Thursday, May 30, 2019 Approved Projects 237 Facilities Project Management Monthly Report

BOIE, GREGG J 28

1.1‐ PLAN/EST 2019‐0042 FCR Leavitt Cntr Transportation Center ‐ Fire Protection Work

Year Approved 5/30/19,

Design Firm: Contractor: Name: Funding: COLLEGE / DEPT ALLOC

1.1‐ PLAN/EST 2019‐0048 RR Elliott Alumni Center ‐ HVAC Modifications and Improvements

Year Approved 5/30/19, Bid initiation form sent to procurement .Working on invitation to bid 2020 Design Firm: HARRIMAN Contractor: Name: Funding: DMA

1.1‐ PLAN/EST 2019‐0227 FCR Nesmith ‐ Air Sourced Heat Pump suite 107

Year Approved 5/30/19, will meet with Michelle

Design Firm: Contractor: Name: Funding: COLLEGE / DEPT ALLOC

1.1‐ PLAN/EST 2019‐0255 FCR Barton Hall & Cole Hall ‐ Exhaust Fan ‐ Vet Clinic

Year Approved 5/30/2019:: ‐ Need to review with EH&S no building codes available to design to.

Design Firm: SMRT Contractor: Name: Funding: COLLEGE / DEPT ALLOC

1.1‐ PLAN/EST 2019‐0307 FCR Woodside Apts Community Building ‐ Air Handler Replacement

Year Approved 5/30/19, Waiting for proposal from SMRT

Design Firm: Contractor: Name: Funding: COLLEGE / DEPT ALLOC

1.1‐ PLAN/EST 2019‐0335 FCR James Hall ‐ Blackboard Replacement Rm 254

Year Approved 5/30/19. Emailed FCR to Joe Licciardi and explained that he needs to send the FCR to his BSC person, .

Design Firm: Contractor: External Name: New England Int. Spec. Funding: COLLEGE / DEPT ALLOC

1.1‐ PLAN/EST 2019‐0351 FCR Rudman Hall ‐ Ground Hydration Station

Year Approved 5/30/19, sent Information to Milestone waiting for proposal.

Design Firm: Contractor: Name: Funding: COLLEGE / DEPT ALLOC

Brenda Whitmore, Director Facilities Project Management Thursday, May 30, 2019 University of New Hampshire Page 1 of 30 2‐ IN DESIGN 2016‐0453 BAR Memorial Union Building ‐ Granite State Chiller Replacement

Year Approved 5/30/19, SMRT is working on design. 2019 Design Firm: SMRT Contractor: Name: Funding: COLLEGE / DEPT ALLOC

2‐ IN DESIGN 2018‐0306 RR New Hampshire Hall ‐ Replacements and Exterior Painting

Year Approved 5/30/19, McHenry Architects provided design development for review and Asset Management decided to 2020 push this project to summer 2020.( GO OUT TO BID FALL 2019)

Design Firm: McHenry Contractor: Name: Funding: DMA

2‐ IN DESIGN 2019‐0276 FCR Health & Wellness Building ‐ 2nd Floor Building Improvements

Year Approved 5/30/19, Harriman working on design. Should have documentation by 5/31/19 2019 Design Firm: Harriman Contractor: Name: Funding: COLLEGE / DEPT ALLOC

2.5‐ IN PROCUREMENT 2018‐0079 FCR Demeritt Hall ‐ Rm 112 Carpet Repairs

Year Approved 5/30/19,PO to Sprague Flooring for Repairs …...Previous Fund Number for larger project was 1XTM36

Design Firm: Contractor: External Name: Sprague Funding: COLLEGE / DEPT ALLOC

2.5‐ IN PROCUREMENT 2018‐0135 RR Dimond Library ‐ Rm 402 Flooring Replacement

Year Approved 5/30/19, Met with Charters Brothers on 5/29 at the Library . 2019 Design Firm: Contractor: External Name: Charters Brrothers Funding: DMA

2.5‐ IN PROCUREMENT 2018‐0338 FCR Morse Hall ‐ Rms 159 and 160 Lab Renovation Design Services

Year Approved 5/30/19 went out to bid on 5/8/19 . Information Meeting on 5/15/19. 2019 Design Firm: SMRT Contractor: Name: Funding: COLLEGE / DEPT ALLOC

2.5‐ IN PROCUREMENT 2019‐0107 RR Huddleston Hall ‐ 307, 308 Carpet Replacement

Year Approved 5/30/19, I will meet with Kevin Sousa. 2019 Design Firm: Contractor: External Name: Milestone Funding: DMA

2.5‐ IN PROCUREMENT 2019‐0289 FCR Memorial Union Building ‐ Remove Mailboxes & Create Storage Area

Year Approved 5/30/19, Careno has PO, scheduled for June 3, 2019. 2019 Design Firm: Contractor: External Name: Careno Construction Funding: COLLEGE / DEPT ALLOC

Brenda Whitmore, Director Facilities Project Management Thursday, May 30, 2019 University of New Hampshire Page 2 of 30 3‐ IN CONSTRUCTION 2010‐0300 RR Dimond Library ‐ South Masonry Repointing

Year Approved 5/30/19, Careno working on repointing south side. Top band is in tough shape and waiting for proposal to 2020 repair.

Design Firm: Contractor: External Name: Careno Construction Funding: DMA

3‐ IN CONSTRUCTION 2017‐0431 FCR Parsons Hall ‐ Rm S128 Ammonia Gas Control System

Year Approved 5/30/19:Andy Glode to write procedure for System . 2018 Design Firm: Norris Contractor: External Name: Norris Funding: COLLEGE / DEPT ALLOC

3‐ IN CONSTRUCTION 2018‐0311 FCR 1 Leavitt Lane ‐ 1st and 2nd Floor Paint and Carpet Estimate

Year Approved 5/30/19, Painting is work in progress. 2019 .

Design Firm: Contractor: External Name: Careno Construction Funding: COLLEGE / DEPT ALLOC

3‐ IN CONSTRUCTION 2019‐0058 RR Paul Creative Arts Center ‐ 1st Floor Music Wing Restoration

Year Approved Emergency Repair 5/30/19, Headwall is in fabrication. 2019 Design Firm: Contractor: External Name: T & S Construction Funding: INST RR

3.1‐ SUBSTANTIAL COMPLETION 2018‐0243 FCR MacFarlane Greenhouse ‐ HVAC Replacement

Year Approved 5/30/19, project completed . 2019 Design Firm: Contractor: External Name: APH Funding: COLLEGE / DEPT ALLOC

3.1‐ SUBSTANTIAL COMPLETION 2018‐0261 FCR James Hall ‐ Rm 348 Eyewash/Shower Installation

Year Approved 5/30/19,Installation complete. 2019 Design Firm: Contractor: External Name: Granite State Funding: COLLEGE / DEPT ALLOC

3.1‐ SUBSTANTIAL COMPLETION 2018‐0344 FCR Kingsbury Hall ‐ Rm S315 INSTALL EYE WASH AND EMERGENCY SHOWER

Year Approved 5/30/19, Installation completed. 2019 Design Firm: Contractor: External Name: Granite State Plumbing and Funding: COLLEGE / DEPT Heating ALLOC

3.1‐ SUBSTANTIAL COMPLETION 2019‐0003 RR Elliott Alumni Center ‐ HVAC Modifications and Upgrades Design

Year Approved 5/30/19, Harriman completed construction documents 5/2/19 . 2019 Design Firm: Harriman Contractor: Name: Funding: DMA

Brenda Whitmore, Director Facilities Project Management Thursday, May 30, 2019 University of New Hampshire Page 3 of 30 3.1‐ SUBSTANTIAL COMPLETION 2019‐0008 RR Tree Removal ‐ Oyster River Blow Down Removal

Year Approved 5/30/19,Tree removed from Oyster River. 2019 Design Firm: Contractor: External Name: Crawfords Logging Funding: DMA

3.1‐ SUBSTANTIAL COMPLETION 2019‐0046 RR Morse Hall ‐ HVAC Unit Replacement and Building Envelope Repairs

Year Approved Emergency Repair 5/30/19, substantial completion. 2019 Design Firm: Contractor: External Name: Careno Construction Funding: INST RR

3.1‐ SUBSTANTIAL COMPLETION 2019‐0199 RR Barton Hall & Cole Hall ‐ Magnetic Holder Installation Rm 102

Year Approved 5/30/19, Magnetic door holder installed. 2019 Design Firm: Contractor: External Name: Yates Electrical Funding: DMA

3.1‐ SUBSTANTIAL COMPLETION 2019‐0248 FCR Spaulding Hall ‐ Rm 132 Remove casework & suspected ACM countertop

Year Approved 5/30/19,Job is substantially complete. 2019 Design Firm: Contractor: External Name: Milestone Construction Funding: COLLEGE / DEPT ALLOC

3.6‐ WEATHER RESTRICTION 2016‐0425 FCR Parsons Hall ‐ Installation of Exterior Window Film

Year Approved 5/30/19 Scheduled for June. 2019 Design Firm: Contractor: External Name: Anderson Films Funding: COLLEGE / DEPT ALLOC

BRICKETT, ALEXANDER J 41

1.1‐ PLAN/EST 2015‐0091 RR Thompson Hall ‐ Single Bottom Cylinder Replacement NHE 1102

Year Approved 5/29/19 Work to occur Spring ʹ20. 2020 Design Firm: Contractor: Name: Funding: DMA

1.1‐ PLAN/EST 2013‐1225 RR Morse Hall ‐ NHE 1997 and 1998 Upgrades

Year Approved 5/29/19 ‐ Working wth building occupants to determine best time to upgrade elevators. Right now it is looking 2020 like the work will be scheduled to occur late fall 2019.

Design Firm: Contractor: Name: Funding: DMA

1.1‐ PLAN/EST 2016‐0363 RR Thompson Hall ‐ Clock Tower Repairs

Year Approved 5/29/19 Work postponed until next year. This project requires a forensic RFQ/P to determine the cause and 2020 subsequent remedies. RFQ/P process to begin late summer early Fall.

Design Firm: Contractor: Name: Funding: DMA

Brenda Whitmore, Director Facilities Project Management Thursday, May 30, 2019 University of New Hampshire Page 4 of 30 1.1‐ PLAN/EST 2018‐0191 FCR Campus ‐ Housing Fire Alarm/CO Detection

Year Approved 5/29/19 ‐ Review current and future efforts with SFMO during future meetings.

Design Firm: SFC Engineering Contractor: External Name: TBD Funding: COLLEGE / DEPT ALLOC

1.1‐ PLAN/EST 2018‐0200 SI Kingsbury Hall ‐ Career Services

Year Approved 5/29/19 ‐ Schematic design of space in progress. Waiting for approval to move forward with full design. 2018 Design Firm: Contractor: Name: Funding: SARRC ALLOC

1.1‐ PLAN/EST 2019‐0055 RR Paul Creative Arts Center ‐ Fire Alarm Design ONLY

Year Approved 5/29/19 ‐ Harriman and SFC to provide proposal for design. 2020 Design Firm: TBD Contractor: External Name: TBD Funding: DMA

1.1‐ PLAN/EST 2019‐0144 SI Murkland Hall ‐ COLA‐BSC Relocation

Year Approved 5/29/19 ‐ Quotes received for and contractor. Working on revising contractor scope to meet budget. 2019 Design Firm: Contractor: Name: Funding: SARRC ALLOC

1.1‐ PLAN/EST 2019‐0232 FCR Nesmith Hall ‐ New HR Suite ADA Door Actuator Installation

Year Approved 5/29/19 ‐ Estimates for this work have been received. An FCR for this work will be issued once confirmed by ADA office.

Design Firm: Contractor: Name: Funding: COLLEGE / DEPT ALLOC

1.1‐ PLAN/EST 2019‐0241 RR Paul Creative Arts Center ‐ Building Life Safety Report Update

Year Approved 5/29/19 ‐ Addendum to Life Safety plan to be reviewed and approved with the SFMO. 2019 Design Firm: Contractor: Name: Funding: DMA

1.1‐ PLAN/EST 2019‐0251 RR Nesmith Hall ‐ Life Safety Review

Year Approved 5/29/19 Life Safety review to occur beginning late summer 2019.

Design Firm: Contractor: Name: Funding: DMA

1.1‐ PLAN/EST 2019‐0305 FCR Rudman Hall ‐ Retro‐Commissioning of ARO HVAC System

Year Approved 5/29/19 ‐ Work to be completed concurrently with project #2010‐0479.

Design Firm: Contractor: Name: Funding: COLLEGE / DEPT ALLOC

1.1‐ PLAN/EST 2019‐0324 FCR Handler Hall ‐ replacement of PVI tanks

Year Approved 5/29/19 ‐ Initial project scope established. Workingwith PVI to determine best replacement options.

Design Firm: Contractor: Name: Funding: COLLEGE / DEPT ALLOC

Brenda Whitmore, Director Facilities Project Management Thursday, May 30, 2019 University of New Hampshire Page 5 of 30 1.1‐ PLAN/EST 2019‐0345 RR Presidentʹs ‐ Solarium Hazmat Assessment and Abatement

Year Approved 5/29/19 ‐ Proposal received from industrial hygenist. Work to be coordinated with the renovation of the solarium.

Design Firm: Contractor: Name: Funding: DMA

2‐ IN DESIGN 2015‐2336 RR Rudman Hall ‐ Conversion to DDC Controls

Year Approved 5/29/19: Reference ID 2010‐0479 for updates. 2018 Design Firm: SMRT Contractor: External Name: StructureTone Funding: DMA

2‐ IN DESIGN 2015‐2352 RR Rudman Hall ‐ Fire Alarm Replacement

Year Approved 5/29/19: Reference ID 2010‐0479 for updates. 2016 Design Firm: SFC / SMRT Contractor: External Name: StructureTone Funding: DMA

2‐ IN DESIGN 2017‐0251 FCR Field House ‐ New Ski Locker Room/Team Area

Year Approved 5/29/19 ‐ Schematic design completed. Harriman is working on space renderings with UNHʹs input. 2018 Design Firm: Harriman Contractor: Name: Funding: COLLEGE / DEPT ALLOC

2‐ IN DESIGN 2018‐0145 RR Parsons Hall ‐ Rms N104, N108 Classroom Renovation Iddles Lecture Design Only

Year Approved 5/29/19 ‐ Design in progress. 2019 Design Firm: Harriman Contractor: External Name: Funding: DMA

2‐ IN DESIGN 2018‐0235 RR ‐ Arena ‐ Design and Replacement of Ice Floor Systems

Year Approved 5/29/19 ‐ RFQ/P posted. SoQ due 5/31. 2018 Design Firm: Contractor: Name: Funding: DMA

2‐ IN DESIGN 2018‐0340 FCR McLaughlin Hall ‐ Fire Alarm System Replacement

Year Approved 5/29/19 Contract to be issued to Gerard Laflamme. Construction scheduled to begin 6/03. 2019 Design Firm: SFC Contractor: External Name: Gerard Laflamme Funding: COLLEGE / DEPT ALLOC

2.5‐ IN PROCUREMENT 2010‐0479 RR Rudman Hall ‐ Laboratory Fume Hood Control System Replacement

Year Approved 5/29/19 ‐ Steam Valve replacement completed. Lab work is in design and is expected to be complete for 2017 bidding purposes by mid‐June. Fire alarm design is complete. GMP work still in progress

Design Firm: SMRT, Inc. Contractor: External Name: StructureTone Funding: DMA

Brenda Whitmore, Director Facilities Project Management Thursday, May 30, 2019 University of New Hampshire Page 6 of 30 2.5‐ IN PROCUREMENT 2010‐0729 FCR Utility Distribution ‐ Edgewood Water Tank ‐ Decomissioning

Year Approved 5/29/19 ‐ Tank level at 1/3 capacity. Work to occur late summer 2019. 2018 Design Firm: Contractor: External Name: Charter Brothers Funding: COLLEGE / DEPT ALLOC

2.5‐ IN PROCUREMENT 2016‐0156 SI Campus Wayfinding ‐ Phase 3

Year Approved 5/29/19 ‐ Project scope established. Work to occur late summer. 2019 Design Firm: Contractor: Name: Funding: SARRC ALLOC

2.5‐ IN PROCUREMENT 2019‐0110 FCR Thompson Hall ‐ Rm 302 Design Help for Conference

Year Approved 5/29/19 ‐ Approved FCR received. POʹs issued to contractors.

Design Firm: Contractor: External Name: Creative Office Pavilion Funding: COLLEGE / DEPT ALLOC

2.5‐ IN PROCUREMENT 2019‐0344 RR Presidentʹs House ‐ Solarium Renovation

Year Approved 5/29/19 ‐ PO issued to Chapman Construction. McHenry Architecture is providing guidance on window 2019 replacements. Aiming to do work in mid June.

Design Firm: McHenry Architecture Contractor: External Name: Chapman Funding: DMA

3‐ IN CONSTRUCTION 2015‐2306 RR Hewitt Hall ‐ Fire Alarm Replacement

Year Approved 4/26/19 ‐ Yates Electric is on‐site installing system. Project completion to occur in early June. 2019 Design Firm: SFC Engineering Contractor: External Name: Yates Electric Funding: DMA

3‐ IN CONSTRUCTION 2017‐0308 FCR Whittemore Center ‐ Arena ‐ Dehumidification System

Year Approved 5/29/19 ‐ Construction in progress. Anticipated completion in mid‐June 2019 Design Firm: Harriman Contractor: External Name: Careno Construction Funding: COLLEGE / DEPT ALLOC

3‐ IN CONSTRUCTION 2018‐0048 RR Parsons Hall ‐ Processed Chilled Water System Replacement

Year Approved 5/29/19 ‐ Commissioning in progress. 2018 Design Firm: Harriman Contractor: External Name: Northern Peabody Funding: INST RR

3‐ IN CONSTRUCTION 2018‐0341 FCR Christensen Hall‐ Replacement

Year Approved 5/29/2019: ‐ Construction in progress. Anticipated finish date of 8/9. 2019 Design Firm: SMRT Contractor: External Name: Viking Funding: COLLEGE / DEPT ALLOC

Brenda Whitmore, Director Facilities Project Management Thursday, May 30, 2019 University of New Hampshire Page 7 of 30 3‐ IN CONSTRUCTION 2018‐0371 FCR Holloway Commons ‐ Dunkin Donuts Space

Year Approved 5/29/19 Construction in progress. Evaporators installed in Dunkinʹ Donuts space. Working on finalizing 2019 location and installation of rooftop condenser.

Design Firm: Contractor: External Name: GSPH Funding: COLLEGE / DEPT ALLOC

3.1‐ SUBSTANTIAL COMPLETION 2013‐1032 RR Presidentʹs House ‐ Building Exterior and Interior Painting and Repairs

Year Approved 5/29/19 ‐ Replacement oven installed. Window treatments for installed. Tile backsplash installed. 2018 Design Firm: Contractor: External Name: Chapman Funding: DMA

3.1‐ SUBSTANTIAL COMPLETION 2016‐0148 RR Rudman Hall ‐ ARO Autoclave Replacement

Year Approved 5/29/19 ‐ Autoclave installed and functioning. Working with GSPH to resolve drain issues. 2019 Design Firm: Harriman Contractor: External Name: Granite State Plumbing & Funding: DMA Heating

3.1‐ SUBSTANTIAL COMPLETION 2016‐0500 FCR Holloway Commons ‐ Retro‐Commissioning Repairs

Year Approved 5/29/19 ‐ RFS Basix, Granite State Plumbing and Heating, performed phase 1 repair work in January. Report 2017 has been issued detailing next steps.

Design Firm: RFS Contractor: External Name: Basix Funding: COLLEGE / DEPT ALLOC

3.1‐ SUBSTANTIAL COMPLETION 2017‐0004 RR Morse Hall ‐ Third Floor Tempid Water Loop

Year Approved 5/29/19 ‐ Final inspection to be completed. 2017 Design Firm: Contractor: External Name: GSPH Funding: DMA

3.1‐ SUBSTANTIAL COMPLETION 2017‐0212 SI Thompson Hall ‐ Graduate Student Center

Year Approved 5/29/19 ‐ Furniture and punchlist items in progress. 2017 Design Firm: Contractor: External Name: Funding: SARRC ALLOC

3.1‐ SUBSTANTIAL COMPLETION 2018‐0132 RR Gregg Hall ‐ Flood Restoration

Year Approved Emergency Repair 5/29/19 ‐ Drywall work to be competed by FCT. Work to be coordinated with John OʹRourke. 2018 Design Firm: Contractor: FCT Name: Funding: INST RR

3.1‐ SUBSTANTIAL COMPLETION 2018‐0166 SI Nesmith Hall ‐ Phone‐a‐thon Fit Out

Year Approved 5/29/19 ‐ Work substantially completed. Thermostat and control work in progress. 2018 Design Firm: Harriman Contractor: External Name: Careno Funding: SARRC ALLOC

3.1‐ SUBSTANTIAL COMPLETION 2018‐0173 SI Nesmith Hall ‐ Room Improvements G17 ‐ G25

Year Approved 5/29/19 ‐ Punchlist items in progress 2018 Design Firm: Contractor: External Name: milestone Funding: SARRC ALLOC

Brenda Whitmore, Director Facilities Project Management Thursday, May 30, 2019 University of New Hampshire Page 8 of 30 3.1‐ SUBSTANTIAL COMPLETION 2018‐0225 FCR Stoke Hall ‐ First Floor Renovation/Paul College Program

Year Approved 5/29/19 ‐ Substantially completed. Punchlist in progress. 2019 Design Firm: Office Interiors Contractor: External Name: Milestone Funding: COLLEGE / DEPT ALLOC

3.1‐ SUBSTANTIAL COMPLETION 2018‐0339 SI Nesmith Hall ‐ Improvements and ADA Accessibility Modifications

Year Approved 5/29/19‐ See project 2015‐2341 for updates. 2018 Design Firm: Cowan & Goudreau Contractor: External Name: Greenleaf Construction Funding: SARRC ALLOC

3.1‐ SUBSTANTIAL COMPLETION 2019‐0002 SI Nesmith Hall ‐ Rm G00CRA Modifications

Year Approved 5/29/19 ‐ replaced on 2/23. Punchlist items in progress. 2018 Design Firm: Contractor: External Name: Milestone Funding: SARRC ALLOC

3.1‐ SUBSTANTIAL COMPLETION 2019‐0186 BAR Whittemore Center ‐ Arena ‐ HV Replacements and A/C ‐ Design Only

Year Approved 5/29/19 ‐ Will begin working with design firms to obtain design fee proposal for chiller plant and AHU replacement to include cooling coils.

Design Firm: TBD Contractor: External Name: TBD Funding: COLLEGE / DEPT ALLOC

GARCIA, CHRISTOPHER E 21

1.1‐ PLAN/EST 2019‐0327 FCR Morse Hall ‐ Rm 332 Renovation

Year Approved 5/29/2019 ‐ Expanded to include ESD flooring throughout. Revising price and breakout

Design Firm: NO Contractor: External Name: Careno Construction Funding: COLLEGE / DEPT ALLOC

1.1‐ PLAN/EST 2019‐0357 FCR Dimond Library ‐ Rm 421 Minor Renovation

Year Approved 5/29/2019 ‐ Working with Office Int for layout and furniture. Milestone for other work. Pricing to arrive.

Design Firm: Office Interiors Contractor: External Name: Milestone Funding: COLLEGE / DEPT ALLOC

1.1‐ PLAN/EST 2019‐0380 RR Nesmith Hall ‐ Warranty Carpet Replacement

Year Approved 5/29/2019 ‐ Working on securing dates for work

Design Firm: Contractor: FCT Name: Utilizing Ops Funding: DMA

2‐ IN DESIGN 2019‐0141 SI Rudman Hall ‐ Vivarium Upgrades ‐ Phase II

Year Approved 5/29/2019: In design. With Campus planning 2019 Design Firm: MPM Contractor: External Name: Charters Brothers Funding: SARRC ALLOC

Brenda Whitmore, Director Facilities Project Management Thursday, May 30, 2019 University of New Hampshire Page 9 of 30 2‐ IN DESIGN 2019‐0260 FCR 10 West Edge Drive ‐ Roof Replacement

Year Approved 5/29/2019‐ Engineering investigation starting June 4,2019 2019 Design Firm: Petersen Engineering Contractor: External Name: Funding: COLLEGE / DEPT ALLOC

2‐ IN DESIGN 2019‐0298 RR New Hampshire Hall ‐ Ground Floor Water Infiltration Design Only

Year Approved 5/29/2019‐ PO released to Careno for design. Investigation underway 2019 Design Firm: Careno Contractor: External Name: Careno Funding: INST RR

2.5‐ IN PROCUREMENT 2019‐0273 RR Thompson Hall ‐ and Roof Accessibility Modifications

Year Approved 5/29/2019 Awaiting responses on roof and attic pricing 2019 Design Firm: Hoyle, Tanner & Associates Contractor: External Name: Funding: DMA / ARM

2.5‐ IN PROCUREMENT 2019‐0349 FCR Parsons Hall ‐ Doorway Replacement ‐ Rm W126 and W126A

Year Approved 5/29/2019‐ Tracking status off custom door frame

Design Firm: Contractor: External Name: Funding: COLLEGE / DEPT ALLOC

2.5‐ IN PROCUREMENT 2019‐0352 RR Smith Hall ‐ Exterior Painting

Year Approved 5/29/2019‐ Lead paint investigation with Desmaris. Finding will impact budget. 2019 Design Firm: Contractor: External Name: Funding: INST RR

2.5‐ IN PROCUREMENT 2019‐0354 RR Service Building ‐ Flooring Abatement and Replacement

Year Approved 5/29/2019 ‐ Awaiting pricing to gather funding

Design Firm: Contractor: External Name: Careno Funding: DMA

3‐ IN CONSTRUCTION 2017‐0214 SI Rudman Hall ‐ Vivarium Upgrades Phase 1

Year Approved 5/29/2019‐ Mitigating the damage due to equipment lead times being 14‐16 weeks. Seeking alternatives to 2017 achieve the least amount of impact on schedule.

Design Firm: Harriman Contractor: Name: StructureTone Funding: SARRC ALLOC

3‐ IN CONSTRUCTION 2018‐0115 RR Rudman Hall ‐ Microbiology Teaching Labs Kitchen Drying Oven

Year Approved 5/29/2019‐ PO to Careno. Work to start in July. 2020 Design Firm: Contractor: External Name: Careno Funding: DMA

3‐ IN CONSTRUCTION 2019‐0226 FCR 121 Technology Drive ‐ Evaluation of Fume Hood SW101

Year Approved 5/29/2019‐ Tekon investigating current duct work and hood 2019 Design Firm: SMRT Contractor: External Name: Funding: COLLEGE / DEPT ALLOC

Brenda Whitmore, Director Facilities Project Management Thursday, May 30, 2019 University of New Hampshire Page 10 of 30 3‐ IN CONSTRUCTION 2019‐0272 RR Hood House ‐ Attic Accessibility Modifications

Year Approved 5/29/2019 ‐ All mechanical work is complete. Working to finish catwalks. 2019 Design Firm: Harriman Contractor: External Name: GSPH / Malthouse Funding: DMA

3‐ IN CONSTRUCTION 2019‐0274 RR Field House ‐ Indoor Accessibility Modifications Room 402

Year Approved 5/29/2019 ‐Light install ready. Loading of materials coordinating 2019 Design Firm: Harriman Contractor: External Name: Scarponi Elec Funding: DMA

3‐ IN CONSTRUCTION 2019‐0317 FCR Dimond Library ‐ Level one Special Collections Furniture and Technology Upgrades

Year Approved 5/29/2019‐ Demo has started. Working with Milestone to continue the project smoothly. 2019 Design Firm: Contractor: External Name: Milestone / Others Funding: COLLEGE / DEPT ALLOC

3.1‐ SUBSTANTIAL COMPLETION 2019‐0012 FCR Rudman Hall ‐ Retrofit Rm B52 for ABSL‐2 Containment

Year Approved 5/29/2019: Coordinating with controls group

Design Firm: Contractor: External Name: TBD Funding: COLLEGE / DEPT ALLOC

3.1‐ SUBSTANTIAL COMPLETION 2019‐0240 SI Paul Creative Arts Center ‐ Rm A203 Art Department Design Lab

Year Approved 5/29/2019: Painting and cleaning is complete. AV & Carpet to complete 2019 Design Firm: Office Interiors Contractor: External Name: multiple contractors Funding: SARRC ALLOC

3.1‐ SUBSTANTIAL COMPLETION 2019‐0299 FCR Chase Ocean Engineering Laboratory ‐ Rm 121 Renovation

Year Approved 5/29/2019‐ Railing touch up. Awaiting furniture set up 2019 Design Firm: Office Interiors LTD Contractor: External Name: Milestone Funding: COLLEGE / DEPT ALLOC

3.1‐ SUBSTANTIAL COMPLETION 2019‐0314 RR Zais Hall ‐ Rms 101, 202, 203 Flooring Abatement and Replacement

Year Approved 5/29/2019‐ Looking into flooring alternates in classroom due to petroleum abatment. 2019 Design Firm: Air Quality Experts Contractor: External Name: Chasco Inc , Sprauge Funding: DMA Flooring

3.1‐ SUBSTANTIAL COMPLETION 2019‐0321 RR Pettee Hall ‐ G00CRB, 100ZOC Interior Painting

Year Approved 5/29/2019 ‐ Repairing sprinkler damage. Punch listing 2020 Design Firm: Contractor: FCT Name: Peak Painting Funding: INST RR

GEUTHER, MARK E 16

Brenda Whitmore, Director Facilities Project Management Thursday, May 30, 2019 University of New Hampshire Page 11 of 30 1.1‐ PLAN/EST 2014‐1773 RR Kendall Hall ‐ Tile Abatement Phase I of II

Year Approved 05‐28‐2019 This will be completed with floor 3 and 4 abatement. 2016 Design Firm: Manypenny Murphy Contractor: External Name: Charters Brothers Funding: DMA

1.1‐ PLAN/EST 2019‐0242 FCR Field House ‐ Water Main Repair

Year Approved 05‐28‐2019: Scheduling meeting to discuss repair this summer

Design Firm: TBD Contractor: External Name: TBD Funding: COLLEGE / DEPT ALLOC

1.1‐ PLAN/EST 2019‐0250 FCR Whittemore Center ‐ Arena ‐ R18 Monitors

Year Approved 05‐28‐2019: Waiting for Clients authorization to proceed.

Design Firm: NA Contractor: External Name: Yates/Red Thread Funding: COLLEGE / DEPT ALLOC

1.1‐ PLAN/EST 2019‐0294 FCR Wildcat Stadium ‐ Victory Club Television

Year Approved 05‐28‐2019: FCR sent to Athletics. Waiting for funding.

Design Firm: N/A Contractor: External Name: Funding: COLLEGE / DEPT ALLOC

2‐ IN DESIGN 2019‐0158 SI Kendall Hall ‐ 3rd Floor Repurposing

Year Approved 05‐28‐2019: Design work is underway. Working toward completing demo and abatement in the summer. 2019 Design Firm: Manypenny Murphy Contractor: External Name: Charters Brothers Funding: SARRC ALLOC

2‐ IN DESIGN 2019‐0161 SI Kendall Hall ‐ 4th Floor Repurposing

Year Approved 05‐28‐2019: See 2019‐0158 2019 Design Firm: Manypenny Murphy Contractor: External Name: Charters Brothers Funding: SARRC ALLOC

2‐ IN DESIGN 2019‐0292 FCR Telecommunications Center ‐ Addition and Renovation

Year Approved 05‐28‐2019: Design underway, final Schematic Design scheduled for review on June 20.

Design Firm: Oak Point Contractor: External Name: Charters Brothers Funding: COLLEGE / DEPT ALLOC

2.5‐ IN PROCUREMENT 2011‐0653 SI Field House ‐ 1st Floor AC Installation

Year Approved 05‐28‐2019: Design 95% Complete. CM Interviews scheduled for 5‐30‐2019 (Careno, Charters Brothers, 2019 Milestone)

Design Firm: Harriman Contractor: External Name: TBD Funding: SARRC ALLOC

2.5‐ IN PROCUREMENT 2019‐0306 RR Field House ‐ Pool Chemical Storage Design and UV Filter Replacement

Year Approved 05‐28‐2019: Design for UV light complete. Charters Brothers soliciting pricing and formulating budget. 2019 Design Firm: Weston & Sampson Contractor: External Name: Charters Brothers Funding: DMA

Brenda Whitmore, Director Facilities Project Management Thursday, May 30, 2019 University of New Hampshire Page 12 of 30 3‐ IN CONSTRUCTION 2008‐0038 SI Water Treatment Plant ‐ New Construction

Year Approved 05‐28‐2019: Process piping on going. Administration building framing ongoing. Electrical and mechanical 2014 ongoing. Preliminary testing and start up scheduled for mid June.

Design Firm: Woodard & Curran Contractor: External Name: Waterline Industries Funding: SARRC ALLOC

3‐ IN CONSTRUCTION 2017‐0285 FCR Outdoor Facility ‐ New Soccer/Lacrosse Field

Year Approved 05‐28‐2019: Field is substantially complete. Pavement complete, final loam and seeding underway. Scheduled 2018 completion 5‐31‐2019.

Design Firm: Tighe & Bond Contractor: External Name: R.A.D. Sports Funding: COLLEGE / DEPT ALLOC

3‐ IN CONSTRUCTION 2019‐0102 FCR Field House ‐ Football Locker Room Renovation – Phase II

Year Approved 05‐28‐2019: Demo 90% complete, abatement underway. 2019 Design Firm: Manypenny Murphy Contractor: External Name: Vantage Builders Funding: COLLEGE / DEPT ALLOC

3.1‐ SUBSTANTIAL COMPLETION 2017‐0325 RR Field House ‐ Steam to Domestic Hot Water System Replacement

Year Approved 05‐28‐2019: Substantially Complete 2018 Design Firm: Harriman Contractor: External Name: Northern Peabody Funding: DMA

3.1‐ SUBSTANTIAL COMPLETION 2018‐0267 SI Campus ‐ South Drive ‐ Temporary Connection to Colovos Road

Year Approved 05‐28‐2019: Substantially Complete. 2019 Design Firm: Tighe & Bond Contractor: External Name: R.A.D. Sports Funding: SARRC ALLOC

3.1‐ SUBSTANTIAL COMPLETION 2019‐0043 RR Taylor Hall ‐ Flood Repairs and Abatement

Year Approved Emergency Repair 05‐28‐2019: Substantially Complete. 2019 Design Firm: Tighe & Bond Contractor: External Name: Milestone/T&S Construction Funding: INST RR

3.5‐ WARRANTY REPAIRS 2018‐0002 FCR Northwest Heat Plant ‐ New Construction

Year Approved 05‐28‐2019 Project Complete. 2018 Design Firm: Wilson Engineering Contractor: External Name: Froling Energy Funding: COLLEGE / DEPT ALLOC

HENRY, PAUL A 34

1.1‐ PLAN/EST 2017‐0402 FCR Huddleston Hall ‐ Creation of Offices within Carsey School

Year Approved 5‐23‐19 ‐ On 1‐4‐19 met with team, waiting on final musical chairs with the Egress project Summer 2019/2020

Design Firm: Harriman Contractor: External Name: Funding: COLLEGE / DEPT ALLOC

Brenda Whitmore, Director Facilities Project Management Thursday, May 30, 2019 University of New Hampshire Page 13 of 30 1.1‐ PLAN/EST 2018‐0270 RR James Hall ‐ HVAC Modifications Investigation and Design

Year Approved 5‐23‐19 ??? Replacing the gasket only, did not fix the problem . We are looking into doing a air flow 2018 around the building to determine a engineered fix. ???? Is this mine?

Design Firm: Harriman Contractor: Name: Funding: DMA

1.1‐ PLAN/EST 2019‐0277 FCR Concord ‐ UNH School of Law ‐ Student Services Consolidation

Year Approved 5‐23‐19 have three options, presenting to SFMO

Design Firm: CP Contractor: Name: Funding: COLLEGE / DEPT ALLOC

1.1‐ PLAN/EST 2019‐0322 FCR Thompson Hall ‐ UNH Testing Center ‐ Phase 2

Year Approved 5‐23‐19 Working with CP, Space will not be available until the COLA BSC moves to Murkland this summer.

Design Firm: TBD Contractor: External Name: TBT Funding: COLLEGE / DEPT ALLOC

2‐ IN DESIGN 2012‐0841 RR Huddleston Hall ‐ Fire Code Assessment and Life Safety Plan

Year Approved 5‐23‐19 Harriman has provided the Occupancy Calcs to the SFMO this task is closed. 2019 Meet with Harriman using the SFC study as a basis of the project code sheet so it is easily referenced back to the study this will also demonstrate we have addressed all the issues identified. Presented to SFMO, Returning to SFMO with Ballroom Occupancy in current condition. waiting for funding for next step….finish design to CD.

Design Firm: SFC Engineering Partnership Contractor: Name: Funding: DMA

2‐ IN DESIGN 2013‐1115 SI South Drive ‐ Design Advancement

Year Approved 5‐23‐19 T&B recently estimated project at DD, up dated estimate 2013 Design Firm: Tighe & Bond Contractor: External Name: Funding: SARRC ALLOC

2‐ IN DESIGN 2013‐1155 RR Huddleston Hall ‐ Design of Egress Modifications

Year Approved 5‐23‐19 MEP Study reviewed scope of work, waiting on funding 2017 Design Firm: Harriman Contractor: External Name: Harriman Funding: DMA

2‐ IN DESIGN 2016‐0165 RR Huddleston Hall ‐ Roof Replacement Design Only

Year Approved 5‐23‐19 Harriman working with ARM to include the design. Design is on hold at SD, waiting for funding. 2017 Design Firm: ARM Contractor: External Name: Harriman Funding: DMA

2‐ IN DESIGN 2018‐0162 RR Philbrook Hall ‐ Steam Study and Investigation

Year Approved 5‐23‐19 Waiting for final Report, working with RFS & EF to install the boiler. 2019 RFS provided three (3) options for steam study. UNH has decided to proceed with using the steam boiler at Philbrook for hot water make up, this will allow the local steam boiler to operate between August ‐ May with continuation operation. During Summer when Philbrook is not open the boiler will be put in dry layup with service assistance from Blake Engineering. Intend to have local boiler online January 2019.

Design Firm: RFS Contractor: External Name: Eckhardt Johnson Funding: DMA

Brenda Whitmore, Director Facilities Project Management Thursday, May 30, 2019 University of New Hampshire Page 14 of 30 2‐ IN DESIGN 2018‐0195 FCR Holloway Commons ‐ Conference Area Carpeting Replacement

Year Approved 5‐23‐19 In Design, construction summer 2020 2019 Design Firm: Harriman Contractor: External Name: TBD Funding: COLLEGE / DEPT ALLOC

2‐ IN DESIGN 2018‐0256 FCR Campus ‐ Lee Circle Water Extension

Year Approved 5‐23‐19 Meet with team, Underwood, consultant, working on Design Constructon Summer 2020 or 2021 depending on progress with easements.

Design Firm: Underwood Eng Contractor: External Name: TBD Funding: COLLEGE / DEPT ALLOC

2‐ IN DESIGN 2019‐0139 FCR Campus ‐ Tennis Court Renovation

Year Approved 5‐23‐19 T&B Working on Design, Meeting 5‐24‐19 to reveiew design and purcurment. 2019 Design Firm: Tighe & Bond Contractor: External Name: TBD Funding: COLLEGE / DEPT ALLOC

2‐ IN DESIGN 2019‐0191 FCR Elliott Alumni Center ‐ 1925 Room

Year Approved 5‐23‐19 Meet on 5‐22 to discuss programing, next meeting to discuss finishes and for SD. 2019 Design Firm: Manny Penny Murphy Contractor: External Name: TBD Funding: SARRC ALLOC

2‐ IN DESIGN 2019‐0257 RR Morrill Hall ‐ Exterior Site Drainage Design

Year Approved 5‐23‐19 Tighe & Bond working on design, have preliminary document to reviw. 2019 Design Firm: Tighe & Bond Contractor: Name: Funding: INST RR

2.5‐ IN PROCUREMENT 2010‐0411 SI Horton Social Science Center ‐ G04 Auditorium – Air Conditioning

Year Approved 5‐23‐19 Bids in, Structuretone apparent low bidder, mobilizing on or about June 10 2019 Design Firm: Harriman Contractor: External Name: Structuretone Funding: SARRC ALLOC

2.5‐ IN PROCUREMENT 2017‐0438 SI Campus ‐ Main Street West Bus Pads, Shelters, AVL

Year Approved 5‐23‐19 Processed contract and PO, waiting for schedule. 2018 Design Firm: Tighe & Bond Contractor: External Name: TBD Funding: GRANT

2.5‐ IN PROCUREMENT 2018‐0100 RR Utility Distribution ‐ College Brook Culvert Repair

Year Approved 5‐23‐19 Design Complete, Re‐routing high voltage lines complete except one circuit, that can be pulled 2019 anytime with two week notice. Having term contractor price for spring. Working with Term Contractors to deliver the project in August when water flow is low.

Design Firm: Tighe & Bond, Site / Contractor: External Name: TBD Funding: DMA Harriman, Electrical

Brenda Whitmore, Director Facilities Project Management Thursday, May 30, 2019 University of New Hampshire Page 15 of 30 2.5‐ IN PROCUREMENT 2019‐0300 FCR Memorial Union Building ‐ Replace Radiator Heating

Year Approved 5‐23‐19 Issuing PO to GSPH work to commence July 8‐19 2020 Design Firm: Contractor: External Name: Granite State Plumbing and Funding: COLLEGE / DEPT Heating ALLOC

3‐ IN CONSTRUCTION 2016‐0010 FCR Huddleston Hall ‐ Ballroom AC Installation and Electrical Service

Year Approved 5‐23‐19 Carsey moved upstairs, started demo in cooler area, starting to demo in corridor for shuring and structurral changes.

Design Firm: Harriman Associates Contractor: External Name: Milestone Funding: COLLEGE / DEPT ALLOC

3‐ IN CONSTRUCTION 2016‐0403 RR New England Center ‐ Boiler Replacement and BAS Controls

Year Approved 5‐23‐19 Abatment complete, site fencing up, starting boiler removal. 2020 Design Firm: Harriman Contractor: Name: Funding: DMA

3‐ IN CONSTRUCTION 2017‐0250 RR Gregg Hall ‐ Chiller Replacement ‐ Funding for Construction

Year Approved 5‐23‐19 2017‐0281 Should be referenced for updates on construction. Working on boiler communication, CB 2019 and vendor working on solution.

Design Firm: Harriman Contractor: External Name: TBD Funding: DMA

3‐ IN CONSTRUCTION 2017‐0399 FCR Philbrook Hall ‐ Kitchen Modifications

Year Approved 5‐23‐19 Currently in full Construction, demo uderway, shoring ongoing, cutting slab for removeal. 2018 Design Firm: Harriman Contractor: External Name: Charters Brothers Funding: COLLEGE / DEPT ALLOC

3‐ IN CONSTRUCTION 2018‐0286 SI Thompson Hall ‐ Suite 301 Finance and Planning Offices

Year Approved 5‐23‐19 Just received approval for funding for AC, unit ordered, working out final purcurment details. 2019 Design Firm: Harriman (AC only) Contractor: External Name: Milestone Funding: SARRC ALLOC

3‐ IN CONSTRUCTION 2018‐0370 FCR Mills Hall ‐ Cooling Towers Replacement

Year Approved 5‐23‐19 Towers installed, sand filter installed, working on final tie in, waiting for Chillers to be re‐built. Have 2019 direction on lighting protection and view screen currnetly pricing. Start up June 23, Commissioining to follow June 26.

Design Firm: Harriman Contractor: External Name: Milestone Funding: COLLEGE / DEPT ALLOC

3‐ IN CONSTRUCTION 2019‐0081 RR Whittemore Center ‐ Arena ‐ Reconstruct Drainage Swales Above Loading Dock

Year Approved 5‐23‐19 Upper drainage complete, sidewalk paved, clean up scheduled for June 3rd when woodsides parking 2019 lot has more room.

Design Firm: Tighe & Bond Contractor: External Name: T&S Construction Funding: DMA

Brenda Whitmore, Director Facilities Project Management Thursday, May 30, 2019 University of New Hampshire Page 16 of 30 3‐ IN CONSTRUCTION 2019‐0258 FCR Adams Tower ‐ New Boiler Installation

Year Approved 5‐23‐19 Boilers installed, working on 2hr Fire Shaft for the Flue. Had glitch in design, had to remove installed 2019 wall to add structureal support. Accessing Cost and Schedule.

Design Firm: Harriman Contractor: External Name: Charter Brothers Funding: COLLEGE / DEPT ALLOC

3‐ IN CONSTRUCTION 2019‐0304 FCR Philbrook Hall ‐ Boiler Replacement

Year Approved 5‐23‐19 Boiler is under construction, taking longer than expected, looking for June completion.

Design Firm: RFS Contractor: External Name: Eckardt & Johnson Funding: COLLEGE / DEPT ALLOC

3.1‐ SUBSTANTIAL COMPLETION 2008‐0203 SI Horton Social Science Center ‐ 1st Floor Renovation ‐ Phase 2

Year Approved 5‐23‐19 Working on finishing heating commissioning (almost done) 2018 Design Firm: Harriman Contractor: External Name: Milestone Funding: SARRC ALLOC

3.1‐ SUBSTANTIAL COMPLETION 2016‐0409 SI Hood House ‐ Minor Renovation for Career and Professional Success Center

Year Approved 5‐23‐19 funded landscape design, Woodburn & Associates, just processed PO. 2016 Design Firm: Mannypenny Murphy Contractor: External Name: Trumbell Nelson Funding: SARRC ALLOC

3.1‐ SUBSTANTIAL COMPLETION 2016‐0410 SI Conant Hall ‐ Minor Interior Renovations

Year Approved 5‐23‐19 During commissioning found a missing VFD, TN working on it. 2017 Design Firm: Mannypenny Murphy Contractor: External Name: Trumbell Nelson Funding: SARRC ALLOC

3.1‐ SUBSTANTIAL COMPLETION 2017‐0205 FCR Campus ‐ UNH Fire Damper Study

Year Approved 5‐23‐19 Survey complete, for first 10 buildings. 4 buildings have been funded working on next set 2017 Design Firm: Harriman Contractor: Name: Funding: COLLEGE / DEPT ALLOC

3.1‐ SUBSTANTIAL COMPLETION 2017‐0281 RR Gregg Hall ‐ Chiller Replacement

Year Approved 5‐23‐19 Charters Brothers, UNH / Multistack, Cross Talk not working, vendor workng on a solution. 2017 Design Firm: Harriman Contractor: External Name: Charters Brothers Funding: DMA Construction

3.1‐ SUBSTANTIAL COMPLETION 2018‐0192 RR Conant Hall ‐ DDC Controls Installation

Year Approved 5‐23‐19 finish commissioning when heat is on line in October, found missing VFD during commissioning, 2018 working on installation.

Design Firm: Harriman Contractor: Name: Funding: DMA

Brenda Whitmore, Director Facilities Project Management Thursday, May 30, 2019 University of New Hampshire Page 17 of 30 3.1‐ SUBSTANTIAL COMPLETION 2019‐0190 SI Thompson Hall ‐ Rm G01A UNH Testing Center

Year Approved 5‐23‐19 Data activated, coordinating, computer and final camera installation, infrastructure complete, 2019 standing by for instructions from end users.

Design Firm: Contractor: External Name: Funding: SARRC ALLOC

HOUDE, DONALD A 37

1.1‐ PLAN/EST 2014‐2033 FCR Morse Hall ‐ Data Center Fire Suppression System

Year Approved 5‐23‐19 : EPO not operational as designed. Troubleshooting ongoing with Yates and Schneider. Working with 2016 data center to coordiante shutdown if required. ‐ This work is not complete. We will be checking and testing the system to confirm propper operation. I have found drawings and related POʹs. making contact with Johnson control rep. I am schedling for June.

Design Firm: SFC Engineering Contractor: FCT Name: Simplex Grinnell Funding: SARRC ALLOC

1.1‐ PLAN/EST 2018‐0190 FCR West Edge AVL Transit Signs Install

Year Approved 5‐23‐19 Waiting for the client to let us know the new Bus stops have been installed. I expect this to happen soon.

Design Firm: Contractor: Name: Funding: GRANT

1.1‐ PLAN/EST 2019‐0099 RR Murkland Hall ‐ Rooftop Mechanical Catwalks

Year Approved 5‐23‐19 I have been forwarded a proposal from Careno const. I have walked this with MM and Todd. I need 2020 to review on site with Careno, The customer is interested in additional access. I have to review the additional with the contractor.

Design Firm: Contractor: Name: Careno Funding: DMA

1.1‐ PLAN/EST 2019‐0117 FCR Parsons Hall ‐ Enhancing Fire Alarm System

Year Approved 5/23/19 : SFMO approved, notification upon loss of power after 10 minutes, message to alert and evacuate building, will play a predetermined number of repeats/ with message telling people how they will be alerted it is safe to return. 4‐01‐19 New. I spoke with Cindi, they are ready, I have to provide an updated FCR.

Project approved by SFMO 3/14, pricing from contractors, Yates/Norris‐ turned over to Don Houde for funding and construction when approved.

Design Firm: Contractor: External Name: Norris Inc. & Yates Funding: COLLEGE / DEPT ALLOC

1.1‐ PLAN/EST 2019‐0231 FCR Christensen Hall ‐ AT&T Cellular Tower Modifications

Year Approved 5‐23‐19 I have met with Maxine Leite and crew and planning work and Crane on 5‐29‐19 2019 Design Firm: Contractor: External Name: AT&T Sub Funding: COLLEGE / DEPT ALLOC

1.1‐ PLAN/EST 2019‐0253 FCR Whittemore Center ‐ Arena ‐ Replace Lights w/LEDʹs

Year Approved 5‐23‐19 project gathering information. My first presentation for a solution was over the intended budget. I need to speak with David Leach on this.

Design Firm: Contractor: Name: Funding: COLLEGE / DEPT ALLOC

Brenda Whitmore, Director Facilities Project Management Thursday, May 30, 2019 University of New Hampshire Page 18 of 30 1.1‐ PLAN/EST 2019‐0270 FCR Dimond Library ‐ Elevator Card Access

Year Approved 5‐23‐19 I have provided a cost to the customer. The customer informed me they would now like to expand the work. .

Design Firm: Housing Contractor: External Name: Stanley , Yates, Housing Funding: COLLEGE / DEPT ALLOC

1.1‐ PLAN/EST 2019‐0279 FCR Service Building ‐ Durham Fire Department Improvements

Year Approved 5‐23‐19 I have met with the customer. I have provided a funding request to the FD for engineering now they want more space. We are in review. Facilities has given up 2 work bays. I will help them make the best of this cituation.

Design Firm: McHenry Architecture Contractor: Name: Funding: COLLEGE / DEPT ALLOC

1.1‐ PLAN/EST 2019‐0318 FCR Keener Dairy Research Building ‐ Rm 127A Grinding Room Safety Improvements

Year Approved 5‐23‐19 I have a proposal for engineering and have submitted it to COLSA, no funding response.

Design Firm: Contractor: Name: Funding: COLLEGE / DEPT ALLOC

1.1‐ PLAN/EST 2019‐0350 FCR PCAC ‐ Johnson Theatre ‐ New 12V Electrical Outlet

Year Approved 5‐23‐19 Assist with permits for electrical work. Work will be done by in house liscensed technitian. Scheduled to be done today.

Design Firm: Contractor: Name: Robert Henry Funding: COLLEGE / DEPT ALLOC

1.1‐ PLAN/EST 2019‐0353 FCR Kingsbury Hall ‐ Installation of Card Access and Wireless Door Openers

Year Approved 5‐23‐19 New project, information gathering is In Progress.

Design Firm: Contractor: Name: Funding: COLLEGE / DEPT ALLOC

1.1‐ PLAN/EST 2019‐0358 FCR Campus Lot‐F ‐ Pay & Display Unit

Year Approved 5‐23‐19 New Reviewing with the custome. June work.

Design Firm: Contractor: Name: Funding: COLLEGE / DEPT ALLOC

1.1‐ PLAN/EST 2019‐0360 FCR Williamson Hall ‐ Installation of Security Cameras

Year Approved 5‐23‐19 New gathering information. I have a scheduled walk through for all parties on Friday 5‐24‐19

Design Firm: Contractor: Name: Funding: COLLEGE / DEPT ALLOC

1.1‐ PLAN/EST 2019‐0372 FCR 1 Leavitt Lane ‐ Hang 50ʹʹ Icd display

Year Approved 5‐23‐19 New I need to contact the customer.

Design Firm: Contractor: Name: Funding: COLLEGE / DEPT ALLOC

Brenda Whitmore, Director Facilities Project Management Thursday, May 30, 2019 University of New Hampshire Page 19 of 30 2‐ IN DESIGN 2016‐0277 FCR Utility Distribution ‐ Eversource Transmission Line

Year Approved 5‐23‐19 Project is under way, fences up, Working in A lot. Working on tree removal by F.H. . 2019 Design Firm: Contractor: Name: Funding: SARRC ALLOC

2‐ IN DESIGN 2019‐0063 RR Combined Heat & Power Plant ‐ Steam to HW Heat Exchanger Replacements Phase I of II

Year Approved 5‐23‐19 Eng. (Harriman) has PO. The UNH/ EMCOR team got together and listed questions, request and notes 2020 for the engineer. Harriman is working on the best design.

Design Firm: Contractor: Name: Funding: DMA

2.5‐ IN PROCUREMENT 2015‐2363 RR Field House ‐ Relocate Special Events Power

Year Approved 5‐23‐19 I have met with my assett manager, we discussed the project I received a verbal OK to proceed I will 2019 work with my BSC to find funding availability. 2020 project. Waiting for the funds to become available.

Design Firm: Contractor: Name: Funding: DMA

2.5‐ IN PROCUREMENT 2017‐0447 FCR Leavitt Cntr Transportation Center ‐ Bus Maintenance Lift Replacements

Year Approved 5‐23‐19 This project has received more funding and will go back out to bid. No new information. 2018 Design Firm: Contractor: External Name: Design build Funding: GRANT

2.5‐ IN PROCUREMENT 2019‐0001 FCR MacFarlane Greenhouse ‐ Renovation/Improvements

Year Approved 5‐23‐19 Careno was the successful DB.. Working on a final submittal from (Nexus) Greenhouse Mfr.. Will start 2018 with test pits.

Design Firm: SMRT Contractor: Name: Funding: COLLEGE / DEPT ALLOC

2.5‐ IN PROCUREMENT 2019‐0128 FCR Keener Dairy Research Building ‐ Standby Generator

Year Approved 5‐23‐19 The customer has received a request for funding. We will proceed with the project upon receipt.

Design Firm: Contractor: External Name: Yates Funding: COLLEGE / DEPT ALLOC

2.5‐ IN PROCUREMENT 2019‐0172 SI Service Building ‐ Art Dept Spray Booth

Year Approved 5/23/19: PO issued to McHenry Architecture, he has provided plans. I have had a review with the SFMO on 2019 Thursday 3‐28‐19. Project is funded, a PO was written for the contractor we expect to proceed in June.

Design Firm: McHenry Architecture Contractor: External Name: TBD Funding: SARRC ALLOC

2.5‐ IN PROCUREMENT 2019‐0282 RR Gables Buildings A, B & C ‐ Transformer Replacements

Year Approved 5‐23‐19 Gables A, B and C Transformer replacement were put into this 1 Project by my BSC. The PO has been 2019 sent to the contractor. We will schedule this work in conjunction with UNH Housing consideration. For June.

Design Firm: Contractor: Name: Funding: INST RR

Brenda Whitmore, Director Facilities Project Management Thursday, May 30, 2019 University of New Hampshire Page 20 of 30 2.5‐ IN PROCUREMENT 2019‐0302 FCR Stoke Hall ‐ Electrical Service Renovation Housing Contribution

Year Approved 5‐23‐19 2019‐0302 This project is inConstruction. Floor demo this week and interior demotition and abatement.

Design Firm: Harriman Contractor: External Name: Milestone const. Funding: COLLEGE / DEPT ALLOC

2.5‐ IN PROCUREMENT 2019‐0303 FCR Stoke Hall ‐ Electrical Service Renovation Utilities Contribution

Year Approved 5‐2‐19 2019‐0303 This project is in Construction status, AIA contract is in progress. This FCR is for the Utilities dept. protion of the funding. Waiting for bonds. To allow a PO.

Design Firm: Harriman Contractor: External Name: Milestone Funding: COLLEGE / DEPT ALLOC

3‐ IN CONSTRUCTION 2016‐0116 SI Hamilton Smith Hall ‐ Bi‐Directional Amplifier Installation

Year Approved 5/23/19: In progress, cable installed, Norris coming to do some connections. 2019 Design Firm: Norris Inc. Contractor: External Name: Norris Inc. Funding: SARRC ALLOC

3‐ IN CONSTRUCTION 2016‐0123 FCR Service Building ‐ Dispatch Center Keltron System

Year Approved 5/23/19: Norris has already built the Gregg hall node removing reverse polarity accounts from service 2018 building. Norris has nodes at Stoke, Print Mail Serivce to complete. Working with Norris to get those completed with available funding in existing plant fund. New proposals came in for Dispatch and 3 Node upgrades. Met on 3‐26‐19 about this Brian Gaon is looking into if there is any reason to persue other companies to replace Keltron. Went back out to bid. Need to get back to this project.

Design Firm: Contractor: External Name: Norris / UNH Telecom Funding: COLLEGE / DEPT ALLOC

3‐ IN CONSTRUCTION 2018‐0214 FCR Campus ‐ FY18 Electric Meter Repairs

Year Approved 5‐23‐19 Meters have been replaced in Dimond and Congreve. James hall will receive a new meter on the transformer once we get set up . This will require a shutdown. IC Reed and I am schedueling a convenient time for the customer.

Design Firm: Contractor: External Name: Yates Funding: COLLEGE / DEPT ALLOC

3‐ IN CONSTRUCTION 2018‐0312 FCR Stoke Hall ‐ High Voltage Replacement ‐ Design Only

Year Approved 5‐23‐19 This work has been awarded to Harriman as the Project engineer. We are in progress. Harriman is now in construction administration.

Design Firm: Harriman Contractor: External Name: Yates support only. Funding: COLLEGE / DEPT ALLOC

3‐ IN CONSTRUCTION 2018‐0364 RR Stoke Hall ‐ Electrical Service Renovation

Year Approved 5‐23‐19 In Construction, Milestone is the GC. Sunday we had a major electrical shutdown and re‐routed the 2020 HV wiring. Most of the floor has been cut. This is a difficult time right now. The business offices are being very cooperative.

Design Firm: Contractor: Name: Funding: DMA

Brenda Whitmore, Director Facilities Project Management Thursday, May 30, 2019 University of New Hampshire Page 21 of 30 3‐ IN CONSTRUCTION 2019‐0123 RR Utility Distribution ‐ Spaulding Pedestrian Bridge Circuit 11 Conduit Replacement

Year Approved 5‐23‐19 ICR provided a cost proposal. $47,500.00 They have a PO and are planning this work in conjunction 2020 with Spaulding/Rudman shutdown . June.

Design Firm: Contractor: External Name: IC Reed and Sons Funding: DMA

3‐ IN CONSTRUCTION 2019‐0187 FCR Combined Heat & Power Plant ‐ Power Factor Correction ‐ Design Only

Year Approved 5‐23‐19 The engineering for this project has been awarded to Waldron, they have a proposed solution. I need 2019 dept approval to spend more $.

Design Firm: Waldron E&C inc. Contractor: External Name: Unknown. Funding: COLLEGE / DEPT ALLOC

3‐ IN CONSTRUCTION 2019‐0243 FCR Utility Distribution ‐ Sub Station 1 ‐ Transformer and Circuit Realignment

Year Approved 4523‐19 This project is in construction. Phase 1 complete. Next phase will happen when the repairs to the 2019 Culvert take place. We are actively working to organize phase 2. budget is in place. Material is on order.

Design Firm: Contractor: External Name: ICR Funding: COLLEGE / DEPT ALLOC

3‐ IN CONSTRUCTION 2019‐0295 RR 6 Leavitt Lane ‐ Electrical Service Replacement

Year Approved 5‐23‐19 This project is in progress. Phase 1 just aboout complete, Phase 2 will be in July. 2020 Design Firm: Contractor: Name: Funding: INST RR

3.1‐ SUBSTANTIAL COMPLETION 2017‐0393 RR James Hall ‐ Heat Exchanger and Potable ‐ Non Potable Water Heater Replacements

Year Approved 5‐23‐19 : . . Contractor, NPI has a C/O owes me work. Close to completion. 2018 Design Firm: Harriman Associates Contractor: External Name: NPI Funding: DMA

3.1‐ SUBSTANTIAL COMPLETION 2018‐0368 RR New Hampshire Hall ‐ Rm 300ZPA Mezzanine Accessibility Modifications

Year Approved 5‐23‐19 The carpentery work is complete. Getting engineer report. Report shows deficiencies, engineer 2019 supplied correction documents. Contractor will provide an estimate to correct deficiencies.

Design Firm: Contractor: Name: Funding: DMA

3.1‐ SUBSTANTIAL COMPLETION 2019‐0024 FCR Campus ‐ District System Heat Exchanger Cleaning

Year Approved 5‐23‐19 Project is complete as requested, there is now discussion about wether we want to insulate the HE 2019 units. This may create a C/O. also some room cleanup in James.

Design Firm: Contractor: External Name: Palmer & Sicard. Funding: COLLEGE / DEPT ALLOC

3.1‐ SUBSTANTIAL COMPLETION 2019‐0124 FCR Parsons Hall ‐ Rm W118 Need a 40 amp 3 Phase knife switch box

Year Approved 5‐23‐19 The electrical work has been started, waiting on equipment to complete. Still waiting on a quote for 2019 the Nitrogen part. Waiting for equipment to connect it. . Nitrogen work has been completed.

Design Firm: Contractor: External Name: Yates Electric. Funding: COLLEGE / DEPT ALLOC

MANCINI, MATTHEW E 4

Brenda Whitmore, Director Facilities Project Management Thursday, May 30, 2019 University of New Hampshire Page 22 of 30 1.1‐ PLAN/EST 2018‐0110 FCR Hewitt Hall ‐ Rm G02 renovations

Year Approved 5/29/2019: Budget Proposal ready to be presented to Customer. 2019 Design Firm: Contractor: External Name: Careno Construction Funding: COLLEGE / DEPT ALLOC

1.1‐ PLAN/EST 2019‐0378 FCR Parsons Hall ‐ Add exhaust ventilation to flammable storage cabinets

Year Approved 5/29/2019: Preliminary meeting held 5/24/2019. Feasibility/Estimate is in progress.

Design Firm: Contractor: Name: Funding: COLLEGE / DEPT ALLOC

1.1‐ PLAN/EST 2019‐0382 FCR Kingsbury Hall ‐ W138 new door location

Year Approved 5/29/2019: Waiting on pricing from Contractor.

Design Firm: Contractor: Name: Funding: COLLEGE / DEPT ALLOC

3.1‐ SUBSTANTIAL COMPLETION 2019‐0381 FCR Rudman Hall ‐ Installation of card swip in 148

Year Approved 5/29/2019: Facilities Team met with Customer. Key lock security was determined to meet requirements. Awaiting confirmation from Lock Shop/Customer.

Design Firm: Contractor: Name: Funding: COLLEGE / DEPT ALLOC

MASON, MICHAEL F 9

1‐ ASSIGNED 2017‐0317 RR Morse Hall ‐ HVAC Evaluation and Feasibility Study

Year Approved 3/25/2019:‐ RFS has begun and expect to have a first draft in late March 2019 Design Firm: RFS Contractor: Name: Funding: DMA

1‐ ASSIGNED 2019‐0323 RR Huddleston Hall ‐ Slate Roof Repairs Rm 307 and 308

Year Approved 3/25/2019 ‐ We need to set up a meeting with the occupants and speak schedule. We are meeting with Viking 2019 on 3/29 to review the work and how it affects the building.

Design Firm: Contractor: External Name: Viking Funding: DMA

1.1‐ PLAN/EST 2018‐0310 FCR Adams Tower ‐ Verizon Wireless Antenna Upgrade

Year Approved 3/25/2019:: ‐ We are coordinating work with Verizon , it looks like they are coordinating with Viking and 2018 Stanley to begin work.

Design Firm: Contractor: External Name: Verizon Funding: COLLEGE / DEPT ALLOC

1.1‐ PLAN/EST 2018‐0337 BAR Memorial Union Building ‐ Roof Replacement Design and Planning

Year Approved 3/25/2019 ‐ No update at this time

Design Firm: ARM Contractor: External Name: Funding: COLLEGE / DEPT ALLOC

Brenda Whitmore, Director Facilities Project Management Thursday, May 30, 2019 University of New Hampshire Page 23 of 30 1.1‐ PLAN/EST 2019‐0021 FCR Adams Tower ‐ T‐Mobile Relocation of Cellular Array

Year Approved 3/25/2019‐ ‐ Waiting on T‐Mobile Coordination 2019 Design Firm: Contractor: Name: Funding: COLLEGE / DEPT ALLOC

1.1‐ PLAN/EST 2019‐0025 FCR Beech Hill Radio Tower ‐ Sprint Cellular Modifications

Year Approved 3/25/2019:‐ Waiting on Sprint to move forward

Design Firm: Contractor: Name: Funding: COLLEGE / DEPT ALLOC

1.1‐ PLAN/EST 2019‐0316 RR Rudman Hall ‐ Building Steam Assessment

Year Approved 3/25/2019 ‐ No update at this time 2019 Design Firm: Contractor: Name: Funding: INST RR

3.6‐ WEATHER RESTRICTION 2018‐0098 RR Pettee Hall ‐ Slate Roof Repairs

Year Approved Emergency Repair 3/25/2019: Repairs remain will perform when weather permits. Once we identify scope we will procure a 2018 contractor

Design Firm: Contractor: External Name: Funding: INST RR

3.6‐ WEATHER RESTRICTION 2018‐0099 RR James Hall ‐ Slate Roof Repairs

Year Approved Emergency Repair 3/25/2019:: Drone flight identified additional issues, work to be complete during better weather, when exact 2018 scope can be identified.

Design Firm: Contractor: External Name: Funding: INST RR

RINES, DANIEL M 32

1.1‐ PLAN/EST 2017‐0031 RR FY20 Road Repairs and Crack Sealing

Year Approved 5‐23‐19 : looking at repairs on Waterworks and Gables Way. 2020 Design Firm: Contractor: Name: Funding: INST RR

1.1‐ PLAN/EST 2018‐0031 SI Train Station & Dairy Bar ‐ Transit Facility Improvements ‐ UNH ‐ Durham Rail Station

Year Approved 5‐24‐19: FTA has awarded funds.

Design Firm: Contractor: Name: Funding: GRANT

1.1‐ PLAN/EST 2019‐0355 RR Field House ‐ G00CRB Concrete Spalling Investigation and Repair

Year Approved 5‐29‐19: Waiting for Proposal back from Engineers.

Design Firm: Contractor: Name: Funding: DMA

Brenda Whitmore, Director Facilities Project Management Thursday, May 30, 2019 University of New Hampshire Page 24 of 30 2‐ IN DESIGN 2016‐0177 RR Utility Distribution ‐ McDaniel Drive STSL ‐ CRL Piping Replacements HVT086 to Handler Hall Design Only

Year Approved 5‐24‐19: Harriman working on SD. CDʹs due early fall. 2020 Design Firm: Harriman Associates Contractor: Name: Funding: DMA

2‐ IN DESIGN 2017‐0384 SI Campus ‐ Main Street South Sidewalk

Year Approved 5‐24‐19: Engineering report approved by NHDOT, project is in Preliminary design, waiting on IB investigation 2018 report.

Design Firm: CMA Engineering Contractor: Name: Funding: GRANT

2‐ IN DESIGN 2018‐0297 FCR Field House ‐ West Parking Lot Repaving

Year Approved 5‐29‐19: 2019 Tighe and Bond Working on SD. Full project has been deffered due to other projects in the area. Patching efforts may take place this summer.

Design Firm: Tighe & Bond Contractor: Name: Funding: COLLEGE / DEPT ALLOC

2‐ IN DESIGN 2018‐0345 SI Campus ‐ Hewitt‐Telecom‐Rudman Study

Year Approved 5‐24‐19: 2019 Study is underway with Campus Planning and Tighe and Bond Engineering.

Design Firm: Tighe and Bond Contractor: Name: Funding: COLLEGE / DEPT ALLOC

2‐ IN DESIGN 2019‐0336 FCR Woodman Horticultural Barn ‐ Repair

Year Approved 5‐24‐19: Hoyle Tanner is working on design. 2019 Design Firm: Hoyle Tanner Contractor: Name: Funding: COLLEGE / DEPT ALLOC

2.5‐ IN PROCUREMENT 2019‐0338 RR Hewitt Hall ‐ Duel Temperature Mechanical Tie‐In

Year Approved 5‐24‐19: Project is still out to bid 2020 Design Firm: Harriman Contractor: External Name: Funding: DMA

3‐ IN CONSTRUCTION 2011‐0674 RR Memorial Union Building ‐ Entrance Driveway Reconstruction

Year Approved 5‐24‐19: 2020 Project work to begin 6‐3‐19. Reported with 2019‐0173.

Design Firm: Hoyle Tanner Contractor: External Name: JTI Site Development. Funding: DMA

3‐ IN CONSTRUCTION 2014‐1746 RR Road Reconstruction ‐ OʹKane Road

Year Approved 5‐24‐19: Drainage work is complete, Awaiting Continental Paving this summer. 2020 Design Firm: Tighe &Bond Contractor: External Name: Continental Paving/ JTI Site Funding: DMA Development

Brenda Whitmore, Director Facilities Project Management Thursday, May 30, 2019 University of New Hampshire Page 25 of 30 3‐ IN CONSTRUCTION 2016‐0536 RR Utility Distribution ‐ Library Way Tunnel Reconstruction

Year Approved 5‐24‐19: 2020 Project is underway.

Design Firm: Harriman Contractor: Name: Funding: DMA

3‐ IN CONSTRUCTION 2017‐0028 RR FY20 Sidewalk and Walkway Repairs

Year Approved 5‐24‐19: Pm and Asset Management have identified repair areas, work will commenece throughout the 2020 summer.

Design Firm: Contractor: External Name: Funding: INST RR

3‐ IN CONSTRUCTION 2017‐0029 RR FY20 Site Stair Repairs

Year Approved 5‐24‐19: 2020 SEE # 2017‐0028 FOR UPDATES

Design Firm: Contractor: Name: Top Quality Funding: INST RR

3‐ IN CONSTRUCTION 2017‐0318 FCR Paul Creative Arts Center ‐ Bratton Recital Hall Improved Access

Year Approved 5‐24‐19 2018 Work is underway.

Design Firm: Tighe & Bond Contractor: External Name: Charters Brothers Funding: COLLEGE / DEPT ALLOC

3‐ IN CONSTRUCTION 2017‐0390 RR Campus ‐ Wildcatessen Courtyard Reconstruction

Year Approved 5‐24‐19: Project is scheduled to start in July due to other projects in the area. 2020 Design Firm: Hoyle Tanner Contractor: External Name: T&S Funding: DMA

3‐ IN CONSTRUCTION 2018‐0080 RR Kingsbury Hall ‐ Building Envelope Repairs North Wall

Year Approved 5‐24‐19: 2020 Work to take place during the month of June.

Design Firm: BEA Contractor: External Name: Careno Funding: DMA

3‐ IN CONSTRUCTION 2019‐0015 BAR Campus ‐ Parking Lot E1 ‐ Repaving

Year Approved 5‐24‐19: Project has been awarded to Advanced Paving and Excavting, project is scheduled to begin 7‐1‐19, 2019 due to orientation.

Design Firm: Tighe & Bond Contractor: External Name: Advanced Paving & Funding: COLLEGE / DEPT Excavating ALLOC

3‐ IN CONSTRUCTION 2019‐0053 FCR Forest Park ‐ Decommissioning and Demolition

Year Approved 5‐24‐19: 2019 Project start date of 6‐3‐19 with full effort to begin 6‐30‐19 after leases are up.

Design Firm: Harriman Contractor: External Name: AQE Funding: COLLEGE / DEPT ALLOC

Brenda Whitmore, Director Facilities Project Management Thursday, May 30, 2019 University of New Hampshire Page 26 of 30 3‐ IN CONSTRUCTION 2019‐0138 RR Utility Distribution ‐ Replace Condensate Line from Mills Hall to Fairchild

Year Approved 5‐24‐19 2020 Project to begin week of 6‐17‐19

Design Firm: Harriman Contractor: External Name: Anderson Welding Funding: DMA

3‐ IN CONSTRUCTION 2019‐0246 FCR Memorial Union Building ‐ Landing Repair/ Strafford Room Exterior Egress

Year Approved 5‐24‐19: PO is out work to begin after June orientation. (7‐1‐19) 2019 Design Firm: Hoyle Tanner Contractor: External Name: Charter Brothers Funding: COLLEGE / DEPT ALLOC

3‐ IN CONSTRUCTION 2019‐0329 FCR Utility Infrastructure ‐ Main Street Catch Basin Replacements

Year Approved 5‐24‐19: 2019 Catch basins will be replaced week of 5‐27‐19

Design Firm: Contractor: External Name: Gagnon Construction Funding: COLLEGE / DEPT ALLOC

3‐ IN CONSTRUCTION 2019‐0330 FCR Main Street ‐ Repaving

Year Approved 5‐24‐19: 2019 Work to begin in the next week or so. Continental to begin Milling roughly the week of 6‐10‐19

Design Firm: Contractor: External Name: Continental Paving Funding: COLLEGE / DEPT ALLOC

3‐ IN CONSTRUCTION 2019‐0333 RR Wolff House ‐ Foundation Repointing and Repairs

Year Approved 5‐24‐19: PO is out, work is scheduled for June off hours per occupant request. 2019 Design Firm: Contractor: External Name: Propoint Funding: DMA

3‐ IN CONSTRUCTION 2019‐0346 RR Campus ‐ Main Street and Edgewood Crosswalk Replacements

Year Approved 5‐24‐19: Work is underway, to be completed before Main Street Paving. 2019 Design Firm: Contractor: External Name: Gagnon Construction Funding: DMA

3.1‐ SUBSTANTIAL COMPLETION 2009‐0078 SI Memorial Union Building ‐ Driveway and Sidewalk ‐ Design Only

Year Approved 5‐24‐19: 2018 CA services provided under the contract. Please see project 2011‐0647 for Construction project updates. Project will be closed out after CA services final invoice is received.

Design Firm: Hoyle Tanner Contractor: Name: Funding: SARRC ALLOC

3.1‐ SUBSTANTIAL COMPLETION 2013‐1176 CP ‐ Expansion & Renovations

Year Approved 5‐24‐19: few punchlist items remain then project will be closed out. 2013 Design Firm: HGA Contractor: FCT Name: Shawmut Funding: COLLEGE / DEPT ALLOC

Brenda Whitmore, Director Facilities Project Management Thursday, May 30, 2019 University of New Hampshire Page 27 of 30 3.1‐ SUBSTANTIAL COMPLETION 2014‐2059 CP Outdoor Pool ‐ Reconstruction of Outdoor Pool Facility

Year Approved 5‐24‐19: Waiting on final invoicing before closing out. 2014 Design Firm: Contractor: External Name: Careno Funding: SARRC ALLOC

3.1‐ SUBSTANTIAL COMPLETION 2017‐0005 RR Utility Distribution ‐ Library Way Dual Temp Lines and Tunnel Replacement Design

Year Approved 5‐24‐19: Please see Project # 2016‐0536 for construction updates. 2017 Design Firm: Harriman Contractor: Name: Funding: DMA

3.1‐ SUBSTANTIAL COMPLETION 2017‐0394 RR Whittemore Center ‐ Arena ‐ Engineering Evaluation for Exterior Concrete and Interior Slab

Year Approved 5‐24‐19: 2018 Project is ready for closeout.

Design Firm: SGH Contractor: External Name: Charters Brothers Funding: DMA

3.1‐ SUBSTANTIAL COMPLETION 2018‐0159 RR Childhood Study & Development Center ‐ Roof Repair and Misc Repairs

Year Approved 5/24/2019: Final punchlist work then closeout. 2018 Design Firm: SMRT Contractor: External Name: Careno Funding: DMA

3.6‐ WEATHER RESTRICTION 2019‐0194 RR Childhood Study & Development Center ‐ Replace Mental Siding and Add Awnings at Rear of Complex

Year Approved 5/24/2019: ‐ final punch list and site restoration before closeout. 2019 Design Firm: Contractor: Name: Careno Funding: DMA

ROULEAU, RICHARD A 12

1.1‐ PLAN/EST 2019‐0291 SI Spaulding Hall ‐ Rms G07 & G11 Phase 1 Make‐Ready Work

Year Approved 5/30/19 ‐Phase I Make Ready work complete.

Design Firm: Ellenzweig / Accentech Contractor: Name: Funding: SARRC ALLOC

1.1‐ PLAN/EST 2019‐0331 RR Paul College ‐ Roof Membrane and Flashing Investigation ‐ Corrective Plan/Design

Year Approved 5/30/19 ‐ No action taken. Intent is to (1) give PC Construction a heads‐up about the problem and (2) bring in 2019 ARM for a study and report. Thereafter, we will determine whether we will go after the roof warranty and/or PC and the roofer. No action taken.

Design Firm: Contractor: Name: Funding: DMA

1.1‐ PLAN/EST 2019‐0337 FCR Holloway Commons ‐ Main Entrance Door Repairs/Investigation

Year Approved 5/30/19 ‐ No Action taken R. Rouleau has been asked to bring in the design and construction teams to review and evaluate. Pending.

Design Firm: Contractor: Name: Funding: COLLEGE / DEPT ALLOC

Brenda Whitmore, Director Facilities Project Management Thursday, May 30, 2019 University of New Hampshire Page 28 of 30 2‐ IN DESIGN 2016‐0278 CP Spaulding Hall ‐ Expansion & Renovations ‐ Biological Science Initiative

Year Approved 5/30/19 ‐ Phase I Make Ready work underway for utility relocations needed for new addition. Work 2016 scheduled to be complete 8/19 and ready for New addition Site work early Fall.

Design Firm: Ellenzweig Contractor: External Name: Skanska USA Building Funding: SARRC ALLOC

3‐ IN CONSTRUCTION 2018‐0210 FCR UNH Manchester ‐ 88 Commercial Street ‐ Bio‐Manufacturing Innovation Center Tenant fit‐out

Year Approved 5/30/19: Construction continues. Lab casework contract awarded and P.O. issued. P.O. for furniture has been issued. Working with customer for equipment orders. The intent is to be substantially complete the project and ready for occupancy by August 2019.

Design Firm: John Jordan Contractor: External Name: by landlord (using Funding: COLLEGE / DEPT Milestone) ALLOC

3‐ IN CONSTRUCTION 2018‐0336 FCR Coastal Marine Lab ‐ Fire Clean‐Up and Repairs

Year Approved 5/30/19‐ No current update. Work is complete except fire‐related window repairs. UNH PM Rouleau assemble roofing package for bidding and line up window repairs.

Design Firm: Contractor: External Name: Careno Construction Funding: COLLEGE / DEPT ALLOC

3.1‐ SUBSTANTIAL COMPLETION 2018‐0117 FCR Stoke Hall ‐ Elevator upgrade

Year Approved 5/30/19: No update. Final invoice received. Payment is pending verification that a few cab upgrade punchlist 2018 items were addressed.

Design Firm: Elevator Consulting Assoc. Contractor: External Name: Careno Construction Funding: COLLEGE / DEPT ALLOC

3.5‐ WARRANTY REPAIRS 2014‐1657 CP Holloway Commons ‐ Expansion Project

Year Approved 5/30/19: No current update. There remain just a few project items that need to be resolved including ongoing 2014 problems with the main entry door during high wind conditions (see project #2019‐0337).

Design Firm: Miller Dyer Spears Contractor: External Name: North Branch Construction Funding: HEFA / COLLEGE / DEPT ALLOC

3.5‐ WARRANTY REPAIRS 2012‐1851 SI Hamilton Smith Hall ‐ Major Renovation Project

Year Approved 5/30/19: Some Skanska warranty work remains. A few furniture warranty items remain open. Skanska 2013 working on a schedule and final punchlist items.

Design Firm: DiMella Shaffer Associates Contractor: External Name: Skanska USA, Inc. Funding: SARRC ALLOC

3.5‐ WARRANTY REPAIRS 2018‐0092 SI 9 Madbury Road ‐ Lease Space Office Fit Up

Year Approved 5/2/2019: Complete. Ready for financial closeout. 2018 Design Firm: Harriman Contractor: External Name: Milestone, Denron, Funding: SARRC ALLOC Martineau, Sprague, Envirovantage

Brenda Whitmore, Director Facilities Project Management Thursday, May 30, 2019 University of New Hampshire Page 29 of 30 3.5‐ WARRANTY REPAIRS 2017‐0472 FCR 10 Pettee Brook Lane ‐ Renovations to Space

Year Approved 5/30/19: Complete. Ready for financial closeout. 2018 Design Firm: Manypenny Murphy Contractor: External Name: Landlord Funding: COLLEGE / DEPT Architecture ALLOC

3.5‐ WARRANTY REPAIRS 2018‐0249 RR Paul Creative Arts Center ‐ New Main Domestic Hot Water System Installation

Year Approved 5/30/19: Complete pending equipment list update and O&M upload. 2019 Design Firm: Harriman Associates Contractor: External Name: Charters Bros. Funding: DMA

WEBBER, TODD M 3

2.5‐ IN PROCUREMENT 2019‐0356 RR Paul Creative Arts Center ‐ Indoor Air Quality Assessment

Year Approved 5‐14‐19‐ IAQ testing took place May 7 ‐ 8 and will be back for additional HVAC testing May 16 ‐ 17. 2019 Design Firm: Contractor: External Name: TRC Companies Funding: DMA

2.5‐ IN PROCUREMENT 2019‐0373 RR Paul Creative Arts Center ‐ Museum Track Lighting and Receptacles

Year Approved 5/28/19 ‐ PO released, working with contractor on scheduling 2019 Design Firm: Contractor: External Name: Scarponi Electric Funding: DMA

2.5‐ IN PROCUREMENT 2019‐0377 FCR Paul Creative Arts Center ‐ Additional Museum Track Lighting and Dimmer Controls

Year Approved 5/28/2019 ‐ Updates will be reported on 2019‐0373 2019 Design Firm: Contractor: External Name: Scarponi Electric Funding: COLLEGE / DEPT ALLOC

Brenda Whitmore, Director Facilities Project Management Thursday, May 30, 2019 University of New Hampshire Page 30 of 30