BEDFORD COUNTY CONSTRUCTION PROGRESS REPORT

MPMS SR – SEC PROJECT TITLE STATUS ANTICIPATED COMPLETION 96033 7216-314 T-314 Barnes Road Bridge 100% Complete 09/02/20 • Bridge rehabilitation • On Barnes Rd over Crooked Run, ¾ mile north of intersection with State Line Rd (T-326) • Anticipated traffic control will consist of a Detour utilizing Barnes Rd, Crooked Run Rd, Barnes Rd, East Shipley Rd (MD), National Hwy (US40)(MD),N Orleans Rd (MD), Clear Ridge Rd (PA26), (8.7 miles) • Mann Township • Prime Contractor: George S. Hann & Son, Inc. • Part of the Street Road over Flintstone Creek Contract • Contractor currently waiting on cure time for recently poured deck, 2 weeks

21515 1005-05B South Cemetery Bridge 100% Complete 08/29/19 • Bridge replacement • On Churchview Rd over Beaver Creek near intersection with Salemville Rd • Anticipated traffic control will consist of a Detour utilizing Churchview Rd, Salemville Rd, Hershberger Rd, Chestnut St, Church St, Brumbaugh Rd (PA 869, Woodbury Pike (PA 36), and Town Hill Rd [9.5 miles] • South Woodbury Township • Prime Contractor: Cottle's Asphalt Maintenance, Inc.

110863 0070-08S CMB I-70 Town Hill to Tpike Ramps 100% Complete 09/25/19 • Installation of High Tension Cable Median Barrier • Anticipated traffic control will consist of short-term lane closures • Various Municipalities in Bedford & Fulton Counties • Prime Contractor: Cottle’s Asphalt Maintenance, Inc.

88128 2029-04B Trib Bridge 100% Complete 09/04/19 • Bridge rehabilitation • On East Mattie Rd over Tributary of Raystown Branch of Juniata River near intersection of South Main Street • Traffic control will consist of a Detour utilizing East Mattie Rd, South Breezewood Rd, I-70 S, Old 126 Rd, South Breezewood Rd, Brush Creek Rd, and E Mattie Rd, [10.8 Miles] • East Providence Township • Prime Contractor: Cottle's Asphalt Maintenance, Inc.

Page 1 of 35 District 9-0 Southern Alleghenies RPO As of 10/07/2019

BEDFORD COUNTY CONSTRUCTION PROGRESS REPORT

MPMS SR – SEC PROJECT TITLE STATUS ANTICIPATED COMPLETION 106489 1020-01B SR 1020 Pipers Run Bridge 100% Complete 08/09/19 • Superstructure replacement, minor roadway approach work and guiderail upgrades • On West Cypher Rd over Pipers Run • Anticipated traffic control will consist of a detour utilizing West Cypher Rd (T-532), Piper Hill Rd (T-528), Snyder Rd (T-537), Recreational Dr (T-530), and West Cypher Rd (T-532), (2.7 miles) • Hopewell Township • Prime Contractor: Wen-Brooke Contracting Inc. • Contractor expects to install guiderail on Oct. 3rd, bridge is currently open to traffic

21466 1015-02B 2019 DF Bedford Box Culvert 100% Complete 10/01/19 • On Replogle Schoool Rd over Tributary to Three Springs Run near intersection of Mill St • Anticipated traffic control will consist of a detour utilizing Replogle School Rd, Potter Creek Rd (PA 868), Woodbury Pike (PA 869) and Replogle School Rd, (6.3 miles) • South Woodbury Township • Prime Contractor: Department Forces

96036 7218-473 T-473 Rose Road Bridge 95% Complete 09/20/20 • Bridge rehabilitation • On Rose Rd over Shawnee Creek approximately ½ mile north of the US30 intersection • Traffic control consists of a detour utilizing Rose Rd, Lincoln Highway (US 30), Hoover Rd and Rose Rd, (2.4 miles) • Napier Township • Prime Contractor: George S. Hann & Son, Inc. • Part of the Street Road over Flintstone Creek Contract • Contractor has completed deck, roadway tie-in to be paved week of October 7th, open to traffic by October 18th

Page 2 of 35 District 9-0 Southern Alleghenies RPO As of 10/07/2019

BEDFORD COUNTY CONSTRUCTION PROGRESS REPORT

MPMS SR – SEC PROJECT TITLE STATUS ANTICIPATED COMPLETION 110865 0869-09S D9 2019 HSIP HFST 86% Complete 11/04/19 • Placement of High Friction Surface Treatment • On Brumbaugh Mtn Rd from King Twp Line (Top of mountain) 0.4 miles toward intersection with PA 867 (Lafayette Rd); also on Sproul Mtn Rd through the curves up mountain approximately 0.7 miles from the intersection with Hoover Rd • Anticipated traffic control will consist of daylight flagging • Bloomfield and South Woodbury Townships (Bedford County) • Prime Contractor: MEKIS Construction Corporation • Contract includes various routes in Blair, Cambria, Fulton, Huntingdon and Somerset Counties • Contractor has completed all counties except Somerset County section on PA 160, will complete in Spring 2020

91606 0030-002 US30 Breezewood Resurface 84% Complete 06/28/20 • Resurfacing, concrete patching, high friction surface treatment, base repairs, drainage improvements, guide rail, signing and traffic signal upgrades. • On Lincoln Highway from West end of concrete in East Providence Twp, Bedford Co. to east end of climbing lane taper in Brush Creek Twp., Fulton Co. • Anticipated traffic control will consist of night time lanes closures in business district, daylight flagging • Prime Contractor: Cottle's Asphalt Maintenance, Inc. • Contractor is finishing up rumble strips, signage and guide rail

111481 0000-HBT H&BT Rail Trail Extension 80% Complete 07/30/20 • On old H&BT railroad alignment from the Riddlesburg trail head north towards the Warriors Path State Park • Trail section will be off line until completion of project • Broad Top Township • Prime Contractor: Broad Top Township Supervisors • Contractor has completed trail grading and trail surface placement is complete; Currently installing pavement markings, paving the parking lot, and roadway overlay repair work; Contractor anticipates completion by mid- October

Page 3 of 35 District 9-0 Southern Alleghenies RPO As of 10/07/2019

BEDFORD COUNTY CONSTRUCTION PROGRESS REPORT

MPMS SR – SEC PROJECT TITLE STATUS ANTICIPATED COMPLETION 110219 0326-005 PA 326 – Main Rd to US30 80% Complete 10/25/19 • Resurfacing (5.4 miles) and guiderail upgrade • On Egolf Rd from US 30 to Main Rd • Anticipated traffic control will consist of daylight flagging • Colerain and Snake Spring Townships • Prime Contractor: New Enterprise Stone & Lime Co., Inc. • Contractor has completed pipe replacements, currently milling roadway, on track to conclude by anticipated completion date

21464 3003-01B Evitts Creek Bridge 72% Complete 10/31/19 • Bridge replacement • On Lake Gordon Rd over Evitts Creek east of intersection with Pine Ridge Rd • Traffic control consists of a Detour utilizing Lake Gordon Road, Hazen Road (MD/PA), Smouses Mill Road (MD 807), Bedford Valley Road (US 220-MD), Pine Ridge Road (MD/PA), and Lake Gordon Rd, (6.5 miles) • Cumberland Valley Township • Prime Contractor: Beech Construction, Inc. • Contractor is currently pouring safety wings to bridge, roadway reconstruction to begin shortly and bridge to be open to traffic on October 20th

96032 7210-413 T-413 Grasser Rd Br Rehab 65% Complete 09/02/20 • Bridge rehabilitation • On Grasser Rd over Raystown Branch of Juniata River at the intersection of New Baltimore Rd • Anticipated traffic control will consist of single lane phased construction with temporary traffic signal • Juniata Township • Prime Contractor: George S. Hann & Son, Inc. • Part of the Street Road over Flintstone Creek Contract • Contractor has poured the deck on one half of structure, currently under a 21-day cure, plans to return the 2nd week of November to pour the 2nd half

Page 4 of 35 District 9-0 Southern Alleghenies RPO As of 10/07/2019

BEDFORD COUNTY CONSTRUCTION PROGRESS REPORT

MPMS SR – SEC PROJECT TITLE STATUS ANTICIPATED COMPLETION 91440 0915-03B Hopewell Bridge Replace 64% Complete 11/21/19 • Bridge Replacement and intersection realignment • On Front St over Raystown Branch of Juniata River at the intersection of Raystown Rd (PA 26) • Hopewell Township, Broad Top Township and Hopewell Borough • Prime Contractor: HRI, Inc. • Contractor is currently placing subbase on the new PA 26 roadway north and south of the bridge, setting beams on the 3rd and final span of the new bridge, and continuing to pour deck sections on beams already placed

88571 0026-13B PA 26/36 Culvert Replacements 58% Complete 07/30/20 • Culvert replacements • On Raystown Rd (PA 26)(3) and one culvert on Woodbury pike (PA 36)(1) • Traffic control consists of temporary roadways for both routes • Hopewell Township (Cottles Corner) • Prime Contractor: New Enterprise Stone & Lime Co., Inc. • Contractor has finished PA 36 culvert, and is finish paving and installing guiderail on PA 26 and expects to switch traffic to new structures by end of October

88126 1019-01B Ravers Run Culvert *Deferred 09/04/20 • Culvert Replacement • On Pinchot Rd over Ravers Run near the intersection of Carberry Road • Anticipated traffic control will consist of Detour utilizing Pinchot Rd, Raystown Rd (PA26), and N Woodcock Valley Rd, (13.7 miles) • Liberty Township • Prime Contractor: New Enterprise Stone Lime Co., Inc. • *At the request of Broad Top Twp and Hopewell Borough this project has been moved to 2020 construction

Page 5 of 35 District 9-0 Southern Alleghenies RPO As of 10/07/2019

BEDFORD COUNTY UPCOMING LETS

MPMS SR – SEC PROJECT TITLE ANTICIPATED LET ANTICIPATED COMPLETION 74411 4009-01B Dunnings Creek Trib Bridge 4th Quarter 2019 Fall 2020 • Bridge replacement • On Business 220 over Tributary to Dunnings Creek just south of intersection with Belden Road • Anticipated traffic control will consist of a Detour utilizing Business 220, I-99, Quaker Valley Rd and Business 220 (6.5 miles) • Bedford Township • Project includes the Brush Run Bridge just south of the entrance to the Bedford County Business Park

88133 4009-02B Brush Run Bridge 4th Quarter 2019 Fall 2020 • Bridge replacement • On Business Route 220 over Brush Run just south of intersection with Commerce Court • Anticipated traffic control will consist of a Detour utilizing Business 220, I-99, Quaker Valley Rd and Business 220 (6.5 miles) • Bedford Township • Part of the Dunnings Creek Trib Bridge

96030 7202-609 T-609 Snyder Creek Road Bridge 4th Quarter 2019 Fall 2020 • Bridge rehabilitation • On Snyder Creek Road (T-609) over Potter Creek at the intersection of Potter Creek Rd (PA868) • Anticipated traffic control will consist of a detour utilizing Potter Creek Rd (PA 868), Cowan School Rd, Furry Dr and Snyder Creek Rd, (3.0 miles) • Bloomfield Township • Part of a grouped letting for 11 non-composite deck replacements in Bedford (5), Fulton (5) and Huntingdon (1) Counties

Page 6 of 35 District 9-0 Southern Alleghenies RPO As of 10/07/2019

BEDFORD COUNTY UPCOMING LETS

MPMS SR – SEC PROJECT TITLE ANTICIPATED LET ANTICIPATED COMPLETION 96031 7204-357 T-357 Harietta Lane Bridge 4th Quarter 2019 Fall 2020 • Bridge rehabilitation • On Harietta Lane over Cove Creek west of the intersection of Rose Lane • Anticipated traffic control will consist of a detour utilizing Harietta Lane, Valley Rd, Centennial Rd and Harietta Lane, (6.8 miles) • Colerain Township • Part of a grouped letting for 11 non-composite deck replacements in Bedford (5), Fulton (5) and Huntingdon (1) Counties

22045 7207-545 Oppenheimer Road Bridge 4th Quarter 2019 Fall 2020 • Bridge rehabilitation • On Oppenheimer Hollow Road over Oppenheimer Run just north of Younts Rd west of the intersection Rose Lane (T-376) • Anticipated traffic control will consist of a Detour utilizing Oppenheimer Hollow Rd, Kauffman Hollow Rd., Younts Rd., Willow Brook Lane, Imlertown Rd., Younts Rd, to Oppenheimer Hollow Rd. [3.5 miles] • East St Clair Township

109135 7212-613 T-613 Colebaugh Road Bridge 4th Quarter 2019 Fall 2020 • Bridge rehabilitation • On Colebaugh Rd over Scrubgrass Creek near intersection of Scrubgrass Rd • Anticipated traffic control will consist of a detour utilizing Colebaugh Rd, Scrubgrass Rd, Feathers Rd, and Schellsburg Rd, (3.0 miles) • King Township • Part of a grouped letting for 11 non-composite deck replacements in Bedford (5), Fulton (5) and Huntingdon (1) Counties

Page 7 of 35 District 9-0 Southern Alleghenies RPO As of 10/07/2019

BEDFORD COUNTY UPCOMING LETS

MPMS SR – SEC PROJECT TITLE ANTICIPATED LET ANTICIPATED COMPLETION 109136 7217-353 T-353 Rice Road Bridge 4th Quarter 2019 Fall 2020 • Bridge rehabilitation • On Rice Rd over West Branch Sideling Hill Creek near intersection of Big Creek Rd • Anticipated traffic control will consist of a detour utilizing Rice Rd, Addison Ridge Rd, Turkey Ridge Rd, and Big Creek Rd, (8.0 miles) • Monroe Township • Part of the T-331 East Pittman Road Bridge grouped letting for 11 non-composite deck replacements in Bedford (5), Fulton (5) and Huntingdon (1) Counties

96035 7217-386 T-386 Akers Road Bridge 4th Quarter 2019 Fall 2020 • Bridge rehabilitation • On Akers Rd over Shaffer Creek • Anticipated traffic control will consist of a detour utilizing Akers Rd, Back Ridge Rd, Akers Rd, Rock Hill Rd, Mechanics Hill Rd, Merriwinds Rd, and McCune Rd, (4.7 miles) • East Providence/Monroe Township Line • Part of a grouped letting for 11 non-composite deck replacements in Bedford (5), Fulton (5) and Huntingdon (1) Counties

74381 0867-01B Trib 1st Quarter 2020 Fall 2020 • Small bridge being replaced by an elliptical pipe • On Lafayette Rd over Halter Creek just north of the intersection of Cross Cove Rd • Anticipated traffic control will consist of a detour utilizing Lafayette Rd, Bloomfield Rd, W Main St, Woodbury Pike (PA 36), Cross Cove Rd, and Lafayette Rd (10.1 miles) • Bloomfield Township • Contract includes the SR 1042 Halter Crk Bridge project

Page 8 of 35 District 9-0 Southern Alleghenies RPO As of 10/07/2019

BEDFORD COUNTY UPCOMING LETS

MPMS SR – SEC PROJECT TITLE ANTICIPATED LET ANTICIPATED COMPLETION 98778 1042-01B SR 1042 Halter Crk Bridge 1st Quarter 2020 Fall 2020 • Bridge replacement with a box culvert • On Sproul Mountain Rd over Halter Creek just west of the intersection of Lafayette Rd (PA 867) • Anticipated traffic control will consist of a detour utilizing Sproul Mountain Rd, Bud Shuster Hwy (I-99), Woodbury Pike (PA 36), Cross Cove Rd, and Lafayette Rd, (17.9 miles) • Bloomfield Township • Part of the Halter Creek Trib Contract

74395 1016-01B 2020 DF Bedford Box Culvert 1st Quarter 2020 Fall 2020 • Culvert replacement • On Chalybeate Rd over Tributary to Dunnings Creek south east of the intersection with Briar Valley Rd • Anticipated traffic control will consist of a detour utilizing Chalybeate Rd, Briar Valley Rd, Imlertown Rd, Rabbit Ln and Chalybeate Rd, (7.8 miles) • Bedford Township • Prime Contractor: Department Forces

88524 0056-24S PA56/SR 4028 Intersection 1st Quarter 2020 Fall 2020 • Intersection Improvement • On Quaker Valley Rd at the Old Town Rd/Hammond Hill Rd intersection • Access management at business locations at the intersection, Quaker Valley Rd 3-lane template will be connected through the area of the intersection, Manor Ln intersection with PA 56 will also be reconfigured, replacement of elliptical concrete pipe at Fishertown Market eastern entrance • Anticipated traffic control will consist of phased construction with signals • East St Clair Township

21362 1034-01B Sandy Run Bridge 2nd Quarter 2020 Fall 2020 • Small bridge being replaced by an elliptical pipe • On Longs Run Rd over Sandy Run Creek near the intersection of Sandy Run Rd (PA 915) • Anticipated traffic control will consist of a detour utilizing Lafayette Rd, Bloomfield Rd, Main St, Woodbury Pike (PA 36), and Cross Cove Rd, (10.1 miles) • Bloomfield Township

Page 9 of 35 District 9-0 Southern Alleghenies RPO As of 10/07/2019

BEDFORD COUNTY UPCOMING LETS

MPMS SR – SEC PROJECT TITLE ANTICIPATED LET ANTICIPATED COMPLETION

106005 0030-04S US 30 Left Turn Lane at T-455 2nd Quarter 2020 Fall 2020 • Construction of a left turn lane • On Lincoln Hwy just east of Lower Snake Spring Rd at Mount Dallas Road • Anticipated traffic control will consist of daylight flagging • Snake Spring Township

96524 1019-002 SR 1019 – PA 26 to PA 26 2nd Quarter 2020 Fall 2020 • Resurfacing (5.2 miles) • On Woodcock Valley Rd/Pinchot Rd from Raystown Rd to Raystown Rd • Traffic control will consist of daylight flagging • Hopewell and Liberty Townships

107209 3002-DF1 DF-SR 3002-Somerset Co Line to PA 96 2nd Quarter 2020 Fall 2020 • Resurfacing (1.9 miles) • On Kennels Mill Rd from Somerset County Line to Hyndman Rd (PA 96) • Anticipated Traffic Control will consist of daylight flagging • Londonderry Township

110279 4009-021 SR 4009 - Weber Ln to E Penn St 2nd Quarter 2020 Fall 2020 • Resurfacing (2.2 miles) • On Business 220/N Richard St from Weber Lane to E Penn St • Anticipated Traffic Control will consist of daylight flagging • Bedford Borough and Bedford Township

113937 1011-000 SR 1011 – US 30 to T-444 Ridge Road 2nd Quarter 2020 Fall 2020 • Resurfacing (5.0 miles) • On East Graceville Rd from Lincoln Hwy (US 30) to Ridge Rd • Anticipated Traffic Control will consist of daylight flagging • East Providence Township

Page 10 of 35 District 9-0 Southern Alleghenies RPO As of 10/07/2019

BEDFORD COUNTY UPCOMING LETS

MPMS SR – SEC PROJECT TITLE ANTICIPATED LET ANTICIPATED COMPLETION

88129 3007-01B Trib to Sweet Root Creek Culvert 3rd Quarter 2020 Fall 2020 • Bridge replacement with box culvert • On Black Valley Road over Sandy Creek near intersection of Sweet Root Rd (T-340) • Phased construction with signal • Southampton Township

109816 0099-012 Turnpike to Sproul/Claysburg 4th Quarter 2020 Fall 2021 • Resurfacing and guiderail upgrades • On Bud Shuster Highway from Turnpike Interchange (Exit #1) north to the Sproul/Claysburg Interchange (Exit #15) • Anticipated traffic control will consist of one-lane closures • Bedford, East St Clair, King and Kimmel Townships; Greenfield Township, Blair County

88098 7203-575 T-575 Cold Spring Road Bridge 1st Quarter 2021 Fall 2021 • Bridge replacement • On Cold Spring Rd over Six Mile Run at the intersection with Main St • Anticipated traffic control will consist of a temporary roadway • Broad Top Township

22816 0070-021 Breezewood-Fulton Co Line 1st Quarter 2021 Fall 2021 • Resurfacing (Mill & overlay), median work, signage and slip-lining metal pipes (11.5 miles – 4 lane) • On Dwight D. Eisenhower Hwy from Lincoln Hwy (US 30) to Fulton Co Line • Anticipated Traffic Control will consist of phased construction East Providence Township, Bedford Co. and Brush, Union and Bethel Townships, Fulton Co.

108176 2001-000 SR 2001 – SR 2003 to SR 2003 2nd Quarter 2021 Fall 2021 • Resurfacing (5.8 miles) • On Artemas Rd from Crooked Run Rd (0.25 mile from Fairview Church, PA 26) to Crooked Run Rd (0.15 mile from Line) • Anticipated Traffic Control will consist of daylight flagging • Mann Township Page 11 of 35 District 9-0 Southern Alleghenies RPO As of 10/07/2019

BEDFORD COUNTY UPCOMING LETS

MPMS SR – SEC PROJECT TITLE ANTICIPATED LET ANTICIPATED COMPLETION

105996 0056-01B Trib Barefoot Run 3rd Quarter 2021 Fall 2022 • Bridge replacement • On Quaker Valley Rd over Tributary to Barefoot Run just west of the intersection with Cortland Rd/King St Clair Rd (PA96) • Anticipated traffic control will consist of phased construction • Pleasantville Borough

Page 12 of 35 District 9-0 Southern Alleghenies RPO As of 10/07/2019

FULTON COUNTY CONSTRUCTION PROGRESS REPORT

MPMS SR – SEC PROJECT TITLE STATUS ANTICIPATED COMPLETION 107162 2005-01B 2019 DF Fulton Box Culvert 100% Complete 09/20/19 • Culvert replacement • On Timber Ridge Rd over Joe’s Run near the intersection of Garland Rd • Traffic control will consist of a Detour utilizing Timber Ridge Rd, Great Cover Rd (US 522), and Pleasant Ridge Rd (PA 655), (14.2 miles) • Belfast Township • Prime Contractor: Department Forces

110865 0869-09S D9 2019 HSIP HFST Contract 86% Complete* 11/04/19 • Placement of High Friction Surface Treatment • On Lincoln Hwy between S Valley Rd and North Valley Rd (Three areas) • On Flickerville Rd from bridge over Little Tonoloway Creek through the curve at Fischer Rd • Anticipated traffic control will consist of daylight flagging • Brush Creek Township, Fulton County • Prime Contractor: MEKIS Construction Corporation • Contract includes various routes in Bedford, Blair, Cambria, Huntingdon and Somerset Counties • *Contractor has completed the 5 sections on the Lincoln Highway (US 30) and PA 643 (Flickerville Pike), a section of PA 160 in Somerset County section will be completed in the Spring

98775 0655-05B PA 655 Sideling Hill Creek 71% Compete 11/07/19 • Bridge Replacement • On Waterfall Rd (PA 655) over Sideling Hill Creek at the intersection with New Grenada Hwy • Anticipated traffic control will be phased construction with signal • Taylor Township • Prime Contractor: Susquehanna Valley Construction Corporation • Contract includes PA 913 Roaring Run Bridge project and Sideling Hill Creek #2 (Huntingdon Co.) • Contractor has finished this structure

Page 13 of 35 District 9-0 Southern Alleghenies RPO As of 10/07/2019

FULTON COUNTY CONSTRUCTION PROGRESS REPORT

MPMS SR – SEC PROJECT TITLE STATUS ANTICIPATED COMPLETION 22833 0913-02B PA 913 Roaring Rn Bridge 71% Complete 11/07/19 • Bridge Replacement • On New Grenada Hwy (PA 913) over Roaring Run near intersection with Hoover Rd • Anticipated traffic control will be phased Construction • Wells Township • Prime Contractor: Susquehanna Valley Construction Corporation • Part of the PA 655 Sideling Hill Creek Contract • Contractor has finished this structure

74444 1005-01B Little Augwick Creek Bridge 26% Complete 08/14/20 • Superstructure replacement • On Aughwick Rd over South Branch of Little near the Dublin/Todd Township Line • Traffic control will consist of a Detour utilizing Aughwick Rd, Lincoln Hwy (US30), Great Cover Rd (US 522), Grist Mill Rd, and Allens Valley Rd, (29.4 miles) • Todd Township • Prime Contractor: Cottle’s Asphalt Maintenance, Inc. • Contractor has poured the deck and has removed the Detour, the deck will be epoxy coated in the Spring under daylight flagging

Page 14 of 35 District 9-0 Southern Alleghenies RPO As of 10/07/2019

FULTON COUNTY UPCOMING LETS

MPMS SR – SEC PROJECT TITLE ANTICIPATED LET ANTICIPATED COMPLETION 112705 0070-38T 2019 S Alleghenies RPO TSMO 4th Quarter 2019 Summer 2020 • Dynamic Message Sign retrofit • On I-70 near Pigeon Cove Rd – Bethel Township, Fulton Co., also on US 22 near Frankstown Branch Juniata River – Porter Township, Huntingdon Co; PA 453 near Spruce Creek Rd – Morris Township, Huntingdon Co.; • Anticipated traffic control will consist of daylight flagging

109200 7201-338 T-338 Laurel Ridge Road Bridge 4th Quarter 2019 Fall 2020 • Bridge deck replacement • On Laurel Ridge Rd over Cove Creek near the intersection of Big Cove Tannery Rd (PA 928) • Anticipated traffic control will consist of a Detour utilizing Shaw Rd, Great Cove Rd (US 522) and Laurel Ridge Rd (PA 928) (7.5 miles) • Ayr Township • Part of a grouped letting for 11 non-composite deck replacements in Bedford (5), Fulton (5) and Huntingdon (1) Counties

109201 7201-372 T-372 Ravensburg Road Bridge 4th Quarter 2019 Fall 2020 • Bridge deck replacement • On Ravensburg Rd over Cove Creek north of the intersection with US 522 • Anticipated traffic control will be phased construction • Ayr Township • Part of a grouped letting for 11 non-composite deck replacements in Bedford (5), Fulton (5) and Huntingdon (1) Counties

109202 7206-404 T-404 Reunion Ground Road Bridge 4th Quarter 2019 Fall 2020 • Bridge deck replacement • On Reunion Ground Road over Licking Creek near the intersection of Big Cove Tannery Rd (PA 655) • Anticipated traffic control will consist of a Detour utilizing Pleasant Ridge Rd (PA 655), Lincoln Highway, Patterson Run Rd, and Reunion Ground Rd (5.0 miles) • Licking Creek Township • Part of a grouped letting for 11 non-composite deck replacements in Bedford (5), Fulton (5) and Huntingdon (1) Counties

Page 15 of 35 District 9-0 Southern Alleghenies RPO As of 10/07/2019

FULTON COUNTY UPCOMING LETS

MPMS SR – SEC PROJECT TITLE ANTICIPATED LET ANTICIPATED COMPLETION 110583 0070-35B I-70 Bridges over PA 915 4th Quarter 2019 Fall 2020 • Bridge Preservation • On Dwight D. Eisenhower Highway (I-70) over South Valley Road (PA 915) and Little Brush Creek • Anticipated traffic control will be phased construction • Brush Creek Township

109203 7208-331 T-331 East Pittman Road Bridge 4th Quarter 2019 Fall 2020 • Bridge Rehabilitation • On East Pittman Rd over Licking Creek approximately 0.2 miles west of Laurel Ridge Rd. • Anticipated traffic control will consist of a detour utilizing East Pittman Rd., Big Cove Tannery Rd., Toll Gate Rd., Gem Bridge Rd., East Pittman Rd, (7.5 miles) • Thompson Township • Part of a grouped letting for 11 non-composite deck replacements in Bedford (5), Fulton (5) and Huntingdon (1) Counties

109204 7210-366 T-366 Old Route 126 Bridge 4th Quarter 2019 Fall 2020 • Bridge deck replacement • On Old Route 126 (T-366) over McKees Run near the intersection of Deneens Gap Road • Anticipated traffic control will consist of a detour utilizing Old Route 126, Fairview Rd., McKees Gap Rd., to Deneens Gap Rd, (4.8 miles) • Union Township

107161 3013-02B 2020 DF Fulton Box Culvert 1st Quarter 2020 Fall 2020 • Culvert replacement • On Sipes Mill Rd over Tributary over Cummings Run Creek just west of intersection with Saw Mill Rd • Anticipated traffic control will consist of a Detour utilizing Saw Mill Rd, Barnhart Rd, Pleasant Grove Rd and Sipes Mill Rd, (4.6 miles) • Belfast Township

Page 16 of 35 District 9-0 Southern Alleghenies RPO As of 10/07/2019

FULTON COUNTY UPCOMING LETS

MPMS SR – SEC PROJECT TITLE ANTICIPATED LET ANTICIPATED COMPLETION 106419 7205-457 Tannery Road Bridge 1st Quarter 2020 Fall 2020 • Bridge Replacement • On Tannery Rd over • Anticipated traffic control will consist of a Detour utilizing Tannery Rd (Fulton & Huntingdon), Mill Hill Rd (Huntingdon), Croghan Pike (US 522), Tannery Rd (Huntingdon & Fulton), (4.8 miles) • Dublin Township

96544 0016-02S US 522 – Franklin Co Line 1st Quarter 2021 Fall 2021 • Resurfacing • On Lincoln Way East/Buchanan Trail from Second St to Franklin Co Line • Anticipated traffic control will be daylight flagging • Bridge rehabilitation • Lincoln Way West over Big Cove Creek between Brooklyn Dr and Borough Line • Anticipated traffic control will consist of phased construction • Culvert rehabilitation • On Lincoln Way East over Trib Cove Creek just east of Second St • Anticipated traffic control will consist of phased construction • McConnellsburg Borough and Ayr Township

112565 0655-007 PA 655 Under 8ft Culverts 1st Quarter 2021 Fall 2021 • Culvert replacements of culverts under 8 feet • On Waterfall Rd from Snyder Lane to Appleby Road • Anticipated traffic control will consist of daylight flagging • Taylor Township

112566 4013-001 Fulton & Huntingdon Co under 8ft Clvrts 1st Quarter 2021 Fall 2021 • Culvert replacements of culverts under 8 feet • On Buck Valley Road in Bethel Twp, Fulton Co., Wells Valley Road in Wells Twp, Fulton Co. • Project also includes Shade Valley Road (PA 35) in Tell Twp, Huntingdon Co., and Warriors Mark Path Road (PA 350) in Franklin Twp, Huntingdon Co. • Anticipated traffic control will consist of daylight flagging

Page 17 of 35 District 9-0 Southern Alleghenies RPO As of 10/07/2019

HUNTINGDON COUNTY CONSTRUCTION PROGRESS REPORT

MPMS SR – SEC PROJECT TITLE STATUS ANTICIPATED COMPLETION 109206 7222-313 T-313 Walnut Grove Road Bridge 100% Compete 09/02/20 • Bridge Rehabilitation • On Walnut Grove Church Rd over sideling Hill Creek east of intersection of Doyle Rd (T-319) • Anticipated Traffic Control will consist of a Detour utilizing Hollow Rd, Selea Hollow Rd, Elliots Run Rd, and Walnut Grove Church Rd (8.5 miles) • Springfield Township • Prime Contractor: George S. Hann & Son, Inc. • Part of the Street Road over Flintstone Creek contract (Bedford Co.) and includes one other local bridge in Huntingdon Co. and six in Bedford Co.

109207 7222-333 T-333 Mathews Bridge Road Bridge 100% Complete 09/02/20 • Bridge Rehabilitation • On Mathews Bridge Rd over Aughwick Creek near intersection of Maddensville Pike (PA475) • Anticipated Traffic Control will consist of a Detour utilizing Maddenville Pike, Meadow Gap Rd, Fleck Rd, Mathews Bridge Rd (6.0 miles) • Springfield Township • Prime Contractor: George S. Hann & Son, Inc.

106468 1008-DF1 DF – SR 1008 - PA 305 to SR1013 100% Complete 04/25/19 • Resurfacing • On Myton Rd from Shavers Creek Rd (PA 305) to Harpers Hill Rd • Anticipated Traffic Control will consist of daylight flagging • West Township • Prime Contractor: Department Forces

110283 4007-001 PA 305 to Cold Springs Rd 100% Complete 09/06/19 • Resurfacing • On Petersburg Pike from King St (PA 305) to Cold Springs Rd • Anticipated Traffic Control will consist of daylight flagging • Petersburg Borough, Oneida and Logan Townships • Prime Contractor: New Enterprise Stone & Lime Co., Inc. • Contract includes the SR 1011 - PA 26 to SR 1001 project

Page 18 of 35 District 9-0 Southern Alleghenies RPO As of 10/07/2019

HUNTINGDON COUNTY CONSTRUCTION PROGRESS REPORT

MPMS SR – SEC PROJECT TITLE STATUS ANTICIPATED COMPLETION 107217 3012-DF1 SR 3012 - PA 26 to End of Route 100% Complete 05/02/19 • Resurfacing • On Garner Rd from Standing Stone Rd (PA 26) to Cul-de-sac Rd • Anticipated Traffic Control will consist of daylight flagging • Penn Township • Prime Contractor: Department Forces • Part of the Street Road over Flintstone Creek contract (Bedford Co.) and includes one other local bridge in Huntingdon Co. and six in Bedford Co.

106473 1011-001 SR 1011 - PA 26 to SR 1001 100% Complete 09/06/19 • Resurfacing • On Murray Run Rd from Standing Stone Rd (PA 26) to Miller Twp Line, and on Gorsuch Rd from Oneida Twp line to Creek Crossing Rd (T-563) • Anticipated Traffic Control will consist of daylight flagging • Oneida & Miller Townships • New Enterprise Stone & Lime Co., Inc. • Part of the PA 305 to Cold Springs Rd Contract

23036 1023-02B Standing Stone Ck #2 100% Compete 09/30/19 • Bridge Replacement • On Alan Seegar Rd over prior changing to Forestry Road • Anticipated traffic control will be a Detour utilizing Alan Seeger Road), Stone Creek Road, Seeger Road, Rag Hollow Road, Greenwood Road (PA 305), McAlevys Fort Rd (PA 26), and Alan Seegar Rd, (19 miles) • Jackson Township • Prime Contractor: Redrock Construction, Inc.

Page 19 of 35 District 9-0 Southern Alleghenies RPO As of 10/07/2019

HUNTINGDON COUNTY CONSTRUCTION PROGRESS REPORT

MPMS SR – SEC PROJECT TITLE STATUS ANTICIPATED COMPLETION 106492 2005-01B SR 2005 Three Springs Bridge 90% Compete 11/12/19 • Superstructure replacement • On Elliots Run Rd from over Three Springs Creek at the intersection of Hudson Street • Anticipated Traffic Control will consist of a Detour utilizing Elliots Run Rd, Cherry Grove Church Rd, Waterfall Rd, Church St, Hudson St (9.0 miles) • Clay Township • Prime Contractor: Clearwater Construction, Inc. • Contractor is planning to seal some minor cracking in deck and overlay with epoxy shortly

110865 0869-09S D9 2019 HSIP HFST Contract 86% Complete* 11/04/19 • Placement of High Friction Surface Treatment (1,800 feet) • On Standing Stone Rd approximately 2.4 miles north of Huntingdon • Anticipated traffic control will consist of daylight flagging • Oneida Township • Prime Contractor: MEKIS Construction Corporation • Contractor expects to be in Hunting County in late Summer • Project is part of the Bedford County Contract and includes various routes in Blair, Cambria, Fulton, and Somerset Counties • *Contractor has completed the section on Standing Stone Rd approximately 2.4 miles north of Huntingdon), a section of PA 160 in Somerset County section will be completed in the Spring

23023 2001-01B Sideling Hill Crk #2 71% Compete 11/07/19 • Bridge Replacement • Selea Hollow Rd over Sideling Hill Creek near the intersection of Bratton Rd • Anticipated traffic control will be phased construction with signal • Clay Township • Prime Contractor: Susquehanna Valley Construction Corporation • Part of the PA655 Sideling Hill Creek Contract in Fulton Co. • Contractor waiting on deck cure, roadway tie ins to follow, expect to be open to traffic by mid-October

Page 20 of 35 District 9-0 Southern Alleghenies RPO As of 10/07/2019

HUNTINGDON COUNTY UPCOMING LETS

MPMS SR – SEC PROJECT TITLE ANTICIPATED LET ANTICIPATED COMPLETION 92696 0026-02B PA26 over Muddy Run Clvrt 4th Quarter 2019 Fall 2020 • Culvert Replacement • On Penn St (PA 26) over Muddy Run at 7th Street • Anticipated traffic control will be a Partial Intersection closure with Detour utilizing US 22 and South 4th St, Truck Detour will utilize US 22 and Penn St • Huntingdon Borough

88150 1009-01B Huntingdon Boro Muddy #2 4th Quarter 2019 Fall 2020 • Culvert Replacement • On Moore St over Muddy Run at intersection with 9th Street • Anticipated traffic control will be a north bound Detour utilizing 7th St, Mifflin St, and 10th St; south bound Detour utilizing 10th St and 7th St and a pedestrian Detour utilizing Moore St, 10th St, and 7th St • Huntingdon Borough

88151 1009-02B Huntingdon Boro Muddy #3 4th Quarter 2019 Fall 2020 • Culvert Replacement • On Moore St over Muddy Run at intersection with 11th Street • Anticipated traffic control will be a north bound Detour utilizing Moore St, 10th St, Washington St, 7th St, Warm Springs Ave, Oneida St, and 13th St; south bound Detour utilizing 13th St, Washington St, and 9th St. and a pedestrian Detour utilizing 12th St, Miflin St, and 10th St • Huntingdon Borough

109205 7206-358 T-358 Covered Bridge Road Bridge 4th Quarter 2019 Summer 2020 • Bridge Rehabilitation • On Covered Bridge Rd over Shade Creek at the intersection of Covered Bridge Rd with Groghan Pike (US 522) • Anticipated Traffic Control will consist of a detour • Cromwell Township • Part of a grouped letting for 11 non-composite deck replacements in Bedford (5), and Fulton (5) Counties

Page 21 of 35 District 9-0 Southern Alleghenies RPO As of 10/07/2019

HUNTINGDON COUNTY UPCOMING LETS

MPMS SR – SEC PROJECT TITLE ANTICIPATED LET ANTICIPATED COMPLETION 74445 1013-01B 2020 DF Huntingdon Box Culvert 1st Quarter 2020 Fall 2020 • Bridge Rehabilitation • On Ewing Rd over Henrys Run just southwest of intersection with Greenwood Rd • Anticipated traffic control will consist of a Detour utilizing Ewing Rd, Myton Rd, Shavers Creek Rd (PA 305), Greenwood Rd (PA 305), (8.0 miles) • Barree Township

23038 0913-01B Great Trough Crk Bridge 2 1st Quarter 2020 Fall 2020 • Bridge Replacement • On Main St over in Village of Robertsdale just north of Lincoln St • Anticipated traffic control will consist of phased construction • Wood Township

91662 0035-000 Richvale Rd to Juniata Co 1st Quarter 2020 Fall 2020 • Resurfacing (4.6 miles) • On Shade Valley Rd (PA 35) from Richvale Rd to Juniata County line • Anticipated Traffic Control will consist of daylight flagging • Tell Township

99322 0026-039 PA 26 – US 22 to Oneida Twp Line 1st Quarter 2020 Fall 2020 • Resurfacing (3.0 miles) • On Raystown Rd/ Ave/Penn St/Second St/Standing Stone Ave from Smithfield Towne Center to Oneida Township Line • Anticipated Traffic Control will consist of daylight flagging • Huntingdon Borough and Smithfield Township

96597 0022-012 Old Rt 22 Rd – PA 26 2nd Quarter 2020 Fall 2020 • Resurfacing (3.4 miles) • On William Penn Hwy from approximately 1.0 mile west of Lincoln Caverns to bridge over Raystown Rd • Anticipated Traffic Control will consist of daylight flagging • Porter and Smithfield Townships

Page 22 of 35 District 9-0 Southern Alleghenies RPO As of 10/07/2019

HUNTINGDON COUNTY UPCOMING LETS

MPMS SR – SEC PROJECT TITLE ANTICIPATED LET ANTICIPATED COMPLETION

105932 2025-001 SR 2025 – PA 747 to US 522 2nd Quarter 2020 Fall 2020 • Resurfacing (0.9 mile) • On East Shirley St from Division St (PA 747) to Groghan Pike (US 522) • Anticipated Traffic Control will consist of daylight flagging • Mount Union Borough and Shirley Township

113700 2003-000 SR 2003 – SR 1011 to PA 475 FDR 2nd Quarter 2020 Fall 2020 • Full Depth Reclamation • On Fort Littleton Rd from Fulton County line to Maddensville Pike (PA 475) • Anticipated traffic control will be Daylight Flagging • Springfield Township

23091 2009-02B SR 2009 Tuscarora Creek Br 3rd Quarter 2020 Summer 2021 • Bridge Replacement • On Tuscarora Creek Rd over Tuscarora Creek between Center Rd and Parsons Rd • Anticipated traffic control will be a Detour utilizing Parsons Rd, Mountain Foot Rd, Tuscarora Creek Rd (4.1 miles) • Tell Township

50725 0026-016 Jackson Corner Slide 4th Quarter 2020 Summer 2021 • Slide/sink hole repair under roadway • On Standing Stone Rd 0.25 mile north of the intersection of E Branch Rd to 0.50 mile south of the Cumminsville Ln (T-516) intersection • Anticipated traffic control will be a Detour utilizing Parsons Rd, Mountain Foot Rd, Tuscarora Creek Rd (4.1 miles) • Miller Township

106420 7411-131 Hill Valley Creek Bridge 4th Quarter 2020 Fall 2021 • Bridge Replacement • On South Moore St over Hill Valley Creek near the intersection of Liverpool Alley • Anticipated traffic control will be a temporary roadway • Mount Union Borough

Page 23 of 35 District 9-0 Southern Alleghenies RPO As of 10/07/2019

HUNTINGDON COUNTY UPCOMING LETS

MPMS SR – SEC PROJECT TITLE ANTICIPATED LET ANTICIPATED COMPLETION 105978 0022-01M US 22 – Mifflin Line to SR 1010 1st Quarter 2021 Fall 2021 • Resurfacing • On William Penn Hwy from Million Dollar Bridge to Mifflin Co Line • Anticipated Traffic Control will consist of daylight flagging • Mill Creek Borough, Henderson and Brady Townships

22990 0305-01B Herod Run Bridge 1st Quarter 2021 Fall 2021 • Bridge Replacement • On Greenwood Rd over Herod Run just adjacent to Yoder Rd (T-532) • Anticipated traffic control will be a Detour utilizing Greenwood Rd (PA 305), Standing Stone Rd (PA 26), Wesley Chapel Rd and Greenwood Rd (9.9 miles) • Jackson Township

22961 0747-001 Hill Valley Creek Bridge #2 4th Quarter 2021 Fall 2022 • Bridge replacement/rehabilitation (TBD) • On Hundred Springs Rd (PA 747) over Hill Valley Creek 0.25 miles from Christoff Rd (T-505) • Anticipated Traffic Control TBD • Shirley Township

23104 0641-01B PA 641 Trib Shade Creek 4th Quarter 2021 Fall 2022 • Culvert replacement/rehabilitation • On Neelyton Rd (PA 641) over Tributary to Shade Creek 0.5 mile south of intersection with Shade Valley Rd (PA 35) • Anticipated Traffic Control TBD • Dublin Township

23105 0641-02B PA 641/Shade Creek 4th Quarter 2021 Fall 2022 • Culvert replacement/rehabilitation • On Neelyton Rd (PA 641) over Branch of Shade Creek 0.65 mile south of intersection of Dell Rd (T-319) • Anticipated Traffic Control TBD • Dublin Township Page 24 of 35 District 9-0 Southern Alleghenies RPO As of 10/07/2019

SOMERSET COUNTY CONSTRUCTION PROGRESS REPORT

MPMS SR – SEC PROJECT TITLE STATUS ANTICIPATED COMPLETION 105982 4043-001 SR 4041 to PA 403 100% Complete 04/29/19 • Resurfacing • On West Campus Ave from Soap Hollow Rd to Main St • Traffic control will consist of daylight flagging • Conemaugh Township • Prime Contractor: HRI, Inc.

48072 0160-022 Wellersburg Safety Improvements 100% Complete 06/28/19 • Extension of existing truck pull-off area and associates signage • On Cumberland Hwy at the top of the mountain • Traffic control will consist of daylight flagging • Southampton Township • Prime Contractor: New Enterprise Stone & Lime Co., Inc.

96059 7219-640 T-640 Reffner Rd Br 100% Complete 10/30/19 • Bridge rehabilitation – new bridge deck • On Reffner Rd over Wells Creek near the intersection of Mosteller Rd • Traffic control will consist of a detour utilizing Reffner Road, West Wind Road, Stoystown Rd (PA 281), Welsh Hill Rd, and Coleman Station Road (3.7 miles) • Quemahoning Township • Prime Contractor: Pugliano Construction Co., Inc. • Part of the T-323 Tub Mill Run Rd Br contract

96639 2033-DF1 DF–Brthrtn Rd-Coleman Stn Rd (FDR) 100% Complete 09/18/19 • Full Depth Reclamation • On Willkow Rd from Glades Pike (PA 31) to Brotherton Rd and on Shaffer Rd From Brotherton Rd to Coleman Station Rd • Anticipated traffic control will be Daylight Flagging • Stonycreek Township • Prime Contractor: New Enterprise Stone & Lime Co., Inc.

Page 25 of 35 District 9-0 Southern Alleghenies RPO As of 10/07/2019

SOMERSET COUNTY CONSTRUCTION PROGRESS REPORT

MPMS SR – SEC PROJECT TITLE STATUS ANTICIPATED COMPLETION 107919 3008-DF1 DF–SR 3008 – PA 281 to Water Level Rd 100% Complete 10/15/19 • Resurfacing (5.2 miles) • On West Mud Pike from New Centerville Rd (PA 281) to Water Level Rd • Anticipated traffic control will be Daylight Flagging • Shade Township

105931 0030-003 US 30 – US 219 to PA 985 95% Complete 09/06/19 • Resurfacing • On Lincoln Hwy/Pitt St from Flight 93 Memorial Hwy to Somerset Pike • Traffic control will consist of daylight flagging • Jenner Township and Jennerstown Borough • Prime Contractor: New Enterprise Stone & Lime Co., Inc. • Contractor currently completing punch list items and cleanup

96053 7206-323 T-323 Tub Mill Run Rd 95% Complete 10/30/19 • Bridge rehabilitation – new bridge deck • On Tub Mill Run Rd over Tub Mill Run Rd approximately ½ mile east of intersection with Oak Dale Rd • Traffic control will consist of a detour utilizing Tub Mill Road, Springs Road (PA 669) and Oak Dale Road • Elk Lick Township • Prime Contractor: Pugliano Construction Co., Inc. • Contractor performing mortar joint repairs

108264 2047-001 Meyersdale Intrchng to US 219 91% Complete 12/13/19 • Resurfacing and slide repair • On Mason Dixon Highway from the northern Meyersdale Interchange to the southern Meyersdale interchange, slide is located in the guiderail section between Johnny Popper Rd and SB pull-off adjacent to NS Railroad signal structure • Traffic control will consist of daylight flagging • Summit Township and Meyersdale Borough • Prime Contractor: Quaker Sales Corporation • Contractor currently placing signage and cleanup one drainage pipe to line in November

Page 26 of 35 District 9-0 Southern Alleghenies RPO As of 10/07/2019

SOMERSET COUNTY CONSTRUCTION PROGRESS REPORT

MPMS SR – SEC PROJECT TITLE STATUS ANTICIPATED COMPLETION 74493 4004-01B 2019 DF Somerset Box Culvert 90% Complete 10/25/19 • Culvert replacement • On Bluebird Spring Rd over Quemahoning Creek 0.9 mile east of intersection with Quecreek Rd • Traffic control will consist of a detour utilizing Bluebird Spring Rd, Emert Rd, and Quecreek Rd • Lincoln Township • Prime Contractor: Pugliano Construction Co., Inc. • Contractor has completed culvert, guiderail to be completed by October 25th

106427 7201-858 T-858 Braddocks Run Bridge 85% Complete 10/30/19 • Bridge rehabilitation – new bridge deck • On Braddocks Run Rd over Braddocks Run approximately 1.5 miles south of intersection with US 40 • Traffic control will consist of a detour utilizing Braddock Run Rd, Polk Hill Rd), and National Pike (US 40) • Addison Township • Prime Contractor: Pugliano Construction Co., Inc. • Contract to pave roadway tie-ins on October 11, then place guiderail, pavement markings and signage

23568 0403-13B PA 403/Pokeytown Run 82% Complete 11/13/19 • Bridge replacement • On Whistler Rd over Pokeytown Run just north of the intersection of Wilbur Rd • Traffic control will be phased construction with signal • Shade Township • Prime Contractor: Charles J. Merlo, Inc. • Contractor has completed replacing bridge and plans to finish paving by October 15th • Contract includes Fallen Timber Run Bridge and PA 403 Dixie Run Culvert projects

23449 0403-12B Fallen Timber Run Bridge 82% Complete 11/13/19 • Bridge replacement • On Barn St over Fallen Timber Run between Grove Ave and South St • Traffic control will be phased construction with signal • Hooversville Borough • Prime Contractor: Charles J. Merlo, Inc. • Contractor has completed replacing bridge and plans to finish paving by October 15th • Part of the PA 403 /Pokeytown Run contract Page 27 of 35 District 9-0 Southern Alleghenies RPO As of 10/07/2019

SOMERSET COUNTY CONSTRUCTION PROGRESS REPORT

MPMS SR – SEC PROJECT TITLE STATUS ANTICIPATED COMPLETION 74440 0403-13B PA 403 Dixie Run Culvert 82% Complete 11/13/19 • Bridge replacement • On Barn St over Dixie Run just north of the intersection of Somerset St • Traffic control will be phased construction with signal • Hooversville Borough • Prime Contractor: Charles J. Merlo, Inc. • Contractor has completed replacing bridge and plans to finish paving by October 15th • Part of the PA 403 /Pokeytown Run contract

113399 0219-45E US 219 Boynton Slide 75% Complete 10/30/19 • Slide correction • On Mason Dixon Hwy near intersection with Moser Rd • Anticipated traffic control will be Daylight Flagging • Elk Lick Township • Prime Contractor: C. H. & D. Enterprises Inc. • Contractor is backfilling recently driven piles and will begin to rebuild the roadway shortly

21592 3010-004 Mud Pike Improvements 12% Complete 11/13/20 • Highway reconstruction including widening and resurfacing, bridge replacement, culvert replacement and a 60” pipe replacement, realignment of Garret Shortcut Road curve just south of East Mud Pike intersection at the former Shaffer Dairy to improve sight distance, addition of a north bound left turn lane off Berlin Plank Rd onto East Mud Pike Rd • On East Mud Pike Rd beginning at the intersection of Garrett Shortcut Rd continuing east to Berlin Plank Rd • Traffic control for Bridge, Culvert and Pipe replacements will consist of a Detours utilizing Mud Pike, Garrett Shortcut Rd, Berlin Plank Rd, Mud Pike; other construction activities will be daylight flagging • Brothersvalley Township • Prime Contractor: New Enterprise Stone & Lime Co., Inc. • Contractor has completed and paved the new turn lane from the Berlin Plank Rd onto E Mud Pike and it is open to traffic

Page 28 of 35 District 9-0 Southern Alleghenies RPO As of 10/07/2019

SOMERSET COUNTY CONSTRUCTION PROGRESS REPORT

MPMS SR – SEC PROJECT TITLE STATUS ANTICIPATED COMPLETION 91671 2047-004 Brotherton Rd to Berlin/Somerset 5% Complete 09/10/21 • Resurfacing and bridge rehabilitations • On Berlin Plank Rd from Main St (PA 31) in Somerset to Washington St in Berlin • Traffic control will consist of daylight flagging for the resurfacing, phased with signal for the bridge rehabilitations • Somerset Borough, Berlin Boroughs, and Somerset Township • Prime Contractor: HRI, Inc. • Contractor is currently on winter shutdown

108289 4023-003 SR 4023 - PA 985 to PA 601 NTP 09/09/19* 06/03/20 • Resurfacing • On Million Dollar Hwy and Blacks Hill Rd from Somerset Pike (PA 985) to Penn Ave (PA 601) • Traffic control will consist of daylight flagging for the resurfacing • Boswell and Jennerstown Boroughs, and Jenner Township • Prime Contractor: Grannas Bros Stone & Asphalt Co., Inc. • *Contractor has not commenced construction activities, may delay until next year

Page 29 of 35 District 9-0 Southern Alleghenies RPO As of 10/07/2019

SOMERSET COUNTY UPCOMING LETS

MPMS SR – SEC PROJECT TITLE ANTICIPATED LET ANTICIPATED COMPLETION 107165 4008-01B 2020 DF Somerset Box Culvert 1st Quarter 2020 Fall 2020 • Culvert replacement • On Beam Church Rd over Spruce Run just west of intersection of Tipton Rd • Traffic control will consist of a Detour utilizing Beam Church Rd, Somerset Pike, Schoolhouse Rd, Keysertown Rd, and Beam Church Rd (8.25 miles) • Jenner Township

111482 2030-BRP Berlin Revitalization Project – Phs II 2nd Quarter 2020 Fall 2020 • Sidewalk restoration • On Main St from Cumberland St to Broadway St • Traffic Control: Pedestrian detours will be utilized • Berlin Borough

96648 4009-DF1 DF – Edgewood Ave to Byers Rd 2nd Quarter 2020 Fall 2020 • Resurfacing (6.1 miles) • On N Edgewood Ave/Felgar Rd/Husband Rd from W Main St to Bakersville Edie Rd • Anticipated traffic control will be Daylight Flagging • Somerset Borough, Lincoln and Somerset Township

105937 4016-DF1 DF - SR 4016 – PA 985 to SR 4035 2nd Quarter 2020 Fall 2020 • Resurfacing • On Moonlight Park Rd from Somerset Pike (PA 281) to Woodstown Hwy • Anticipated traffic control will be Daylight Flagging • Conemaugh Township

107213 4053-001 SR 4053 – US 30 to SR 4028 2rd Quarter 2020 Fall 2020 • Resurfacing • On Main St from northern connection with Lincoln Hwy (US 30) to Stoystown Rd (PA 281) • Anticipated traffic control will consist of daylight flagging • Stoystown Borough and Quemahoning Township

Page 30 of 35 District 9-0 Southern Alleghenies RPO As of 10/07/2019

SOMERSET COUNTY UPCOMING LETS

MPMS SR – SEC PROJECT TITLE ANTICIPATED LET ANTICIPATED COMPLETION 105939 4028-000 SR 4028 - US 30 to PA 281 2nd Quarter 2020 Fall 2020 • Resurfacing • On Moonlight Park Rd from Somerset Pike (PA 281) to Woodstown Hwy • Anticipated traffic control will be Daylight Flagging • Conemaugh Township

92699 0985-01B PA 985 Trib Beaverdam Rn Br 3rd Quarter 2020 Fall 2021 • Bridge replacement • On Somerset Pike over Tributary to Beaverdam Run just south of the intersection of Pelesky Rd • Traffic control will consist of a Detour utilizing Somerset Pike (PA 985), Lincoln Highway (US 30), Million Dollar Highway, and Somerset Pike (PA 985), (6.0) miles • Jenner Township

92700 0985-02B PA 985 Trib Bens Crk Br 3rd Quarter 2020 Fall 2021 • Culvert replacement • On Somerset Pike over Tributary to Bens Creek near the intersection of Brehm Rd (T-586) • Traffic control will consist of phased construction with signal • Jenner Township

105960 0000-911 Sept 11th National Memorial Trail 3rd Quarter 2020 Summer 2021 • Trail construction • Beginning at the section of the Great Allegheny Passage trail at Garrett and continuing north 1.25 miles toward Berlin • Summit and Brothersvalley Township

74476 2016-01B Rhoads Creek Bridge 3rd Quarter 2020 Summer 2021 • Bridge replacement • On Rockdale Rd over Rhoads Creek Just north of Old Dirt Rd • Traffic control will consist of a Detour utilizing Rockdale Rd, Fox Rd, Markleton School Rd, and Rockdale Rd (4.7) miles • Black Township

Page 31 of 35 District 9-0 Southern Alleghenies RPO As of 10/07/2019

SOMERSET COUNTY UPCOMING LETS

MPMS SR – SEC PROJECT TITLE ANTICIPATED LET ANTICIPATED COMPLETION 105997 3015-02B Rockwood Trib Coxes Creek #1 3rd Quarter 2020 Fall 2021 • Bridge replacement • On Water Level Rd over Tributary to Coxes Creek southwest of the Coalyard Rd intersection • Traffic control will consist of a Detour utilizing Water Level Rd, Gebhart Rd, West Mud Pike, and Water Level Rd (4.8) miles • Milford Township

105998 3015-03B Rockwood Trib Coxes Creek #2 3rd Quarter 2020 Fall 2021 • Bridge replacement • On Water Level Rd over Tributary to Coxes Creek northeast of intersection with Coalyard Rd • Traffic control will consist of a Detour utilizing Water Level Rd, Gebhart Rd, West Mud Pike, and Water Level Rd (4.8) miles • Milford Township

96607 0403-001 Wilbur Rd – US 219 3rd Quarter 2020 Fall 2021 • Resurfacing (13.8 miles) • On Whistler Rd/Barn St/Whistler Rd/Border St/N & S Main St/Tire Hill Rd (PA 403) from Wilbur Rd to the US 219 • Anticipated traffic control will be Daylight Flagging • Hooversville Borough, Shade, Quemahoning, Paint, and Conemaugh Townships

56644 3039-02B Triple Creek Rd over Allen Creek 4th Quarter 2020 Fall 2021 • Bridge replacement/rehabilitation • On Triple Creek Rd over Allen Creek approximately ½ mile from the intersection of Pritts Distillery Rd (T-545) • Traffic control will consist of phased construction with signal • Middlecreek Township 113624 0219-46B McNally Bridge Preservation 4th Quarter 2020 Fall 2021 • Bridge preservation • On Flight 93 Memorial Highway Hwy over CSX Railroad and Stonycreek River • Anticipated traffic control will be phase construction • Conemaugh Township

23434 0160-08B Dark Shade Creek Bridge 4th Quarter 2020 Fall 2021 Page 32 of 35 District 9-0 Southern Alleghenies RPO As of 10/07/2019

SOMERSET COUNTY UPCOMING LETS

MPMS SR – SEC PROJECT TITLE ANTICIPATED LET ANTICIPATED COMPLETION • Bridge replacement • On Sunshine Ave over Dark Shade Creek near the Fire Hall • Anticipated traffic control will be a Detour utilizing Sunshine Ave, Central Ave, Lambert St, School Rd, McGregor Ave, Dark Shade Dr, Main St and Sunshine Ave (3.0 miles) • Central City Borough

111994 4025-03B 2021 DF Somerset Box Culvert 1st Quarter 2021 Fall 2021 • Culvert replacement • On Ralphton Rd over Two Mile Run near US 219 over overpass • Anticipated traffic control will be a Detour utilizing Ralphton Rd, Penn Ave/Front St, Lincoln Hwy, and Ralphton Rd (6.5 miles) • Quemahoning Township

96599 0030-016 PA 160 to Bedford Co Line 1st Quarter 2021 Fall 2021 • Resurfacing (3.9 miles) • On Lincoln Highway from Huckleberry Hwy/Rock Cut Rd intersection east to the Bedford County Line • Anticipated traffic control will consist of Daylight Flagging • Shade and Stonycreek Townships

92702 0031-01B PA31 Trib Stonycreek Br 1 1st Quarter 2021 Fall 2021 • Bridge replacement • On Glades Pike over Stonycreek River ¼ mile east of Beulah Rd • Traffic control will consist of Detour utilizing Glades Pike (PA31), Beulah Rd (PA160), Main St, Broadway St, Brotherton Rd, Glades Pike (7.0 miles) • Stonycreek and Brothersvalley Townships

23566 0601-01B PA 601/Shade Creek 1st Quarter 2021 Fall 2021 • Super Structure replacement • On Seanor Rd over Shade Creek between River Rd and Fyock Dr intersections in Village of Seanor • Anticipated traffic control will be Detour utilizing Seanor Rd, Scalp Ave (PA56), Flight 93 Memorial Hwy (US219), Main St (PA403), Seanor Rd (15.0 miles) • Paint Township

Page 33 of 35 District 9-0 Southern Alleghenies RPO As of 10/07/2019

SOMERSET COUNTY UPCOMING LETS

MPMS SR – SEC PROJECT TITLE ANTICIPATED LET ANTICIPATED COMPLETION 112568 0031-016 PA 31 & SR 3029 Under 8ft Culverts 1st Quarter 2021 Fall 2021 • Culvert replacements (2) • On Glades Pike (PA 31) just east of Stahl Rd over unnamed stream in Jefferson Township • On Copper Kettle Hwy just west of Chippewa Rd over Middle Creek in Milford Township • Anticipated traffic control will be Daylight Flagging

106472 4002-002 SR 4002 – SR 4013 to SR 4015 1st Quarter 2021 Fall 2021 • Resurfacing (3.0 miles) • On School House Rd from Keysertown Rd to Quecreek Rd • Anticipated traffic control will be Daylight Flagging • Lincoln Township

105110 0219-035 US 219 Salisbury Rockfall 1st Quarter 2021 Fall 2021 • Slide correction • On from Oester Lane (T-446) to Old Route 219 (T-444) • Anticipated traffic control phased construction with signal • Salisbury Borough

96647 4005-001 PA 31 to Westmoreland County 2nd Quarter 2021 Fall 2021 • Resurfacing (9.8 miles) • On Coxes Creek Rd from Glades Pike to Westmoreland County Line • Anticipated traffic control will be Daylight Flagging • Somerset, Jefferson and Lincoln Townships

92711 0040-002 Addison Resurface 3rd Quarter 2021 Fall 2021 • Resurfacing • On National Pike (US 40) from the Maryland State Line to Fayette Co. Line (6.2 miles) • Anticipated traffic control will be Daylight Flagging • Addison Borough and Addison Township

Page 34 of 35 District 9-0 Southern Alleghenies RPO As of 10/07/2019

SOMERSET COUNTY UPCOMING LETS

MPMS SR – SEC PROJECT TITLE ANTICIPATED LET ANTICIPATED COMPLETION 74452 1007-04B North Shanksville Trib 4th Quarter 2020 Fall 2021 • Culvert replacement • On Lambertsville Rd over Tributary of Stonycreek River .2 mile south of the intersection with Covered Bridge Rd (T-565) • Anticipated traffic control will be a Detour utilizing Lambertsville Rd, Buckstown Rd, Lincoln Hwy, Huckleberry Hwy, Cornerstone Rd, Main St., Bridge St., North St., and Lambertsville Rd (14.4 miles) • Stonycreek Township

91444 1007-04B N. Shanksville Grove Run 4th Quarter 2020 Fall 2021 • Culvert replacement • On Lambertsville Rd over Grove Run 0.55 mile south of Flight 93 entrance road • Anticipated traffic control will be a Detour utilizing Lambertsville Rd, Lincoln Hwy, Buckstown Rd, and Lambertsville Rd (11.2 miles) • Stonycreek Township

Page 35 of 35 District 9-0 Southern Alleghenies RPO As of 10/07/2019