated. much ers. and quired spent were

required

Work

Deep

south

crane

slopes rock The

gradients.

areas construction.

in

coring of

more enough cleaned needed

of

These

long

outrigger

with

most caisson

the

at

bottoms

to

Construction

cutting

short

abutment

There

travel

required of

the

difficult

at

through

access

continuous

conventional

and

roads

areas the

to

flat

the

out

spurs

site

drilling

set

buckets.

pads was

without of

Drilling

temporary

area.

points

by

shoring

roads only

than

were fractured all began

up. and

alignment. earthquake

Fig.

off

significant

were

hand.

of

A

casings

originally wide the followed Several 10.

of Drilling

earth had

generally

the outriggers. was

where

few

with to

created

Nine

the

museum

rock

This

caissons

create

20 enough

access

accom

The

augers

of

(January

main

to

con

time

horizontal sec

per

was

lay

the

the the

an

re

on

structure

be

a

a

17,

installed had ing cessed Drilling access vating A was from a drilling was access

holes cages continuous hole 24 ied depths cages sulting tion 30 space

curves

special

Five

Continuous

A

small survived

1994)

m m

cleanout

up

to

suspended

impossible.

was

critical

to

a

restrictions (100

(80

roads (see

these

be

were

were to

large

caisson

road

location.

top reinforcing only

ranged

with

temporarily make

remote-operated

without

long

orientation

transported

13

ft)

the

ft) Fig.

of

during

shafts, aspect

fabricated

truck operations.

m

from installed

directly

and by

conventional

reach

long. the up

spiral-tied

nearby over

(42 locations

up

Instead

damage.

14).

foot

the

on

column

crane

cross-head.

the drilling.

of

the ft).

to

cages

drilling

the

All

in

site. of

up

guideway

The

the

uphill

Northridge

(see

approximately Some contractor in

bottom

each

off-site

the

side

These

located of

of

and

could

cage

PCI

diesel

the

heights

were

reinforcing cages

hand

the

equipment

vertical

apparatus.

Fig.

of

down hole

from

of

JOURNAL

cleaned

Caisson

installa

casings

caisson the

be

of

due the

on

nearly

auger

exca

were

used

13). dur

var

hill

ac the the the

the

re

re

to had truding May-June cross-head, cage inforcing erection. cross-heads Fig. to 11. was be above The 1995 continuous in bar the erection atop the the pattern. reinforcing correct the top crane to columns. of the Because pattern. the - was top bar caissons A able of precast pro The the the to back .,“-, concrete forcing imuth above pattern zontal out a orientation; ground location narrower cross-head 7. had bar, to as level, be much and access in the is at being the had as top the road 13 correct to of correct rigged m be without the (42 at hori rein for the az ft) for the inforcing and cranes 225-t were the Several (180 accomplished chitectural production. means

the scale Superstructure These

columns currently Cross-head cast-in-place beams these tom tion common were as two larger strength sleeves bars. and into included set heads ing alignment each bar forms. using rication son/column used caisson much correct Special Precast A At The The the cross-heads. a precast columns. of web significant alignment columns. template into of matches erected matched the ton) some mock-up These special column (250 poured pile (see and locations, beam working cross-heads vertical tighter 1.07 typical the columns were A elevation. construction, picks, in and cross-head cross-heads. and grout. the lifting were 16 concrete bar conventional methods of special manufacturing caps Fig. locations, each guideway ton) with details The dowels m cages. elements Most on stem double vertical pile each the

precast and installation supported form These was because sleeves than that of set reinforcing corrugated contribution (42 15). however, together. with were area. frames the crane At filled mock-up elevation

the Construction were caps the precast The beams vertical when of double used were (see was in.) erection to matched and normal the piece. station templates had the cross-head, the constructed (see #9, a so to concrete ensure were or tolerances cast-in-place After at they Fig. were diameter constructed single bypass with cast construction prevent on the truck terrain supported to the erection Cross-heads followed yard directly both grade #10, verified sleeves Fig. of required dowel reinforcing bar of guideway was ahead, be for the 17). contractor followed up grouted, shared columns required the in erection accurate the prior a for aligned pattern crane. or 16). of drilled a eleva with 160-t cross- top areas, level. them place these high pass con full- cais was steel were bot the cast #11 fab re on ar 31 on by to in In a of a a Fig.

from over

center curvatures Fig. The the ing component sulted from matically curvature without lateral 32

Special

crane

points. 13.

14.

30

frames

rolling the

of in

clamps

Some

Reinforcing m

readjustment

connection the

gravity

cross

(lOOft)

compensate

heavy

of

The

conditions

being

were

many

center column

over.

were

lifting

section

diagonal

of

long.

configured

located

steel

of

The

also the

of

point

(see

locations

the

frames

for

gravity

encountered available

cages of

fabricated lengths

Fig.

elements

outside to

braces

any

the

be

to

allowed

18).

were

for

of beam. of

offset

auto

and

lift drilled

and

the

the the

re

only

to

accessible

shaft

transmit precast head. 0.76 beams in erected, ment After agonal correct hardware and

Other

the

foundations

used

m

installation

with

transverse After

served

(30

concrete

braces

horizontal

they

again special the

by

was

in.)

each

foot.

two

torsional

were

to

deep,

on devised could

and

beam

hold direction.

erection of

other

the

parallel

and

the tied

columns

wide

next

then

the end

force

by

web

vertical

(see

together

flange

span. web

and to

be

the

These webs

beams,

were the

Fig.

from

removed

contrac

bracing pairs

beams

align cross-

were

large

with

19).

the

di

in

prior bearings tor place downhill bearing physical

crete cross-heads. also concrete cross-heads

closures deck and tached strainer ements.

multispan groups tensioned

cross 22). guideway; cast-in-place cast

the elements, crete Flying this air-supported ances

wear affect tolerance

percent about face cally site, culty

the and the gether

installation, vised and ances as-built of

surface

The

The

There

Concrete

to

the

precast

desired

curves. required

concrete.

fixed

surface

measurement

is where

a The to

life

was

webs

closures. keep in flying

correct section

for formwork

to entire to flying

a

superflat

with

of a the the pads

lugs

Surface

connection grade,

and

was After

measurements

included

sections overlap

defining measuring

in helix,

the

of

be

flatwork was

is together

individual on-grade

smoothness

bridge

supported

however,

bearings

concrete

vehicle ability the

There surface. and by the

the

the and (see

topped steel

used

successful analyzed and

precast

The

guideway, are

because

surface. placement concrete

surface

vehicle

shape

the

matching

and

considerable

not

cast-in-place

air-cushion

vehicle longitudinal

beams

cast-in-place

Figs. Temporary

floor

stems above

critical support

were

for

lugs

Construction

the ends

to

the

structures

was decks

at

a where

methods to

by

to to

The

scheme

concrete

flat control

was

ride of

guideway such

the

spans

the

glides.

proper

upon and form the permanent

20

through the

by

rather

joined consultant,

and

from a the

also

achieve

due

of

system

from

the

the

including

had

plane,

superfiat

contractor,

on because sidewalls and shelves were

cast-in-place placed the

the

precast

hangers

data, quality

a

PCI

the

lateral

permanent

flatness

pads.

to were

a

demanding top flying some

which

an

to the

the

The

tolerances direction

minimal and

(see than closures;

geometri

21).

beam elevated

vertical series

over

moving JOURNAL concern concrete a

cast-in-

precast

placed,

supplier in

existing achieve

and

number

of

quality

on

has

flying

high-

were

toler post-

slide

toler

con

all

diffi

both

con

Fig. they

pre

took

and

sur

re the the

the are

at

el

for a

de

to of

of

a

7 of special quality control measures. These measures included tight control of the concrete mix proportions and timing of deliveries, high precision formwork measuring and leveling tools, special wet finishing techniques, prompt and thorough wet curing, and immediate measurement and reporting of results so daily corrections could be made (see Figs. 23 and 24).

PRECAST CONCRETE FABRICATION The structural solution to the design challenges was largely due to the effi cient use of precast concrete compo nents. In total, 134 components were used as follows: • L-shaped web beams • Flanged rectangular stem beams • Single-lane cross-heads • Bypass single column cross-heads Fig. 15. Precise jigs were used to ensure that reinforcing steel protruding from the • Bypass dual column cross-heads tops of cast-in-place concrete columns aligned properly with mating sleeves in Table 1 shows the shape, number precast concrete cross-heads. and principal dimensions of the pre cast concrete components.

Precast Concrete Cross-heads As previously noted, a key concept in solving this project’s construction difficulties was casting the precast concrete cross-heads. Typical precast cross-heads were 4.67 m (15 ft 4 in.) wide and weighed 140 kN (31,000 ibs); bypass cross-heads measured up to 7.82 m (25 ft 8 in.) and weighed 350 kN (80,000 lbs). Forming cross- heads was straightforward, using stan dard steel forms similar to those used for cast-in-place cross-heads on top of the columns. Tying the reinforcing bars was more complicated because the ductility requirements called for a series of closed, interlocking, progres sively tapered welded loops requiring a systematic placement sequence that took a few tries to figure out. The real challenge, however, and the key to the successful use of the precast concrete cross-heads was the templating system devised to ensure that they would meet with a cast-in- place column in the field. The connec tion detail was designed to fit the cross-head over the extended column Fig. 16. At some locations, the guideway profile was nearly at ground level. vertical steel, 16 bars in a 0.9 m (3 ft) At these locations, the guideway superstructure was supported directly on diameter circle. cast-in-place pile caps.

May-June1995 33 Table 1. Breakdown of precast and prestressed concrete components used in tram guideway.

Flanged rectangular stem beams: 19 components Minimum length — 13.9 iii (45 ft 6 in.) Maximum length— 21.5 rn (70 ft 6 in.)

L-shaped precast prestressed web beams: 84 components Minimum length — 13.9 m (45 ft 6 in.) Maximum length —22.1 m (72 ft 6 in.)

2-4”

15-4”

Single-lane cross-heads: 19 components Width of cross-head — 1.5 m (5 ft)

Varies 15-4” to 19-8-1/2” Ii

j Bypass single-column c9 cross-heads: 7 components 9 Width of cross-head — 1.5 m (5 ft) C.,

Pocket forStemBeam

Bypass dual-column cross-heads: 5 components Width of cross-head — 1.5 m (5 ft)

Varies 22-2 to 25-8

Poet or Stem Beam

34 PCI JOURNAL In order to clear cross-head reinforc ing, sleeves were limited to 40 mm (1.5 in.) diameter corrugated tubes for #11 bars, leaving very little clearance per sleeve. The fabricator of the mis cellaneous metal components devised a precise jig that remained in his shop. All templates for the project, both I field and shop, were made against that master template to guard against pro gressive creep in dimensions. For the cross-heads, a template in the form’s baseplate matched the in side diameter of the corrugated sleeves. A similar template at the top, with “handles” that would support it from the form sides, aligned the sleeves vertically and in plan. PVC pipes inside the corrugated sleeves acted as stiffeners. In the field, all Fig. 17. Prior to production, a full-scale mock-up was constructed at the precast cross-heads fit and aligned correctly. manufacturing yard.

Precast Concrete Web and Stem Beams The L-shaped precast concrete beam sections, or webs, ranged from 11.6 to 22.0 m (38 to 72 ft 4 in.) long, with corresponding weights of 132 to 250 kN (29,500 to 55,800 lbs). Geometry was complex, as even an 11.6 m (38 ft) beam might include a tangent, spi ral, and constant radius alignment. Ra diuses were 64, 69, 75, and 305 m (210, 225, 245, and 1000 ft) each with spiral transitions into and out of the tangent or straight sections. The necessary alignment came from a profile grade line (PGL) at the center of the flying surface. In two locations, the PGL also required a vertical curve (VC). The design allowed the webs to “chord” between cross-heads and com pensate for the VC with the cast-in- place flying surface. The embedments, Fig. 18. Special liftingframes were fabricated to allow picking outside the center of however, to follow the PGL, needed the web beam cross section. which meant that at these two loca tions, embedments were not a constant height relative to the web section. could be used in the plant for form plywood sub-base and 13 mm (‘/2 in.) Web form layout was clearly a layout and control. high density overlay (HDO) plywood major challenge. The entire structure The forms had to be able to twist to were laid down for the casting surface. was drawn in three dimensions using match the required shape. The form Setting the table was a two-step pro AutoCAD 12.0. The individual beam pallet was built with 0.6 m (2 ft) on cess. First, each double channel was sections were cut out on the computer, center back-to-back channels 2.4 m (8 “aimed” at the center of curvature by and rotated into a horizontal, casting ft) long resting on screw jacks set into sliding the screw jacks perpendicular position, which resulted in a twisted a longitudinal track (see Fig. 9). To to the channels. Thus, for example at shape relative to the beam centerpoint. make a flexible base over the double the outside of a curve, the center-to- Horizontal and vertical offsets were channels, flat 0.6 x 1.8 m (2 x 6 ft) center dimension might be 620 mm then calculated from control lines that timber sleepers with a 19 mm (3/4 in.) (2.034 ft) and the inside 595 mm

May-June1995 35 erection. justed Fig. be minus 36 drawing (1.952 plus 19. vertically ft). 4 W30 4 had mm mm Screw steel these (0.013 (0.013 so jacks sections that dimensions ft) ft). one were and were Each end the then calcu used might other shop ad to tie radial beams could lated level the web in approach. be and set beams tabular done the vertical correct with securely form, This adjustment a warp simple combination so together to that the tape layout pallet. of after and the of building of 0.6 flat 26). flect ated enough sheathed curately. beam down to ‘/2 form lengths, the embedments of sequence through blies layout production sides, zontal a cleaned and forcing They form area. stripping ping stressing. to at inforcing reconfigured and tied ble. and placement then lowing embedments, would fore place, post-tensioning first tensioning Beam The small Two The all the in.) glued After go 6 x exact, became a 0.6 Side the yarding between They a.m. cage, crew could components, reconfigurations. stage, the setting 1.8 buttoned-up to home There would sides flexible so twisting and HDO 90-degree differences the cleaned to forms the thus to stressing stripping day’s steel a any and x with sides oversize complete m and was forms, end follow At bar and vertical beams went tight series Meanwhile, would the minimize cycle the be 1.8 were double by (2 area. simple-span plywood. be the was and necessary a oiled, the consisted if supports screwed be developed crew form were and in shifted 19 of next x pallet lunchtime. handling cages. beam post-tensioning “poured m necessary, were over form eight-hole concrete curves 6 subcontractor reinforcing always like started of same the were ready sufficient heads the frames and crew, curves. then sorted Every caused ft) (2 checked channels holes embedment the morning. that would and built. 90-degree to below. minor design the into to timber pallet shift. x controlled Again, 13 The but sent plywood time, forms, pre-tie the Templates dry of and where out” would the pulling at 6 by cope ready perpendicular for in placing without Monday, post-tension- mm were in pallet, PCI by The plates the ft) then was 3 set other pattern form to curves finish a mild and spirals details so form The A bar would and the a.m. concrete the (see to the JOURNAL database this with the the (3/4 planks applica that the storage not located frames casting for typical assem did bolted limber the major ducts, forms allow crews ready form, crew. form were strip hori over rein form crew with post- with Fig. pre cre took was and pre and de fol ac the for the the by be set the the re be Fig. 22. After__._Jprecast concrete beams were erected, closure pours were cast to make the precast units into four- to six-span continuous beam units. w

Fig. 21. Stem beams in the bypass area were set into notches cast into the precast concrete cross-heads. CONCLUDING REMARKS The J. Paul Getty Trust is construct ing and grouting, in the yard. This the deck, the tolerances were less chal ing a world-class art facility and is de schedule allowed the weekend cure lenging than the webs. A similar bed manding the highest quality in design even on Friday’s casting, met early system was used (see Fig. 25). and construction. The tramway ride strength requirements without overly In all, over 500 shop drawings were quality, passenger comfort, and dura aggressive mix designs and heating prepared to detail the 134 precast con bility were important requirements systems, and gave the post-tensioning crete components. Putting the effort that necessitated the complex design and close tolerances. subcontractor at least five beams for a into details, especially into a simpli full day’s work cycle. The balance of fied layout system, paid dividends in The construction of the Getty Cen the prestressing was done in the field. the production cycle and achieved ter guideway was a model of cooper The small “T” beams that supported good dimensional tolerances. No in ation between owner, designers, and the deck at the wide, bypass locations serts cast directly into the precast con builders. Direct lines of communica were dubbed “stems.” Although of crete units had to be reworked because tion were established early to facili complex shape, as these poured into of out-of-tolerance positioning. tate a response to questions and to ensure that design intent was being followed and that guideway require ments for the vehicle system were being achieved. Use of precast, prestressed concrete made the construction feasible and cost effective. The resulting finished product is a graceful and dramatic structure suspended along the hillside that will provide an exciting, wel coming experience for visitors to the J. Paul Getty Museum. The project won an award in the 1994 PCI Design Awards Program. The citation of the jury read: “This project really fits the site and environ mental conditions, and through the in novative use of precast/prestressed concrete elements provides an ex tremely efficient solution to a difficult transportation problem.” It is expected that the people-mover tramway system (see Fig. 27) will be Reinforcing steel placed in the flying surface at the Entry operational by the end of 1995.

May-June1995 37 Fig. 25. Two stem beams in the storage yard are ready for Fig. 26. - b beam forms were made from plywood secured transport to the site. Precast concrete beams were post- to a series of 90-degree timber frames. Side forms were flat tensioned in the yard to carry their own weight and planks sheathed with plywood, thus creating a flexible yet construction loads. not too rigid form.

38 PCIJOURNAL Fig. 27. Panoramic view of guideway project nearing completion.

CREDITS Owner: The J. Paul Getty Trust, Santa People-Mover System Contractor: Guideway Designer: BERGERJABAM Monica, California Otis Transit Systems, Inc., Farming- Engineers Inc., Federal Way, ton, Connecticut Washington Getty Center Project Contractor: Din Tram Guideway Contractor: A. T. widdie Construction Company, Los Curd Constructors, Inc., Glendale, Aerial Photography: Warren Aerial Angeles, California California Photography Inc. Getty Center Project Architect: Precast Concrete Manufacturer: The Richard Meier & Partners Archi Niobrara River Company, Rialto, Other Photography: Construction Doc tects, Los Angeles, California California umentation Services, Inc.

May-June 1995 39