CONNECTING EUROPE FACILITY (CEF) – Transport grants 2014-2020

NETHERLANDS

1. Key facts and figures

State of play

Dutch beneficiaries participate in 81 projects and receive €508.4 million in CEF Transport co-funding, with investments in these projects of €1.6 billion.1

Additionally 13 projects are located in but without the involvement of Dutch beneficiaries. These projects correspond to a total of €118.5 million of CEF Transport funding and a total investment of €434.3 million.

CEF Transport funding per national/multinational CEF Transport funding per type (works/studies) projects - € million (number of projects) € million (number of projects) 280.7 319.3 (49) 227.6 (38) (32)

115.4 (9) 73.7 (34)

Multinational National Works Mixed Studies

CEF Transport funding top 5 priorities CEF Transport funding per transport mode2 € million (number of projects) € million (number of projects)

Single European Sky - SESAR 127.4 (9) Rail 157.3 (16)

Road 137.1 (31) New technologies and innovation 113.1 (21) Air 127.4 (9) Pre-identified projects on the Core 103.5 (5) Network corridors Inland 54.5 (11) Waterways Projects on the Core and 63.8 (9) Comprehensive Networks Maritime 28.0 (12) European Rail Traffic Management 42.0 (6) System (ERTMS) Other 4.2 (2)

1State of play: June 2020, including grants under preparation following the 2019 BF call. The charts refer to the actual (or final for closed actions) CEF Transport funding/investments of Dutch beneficiaries. They exclude the projects located in the Netherlands where no Dutch beneficiary is involved. For details on such projects please refer to Section 3. 2 The “Other” transport mode refers to digitalisation of multimodal transport.

1

2. List of projects with Dutch beneficiaries

Out of which: Out of which: Actual CEF co- Actual CEF co- Eligible costs Eligible costs for Transport Mode / Project Actual End funding Title Project Status Priority Type funding for Dutch (at project level) Dutch Code Date (at project level) Beneficiaries (€) Beneficiaries (€) (€) (€)

Air 1,218,719,902 127,404,213 2,694,776,508 275,475,750

Single European 2014-EU-TM-0136-M DP Implementation – call CEF 2014 Ongoing Mixed 31/12/2020 289,733,197 7,314,579 586,107,115 14,629,158 Sky - SESAR SESAR Deployment Programme Single European 2015-EU-TM-0193-M Ongoing Mixed 31/12/2019 86,857,312 2,320,048 216,638,426 4,640,096 implementation 2015 – Cluster 1 Sky - SESAR SESAR Deployment Programme Single European 2015-EU-TM-0196-M Ongoing Mixed 31/12/2021 334,869,571 49,696,139 766,392,249 110,178,116 implementation 2015 – Cluster 2 Sky - SESAR Single European 2015-NL-TM-0402-W Civil / Military Co-location at Schiphol Closed Works 30/06/2018 4,922,224 4,922,224 9,844,449 9,844,449 Sky - SESAR SESAR Deployment Programme Single European 2016-EU-TM-0117-M implementation 2016 – Cluster 1: Ongoing Mixed 31/12/2020 259,502,120 30,350,276 628,791,150 70,582,038 Sky - SESAR General Performance Based Navigation procedures and rationalisation of Air Single European 2016-NL-TM-0336-W Ongoing Works 31/12/2020 3,952,500 3,952,500 7,905,000 7,905,000 Navigation infrastructure in the Sky - SESAR Netherlands SESAR Deployment Programme Single European 2017-EU-TM-0076-M Ongoing Mixed 31/12/2023 228,156,524 18,121,994 457,645,213 36,243,987 Implementation - 2017 Sky - SESAR Remote tower and relocation of local Single European 2017-NL-TM-0127-W Approach for Groningen Airport Eelde Ongoing Works 31/12/2022 7,668,553 7,668,553 15,337,106 15,337,106 Sky - SESAR and Maastricht Aachen Airport Replacement of secondary surveillance radars for Amsterdam Single European 2017-NL-TM-0130-W Ongoing Works 31/12/2021 3,057,900 3,057,900 6,115,800 6,115,800 Airport Schiphol and Groningen Sky - SESAR Airport Eelde by WAM/ADS-B

Inland Waterways 109,317,959 54,483,585 296,041,340 171,055,466

Pre-identified New Lock Terneuzen (preparatory projects on the 2014-EU-TM-0129-W Ongoing Works 31/12/2020 48,094,800 8,103,974 120,237,000 20,259,935 and ancillary works) Core Network corridors

Pre-identified Maasroute upgrading phase 2b projects on the 2014-NL-TM-0069-W Ongoing Works 31/12/2019 13,555,597 13,555,597 33,888,993 33,888,993 2015-2018 Core Network corridors

2

Out of which: Out of which: Actual CEF co- Actual CEF co- Eligible costs Eligible costs for Transport Mode / Project Actual End funding Title Project Status Priority Type funding for Dutch (at project level) Dutch Code Date (at project level) Beneficiaries (€) Beneficiaries (€) (€) (€)

Pre-identified Preparatory activities and project projects on the 2014-NL-TM-0241-W management for the new large Ongoing Works 31/12/2019 11,095,628 11,095,628 27,739,070 27,739,070 Core Network Amsterdam lock corridors New Breakthrough LNG deployment in 2014-NL-TM-0394-S Ongoing technologies Studies 31/12/2019 4,944,755 3,757,948 9,889,510 7,515,896 Inland Waterway Transport and innovation River Information Services Corridor River 2015-EU-TM-0036-W Management Execution (Cohesion Ongoing Information Works 31/12/2020 5,718,661 - 6,727,837 - Call) Services (RIS) River Information Services Corridor River 2015-EU-TM-0038-W Management Execution (General Ongoing Information Works 31/12/2020 9,886,679 3,107,000 19,773,358 6,214,000 Call) Services (RIS) Pre-identified Optimizing Inland Waterway- and projects on the 2017-EU-TM-0024-W Multimodal Transport in the Euregio, Ongoing Works 31/05/2022 10,873,127 10,849,727 56,422,015 56,344,015 Core Network along the North Sea Baltic Corridor. corridors New Port-Liner, "zero emission" ships for 2017-NL-TM-0056-W Terminated technologies Works 31/12/2019 - - - - inland waterways and innovation New ACCEL BARGE: Accelerated 2017-NL-TM-0140-W Terminated technologies Works 31/03/2020 - - - - Electrification of Inland Waterways and innovation Upgrade of the Combined Cargo Multimodal 2018-NL-TM-0096-W terminal rail infrastructure at the Ongoing logistics Works 31/12/2020 3,688,711 3,688,711 18,443,557 18,443,557 Port of Moerdijk platforms River Masterplan Digitalisation of Inland 2018-EU-TM-0020-S Ongoing Information Studies 02/12/2022 1,460,000 325,000 2,920,000 650,000 Waterways Services (RIS) Maritime 87,125,350 27,978,869 259,945,874 110,653,613

ReaLNG: Turning LNG as marine fuel Motorways of 2014-EU-TM-0095-W into reality in the North Sea-Baltic Closed Works 30/09/2017 12,581,818 12,296,252 38,126,720 37,657,136 the Sea (MoS) region Motorways of 2014-EU-TM-0206-S STM Validation Project Ongoing Studies 30/06/2019 21,488,717 65,000 42,977,434 130,000 the Sea (MoS) New Pilot LNG-powered multipurpose 2014-EU-TM-0383-S Terminated technologies Studies 31/12/2017 - - - - RoRo ship and innovation Environmental compliance and Motorways of 2014-EU-TM-0385-M upgrade of the North Sea MoS Closed Works 31/12/2016 1,302,000 69,000 4,340,000 230,000 the Sea (MoS) Felixstowe-Vlaardingen

3

Out of which: Out of which: Actual CEF co- Actual CEF co- Eligible costs Eligible costs for Transport Mode / Project Actual End funding Title Project Status Priority Type funding for Dutch (at project level) Dutch Code Date (at project level) Beneficiaries (€) Beneficiaries (€) (€) (€)

Motorways of 2014-EU-TM-0451-M Scrubbers: Closing the loop Ongoing Mixed 31/12/2018 6,344,400 332,650 20,083,000 865,500 the Sea (MoS) Compliance monitoring pilot for Motorways of 2014-EU-TM-0546-S Closed Studies 31/12/2016 1,469,616 137,364 2,939,231 274,727 Marpol Annex VI (CompMon) the Sea (MoS) DOOR2LNG -Upgrade of the maritime link integrated in the Motorways of 2015-EU-TM-0098-M Ongoing Mixed 30/06/2020 16,862,636 2,256,000 55,742,120 7,520,000 multimodal container transport the Sea (MoS) routes S/F SamueLNG for a blue Atlantic Motorways of 2015-EU-TM-0307-M Ongoing Mixed 30/06/2019 9,862,060 36,000 19,724,119 72,000 Arch the Sea (MoS) New GAINN4MID -GAINN for Mobile 2017-EU-TM-0062-W Ongoing technologies Works 31/08/2020 6,165,304 5,207,304 31,870,000 26,700,000 Infrastructure Deployment and innovation Application of Industry 4.0 New 2018-EU-TM-0135-S Technologies towards Digital Port Ongoing technologies Studies 31/12/2021 3,700,250 230,750 7,400,500 461,500 Container Terminals – iTerminals 4.0 and innovation Multimodal Upgrade of the combined transport 2018-NL-TM-0007-W Ongoing logistics Works 31/12/2022 1,759,550 1,759,550 8,797,750 8,797,750 RSC terminal platforms Multimodal Upgrade of combined transport 2018-NL-TM-0144-W Ongoing logistics Works 31/12/2022 5,589,000 5,589,000 27,945,000 27,945,000 Rotterdam World Gateway terminal platforms Rail 165,430,849 157,274,402 456,149,284 434,436,396

Implementation study for the quality Projects on the improvement of the cross-border Core and 2014-EU-TA-0122-S Ongoing Studies 28/02/2019 8,330,753 8,212,199 16,661,506 16,424,398 railway connection between Comprehensive Groningen (NL) and Bremen (GE) Networks

Projects on the European Rail Freight Line System on Core and 2014-EU-TA-0131-S Ongoing Studies 30/11/2018 625,000 137,500 1,250,000 275,000 the Rhine-Alpine Corridor Comprehensive Networks Pre-identified Rhein-Ruhr Rail Connection: projects on the 2014-EU-TM-0407-S Feasibility study on an alternative Closed other sections Studies 31/12/2017 465,572 - 931,144 - cross-border railway link (“3RX”) of the Core Network Projects on the 3EUStates2cross (Study, Rail, Core and 2014-NL-TA-0680-S Closed Studies 15/11/2018 4,757,500 4,757,500 9,515,000 9,515,000 Limburg S-E Netherlands) Comprehensive Networks

4

Out of which: Out of which: Actual CEF co- Actual CEF co- Eligible costs Eligible costs for Transport Mode / Project Actual End funding Title Project Status Priority Type funding for Dutch (at project level) Dutch Code Date (at project level) Beneficiaries (€) Beneficiaries (€) (€) (€)

Preparatory Study for deployment of ERTMS on the railway line section European Rail Kijfhoek (Port of Rotterdam) – Traffic 2014-NL-TM-0230-S Closed Studies 31/03/2018 1,069,068 1,069,068 2,138,136 2,138,136 Roosendaal – Belgian border – Core Management Network Corridor / Rail Freight System (ERTMS) Corridor North Sea – Mediterranean

Removing the bottleneck on the rail Pre-identified freight corridor between mainport projects on the 2014-NL-TM-0233-W Rotterdam and the European Ongoing Works 31/03/2021 59,892,117 59,892,117 199,640,390 199,640,390 Core Network hinterland by realising the corridors Theemsweg railway section.

European Rail Deployment of ERTMS level-2 (only) Traffic 2015-NL-TM-0264-W trackside at the railway line Kijfhoek- Terminated Works 31/12/2020 - - - - Management Roosendaal- Belgian border System (ERTMS)

European Rail ERTMS L2 B3 On-board deployment Traffic 2015-NL-TM-0328-W on NS vehicles for operation on – Ongoing Works 31/12/2020 17,100,000 17,100,000 34,200,000 34,200,000 Management CNC North Sea - Mediterranean System (ERTMS)

Projects on the Core and 2016-EU-TA-0108-W 2EUStates2cross Ongoing Works 31/12/2020 28,680,000 24,240,000 71,700,000 60,600,000 Comprehensive Networks

Implementation Study for Projects on the optimization of cross-border rail Core and 2016-EU-TA-0174-S Ongoing Studies 30/09/2020 642,130 614,020 1,284,260 1,228,040 infrastructure in the port area Ghent Comprehensive - Terneuzen Networks Freight Sharing of train tracking & ETA 2016-EU-TA-0185-S Ongoing Transport Studies 31/12/2019 1,429,076 377,124 2,858,152 754,248 information Services European Rail ERTMS baseline 3 upgrade of TEN-T Traffic 2016-NL-TM-0112-W Terminated Works 31/12/2020 - - - - freight locomotives Management System (ERTMS)

European Rail ERTMS Baseline 3 upgrade on-board Traffic 2017-NL-TM-0046-W units (OBU’s) Rhine-Alpine freight Ongoing Works 31/12/2023 17,741,250 17,741,250 39,425,000 39,425,000 Management locomotives System (ERTMS)

5

Out of which: Out of which: Actual CEF co- Actual CEF co- Eligible costs Eligible costs for Transport Mode / Project Actual End funding Title Project Status Priority Type funding for Dutch (at project level) Dutch Code Date (at project level) Beneficiaries (€) Beneficiaries (€) (€) (€)

European Rail ERTMS Baseline 3 upgrade on-board Traffic 2017-NL-TM-0101-W units (OBUs) Rhine-Alpine freight Ongoing Works 31/12/2023 6,073,508 6,073,508 13,496,684 13,496,684 Management locomotives - II System (ERTMS)

Projects on the The Wunderline: Borderless European Core and 2019-EU-TA-0003-W rail connection between Ongoing Works 31/12/2023 12,694,875 11,130,116 51,189,012 44,879,500 Comprehensive and The Netherlands Networks

Projects on the Removing bottlenecks on the cross- Core and 2019-NL-TA-0063-S border rail section (NL) - Ongoing Studies 31/12/2023 5,930,000 5,930,000 11,860,000 11,860,000 Comprehensive Kaldenkirchen (DE) Networks

Road 319,976,812 137,052,499 1,265,670,753 609,713,627

Other Telematic 2014-EU-TA-0582-S I_HeERO Closed Application Studies 31/03/2018 13,164,667 173,452 26,329,333 346,903 Systems Intelligent Transport 2014-EU-TM-0317-S EU ITS Platform Ongoing Studies 31/12/2020 6,474,875 584,750 12,949,750 1,169,500 Services for road (ITS)

Intelligent Transport 2014-EU-TM-0365-W URSA MAJOR 2 Ongoing Works 31/12/2020 18,456,120 826,600 92,280,600 4,133,000 Services for road (ITS)

Intelligent Transport 2014-EU-TM-0597-W Arc Atlantique Corridor Phase II Ongoing Works 31/12/2017 23,031,862 2,188,800 115,159,310 10,944,000 Services for road (ITS) New 2014-EU-TM-0630-S Connect2LNG Ongoing technologies Studies 31/12/2020 4,546,250 1,092,874 9,092,500 2,185,748 and innovation H2Nodes – evolution of a European New hydrogen refuelling station network 2014-EU-TM-0643-S Ongoing technologies Studies 30/06/2021 13,531,200 2,855,224 27,062,400 5,710,448 by mobilising the local demand and and innovation value chains

Projects on the ViA15 road project, missing link Core and 2014-NL-TA-0072-S study – Rhine-Alpine Core Network Closed Studies 31/12/2016 2,844,968 2,844,968 5,689,935 5,689,935 Comprehensive Corridor Networks

6

Out of which: Out of which: Actual CEF co- Actual CEF co- Eligible costs Eligible costs for Transport Mode / Project Actual End funding Title Project Status Priority Type funding for Dutch (at project level) Dutch Code Date (at project level) Beneficiaries (€) Beneficiaries (€) (€) (€)

Safe & Secure Truck Parkings on Safe and secure 2014-NL-TM-0153-W Closed Works 31/12/2017 1,231,744 870,536 6,158,719 4,352,682 core network in the Netherlands infrastructure Intelligent Transport 2015-EU-TM-0159-S InterCor Ongoing Studies 29/02/2020 15,000,000 3,957,850 29,999,999 7,915,700 Services for road (ITS) New Models for Economic Hydrogen 2015-EU-TM-0316-S Ongoing technologies Studies 31/12/2020 5,509,500 811,750 11,019,000 1,623,500 Refuelling Infrastructure and innovation New 2015-EU-TM-0367-S ULTRA-E Ongoing technologies Studies 31/12/2019 6,542,650 767,450 13,085,300 1,534,900 and innovation Intelligent Transport 2015-EU-TM-0380-S C-Roads Belgium/Flanders Ongoing Studies 31/12/2020 1,588,250 1,002,750 3,176,500 2,005,500 Services for road (ITS) New LNG motion: Fuelling trucks with 2015-EU-TM-0422-S Ongoing technologies Studies 30/06/2021 12,411,412 8,557,946 24,822,823 17,115,891 LNG/CNG along the core network and innovation Intelligent Transport 2016-EU-TM-0044-M URSA MAJOR neo Ongoing Mixed 31/12/2020 32,129,388 4,976,009 149,461,712 14,579,818 Services for road (ITS)

Intelligent Transport 2016-EU-TM-0148-S SOCRATES 2.0 Ongoing Studies 31/12/2020 5,485,750 3,548,250 10,971,500 7,096,500 Services for road (ITS) New 2016-EU-TM-0175-S H2Benelux Ongoing technologies Studies 31/12/2020 7,218,875 3,665,100 17,484,549 10,377,000 and innovation New 2016-EU-TM-0277-S BENEFIC Ongoing technologies Studies 31/12/2020 7,580,000 2,913,890 37,150,000 14,281,780 and innovation Intelligent Transport 2016-EU-TM-0316-W Arc Atlantique Phase 3 Ongoing Works 31/12/2020 12,996,465 457,800 64,982,325 2,289,000 Services for road (ITS)

7

Out of which: Out of which: Actual CEF co- Actual CEF co- Eligible costs Eligible costs for Transport Mode / Project Actual End funding Title Project Status Priority Type funding for Dutch (at project level) Dutch Code Date (at project level) Beneficiaries (€) Beneficiaries (€) (€) (€)

Intelligent Transport 2016-EU-TM-0327-S CONCORDA Ongoing Studies 30/06/2020 10,000,000 1,767,000 20,000,000 3,534,000 Services for road (ITS)

Projects on the ViA15: solving the missing link in the Core and 2016-NL-TA-0019-W cross-border road infrastructure on Ongoing Works 31/12/2020 5,884,616 5,884,616 58,846,156 58,846,156 Comprehensive the Rhine-Alpine corridor Networks New 2016-NL-TM-0339-S BIOLNG4EU Ongoing technologies Studies 31/12/2022 8,200,000 8,200,000 16,400,000 16,400,000 and innovation New MEGA-E: Metropolitan Greater Areas 2017-EU-TM-0068-W Ongoing technologies Works 31/12/2021 29,300,331 29,300,331 146,501,653 146,501,653 - Electric and innovation Nodes of the 2017-NL-TM-0060-W REMETBUS2 Rotterdam Ongoing Works 31/12/2021 3,266,579 3,266,579 41,825,600 41,825,600 Core Network New 2017-EU-TM-0080-W BioLNG EuroNet Ongoing technologies Works 31/12/2023 25,409,600 11,449,600 127,048,000 57,248,000 and innovation Zero emission public transport New 2017-NL-TM-0143-W services for Schiphol Amsterdam Ongoing technologies Works 31/03/2022 13,542,429 13,542,429 67,712,145 67,712,145 Airport and along the core corridors. and innovation Innovative and digital bike storage New solutions in urban nodes for efficient 2018-NL-TM-0036-W Ongoing technologies Works 31/12/2023 2,822,500 2,822,500 14,112,500 14,112,500 passenger transfer and last-mile and innovation connections Secure Truck Parking on the Safe and secure 2018-NL-TM-0091-W Topcorridors in the Netherlands Ongoing Works 31/12/2022 3,769,055 3,769,055 18,930,460 18,930,460 infrastructure (SecureNL) Safe and secure 2018-NL-TM-0111-S Central Gate Ongoing Studies 31/05/2021 796,500 796,500 1,593,000 1,593,000 infrastructure Intelligent Transport 2018-FR-TM-0097-S InDiD Ongoing Studies 31/12/2023 10,766,707 250,000 21,533,414 500,000 Services for road (ITS) Safe and secure 2018-EU-TM-0079-S sAFE Ongoing Studies 31/12/2020 2,693,681 127,050 5,387,362 254,100 infrastructure Zero Emission Buses for public New 2019-NL-TM-0072-W transport in Amsterdam, The GA Preparation technologies Works 30/09/2023 13,780,842 13,780,842 68,904,208 68,904,208 Netherlands and innovation

8

Out of which: Out of which: Actual CEF co- Actual CEF co- Eligible costs Eligible costs for Transport Mode / Project Actual End funding Title Project Status Priority Type funding for Dutch (at project level) Dutch Code Date (at project level) Beneficiaries (€) Beneficiaries (€) (€) (€)

Other 42,957,834 4,185,510 85,915,668 8,371,020

New A European FEderated Network of 2018-EU-TM-0077-S Ongoing technologies Studies 31/03/2022 30,306,732 1,885,510 60,613,464 3,771,020 Information eXchange in Logistics and innovation New 2018-EU-TM-0119-S FEDeRATED Ongoing technologies Studies 29/12/2023 12,651,102 2,300,000 25,302,204 4,600,000 and innovation

3. List of projects located in the Netherlands without Dutch beneficiaries

Out of which: Actual CEF co- Out of which: Actual CEF Eligible costs funding Eligible costs Transport Mode / Project Project Actual End co-funding (at project Title Priority Type (at project for Dutch Code Status Date for Dutch level) level) Beneficiaries Beneficiaries (€) (€) (€) (€)

Air 23,519,092 47,038,184

Radio Direction Finder supporting 2014-BE-TM-0189-W Closed Single European Sky - SESAR Works 30/06/2017 1,187,550 2,375,100 SES performance 2014-EU-TM-0032-S ATM Data 'as a service' Closed Single European Sky - SESAR Studies 31/12/2017 1,599,712 3,199,424

FABEC N-VCS Voice 2014-EU-TM-0322-W Communication System Ongoing Single European Sky - SESAR Works 31/12/2020 20,731,830 41,463,660

implementation Inland Waterways 6,955,025 13,910,050

New technologies and 2014-BE-TM-0578-S Watertruck+ Ongoing Studies 30/06/2021 6,955,025 13,910,050 innovation Rail 27,978,062 - 55,956,123 -

Support and coordination of Rail Freight Corridor Rhine-Alpine for its long term sustainable 2014-DE-TM-0299-S Ongoing Rail interoperability Studies 31/12/2018 2,855,000 5,710,000 operation as required by the EU Regulations 913/2010, 1315/2013 and 1316/2013.

Improvement and promotion of 2014-EU-TM-0043-S Rail Freight Corridor North Sea – Closed Rail interoperability Studies 31/12/2018 1,761,875 3,523,749

Mediterranean

9

Out of which: Actual CEF co- Out of which: Actual CEF Eligible costs funding Eligible costs Transport Mode / Project Project Actual End co-funding (at project Title Priority Type (at project for Dutch Code Status Date for Dutch level) level) Beneficiaries Beneficiaries (€) (€) (€) (€)

Establishment of Rail Freight Corridor „North Sea – Baltic“ and 2014-EU-TM-0217-S its further development aiming at Ongoing Rail interoperability Studies 31/12/2020 4,131,250 - 8,262,500 - improving conditions for international rail freight transport European Rail Traffic Support to the implementation of 2014-EU-TM-0279-S Closed Management System Studies 31/12/2017 5,143,589 10,287,178 ERTMS (ERTMS) Deployment of ETCS Bsl3 L2 on European Rail Traffic 106 AM Break motor units - 2015-BE-TM-0122-W Ongoing Management System Works 31/12/2020 13,250,000 26,500,000 Retrofit action to promote safety (ERTMS) and cross border transport Rhine-Alpine Integrated and 2015-EU-TM-0028-S Ongoing Nodes of the Core Network Studies 31/12/2019 836,348 1,672,696 Seamless Travel Chain (RAISE-IT)

Road 60,094,630 317,453,787

Study of Innovative Natural Gas Solutions for Road Transport in New technologies and 2014-UK-TM-0388-S North West Europe with Pilot Ongoing Studies 31/12/2018 3,994,251 8,626,893 innovation Deployment in UK and Netherlands EUROP-E: European Ultra-Charge New technologies and 2017-DE-TM-0064-W Ongoing Works 31/12/2021 39,105,379 195,526,894 Roll Out Project - Electric innovation

GA New technologies and 2019-FR-TM-0073-W Total High Power Charging Works 30/06/2023 16,995,000 113,300,000 Preparation innovation

10