Deutsche Bahn Project History and current status

DB Projekt Stuttgart–Ulm GmbH | Manfred Leger | 21.11.2017

Gemeinsam für das Bahnprojekt Stuttgart–Ulm

DIESES PROJEKT WIRD VON DER EUROPÄISCHEN UNION KOFINANZIERT

TRANSEUROPÄISCHE NETZE FÜR VERKEHRSINFRASTRUKTUREN What are we doing?

2 DB Projekt Stuttgart–Ulm GmbH | Manfred Leger | 21.11.2017 We complete the important European long-distance corridor from Paris to

3 DB Projekt Stuttgart–Ulm GmbH | Manfred Leger | 21.11.2017 How do we do this?

4 DB Projekt Stuttgart–Ulm GmbH | Manfred Leger | 21.11.2017 We construct a new high speed line between Wendlingen and Ulm.

5 DB Projekt Stuttgart–Ulm GmbH | Manfred Leger | 21.11.2017 The Magistrale for Europe The Stuttgart–Ulm rail project Part of the cross-border high-speed rail connection in central Europe

6 DB Projekt Stuttgart–Ulm GmbH | Manfred Leger | 21.11.2017 …right through the middle of Stuttgart...

7 DB Projekt Stuttgart–Ulm GmbH | Manfred Leger | 21.11.2017 … with a new central railway station …

8 DB Projekt Stuttgart–Ulm GmbH | Manfred Leger | 21.11.2017 … and a restructured Stuttgart rail hub…

9 DB Projekt Stuttgart–Ulm GmbH | Manfred Leger | 21.11.2017 Why are we doing this?

10 DB Projekt Stuttgart–Ulm GmbH | Manfred Leger | 21.11.2017 The Magistrale for Europe The Stuttgart–Ulm rail project Part of the cross-border high-speed rail connection in central Europe

4 Countries catchment area: 35 m residents 16 m employees

11 DB Projekt Stuttgart–Ulm GmbH | Manfred Leger | 21.11.2017 We increase capacity und faster connections for short- and long-distance traffic.

12 DB Projekt Stuttgart–Ulm GmbH | Manfred Leger | 21.11.2017 urban development

approx. 150 Scoccer fields for urban development

13 DB Projekt Stuttgart–Ulm GmbH | Manfred Leger | 21.11.2017 Previously…

14 DB Projekt Stuttgart–Ulm GmbH | Manfred Leger | 21.11.2017 history The history of the rail project Stuttgart-Ulm is a long story…

15 DB Projekt Stuttgart–Ulm GmbH | Manfred Leger | 21.11.2017 Two parts and plenty of challenges!

16 DB Projekt Stuttgart–Ulm GmbH | Manfred Leger | 21.11.2017 project structure The rail project Stuttgart–Ulm is divided in two parts.

STUTTGART 21 NBS WENDLINGEN–ULM

8 approval sections 5 approval sections financing framework: 6.526 Mio. EUR total value: 3.259 Mio. EUR

17 DB Projekt Stuttgart–Ulm GmbH | Manfred Leger | 21.11.2017 Key figures The rail project Stuttgart-Ulm

1 Central station 55 bridges 120 km railway line

64 km tunnel 2 city districts sidings 1 Airport train station 25 tunnel and passages holding 1 suburban train station new

18 DB Projekt Stuttgart–Ulm GmbH | Manfred Leger | 21.11.2017 Status We are making visible progress at Stuttgart Central Station

Stuttgart Central Station

 1997 realisation competition for Stuttgart central station  The jury unanimously nominates the design by Ingenhoven Architects  The new Stuttgart Main Station, which is rotated through 90˚ to the present terminus an runs at a depth of eleven meters, is the heart of the Rail Project Stuttgart-Ulm – It comprises a total of eight tracks at four central platforms, each of which is 420 m in length – Arched ceiling with the 28 cally columns – 27 glass “light eyes” that allow daylight down to platform level – Accessible station roof

Status

 The lower part of the first three cally columns are concreted  Start of the concreting of the first upper part of a cally column in 2017  The first platforms of the new Central Railway Station are already visible  Finishing the ceiling for the new subway station

19 DB Projekt Stuttgart–Ulm GmbH | Manfred Leger | 21.11.2017 Status Mastering the challenges faced by city-based construction projects

Construction in the city

 Disposal – 8 Mio. tonnes construction waste from the Stuttgart city center – 12 Mio. tonnes construction waste from Fildern and the area – 50 percent of the construction waste is recyclable – Over 5.000 trains with construction waste deposed by the construction site logistics – A system of construction and logistic roads to relieve the Stuttgart city traffic

 Noise and emission control – Monitoring of noise pollution and emissions – Initiate countermeasures

20 DB Projekt Stuttgart–Ulm GmbH | Manfred Leger | 21.11.2017 Status More than 50 percent of the tunnel kilometers are already done

Anhydrite

 The tunnels Cannstatt, Feuerbach, Ober-/Untertürkheim and Fildertunnel passes through anhydrite  The tunnels are built with mining technique  No rock swelling so far  Expert panel established

Karst

 At the Albhochfläche different kinds of karst were detected  Geo-physical explorations along the new high speed line Wendlingen-Ulm  Stabilization of the ground with concrete

21 DB Projekt Stuttgart–Ulm GmbH | Manfred Leger | 21.11.2017 Status Protection of nature and species has a particular importance

Species protection

 Lizards – approx. 10.000 lizards in several parts of the project – 80 m² to 150 m² space needed for every grown-up lizard  Beetles (Juchtenkäfer) detected in a nature reserve in Stuttgart  Protection of nature and species effects the planning permissions

Nature protection

 Construction waste with higher levels of sulphates (pyrite) detected at Boßlertunnel und Albvorlandtunnel  Additional disposal costs  New negotiations with construction companies

22 DB Projekt Stuttgart–Ulm GmbH | Manfred Leger | 21.11.2017 Status Stakeholder management and public relation work are essential

Stakeholder

 Less resistance against the project  Cooperation with authorities and project partners is well established

Public

 Still high public attention  Public information about progress and next steps  Regular citizens events  Guided tours of the building site, project homepage, project magazine, public events (FaSzination S21, Tag der offenen Baustelle etc.)

23 DB Projekt Stuttgart–Ulm GmbH | Manfred Leger | 21.11.2017 Next steps There are still many challanges, but we are looking forward to some special highlights

Highlights

 2017: Completion of first cally column for the new central station in Stuttgart

 Albvorlandtunnel – Tunnel driving with two tunnel boring machines – Good progress expected

 2018: construction start of the railway technology for the high speed line Wendlingen–Ulm

 Tunnel breakthrough at Tunnel Feuerbach in direction of central station in spring 2018

24 DB Projekt Stuttgart–Ulm GmbH | Manfred Leger | 21.11.2017 Thank you!