BEDFORD COUNTY CONSTRUCTION PROGRESS REPORT

MPMS SR – SEC PROJECT TITLE STATUS ANTICIPATED COMPLETION 107208 2023-DF1 DF – SR 2021 to Dead End 100% Complete 06/20/19 • Resurfacing 1.68 miles • On Ott Town Rd from Yellow Rd to Cul-de-sac at end of roadway • Anticipated traffic control will consist of daylight flagging • Snake Spring Township

109159 7220-307 Street Road over Flintstone Creek 100% Complete 09/02/20 • Bridge rehabilitation • On Street Rd over Flintstone Creek Rd • Anticipated traffic control will consist of a Detour utilizing Flintstone Creek Rd NE (MD), W Flintstone Creek Rd NE (MD), Street Rd NE (MD), (4.4 miles) • Southampton Township • Prime Contractor: George S. Hann & Son, Inc. • Contract includes five other local bridges in Bedford Co. & two in Huntingdon Co.

96037 7227-584 T-584 Reed Road Bridge 100% Complete 09/02/20 • Bridge rehabilitation • On Reed Rd over Barefoot Run near intersection of Quaker Valley Rd (PA 56) • Anticipated traffic control will consist of a Detour utilizing Reed Rd, Quaker Valley Rd, King St Clair Rd (PA 96), Gordon Hall Rd, and Reed Rd • West St Clair Township • Prime Contractor: George S. Hann & Son, Inc. • Part of the Street Road over Flintstone Creek contract

96034 7216-328 T-328 Moss Road Bridge 100% Complete 09/02/20 • Bridge rehabilitation • On Moss Rd over Piney Creek east of the intersection of Clear Ridge Rd (PA 26) • Anticipated traffic control will consist of a detour utilizing Moss Rd, Clingerman Rd, Clear Ridge Rd (PA 26), and Moss Rd, (4.2 miles) • Mann Township • Prime Contractor: George S. Hann & Son, Inc. • Part of the Street Road over Flintstone Creek Contract

Page 1 of 33 District 9-0 Southern Alleghenies RPO As of 06/24/2019

BEDFORD COUNTY CONSTRUCTION PROGRESS REPORT

MPMS SR – SEC PROJECT TITLE STATUS ANTICIPATED COMPLETION 96033 7216-314 T-314 Barnes Road Bridge 85% Complete 09/02/20 • Bridge rehabilitation • On Barnes Rd over Crooked Run, ¾ mile north of intersection with State Line Rd (T-326) • Anticipated traffic control will consist of a Detour utilizing Barnes Rd, Crooked Run Rd, Barnes Rd, East Shipley Rd (MD), National Hwy (US40)(MD),N Orleans Rd (MD), Clear Ridge Rd (PA26), (8.7 miles) • Mann Township • Prime Contractor: George S. Hann & Son, Inc. • Part of the Street Road over Flintstone Creek Contract • Contractor currently waiting on cure time for recently poured deck, 2 weeks

91440 0915-03B Hopewell Bridge Replace 54% Complete 11/21/19 • Bridge Replacement and intersection realignment • On Front St over Raystown Branch of at the intersection of Raystown Rd (PA 26) • Hopewell Township, Broad Top Township and Hopewell Borough • Prime Contractor: HRI, Inc. • Contractor has completed stabilization of rock hillside and installed mesh netting • Abutment #1, and piers 1 & 2 are complete, shoring being placed for abutment #2

21458 1036-04B Defiance Six Mile Run Bridge 42% Complete 11/01/19 • Bridge Replacement • On Six Mile Run Rd over Six Mile Rub near the intersection of Hitchens Rd (T-578) • Anticipated traffic control will consist of phased construction with signal, College St. will be detoured one block • Broad Top Township • Prime Contractor: Wen-Brooke Contracting Inc. • Contractor placed deck for phase 1 on June 21st

Page 2 of 33 District 9-0 Southern Alleghenies RPO As of 06/24/2019

BEDFORD COUNTY CONSTRUCTION PROGRESS REPORT

MPMS SR – SEC PROJECT TITLE STATUS ANTICIPATED COMPLETION 88571 0026-13B PA 26/36 Culvert Replacements 29% Complete 07/30/20 • Culvert replacements • On Raystown Rd (PA 26)(3) and one culvert on Woodbury pike (PA 36)(1) • Anticipated traffic control will consist of temporary roadways for both routes • Hopewell Township (Cottles Corner) • Prime Contractor: New Enterprise Stone & Lime Co., Inc. • Contractor completed culvert and currently finish paving on Woodbury Pike, to begin working on the Raystown Rd culverts

88128 2029-04B Trib Juniata River Bridge 18% Complete 09/04/19 • Bridge rehabilitation • On East Mattie Rd over Tributary of Raystown Branch of Juniata River near intersection of South Main Street • Traffic control will consist of a Detour utilizing East Mattie Rd, South Breezewood Rd, I-70 S, Old 126 Rd, South Breezewood Rd, Brush Creek Rd, and E Mattie Rd, [10.8 Miles] • East Providence Township • Prime Contractor: Cottle's Asphalt Maintenance, Inc. • Contractor placed concrete for new box floor June 21st

21515 1005-05B South Cemetery Bridge 16% Complete 08/29/19 • Bridge replacement • On Churchview Rd over Beaver Creek near intersection with Salemville Rd • Anticipated traffic control will consist of a Detour utilizing Churchview Rd, Salemville Rd, Hershberger Rd, Chestnut St, Church St, Brumbaugh Rd (PA 869, Woodbury Pike (PA 36), and Town Hill Rd [9.5 miles] • South Woodbury Township • Prime Contractor: Cottle's Asphalt Maintenance, Inc. • Contractor has implemented Detour, cast-in-place bridge is to be delivered and begin crane installation week of July 1st

Page 3 of 33 District 9-0 Southern Alleghenies RPO As of 06/24/2019

BEDFORD COUNTY CONSTRUCTION PROGRESS REPORT

MPMS SR – SEC PROJECT TITLE STATUS ANTICIPATED COMPLETION 88126 1019-01B Ravers Run Culvert NTP issued 10/05/18 09/13/19 • Culvert Replacement • On Pinchot Rd over Ravers Run near the intersection of Carberry Road • Anticipated traffic control will consist of Detour utilizing Pinchot Rd, Raystown Rd (PA26), and N Woodcock Valley Rd, (13.7 miles) • Liberty Township • Prime Contractor: New Enterprise Stone Lime Co., Inc. • At the request of Broad Top Twp and Hopewell Borough this project has been moved to 2020 construction

96032 7210-413 T-413 Grasser Rd Br Rehab NTP issued 12/03/18 09/02/20 • Bridge rehabilitation • On Grasser Rd over Raystown Branch of Juniata River at the intersection of New Baltimore Rd • Anticipated traffic control will consist of single lane phased construction with temporary traffic signal • Juniata Township • Prime Contractor: George S. Hann & Son, Inc. • Part of the Street Road over Flintstone Creek Contract • Contractor plans on starting this structure late summer

96036 7218-473 T-473 Rose Road Bridge NTP issued 12/03/18 09/02/20 • Bridge rehabilitation • On Rose Rd over Shawnee Creek approximately ½ mile north of the US30 intersection • Anticipated traffic control will consist of a detour utilizing Rose Rd, Lincoln Highway (US 30), Hoover Rd and Rose Rd, (2.4 miles) • Napier Township • Prime Contractor: George S. Hann & Son, Inc. • Part of the Street Road over Flintstone Creek Contract • Contractor plans on starting this structure late summer

Page 4 of 33 District 9-0 Southern Alleghenies RPO As of 06/24/2019

BEDFORD COUNTY CONSTRUCTION PROGRESS REPORT

MPMS SR – SEC PROJECT TITLE STATUS ANTICIPATED COMPLETION 91606 0030-002 US30 Breezewood Resurface 21% Complete 09/06/19 • Resurfacing, concrete patching, high friction surface treatment, base repairs, drainage improvements, guide rail, signing and traffic signal upgrades. • On Lincoln Highway from West end of concrete in East Providence Twp, Bedford Co. to east end of climbing lane taper in Brush Creek Twp., Fulton Co. • Anticipated traffic control will consist of night time lanes closures in business district, daylight flagging • Prime Contractor: Cottle's Asphalt Maintenance, Inc. • Contractor has completed patching, working on spall repairs and drainage up grades • Pipework, concrete grinding, and shoulder widening in bituminous section to begin after July 4th

110865 0869-09S D9 2019 HSIP HFST 16% Complete 11/04/19 • Placement of High Friction Surface Treatment • On Brumbaugh Mtn Rd from King Twp Line (Top of mountain) 0.4 miles toward intersection with PA 867 (Lafayette Rd); also on Sproul Mtn Rd through the curves up mountain approximately 0.7 miles from the intersection with Hoover Rd • Anticipated traffic control will consist of daylight flagging • Bloomfield and South Woodbury Townships (Bedford County) • Prime Contractor: MEKIS Construction Corporation • Contractor has completed Sproul Mtn Rd section, working on the Brumbaugh Rd section • Contract includes various routes in Blair, Cambria, Fulton, Huntingdon and Somerset Counties

110863 0070-08S CMB I-70 Town Hill to Tpike Ramps 50% Complete 09/25/19 • Installation of High Tension Cable Median Barrier • Anticipated traffic control will consist of short-term lane closures • Various Municipalities in Bedford & Fulton Counties • Prime Contractor: Cottle’s Asphalt Maintenance, Inc. • Contractor to begin drilling holes for posts 1st week of August and start stringing cable at the end of August

Page 5 of 33 District 9-0 Southern Alleghenies RPO As of 06/24/2019

BEDFORD COUNTY CONSTRUCTION PROGRESS REPORT

MPMS SR – SEC PROJECT TITLE STATUS ANTICIPATED COMPLETION 21466 1015-02B 2019 DF Bedford Box Culvert 5% Complete 10/01/19 • On Replogle Schoool Rd over Tributary to Three Springs Run near intersection of Mill St • Anticipated traffic control will consist of a detour utilizing Replogle School Rd, Potter Creek Rd (PA 868), Woodbury Pike (PA 869) and Replogle School Rd, (6.3 miles) • South Woodbury Township • Prime Contractor: Department Forces • Contractor expects Box delivery by mid-July

106489 1020-01B SR 1020 Pipers Run Bridge NTP issued 12/28/18 08/09/19 • Superstructure replacement, minor roadway approach work and guiderail upgrades • On West Cypher Rd over Pipers Run • Anticipated traffic control will consist of a detour utilizing West Cypher Rd (T-532), Piper Hill Rd (T-528), Snyder Rd (T-537), Recreational Dr (T-530), and West Cypher Rd (T-532), (2.7 miles) • Hopewell Township • Prime Contractor: Wen-Brooke Contracting Inc. • Contractor has removed old super structure, and poured new caps on existing abutments

21464 3003-01B Evitts Creek Bridge NTP 05/13/19 10/31/19 • Bridge replacement • On Lake Gordon Rd over Evitts Creek east of intersection with Pine Ridge Rd • Anticipated traffic control will consist of a Detour utilizing Lake Gordon Road, Hazen Road (MD/PA), Smouses Mill Road (MD 807), Bedford Valley Road (US 220-MD), Pine Ridge Road (MD/PA), and Lake Gordon Rd, (6.5 miles) • Cumberland Valley Township • Prime Contractor: Beech Construction, Inc. • Contractor has implemented the Detour is working on E &S controls and planning to demolish existing structure soon after July 1st

Page 6 of 33 District 9-0 Southern Alleghenies RPO As of 06/24/2019

BEDFORD COUNTY CONSTRUCTION PROGRESS REPORT

MPMS SR – SEC PROJECT TITLE STATUS ANTICIPATED COMPLETION 110219 0326-005 PA 326 – Main Rd to US30 Anticipated NTP 07/22/19 10/15/19 • Resurfacing (5.4 miles) • On Egolf Rd from US 30 to Main Rd • Anticipated traffic control will consist of daylight flagging • Colerain and Snake Spring Townships • Prime Contractor: New Enterprise Stone & Lime Co., Inc.

Page 7 of 33 District 9-0 Southern Alleghenies RPO As of 06/24/2019

BEDFORD COUNTY UPCOMING LETS

MPMS SR – SEC PROJECT TITLE ANTICIPATED LET ANTICIPATED COMPLETION 111481 0000-HBT H&BT Rail Trail Extension 3rd Quarter 2019 Fall 2019 • On old H&BT railroad alignment from the Riddlesburg trail head north towards the Warriors Path State Park • Trail section will be off line until completion of project • Broad Top Township

110220 2006-DF1 DF - Fulton Co Line to Robinsonville Rd 3rd Quarter 2019 Fall 2019 • Resurfacing (1.3 miles) • On Amaranth Rd from Fulton County Line to Robinsonville Rd • Traffic control will consist of daylight flagging • Colerain & Snake Spring Townships

107206 2008-DF1 DF - SR 2008 – SR 2007 – SR 2011 3rd Quarter 2019 Fall 2019 • Resurfacing (1.4 miles) • On Turkey Ridge Rd from Big Creek Rd to Robinsonville Rd • Traffic control will consist of daylight flagging • Monroe Township

108158 2010-DF1 DF - SR 2010 – PA 26 – SR 2009 3rd Quarter 2019 Fall 2019 • Resurfacing (3.5 miles) • On Pleasant Union Rd from Clear Ridge Rd (PA26) to Piney Creek Rd • Traffic control will consist of daylight flagging • Monroe Township

74411 4009-01B Dunnings Creek Trib Bridge 4th Quarter 2019 Fall 2020 • Bridge replacement • On Business 220 over Tributary to Dunnings Creek just south of intersection with Belden Road • Anticipated traffic control will consist of a Detour utilizing Business 220, I-99, Quaker Valley Rd and Business 220 (6.5 miles) • Bedford Township • Project includes the Brush Run Bridge just south of the entrance to the Bedford County Business Park

Page 8 of 33 District 9-0 Southern Alleghenies RPO As of 06/24/2019

BEDFORD COUNTY UPCOMING LETS

MPMS SR – SEC PROJECT TITLE ANTICIPATED LET ANTICIPATED COMPLETION 88133 4009-02B Brush Run Bridge 4th Quarter 2019 Fall 2020 • Bridge replacement • On Business Route 220 over Brush Run just south of intersection with Commerce Court • Anticipated traffic control will consist of a Detour utilizing Business 220, I-99, Quaker Valley Rd and Business 220 (6.5 miles) • Bedford Township • Part of the Dunnings Creek Trib Bridge

109816 0099-012 Turnpike to Sproul/Claysburg 4th Quarter 2019 Fall 2020 • Resurfacing and guiderail upgrades • On Bud Shuster Highway from Turnpike Interchange (Exit #1) north to the Sproul/Claysburg Interchange (Exit #15) • Anticipated traffic control will consist of one-lane closures • Bedford, East St Clair, King and Kimmel Townships; Greenfield Township, Blair County

96030 7202-609 T-609 Snyder Creek Road Bridge 4th Quarter 2019 Fall 2020 • Bridge rehabilitation • On Snyder Creek Road (T-609) over Potter Creek at the intersection of Potter Creek Rd (PA868) • Anticipated traffic control will consist of a detour utilizing Potter Creek Rd (PA 868), Cowan School Rd, Furry Dr and Snyder Creek Rd, (3.0 miles) • Bloomfield Township • Part of a grouped letting for 11 non-composite deck replacements in Bedford (5), Fulton (5) and Huntingdon (1) Counties

96031 7204-357 T-357 Harietta Lane Bridge 4th Quarter 2019 Fall 2020 • Bridge rehabilitation • On Harietta Lane over Cove Creek west of the intersection of Rose Lane • Anticipated traffic control will consist of a detour utilizing Harietta Lane, Valley Rd, Centennial Rd and Harietta Lane, (6.8 miles) • Colerain Township • Part of a grouped letting for 11 non-composite deck replacements in Bedford (5), Fulton (5) and Huntingdon (1) Counties Page 9 of 33 District 9-0 Southern Alleghenies RPO As of 06/24/2019

BEDFORD COUNTY UPCOMING LETS

MPMS SR – SEC PROJECT TITLE ANTICIPATED LET ANTICIPATED COMPLETION 22045 7207-545 Oppenheimer Road Bridge 4th Quarter 2019 Fall 2020 • Bridge rehabilitation • On Oppenheimer Hollow Road over Oppenheimer Run just north of Younts Rd west of the intersection Rose Lane (T-376) • Anticipated traffic control will consist of a Detour utilizing Oppenheimer Hollow Rd, Kauffman Hollow Rd., Younts Rd., Willow Brook Lane, Imlertown Rd., Younts Rd, to Oppenheimer Hollow Rd. [3.5 miles] • East St Clair Township

109135 7212-613 T-613 Colebaugh Road Bridge 4th Quarter 2019 Fall 2020 • Bridge rehabilitation • On Colebaugh Rd over Scrubgrass Creek near intersection of Scrubgrass Rd • Anticipated traffic control will consist of a detour utilizing Colebaugh Rd, Scrubgrass Rd, Feathers Rd, and Schellsburg Rd, (3.0 miles) • King Township • Part of a grouped letting for 11 non-composite deck replacements in Bedford (5), Fulton (5) and Huntingdon (1) Counties

96035 7217-386 T-386 Akers Road Bridge 4th Quarter 2019 Fall 2020 • Bridge rehabilitation • On Akers Rd over Shaffer Creek • Anticipated traffic control will consist of a detour utilizing Akers Rd, Back Ridge Rd, Akers Rd, Rock Hill Rd, Mechanics Hill Rd, Merriwinds Rd, and McCune Rd, (4.7 miles) • East Providence/Monroe Township Line • Part of a grouped letting for 11 non-composite deck replacements in Bedford (5), Fulton (5) and Huntingdon (1) Counties

Page 10 of 33 District 9-0 Southern Alleghenies RPO As of 06/24/2019

BEDFORD COUNTY UPCOMING LETS

MPMS SR – SEC PROJECT TITLE ANTICIPATED LET ANTICIPATED COMPLETION 109136 7217-353 T-353 Rice Road Bridge 4th Quarter 2019 Fall 2020 • Bridge rehabilitation • On Rice Rd over West Branch Sideling Hill Creek near intersection of Big Creek Rd • Anticipated traffic control will consist of a detour utilizing Rice Rd, Addison Ridge Rd, Turkey Ridge Rd, and Big Creek Rd, (8.0 miles) • Monroe Township • Part of the T-331 East Pittman Road Bridge grouped letting for 11 non-composite deck replacements in Bedford (5), Fulton (5) and Huntingdon (1) Counties

74381 0867-01B Trib 1st Quarter 2020 Fall 2020 • Small bridge being replaced by an elliptical pipe • On Lafayette Rd over Halter Creek just north of the intersection of Cross Cove Rd • Anticipated traffic control will consist of a detour utilizing Lafayette Rd, Bloomfield Rd, Main St, Woodbury Pike (PA 36), and Cross Cove Rd, (10.1 miles) • Bloomfield Township

98778 1042-01B SR 1042 Halter Crk Bridge 1st Quarter 2020 Fall 2020 • Small bridge being replaced by an elliptical pipe • On Lafayette Rd over Halter Creek just north of the intersection of Cross Cove Rd • Anticipated traffic control will consist of a detour utilizing Lafayette Rd, Bloomfield Rd, Main St, Woodbury Pike (PA 36), and Cross Cove Rd, (10.1 miles) • Bloomfield Township

74395 1016-01B 2020 DF Bedford Box Culvert 1st Quarter 2020 Fall 2020 • On Replogle Schoool Rd over Tributary to Three Springs Run near intersection of Mill St • Anticipated traffic control will consist of a detour utilizing Replogle School Rd, Potter Creek Rd (PA 868), Woodbury Pike (PA 869) and Replogle School Rd, (6.3 miles) • South Woodbury Township • Prime Contractor: Department Forces

Page 11 of 33 District 9-0 Southern Alleghenies RPO As of 06/24/2019

BEDFORD COUNTY UPCOMING LETS

MPMS SR – SEC PROJECT TITLE ANTICIPATED LET ANTICIPATED COMPLETION 88524 0056-24S PA56/SR 4028 Intersection 1st Quarter 2020 Fall 2020 • On Raystown Rd (PA 26)(3) and one culvert on Woodbury pike (PA 36)(1) • Anticipated traffic control will consist of temporary roadways for both routes • Hopewell Township (Cottles Corner) • Prime Contractor: New Enterprise Stone & Lime Co., Inc. • Construction to resume in the Spring

21362 1034-01B Sandy Run Bridge 1st Quarter 2020 Fall 2020 • Small bridge being replaced by an elliptical pipe • On Lafayette Rd over Halter Creek just north of the intersection of Cross Cove Rd • Anticipated traffic control will consist of a detour utilizing Lafayette Rd, Bloomfield Rd, Main St, Woodbury Pike (PA 36), and Cross Cove Rd, (10.1 miles) • Bloomfield Township

106005 0030-04S US 30 Left Turn Lane at T-455 2nd Quarter 2020 Fall 2020 • Construction of a left turn lane • On Lincoln Hwy just east of Lower Snake Spring Rd at Mount Dallas Road • Anticipated traffic control will consist of daylight flagging • Snake Spring Township

96524 1019-002 SR 1019 – PA 26 to PA 26 2nd Quarter 2020 Fall 2020 • On Woodcock Valley Rd/Pinchot Rd from Raystown Rd to Raystown Rd • Traffic control will consist of daylight flagging • Hopewell and Liberty Townships

111660 0000-BHT Shuster Way Heritage Trail 2nd Quarter 2020 Fall 2020 • On Raystown Rd (PA 26)(3) and one culvert on Woodbury pike (PA 36)(1) • Anticipated traffic control will consist of temporary roadways for both routes • Hopewell Township

Page 12 of 33 District 9-0 Southern Alleghenies RPO As of 06/24/2019

BEDFORD COUNTY UPCOMING LETS

MPMS SR – SEC PROJECT TITLE ANTICIPATED LET ANTICIPATED COMPLETION 21362 1034-01B Trib to Sweet Root Creek Culvert 2nd Quarter 2020 Fall 2020 • Bridge being replaced by an elliptical pipe • On Lafayette Rd over Halter Creek just north of the intersection of Cross Cove Rd • Anticipated traffic control will consist of a detour utilizing Lafayette Rd, Bloomfield Rd, Main St, Woodbury Pike (PA 36), and Cross Cove Rd, (10.1 miles) • Bloomfield Township

111447 1044-003 Everett Bus. Dist. Access Improv 2nd Quarter 2020 Fall 2020 • Bridge being replaced by an elliptical pipe • On Lafayette Rd over Halter Creek just north of the intersection of Cross Cove Rd • Anticipated traffic control will consist of a detour utilizing Lafayette Rd, Bloomfield Rd, Main St, Woodbury Pike (PA 36), and Cross Cove Rd, (10.1 miles) • Bloomfield Township

105996 0056-01B Trib Barefoot Run 1st Quarter 2021 Fall 2021 • Bridge being replaced by an elliptical pipe • On Quaker Valley Rd over Barefoot Run just west of the intersection with Cortland Rd/King St Clair Rd (PA96) • Anticipated traffic control will consist of phased construction • Pleasantville Borough

88098 7203-575 T-575 Cold Spring Road Bridge 1st Quarter 2021 Fall 2021 • Bridge being replaced by an elliptical pipe • On Cold Spring Rd over Six Mile Run at the intersection with Main St • Anticipated traffic control will consist of a temporary roadway • Broad Top Township

Page 13 of 33 District 9-0 Southern Alleghenies RPO As of 06/24/2019

FULTON COUNTY CONSTRUCTION PROGRESS REPORT

MPMS SR – SEC PROJECT TITLE STATUS ANTICIPATED COMPLETION 98775 0655-05B PA 655 Sideling Hill Creek 34% Compete 11/07/19 • Bridge Replacement • On Waterfall Rd (PA 655) over Sideling Hill Creek at the intersection with New Grenada Hwy • Anticipated traffic control will be phased construction with signal • Taylor Township • Prime Contractor: Susquehanna Valley Construction Corporation • Contract includes PA 913 Roaring Run Bridge project and Sideling Hill Creek #2 in Huntingdon Co. • Contractor preparing to set beams and pour deck

22833 0913-02B PA 913 Roaring Rn Bridge 34% Complete 11/07/19 • Bridge Replacement • On New Grenada Hwy (PA 913) over Roaring Run near intersection with Hoover Rd • Anticipated traffic control will be phased Construction • Wells Township • Prime Contractor: Susquehanna Valley Construction Corporation • Part of the PA 655 Sideling Hill Creek Project • Contractor preparing to set beams and pour deck

74444 1005-01B Little Augwick Creek Bridge NTP 01/08/19 08/14/20 • Superstructure replacement • On Aughwick Rd over South Branch of Little near the Dublin/Todd Township Line • Traffic control will consist of a Detour utilizing Aughwick Rd, Lincoln Hwy (US30), Great Cover Rd (US 522), Grist Mill Rd, and Allens Valley Rd, (29.4 miles) • Todd Township • Prime Contractor: Cottle’s Asphalt Maintenance, Inc. • Contractor will begin construction on September 23rd

Page 14 of 33 District 9-0 Southern Alleghenies RPO As of 06/24/2019

FULTON COUNTY CONSTRUCTION PROGRESS REPORT

MPMS SR – SEC PROJECT TITLE STATUS ANTICIPATED COMPLETION 107162 2005-01B 2019 DF Fulton Box Culvert 5% Complete 09/20/19 • Culvert replacement • On Timber Ridge Rd over Joe’s Run near the intersection of Garland Rd • Traffic control will consist of a Detour utilizing Timber Ridge Rd, Great Cover Rd (US 522), and Pleasant Ridge Rd (PA 655), (14.2 miles) • Belfast Township • Prime Contractor: Department Forces • Contractor expects delivery of Box week of June 17

110865 0869-09S D9 2019 HSIP HFST 16% Complete 11/04/19 • Placement of High Friction Surface Treatment • On Lincoln Hwy between S Valley Rd and North Valley Rd (Three areas) • On Flickerville Rd from bridge over Little Tonoloway Creek through the curve at Fischer Rd • Anticipated traffic control will consist of daylight flagging • Brush Creek Township, Fulton County • Prime Contractor: MEKIS Construction Corporation • Contract includes various routes in Bedford, Blair, Cambria, Huntingdon and Somerset Counties • Contractor is currently in Bedford County and expects to be in Fulton County in late July

Page 15 of 33 District 9-0 Southern Alleghenies RPO As of 06/24/2019

FULTON COUNTY UPCOMING LETS

MPMS SR – SEC PROJECT TITLE ANTICIPATED LET ANTICIPATED COMPLETION 112705 0070-38T 2019 S Alleghenies RPO TSMO 4th Quarter 2019 Summer 2020 • Dynamic Message Sign retrofit • On I-70 near Pigeon Cove Rd – Bethel Township, Fulton Co., also on US 22 near Frankstown Branch Juniata River – Porter Township, Huntingdon Co; PA 453 near Spruce Creek Rd – Morris Township, Huntingdon Co.; • Anticipated traffic control will consist of daylight flagging

109200 7201-338 T-338 Laurel Ridge Road Bridge 4th Quarter 2019 Fall 2020 • Bridge deck replacement • On Laurel Ridge Rd over Cove Creek near the intersection of Big Cove Tannery Rd (PA 928) • Anticipated traffic control will consist of a Detour utilizing Shaw Rd, Great Cove Rd (US 522) and Laurel Ridge Rd (PA 928) (7.5 miles) • Ayr Township • Part of a grouped letting for 11 non-composite deck replacements in Bedford (5), Fulton (5) and Huntingdon (1) Counties

109201 7201-372 T-372 Ravensburg Road Bridge 4th Quarter 2019 Fall 2020 • Bridge deck replacement • On Ravensburg Rd over Cove Creek north of the intersection with US 522 • Anticipated traffic control will be phased construction • Ayr Township • Part of a grouped letting for 11 non-composite deck replacements in Bedford (5), Fulton (5) and Huntingdon (1) Counties

109202 7206-404 T-404 Reunion Ground Road Bridge 4th Quarter 2019 Fall 2020 • Bridge deck replacement • On Reunion Ground Road over Licking Creek near the intersection of Big Cove Tannery Rd (PA 655) • Anticipated traffic control will consist of a Detour utilizing Pleasant Ridge Rd (PA 655), Lincoln Highway, Patterson Run Rd, and Reunion Ground Rd (5.0 miles) • Licking Creek Township • Part of a grouped letting for 11 non-composite deck replacements in Bedford (5), Fulton (5) and Huntingdon (1) Counties

Page 16 of 33 District 9-0 Southern Alleghenies RPO As of 06/24/2019

FULTON COUNTY UPCOMING LETS

MPMS SR – SEC PROJECT TITLE ANTICIPATED LET ANTICIPATED COMPLETION 109203 7208-331 T-331 East Pittman Road Bridge 4th Quarter 2019 Fall 2020 • Bridge Rehabilitation • On East Pittman Rd over Licking Creek approximately 0.2 miles west of Laurel Ridge Rd. • Anticipated traffic control will consist of a detour utilizing East Pittman Rd., Big Cove Tannery Rd., Toll Gate Rd., Gem Bridge Rd., East Pittman Rd, (7.5 miles) • Thompson Township • Part of a grouped letting for 11 non-composite deck replacements in Bedford (5), Fulton (5) and Huntingdon (1) Counties

109204 7210-366 T-366 Old Route 126 Bridge 4th Quarter 2019 Fall 2020 • Bridge deck replacement • On Old Route 126 (T-366) over McKees Run near the intersection of Deneens Gap Road • Anticipated traffic control will consist of a detour utilizing Old Route 126, Fairview Rd., McKees Gap Rd., to Deneens Gap Rd, (4.8 miles) • Union Township

107161 3013-02B 2020 DF Fulton Box Culvert 1st Quarter 2020 Fall 2020 • Culvert replacement • On Sipes Mill Rd over Tributary over Cummings Run Creek just west of intersection with Saw Mill Rd • Anticipated traffic control will consist of a Detour utilizing Saw Mill Rd, Barnhart Rd, Pleasant Grove Rd and Sipes Mill Rd, (4.6 miles) • Belfast Township

106419 7205-457 Tannery Road Bridge 1st Quarter 2020 Fall 2020 • Bridge Replacement • On Tannery Rd over • Anticipated traffic control will consist of a Detour utilizing Tannery Rd (Fulton & Huntingdon), Mill Hill Rd (Huntingdon), Croghan Pike (US 522), Tannery Rd (Huntingdon & Fulton), (4.8 miles) • Dublin Township

Page 17 of 33 District 9-0 Southern Alleghenies RPO As of 06/24/2019

FULTON COUNTY UPCOMING LETS

MPMS SR – SEC PROJECT TITLE ANTICIPATED LET ANTICIPATED COMPLETION 110583 0070-35B I-70 Bridges over PA 915 1st Quarter 2020 Fall 2020 • Bridge Replacement • On Tannery Rd over Little Aughwick Creek • Anticipated traffic control will be phased with signal • Dublin Township

22802 3013-03B Sipes Mill Bridge 1st Quarter 2021 Fall 2021 • Bridge Replacement • On Sipes Mill Rd over Little Tonoloway Creek near intersection of Black Bear Rd • Anticipated traffic control will consist of Detour utilizing Blairs Hill Rd, Wertzville Rd, Palmer Rd, and Sipes Mill Rd (3.9 miles) • Belfast Township

111992 0655-06B 2021 DF Fulton Box Culvert 1st Quarter 2021 Fall 2021 • Culvert replacement • On Pine Ridge Rd over unnamed Tributary of Licking Creek near intersection with Doe Rd • Anticipated traffic control will consist of a single-lane temporary road with signal • Licking Creek Township

108198 1001-001 SR 1001 – SR 1002 to PA 16 1st Quarter 2021 Fall 2021 • On Cito Rd from Union Church Rd to (PA16) • Anticipated traffic control will consist of daylight flagging • McConnellsburg Borough and Ayr Township

Page 18 of 33 District 9-0 Southern Alleghenies RPO As of 06/24/2019

HUNTINGDON COUNTY CONSTRUCTION PROGRESS REPORT

MPMS SR – SEC PROJECT TITLE STATUS ANTICIPATED COMPLETION 106468 1008-DF1 DF – SR 1008 - PA 305 to SR1013 100% Complete 04/25/19 • Resurfacing • On Myton Rd from Shavers Creek Rd (PA 305) to Harpers Hill Rd • Anticipated Traffic Control will consist of daylight flagging • West Township • Prime Contractor: Department Forces

107217 3012-DF1 SR 3012 - PA 26 to End of Route 100% Complete 05/02/19 • Resurfacing • On Garner Rd from Standing Stone Rd (PA 26) to Cul-de-sac Rd • Anticipated Traffic Control will consist of daylight flagging • Penn Township • Prime Contractor: Department Forces

109206 7222-313 T-313 Walnut Grove Road Bridge 95% Compete 09/02/20 • Bridge Rehabilitation • On Walnut Grove Church Rd over sideling Hill Creek east of intersection of Doyle Rd (T-319) • Anticipated Traffic Control will consist of a Detour utilizing Hollow Rd, Selea Hollow Rd, Elliots Run Rd, and Walnut Grove Church Rd (8.5 miles) • Springfield Township • Prime Contractor: George S. Hann & Son, Inc. • Contractor currently performing pier preservation • Part of the Street Road over Flintstone Creek contract (Bedford Co.) and includes one other local bridge in Huntingdon Co. and six in Bedford Co.

Page 19 of 33 District 9-0 Southern Alleghenies RPO As of 06/24/2019

HUNTINGDON COUNTY CONSTRUCTION PROGRESS REPORT

MPMS SR – SEC PROJECT TITLE STATUS ANTICIPATED COMPLETION 109207 7222-333 T-333 Mathews Bridge Road Bridge 65% Complete 09/02/20 • Bridge Rehabilitation • On Mathews Bridge Rd over Aughwick Creek near intersection of Maddensville Pike (PA475) • Anticipated Traffic Control will consist of a Detour utilizing Maddenville Pike, Meadow Gap Rd, Fleck Rd, Mathews Bridge Rd (6.0 miles) • Springfield Township • Prime Contractor: George S. Hann & Son, Inc. • Contractor to pour deck on June 27th • Part of the Street Road over Flintstone Creek contract (Bedford Co.) and includes one other local bridge in Huntingdon Co. and six in Bedford Co.

23036 1023-02B Standing Stone Ck #2 24% Compete 09/30/19 • Bridge Replacement • On Alan Seegar Rd over prior changing to Forestry Road • Anticipated traffic control will be a Detour utilizing Alan Seeger Road), Stone Creek Road, Seeger Road, Rag Hollow Road, Greenwood Road (PA 305), McAlevys Fort Rd (PA 26), and Alan Seegar Rd, (19 miles) • Jackson Township • Prime Contractor: Redrock Construction, Inc. • Contractor currently preparing to set beams

23023 2001-01B Sideling Hill Crk #2 12% Compete 11/07/19 • Bridge Replacement • Selea Hollow Rd over Sideling Hill Creek near the intersection of Bratton Rd • Anticipated traffic control will be phased construction with signal • Clay Township • Prime Contractor: Susquehanna Valley Construction Corporation • Part of the PA655 Sideling Hill Creek Contract in Fulton Co. • Contractor currently working on bridge foundations

Page 20 of 33 District 9-0 Southern Alleghenies RPO As of 06/24/2019

HUNTINGDON COUNTY CONSTRUCTION PROGRESS REPORT

MPMS SR – SEC PROJECT TITLE STATUS ANTICIPATED COMPLETION 110283 4007-001 PA 305 to Cold Springs Rd NTP 05/15/19 09/06/19 • Resurfacing • On Petersburg Pike from King St (PA 305) to Cold Springs Rd • Anticipated Traffic Control will consist of daylight flagging • Petersburg Borough, Oneida and Logan Townships • Contract includes the SR 1011 - PA 26 to SR 1001 project

106473 1011-001 SR 1011 - PA 26 to SR 1001 NTP 05/15/19 09/06/19 • Resurfacing • On Murray Run Rd from Standing Stone Rd (PA 26) to Miller Twp Line, and on Gorsuch Rd from Oneida Twp line to Creek Crossing Rd (T-563) • Anticipated Traffic Control will consist of daylight flagging • Oneida & Miller Townships • Part of the PA 305 to Cold Springs Rd Contract

106492 2005-01B SR 2005 Three Springs Bridge Anticipated NTP 05/28/19 09/06/19 • Superstructure replacement • On Elliots Run Rd from over Three Springs Creek at the intersection of Hudson Street • Anticipated Traffic Control will consist of a Detour utilizing Elliots Run Rd, Cherry Grove Church Rd, Waterfall Rd, Church St, Hudson St (9.0 miles) • Clay Township

110865 0869-09S D9 2019 HSIP HFST 16% Complete 11/04/19 • Placement of High Friction Surface Treatment (1,800 feet) • On Standing Stone Rd approximately 2.4 miles north of Huntingdon • Anticipated traffic control will consist of daylight flagging • Oneida Township • Prime Contractor: MEKIS Construction Corporation • Contractor expects to be in Hunting County in late Summer • Project is part of the Bedford County Contract and includes various routes in Blair, Cambria, Fulton, and Somerset Counties

Page 21 of 33 District 9-0 Southern Alleghenies RPO As of 06/24/2019

HUNTINGDON COUNTY UPCOMING LETS

MPMS SR – SEC PROJECT TITLE ANTICIPATED LET ANTICIPATED COMPLETION 92696 0026-02B PA26 over Muddy Run Clvrt 4th Quarter 2019 Fall 2020 • Culvert Replacement • On Penn St (PA 26) over Muddy Run at 7th Street • Anticipated traffic control will be a Partial Intersection closure with Detour utilizing US 22 and South 4th St, Truck Detour will utilize US 22 and Penn St • Huntingdon Borough

88150 1009-01B Huntingdon Boro Muddy #2 4th Quarter 2019 Fall 2020 • Culvert Replacement • On Moore St over Muddy Run at intersection with 9th Street • Anticipated traffic control will be a north bound Detour utilizing 7th St, Mifflin St, and 10th St; south bound Detour utilizing 10th St and 7th St and a pedestrian Detour utilizing Moore St, 10th St, and 7th St • Huntingdon Borough

88151 1009-02B Huntingdon Boro Muddy #3 4th Quarter 2019 Fall 2020 • Culvert Replacement • On Moore St over Muddy Run at intersection with 11th Street • Anticipated traffic control will be a north bound Detour utilizing Moore St, 10th St, Washington St, 7th St, Warm Springs Ave, Oneida St, and 13th St; south bound Detour utilizing 13th St, Washington St, and 9th St. and a pedestrian Detour utilizing 12th St, Miflin St, and 10th St • Huntingdon Borough

109205 7206-358 T-358 Covered Bridge Road Bridge 4th Quarter 2019 Summer 2020 • Bridge Rehabilitation • On Covered Bridge Rd over Shade Creek at the intersection of Covered Bridge Rd with Groghan Pike (US 522) • Anticipated Traffic Control will consist of a detour • Cromwell Township • Part of a grouped letting for 11 non-composite deck replacements in Bedford (5), and Fulton (5) Counties

Page 22 of 33 District 9-0 Southern Alleghenies RPO As of 06/24/2019

HUNTINGDON COUNTY UPCOMING LETS

MPMS SR – SEC PROJECT TITLE ANTICIPATED LET ANTICIPATED COMPLETION 74445 1013-01B 2020 DF Huntingdon Box Culvert 1st Quarter 2020 Fall 2020 • Bridge Rehabilitation • On Ewing Rd over Henrys Run just southwest of intersection with Greenwood Rd • Anticipated traffic control will consist of a Detour utilizing Ewing Rd, Myton Rd, Shavers Creek Rd (PA 305), Greenwood Rd (PA 305), (8.0 miles) • Barree Township

23038 0913-01B Great Trough Crk Bridge 2 1st Quarter 2020 Fall 2020 • Bridge Replacement • On Main St over in Village of Robertsdale just north of Lincoln St • Anticipated traffic control will be a phased • Wood Township

106420 7411-131 Hill Valley Creek Bridge 1st Quarter 2020 Fall 2020 • Bridge Replacement • On Main St over Great Trough Creek in Village of Robertsdale just north of Lincoln St • Anticipated traffic control will be a temporary roadway • Wood Township

96597 0022-012 Old Rt 22 Rd – PA 26 2nd Quarter 2020 Fall 2020 • Resurfacing (3.4 miles) • On William Penn Hwy from approximately 1.0 mile west of Lincoln Caverns to bridge over Raystown Rd • Anticipated Traffic Control will consist of daylight flagging

23091 2009-02B SR2009 Tuscarora Creek Br 3rd Quarter 2020 Summer 2021 • Bridge Replacement • On Tuscarora Creek Rd over Tuscarora Creek between Center Rd and Parsons Rd • Anticipated traffic control will be a Detour utilizing Parsons Rd, Mountain Foot Rd, Tuscarora Creek Rd (4.1 miles) • Tell Township

Page 23 of 33 District 9-0 Southern Alleghenies RPO As of 06/24/2019

SOMERSET COUNTY CONSTRUCTION PROGRESS REPORT

MPMS SR – SEC PROJECT TITLE STATUS ANTICIPATED COMPLETION 107967 0000-USS Uptown Somerset Sidewalk Enhance 100% Complete 07/12/19 • Sidewalk replacement and new installation cha • On West Main Street between South Edgewood Ave and Center Ave • Somerset Borough • Prime Contractor: M and B Services, LLC

21615 1018-01B S Central City Bridge 95% Complete 11/01/19 • Bridge rehabilitation – bridge deck overlay • On Shaffer Mtn Rd over Dark Shade Creek just east of the intersection of Statler St • Traffic control will consist of a Detour utilizing Shaffer Mtn Rd, Lambert St, Central Ave, Sunshine Ave, Main St, Shaffer Mtn Rd, (1 mile) • Shade Township • Prime Contractor: Cottle’s Asphalt Maintenance, Inc. • Contractor will open roadway by 4th of July

105982 4043-001 SR 4041 to PA 403 91% Complete 04/29/19 • Resurfacing • On West Campus Ave from Soap Hollow Rd to Main St • Traffic control will consist of daylight flagging • Conemaugh Township • Prime Contractor: HRI, Inc. • Contractor currently completing miscellaneous items

48072 0160-022 Wellersburg Safety Improvements 82% Complete 06/28/19 • Extension of existing truck pull-off area and associates signage • On Cumberland Hwy at the top of the mountain • Traffic control will consist of daylight flagging • Southampton Township • Prime Contractor: New Enterprise Stone & Lime Co., Inc. • Contractor currently placing conduit and electric to DMS boards and flashing warning lights on signs, DMS and cameras to be set at the truck pull-off by mid-May

Page 24 of 33 District 9-0 Southern Alleghenies RPO As of 06/24/2019

SOMERSET COUNTY CONSTRUCTION PROGRESS REPORT

MPMS SR – SEC PROJECT TITLE STATUS ANTICIPATED COMPLETION 96059 7219-640 T-640 Reffner Rd Br 50% Complete 10/30/19 • Bridge rehabilitation – new bridge deck • On Reffner Rd over Wells Creek near the intersection of Mosteller Rd • Traffic control will consist of a detour utilizing Reffner Road, West Wind Road, Stoystown Rd (PA 281), Welsh Hill Rd, and Coleman Station Road (3.7 miles) • Quemahoning Township • Prime Contractor: Pugliano Construction Co., Inc. • Contractor has poured deck, will begin forming parapets by end of June • Part of the T-323 Tub Mill Run Rd Br contract

108264 2047-001 Meyersdale Intrchng to US 219 40% Complete 09/27/19 • Resurfacing and slide repair • On Mason Dixon Highway from the northern Meyersdale Interchange to the southern Meyersdale interchange, slide is located in the guiderail section between Johnny Popper Rd and SB pull-off adjacent to NS Railroad signal structure • Traffic control will consist of daylight flagging • Summit Township and Meyersdale Borough • Prime Contractor: Quaker Sales Corporation • Contractor has repaired slide, currently working on inlets and will begin paving at the end of July

23507 7206-353 T-353 Moser Rd Bridge 38% Complete 10/24/19 • Bridge replacement • On Moser Rd over Casselman River near the intersection of Skyline Dr • Traffic control will consist of a detour • Elk Lick Township • Prime Contractor: Allison Park Contractors, Inc. • Contractor has dissembled and removed the trusses; some members will be refabricated, all will be prepared for galvanization which is expected to be back on site by mid-August

Page 25 of 33 District 9-0 Southern Alleghenies RPO As of 06/24/2019

SOMERSET COUNTY CONSTRUCTION PROGRESS REPORT

MPMS SR – SEC PROJECT TITLE STATUS ANTICIPATED COMPLETION 105931 0030-003 US 30 – US 219 to PA 985 30% Complete 09/06/19 • Resurfacing • On Lincoln Hwy/Pitt St from Flight 93 Memorial Hwy to Somerset Pike • Traffic control will consist of daylight flagging • Jenner Township and Jennerstown Borough • Prime Contractor: New Enterprise Stone & Lime Co., Inc. • Contractor currently placing concrete patches; planning to mill and pave in July, install raised pavement markers and guiderail sometime in August

106427 7201-858 T-858 Braddocks Run Bridge NTP 04/08/19 10/30/19 • Bridge rehabilitation – new bridge deck • On Braddocks Run Rd over Braddocks Run approximately 1.5 miles south of intersection with US 40 • Traffic control will consist of a detour utilizing Braddock Run Rd, Polk Hill Rd), and National Pike (US 40) • Addison Township • Prime Contractor: Pugliano Construction Co., Inc. • Construction to begin after T-640 Reffner Rd Br project is complete

96053 7206-323 T-323 Tub Mill Run Rd NTP 04/08/19 10/30/19 • Bridge rehabilitation – new bridge deck • On Tub Mill Run Rd over Tub Mill Run Rd approximately ½ mile east of intersection with Oak Dale Rd • Traffic control will consist of a detour utilizing Tub Mill Road, Springs Road (PA 669) and Oak Dale Road • Elk Lick Township • Prime Contractor: Pugliano Construction Co., Inc. • Construction to begin after T-858 Braddocks Run Bridge is complete

74440 0403-13B PA 403 Dixie Run Culvert 0% Complete 11/13/19 • Bridge replacement • On Barn St over Dixie Run just north of the intersection of Somerset St • Traffic control will be phased construction with signal • Hooversville Borough • Prime Contractor: Charles J. Merlo, Inc. • Contractor to have temporary signal in operation week of July 8th to begin construction • Part of the PA 403 /Pokeytown Run contract Page 26 of 33 District 9-0 Southern Alleghenies RPO As of 06/24/2019

SOMERSET COUNTY CONSTRUCTION PROGRESS REPORT

MPMS SR – SEC PROJECT TITLE STATUS ANTICIPATED COMPLETION 74493 4004-01B 2019 DF Somerset Box Culvert NTP 02/26/19 07/26/19 • Culvert replacement • On Bluebird Spring Rd over Quemahoning Creek 0.9 mile east of intersection with Quecreek Rd • Traffic control will consist of a detour utilizing Bluebird Spring Rd, Emert Rd, and Quecreek Rd • Lincoln Township • Prime Contractor: Pugliano Construction Co., Inc. • Constractor implemented Detour June 24th

96639 2033-DF1 DF–Brthrtn Rd-Coleman Stn Rd (FDR) NTP 05/31/19 09/18/19 • Full Depth Reclamation • On Willkow Rd from Glades Pike (PA 31) to Brotherton Rd and on Shaffer Rd From Brotherton Rd to Coleman Station Rd • Anticipated traffic control will be Daylight Flagging • Stonycreek Township

21592 3010-004 Mud Pike Improvements NTP 06/24/19 11/13/20 • Highway reconstruction including widening and resurfacing, bridge replacement, culvert replacement and a 60” pipe replacement, realignment of Garret Shortcut Road curve just south of East Mud Pike intersection at the former Shaffer Dairy to improve sight distance, addition of a north bound left turn lane off Berlin Plank Rd onto East Mud Pike Rd • On East Mud Pike Rd beginning at the intersection of Garrett Shortcut Rd continuing east to Berlin Plank Rd • Traffic control for Bridge, Culvert and Pipe replacements will consist of a Detours utilizing Mud Pike, Garrett Shortcut Rd, Berlin Plank Rd, Mud Pike; other construction activities will be daylight flagging • Brothersvalley Township • Prime Contractor: New Enterprise Stone & Lime Co., Inc.

Page 27 of 33 District 9-0 Southern Alleghenies RPO As of 06/24/2019

SOMERSET COUNTY UPCOMING LETS

MPMS SR – SEC PROJECT TITLE ANTICIPATED LET ANTICIPATED COMPLETION 91671 2047-004 Brotherton Rd to Berlin/Somerset 3nd Quarter 2019 Fall 2019 • Resurfacing and bridge rehabilitations • On Berlin Plank Rd from Main St (PA 31) in Somerset to Washington St in Berlin • Traffic control will consist of daylight flagging for the resurfacing, phased with signal for the bridge rehabilitations • Somerset Borough, Berlin Boroughs, and Somerset Township

108289 4023-003 SR 4023 - PA 985 to PA 601 3rd Quarter 2019 Fall 2019 • Resurfacing • On Million Dollar Hwy and Blacks Hill Rd from Somerset Pike (PA 985) to Penn Ave (PA 601) • Traffic control will consist of daylight flagging for the resurfacing • Boswel and Jennerstown Boroughs, and Jenner Township

107919 3008-DF1 DF - SR 3008 – PA 281 to Water Lvl Rd 3rd Quarter 2019 Fall 2019 • Resurfacing • On West Mud Pike from New Centerville Rd (PA 281) to Water Level Rd • Anticipated traffic control will be Daylight Flagging • New Centerville Borough and Milford Township

105937 4016-DF1 DF - SR 4016 – PA 985 to SR 4035 3rd Quarter 2019 Fall 2019 • Resurfacing • On Moonlight Park Rd from Somerset Pike (PA 281) to Woodstown Hwy • Anticipated traffic control will be Daylight Flagging • Conemaugh Township

108286 4019-003 DF - SR 4019 – SR 4017 to T-668 3rd Quarter 2019 Fall 2019 • Resurfacing • On Bicycle Rd/Somerset St/Quemahoning St and Plank Rd from Horner Church Rd through Stoystown Borough to Bassett Rd • Anticipated traffic control will be Daylight Flagging • Quemahoning Township and Stoystown Borough

Page 28 of 33 District 9-0 Southern Alleghenies RPO As of 06/24/2019

SOMERSET COUNTY UPCOMING LETS

MPMS SR – SEC PROJECT TITLE ANTICIPATED LET ANTICIPATED COMPLETION 105960 0000-911 Sept 11th National Memorial Trail 1st Quarter 2020 Fall 2020 • Trail construction • Beginning at the section of the Great Allegheny Passage trail at Garrett and continuing north 1.25 miles toward Berlin • Summit and Brothersvalley Township

107165 4008-01B 2020 DF Somerset Box Culvert 1st Quarter 2020 Fall 2020 • Culvert replacement • On Beam Church Rd over Spruce Run just west of intersection of Tipton Rd • Traffic control will consist of a Detour utilizing Beam Church Rd, Somerset Pike, Schoolhouse Rd, Keysertown Rd, and Beam Church Rd (8.25 miles) • Jenner Township

92699 0985-01B PA 985 Trib Beaverdam Run 1st Quarter 2020 Fall 2020 • Bridge replacement • On Somerset Pike over Tributary to Beaverdam Run just south of the intersection of Pelesky Rd • Traffic control will consist of a Detour utilizing Somerset Pike, Lincoln Highway (US 30), Million Dollar Highway, and Somerset Pike, (6.0) miles • Jenner Township

111482 2030-BRP Berlin Revitalization Project – Phs II 2nd Quarter 2020 Fall 2020 • Sidewalk restoration • On Main St from Cumberland St to Broadway St • Pedestrian detours will be utilized • Berlin Borough

107213 4053-001 SR 4053 – US 30 to SR 4028 3rd Quarter 2020 Fall 2020 • Resurfacing • On Oak Ave from US 30 to West Main St (465’) • Traffic control will consist of daylight flagging • Stoystown Borough and Quemahoning Township

Page 29 of 33 District 9-0 Southern Alleghenies RPO As of 06/24/2019

SOMERSET COUNTY UPCOMING LETS

MPMS SR – SEC PROJECT TITLE ANTICIPATED LET ANTICIPATED COMPLETION 74476 2016-01B Rhoads Creek Bridge 3rd Quarter 2020 Summer 2021 • Bridge replacement • On Rockdale Rd over Rhoads Creek Just north of Old Dirt Rd • Traffic control will consist of a Detour utilizing Rockdale Rd, Fox Rd, Markleton School Rd, and Rockdale Rd (4.7) miles • Black Township

105997 3015-02B Rockwood Trib Coxes Creek #1 3rd Quarter 2020 Fall 2021 • Bridge replacement • On Water Level Rd over Tributary to Coxes Creek southwest of the Coalyard Rd intersection • Traffic control will consist of a Detour utilizing Water Level Rd, Gebhart Rd, West Mud Pike, and Water Level Rd (4.8) miles • Milford Township

105998 3015-03B Rockwood Trib Coxes Creek #2 3rd Quarter 2020 Fall 2021 • Bridge replacement • On Water Level Rd over Tributary to Coxes Creek northeast of intersection with Coalyard Rd • Traffic control will consist of a Detour utilizing Water Level Rd, Gebhart Rd, West Mud Pike, and Water Level Rd (4.8) miles • Milford Township

92711 0040-002 Addison Resurface 4th Quarter 2020 Summer 2021 • Resurfacing • On National Pike (US 40) from the State Line to Fayette Co. Line (6.2 miles) • Anticipated traffic control will be Daylight Flagging • Addison Borough and Addison Township

Page 30 of 33 District 9-0 Southern Alleghenies RPO As of 06/24/2019

SOMERSET COUNTY UPCOMING LETS

MPMS SR – SEC PROJECT TITLE ANTICIPATED LET ANTICIPATED COMPLETION 56644 3039-02B Triple Creek Rd over Allen Creek 4th Quarter 2020 Fall 2021 • Bridge replacement • On Triple Creek Rd over Allen Creek approximately ½ mile from intersection of Pritts Distillery Rd • Traffic control will consist of a Detour utilizing Triple Creek Rd, County Line Rd, Barron Church Rd, and Triple Creek Rd (6.1 miles) • Middlecreek Township

23566 0601-01B PA 601/Shade Creek 4th Quarter 2020 Summer 2021 • Super Structure replacement • On Seanor Rd over Shade Creek between River Rd and Fyock Dr intersections in Village of Seanor • Anticipated traffic control will be Detour utilizing Seanor Rd, Scalp Ave (PA56), Flight 93 Memorial Hwy (US219), Main St (PA403), Seanor Rd (15.0 miles) • Paint Township

92702 0031-01B PA31 Trib Stonycreek Br 1 4th Quarter 2020 Fall 2021 • Bridge replacement • On Glades Pike over Stonycreek River ¼ mile east of Beulah Rd • Traffic control will consist of Detour utilizing Glades Pike (PA31), Buelah Rd (PA160), Main St, Broadway St, Brotherton Rd, Glades Pike (7.0 miles) • Stonycreek and Brothersvalley Townships

23434 0160-08B Dark Shade Creek Bridge 4th Quarter 2020 Fall 2021 • Bridge replacement • On Sunshine Ave over Dark Shade Creek near the Fire Hall • Anticipated traffic control will be a Detour utilizing Sunshine Ave, Central Ave, Lambert St, School Rd, McGregor Ave, Dark Shade Dr, Main St and Sunshine Ave (3.0 miles) • Central City Borough

Page 31 of 33 District 9-0 Southern Alleghenies RPO As of 06/24/2019

SOMERSET COUNTY UPCOMING LETS

MPMS SR – SEC PROJECT TITLE ANTICIPATED LET ANTICIPATED COMPLETION 96607 0403-001 Wilbur Rd – Cambria Co Line 4th Quarter 2020 Summer 2021 • Resurfacing (13.8 miles) • On Whistler Rd/Barn St/Whistler Rd/N & S Main St/Tire Hill Rd (PA 403) from Wilbur Rd to the Cambria County Line • Anticipated traffic control will be Daylight Flagging • Hooversville Borough, Shade, Quemahoning, Paint, and Conemaugh Townships

105988 4041-DF1 DF – SR 4041 – SR 4016 to Cambria Co 1st Quarter 2021 Summer 2021 • Resurfacing (5.5 miles) • On Soap Hollow Rd from Moonlite Park Rd to Cambria County line • Anticipated traffic control will be Daylight Flagging • Conemaugh Township

96599 0030-016 PA 160 to Bedford Co Line 1st Quarter 2021 Fall 2021 • Resurfacing (3.9 miles) • On Lincoln Highway from Huckleberry Hwy/Rock Cut Rd intersection east to the Bedford County Line • Anticipated traffic control will be Daylight Flagging • Shade and Stonycreek Townships

108263 0031-020 PA31 – SR 3037 to Somerset Boro 1st Quarter 2021 Fall 2021 • Resurfacing (5.6 miles) • On Glades Pike from Trent Rd to Somerset Borough Line • Traffic control will consist of daylight flagging • Jefferson and Somerset Townships

108269 1035-DF1 DF – SR 1035 – SR 1018 to Bedford Co 1st Quarter 2021 Fall 2021 • Resurfacing (5.2 miles) • On Lambert Mtn Rd from Shaffer Mtn Rd to Bedford County Line • Anticipated traffic control will be Daylight Flagging • Shade Township

Page 32 of 33 District 9-0 Southern Alleghenies RPO As of 06/24/2019

SOMERSET COUNTY UPCOMING LETS

MPMS SR – SEC PROJECT TITLE ANTICIPATED LET ANTICIPATED COMPLETION 96640 2037-DF1 DF – Rockdale Rd to PA 653 1st Quarter 2021 Fall 2021 • Resurfacing (2.6 miles) • On Johnson Rd/Berlin St from Rockdale Rd to Jackson St (PA 653) • Anticipated traffic control will be Daylight Flagging • Garrett Borough and Summit Township

96648 4009-DF1 DF – Edgewood Ave to Byers Rd 1st Quarter 2021 Fall 2021 • Resurfacing (6.1 miles) • On N Edgewood Ave/Felgar Rd/Husband Rd from W Main St to Bakersville Edie Rd • Anticipated traffic control will be Daylight Flagging • Somerset Borough, Lincoln and Somerset Township

111994 4025-03B 2021 DF Somerset Box Culvert 1st Quarter 2021 Fall 2021 • Culvert replacement • On Ralphton Rd over Two Mile Run near US 219 over overpass • Anticipated traffic control will be a Detour utilizing Ralphton Rd, Penn Ave/Front St, Lincoln Hwy, and Ralphton Rd (6.5 miles) • Quemahoning Township

105988 4041-DF1 DF – SR 4041 - SR 2016 to Cambria Line 1st Quarter 2021 Fall 2021 • Resurfacing (5.5 miles) • On Soap Hollow Rd from Moonlite Park Rd to Cambria County • Anticipated traffic control will be Daylight Flagging • Conemaugh Township

96599 0030-016 PA 160 to Bedford Co Line 1st Quarter 2021 Fall 2021 • Resurfacing (5.5 miles) • On Lincoln Hwy (US 30) from Huckleberry Hwy/Rock Cut Rd (PA 160) intersection to the Bedford County Line • Anticipated traffic control will be Daylight Flagging • Shade and Stonycreek Townships

Page 33 of 33 District 9-0 Southern Alleghenies RPO As of 06/24/2019