Transport Statement

Proposed Residential Development Forge Road,

Wainhomes (NW) LTD

March 2018

DOC REF: VAL/18056/TS/1

18056 - Proposed Residential Development, Forge Road, Chinley Transport Statement

Prepared by: VAL

Vicky Lomas

Checked by: MD

Mark Devenish CEng MCIHT

Document Revision Control

Revision Date Status Prepared By Approved By

0 14.03.2018 Planning VAL MD

Colwyn Chambers 19 York Street M2 3BA

T: 0161 832 4400

E: [email protected] W: www. scptransport.co.uk

This document has been prepared for the titled project or named part thereof and should not be relied upon or used for any other project without an independent check being carried out as to its suitability and prior written authority of SCP being obtained. SCP accepts no responsibility or liability for the consequence of this document being used for a purpose other than the purposes for which it was commissioned. Any person using or relying on the document for such other purposes agrees and will by such use or reliance be taken to confirm his agreement to indemnify SCP for all loss or damage resulting there from. SCP accepts no responsibility or liability for this document to any party other than the person by whom it was commissioned.

Page i 18056 - Proposed Residential Development, Forge Road, Chinley Transport Statement

CONTENTS

1.0 INTRODUCTION ...... 1 2.0 EXISTING CONDITIONS ...... 3 3.0 SUSTAINABLE TRANSPORT APPRAISAL ...... 7 4.0 PROPOSED DEVELOPMENT ...... 13 5.0 TRIP GENERATION ...... 14 6.0 SUMMARY AND CONCLUSIONS ...... 15

APPENDICES

1 APPEAL DECISION LETTER 2 HIGHWAY IMPROVEMENTS 3 PROPOSED SITE LAYOUT PLANS 4 VISBILITY SPLAYS 5 SWEPT PATH ANAYLSIS 6 TRICS RESULTS

Page ii 18056 - Proposed Residential Development, Forge Road, Chinley Transport Statement

1.0 INTRODUCTION

Overview

1.1 SCP have been instructed by Wainhomes to provide transport advice in connection with their proposal for 17 residential units on Forge Road, Chinley. This will effectively be Phase 3 of their proposed development at Forge Works.

1.2 Phase 1 and 2 of the development gained outline consent under the application ref (HPK/2012/0323); this was refused planning permission in 2012 but approved at appeal. The consent is for up to 182 dwellings, 1,672sqm business floor space, 279sqm of D1 non- residential, community facilities and associated infrastructure. The appeal decision notice can be found in Appendix 1.

1.3 In 2013 an application was submitted for the approval of reserved matters (HPK/2013/0577) in accordance with Phase 1 which was approved. In 2016 a second application was submitted for the approval of reserved matters (HPK/2016/0313) in accordance with Phase 2 of the scheme which was approved.

1.4 The location of the site is indicated on the aerial photograph below:

Figure 1.1 – Site Location

Forge Road Phase 1 and Phase 2

Site

Page 1 18056 - Proposed Residential Development, Forge Road, Chinley Transport Statement

1.5 The site is located on Forge Road, to the south of Chinley village centre.

1.6 The site is bounded by Forge Road to the north, Phase 1 and 2 of the scheme to the east, Greenfield land to the south and residential properties and a scout hut to the west.

1.7 The site is undeveloped land which backs onto the Tramway Trial and it is allocated as countryside in the adopted Local Plan.

1.8 This report considers the traffic and transportation aspects of the proposed development and draws upon the planning consent of Phase 1 and 2 to inform this.

1.9 The following sections of this report is sub-divided into the following:

• Section 2 – Sets out the existing context and transport network

• Section 3 – Looks at the accessibility of the site.

• Section 4 – Provides details of the proposed development.

• Section 5 – Analyses the development related traffic movements

• Section 6 – Provides our summary and conclusions

Page 2 18056 - Proposed Residential Development, Forge Road, Chinley Transport Statement

2.0 EXSITING CONDITIONS

Overview 2.1 This Chapter provides a detailed description of the location of the site and composition, planning history, local highway network and road safety record.

Site Location and Composition

2.2 The site is located approximately 800m to the south of Chinley centre, on the western edge of the Peak District National Park. Phase 1 and 2 of the development scheme was last used for industrial manufacturing purposes and incorporated areas for storages such that the use class was B2.

2.3 The site is bounded by Forge Road to the north, Phase 1 and 2 of the scheme to the east, Greenfield land to the south and residential properties to the west.

2.4 The site which has been proposed for Phase 3 of the development is undeveloped land which backs onto the Peak Forest Tramway Trial.

Planning history

2.5 The outline application which was made up Phase 1 and 2 of the development which gained outline consent under the application ref (HPK/2012/0323); this was refused planning permission in 2012 but approved at appeal. The consent is for up to 182 dwellings, 1,672sqm business floor space, 279sqm of D1 non-residential, community facilities and associated infrastructure.

2.6 In 2013 the case was approved on appeal for Phase 1 and 2.

2.7 In the appeal decision the inspector concluded:

24) The proposed development would include a number of improvements to the highway network in the vicinity of the junction of Forge Road with Whitehough Head Lane/Green Lane. Firstly, the appellants propose a slight realignment of the junction such that to the north, along Green Lane, there would be visibility in excess of 36m. Further, a scheme of traffic calming is proposed including raised junction platforms, raised tables at pedestrian crossing points and a pedestrian priority area with a 40mm kerb upstand in the carriageway, along with improved street lighting and improved road signs and road markings. These works are supported by the Highway Authority.

Page 3 18056 - Proposed Residential Development, Forge Road, Chinley Transport Statement

In my opinion, the improvements proposed to this junction would sufficiently increase visibility for drivers exiting Forge Road to see and be seen clearly by drivers of vehicles travelling along Whitehough Head Lane/Green lane. Further, the proposed traffic calming scheme along this part of the highway would substantially reduce the speed of vehicles approaching this junction.

25) Although the existing junction of Forge Road with Whitehough Head Lane/Green Lane is substandard, given the evidence that it has operated safely since 2001, including a time when the previous factory was in operation on the appeal site, and the relatively low speeds and numbers of vehicles travelling along Whitehough Head Lane/Green Lane, along with the scheme of improvements and traffic calming proposed by the appellants, I am satisfied that the modest increase in traffic movements associated with the proposed development would be safely accommodated within the highway network. As such, it would not be detrimental to highway safety.

29) I conclude, therefore, that the proposed development would not harm highway and pedestrian safety. As such, it would not be contrary to Local Plan Policies TR4 and TR5 or the guidance in The Framework.

33) I conclude, therefore, that the proposal would represent a sustainable form of development. As such, it would accord with the guidance in The Framework.

2.8 Phase 1 and 2 of the scheme have already been granted planning permission and this transport statement supports Phase 3 of the scheme. All phases of the scheme are located on land to the south of Forge Road.

2.9 A reserved matters applications for Phase 1 (Ref: HPK/2013/0577) was granted planning permission on the 27th January 2014 for 91 dwellings, 1 No. B1 office unit and 1 No. D1 Crèche unit. The site is already under construction.

2.10 Phase 2 (Ref: HPK/2016/0313) was granted planning permission subject to conditions on the 29th November 2017 for 62 dwellings and associated work pursuant to Phase 1’s conditions.

2.11 Phase 1 and 2 included vehicle speed reducing features and areas of pedestrian priority, the improvements are included in Appendix 2 and include:

• Raised junction platforms

• Raised tables at pedestrian crossing points

• Pedestrian priority area with a 40mm kerb upstand in the carriageway

Page 4 18056 - Proposed Residential Development, Forge Road, Chinley Transport Statement

• Improved street lighting

• Improved road signs and road markings

Local Highway Network

2.12 The site will be accessed from Forge Road, where there were no previous footways or street lighting provided, however a footway is approved as part of Phase 1 & 2.

2.13 The existing road network is made up of Forge Road from which Phase 1, 2 and 3 of the development will have direct access.

2.14 Forge Road connects to Green Lane at a priority junction at the western edge of the development site.

2.15 Green Lane is a single carriageway road and is subject to a 30mph speed limit. The road provides a connection to the B6062, through the village centre to the north of the site, and continues southwards from the site access as Whitehough Head Lane.

2.16 There is currently no footway along sections of Green Lane, to the north of the site access. As part of the permission of Phase 1, it has been agreed that the applicant is to undertake works in the vicinity of the site access to improve conditions for all road users along Green Lane. It has been acknowledged by the County Council that there is insufficient width to provide a standard footway link, therefore a pedestrian priority scheme is to be implemented.

Visibility

2.17 Following improvements to the junction as part of the previous Phases visibility splays of 2.4m X 36m are achievable at the junction between Whitehough lane and Forge Road.

2.18 The Phase 1 and Phase 2 Appeal Decision noted:

The proposed development would include a number of improvements to the highway network in the vicinity of the junction of Forge Road with Whitehough Head Lane/Green Lane. Firstly, the appellants propose a slight realignment of the junction such that to the north, along Green Lane, there would be visibility in excess of 36m. Further, a scheme of traffic calming is proposed including raised junction platforms, raised tables at pedestrian crossing points and a pedestrian priority area with a 40mm kerb upstand in the carriageway, along with improved street lighting and improved road signs and road markings. These works are supported by the Highway Authority.

Page 5 18056 - Proposed Residential Development, Forge Road, Chinley Transport Statement

In my opinion, the improvements proposed to this junction would sufficiently increase visibility for drivers exiting Forge Road to see and be seen clearly by drivers of vehicles travelling along Whitehough Head Lane/Green lane. Further, the proposed traffic calming scheme along this part of the highway would substantially reduce the speed of vehicles approaching this junction.

Although the existing junction of Forge Road with Whitehough Head Lane/Green Lane is substandard, given the evidence that it has operated safely since 2001, including a time when the previous factory was in operation on the appeal site, and the relatively low speeds and numbers of vehicles travelling along Whitehough Head Lane/Green Lane, along with the scheme of improvements and traffic calming proposed by the appellants, I am satisfied that the modest increase in traffic movements associated with the proposed development would be safely accommodated within the highway network. As such, it would not be detrimental to highway safety.

2.19 Accident records confirm that there has been no accidents in the vicinity of Forge Road over the last 15 year period, which includes a period when the former industrial site (Phase 1 and Phase 2) was still operational.

Page 6 18056 - Proposed Residential Development, Forge Road, Chinley Transport Statement

3.0 ACCESSIBILITY OF THE SITE

3.1 The accessibility of the application site by non-car modes is a key consideration in the planning process. The requirement to ensure that sites are accessible by non-car modes of transport is set out in both local and national planning policy (National Planning Policy Framework).

Walking

3.2 A walk distance of 2km is suggested as being able to replace short car journeys. As illustrated by Figure 3.1 overleaf the site is within walking distance of amenities and employment areas. This demonstrates that, residents will be able to access a whole range of facilities within an easy walk of the site.

3.3 For access into the village centre, the most direct route is from the Forge Road/Green Lane junction; the main entrance to the site. There is a section of approximately 100m to the north from the site where there is no footway provision but after this initial 100m length there are footways on both sides of Green Lane that are well surfaced and street lit.

3.4 There are a number of Public Rights of Way (PROW) providing connections to Chinley Village and the wider area. Footpath routes FP172 and FP124 link between Whitehough Head Lane and Charley Lane. FP124 is part of the Peak Forest Tramway Trial, which runs between Bugsworth Basin in and Charley Lane.

3.5 As mentioned previously, currently there is no footway along sections of Green Lane, to the north of the site access. As part of the permission of Phase 1 and 2 it has been agreed that the applicant to undertake works in the vicinity of the site access to improve conditions for all road users along Green Lane.

3.6 In addition, work to create a new footway along Forge Road has been agreed by the applicant and DCC under the Outline consent.

Page 7 18056 - Proposed Residential Development, Forge Road, Chinley Transport Statement

Figure 3.1 – 2km Walk Accessibility

3.7 As the plan above shows, the site is within 800m walking distance of the centre of Chinley and its associated facilities. Within 1km walk from the development site (equal to 12 minutes) is Chinley Railway Station, allowing for easy access to employment opportunities in the larger towns and cities within the region and beyond.

3.8 Table 3.1 overleaf demonstrates that a number of facilities and amenities are within close walking distance of the site.

Page 8 18056 - Proposed Residential Development, Forge Road, Chinley Transport Statement

Table 3.1 – Accessibility to Local Facilities from the Development Site

Facility Name Distance from the Development Site Nursery Chinley Day Nursery On-Site Public House Old Hall Inn 600m Takeout Café Bombay 700m Pharmacy Peak Pharmacy 700m Post Office Chinley Post Office 700m ATM Chinley Stores 750m Convenience Store Chinley Stores 750m Community Centre Chinley Community Centre 900m Railway Station Chinley Railway Station 1.0km Primary School Chinely Primary School 1.7km

3.9 Overall, the walk accessibility of the development provides a good opportunity for short trips to be made by foot to and from the development site.

Cycling

3.10 Cycling is a cheap, efficient and healthy way to travel. Cycling also provides a predictable arrival time which is often quicker than driving or using public transport, and is subject to fewer traffic and congestion delays.

3.11 Transport Policy identifies that cycling represents a realistic and healthy alternative to the use of the private car for making journeys up to 5km as a whole journey or as part of a longer journey by public transport.

3.12 As mentioned previously, FP124 forms part of the Peak Forest Tramway Trail, which runs between Buxworth and Charley Lane. This route is traffic-free between Charley Lane and Whitehough Head Lane but then changes to an on-road route for the remainder of its length. The route terminates on Brookside which connects to Route 68 of the National Cycle Network (NCN).

3.13 Route 68 runs between Etwall and Charlesworth and is made up of a combination of on-road and traffic-free sections along its length. Route 68 forms part of the Pennine Cycleway which is a long-distance route between Derby and Berwick-upon-Tweed. Route 68 also connects to other NCN routes along its route, allowing for other destinations to be accessed when utilising these routes.

3.14 Technical guidance states that cycling also has potential to substitute for short car trips, particularly those under 5km, and to form part of a longer journey by public transport.

Page 9 18056 - Proposed Residential Development, Forge Road, Chinley Transport Statement

3.15 A 5km cycle catchment from the site has been undertaken, to illustrate cycle routes and the areas within this catchment, and is shown in Figure 3.2 below.

Figure 3.2 – 5km Cycle Accessibility

3.16 As the plan shows, the site is within cycling distance of Chinley, Whaley Bridge and Chapel-en- le-Frith, which is ideal for accessing local employment opportunities and leisure activities. When travelling by cycle, Chinley and Chapel-en-le-Frith railway stations can be accessed within this 5km distance.

3.17 Overall, the cycle accessibility of the development provides a good opportunity for short trips to be made by cycle to the development site.

Public Transport

3.18 Guidance published by the IHT ‘Planning for Public Transport in Developments’ (1999), recommends that the maximum walking distance to a bus stop should be 400 metres, equating approximately to a five minute walk.

Page 10 18056 - Proposed Residential Development, Forge Road, Chinley Transport Statement

3.19 The nearest bus stops to the development site are located in Chinley village, approximately 800m from the centre of the development site, along Station Road. Additional stops are provided along Station road approximately 1.0km from the centre of the development site. The stops along Station Road are sheltered with seating while the stops along Lower Lane are flag and poles with timetables.

3.20 A summary of the bus routes which serve these bus stops is provided below:

Table 3.2 – Bus Route Summary

Bus Stop Locations Average Frequency Service Station Lower Route Description Number Monday to Saturday Saturday Sunday Rd Ln ✓ Buxton - Chapel-en-le-Frith - New Mills - No No DCB  60 mins Glossop - Tintwistle Service Service

 ✓ Bridgemont - Buxworth - Chinley - 1 service per day in No No 40 Chapel High School (school service) either direction Service Service

Glossop - Little Hayfield - Birch Vale -  ✓ 1 service per day in No No 68 New Mills - Chinley - Buxton (school either direction Service Service service)

✓ ✓ Buxton Chapel-en-le-Frith Chinley No 190 – – – 2 hours 2 hours Whaley Bridge Service

✓ ✓ Buxworth - New Mills - Marple College 1 service per day in No No 399 (college service) either direction Service Service

Source: Traveline East Midlands

3.21 The 190 service provides a two hourly service throughout the day between Buxton and Whaley Bridge and passes a Tesco and Morrisons supermarket, several high schools and Whaley Bridge Railway Station.

Public Transport – Train

3.22 Chinley also benefits from a railway station, which is located approximately 1.0km to the northwest of the site. This provides services between Manchester, and Nottingham.

3.23 Services from this station typically run on an hourly frequency during the day but also provide direct connections to other stations including Stockport and Liverpool in the commuter peak hours.

Page 11 18056 - Proposed Residential Development, Forge Road, Chinley Transport Statement

3.24 TRACC software has been used to map a 60 minute journey time using public transport, including the walk to the nearby bus stops, tram stops and railway stations, and are presented in Figure 3.3. The analysis demonstrates that it is possible to reach a vast array of areas in the north-west region such as Manchester, Stockport, Glossop and Macclesfield amongst others, within an acceptable 60 minute commute time.

Figure 3.3 – 60 minute public transport accessibility

Conclusion

3.25 As such, it can be seen that the site is in an accessible location and has good potential for sustainable travel to and from the development, with public transport links along with a number of local amenities in close proximity.

3.26 The Phase 1 and 2 appeal decision noted:

I conclude, therefore, that the proposal would represent a sustainable form of development. As such, it would accord with the guidance in The Framework.

Page 12 18056 - Proposed Residential Development, Forge Road, Chinley Transport Statement

4.0 PROPOSED DEVELOPMENT

4.1 The proposed development will form Phase 3 of the Forge Road development and will provide up to 17 dwellings, which will be in addition to the 91 (Phase 1) and 62 (Phase 2) dwellings, office unit and crèche unit approved in January 2015 and November 2017.

4.2 There will also be a footpath through the site which directly links the site to Phase 1 and 2 of the development.

4.3 The site layout can be seen in Appendix 3.

Proposed Access Arrangements

4.4 The site will be served by a new access from Forge Road, which will provide for both vehicle and pedestrians in and out of the site. A preliminary layout for this is included in Appendix 4.

4.5 The site accesses provide visibility splays that have an ‘x’ (minor arm setback distance) of 2.4m and a ‘y’ (major road visibility) distance in excess of 25m in both directions, suitable for vehicle speeds of 20mph in accordance with Manual for Streets. Given the proximity of the access to the junction with Whitehough Head Lane to the west, the proposed traffic calming and given that Forge Road is a cul-de-sac it is considered that vehicle speeds are unlikely to exceed 20mph.

Servicing and Refuse Collection

4.6 The internal road network has been designed to ensure the movement of service and refuse vehicles can be accommodated without allowing their requirements to dominate the layout, in accordance with the principle set out in Manual for Streets.

4.7 Swept path analysis has been undertaken of the site access which demonstrates that the movements of a large refuse vehicle can be accommodates. Swept path analysis is shown on drawing number SCP/18056/ATRO1 presented in Appendix 5.

Scout Group Car Park

4.8 As shown on the proposed site layout plan at Appendix 3, the proposed scheme also provides off-street car parking for the First Chinley Scout Group who are based at Victory Hall at the junction of Forge Road, Whitehough Head Lane and Green Lane. Currently visitors to Victory Hall currently park alongside the wall outside of the premises.

Page 13 18056 - Proposed Residential Development, Forge Road, Chinley Transport Statement

4.9 Indeed, once Forge Road becomes adopted the area currently utilised by the Scout Group for parking will become highway verge and Forge Road itself at the junction with Green Lane and Whitehough Head Lane will be subject to parking restrictions.

4.10 Working collaboratively with the First Chinley Scout Group the application includes a new car park for the sole use of the Scouts and which contains 20 spaces, with a separate dedicated access provided from Forge Road. Therefore, the proposed car park for the Scout Group will remove the existing on-street parking and accommodate displacement of this following the adoption of Forge Road.

Page 14 18056 - Proposed Residential Development, Forge Road, Chinley Transport Statement

5.0 TRIP GENERATION

5.1 This chapter provides an estimate of the Multi Modal trips generated by the proposed use of the site.

Trip Generation

5.2 To estimate the trip generating potential of the residential use of the site, the TRIP rates used for Phase 1 and 2 have been applied to 17 dwellings. The sites selected for Phase 1 and 2 were restricted to those sites containing between 50 and 300 houses, which can be found in Appendix 6. Table 5.1 below summaries the trip rates for housing derived from the TRICS database, and the resulting development traffic.

5.3 By applying the same trip rates which were used for Phase 1 and 2, it is inevitable that this will be a robust assessment of the development as sites containing a much higher number of dwellings have been used to assess the development site.

Table 5.1 – Residential Trip Rates (Trip Rate per Dwelling)

Weekday AM Peak Hour (08:00 Weekday PM Peak Hour (17:00 Daily to 09:00) to 18:00) Mode

Arrivals Departures Arrivals Departures Arrivals Departures

Vehicles 0.168 0.431 0.408 0.025 2.757 2.852

Trip 3 7 7 4 47 48 Generation

5.4 It can be seen from the above table that the proposed development would generate a total of 10 movements two-way in the AM Peak and 11 movements two-way in the PM peak.

5.5 The outline consent included 182 dwellings for Phases 1 and 2, however the pursuant reserved matters applications included a combined total of 153 units. Therefore the cumulative trip generated by the Phase 3 proposals would be within that permitted by the outline consent.

5.6 The scout car park is to accommodate existing demand so will not generate any additional vehicle trips.

5.7 In summary the above trip rates show that the proposed development will not have a material traffic impact.

Page 15 18056 - Proposed Residential Development, Forge Road, Chinley Transport Statement

6.0 SUMMARY AND CONCLUSIONS

6.1 This transport statement has been prepared by SCP on behalf of Wainhomes Ltd to support a planning application for phase 3 of a development on undeveloped land at Forge Road.

6.2 It has been demonstrated that the site is accessible by sustainable transport modes infrastructure from the site is reasonable with access to cycle routes and bus and train services to a range of facilities.

6.3 The proposed development is for Phase 3 of a 3 part development. Phase 1 and 2 have both been granted planning permission for 91 and 62 dwellings, office space and a crèche.

6.4 As part of the application a 20 space car park is proposed for the adjacent scout group building, which will accommodate the existing on-street car parking associated with this.

6.5 Phase 1 and 2 have been granted planning permission subject to conditions which incorporate a number of highway and transport improvements. These measures include:

• A more defined junction of Forge Road with Whitehough Head Lane which provides kerbs on the Forge Road carriageway, improved sight lines for traffic emerging from Forge Road and footways along Forge Road.

• Traffic calming along Green Lane and Whitehough Head Lane to further control traffic speeds and incorporating a pedestrian priority area along Green lane.

• Improve street lighting on Green Lane

• Funding to improve cycle stands at the railway station and/or to improve bus stops on Lower Lane.

• Pedestrian and cycle connections between the site and the Peak Forest Tramway Trail.

6.6 The proposed development is predicted to generate low levels of vehicular traffic in both the morning and evening peak hours which would not have a material impact on the highway network. The cumulative levels of vehicular traffic for Phases 1-3 combined is lower than that permitted in (Ref: HPK/2013/0577).

6.7 Overall, our investigations have confirmed that the Phase 3 proposals are acceptable with regard to transport.

Page 16 APPENDIX 1

Appeal Decision Inquiry held on 23 - 25 April 2013 Site visit made on 25 April 2013 by Karen L Baker DipTP MA DipMP MRTPI an Inspector appointed by the Secretary of State for Communities and Local Government

Decision date: 29 May 2013

Appeal Ref: APP/H1033/A/13/2189819 Forge Works, Forge Road, Chinley, SK23 6BW ñ The appeal is made under section 78 of the Town and Country Planning Act 1990 against a refusal to grant outline planning permission. ñ The appeal is made by Innovation Forge Limited and Woodford Land Limited against the decision of High Peak Borough Council. ñ The application Ref. HPK/2012/0323, dated 31 May 2012, was refused by notice dated 30 November 2012. ñ The development proposed is the demolition of all remaining structures and redevelopment for up to 182 dwellings, up to 1,672sqm of business floorspace (Use Class B1), up to 279sqm of non-residential institution floorspace (Use Class D1), community facilities and associated infrastructure.

Procedural Matters

1. The planning application was made in outline with all matters reserved for subsequent approval, with the exception of access.

2. It was agreed at the Inquiry that the planning application was determined on the basis of the following plans: Location Plan (Drawing No. 1206CLH/FRC-LP01 Rev. A); Topographic Survey (Drawing No. P(00)004); Illustrative Masterplan (Drawing No. 1206CLH/FRC-IM02 Rev. A); Illustrative Streetscenes (Drawing No. 1206CLH/FRC-SS01 Rev. A); and, Proposed Site Access Arrangement (Drawing No. 11149/SCP4 Rev. C).

3. The appellants have submitted 2 amended plans as part of this appeal: Location Plan (Drawing No. 1206CLH/FRC-LP01 Rev. B); and, Illustrative Masterplan (Drawing No. 1206CLH/FRC-IM02 Rev. B). These amended plans, which include a revised site boundary to reflect more accurately the site‘s ownership, along with changes to the Design and Access Statement, which include scale parameters for the proposed development, were subject to a 4 week consultation period prior to the Inquiry. The changes were advertised in the Buxton Advertiser on 28 February 2013 and were subject to a letter sent to interested parties. One objection was received to these changes. At the Inquiry, the Council confirmed that it had no objections to my consideration of these amended plans and changes to the Design and Access Statement as part of this appeal. Indeed, given the minor nature of the changes proposed to the plans and the Design and Access Statement, I am satisfied that my consideration of these matters would not prejudice the Council‘s case or be detrimental to the interests of third parties. I have therefore considered the appeal on this basis.

www.planningportal.gov.uk/planninginspectorate Appeal Decision APP/H1033/A/13/2189819

4. At the Inquiry, the appellants submitted a Section 106 Agreement, which includes the provision of affordable housing as part of the development, financial contributions in respect of open space, play space, primary school places, off site highways works, off site footpath works and a Full Travel Plan, and other matters relating to the consideration of a Financial Viability Assessment, if there are material changes in financial circumstances, the timing of the completion of the non-residential development and affordable housing, the relinquishing of permitted development rights in respect of the affordable housing units and the establishment of a Site Management Company to maintain the on site roads and areas of open space. I have had regard to this Section 106 Agreement during my consideration of this appeal.

5. At the Inquiry, the Council confirmed that it would withdraw its second reason for refusal, following the submission of the Section 106 Agreement, which deals acceptably with its concerns in this regard.

Decision

6. The appeal is allowed and outline planning permission is granted for the demolition of all remaining structures and redevelopment for up to 182 dwellings, up to 1,672sqm of business floorspace (Use Class B1), up to 279sqm of non-residential institution floorspace (Use Class D1), community facilities and associated infrastructure at Forge Works, Forge Road, Chinley, Derbyshire SK23 6BW in accordance with the terms of the application, Ref. HPK/2012/0323, dated 31 May 2012, and subject to the conditions listed in Appendix 1.

Main Issues

7. The main issues in this appeal are:

a) the effect of the proposed development on highway and pedestrian safety; and,

b) whether or not the proposal would represent a sustainable form of development.

Reasons

Highway and Pedestrian Safety

8. The appeal site is located to the south of the settlement of Chinley, to the east of Whitehough Head Lane/Green Lane. The Peak Forest Tramway Trail abuts the southern boundary of the appeal site, with open countryside beyond. Residential development within Chinley is located to the north of the western part of the appeal site, beyond Forge Road and Black Brook. The land to the north of the eastern part of the appeal site is open countryside, used mostly for the grazing of cattle. A waste water treatment works lies to the east of the appeal site. To the west of the appeal site and to the south of Forge Road, beyond a field, is Victory Hall, used by the 1st Chinley Scout Group and residential properties along Whitehough Head Lane. To the south west of the appeal site, along Whitehough Head Lane is the hamlet of Whitehough.

9. The appeal site is around 7.48ha and was previously used as a factory, with an ancillary shop, by Dorma. The appeal site was historically occupied by a bleaching and dyeing company and more latterly by a fabric company, until the closure of the factory in 2005. The only vehicular access to the former factory www.planningportal.gov.uk/planninginspectorate 2 Appeal Decision APP/H1033/A/13/2189819

was via the junction of Whitehough Head Lane/Green Lane and Forge Road. It was agreed at the Inquiry, between the main parties, that 105 car parking spaces, associated with this former use, had been identified on the appeal site.

Highway Safety

10. The Council considers that, given the previous use of the appeal site, it would be reasonable to redevelop it provided that there would be an equitable exchange in respect of the level of traffic generated, whereby the level of the previous use is the benchmark against which traffic generation of the appeal proposal should be judged. The Council‘s basis for this assessment being that the traffic related to the previous industrial use of the land prior to 2005 came and went without causing any highway safety issues. As such, the Council would not want proposed traffic levels to exceed the benchmark levels. However, there is dispute between the Council and the appellants relating to the levels of traffic generated by the previous use of the appeal site.

11. It is apparent, from the evidence given by local residents at the Inquiry, that HGVs visited the appeal site, along with buses transporting staff to and from the factory. Given the number of car parking spaces, it is clear that some workers would have travelled by car, and, from the evidence given by local residents at the Inquiry, it appears that up to 4 shifts operated at the factory. Further, there is some suggestion of the use of the on site factory shop by members of the public and the sub-letting of units of accommodation within the appeal site to other businesses. I acknowledge that some staff would have travelled on foot or by bicycle from the neighbouring settlements to the factory, as would some visitors to the shop. Nevertheless, there is no definitive evidence relating to the number of people employed at the factory, including their working patterns, and the number of visitors to the factory shop, along with its opening hours, or their means and extent of travel to and from the appeal site.

12. The main parties have, therefore, each examined the likely levels of traffic generated by the previous use of the appeal site through the use of the TRICS database. I acknowledge the shortcomings of using the TRICS database in this case due to the difficulties in finding a comparable match for the former factory use. This has led to 2 approaches to the analysis of this data, with the appellants‘ Highways Consultant considering a broader sample of sites (17) and the Council‘s Highways Consultant considering a smaller sample of sites (7). I note, however, that the approach adopted by the Appellants‘ Highways Consultant was agreed with Derbyshire County Council, the Highway Authority, at the outset.

13. While the TRICS database is the industry standard tool for determining trip rates for most land uses, I acknowledge that no 2 sites are the same, either in scale, location or business operations. Indeed, the TRICS Good Practice Guide 2012 recommends caution in the interpretation of results from the database and accepts that unless parameters are agreed at the outset then different results are likely to be obtained by different users.

14. The appellants‘ Highways Consultant based his assessment on a single user industrial unit, with selection parameters including a minimum floor area of 1,000sqm, no weekend surveys and no regional exclusions. His analysis of a group of 17 sites showed that trips associated with the previous factory use of

www.planningportal.gov.uk/planninginspectorate 3 Appeal Decision APP/H1033/A/13/2189819

per hour entering/leaving the appeal site during the day. In my opinion, this would represent only a modest increase in vehicle movements along Whitehough Head Lane/Green Lane on a part of the local highway network where vehicle movements are relatively low.

22. The appellants also undertook a survey of vehicle speeds over a 7 day period in September 2011. The results of this survey indicated that the average speed of traffic over the whole week was 25mph in each direction, with the 85th percentile speed of both northbound and southbound traffic being 29.2mph. I note that with an adjustment for wet weather, the 85th percentile design speed for junction visibility is 27.8mph and the appellants‘ Highways Consultant‘s statement that, based on this design speed, visibility splays of 2.4m x 36m2 would be required by Manual for Streets at the site access onto Whitehough Head Lane/Green Lane. While it is agreed by the main parties that this visibility could be achieved to the north of the proposed access, visibility to the south would only be around 13m to the back of the kerb. Paragraph 10.5.9 of Manual for Streets 2 says that, unless there is local evidence to the contrary, a reduction in visibility below recommended levels will not necessarily lead to a significant problem. I acknowledge that the accident records dating back to 2001, when the previous factory use was still operational, for the junction of Forge Road with Whitehough Head Lane/Green Lane confirm that there have been no accidents in this location during that time. As such, despite its substandard visibility to the south, the junction has operated safely in the past.

23. The appellants‘ Highways Consultant suggests that drivers of vehicles exiting Forge Road could edge out slightly into the carriageway in order to achieve visibility in excess of 36m in both directions and that the principle of edging out is considered in Section 10.7 of Manual for Streets 2. Indeed, it states that at urban junctions where visibility is limited by buildings and parked cars, drivers of vehicles on the minor arm tend to nose out carefully until they can see oncoming traffic, and vice versa. I also note the safe operation of other junctions with poor visibility within Chinley, in particular Hunters Green Close and Ash Grove at their junctions with Green Lane, which are close to the appeal site.

24. The proposed development would include a number of improvements to the highway network in the vicinity of the junction of Forge Road with Whitehough Head Lane/Green Lane. Firstly, the appellants propose a slight realignment of the junction such that to the north, along Green Lane, there would be visibility in excess of 36m. Further, a scheme of traffic calming is proposed including raised junction platforms, raised tables at pedestrian crossing points and a pedestrian priority area with a 40mm kerb upstand in the carriageway, along with improved street lighting and improved road signs and road markings. These works are supported by the Highway Authority. In my opinion, the improvements proposed to this junction would sufficiently increase visibility for drivers exiting Forge Road to see and be seen clearly by drivers of vehicles travelling along Whitehough Head Lane/Green Lane. Further, the proposed traffic calming scheme along this part of the highway would substantially reduce the speed of vehicles approaching this junction.

25. Although the existing junction of Forge Road with Whitehough Head Lane/Green Lane is substandard, given the evidence that it has operated safely since 2001, including a time when the previous factory was in operation on the

2 Table 7.1 of Manual for Streets www.planningportal.gov.uk/planninginspectorate 6 Appeal Decision APP/H1033/A/13/2189819

appeal site, and the relatively low speeds and numbers of vehicles travelling along Whitehough Head Lane/Green Lane, along with the scheme of improvements and traffic calming proposed by the appellants, I am satisfied that the modest increase in traffic movements associated with the proposed development would be safely accommodated within the highway network. As such, it would not be detrimental to highway safety.

Pedestrian Safety

26. The Council and local residents are concerned about pedestrian safety along Whitehough Head Lane/Green Lane. At present pedestrians walking along this highway between Whitehough and Chinley are required to walk within the carriageway for part of this journey as there is no footway along the full length of this route. Although a footway exists to the south of Forge Road along Whitehough Head Lane, no such footway is present along Whitehough Head Lane and Green Lane for around 100m to the north of Forge Road, with the exception of a small footway around the entrance to Hunters Green Close.

27. The appellants would provide 2 pedestrian priority areas, with a 40mm kerb upstand, along the eastern side of Green Lane for part of this 100m section of highway. The pedestrian priority area would be denoted by buff surfacing and would be up to 1m in width. I acknowledge that this proposal is supported by the Highway Authority.

28. It was apparent from my site visit and from the evidence presented to the Inquiry by the Council and third parties that this route is popular with pedestrians walking to and from the services and facilities in Chinley, as well as the public houses in Whitehough. Indeed, it would also be the pedestrian route used by residents, staff and visitors of the proposed development. Although there is currently no formal footway for part of this route between Forge Road and Chinley, it is well used by pedestrians, with them mostly walking along the eastern side of Whitehough Head Lane/Green Lane. Although the proposed development would lead to an increase in the number of vehicles travelling along this part of Whitehough Head Lane/Green Lane, given the proposed traffic calming scheme, which would include a raised table at a pedestrian crossing point to the north of the pedestrian priority areas and raised junction platforms to the south, I consider that vehicle speeds in the vicinity of this part of Green Lane would be substantially reduced. This, added to the pedestrian priority areas denoted along this part of Green Lane, would, in my view, represent a significant improvement upon the existing conditions for pedestrians. I am satisfied, therefore, that the proposed development would not be detrimental to pedestrian safety.

29. I conclude, therefore, that the proposed development would not harm highway and pedestrian safety. As such, it would not be contrary to Local Plan Policies TR4 and TR5 or the guidance in The Framework.

Sustainability

30. Paragraph 6 of The Framework states that the purpose of the planning system is to contribute to the achievement of sustainable development and that policies in paragraphs 18 to 219, taken as a whole, constitute the Government‘s view of what sustainable development in England means in practice for the planning system. Indeed, paragraph 14 states that at the heart of The Framework is a presumption in favour of sustainable development,

www.planningportal.gov.uk/planninginspectorate 7 Appeal Decision APP/H1033/A/13/2189819

which should be seen as a golden thread running through both plan-making and decision-taking.

31. The centre of the appeal site is located around 0.7km from shops within the centre of Chinley, around 1km from Chinley Railway Station and around 1.7km from Chinley Primary School, or around 0.9km via a proposed new footpath. I note the concerns of local residents and the Council relating to the quality of the pedestrian links from the appeal site to these services and facilities and the topography of the area. I also acknowledge that there are existing parking problems at the railway station and within Chinley and that there have been reductions recently in the frequency of both bus and rail services in the area.

32. The appeal site is previously developed land on the edge of the settlement of Chinley, which benefits from a range of local services and facilities. The appellants submitted a Travel Plan with the planning application and propose a financial contribution towards the provision and maintenance of cycle stands at Chinley Railway Station and/or shelters at the bus stop outside the railway station in the Section 106 Agreement. Given this, along with the improvements proposed by the appellants to Green Lane, including a raised table at a pedestrian crossing point to the north of the pedestrian priority areas, I am satisfied that opportunities for sustainable transport modes have been taken up and that safe and suitable access to the appeal site can be achieved for all people.

33. I conclude, therefore, that the proposal would represent a sustainable form of development. As such, it would accord with the guidance in The Framework.

Other Matters

34. The Council and the appellants agree in the Statement of Common Ground that there is not currently a continuous 5 year supply of deliverable housing land in the Borough. Indeed, the Council accepted at the Inquiry that the housing land supply is currently around 2.8 years. Further, the main parties agree that there is a need for affordable homes across the Borough. At the Inquiry, the appellants confirmed that the proposed development could be completed within 5 years. The proposed development would, therefore, contribute significantly towards reducing the current shortfall in housing land supply and meeting some of the need for affordable housing. As such, these matters carry significant weight in my consideration of this proposal.

35. A small part of Forge Road within the appeal site lies within the Chinley and Whitehough Conservation Area, which was designated in 1990. I note that English Heritage have no objections to the proposed development. Given the existing run down nature of the appeal site, I am satisfied that the proposed development would preserve or enhance the character or appearance of the conservation area and would not adversely affect its setting.

36. A small part of the appeal site to the north of Black Brook is within the Green Belt, as shown on the Local Plan Proposals Map. This area of the appeal site previously contained tanks associated with the historic use of the land. The Illustrative Masterplan, submitted with the planning application, indicates that this area would be predominantly used as rear gardens to some of the proposed dwellings. Given this, along with the previous use of this part of the site, I am satisfied that the proposed development would not materially harm the openness or visual amenities of the Green Belt in this location.

www.planningportal.gov.uk/planninginspectorate 8 Appeal Decision APP/H1033/A/13/2189819

37. I have considered all the other matters raised by the Council and third parties, including, the scale of the development proposed; the increase in population and its impact on the settlement of Chinley and the hamlet of Whitehough; flooding concerns; the impact of the proposed development on the Peak Forest Tramway Trail; contamination on the appeal site; the impact of the proposed development on the living conditions of the occupiers of Forge Terrace; and the impact of the proposal on ecology; but none changes my overall conclusion that the appeal should be allowed.

Section 106 Agreement

38. The appeal proposal is accompanied by a signed and dated Section 106 Agreement between the appellants, along with other parties with an interest in the land, and High Peak Borough Council and Derbyshire County Council. It includes a number of obligations to come into effect if outline planning permission is granted. I have considered these in light of the statutory tests contained in Regulation 122 of the Community Infrastructure Levy (CIL) Regulations 2010. I have also had regard to the Council‘s Planning Obligations Supplementary Planning Document (SPD 1), adopted in December 2005. The Agreement relates to the following matters.

39. Affordable Housing: Local Plan Policy H9 seeks to ensure the provision of a proportion of affordable housing for local needs in new residential development schemes. Paragraph 6.60 of the reasoned justification to this policy recommends that at least 30% of units on sites of 0.5ha and over or 15 units or more should be provided as affordable homes. The Agreement provides for 30% of the total number of dwellings to be erected on the site to be affordable, which would comprise 60% social rented housing and 40% shared ownership housing. Further, the Agreement allows for the consideration of a Financial Viability Assessment if it is considered, and can be demonstrated, that there have been material changes in financial circumstances which could be used to determine whether the percentage of affordable housing may be reduced. In addition, the Agreement sets out the requirement that no more than 40% of the commercial dwellings shall be completed until the affordable units have been completed and transferred to a registered provider and removes permitted development rights in respect of the affordable housing units. I consider that these obligations would be necessary to make the development acceptable in planning terms, directly related to the development and fairly and reasonably related in scale and kind to the development. As such, they would pass the statutory tests.

40. Non Residential Development: The Agreement requires that no more than 65% of the commercial dwellings shall be occupied until the non-residential development has been completed, is being marketed and is available for occupation. Paragraph 38 of The Framework seeks to promote a mix of uses for larger scale residential developments in order to provide opportunities to undertake day-to-day activities including work on site. This obligation would ensure that the crèche and industrial elements of the proposal were completed and available prior to the completion of the residential development which would ensure a mix of uses on the site. As such, I consider that this obligation would pass the statutory tests.

41. Off Site Highways Contribution: Local Plan Policy TR1 requires new development to seek to widen transport choice for people and goods. Local Plan Policy TR4 seeks to ensure that adequate public transport infrastructure is

www.planningportal.gov.uk/planninginspectorate 9 Appeal Decision APP/H1033/A/13/2189819

provided and Policy TR5 requires safe and appropriate provision for access and egress by pedestrians, cyclists and public transport users. The Agreement provides for the contribution of £25,000 for the provision and maintenance of cycle stands at Chinley Railway Station and/or shelters at the bus stop outside the railway station. I am satisfied that this obligation would provide adequate public transport infrastructure and widen transport choices for residents of, and visitors to, the proposed development. As such, I consider that it would pass the statutory tests.

42. Primary School Contribution: Where new residential development necessitates a significant upgrading of existing educational facilities, Local Plan Policy CF3 requires contributions for their improvement. Derbyshire County Council, as local education authority, stated in its letter, dated 28 June 2012, in response to the planning application, that there would be a requirement for a financial contribution towards the provision of 30 primary school places. The Agreement provides for a financial contribution calculated in accordance with the provisions set out in Schedule 2 Part III of the Agreement towards the improvement and/or works to increase capacity at Chinley Primary School. Given the size of the proposed development and the number and type of units proposed, along with the number of pupils currently on roll at Chinley Primary School and the projected future numbers, I consider that this obligation would pass the statutory tests.

43. Off Site Footpath Contribution: A sum of £26,250 has been included in the Agreement for the provision of a footpath between the northern boundary of the appeal site and Buxton Road, with the primary purpose being to shorten the walking distance between the proposed dwellings and Chinley Primary School. The distance from the centre of the appeal site to the school is 1.7km via the existing highway network, but this would be reduced to 0.9km via the proposed footpath. Paragraph 38 of The Framework says that where practical, particularly within large scale developments, key facilities such as primary schools and local shops should be located within walking distance of most properties. Although Local Plan Policy TR1 requires new development to seek to widen transport choice for people and goods and Policy TR14 seeks the construction of cycle and pedestrian facilities where the development creates a need for them, I am not satisfied that in this case such a need has been demonstrated. Indeed, I am satisfied that the Primary School is within walking distance of most properties on the appeal site. As such, I am unable to conclude that this obligation would pass tests (a) and (b) in CIL Regulation 122.

44. Open Space and Play Space Contributions: The Agreement provides for a financial contribution calculated in accordance with the provisions set out in Schedule 2 Part I of the Agreement, in respect of open space, towards the purchase, development and maintenance including the purchase of associated facilities of open spaces, including allotments and other open areas in Chinley and the surrounding area being within 1 mile from any point on the boundary of the site. It also provides for a financial contribution calculated in accordance with the provisions set out in Schedule 2 Part II of the Agreement, in respect of play space, towards the development, maintenance and/or refurbishment, including the purchase of new equipment and/or facilities within Chinley or the surrounding area being within a 2 mile radius of any point on the boundary of the site. Local Plan Policy H12 requires that, where appropriate, in place of direct provision of open space, a contribution may be made towards the

www.planningportal.gov.uk/planninginspectorate 10 Appeal Decision APP/H1033/A/13/2189819

improvement of a nearby existing public recreational facility which would meet the needs of the occupiers of the new housing. SPD 1 sets out the requirements for such provision. I note that the Council‘s preference, expressed in the Statement of Common Ground, is for the majority of open space provision to be dealt with by way of contributions to existing facilities in the area and that the appellants have no objection to this approach. Given the size of the proposed development, along with its siting immediately to the south of the settlement of Chinley, I am satisfied that this approach would be appropriate in this case. As such, I consider that this obligation would pass the statutory tests.

45. Travel Plan Contribution: Local Plan Policies TR4 and TR5 require the submission of a Transport Assessment, to assess the likely effects of the development on the local transport network, and a Travel Plan, to reduce car dependency, respectively. Condition No. 11, in Appendix 1 of this Decision, requires the submission and approval of a Full Travel Plan, along with its monitoring for a period of 5 years. A sum of £6,000 has been included in the Agreement as a contribution towards the cost of monitoring the Travel Plan. Given the scale of the development proposed, along with the requirement for monitoring the Travel Plan contained within the condition, I consider that this obligation would pass the statutory tests.

46. Site Management Company: The Agreement includes a requirement for the establishment of a Site Management Company in order to manage the on site roads and public open space. In my opinion, such a provision would be necessary to ensure that the on site roads and open space are maintained to an appropriate standard in the event that they are not adopted by the County and Borough Councils respectively. As such, I consider that this obligation would pass the statutory tests.

Conditions

47. The Council and the appellants submitted a list of agreed suggested conditions at the Inquiry. I have had regard to Circular 11/95 during my consideration of these conditions. In addition to the standard time limit and approval of reserved matters conditions, 27 conditions have been suggested. Conditions requiring that space be provided within the site curtilage for storage of plant and materials, site accommodation, loading and unloading of goods vehicles, parking and manoeuvring of site operatives‘ and visitors‘ vehicles, and the provision of wheel cleaning facilities, would be necessary in the interests of highway safety. Conditions requiring the submission and approval of a detailed scheme of the junction layout for Forge Road with Whitehough Head Lane/Green Lane, along with its modification in accordance with the approved scheme, which could be combined into a single condition, and that the visibility splays be kept free of obstruction, would be necessary in the interests of highway safety.

48. Conditions requiring the submission and approval of a detailed scheme of highway improvement works for Whitehough Head Lane/Green Lane, details of phasing of the development/construction operations and the requirement that the premises shall not be occupied or come into use until the new estate roads between each respective plot and the existing public highway have been laid out in accordance with the details submitted as part of the reserved matters application, would be reasonable in the interests of highway safety. A condition requiring the submission and approval of a Full Travel Plan would be

www.planningportal.gov.uk/planninginspectorate 11 Appeal Decision APP/H1033/A/13/2189819

reasonable in the interests of promoting sustainable transport measures. A condition requiring that there be no gates or other barriers on Forge Road within 15m of the nearside highway boundary and that any gates shall open inwards only would be necessary in the interests of highway safety.

49. A condition requiring that space be provided within the site curtilage for the parking, loading and unloading, picking up and setting down of passengers and manoeuvring of residents, visitors, staff, customers, service and delivery vehicles, and cycle parking, would be reasonable in the interests of highway safety. Conditions requiring the implementation of surface water drainage works, the mitigation measures detailed within the Flood Risk Assessment and the diversion of minor watercourses which pass through the site, would be necessary to safeguard the development from flooding. Conditions requiring the submission and approval of a scheme to deal with the risks associated with contamination of the site, the implementation of the approved remediation strategy and the strategy for dealing with unexpected contamination, would be reasonable to safeguard the living and working conditions of future occupiers of the proposed development.

50. A condition requiring the submission and approval of a scheme for the provision and management of an undeveloped buffer zone, at least 8m wide, from the bank top of Black Brook would be reasonable to safeguard the environment. Conditions restricting the hours of construction work, including demolition and site clearance, and piling would be necessary to safeguard the living conditions of neighbouring residents. A condition requiring that the noise generated from the individually occupied non-residential properties at the site shall not exceed the approved noise rating levels representative of background noise (night-time and daytime) would be reasonable to safeguard the living conditions of neighbouring residents and to ensure that the living conditions of the future occupiers of the proposed dwellings on the appeal site would be satisfactory with regards to noise.

51. A condition requiring the submission and approval of a scheme of dust suppression measures would be reasonable to safeguard the living conditions of neighbouring residents. A condition requiring the monitoring of the site for ground/landfill gas would be reasonable in the interests of safeguarding the environment. A condition requiring the submission and approval of a Conservation Statement would be reasonable to safeguard the character and appearance of the Peak Forest Tramway Trail. Conditions requiring the submission and approval of a Written Scheme of Investigation for historic building recording and archaeological work, the carrying out of the development in accordance with this Scheme and the approved Conservation Statement, and the carrying out of the site investigation and post investigation assessment prior to the occupation of the development, would be reasonable in the interests of recording and analysing the site‘s heritage. Karen Baker

INSPECTOR

www.planningportal.gov.uk/planninginspectorate 12 Appeal Decision APP/H1033/A/13/2189819

9) Details of phasing of the development/construction operations shall be submitted to and approved in writing by the local planning authority in advance of works commencing on site. Thereafter development shall proceed strictly in accordance with the agreed phasing programme. Access for the residents of Forge Terrace along Forge Road shall be maintained at all times. 10) The premises hereby approved, shall not be occupied/taken into use until the new estate streets between each respective plot and the existing public highway have been laid out in accordance with details submitted as part of any reserved matters application to accord generally with the advice given in Derbyshire County Council's current residential design guide, constructed to base level, drained and lit in accordance with Derbyshire County Council's specification for new housing/industrial development roads. 11) The premises hereby approved, shall not be occupied until a Full Travel Plan has been submitted to and approved in writing by the local planning authority. Reports demonstrating progress in promoting sustainable transport measures shall be submitted annually, on each anniversary of the date of the planning consent, to the local planning authority for approval for a period of five years from first occupation of the development. 12) There shall be no gates or other barriers on Forge Road within 15m of the nearside highway boundary and any gates shall open inwards only. 13) The premises hereby approved, shall not be occupied/taken into use until space has been provided within the site curtilage for the parking, loading and unloading, picking up and setting down of passengers and manoeuvring of residents, visitors, staff, customers, service and delivery vehicles (including secure/covered cycle parking), located, designed, laid out and constructed all as agreed in writing with the local planning authority and maintained throughout the life of the development free from any impediment to its designated use. 14) No building hereby permitted shall be occupied until surface water drainage works have been implemented in accordance with details that have been submitted to and approved in writing by the local planning authority. Before these details are submitted an assessment shall be carried out of the potential for disposing of surface water by means of a sustainable drainage system in accordance with the principles set out in The Technical Guidance to the National Planning Policy Framework (or any subsequent version), and the results of the assessment provided to the local planning authority. Where a sustainable drainage scheme is to be provided, the submitted details shall: i) provide information about the design storm period and intensity, the method employed to delay and control the surface water discharged from the site and the measures taken to prevent pollution of the receiving groundwater and/or surface waters; ii) include a timetable for its implementation; and iii) provide a management and maintenance plan for the lifetime of the development which shall include the arrangements for adoption by any public authority or statutory undertaker and any other

www.planningportal.gov.uk/planninginspectorate 16 Appeal Decision APP/H1033/A/13/2189819

arrangements to secure the operation of the scheme throughout its lifetime. 15) The development permitted by this planning permission shall only be carried out in accordance with the approved Flood Risk Assessment (Version 10, dated 17 May 2012) (or any submitted Flood Risk Assessment subsequently approved by the local planning authority) and the following mitigation measures detailed within the Flood Risk Assessment: a. Limiting the surface water run-off generated by the proposed development, so that it will not exceed the run-off from the undeveloped site and not increase the risk of flooding off-site. b. Managing the risk of flooding from overland flow of surface water during severe rainfall events, such that new and existing buildings are not affected. c. Provision of compensatory flood storage on/or in the vicinity of the site to a 1 in 100 years standard (1% annual exceedence probability). d. Identification and provision of safe route(s) into and out of the site to an appropriate safe haven. e. Finished floor levels of proposed buildings are set no lower than the relevant 1 in 100 years design river flood level plus allowance for climate change plus 600mm freeboard. 16) Submission of reserved matters shall include a scheme to divert the minor watercourses that pass through the site to be approved in writing by the local planning authority. The scheme shall show that new buildings are not sited above the route of any culverted sections and be fully implemented and subsequently maintained, in accordance with the timing/phasing arrangements embodied within the scheme, or within any other period as may subsequently be agreed, in writing, by the local planning authority. 17) Prior to the commencement of the development hereby approved (or such other date or stage in development as may be agreed in writing with the local planning authority), the following components of a scheme to deal with the risks associated with contamination of the site shall each be submitted to, and approved in writing by, the local planning authority: a) A preliminary risk assessment which has identified: ñ all previous uses; ñ potential contaminants associated with those uses; ñ a conceptual model of the site indicating sources, pathways and receptors; and, ñ potentially unacceptable risks arising from contamination at the site. b) A site investigation scheme, based on a) to provide information for a detailed assessment of the risk to all receptors that may be affected, including those off site. c) The results of the site investigation and detailed risk assessment

www.planningportal.gov.uk/planninginspectorate 17 Appeal Decision APP/H1033/A/13/2189819

referred to in b) and, based on these, an options appraisal and remediation strategy giving full details of the remediation measures required and how they are to be undertaken. d) A verification plan providing details of the data that will be collected in order to demonstrate that the works set out in the remediation strategy in c) are complete and identifying any requirements for longer-term monitoring of pollutant linkages, maintenance and arrangements for contingency action. Any changes to these components require the express consent of the local planning authority. The scheme shall be implemented as approved. 18) Prior to commencement of development, (excluding demolition/site clearance) a verification report demonstrating completion of the works set out in the approved remediation strategy and the effectiveness of the remediation shall be submitted to and approved, in writing, by the local planning authority. The report shall include results of sampling and monitoring carried out in accordance with the approved verification plan to demonstrate that the site remediation criteria have been met. It shall also include any plan (a "long-term monitoring and maintenance plan") for longer-term monitoring of pollutant linkages, maintenance and arrangements for contingency action, as identified in the verification plan, and for the reporting of this to the local planning authority. The long-term monitoring and maintenance plan shall be implemented as approved. 19) If, during development, contamination not previously identified is found to be present at the site then no further development (unless otherwise agreed in writing with the local planning authority) shall be carried out until the developer has submitted, and obtained written approval from the local planning authority for, a remediation strategy detailing how this unexpected contamination shall be dealt with. The remediation strategy shall be implemented as approved. 20) Submission of reserved matters shall include a scheme for the provision and management of an undeveloped buffer zone (at least 8m wide) from the bank top of Black Brook to be agreed in writing by the local planning authority. Thereafter the development shall be carried out in accordance with the approved scheme and any subsequent amendments shall be agreed in writing with the local planning authority. The scheme shall include: ñ plans showing the extent and layout of the buffer zone; ñ details of any planting scheme (for example, native species); ñ details demonstrating how the buffer zone will be protected during development and managed/maintained over the longer term; and, ñ details of any footpaths, fencing and any other structures to be sited within the buffer zone. 21) No construction work, including demolition and site clearance, or related deliveries shall take place outside the following hours: 0700hrs and 1900hrs Monday to Friday; and, 0800hrs and 1600hrs on Saturdays.

www.planningportal.gov.uk/planninginspectorate 18 Appeal Decision APP/H1033/A/13/2189819

Nor at any time on Sundays or Public Holidays. 22) No piling shall take place outside 0900hrs and 1600hrs Monday to Friday. 23) Noise generated from individually occupied non-residential properties at the site shall not exceed the approved noise rating levels representative of background noise (night-time and daytime), measured as a 1 hour LAeq for daytime measurements, and a 5 minute LAeq for night-time measurements, at any noise sensitive property. Measurements shall be undertaken in accordance with the procedures outlined in BS4142:1997. 24) A scheme of dust suppression measures shall be submitted to and approved in writing by the local planning authority prior to the commencement of development on site. The scheme shall include measures to prevent dust escaping from the site (for example wet suppression of dust during dry periods or cessation of activities during windy conditions). The approved scheme shall be implemented in its entirety during the entire construction period. 25) No development (excluding demolition/site clearance) shall take place until monitoring at the site for the presence of ground/landfill gas and a subsequent risk assessment has been carried out in accordance with a scheme to be agreed in writing by the local planning authority. The results of the monitoring shall be forwarded to the local planning authority as soon as they are available. If the presence of ground/landfill gas is confirmed, or there is evidence that migration of ground/landfill gas is likely to occur, development shall not be commenced until remedial measures have been taken to control and manage the gas, and to monitor the effectiveness of the measures. All such measures shall be agreed in writing by the local planning authority before the commencement of the development. 26) No development, including demolition, shall take place until a Conservation Statement has been submitted to and approved by the local planning authority in writing. This document shall provide details of the proposed retention of features relating to the Peak Forest Tramway Trail along the southern boundary of the site, and the measures to be taken during the development to avoid impacts to these features. 27) No development, including demolition, shall take place until a Written Scheme of Investigation for historic building recording and archaeological work has been submitted to and approved in writing by the local planning authority, and until any prestart element of the approved scheme has been completed in accordance with the approved scheme. The scheme shall include an assessment of significance and research questions; and: a) The programme and methodology of site investigation and recording; b) The programme for post investigation assessment; c) Provision to be made for analysis of the site investigation and recording; d) Provision to be made for publication and dissemination of the analysis and records of the site investigation; e) Provision to be made for archive deposition of the analysis and records of the site investigation; and,

www.planningportal.gov.uk/planninginspectorate 19 Appeal Decision APP/H1033/A/13/2189819

f) Nomination of a competent person or persons/organization to undertake the works set out within the Written Scheme of Investigation. 28) No development shall take place other than in accordance with the archaeological Conservation Statement and Written Scheme of Investigation approved under Condition Nos. 26 and 27. 29) The development shall not be occupied until the site investigation and post investigation assessment has been completed in accordance with the programme set out in the archaeological Written Scheme of Investigation approved under Condition No. 27 and the provision to be made for analysis, publication and dissemination of results and archive deposition has been secured.

www.planningportal.gov.uk/planninginspectorate 20 APPENDIX 2

APPENDIX 3

APPENDIX 4

APPENDIX 5

APPENDIX 6 TRI CS 2011(b)v6.8.2 270911 B14.59 (C) 2011 JMP Consultants Ltd on behalf of the TRICS Consortium Tuesday 04/ 10/ 11 Page 1 OFF-LI NE VERSI ON SCP Mount Street Manchester Licence No: 726001

TRI P RATE CALCULATI ON SELECTI ON PARAMETERS:

Land Use : 03 - RESIDENTIAL Category : A - HOUSES PRIVATELY OWNED VEHI CLES

Selected regions and areas: 01 GREATER BT BRENT 1 days 02 SOUTH EAST BD BEDFORDSHIRE 2 days EX ESSEX 1 days 03 SOUTH WEST CW CORNWALL 1 days DC DORSET 1 days WL WILTSHIRE 1 days 04 EAST ANGLI A SF SUFFOLK 3 days 05 EAST MI DLANDS LN LINCOLNSHIRE 2 days NT NOTTINGHAMSHIRE 1 days 06 WEST MI DLANDS SH SHROPSHIRE 1 days WM WEST MIDLANDS 2 days WO WORCESTERSHIRE 2 days 07 YORKSHI RE & NORTH LI NCOLNSHI RE NY NORTH YORKSHIRE 2 days 08 NORTH WEST CH CHESHIRE 2 days LC LANCASHIRE 2 days 09 NORTH CB CUMBRIA 1 days TV TEES VALLEY 1 days TRI CS 2011(b)v6.8.2 270911 B14.59 (C) 2011 JMP Consultants Ltd on behalf of the TRICS Consortium Tuesday 04/ 10/ 11 Page 2 OFF-LI NE VERSI ON SCP Mount Street Manchester Licence No: 726001

Filtering Stage 2 selection:

Parameter: Number of dwellings Range: 51 to 237 (units: )

Public Transport Provision: Selection by: Include all surveys

Date Range: 01/01/03 to 21/06/09

Selected survey days: Monday 5 days Tuesday 9 days Wednesday 3 days Thursday 6 days Friday 3 days

Selected survey types: Manual count 26 days Directional ATC Count 0 days

Selected Locations: Suburban Area (PPS6 Out of Centre) 13 Edge of Town 13

Selected Location Sub Categories: Residential Zone 19 Out of Town 1 No Sub Category 6 TRI CS 2011(b)v6.8.2 270911 B14.59 (C) 2011 JMP Consultants Ltd on behalf of the TRICS Consortium Tuesday 04/ 10/ 11 Page 3 OFF-LI NE VERSI ON SCP Mount Street Manchester Licence No: 726001

TRIP RATE for Land Use 03 - RESIDENTIAL/A - HOUSES PRIVATELY OWNED VEHI CLES Calculation factor: 1 DWELLS BOLD print indicates peak (busiest) period

ARRIVALS DEPARTURES TOTALS No. Ave. Trip No. Ave. Trip No. Ave. Trip Time Range Days DWELLS Rate Days DWELLS Rate Days DWELLS Rate 00:00 - 01:00 0 0 0.000 0 0 0.000 0 0 0.000 01:00 - 02:00 0 0 0.000 0 0 0.000 0 0 0.000 02:00 - 03:00 0 0 0.000 0 0 0.000 0 0 0.000 03:00 - 04:00 0 0 0.000 0 0 0.000 0 0 0.000 04:00 - 05:00 0 0 0.000 0 0 0.000 0 0 0.000 05:00 - 06:00 0 0 0.000 0 0 0.000 0 0 0.000 06:00 - 07:00 0 0 0.000 0 0 0.000 0 0 0.000 07:00 - 08:00 26 128 0.082 26 128 0.302 26 128 0.384 08:00 - 09:00 26 128 0.168 26 128 0.431 26 128 0.599 09:00 - 10:00 26 128 0.179 26 128 0.227 26 128 0.406 10:00 - 11:00 26 128 0.160 26 128 0.200 26 128 0.360 11:00 - 12:00 26 128 0.200 26 128 0.190 26 128 0.390 12:00 - 13:00 26 128 0.217 26 128 0.200 26 128 0.417 13:00 - 14:00 26 128 0.195 26 128 0.183 26 128 0.378 14:00 - 15:00 26 128 0.200 26 128 0.197 26 128 0.397 15:00 - 16:00 26 128 0.305 26 128 0.225 26 128 0.530 16:00 - 17:00 26 128 0.343 26 128 0.210 26 128 0.553 17:00 - 18:00 26 128 0.408 26 128 0.250 26 128 0.658 18:00 - 19:00 26 128 0.300 26 128 0.237 26 128 0.537 19:00 - 20:00 0 0 0.000 0 0 0.000 0 0 0.000 20:00 - 21:00 0 0 0.000 0 0 0.000 0 0 0.000 21:00 - 22:00 0 0 0.000 0 0 0.000 0 0 0.000 22:00 - 23:00 0 0 0.000 0 0 0.000 0 0 0.000 23:00 - 24:00 0 0 0.000 0 0 0.000 0 0 0.000 Total Rates: 2.757 2.852 5.609

Parameter summary

Trip rate parameter range selected: 51 - 237 (units: ) Survey date date range: 01/01/03 - 21/06/09 Number of weekdays (Monday-Friday): 26 Number of Saturdays: 0 Number of Sundays: 0 Surveys manually removed from selection: 0