<<

ReturnClose and to SessionReturn

THE ST. JOHNS WOOD - ELSTREE EXPERIENCE – TESTING A 20KM LONG 400KV XLPE-INSULATED CABLE SYSTEM AFTER INSTALLATION

Simon SUTTON, National Grid, (UK), [email protected] Ronald PLATH, IPH Berlin, (Germany), [email protected] Gero SCHRÖDER, Südkabel GmbH, (Germany), [email protected]

The cable system was installed in a 20-km-long ABSTRACT tunnel running at an average depth of 30 m (see This paper deals with the 400kV cable connection between Fig. 1), which links the north-western outskirts of St. Johns Wood and Elstree, one of the largest XLPE cable (Elstree) with (St. Johns projects in the world. This cable route is a connecting link to the city of London and was commissioned in 2005. Wood).

KEYWORDS THE CABLE Power cables, testing after installation, partial The cable type is: 2XS(FL)2Y 1x2500 RMS/400 discharges 230/400 kV. Its outer diameter is 150 mm, and it weighs 40 kg/m. The copper conductor has a INTRODUCTION cross section of 2500 mm2 with 6 segments in The 400 kV cable connection between St. Johns order to reduce skin effect losses and the XLPE Wood and Elstree in London is one of the world’s insulation thickness was chosen to be 28 mm. largest cable projects ever: 20 km XLPE three- This leads to an electrical stress of 10.8 kV/mm phase cable system including 60 cross-bonding at the inner semi-conductive layer and joints and 6 GIS terminations. The system with 5.8 kV/mm at the outer semi-conductive layer 2500 mm2 copper conductor has a transmission during normal operation voltage of 230 kV capacity of 1600 MVA. The cable system was (UN/√3). laid in a tunnel ~30 m below surface. The inner and outer semi-conducting layers are The motivation for this outstanding project goes bonded to the insulation material. The back to 1997, when the national transmission production process is a triple head extrusion operator of the networks in and Wales, process followed by a dry curing process to avoid National Grid (NG), decided on an upgrade of water penetration into the insulation material. London’s electricity infrastructure. The key The metallic screen consists of copper wires considerations were a large number of the which are imbedded with crepe paper to reduce existing 275 kV systems in London were mechanical and thermal impact from the screen approaching their predicted and agreed lifetime wires on the underlying insulation. A copper limits, the need to maintain the reliability and screen with a 400 mm2 cross section was used to security of supply, and meet growing energy meet the short circuit current requirements. The demand in the capital. gaps between the screen wires are filled with swelling powder to achieve longitudinal water THE TUNNEL tightness. The outer protection of the cable is provided by a Centennial Park Kilburn Park Depth: 38 m Depth: 36 m 10.3 m dia. laminated sheath made of extruded PE over and St Johns Wood 7.5 m dia. Canons 400 kV Substation Corner Depth: 24 m Cricklewood Depth: 28 m bonded to an aluminium foil on its inside. The 10.3 m dia. Sidings 10.3 m dia. Depth: 35 m 10.3 m dia. Depth: 20 m PE-oversheath delivers both, high mechanical 7.5 m dia. Elstree Substation and corrosion protection of the cable. The Depth: 8 m 10.3 m dia. aluminium foil provides an effective water barrier between the insulation and the outside into the cable. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 For subsequent temperature monitoring of the cable route, a thin steel tube with a fibre-optic Fig. 1 The St. John´s Wood - Elstree cable tunnel cable has been integrated into the cable shield,