Monday, March 1, 2021 Approved Project 131 Facilities Project Management Monthly Report by Building

PM Project Project PROJECT TITLE Accountable Number: Code 1 Leavitt Lane Projects in Building 1

GEUTHER, MARK E 2020‐0055 RR 1 Leavitt Lane ‐ Convert boiler to natural gas

1.1‐ PLAN/EST 02‐24‐2021: Project newly reassigned to me. Getting up to speed.

Year Approved:

Design Firm: OPA Contractor: Contractor Name:

18 Waterworks Road Projects in Building 1

PETERS, NICK E 2020‐0170 FCR 18 Waterworks Road ‐ Install 2 monitors connected to the UNH system

1.1‐ PLAN/EST 26 Feb 2021 ‐ Permits received. Receiving materials first week fo March. Scheduling install dates upon arrival.

Year Approved: 2021

Design Firm: N/A Contractor: External Contractor Name: Various

2 Leavitt Lane Projects in Building 1

GEUTHER, MARK E 2020‐0054 RR 2 Leavitt Lane ‐ new natural gas boiler

1.1‐ PLAN/EST 02‐24‐2021: Project newly reassigned to me. Getting up to speed.

Year Approved:

Design Firm: Oak Point Assoc. Contractor: External Contractor Name: TBD

6 Leavitt Lane Projects in Building 1

GEUTHER, MARK E 2020‐0056 RR 6 Leavitt Lane ‐ New Gas Line and Boiler

1.1‐ PLAN/EST 02‐24‐2021: Project newly reassigned to me. Getting up to speed.

Year Approved:

Design Firm: OPA Contractor: Contractor Name:

88 Commercial Street Projects in Building 1

Facilities Project Management Monday, March 1, 2021 University of New Hampshire Page 1 of 26 PM Project Project PROJECT TITLE Accountable Number: Code

ROULEAU, RICHARD A 2018‐0210 FCR 88 Commercial Street ‐ UNH Manchester ‐ Bio‐Manufacturing Innovation Center Tenant fit‐out

3.1‐ SUBSTANTIAL COMPLETION 2/26/2021 ‐ Working with Control Tech, Inc. and UNH IT to set up a virtual server for HVAC controls associated with the 6th floor and the 5th floor lab block. Working with Milestone, Granite State Plumbing & Heating and Control Tech on adding one oxygen sensor and installing remote alarms for both oxygen sensors. Otherwise, project is complete. Use and occupancy of the space is increasing. Lab is being used for COVID testing for UNH Manchester and UNH Law School.

Year Approved: 2019

Design Firm: John Jordan Contractor: External Contractor Name: by landlord (using Milestone)

Adams Tower Projects in Building 2

GEUTHER, MARK E 2021‐0083 FCR Adams Tower West ‐ Major AC System Repairs

1.1‐ PLAN/EST 02‐24‐2021: Project approved. Work to be scheduled after commencement.

Year Approved:

Design Firm: N/A Contractor: External Contractor Name: Carrier

HENRY, PAUL A 2018‐0310 FCR Adams Tower ‐ Verizon Wireless Antenna Upgrade

2.5‐ IN PROCUREMENT 3‐2‐21 Version not ready for installation, will have to wait until after commencement.

Year Approved: 2018

Design Firm: Contractor: External Contractor Name: Verizon

Babcock Hall Projects in Building 2

PETERS, NICK E 2021‐0090 FCR Babcock Hall ‐ Roof Access Hatch

2‐ IN DESIGN 26 Feb 2021. Issues with COVID testing has pushed contractors from the project. Site conditions re‐evaluated, and determined the hatch will operate as functioned until summer.

Year Approved:

Design Firm: N/A Contractor: External Contractor Name: Skyline Roofing

WEBBER, TODD M 2021‐0001 FCR Babcock Hall ‐ Adams Tower ‐ Electrical Investigation COVID Preparation

3.1‐ SUBSTANTIAL COMPLETION Investigation is complete, no instruction to move forward with the proposed work at this time.

Year Approved:

Design Firm: Contractor: Contractor Name:

Barton Hall & Cole Hall Projects in Building 4

Facilities Project Management Monday, March 1, 2021 University of New Hampshire Page 2 of 26 PM Project Project PROJECT TITLE Accountable Number: Code

MANCINI, MATTHEW E 2020‐0091 SI Barton Hall ‐ 2nd Floor Reno for Diagnostic Labs

2‐ IN DESIGN 3/1/2021: Design effort under way. Early permit review has begun to address egress. Construction Documents expected by April/May 2021.

Year Approved: 2020

Design Firm: H.L. Turner Group Contractor: External Contractor Name:

HEALEY, SCOTT M 2021‐0040 RR Barton Hall ‐ Utility Distribution ‐ Transformer Replacement

2.5‐ IN PROCUREMENT 1‐29‐21 ‐ Transformer should arrive in the middle of March, and need to be installed before June. Ordered 10‐20 ‐ 23 week lead time.

Year Approved: 2021

Design Firm: Contractor: External Contractor Name: IC Reed

MANCINI, MATTHEW E 2020‐0092 SI Cole Hall ‐ Instructional Space Improvements

3.1‐ SUBSTANTIAL COMPLETION 3/1/2021: Project is substantially complete. HVAC scope will be deferred.

Year Approved: 2020

Design Firm: John L Turner Contractor: External Contractor Name: Multiple

RINES, DANIEL M 2021‐0041 FCR Barton Hall & Cole Hall ‐ Bus Shelter Install

3.1‐ SUBSTANTIAL COMPLETION 2‐24‐21: Project is substancially complete.

Year Approved:

Design Firm: Contractor: External Contractor Name: T&S

Campus Projects in Building 9

WEBBER, TODD M 2019‐0369 RR FY21 Campus Envelope and Interior Painting

1.1‐ PLAN/EST

Year Approved: 2021

Design Firm: N/A Contractor: FCT Contractor Name:

PETERS, NICK E 2021‐0084 FCR Multi Housing Building‐ Hydration Station Installs

1.1‐ PLAN/EST 26 Feb 2021 ‐ Received proposal from consultants and contractors. Awaiting approval for funding.

Year Approved: 2021

Design Firm: McHenry Architecture Contractor: External Contractor Name: Charters Brothers

Facilities Project Management Monday, March 1, 2021 University of New Hampshire Page 3 of 26 PM Project Project PROJECT TITLE Accountable Number: Code

HENRY, PAUL A 2021‐0064 FCR Campus ‐ Parking Lot ‐ Sage Way Visitor Lot ‐ Parking Spot & Drop Box

1.1‐ PLAN/EST 3‐2‐21 Looking for more information

Year Approved:

Design Firm: Contractor: Contractor Name:

PETERS, NICK E 2021‐0092 FCR Campus ‐ Bus Shelter Solar Lighting Upgrades

1.1‐ PLAN/EST 26 Feb 2021 ‐ Initial expected contractor does not provide the services requested anymore. Soliciting to other product manufacturers to locate a source to submit for grant funding.

Year Approved:

Design Firm: Contractor: Contractor Name:

PETERS, NICK E 2021‐0008 FCR Campus Wide ‐ OBA COVID Barrier Installations

3‐ IN CONSTRUCTION 26 Feb 2021 ‐ OBA barriers installed. Broken barriers found in Stillings and Philbrook, and to be repaired through contractor. Another order to be placed to accommodate winter weather and expanded dining requirements.

Year Approved: 2021

Design Firm: N/A Contractor: External Contractor Name: Milestone / WB Mason / Malthouse

PETERS, NICK E 2021‐0009 FCR Campus Wide ‐ Academic / E&G Hydration Stations

3‐ IN CONSTRUCTION 28 Feb 2021 ‐Preliminary construction complete campus‐wide. Awaiting arrival of water bottle fill stations.

Year Approved: 2021

Design Firm: N/A Contractor: External Contractor Name: Milestone / Charters Brothers

RINES, DANIEL M 2020‐0276 FCR Campus ‐ Main Street Paving and Crosswalks

3‐ IN CONSTRUCTION 2‐24‐21: Project is via the TOD contract with Continental. Main Street Paving will take place after South sidewalk road impacts are complete,continental and the town planning early June for paving to begin.

Year Approved: 2021

Design Firm: Contractor: Contractor Name: continental

HOUDE, DONALD A 2021‐0024 SI Campus – High Voltage Monitoring Sensor Installation

3‐ IN CONSTRUCTION 02‐19‐21 All 11 monitors and the 1 gateway are installed with satisfactory signal strength. I will log in all locations and plot on a UNH Map for the record.

Year Approved: 2021

Design Firm: Contractor: Contractor Name:

Facilities Project Management Monday, March 1, 2021 University of New Hampshire Page 4 of 26 PM Project Project PROJECT TITLE Accountable Number: Code

PETERS, NICK E 2020‐0279 FCR Campus Wide ‐ Academic/E&G COVID Barrier Installations

3‐ IN CONSTRUCTION 28 Feb 2021 ‐Shields have been installed through‐out Durham, Manchester, and Concord campuses.

Year Approved: 2020

Design Firm: Contractor: External Contractor Name: WB Mason, Milestone,

Chase Ocean Engineering Laboratory Projects in Building 1

ROULEAU, RICHARD A 2020‐0149 FCR Chase Ocean Engineering Laboratory ‐ Rm S210 HVAC Recommendations and Repair

2‐ IN DESIGN 2/26/2021 ‐ Final review documents received and review is nearly complete. Construction estimate received. FCR to be prepared and forwarded to the customer, who has indicated that they intend to proceed. Due to the fact that we are nearly into heating season, the intent is to replace RTU‐2 with a smaller unit next cooling season. New RTU will be 100% recirc except when economizing, able to stage and will have reheat. Energy Office put in place a temporary solution for this summer making RTU‐1 primary for the server room and RTU‐2 secondary during unit swap out.

Year Approved: 2020

Design Firm: H.L. Turner Group Contractor: External Contractor Name: TBD

Child Study & Development Center Projects in Building 2

GEUTHER, MARK E 2020‐0250 FCR Child Study & Development Center ‐ Decks

1.1‐ PLAN/EST 02‐24‐2021: Waiting for estimate

Year Approved:

Design Firm: Contractor: External Contractor Name: TBD

GEUTHER, MARK E 2020‐0173 FCR Child Study & Development Center ‐ Playground Repairs

3‐ IN CONSTRUCTION 02‐24‐2021: On site construction has stopped until Spring 2021. Deck building will take place off site.

Year Approved: 2020

Design Firm: Ironwood Contractor: External Contractor Name: T&S Construction

Christensen Hall Projects in Building 1

PETERS, NICK E 2021‐0093 FCR Christensen Hall ‐ T‐Mobile Antenna Upgrades ‐

1.1‐ PLAN/EST 26 Feb 2021 ‐ Construction documents received and preparing permit applications. EME or RF study requested from contractor.

Year Approved: 2021

Design Firm: Contractor: Contractor Name:

Dimond Library Projects in Building 2

Facilities Project Management Monday, March 1, 2021 University of New Hampshire Page 5 of 26 PM Project Project PROJECT TITLE Accountable Number: Code

MANCINI, MATTHEW E 2010‐0281 RR Dimond Library ‐ Interior Heating Distribution ‐ Design Only

2‐ IN DESIGN 3/1/2021: Wrapping up final design and material considerations. Construction Documents expected in April 2021.

Year Approved: 2021

Design Firm: Harriman Contractor: External Contractor Name:

HENRY, PAUL A 2021‐0029 FCR Dimond Library ‐ Minor Modifications to Shelving/Floor 301

2.5‐ IN PROCUREMENT 3‐2‐21 going to remove shelving and paint room with gift funds

Year Approved:

Design Firm: Contractor: Contractor Name:

Field House Projects in Building 7

RINES, DANIEL M 2021‐0101 RR Field House ‐ Indoor Pool North Wall Investigation

1.1‐ PLAN/EST 2‐24‐21: Project assigned, Pm to work with stakeholders to identify the trouble areas, and begin investigation with term structural firm.

Year Approved: 2021 Emergency Repair

Design Firm: Contractor: Contractor Name:

GEUTHER, MARK E 2013‐1044 RR Field House ‐ Glass Wall, Outdoor Deck/Roof and Door Replacement Design Only

2‐ IN DESIGN 02‐24‐2021: Preliminary to be reviewed by UNH. Goal is to have the design and cost estimate completed by the end of June. Construction planned FYʹ23.

Year Approved: 2021

Design Firm: LaVallee Brensinger Contractor: External Contractor Name: TBD

GEUTHER, MARK E 2020‐0181 RR Field House ‐ Pool Chemical Storage ‐ Design Only

2‐ IN DESIGN 02‐24‐2021: Design is continuing.

Year Approved: 2020

Design Firm: Weston & Sampson Contractor: External Contractor Name: TBD

RINES, DANIEL M 2021‐0091 RR Field House ‐ Indoor Pool Crack Repairs

3‐ IN CONSTRUCTION 2‐24‐21: Cracks temporarily repaired so pool can be filled, AM to allocated funds for future long term repair.

Year Approved: 2021 Emergency Repair

Design Firm: Contractor: External Contractor Name: Guarinos Swimming pool service

Facilities Project Management Monday, March 1, 2021 University of New Hampshire Page 6 of 26 PM Project Project PROJECT TITLE Accountable Number: Code

GEUTHER, MARK E 2019‐0306 RR Field House ‐ UV Filter Replacement

3.1‐ SUBSTANTIAL COMPLETION 02‐24‐2021: Working on close out documentation.

Year Approved: 2019

Design Firm: Weston & Sampson Contractor: External Contractor Name: Charters Brothers

GEUTHER, MARK E 2011‐0653 SI Field House ‐ 1st Floor AC Installation

3.1‐ SUBSTANTIAL COMPLETION 02‐24‐2021: Substantially Complete. Working on close out.

Year Approved: 2019

Design Firm: Harriman Contractor: External Contractor Name: Charters Brothers

RINES, DANIEL M 2020‐0129 RR Field House ‐ Indoor Pool Concrete Repairs

3.1‐ SUBSTANTIAL COMPLETION 2‐24‐21: Work is sunbstancially complete. Campus Rec has added scope for pool maintinance items, which have been completed, few minor concrete fixes needed for punclist.then closeout.

Year Approved: 2021

Design Firm: Hoyle Tanner Contractor: External Contractor Name: Structural Preservation Systems

Future Design and Planning Projects in Building 1

HEISNER, MICHELE 2020‐0231 FCR Health Sciences Initiative CHHS Building

3‐ IN CONSTRUCTION 02/24/21 ‐ Simulation wing exterior framed, slab on grade first week of March; office wing exterior framed. Project scheduled to be complete 8/2021

Year Approved: 2020

Design Firm: LVBPA‐DB Contractor: External Contractor Name: Wright Ryan

Gregg Hall Projects in Building 2

ROULEAU, RICHARD A 2018‐0254 RR Gregg Hall ‐ Boiler Plant Replacement

1‐ ASSIGNED

Year Approved: 2022

Design Firm: Contractor: Contractor Name:

Facilities Project Management Monday, March 1, 2021 University of New Hampshire Page 7 of 26 PM Project Project PROJECT TITLE Accountable Number: Code

HENRY, PAUL A 2021‐0081 FCR Gregg Hall‐ Rm 337‐ Expanded COVID Testing Lab

3.1‐ SUBSTANTIAL COMPLETION 3‐2‐2 Lab is substancilly complete, occupants moviing and testing equipment, lab team is still waiting for some qupipment pror to operation. There is always some small issues to solve prior to going live.

Year Approved:

Design Firm: Harriman Contractor: External Contractor Name: Charter Brothers

Haaland Hall Projects in Building 1

RINES, DANIEL M 2020‐0253 FCR Haaland Hall – PVI Tank Replacement

3‐ IN CONSTRUCTION 2‐24‐21: Tank has been installed, Same issues with original flue and chimney as Handler Hall project cited by SFMO. PM working on solutions.

Year Approved: 2020

Design Firm: Harriman Contractor: External Contractor Name: United Mechanical

Hamel Recreation Center Projects in Building 1

RINES, DANIEL M 2020‐0245 FCR ‐ Covid‐19 Surge Facility

1.1‐ PLAN/EST 2‐24‐21:Site has been demobilized, but may need to be reopened in short notice.

Year Approved: 2020

Design Firm: Contractor: Contractor Name:

Hamilton Smith Hall Projects in Building 2

ROULEAU, RICHARD A 2016‐0116 SI Hamilton Smith Hall ‐ Bi‐Directional Amplifier Installation

1‐ ASSIGNED

Year Approved: 2021

Design Firm: Norris Inc. Contractor: External Contractor Name: Norris Inc.

Facilities Project Management Monday, March 1, 2021 University of New Hampshire Page 8 of 26 PM Project Project PROJECT TITLE Accountable Number: Code

ROULEAU, RICHARD A 2020‐0030 FCR Hamilton Smith Hall ‐ Rms G13, G15 Water Infiltration Investigation and Repair

1.1‐ PLAN/EST 2/26/2021 ‐ T&S Construction to develop budgetary construction estimate for UNH planning purposes. ‐ ON HOLD ‐ During recent heavy rain, it was confirmed that water is percolating up between the foundation wall and the floor slab. This suggests too much water is coming off the roof for the perimeter drain to handle resulting in hydrostatic pressure pushing water under the foundation wall and/or footing and up between the wall and slab. While this could possibly be considered a design error, it does not suggest improper construction by the original contractor. Logical solution is to intercept and divert roof run‐off rather than trying to upsize existing perimeter drain, which may not solve the underlying problem of simply too much water. A solution is to line the perimeter drain with waterproof membrane and drain the resulting bathtub to an adjacent storm drain manhole. This is the same approach used at Taylor Hall several years ago. Reached out to term civil engineer Hoyle Tanner & Associates and received a proposal. However, project is on hold due to the Universityʹs cash flow limitations.

Year Approved: 2020

Design Firm: Contractor: External Contractor Name: tbd

Handler Hall Projects in Building 1

RINES, DANIEL M 2019‐0324 FCR Handler Hall ‐ Replacement of PVI Hot Water Tanks

3‐ IN CONSTRUCTION 2/24/21 ‐ Tanks have been installed, currently running on steam only, as SFMO tagged original building construction project code violations. PM, NPI and Harriman working on solutions to code issues from original construction in conjunction with the SFMO. Sizable remediation project planned for this summer.

Year Approved: 2020

Design Firm: Harriman Contractor: External Contractor Name: NPI

Health & Wellness Building Projects in Building 1

HENRY, PAUL A 2020‐0281 FCR Health & Wellness Building ‐ COVID‐19 Testing Instrumentation

2‐ IN DESIGN 3‐2‐21 Have approval for AC in Lab, CB ordering materials, coordinating with lab for installation dates, most likely after Gregg Hall Lab is on line.

Year Approved: 2020

Design Firm: Contractor: Contractor Name:

Hewitt Hall Projects in Building 1

RINES, DANIEL M 2019‐0338 RR Hewitt Hall ‐ Duel Temperature Mechanical Tie‐In

3.1‐ SUBSTANTIAL COMPLETION 2‐24‐21: . Commissioning and Balancing complete, minor punchlist, and document closeout underway.

Year Approved: 2020

Design Firm: Harriman Contractor: External Contractor Name: Anderson Welding

Holloway Commons Projects in Building 1

Facilities Project Management Monday, March 1, 2021 University of New Hampshire Page 9 of 26 PM Project Project PROJECT TITLE Accountable Number: Code

PETERS, NICK E 2020‐0267 FCR Holloway Commons/MUB ‐ Verizon Wireless In‐Building Antenna System

3‐ IN CONSTRUCTION 26 Feb 2021 ‐ Construction through kitchen complete. Contractors are continuing with work as scheduled.

Year Approved: 2020

Design Firm: Verizon Wireless Contractor: Contractor Name: Verizon Wireless

Horton Social Science Center Projects in Building 1

HENRY, PAUL A 2010‐0411 SI Horton Social Science Center ‐ G04 Auditorium – Air Conditioning

3.1‐ SUBSTANTIAL COMPLETION 3‐2‐21 replaced faulty VFD drives, waiting for final commissioning report.

Year Approved: 2019

Design Firm: Harriman Contractor: External Contractor Name: Structuretone

James Hall Projects in Building 3

HEISNER, MICHELE 2020‐0251 FCR James Hall ‐ Suite 364 Fire Alarm Strobes

1.1‐ PLAN/EST 02/24/21 ‐ Due to the uncertainty and fluctuation of contractor availability and schedule constraints related to covid, recommend this work be rescheduled

Year Approved:

Design Firm: Contractor: Contractor Name:

HEISNER, MICHELE 2020‐0252 FCR James Hall ‐ Suite 364 Lab Repairs

1.1‐ PLAN/EST 02/24/21 ‐ Due to the uncertainty and fluctuation of contractor availability and schedule constraints related to covid, recommend this work be rescheduled. Cleanroom lab schedules to be coordinated with end users.

Year Approved:

Design Firm: Contractor: Contractor Name:

ROULEAU, RICHARD A 2018‐0270 RR James Hall ‐ HVAC Modifications Investigation and Design

3.1‐ SUBSTANTIAL COMPLETION 2/26/2021 ‐ No change. Repairs and adjustment complete. The Energy Office is addressing unrelated hood air flow and hood alarm issues. They have pulled in Cx Agent I.C.O. for assistance. Once the building has been recommissioned and issues identified have been corrected, we will run the kiln and, hopefully, confirm no transfer from the exhaust air stream to the intake/supply air. Failing that, the correct solution and what probably should have been done originally will be a dedicated hood exhaust.

Year Approved: 2018

Design Firm: Contractor: Contractor Name:

Kendall Hall Projects in Building 5

Facilities Project Management Monday, March 1, 2021 University of New Hampshire Page 10 of 26 PM Project Project PROJECT TITLE Accountable Number: Code

GEUTHER, MARK E 2021‐0094 FCR Kendall Hall ‐ Rms 506 & 506A Improvements rms 506 & 506A

1.1‐ PLAN/EST 02‐24‐2021 ‐ Space not appropriate for the intended use per SFMO.

Year Approved:

Design Firm: Contractor: Contractor Name:

GEUTHER, MARK E 2021‐0095 FCR Kendall Hall ‐ Rm 517 Improvements

1.1‐ PLAN/EST 02‐24‐2021: Space not appropriate for the intended use per SFMO. PI might modify his intent, waiting to hear.

Year Approved:

Design Firm: N/A Contractor: External Contractor Name: TBD

GEUTHER, MARK E 2021‐0097 FCR Kendall Hall ‐ Rm 409 Sink Installation

1.1‐ PLAN/EST 02‐24‐2021: Met with client, waiting to hear back on need.

Year Approved:

Design Firm: Harriman Contractor: External Contractor Name: Charters Brothers

GEUTHER, MARK E 2019‐0158 SI Kendall Hall ‐ 3rd Floor Repurposing

3.1‐ SUBSTANTIAL COMPLETION 02‐24‐2021: Occupancy approved by SFMO. Working on close out documentation. Hydronic balancing ongoing.

Year Approved: 2019

Design Firm: Manypenny Murphy Contractor: External Contractor Name: Charters Brothers

GEUTHER, MARK E 2019‐0161 SI Kendall Hall ‐ 4th Floor Repurposing

3.1‐ SUBSTANTIAL COMPLETION 02‐24‐2021: See 2019‐0158

Year Approved: 2019

Design Firm: Manypenny Murphy Contractor: External Contractor Name: Charters Brothers

Kingsbury Hall Projects in Building 4

MANCINI, MATTHEW E 2021‐0099 FCR Kingsbury Hall ‐ Room Improvements rm W136

1.1‐ PLAN/EST 3/1/2021: Scheduling to meet with stakeholders to define scope and then develop an RFP for Term Contractors.

Year Approved:

Design Firm: Contractor: Contractor Name:

Facilities Project Management Monday, March 1, 2021 University of New Hampshire Page 11 of 26 PM Project Project PROJECT TITLE Accountable Number: Code

KOHLER, ADAM S 2020‐0187 FCR Kingsbury Hall ‐ Retro‐Commissioning

3‐ IN CONSTRUCTION

Year Approved: 2020

Design Firm: Contractor: Contractor Name:

HENRY, PAUL A 2020‐0049 RR Kingsbury Hall ‐ Compressor and Air Dryer Replacement

3.1‐ SUBSTANTIAL COMPLETION 3‐2‐21 New compressor arrived last week, operations starting installation, will veriify with oiperations, but believe it is complete.

Year Approved: 2021 Emergency Repair

Design Firm: Contractor: Contractor Name:

PETERS, NICK E 2020‐0216 FCR Kingsbury Hall ‐ Career Services Center

3.1‐ SUBSTANTIAL COMPLETION 28 Feb 2021 ‐ Tabletops being replaced. Room Signage being ordered.

Year Approved: 2020

Design Firm: Placework Contractor: External Contractor Name: Charter Brothers

Leavitt Cntr Transportation Center Projects in Building 2

HENRY, PAUL A 2021‐0006 FCR Leavitt Cntr Transportation Center‐ Installation of Safety Harness System

2‐ IN DESIGN 3‐2‐21 Awaitng final design and installation schedule, we has provided some dimention verification two weeks ago.

Year Approved: 2021

Design Firm: DFP Contractor: External Contractor Name: DDP

PETERS, NICK E 2020‐0287 RR Leavitt Cntr Transportation Center ‐ Partial EPDM Roof Replacement

3.1‐ SUBSTANTIAL COMPLETION 27Feb 2021 ‐ Purchase Order issued. Working with Viking for scheduling.

Year Approved: 2021 Emergency Repair

Design Firm: N/A Contractor: External Contractor Name: Viking

Marine Research Facility Projects in Building 1

Facilities Project Management Monday, March 1, 2021 University of New Hampshire Page 12 of 26 PM Project Project PROJECT TITLE Accountable Number: Code

ROULEAU, RICHARD A 2018‐0336 FCR Coastal Marine Lab ‐ Fire Clean‐Up and Repairs

3.1‐ SUBSTANTIAL COMPLETION 2/26/2021 ‐ No Change ‐ Project suspension due to COVID‐19 said to have been lifted on 4/27; however, spending restrictions are preventing this project from moving forward. Next steps are to assemble roofing package for bidding and line up window repairs.

Year Approved: PROJECT SUSPENDED

Design Firm: Contractor: External Contractor Name: Careno Construction

McGregor Memorial EMS Projects in Building 1

PETERS, NICK E 2020‐0196 RR McGregor Memorial EMS ‐ Envelope and Interior Repairs

3‐ IN CONSTRUCTION 26 Feb 2021: Roofing and exterior water treatment completed. Abatement completed. Design fees accepted and approved. Design package received and submitted to contractor. Awaiting proposal.

Year Approved: 2021

Design Firm: N/A Contractor: External Contractor Name: Careno Const

Memorial Union Building Projects in Building 2

ROULEAU, RICHARD A 2021‐0070 FCR Memorial Union Building ‐ 110 Ton Rooftop Chiller ‐ Design Only

2‐ IN DESIGN 2/26/2021 ‐ 75% complete review documents from SMRT are in hand for review. Comments received from Adam Kohler and Scott Lindquist.

Year Approved: 2021

Design Firm: SMRT Contractor: External Contractor Name: tbd

MANCINI, MATTHEW E 2021‐0021 FCR Memorial Union Building ‐ Accessing Systems

3.1‐ SUBSTANTIAL COMPLETION 3/1/2021: Project is substantially complete.

Year Approved: 2021

Design Firm: Contractor: External Contractor Name: Yates Electric

Morse Hall Projects in Building 10

GEUTHER, MARK E 2021‐0022 FCR Morse Hall ‐ Rm 331 Renovations

1.1‐ PLAN/EST 02‐24‐2021: Project approved to move forward. Design kick off meeting scheduled for 02‐25‐2021

Year Approved: 2021

Design Firm: Harriman Contractor: External Contractor Name: Milestone

Facilities Project Management Monday, March 1, 2021 University of New Hampshire Page 13 of 26 PM Project Project PROJECT TITLE Accountable Number: Code

ROULEAU, RICHARD A 2021‐0014 FCR Morse Hall ‐ Rm 119 Fire Suppression ‐ Self Made Room Fabrications

1.1‐ PLAN/EST 2/26/2021 ‐ No change since last update. The EMI/RFI‐sheilded room, which is used for welding, was constructed shortly after the original construction due to concerns about electrical issues the welding might cause the computers of the mid‐80s. At this point, they rarely do any welding. I asked Phil Demaine whether it could be removed, which would make the issue go away. Mr. Demaine was to check with his superiors. I pinged him again via email but still no response.

Year Approved:

Design Firm: Contractor: External Contractor Name: Johnson Controls, possibly Norris

ROULEAU, RICHARD A 2021‐0018 FCR Morse Hall ‐ Rm A132 Fire Suppression ‐ Self Made Room Fabrications

1.1‐ PLAN/EST 2/26/2021 ‐ No change since last update. The chamber is a small constant temperature room. It appears that it may not be in use except maybe for storage. I have reviewed it with Phil Biron. It will need a sprinkler head, not frost free because researcher Joe Salisbury tells me it does not go down below freezing. Given the room is so small, Phil thinks it unlikely anyone would work inside the room and, therefore, it doesnʹt need a fire alarm notification appliance. I have a price from Johnson Controls and can now prepare an FCR.

Year Approved:

Design Firm: Contractor: External Contractor Name: Johnson Controls

ROULEAU, RICHARD A 2021‐0019 FCR Morse Hall ‐ Rm 249 Fire Suppression ‐ Self Made Room Fabrications

1.1‐ PLAN/EST 2/26/2021 ‐ No change since last update. The chamber in this room requires clean room attire. I have received a sketch of the chmber from Marc Lessard and am waiting for photos and response to other questions. There are two rooms within the chamber. One is a control room and one is an optical calibration room for highly‐sensitive devices used in space. Sprinkler and fire alarm AV notification are required. Phil Biron suggested an AV in Room 249 itself and strobe only devices in the rooms within the chamber. However, Marc Lessard tells me any unplanned light in the enclosure during calibration could damage the equipment being calibrated. Storage on top of the unit is also an issue. Signage can probably address that issue. Once scope is established, I will reach out to term sprinkler and fire alarm contractors for pricing.

Year Approved:

Design Firm: Contractor: External Contractor Name: Johnson Controls, Norris

ROULEAU, RICHARD A 2021‐0025 FCR Morse Hall ‐ Rm 118 Fire Suppression ‐ Anechoic Chamber

1.1‐ PLAN/EST 2/26/2021 ‐ No change since last update ‐ Room 118: This EMI/RFI‐shielded room is an anechoic chamber that also needs sprinkler coverage. Per discussion with Phil Biron (SFMO), it does not need a fire alarm notification appliance because no one is ever enclosed in the chamber with the door closed as per Nick Kirsh, the researcher responsible for the room,. There are ports in the top of the chamber for sprinkler and there are specialty extending sprinkler heads made by a company in Seabrook specifically for this application. I have spoken with Nick Kirsh and requested information on the foam and coating. I am working with Johnson Controls to get pricing for the speciality sprinkler heads.

Year Approved:

Design Firm: Contractor: External Contractor Name: Johnson Controls

Facilities Project Management Monday, March 1, 2021 University of New Hampshire Page 14 of 26 PM Project Project PROJECT TITLE Accountable Number: Code

MANCINI, MATTHEW E 2020‐0189 SI Morse Hall ‐ Former Clean Rm Renovation

2‐ IN DESIGN 3/1/2021: Design is under way to support Spaulding swing space. EOS will be primary occupant when finished. Have funding for Design 2021 and Construction FY2022

Year Approved: 2020

Design Firm: Harriman Contractor: External Contractor Name: tbd

HEISNER, MICHELE 2020‐0190 FCR Morse Hall ‐ Rm 419 Adding New Equipment

3‐ IN CONSTRUCTION 02/24/21 ‐ Temporary utility connections made to allow for partial utilization of lab equipment and early experimentation for customer to meet early March deadline. Timing of full ʹbuild outʹ TBD.

Year Approved: 2020

Design Firm: SMRT Contractor: Contractor Name:

PETERS, NICK E 2020‐0150 FCR Morse Hall ‐ Emergency Eyewash Installation

3.1‐ SUBSTANTIAL COMPLETION 28Feb 2021 ‐ Construction completed. Working on commissioning and closeout documentation.

Year Approved: 2020

Design Firm: N/A Contractor: External Contractor Name: Milestone Eng & Const, Inc

ROULEAU, RICHARD A 2020‐0271 RR Morse Hall ‐ Interior Main Heating Line Connections

3.1‐ SUBSTANTIAL COMPLETION 2/26/2021 ‐ Work is complete. Final inspection letter received from SFMO. Once this letter and other project documentation is put into Meridian, this project will be complete and ready to be closed out.

Year Approved: 2021

Design Firm: Harriman Contractor: External Contractor Name: United Mechanical

HOUDE, DONALD A 2020‐0214 SI Morse Hall ‐ Stand By Generator and Distribution ‐ Design ONLY

3.1‐ SUBSTANTIAL COMPLETION 02‐19‐2021 ‐ Report received on January 22nd. From Harriman A&E.Phase 1 completed.

Year Approved: 2020

Design Firm: Contractor: Contractor Name:

New England Center Projects in Building 1

HENRY, PAUL A 2016‐0403 RR New England Center ‐ Boiler Replacement and BAS Controls

3.1‐ SUBSTANTIAL COMPLETION 3‐2‐21 complete, waiting for final commissioning report, finalizing close out.

Year Approved: 2020

Design Firm: Harriman Contractor: Contractor Name:

Facilities Project Management Monday, March 1, 2021 University of New Hampshire Page 15 of 26 PM Project Project PROJECT TITLE Accountable Number: Code Parsons Hall Projects in Building 1

HENRY, PAUL A 2021‐0028 FCR Parsons Hall ‐ Set up Lab Space W202

2.5‐ IN PROCUREMENT 3‐2‐21 have CPR and funding, workign with contractor to start.

Year Approved: 2021

Design Firm: Contractor: External Contractor Name: Charter Brothers

Paul College Projects in Building 2

ROULEAU, RICHARD A 2019‐0331 RR Paul College ‐ Roof Membrane and Flashing Investigation ‐ Corrective Plan/Design

1.1‐ PLAN/EST 2/26/2021 ‐ No Change ‐ ARM recommends water testing to determine where/how the water is getting in. Proposal for testing is in hand. P.O. request will be submitted now that Covid‐19 suspension has been lifted. Depending on the results, we will pursue a warranty claim and/or involve PC Construction and the roofer. Using remaining funds from original construction for this effort (ref. 2009‐0980 / 1XT955)

Year Approved: 2019

Design Firm: ARM, LLC (roofing consultan Contractor: Contractor Name:

HOUDE, DONALD A 2021‐0079 RR Paul College ‐ Investigation of Voltage Fluctuations

3‐ IN CONSTRUCTION 02‐19‐2021 ‐ Paul College‐ the Electrical Service for this building from the Hi Voltage 34,500 to the low 120V has beeen checked and tested. We are still looking at different issues and checking system loads. We have asked IT to look into the equipment programming and Telecom to check the LAN..We think the issue has gone away.

Year Approved: 2021 Emergency Repair

Design Firm: Contractor: Contractor Name:

Paul Creative Arts Center Projects in Building 6

HENRY, PAUL A 2019‐0241 RR Paul Creative Arts Center ‐ Building Life Safety Report Update

1.1‐ PLAN/EST 3‐2‐21 Need to review report and finilize

Addendum to Life Safety plan to be reviewed and approved with the SFMO.

Year Approved: 2019

Design Firm: Contractor: Contractor Name:

ROULEAU, RICHARD A 2021‐0098 FCR Paul Creative Arts Center ‐ Art Museum ‐ HVAC Design

1.1‐ PLAN/EST 2/26/2021 ‐ RFS Engineering has walked the site. They are preparing a proposal that will include a hard number for a study, potential solutions and recommendations and conservative/budgetary numbers schematic, DD and CD.

Year Approved:

Design Firm: RFS Engineering Contractor: Contractor Name:

Facilities Project Management Monday, March 1, 2021 University of New Hampshire Page 16 of 26 PM Project Project PROJECT TITLE Accountable Number: Code

HENRY, PAUL A 2019‐0055 RR Paul Creative Arts Center ‐ Fire Alarm Design Only

2‐ IN DESIGN 3‐2‐21 design uder review, then handing off to Matt, meeting with Harriman to review.

Year Approved: 2020

Design Firm: TBD Contractor: External Contractor Name: TBD

MANCINI, MATTHEW E 2016‐0032 RR Paul Creative Arts Center ‐ Sprinkler Installation ‐ Design Only

2‐ IN DESIGN 3/1/2021: Design Draft review scheduled for March 4th.

Year Approved: 2021

Design Firm: Contractor: Contractor Name:

HOUDE, DONALD A 2017‐0106 RR Paul Creative Arts Center ‐ High Voltage Electrical Service Replacement

3‐ IN CONSTRUCTION 02‐19‐21 95% of the conduit is in place. I have been asked to complete this work this winter. I expect to have the transformer base and transformer set in place next Tuesday (2‐23‐21) then install Hi V cables shortly after and the secondary loads at the same time .

Year Approved: 2021

Design Firm: Harriman Contractor: External Contractor Name: ICR

ROULEAU, RICHARD A 2018‐0249 RR Paul Creative Arts Center ‐ New Main Domestic Hot Water System Installation

3.5‐ WARRANTY REPAIRS 2/26/2021 ‐ No change. Complete pending equipment list update and O&M upload.

Year Approved: 2019

Design Firm: Harriman Associates Contractor: External Contractor Name: Charters Bros.

Philbrook Hall Projects in Building 2

HENRY, PAUL A 2018‐0162 RR Philbrook Hall ‐ Steam Study and Investigation

2‐ IN DESIGN 3‐2‐21 need to reiew final report and finilize

RFS provided three (3) options for steam study. UNH has decided to proceed with using the steam boiler at Philbrook for hot water make up, this will allow the local steam boiler to operate between August ‐ May with continuation operation. During Summer when Philbrook is not open the boiler will be put in dry layup with service assistance from Blake Engineering. Intend to have local boiler online January 2019.

Year Approved: 2019

Design Firm: RFS Contractor: External Contractor Name: Eckhardt Johnson

Facilities Project Management Monday, March 1, 2021 University of New Hampshire Page 17 of 26 PM Project Project PROJECT TITLE Accountable Number: Code

HENRY, PAUL A 2019‐0304 FCR Philbrook Hall ‐ Boiler Replacement

3.1‐ SUBSTANTIAL COMPLETION 3‐2‐21 working on final closeout

Year Approved: 2019

Design Firm: RFS Contractor: External Contractor Name: Eckardt & Johnson

Putnam Hall Projects in Building 2

HEISNER, MICHELE 2020‐0204 SI Putnam Hall ‐ Spaulding Hall Swing Space

1.1‐ PLAN/EST 02/24/21 ‐ McGregor EMS to vacate Putnam by mid, late June. Planning is back in motion for collections temporary relocation from Spaulding. Updated and toured Putnam with new herbarium collections manager, insectarium collections manager and Chris Neefus.

Year Approved:

Design Firm: Contractor: Contractor Name:

RINES, DANIEL M 2020‐0244 FCR Putnam Hall ‐ EMS ‐ Covid‐19 Preparations

2‐ IN DESIGN 2‐24‐21: EMS to move back to College Road. Code study, and feasibility underway for long term build out of Putnam.

Year Approved:

Design Firm: McHenry Contractor: External Contractor Name: T&S Construction

Roads/Grounds Projects in Building 8

HENRY, PAUL A 2013‐1115 SI South Drive ‐ Design Advancement

2‐ IN DESIGN 3‐2‐21 Tighe & Bond working on updating the wetland permits with NH DES, looking at mitigation locations for application.

Year Approved: 2013 PROJECT SUSPENDED

Design Firm: Tighe & Bond Contractor: External Contractor Name:

RINES, DANIEL M 2019‐0371 RR FY21 Major Road Repairs ‐ Under Town of Durham Contract

3‐ IN CONSTRUCTION 2‐24‐21: Paving work complete pending closeout and final invoicing.

Year Approved: 2021

Design Firm: Contractor: External Contractor Name: Continental

Facilities Project Management Monday, March 1, 2021 University of New Hampshire Page 18 of 26 PM Project Project PROJECT TITLE Accountable Number: Code

RINES, DANIEL M 2019‐0228 SI Campus ‐ Main Street South Sidewalk

3‐ IN CONSTRUCTION 2‐24‐21: Project is tracking funding for grant, please see 2017‐0384 for updates on project.

Year Approved: 2019

Design Firm: Contractor: Contractor Name:

HOUDE, DONALD A 2021‐0037 RR Campus ‐ A‐Lot Fencing Replacement

3.1‐ SUBSTANTIAL COMPLETION 02‐19‐2021 Last section of fence to be installed when good weather comes. All tree clearing completed.

Year Approved: 2021

Design Firm: Contractor: Contractor Name:

RINES, DANIEL M 2017‐0275 RR FY21 Sidewalk and Walkway Repairs

3.1‐ SUBSTANTIAL COMPLETION 2‐24‐21: List complete, keeping open for any pedestrian hazards identified.

Year Approved: 2021

Design Firm: N/A Contractor: External Contractor Name: Top Quality Construction

RINES, DANIEL M 2019‐0368 RR FY21 Site Stair Repairs

3.1‐ SUBSTANTIAL COMPLETION 2‐24‐21; List complete, project remains open in case of pedestrian hazards identified over winter months.

Year Approved: 2021

Design Firm: N/A Contractor: External Contractor Name: Top Quality Construction

GEUTHER, MARK E 2018‐0267 SI Campus ‐ South Drive ‐ Temporary Connection to Colovos Road

3.1‐ SUBSTANTIAL COMPLETION 02‐24‐2021: Substantially Complete.

Year Approved: 2019

Design Firm: Tighe & Bond Contractor: External Contractor Name: R.A.D. Sports

RINES, DANIEL M 2017‐0384 SI Campus ‐ Main Street South Sidewalk

3.1‐ SUBSTANTIAL COMPLETION 2‐24‐21: Project is underway, punchlist to be completed in the spring.

Year Approved: 2018

Design Firm: CMA Engineering Contractor: Contractor Name:

Rudman Hall Projects in Building 7

Facilities Project Management Monday, March 1, 2021 University of New Hampshire Page 19 of 26 PM Project Project PROJECT TITLE Accountable Number: Code

MANCINI, MATTHEW E 2013‐0865 RR Rudman Hall ‐ Steam Absorber #1 Replacement

1.1‐ PLAN/EST 3/1/2021: A site visit for engineering term contractors has been set for March 4th. Design documents to be furnished for Besign‐Build delivery.

Year Approved: 2022

Design Firm: Contractor: Contractor Name:

MANCINI, MATTHEW E 2015‐2336 RR Rudman Hall ‐ Conversion to DDC Controls

3‐ IN CONSTRUCTION 3/1/2021: Reference ID 2010‐0479 for updates. Work expected to continue with conversion of office wings following completion of overall HVAC project.

Year Approved: 2018

Design Firm: SMRT Contractor: External Contractor Name: StructureTone

MANCINI, MATTHEW E 2021‐0013 RR Rudman Hall ‐ DDC Controls Backstop

3‐ IN CONSTRUCTION 3/1/2021: Backstop project to support relocation of mass spectrometer. General exhaust to be added to room per SMRTʹs direction. Additional direct‐exchange cooling to be included. Awaiting final design. Refer to Project 2017‐0288

Year Approved: 2021

Design Firm: SMRT Contractor: External Contractor Name: Structuretone

MANCINI, MATTHEW E 2019‐0305 FCR Rudman Hall ‐ Retro‐Commissioning of ARO HVAC System

3‐ IN CONSTRUCTION 3/1/2021: Reference ID 2010‐0479 for updates. Project to continue.

Year Approved:

Design Firm: SMRT Contractor: Contractor Name: Structuretone

MANCINI, MATTHEW E 2010‐0479 RR Rudman Hall ‐ Laboratory Fume Hood Control System Replacement

3‐ IN CONSTRUCTION 3/1/2021: Project continues. Currently, Phase 15 of 18 Labs are under way. HVAC work completion projected for June 2021.

Year Approved: 2017

Design Firm: SMRT Contractor: External Contractor Name: StructureTone

MANCINI, MATTHEW E 2020‐0128 RR Rudman Hall ‐ AHU‐3 Replacement

3‐ IN CONSTRUCTION 3/1/2021: Project to replace air handler is nearing completion.

Year Approved: 2021

Design Firm: SMRT Contractor: External Contractor Name: MB Mechanical Contractors Inc.

Facilities Project Management Monday, March 1, 2021 University of New Hampshire Page 20 of 26 PM Project Project PROJECT TITLE Accountable Number: Code

MANCINI, MATTHEW E 2015‐2352 RR Rudman Hall ‐ Fire Alarm Replacement

3.1‐ SUBSTANTIAL COMPLETION 3/1/2021: Project is substantially complete.

Year Approved: 2016

Design Firm: SFC / SMRT Contractor: External Contractor Name: StructureTone

Service Building Projects in Building 5

RINES, DANIEL M 2010‐0356 RR Service Building ‐ Fire Department Sprinkler Installation and Building Envelope Repairs

2‐ IN DESIGN 2/24/21 : Design efforts underway.

Year Approved: 2021

Design Firm: McHenry Architecture Contractor: External Contractor Name:

RINES, DANIEL M 2021‐0085 FCR Service Building – DFD Expansion / SPA renovations

2‐ IN DESIGN 2‐24‐21: Code study and design efforts underway, quick transition into permitting and construction under term contact anticipated.

Year Approved: 2021

Design Firm: McHenry Architecture Contractor: External Contractor Name: TBD

RINES, DANIEL M 2021‐0089 FCR Service Building ‐ Fire Dept New Vehicle Exhaust Extraction System

2.5‐ IN PROCUREMENT 2‐24‐21: PM working with DFD to secure electrical firm contract, work anticipated to begin by the end of March.

Year Approved:

Design Firm: Contractor: Contractor Name:

HOUDE, DONALD A 2016‐0123 FCR Service Building ‐ Dispatch Center Keltron System

3.1‐ SUBSTANTIAL COMPLETION 01‐27‐21 ‐ Contractors have POʹs and incumbrances. Norris has prepared all new digital circuits. A schedule with dispatch has been set up to verify transfer of lines. Project progressing about 99% complete. 1 circuit to be relocated.

Year Approved: 2018

Design Firm: Contractor: External Contractor Name: Norris / UNH Telecom

Facilities Project Management Monday, March 1, 2021 University of New Hampshire Page 21 of 26 PM Project Project PROJECT TITLE Accountable Number: Code

ROULEAU, RICHARD A 2020‐0272 RR Service Building ‐ Interior Heating Main Connections

3.1‐ SUBSTANTIAL COMPLETION 2/26/2021 ‐ All work complete. Rough and final mechanical inspections complete. Electrical demo and SFMO final inspections can be scheduled. Somewhat related work in Zais pending electronic valve replacement by Facilities Operations.

Year Approved: 2021

Design Firm: Harriman Contractor: External Contractor Name: Careno / NPI

Spaulding Hall Projects in Building 3

HEISNER, MICHELE 2020‐0249 FCR Spaulding Hall ‐ Move Coordination and Support

1.1‐ PLAN/EST 02/24/21 ‐Project is part of Spaulding and in support of swing space and move coordination.

Year Approved:

Design Firm: Contractor: Contractor Name:

BRICKETT, ALEXANDER J 2020‐0246 FCR Spaulding Hall ‐ Utility and Infrastructure

3‐ IN CONSTRUCTION 2/26/2021‐ Please see Project #2016‐0278 for updates.

Year Approved: 2020

Design Firm: Contractor: Contractor Name:

BRICKETT, ALEXANDER J 2016‐0278 CP Spaulding Hall ‐ Expansion & Renovations ‐ Biological Science Initiative

3‐ IN CONSTRUCTION 2/26/2021‐ Building envelope completed. Final exterior trim in progress. Interior mechanical, electrical, plumbing , framing, elevator, and sprinkler work in progress.

Year Approved: 2016

Design Firm: Ellenzweig Contractor: External Contractor Name: Skanska USA Building

Stoke Hall Projects in Building 2

GEUTHER, MARK E 2021‐0096 FCR Stoke Hall ‐ Space Improvements in BIP Program Space

1.1‐ PLAN/EST 02‐24‐2021: Met with client and Milestone to define scope. Estimate in progress.

Year Approved:

Design Firm: TBD Contractor: External Contractor Name: Milestone

Facilities Project Management Monday, March 1, 2021 University of New Hampshire Page 22 of 26 PM Project Project PROJECT TITLE Accountable Number: Code

HENRY, PAUL A 2020‐0012 FCR Stoke Hall ‐ Gas Code Violations

2‐ IN DESIGN 3‐2‐21 Looking at reducing the foot print in the laundry rooms, considering an ouside MAU and ducted into the laundry rooms. Team currently looking into.

Year Approved: 2021

Design Firm: Harriman Contractor: External Contractor Name: TBD

Telecommunications Center Projects in Building 2

GEUTHER, MARK E 2021‐0010 FCR Telecommunications Center ‐ Convert Old Staff Area

1.1‐ PLAN/EST 02‐24‐2021: Requesting approval to move forward with design in FYʹ21 with funds remaining from the addition.

Year Approved: 2022

Design Firm: Oak Point Associates Contractor: External Contractor Name: TBD

GEUTHER, MARK E 2019‐0292 FCR Telecommunications Center ‐ Addition and Renovation

3.1‐ SUBSTANTIAL COMPLETION 02‐24‐2021: Permission to occupy received. Working on Punch List and close out documentation.

Year Approved: 2019

Design Firm: Oak Point Contractor: External Contractor Name: Charters Brothers

Thompson Hall Projects in Building 1

HEISNER, MICHELE 2021‐0059 FCR Thompson Hall ‐ Rm 203 ‐ Add DW to mini kitchen

1.1‐ PLAN/EST 02/24/21‐ Cost estimate and scope presented for approval. Awaiting approval.

Year Approved:

Design Firm: Contractor: Contractor Name:

Transportation Garage Projects in Building 1

HEALEY, SCOTT M 2021‐0039 RR Transportation Garage ‐ Utility Distribution ‐ Replace Existing transformer

2.5‐ IN PROCUREMENT 1‐29‐21 ‐ Transformer should arrive in the middle of March, and need to be installed before June. Ordered 10‐20 ‐ 23 week lead time.

Year Approved: 2021

Design Firm: Contractor: Contractor Name: IC Reed

Utility Distribution Projects in Building 5

Facilities Project Management Monday, March 1, 2021 University of New Hampshire Page 23 of 26 PM Project Project PROJECT TITLE Accountable Number: Code

RINES, DANIEL M 2020‐0004 RR Utility Distribution ‐ Tunnel Repairs and Utility Line Replacement Leaving Central Plant ‐ Design Only

2‐ IN DESIGN 2‐24‐21: Design consulatant awarded to RMF. Inspection and report underway. Phase 2 of contract, and DD to begin.

Year Approved: 2021

Design Firm: RMF Engineering Contractor: Contractor Name:

RINES, DANIEL M 2018‐0256 FCR Utility Distribution ‐ Lee Circle Water Line Extension

2‐ IN DESIGN 2‐24‐21 Consultant working on design, construction summer 2021 via the TOD

Year Approved:

Design Firm: Underwood Eng Contractor: External Contractor Name: TBD

HEISNER, MICHELE 2021‐0082 RR Utility Distribution ‐ Sector Cabinet Installation and Cable Replacement

2.5‐ IN PROCUREMENT 02/24/21‐ Location coordinated with 2020 0231 HSSC project site utility drawings. Equipment on order. Installation work to be coordinated with HSSC.

Year Approved: 2021

Design Firm: Contractor: Contractor Name:

ROULEAU, RICHARD A 2019‐0022 FCR Utility Distribution ‐ Dual Temp Interconnection

3‐ IN CONSTRUCTION 2/26/2021 ‐ Chilled water pump skid has been installed and has been piped. Work in the McDaniel Drive Chiller Plant is essentially complete. Other than some controls work and a floor drain installation, work to wind down until beginning of cooling season in late‐May.

Year Approved: 2019

Design Firm: Harriman Associates Contractor: External Contractor Name: Careno Construction

RINES, DANIEL M 2018‐0362 RR Utility Distribution ‐ Piping Replacements from Heating Vault HVT086 to Handler Hall

3.1‐ SUBSTANTIAL COMPLETION 2‐24‐21: working on minor punchlist, and project closeout. Warranty work identified in pit 4 as well as valve in Handler Hall to be repaired post commencement.

Year Approved: 2021

Design Firm: Harriman Contractor: External Contractor Name: Anderson Welding

Verizon Head End Building Projects in Building 1

Facilities Project Management Monday, March 1, 2021 University of New Hampshire Page 24 of 26 PM Project Project PROJECT TITLE Accountable Number: Code

PETERS, NICK E 2020‐0270 FCR Verizon Wireless Head End Building ‐ Construction

1.1‐ PLAN/EST 26 Feb 2021 ‐ Pre‐bid walk through with subcontractors held 5 Oct. Contractor selection and preparing submittals. Awaiting permitting information, which will fall through Town of Durham, not SFMO. SFMO now responsible for connections between this building and campus.

Year Approved: 2020

Design Firm: Verizon Wireless Contractor: Contractor Name: Verizon Wireless

Water Treatment Plant Projects in Building 1

GEUTHER, MARK E 2008‐0038 SI Water Treatment Plant ‐ New Construction

3.1‐ SUBSTANTIAL COMPLETION 02‐24‐2021: Working on close out documentation.

Year Approved: 2014

Design Firm: Woodard & Curran Contractor: External Contractor Name: Waterline Industries

Whittemore Center ‐ Arena Projects in Building 4

GEUTHER, MARK E 2021‐0087 RR ‐ Arena ‐ Section 112R ‐ Clean Air Compliance

1.1‐ PLAN/EST 02‐24‐2021: Project approved. Exception to Bid approved. Consultant schedule to be on campus 03‐08‐2021.

Year Approved: 2021

Design Firm: HCG Associates Contractor: External Contractor Name: TBD

HENRY, PAUL A 2020‐0229 RR Whittemore Center ‐ Arena ‐ Fire Alarm and Sound System Control Panel Repairs

2‐ IN DESIGN 3‐2‐21 Installed UPS in equipment rack a the Field House, Jeff Murphy is working on testing proceedure for training.

Year Approved: 2021 Emergency Repair

Design Firm: SFC Eng. Contractor: External Contractor Name: Norris ‐ Scarponi

PETERS, NICK E 2020‐0269 FCR Whittemore Center ‐ Arena ‐ Verizon Wireless In‐Building Cellular Antenna System

3‐ IN CONSTRUCTION 28 Feb 2021 ‐ Preliminary runs have been accomplished in telecom rooms. Primary construction will begin late‐March to early‐April.

Year Approved: 2020

Design Firm: Contractor: External Contractor Name: Verizon Wireless

Facilities Project Management Monday, March 1, 2021 University of New Hampshire Page 25 of 26 PM Project Project PROJECT TITLE Accountable Number: Code

BRICKETT, ALEXANDER J 2017‐0308 FCR Whittemore Center ‐ Arena ‐ Dehumidification System

3.1‐ SUBSTANTIAL COMPLETION 2/26/2021 ‐ New unit has been installed. Commissioning in progress, to be completed when hot weather returns

Year Approved: 2019

Design Firm: Harriman Contractor: External Contractor Name: Careno Construction

Wildcat Stadium Projects in Building 1

PETERS, NICK E 2020‐0268 FCR Wildcat Stadium ‐ Verizon Wireless Distributed Antenna Installation

3‐ IN CONSTRUCTION 28Feb 2021 ‐ Contractors have begun electrical permitting. Installation has commenced.

Year Approved: 2020

Design Firm: Verizon Wireless Contractor: External Contractor Name: Verizon Wireless

Woodside Projects in Building 1

HENRY, PAUL A 2021‐0086 FCR Woodside ‐ Mechanical Room Exhaust ‐ Design Only

1.1‐ PLAN/EST 3‐2‐21 Submitted CPR for approval still waitng, Design only.

Year Approved:

Design Firm: Harriman Contractor: External Contractor Name: TBD

Facilities Project Management Monday, March 1, 2021 University of New Hampshire Page 26 of 26