Resettlement External Monitoring Report
#7 June–December 2018 January 2019
People’s Republic of China: Chongqing Urban–Rural Infrastructure Development Demonstration II Project — Resettlement External Monitoring Report (No. 7)
Prepared by the Halcrow (Chongqing) Engineering Consulting Co. Ltd. for the People’s Republic of China and the Asian Development Bank.
This resettlement external monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature.
In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
ADB-Financed Chongqing Urban–Rural Infrastructure Development Demonstration Project II
Resettlement External Monitoring Report (No. 7)
(Jun 2018---Dec 2018)
Halcrow (Chongqing) Engineering Consulting Co. Ltd. Jan 2019
I
Contents Contents ...... II 1. Introduction ...... 1 1.1 Brief Introduction of the Project ...... 1 1.2 General Resettlement Action Plan ...... 1 1.3 Overall Implementation Progress...... 2 2. Status of Compensation ...... 6 2.1 Rongchang RongFeng River Comprehensive Flood Control Subproject ...... 9 2.2 Fuling Urban and Rural Road Network Reconstruction Project ...... 9 2.2.1 Permanent Land Acquisition Impacts ...... 9 2.2.2 Payment Status of Resettlement Compensation ...... 10 2.2.3 Compensation of LA and HD ...... 12 2.2.4 Enterprises Demolition Impacts ...... 13 2.3 Wanzhou Water Supply Subproject ...... 14 2.4 Chengkou County Urban and Rural Road Reconstruction Project ...... 14 2.4.1 Project Impacts ...... 14 2.4.2 Implementation Progress of project ...... 14 2.4.3 Compensation of LA and HD ...... 14 2.4.4 Payment Status of Resettlement Fund...... 23 2.4.6 Ground Attachments Impacts ...... 30 2.5 Wulong River Flood Control Project ...... 30 2.5.1 Project Impacts ...... 30 2.5.2 Payment Status of Resettlement Fund...... 30 2.5.3 Compensation of LA and HD ...... 30 2.5.4 House Demolition Impacts ...... 31 2.5.5 Companies Demolition Impacts ...... 31 2.6 Shizhu County Urban and Rural Road Network Reconstruction Project ...... 32 2.6.1 Project Impacts ...... 32 2.6.2 Payment Status of Resettlement Fund...... 33 2.6.3 Implementation Progress of project ...... 33 2.6.4 Compensation of LA and HD ...... 33 2.6.5 House Demolition Impacts ...... 34
II
2.7 Evaluation and Conclusion ...... 34 2.8 Recommendations ...... 35 3. Urbanization of APs ...... 35 3.1 Rongchang RongFeng River Flood Control Comprehensive Renovation ...... 36 3.1.1 Rongchang Vulnerable Groups Case ...... 36 3.2 Fuling Urban and Rural Road Network Reconstruction Project ...... 37 3.3 Wanzhou Water Supply Subprojects ...... 38 3.4 Chengkou County Urban and Rural Road Reconstruction Project ...... 38 3.4.1 Non-agricultural Progress ...... 38 3.4.2 Vulnerable Group Case Studies ...... 38 3.5 Wulong River Flood Control Project ...... 39 3.6 Shizhu County Urban and Rural Road Network Reconstruction Project ...... 41 3.6.1 Non-agricultural Progress ...... 41 3.6.2 Vulnerable Group Case Studies(Tujia minority) ...... 41 3.7 Evaluation and Conclusion ...... 42 3.8 Recommendations ...... 43 4. Use of Compensation Payments and Subsidies ...... 44 4.1 Fuling Urban and Rural Road Network Reconstruction Project ...... 44 4.2 Shizhu County Urban and Rural Road Network Reconstruction Project ...... 44 4.3 Evaluation and Conclusion ...... 44 4.4 Recommendations ...... 44 5. Skills Training, Job Creation and Other Income Restoration Measures ...... 46 5.1 Participation of the Construction Works ...... 46 5.2 Job skills training for local laborers ...... 47 5.3 Evaluation and Conclusion ...... 48 5.4 Recommendations ...... 48 6. Public Participation, Complaint Handling ...... 50 6.1 Public Participation ...... 50 6.2 Complaints and Grievances ...... 55 6.3 Report and Handling of Complaints ...... 55 6.4 Evaluation and Conclusion ...... 60 6.5 Recommendations ...... 60 III
7. Sample HH in Survey ...... 62 7.1 Scope of the Survey ...... 62 7.2 Household Demographics ...... 62 7.3 Annual Household Income...... 62 7.5 Ethnic Distribution ...... 63 7.6 Education Background ...... 63 7.7 Religious Beliefs and Language and Culture ...... 63 8. Plans for the Next Monitoring Period ...... 64 8.1 Changes of Project Scopes and LAR Impacts ...... 64 8.2 Progress of Project Resettlement Implementation ...... 64 8.3 Recommendations ...... 65 8.3.1 Urging all IAs, LAR Officer and Village Leaders to Speed up Compensation to Individual AP...... 65 8.3.2 More Efforts on the Progress of Transferring from Agriculture and Non-agriculture to Ensure the Interest of APs...... 65 8.3.3 Paying More Attention on Vulnerable Groups and Increasing Support for Them ...... 65 8.3.4 The IAs of all districts and counties should confirm the data of land acquisition, demolition and compensation timely ...... 65 Annex 1: List of Persons Met based on Interviews, Meetings, FGDs ...... 66
IV
1. Introduction
1.1 Brief Introduction of the Project
Asia Development Bank (ADB) financed Chongqing Urban-Rural Infrastructure Development Demonstration Project II aims to attain socially inclusive and economically balanced growth by integrating urban and rural development in Chongqing. Given its imbalanced urban and rural growth which resulted in socioeconomic development gaps, the project will selectively enhance development potentials of small and medium sized cities and villages through: (i) Economically and environmentally sustainable water sector reform; (ii) Urban flood risk management for various river sizes; and (iii) Improving local road connections between poverty stricken remote areas and their nearest urban centers. The Project includes seven physical components and one consulting service: (i) Chengkou urban-rural road network improvement; (ii) Shizhu urban-rural road network improvement; (iii) Fuling urban-rural road network improvement; (iv) Wanzhou Yangliu water supply plant; (v) Youyang Longtan River flood management (Youyang County has withdrawn from the subproject list and is no longer financed by ADB); (vi) Wulong Wujiang River flood management; (vii) Rongchang Rongfeng River flood management; (viii) Consulting service subproject.
1.2 General Resettlement Action Plan
All of the 6 components of Chongqing urban-rural infrastructure construction project prepared Resettlement Plans (RPs). The resettlement plans are prepared based on detailed measurement survey of the project impact and fully asking for villagers’ opinions in accordance with the requirements of the ADB and the related domestic policies. The resettlement plans summarized relevant policy frameworks and puts forward effective measures to alleviate the negative effects caused by the project, through a series of public participation in activities and full consultation. All policies proposals and compensation measures in the RPs are committed to achieve “to make sure those who have lost their land or property inevitably in the developmental plan obtain the same or better livelihood and living standard in state of “no project”. The staff from the External Monitoring Agency carried out site investigation of the ADB projects located in various districts and counties in December 2018 and at the beginning of January 2019, and interviewed affected people and conducted household survey. In addition, they met with leaders of the land acquisition offices and
1
various communities. The Resettlement External Monitoring Team (EMT) mainly has six staff, namely, Wang Hong, Song Nan, Hu Yushu, Zhou Xinzhu,Xian Jihong, Tang Huayuan. Annex 1 shows the details of the visits made by the external monitoring people.
Table 1-1 Site Visiting Record
District/County Date of Site Visits (Start) Date of Site Visits (End) Rongchang Dec 5, 2018 Dec 5, 2018 Dec 19, 2018 Dec 19, 2018 Fuling Jan 19, 2019 Jan 19, 2019 Chengkou Jan 7 2019 Jan 8 Wulong Dec 20, 2018 Dec 21, 2018 Shizhu Dec 23,2018 Dec 23,2018 Date of Meeting Conference content Consulting with GM Liu about the construction of the of Landscape Π , and the estimated completion time; Dec 5, a.m 2018 Rongchang Household survey of Group 11 in Huangjinpo village; Household survey of Group 9 in Hailuo village; Household survey of Donghu community; Dec 5, p.m 2018 Rongchang Consulting with secretary Chen about the social training situation Consulting with project manager Wu about the construction progress Dec 19 2018 Fuling Interviewing with the affected household who enjoys the five guarantees policy On-site inspections to understand design changes, land acquisition resettlement changes and Jan 19 2019 Fuling corporate demolition progress Consulting with Deputy general manager Cheng about the Project Status Dec 20 2018 Wulong Visit the construction site Interview with project manager Liu about the construction progress Dec 21 2018 Wulong Household survey Site visit, understand the construction progress and affected land compensation situation of the Dec 23 2018 Shizhu villages Visit the construction site of Contract A Jan 7 2019 Chengkou Consulting with project manager Tan on construction progress and variations Household survey in Yinghong village Visit the construction site of Contract B Jan 8 2019 Chengkou Consulting with project manager Yue, engineer Li about the construction progress Household survey in Xiaoshuiba village
1.3 Overall Implementation Progress
By the end of Dec 2018, C01, C02 of Wanzhou have been completed, C04 has basically completed, and equipment debugging is underway; C01, C02 and C03 of Rongchang have been completed, the completion percentage of C04 is 85%; After the medium-term adjustment, the new subproject C07 in Rongchang started on 28 Nov 2018, is currently doing construction site clearance. As Rongchang has new subprojects, the total contract amount has increased to 935.8114million. Because the engineering variations and new prices have not been approved by ADB, the construction of Wulong and Fuling subprojects almost are in suspension in the second half of 2018. The progress of Chengkou goes relatively fast, and the tunnel was been broken through on December 19, 2018. The Shizhu C02 progressed rapidly, the bridge upper structure has been completed in Dec 2018, and the progress of C01 is slower due to variations and material cost increasing. The total completion percentage of the ADB project is around 81.22%. The project implementation progress for each component is summarized in Table 1- 2 below.
2
Table 1-2 Construction Progress for Each Component
District/Cou Complet Completion % Completion% Contract Contract value Note nty ed (by Jun 2018) (by Dec 2018)
Completed in Oct 2016,The completion contract value is 15 million, and the actual RO-C01 1826.10 1500 100% 100% engineering quantity is less than the contracted engineering quantity.
Completed in May 2018 RO-C02 1658.37 1873 112.94% 113.5% Payment CNY 13.42 million Rongchang Completed in Jul 2018 RO-C03 1497.09 1490 99.53% 99.5% Payment CNY 11.82 million
RO-C04 2098.43 1803 49% 85.9% To be completed by the end of Mar 2019
New contract in medium-term adjustment To RO-C07 6062.73 160 0% 2.6% be completed by May 2020
Completed in May 2016 WA-C01 5963.54 5963.54 100% 100% Payment CNY 40.47 million
Wanzhou To be completed in Aug 2018 WA-C02 7295.66 7973 109.3% Payment CNY 79.73 million
WA-C04 1683.22 1190 71%
11851.28 The contract value was increased to CNY 118,512,834.30 on 4 Dec 2017 WU-C01 13339 80.16% 113% (original 10673.15) To be completed by May 2019
15159.18 The contract amount became CNY 151,591,774.31 at Dec 4, 2017 Wulong WU-C02 13807 85.80% 91% (original 8318.69) To be completed by May 2019
15573.26 The contract value was increased to CNY 155,732,643.33 on 4 Dec 2017 WU-C03 13383 84.82% 86% (original 9840.89) To be completed by May 2019
SZ-C01 4777.78 3470 63.00% 73% To be completed in Aug 2019 Shizhu SZ-C02 3910.76 4059 76.71% 104% To be completed in Aug 2019
CH-C01 1757.68 1600 62.58% 91% To be completed in May 2019 Chengkou CH-C02 4483.48 3000 30.11% 67% To be completed in June 2019
Fuling FL-C02 7982.58 1400 17.54% 17.54% to be determined
Total 93581.14 76010.54 65.62% 81.22%
3
Interview with AP in Huangjinpo village Site visiting with PM Liu of Contract C04
Fuling site Interview with PM Wu in Fuling
Yinghong village community Interview with PM Tan of A in Chengkou
4
Site of contract A in Wulong Consulting with deputy GM Cheng in Wulong
Site of Shizhu subproject Site of Shizhu subproject Figure 1.1 Site visiting
Considering that compensation payments have been almost completed this monitoring focus on the following activities:
(i) urbanization of the affected households;
(ii) use of compensation and subsidy based on village meetings;
(iii) skills training and other income restoration related activities;
(iv) remaining house relocation;
(v) non-residential houses demolition and relocation;
(vi) support to vulnerable groups.
5
2. Status of Compensation
Land acquisition and house demolition in Rongchang, Wulong, Wanzhou and Shizhu have basically been completed, and compensation payments have basically been made; So this report focuses on the outstanding land compensations and house demolition compensation in Chengkou and Fuling. Resettlement subsidy for transferring from agricultural to non-agricultural residents in Rongchang has been fully completed. The name list of transferring into Non-agricultural residents in Wulong subproject had been made with 162 APs. Resettlement subsidies have been distributed to the APs fully completed in Aug 2018. In Shizhu County, the non-agricultural name list has been confirmed. Huangshui Town involves 88 people. The APs who have reached the age (female: 55, male: 60) have started to receive the insurance monthly. But the resettlement subsidies have not been distributed. It is expected that APs will receive the resettlement subsidies in the first half of 2019; Only one AP is transferred into non-agricultural resident in Yuchi Town. As the AP has reached the age of receiving insurance, he has received the pension every month; resettlement subsidies in Yuelai Town have been basically completed, only a few migrant workers has not received due to outside working. In Chengkou, the first 2 demolishment households (Tang Hongyou and Liu Yiguo) have received the house demolition compensation. The demolishment of another 6 houses newly added because of the landslide have been completed as well. 88.7% of household land compensation has been paid, 11.3% is remained due to land border dispute and some villagers working outside. For the land compensation in Chengkou, It is planned to be completed by the end of first half of 2019. 75 graves have been relocated with the compensation of RMB 9500/ per grave. The land acquisition, house demolition and compensation for Contract A in Fuling have been completed; The land acquisition and enterprise relocation of contract B in Fuling is still under the progress. Damu town had paid the land compensation to VC in December 2017(about RMB 840,000). The land compensation in Yingxin Village had been distributed to the APs at the end of March 2018. The land compensation in Tujing village will be paid to the APs in the first half of 2019. In Jiaoshi town, it is estimated that the land compensation will be completed in the first half of 2019. As IA is trying to change the type of the ADB road to rural roads, now they are awaiting for the final approval of the Fuling Land Bureau. The IA planned compensation standard is consistent with the URP, and EMT will continue to pay attention to the changes in Fuling. The relocation of Fuling enterprises has not yet begun, and the Fuling government is still negotiating with the manufacturers.
6
Table 2-1 Payment of compensation for each Subproject
Project Name Rongchang Wulong Wanzhou Shizhu Chengkou Fuling Item
1. Land compensation payment Completed Completed Completed Ongoing Ongoing Ongoing
URP/RP 997.05 107.07 1410.87 964.35 846.51 641.31
Cumulative amount(unit:10k 1083.94 2696.25 56.18 694.24 742 84 yuan)(Distributed to APs) 2. Resettlement subsidies(unit:10k Completed Completed / Ongoing / Ongoing yuan) URP/RP 742.5 269.5 32.4 716.4 364.00 374.5 Cumulative amount(unit:10k yuan) / 423.77 53.15 148.52 / / 3. House demolition payment Completed Completed Completed Completed Completed / URP/RP 147.55 4657.93 7 54.35 45.57 1283.74 Cumulative amount(unit:10k yuan) 1248.44 334.37 36 145.5 340.56 / 4. Company relocation and payment / Ongoing Completed / / Ongoing
URP/RP / 4338.08 257.50 / / 380 Cumulative amount(unit:10k yuan) / 5903.20 141.46 / /
Table 2-2 Status of HHs and Enterprises
Unit Rongchang Wulong Wanzhou Shizhu Chengkou Fuling Area of house m2 1,650 9,802.43 200 729 400 12,789 demolition in URP Demolished house area m2 0 777.43 200 1,120 1,056 5,089.17 Demolished proportion % / 7.9 100 100 100 39.8 Households to be HH 0 2 1 3 4 15 resettled in URP Households have been HH 0 2 1 3 8 15 resettled Demolition of Resettlement proportion % 0 100 100 100 200 100 houses and Enterprises to be 0 2 0 1 0 3 enterprises resettled in URP Enterprises have been 0 2 0 0 0 0 resettled Resettlement proportion % / 100 / / / 0 Budget for demolition in 10k 22 4,657.93 23.06 173.19 45.57 1,672.45 URP yuan Demolition payment has 10k 22 5,871.81 23.06 173.19 295.56 / been paid yuan Payment completion % % 100 >100 100 100 648.6 /
7
Table 2-3 COMPARISON OF LAND ACQUISITION IMPACTS
COMPARISON OF LAND ACQUISITION IMPACTS Rongchang Wulong Wanzhou Shizhu Chengkou Fuling IMPACTS Contract A Contract B COUNTY URP Actual URP Actual URP Actual URP Actual URP Actual URP Actual Actual 188. 1. Permanent LA(mu) 465 412.52 255.62 255.62 196.2 642.9 666.41 359.18 415.7+41.1 427.54 77.94 339.12+64.18 2 1.1 Collective Land (mu) 450 97.52 76.48 76.48 37 45 642.9 658.62 359.18 415.7+41.1 427.54 77.94 337.22 Affected households 190 178 22 19 0 0 289 299 43 168 229 20 111 Affected persons 750 700 77 60 0 0 1018 1043 152 588 792 120 328 151. 1.2 stated owned Land (mu) 315 315 179.14 179.14 151.2 0 7.79 0 0 0 0 66.08 2 1.3 Status Completed Completed Completed Ongoing Ongoing Completed Ongoing
2. Residential House
Demolition Area(m2) 1650 4450.54 777.43 777.43 200 200 729 1120 400 - 12789 4953.67 Affected households 10 41 2 2 1 1 5 3 2 8 32 10 Affected persons 26 / 8 8 9 9 21 15 7 28 156 73 Status Completed Completed Completed Completed Completed Completed
3. Non-residential house
Demolition Area(m2) 0 0 9672 9672 1500 1500 0 0 0 676 - Number 0 0 2 2 2 2 0 0 0 2 3 Status Ongoing Ongoing
-=number/information is not available during the mission. LA = land acquisition,m2= square meter, mu = a Chinese unit of measurement (1 mu =666.667 square meters),URP = updated resettlement plan.
8
2.1 Rongchang RongFeng River Comprehensive Flood Control Subproject
Land compensation in Rongchang had already been completed, specific details can be seen in No. 6 EMR.
2.2 Fuling Urban and Rural Road Network Reconstruction Project
2.2.1 Permanent Land Acquisition Impacts