The World Bank Report No: ISR13849

Implementation Status & Results Third Medium Cities Infrastructure (P099224)

Operation Name: Liaoning Third Medium Cities Infrastructure (P099224) Project Stage: Implementation Seq.No: 8 Status: ARCHIVED Archive Date: 04-Jun-2014 Country: China Approval FY: 2008

Public Disclosure Authorized Product Line:IBRD/IDA Region: EAST ASIA AND PACIFIC Lending Instrument: Specific Investment Loan Implementing Agency(ies): Key Dates Board Approval Date 27-May-2008 Original Closing Date 31-Dec-2013 Planned Mid Term Review Date 01-Nov-2012 Last Archived ISR Date 22-Dec-2013 Public Disclosure Copy Effectiveness Date 18-Nov-2008 Revised Closing Date 31-Dec-2014 Actual Mid Term Review Date 03-Dec-2012

Project Development Objectives Project Development Objective (from Project Appraisal Document) The project development objective is to assist Liaoning Province in improving the energy efficiency and environmental performance of heating and gas services in Project areas of the Project Cities. Has the Project Development Objective been changed since Board Approval of the Project?

Yes No Public Disclosure Authorized Component(s)

Component Name Component Cost Central Heating Component 364.00 Nanfen Heating Subproject 14.20 Benxi Steel Heat Recovery Subproject 37.20 Haicheng Heating Subproject 23.60 YJZZ Subproject 17.60 EDZ Heating Subproject 55.70 Yingkou Heating Subproject 30.90 Yingkou North Central Heating Subproject 61.10

Public Disclosure Authorized Gas Component 11.00 Yingkou Gas Subproject Institutional Development 1.20 Gonchangling Central Heating Subproject 11.70

Public Disclosure Copy Benxi Central Heating Subproject 48.40 Kangping Central Heating Subproject 31.84 Central Heating Subproject 36.60

Page 1 of 6 Public Disclosure Authorized The World Bank Report No: ISR13849

Overall Ratings Previous Rating Current Rating Progress towards achievement of PDO Moderately Unsatisfactory Moderately Satisfactory Overall Implementation Progress (IP) Moderately Unsatisfactory Moderately Satisfactory Overall Risk Rating Substantial Substantial

Implementation Status Overview The progress towards meeting the development objective and the implementation progress by the closing date are both Moderately Satisfactory. Since last supervision in November 2013, progress was made both in the implementation and the disbursement and restructuring. The implementation of the two newly added, Kangping and Lingyuan subproject, and other three current subprojects, Yangjiazhangzi, Nanfen, and Benxi Steel are all moving forward on track. For Kangping, there are two contracts, one for civil works, pipeline procurement and installation, ninety percent is completed, and the other one is equipment, substation Public Disclosure Copy procurement and installation, the bidding evaluation is completed and contract will be signed in late May. For Lingyuan, there are five contracts. All the bidding documents were prepared in Chinese and were under review by consulting company. All the other current subprojects are performing well both in terms of heating service and emission reduction, and demonstration of building level substation and heat meters. The disbursement rate increased to 38.25% compared to 37.14% during the last supervision mission. The disbursement rate is expected to reach 47% by end of May, since US$ 10 million is under processing in Provincial Financial Bureau and will be disbursed soon. The first restructuring was approved by the Board on January 10, 2014. The content of the restructuring are: (i) cancelling the five subprojects: Benxi (Central Heating Supply), (Power Plant Heating Network Expansion), Haicheng (Central Heating Supply), Northern Yingkou (Central Heating Supply), and Urban Natural Gas Infrastructure in the Loan Agreement (and changing the Development Objective to reflect the drop of Urban Natural Gas Infrastructure subproject); (ii) adding two new subprojects, Kangping and Lingyuan; and (iii) extending the project closing date by one year. The request for a second restructuring, bringing in two more new subprojects, Chaoyang central heating project and Yixian central heating project, plus another one year closing date extension to accommodate the construction of the two new subprojects, has been submitted to the Ministry of Finance. For Chaoyang project, the design institute has already completed design of project and will complete the bidding documents for 4 contracts by end of May. While for Yixian project, the Chinese version of the bidding documents are under preparation and will to be submitted to the Bank for NOL late June . With the second restructuring, assuming the targets of Chaoyang and Yixian can be achieved, it is expected that the energy consumption indicators of the project development target can be largely achieved.

Locations Country First Administrative Division Location Planned Actual China Liaoning Dashiqiao Shi

China Liaoning Yingkou Shi

China Liaoning Huludao Shi

China Liaoning Haicheng Shi

China Liaoning Fushun Shi

China Liaoning Benxi Shi

Public Disclosure Copy China Liaoning Gongchangling Qu

China Liaoning Tiedong Qu

Page 2 of 6 The World Bank Report No: ISR13849

Country First Administrative Division Location Planned Actual China Liaoning Yangjiazhangzi

Results

Project Development Objective Indicators Indicator Name Core Unit of Measure Baseline Current End Target Fuel consumption per connected floor area Text Value 199.5 kWh/m2 142.8 in Gongchangling; 132 147 kWh/m2 in Dashiqiao; and 148 in Yingkou EDZ

Public Disclosure Copy Date 27-May-2008 18-Feb-2014 31-Dec-2014 Comments 142.8 in Gongchangling; 132 in Dashiqiao; and 148 in Yingkou EDZ Electricity used for DH/connected floor area Text Value 4.4 kWh/m2 2.52 in Gongchangling; 1.92 2.5 kWh/m2 in Dashiqiao; and 1.19 in Yingkou EDZ Date 27-May-2008 18-Feb-2014 31-Dec-2014 Comments 2.52 in Gongchangling; 1.92 in Dashiqiao; and 1.19 in Yingkou EDZ Make-up water used /connected floor area Text Value 115.4 ltr/m2 90.4 in Gongchangling; 50 in 71 ltr/m2 Dashiqiao; and 42.8 in Yingkou EDZ Date 27-May-2008 18-Feb-2014 31-Dec-2014 Comments 90.4 in Gongchangling; 50 in Dashiqiao; and 42.8 in Yingkou EDZ TSP emissions /connected floor area Text Value 0.494 kg/m2 0.0058 in Gongchangling; 0.015 kg/m2 0.0022 in Dashiqiao; and 0.0022 in Yingkou EDZ Date 27-May-2008 18-Feb-2014 31-Dec-2014 Comments 0.0058 in Gongchangling; 0.0022 in Dashiqiao; and 0.0022 in Yingkou EDZ SO2 emissions /connected floor area Text Value 0.285 kg/m2 0.038 in Gongchangling; 0.04 0.046 kg/m2 in Dashiqiao; and 0.0429 in

Public Disclosure Copy Yingkou EDZ Date 27-May-2008 18-Feb-2014 31-Dec-2014

Page 3 of 6 The World Bank Report No: ISR13849

Comments 0.038 in Gongchangling; 0.04 in Dashiqiao; and 0.0429 in Yingkou EDZ

Intermediate Results Indicators Indicator Name Core Unit of Measure Baseline Current End Target Central Heating: % of planned m2 connected Text Value 0% 100% to centralized heating Date 27-May-2008 18-Feb-2014 31-Dec-2014 Comments 96% for Dashiqiao; 100% for Yingkou EDZ; and 75% for Gongchangling Public Disclosure Copy Central Heating: % of planned kilometers of Text Value 0% 100% pipelines installed Date 27-May-2008 18-Feb-2014 31-Dec-2014 Comments 96% for Dashiqiao; 67% for Yingkou EDZ (this number is bigger than 100% in fact, because of the target in the PAD stage is wrong; 92% for Gongchangling; 90% for Yangjiazhangzi Central Heating: % of planned number of Text Value 0% 100% substations installed Date 27-May-2008 18-Feb-2014 31-Dec-2014 Comments 100% for Dashiqiao; 96% for Yingkou EDZ; 65% for Gongchangling; 3% for Yangjiazhangzi Central Heating: % of planned number of heat Text Value 0% 100% meters installed Date 27-May-2008 29-Mar-2013 28-Jun-2013 Comments Yingkou EDZ 100%, Yingkou Dashiqiao 100%, Gongchangling 23% Central Heating: % of planned capacity of Text Value 0% 100% boilers installed Date 27-May-2008 18-Feb-2014 31-Dec-2014 Comments 100% for Dashiqiao;100% for Gongchangling; 100% for Yingkou EDZ. Public Disclosure Copy

Page 4 of 6 The World Bank Report No: ISR13849

Central Heating: % of planned number and Text Value Number: 0% Capacity: 0% Capacity: 100% capacity of boilers replaced with centralized Date 27-May-2008 18-Feb-2014 31-Dec-2014 heating Comments 100% for Dashiqiao;100% for Gongchangling; 100% for Yingkou EDZ. Institutional Development: Number of person- Text Value 0 135 days training Date 27-May-2008 18-Feb-2014 31-Dec-2014 Comments 120 person-days

Data on Financial Performance (as of 13-Mar-2014) Public Disclosure Copy Financial Agreement(s) Key Dates Project Ln/Cr/Tf Status Approval Date Signing Date Effectiveness Date Original Closing Date Revised Closing Date P099224 IBRD-75240 Effective 27-May-2008 01-Jul-2008 18-Nov-2008 31-Dec-2013 31-Dec-2014

Disbursements (in Millions) Project Ln/Cr/Tf Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P099224 IBRD-75240 Effective USD 191.00 191.00 0.00 73.06 117.94 38.00

Disbursement Graph Public Disclosure Copy

Page 5 of 6 The World Bank Report No: ISR13849

Key Decisions Regarding Implementation The restructuring was approved on January 10, 2014.

Restructuring History There has been no restructuring to date.

Related Projects There are no related projects. Public Disclosure Copy Public Disclosure Copy