Social Monitoring Report

Semi Annual Social Monitoring Report

July to December 2020

Project Number: 44219-014 Loan/ Grant Number: 3139/0397 (NEP) March 2021

Nepal: South Asia Subregional Economic Cooperation Power System Enhancement Project

Prepared by the Electricity Authority (NEA) for Asian Development Bank.

This Social Monitoring Report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature.

In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

8th Semiannual Social Monitoring Report July-December 2020

ACRONYMS AND ABBREVIATIONS

ADB Asian Development Bank AP Angle Point APs Affected Peoples CDC Compensation Determination Committee CDO Chief District Officer CF Community Forest CFUGs Community Forest User Groups CSR Corporate Social Responsibility CTEVT Council for Technical Education and Vocational Training DKTLP Dana- 220kV Transmission Line Project EIB European Investment Bank EM Entitlement Matrix ESMU Environmental and Social Management Unit ESSD Environment and Social Studies Department GoN Government of Nepal GRC Grievance Redress Committee ha hectare HH Household IEE Initial Environmental Examination IP Indigenous People IPP Indigenous People’s Plan IR Involuntary Resettlement KNBTLP Kushma-New Butwal 220kV Transmission Line Project kV kilovolt LCF Local Consultative Forum LF Leasehold Forest MKTLP Marsyangdi-Kathmandu 220kV Transmission Line Project NEA Nepal Electricity Authority PAF Project Affected Family PAP Project Affected People PCP Public Communication Policy, 2011 PMD Project Management Directorate PSC Project Supervision Consultant

i

8th Semiannual Social Monitoring Report July-December 2020 PCC Plain Cement Concrete RAP Resettlement Action Plan RIPP Resettlement and Indigenous People’s Plan RM Rural Municipality RP Resettlement Plan RoW Right of Way SASEC South Asia Sub-Regional Economic Cooperation SPS Safeguard Policy Statement TL Transmission Line UMBTLP Udipur-Markichowk-Bharatpur 220kV Transmission Line Project VDC Village Development Committee

ii

8th Semiannual Social Monitoring Report July-December 2020 TABLE OF CONTENTS

1. THE PROJECT DETAILS ...... 1 1.1 Background of the project ...... 1 1.2 Physical Progress of the Project Activities ...... 2 1.3 Reporting Period ...... 4 1.4 Monitoring Requirements and Frequency of Submission ...... 4 1.5 Scope of Semiannual Monitoring Report ...... 5 2. CHANGES IN PROJECT SCOPE AND ADJUSTED SAFEGUARD MEASURES ...... 5 3. QUALITATIVE AND QUANTITATIVE DATA ...... 5 4. MONITORING PARAMETERS/INDICATORS AND METHODS ...... 6 5. SEMIANNUAL MONITORING RESULTS ...... 6 5.1 Documentation and Approval ...... 6 5.2 Land Acquisition and Compensation Distribution ...... 6 5.2.2 Compensation for Acquired Land ...... 9 5.2.3 Compensation Distribution for Structure Loss ...... 14 5.2.4 Compensation Distribution for Crop, Tree and Grass Loss ...... 15 5.2.5 Compensation Distribution for Fruits Loss...... 18 5.2.6 Progress on Assistance to Vulnerable Households...... 20 5.2.7 Additional Assistant to the PAFs ...... 23 5.2.8 Major Issues associated with Land Acquisition and Compensation ...... 23 5.2.9 Safeguard Implementation Progress ...... 24 5.2.10 Livelihood Restoration Program ...... 25 5.2.10.1 Effectiveness of Trainings ...... 26 5.2.11 Impact on Indigenous People (IPs)...... 28 5.3 Monitoring Results compared against IR and IPs Safeguards ...... 33 6. GRIEVANCE REDRESSAL MECHANISM ...... 43 7. PUBLIC CONSULTATION AND PARTICIPATION AND INFORMATION DISCLOSURE ...... 43 8. CORRECTIVE ACTIONS FOR NON-COMPLIANCE AND MAJOR GAPS ...... 45 9. RECOMMENDATION FOR MONITORING ADJUSTMENT ...... 45 10. INSTITUTIONAL ARRANGEMENT FOR MONITORING ...... 45 10.1 Central Level Arrangement ...... 45 10.1.1 Environment and Social Studies Department (ESSD)...... 45 10.1.2 Central Level Line Agencies ...... 45 10.2 Project Level Arrangement ...... 46 10.2.1 Project Management Directorate, NEA (PMD Office)...... 46 10.2.2 Project Manager...... 46 10.2.3. Environment and Social Monitoring Unit (ESMU)...... 46 10.2.4 Project Supervision Consultant (PSC) ...... 46 10.2.5 Compensation Determination Committee ...... 47 10.2.6 Construction Contractor ...... 47

iii

8th Semiannual Social Monitoring Report July-December 2020

11. PROPOSED MAJOR ITEM OF FOCUS FOR NEXT REPORT ...... 48

LIST OF TABLES Table 1: Physical Progress of the sub-projects ...... 2 Table 2: Scope of Semiannual Monitoring Report ...... 5 Table 3: Details of Land Acquisition ...... 7 Table 4: Rate fixation for Land Acquisition ...... 8 Table 5: Compensation Distribution Status ...... 11 Table 6: Compensation Distribution Status for Structure loss ...... 15 Table 7: Compensation Distribution Status for Crop loss ...... 17 Table 8: Compensation Distribution Status for Tree loss and Fodder loss ...... 18 Table 9: Compensation Distribution Status for Fruit loss ...... 20 Table 10: Affected vulnerable HHs in DKTLP ...... 21 Table 11: Affected vulnerable HHs in MKTLP ...... 21 Table 12: Affected vulnerable HHs in KNBTLP ...... 22 Table 13: Major issues associated with land acquisition and compensation in project sites 23 Table 14: Status of Safeguard implementation progress ...... 24 Table 15: Implementation Status Livelihood Restoration Program in SASEC TL Projects ... 26 Table 16: Implementation Status of Skill Development Training ...... 27 Table 17: Implementation other General Training ...... 27 Table 18: Resettlement Impact and Impacts on IPs ...... 29 Table 19: Compliance Monitoring Results in terms of Involuntary Resettlement Safeguards ...... 34 Table 20: Monitoring Results in terms of Indigenous Peoples Safeguards ...... 40 Table 21: Summary of the Grievances registered and GRC meetings ...... 43 Table 22: Summary of Public Consultation Meetings ...... 44 Table 23: Corrective actions for non-compliance ...... 45 Table 24: Proposed Major items of focus for the Next Report ...... 48 LIST OF ANNEXURES Annexure 1: Tower Foundation and Tower Erection Details Annexure 2: Status of Compliance and loan Covenants Annexure 3: Acquired Additional Land Annexure 4: Grievance Redress Committee Meeting Matrix Annexure 5: Letter related to Recorded Grievances Annexure 6: Public Consultation Matrix Annexure 7: Participants List of the training Annexure 8: Photographs

iv

8th Semiannual Social Monitoring Report July-December, 2020 1. THE PROJECT DETAILS 1.1 Background of the project Asian Development Bank (ADB) approved the South Asia Sub-Regional Economic Cooperation (SASEC) Power System Expansion Project on July 4, 2011 and signed the loan/grant/project agreement with the Government of Nepal (GoN) on July 11, 2014. Nepal Electricity Authority (NEA) has received financial assistance from the ADB with co-financing from Norway and loan from European Investment Bank (EIB) for Implementation of above project. However, the safeguard implementation and monitoring cost shall be borne by NEA.

The project will contribute to Nepal’s energy development objectives by (i) scaling up the ongrid and off-grid renewable energy supply, (ii) facilitating cross-border power exchange, (iii) increasing access to renewable energy in rural areas, (iv) building capacity for on-grid and offgrid power sector development, and (v) utility scale solar photovoltaic project development. The project targets the strengthening and expansion of transmission and distribution systems that will enable Nepal to further benefit from power trading and development of its abundant hydropower resources. Transmission network strengthening and expansion, in conjunction with current hydropower generation development, is a precondition to reducing load shedding and increased cross border electricity trade. The transmission line corridors and distribution system expansion project are listed below: 1. Kali Gandaki Corridor: • Dana – Kushma 220kV transmission line (length: 38.85km). • Kushma – New Butwal 220kV transmission line (length: 88km) • New Butwal – Bardaghat 220kV transmission line (length:21km) • Construction of grid substations: 100MVA (33.33MVA X 3 single phase unit), 220kV/132kV at each of Dana and Kushma substation and 25MVA, three phase, 132kV/33kV at Dana and 100MVA, 3 phase, 220kV/132kV at New Butwal along Kali Gandaki Corridor. However, alignment survey, tree counting works are in progress, GRC has been formed and public consultation ongoing regularly. 2. Marsyangdi Corridor: • Udipur–Markichowk–Bharatpur 220kV transmission line (length: 64.45 km), and substation at Khudi, switchyard at Udipur, Markichowk substation, and bay extension at Bharatpur • Manang–Khudi–Udipur 220kV transmission line (length:45km), and associated substations at Manang and bay extension at Khudi In Manang-Khudi-Udipur 220kV transmission detail survey has been completed however due to the undesirable demand of the locals, check survey is being halted (the project is taking initiation to resolve the problem of hinder activities of transmission line conducting the direct consultations with locals and affected along with local authorities) 3. Marsyangdi to Kathmandu:

• Marki Chowk – Matatirtha 220kV transmission line, and associated bay extension at Matatirtha (length: 82km) • Construction of 480MVA, 220kV/132kV grid substations along Marsyangdi– Kathmandu route

SASEC-PSEP 1 NEA-ESSD 8th Semiannual Social Monitoring Report July-December, 2020 4. Power distribution network improved: Construction and or Upgrading of 410km of 33kV, 545km of 11kV and 725km of 400V distribution lines, 216MVA, 33/11kV Substations, and 20MVA distribution substations in The East, Central and West regions. • Lot 1: Distribution System expansion in eastern and central Nepal • Lot 2: Distribution System expansion in western Nepal • Lot 3: Up-gradation of distribution networks. 1.2 Physical Progress of the Project Activities Consultant has deployed Social Safeguard Officers in each subproject under the authorization of Environment and Social Studies Department, NEA. The officers have collected the necessary information and data by consulting senior technical officials, representatives of the district, local authorized persons, affected people, contractors and locals to prepare this progress report. In this reporting period the progress has not been achieved so far as targeted due to the influence of COVID-19 pandemic throughout the nation as well as the whole world. The work has been carried out partially due to the lockdown enforced by the government of Nepal. Nevertheless, the progress made by the subprojects in the semiannual reporting period of July to December, 2020 has been summarized below in Table 1 and Tower Foundation and Tower Erection details has been attached in Annexure 1. Table 1: Physical Progress of the sub-projects

SN Sub-Projects Status of Project Activities Kali Gandaki Corridor: 1 Dana– Khurkot (Kushma) Substation and Access Road Kushma • All equipment testing work ongoing 220kV Transmission Dana Substation Line and • Equipmant Testing work ongoing substations at Tower Footing (Angle Points) Dana and • In DKTLP, total 110 tower foundation and 110 tower erections have been Kushma completed. Total 38.94 Kilometer of stringingwork has been completed till this reporting period. • In , 56 tower foundationsand 56 tower erections have been completed. • In Myagdi District, 54 tower foundations and 54 tower erections have been completed. • Details of tower foundation have been attached in Annexure 1. 2 Kushma– New New Butwal (Badera) Substation Butwal 132 and 220kv switch yard erection and stringing work completed 220kVTL Cable trench work is in progress B type building plastering work under progress C-type building 2nd floor concreeting work has been finished and wall plastering work under progress D-type building construction work is ongoing. Water tank construction work is in process. Street light pole erection work under progress. Boundary wall work & fencing is in progress. Main gate work is in progress. Few labors (60) are currently working insubstation regularly. Tower Footing (Angle Points) • In KNBTLP, total 106 tower foundation and 69 tower erections have been completed and 6 tower foundations & 4 tower erections are in progress till this reporting period.

SASEC-PSEP 2 NEA-ESSD 8th Semiannual Social Monitoring Report July-December, 2020

SN Sub-Projects Status of Project Activities • In , total 41 tower foundation and 20 tower erection works have been completed. • 2 tower foundation works are ongoing and 1 has been stopped. Likewise, 2 tower erection works are ongoing. • In Syangja district, total 16 tower foundation works have been completed and 4 tower erection works have been completed. 5 tower foundation works are under progress till this reporting period. • In Parbat district, total 49 tower foundation and 45 tower erections work have been completed till this reporting period. • Details of tower foundation & erection work have been attached in Annexure 1. New Butwal – Bardaghat 220kVtransmission line (length:21km) 3 New Butwal – New Butwal – Bardaghat 220kVTransmission line (length: 21km) effective from Bardaghat 23rd June 2020. 220kVtransmis The contractor M/S POWER CHINA SEPCO1 Electrical Power Construction sion line Company Limited, China has just finished detail survey but report has not been (length:21km) approved by NEA. Check survey and cadastral survey has been planned before the approval. Marsyangdi–Kathmandu 220kV transmission line and substations at Matatirtha and Markichowk 4 Marsyangdi Matatirtha Substation Kathmandu • Construction of sharewall is in final stage at transformer installation site 220kV • Construction of column work is in progress at Gantry point. Transmission • Construction work of control building up to foundation beam has been Line and completed. substations at • Construction work of B- type building has been completed upto plinth level Matatirtha and and rebar work above plinth level is in progress. Markichowk • Construction work of plinth beam is in progress of C- type building. • PCC work has been completed at water tank site. • Construction of drainage system is in progress. Markichowk Substation • Total 10 gantry tower foundation footing has been completed for 220 kV • Total 6 gantry tower foundation footing has been completed for 132 kV • First floor slab of C type building is completed and column above slab is completed and 2nd beam and slab formation and rebar work are in progress. • First-floor slab of D type building completed. • First floor slab of transit camp building is completed and column above slab is completed and 2nd beam and slab formation and rebar work are in progress. • All main block of transformer completed. • 1st beam of 5 no. of transformer firewall is completed. • Column up to FGL of firewall is completed. • 28 number of 220kV Equipment foundation PCC work completed among which 21 number of 220kV Equipment foundation’s footing is completed. (Note*: The progress activities of Matatirtha substation is same as mentioned in December 2019. No additional work progress has been achieved so far in this reporting period as the contractor has left the work since December 2019.)

**MKTLP Project Manager Office has published a bid invitation notice on 23 June 2020 for the Design, Supply, and Installation and Commissioning of 220 kV Air insulated Substation (AIS) in Matatirtha, Kathmandu and 220kV Gas Insulated Substation (GIS) in Markichowk, Marsyangdi. PMO office is in process to make an agremment with contractor for the implementation remaining work of substation. Tower Footing (Angle Points)

SASEC-PSEP 3 NEA-ESSD 8th Semiannual Social Monitoring Report July-December, 2020

SN Sub-Projects Status of Project Activities • In MKTLP, total 229 tower foundations have been completed and 228 tower erection works have been completed till this reporting period. Total 76.9 km of stringing work has been completed till this reporting period. • In Dhading District, 141 tower foundation and 141 tower erections have been completed. Stringing work has been completed in 49.6 km span till this reporting period. • In Chitwan District, 29 tower foundations and 29 tower erections have been completed. Total 9.64km stringing work has been completed in Chitwan. • In Gorkha District, 51 tower foundation and 50tower erection have been completed. Total 16km stringing work has been completed in Gorkha. • In Tanahun District, 4 tower foundations and 4 tower erections have been completed. Total 900m stringing work has been completed in Tanahun • In Kathmandu District, 4 tower foundationand 4tower erections have been completed. Stringing work has been completed in 1.69km span The details have been attached in Annexure 1.

**MKTLP Project Manager Office has published a bid invitation notice on 18 June 2020 for construction work of stone masonry and gabion retaining wall for the protection of tower NEA-PMD-MKTLP. Marsyangdi Corridor 5 Udipur- Udipur substation Markichowk- • L & T company ltd. Is working as a contractor for the substation. Bharatpur • Construction of labour Camp is in progress. 220kV TL) • Boundary wall work is in progress • Grading work is ongoing. • Water tank construction work is in process Bharatpur substation • L & T company ltd. Is working as a contractor for the substation. • Soil test work has been completed. Tower Footing (Angle Points) • In UMBTLP, 24 tower foundation works has been completed at and 6tower foundation works are in progressin Lamgung district and 1 tower foundation is in progress in Tanahun district in this reporting period. The details have been attached in Annexure 1.

1.3 Reporting Period The reporting period of this Semiannual Social Monitoring Report covers the activities conducted during the period of July to December 2020. In this reporting period the progress has not been achieved so far as targeted due to the influence of COVID-19 pandemic throughout the nation as well as the whole world. The work has been carried out partially due to the lockdown enforced by the government of Nepal.

1.4 Monitoring Requirements and Frequency of Submission As per the reporting guidelines, this Semiannual Social Safeguard Monitoring Report has been prepared and submitted to PMD/NEA, NEA in compliance with the ADB requirements. This Semiannual social monitoring report has been prepared in compliance with the ADB requirements covering period of July to December 2020. It has been prepared by the review of approved documents, field information and public consultation with stakeholders, affected persons, and the relevant project staffs.

SASEC-PSEP 4 NEA-ESSD 8th Semiannual Social Monitoring Report July-December, 2020 1.5 Scope of Semiannual Monitoring Report This Semiannual monitoring report covers all the information on execution of different subprojects/components including land acquisition and RIPP implementation activities and also ensures safeguard provisions and compliance verification as applicable. The main scope of this semiannual report includes the following project components detailed in Table 2. PSC is responsible for monitoring and supervision of NEA components only and therefore, the projects under NEA components only has been considered/ reported in this report.

The distribution system augmentation and expansion project cover 25 distribution substations in different districts of Eastern, Central and Western parts of Nepal. The total land acquired for the construction of distribution substations is 129761.81sq.m. There are in total 39 APs, among which 5 are IPs, 3 Dalits and 14 are women. Altogether compensation of NPR.156,863,554 have been distributed to landowners for the distribution system augmentation and expansion project in all substations. There are no land issues for the all- distribution substations. Table 2: Scope of Semiannual Monitoring Report

S. N Sub–Project Components 1 Dana–Kushma 220kV transmission line and associated substations under Kali Gandaki Corridor 2 Kushma–New Butwal 220kV transmission line and associated substations under Kali Gandaki Corridor 3 Marsyangdi–Kathmandu 220kV transmission line and associated substations 4 Udipur-Markichowk-Bhartpur 220kV transmission line and associated substation under Marsyangdi Corridor 5 Power distribution network improved • Lot-1: Distribution System expansion in eastern and central Nepal • Lot-2: Distribution System expansion in western Nepal • Lot-3: Up-gradation of distribution networks

2. CHANGES IN PROJECT SCOPE AND ADJUSTED SAFEGUARD MEASURES According to ADB SPS 2009, the Project is categorized as “A” for involuntary resettlement and “B” for indigenous peoples. The project scope is same as approved. The combined updated RIPP is being prepared for DKTLP and MKTLP.

3. QUALITATIVE AND QUANTITATIVE DATA This social monitoring report collected data utilizing both quantitative and qualitative tools and techniques to draw inference related to safeguard issues and implementation. The quantitative data are collected to measure the status and change of a specific variable which are quantifiable such as affected households, acquired land, compensation distribution status, total structure loss, total crop loss etc.

The qualitative data are also collected in order to identify the issues as well as get detailed information during the implementation process through observation, open-ended interviews, meaningful consultation meetings, GRC meetings, discussions, formal meetings with project staffs, project affected families, local communities, and other stakeholders etc.

SASEC-PSEP 5 NEA-ESSD 8th Semiannual Social Monitoring Report July-December, 2020 4. MONITORING PARAMETERS/INDICATORS AND METHODS The consultant has deployed social safeguard officers in each subproject under the authorization of Environment and Social Studies Department (ESSD), NEA. The officers have collected the necessary information and data by consulting senior technical officials, representatives of the district, local authorized persons, affected people, contractors and locals to prepare this progress report. The report is based on following parameters/indicators: (i) type of acquisition impacts, (ii) extent of impacts, (iii) measures adopted to minimize the impacts, (iv) implementation status of mitigating measures, (v) consultation and participation, (vi) grievance redressed, (vii) compensation payment and (viii) resettlement and rehabilitation etc. 5. SEMIANNUAL MONITORING RESULTS This Semiannual Social Monitoring work is essential for proper implementation of social safeguard measures. The results of monitoring are summarized in the following sections:

5.1 Documentation and Approval Combined Resettlement and Indigenous People Plan (RIPP) for the Project was prepared by NEA and approved by the ADB in June 2011 at appraisal. The first draft of updated RIPP was submitted to ADB in April 2018, which included updated impact assessment of all substations and all tower foundation of DKTLP and partial tower foundation of MKTLP. The household survey for the structure loss household under RoW of MKTLP and RoW of DKTLP has been completed. The updated RIPP report including update of MKTLP and DKTLP along with RoW information (information of structure loss HHs) has been prepared and submitted to ADB in December 2020 incorporating ADB’s comments. The ADB sent further comments on December 2020 version and under revision in PMD and PSC. The household survey of Parbat, Palpa and Syangja Districts has been completed in KNBTLP whereas household survey in remaining districts is ongoing. Similarly, household survey of Lamjung District has been completed in UMBTLP whereas household survey in remaining districts is ongoing. 5.2 Land Acquisition and Compensation Distribution Land acquisition of Dana and Kushma substations under Kali Gandaki Corridor and Markichowk & Matatirtha substations under Marsyangdi-Kathmandu section has been completed. Comparatively, the land acquisition data differs from original RIPP, because the entire land requirement presented in original RIPP was based on estimation. Whereas, this prepared report is based on actual land acquired after check survey and detailed design. The compensation distribution for the APs is under process. With regards to land acquisition for tower foundation, 6.68ha and 9.93ha land has been acquired for Dana-Kushma 220kV subproject under Kali Gandaki corridor and Marsyangdi-Kathmandu 220kV subproject respectively. The details of proposed land in original RIPP and actual land acquired are mentioned below in Table 3:

SASEC-PSEP 6 NEA-ESSD 8th Semiannual Social Monitoring Report July-December, 2020

Table 3: Details of Land Acquisition

Achievement till As per origin S.N. Sub-project Components reporting period RIPP (ha) (ha) • Kali Gandaki Corridor 1.1 Dana-Kushma 220kV TL (DKTLP) under Kali Gandaki Corridor • Dana Substation 5 5.45 • Kushma Substation 7.91 • Kushma Substation (Addl.) 10 1.7 • Tower Foundation (Dana-Kushma line) 2.97 6.68 Sub-Total 17.97 21.74 1.2 Kushma-New Butwal 220kV TL (KNBTLP) • New Butwal S/S 10 8.55 • Tower Foundation (Kushma-New Butwal TL) - 3.255 Sub-Total 10 11.775 1.3 New Butwal-Bardaghat 220kV TL (NBBTLP) 1 • • Tower Foundation (New Butwal Bardaghat - - Line) • Marsyangdi-Kathmandu 220kV TL (MKTLP) • Markichowk Substation 3.5 3.02 • Matatirtha Substation 5 6.19 • Tower Foundation (Marsyangdi-Kathmandu TL) 5.87 9.93 Sub-Total 14.37 19.14 • Marsyangdi Corridor 3.1 Udipur-Markichowk-Bharatpur 220kV TL (UMBTL) 2 • Udipur Substation 4 5.18 • Bharatpur Substation - 2.5 • Tower Foundation (Udipur-Markichowk-Bharatpur TL) 4.41 1.53 Sub-Total 8.41 9.21 3.2 Manang-Khudi-Udipur 220kV TL (MKUTL) 3 • Manang Substation - - • Khudi Substation - - • Tower Foundation (Manang-Khudi-Udipur TL) - - Sub-Total - - • Samundratar Trishuli 3B Hub TL 132kV (STR3BTL) 4 • Samundratar Substation - - • Trishuli 3B Hub Substation - - • Tower Foundation (Samundratar Trishuli 3B Hub TL) - -

1 The details of Land acquisition of NBBTL has not been displayed as construction work has not started yet. 2 The details of Land acquisition of UMBTL has not been displayed for tower foundation as construction work has not been started yet and land has been acquired for Bharatpur substation by NEA. 3 The details of Land acquisition of MKUTL has not been displayed as construction work has not been started yet. 4 The details of Land acquisition of STR3BTL has not been displayed as construction work has not been started yet.

SASEC-PSEP 7 NEA-ESSD 8th Semiannual Social Monitoring Report July-December, 2020

Sub-Total - - Total 50.75 61.883 DKTLP For Dana-Kushma 220 kV project under Kali Gandaki Corridor, land acquired for Dana substation and Khurkot substation is 5.45 ha and 9.61 ha respectively as reported in previous reports. Similarly, 6.68 ha land is acquired for tower foundations in Myagdi and Parbat district till the reporting period. In Dana and Kushma Substations, acquisition of 15.06 ha land has been achieved.

MKTLP For Marsyangdi-Kathmandu 220 kV project, land acquired for Matatirtha substation and Markichowk substation is 6.19 ha and 3.02 ha respectively. Similarly, 9.93ha land has been acquired for tower foundation in Dhading, Gorkha, Chitwan and Kathmandu districts till this reporting period. In Matatirtha and Markichowk Substation, acquisition of 9.21 ha land has been achieved. In Matatirtha Substation 100 % compensation has been distributed to the affected HHs.

KNBTLP For New Butwal substation of Kushma-New Butwal 220 kV TL Project under Kali Gandaki Corridor, land acquisition for 8.55 ha has been achieved.

UMBTLP For Udipur substation of Udipur-Markichowk-Bharatpur 220 kV TL Project under Marsyangdi Corridor, land acquisition for 5.18 ha of land has been achieved. 5.2.1 Rate Fixation for Land Acquisition The summary of Rate fixation for Land Acquisition is mentioned below: Table 4: Rate fixation for Land Acquisition

No. of CDC meetings No. of CDC meetings conducted in this Rate Fixation of land / TL Projects conducted till the date of Semiannual Reporting Compensation Status Reporting Period (July to (%) December, 2020)

DKTLP 16 4 95

MKTLP 16 3 90

KNBTLP 4 1 65

NBBTLP 1 4 NA

UMBTLP 5 2 57

Total 42 13 Avg. 76.75

Till the date 42 CDC meetings have been conducted in SASEC TL. Approximately 77% of compensation works have been completed till the date.

SASEC-PSEP 8 NEA-ESSD 8th Semiannual Social Monitoring Report July-December, 2020 In this Semiannual reporting period of July to December 2020, 13 CDC meetings have been conducted throughout the SASEC TL. CDC meetings for the rate fixations are conducted as per the requirement of the project if needed for land Acquisition.

5.2.2 Compensation for Acquired Land DKTLP Under Tower Foundation A total number of 346 APs are affected due to land acquisition in Dana and Kushma substations and tower foundations in Myagdi and Parbat districts under Dana-Kushma section of Kali Gandaki Corridor. A total of 126 APs of Dana and Kushma substation including additional land has been compensated by the project. There have been 15 APs and 4 APs added in Myagdi and Parbat districts respectively due to additional land for transmission line. Therefore, in total 87 and 134 people are affected due to land acquisition for transmission line in Myagdi and Parbat districts respectively. 68 APs and 74 APs, who are affected due to the land for the towers, have been compensated in Myagdi and Parbat Districts respectively. Under RoW Total 952 APs are affected due to land acquisition under RoW in Parbat district and 562 APs are affected in Myagdi district. In the month of December 2020, 68 APs have been compensated by NPR 15,446,345.50 for RoW land loss in DKTLP. In Myagdi 62 APs have been compensated by NPR 14,495,808.50 and in Parbat district 6 APs have been compensated by NPR 950,546.00. So, altogether 124 APs have been compensated for land loss along the RoW (84 APs in Myagdi district and 40 APs in Parbat district) till this reporting period. MKTLP Under Tower Foundation A total of 153 APs has been affected due to the land acquisition for Markichowk and Matatirtha substations and 320 APs affected in Gorkha, Dhading and Chitwan district by tower foundation under Marsyangdi-Kathmandu 220 kV line section. In this reporting period 7 APs have received land compensation in the month of October, 4 APs in November and 2 APs in December under Tower foundation in Dhading district. Till this reporting period, total 176 APs, 71 APs, 21 APs, 3APs and 2 APs due to the land for the towers have been compensated in Dhading, Gorkha, Chitwan, Kathmandu and Tanahun districts respectively. Thus, remaining 27 APs, 19APs, 4APs and 5APs are yet to be compensated in Dhading, Gorkha, Chitwan and Kathmandu districts respectively. Under RoW In this reporting period 31 APs have received NPR 10,699,156.25/- land compensation under RoW in Dhading district. Likewise, 6 APs have received NPR10,868,125/- land compensation under RoW in Kathmandu district and 7 APs have received compensation NPR 858,200.6 for land under RoW in Gorkha district in this reporting period. Likewise, in the reporting period of August, 34 APs have received NPR 14098515.62/-land compensation under RoW in Dhading district. Similarly, no compensation has been distributed for land under RoW in Gorkha district in this reporting period. Therefore, altogether 302 APs have received 20% compensation of NPR 86,532,270.1 for land under RoW in Gorkha district till this reporting period. Likewise, in

SASEC-PSEP 9 NEA-ESSD 8th Semiannual Social Monitoring Report July-December, 2020 September 2020, 40 APs have received NPR 15,482,734.37 land compensation under RoW in Dhading district.

In the reporting period, 58 APs under RoW in October, 33 APs in November and 9 APs in the month of December have received land compensation in Dhading district.

Likewise, 5 APs have received land compensation under RoW in Gorkha district and 8 APs in Chitwan district.

22 APs have received NPR 5564250 for 20% land compensation under ROW of in Chitwan district in this reporting period.

Therefore, altogether, 568 APs have received land compensation under RoW in Dhading district till this reporting period. Similarly, altogether 312 APs have received 20% compensation of NPR 88865116.7for land under RoW in Gorkha district. Likewise, altogether 6 APs have received NPR10, 868,125/- land compensation under RoW in Kathmandu district till this reporting period.

KNBTLP A total of 137 APs has been affected due to the land acquisition of transmission line. 18 APs have received compensation under tower foundation in the month of October and 2 APs in the month of November. Altogether 59 APs have received total compensation of NPR 1299692.72 for land acquired for tower construction in Palpa district and 18 APs in the Syangja and Parbat district till this reporting period.

UMBTLP Total 83 APs are affected in Lamjung district by tower foundation work under Udipur- Markichowk- Bharatpur 220 kV transmission line. Among them total 2 APs have been compensated with total amount of NRs 1,364,062 in Lamjung district in the month of November Therefore, altogether total 47 APs have been compensated of amount NRs 42,709,467 in Lamjung district tiil this reporting period.

The detail of compensation of substations and tower foundation that has been disbursed by concerned District Administration Office until this reporting period is given below in Table 4.

SASEC-PSEP 10 NEA-ESSD 8th Semiannual Social Monitoring Report January-June, 2020

Table 5: Compensation Distribution Status

HHs who have Compensation Affected Acquired Compensation Compensation SN Sub-project Components received Progress % in terms HHs Land target (NPR) paid (NPR) Compensation of HHs

1. Kaligandaki Corridor 1.1. Dana-Kushma 220kV TL Project under Kali Gandaki Corridor (DKTLP)

i Dana Substation 21 5.45 21 27,118,086 27,118,086 100%

ii Kushma Substation 84 7.91 84 149,682,530.81 149,682,530.81 100%

Sub-total (i+ii) 105 13.36 105 176,800,616.81 176,800,616.81 100%

iii Tower Foundation (Myagdi) 87 2.976 68 48,293,147.91 38,398,138 78%

iv Tower Foundation (Parbat) 134 3.708 74 36,668,794.09 16,673,246 55%

v Kushma substation (Addl.) 21 1.7 21 10,239,644 10,239,644 100%

vi RoW (Myagdi) 296 23.2 22 NA 21,300,568.53 7% vii RoW (Parbat) 601 34 NA 5,204,471 6%

Sub-Total (iii+iv+v+vi+vii) 1139 31.584 219 95,201,586.00 19%

1.2. Kushma-New Butwal 220kV TL Projectunder Kali Gandaki Corridor (KNBTLP)

6 HHs and 3 6 HHs and 3 i New Butwal Substation private 8.55 136,251,875.00 136,251,875.00 100% private companies Companies

SASEC-PSEP 11 NEA-ESSD 8th Semiannual Social Monitoring Report January-June, 2020

HHs who have Compensation Affected Acquired Compensation Compensation SN Sub-project Components received Progress % in terms HHs Land target (NPR) paid (NPR) Compensation of HHs

ii Tower Foundation (Palpa) 131 3.225 59 16,740,781.48 12996972.82 45%

84,90,619 12% iii Tower Foundation (Parbat) 149 18 Housholds

Sub-Total (i+ii) 282 11.805 83 152992656.48 29% 2. Marsyangdi-Kathmandu

i Markichowk Substation 15 3.024 15 60,768,621.02 60,768,621.02 100%

ii Matatirtha Substation 138 6.19 138 1,106,616,063.58 1,106,616,063.58 100% Sub-Total (i+ii) 153 9.22 153 1,167,384,684.60

Tower Foundation 104789778.81 iii 203 6.22 176 90,000,000 87% (Dhading)

iv RoW Dhading 1335 143.53 568 NA 192382086.95 43%

Tower Foundation v 7 0.166 3 19,000,000 5994377 42% (Kathmandu)

vi RoW Kathmandu 73 4.30 6 NA 10868125 8% vii Tower Foundation (Gorkha) 90 2.49 71 38,000,000 37,493,901.26 79% viii RoW Gorkha 622 - 312 NA 88865116.7 50%

Tower Foundation ix 25 1.176 21 15,000,000 12,728,425.00 84% (Chitwan)

SASEC-PSEP 12 NEA-ESSD 8th Semiannual Social Monitoring Report January-June, 2020

HHs who have Compensation Affected Acquired Compensation Compensation SN Sub-project Components received Progress % in terms HHs Land target (NPR) paid (NPR) Compensation of HHs

x RoW Chitwan 57 30 NA 8545375 53%

Tower Foundation xi 2 0.014 2 274218.75 274,218.75 100% (Tanahun) xii RoW Tanahun 20

Sub-Total 2434 157.896 1189 162,274,219 48% (iii+iv+v+vi+vii+viii+ix+x+xi+xii)

3. Marsyangdi Corridor

3.1. Udipur-Markichowk-Bharatpur under Marsyangdi Corridor (UMBTLP)

i Udipur Substation 6 5.18 6 53,925,719.09 53,925,719.09 100%

Tower Foundation ii 83 1.53 47 59,675,976.56 42,709,467 57% (Lamjung) Sub-Total (i+ii) 89 6.71 53 113,601,695.65 96635186.09 60%

SASEC-PSEP 13 NEA-ESSD 8th Semiannual Social Monitoring Report July-December, 2020 5.2.3 Compensation Distribution for Structure Loss The compensation distribution for Structure loss for the subprojects has been described as follows:

DKTLP Under Tower Foundation In total 4 APs have been compensated by NPR. 2,999,198 for structure loss under tower foundation in Parbat district and 8 APs have been compensated by NPR. 10,084,899 for structure loss under tower foundation in Myagdi district till this reporting period. All total 12 APs have been compensated for structure loss under tower foundation. Under RoW 22 APs have been compensated by NPR 20,891,622.63 for structural loss in Myagdi district and 1 AP has been compensated by NPR 81,425 in Parbat District for structure loss under RoW till this reporting period. MKTLP In MKTLP, there are total 85 APs, 47 APs, 9 APs and 6 APs affected due to structure loss in Dhading, Gorkha, Chitwan and Tanahun districts respectively under tower foundation and RoW. Under Tower Foundation In total 10 APs have received structure loss compensation NPR 4,673,443.66/-under tower foundation in Dhading district till this reporting period. Similarly, total 4 APs have been compensated by NPR.10,58,758.99 in Gorkha districtand 3 APs have been compensated by NPR 1,520,871.41 in Chitwan district for structure loss under tower foundation till this reporting period. Similarly, 3 Community buildings have been compensated by NPR. 1,527,979.95 for structure loss under tower foundation in Chitwan district. Under RoW Altogether 57 APs out of 74 have received compensation NPR 27056067.42/- under RoW in Dhading district till this reporting period. Similarly, 4 APs have received compensation amount NPR 3,175,763.55 for structure loss under RoW in Chitwan and 27 APs in Gorkha district, have received compensation amount of NPR 45844909.02 for structure loss under RoW till reporting period.

KNBTLP The structure loss and compensation payment in KNBTLP is not in progress because the project is enlisting the exact number of structure loss due to tower foundation.

UMBTLP The structure loss and compensation payment are not in progress because the project is enlisting the exact number of structure loss due to tower foundation. The details of compensation for structure loss under tower foundation & RoW that have been disbursed by concerned District Administration Office until this reporting period are given below in Table 6.

SASEC-PSEP 14 NEA-ESSD 8th Semiannual Social Monitoring Report July-December, 2020

Table 6: Compensation Distribution Status for Structure loss

No. of APs No. of APs Amount of Amount of received received compensation Compensation Sub-project compensation compensation SN in the till the Components in this till the reporting reporting reporting reporting period (NPR) period (NPR) period period

1. Kaligandaki Corridor

1.1. Dana-Kushma 220kV TL Project under Kali Gandaki Corridor (DKTLP)

Under Tower Foundation i Myagdi 0 0 8 10084899 ii Parbat 0 0 4 2999198 Subtotal 12 13084097 Under RoW i Myagdi 0 0 22 20891622.63 ii Parbat 0 0 1 81425.00 Sub-Total 23 20973048

2. Marsyangdi-Kathmandu TL Project (MKTLP)

Under Tower Foundation i Dhading 0 0 10 4,673,443.66 ii Gorkha 0 0 4 1,058,758.99 iii Chitwan 0 0 3 1,520,871.41 Sub-Total 17 7,253,074.06 Under RoW i Dhading 2 884105.58 57 27056067.42 ii Gorkha 0 0 27 45,844,909.02 iii Chitwan 0 0 4 3,175,763.55 iv Tanahun v Kathmandu Sub-Total 88 76,076,739.99

5.2.4 Compensation Distribution for Crop, Tree and Grass Loss The Compensation distribution for crop loss in each subproject has been described as follows:

DKTLP Under RoW

In DKTLP, altogether total 155 APs have received compensation NPR 1,690,097.67 in Parbat district and 28 APs have received compensation NPR 644,219.20 in Myagdi district for crop loss under RoWtill this reporting period. Similarly, altogether, 82 APs have received compensation NPR 2038008.29 in Parbat district and 76 APs have received compensation NPR 3838631.46 in Myagdi district for tree lossunder RoW till this reporting period. Therefore, till the reporting period 82 APs amounting to NPR 2038008.29 and 76 APs amounting to NPR 3838631.46 have been compensatedfor the trees loss under RoWin Parbat District and Myagdi District respectively.

SASEC-PSEP 15 NEA-ESSD 8th Semiannual Social Monitoring Report July-December, 2020 MKTLP Under Tower Foundation

Altogether 104 APs have been compensated crop loss under tower foundation NPR 2,308,436.25 in Dhading district till this reporting period. Similarly, 14 APs have been compensated by NPR 260,251 under tower foundation in Chitwan district and 65 APs have been compensated by NPR. 670,907 under tower foundation in Gorkha district.

Under RoW

In this reporting period 18 APs have received crop loss compensation under RoW NPR 470730/-in Dhading district. 43 APs have received NPR 2368000.00 for fodder tree loss compensation, 27 APs have received 716871.80 for tree loss compensation and 31 APs have received 726676.30 for crop loss compensation under RoW in Gorkha district. In the reporting period of September, 46 APs have received crop loss compensation under RoW NPR 815,308/- in Dhading district.

In this reporting period 43 APs have received crop loss compensation under RoW in October, 57 APs in November and 18 APs in December 2020 in Dhading district.

Therefore, altogether 530 APs have been compensated NPR 19601886.07/- for crop loss under RoW in Dhading district and 23 APs have been compensated by NPR 1,277,354 under RoW in Chitwan District under RoW till this reporting period Likewise, altogether 7 APs have received tree loss compensation of NPR. 2,172.18 and 31 APs have received fodder tree loss compensation of NPR. 1,447,100 in Chitwan district. In Gorkha 39 APs have received compensation for tree and fodder loss in the month of October and 57 APs in November 2020. Altogether, in Gorkha 57APs have received compensation of NPR 2,175,000 for fodder tree loss in Gorkha district till this reporting period. Similarly, 141 APs have received fodder trees loss compensation under RoW NPR 5727300/- in Dhading district till this reporting period. Similarly, 35 APs have received fodder trees loss compensation under RoW in in this month of October 2020 and 46 APs in November in Dhading district. KNBTLP The crop loss and compensation payment are not in progress because the project is enlisting the exact number of loss due to tower foundation.

UMBTLP In UMBTLP, total 2 HHs have received crop loss compensation under Tower Foundation amountsto NRs 43000 till this reporting period in Lamjung district. The details of compensation for crop loss and tree loss under tower foundation & RoW that have been disbursed by concerned District Administration Office until this reporting period are given below in Table 7 and Table 8 respectively.

SASEC-PSEP 16 NEA-ESSD 8th Semiannual Social Monitoring Report July-December, 2020

Table 7: Compensation Distribution Status for Crop loss

No. of APs No. of APs Amount of Amount of received received compensation Compensation Sub-project compensation compensation SN in the till the Components in this till the reporting reporting reporting reporting period (NPR) period (NPR) period period 1. Kaligandaki Corridor 1.1. Dana-Kushma 220kV TL Project under Kali Gandaki Corridor (DKTLP) Under Tower Foundation i Myagdi - - - - ii Parbat - - - - Subtotal - - - - Under RoW i Myagdi - - 28 644,219 ii Parbat - - 155 1,690,097 Sub-Total - - 2,334,316 2. Marsyangdi-Kathmandu TL Project (MKTLP) Under Tower Foundation i Dhading - - 104 2,308,436.25 ii Gorkha - - 65 670,907 iii Chitwan - - 14 260,251 Sub-Total - - 183 3,239,594.25 Under RoW i Dhading 118 10,582,536.25 530 19601886.07 ii Gorkha 31 726676.30 31 726676.30 iii Chitwan - - 23 1,277,354 iv Tanahun - - - - v Kathmandu - - - -

Sub-Total 149 11,309,212.55 584 32605916.07

3. Udipur-Markichowk-Bharatpur 220 kVTL Project under Marsyangdi Corridor (UMBTLP)

Under Tower Foundation

I Lamjung - - 2 43,000 Ii Gorkha - - - - Iii Tanahun - - - - Iv Chitwan - - - - Sub-Total 2 43,000 Under RoW i Lamjung - - - - ii Gorkha - - - - iii Chitwan - - - - iv Tanahun - - - - Sub-Total - - - - Total 149 11,309,212.55 953 38,222,826.32

SASEC-PSEP 17 NEA-ESSD 8th Semiannual Social Monitoring Report July-December, 2020 The details of compensation for tree loss under tower foundation & RoW that have been disbursed by concerned District Administration Office until this reporting period are given below in Table 8.

Table 8: Compensation Distribution Status for Tree loss and Fodder loss

No. of APs No. of APs Amount of Amount of received received compensation Compensation Sub-project compensation compensation SN in the till the Components in this till the reporting reporting reporting reporting period (NPR) period (NPR) period period

1. Kaligandaki Corridor

1.1. Dana-Kushma 220kV TL Project under Kali Gandaki Corridor (DKTLP)

Under Tower Foundation i Myagdi - - - - ii Parbat - - - - Subtotal - - - - Under RoW i Myagdi - - 76 2,038,008 ii Parbat - - 82 3,839,631

Sub-Total - - 158 5,877,639

2. Marsyangdi-Kathmandu TL Project (MKTLP)

Under Tower Foundation i Dhading - - - - ii Gorkha - - - - iii Chitwan - - - - Sub-Total - - - - Under RoW i Dhading 111 4,867,000 141 5,727,300 ii Gorkha 109 4,434,872 127 525,9871.8 iii Chitwan - - 38 1,449,272.18 iv Tanahun - - - - v Kathmandu -

Sub-Total 12,436,443.98 220 9,301,872 306

5.2.5 Compensation Distribution for Fruits Loss. DKTLP The Project has compensated all the affected HHs for the fruit loss in Myagdi and Parbat district. The data is still not finalized and is in the process of updating.

MKTLP In MKTLP, total 159 APs and 114 APs are affected due to fruits loss in Dhading and Chitwan districts respectively.

SASEC-PSEP 18 NEA-ESSD 8th Semiannual Social Monitoring Report July-December, 2020 Under Tower Foundation

In total, 54 APs have been compensated fruit tree loss under tower foundation NPR 1642870 in Dhading district till this reporting period.

Under RoW In the reporting period of July, 30 APs have received fruit tree loss compensation under RoW NPR 769,500 in Dhading. Likewise, in August, 18 APs have received fruit tree loss compensation under RoW NPR 433000/- in Dhading.

Therefore, in total 108 APs have been compensated NPR 3078538/-for fruit tree loss under RoW in Dhading district till this reporting period. Similarly, 3 APs have been compensated by NPR 186,480 in Chitwan districts for fruits loss under RoW till this reporting period. KNBTLP The fruits loss and compensation payment are not in progress because the project is enlisting the exact number of loss due to tower foundation.

UMBTLP The fruits loss and compensation payment are not in progress because the project is enlisting the exact number of loss due to tower foundation.

The details of compensation for fruit loss under tower foundation & RoW that have been disbursed by concerned District Administration Office until this reporting period are given below in Table 9.

SASEC-PSEP 19 NEA-ESSD 8th Semiannual Social Monitoring Report July-December, 2020

Table 9: Compensation Distribution Status for Fruit loss

No. of HHs received Amount paid Cumulative Cumulative Sub-project compensation SN in reporting progress Progress Components in this period (NPR) (HHs) (NPR) reporting period 1. Kaligandaki Corridor 1.1. Dana-Kushma 220kV TL Project under Kali Gandaki Corridor (DKTLP) Under Tower Foundation i Myagdi - - - - ii Parbat - - - - Subtotal - - - - Under RoW i Myagdi - - - - ii Parbat - - - -

Sub-Total

2. Marsyangdi-Kathmandu TL Project (MKTLP) Under Tower Foundation i Dhading - - 54 1642870 ii Gorkha - - - - iii Chitwan - - - Sub-Total - - 54 1642870 Under RoW i Dhading - - 108 3078538 ii Gorkha - - - - iii Chitwan - - 3 186,480 iv Tanahun - - - - v Kathmandu - - - - Sub-Total - - 111 3265018

5.2.6 Progress on Assistance to Vulnerable Households Permanent Loss In Parbat District, among interviewed HHsunder Tower Foundation and for structure loss under RoW, 53 APs have been identified as vulnerable groups among them 14 are Dalits, 5 are IPs, 15 are women headed, 4 are disabled and 24 are below poverty line during RIPP update where mentioned numbers are non-additive. Similarly, in Myagdi District, among interviewed HHs under Tower Foundation and for structure loss under RoW, 58 APs have been identified as vulnerable group among them 2 are Dalits, 41 are IPs, 15 are women headed, 10 are below poverty line and 2 are disabled persons during RIPP update where mentioned numbers are non-additive. The assistance to vulnerable households has not yet been released till this reporting period. The details of affected vulnerable HHs in DKTLP have been attached in Table 10 below:

SASEC-PSEP 20 NEA-ESSD 8th Semiannual Social Monitoring Report July-December, 2020

Table 10: Affected vulnerable HHs in DKTLP

District/Types of Woman BPL Dalit IPs Disabled Total Vulnerability Headed

Permanent Loss 10 15 2 41 2 70 Myagdi Temporary Loss 0 0 0 0 0 0 Total 10 15 2 41 2 70 % 14.29 21.43 2.86 58.57 2.86 100.00 Permanent Loss 24 15 14 5 4 62 Parbat Temporary Loss 0 0 0 0 0 0 Total 24 15 14 5 4 62 % 38.71 24.19 22.58 8.06 6.45 100.00 Permanent Loss 34 30 16 46 6 132 Total Temporary Loss 0 0 0 0 0 0 Total 34 30 16 46 6 132 % 25.76 22.73 12.12 34.85 4.55 100.00 Source: Socio Economic Survey, 2017, 2018 and 2019 MKTLP Permanent Loss In Dhading District, among interviewed HHsunder Tower Foundation and for structure loss under RoW,113 APs have been identified as vulnerable groups among them 15 are dalit, 74 are IPs, 24 are women headed, 8 are disabled and 13 are below poverty line during RIPP update where mentioned numbers are non-additive. In Gorkha District, among interviewed HHsunder Tower Foundation and for structure loss under RoW, 69 APs have been identified as vulnerable group among them 27 are dalit, 28 are IPs, 16 are women headed, 17 are below poverty line and 6 are disabled during RIPP update where mentioned numbers are non-additive. In Chitwan district, among interviewed HHsunder Tower Foundation and for structure loss under RoW, 27 APs have been identified as vulnerable groups among them 25 are IPs, 6 are women headed, 3 are under BPLand 1 is disabled during RIPP update where mentioned numbers are non-additive. In this reporting period due to additional land in Chitwan district 4 APs have been increased. In Kathmandu district, among interviewed HHsunder Tower Foundation, 5 APs are identified as vulnerable groups among them 5 are IPs and 1 is disabled during RIPP update where mentioned numbers are non-additive. In Tanahun district, among interviewed HHsunder Tower Foundation and for structure loss under RoW, 7 APs are identified vulnerable groups among them 7 are IPs, 2 are women headed and 1 is under BPL during RIPP update where mentioned numbers are non-additive. Allowances as per entitlement matrix is yet to be distributed to the vulnerable HHs in the districts. The details of affected vulnerable HHs in MKTLP have been attached in Table 11 below:

Table 11: Affected vulnerable HHs in MKTLP

District/Types of BPL WH Dalit IPs Disabled Total Vulnerability Permanent 0 0 0 5 1 6 Kathmandu Loss % 0 0 0 83.33 16.67 100

SASEC-PSEP 21 NEA-ESSD 8th Semiannual Social Monitoring Report July-December, 2020

District/Types of BPL WH Dalit IPs Disabled Total Vulnerability Permanent 13 24 15 74 8 134 Loss Temporary 0 0 0 0 0 0 Dhading Loss Total 13 24 15 74 8 134 % 9.70 17.91 11.19 55.22 5.97 100.00 Permanent 17 16 27 28 6 94 Loss Temporary 0 0 0 0 0 0 Gorkha Loss Total 17 16 27 28 6 94 % 18.09 17.02 28.72 29.79 6.38 100.00 Permanent 3 6 0 25 1 35 Loss Temporary 0 0 0 0 0 0 Chitwan Loss Total 3 6 0 25 1 35 % 8.57 17.14 0.00 71.43 2.86 100.00 Permanent 1 2 0 7 0 10 Loss Temporary 0 0 0 0 0 0 Tanahun Loss Total 1 2 0 7 0 10 % 10 20 0 70 0 100 Permanent 34 48 42 139 16 279 Loss Temporary 0 0 0 0 0 0 Total Loss Total 34 48 42 139 16 279 % 12.19 17.20 15.05 49.82 5.73 100.00 Source: Socio Economic Survey, 2017, 2018 and 2019 KNBTLP The household survey of affected person under tower foundation of Parbat, Palpa and Syangja districts have been just completed and data analysis isin progress for RIPP update of KNBTLP section. In Palpa section, among the the total of 73 household surveyed, 61 households were categorized as vulnerable HHs. Likewise, in Parbat and Syangja section among the total surveyed households of respective 222 & 63 HHs, 70 of Parbat and 32 of Syangja were categorized as vulnerable HHs. The details of affected vulnerable HHs in KNBTLP have been attached below:

Table 12: Affected vulnerable HHs in KNBTLP

District/Types of BPL WH Dalit IPs Disabled Total Vulnerability Permanent 5 4 5 47 0 61 Palpa Loss % 8.19 6.55 8.19 77.04 0 100 Parvat Permanent 2 28 8 25 7 70 Loss % 3 40 11 36 10 100

SASEC-PSEP 22 NEA-ESSD 8th Semiannual Social Monitoring Report July-December, 2020

District/Types of BPL WH Dalit IPs Disabled Total Vulnerability Syangja Pemanent 1 6 1 19 5 32 Loss % 3 19 3 59 16 100 Source: Socio Economic Survey, 2017, 2018 and 2019 . UMBTLP The household survey of affected person under tower foundation of Lamjung district hasjust been completed. Therefore, in Lamjumg district, out of 83 interviwed APs under Tower foundation, 26 APs are identified as IPs and 20 APs are identified as woman headed. 5.2.7 Additional Assistant to the PAFs Till this semiannual reporting period from July to December, 2020 the APs are yet to receive additional assistance. However, the lists of APs who are eligible to get additional assistance under tower foundation are being finalized and distributed. This assistance includes livelihood rehabilitation, transportation assistance, vulnerable assistance etc., as per approved entitlement matrix of the RIPP. 5.2.8 Major Issues associated with Land Acquisition and Compensation The details of the issues recorded in projects sites have been described below in Table 13:

Table 13: Major issues associated with land acquisition and compensation in project sites

SN Major Issues

DKTLP

1 Dhan Bahadur Baruwal the affected person for structural loss at AP 43 to 44 has demanded the land for new building construction.

2 The survey office has decleared the structure of AP 10 to AP 11 is under row on his cadastral survey but in the contractors survey it out of the RoW. Now the project and CDC committee will come in action for its final decision.

3 The problem in Annapurna-6, Pokharebagar at 6 APs of Tower foundation has been solved. One of the affected, Pokharebagar Dhan Bahadur Baruwal whose residential building is affected by RoW (43 Ap–44 AP) is still demanding for revaluation of his building and demanding the homestead land in the same vicinity. The issue is in the process of solving by project. CDC has already determined his losses due to the Transmission Line activities, but he is denying to receive/accept the money.

4 The affected people at Dana Substation stopped the construction activities of substation on 2077/3/10. Meeting was conducted at CDO office on 2077/3/14 to address their demands and the work has been resumed after the negotiation was done between the project and local people. Now the local people are in the process to submit the financial and technical proposal to the project as per their demands.

MKTLP

5 At AP74/2, total of 9.5 Ropani land is impacted by tower foundation including RoW of a single household at Gorkha- 14. PAFs have demanded either to provide land for land or to pay full compensation (not only 20% as per CDC) of affected land under RoW. The issue has been under discussion in second and third level GRC. A subcommittee, led by Assistant Chief District Officer has been formed by the CDC meeting which was held on 2076/10/06 to investigate the losses

SASEC-PSEP 23 NEA-ESSD 8th Semiannual Social Monitoring Report July-December, 2020

of concerned PAFs. Site visit and consultation meeting with PAF has been done and Subcommittee has submitted the report to CDO office.

6 Community of Siddhalek RM-7, pipaltar of Dhading district has been demanding shifting of tower alignment from pipaltar village so the contruction work of two tower ie. AP24E/0 and 24F/0 are still remaining. Discussions are continuous with concerned stakeholders to solve the issue as early as possible. Likewise, Stringing work is also remaining at AP 7D/2 & 7E/0 due to the dissatisfaction over land compensation by affected HH.

KNBTLP

7 AP 49/0, PAFs & community peoples have demanded to manage access road from north side of tower pad which has been stopped since a year ago because of delay in designing of wall for the access road by the project & contractors.

8 At AP 56A, PAFs have demanded to put iron ganger on the wall for security, which is under consideration in project office and technical studies are going on to address the demand which is still in the process of solving by NEA 9 58B/0, PAF Mr. Lila Bahadur Rana has demanded security of his house which is at sloppy area and also demanded for compensation of house. It is still in process of solving

UMBTLP

10 Community people of Palungtar -4 and 5 are still demanding to shift the alignment from Thatipokhari market area due to the plan of smart city and scope of paragliding in that area. They have submitted the letter to Nepal electricity authority Kathmandu and Ministry of Energy, water resources and Irrigation. 11 Community people in AP44, AP45/2 and AP46 of Rainas-6 are demanding re- determination of land compensation and determination of RoW compensation as earliest.

5.2.9 Safeguard Implementation Progress The status of safeguard implementation progress is given in below Table 14.

Table 14: Status of Safeguard implementation progress

SN Subprojects Status

Kali Gandaki Corridor

1 Dana-Kushma 220kV • Compensation distributed for 40 APs on behalf of landloss transmission line, and under RoW in Myagdi and parbat district substations at Dana and • Conduction of GRC meetings Kushma • Conducted CDC meeting on Parbat district. • Conducted CDC meeting on Myagdi district.

2 Kushma-New Butwal • Consultation review meeting have been conducted at new 220kV transmission line, butwal substation and substation at New • Conducted CDC meeting on Nawalparasi district Butwal • GRC meetings have been conducted. • Informed and managed documentation of PAFs for receiving compensation process by project. • Detail survey, check survey& cadastral survey is completed from AP 80 to Badera SS but report has not been submitted and.

SASEC-PSEP 24 NEA-ESSD 8th Semiannual Social Monitoring Report July-December, 2020

• Informed and managed documentation of PAFs for receiving compensation process by project. • Compensation distribution work is going on in Palpa and Parbat district • Coordination with PAFs and counsel to them for clearance of tower pad foundation & erection work. • Crop and fruit loss data collection is ongoing. • Tree marking work is ongoing at Palpa district under RoW. • Coordination with land revenue office to easy for PAFs & project documentation.

3 New butwal bardaghat • Coordination with project and contractor for detail survey. 220kv transmission line

Marsyangdi-Kathmandu 220kV transmission line and substations at Matatirtha and Markichowk

4 Marsyangdi - Kathmandu • Conducted informal public consultation with PAFs, local 220kV transmission line community and ward chairman at Siddhalek RM-7, Pipaltar on and substations at private land issue for the contruction of tower foundation work Matatirtha and of AP24E/0 and AP24F/0. Markichowk • Construction work of Shatighat (Cremation place) for IPs (Tamang & Gurung community) has been completed at Thakre-8 in July 2020. • Compensation is being provided to APs against loss of private land, and crops. • Site visit in project site with external monitoring consultant deployed by PMD and discussion with project affected families on resettlement issues. • Consultation with community and Project affected HHs as necessary.

Marsyangdi Corridor

5 Udipur-Markichowk- • Conduction of Public Consultation meetings Bharatpur • Household survey has been completed for tower pad in 220kVtransmission line Lamjung district and substation at Udipur • Cadastral survey has been completed in Lamjung district and Tanahun district. • Cadastral survey has been completed from AP 62 to AP 79 of Gorkha district. Other process is ongoing at Gorkha district. • Tree marking (Chhapan) work is ongoing at Lamjung Distrist. • Tree marking work has beencompleted in Chitwan District.

5.2.10 Livelihood Restoration Program For any loss of livelihood, restoration measures have been identified in the updated RIPP. ESSD has been planning to implement livelihood restoration and enhancement skill development training as a part of safeguard measures of the project. The proposed training will be conducted following the curriculum of Council for Technical Education and Vocational Training (CTEVT) 1st level skill development training. PSC consultant will facilitate the trainings.

SASEC-PSEP 25 NEA-ESSD 8th Semiannual Social Monitoring Report July-December, 2020 Till this reporting period altogether 23 trainings have been organized and successfully completed in SASEC TL sub-projects. In this semiannual reporting period two trainings have been started. Some training programs scheduled for the implementation have been postponed due to the impact of COVID-19 pandamic. The details of implementation status of Livelihood Restoration Program in SASEC TL projects are given in Table 15.

Table 15: Implementation Status Livelihood Restoration Program in SASEC TL Projects

Total no. of Name of Trainings Current Trainings Participants TL Projects conducted in this Total Status completed till reporting Period the Date Male Female NA DKTLP 5 0 0 0 NA Driving (Dhading and MKTLP 18 Tanahun) 31 0 31 Ongoing

NA KNBTLP 0 0 0 0 NA UMBTLP 0 NA 0 0 0 NA Total 23 31 0 31

5.2.10.1 Effectiveness of Trainings Implementation of livelihood restoration program is ongoing throughout the project affected area as a part of safeguard measures of the project. ESSD has been implementing mitigation activities as identified in RIPP and IEE. Skill development training programs like Beautician, Tailoring, Driving, Computer training has already been completed to restore livelihood and enhancement of skills among 136 project affected families in MKTLP till the end of July, 2020. While implementing skill development training Curriculum of Council for Technical Education and Vocational Training (CTEVT), level 1 is used by trainers. While carrying monitoring works in project-affected areas, effectiveness of livelihood restoration programs is being assessed by consultation meetings, telephonic conversations, door-to-door visits, etc. During such monitoring works, participants are asked about application of skills after training programs. In case of tailoring training trainees, none of them was able to establish own enterprise and enrolled in jobs in the nearby market but found that many trainees are applying their skills at home and generating little bit income for supporting their livelihood, which is found possible due to provision of distribution of tailoring machines among tailoring trainees. While site visit and conversation it was found that if trained trainees are linked with credit facilities then they might do very well in the future by establishing their own enterprise. In case of driving training trainees, some of them are applying their skills, starting new job, and generating the income after training. Some of them have faced challenge to get the driving license and trying to get job after license. After training, some trainees have started their job as an assistant driver in different vehicles and now some of them are working as a driver and some of them are still working as an assistant driver. The detils of Training Participants have been attached in Annexure 7.

SASEC-PSEP 26 NEA-ESSD 8th Semiannual Social Monitoring Report July-December, 2020 Effectiveness of computer training is yet to be assessed and results will be presented in upcoming monitoring reports. The details of Implementation status of skill development trainings and other general trainings are given in Table 16 and Table 17 respectively.

Table 16: Implementation Status of Skill Development Training

Participants Skill Current TL Projects Name of Trainings Implementation Status Male Female Total Status (%)

Tailoring - 20 20

Electrician 16 - 16 DKTLP Completed Computer 13 3 16

Driving 15 - 15

Sub-total - 44 23 67

Yet to be Beautician - 26 26 Completed assessed

Tailoring - 52 52 13.46 MKTLP Driving 27 - 27 16

Yet to be Computer 15 18 33 assessed

Sub-total - 42 96 138 -

Grand Total - 86 119 205 -

Table 17: Implementation other General Training

Participants Skill Current Implementation TL Projects Name of Trainings Tota Male Female Status Status (%) l

Agriculture 80

NTFP 137 88 225 Complete Yet to be assessed d DKTLP Conservation Awareness 100

Capacity Building 50 Training

Sub-total 137 88 455

Agriculture 53 52 105 Complete MKTLP Vegetable 63 47 110 d Yet to be assessed

NTFP 91 73 164

SASEC-PSEP 27 NEA-ESSD 8th Semiannual Social Monitoring Report July-December, 2020

Participants Skill Current Implementation TL Projects Name of Trainings Tota Male Female Status Status (%) l

Conservation 137 92 229

5.2.11 Impact on Indigenous People (IPs) At Dana substation under Kali Gandaki Corridor, out of 21 APs, 18 are IPs. Likewise, at Khurkot substation (additional land 1.7 ha affected households of 21), out of 105 APs none are IPs. In Myagdi district, out of 73 interviewed APs under TF, 26 are IPS and in Parbat, out of 131 interviewed APs, 5 are IPs of Dana-Kusma 220kV Transmission Line under Kaligandaki Corridor at the time of household survey for Updated RIPP. Out of total 138 APs, 25 are IPs in Matatirtha substation and all 15 APs are IPs in Markichowk substation of Marsyangdi-Kathmandu 220kV Transmission Line project. In Dhading, out of 162 interviewed APs, 45 are IPs; in Chitwan, out of 20 interviewed APs, 18 are IPs, in Gorkha, out of 65 interviewed APs, 15 are IPs, in Kathmandu out of 5 interviewed APs, 5 are IPs and in Tanahun out of 2 interviewed APs, 1is IP of Marsyangdi-Kathmandu 220kV transmission line project. Similarly, for structure under RoW in Dhading district out of 65 APs, 33 are IPs and in Chitwan district out of 9 APs, 7 are IPs at the time of household survey for Updated RIPP. In DKTLP out of 18 interviewed APs under RoW, 15 are IPs in Maygdi and Parbat districts at the time of household survey for Updated RIPP. In MKTLP, out of 124 interviews APs under RoW, 56 are IPs at the time of household survey. The household survey under RoW has been done for structure loss only in DKTLP and MKTLP. At Udipur substation under Marsyangdi Corridor, out of 6 APs, 3 are IPs. In Lamjung district, out of 83 APs, 26 are IPs of Udipur-Markichowk-Bharatpur 220kV Transmission Line under Marsyangdi Corridor at the time of household survey for Updated RIPP. 100% compensation has been disbursed in Dana Substation, Kushma Substation, New- Butwal substation and Udipur substation. IPs was provided full compensation of their affected assets and other assistance as per entitlement matrix. Details are presented in the Table 18 below

SASEC-PSEP 28 NEA-ESSD 8th Semiannual Social Monitoring Report July-December, 2020

Table 18: Resettlement Impact and Impacts on IPs

Total Affected IPs Interviewed APs Total IPs (received SN Name of Projects Total APs among interviewed APs Remarks during RIPP update compensation) during Updated RIPP

1. Kali Gandaki Corridor 1.1 Dana-Kushma 220kV TL Project under Kali Gandaki Corridor 100% compensation has been 1 Dana S/S 21 - 18 18 disbursed There has been no affected IPs in 2 Kushma S/S 84 - 0 0 Kushma S/S. Tower in Myagdi 35 IPs have received compensation 3 87 71 26 35 (Land) and remaining are in progress Towers in Parbat 3 IPs have received compensation and 4 134 130 5 3 (Land) remaining are in progress RoW in Myagdi 5 296 NA NA - (Land) RoW in Parbat 6 601 NA NA 4 (Land) Structures under 7 RoW 20 18 15 14 (Myagdi) Structures under 8 RoW 2 2 0 0 (Parbat) Kushma S/S There has been no affected IPs in 9 21 20 0 0 (Additional) Addl. Kushma S/S. Sub-Total (A) 1266 241 64 74 1.2 Kushma-New Butwal under Kali Gandaki Corridor

SASEC-PSEP 29 NEA-ESSD

8th Semiannual Social Monitoring Report July-December, 2020

Total Affected IPs Interviewed APs Total IPs (received SN Name of Projects Total APs among interviewed APs Remarks during RIPP update compensation) during Updated RIPP

6 APs and 3 10 New Butwal S/S Private - 0 0 Companies5 Total 131 Aps, 74 IPs and 42 IPs have 11 Towers in Palpa 131 128 74 42 received compensation from project. Sub-Total (B) 140 128 74 42 2. Marsyangdi-Kathmandu 220kV TL (MKTLP) 100% compensation has been 1 Markichowk S/S 15 - 15 15 disbursed. 100% compensation has been 2 Matatirtha S/S 138 - 25 25 disbursed. 2 IPs have received land Towers in KTM 3 5 5 6 2 compensation amount and remaining (Land) are in progress. 176 HHs have received land compensation NPR 105604817.87/- Towers in Dhading 4 203 162 48 50 1till this reporting period. Altogether 50 (Land) IPs and 10 Dalit have received land compensation amount. Compensation has been received by Towers in Chitwan 5 26 20 18 17 21 HHs among which 17 HHs are IPs (Land) and remaining are in progress

5 Name list of 3 Private companies: 1. Kaligandaki Cement Udhyog Pvt. Ltd. 2. Indreni Crusher Udhyog Pvt. Ltd. 3. Asian Cement Pvt. Ltd.

SASEC-PSEP 30 NEA-ESSD

8th Semiannual Social Monitoring Report July-December, 2020

Total Affected IPs Interviewed APs Total IPs (received SN Name of Projects Total APs among interviewed APs Remarks during RIPP update compensation) during Updated RIPP

70 HHs have received land Towers in Gorkha compensation. 41 IPs have received 6 93 65 15 41 (Land) compensationand remaining are in progress Towers in Tanahun 2 HHs have received land 7 2 2 1 1 (Land) compensation among them one is IPs. 568 HHs have received land RoW in Dhading compensation under RoW NPR 8 1335 NA NA 168 (Land) 192382086.95/- till this reporting period. 6 HH have received land RoW in Kathmandu 9 73 NA NA 6 compensation under RoW NPR (Land) 10868125/- till this reporting period. RoW in Gorkha 302HHs have received land 10 630 NA NA 124 (Land) compensationunderRoW RoW in Chitwan 11 57 NA NA - (Land) RoW in Tanahun 12 20 NA NA - (Land) Structures under 7 IPs have received compensation for 13 TF and RoW 7 7 7 7 structure loss and remaining are in (Chitwan) progress

Structures under 57 HHs have received structure loss compensation NPR27056067.42/- 14 TF and RoW 85 71 29 29 under RoW till this reporting period. 23 (Dhading) HHs were IPs and 4 HH were dalit

SASEC-PSEP 31 NEA-ESSD

8th Semiannual Social Monitoring Report July-December, 2020

Total Affected IPs Interviewed APs Total IPs (received SN Name of Projects Total APs among interviewed APs Remarks during RIPP update compensation) during Updated RIPP

Similarly, 10 HHs have received structure loss compensation under TF NPR 4673443.66 till this reporting period. 7 HHs were IPs. 8 APs have received compensation Structures under under Tower pad for structure loss, 15 TF and RoW 42 40 12 3 among which 3 is IP and remaining are (Gorkha) in progress Structures under 16 TF and RoW 6 6 6 - (Tanahun) Structures under 17 TF and RoW 5 0 - - (Kathmandu) Sub- Total (C) 2742 378 182 481 3. Marsyangdi Corridor 3.1 Udipur-Markichowk-Bharatpur 220kV TL (UMBTLP) 100% compensation has been 1 Udipur Substation 6 - 3 3 disbursed. 47 HHs have received the 2 Tower in Lamjung 83 53 15 17 compensation of NRs 42709467 in Lamjung district. Sub- Total (D) 89 53 18 20

SASEC-PSEP 32 NEA-ESSD

8th Semiannual Social Monitoring Report July-December, 2020 5.3 Monitoring Results compared against IR and IPs Safeguards The Compliance status against Loan Covenants related to resettlement and Indigenous People safeguards has been annexed as Annexure 2.

The overall details of Monitoring Results compared against IR and IPs Safeguards for all the subprojects have been described in Table 8 and Table 9 below:

SASEC-PSEP 33 NEA-ESSD

8th Semiannual Social Monitoring Report July-December, 2020

Table 19: Compliance Monitoring Results in terms of Involuntary Resettlement Safeguards

Monitoring Compliance Status SN Indicators Aspects DKTLP MKTLP KNBTLP UMBTLP

1 Delivery of ➢ Entitlements disbursed, compared with Being complied with: Being complied with: Being Complied Being Complied with: Entitlements no. and category of losses set out in with: Compensation Compensation Compensation the Entitlement matrix. distribution in Myagdi distribution in Dhading, Compensation distribution for Udipur ➢ Disbursements against timelines and Parbat districts are Gorkha and Chitwan distribution for substation has been ➢ Identification of the displaced persons under process for districts are under New-Butwal completed and losing land temporarily, e.g., through transmission lines. process for transmission substation has compensation soil disposal, borrow pits, contractors’ Social safeguard lines. Social safeguard been distribution is ongoing camps, been included measures for the APs measures for the APs completedand in Lamjung district for are at various stage of are at various stage of compensation tower pad. ➢ Restoration of social infrastructure and implementation. implementation. distribution is services. ongoing in Palpa ➢ Progress on income and livelihood In process of In MKTLP, training on district under tower restoration activities being implementation of other Computer, driving, pad. No progress in implemented as set out in the income remaining trainings. tailoring, Agriculture Syangja and Parbat restoration plan, for example, utilizing productivity and Crop In DKTLP, skill district. The check replacement land, commencement of Intensification have development training survey & cadastral production, the no. of the displaced been conducted and program on safety for survey of persons trained in employment with implemented. laborers; electrician, transmission line is jobs, Micro-credit disbursed, no. of tailoring, computer, remaining from AP income-generating activities assisted. driving trainings have 80 to sub-station at ➢ Quality of new plots and issue of land been conducted and Badera. titles implemented.

2 Consultation ➢ Consultations organized as scheduled Being complied with: Being complied with: Being complied Being Complied with: and including meetings, groups, and with 12 GRC 5 GRC meeting has 3 GRC meeting has 1 GRC meeting has Grievances community activities. meeting has been been conducted in this been conducted. been conducted. ➢ Knowledge of entitlements by the conducted. reporting period displaced persons.

SASEC-PSEP 34 NEA-ESSD

8th Semiannual Social Monitoring Report July-December, 2020

Monitoring Compliance Status SN Indicators Aspects DKTLP MKTLP KNBTLP UMBTLP

➢ Use of the grievance redresses 1 Public Consultation 7 Public Consultation 20 Pulbic 5 Public Consultation mechanism by the displaced persons. meeting has been meeting has been Consultation meeting has been ➢ Information on the resolution of the conducted for this conducted for this Meetings have conducted for this grievances. reporting period. reporting period. been conducted in reporting period. ➢ Information on the implementation of Altogether 15 peoples Altogether 83 peoples this reporting Altogether 55 peoples the social preparation phase. have participated have participated period. Among total have participated ➢ Implementation of special measures among them 9 were among them 76 were of 210 participants among them 47 were for Indigenous Peoples male and 6 were male and 7 were female. 190 were male and male and 8 were female. 20were Females, female. 3 CDC meetings have 10 were IPs & 8 4 CDC meetings have been conducted for this 2 CDC meetings have were Dalits been conducted for this reporting period. been conducted for this participated at the reporting period. reporting period. meetings. 1 CDC meetings have been conducted for this reporting period. One consultation review meeting has been conducted in this month at New Butwal Substation.

3 Communicatio ➢ Percentage of women out of total Being complied with: Being complied with: Being complied Being Complied with: n and participants. with: 12 GRC 5 GRC meeting has 3 GRC meeting has 1 GRC meeting has Participation ➢ No. of meetings exclusively with meeting has been been conducted in this been conducted. been conducted. women. conducted. reporting period.

SASEC-PSEP 35 NEA-ESSD

8th Semiannual Social Monitoring Report July-December, 2020

Monitoring Compliance Status SN Indicators Aspects DKTLP MKTLP KNBTLP UMBTLP

➢ No. of meetings exclusively with 1 Public Consultation 7 Public Consultation 20 Public 5 Public Consultation vulnerable groups. meeting has been meeting has been consultation meeting has been ➢ No. of meetings at new sites. conducted for this conducted for this meeting has been conducted for this ➢ No. of meetings between hosts and the reporting period. reporting period. conducted in this reporting period. displaced persons. Altogether 15 peoples Altogether 83 peoples reporting period Altogether 55 peoples ➢ Level of participation in meetings (of have participated have participated where total of 210 have participated women, men, and vulnerable groups). among them 9 were among them 76 were people among them 47 were male and 6 were male and 7 were female. male and 8 were ➢ Level of information communicated— participatedamong female. female. adequate or inadequate. 3 CDC meetings have them 190 were mle ➢ Information disclosure. 4 CDC meeting has been conducted for this and 20 were ➢ Translation of information disclosure in been conducted for this reporting period. female. 2 CDC meetings have the local languages reporting period. 1 CDC meeting has been conducted for this been conducted for reporting period. this reporting period.

4 Budget and ➢ Land acquisition and resettlement staff Being complied with: Being complied with: Being complied Being complied with: Time Frame appointed and mobilized on schedule with: The compensation for The compensation for The compensation for for the field and office work. acquired land has been acquired land has been The compensation the affected household ➢ Capacity building and training activities compensated to APs disbursed to APs under for the affected under substation has completed on schedule. under Substation and Substation and tower people under been disbursed and under tower foundation foundations are being substation has compensation ➢ Achieving resettlement are being compensated compensated as per the been disbursed and distribution is ongoing implementation activities against the as per the entitlement entitlement matrix of under tower in Lamjung district for agreed implementation plan. matrix of resettlement resettlement and foundations are tower pad as per the ➢ Funds allocation for resettlement-to- and indigenous people indigenous people plan. being compensated entitlement matrix of resettlement and resettlement agencies on time. plan. The APs under The APs under RoW are in Palpa district as per the entitlement indigenous people ➢ Receipt of scheduled funds by RoW are being being compensated as matrix of plan. resettlement offices. compensated as per the per the decision made

SASEC-PSEP 36 NEA-ESSD

8th Semiannual Social Monitoring Report July-December, 2020

Monitoring Compliance Status SN Indicators Aspects DKTLP MKTLP KNBTLP UMBTLP

➢ Funds disbursement according to the decision made by by Compensation resettlement and resettlement plan. Compensation Determination indigenous people ➢ Social preparation phase as per Determination Committee (CDC). plan. schedule. Committee (CDC). Similarly, APs for ➢ Land acquisition and occupation in Similarly, APs for structure loss, crop loss, time for implementation. structure loss, crop loss, fruits loss, tree loss and fruits loss, tree loss and grass loss are being grass loss are being compensated as per the compensated as per the decision made by decision made by Compensation Compensation Determination Determination Committee (CDC). Committee (CDC).

5 Livelihood ➢ No. of displaced persons under the Being complied with: Being complied with: Beingcomplied with Not Complied with: and Income rehabilitation programs (women, men, • Safety Training has • 12 APs (all IPs) One day social Not implemented the Restoration and vulnerable groups). been provided to participated in awareness livelihood ➢ No. of displaced persons who received 118 laborers. driving training in program scheduled enhancement trainings vocational training (women, men, and • 16 male participants Gorkha. for this reporting and income restoration vulnerable groups). enrolled in the • 8 APs (2 IPs) period has been programs till the date. ➢ Types of training and no. of Electrician training participated in 2 halted due to the participants in each. in Myagdi. months (60 days) outbreak of Corona ➢ No. and percentage of displaced • 20 females long basic Computer Virus COVID-19 persons covered under livelihood participated in the training in Gorkha, which will be programs (women, men, and tailoring training in Tanahun and conducted in next vulnerable groups). Myagdi. Chitwan reporting period. ➢ No. of displaced persons who have • 16 participants have • 25 APs (7 men and restored their income and livelihood been enrolled in 18 women) Computer training participated in 2

SASEC-PSEP 37 NEA-ESSD

8th Semiannual Social Monitoring Report July-December, 2020

Monitoring Compliance Status SN Indicators Aspects DKTLP MKTLP KNBTLP UMBTLP

patterns (women, men, and vulnerable in which 13 were months (60 days) groups). female and 3 were long basic computer ➢ No. of new employment activities. male in Myagdi. training in Dhading • 25 people district. ➢ Extent of participation in rehabilitation participated in • 5 APs (2Ips and 3 programs. driving training (20 Dalits) enrolled in 30 ➢ Extent of participation in vocational male, 5 female, 2 days driving training training programs. IPs and 2 dalits) in in Tanahun and ➢ Degree of satisfaction with support Parbat Gorkha received for livelihood programs. • Remaining trainings • 11 APs (7 Dalits and ➢ Percentage of successful enterprises are in the process of 3 IPs) enrolled in 2 breaking even (women, men, and implementation. months tailoring vulnerable groups). training in Gorkha ➢ Percentage of displaced persons who and Tanahu improved their income (women, men, districts. and vulnerable groups) • 24 APs (9 women & ➢ Percentage of displaced persons who 2 Dalits) enrolled in improved their standard of living 7 days Agriculture (women, men, and vulnerable groups) productivity and ➢ No. of displaced persons with Crop Intensification replacement agriculture land (women, Trainings in Dhading men, and vulnerable groups) • 1-month driving has ➢ Quantity of land owned/contracted by been implemented displaced persons (women, men and in Chitwan district vulnerable groups) No. of households where 10 APs with agricultural equipment participated. • 2 months tailoring training has been implemented for 21 females.

SASEC-PSEP 38 NEA-ESSD

8th Semiannual Social Monitoring Report July-December, 2020

Monitoring Compliance Status SN Indicators Aspects DKTLP MKTLP KNBTLP UMBTLP

• Remaining trainings are in the process of implementation.

6 Benefit ➢ Noticeable changes in patterns of Being complied with: Being complied with: Being Complied Not Complied with: Monitoring occupation, production, and resource with Benefit monitoring can’t Benefit monitoring can’t Benefit monitoring use compared to the pre-project be done yet be done yet Benefit monitoring can’t be done yet situation. becauseproject is still in becauseproject is still in can’t be done yet because project is still ➢ Noticeable changes in income and the initial construction the initial construction because project is in the initial expenditure patterns compared to the phase and Livelihood phase and Livelihood still in the initial construction phase. pre-project situation. and Income Restoration and Income Restoration construction phase ➢ Changes in key social and cultural program is ongoing. program is ongoing. and Livelihood and parameters relating to living standards. Benefits from the Benefits from the Income Restoration ➢ Changes occurred for vulnerable intervention shall be intervention shall be program is groups. analyzed once the analyzed once the ongoing. Benefits ➢ Benefiting from the project to the intervention accrues intervention accrues from the displaced persons. some maturity. some maturity. intervention shall be analyzed once

the intervention accrues some maturity.

SASEC-PSEP 39 NEA-ESSD

8th Semiannual Social Monitoring Report July-December, 2020

Table 20: Monitoring Results in terms of Indigenous Peoples Safeguards

SN Monitoring Indicators Compliance Status Aspects DKTLP MKTLP KNBTLP UMBTLP

1 Demographic ➢ The no. of affected Indigenous Being complied with: Being complied with: Being Complied with: Being Complied with Baseline Peoples (IP) by category of impact, RIPP of DKTLP section has RIPP of MKTLP Household survey has Census survey and gender, age, habitat (village etc.), been prepared / updated section has been been completed in Household survey has income, status and position and has been submitted to prepared/updated and Palpa, Parbat and been completed for ➢ No. of households with handicapped, ADB. has been submitted to Syangja districts where tower pad in Lamjung elderly or invalid members ADB. as household survey. district. Data analysis ➢ No. of female headed households Data analysis is ongoing is ongoing for RIPP ➢ No. of vulnerable households (poor, for RIPP update. update. ➢ elderly) ➢ No. of households by ethnic group ➢ No. of births and deaths 2 Consultation ➢ No. of consultation and participation Being complied with: Being complied with: Being complied with: Being Complied with: and activities that occur meetings, — 1 Public Consultation 7 Public Consultation 20 Public consultation 5 Public Consultation participation information dissemination, brochures; meeting has been meeting has been meeting has been meeting has been flyers, training Percentage of IP conducted for this reporting conducted for this conducted in this conducted for this women as participants; no. of period. Altogether 15 reporting period. reporting period where reporting period. meetings exclusively with IP women peoples have participated Altogether 83 peoples total of 210 people Altogether 55 peoples ➢ Percentage of vulnerable IP groups among them 9 were male have participated participatedamong them have participated represented / attending meetings; no. and 6 were female. among them 76 were 190 were mle and 20 among them 47 were of meetings exclusively with male and 7 were were female. male and 8 were vulnerable IP groups. . female. female. ➢ Languages used at meetings ➢ Good faith negotiations—recording of process, participants, locations, correspondence ➢ Broad community support—record of processes, participants, locations and agreement obtained

SASEC-PSEP 40 NEA-ESSD

8th Semiannual Social Monitoring Report July-December, 2020

SN Monitoring Indicators Compliance Status Aspects DKTLP MKTLP KNBTLP UMBTLP

➢ Consultation and participation progress against plan and budget 3 Mitigation ➢ Progress of implementation of Being complied with: Being complied with: Not Complied with: Not Complied with: mitigation / beneficial measures Measures ESSD has conducted the ESSD has conducted HHs survey and HHs survey and against plan different trainings for the the different trainings cadastral has not been cadastral has not ➢ No. of activities that APs under tower for the APs under completed under RoW been completed occur/completed such as — foundation. tower foundation. so, IPs or affected under RoW so, IPs or construction, livelihood restoration, disadvantaged people affected disbursements, training Implementation of Implementation of have not been finalized disadvantaged people ➢ Percentage progress against remaining Skill remaining Skill under RoW to conduct have not been timelines and budget Development trainings are Development trainings training finalized under RoW in progress are in progress. to conduct training

4 Grievance ➢ Total no. of people/groups using the Being Complied with: Being Complied with: Being Complied with: Being Complied with: Redress grievance redress procedure. 5 GRC meetings have been 3 GRC meetings have 12 GRC meetings have 1 GRC meetings ➢ No. of distinct people/groups. Any IP conducted in this reporting conducted in this conducted in this have conducted in this group with significantly more period where 49 people reporting period where reporting period where reporting period grievances? participated (45 male and 4 24 people participated 139 people participated where 10 people ➢ How many times has a household female). (23 male and 1 (123 male and 16 participated among submitted the same grievance? female). female). them all were male. ➢ No. of grievances resolved? ➢ Length of time taken to be resolved? No any grievances in No any grievance has ➢ Types of grievance categories and New butwal section for been recorded in this prevalence this reporting period. reporting period. The previously recorded 2 Among the previously grievance is also in recorded grievances, 2 process of solving are still in process of solving

SASEC-PSEP 41 NEA-ESSD

8th Semiannual Social Monitoring Report July-December, 2020

SN Monitoring Indicators Compliance Status Aspects DKTLP MKTLP KNBTLP UMBTLP

5 Implementation ➢ Identified delays— (days, cost) due to No problems were identified No problems were Yes, one problem was No problems were personnel, capacity, insufficient during this reporting period. identified during this identified and solved identified during this Problems funds, etc. reporting period. during this period. reporting period. ➢ No. of times implementation schedule revised

SASEC-PSEP 42 NEA-ESSD

8th Semiannual Social Monitoring Report July-December, 2020 6. GRIEVANCE REDRESSAL MECHANISM Land Acquisition Act, 1977 encourages forming Grievance Redress Committee (GRC) to solve the grievances related to the acquisition that may be submitted in land acquisition process. PMU issued the letter to MC/RMC for formation of GRC. In the reporting period of July to December 2020, 2 grievances have been registered throughout the SASEC TL- projects. Likewise, 21 GRC meetings have been conducted in which total 222 participants have participated among them 201 were male and 21 were female. Table 21: Summary of the Grievances registered and GRC meetings

Sub- No. of No of GRC Participants Total Topics of discussion/ Grievance projects Grievances meetings Agenda Status Recorded in conducted Male Female this this reporting reporting period period

Regarding the Ongoing DKTLP 0 5 45 4 49 compensation of land loss Previously and structural loss recorded

Regarding the Ongoing MKTLP 0 3 23 1 24 compensation of land loss Previously and structural loss recorded

one has been Regrding land loss, crop solved and KNBTLP 2 12 123 16 139 loss and structural loss the other is compensation still on process

NBBTLP NA NA NA NA NA NA NA

Ongoing Regarding the demand of UMBTLP 0 1 10 0 10 Previously CSR recorded

Total 2 21 201 21 222

The details of Grievance Redress Committee Meeting Matrix have been attached in Annexure 4. Likewise, letter related to the recorded grievances have been attached in Annexure 5 of this report.

7. PUBLIC CONSULTATION AND PARTICIPATION AND INFORMATION DISCLOSURE While implementing the RIPP, meaningful consultation program with project-affected people was carried out, in line with requirements pertaining to receive compensation and compensation determination procedure. The meaningful consultation ensures the presence of different categories of representatives (i.e., representative sampling) in the consultation process so as to obtain a balanced public opinion, equitable and non-discriminatory participation, provide transparent and factual information with prior information about the project, systematic documentation of the process, public disclosure of relevant parts etc. The

SASEC-PSEP 43 NEA-ESSD

8th Semiannual Social Monitoring Report July-December, 2020 consultations in instant case were so designed that these basic criteria of a truly participative and meaningful consultation process are meet in its letter and spirit.

Table 22: Summary of Public Consultation Meetings

No. of Consultations Participants in this Semiannual Informations Disseminated in TL Projects Reporting Preiod Total the Meeting (July to December Male Female 2020) Regarding the resolution of the landslide by visiting the site for DKTLP 1 9 6 15 the protection of the landslide area by the project.

Disscused on the construction status of shatighat and community building supported by ESSD under CSR activity. Requested with PAFs, local community and ward Office of MKTLP 7 76 7 83 Siddhalek RM-7, Dhading to create positive environment among community to start the foundation work of AP24E/0 and AP 24F/0

Affected person are demanding to pay compensation but project is yet to arrange paying compensation for valuable land, paddy field and access KNBTLP 20 190 20 210 roads of 33B and 43 and 43A. PAFs were kept maintaining social diistancing in their own area.

To provide appropriate compensation to the APs by the contractor for the use of land as UMBTLP 5 47 8 55 access road and crops loss. Implementation of CSR within the limit of CSR fund in dordi 1.

Total 33 322 41 363

Percentage 89% 11% 100%

Upto this semiannual reporting period from July to December 2020, a total of 33 consultations were carried out in SASEC TL Projects in which altogether 363 local participants have participated. Of the participants, around (89%) were male and (11%) were female (Table-23). In the meeting, discussion was made with the participants regarding the skill development training objectives, training venue and convenient time for training. Similarly, all the necessary information about the project and its merit demerits were dissipated well in advance to address information asymmetry in target group. The public, CFUGs, business owners, affected people

SASEC-PSEP 44 NEA-ESSD

8th Semiannual Social Monitoring Report July-December, 2020 and local level leaders were informed about the project activities. The consultation also focused on entitlement matrix of the project and compensation receiving procedure. The techniques were observation, consultation meetings, interviews and structured questionnaires. These consultations provided inputs for identification of the needs of the communities and the relevant stakeholders. The detail of public consultation matrix of public consultation has been attached in Annexure 6. The consulted people were informed about different aspects of the projects and likely about resettlement impacts and mitigation measures. They were also informed about the (i) process of assessing resettlement and confirming the scope of impacts (ii) process of compensation determination in accordance to the Land Acquisition Act 1977 and provisions of compensation and other assistance made in the Entitlement Matrix (iii) Mitigation measures including livelihood restoration and enhancement programs for PAF.

8. CORRECTIVE ACTIONS FOR NON-COMPLIANCE AND MAJOR GAPS Following corrective actions are required in order to improve the monitoring activities, which has been presented in Table 23: Table 23: Corrective actions for non-compliance

SN Issues Corrective actions Responsibility Remarks 1 Delay in implementation of Entitlement provisioned in PMO Office and RIPP entitlement matrix entitlement matrix to be PSC provided to affected HHs soon.

9. RECOMMENDATION FOR MONITORING ADJUSTMENT The monitoring of social safeguard activities and implementation will be continued during the project implementation. There is no adjustement required for monitoring.

10. INSTITUTIONAL ARRANGEMENT FOR MONITORING 10.1 Central Level Arrangement 10.1.1 Environment and Social Studies Department (ESSD) The scope of ESSD engagement based on MOU signed with PMD and ESSD is given here below: • ESSD shall mobilize environmental/social staff to the site for the environmental management. • ESSD will establish site based ESMU offices. • ESSD shall work in coordination with the PSC safeguard specialists to avoid any duplication of jobs. • ESSD shall be responsible for implementation of environmental, social measures including GESI. • ESSD shall be responsible for compliances and impact monitoring, assist project for grievances handling. • ESSD shall assist implementation of resettlement plan.

10.1.2 Central Level Line Agencies The central level line agencies such as Ministry of Energy, Ministry of Forest and Department of Electricity Development have responsibility for the monitoring of project activities concerning

SASEC-PSEP 45 NEA-ESSD

8th Semiannual Social Monitoring Report July-December, 2020 Environmental and Social Management, Mitigation and Monitoring Plan. ESSD is coordinating with central level line agencies regarding the monitoring work. As the concerned line agency, Department of Forest is responsible for the implementation of forestation program as per the Procedural Guideline for the Use of Forest Land 2063.

10.2 Project Level Arrangement 10.2.1 Project Management Directorate, NEA (PMD Office) The PMD office is overall responsible for the implementation of RIPP. It is also deputed a Senior Environment Specialist (SES) and a Senior Social Safeguards specialist (SSS) in the PMD office for Safeguard implementation and monitoring works of the SASEC TL Projects. The responsibility of safeguard specialist to cooperate with and provide guidance to the social safeguards teams of NEA on all tasks related in updating and finalizing the Resettlement and Indigenous Peoples Plan (RIPP), to provide guidance to NEA’s concerned staff responsible for social safeguards for detailed census surveys of affected persons and update the list of affected and displaced persons, to provide required training (in –house and on-the job) to the enumerators and surveyors to carry out the census survey and work closely with the NEA team to involve them in the project planning from the initial period.

10.2.2 Project Manager The Kali Gandaki Corridor (Dana-Kushma Section) and Marsyangdi-Kathmandu section Project 220 kV TL Project Manager Office has been established under the organizational setup of PMD. The Project Manager will be responsible for establishment of Compensation Determination Committee (CDC). He will be responsible to coordinate valuation by the valuation committee (CDC) and finalization of compensation packages, to provide necessary guidance in the classification, and development of all social safeguards documents, including the provision of training in the development and implementation of RIPP, to prepare Update land acquisition and resettlement impact assessment based on all available data on land acquisition as per the detailed layout for each subproject and collect additional data as required and to make sure the allocation of necessary budget for the implementation of the program. He will be responsible for the overall coordination of the work and make final decision on environmental, social and public concern issues.

10.2.3. Environment and Social Monitoring Unit (ESMU) Environment and Social Monitoring Unit has been established under ESSD umbrella for day to day environmental and social monitoring of the project (One in Dana-Kushma Section, where it has one Environmental Safeguard Officer and one Social Safeguard Officer) , (One in Marsyangdi- Kathmandu section, where it has two Environmental Safeguard Officers and Two Social Safeguard Officers ), (One in Kushma New Butwal Section, where it has two Environmental Safeguard Officer and two Social Safeguard Officer) and (One in Udipur- Markichok Section where it has one Environmental Safeguard Officer and one Social Safeguard Officer) in coordination of work with PAFs, local communities, Rural Municipality/Municipality and district level line agencies. The unit has site office for day-to-day monitoring of the social and environmental impacts and responsible for submitting the compliance monitoring reports to ESSD.

10.2.4 Project Supervision Consultant (PSC) The project supervision consultant will have social safeguard specialist. They will be responsible for updating/ finalizing the RIPP based on the final engineering design and check survey to be done by the construction contractor. This will be done in close coordination with

SASEC-PSEP 46 NEA-ESSD

8th Semiannual Social Monitoring Report July-December, 2020 PMU/PIU. The consultant will further assist in overall supervision of the projects and ensure all plans are implemented in a smooth and timely manner in accordance with the provisions of the RIPP. They will also prepare and implement training and capacity development programs for resettlement and indigenous planning for the PIU and PMU of NEA and their concerned staff and will closely work with the PMU and PIUs to ensure displaced persons and compensated before the construction activities. The PSC safeguard specialist will also be responsible for assisting NEA for preparation of monitoring reports.

10.2.5 Compensation Determination Committee CDC’s have been formed in each district of project site to fix compensation for loss of land, structure, crops and private property. The CDC is comprised of Chief District Officer, District Land Revenue Officer, DCC Representative, Project Representative and PAP/HHs Representative. The main function of the CDC is confirmation of entitled process, assessment/Identification of PAP/HHs, compensation determination for land and private property and grievance resolution. It is in process to establish CDC in Kathmandu district. CDC is formed in Gorkha, Dhading and Chitwan districts in MKTLP, Myagdi and Parbat districts in DKTLP, Nawalparasi district in KNBTLP and Lamjung district in UMBTLP.

10.2.6 Construction Contractor The construction contractor is responsible for implementation of some of the social mitigation measures specified in his part and compliance with the tender clauses. He is responsible for implementation of construction related mitigation measures such as occupational safety, recruitment of local labor, health and sanitation measures etc. In MKTLP – TATA Project Limited (working for Transmission Line) and SHENZHEN Farad (working for Substation - Matatirtha and Markichowk) are responsible construction contractor. In DKTLP, TATA and Chints Limited are responsible construction contractors. Similarly, in KNBTLP, TATA Projects Limited (working in Substation) and LNT Limited (working in Tower foundation) are responsible construction contractor. In UMBTLP, Pinggao Group Co. Ltd. is responsible construction contractor for Transmission line and Tower foundation.

SASEC-PSEP 47 NEA-ESSD

8th Semiannual Social Monitoring Report July-December, 2020 11. PROPOSED MAJOR ITEM OF FOCUS FOR NEXT REPORT The next report will be focused in completing the following activities in different subprojects:

Table 24: Proposed Major items of focus for the Next Report

Subprojects General items of focus for next Specific items of focus for next report Achievement in this reporting period report

DKTLP • Field visit to different sites • Tree cutting lagat monitoring Activities • Tree cutting lagat data have been recorded from and facilitate to solve the • Follow up action for the issue of AP 10 to different CFs and submitted to the Project. project related issues AP 11 for the decision to be made either • Organized informal Public consultation with affected the structure lies under the RoW or not. HHs of of AP 10 to AP 11. • Compensation data details included. Household survey data details included under ROW Structure. MKTLP • Field visit in project sites, • Organize public consultation • Carried out joint field visit with NEA and TATA team at coordination with • Preparatory work for the implementation project sites. stakeholders and interaction of remaining skill development training to • One-month basic skill training on driving started for with PAFs affected HHs, project affected HHs. • Coordination with PMO Office and TATA • Affected HHs received land loss compensation under pvt. Row, crop loss compensation and fodder tree loss • Assist affected HHs for receiving compensation. compensation • Organized public consultation with community at Gorkha • Planning for the implementation of • Organized Public consultation with affected HHs at Remaining training training to project siddhalek RM-7 affected HHs

KNBTLP • Field visit to different sites • Conduct GRC and public consultation • Carried out joint field visit with NEA and L&T team. and facilitate to solve the meeting for RoWclerance • Organized GRCs meetings project related issues • Coordination with Ward Chairs and other stakeholders. • Carried out joint field visit with NEA and L&T team. • Affected HHs received land loss compensation under tower PAD, Row, crop loss compensation and fodder tree loss compensation • Organized consultation meeting with project, contractor & ESMU regarding safety measures during COVID-19 SASEC-PSEP 48 NEA-ESSD

8th Semiannual Social Monitoring Report July-December, 2020

pandemic for the continuation of the construction activities at new butwal SS. NBBTLP NA NA NA

UMBTLP • Field visit in project sites, • Organize GRC meetingand public • Organized Public Consultation meeting with affected coordination with consultation HHs stakeholders and interaction • Coordination with PMO Office and • Tree marking monitoring for the ongoing work at with PAFs. contractor. Lamjung • Regular monitoring of • Assist affected HHs for receiving • Participated and assisted for ongoing Cadastral survey construction site compensation • Planning of GRC formation in Bhanu Municipality and Aanbukhaireni RM

SASEC-PSEP 49 NEA-ESSD

8th Semiannual Social Monitoring Report July-December, 2020

ANNEXURES

8th Semiannual Social Monitoring Report July-December, 2020

Annexure 1: Tower Foundation and Tower Erection Details

8th Semiannual Social Monitoring Report July-December, 2020 Annexure 1: Tower Foundation and Tower Erection Details

DKTLP

PROJECT: DANA - KUSHMA 220KV TRANSMISSION LINE

Tranmission Line Update

Parba Foundation t Tower Location in Area Total Unde Length Tower Leng Angle r (M) Under Erecti Stringing th Remarks Location Point Complet J progr S. No. Progre on (M) ed u Ailani ess ss Private n (Semi Land gl Gvt) e 0 Gentry 0

1 AP01 1 ✓ 1 70 70 Kushma 2, 2 AP01A 1 ✓ 1 123 193 Khurkot 3 AP01B 1 ✓ 1 360 553 4 AP01C 1 ✓ 1 527 1080 5 AP02 1 ✓ 1 257 1337 AP02/ 6 ✓ 487 1824 1 1 1 AP02/ 7 ✓ 331 2155 Kushma 1, Pang 2 1 1 AP02A 8 ✓ 265 2420 /0 1 1 9 AP03 1 ✓ 1 390 2810

8th Semiannual Social Monitoring Report July-December, 2020

10 AP04 1 ✓ ✓ 1 395 3205 11 AP05 1 ✓ 1 649 3854 12 AP06 1 ✓ 1 951 4805 Jaljala 8, 13 AP06A ✓ 350 5155 1 1 Nanglibang 14 AP06B 1 ✓ 1 385 5540 15 AP07 1 ✓ 1 314 5854 16 AP07A 1 ✓ 1 1062 6916

17 AP08 1 ✓ 1 111 7027

18 AP08A 1 ✓ 1 169 7196

19 AP09 1 ✓ 1 151 7347 Jaljala 8, Farse

20 AP09A 1 ✓ 1 219 7566

21 AP09B 1 ✓ 1 215 7781

22 AP09C 1 ✓ 1 270 8051 23 AP10 1 ✓ 1 80 8131 24 AP11 1 ✓ 1 438 8569 25 AP11A 1 ✓ 1 291 8860 Jaljala 7, Farse 26 AP12 1 ✓ 1 352 9212 27 AP13 1 ✓ 1 497 9709 AP13/ 28 ✓ 92 9801 1 1 1 Jaljala 7, 29 AP13A 1 ✓ 1 267 10068 Milanchok 282 30 AP13B 1 ✓ 1 10350

8th Semiannual Social Monitoring Report July-December, 2020

31 AP13C 1 ✓ 1 185 10535 Reconstructi 32 AP14 ✓ 104 10639 1 1 1 on AP14/ 33 ✓ 107 10746 1 1 1 34 AP14A 1 ✓ 1 80 10826 35 AP15 1 ✓ 1 411 11237 ✓ 36 AP16 1 1 768 12005 37 AP16A 1 ✓ 1 47 12052

38 AP17 1 ✓ 1 671 12723 Jaljala 4, 39 AP17A 1 ✓ 1 131 12854 Fadkedhunga 40 AP17B 1 ✓ 1 425 13279 41 AP18 1 ✓ 1 251 13530 42 AP18A 1 ✓ 1 280 13810 43 AP18B 1 ✓ 1 286 14096 44 AP18C 1 ✓ 1 159 14255 Jaljala 3, Mallaj 45 AP19 1 ✓ 1 187 14442 46 AP20 1 ✓ 1 305 14747 47 AP21 1 ✓ 1 355 15102 48 AP21A 1 ✓ 1 337 15439 Jaljala 2, 49 AP22 1 ✓ 1 104 15543 Majhfat 50 AP23 1 ✓ 1 283 15826 51 AP24 1 ✓ 1 330 16156

8th Semiannual Social Monitoring Report July-December, 2020

52 AP24A 1 ✓ 1 547 16703 53 AP25 1 ✓ 1 413 17116 54 AP25A 1 ✓ 1 256 17372

55 AP25B 1 ✓ 1 318 17690 Jaljala 1, 56 AP26 1 ✓ 1 310 18000 Sub 7 Total 56 0 40 9 56 0

Distri Myagd ct: i Remaining Unde Under Tower Angle Complet J r S. No. Progre u Ailani Erecti Remarks Location Point ed Private progr ss n (Semi on Land ess gl Gvt) e 57 27/0 1 ✓ 1 485 18485 58 27A/0 1 ✓ 1 317 18802 59 27B/0 ✓ 388 19190 1 1 Raghuganga 3, Ranipauwa 60 28/0 1 ✓ 1 97 19287 ✓ 61 28A/0 1 1 292 19579 62 29/0 1 ✓ 1 265 19844 63 30/0 ✓ 881 20725 1 1 64 31/0 1 ✓ 1 577 21302 Raghuganga 2, 65 32/0 1 ✓ 1 701 22003 Rakhu 66 32A/0 1 ✓ 1 551 22554

8th Semiannual Social Monitoring Report July-December, 2020

67 33/0 1 ✓ 1 553 23107 68 33A/0 1 ✓ 1 179 23286 69 33B/0 1 ✓ 1 404 23690 70 34/0 1 ✓ 1 407 24097 71 34A/0 1 ✓ 1 277 24374 72 34B/0 1 ✓ 1 284 24658 73 35/0 1 ✓ 1 602 25260 74 35A/0 1 ✓ 1 47 25307 75 35B/0 1 ✓ 1 675 25982 Raghuganga 1, Baduk 76 35C/0 1 ✓ 1 329 26311 77 36/0 1 ✓ 1 197 26508 78 36A/0 1 ✓ 1 385 26893 79 37/0 1 ✓ 1 333 27226 80 38/0 1 ✓ 1 385 27611 81 39/0 1 ✓ 1 541 28152 Annapurna 7, 82 39A/0 1 ✓ Guthi 1 228 28380 Histan 83 39B/0 1 ✓ Guthi 1 265 28645 84 39C/0 1 ✓ 1 217 28862 Annapurna 1, 85 39D/0 ✓ 418 29280 1 1 Doba Annapurna 6, 86 40/0 ✓ 541 29821 1 1 Ghar Annapurna 1, 87 40A/0 ✓ 727 30548 1 1 Doba Annapurna 1, 88 41/0 ✓ 57 30605 1 1 Doba

8th Semiannual Social Monitoring Report July-December, 2020

89 41A/0 ✓ 395 31000 1 1 Annapurna 6, Dhirchang 90 41B/0 ✓ 242 31242 1 1 Annapurna 6, 91 42/0 ✓ 321 31563 1 1 Ratopani 92 42A/0 ✓ 460 32023 Annapurna 6, 1 1 Pokharebagar 93 42B/0 1 ✓ 1 280 32303 Annapurna 6, baiseri 94 43/0 ✓ 224 32527 1 1 Completed 95 44/0 ✓ 1190 33717 1 1 Annapurna 2, 96 44A/0 1 ✓ 1 404 34121 Tatopani 97 45/0 1 ✓ 1 347 34468 98 46/0 1 ✓ 1 516 34984 99 46A/0 1 ✓ 1 92 35076

100 46B/0 1 ✓ 1 174 35250 101 47/0 1 ✓ 1 149 35399

102 47A/0 1 ✓ 1 465 35864 Annapurna 3, 103 ✓ 36338 47B/0 1 1 474 Dana 104 47C/0 1 ✓ 1 285 36623

105 48/0 1 ✓ 1 139 36762

106 48A/0 1 ✓ 1 257 37019

107 49/0 1 ✓ 1 201 37220

108 50/0 1 ✓ 1 426 37646

8th Semiannual Social Monitoring Report July-December, 2020

109 51/0 1 ✓ 1 906 38552 DE 110 ✓ 38868 (52) 1 1 316

Gentry 80 38948 Sub 1 Total 54 47 6 54 0

G. Total 110 0 110 0 38948

Work in Progress Completed ROW issue

8th Semiannual Social Monitoring Report July-December, 2020 MKTLP

Kathmandu

Foundation Tower Location Tow Stringing S. Under Angle er Earthin Remark No Under progres Under Location Length(m) Point Comple Private Ailani/ Erec Complet g s . Progres Ailani s Progres ted Land Govt tion e s Forest s

1 TP 0 0 0 0 0 0 Bandbhanjyan g, Ktm. AP-0/0 Bandbhanjyan 2 1 1 1 0 110 110 110 DE g 110 Bandbhanjyan 3 AP-1/0 1 1 1 0 621 621 621 g 621 Bandbhanjyan 4 AP-2/0 1 1 1 0 406 406 406 g 406 Bandbhanjyan 5 AP-2/A 1 1 1 0 553 553 553 g 553 Total 4 0 3 0 0 1 4 0 1690 1690 1690 0 KTM 1690

8th Semiannual Social Monitoring Report July-December, 2020 Dhading

Under Tower Location Stringing S. Angle Complet Tower Under Earthi Length Progre Private Ailani/Go Under Remarks Location No. Point ed Ailani Forest Erection progress Complete ng (m) ss Land vt Progress Naubise, 1 AP-2/B 1 1 0 0 0 1 403.0 0.0 0.0 Dhunibesi 403 Naubise, 2 AP-2/C 1 1 0 0 0 1 477.0 0.0 0.0 Dhunibesi 477 Naubise, 3 AP-3/0 1 1 1 78.0 0.0 0.0 Dhunibesi 78 Naubise, 4 AP-4/0 1 0.0 0.0 0.0 1 Dhunibesi 404 Naubise, 5 AP-5/0 1 1 1 1027.0 0.0 0.0 Dhunibesi 1027 Naubise, 6 AP-5/A/0 1 1 1 423.0 0.0 0.0 Dhunibesi 423 Naubise, 7 AP-5/B/0 1 1 1 138.0 0.0 0.0 Dhunibesi 138 Naubise, 8 AP-6/0 1 1 0.0 0.0 0.0 Dhunibesi 499 Naubise, 9 AP-6/A/0 1 1 0.0 0.0 0.0 Dhunibesi 268 Naubise, 10 AP-7/0 1 1 1 328.0 0.0 0.0 Dhunibesi 328 Naubise, 11 AP-7/A 1 1 1 181.0 0.0 0.0 Dhunibesi 181 Naubise, 12 AP-7/B 1 1 1 106.0 0.0 0.0 Dhunibesi 106 Naubise, 13 AP-7/C 1 1 1 248.0 0.0 0.0 Dhunibesi 248 Naubise, 14 AP-7/D 1 1 1 388.0 0.0 0.0 Dhunibesi 388 Naubise, 15 AP-7/D/1 1 1 1 0.0 0.0 0.0 Dhunibesi 193 Naubise, 16 AP-7/D/2 1 1 1 0.0 0.0 0.0 Dhunibesi 158 Naubise, 17 AP-7/E 1 1 1 176.0 0.0 0.0 Dhunibesi 176 18 AP8/0 1 1 1 240.0 0.0 0.0 240 19 AP8/1 1 1 1 407.0 0.0 0.0 Archale 407

8th Semiannual Social Monitoring Report July-December, 2020

Under Tower Location Stringing S. Angle Complet Tower Under Earthi Length Progre Private Ailani/Go Under Remarks Location No. Point ed Ailani Forest Erection progress Complete ng (m) ss Land vt Progress 20 AP8/2 1 1 1 296.0 0.0 0.0 Archale 296 21 AP-8/A 1 1 1 193.0 0.0 0.0 Ganishe 193 22 AP-8/B 1 1 1 351.0 0.0 0.0 GanisheChaur 351 23 AP-9/0 1 1 1 368.0 0.0 0.0 GanisheChaur 368 24 AP-10/0 1 1 1 367.0 0.0 0.0 Pandit Pauwa 367 25 AP-11/0 1 1 1 325.0 0.0 0.0 Pandit Pauwa 325 26 AP-11/A 1 1 1 271.0 0.0 0.0 Pandit Pauwa 271 27 AP-11/B 1 1 1 324.0 0.0 0.0 Pandit Pauwa 324 28 AP-11/C 1 1 1 208 0.0 0.0 Pandit Pauwa 208 29 AP-12/0 1 1 1 218.0 0.0 0.0 Pandit Pauwa 218 30 AP-12A 1 1 1 500.0 0.0 0.0 Kebalpur 500 31 AP-12/A/1 1 1 1 188.0 0.0 0.0 Kebalpur 188 32 AP-12/B 1 1 1 142.0 0.0 0.0 Kebalpur 142 33 AP-13/0 1 1 1 376.0 0.0 0.0 Kebalpur 376 34 AP-13/A 1 1 1 301.0 0.0 0.0 Kebalpur 301 35 AP-13/B 1 1 1 454.0 0.0 0.0 Kebalpur 454 36 AP-13/C 1 1 1 384.0 0.0 0.0 Kebalpur 384 37 AP-13/D 1 1 1 551.0 0.0 0.0 Kebalpur 551 38 AP-14/0 1 1 1 479.0 0.0 0.0 Kebalpur 479 39 AP-14/A 1 1 1 515.0 0.0 0.0 Kebalpur 515 40 AP-14/B 1 1 1 135.0 0.0 0.0 Kebalpur 135 41 AP-14/C 1 1 1 516.0 0.0 0.0 Kebalpur 516 42 AP-15/0 1 1 1 301.0 0.0 0.0 Kebalpur 301 43 AP-16/0 1 1 1 504.0 0.0 0.0 Goganpani 504 44 AP-16/A 1 1 1 340.0 0.0 0.0 Goganpani 340 45 AP-16/B 1 1 1 151.0 0.0 0.0 Goganpani 151 46 AP-16/C 1 1 1 177.0 0.0 0.0 Goganpani 177 47 AP-17/0 1 1 1 663.0 0.0 0.0 Goganpani 663 48 AP-17/A 1 1 1 407.0 0.0 0.0 Goganpani 407 49 AP-17/B 1 1 1 465.0 0.0 0.0 Goganpani 465 50 AP-18/0 1 1 1 778.0 0.0 0.0 Goganpani 778

8th Semiannual Social Monitoring Report July-December, 2020

Under Tower Location Stringing S. Angle Complet Tower Under Earthi Length Progre Private Ailani/Go Under Remarks Location No. Point ed Ailani Forest Erection progress Complete ng (m) ss Land vt Progress 51 AP-18/A 1 1 1 1000.0 0.0 1 Goganpani 1000 52 AP-18/B 1 1 1 248.0 0.0 1 Goganpani 248 53 AP-18/B/1 1 1 1 154.0 0.0 0.0 Goganpani 154 54 AP-18/C 1 1 1 250.0 0.0 0.0 Goganpani 250 55 AP19/0 1 1 1 693.0 0.0 1 Goganpani 693 56 AP-19/A 1 1 1 430.0 0.0 1 Goganpani 430 57 AP-19/B 1 1 1 104.0 0.0 1 Goganpani 104 58 AP-19/C 1 1 1 605.0 0.0 0.0 Goganpani 605 59 AP-20/0 1 1 1 272 0.0 0 Galchhi 272 60 AP-20/A 1 1 1 343 0.0 0 Galchhi 343 61 AP-20/B 1 1 1 492 0.0 0 Galchhi 492 62 AP-20/C 1 1 1 188 0.0 0 Galchhi 188 63 AP-20/D 1 1 1 429 0.0 0 Galchhi (Kalleri) 429 64 AP-21/0 1 1 1 108 0.0 0 Galchhi 108 65 AP-21/1 1 1 1 355 0.0 0 Galchhi 355 66 AP-21/1/1 1 1 1 203 0.0 0 Galchhi 198 67 AP-21/A 1 1 1 203 0.0 0 Galchhi 203 68 AP-21/B 1 1 1 391 0.0 0 Galchhi 391 69 AP-21/C 1 1 1 573 0.0 1 Galchhi 573 70 AP-21/D 1 1 1 365 0.0 1 Galchhi 365 71 AP-21/E 1 1 1 214 0.0 1 Galchhi 214 72 AP-21/F 1 1 1 327 0.0 1 Galchhi 327 73 AP-21/G 1 1 1 542 0.0 0 Baireni 542 74 AP-21/H 1 1 1 533 0.0 0 Baireni 533 75 AP-21/I 1 1 1 432 0.0 0 Baireni 432 76 AP-21/J 1 1 1 174 0.0 0 Baireni 174 77 AP-22/0 1 1 1 822 0.0 1 Pida 822 78 AP-23/0 1 1 1 424 0.0 1 Pida 424 79 AP-23/A 1 1 1 702 0.0 1 Pipaltar, Kumpur 702 80 AP-24/0 1 1 1 403 0.0 1 Pipaltar, Kumpur 403 81 AP-24/1 1 1 1 425 0.0 1 Pipaltar, Kumpur 425

8th Semiannual Social Monitoring Report July-December, 2020

Under Tower Location Stringing S. Angle Complet Tower Under Earthi Length Progre Private Ailani/Go Under Remarks Location No. Point ed Ailani Forest Erection progress Complete ng (m) ss Land vt Progress 82 AP-24/A 1 1 1 143 0.0 1 Pipaltar, Kumpur 143 83 AP-24/B 1 1 1 532 0.0 1 Pipaltar, Kumpur 532 84 AP-24/C 1 1 1 145 0.0 1 Pipaltar, Kumpur 145 85 AP-24/D 1 1 1 184 0.0 1 Pipaltar, Kumpur 184 86 AP-24/D/1 1 1 1 274 0.0 1 Pipaltar, Kumpur 274 87 AP-24/D/2 1 1 1 381 0 1 Pipaltar, Kumpur 381 88 AP-24/D/3 1 1 1 0 0 0 Pipaltar, Kumpur 350 ROW 89 AP-24/E 1 0 0 0 Pipaltar, Kumpur Issue 299 90 AP-24/F 1 0 0 0 Pipaltar, Kumpur 365 91 AP-24/G 1 1 1 0 0 1 Pipaltar, Kumpur 901 92 AP-25/0 1 1 1 115 0 1 Chhapdanda 115 93 AP-25/A 1 1 1 277 0 1 Chhapdanda 277 94 AP-25/B 1 1 1 187 0 1 Chhapdanda 187 95 AP-25/B/1 1 1 1 273 0 1 Chhapdanda 273 96 AP-25/C 1 1 1 425 0 0 Chhapdanda 425 97 AP-26/0 1 1 1 492 0 1 Chhapdanda 492 98 AP-26/A 1 1 1 125 0 1 Kumpur (Siddalek) 125 99 AP-27/0 1 1 1 641 0 1 Kumpur 641 100 AP-27/A 1 1 1 320 0 0 Kumpur 320 101 AP-27/A/1 1 1 1 59 0 0 Kumpur 59 102 AP-27/B 1 1 1 403 0 0 Kumpur 403 103 AP-27/C 1 1 1 136 0 0 Kumpur 136 104 AP-27/D 1 1 1 308 0 1 Kumpur 308 105 AP-27/E 1 1 1 149 0 1 Kumpur 149 106 AP-28/0 1 1 1 740 0 1 Kumpur 740 Dhading Besi 107 AP-28/A 1 1 1 563 0 1 Road 563 108 AP-29/0 1 1 1 370 0 0 Malekhu 370 109 AP-29/A 1 1 1 561 0 0 Malekhu 561 110 AP-29/B 1 1 1 313 0 Malekhu 313

8th Semiannual Social Monitoring Report July-December, 2020

Under Tower Location Stringing S. Angle Complet Tower Under Earthi Length Progre Private Ailani/Go Under Remarks Location No. Point ed Ailani Forest Erection progress Complete ng (m) ss Land vt Progress 111 AP-30/0 1 1 1 206 0 0 Malekhu 206 112 AP-30/A 1 1 1 79 0 Malekhu 79 113 AP-31/0 1 1 1 657 0 1 Salang 657 114 AP-31/1 1 1 1 353 0 1 Salang 353 115 AP-31/2 1 1 1 205 0 1 Salang 205 116 AP-31/A 1 1 1 472 0 1 Salang 472 117 AP-32/0 1 1 1 390 0 1 Salang 390 118 AP-32/1 1 1 1 371 0 1 Salang 371 119 AP-33/0 1 1 1 381 0 1 Salang 381 120 AP-33/A 1 1 1 186 0 1 Salang 186 121 AP-33/B 1 1 1 71 0 1 Salang 71 122 AP-33/B/1 1 1 1 234 0 1 Salang 410 123 AP-34/0 1 1 1 234 0 1 Salang 234 124 AP-34/A 1 1 1 338 0 0 Benighat 338 125 AP-34/A/1 1 1 1 324 0 1 Salang 324 126 AP-35/0 1 1 1 98 0 1 Salang 98 127 AP-37/0 1 1 1 705 0 1 Bishaltar 705 128 AP-37/A 1 1 1 327 0 1 Bishaltar 327 129 AP-43/B 1 1 1 401 0 1 Jogimara 401 130 AP-44/0 1 1 1 599 0 1 Jogimara 599 131 AP-44/A 1 1 1 166 0 1 Jogimara 166 132 AP-45/0 1 1 1 484 0 1 Jogimara 484 133 AP-46/0 1 1 1 790 0 1 Jogimara 790 134 AP-46/1 1 1 1 260 0 1 Jogimara 260 135 AP-46/A 1 1 1 251 0 1 Jogimara 251 136 AP-46/B 1 1 1 510 0 1 Jogimara 510 137 AP-46/C 1 1 1 449 0 1 Jogimara 449 138 AP-47/0 1 1 1 121 0 1 Jogimara 121 139 AP-47/A 1 1 1 382 0 1 Jogimara 382 140 AP-47/B 1 1 1 918 0 1 Jogimara 918 141 AP-47/C 1 1 1 242 0 1 Jogimara 242

8th Semiannual Social Monitoring Report July-December, 2020

Under Tower Location Stringing S. Angle Complet Tower Under Earthi Length Progre Private Ailani/Go Under Remarks Location No. Point ed Ailani Forest Erection progress Complete ng (m) ss Land vt Progress 142 AP-47/D 1 1 1 327 0 1 Jogimara 327 143 AP-48/0 1 1 1 150 0 1 Jogimara 150 Total (Dhading) 141 63 22 32 26 141 48473 0 62 0 0 51677

8th Semiannual Social Monitoring Report July-December, 2020 Chitwan

Remaining Stringing

Angle Under Ailani Tower Under S. No. Completed Private Under Earthing Remarks Location Point Progress Jungle (Semi Erection progress Complete Land Progress Gvt)

1 AP-49/0 1 1 0 0 0 Darechowk 2 AP-49/A 1 1 0 0 0 Darechowk 3 AP-49/B 1 1 0 0 1 Darechowk 4 AP-50/0 1 1 0 275 1 Darechowk 5 AP-50/A 1 1 172 0 1 Darechowk 6 AP-51/0 1 1 409 0 1 Darechowk 7 AP-51/A 1 1 213 0 1 Darechowk 8 AP-51/B 1 1 584 0 1 Darechowk 9 AP-52/0 1 1 323 0 1 Darechowk 10 AP-52/A 1 1 0 0 0 Darechowk 11 AP-52/B 1 1 0 0 1 Darechowk 12 AP-53/0 1 1 0 88 1 Darechowk 13 AP-54/0 1 1 718 1 Darechowk 14 AP-54/A 1 1 222 1 Darechowk 15 AP-54/B 1 1 0 161 1 Darechowk 16 AP-54/C 1 1 0 0 0 Darechowk 17 AP-55/0 1 1 0 0 0 Darechowk 18 AP-56/0 1 1 0 0 0 Darechowk 19 AP-56/A 1 1 0 0 0 Darechowk 20 AP-57/0 1 1 0 0 0 Darechowk 21 AP-57/A 1 1 0 0 0 Darechowk 22 AP-57/B 1 1 0 0 0 Darechowk 23 AP-57/C 1 1 0 0 1 Darechowk

8th Semiannual Social Monitoring Report July-December, 2020

Remaining Stringing

Angle Under Ailani Tower Under S. No. Completed Private Under Earthing Remarks Location Point Progress Jungle (Semi Erection progress Complete Land Progress Gvt)

24 AP-58/0 1 1 0 0 1 Darechowk 25 AP-58/A 1 1 0 0 0 Darechowk 26 AP-58/B 1 1 0 0 0 2 pit Darechowk 27 AP-58/C 1 1 0 0 0 3pit Darechowk 28 AP-59/0 1 1 0 0 0 Darechowk 29 AP-60/0 1 1 0 0 0 Darechowk

Total 29 0 0 0 29 0 2641 524 14 29 (Chitwan)

Gorkha

Remaining Tower Erection Stringing Angle Under Ailani SN Completed Private Under Under Earthing Remarks Location Point Progress Jungle (Semi completed Complete Land progress Progress Gvt)

1 AP-35/1 1 1 0 460 1 Siurenitar 2 AP-35/A 1 1 477 1 Siurenitar 3 AP-36/0 1 1 348 1 Siurenitar 4 AP-37/B 1 1 0 475 1 Ghyalchowk 5 AP-37/C 1 1 0 237 1 Ghyalchowk 6 AP-37/D 1 1 0 541 1 Ghyalchowk 7 AP-38/0 1 1 0 0 1 Ghyalchowk 8 AP-38/1 1 1 0 0 1 Ghyalchowk 9 AP-38/A 1 1 0 370 1 Ghyalchowk 10 AP-38/B 1 1 0 470 1 Ghyalchowk

8th Semiannual Social Monitoring Report July-December, 2020

Remaining Tower Erection Stringing Angle Under Ailani SN Completed Private Under Under Earthing Remarks Location Point Progress Jungle (Semi completed Complete Land progress Progress Gvt)

11 AP-39/0 1 1 0 0 1 Ghyalchowk 12 AP-39/A 1 1 0 319 1 Ghyalchowk 13 AP-40/0 1 1 483 0 1 Ghyalchowk 14 AP-40/A 1 1 365 0 1 Ghyalchowk 15 AP-41/0 1 1 574 0 1 1422 Ghyalchowk 16 AP-42/0 1 1 324 0 1 Ghyalchowk 17 AP-43/0 1 1 0 147 1 Ghyalchowk 18 AP-43/A 1 1 0 0 1 Ghyalchowk 19 AP-60/A 1 0 0 1 Gyaja 20 AP-61/0 1 1 0 0 1 Gyaja 21 AP-61/1 1 1 0 0 1 Gyaja 22 AP-61/A 1 1 0 0 1 Gyaja 23 AP-61/B 1 1 0 0 1 Gyaja 24 AP-62/0 1 1 0 428 1 Gyaja 25 AP-63/0 1 1 297 1 Gyaja 26 AP-64/0 1 1 224 1 Gyaja 27 AP-65/0 1 1 539 1 Gyaja 28 AP-65/A 1 1 328 0 1 Gyaja 29 AP-65/B 1 1 238 0 1 Gyaja 30 AP-66/0 1 1 287 0 1 Gyaja 31 AP-67/0 1 1 932 0 1 Gyaja 32 AP-67/A 1 1 217 0 1 Manakamana 33 AP-68/0 1 1 406 1 Manakamana 34 AP-69/0 1 1 557 1 Manakamana 35 AP-69/1 1 1 599 1 Manakamana 36 AP-69/A 1 1 254 1 Manakamana

8th Semiannual Social Monitoring Report July-December, 2020

Remaining Tower Erection Stringing Angle Under Ailani SN Completed Private Under Under Earthing Remarks Location Point Progress Jungle (Semi completed Complete Land progress Progress Gvt)

37 AP-70/0 1 1 598 0 1 Deurali 38 AP-70/A 1 1 157 1 Deurali 39 AP-70/B 1 1 159 1 Deurali 40 AP-70/C 1 1 140 1 Deurali 41 AP-70/D 1 1 189 1 Deurali 42 AP-71/0 1 1 535 1 Deurali 43 AP-72/0 1 1 392 1 Deurali 44 AP-72/A 1 1 237 1 Deurali 45 AP-72/B 1 1 174 1 Deurali 46 AP-73/0 1 1 377 1 Deurali 47 AP-73/A 1 1 189 1 Deurali 48 AP-74/0 1 1 220 1 Deurali 49 AP-74/1 1 1 0 211 1 Deurali 50 AP-74/2 1 0 0 0 Deurali 51 AP-75/0 1 1 0 0 1 Deurali Total 51 0 0 0 50 0 11276 3198 50 51 (Gorkha)

8th Semiannual Social Monitoring Report July-December, 2020 Tanahun

Remaining Stringing Under Ailani Tower Under S. No. Angle Point Completed Private Under Earthing Remarks Location Progress Jungle (Semi Erection progress Complete Land Progress Gvt)

1 AP-75/A 1 1 0 321 1 2 AP-75/B 1 1 174 1 3 AP-75/C 1 1 189 1 4 AP-76/0 1 1 185 1 Markichowk Total) 4 0 0 0 4 0 869 0 4 4

GRAND TOTAL 229 0 11 1 228 2 42397 12389 130 231

8th Semiannual Social Monitoring Report July-December, 2020 KNBTLP Remaining Conductor stringing (m) Tower Angle Under Tower Under SN foundation Private Under Earthing Remarks Location Point Progress Jungle Ailani Erection progress Completed Completed Land Progress

District: Palpa 1 AP48/0 1 0 1 Majheta, 2 AP48A/0 1 Yamgha 3 AP48B/0 1 Yamgha 4 AP49/0 1 1 Gunga, Yamgha 5 AP50/0 1 0 1 1 Yamgha 6 AP50A/0 1 0 1 Darlam 7 AP51/0 1 0 1 1 Darlam 8 AP51A/0 1 0 1 1 , 9 AP51B/0 1 0 1 1 Khanigau, Chappani 10 AP52/0 1 0 1 1 Chappani 11 AP52A/0 1 0 1 Chappani 12 AP52B/0 1 0 1 Chappani 13 AP53/0 1 0 1 1 Bagnasdada 14 AP54/0 1 0 1 1 belautikharka 15 AP54A/0 1 0 1 1 Chirtungdhara 16 AP54B/0 1 0 1 1 Chirtungdhara 17 AP54C/0 0 1 1 Chirtungdhara 18 AP54D/0 Removed

19 AP55/0 1 0 1 1 Chirtungdhara 20 AP55A/0 1 0 1 1 Chirtungdhara 21 AP55B/0 1 Chirtungdhara 22 AP56/0 1

8th Semiannual Social Monitoring Report July-December, 2020

Remaining Conductor stringing (m) Tower Angle Under Tower Under SN foundation Private Under Earthing Remarks Location Point Progress Jungle Ailani Erection progress Completed Completed Land Progress

23 AP56A/0 1 0 1 1 Chirtungdhara, piple Chirtungdhara, 24 AP57/0 1 0 1 1 Madiphat 25 AP57/1 0 1 Madiphat 26 AP57/2 0 1 Madiphat 27 AP57/3 0 1 Madiphat 28 AP57/4 1 0 1 1 Madiphat 29 AP57/5 1 0 1 1 Madiphat 30 AP57/6 1 0 1 1 Madiphat 31 AP57A/0 0 1 1 Madiphat 32 AP58/0 1 0 1 dumaidada Madanpokhara 33 AP58A/0 0 0 1 dumaidada Madanpokhara 34 AP58B/0 0 0 1 dumaidada 35 AP59/0 0 1 Madanpokhara Biskundada, 36 AP60/0 1 0 1 1 koldada Biskundada, 37 AP60A/0 1 0 1 1 koldada Biskundada, 38 AP61/0 1 0 1 koldada 39 AP61A/0 1 0 1 Kaseni 40 AP62/0 1 0 1 Koldada batase 41 AP62A/0 1 0 1 Koldada batase 42 AP63/0 1 0 1 Koldada batase 43 AP63A/0 1 0 1 Koldada batase 44 AP64/0 1 Koldada

8th Semiannual Social Monitoring Report July-December, 2020

Remaining Conductor stringing (m) Tower Angle Under Tower Under SN foundation Private Under Earthing Remarks Location Point Progress Jungle Ailani Erection progress Completed Completed Land Progress

45 AP64A/0 1 Koldada 46 AP65/0 1 0 1 Koldada 47 AP65A/0 1 1 Koldada 48 AP66/0 1 0 1 Koldada chhap , 49 AP67/0 1 0 1 baunsidada Gothadi, 50 AP67A/0 1 0 1 1 baunsidada Gothadi, 51 AP68/0 1 0 1 1 baunsidada 52 AP68A/0 1 Gothadi, 53 AP69/0 1 Gothadi, 54 AP69A/0 1 Gothadi, 55 AP70/0 1 Gothadi, 56 AP70A/0 1 Gothadi, 57 AP70B/0 1 Gothadi, 58 AP70C/0 1 0 1 Gothadi, 59 AP71/0 1 0 1 Gothadi, 60 AP72/0 1 0 1 Gothadi, Bhanjyang Gothadi, 61 AP72A/0 1 1 Okhaldhunga 62 AP72B/0 1 Gothadi, 63 AP72C/0 1 Gothadi, 64 AP[73/0 1 0 1 Gothadi, Dhawa 65 AP73A/0 1 0 1 Gothadi, Dhawa 66 AP74/0 1 Gothadi, Dhawa Sub Total: 41 2 52 12 1 20 2

8th Semiannual Social Monitoring Report July-December, 2020

Remaining Conductor stringing (m) Tower Angle Under Tower Under SN foundation Private Under Earthing Remarks Location Point Progress Jungle Ailani Erection progress Completed Completed Land Progress

District: Syangja 1 AP37F/0 1 0 1 1 Syangja 2 AP38/0 1 Syangja 3 AP39/0 1 0 1 Syangja 4 AP40/0 1 0 1 1 Syangja 5 AP40A/0 1 0 1 1 Syangja 6 AP40B/0 Syangja 7 AP40C/0 Syangja 8 AP41/0 1 Syangja 9 AP41A/0 Syangja 10 AP41B/0 Syangja 11 AP41C/0 1 0 1 Syangja 12 AP41D/0 Syangja 13 AP42/0 1 0 Syangja 14 AP43/0 Syangja 15 AP43A/0 Syangja 16 AP43B/0 1 Syangja 17 AP43C/0 Syangja 18 AP44/0 Syangja AP 19 1 0 1 0 0 1 0 0 0 0 Syangja 44A/0 Kaligandaki RM-6, 20 AP44B/0 1 0 1 0 0 0 0 0 0 Syangja Kaligandaki RM, 21 AP45/0 1 0 1 0 0 0 0 0 0 0 Syangja Kaligandaki RM, 22 AP45A/0 1 0 1 0 0 0 0 0 0 0 Syangja 23 AP45B/0 1 0 Syangja 24 AP46/0 1 0 1 Syangja 25 AP46A/0 0 Syangja

8th Semiannual Social Monitoring Report July-December, 2020

Remaining Conductor stringing (m) Tower Angle Under Tower Under SN foundation Private Under Earthing Remarks Location Point Progress Jungle Ailani Erection progress Completed Completed Land Progress

26 AP46B/0 0 Syangja 27 AP46C/0 0 Syangja 28 AP46D/0 0 1 Syangja 29 AP46E/0 0 Syangja 30 AP47/0 1 0 1 0 0 1 0 0 0 0 Syangja Sub Total 16 5 11 0 0 4 0 0 0 0 Syangja District: Parbat 1 AP8/0 Parbat 2 AP8/A 1 Parbat 3 AP8B/0 1 1 Parbat 4 AP8C/0 1 1 Parbat 5 AP9/0 1 1 Parbat 6 AP9A/0 1 1 Parbat 7 AP10/0 Parbat 8 AP10A/0 Parbat 9 AP11/0 Parbat 10 AP12/0 1 1 Parbat 11 AP13A/0 1 Parbat 12 AP14/0 1 Parbat 13 AP15/0 Parbat 14 AP15A/0 1 1 Parbat 15 AP16/0 Parbat 16 AP16A/0 Parbat 17 AP17/0 Parbat 18 AP18/0 Parbat 19 AP19/0 Parbat

8th Semiannual Social Monitoring Report July-December, 2020

Remaining Conductor stringing (m) Tower Angle Under Tower Under SN foundation Private Under Earthing Remarks Location Point Progress Jungle Ailani Erection progress Completed Completed Land Progress

20 AP19A/0 Parbat 21 AP20/0 Parbat 22 AP20A/0 Parbat 23 AP20B/0 Parbat 24 AP21/0 Parbat 25 AP21A/0 Parbat 26 AP21B/0 1 1 Parbat 27 AP22/0 1 1 Parbat 28 AP22A/0 1 Parbat 29 AP23/0 1 1 1 Parbat 30 AP23A/0 Parbat 31 AP24/0 1 1 1 Parbat 32 AP24A/0 1 1 1 Parbat 33 AP24B 1 1 1 Parbat 34 AP25/0 1 1 1 Parbat 35 AP25A 1 1 1 Parbat 36 AP26/0 1 Parbat 37 AP27/0 1 1 1 Parbat 38 AP 28/0 1 1 1 Parbat 39 AP28A/0 1 1 1 Parbat 40 AP29/0 1 1 1 Parbat 41 AP29A/0 1 1 1 Parbat 42 AP 29B/0 1 1 1 Parbat 43 AP 29C/0 1 1 1 Parbat 44 AP29D /0 1 1 1 Parbat 45 AP29E/0 1 1 1 Parbat

8th Semiannual Social Monitoring Report July-December, 2020

Remaining Conductor stringing (m) Tower Angle Under Tower Under SN foundation Private Under Earthing Remarks Location Point Progress Jungle Ailani Erection progress Completed Completed Land Progress

46 AP30/0 1 1 1 Parbat 47 AP30A/0 1 1 1 Parbat 48 AP30B/0 1 1 1 Parbat 49 AP30C/0 1 1 1 Parbat 50 AP30D/0 1 1 1 Parbat 51 31/0 1 1 1 Parbat AP 31A 52 1 1 1 Parbat /0 53 AP31B/0 1 1 1 Parbat 54 AP31C/0 1 1 1 Parbat 55 AP 32 /0 1 1 1 Parbat 56 AP 33/0 1 1 1 Parbat 57 AP 33A/0 1 1 1 Parbat 58 AP33B/0 1 1 1 Parbat 59 AP34/0 1 1 1 Parbat 60 AP34A/0 1 1 1 Parbat 61 AP34B/0 1 1 1 Parbat 62 AP35/0 1 1 1 Parbat 63 AP36/0 1 1 Parbat 64 AP37/0 1 1 1 Parbat 65 AP37A/0 1 1 1 Parbat 66 AP37B/0 1 1 1 Parbat 67 AP 37C/0 1 1 1 Parbat 68 AP 37D/0 1 Parbat 69 AP 37E/0 1 Parbat Total 49 5 45 3 Parbat

8th Semiannual Social Monitoring Report July-December, 2020

Remaining Conductor stringing (m) Tower Angle Under Tower Under SN foundation Private Under Earthing Remarks Location Point Progress Jungle Ailani Erection progress Completed Completed Land Progress

GRAND TOTAL 106 51 69 5 KNBTLP

8th Semiannual Social Monitoring Report July-December, 2020 UMBTLP

Conductor stringing Remaining Under Tower Under (m) Total S. Angle Complete Earthin Remark Progres Erectio progres Under Location Length( No. Point d Privat Jungl Ailan Complet g s s n s Progres m) e Land e i e s District: Lamjung Beshishar-1 1 AP 27A 1 0 1 0 0 0 0 0 Udipur, Lamjung Beshishar-11 2 AP 29 1 0 1 0 0 0 0 0 , Lamjung Beshishar-11 3 AP 30 1 0 1 0 0 0 0 0 chiti, Lamjung Beshishar-11 4 AP 31/1 1 0 1 0 0 0 0 0 chiti, Lamjung Dordi-2 5 AP 32 1 0 1 0 0 0 0 0 , Lamjung Dordi-2 6 AP 33C 1 0 1 0 0 0 0 0 Archalbot, Lamjung 7 AP36 1 0 1 0 0 0 0 0 -9 Fulbari, Lamjung Sundarbazar 8 AP 36A 1 0 1 0 0 0 0 0 -9 Fulbari, Lamjung Sundarbazar 9 AP 37 1 - 1 0 0 0 0 0 -9 Lamjung

8th Semiannual Social Monitoring Report July-December, 2020

Conductor stringing Remaining Under Tower Under (m) Total S. Angle Complete Earthin Remark Progres Erectio progres Under Location Length( No. Point d Privat Jungl Ailan Complet g s s n s Progres m) e Land e i e s Sundarbazar 10 AP 37A 1 0 1 0 0 0 0 0 0 0 -9 Fulbari, Lamjung Rainas -8 11 AP 39 1 0 1 0 0 0 0 0 0 0 , Lamjung Beshishar-11 12 AP 28A 1 0 1 0 0 0 0 0 0 0 chiti Sundarbazar 13 AP 31 1 0 1 0 0 0 0 0 0 0 -8 Beshishar-11 14 AP 28 B 1 0 1 0 0 0 0 0 0 0 Chiti Beshishar -1 15 AP 28 1 0 1 0 0 0 0 0 0 0 Udipur Dordi-2, 16 AP 33B 1 0 1 0 0 0 0 0 0 0 Archalbot

17 AP 33 E 1 0 1 0 0 0 0 0 0 0 Dordi -1 Aale

AP 18 0 1 1 1 0 0 0 0 0 0 Dordi -1 33E/1

19 AP 33D 0 1 0 1 0 0 0 0 0 0 Dordi -1 NEA Beshishar 1 20 AP 27 1 0 0 1 0 0 0 0 0 0 premise Udipur s land Dordi-2 21 AP 33 1 0 1 0 0 0 0 0 0 0 Archalbot Dordi-2 22 AP 33A 1 0 1 0 0 0 0 0 0 0 Archalbot

23 AP 34 1 0 1 0 0 0 0 0 0 0 Dordi -1

8th Semiannual Social Monitoring Report July-December, 2020

Conductor stringing Remaining Under Tower Under (m) Total S. Angle Complete Earthin Remark Progres Erectio progres Under Location Length( No. Point d Privat Jungl Ailan Complet g s s n s Progres m) e Land e i e s Rainas -8, 24 AP 50 1 0 1 0 0 Garambesi Rainas -8, 25 AP 51 0 1 1 0 0 Garambesi Rainas 8- 26 AP 40 1 0 1 0 0 Tarkughat Rainas 8- 27 AP 41 1 0 1 0 0 Tarkughat Sundarbazar 28 AP 34A 0 1 1 0 0 9 Rainas-7 29 AP 49 0 1 1 0 0 Garambesi Rainas -8 30 AP 42 0 1 1 0 0 Tarkughat Sub Total: 24 6 28 3 0 District: Tanahun Aanbukhaire 1 AP 14A 0 1 1 0 0 ni -4 Bhage Sub Total 0 1 1 0 0 Grand Total 24 7 29 3 -

7th Semiannual Social Monitoring Report July-December, 2020

ANNEXURE 2:

Status of Compliance with Loan Covenants

7th Semiannual Social Monitoring Report January-June, 2020

Annexure-2: Status of Compliance with Loan Covenants

Sch. Para Description Current Status No.

4. 9. The Borrower shall ensure that no Works contract which involves involuntary resettlement impacts is Being complied: awarded, until the Borrower and NEA have prepared and submitted to ADB the final RIPP based on The Concurrence letter for the Phase wise the Project’s detailed design, and obtained ADB’s clearance of such RIPP. updated RIPP (DKTL and MKTL) has been achieved from ADB whereas final RIPP update including KNBTL and NBBTL is under process.

:4. 10. The Borrower shall ensure that no Works contract which involves impacts on indigenous peoples is Being complied: awarded until the Borrower and NEA have prepared and submitted to ADB the final RIPP, and The Concurrence letter for the Phase wise obtained ADB’s clearance of such RIPP. updated RIPP (DKTL and MKTL) has been achieved from ADB whereas final RIPP update including KNBTL and NBBTL is under process.

5. 7. The Borrower shall establish and maintain, or cause NEA and AEPC to establish and maintain, a Being complied: grievance redress mechanism acceptable to ADB for the purpose of addressing any grievances The grievance redress mechanism (GRM) is arising out of the Project, including those from affected peoples concerning land acquisition, formed at the subprojects namely DKTL and environment and any other social issues in a timely manner. KNBTL under Kaligandaki Corridor and MKTL of SASEC whereas GRM is yet to be established in NBBTL under Kaligandaki Corridor due to final check survey is ongoing and formation of GRM is under process. 5. 12. The Borrower shall ensure, or cause NEA and AEPC, as applicable, to ensure, that all land and all Being Complied rights-of-way required for the Project, each Subproject and all Project facilities are made available to the Works contractor in accordance with the schedule agreed under the related Works contract and all land acquisition and resettlement activities are implemented in compliance with (a) all applicable laws and regulations of the Borrower relating to land acquisition and involuntary resettlement; (b) the Involuntary Resettlement Safeguards; (c) the RF (for Subprojects); and (d) all measures and

7th Semiannual Social Monitoring Report January-June, 2020

Sch. Para Description Current Status No.

requirements set forth in the RIPP, as appropriate, and any corrective or preventative actions set forth in the Safeguards Monitoring Report.

5. 13. Without limiting the application of the Involuntary Resettlement Safeguards or the RIPP, the Being Complied: Borrower shall ensure, or cause NEA to ensure, that no physical or economic displacement takes The resettlement assistance as per the place in connection with the Project until: entitlement matrix of RIPP is being distributed (a) compensation and other entitlements have been provided to affected people in accordance in DKTL subproject under Kaligandaki Corridor with the RIPP, as appropriate; and whereas it is under process of distribution in (b) a comprehensive income and livelihood restoration program has been established in KNBTL and NBBTL under Kaligandaki Corridor accordance with the RIPP, as appropriate. and MKTL. 5. 14. The Borrower shall ensure, or cause NEA and AEPC to ensure, as applicable, that the preparation, Being Complied design, construction, implementation and operation of the Project, each Subproject and all project facilities comply with (a) all applicable laws and regulations of the Borrower relating to indigenous peoples; (b) the Indigenous Peoples Safeguards; and (c) the IPPF (for Subprojects); and (d) all measures and requirements set forth in the RIPP, as appropriate, and any corrective or preventative actions set forth in a Safeguards Monitoring Report. 5. 15. The Borrower shall ensure that Part 3 of the Project does not have any indigenous peoples or Being Complied involuntary resettlement impacts, all within the meaning of SPS. In the event that Part 3 of the Project does have any such impact, the Borrower shall take all steps to ensure that the Project complies with (a) the applicable laws and regulations of the Borrower; (b) the SPS; and (c) the IPPF and the RF, as applicable.

5. 16. The Borrower shall make available, or cause NEA and AEPC to make available, necessary Being Complied budgetary and human resources to fully implement the EMP and the RIPP.

7th Semiannual Social Monitoring Report January-June, 2020

Sch. Para Description Current Status No.

5. 17. The Borrower shall ensure, or cause NEA and AEPC to ensure, that all bidding documents and Being Complied contracts for Works contain provisions that require contractors to: (a) comply with the measures relevant to the contractor set forth in the IEE, the EMP and the RIPP (to the extent they concern impacts on affected people during construction), and any corrective or preventative actions set forth in a Safeguards Monitoring Report; (b) make available a budget for all such environmental and social measures; (c) provide the Borrower with a written notice of any unanticipated environmental, resettlement or indigenous peoples risks or impacts that arise during construction, implementation or operation of the Project that were not considered in the IEE, the EMP and the RIPP; (d) adequately record the condition of roads, agricultural land and other infrastructure prior to starting to transport materials and construction; and (e) Reinstate pathways, other local infrastructure, and agricultural land to at least their pre- project condition upon the completion of construction. 5. 18. The Borrower shall do the following or cause NEA and AEPC to do the following: Being Complied

(a) submit semiannual Safeguards Monitoring Reports to ADB and disclose relevant information from such reports to affected persons promptly upon submission;

(b) if any unanticipated environmental and/or social risks and impacts arise during construction, implementation or operation of the Project that were not considered in the IEE, the EMP, and the RIPP, promptly inform ADB of the occurrence of such risks or impacts, with detailed description of the event and proposed corrective action plan;

(c) report any actual or potential breach of compliance with the measures and requirements set forth in the EMP and the RIPP promptly after becoming aware of the breach.

8th Semiannual Social Monitoring Report July-December, 2020

Annexure 3: Acquired Additional Land

Annexure 3.7: Acquired Additional Land for the UMBTLP Marsyangdi Corridor in Tanahun District-UMBTLP

Total Area Required Area S. Previous Plot AP No. Land Owner Name Father Name Grand Father N Address No P D R P D R. A. Sq.m A. Sq.m . . . . .

AP 45 Shree Gorakhkali Guthi Purkot 1 (Mohi BasantiGurung Man Bahadur Basraj 4/Ka 41 7 2 2 1 3642.6 0 9 0 1 288.09 Prem Bahadur Purkot 1 2 AP 45 Man Kumari Gurung Gurung Sunar 4/Ka 1258 6 3 2 3 3487.5 0 9 0 1 288.09 Kamal Narayan Purkot 1 3 AP Shrestha Chhabilal Gunjaman 2/Ka 301 0 3 1 3 427.15 0 1 0 2 35.75 46/1 Purkot 4 Juthi Shrestha Mohanlal Harkaman 2/Ka 718 2 0 1 2 1029.4 0 6 1 3 204.62

8th Semiannual Social Monitoring Report July-December, 2020

Purkot 5 Harka Man Shrestha Kabindra Rudraman 2/Ka 302 2 7 0 1 1242 0 4 3 2 154.94 Satrasaya 6 Humnidhi Panta Ramnath Balabhadra Aabu 3/Ga 505 8 0 1 3 4083.8 0 5 1 0 166.89

AP 0A Satrasaya 7 Bhim Bd. Gurung Gun Bahadur Bhakta singh Aabu 3 /Ga 1045 2 5 3 2 1204.2 0 4 1 1 137.08 Satrasaya 8 Gam Bd. Gurung Gun Bahadur Bhakta singh Aabu 3/ Ga 1044 2 5 3 2 1204.2 0 1 3 0 55.61 Satrasaya 9 Asha Kumari Thapa Aabu 3/ Ga 559 1 6 2 2 719.32 0 1 3 1 57.59 Purna kumari Ale Satrasaya AP 3 10 (Purna Maya Ale) Dilbahadur Pahalman Aabu 3 Ga 463 3 9 2 0 1828.2 0 1 3 0 55.61 Satrasaya 1 11 Chhabilal Ale PahalMan Abbal Aabu 3 /Ga 462 1 2 2 3 912.04 0 6 1 1 200.66 Satrasaya Makar Bahadur Aabu 5/ 12 Gurung Bombahadur Mehanman Gha 860 5 4 1 0 2678.8 1 8 1 3 776.94 Satrasaya AP 4 Aabu 13 Mina Gurung Aek Bahadur Bombahadur 5/Gha 859 1 0 0 0 508.74 0 9 1 2 298.01 Satrasaya Bishnu Aabu 1 14 Yam Maya Ale Laxman Bahadur 5/Gha 359 1 0 3 1 852.44 0 1 0 2 35.75 Deepak Kumar Satrasaya 15 Shrestha Santabir Raghubir Aabu 6/Ka 625 2 0 0 0 1017.5 0 8 2 2 274.16

AP 5 Deepak Kumar Satrasaya 1 16 Shrestha Santabir Raghubir Aabu 6/Ka 35 1 0 3 3 856.4 0 7 0 3 228.47 Purna Buddhi Satrasaya 17 Sher Bd. B.K Bahadur Bahadur Aabu 6/Ka 626 8 5 0 0 4228.9 0 1 0 0 31.79

AP 5A Satrasaya 1 1 18 Sambhulal Shrestha Durga Man Kalu Aabu 6/Ka 94 1 2 2 1 908.08 0 1 1 3 363.57

8th Semiannual Social Monitoring Report July-December, 2020

Satrasaya 19 Indra Bd. Sunar Masure Kale Aabu 6/Ka 93 1 6 2 1 717.34 0 4 0 1 129.14 Satrasaya 20 Tek Bahadur Shrestha Siddhiman Aabu 6/Ka 350 1 8 0 0 763.06 0 4 1 0 135.1 Damber Satrasaya 21 Mekh Bd. Thapa Nar Bahadur Bahadur Aabu 6/Ka 348 1 2 1 3 586.2 0 1 1 3 45.67 Damber Satrasaya 1 22 Krishna Bd. Kami Man Bahadur Bahadur Aabu 6/Ka 349 2 3 1 0 1120.8 0 1 0 1 351.67 AP 6 Damber Satrasaya 23 Krishna Bd. Kami Man Bahadur Bahadur Aabu 6/Ka 349 2 3 1 0 1120.8 0 2 1 2 75.48 Damber Satrasaya 24 Mekh Bd. Thapa Nar Bahadur Bahadur Aabu 6/Ka 707 1 6 1 0 707.42 0 0 3 2 27.78

AP 7 Tirtha Damber Satrasaya 25 Tuk Bahadur Thapa Bahadur Bahadur Aabu 6/Ka 706 1 6 1 0 707.42 0 6 2 0 206.62 Satrasaya 26 Dal Bahadur Chandi Aabu 6/Ka 540 4 6 2 0 2241.6 0 3 3 1 121.17 Satrasaya 1 27 Hom Bahadur Thapa Bal Bahadur Raghubir Aabu 6 /Na 53 2 1 1 1 1377.1 0 3 3 0 119.19 AP 8 Satrasaya 28 Min Bahadur Ale Jagat Bahadur Balbahadur Aabu 6 /Na 52 4 1 3 3 2096.5 0 7 2 3 244.35

Jut Bahadur Satrasaya 1 29 Kharka Bahadur Thapa Kale Aabu 6 /Na 70 6 0 0 1 3372.3 0 4 3 0 150.98 AP 9 Khadka Bd. Indra Udaya Satrasaya 30 Thapamagar Bahadur Bahadur Aabu 6 /Na 71 2 5 0 1 1178.4 0 6 3 0 214.56 Satrasaya Aabu 31 AP 10 Lil Maya Sunar Hasta Bd. Min Bahadur 6/Kha 269 3 1 0 1 1560 0 4 3 0 150.98 A Satrasaya Aabu 1 32 Nabraj Mishra 6/Kha 305 4 1 2 0 2400.5 0 5 0 0 158.95

8th Semiannual Social Monitoring Report July-December, 2020 Satrasaya Aabu 33 Yubraj Magar Manbir Prem Bahadur 6/Kha 327 4 1 0 0 2066.8 0 6 0 0 190.74 Satrasaya Aabu 34 Subash Mishra Dayakrishna Nityananda 6/Kha 182 1 5 3 0 691.51 0 0 2 1 17.86 Satrasaya 35 Bhuban Bd. Khawas Birkha Bd. Kirtiman Aabu 7/Ka 388 3 0 2 3 1548 0 1 0 0 31.79 AP 11 Satrasaya 1 36 Musimaya Khawas Pahalbahadur Maniraj Aabu 7/Ka 387 2 4 0 0 1462.5 0 7 1 0 230.47 Ambar Satrasaya 37 Dambar Bd. Khawas Bhim Bahadur Bahadur Aabu 7/Ka 386 2 8 0 1 1273.8 0 8 1 0 262.26 Satrasaya 38 Bhim Bahadur Ale Nande Buddhiman Aabu 7/Ka 435 3 1 3 3 1587.8 1 1 0 0 540.53 AP 12 Satrasaya 1 39 Narbir Ale Bire Ale Aabu 7/Ka 436 1 1 2 1 876.29 0 0 3 2 27.78 Satrasaya Aabu 1 1 1 40 Surya Maya Thapa 8/Kha 76 6 2 0 1 8523.3 0 5 3 0 500.67 AP 13 Satrasaya Chandra Man Thapa Aabu 41 Magar Bieman jitman 8/Kha 75 7 8 0 0 3815.5 0 0 3 0 23.82 Satrasaya AP Nar Bahadur Thapa Aabu 42 13/1 Magar Sher Bahadur Hasta Bahadur 8/Kha 168 4 5 1 0 2201.9 0 9 0 1 288.09 Satrasaya Aabu 1 1 43 Kalu Bhujel Polman Rising 8/Kha 11 5 2 0 0 8012.6 1 0 2 0 524.62 AP 15A Satrasaya Aabu 1 44 Dhan Bahadur Gurung Manlal 8/Kha 6 9 5 1 2 5067.4 0 0 2 0 15.88

8th Semiannual Social Monitoring Report July-December, 2020

Samsher Bahadur Hilekharka 1 45 AP 16 Chepang Bahabal Kande 1/Chha 3 1 7 3 1 5844.5 1 2 2 2 592.16 AP 16 Hilekharka 46 A Kabiraj Gurung Nar Bahadur Kulman 1/Chha 7 8 0 1 3 4083.8 1 2 1 0 580.26 Hilekharka 1 47 AP 19 Virus Bhujel Aitaram Neste 1/Cha 20 5 6 1 0 2742.4 0 1 3 0 373.51 Hilekharka 48 Budhe Bhujyal Hange Aita 1/Cha 19 1 4 1 1 645.82 0 3 0 1 97.35 Hilekharka 1 AP 21 49 Bara Devi Sthan 1/ka 29 5 9 3 1 7943 0 3 0 0 95.37 Hilekharka 1 50 Aitaram Bhujel Nepte Dhansur 1/ka 2 2 4 2 1 1480.4 0 6 3 0 214.56 Hilekharka 1 51 AP 21 Khaman Singh Gurung Kajiman Dharmaraj 1/ka 44 7 6 0 3 3757.9 0 3 0 0 413.27 A Hilekharka 52 Lok Bahadur Gurung Kajiman Dharmaraj 1/ka 45 8 9 0 0 4356 0 3 2 0 111.25 Purna Hilekharka 1 53 Mansari Gurung Bahadur Lalsingh 1/Gha 1 5 4 3 3 2700.6 0 2 2 0 397.36 AP 20 Hilekharka 54 B Aitaram Bhujel Nepte Dhansur 1/Gha 2 3 4 2 3 1675.2 0 5 2 0 174.83 12313 11489.6 51HHs 54 8 9

8th Semiannual Social Monitoring Report July-December, 2020

ANNEXURE 4: Grievance Redress Committee Meeting Matrix

8th Semiannual Social Monitoring Report July-December, 2020 Annexure 4: Grievance Redress Committee Meeting Matrix

8th Semiannual Social Monitoring Report July-December, 2020

No. of Topics/ issue S.N. Date Type of Participants Location Information disseminated Participant discussed

DKTLP

Total-9 Regarding CSR budget distrirbution by the rd Ward Chairman and 1 3 July2020 Male-9 About CSR Annapurna 3 GRC Members project on CDC meeting Myagdi Female-0 th Total- 4 12 July Ward Chairman and About Grivances Regarding grievances which is recorded on 2 Male-4 Raghuganga 2 2020 GRC Members recorded on CDC CDC about CSR Female-0 RM Chairman, Ward st Total-29 21 July Chairman, GRC 3 Male-28 About ROW Raghuganga-3 Regarding ROW land loss compensation 2020 Members and Female-1 affected person th Total-8 28 July Ward Chairman and Regarding some invironment issues on the 4 Male-7 About social issues Kushma-2 2020 GRC Members Naya pul Kushma-2 Female-1 Total 7 Ward chairman grc Annapurna 2, Rs 50,000 for road maitanance which is 5 27 Dec 2020 Male 5 For CSR members Tatopanni demanded by Annapurna RM Female 2

MKTLP

1 2077/6/15 Male – 8 GRC committee Labor Camp fee Issue Sahidlakhan Labor Camp Rental fee (4 months) has not members RM- 3, Gorkha provided by contractor for local people who Female 0 – provided shelter during Tower foundation Total - 8 construction work in Gyaja village GRC team has been decided to provide rental fee for house owner by contractor.

8th Semiannual Social Monitoring Report July-December, 2020

2 2077/6/16 Male – 8 GRC committee Issue regarding Road The issue was Impact on road and water tank members and water resources due to movement of vehicle during construction Female – 10 Ichchhakamana during construction in Chumlingtar –Khalang Road GRC team has RM 3 Chitwan Total - 8 – been decided for site verification withtechnical person to find the actual loss during construction.

3 2077/6/16 Male – 8 GRC committee Compensation Issue Gorkha Mrs. Parbati Karakheti has recorded grievance members Municipality- 14, for land compensation because her land has Female 0 – Yangkot affected by ROW but she has not received the Total - 8 compensation till the date. The same land plot has been divided into two plots for two households after family separation and the project office estimated the compensation based on the old land plot. She is unknown, how many areas have been affected by ROW on his new plot. Her brother-in-law has received the compensation she has not. The Issue has been addressed and GRC team was coordinated with related stakeholder for finalized the actual loss individually. Now they received their compensation as per their land loss.

KNBTLP

Total: 11

Ward Chair Person, Kaligandaki Male: 7 Regarding grievances which is recorded 1 9 July 2020 GRC Members, Ward About Grievances RM ward no-5, on CDC about CSR Female:4 Secretary & PAFs Syangja.

IP:0

8th Semiannual Social Monitoring Report July-December, 2020

Total:7

Ward Chair Person, Kaligandaki RM Male:6 Regarding grievances which is recorded on 2 11July 2020 GRC Members, & About Grievances ward no-6, CDC about CSR Female:1 PAFs Syangja.

IP:0

Total:9

Male:8

Ward Chair Person, Female: 1 Kaligandaki RM Regarding grievances which is recorded on 3 12 July 2020 GRC Members, & Regarding Grievances -7, Syangja CDC about CSR IP:3 PAFs

8th October, Male -15 Ward chair, PAFs of Compensation of Bagnaskali-9 Discussion compensation of acquired land, 2020 Female-2 tower pad and ROW, acquired land, Chappani, compensation processes of crop/fruit/and other Project crop/fruit & other Palpa lossess. Access road compensation provided Total-17 representative, loses, access road, by contractor, safety from COVID-19 at working 4 2077/06/22 ESMU& Contractor Notice publication of areas & community, management of land representative remaining plots, owners’ trees under ROW, Soil management of Covid-19 & others tower pad & Tower erection work and allowances of GRC meeting.

9th October, Male -15 Ward chair, PAFs of Compensation of Bagnaskali-1 Discussion compensation of acquired land, 2020 Female-2 tower pad and ROW, acquired land, Chirtungdhara, compensation processes of crop/fruit/and other Project crop/fruit & other Palpa lossess. Access road compensation provided Total-17 5 representative, loses, access road, by contractor, safety from COVID-19 at working 2077/06/23 ESMU & Contractor Notice publication of areas & community, management of land representative remaining plots, owners’ trees under ROW, Soil management of Covid-19 & others

8th Semiannual Social Monitoring Report July-December, 2020

tower pad &tower erection work and allowances of GRC meeting.

Nov 5, 2020 12 Ward Chair, PAFs, Access road of 33B 33B of Bihadi-3, Access road can be opened immediately 6 L&T and Project Parvat

Nov 6, 2020 7 Ward Chair, PAFs RoW of 26 B and Bihadi-1, Issue has been submitted to Project for solving 7 and Project Public Demand Issue , soon. Parvat 17th Dec, Male – 15 Ward Chair, PAFs, Selection of Tinau-4 Chhap, Conduct GRC meeting & selection participants 2020 Female – 1 L&T and Project particapants & Crop Palpa from PAFs for conduct social mitigation training Total -16 loss compensation of (livestock farming). And second issue was crop 8 access road of AP66 loss compensation it should be payment within & 65A/0 location 15 Paush 2077 by contractor& continuation of foundation work. If contractor have not payment within given period social safeguard officer have taken response. 17th Dec, Male – 13 Ward member, GRC Selection of Mathagadhi-5 Conduct GRC meeting & selection participants 2020 Female – 2 member, PAFs, L&T particapants & Crop Banshidada, from PAFs for conduct social mitigation training Total -15 and Project loss compensation of Palpa (livestock farming). Observation & conformed access road of AP house& shed structure of ROW under AP 67/0 9 67A/0 & AP68/0 to AP67A/0(one tin shed house, one goath & one kadkuro (daura rakhne). And to manage crop loss compensation of access road and foundation activities within 15 days next meeting. 21st Dec, Male – 7 Ward member, GRC Regarding grivences, Tinau-5 Regarding protection of drinking water 2020 Female – 2 member, PAFs, L&T Selection of charchare resources after observation we will discussion Total -9 and Project participants, Crop loss Palpa next meeting, selection participants from PAFs 10 compensation& notice for conduct social mitigation training publication (mushroom), informed & discussion remaining plot notic published and informed and request to project to provide crop loss compensation for public as soon as possible under tower pad.

8th Semiannual Social Monitoring Report July-December, 2020

22nd Dec, Male – 8 Ward chair, GRC Selection of Tansen- Selection participants from PAFs for conduct 2020 Female – 2 member, PAFs, L&T participants, Crop loss 9Madanpokhara social mitigation training(mooshroom), Total -10 and Project compensation& notice damkada, Palpa informed & discussion remaining plot notic 11 publication published and request to PAFs for updating the land certificate and informed and request to project to provide crop loss compensation for PAFs as soon as possible under tower pad. 23rd Dec, Male – 9 Ward chair, GRC Selection of Bagnaskali- Selection participants from PAFs for conduct 2020 Female – 0 member, PAFs, L&T participants, Crop loss 1Chirtungdhara social mitigation training (vegetable, Total -9 and Project compensation& notice Palpa mooshroom& driving), informed & discussion publication remaining plot notic published and request to 12 PAFs for updating the land certificate and informed and request to contractor(L&T) to provide crop loss compensation for PAFs as soon as possible access road and request to neatness and cleanliness as under labor camp. UMBTLP

1 Male – 10 GRC committee CSR demand Sundarbazar CSR demands such as road 2077/06/20 Female – 0 municipality-7, maintained and help for temple Total - 10 Lamjung construction. 6th October 2020

8th Semiannual Social Monitoring Report July-December, 2020

8th Semiannual Social Monitoring Report July-December, 2020

Annexure 5:

Letter related to Recorded Grievances

8th Semiannual Social Monitoring Report July-December, 2020 Annexure 5.1: Letter related to Recorded Grievances- (DKTLP)

8th Semiannual Social Monitoring Report July-December, 2020

8th Semiannual Social Monitoring Report July-December, 2020 Annexure 5.2: Letter related to Recorded Grievances- (KNBTLP)

8th Semiannual Social Monitoring Report July-December, 2020

8th Semiannual Social Monitoring Report July-December, 2020

ANNEXURE 6:

Public Consultation Matrix

8th Semiannual Social Monitoring Report July-December, 2020 Annexure 6: Public Consultation Matrix

No. of Topics/ Issues SN Date Type of Participants Location Information Disseminated Participants discussed

DKTLP

Total-15 Ward chairman, Project About landslide by 29th July representative, MC Field visit and preparation protect advice to the 1 Male-9 project substation Kushma-2, Naya pul 2020 engineer, landslide project. construction side Female-6 department engineer

MKTLP

The consultation meeting has done in Total -7 Compensation, Ichchhakamana RM -4 Kurintarregarding the 22nd July, PAFs, Ichchhakamana RM -4 1 Male -7 Coordination and issue of compensation receiving process of 2020 ESMU Officer, Kurintar Female-0 Grievances ROW, grievances and coordination process of the project representative. Affected HHs of AP 7D/2 were demanding protection work to prevent the soil erosion due to construction of AP 7D/2 and they were unhappy with the project citing that the Total -5 Protections work at 12th August, PAFs, Ward Office protection work has not been started yet.They 2 Male -5 AP 7D/2 to prevent Dhunibesi Municipality-6 2020 And Contractor were informed that the protection work has Female-0 erosion. been delaying due to rainy season and Covid - 19 effect. They were also informed that the contractor will start the work immediately when the situation will be normal. Requested with PAFs, local community and 27th PAFs, Ward Office,local Foundation work of ward Office of Siddhalek RM-7, Dhading to 3 September, Informal community,project staffs AP24E/0 and Siddhalek RM-7 create positive environment among community 2020 And Contractor AP24F/0 to start the foundation work of AP24E/0 and AP

8th Semiannual Social Monitoring Report July-December, 2020

24F/0.Also communicate them that only 2 tower construction works are remaining in MKTLP. Disscused on the construction status of shatighat and community building supported by 20 October, Community of Thakre 4 29 Thakre RM-8 ESSD under CSR activity. The construction 2020 RM-8 work was found completed and utilized by community properly. Ward representative, 25 Total-10 Discussion on implementation of skill PAFs, local community Skill Development Gokha Municipality-14/13 5 November, Male-6 development program for Project affected people, ESMU & Training Yangkot 2020 Female-4 people. Contractor representative 18th Total-22 Project office staffs, One-month basic Siddhalek RM-4 One month long basic driving skill training to 20 December Male-22 ESMU, project affected driving skill training affected HHs of Siddhalek RM ward 3 &4 will be 6 2020 Female-0 HHs and Ward Office started at Malekhu Dhading from 18th December 2020. Total-10 28 Discussion on implementation of skill Male-10 Project Affected People, Skill Development Gokha Municipality-14/13 7 November, development program for Project affected Female-0 Trainer, ESMU officers Training Yangkot 2020 people.

KNBTLP

Discussed regarding current scenario of COVID-19 pandemic standard operating procedure (SOP) set from ADB and recent lockdown (seal) announced by Sunawal Total -10 Safety measures Project office new butwal 10th Sep, Project office staffs, Municipality. It is also discussed the 1 Male -9 during covid substation, Sunuwal mun- 2020 ESMU & Contractor construction activities shall be continued with Female-1 Pandemic 13, Nawalparasi proper safety precautions. The groupwise isolation of inside workers shall be continued more strictly even in daily site work.

8th Semiannual Social Monitoring Report July-December, 2020

Visitors are restricted to enter to the site incase of emergency visitor pass from NEA shall be issued. Total -4 Compensation of PAFs, Ward Chair of 3 Compensations must be distributed soon. 13 September, Male -3 Land, crops and trees Bihadi RM -3, Ranipan, Bihadi, Ranipani Participants of this meeting have no objection 2 2020 Female-1 etc and access road Parvati of opening Access Road. of AP 33B.

Workers and any staffs must be presented in ward having PCR negative report within 24 Regarding hours of having report which is a directive of Total- 2 14 September Ward Chair and Social compensation and Bihadi RM-2, Barrachaur Bihadi RM followed the circular of District 3 Male-2 2020 Safeguard Officer resumption of Parvat Administrative Office, Parvat. Female-0 constrcuction Likewise, Compensation must be distributed

soon. Commitment must be fulfilled by Project to ward regarding to construct road AP29C to 29D Regarding Compensation is delayed, so it must be done Total-11 15 compensation and as soon as possible and distructed land, field, 4 Male-11 Ward Chair and PAFs Bihadi-1, Bachchha, Parvat September resumption of canal must be mended as previous by Female-0 2020 construction in concerned stakeholders.

remained locations Regarding Compensation must be distributed soon and in 15 Total-7 compensation & order to open access road for AP 37 D & 37E, 5 Bihadi-6, Saligram, Parvat September Male-4 Ward Chair and PAFs resumption of contractor and project official must visit in these

2020 Female-3 Construction work locations and conclude.

Regarding 21 Total-9 Ward Chair, Compensation and Phalebash-4, , Compensation must be distributed soon and 6 September Male: 6 representatives, PAFs resumption of Parvat work can done after harvesting Paddy, in First 2020 Female:3 construction work week of January 2021, approximately.

8th Semiannual Social Monitoring Report July-December, 2020

Regarding Total: 11 21September Compensation and Phalebas-6, Devisthan, Compensation must be distributed soon and Male:10 Ward Chair and PAFs 7 2020 resumption of Parvat AP must be added not to harm proposed Female: 1 construction work stadium in between AP10/0 and 10A/0

Compensation must be distributed soon and Regarding work of AP15/0 can be constrcucted after

Total-5 Compensation and Phalebash-10, AP15/0, compensated Banana Fruit owner Chhabilal 22 September Ward Chair and PAFs 8 Male-4 resumption of Parvat Poudel (son of PAF – TejkumariPoudel) have 2020 Female- 1 construction work registered his agro farm in authoriged office of

government of Nepal.

Regarding 22 Total-14 Compensation and Phalebash-11, , Ward Chair and PAFs Compensation must be handed over to PAFs 9 September Male-12 resumption of Parvat and work can be done after harvesting paddy. 2020 Female- 2 construction work

Discussion on previous proposes integreated Ward chair, ward multi-circuit transmission line between New 6th October, Total -10 representative, PAFs, Integreated Multi- Ward office Badera at butwal substation to Mahendra highway and 10 2020 Male -9 local community people, circuit Transmission Sunuwal mun-13, compensation of tower pad and underROW 2077/06/20 Female-1 ESMU & Contractor line root Nawalparasi (minimum losses of valuable land & provide representative maximum compensation for PAFs uses land) Total -14 6 October, Regarding to open In order to open access road, meeting held Male-14 2020 PAFs, Ward Chair of 7 access road for 43 Kaligandaki RM -7, Parvati among PAFs, Ward representative, NEA Female-0 Kaligandaki RM, Syangja, and 43A representative and L & T but it is still in process 11 IPs-5 PAFs, NEA staffs, L&T of solving

staffs

7, October 12 2020 Total- 10 Regarding the issue Bihadi RM-3, Ranipani In order to open access road for 33B, meeting Male-10 of 33B Parvat held among PAFs, Ward representative, NEA

8th Semiannual Social Monitoring Report July-December, 2020

Female-0 Ward Chair, PAFs of representative and L & T but it is still in process IP-1 Bihadi-3 Parvat, NEA and of solving. L&Tstaffs,

Discussion on minimum social responsibility in Total -9 Ward Chair, Project community from project. contractor should 9th October, Social responsibility Tansen mun -7 Male -9 representative, ESMU, & manage 11 trip of mix rock for road grabbling, 2020 of contractor & chuchchebari, Bastari of 13 Female-0 Contractor (L&T) tax clearance of uses land rent, adopt safety 2077/06/23 Project in community Palpa precaution to load & unload vehicles, should be at store area PCR negative report with labours. Other decision should be discussion next meeting. 13thOctober, Total -4 Discussions with PAFs for manage Manage Bagnaskali -9 bagnasdada 14 2020 Male -4 PAFs and ESMU documentation to get land acquired documentation chappani, Palpa (AP53/0) 2077/06/27 Female-0 compensation from project. Discussion with community people about crop loss compensation of access road. Contractor Ward member, GRC Regarding access (L&T) should have responsible to payment so 29thNovember, Total -19 member, PAFs, local road crop loss contractor immediately provide Rs.20000.00 Tinau -4 Chhap Community 15 2020 Male -17 community people, compensation & and remaining will be provide within 15 days and Palpa 2077/08/14 Female-2 ESMU & Contractor continuing project Contractor (L&T) will be help to JCB machine for representative work digging ghaderi construction for women community house and continuing project work.

29th Discussions with PAFs & contractor at land Total -6 November, PAFs, ESMU & Regarding Bagnaskali -9 chappani, owner house than contractor payment 16 Male -6 2020 contractor compensation Palpa (AP51A/0) immediately compensation amount and solved Female-0 2077/08/14 this issue. Regarding land Discussions with school management Total -19 School management compensation, committee about project activities. Informed Bagnaskali-5 Darlamdada 17 3rd Dec, 2020 Male -17 committee, Project, erection work & notice publication process of remaining plot, ma.vi. Darlam, Palpa Female-2 ESMU & contractor school support valuation process, project working activities and program taking agreement continuing the project work.

8th Semiannual Social Monitoring Report July-December, 2020

Ward chair, ward To solve the issue Discussion held among PAFs, Project and L & T. Total -10 representative, PAFs, on the losses due to Meetings has decided to construct collapassed 18 26 Nov 2020 Male -10 local community people, excavation of Bihadi-1, Parvat canal of land woner after erecting tower. Female-0 ESMU & Contractor Approach Road of

representative 22/0 Total -12 Regarding Fruit Banana and other trees have been counted in Male-11 17 Dec 2020 Compensation of presence of NEA staffs, PAF and L& T. Decision Female-1 Phalebas-10, Parvat Tower PAD of 15/0 has been done to compensate PAFs in 19 PAFs, NEA, L&T staffs accordance with the rate of Agriculure

Knowledge Cetre of Kusma, Parvat.

Total- 10 22Dec 2020 Regarding the issue Male-10 of 38/0 & 39 Female-0 PAFs, & L n' T Staffs Decision has been done to compensate of 20 Dalit -0 Galyang-5, Syangja access road losses to PAFs in accordance with

the previous commitment of L & T to PAFs.

Total -9 Ward Chair, ESMU, & Decision has been done to open excess road of 25 Dec 2020 Male -8 Contractor (L&T) Regarding to open Bihadi-1, Parvat 23A/0 and contractor will copensate crop 21 Female-1 excess road of 23A/0 losses of PAFs within the period of construction

work.

UMBTLP

2077-06-21 Total – 21 Forest user group, Project CSR, Tree marking Brief summary of CSR implementation by the th Male – 16 Beshishar-1, Udipur Lamjung 1 7 October and Local Representative activities project and Tree marking process 2020 Female – 5

8th Semiannual Social Monitoring Report July-December, 2020

2077-08-8 Total – 6 Affected HHs, Contractor Compensation for Rainas-7, Lamjung To provide appropriate compensation to the APs Male – 5 and ESMU access road by the contractor for the use of land as access 23rd Female – 1 road. November 2 2020 IPs – 5

2077-8-12 Total – 10 Project, Affected HHs, Compensation for Dordi – 1 Lamjung To provide appropriate compensation to the APs Male – 9 Contractor and ESMU Crops loss by the contractor for crop loss outside the tower 27th Female – 1 pad during the construction activities, 3 November Management of damage irrigation canal during 2020 IPs – 1 construction work and debris management.

2077-8-12 Total – 10 Local representative, CSR demand Dordi – 1 Lamjung Implementation of CSR within the limit of CSR Male – 10 Project, Forest user group fund in dordi 1 27th Female – 0 and ESMU 4 November 2020 IPs – 3

2077-08-14 Total – 8 Ward Chairperson, CSRdemand Beshishar-1, Lamjung Implementation of CSR within the limit of CSR Male – 7 CFUGs, Project authority fund in Beshishar 1 29th Female – 1 and ESMU November CFUGs has agreed to help the project in forest 5 2020 IPs – 1 activities.

8th Semiannual Social Monitoring Report July-December, 2020

ANNEXURE 7:

Participants List of the training

8th Semiannual Social Monitoring Report July-December, 2020 Annexure 7.1: Participants List of the Driving Training in Chitwan, MKTLP Training Participant List

Driving Training under Skill Development Program

Location: Kurintar Chitwan

SN. Name Address Contact 1 Rupesh Gurung Sahidlakhan -3 Gorkha 9817221603 2 Bharat Gurung Sahidlakhan-3 Gorkha 9805873458

8th Semiannual Social Monitoring Report July-December, 2020 Annexure 7.2: Participants List of the Driving Training in Chitwan and Tanahun, MKTLP

Marsyangdi- Kathmandu 220 kV Transmission Line Project Driving Training under Skill Development Training Program November-December 2020

Training Participant List:

SN. Name Address Contact 1 Amar Bahadur Khatri Gorkha Municipality-13, Simlefat, Gorkha 9824149508 2 Awas Adhikari Gorkha Municipality-13 Simlefat, Gorkha 9869382792 3 Santosh Nepali Gorkha Municipality-14 Gorkha 9829110510 4 Milan Mahat Gorkha Municipality-14 Gorkha 9817132379 5 Saurav Karakheti Gorkha Municipality-14 Gorkha 9811614203 6 Asal Kaini Gorkha Municipality-14 Gorkha 9805890783 7 Chabilal Shrestha Aabukhaireni -2 Markichowk, Tanahun 9845047309 8 Ganga Bdr. Chepang Ichchhakamana RM -3 Lewatar 9806847166 9 Rudra Bdr. Chepang Ichchhakamana RM-3 Kurintar 9809235600

8th Semiannual Social Monitoring Report July-December, 2020

ANNEXURE 8

Photographs

8th Semiannual Social Monitoring Report July-December, 2020 Annexure 15: Photographs

Pic 1 : Cadastral survey at AP 0A and 0B in Pic 2 : Informal consultation at AP 0B in Aanbukhaireni 2 Markichowk Tanahun – Aanbukhaireni 2 Markichowk, Tanahun – UMBTLP UMBTLP

Pic 3: Construction site at AP 27 in Beshishar 1 Pic 4: Tree marking (Chhapan) at raniswara Udipur– UMBTLP sakharpakha community forest in Dordi 2 Lamjung– UMBTLP

Pic 5: Tree marking (Chhapan) at raniswara Pic 6: Land slide at AP 33D in Dordi 1 Lamjung– UMBTLP

8th Semiannual Social Monitoring Report July-December, 2020

sakharpakha community forest in Dordi 2 Lamjung– UMBTLP

Pic 7: Equipment setting under power control Pic 8: Equipment setting under power control building at New butwal sub-station building at New butwal sub-station

Pic 9: Water disturbance of cable trench work at Pic 10: Water tank construction situation at New New butwal sub-station butwal sub-station

Pic 12: Labour are joining wall &plastering ceiling

8th Semiannual Social Monitoring Report July-December, 2020

Pic 11: Labour are working inner of vehicle kepping house

Pic 13: Stinging scinarieo of New butwal Pic 14: Labour are working cable trench work substation

Pic 15: Outlet drain of New butwal substation Pic 16: Store Rope & other equipment at bastari of Palpa by contractor ( L&T ) under KNBTLP

Pic 17: Store steel plate& other equipment at Pic 18: Store steel plate & other equipment at bastari of Palpa by contractor ( L&T ) under bastari of Palpa by contractor ( L&T ) under KNBTLP KNBTLP

8th Semiannual Social Monitoring Report July-December, 2020

Pic 20: GRC Meeting in Kaligandaki RM-6, Syangja, KNBTLP Pic 19: GRC Meeting in Kaligandaki RM-5, Syangja, KNBTLP

Pic 21: GRC Meeting in Kaligandaki RM-7, Pic 22: Interaction with tailoring training Syangja, KNBTLP participants at Thakre-8,MKTLP,Dhading

Pic 23: Shade construction work at Markichowk Pic 24: Shade construction work at Markichowk Substation (MKTLP) Substation (MKTLP)

8th Semiannual Social Monitoring Report July-December, 2020

Pic 25: Stiring work on AP 57A to 57 B at Kurintar Pic 26: Consultation meeting with Project Affect Chitwan (MKTLP) People in Chitwan District (MKTLP)

Pic 27: Orientation for labour before working Pic 28: Orientation for labour before working activities by safety officer (Contractor) (MKTLP) activities by safety officer (Contractor) (MKTLP)

Pic 29: Stiring work on AP 57A to 57 B at Kurintar Pic 30: Stiring work on AP 57A to 57 B at Kurintar Chitwan (MKTLP) Chitwan (MKTLP)

8th Semiannual Social Monitoring Report July-December, 2020

Pic 31: Tower foundation work at AP 6/0, MKTLP, Pic 32: Construction of apparoach road to AP Dhading. 6A/0, MKTLP, Dhading.

Pic 33: Constructed Satighat (Creamation Place Pic 34: Constructed community building (Pati) ) for IPs under CSR at Thakre-8,MKTLP,Dhading under CSR at Thakre-8,MKTLP,Dhading

Pic 35: Driving Training at Ichchhakamana RM, Pic 36: Driving Training at Ichchhakamana RM, Chitwan (MKTLP) Chitwan (MKTLP)

8th Semiannual Social Monitoring Report July-December, 2020

Pic 37: Stiring work on AP 57A to 57 B at Kurintar Pic 38: Interaction with community and ward Chitwan (MKTLP) chairman at Dhunibesi MC-6, MKTLP, Dhading

Pic 39: Stiring work on AP 38 to 39 at Ghyalchowk Pic 40: Crop loss during stiring work in Gorkha Gorkha(MKTLP) District (MKTLP)

Pic 41: Stringing work at AP 5B/0, Dhunibesi MC- Pic 42: Stringing work at AP 7/0, Dhunibesi MC- 7, MKTLP, Dhading. 6, MKTLP, Dhading.

8th Semiannual Social Monitoring Report July-December, 2020

Pic 43: APs receiving compensation amount from Pic 44: Consultation with APs at Dhunibesi MC- Project Office, MKTLP, Dharke 6, MKTLP, Dhading

Pic 45: Labors working in D-type building at New Pic 46: Labors working in D-type building at New Butwal Substation, KNBTLP Butwal Substation, KNBTLP

Pic 47: Insulator setting in 220kv section at New Pic 48: Water tank construction situation at New Butwal sub-station, KNBTLP Butwal sub-station, KNBTLP