• SA Road Network • NDP, PICC & SIP’s • Demand on KZN Network • Challenges on KZN Network • Conclusions

Authority Paved Gravel Total

SANRAL 19 686 0 19 686

Provinces - 9 44 660 136 640 181 300

Metros - 9 51 682 14 461 66 143

Municipalities 37 691 302 158 339 849

Total 153 719 453 259 606 978

Un-proclaimed (Estimate) 140 000 140 000

Estimated Total 153 719 593 259 746 978

Currently =1,422km Supporting Primary= 3,631km • National Planning Commission identified major constraints in mapping current issues facing SA

• NDP endorsed by Cabinet including National Infrastructure Plan

• Cabinet decision to establish a body to integrate and coordinate the long term infrastructure build, namely the Presidential Infrastructure Coordinating Commission (PICC) with its supporting management structures

• Through the PICC, Strategic Integrated Projects (SIP’s) established.

Town ADT ADTT % HV %night 11477 4987 43 25 Ladysmith 10031 5039 50 28.4 14244 5624 40 24.2 16425 6275 38.2 21 39576 7884 20 13 58138 7944 14 11 111968 8322 5.7 10

120000 111968 100000 80000 58138 60000 39576 40000 ADT ADTT 14244 16425 8322 20000 11477 10031 4987 5039 5624 6275 7884 7944 0 ● The between Durban and Pietermaritzburg was completed between the late 70’s and mid 80’s-current toll section between Paradise Valley and Key Ridge ● Consists of a dual divided carriageway freeway with three lanes per direction between Durban and , and thereafter two lanes per direction up to Pietermaritzburg ● Carries in excess of 40,000 vehicles per day – mix of urban commuter traffic, long distance traffic and substantial heavy vehicles, with some sections in excess of 25% heavies ● The n3 corridor carries in excess of 40 million tons of freight per annum, with currently approx. 9000 heavy vehicles per day ● Substantial delay costs and safety concerns (Townhill, Key Ridge) especially sections with two lane capacity, requiring major upgrading of freeway (add. of lanes) and interchanges and underpass/overpass bridges • Considering a 35 year planning horizon up to 2047 to tie in with port upgrade plans • Need a phased approach – funding limitations • Route being assessed holistically as the Durban- Freight Corridor together with NDoT, Transnet, provinces, municipalities, and dept’s • Ensuring capacity meets future demands when required • Consideration of a freight route out of port to N3 also being considered Transnet FDM Data

7,000 Gauteng -> Durban Safety capacity factor (30% rail) 2012 2020 2042 Seasonal capacity factor (15% total) 6,000 Containers 506 648 620 Other Other Agriculture 260 328 579 Vegetables 5,000 Manganese: Exports 25 98 211 Other Chemicals 4,000 Cement Non-Ferrous Metal Products 29 45 172 Paper & Paper Products Processed Foods 235 236 167 3,000 Beverages

trucks per day per trucks Bricks 15 26 148 Bricks 2,000 Beverages 85 106 147 Processed Foods Paper & Paper Products 37 48 109 1,000 Non-Ferrous Metal Products Manganese: Exports Cement 8 17 102 0 Other Agriculture Other Chemicals 38 47 93

Containers Total 2,920 2,976 3,815

2011 2013 2015 2017 2019 2021 2023 2025 2027 2029 2031 2033 2035 2037 2039 2041

10,000 Durban -> Gauteng Safety capacity factor (30% rail) Stone 15 82 878 9,000 Seasonal capacity factor (15% total) Containers 559 643 611 8,000 Other Iron & Steel Limestone 23 61 335 7,000 Other Agriculture Processed Foods 456 486 381 6,000 Wood & Wood Products Other Chemicals 180 181 245 5,000 Sugar cane Cement 40 73 226 4,000 Non-Ferrous Metal Products Non-Ferrous Metal trucks per day per trucks Products 50 70 185 3,000 Cement Other Chemicals Sugar cane 95 104 115 2,000 Processed Foods Wood & Wood Products 48 65 112 1,000 Limestone Other Agriculture 153 210 111 - Containers Total 2,789 3,344 5,046

Stone

2011 2013 2015 2017 2019 2021 2023 2025 2027 2029 2031 2033 2035 2037 2039 2041 25,000

20,000

N3: Port-related plus all other Heavies

15,000

10,000 ADTT (heavy veh/day) (heavy ADTT

5,000 Freight Route: Port-related heavy veh volumes are less than half that on N3 0 2010 2015 2020 2025 2030 2035 2040 2045 Target Year

N3 West of Marianhill Plaza Freight Route, Table 11, East Approach, Shongweni I/C

160,000 160,000 Parallel (Freight) Parallel (PMB Bypass)

140,000 140,000

120,000 120,000

100,000 100,000

2017 2027 80,000 80,000 2037

6 Lanes AADT (pcu/day) AADT 60,000 60,000 8 lanes 10 lanes

40,000 40,000

20,000 20,000

- -

Section

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23

Dard

Hilton Cato Market Chota Cedara Hilton Forecast Conditions (Cato Ridge-PMB) Athlone (P Brown) Existing Forecast Chatterton Rd Existing Lanes 2010 2017 2022 2027 Existing Lanes Existing Lanes Existing Lanes Existing Lanes Sanctuary Rd AADT AADT AADT AADT From Interchange From Interchange (PCU) (PCU) (PCU) (PCU) PH V/C LOS PH V/C LOS PH V/C LOS PH V/C LOS Chota Motalla Hilton Cedara 52 800 0.43 B 72 400 0.59 C 86 400 0.71 C 100 400 0.82 D Orthmann Rd Athlone Hilton 56 400 0.46 B 77 100 0.63 C 91 800 0.75 D 106 500 0.87 D Chatterton Athlone New England 46 600 0.38 B 63 100 0.52 C 74 800 0.61 C 86 600 0.71 C Sanctuary Rd Chatterton 32 300 0.27 A 43 600 0.36 B 51 700 0.42 B 59 700 0.49 B Epworth Chota Motala Sanctuary Rd 62 200 0.38 B 80 400 0.50 C 93 300 0.57 C 106 300 0.65 C Ohrtmann Rd Chota Motala Market St 49 700 0.61 C 64 700 0.80 D 75 500 0.93 E 86 200 1.06 F New England Rd Ohrtmann Rd 66 800 0.82 D 86 900 1.07 F 101 300 1.25 F 115 700 1.43 F Ashburton Epworth New England Rd 54 400 0.67 C 72 000 0.89 D 84 600 1.04 F 97 200 1.20 F Market Rd Epworth Lion Park 66 300 0.82 D 86 600 1.07 F 101 000 1.24 F 115 500 1.42 F Ashburton Market Rd 56 500 0.70 C 74 100 0.91 D 86 700 1.07 F 99 300 1.22 F Dardanelles Lynnfield Park Ashburton 56 800 0.70 C 74 700 0.92 E 87 500 1.08 F 100 300 1.24 F Camperdown Dardanelles Lynnfield Park 59 100 0.73 C 78 000 0.96 E 91 600 1.13 F 105 100 1.30 F Cato Ridge Camperdown Dardanelles 55 100 0.68 C 72 400 0.90 E 84 700 1.04 F 97 000 1.20 F BP Engen Cato Ridge Camperdown 55 300 0.68 C 71 900 0.90 E 83 800 1.03 F 95 600 1.18 F Hammarsdale

Cliffdale

M13

Shongweni

Mahogany Ridge

Richmond Rd

St James Rd M7

M13 N3 Planning and Upgrading – Safety Considerations Town Hill High Accident Zones

PMB

N3

Dardanelle’s i/c Safety Issues Key Ridge M13 – MRI Link Cato Ridge Proposed Grindrod Logistics M13 Hub

Freight Route 7 M7

Port of Durban N3 Planning and Upgrading

Scope • Addition of 2 and 3 lanes per direction resulting in a eight to ten lane freeway over a distance of 84km • Existing Toll section between Paradise Valley and Key Ridge (18km) to be upgraded from 6 lanes to 8 lanes and 10 on some sections • Median consisting of a concrete barrier with drainage • Road surface of asphalt and concrete over most sections due to extreme loads from heavy vehicles • Upgrading of twenty four interchanges • Ninety five underpass/overpass bridges required to be upgraded • Ringroad to Pietermaritzburg being considered • Key Ridge Re-alignment being considered • M13 –N3 link being considered • Tunnels on Pietermaritzburg Ringroad and at Townhill as options • 36 -42 month construction duration

N3 upgrades required - additional lanes & upgraded interchanges Town Hill/Key Ridge: - Safety issues: steep gradients due to topography 3 truck stops introduced for safety long moving queues of trucks safety issues at interchanges - Other issues: geological problems limited land availability - Alternative required: to improve safety to meet demand convenient link to Dube Trade Port

 Route Location Study:

- Routes identified and analysed according to: length false rise cost

- Routes assessed according to impact on: existing infrastructure land use

LYNNFIELD PARK INTERCHANGE DARDENELLES INTERCHANGE ASHBURTON INTERCHANGE MARKET – EPWORTH INTERCHANGE NEW ENGLAND ROAD INTERCHANGE OHRTMANN ROAD INTERCHANGE SANCTUARY ROAD INTERCHANGE

Estimated Cost (R Section Length (km) million) in 2013 rand Candella Road-M13 (Paradise Valley) 7.0 1 904 M13 (Paradise Valley) to Richmond Road I/C 5.6 1 284 M7 between N2 and N3 9.1 1 825 Key Ridge-Hammarsdale I/C 5.3 1 327 Cato Ridge to Lion Park 12.5 2 186 Lion Park to Market Road 9.2 1 708 Market Road to Epworth 1.5 582 Epworth to Cedara 19.6 2 471 Candella Road-M13 (Paradise Valley) 7.0 1 904 TOTALS 69.9 13 290

Estimated Cost (R Section Length (km) million) in 2013 rand Richmond Road I/C to Key Ridge 12.3 1 568 Hammarsdale I/C to Cato Ridge 11.3 2 162 Pietermaritzburg Ringroad (Tunnel Option) 11.0 11 550 TOTALS 34.6 15 610 • Preliminary Designs Completed • Detail designs on hold • Land Acquisition commenced • Environmental process with specialist studies commenced • PPP to commence within next 2-3 months • PMB Ringroad environmental fatal flaw scan underway

Town ADT ADTT % %night Mtubatuba 6686 1266 18.9 15.2 Mkuze 3572 968 27.1 13 Mvoti 20742 2476 12 11.2 King Shaka 21371 1472 7 11.8 Mhloti 45153 3296 7.3 12.7 EB Cloete 129478 9000 7.0 12.5 Coedmore 79244 5145 6.5 11.1 Winkelspruit 27425 2060 7.5 11 Park Rynie 15655 1736 11 12 Kokstad 6589 825 12.5 11

140000 129478 120000 100000 79244 80000 60000 45153 ADT 40000 27425 ADTT 20742 21371 15655 20000 9000 6686 5145 6589 1266 3572968 2476 1472 3296 2060 1736 825 0 Mhloti

Isipingo

Background ● The N2 Outer Ring Road was completed in the mid 70’s ● Consists of a dual divided carriageway freeway with three lanes per directions ● Carries in excess of 130,000 vehicles per day - mainly urban commuter traffic ● Substantial delay costs during peak periods, requiring major upgrading of freeway (add. of lanes) and interchanges (4) and underpass/overpass bridges (60)

Mgeni I/C 65,359 NB 66,105 SB 55,650 EB 131,464 T 56,318 WB 111,968 T EB Cloete I/C

50,486 NB 50,648 SB 101,134 T

Edwin Swales I/C

31,280 NB 31,347 SB 62,627 T Higginson H’way I/C  Mt Edgecombe I/C 41,165 NB 41,788 SB 82,953 T

Kwamashu I/C

50,251 NB 48,824 SB 99,075 T

Mgeni/Inanda I/C Ballito I/C

11,673 NB 12,127 SB  23,800 T

Mhloti I/C

23,141 NB 25,158 SB 48,299 T

Mt Edgecombe I/C Upgrade Benefits - a higher average speed; - a greater capacity; - an overall vehicle safety along with a reduction in accidents and incidents; - Substantial reduction in delay time. ● Job Creation Estimate: 14,100 direct, indirect and induced jobs (potential) ● Currently under preliminary design for various sections ● Major constraint to upgrade is funding from fiscus due to large capital outlay required – alternative funding source required Scope of Work • Addition of 2 to 3 lanes per direction resulting in a ten to twelve lane freeway over a distance of 50km • Addition of auxillary lanes between interchanges • Median consisting of a concrete barrier with drainage • Road surface of asphalt or concrete where required • Upgrading of four interchanges • Sixty underpass/overpass bridges required to be upgraded • Median lighting • Estimated to cost between R 7,5 to R8 billion

• Future Cross section Ramp B1 Pedestrian bridge

Ramp A3 Ramp A2

Ramp C1 Ramp D3 Ramp D4 Ramp D2 Ramp D5 Ramp C2

Pedestria Ramp A1 n bridge

Ramp D1

Background

E B Cloete StructureEB Improvements CLOETE I/C – Where’s the problem

Arch StructureLANE ADDITIONS

Existing Trestle Arch

Proposed Trestle

The central column to the trestle structure will be replaced with cable stays supported from an arch structure spanning the entire interchange. Estimated Cost (R Length Section million) in 2013 (km) rand i/c to Edwin Swales i/c 20.6 2 369 Edwin Swales i/c to Mgeni i/c 8.9 2 022 Mgeni i/c to Mt Edgecombe i/.c 11.7 2 023 Mt Edgecombe i/c to Mhloti i/c 8.9 694 TOTALS 50.1 7 109 • FUNDING FOR CONSTRUCTION – Challenges : – Substantial Upgrade costs – User Pay versus Fiscus Funding – Balancing of Taxes and Fuel Levy – limited tax base – User Pay allows substantial early commencement of upgrades when required – Upgrading N2/N3 through fiscus funding could take substantially long – PICC to make a decision on funding options • INTERGRATED TRANSPORT PLANNING • BALANCING OF RAIL VS ROAD • PRESERVING MOBILITY AND SAFETY OF THE NATIONAL ROAD NETWORK • LIMITING NEW ACCESSES WHERE POSSIBLE • ENGAGING WITH OTHER ROADS AUTHORITES